Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan September 28, 2015 2. Date of General Procurement Notice: August 10, 2016 3. Period covered by this procurement plan: The procurement period of project covered from year June 2016 to December 2018. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Prior Review Comments Method Threshold US$ 1. ICB and LIB (Goods) All 2. NCB (Goods) Above US$ 2,000,000 3. ICB (Works) All 4. NCB (Works) Above US$ 10,000,000 2. Pre-qualification. Not applicable. 3. Reference to (if any) Project Operational/Procurement Manual: January 28, 2016. 4. Any Other Special Procurement Arrangement: None 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref Description Estimat Packa Domesti Review Comments . ed ges c by Bank No. Cost Prefere (Prior / US$ nce Post) million (yes/no) 1 Summary of 21.91 1 No Prior the ICB (Works) 2 Summary of 119.12 11 No Prior/Post the NCB (Works) III. Selection of Consultants March 29, 2017 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$1,000,000 2. Single Source (Firms) For SSS, USD50,000 (Para 3.9 of Consultant Guidelines, January 2011) and all other SSS contracts. 3. Individual Individuals ≥ USD 0.3 million; and for essential assignments (procurement / legal consultant). For SSS, USD20,000 (Para 5.6 of Consultant Guidelines, January 2011) 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not applicable. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Descriptio Estimat Package Review Comment n of ed s by s Assignme Cost Bank nt US$ (Prior / million Post) Summary 5.91 5 Prior QCBS of number of contracts that will be let under QCBS Summary 1.04 5 Prior/Po CQS/IC of number st of contracts that will be let under other methods March 29, 2017 March 29, 2017 PROCUREMENT Vietnam : Can Tho Urban Development and Resilience PLAN General Information Country: Vietnam 2016-08-15 Bank’s Approval Date of the Original Procurement Plan: 2022-08-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152851 GPN Date: 2016-08-10 Project Name: Can Tho Urban Development and Resilience Loan / Credit No: IDA / 57790, IBRD / 85980, TF / A3723 Can Tho PMU for ODA funded Construction and Investment Projects Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CT3 PW 1 7 / Construction of tide sluice gates on route co Flood risk management, and Single Stage - One E 3,612,666.6 2018-08-1 IDA / 57790 Prior Request for Bids Open - National 6,041,900.00 Signed 2016-10-04 2017-05-23 2016-12-06 2017-01-05 2017-11-29 2017-02-19 2018-05-18 2017-04-20 2018-05-24 nnection with Cach Mang Tha environmental sanitation nvelope 3 8 ng 8 Street to Provincial road 918 CT3 PW 2 1 / Construction of Quang Trung Bridge, module 2 and extension of the span Spatial planning platform an of module 1 and reinforceme Single Stage - One E 16,872,300.0 9,684,289.2 2019-02-2 IBRD / 85980 d financial and social protect Prior Request for Bids Open - National Signed 2016-10-14 2017-04-14 2016-12-16 2017-01-16 2017-05-24 2017-03-02 2017-10-17 2017-05-01 2017-11-08 nt of existing bridge, lighting nvelope 0 8 5 ion instruments system and architecture reha bilitation of the Quang Trung Bridge, approach roads at th e both sides of the Bridge CT3 PW 2 3 / Construction of the parallel road form Tran H Spatial planning platform an oang Na street to the IC3 int Single Stage - One E 2,874,545.4 2018-08-1 IBRD / 85980 d financial and social protect Post Request for Bids Open - National 8,081,800.00 Terminated 2016-10-04 2016-12-06 2017-01-05 2017-10-05 2017-02-20 2017-12-08 2017-04-20 2017-12-18 ersection and approach road nvelope 2 8 ion instruments from intersection to the bus s tation including the intersecti on with NH1A CT3 PW 2 2 / Construction of Spatial planning platform an