PHILIPPINE RURAL DEVELOPMENT PROJECT LN 8421-PH ORIGINAL LOAN Procurement Plan As of June 2018 I. General 1. Bank’s approval Date of the Procurement Plan : September 9, 2014 2. Date of General Procurement Notice : September 25, 2012 3. Period covered by this procurement plan : July 2018 – June 2019 II. Goods and Works and non-consulting services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Method Threshold Prior Review No. Procurement Method US$ Threshold US$ International Competitive 1. 3M and above All contracts Bidding (ICB) (Goods) National Competitive Bidding 2. less than 3M 2M and above (NCB) (Goods) packages 3. Shopping (Goods) less than 0.2M None 4. ICB (Works) packages 15M and above All contracts 5. NCB (Works) packages less than 15M 10M and above 6. Shopping (Works) less than 0.2M None Subject to justification in accordance with para. 3.7 of 5. Direct Contracting (Goods) 2M and above Procurement Guidelines at the Procurement Plan stage 6. Commercial Practice less than 0.1M None 7. Community Participation less than 0.05M None 2. Reference to Project Operational/Procurement Manual including Community Participation: Original version dated : May 2014 To be updated by : July 2018 (Revised Operations Manual submitted September 4, 2017) 3. Summary of the Procurement Packages (with international competition, direct contracting, requiring Bank’s prior review): PHILIPPINE RURAL DEVELOPMENT PROJECT Summary of the Procurement Packages LN 8421 PH Procurement Plan Updated June 2018 (with International Competition, Direct Contracting requiring Bank’s prior review) 1 2 3 4 5 6 7 8 9 10 Domest Estimated ic Expected Procurin Procurem Cost Funding Prefere Review Bid Comment Ref. No. Description g ent US$1= Source nce by Bank Opening s Agency Method Php 50) (yes/no Date ) No subprojects for Bank’s prior review III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines on Selection and Employment of Consultants: Prior Review No. Selection Method Method Threshold US$ Threshold US$ 1. Competitive Methods 0.3M & above (may be used for 1m and above (QCBS, QBS, FBS) also less than 0.3M) (Firms) 2. Competitive Method less than 0.3M None CQS (Firms) 3. Individuals Competitive regardless of amount 0.3M and above 2. Single Source (Firms & on exceptional basis subject to Firms: 1M and Individuals) justification in accordance with above; paras. 3.9 and 5.4 respectively of Individuals 0.3M and Consultant Guidelines at the above. Procurement Plan stage 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Summary of the Consultancy Assignments/Packages (using international competition, single/sole source selection, requiring Bank’s prior review): PHILIPPINE RURAL DEVELOPMENT PROJECT Summary of the Procurement Packages (with International Competition) 1 2 3 4 5 6 7 8 Ref Description of Procurin Expected Bid Estimated Cost (USD Funding Selection Comm . Contract g Opening million) Source Method ents No. Package Agency Date Various PRDP Technical Consultant and Staff (provided with No Objection December 22, 2017) US$1,042,75 Single Source NPCO ( Php53.178 LP/GoP Selection million) US$1,042,75 Single Source Luzon A ( Php59.152 LP/GoP Selection million) LN 8421 PH Procurement Plan Updated June 2018 US$1,042,75 Single Source Luzon B ( Php48.614 LP/GoP Selection million) US$1,042,75 Single Source Visaya ( Php29.612 LP/GoP Selection million) US$1,042,75 Single Source Mindanao ( Php million) LP/GoP Selection Prepared by: Reviewed by: ENGR. ROMEO L. MALONG ENGR. CHRISTOPHER V. MORALES Alternate Procurement Unit Head Procurement Unit Head LN 8421 PH Procurement Plan Updated June 2018 PROCUREMENT Philippines : Philippine Rural Development Project PLAN General Information Country: Philippines Bank’s Approval Date of the Original Procurement Plan: 2019-03-11 2022-02-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P132317 GPN Date: Project Name: Philippine Rural Development Project Loan / Credit No: IBRD / 84210, IBRD / 88160, IBRD / 92710 PRDP PSO Visayas, Department of Agriculture Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification High SEA/SH Process Prequalification Specific Procurement Bidding Documents Proposal Submission Contract Description Component Review Type Method Document Amount Amount qualification Document / and Recommendation Signed Contract No. Approach Process (Y/N) Risk Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Completion Type (US$) (US$) Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PRDP-IB-R006-NOC-008- Under 000-000-2015-AF / Component 2: Infrastructure Single Stage - One 2018-09- 2018-07- 2018-09- 2018-10- 2018-10- 2018-11- 2018-12- 2019-06- IBRD / 88160 Post Request for Bids Open - National 953,274.51 0.00 Implementa Rehabilitation of Brgy. 1-A to Development Envelope 07 02 12 24 09 23 28 26 tion Brgy. Punta Salong FMR PRDP-IB-R008-LEY-005- DAG-001-2014-AF / Component 2: Infrastructure Single Stage - One 2018-08- 2018-06- 2018-09- 2018-10- 2018-09- 2018-11- 2018-11- 2018-12- 2019-03- 2019-06- IBRD / 88160 Post Request for Bids Open - National 524,156.86 515,997.76 Signed Concreting of Brgy. Abaca - Development Envelope 28 20 02 14 28 13 20 18 07 16 Pandan Farm-to-Market Road PRDP-IB-R008-NOS-007- ROS-001-2015-AF / Component 2: Infrastructure Single Stage - One 2018-08- 2018-07- 2018-08- 2018-10- 2018-09- 2018-11- 2018-11- 2018-12- 2019-02- 2019-06- Concreting of Salhag - IBRD / 88160 Post Request for Bids Open - National 978,392.16 957,606.49 Signed Development Envelope 20 02 25 06 24 05 21 10 06 08 Kailingan Farm-to-Market Road PRDP-IB-R006-ILO-006- 000-000-2015-AF / Component 2: Infrastructure Single Stage - One 3,632,179.9 3,755,092. 2018-11- 2019-01- 2018-11- 2018-12- 2019-04- 2019-01- 2019-06- 2019-02- 2019-08- 2019-08- Rehabilitation/Concreting of IBRD / 88160 Post Request for Bids Open - National Signed Development Envelope 2 75 02 06 07 19 02 18 26 22 08 21 Bongol - Tambal - Quipot Farm to Market Road PRDP-IB-R006-AKL-003- Under 000-000-2015-AF / Component 2: Infrastructure Single Stage - One 1,228,392.1 2018-11- 2018-07- 2018-11- 2018-12- 2019-03- 2019-01- 2019-05- 2019-02- 2019-08- IBRD / 88160 Post Request for Bids Open - National 0.00 Implementa Rehabilitation and Development Envelope 6 02 02 07 19 12 18 22 22 21 tion Improvement of Lalab - Bay- ang - Magpag-ong Road PRDP-IB-R006-NOC-013- Pending 000-000-2018-AF / Component 2: Infrastructure Single Stage - One 1,347,435.8 2018-11- 2018-11- 2018-12- 2019-01- 2019-02- 2019-08- IBRD / 88160 Post Request for Bids Open - National 0.00 Implementa Construction of Ninety (90) Development Envelope 8 02 07 19 18 22 21 tion L.M. Himoga-an Bridge III PRDP-IB-R007-SIQ-002- Under 000-000-2017-AF / Component 2: Infrastructure Single Stage - One 2018-11- 2018-12- 2018-11- 2018-12- 2019-03- 2019-01- 2019-04- 2019-02- 2019-08- IBRD / 88160 Post Request for Bids Open - National 605,000.00 0.00 Implementa Construction of Siquijor Development Envelope 02 06 07 19 28 18 23 22 21 tion Provincial AA Abattoir PRDP-IB-R007-NOR-001- 000-000-2017-AF / Component 2: Infrastructure Single Stage - One 6,403,024.9 6,275,158. 2018-11- 2019-01- 2018-11- 2018-12- 2019-03- 2019-01- 2019-05- 2019-02- 2019-08- 2019-08- Rehabilitation and IBRD / 88160 Post Request for Bids Open - National Signed Development Envelope 7 09 02 06 07 19 20 18 08 22 13 21 Improvement of Hilaitan to Trinidad Farm to Market Road PRDP-IB-R008-NOS-004- 000-000-2015-AF / Under Construction/Rehabilitation Component 2: Infrastructure Single Stage - One 2,738,568.6 2018-11- 2018-07- 2018-11- 2018-12- 2019-01- 2019-02- 2019-08- IBRD / 88160 Post Request for Bids Open - National 0.00 Implementa of Camparanga - Manahaw - Development Envelope 3 02 02 07 19 18 22 21 tion San Ramon - Canjumadal Farm-to-Market Road PRDP-IB-R008-NOS-005- BOB-001-2015-AF / Construction/Improvement Component 2: Infrastructure Single Stage - One 2018-11- 2018-07- 2018-11- 2018-12- 2019-03- 2019-01- 2019-04- 2019-02- 2019-06- 2019-08- IBRD / 88160 Post Request for Bids Open - National 678,796.34 743,676.13 Signed of Brgy. Dancalan - Sitio Development Envelope 02 02 07 19 14 18 29 22 27 21 Inamburacay Farm-to- Market Road PRDP-IB-R008-SAM-010- 000-000-2015-AF / Under Component 2: Infrastructure Single Stage - One 1,726,362.5 2018-11- 2020-02- 2018-11- 2021-02- 2018-12- 2019-01- 2019-02- 2019-08- Improvement/Concreting of IBRD / 88160 Post Request for Bids Open - National 0.00 Implementa Development Envelope 2 02 17 07 02 19 18 22 21 Brgy. Cogon - Brgy. Villa tion Aurora FMR PRDP-IB-R006-ILO-008- Pending 000-000-2018-AF / Component 2: Infrastructure Single Stage - One 2019-10- 2019-10- 2019-11- 2019-12- 2020-01- 2020-07- IBRD / 88160 Post Request for Bids Open - National 738,176.47 0.00 Implementa Construction of Sixty (60) Development Envelope 01 06 17 17 21 19 tion L.M. PSCG Cabacanan Bridge PRDP-IB-R007-BOH-005- 000-000-2014-AF / Component 2: Infrastructure Single Stage - One 1,432,607.8 2,462,223. 2019-10- 2019-01- 2019-10- 2019-11- 2019-05- 2019-12- 2019-06- 2020-01- 2019-11- 2020-07- IBRD / 88160 Post Request for Bids Open - National Signed Rehabilitation of Dagnawan Development Envelope 4 86 01 06 06 17 03 17 26 21 14 19 to Dagohoy Farm to Market Road PRDP-IB-R007-LEY-006-HIL- 001-2016-AF / Concreting Component 2: Infrastructure Single Stage - One 2,591,784.3 5,108,557. 2018-08- 2018-06- 2018-08- 2018-09- 2018-08- 2018-10- 2018-09- 2018-11- 2018-10- 2019-05- of Brgy. Concepcion - IBRD / 88160 Post Request for Bids Open - National Completed Development Envelope 1 98 01 20 06 17 31 17 27 21 29 20 Bagumbayan - Hampangan Farm-to-Market Road National PRDP-IB-R006-AKL-005- Procurement Pending Component 2: Infrastructure Single Stage - One 2022-02- 2022-03- 2022-04- 2022-05- 2022-06- 2022-12- 000-000-2018-AF / IBRD / 92710 Post Request for Bids Open - National Document - 1 209,379.74 0.00 Implementa Development Envelope 24 01 12 12 16 13 Construction of Magpag-ong Envelope process tion Fish Port (Non Bank-SPD) PRDP-IB-R006-AKL-008-LIB- National 001-2019 / Procurement Pending Construction/Concreting of Component 2: Infrastructure Single Stage - One 9,788,761.9 2022-03- 2022-04- 2022-05- 2022-06- 2022-07- 2023-01- IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Manika-Oyang-Dalagsaan Development Envelope 8 27 01 13 12 17 13 Envelope process tion Farm-to-Market Road with (Non Bank-SPD) Bridges PRDP-IB-R006-NOC-017- National 000-000-2018-AF / Procurement Pending Rehabilitation of Brgy. Component 2: Infrastructure Single Stage - One 9,552,157.0 2022-03- 2022-04- 2022-05- 2022-06- 2022-07- 2023-01- IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Talacagay to Brgy. Development Envelope 7 27 01 13 12 17 13 Envelope process tion Bacuyangan to Brgy. (Non Bank-SPD) Damutan FMR with Bridge PRDP-IB-R007-BOH-006- National 000-000-2014-AF / Procurement Pending Component 2: Infrastructure Single Stage - One 3,973,560.0 2022-03- 2022-04- 2022-05- 2022-06- 2022-07- 2023-01- Rehabilitation of Campagao- IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Development Envelope 0 27 01 13 12 17 13 Cabacnitan Farm to Market Envelope process tion Road (Non Bank-SPD) PRDP-IB-R007-BOH-007- National 000-000-2014-AF / Procurement Pending Component 2: Infrastructure Single Stage - One 2,280,820.0 2022-03- 2022-04- 2022-05- 2022-06- 2022-07- 2023-01- Rehabilitation of Pondol- IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Development Envelope 0 27 01 13 12 17 13 Candaigan Farm to Market Envelope process tion Road (Non Bank-SPD) PRDP-IB-R008-SOL-009- National MAA-001-2015-AF / Procurement Pending Component 2: Infrastructure Single Stage - One 3,073,578.0 2022-03- 2022-04- 2022-05- 2022-06- 2022-07- 2023-01- Construction and Concreting IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Development Envelope 1 27 01 13 12 17 13 of Brgy. Hantag - Brgy. Envelope process tion Laboon FMR (Non Bank-SPD) PRDP-IB-R008-EAS-006- National 000-000-2016 / Procurement Pending Component 2: Infrastructure Single Stage - One 3,313,526.2 2022-03- 2022-04- 2022-05- 2022-06- 2022-07- 2023-01- Improvement/Concreting of IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Development Envelope 4 27 01 13 12 17 13 Bura-Mabuhay-Bantayan- Envelope process tion Kalaw Farm-to-Market Road (Non Bank-SPD) PRDP-IB-R008-SAM-005- National 000-000-2014-AF / Procurement Pending Improvement/Concreting of Component 2: Infrastructure Single Stage - One 2,604,299.5 2022-03- 2022-04- 2022-05- 2022-06- 2022-07- 2023-01- IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa San Agustin - Brgy. Development Envelope 3 27 01 13 12 17 13 Envelope process tion Villahermosa Oriental Farm- (Non Bank-SPD) to-Market Road PRDP-IB-R008-SAM-004- National 000-000-2014-AF / Procurement Pending Component 2: Infrastructure Single Stage - One 2,793,610.0 2022-03- 2022-04- 2022-05- 2022-06- 2022-07- 2023-01- Improvement/Concreting of IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Development Envelope 2 27 01 13 12 17 13 Brgy. Cambaguio - Brgy. San Envelope process tion Andres Farm-to-Market (Non Bank-SPD) Road National PRDP-IB-R006-ILO-008- Procurement Pending 000-000-AF / Construction Component 2: Infrastructure Single Stage - One 2022-03- 2022-04- 2022-05- 2022-06- 2022-07- 2023-01- IBRD / 92710 Post Request for Bids Open - National Document - 1 914,885.57 0.00 Implementa of Sixty (60) L.M. PSCG Development Envelope 27 01 13 12 17 13 Envelope process tion Cabacanan Bridge (Non Bank-SPD) National PRDP-IB-R006-ILO-011- Procurement Pending Component 2: Infrastructure Single Stage - One 2022-05- 2022-05- 2022-06- 2022-07- 2022-08- 2023-02- 000-000-2021-AF / IBRD / 92710 Post Request for Bids Open - National Document - 1 646,749.05 0.00 Implementa Development Envelope 05 10 21 21 25 21 Establishment of Concepcion Envelope process tion Abattoir (Non Bank-SPD) National PRDP-IB-R006-ILO-010- Procurement Pending Component 2: Infrastructure Single Stage - One 2022-05- 2022-05- 2022-06- 2022-07- 2022-08- 2023-02- 000-000-2020-AF / IBRD / 92710 Post Request for Bids Open - National Document - 1 963,137.55 0.00 Implementa Development Envelope 05 10 21 21 25 21 Establishment of Oton Envelope process tion Abattoir (Non Bank-SPD) National PRDP-IB-R006-GUI-008- Procurement Pending NUE-001-2021-AF / Component 2: Infrastructure Single Stage - One 2022-05- 2022-05- 2022-06- 2022-07- 2022-09- 2023-02- IBRD / 92710 Post Request for Bids Open - National Document - 1 739,556.28 0.00 Implementa Establishment of Nueva Development Envelope 12 17 28 28 01 28 Envelope process tion Valencia Municipal Abattoir (Non Bank-SPD) National PRDP-IB-R007-BOH-011- Procurement Pending Component 2: Infrastructure Single Stage - One 2022-05- 2022-05- 2022-06- 2022-07- 2022-09- 2023-02- 000-000-2018-AF / Brgy. IBRD / 92710 Post Request for Bids Open - National Document - 1 266,829.72 0.00 Implementa