PROCUREMENT PLAN (Textual Part) CAMBODIA Land Allocation for Social and Economic Development Project III (LASED III - P171331) Project Implementation agency: • Ministry of Land Management Urban Planning and Construction (MLMUPC) as Executing Agency (EA) • Ministry of Agriculture, Forestry and Fisheries (MAFF) as Implementing Agency (IA) Date of the Procurement Plan: April 2020 Period covered by this Procurement Plan: Sept 2020 – June 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Government of the Kingdom of Cambodia’s Updated Standard Operating Procedures and Procurement Manual for All Externally Financed Projects/Programs, promulgated through the Sub‐decree 181 ANK/BK dated December 2, 2019, which is issued pursuant to Article 3 of the Government of the Kingdom of Cambodia’s Law on Public Procurement dated January 14, 2012, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. i. Procurement shall be open to eligible firms from any country; ii. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights as per attached confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including format; iii. Each Project shall put in place an effective complaint review system that includes review by the implementing agency and subsequent review by another party not involved in the in the procurement process, if not satisfied with the review of the implementing agency When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Other Relevant Procurement Information. Except the sub-national procurement activities under Component 2 Community Infrastructure Development of the project that will be followed the Project Implementation Manual and the Community Operational Manual; all the procurement activities under other components and sub-components will be governed by World Bank Procurement Regulations for IPF Borrowers, July 2016 (revised November 2017 and Revised August 2018) Procurement Method and Prior Review Thresholds Procurement at National Open (USD) Prior Review Level Threshold International National RFQ (*) Substantial Risk Works include CDD 2 mil & above Below 2 mil Below 200k 10 million Goods, IT and non-consulting 600k & above Below 600k Below 100k 2 million services Consulting Firm 200k & above Below 200k N/A 1 million Individual Consultant 0.3 million (*) if the estimated cost over USD 50,000, SPN is required. Procurement at Sub-national levels Contract Value Procurement Prior Review Thresholds Comments Methods Threshold ($’000) (US$) This method is used when there is only one source available, emergency, very small value, the need to adopt certain technology or Direct Contracting - Non a repeat order. This method is (Goods & Works) subject to the prior review by the national office and provincial office of LASED III. Open Competitive if estimated contract amount is Bidding as per <25,000 Non US$25,000 or more, the C/S PIM (Goods procurement will be carried out and Works) by the national level. All contracts at the sub-national levels will not be subject the Bank's prior review. All contracts are subject to post review. 1. The National Project Office will randomly select at least 10% of community procurement packages for its post review exercise. 2. The procurement activities at sub-national levels and CDF will be audited by the external audit firm PROCUREMENT Cambodia : Land Allocation for Social and Economic Development Project III PLAN General Information Country: Cambodia Bank’s Approval Date of the Original Procurement Plan: 2020-11-17 2022-01-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171331 GPN Date: 2020-11-12 Project Name: Land Allocation for Social and Economic Development Project III Loan / Credit No: IDA / 67060 M Executing Agency(ies): inistry of Land Management, Urban Planning and Construction WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 1: Selection and Development Planning of Pending MLMUPC-W-3 / IC Study Single Stage - One 2022-04- IDA / 67060 Social Land Concession and Post Request for Bids Open - National 300,000.00 0.00 Implementat 2021-06-15 2021-06-20 2021-08-01 2021-08-31 2021-10-05 Center Envelope 03 Indigenous Communal Land ion Titling Component 1: Selection and Development Planning of Request for Pending MLMUPC-W-4 / Billboards Request for Single Stage - One 2022-09- IDA / 67060 Social Land Concession and Post Open - National Quotations (Non 74,250.00 0.00 Implementat 2022-01-15 2022-03-21 and Boundary Markers Quotations Envelope 17 Indigenous Communal Land Bank-SPD) ion Titling GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Selection and Development Planning of Pending Request for Single Stage - One MLMUPC-G-2 / A Plotter IDA / 67060 Social Land Concession and Post Open - National 50,000.00 0.00 Implementati 2020-12-06 2021-01-31 2021-07-30 Quotations Envelope Indigenous Communal Land on Titling Component 1: Selection and Development Planning of Pending Request for Single Stage - One MLMUPC-G-3 / 2 Drones IDA / 67060 Social Land Concession and Post Open - National 15,000.00 0.00 Implementati 2020-12-05 2021-01-30 