Single Stage - One E 10,927,100.0 8,445,162.0 2018-09-1 Tran Hoang Na road from Ng IBRD / 85980 d financial and social protect Prior Request for Bids Open - National Signed 2016-10-27 2017-09-11 2016-12-29 2017-02-06 2017-10-17 2017-03-23 2017-12-26 2017-05-14 2017-12-28 nvelope 0 3 1 uyen Van Cu road to Tran Ho ion instruments ang Na Bridge. CT3 PW 2 5 / Construction of Spatial planning platform an Single Stage - One E 16,012,000.0 2018-06-2 connection road CMT8 to Pro IBRD / 85980 d financial and social protect Prior Request for Bids Open - National 0.00 Canceled 2016-10-14 2016-12-16 2017-01-16 2017-03-01 2017-04-28 nvelope 0 7 vincial road 918 ion instruments CT3 PW 2 6 / Construction of connection road CMT8 to Pro Spatial planning platform an Single Stage - One E 12,502,890.0 12,014,472. 2020-01-1 vincial road 918: road from in IBRD / 85980 d financial and social protect Prior Request for Bids Open - National Signed 2018-01-27 2017-11-28 2018-02-12 2018-03-19 2018-01-10 2018-04-14 2018-09-06 2018-05-23 2018-09-08 nvelope 0 55 3 tersection of Vo Van Kiet Roa ion instruments d to Provincial road 918 (Km 1+820 - Km 5+ 333). CT3 PW 1 1 / Construction of Flood risk management, and Single Stage - One E 7,207,052.0 2020-03-1 the Can Tho River Revetment IBRD / 85980 Prior Request for Bids Open - National 8,121,572.00 Signed 2018-04-21 2019-02-25 2018-04-26 2018-05-26 2019-03-29 2018-06-30 2019-11-25 2018-07-14 2019-12-05 environmental sanitation nvelope 4 3 from Km 0+00 to Km 1+600 CT3 PW 2 5 / Construction o f connection road CMT8 to Pr Spatial planning platform an Single Stage - One E 6,845,270.6 2019-04-1 ovincial road 918: road from IBRD / 85980 d financial and social protect Post Request for Bids Open - National 9,243,973.00 Signed 2017-10-28 2017-10-27 2017-11-14 2017-12-18 2017-11-29 2018-01-13 2018-05-18 2018-02-22 2018-06-14 nvelope 6 8 CMT8 Street to intersection o ion instruments f Vo Van Kiet Road (Km0+00 - Km1+820). CT3 PW 1 3 / Construction of Flood risk management, and Single Stage - One E 5,523,767.7 2019-02-1 the Can Tho River Revetment IBRD / 85980 Prior Request for Bids Open - National 9,932,348.00 Signed 2017-03-01 2019-01-30 2017-05-03 2017-06-02 2019-05-28 2017-07-17 2019-07-24 2017-09-15 2019-08-28 environmental sanitation nvelope 0 2 from km 3+00 to end of rout e CT3 PW 1 4 / Construction of Flood risk management, and Single Stage - One E 2019-05-1 the park at the rear of Can T IBRD / 85980 Post Request for Bids Open - National 2,846,400.00 0.00 Canceled 2017-09-29 2017-12-01 2017-12-29 2018-02-12 2018-04-13 environmental sanitation nvelope 3 ho River Revetment CT3 PW 2 7 / Leveling of An Spatial planning platform an Single Stage - One E 3,017,075.6 2020-03-0 Binh Resettlement Site for Ph IBRD / 85980 d financial and social protect Post Request for Bids Open - National 3,529,309.00 Signed 2019-05-02 2019-07-12 2019-05-17 2019-06-17 2019-08-15 2019-07-31 2019-12-31 2019-08-21 2020-01-09 nvelope 2 6 ase 1 ion instruments CT3 PW 1 5 / Construction of Flood risk management, and Single Stage - One E 4,947,676.5 2022-03-3 IBRD / 85980 Post Request for Bids Open - National 5,773,353.00 Signed 2020-04-01 2020-09-11 2020-04-19 2020-05-19 2020-10-12 2020-07-02 2020-11-02 2020-07-29 2020-11-16 Dau Sau tide Sluice gate environmental sanitation nvelope 4 0 CT3 PW 2 8 / Construction of Single Stage - One E 5,809,214.6 2020-10-1 the technical infrastructure o IBRD / 85980 Urban corridor development Post Request for Bids Open - National 7,600,245.00 Signed 2019-05-31 2019-10-28 2019-06-21 2019-07-22 2019-11-28 2019-09-03 2019-12-23 2019-09-27 2020-02-12 nvelope 9 2 f An Binh Resettlement Site f or Phase 1 CT3 PW 1 16 / Improvement Cai Son – Muong Khai canals Flood risk management, and Single Stage - One E 14,516,125.0 11,648,140. 