Development Envelope 12 17 28 28 01 28 Cataban Potable Water Envelope process tion System (Non Bank-SPD) GOODS Page 1 Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Pending DA-PRDP-VIS-GOODS-2022- Component 4: Project Request for Single Stage - One 2022-06- 2022-07- 2023-01- IBRD / 92710 Post Limited 30,000.00 0.00 Implementat 001 / Laptop Computer Implementation Support Quotations Envelope 01 27 23 ion NON CONSULTING SERVICES Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRDP-IS-VIS-DPD-006-000- Individual Component 4: Project Under 2018-08- 2018-09- 2018-10- 2019-04- 2018-AF / Project IBRD / 84210 Post Consultant Open 8,470.59 0.00 2018-07-01 Implementation Support Implementation 19 09 14 12 Development Associate Selection PRDP-IS-VIS-PRO-003-000- Individual Component 4: Project Pending 2018-08- 2018-09- 2018-10- 2019-04- 2018-AF / Procurement IBRD / 84210 Post Consultant Open 12,705.88 0.00 2018-07-01 Implementation Support Implementation 19 09 14 12 Officer Selection PRDP-IS-VIS-PRO-004-000- Individual Component 4: Project Pending 2018-08- 2018-09- 2018-10- 2019-04- 2018-AF / Procurement IBRD / 84210 Post Consultant Open 12,705.88 0.00 2018-07-01 Implementation Support Implementation 19 09 14 12 Officer Selection PRDP-IS-VIS-SES-003-000- Individual Component 4: Project Pending 2018-08- 2018-09- 2018-10- 2019-04- 2018-AF / Project IBRD / 84210 Post Consultant Open 8,470.59 0.00 2018-07-01 Implementation Support Implementation 19 09 14 12 Development Associate Selection Individual PRDP-IS-VIS-BUD-001-000- Component 4: Project Pending 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 84210 Post Consultant Open 14,117.65 0.00 2018-07-01 2018-AF / Budget Specialist Implementation Support Implementation 19 09 14 12 Selection PRDP-IS-VIS-ADM-003-000- Individual Component 4: Project Pending 2018-08- 2018-09- 2018-10- 2019-04- 2018-AF / Administrative IBRD / 84210 Post Consultant Open 9,882.35 0.00 2018-07-01 Implementation Support Implementation 19 09 14 12 Officer III Selection PRDP-IS-VIS-ADM-008-000- Individual Component 4: Project Pending 2018-08- 2018-09- 2018-10- 2019-04- 2018-AF / Administrative IBRD / 84210 Post Consultant Open 5,647.06 0.00 2018-07-01 Implementation Support Implementation 19 09 14 12 Staff Selection Individual PRDP-IS-VIS-ADM-009-000- Component 4: Project Pending 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 84210 Post Consultant Open 5,647.06 0.00 2018-07-01 2018-AF / Cash Clerk Implementation Support Implementation 19 09 14 12 Selection Individual PRDP-IS-VIS-R008-ECO- Component 4: Project Pending 2018-02- 2018-03- 2018-04- 2018-10- IBRD / 84210 Post Consultant Open 8,470.59 0.00 2018-01-01 001-2018-AF / Economist Implementation Support Implementation 19 12 16 13 Selection PRDP-IS-VIS-R008-ACC- Individual Component 4: Project Pending 2018-02- 2018-03- 2018-04- 2018-10- 001-2018-AF / Financial IBRD / 84210 Post Consultant Open 9,882.35 0.00 2018-01-01 Implementation Support Implementation 19 12 16 13 Analyst I Selection PRDP-IS-VIS-R008-PRO- Individual Component 4: Project Pending 2018-02- 2018-03- 2018-04- 2018-10- 001-2018-AF / Procurement IBRD / 84210 Post Consultant Open 11,294.12 0.00 2018-01-01 Implementation Support Implementation 19 12 16 13 Officer Selection PRDP-IS-VIS-PRO-001-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Procurement Unit IBRD / 84210 Post Direct Selection Direct 19,764.71 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Head PRDP-IS-VIS-BUD-003-000- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-AF / Financial Analyst I Implementation Support 11 17 13 PRDP-IS-VIS-R006-GGU- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 002-2018-AF / GIS Data Implementation Support 11 17 13 Officer PRDP-IS-VIS-GGU-002-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Development Associate PRDP-IS-VIS-R006-IB-004- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Infrastructure Engineer PRDP-IS-VIS-MAE-002-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Monitorig & IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Evaluation Officer PRDP-IS-VIS-MAE-003-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Monitorig & IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Evaluation Officer PRDP-IS-VIS-INF-001-000- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-AF / Writer / InfoAce Implementation Support 11 17 13 PRDP-IS-VIS-PRO-002-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Procurement IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Officer PRDP-IS-VIS-R006-FIN-002- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-AF / Financial Analyst I Implementation Support 11 17 13 PRDP-IS-VIS-R006-ADM- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 4,235.29 0.00 Canceled 2018-01-01 003-2018-AF / Cash Clerk Implementation Support 11 17 13 PRDP-IS-VIS-R008-SES-001- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Environmental IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Safeguard Officer PRDP-IS-VIS-R008-BUD- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 001-2018-AF / Financial Implementation Support 11 17 13 Analyst I PRDP-IS-VIS-R008-ADM- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 4,235.29 0.00 Canceled 2018-01-01 003-2018-AF / Cash Clerk Implementation Support 11 17 13 PRDP-IS-VIS-ADM-005-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Administrative IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Staff PRDP-IS-VIS-R006-MAE- Component 4: Project 2018-01- 2018-03- 2018-09- 004-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Development Associate PRDP-IS-VIS-R008-SES-002- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Environmental IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Safegusrd Officer PRDP-IS-VIS-R006-MAE- Component 4: Project 2018-01- 2018-03- 2018-09- 001-2018-AF / Monitoring IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 and Evaluation Officer PRDP-IS-VIS-R006-FIN-004- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Development Associate PRDP-IS-VIS-R008-GGU- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 001-2018-AF / GIS Data Implementation Support 11 17 13 Officer PRDP-IS-VIS-R008-ADM- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 002-2018-AF / Driver Implementation Support 11 17 13 PRDP-IS-VIS-INF-002-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Layout Artist / IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Videographer PRDP-IS-VIS-SES-001-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Environmental IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Safeguard Officer PRDP-IS-VIS-BUD-002-000- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-AF / Financial Analyst I Implementation Support 11 17 13 PRDP-IS-VIS-FIN-003-000- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 2018-AF / Financial Analyst Implementation Support 11 17 13 II Page 2 PRDP-IS-VIS-R006-IB-008- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Development Associate PRDP-IS-VIS-R006-PRO- Component 4: Project 2018-01- 2018-03- 2018-09- 001-2018-AF / Procurement IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Specialist PRDP-IS-VIS-R006-PRO- Component 4: Project 2018-01- 2018-03- 2018-09- 002-2018-AF / Procurement IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Officer PRDP-IS-VIS-R006-PRO- Component 4: Project 2018-01- 2018-03- 2018-09- 003-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Development Associate PRDP-IS-VIS-R006-BUD- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 001-2018-AF / Budget Implementation Support 11 17 13 Specialist PRDP-IS-VIS-R008-000- Component 4: Project 2018-01- 2018-03- 2018-09- 003-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Development Associate PRDP-IS-VIS-DPD-004-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Executive IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Assistant PRDP-IS-VIS-GGU-001-000- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 2018-AF / GIS Data Officer Implementation Support 11 17 13 PRDP-IS-VIS-R006-OPD- Component 4: Project 2018-01- 2018-03- 2018-09- 001-2018-AF / Executive IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Assistant PRDP-IS-VIS-R006-BUD- Component 4: Project 2018-01- 2018-03- 2018-09- 002-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Development Associate PRDP-IS-VIS-R006-FIN-001- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-AF / Financial Analyst Implementation Support 11 17 13 II PRDP-IS-VIS-R006-ADM- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 004-2018-AF / Driver Implementation Support 11 17 13 PRDP-IS-VIS-R008-MAE- Component 4: Project 2018-01- 2018-03- 2018-09- 001-2018-AF / Monitoring IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 and Evaluation Officer PRDP-IS-VIS-R006-IB-001- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Alternate I-BUILD IBRD / 84210 Post Direct Selection Direct 16,941.18 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Component Head PRDP-IS-VIS-R006-SES-003- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Development Associate PRDP-IS-VIS-R006-SES-001- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Environmental IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Safeguard Specialist PRDP-IS-VIS-R006-GGU- Component 4: Project 2018-01- 2018-03- 2018-09- 001-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Development Associate PRDP-IS-VIS-R008-IB-005- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Development Associate PRDP-IS-VIS-R008-ADM- Component 4: Project 2018-01- 2018-03- 2018-09- 001-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Development Associate PRDP-IS-VIS-ECO-001-000- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 14,117.65 0.00 Canceled 2018-01-01 2018-AF / Economist Implementation Support 11 17 13 PRDP-IS-VIS-R008-000- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 002-2018-AF / Planning Implementation Support 11 17 13 Officer PRDP-IS-VIS-R006-MAE- Component 4: Project 2018-01- 2018-03- 2018-09- 002-2018-AF / Monitoring IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 and Evaluation Specialist PRDP-IS-VIS-R006-ADM- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 005-2018-AF / Driver Implementation Support 11 17 13 PRDP-IS-VIS-ADM-014-000- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 4,235.29 0.00 Canceled 2018-01-01 2018-AF / Utility Staff Implementation Support 11 17 13 PRDP-IS-VIS-R006-MAE- Component 4: Project 2018-01- 2018-03- 2018-09- 003-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Development Associate PRDP-IS-VIS-ADM-013-000- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 5,082.35 0.00 Canceled 2018-01-01 2018-AF / Messengerial Implementation Support 11 17 13 Staff PRDP-IS-VIS-FIN-004-000- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-AF / Financial Analyst I Implementation Support 11 17 13 PRDP-IS-VIS-R008-000- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 001-2018-AF / Planning Implementation Support 11 17 13 Officer PRDP-IS-VIS-R006-SES-002- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Social Safeguard IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Specialist PRDP-IS-VIS-R008-FIN-001- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-AF / Financial Analyst I Implementation Support 11 17 13 PRDP-IS-VIS-OPD-003-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Executive IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Assistant PRDP-IS-VIS-R006-FIN-003- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-AF / Financial Analyst I Implementation Support 11 17 13 PRDP-IS-VIS-R008-PRO- Component 4: Project 2018-01- 2018-03- 2018-09- 002-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Development Associate PRDP-IS-VIS-R006-ADM- Component 4: Project 2018-01- 2018-03- 2018-09- 002-2018-AF / IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Administrative Officer I PRDP-IS-VIS-IB-004-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Infrastructure Engineer PRDP-IS-VIS-PRO-006-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Development Associate PRDP-IS-VIS-ACC-010-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Development Associate PRDP-IS-VIS-SES-002-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Environmental IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Safeguard Officer PRDP-IS-VIS-R008-IB-001- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Infrastructure Engineer PRDP-IS-VIS-FIN-001-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / LGU Finance IBRD / 84210 Post Direct Selection Direct 16,941.18 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Supervisor PRDP-IS-VIS-R006-INF-001- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-AF / Web Implementation Support 11 17 13 Administrator PRDP-IS-VIS-ADM-011-000- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-AF / Driver Implementation Support 11 17 13 PRDP-IS-VIS-ADM-006-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Administrative IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Staff PRDP-IS-VIS-FIN-005-000- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-AF / Financial Analyst I Implementation Support 11 17 13 PRDP-IS-VIS-MAE-004-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Development Associate Page 3 PRDP-IS-VIS-ADM-001-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Administrative IBRD / 84210 Post Direct Selection Direct 19,764.71 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Unit Head PRDP-IS-VIS-PRO-005-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Development Associate PRDP-IS-VIS-OPD-002-000- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 15,529.41 0.00 Canceled 2018-01-01 2018-AF / Legal Officer Implementation Support 11 17 13 PRDP-IS-VIS-ADM-004-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Administrative IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Officer I PRDP-IS-VIS-R006-IB-002- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Infrastructure Engineer PRDP-IS-VIS-R008-IB-002- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Infrastructure Engineer PRDP-IS-VIS-ADM-012-000- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-AF / Driver Implementation Support 11 17 13 PRDP-IS-VIS-FIN-006-000- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-AF / Financial Analyst I Implementation Support 11 17 13 PRDP-IS-VIS-R006-IB-007- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Infrastructure Engineer PRDP-IS-VIS-DPD-001-000- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 14,117.65 0.00 Canceled 2018-01-01 2018-AF / Compliance Implementation Support 11 17 13 Officer PRDP-IS-VIS-IB-002-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Infrastructure Engineer PRDP-IS-VIS-IB-005-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Infrastructure Engineer