2022-06-3 (area from K1+883 – K4+197 IBRD / 85980 Prior Request for Bids Open - National Signed 2020-03-31 2020-08-11 2020-04-24 2020-05-24 2020-09-28 2020-07-24 2020-12-15 2020-08-26 2020-12-23 environmental sanitation nvelope 0 23 0 ) and construction tidal sluice gate in Pho Tho and Cay Dua canals CT3 PW 1 2 / Construction of the Can Tho River Revetment Flood risk management, and Single Stage - One E 16,319,594.0 12,936,389. 2022-06-3 IBRD / 85980 Prior Request for Bids Open - National Signed 2020-03-31 2020-05-08 2020-04-24 2020-05-24 2020-05-08 2020-07-24 2020-08-12 2020-08-26 2020-08-19 , road at the rear of revetme environmental sanitation nvelope 0 72 0 nt from Km 1+600 to Km 3+ 000 CT3 PW 1 18 / Improvement Flood risk management, and Single Stage - One E Pending Imp 2022-06-3 Dau Sau, Muong Cui, Xeo Nh IBRD / 85980 Post Request for Bids Open - National 9,847,343.00 0.00 2020-06-30 2020-07-23 2020-08-22 2020-10-22 2020-11-24 environmental sanitation nvelope lementation 0 um, Nga Bat and Muong Lo ( 91B) canals CT3 PW 1 15 / Improvement Flood risk management, and Single Stage - One E 4,888,981.3 2022-04-0 Cai Son – Muong Khai canals IBRD / 85980 Prior Request for Bids Open - National 8,521,752.00 Signed 2020-03-31 2020-05-08 2020-04-19 2020-05-19 2020-06-11 2020-07-02 2020-08-25 2020-07-30 2020-08-27 environmental sanitation nvelope 1 1 (area from K0 - K1+695) CT3 PW 1 19 / Improvement Flood risk management, and Single Stage - One E Pending Imp 2022-06-3 Ong Ta, Xeo La, Cay Me, Ong IBRD / 85980 Post Request for Bids Open - National 6,697,748.00 0.00 2020-06-30 2020-07-19 2020-08-18 2020-10-01 2020-10-27 environmental sanitation nvelope lementation 0 Dao, Tu Ho and Sao Canals CT3 PW 1 20 / Construction Flood risk management, and Single Stage - One E Pending Imp 2022-06-3 of reservoirs in University Vill IBRD / 85980 Post Request for Bids Open - National 4,615,419.00 0.00 2020-09-30 2020-10-19 2020-11-19 2021-01-04 2021-01-30 environmental sanitation nvelope lementation 0 age and Long Hoa Lakes Page 1 CT3 PW 2 4 / Construction of Bridge over Can Tho River co Open - Internationa Single Stage - One E 37,683,000.0 34,146,921. 2022-06-3 IBRD / 85980 Urban corridor development Prior Request for Bids Signed 2020-02-17 2020-05-01 2020-02-28 2020-05-04 2020-04-28 2020-05-05 2020-07-14 2020-09-10 2020-09-30 2020-09-17 nnection Tran Hoang Na Roa l nvelope 0 12 0 d with approaching road of C an Tho Bridge. CT3 PW 1 9 / Construction of Flood risk management, and Single Stage - One E 9,335,367.3 2022-05-2 IBRD / 85980 Post Request for Bids Open - National 6,762,200.00 Signed 2020-05-31 2020-11-10 2020-06-18 2020-07-18 2020-12-11 2020-09-01 2020-12-15 2020-09-28 2020-12-23 Hang Bang Water Lock environmental sanitation nvelope 1 9 CT3 PW 1 13 / Improving an d upgrading the infrastructur Flood risk management, and Single Stage - One E 2,717,020.8 2021-08-2 IBRD / 85980 Post Request for Bids Open - National 5,612,111.00 Signed 2019-05-15 2019-10-31 2019-06-03 2019-07-03 2019-12-04 2019-08-16 2020-01-22 2020-02-17 2020-02-28 e of Hoang Quoc Viet Street, environmental sanitation nvelope 8 0 from Km1 + 952.5 to Km3 + 461 CT3 PW 1 6 / Construction of Flood risk management, and Single Stage - One E 1,833,020.3 2021-06-0 tide sluice gates on route at t IBRD / 85980 Post Request for Bids Open - National 2,385,200.00 Signed 2017-03-29 2019-11-01 2017-05-31 2017-06-30 2019-12-05 2017-08-14 2019-12-26 2020-02-18 2020-01-20 environmental sanitation nvelope 4 4 he rear of Can Tho River reve tment National Procure CT3 PW 1 8 / Construction of Flood risk management, and Single Stage - One E ment Document - 19,162,592.0 Under Imple 2024-03-2 IBRD / 85980 