PRDP-IS-VIS-R008-IB-003- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Infrastructure Engineer PRDP-IS-VIS-ADM-007-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Administrative IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Staff PRDP-IS-VIS-R006-IB-005- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Infrastructure Engineer PRDP-IS-VIS-ADM-002-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Administrative IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Officer III PRDP-IS-VIS-MAE-001-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Monitorig & IBRD / 84210 Post Direct Selection Direct 19,764.71 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Evaluation Unit Head PRDP-IS-VIS-R008-IB-004- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Infrastructure Engineer PRDP-IS-VIS-R006-IB-006- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Infrastructure Engineer PRDP-IS-VIS-ADM-010-000- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-AF / Driver 1 Implementation Support 11 17 13 PRDP-IS-VIS-R006-IB-003- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Infrastructure Engineer PRDP-IS-VIS-FIN-002-000- Component 4: Project 2018-01- 2018-03- 2018-09- IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 2018-AF / Financial Analyst Implementation Support 11 17 13 II PRDP-IS-VIS-R006-ADM- Component 4: Project 2018-01- 2018-03- 2018-09- 001-2018-AF / IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Administrative Officer III PRDP-IS-VIS-DPD-005-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Development Associate PRDP-IS-VIS-IB-006-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Development Associate PRDP-IS-VIS-IB-003-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Infrastructure Engineer PRDP-IS-VIS-IB-001-000- Component 4: Project 2018-01- 2018-03- 2018-09- 2018-AF / I-BUILD IBRD / 84210 Post Direct Selection Direct 19,764.71 0.00 Canceled 2018-01-01 Implementation Support 11 17 13 Component Head PRDP-VIS-DPD-AF-2019- Individual Component 4: Project Under 2018-12- 2019-04- 2019-05- 2019-06- 2019-12- 001 / Compliance/Legal IBRD / 88160 Post Consultant Open 11,764.71 0.00 2019-03-01 Implementation Support Implementation 05 19 10 14 11 Officer Selection PRDP-VIS-DPD-AF-2019- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- 002 / Administrative Officer IBRD / 88160 Post Consultant Open 7,058.82 0.00 2019-03-01 Implementation Support Implementation 19 10 14 11 II Selection Individual PRDP-VIS-DPD-AF-2019- Component 4: Project 2018-12- 2019-04- 2019-02- 2019-05- 2019-02- 2019-06- 2019-02- 2019-12- 2019-12- IBRD / 88160 Post Consultant Open 10,588.24 9,529.41 Completed 2019-03-01 004 / Economist Implementation Support 06 19 04 10 18 14 18 11 31 Selection PRDP-VIS-INF-AF-2019- Individual Component 4: Project Under 2018-12- 2019-04- 2019-05- 2019-06- 2019-12- 005 / Media Production IBRD / 88160 Post Consultant Open 8,235.29 0.00 2019-03-01 Implementation Support Implementation 05 19 10 14 11 Officer Selection Individual PRDP-VIS-INF-AF-2019- Component 4: Project 2018-12- 2019-01- 2018-11- 2019-02- 2018-12- 2019-03- 2018-12- 2019-09- 2019-12- IBRD / 88160 Post Consultant Direct 11,294.12 11,294.12 Completed 2019-01-01 006 / Writer Implementation Support 05 11 12 01 28 08 28 04 31 Selection Individual PRDP-VIS-IB-AF-2019-001 Component 4: Project 2018-12- 2019-01- 2018-11- 2019-02- 2018-12- 2019-03- 2018-12- 2019-09- 2019-12- IBRD / 88160 Post Consultant Direct 19,764.71 19,795.76 Completed 2019-01-01 / I-BUILD Component Head Implementation Support 06 11 12 01 28 08 28 04 31 Selection PRDP-VIS-IB-AF-2019-002 Individual Component 4: Project 2018-12- 2019-01- 2018-11- 2019-02- 2018-12- 2019-03- 2018-12- 2019-09- 2019-12- / Rural Infrastructure IBRD / 88160 Post Consultant Direct 12,705.88 12,725.85 Completed 2019-01-01 Implementation Support 06 11 12 01 28 08 28 04 31 Engineer - 1 Selection PRDP-VIS-IB-AF-2019-003 Individual Component 4: Project 2018-12- 2019-01- 2018-11- 2019-02- 2018-12- 2019-03- 2018-12- 2019-09- 2019-12- / Rural Infrastructure IBRD / 88160 Post Consultant Direct 12,705.88 12,725.85 Completed 2019-01-01 Implementation Support 06 11 12 01 28 08 28 04 31 Engineer - 2 Selection PRDP-VIS-IB-AF-2019-004 Individual Component 4: Project 2018-12- 2019-01- 2018-11- 2019-02- 2018-12- 2019-03- 2018-12- 2019-09- 2019-12- / Rural Infrastructure IBRD / 88160 Post Consultant Direct 12,705.88 12,725.85 Completed 2019-01-01 Implementation Support 06 11 12 01 28 08 28 04 31 Engineer - 3 Selection PRDP-VIS-IB-AF-2019-005 Individual Component 4: Project 2018-12- 2019-01- 2018-11- 2019-02- 2019-01- 2019-03- 2019-01- 2019-09- 2019-12- / Project Development IBRD / 88160 Post Consultant Direct 8,470.59 8,483.90 Completed 2019-01-01 Implementation Support 06 11 12 01 03 08 03 04 31 Associate Selection PRDP-VIS-IS-PRO-AF-2019- Individual Component 4: Project 2018-12- 2019-01- 2018-11- 2019-02- 2019-01- 2019-03- 2019-01- 2019-09- 2019-12- 001 / Procurement Unit IBRD / 88160 Post Consultant Direct 18,352.94 18,649.14 Completed 2019-01-01 Implementation Support 06 11 12 01 03 08 03 04 31 Head Selection PRDP-VIS-IS-PRO-AF-2019- Individual Component 4: Project 2018-12- 2019-01- 2018-11- 2019-02- 2018-12- 2019-03- 2018-12- 2019-09- 2019-12- 002 / Procurement Officer - IBRD / 88160 Post Consultant Direct 12,705.88 12,910.94 Completed 2019-01-01 Implementation Support 06 11 12 01 28 08 28 04 31 1 Selection PRDP-VIS-IS-PRO-AF-2019- Individual Component 4: Project 2018-12- 2019-01- 2018-11- 2019-02- 2019-01- 2019-03- 2019-01- 2019-09- 2019-12- 003 / Procurement Officer - IBRD / 88160 Post Consultant Direct 12,705.88 12,980.77 Completed 2019-01-01 Implementation Support 06 11 12 01 03 08 03 04 31 2 Selection PRDP-VIS-IS-PRO-AF-2019- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- 004 / Associate Procurement IBRD / 88160 Post Consultant Open 9,411.76 0.00 2019-03-01 Implementation Support Implementation 19 10 14 11 Officer Selection PRDP-VIS-IS-MAE-AF-2019- Individual Component 4: Project Under 2018-12- 2019-01- 2018-11- 2019-02- 2019-03- 2019-09- 001 / Monitorig & Evaluation IBRD / 88160 Post Consultant Direct 18,352.94 0.00 2019-01-01 Implementation Support Implementation 05 11 12 01 08 04 Unit Head Selection PRDP-VIS-IS-MAE-AF-2019- Individual Component 4: Project Under 2018-12- 2019-01- 2018-11- 2019-02- 2018-12- 2019-03- 2019-09- 002 / Monitorig & Evaluation IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2019-01-01 Implementation Support Implementation 05 11 12 01 28 08 04 Officer - 1 Selection Page 4 PRDP-VIS-IS-MAE-AF-2019- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- 003 / Monitorig & Evaluation IBRD / 88160 Post Consultant Open 10,588.24 0.00 2019-03-01 Implementation Support Implementation 19 10 14 11 Officer - 2 Selection Individual PRDP-VIS-IS-GGU-AF-2019- Component 4: Project 2018-12- 2019-01- 2018-11- 2019-02- 2019-01- 2019-03- 2019-01- 2019-09- 2019-12- IBRD / 88160 Post Consultant Direct 12,705.88 12,705.88 Completed 2019-01-01 001 / GIS Officer - 1 Implementation Support 05 11 12 01 03 08 03 04 31 Selection Individual PRDP-VIS-IS-GGU-AF-2019- Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 88160 Post Consultant Open 10,588.24 0.00 2019-03-01 002 / GIS Officer - 2 Implementation Support Implementation 19 10 14 11 Selection Individual PRDP-VIS-IS-SES-AF-2019- Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 88160 Post Consultant Open 11,764.71 0.00 2019-03-01 001 / SES Specialist Implementation Support Implementation 19 10 14 11 Selection Individual PRDP-VIS-IS-SES-AF-2019- Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 88160 Post Consultant Open 10,588.24 0.00 2019-03-01 002 / SES Officer - 1 Implementation Support Implementation 19 10 14 11 Selection Individual PRDP-VIS-IS-SES-AF-2019- Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 88160 Post Consultant Open 10,588.24 0.00 2019-03-01 003 / SES Officer - 2 Implementation Support Implementation 19 10 14 11 Selection Individual PRDP-VIS-IS-BUD-AF-2019- Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 88160 Post Consultant Open 9,411.76 0.00 2019-03-01 001 / Budget Analyst Implementation Support Implementation 19 10 14 11 Selection PRDP-VIS-IS-FIN-AF-2019- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- 001 / Finance Analyst III / IBRD / 88160 Post Consultant Open 11,764.71 0.00 2019-03-01 Implementation Support Implementation 19 10 14 11 Finance Specialist Selection Individual PRDP-VIS-IS-FIN-AF-2019- Component 4: Project 2018-12- 2019-01- 2018-11- 2019-02- 2019-01- 2019-03- 2019-01- 2019-09- 2019-12- IBRD / 88160 Post Consultant Direct 12,705.88 12,954.82 Completed 2019-01-01 002 / Finance Analyst II - 1 Implementation Support 05 11 12 01 03 08 03 04 31 Selection Individual PRDP-VIS-IS-FIN-AF-2019- Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 88160 Post Consultant Open 10,588.24 0.00 2019-03-01 003 / Finance Analyst II - 2 Implementation Support Implementation 19 10 14 11 Selection Individual PRDP-VIS-IS-FIN-AF-2019- Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 88160 Post Consultant Open 10,588.24 0.00 2019-03-01 004 / Finance Analyst II - 3 Implementation Support Implementation 19 10 14 11 Selection Individual PRDP-VIS-IS-FIN-AF-2019- Component 4: Project 2018-12- 2019-01- 2018-11- 2019-02- 2018-12- 2019-03- 2018-12- 2019-09- 2019-12- IBRD / 88160 Post Consultant Direct 11,294.12 11,515.39 Completed 2019-01-01 005 / Finance Analyst I Implementation Support 05 11 12 01 28 08 28 04 31 Selection PRDP-VIS-IS-ADM-AF-2019- Individual Component 4: Project Under 2018-12- 2019-01- 2019-02- 2019-03- 2019-09- 001 / Administrative Unit IBRD / 88160 Post Consultant Direct 18,352.94 0.00 2019-01-01 Implementation Support Implementation 05 11 01 08 04 Head Selection PRDP-VIS-IS-ADM-AF-2019- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 002 / Administrative Officer IBRD / 88160 Post Consultant Direct 8,470.59 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 III Selection PRDP-IS-VIS-OPD-003-000- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Executive IBRD / 88160 Post Consultant Direct 823.53 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Assistant Selection PRDP-IS-VIS-DPD-001-000- Individual Component 4: Project 2018-12- 2019-01- 2018-12- 2019-02- 2018-12- 2019-03- 2018-12- 2019-09- 2019-02- 2018-AF-E / Compliance IBRD / 88160 Post Consultant Direct 2,352.94 1,238.03 Completed 2019-01-01 Implementation Support 05 11 27 01 28 08 28 04 28 Officer Selection Individual PRDP-IS-VIS-OPD-002-000- Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 2,588.24 0.00 2019-01-01 2018-AF-E / Legal Oficer Implementation Support Implementation 11 01 08 04 Selection PRDP-IS-VIS-DPD-004-000- Individual Component 4: Project Under 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Executive IBRD / 88160 Post Consultant Direct 1,647.06 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Assistant Selection PRDP-IS-VIS-DPD-005-000- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,411.76 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Development Associate Selection PRDP-IS-VIS-GGU-002-000- Individual Component 4: Project 2018-12- 2019-01- 2018-11- 2019-02- 2018-12- 2019-03- 2018-12- 2019-09- 2019-02- 2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,411.76 743.56 Completed 2019-01-01 Implementation Support 05 11 12 01 28 08 28 04 28 Development Associate Selection PRDP-IS-VIS-INF-002-000- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Graphic Layout IBRD / 88160 Post Consultant Direct 1,647.06 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Artist Selection PRDP-IS-VIS-IB-005-000- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Rural IBRD / 88160 Post Consultant Direct 2,117.65 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Infrastructure Engineer Selection PRDP-IS-VIS-PRO-005-000- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,411.76 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Development Associate Selection PRDP-IS-VIS-PRO-006-000- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,411.76 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Development Associate Selection PRDP-IS-VIS-MAE-003-000- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Monitoring & IBRD / 88160 Post Consultant Direct 2,117.65 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Evaluation Officer Selection PRDP-IS-VIS-SES-002-000- Individual Component 4: Project Under 2018-12- 2019-01- 2018-11- 2019-02- 2019-03- 2019-09- 2018-AF-E / Environmental IBRD / 88160 Post Consultant Direct 2,117.65 0.00 2019-01-01 Implementation Support Implementation 05 11 12 01 08 04 Safeguard Officer Selection PRDP-IS-VIS-SES-001-000- Individual Component 4: Project 2018-12- 2019-01- 2018-11- 2019-02- 2018-12- 2019-03- 2018-12- 2019-09- 2019-02- 2018-AF-E / Environmental IBRD / 88160 Post Consultant Direct 2,117.65 1,114.27 Completed 2019-01-01 Implementation Support 05 11 12 01 28 08 28 04 28 Safeguard Officer Selection PRDP-IS-VIS-FIN-002-000- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Budget IBRD / 88160 Post Consultant Direct 2,352.94 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Specialist Selection PRDP-IS-VIS-FIN-004-000- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Finance Analyst IBRD / 88160 Post Consultant Direct 1,882.35 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 I Selection PRDP-IS-VIS-BUD-003-000- Individual Component 4: Project 2018-12- 2019-01- 2018-11- 2019-02- 2018-12- 2019-03- 2018-12- 2019-09- 2019-02- 2018-AF-E / Finance Analyst IBRD / 88160 Post Consultant Direct 1,882.35 991.41 Completed 2019-01-01 Implementation Support 05 11 12 01 27 08 28 04 28 I Selection PRDP-IS-VIS-BUD-002-000- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Finance Analyst IBRD / 88160 Post Consultant Direct 1,882.35 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 I Selection PRDP-IS-VIS-FIN-003-000- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Finance Analyst IBRD / 88160 Post Consultant Direct 2,117.65 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 II Selection PRDP-IS-VIS-ADM-003-000- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Administrative IBRD / 88160 Post Consultant Direct 1,607.84 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Officer III Selection PRDP-IS-VIS-ADM-004-000- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Administrative IBRD / 88160 Post Consultant Direct 1,411.76 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Officer I Selection PRDP-VIS-R006-IB-AF- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- 2019-001 / Rural IBRD / 88160 Post Consultant Open 10,588.24 0.00 2019-03-01 Implementation Support Implementation 19 10 14 11 Infrastructure Specialist Selection PRDP-VIS-R006-IS-MAE-AF- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- 2019-002 / Associate M&E IBRD / 88160 Post Consultant Open 8,235.29 0.00 2019-03-01 Implementation Support Implementation 19 10 14 11 Officer Selection Individual PRDP-VIS-R006-IS-SES-AF- Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 88160 Post Consultant Open 9,411.76 0.00 2019-03-01 2019-001 / SES Officer - 1 Implementation Support Implementation 19 10 14 11 Selection Individual PRDP-VIS-R006-IS-SES-AF- Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 88160 Post Consultant Open 9,411.76 0.00 2019-03-01 2019-002 / SES Officer - 2 Implementation Support Implementation 19 10 14 11 Selection PRDP-VIS-R006-IS-SES-AF- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- 2019-003 / Associate SES IBRD / 88160 Post Consultant Open 8,235.29 0.00 2019-03-01 Implementation Support Implementation 19 10 14 11 Officer Selection PRDP-VIS-R006-IS-INF-AF- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- 2019-001 / Media IBRD / 88160 Post Consultant Open 7,058.82 0.00 2019-03-01 Implementation Support Implementation 19 10 14 11 Production Officer Selection PRDP-VIS-R006-IS-PRO-AF- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- 2019-002 / Associate IBRD / 88160 Post Consultant Open 8,235.29 0.00 2019-03-01 Implementation Support Implementation 19 10 14 11 Procurement Officer Selection PRDP-VIS-R006-IS-ADM-AF- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- 2019-001 / Administrative IBRD / 88160 Post Consultant Open 5,882.35 0.00 2019-03-01 Implementation Support Implementation 19 10 14 11 Officer II Selection Page 5 PRDP-VIS-R007-IB-AF- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- 2019-001 / Rural IBRD / 88160 Post Consultant Open 9,529.41 0.00 2019-03-01 Implementation Support Implementation 19 10 14 11 Infrastructure Specialist Selection PRDP-VIS-R007-IS-MAE-AF- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- 2019-002 / Associate M&E IBRD / 88160 Post Consultant Open 8,235.29 0.00 2019-03-01 Implementation Support Implementation 19 10 14 11 Officer Selection Individual PRDP-VIS-R007-IS-SES-AF- Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 88160 Post Consultant Open 9,411.76 0.00 2019-03-01 2019-001 / SES Officer Implementation Support Implementation 19 10 14 11 Selection PRDP-VIS-R007-IS-ADM-AF- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- 2019-001 / Administrative IBRD / 88160 Post Consultant Open 7,058.82 0.00 2019-03-01 Implementation Support Implementation 19 10 14 11 Officer II Selection PRDP-VIS-R008-IB-AF- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2019-002 / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Infrastructure Engineer - 2 Selection PRDP-VIS-R008-IB-AF- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2019-003 / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Infrastructure Engineer - 3 Selection PRDP-VIS-R008-IB-AF- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2019-004 / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Infrastructure Engineer - 4 Selection PRDP-VIS-R008-IB-AF- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2019-005 / Project IBRD / 88160 Post Consultant Direct 7,058.82 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Development Associate Selection Individual PRDP-VIS-R008-IS-GGU-AF- Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2019-01-01 2019-001 / GIS Data Officer Implementation Support Implementation 11 01 08 04 Selection Individual PRDP-VIS-R008-IS-BUD-AF- Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2019-01-01 2019-001 / Budget Analyst I Implementation Support Implementation 11 01 08 04 Selection PRDP-VIS-R008-IS-FIN-AF- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2019-001 / Finance Analyst IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 I-1 Selection PRDP-VIS-R008-IS-ACC-AF- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2019-002 / Finance Analyst IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 I-2 Selection PRDP-VIS-R008-IS-PRO-AF- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- 2019-001 / Procurement IBRD / 88160 Post Consultant Open 9,411.76 0.00 2019-03-01 Implementation Support Implementation 19 10 14 11 Officer Selection PRDP-VIS-R008-IS-PRO-AF- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- 2019-002 / Associate IBRD / 88160 Post Consultant Open 8,235.29 0.00 2019-03-01 Implementation Support Implementation 19 10 14 11 Procurement Officer Selection Individual PRDP-VIS-R008-IS-MAE-AF- Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 88160 Post Consultant Open 9,411.76 0.00 2019-03-01 2019-001 / M&E Officer Implementation Support Implementation 19 10 14 11 Selection PRDP-VIS-R008-IS-MAE-AF- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- 2019-002 / Associate M&E IBRD / 88160 Post Consultant Open 8,235.29 0.00 2019-03-01 Implementation Support Implementation 19 10 14 11 Officer Selection Individual PRDP-VIS-R008-IS-SES-AF- Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 88160 Post Consultant Open 9,411.76 0.00 2019-03-01 2019-001 / SES Officer Implementation Support Implementation 19 10 14 11 Selection PRDP-VIS-R008-IS-SES-AF- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- 2019-002 / Associate SES IBRD / 88160 Post Consultant Open 8,235.29 0.00 2019-03-01 Implementation Support Implementation 19 10 14 11 Officer Selection Individual PRDP-VIS-R008-IS-INF-AF- Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 88160 Post Consultant Open 8,235.29 0.00 2019-03-01 2019-001 / Writer Implementation Support Implementation 19 10 14 11 Selection PRDP-IS-VIS-R006-OPD- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 001-2018-AF-E / Executive IBRD / 88160 Post Consultant Direct 1,411.76 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Assistant Selection PRDP-IS-VIS-R006-OPD- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 003-2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,176.47 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Development Associate Selection PRDP-IS-VIS-R006-PRO- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 003-2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,176.47 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Development Associate Selection PRDP-IS-VIS-R006-MAE- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 003-2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,176.47 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Development Associate Selection PRDP-IS-VIS-R006-SES-001- Individual Component 4: Project Under 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Environmental IBRD / 88160 Post Consultant Direct 2,117.65 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Safeguard Specialist Selection PRDP-IS-VIS-R006-SES-002- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Social IBRD / 88160 Post Consultant Direct 2,117.65 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Safeguard Specialist Selection PRDP-IS-VIS-R006-SES-003- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,176.47 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Development Associate Selection PRDP-IS-VIS-R006-INF-001- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Web IBRD / 88160 Post Consultant Direct 1,647.06 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Administrator Selection PRDP-IS-VIS-R006-FIN-004- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,176.47 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Development Associate Selection PRDP-IS-VIS-R006-IB-001- Individual Component 4: Project Under 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Alternate I- IBRD / 88160 Post Consultant Direct 2,823.53 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 BUILD Component Head Selection PRDP-IS-VIS-R006-IB-003- Individual Component 4: Project Under 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Rural IBRD / 88160 Post Consultant Direct 1,882.35 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Infrastructure Engineer - 1 Selection PRDP-IS-VIS-R006-IB-004- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Rural IBRD / 88160 Post Consultant Direct 1,882.35 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Infrastructure Engineer - 2 Selection PRDP-IS-VIS-R006-IB-005- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Rural IBRD / 88160 Post Consultant Direct 1,882.35 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Infrastructure Engineer - 3 Selection PRDP-IS-VIS-R007-IB-001- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Rural IBRD / 88160 Post Consultant Direct 1,882.35 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Infrastructure Engineer - 4 Selection PRDP-IS-VIS-R007-SES-001- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Environmental IBRD / 88160 Post Consultant Direct 1,882.35 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Safeguard Officer - 1 Selection PRDP-IS-VIS-R007-SES-002- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Environmental IBRD / 88160 Post Consultant Direct 1,882.35 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Safeguard Officer - 2 Selection PRDP-IS-VIS-R007-SES-003- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Social IBRD / 88160 Post Consultant Direct 1,882.35 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Safeguard Officer Selection PRDP-IS-VIS-R007-MAE- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 003-2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,176.47 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Development Associate Selection PRDP-IS-VIS-R007-OPD- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 003-2018-AF-E / IBRD / 88160 Post Consultant Direct 2,117.65 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Compliance Officer Selection PRDP-IS-VIS-R008-SES-001- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Environmental IBRD / 88160 Post Consultant Direct 1,882.35 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Safeguard Officer - 1 Selection PRDP-IS-VIS-R008-SES-002- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2018-AF-E / Environmental IBRD / 88160 Post Consultant Direct 1,882.35 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Safeguard Officer - 2 Selection PRDP-IS-VIS-R008-ADM- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 001-2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,176.47 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Development Associate Selection PRDP-IS-VIS-R008-PRO- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 002-2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,176.47 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Development Associate Selection Page 6 PRDP-VIS-R007-IS-SES-AF- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- 2019-002 / Associate SES IBRD / 88160 Post Consultant Open 8,235.29 0.00 2019-03-01 Implementation Support Implementation 19 10 14 11 Officer Selection PRDP-VIS-R007-IS-PRO-AF- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2019-001 / Procurement IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Officer Selection Individual PRDP-VIS-R007-IS-GGU-AF- Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2019-01-01 2019-001 / GIS Officer Implementation Support Implementation 11 01 08 04 Selection Individual PRDP-VIS-R007-IS-MAE-AF- Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2019-01-01 2019-001 / M&E Officer Implementation Support Implementation 11 01 08 04 Selection Individual PRDP-VIS-R007-IS-INF-AF- Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2019-01-01 2019-001 / Writer Implementation Support Implementation 11 01 08 04 Selection PRDP-VIS-R008-IB-AF- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2019-001 / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Infrastructure Engineer - 1 Selection PRDP-VIS-R007-IS-PRO-AF- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2019-002 / Associate IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Procurement Officer Selection PRDP-VIS-R006-IB-AF- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2019-002 / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Infrastructure Engineer - 1 Selection PRDP-VIS-R006-IB-AF- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2019-003 / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Infrastructure Engineer - 2 Selection PRDP-VIS-R006-IB-AF- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- 2019-005 / Rural IBRD / 88160 Post Consultant Open 9,411.76 0.00 2019-03-01 Implementation Support Implementation 19 10 14 11 Infrastructure Engineer - 3 Selection PRDP-VIS-R006-IB-AF- Individual Component 4: Project Under 2018-12- 2019-04- 2019-05- 2019-06- 2019-12- 2019-006 / Rural IBRD / 88160 Post Consultant Open 9,411.76 0.00 2019-03-01 Implementation Support Implementation 06 19 10 14 11 Infrastructure Engineer - 4 Selection PRDP-VIS-R006-IB-AF- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-12- 2019-007 / Rural IBRD / 88160 Post Consultant Open 9,411.76 0.00 2019-03-01 Implementation Support Implementation 19 10 14 11 Infrastructure Engineer - 5 Selection PRDP-VIS-R006-IB-AF- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2019-004 / Project IBRD / 88160 Post Consultant Direct 7,058.82 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Development Associate Selection Individual PRDP-VIS-R006-IS-MAE-AF- Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2019-01-01 2019-001 / M&E Officer Implementation Support Implementation 11 01 08 04 Selection Individual PRDP-VIS-R006-IS-GGU-AF- Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2019-01-01 2019-001 / GIS Officer Implementation Support Implementation 11 01 08 04 Selection PRDP-VIS-R006-IS-PRO-AF- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2019-001 / Procurement IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Officer Selection Individual PRDP-VIS-R006-IS-BUD-AF- Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2019-01-01 2019-001 / Budget Analyst I Implementation Support Implementation 11 01 08 04 Selection PRDP-VIS-R006-IS-FIN-AF- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2019-001 / Finance Analyst IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 I-1 Selection PRDP-VIS-R006-IS-FIN-AF- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2019-002 / Finance Analyst IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 I-2 Selection PRDP-VIS-R006-IS-FIN-AF- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2019-003 / Finance Analyst IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 I-3 Selection Individual PRDP-VIS-R007-IS-ECO-AF- Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2019-01-01 2019-001 / Economist Implementation Support Implementation 11 01 08 04 Selection PRDP-VIS-R007-IB-AF- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2019-002 / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Infrastructure Engineer - 1 Selection