Prior Request for Bids Open - National 0.00 2021-12-14 2022-03-24 2021-12-30 2022-01-30 2022-05-16 2022-02-28 2022-03-20 Cai Khe Water Lock environmental sanitation nvelope 1 Envelope proce 0 mentation 0 ss (Non Bank-SPD ) National Procure CT3 PW 1 10 / Improving an ment Document - d upgrading the infrastructur Flood risk management, and Single Stage - One E Pending Imp 2024-05-1 IBRD / 85980 Post Request for Bids Open - National 1 Envelope proce 8,011,590.00 0.00 2022-03-22 2022-03-30 2022-04-29 2022-05-15 2022-05-19 e of Hoang Quoc Viet Street, environmental sanitation nvelope lementation 9 ss (Non Bank-SPD from Km0+000 to Km1+952, ) 5 National Procure CT3 PW 1 17 / Improvement ment Document - Ba Bo, Dau Sau and Hang Ba Flood risk management, and Single Stage - One E 17,061,422.0 Under Imple 2024-03-1 IBRD / 85980 Prior Request for Bids Open - National 1 Envelope proce 0.00 2022-03-22 2022-07-29 2022-03-30 2022-04-29 2022-05-15 2022-05-19 ng canals as well as Hang Ba environmental sanitation nvelope 0 mentation 9 ss (Non Bank-SPD ng canal's branch ) National Procure CT3 PW 1 11 / Improving Wa ment Document - Flood risk management, and Single Stage - One E 12,644,455.0 13,447,137. 2024-01-1 ter Drainage system at Centr IBRD / 85980 Post Request for Bids Open - National 1 Envelope proce Signed 2022-03-22 2022-06-08 2022-03-30 2022-04-29 2022-07-08 2022-05-15 2022-07-18 2022-05-19 2022-07-25 environmental sanitation nvelope 0 00 9 al area in Ninh Kieu District ss (Non Bank-SPD ) CT3-PW-2.3.1 / Construction of the parallel road form Tran National Procure Hoang Na street to the IC3 in ment Document - tersection and approach road Single Stage - One E Pending Imp 2023-07-2 IBRD / 85980 Urban corridor development Post Request for Bids Open - National 1 Envelope proce 3,474,867.00 0.00 2022-07-20 2022-08-30 2022-09-30 2022-10-10 2022-10-20 from intersection to the bus s nvelope lementation 0 ss (Non Bank-SPD tation including the intersecti ) on with NH1A (completion of the remaining works under t he package) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Spatial planning platform an CT3 PG 3 1 / Spatial Plannin Single Stage - One E TF / A3723 d financial and social protect Prior Request for Bids Open - National 1,633,435.00 1,489,322.25 Signed 2019-05-10 2019-12-02 2019-06-03 2019-07-05 2020-05-15 2019-08-20 2020-08-13 2019-09-20 2020-08-19 2021-03-26 g Platform (SPP) nvelope ion instruments CT3 PG 3 2 / The Design, De Spatial planning platform an velopment and Implementati Single Stage - One E TF / A3723 d financial and social protect Post Request for Bids Open - National 273,000.00 210,777.66 Signed 2019-05-10 2019-07-16 2019-05-24 2019-06-24 2019-08-19 2019-08-08 2019-10-03 2019-08-29 2019-10-31 2020-06-03 on of Integrated Social Assist nvelope ion instruments ance (ISA) System NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CT3 NC 3 3 / Survey to devel Spatial planning platform an op a household database in r Single Stage - One E IDA / 57790 d financial and social protect Post Request for Bids Open - National 101,633.00 85,401.26 Signed 2019-05-20 2019-07-16 2019-06-03 2019-07-05 2019-08-19 2019-08-19 2019-10-03 2019-09-10 2019-11-13 2020-05-18 esponse to flood risks and cli nvelope ion instruments mate change impacts. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CT3 CS TV03 / Construction Spatial planning platform an supervision and contract ma Consultant Qualifi Pending Impleme IDA / 57790 d financial and social protect Post Open - National 175,500.00 0.00 2016-10-24 2016-11-01 2016-12-26 2017-02-16 2017-04-03 2018-01-27 nagement Consultant for of cation Selection ntation ion instruments Resettlement area phase 1 ( CT3-PW-2.7) CT3 CS TV01 / Construction Supervision and contract ma nagement Consultant for pac kages under Component 1 (C Flood risk management, and Quality And Cost- Open - Internationa IDA / 57790 Prior 3,804,300.00 3,178,673.71 Signed 2016-07-15 2016-08-30 2016-07-20 2016-11-21 2016-10-13 2017-09-06 2016-12-13 2017-10-09 2017-01-24 2018-05-15 2017-02-20 2018-07-12 2017-05-05 2018-07-27 2019-07-04 an Tho River Revetment: CT3 environmental sanitation Based Selection l -PW-1.1, CT3-PW-1.2, CT3-P W-1.3, CT3-PW-1.4, CT3-PW- 1.5, CT3-PW-1.6, CT3-PW-1.8 and CT3-PW-1.9) CT3 CS TV05 / Independent Flood risk management, and Consultant Qualifi consultant for monitoring en IDA / 57790 Post Open - National 200,000.00 160,207.10 Signed 2016-10-13 2017-04-12 2016-10-21 2016-12-16 2018-03-02 2017-02-06 2018-04-20 2017-03-22 2018-04-24 2021-10-21 environmental sanitation cation Selection vironment on project CT3 CS TV07 / Independent Flood risk management, and Consultant Qualifi IDA / 57790 Prior Open - National 250,000.00 51,854.28 Signed 2016-08-29 2017-01-24 2016-09-05 2016-10-31 2018-04-26 2016-12-21 2018-07-08 2017-02-06 2018-07-13 2020-01-31 Consultant for auditing environmental sanitation cation Selection CT3 CS TV11 / Construction Supervision and contract ma nagement Consultant for pac kages of Improving and upgr Flood risk management, and Consultant Qualifi Pending Impleme IDA / 57790 Post Open - National 295,800.00 0.00 2017-02-06 2017-02-13 2017-04-10 2017-05-24 2017-07-10 2019-05-06 ading the infrastructure of H environmental sanitation cation Selection ntation oang Quoc Viet Street and Im proving Water Drainage syst em at Central area in Ninh Ki eu District: CT3-PW-1.10, CT 3-PW-1.11. Page 2 CT3 CS TV12 / Assistant tech nical (TA) for doing Bidding d ocuments and Bid evaluation Flood risk management, and Consultant Qualifi IDA / 57790 Prior Open - National 280,000.00 196,533.63 Signed 2016-07-24 2016-12-13 2016-07-31 2016-12-18 2018-03-06 2017-05-23 2018-04-26 2017-07-23 2018-05-14 2019-07-23 for all packages under the pr environmental sanitation cation Selection ocurement plan for the first 1 8 months and Bidding docum ents for Phase 2 CT3 CS TV02 / Construction Supervision and contract ma nagement Consultant for pac kages under Component 2 an Flood risk management, and Quality And Cost- Open - Internationa d tide sluice gates on route c IDA / 57790 Prior 3,381,800.00 2,783,739.97 Signed 2016-07-15 2016-08-30 2016-07-21 2016-11-21 2016-10-13 2017-09-09 2016-11-10 2017-10-18 2016-12-22 2018-04-07 2017-02-20 2018-05-28 2017-04-20 2018-05-31 2020-04-19 environmental sanitation Based Selection l onnection with Cach Mang Th ang 8 Street to Provincial roa d 918 (CT3-PW-2.1, CT3-PW- 2.2, CT3-PW-2.3, CT3-PW-2.4 , CT3-PW-2.5 and CT3-P CT3 CS TV06 / Independent Flood risk management, and Consultant Qualifi Under Implement consultant for resettlement s IBRD / 85980 Post Open - National 150,000.00 132,155.49 2016-08-24 2018-08-15 2016-08-31 2016-10-26 2018-02-26 2018-04-16 2018-04-18 2018-04-28 2022-04-27 environmental sanitation cation Selection ation upervision on project CT3-CS-TV08 / Establishing F Spatial planning platform an Quality And Cost- Open - Internationa lood Risk Management Infor TF / A3723 d financial and social protect Prior 1,700,000.00 1,657,588.00 Signed 2018-04-26 2018-12-04 2018-07-12 2019-01-06 2018-10-19 2019-08-12 2018-12-14 2019-08-02 2019-03-06 2019-11-27 2019-04-20 2020-05-11 2019-05-23 2020-05-18 2021-01-20 Based Selection l mation System (FRMIS) for c ion instruments an Tho City CT3 CS TV04 / Consulting se rvice for monitoring and eval Flood risk management, and Consultant Qualifi IDA / 57790 Post Open - National 150,000.00 0.00 Canceled 2016-08-24 2016-09-01 2016-10-27 2016-12-17 2017-02-06 2022-02-05 uation on