PRDP-VIS-R007-IB-AF- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2019-003 / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Infrastructure Engineer - 2 Selection PRDP-VIS-R007-IB-AF- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2019-004 / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Infrastructure Engineer - 3 Selection PRDP-VIS-R007-IB-AF- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 2019-005 / Program IBRD / 88160 Post Consultant Direct 7,058.82 0.00 2019-01-01 Implementation Support Implementation 11 01 08 04 Development Associate Selection Individual PRDP-VIS-R007-IS-BUD-AF- Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2019-01-01 2019-001 / Budget Analyst I Implementation Support Implementation 11 01 08 04 Selection PRDP-VIS-R007-IS-ACC-AF- Individual Component 4: Project Under 2018-12- 2019-01- 2019-02- 2019-03- 2019-09- 2019-001 / Finance Analyst IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2019-01-01 Implementation Support Implementation 06 11 01 08 04 I Selection PRDP-VIS-002-ADM-001- Individual Component 4: Project Under 2019-12- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Administrative IBRD / 88160 Post Consultant Direct 8,470.59 0.00 2020-01-02 Implementation Support Implementation 19 12 02 08 04 Officer II Selection PRDP-VIS-001-DPD-001- Individual Component 4: Project Under 2018-12- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Compliance IBRD / 88160 Post Consultant Direct 14,117.65 0.00 2020-01-02 Implementation Support Implementation 05 12 02 08 04 Officer Selection Individual PRDP-VIS-003-DPD-002- Component 4: Project Under 2018-12- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 2020-AF / Economist Implementation Support Implementation 06 12 02 08 04 Selection Individual PRDP-VIS-004-DPD-003- Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 2020-AF / GIS Officer -1 Implementation Support Implementation 01 12 02 08 04 Selection Individual PRDP-VIS-005-DPD-004- Component 4: Project Under 2018-12- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 2020-AF / GIS Officer -2 Implementation Support Implementation 05 12 02 08 04 Selection PRDP-VIS-006-IB-001- Individual Component 4: Project Under 2018-12- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / I-BUILD IBRD / 88160 Post Consultant Direct 19,764.71 0.00 2020-01-02 Implementation Support Implementation 06 12 02 08 04 Component Head Selection PRDP-VIS-007-IB-002- Individual Component 4: Project Under 2018-12- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Rural IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 Implementation Support Implementation 06 12 02 08 04 Infrastructure Engineer -1 Selection PRDP-VIS-008-IB-003- Individual Component 4: Project Under 2018-12- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Rural IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 Implementation Support Implementation 06 12 02 08 04 Infrastructure Engineer -2 Selection PRDP-VIS-009-IB-004- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Rural IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Infrastructure Engineer -3 Selection PRDP-VIS-010-IB-005- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Rural IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Infrastructure Engineer -4 Selection PRDP-VIS-011-IB-006- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Project IBRD / 88160 Post Consultant Direct 8,470.59 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Development Associate Selection PRDP-VIS-012-PRO-001- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Procurement Unit IBRD / 88160 Post Consultant Direct 18,352.94 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Head Selection PRDP-VIS-013-PRO-002- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Procurement IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Officer Selection PRDP-VIS-014-MNE-001- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Monitoring & IBRD / 88160 Post Consultant Direct 18,352.94 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Evaluation Unit Head Selection PRDP-VIS-015-MNE-002- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Monitoring & IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Evaluation Officer Selection Page 7 Individual PRDP-VIS-016-SES-001- Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 14,117.65 0.00 2020-01-02 2020-AF / SES Specialist Implementation Support Implementation 12 02 08 04 Selection Individual PRDP-VIS-017-FIN-001- Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 14,117.65 0.00 2020-01-02 2020-AF / Finance Analyst III Implementation Support Implementation 12 02 08 04 Selection PRDP-VIS-018-FIN-002- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Finance Analyst II IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 / Accountant Selection Individual PRDP-VIS-019-FIN-003- Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 2020-AF / Finance Analyst II Implementation Support Implementation 12 02 08 04 Selection Individual PRDP-VIS-020-FIN-004- Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 2020-AF / Finance Analyst I Implementation Support Implementation 12 02 08 04 Selection Individual PRDP-VIS-021-BUD-001- Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 2020-AF / Budget Analyst Implementation Support Implementation 12 02 08 04 Selection PRDP-VIS-022-ADM-001- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Administrative IBRD / 88160 Post Consultant Direct 18,352.94 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Unit Head Selection PRDP-VIS-023-ADM-002- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Adminstrative IBRD / 88160 Post Consultant Direct 8,470.59 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Officer II Selection PRDP-VIS-R006-001-ADM- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / IBRD / 88160 Post Consultant Direct 7,058.82 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Administrative Officer II Selection PRDP-VIS-R006-002-IB- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Rural IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Infrastructure Specialist Selection PRDP-VIS-R006-003-IB- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Infrastructure Engineer -1 Selection PRDP-VIS-R006-004-IB- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 003-2020-AF / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Infrastructure Engineer -2 Selection PRDP-VIS-R006-005-IB- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 004-2020-AF / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Infrastructure Engineer -3 Selection PRDP-VIS-R006-006-IB- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 005-2020-AF / Program IBRD / 88160 Post Consultant Direct 7,058.82 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Development Associate Selection Individual PRDP-VIS-R006-007-GGU- Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 001-2020-AF / GIS Officer Implementation Support Implementation 12 02 08 04 Selection PRDP-VIS-R006-008-PRO- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Procurement IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Officer Selection PRDP-VIS-R006-009-PRO- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Procurement Officer Selection Individual PRDP-VIS-R006-010-MNE- Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 001-2020-AF / M&E Officer Implementation Support Implementation 12 02 08 04 Selection PRDP-VIS-R006-011-MNE- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 M&E Officer Selection Individual PRDP-VIS-R006-012-SES- Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 001-2020-AF / SES Officer Implementation Support Implementation 12 02 08 04 Selection PRDP-VIS-R006-013-SES- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 SES Officer Selection Individual PRDP-VIS-R006-014-ACE- Component 4: Project Pending 2020-04- 2020-05- 2020-06- 2020-12- IBRD / 88160 Post Consultant Open 9,882.35 0.00 2020-03-01 001-2020-AF / Writer Implementation Support Implementation 19 10 14 11 Selection PRDP-VIS-R006-015-FIN- Individual Component 4: Project Pending 2020-04- 2020-05- 2020-06- 2020-12- 001-2020-AF / Finance IBRD / 88160 Post Consultant Open 9,882.35 0.00 2020-03-01 Implementation Support Implementation 19 10 14 11 Analyst I -1 Selection PRDP-VIS-R006-016-FIN- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF / Finance IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Analyst I -2 Selection PRDP-VIS-R006-017-FIN- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 003-2020-AF / Finance IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Analyst I Selection PRDP-VIS-R006-018-BUD- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Budget IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Analyst I Selection PRDP-VIS-R007-001-IB- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Road and IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Bridges Specialist Selection PRDP-VIS-R007-002-IB- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Infrastructure Engineer -1 Selection PRDP-VIS-R007-003-IB- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 003-2020-AF / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Infrastructure Engineer -2 Selection PRDP-VIS-R007-004-IB- Individual Component 4: Project Pending 2020-04- 2020-05- 2020-06- 2020-12- 004-2020-AF / Rural IBRD / 88160 Post Consultant Open 9,411.76 0.00 2020-03-01 Implementation Support Implementation 19 10 14 11 Infrastructure Engineer -3 Selection PRDP-VIS-R007-005-IB- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 005-2020-AF / Program IBRD / 88160 Post Consultant Direct 7,058.82 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Development Associate Selection PRDP-VIS-R007-006-BUD- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Budget IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Analyst I Selection PRDP-VIS-R007-007-ACTG- Individual Component 4: Project Pending 2020-04- 2020-05- 2020-06- 2020-12- 001-2020-AF / Finance IBRD / 88160 Post Consultant Open 9,882.35 0.00 2020-03-01 Implementation Support Implementation 19 10 14 11 Analyst I (Acctg) Selection PRDP-VIS-R007-008-FIN- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Finance IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Analyst I (Finance) Selection PRDP-VIS-R007-009-ADM- Individual Component 4: Project Pending 2020-04- 2020-05- 2020-06- 2020-12- 001-2020-AF / IBRD / 88160 Post Consultant Open 7,058.82 0.00 2020-03-01 Implementation Support Implementation 19 10 14 11 Administrative Officer II Selection Individual PRDP-VIS-R007-010-SES- Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 001-2020-AF / SES Officer Implementation Support Implementation 12 02 08 04 Selection PRDP-VIS-R007-011-SES- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 SES Officer Selection Individual PRDP-VIS-R007-012-GGU- Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 001-2020-AF / GIS Officer Implementation Support Implementation 12 02 08 04 Selection Individual PRDP-VIS-R007-013-MNE- Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 001-2020-AF / M&E Officer Implementation Support Implementation 12 02 08 04 Selection PRDP-VIS-R007-014-MNE- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 M&E Officer Selection PRDP-VIS-R007-015-PRO- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Procurement IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Officer Selection PRDP-VIS-R007-016-PRO- Individual Component 4: Project Pending 2020-04- 2020-05- 2020-06- 2020-12- 002-2020-AF / Associate IBRD / 88160 Post Consultant Open 9,882.35 0.00 2020-03-01 Implementation Support Implementation 19 10 14 11 Procurement Officer Selection Page 8 Individual PRDP-VIS-R007-017-DPD- Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 001-2020-AF / Economist Implementation Support Implementation 12 02 08 04 Selection Individual PRDP-VIS-R007-018-ACE- Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 001-2020-AF / Writer Implementation Support Implementation 12 02 08 04 Selection PRDP-VIS-R008-001-ADM- Individual 001-2020-AF / Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 7,058.82 0.00 2020-01-02 Administrative Officer II - Implementation Support Implementation 12 02 08 04 Selection ORDPD PRDP-VIS-R008-002-IB- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Infrastructure Engineer -1 Selection PRDP-VIS-R008-003-IB- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Infrastructure Engineer -2 Selection PRDP-VIS-R008-004-IB- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 003-2020-AF / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Infrastructure Engineer -3 Selection PRDP-VIS-R008-005-IB- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 004-2020-AF / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Infrastructure Engineer -4 Selection PRDP-VIS-R008-006-IB- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 005-2020-AF / Project IBRD / 88160 Post Consultant Direct 7,058.82 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Development Associate Selection Individual PRDP-VIS-R008-007-GGU- Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 001-2020-AF / GIS Officer Implementation Support Implementation 12 02 08 04 Selection PRDP-VIS-R008-008-GGU- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Procurement Officer Selection Individual PRDP-VIS-R008-009-MNE- Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 001-2020-AF / M&E Officer Implementation Support Implementation 12 02 08 04 Selection PRDP-VIS-R008-010-MNE- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 M&E Officer Selection Individual PRDP-VIS-R008-011-SES- Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 001-2020-AF / SES Officer Implementation Support Implementation 12 02 08 04 Selection PRDP-VIS-R008-012-SES- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 SES Officer Selection PRDP-VIS-R008-013-BUD- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Budget IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Analyst I Selection PRDP-VIS-R008-014-FIN- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Finance IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Analyst I -1 Selection PRDP-VIS-R008-015-ACT- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Finance IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 12 02 08 04 Analyst I -2 Selection Individual PRDP-VIS-DPD-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 5,000.00 0.00 2021-01-01 001 / Compliance Officer Implementation Support Implementation 31 11 01 08 04 Selection PRDP-VIS-DPD-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 002 / Administrative Officer IBRD / 88160 Post Consultant Direct 3,000.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 II Selection PRDP-VIS-DPD-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 003 / Administrative Officer IBRD / 88160 Post Consultant Direct 3,500.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 III Selection Individual PRDP-VIS-ECON-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 4,500.00 0.00 2021-01-01 004 / Economist Implementation Support Implementation 31 11 01 08 04 Selection Individual PRDP-VIS-GGU-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 4,500.00 0.00 2021-01-01 005 / GIS Officer Implementation Support Implementation 31 11 01 08 04 Selection Individual PRDP-VIS-GGU-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 4,500.00 0.00 2021-01-01 006 / GIS Officer Implementation Support Implementation 31 11 01 08 04 Selection Individual PRDP-VIS-INF-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 4,000.00 0.00 2021-01-01 007 / Writer Implementation Support Implementation 31 11 01 08 04 Selection PRDP-VIS-INF-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 008 / Media Production IBRD / 88160 Post Consultant Direct 3,500.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Officer Selection Individual PRDP-VIS-IB-AF-2021-009 Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 7,000.00 0.00 2021-01-01 / I-BUILD Component Head Implementation Support Implementation 31 11 01 08 04 Selection PRDP-VIS-IB-AF-2021-010 Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- / Rural Infrastructure IBRD / 88160 Post Consultant Direct 4,500.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Engineer Selection PRDP-VIS-IB-AF-2021-011 Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- / Rural Infrastructure IBRD / 88160 Post Consultant Direct 4,500.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Engineer Selection PRDP-VIS-IB-AF-2021-012 Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- / Rural Infrastructure IBRD / 88160 Post Consultant Direct 4,500.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Engineer Selection PRDP-VIS-IB-AF-2021-013 Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- / Rural Infrastructure IBRD / 88160 Post Consultant Direct 4,500.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Engineer Selection PRDP-VIS-IB-AF-2021-014 Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- / Project Development IBRD / 88160 Post Consultant Direct 3,000.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Associate Selection PRDP-VIS-PRO-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 015 / Procurement Unit IBRD / 88160 Post Consultant Direct 6,500.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Head Selection Individual PRDP-VIS-PRO-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 4,500.00 0.00 2021-01-01 016 / Procurement Officer Implementation Support Implementation 31 11 01 08 04 Selection Individual PRDP-VIS-PRO-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 4,500.00 0.00 2021-01-01 017 / Procurement Officer Implementation Support Implementation 31 11 01 08 04 Selection PRDP-VIS-PRO-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 018 / Project Development IBRD / 88160 Post Consultant Direct 3,000.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Associate Selection PRDP-VIS-MAE-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 019 / Monitoring & IBRD / 88160 Post Consultant Direct 6,500.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Evaluation Unit Head Selection PRDP-VIS-MAE-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 020 / Monitoring & IBRD / 88160 Post Consultant Direct 4,500.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Evaluation Officer Selection Individual PRDP-VIS-SES-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 5,000.00 0.00 2021-01-01 021 / SES Specialist Implementation Support Implementation 31 11 01 08 04 Selection Individual PRDP-VIS-SES-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 4,500.00 0.00 2021-01-01 022 / SES Officer Implementation Support Implementation 31 11 01 08 04 Selection Individual PRDP-VIS-FIN-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 5,000.00 0.00 2021-01-01 023 / Financial Analyst III Implementation Support Implementation 31 11 01 08 04 Selection PRDP-VIS-FIN-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 024 / Financial Analyst IBRD / 88160 Post Consultant Direct 4,500.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 II/Accountant Selection Individual PRDP-VIS-FIN-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 4,500.00 0.00 2021-01-01 025 / Financial Analyst II Implementation Support Implementation 31 11 01 08 04 Selection Page 9 Individual PRDP-VIS-FIN-AF-2021- Component 4: Project Under 2020-12- 2021-02- 2021-03- 2021-04- 2021-10- IBRD / 88160 Post Consultant Open 4,500.00 0.00 2021-01-01 026 / Financial Analyst II Implementation Support Implementation 31 19 12 16 13 Selection Individual PRDP-VIS-FIN-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 4,000.00 0.00 2021-01-01 027 / Financial Analyst I Implementation Support Implementation 31 11 01 08 04 Selection Individual PRDP-VIS-BUD-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 4,000.00 0.00 2021-01-01 028 / Budget Analyst Implementation Support Implementation 31 11 01 08 04 Selection PRDP-VIS-ADM-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 029 / Administrative Unit IBRD / 88160 Post Consultant Direct 6,500.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Head Selection PRDP-VIS-ADM-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 030 / Administrative Officer IBRD / 88160 Post Consultant Direct 3,000.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 II Selection PRDP-VIS-ADM-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 031 / Administrative IBRD / 88160 Post Consultant Direct 2,000.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Assistant Selection PRDP-VIS-R6-ADM-AF- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 2021-032 / Administrative IBRD / 88160 Post Consultant Direct 2,007.25 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Officer II Selection Individual PRDP-VIS-R6-GGU-AF- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 3,211.60 0.00 2021-01-01 2021-033 / GIS Officer Implementation Support Implementation 31 11 01 08 04 Selection Individual PRDP-VIS-R6-PRO-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 3,211.60 0.00 2021-01-01 034 / Procurement Officer Implementation Support Implementation 31 11 01 08 04 Selection PRDP-VIS-R6-PRO-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 035 / Associate Procurement IBRD / 88160 Post Consultant Direct 2,818.17 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Officer Selection Individual PRDP-VIS-R6-MAE-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 3,211.60 0.00 2021-01-01 036 / M & E Officer Implementation Support Implementation 31 11 01 08 04 Selection Individual PRDP-VIS-R6-MAE-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 2,818.17 0.00 2021-01-01 037 / Associate M&E Officer Implementation Support Implementation 31 11 01 08 04 Selection Individual PRDP-VIS-R6-SES-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 3,613.06 0.00 2021-01-01 038 / SES Officer Implementation Support Implementation 31 11 01 08 04 Selection Individual PRDP-VIS-R6-SES-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 2,810.17 0.00 2021-01-01 039 / Associate SES Officer Implementation Support Implementation 31 11 01 08 04 Selection Individual PRDP-VIS-R6-INF-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 2,810.17 0.00 2021-01-01 040 / Writer Implementation Support Implementation 31 11 01 08 04 Selection Individual PRDP-VIS-R6-FIN-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 2,810.17 0.00 2021-01-01 041 / Finance Analyst I Implementation Support Implementation 31 11 01 08 04 Selection Individual PRDP-VIS-R6-FIN-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 2,810.17 0.00 2021-01-01 042 / Finance Analyst I Implementation Support Implementation 31 11 01 08 04 Selection Individual PRDP-VIS-R6-FIN-AF-2021- Component 4: Project Under 2020-12- 2021-02- 2021-03- 2021-04- 2021-10- IBRD / 88160 Post Consultant Open 2,810.17 0.00 2021-01-01 043 / Finance Analyst I Implementation Support Implementation 31 19 12 16 13 Selection Individual PRDP-VIS-R6-BUD-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 2,810.17 0.00 2021-01-01 044 / Budget Analyst I Implementation Support Implementation 31 11 01 08 04 Selection PRDP-VIS-R6-IB-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 045 / Rural Infrastructure IBRD / 88160 Post Consultant Direct 3,613.06 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Specialist Selection PRDP-VIS-R6-IB-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 046 / Rural Infrastructure IBRD / 88160 Post Consultant Direct 3,211.60 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Engineer Selection PRDP-VIS-R6-IB-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 047 / Rural Infrastructure IBRD / 88160 Post Consultant Direct 3,211.60 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Engineer Selection PRDP-VIS-R6-IB-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 048 / Rural Infrastructure IBRD / 88160 Post Consultant Direct 3,211.60 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Engineer Selection PRDP-VIS-R6-IB-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 049 / Program Development IBRD / 88160 Post Consultant Direct 2,007.25 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Associate Selection PRDP-VIS-R7-IB-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 050 / Rural Infrastructure IBRD / 88160 Post Consultant Direct 4,541.67 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Specialist Selection PRDP-VIS-R7-IB-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 051 / Rural Infrastructure IBRD / 88160 Post Consultant Direct 4,000.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Engineer Selection PRDP-VIS-R7-IB-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 052 / Rural Infrastructure IBRD / 88160 Post Consultant Direct 3,958.33 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Engineer Selection PRDP-VIS-R7-IB-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 053 / Project Development IBRD / 88160 Post Consultant Direct 2,500.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Associate Selection Individual PRDP-VIS-R7-BUD-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 3,500.00 0.00 2021-01-01 054 / Budget Analyst I Implementation Support Implementation 31 11 01 08 04 Selection PRDP-VIS-R7-FIN-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 055 / Financial Analyst I IBRD / 88160 Post Consultant Direct 3,500.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 (Finance) Selection PRDP-VIS-R7-FIN-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 056 / Financial Analyst I IBRD / 88160 Post Consultant Direct 3,500.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 (Acctg ) Selection Individual PRDP-VIS-R7-SES-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 4,000.00 0.00 2021-01-01 057 / SES Officer Implementation Support Implementation 31 11 01 08 04 Selection Individual PRDP-VIS-R7-SES-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 3,500.00 0.00 2021-01-01 058 / Associate SES Officer Implementation Support Implementation 31 11 01 08 04 Selection Individual PRDP-VIS-R7-GGU-AF- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 4,000.00 0.00 2021-01-01 2021-059 / GIS Officer Implementation Support Implementation 31 11 01 08 04 Selection PRDP-VIS-R7-MAE-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 060 / Associate M & E IBRD / 88160 Post Consultant Direct 3,500.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Officer Selection Individual PRDP-VIS-R7-MAE-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 4,000.00 0.00 2021-01-01 061 / M & E Officer Implementation Support Implementation 31 11 01 08 04 Selection Individual PRDP-VIS-R7-PRO-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 4,000.00 0.00 2021-01-01 062 / Procurement Officer Implementation Support Implementation 31 11 01 08 04 Selection Individual PRDP-VIS-R7-INF-AF-2021- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 3,500.00 0.00 2021-01-01 063 / Writer Implementation Support Implementation 31 11 01 08 04 Selection Individual PRDP-VIS-R7-ECON-AF- Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 4,000.00 0.00 2021-01-01 2021-064 / Economist Implementation Support Implementation 31 11 01 08 04 Selection PRDP-VIS-R8-ODPD-AF- Individual Component 4: Project Under 2018-12- 2021-01- 2021-02- 2021-03- 2021-09- 2021-065 / Admininstrative IBRD / 88160 Post Consultant Direct 3,125.00 0.00 2021-01-01 Implementation Support Implementation 05 11 01 08 04 Officer II- ORDPD Selection PRDP-VIS-R8-IB-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 066 / Rural Infrastructure IBRD / 88160 Post Consultant Direct 5,000.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Engineer Selection PRDP-VIS-R8-IB-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 067 / Rural Infrastructure IBRD / 88160 Post Consultant Direct 5,000.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Engineer Selection Page 10 PRDP-VIS-R8-IB-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 068 / Rural Infrastructure IBRD / 88160 Post Consultant Direct 5,000.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Engineer Selection PRDP-VIS-R8-IB-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 069 / Rural Infrastructure IBRD / 88160 Post Consultant Direct 5,000.