implementation of environmental sanitation cation Selection project Consultancy CT3-CS-TV09 / Sustainable U Spatial planning platform an rban Public Transport & Cent Quality And Cost- Open - Internationa IDA / 57790 d financial and social protect Post 475,000.00 410,263.00 Signed 2018-06-12 2018-10-08 2018-07-16 2018-10-15 2018-10-23 2019-05-13 2018-12-19 2019-06-28 2019-03-13 2019-08-26 2019-04-26 2019-09-25 2019-05-28 2019-12-12 2021-01-25 ral Area Traffic Management Based Selection l ion instruments Study for Can Tho City CT3 CS TV04 / Consulting se rvice for monitoring and eval Flood risk management, and Consultant Qualifi IBRD / 85980 Post Open - National 220,000.00 264,483.47 Signed 2018-12-12 2019-02-18 2018-12-27 2019-02-09 2019-07-30 2019-03-11 2019-09-14 2019-03-29 2019-10-17 2021-09-25 uation on implementation of environmental sanitation cation Selection project Consultancy Spatial planning platform an CT3-CS-TV10 / Spatial Planni Quality And Cost- Open - Internationa TF / A3723 d financial and social protect Prior 1,634,000.00 0.00 Canceled 2018-07-05 2018-08-08 2018-11-15 2019-01-11 2019-04-05 2019-05-20 2019-06-20 2020-12-18 ng Platform (SPP) Based Selection l ion instruments CT3-CS-TV14 / Consultancy Spatial planning platform an Service for the Design, Devel Consultant Qualifi IDA / 57790 d financial and social protect Post Open - National 267,000.00 0.00 Canceled 2018-06-30 2018-08-03 2018-11-16 2019-01-14 2019-02-15 2019-11-15 opment and Implementation cation Selection ion instruments of Integrated Social Assistanc e (ISA) System CT3-CS-TV15 / Consulting Se rvice to carry out a Geo-Refe Spatial planning platform an Quality And Cost- Pending Impleme renced Households Vulnerabi IDA / 57790 d financial and social protect Post Open - National 295,000.00 0.00 2018-07-06 2018-07-27 2018-11-05 2018-12-12 2019-02-08 2019-03-25 2019-04-29 2021-12-28 Based Selection ntation lity Survey and data update ion instruments against Flood in Can Tho City CT3 CS TV13 / Consultant of Consultant Qualifi IBRD / 85980 Urban corridor development Post Open - National 93,761.00 89,091.66 Signed 2019-05-02 2019-04-17 2019-05-06 2019-07-05 2019-07-26 2019-10-21 2019-09-09 2019-11-08 2019-10-17 2021-04-29 communication on the projec cation Selection t. CT3 CS TV17 / Transportatio Spatial planning platform an Quality And Cost- Open - Internationa Pending Impleme n system improvement and r IDA / 57790 d financial and social protect Prior 1,000,000.00 0.00 2020-05-18 2020-06-17 2020-09-18 2020-11-06 2020-12-16 2021-03-04 2021-04-13 2022-06-30 Based Selection l ntation esearch Consultant - Phase ion instruments 2 CT3 CS TV16 / Construction Supervision and contract ma Flood risk management, and Quality And Cost- Open - Internationa IBRD / 85980 Post 356,675.00 0.00 Canceled 2020-02-28 2020-03-29 2020-05-18 2020-06-17 2020-07-17 2020-08-30 2020-09-30 2022-04-06 nagement Consultant for pac environmental sanitation Based Selection l kages under Component 1 fo r Phase II CT3-CS-TV19 / Independent Flood risk management, and Consultant Qualifi IBRD / 85980 Post Open - National 100,517.00 39,678.87 Signed 2020-09-30 2021-05-04 2020-10-03 2020-10-23 2021-07-13 2020-11-24 2021-08-26 2020-11-28 2021-08-26 2023-11-28 Consultant for auditing for Ph environmental sanitation cation Selection ase 2 CT3-CS-TV16 / The Consulta ncy for construction supervisi Flood risk management, and Consultant Qualifi Pending Impleme on and contract managemen IBRD / 85980 Post Open - National 292,178.00 0.00 2020-07-04 2020-10-03 2020-10-23 2020-11-23 2020-11-28 2022-09-28 environmental sanitation cation Selection ntation t for improving primary cana ls and urban drainage impro vement. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3