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Engineer Selection PRDP-VIS-R8-IB-AF-2021- Individual Component 4: Project Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- 070 / Program Development IBRD / 88160 Post Consultant Direct 3,125.00 0.00 2021-01-01 Implementation Support Implementation 31 11 01 08 04 Associate Selection Individual PRDP-VIS-R8-GGU-AF- Component 4: Project Under 2018-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 5,000.00 0.00 2021-01-01 2021-071 / GIS Officer Implementation Support Implementation 05 11 01 08 04 Selection Individual PRDP-VIS-R8-PRO-AF-2021- Component 4: Project Under 2018-12- 2021-02- 2021-03- 2021-04- 2021-10- IBRD / 88160 Post Consultant Open 4,833.33 0.00 2021-01-01 072 / Procurement Officer Implementation Support Implementation 06 19 12 16 13 Selection PRDP-VIS-R8-PRP-AF-2021- Individual Component 4: Project Under 2018-12- 2021-01- 2021-02- 2021-03- 2021-09- 073 / Associate Procurement IBRD / 88160 Post Consultant Direct 3,500.00 0.00 2021-01-01 Implementation Support Implementation 06 11 01 08 04 Officer Selection Individual PRDP-VIS-R8-MAE-AF-2021- Component 4: Project Under 2018-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 4,000.00 0.00 2021-01-01 074 / M & E Officer Implementation Support Implementation 05 11 01 08 04 Selection PRDP-VIS-R8-MAE-AF-2021- Individual Component 4: Project Under 2018-12- 2021-01- 2021-02- 2021-03- 2021-09- 075 / Associate M & E IBRD / 88160 Post Consultant Direct 3,500.00 0.00 2021-01-01 Implementation Support Implementation 05 11 01 08 04 Officer Selection Individual PRDP-VIS-R8-SES-AF-2021- Component 4: Project Under 2018-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 4,000.00 0.00 2021-01-01 076 / SES Officer Implementation Support Implementation 05 11 01 08 04 Selection Individual PRDP-VIS-R8-SES-AF-2021- Component 4: Project Under 2018-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 3,500.00 0.00 2021-01-01 077 / Associate SES Officer Implementation Support Implementation 05 11 01 08 04 Selection PRDP-VIS-R8-INF-AF-2021- Individual Component 4: Project Under 2018-12- 2021-01- 2021-02- 2021-03- 2021-09- 078 / Information IBRD / 88160 Post Consultant Direct 3,500.00 0.00 2021-01-01 Implementation Support Implementation 05 11 01 08 04 Officer/Writer Selection Individual PRDP-VIS-R8-BUD-AF-2021- Component 4: Project Under 2018-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88160 Post Consultant Direct 3,500.00 0.00 2021-01-01 079 / Budget Analyst Implementation Support Implementation 05 11 01 08 04 Selection PRDP-VIS-R8-FIN-AF-2021- Individual Component 4: Project Under 2018-12- 2021-01- 2021-02- 2021-03- 2021-09- 080 / Financial Analyst I IBRD / 88160 Post Consultant Direct 3,500.00 0.00 2021-01-01 Implementation Support Implementation 05 11 01 08 04 (LGU) Selection PRDP-VIS-R8-FIN-AF-2021- Individual Component 4: Project Under 2018-12- 2021-01- 2021-02- 2021-03- 2021-09- 081 / Financial Analyst I IBRD / 88160 Post Consultant Direct 3,500.00 0.00 2021-01-01 Implementation Support Implementation 05 11 01 08 04 (Accounting) Selection Individual PRDP-VIS-IP-AF-2022-001 Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 20,160.00 0.00 2022-01-01 / IPLAN Component Head Implementation Support Implementation 11 11 01 08 04 Selection Individual PRDP-VIS-IP-AF-2022-002 Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 12,960.00 0.00 2022-01-01 / Planning Officer Implementation Support Implementation 11 11 01 08 04 Selection Individual PRDP-VIS-IP-AF-2022-003 Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 12,960.00 0.00 2022-01-01 / Planning Officer Implementation Support Implementation 11 11 01 08 04 Selection PRDP-VIS-IP-AF-2022-004 Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- / Project Development IBRD / 92710 Post Consultant Direct 8,640.00 0.00 2022-01-01 Implementation Support Implementation 07 11 01 08 04 Associate (PDA) Selection Individual PRDP-VIS-IB-AF-2022-005 Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 20,160.00 0.00 2022-01-01 / I-BUILD Component Head Implementation Support Implementation 07 11 01 08 04 Selection PRDP-VIS-IB-AF-2022-006 Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- / Rural Infrastructure IBRD / 92710 Post Consultant Direct 12,960.00 0.00 2022-01-01 Implementation Support Implementation 07 11 01 08 04 Engineer Selection PRDP-VIS-IB-AF-2022-007 Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- / Rural Infrastructure IBRD / 92710 Post Consultant Direct 12,960.00 0.00 2022-01-01 Implementation Support Implementation 07 11 01 08 04 Engineer Selection PRDP-VIS-IB-AF-2022-008 Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- / Rural Infrastructure IBRD / 92710 Post Consultant Direct 12,960.00 0.00 2022-01-01 Implementation Support Implementation 07 11 01 08 04 Engineer Selection PRDP-VIS-IB-AF-2022-009 Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- / Rural Infrastructure IBRD / 92710 Post Consultant Direct 12,960.00 0.00 2022-01-01 Implementation Support Implementation 07 11 01 08 04 Engineer Selection PRDP-VIS-IB-AF-2022-010 Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- / Project Development IBRD / 92710 Post Consultant Direct 8,640.00 0.00 2022-01-01 Implementation Support Implementation 07 11 01 08 04 Associate Selection Individual PRDP-VIS-IR-AF-2022-011 Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 20,160.00 0.00 2022-01-01 / I-REAP Component Head Implementation Support Implementation 11 11 01 08 04 Selection PRDP-VIS-IR-AF-2022-012 Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- / Enterprise Development & IBRD / 92710 Post Consultant Direct 14,400.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Marketing Specialist Selection PRDP-VIS-IR-AF-2022-013 Individual Component 4: Project Under 2021-11- 2022-02- 2022-03- 2022-04- 2022-10- / Organizational IBRD / 92710 Post Consultant Open 14,400.00 0.00 2022-01-01 Implementation Support Implementation 21 19 12 16 13 Development Specialist Selection PRDP-VIS-IR-AF-2022-014 Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- / Business Development IBRD / 92710 Post Consultant Direct 12,960.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Officer Selection PRDP-VIS-IR-AF-2022-015 Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- / Business Development IBRD / 92710 Post Consultant Direct 12,960.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Officer Selection PRDP-VIS-IR-AF-2022-016 Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- / Business Development IBRD / 92710 Post Consultant Direct 12,960.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Officer Selection PRDP-VIS-IR-AF-2022-017 Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- / Project Development IBRD / 92710 Post Consultant Direct 8,640.00 0.00 2022-01-01 Implementation Support Implementation 08 11 01 08 04 Associate (PDA) Selection Individual PRDP-VIS-DPD-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 14,400.00 0.00 2022-01-01 018 / Compliance Officer Implementation Support Implementation 08 11 01 08 04 Selection PRDP-VIS-DPD-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 019 / Administrative Officer IBRD / 92710 Post Consultant Direct 10,080.00 0.00 2022-01-01 Implementation Support Implementation 08 11 01 08 04 III Selection PRDP-VIS-DPD-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 020 / Administrative Officer IBRD / 92710 Post Consultant Direct 8,640.00 0.00 2022-01-01 Implementation Support Implementation 08 11 01 08 04 II Selection Individual PRDP-VIS-ECON-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 12,960.00 0.00 2022-01-01 021 / Economist Implementation Support Implementation 08 11 01 08 04 Selection Individual PRDP-VIS-ECON-AF-2022- Component 4: Project Under 2021-10- 2022-02- 2022-03- 2022-04- 2022-10- IBRD / 92710 Post Consultant Open 11,520.00 0.00 2022-01-01 022 / Economist (RPCO) Implementation Support Implementation 08 19 12 16 13 Selection Individual PRDP-VIS-GGU-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 12,960.00 0.00 2022-01-01 023 / GIS Officer Implementation Support Implementation 08 11 01 08 04 Selection Individual PRDP-VIS-GGU-AF-2022- Component 4: Project Under 2021-10- 2022-02- 2022-03- 2022-04- 2022-10- IBRD / 92710 Post Consultant Open 12,960.00 0.00 2022-01-01 024 / GIS Officer Implementation Support Implementation 08 19 12 16 13 Selection Individual PRDP-VIS-INF-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 025 / Writer Implementation Support Implementation 08 11 01 08 04 Selection PRDP-VIS-INF-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 026 / Media Production IBRD / 92710 Post Consultant Direct 12,960.00 0.00 2022-01-01 Implementation Support Implementation 08 11 01 08 04 Officer Selection PRDP-VIS-IS-AF-2022-027 Individual Component 4: Project 2022-02- 2022-03- 2022-04- 2022-10- / I-SUPPORT Component IBRD / 92710 Post Consultant Open 20,160.00 0.00 Canceled 2022-01-01 Implementation Support 19 12 16 13 Head Selection PRDP-VIS-PRO-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 028 / Procurement Unit IBRD / 92710 Post Consultant Direct 18,720.00 0.00 2022-01-01 Implementation Support Implementation 08 11 01 08 04 Head Selection Page 11 Individual PRDP-VIS-PRO-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 12,960.00 0.00 2022-01-01 029 / Procurement Officer Implementation Support Implementation 08 11 01 08 04 Selection Individual PRDP-VIS-PRO-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 12,960.00 0.00 2022-01-01 030 / Procurement Officer Implementation Support Implementation 08 11 01 08 04 Selection PRDP-VIS-PRO-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 031 / Project Development IBRD / 92710 Post Consultant Direct 8,640.00 0.00 2022-01-01 Implementation Support Implementation 08 11 01 08 04 Associate Selection PRDP-VIS-MAE-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 032 / Monitoring & IBRD / 92710 Post Consultant Direct 18,720.00 0.00 2022-01-01 Implementation Support Implementation 08 11 01 08 04 Evaluation Unit Head Selection PRDP-VIS-MAE-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 033 / Monitoring & IBRD / 92710 Post Consultant Direct 12,960.00 0.00 2022-01-01 Implementation Support Implementation 08 11 01 08 04 Evaluation Officer Selection Individual PRDP-VIS-SES-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 14,400.00 0.00 2022-01-01 034 / SES Specialist Implementation Support Implementation 08 11 01 08 04 Selection Individual PRDP-VIS-SES-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 12,960.00 0.00 2022-01-01 035 / SES Officer Implementation Support Implementation 08 11 01 08 04 Selection Individual PRDP-VIS-SES-AF-2022- Component 4: Project Pending 2022-02- 2022-03- 2022-04- 2022-10- IBRD / 92710 Post Consultant Open 11,520.00 0.00 2022-01-01 036 / Associate SES Officer Implementation Support Implementation 19 12 16 13 Selection Individual PRDP-VIS-FIN-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 14,400.00 0.00 2022-01-01 036 / Financial Analyst III Implementation Support Implementation 08 11 01 08 04 Selection PRDP-VIS-FIN-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 037 / Financial Analyst IBRD / 92710 Post Consultant Direct 12,960.00 0.00 2022-01-01 Implementation Support Implementation 08 11 01 08 04 II/Accountant Selection Individual PRDP-VIS-FIN-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 12,960.00 0.00 2022-01-01 038 / Financial Analyst II Implementation Support Implementation 08 11 01 08 04 Selection Individual PRDP-VIS-FIN-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 12,960.00 0.00 2022-01-01 039 / Financial Analyst II Implementation Support Implementation 08 11 01 08 04 Selection Individual PRDP-VIS-FIN-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 040 / Financial Analyst I Implementation Support Implementation 08 11 01 08 04 Selection Individual PRDP-VIS-BUD-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 041 / Budget Analyst Implementation Support Implementation 08 11 01 08 04 Selection PRDP-VIS-ADM-AF-2022- Individual Component 4: Project Under 2021-10- 2022-02- 2022-03- 2022-04- 2022-10- 042 / Administrative Officer IBRD / 92710 Post Consultant Open 10,080.00 0.00 2022-01-01 Implementation Support Implementation 08 19 12 16 13 III Selection PRDP-VIS-ADM-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 043 / Administrative Officer IBRD / 92710 Post Consultant Direct 8,640.00 0.00 2022-01-01 Implementation Support Implementation 08 11 01 08 04 II Selection Individual PRDP-VIS-R6-IP-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 044 / Planning Officer Implementation Support Implementation 11 11 01 08 04 Selection Individual PRDP-VIS-R6-IP-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 045 / Planning Officer Implementation Support Implementation 11 11 01 08 04 Selection PRDP-VIS-R6-IB-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 046 / Rural Infrastructure IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Engineer Selection PRDP-VIS-R6-IB-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 047 / Rural Infrastructure IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Engineer Selection PRDP-VIS-R6-IB-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 048 / Rural Infrastructure IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Engineer Selection PRDP-VIS-R6-IB-AF-2022- Individual Component 4: Project Under 2021-10- 2022-02- 2022-03- 2022-04- 2022-10- 049 / Rural Infrastructure IBRD / 92710 Post Consultant Open 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 19 12 16 13 Engineer Selection PRDP-VIS-R6-IB-AF-2022- Individual Component 4: Project Under 2021-10- 2022-02- 2022-03- 2022-04- 2022-10- 050 / Rural Infrastructure IBRD / 92710 Post Consultant Open 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 19 12 16 13 Engineer Selection PRDP-VIS-R6-IB-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 051 / Program Development IBRD / 92710 Post Consultant Direct 7,200.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Associate Selection PRDP-VIS-R6-IR-AF-2022- Individual Component 4: Project Under 2021-10- 2022-02- 2022-03- 2022-04- 2022-10- 052 / Enterprise IBRD / 92710 Post Consultant Open 12,960.00 0.00 2022-01-01 Implementation Support Implementation 11 19 12 16 13 Development & Marketing Selection Specialist PRDP-VIS-R6-IR-AF-2022- Individual Component 4: Project Under 2021-11- 2022-02- 2022-03- 2022-04- 2022-10- 053 / Organizational IBRD / 92710 Post Consultant Open 11,520.00 0.00 2022-01-01 Implementation Support Implementation 21 19 12 16 13 Development Officer Selection PRDP-VIS-R6-IR-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 054 / Business Development IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Officer Selection PRDP-VIS-R6-IR-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 055 / Business Development IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Officer Selection PRDP-VIS-R6-IR-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 056 / Business Development IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Officer Selection PRDP-VIS-R6-IR-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 057 / Business Development IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Officer Selection PRDP-VIS-R6-IR-AF-2022- Individual Component 4: Project Under 2022-02- 2022-02- 2022-03- 2022-04- 2022-10- 058 / Procurement Officer IBRD / 92710 Post Consultant Open 11,520.00 0.00 2022-01-01 Implementation Support Implementation 09 19 12 16 13 (IREAP SPs) Selection PRDP-VIS-R6-IR-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 059 / Project Development IBRD / 92710 Post Consultant Direct 7,200.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Associate (PDA) Selection PRDP-VIS-R6-ADM-AF- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 2022-060 / Administrative IBRD / 92710 Post Consultant Direct 7,200.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Officer II Selection Individual PRDP-VIS-R6-DPD-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 061 / Economist Implementation Support Implementation 11 11 01 08 04 Selection Individual PRDP-VIS-R6-GGU-AF- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 2022-062 / GIS Officer Implementation Support Implementation 11 11 01 08 04 Selection Individual PRDP-VIS-R6-PRO-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 063 / Procurement Officer Implementation Support Implementation 11 11 01 08 04 Selection PRDP-VIS-R6-PRO-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 064 / Associate Procurement IBRD / 92710 Post Consultant Direct 10,080.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Officer Selection Individual PRDP-VIS-R6-MAE-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 065 / M & E Officer Implementation Support Implementation 11 11 01 08 04 Selection Individual PRDP-VIS-R6-MAE-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 10,080.00 0.00 2022-01-01 066 / Associate M&E Officer Implementation Support Implementation 11 11 01 08 04 Selection Individual PRDP-VIS-R6-SES-AF-2022- Component 4: Project Under 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 067 / SES Officer Implementation Support Implementation 11 01 08 04 Selection Individual PRDP-VIS-R6-SES-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 10,080.00 0.00 2022-01-01 068 / Associate SES Officer Implementation Support Implementation 11 11 01 08 04 Selection Individual PRDP-VIS-R6-SES-AF-2022- Component 4: Project Under 2021-10- 2022-02- 2022-03- 2022-04- 2022-10- IBRD / 92710 Post Consultant Open 10,080.00 0.00 2022-01-01 069 / Associate SES Officer Implementation Support Implementation 11 19 12 16 13 Selection Page 12 Individual PRDP-VIS-R6-INF-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 10,080.00 0.00 2022-01-01 070 / Writer Implementation Support Implementation 11 11 01 08 04 Selection Individual PRDP-VIS-R6-FIN-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 10,080.00 0.00 2022-01-01 071 / Finance Analyst I Implementation Support Implementation 11 11 01 08 04 Selection Individual PRDP-VIS-R6-FIN-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 10,080.00 0.00 2022-01-01 072 / Finance Analyst I Implementation Support Implementation 11 11 01 08 04 Selection Individual PRDP-VIS-R6-FIN-AF-2022- Component 4: Project Under 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 10,080.00 0.00 2022-01-01 073 / Finance Analyst I Implementation Support Implementation 11 01 08 04 Selection Individual PRDP-VIS-R6-BUD-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 10,080.00 0.00 2022-01-01 074 / Budget Analyst I Implementation Support Implementation 11 11 01 08 04 Selection Individual PRDP-VIS-R7-IP-AF-2022- Component 4: Project Under 2021-10- 2022-02- 2022-03- 2022-04- 2022-10- IBRD / 92710 Post Consultant Open 11,520.00 0.00 2022-01-01 075 / Planning Officer Implementation Support Implementation 11 19 12 16 13 Selection Individual PRDP-VIS-R7-IP-AF-2022- Component 4: Project Under 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 076 / Planning Officer Implementation Support Implementation 11 01 08 04 Selection PRDP-VIS-R7-IB-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 077 / Rural Infrastructure IBRD / 92710 Post Consultant Direct 12,960.00 0.00 2022-01-01 Implementation Support Implementation 28 11 01 08 04 Specialist Selection PRDP-VIS-R7-IB-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 078 / Rural Infrastructure IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Engineer Selection PRDP-VIS-R7-IB-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 079 / Rural Infrastructure IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Engineer Selection PRDP-VIS-R7-IB-AF-2022- Individual Component 4: Project Under 2021-10- 2022-02- 2022-03- 2022-04- 2022-10- 080 / Rural Infrastructure IBRD / 92710 Post Consultant Open 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 19 12 16 13 Engineer Selection PRDP-VIS-R7-IR-AF-2022- Individual Component 4: Project Under 2021-10- 2022-02- 2022-03- 2022-04- 2022-10- 082 / Enterprise IBRD / 92710 Post Consultant Open 12,960.00 0.00 2022-01-01 Implementation Support Implementation 11 19 12 16 13 Development & Marketing Selection Specialist PRDP-VIS-R7-IR-AF-2022- Individual Component 4: Project Under 2021-11- 2022-02- 2022-03- 2022-04- 2022-10- 083 / Organizational IBRD / 92710 Post Consultant Open 11,520.00 0.00 2022-01-01 Implementation Support Implementation 21 19 12 16 13 Development Officer Selection PRDP-VIS-R7-IR-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 084 / Business Development IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Officer Selection PRDP-VIS-R7-IR-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 085 / Business Development IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Officer Selection PRDP-VIS-R7-IR-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 086 / Business Development IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Officer Selection PRDP-VIS-R7-IR-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 087 / Business Development IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Officer Selection PRDP-VIS-R7-IR-AF-2022- Individual Component 4: Project Under 2022-02- 2022-02- 2022-03- 2022-04- 2022-10- 088 / Procurement Officer IBRD / 92710 Post Consultant Open 11,520.00 0.00 2022-01-01 Implementation Support Implementation 09 19 12 16 13 (IREAP SPs) Selection Individual PRDP-VIS-R7-BUD-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 10,080.00 0.00 2022-01-01 090 / Budget Analyst I Implementation Support Implementation 11 11 01 08 04 Selection PRDP-VIS-R7-FIN-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 091 / Financial Analyst I IBRD / 92710 Post Consultant Direct 10,080.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 (Finance) Selection PRDP-VIS-R7-FIN-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 092 / Financial Analyst I IBRD / 92710 Post Consultant Direct 10,080.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 (Acctg ) Selection Individual PRDP-VIS-R7-SES-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 093 / SES Officer Implementation Support Implementation 11 11 01 08 04 Selection Individual PRDP-VIS-R7-SES-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 10,080.00 0.00 2022-01-01 094 / Associate SES Officer Implementation Support Implementation 11 11 01 08 04 Selection Individual PRDP-VIS-R7-SES-AF-2022- Component 4: Project Under 2021-10- 2022-02- 2022-03- 2022-04- 2022-10- IBRD / 92710 Post Consultant Open 10,080.00 0.00 2022-01-01 095 / Associate SES Officer Implementation Support Implementation 28 19 12 16 13 Selection Individual PRDP-VIS-R7-GGU-AF- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 2022-096 / GIS Officer Implementation Support Implementation 11 11 01 08 04 Selection Individual PRDP-VIS-R7-MAE-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 097 / M & E Officer Implementation Support Implementation 11 11 01 08 04 Selection PRDP-VIS-R7-MAE-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 098 / Associate M & E IBRD / 92710 Post Consultant Direct 10,080.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Officer Selection Individual PRDP-VIS-R7-PRO-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 099 / Procurement Officer Implementation Support Implementation 11 11 01 08 04 Selection PRDP-VIS-R7-PRO-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 100 / Associate Procurement IBRD / 92710 Post Consultant Direct 10,080.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Officer Selection Individual PRDP-VIS-R7-INF-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 10,080.00 0.00 2022-01-01 101 / Writer Implementation Support Implementation 11 11 01 08 04 Selection Individual PRDP-VIS-R7-ECON-AF- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 2022-102 / Economist Implementation Support Implementation 11 11 01 08 04 Selection Individual PRDP-VIS-R8-IP-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 103 / Planning Officer Implementation Support Implementation 11 11 01 08 04 Selection Individual PRDP-VIS-R8-IP-AF-2022- Component 4: Project Under 2021-10- 2022-02- 2022-03- 2022-04- 2022-10- IBRD / 92710 Post Consultant Open 11,520.00 0.00 2022-01-01 104 / Planning Officer Implementation Support Implementation 11 19 12 16 13 Selection PRDP-VIS-R8-IB-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 105 / Rural Infrastructure IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Engineer Selection PRDP-VIS-R8-IB-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 106 / Rural Infrastructure IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Engineer Selection PRDP-VIS-R8-IB-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 107 / Rural Infrastructure IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Engineer Selection PRDP-VIS-R8-IB-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 108 / Rural Infrastructure IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Engineer Selection PRDP-VIS-R8-IB-AF-2022- Individual Component 4: Project Under 2021-10- 2022-02- 2022-03- 2022-04- 2022-10- 109 / Rural Infrastructure IBRD / 92710 Post Consultant Open 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 19 12 16 13 Engineer Selection PRDP-VIS-R8-IB-AF-2022- Individual Component 4: Project Under 2021-10- 2022-02- 2022-03- 2022-04- 2022-10- 110 / Rural Infrastructure IBRD / 92710 Post Consultant Open 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 19 12 16 13 Engineer Selection PRDP-VIS-R8-IB-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 111 / Program Development IBRD / 92710 Post Consultant Direct 7,200.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Associate Selection PRDP-VIS-R8-IR-AF-2022- Individual Component 4: Project Under 2021-10- 2022-02- 2022-03- 2022-04- 2022-10- 112 / Enterprise IBRD / 92710 Post Consultant Open 12,960.00 0.00 2022-01-01 Implementation Support Implementation 11 19 12 16 13 Development & Marketing Selection Specialist PRDP-VIS-R8-IR-AF-2022- Individual Component 4: Project Under 2021-11- 2022-02- 2022-03- 2022-04- 2022-10- 113 / Organizational IBRD / 92710 Post Consultant Open 11,520.00 0.00 2022-01-01 Implementation Support Implementation 21 19 12 16 13 Development Officer Selection Page 13 PRDP-VIS-R8-IR-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 114 / Business Development IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Officer Selection PRDP-VIS-R8-IR-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 115 / Business Development IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Officer Selection PRDP-VIS-R8-IR-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 116 / Business Development IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Officer Selection PRDP-VIS-R8-IR-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 117 / Business Development IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Officer Selection PRDP-VIS-R8-IR-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 118 / Project Development IBRD / 92710 Post Consultant Direct 7,200.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Associate (PDA) Selection PRDP-VIS-R8-ODPD-AF- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 2022-119 / Admininstrative IBRD / 92710 Post Consultant Direct 7,200.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Officer II- ORDPD Selection Individual PRDP-VIS-R8-GGU-AF- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 2022-120 / GIS Officer Implementation Support Implementation 11 11 01 08 04 Selection Individual PRDP-VIS-R8-PRO-AF-2022- Component 4: Project Under 2022-02- 2022-02- 2022-03- 2022-04- 2022-10- IBRD / 92710 Post Consultant Open 11,520.00 0.00 2022-01-01 121 / Procurement Officer Implementation Support Implementation 09 19 12 16 13 Selection PRDP-VIS-R8-PRP-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 122 / Associate Procurement IBRD / 92710 Post Consultant Direct 10,080.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Officer Selection Individual PRDP-VIS-R8-MAE-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 123 / M & E Officer Implementation Support Implementation 11 11 01 08 04 Selection PRDP-VIS-R8-MAE-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 124 / Associate M & E IBRD / 92710 Post Consultant Direct 10,080.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Officer Selection Individual PRDP-VIS-R8-SES-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2022-01-01 125 / SES Officer Implementation Support Implementation 11 11 01 08 04 Selection Individual PRDP-VIS-R8-SES-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 10,080.00 0.00 2022-01-01 126 / Associate SES Officer Implementation Support Implementation 11 11 01 08 04 Selection Individual PRDP-VIS-R8-SES-AF-2022- Component 4: Project Under 2021-10- 2022-02- 2022-03- 2022-04- 2022-10- IBRD / 92710 Post Consultant Open 10,080.00 0.00 2022-01-01 127 / Associate SES Officer Implementation Support Implementation 11 19 12 16 13 Selection PRDP-VIS-R8-INF-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 128 / Information IBRD / 92710 Post Consultant Direct 10,080.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Officer/Writer Selection Individual PRDP-VIS-R8-BUD-AF-2022- Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Post Consultant Direct 10,080.00 0.00 2022-01-01 129 / Budget Analyst Implementation Support Implementation 11 11 01 08 04 Selection PRDP-VIS-R8-FIN-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 130 / Financial Analyst I IBRD / 92710 Post Consultant Direct 10,080.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 (LGU) Selection PRDP-VIS-R8-FIN-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 131 / Financial Analyst I IBRD / 92710 Post Consultant Direct 10,080.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 (Accounting) Selection PRDP-VIS-R7-IB-AF-2022- Individual Component 4: Project Under 2022-01- 2022-02- 2022-03- 2022-09- 081 / Project Development IBRD / 92710 Post Consultant Direct 7,200.00 0.00 2022-01-01 Implementation Support Implementation 11 01 08 04 Associate Selection PRDP-VIS-R7-IR-AF-2022- Individual Component 4: Project Under 2021-10- 2022-01- 2022-02- 2022-03- 2022-09- 089 / Project Development IBRD / 92710 Post Consultant Direct 7,200.00 0.00 2022-01-01 Implementation Support Implementation 11 11 01 08 04 Associate (PDA) Selection PRDP-VIS-R6-IB-AF-2022- Individual Component 4: Project Pending 2022-01- 2022-02- 2022-03- 2022-09- 045 / Rural Infrastructure IBRD / 92710 Post Consultant Direct 12,960.00 0.00 2022-01-01 Implementation Support Implementation 11 01 08 04 Specialist Selection PRDP-VIS-ADM-AF-2022- Individual Component 4: Project Pending 2022-01- 2022-02- 2022-03- 2022-09- 132 / Admininstrative Unit IBRD / 92710 Post Consultant Direct 19,200.00 0.00 2022-01-01 Implementation Support Implementation 11 01 08 04 Head Selection Page 14