2021-07-29 Quotations Envelope Indigenous Communal Land on Titling Component 1: Selection and Development Planning of Pending MLMUPC-G-5 / 3 Digital Request for Single Stage - One IDA / 67060 Social Land Concession and Post Open - National 4,500.00 0.00 Implementati 2020-12-05 2021-01-30 2021-07-29 Cameras Quotations Envelope Indigenous Communal Land on Titling Component 1: Selection and Development Planning of Single Stage - One MLMUPC-G-6 / 7 Pick-up IDA / 67060 Social Land Concession and Post Request for Bids Open - National 210,000.00 0.00 Canceled 2020-11-30 2020-12-05 2021-01-16 2021-02-15 2021-03-22 2021-09-18 Envelope Indigenous Communal Land Titling Component 1: Selection and Development Planning of Pending Request for Single Stage - One MLMUPC-G-7 / Motorcycle IDA / 67060 Social Land Concession and Post Open - National 68,400.00 0.00 Implementati 2020-12-05 2021-01-30 2021-07-29 Quotations Envelope Indigenous Communal Land on Titling Component 4: Project Under MLMUPC-G-12 / Office Request for Single Stage - One IDA / 67060 Management, Coordination Post Open - National 15,000.00 0.00 Implementati 2020-12-05 2021-01-30 2021-07-29 Furniture Quotations Envelope and M&E on Component 4: Project MLMUPC-G-13 / Accounting Request for Single Stage - One IDA / 67060 Management, Coordination Post Open - National 6,000.00 0.00 Canceled 2020-12-05 2021-01-30 2021-07-29 Software (Sage C50) Quotations Envelope and M&E Component 1: Selection and Development Planning of Pending Single Stage - One MLMUPC-G-1 / DGPS IDA / 67060 Social Land Concession and Prior Request for Bids Open - International 5,000,000.00 0.00 Implementati 2021-01-03 2021-01-08 2021-02-19 2021-03-21 2021-04-25 2021-10-22 Envelope Indigenous Communal Land on Titling MLMUPC-G-11 / Hardware Component 4: Project Pending Single Stage - One and Software for MIS Web- IDA / 67060 Management, Coordination Post Request for Bids Open - National 130,500.00 0.00 Implementati 2021-03-15 2021-03-20 2021-05-01 2021-05-31 2021-07-05 2022-01-01 Envelope based Expansion and M&E on Component 4: Project Under MLMUPC-G-4 / Office Request for Single Stage - One IDA / 67060 Management, Coordination Post Open - National 95,500.00 0.00 Implementati 2021-01-09 2021-09-17 2021-03-06 2021-09-02 Equipment Quotations Envelope and M&E on Component 1: Selection and Development Planning of Under Single Stage - One MLMUPC-G14 / 7 pick-up IDA / 67060 Social Land Concession and Post Request for Bids Open - National 315,000.00 0.00 Implementati 2021-04-26 2021-08-29 2021-05-01 2021-08-30 2021-06-12 2021-09-30 2021-07-12 2021-08-16 2022-02-12 Envelope Indigenous Communal Land on Titling Component 1: Selection and Development Planning of Pending MLMUPC-G15 / Video Request for Single Stage - One IDA / 67060 Social Land Concession and Post Open - National 80,000.00 0.00 Implementati 2021-05-05 2021-06-30 2021-12-27 Conference Equipment Quotations Envelope Indigenous Communal Land on Titling Component 1: Selection and Development Planning of Pending MLMUPC-G-15 / GPS and I- Request for Single Stage - One IDA / 67060 Social Land Concession and Post Open - National 33,000.00 0.00 Implementati 2022-01-15 2022-03-19 2022-05-18 Com Quotations Envelope Indigenous Communal Land on Titling Page 1 Component 1: Selection and MLMUPC-G-14 / Machine Development Planning of Pending Request for Single Stage - One and software for map IDA / 67060 Social Land Concession and Post Limited 20,000.00 0.00 Implementati 2022-01-06 2022-03-03 2022-03-03 Quotations Envelope processing Indigenous Communal Land on Titling Component 4: Project Pending MLMUPC-G-16 / Accounting Request for Single Stage - One IDA / 67060 Management, Coordination Post Open - National 6,000.00 0.00 Implementati 2021-11-26 2022-01-21 2023-01-21 system Sage 50,10 users Quotations Envelope and M&E on MLMUPC-CS-58 / Office Component 4: Project Pending Request for Single Stage - One Furniture Support at National IDA / 67060 Management, Coordination Post Open - National 27,000.00 0.00 Implementati 2022-01-28 2022-04-08 2022-10-05 Quotations Envelope Team and M&E on Component 4: Project Pending MLMUPC-CS-59 / Office Request for Single Stage - One IDA / 67060 Management, Coordination Post Open - National 25,872.00 0.00 Implementati 2022-02-04 2022-04-29 2022-10-26 Equipment and Loud Speaker Quotations Envelope and M&E on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Selection and Development Planning of Consultant MLMUPC-CS-17 / General IDA / 67060 Social Land Concession and Post Qualification Open - National 50,000.00 0.00 Under Review 2020-12-04 2021-12-16 2020-12-25 2021-02-07 2021-03-09 2021-04-13 2021-10-10 Baseline Survey Indigenous Communal Land Selection Titling Component 1: Selection and MLMUPC-CS-03 / Indigenous Development Planning of Consultant Pending Community Investment IDA / 67060 Social Land Concession and Post Qualification Open - National 187,500.00 0.00 2021-03-18 2021-04-08 2021-05-22 2021-06-21 2021-07-26 2022-01-22 Implementation Planning and Prioritization Indigenous Communal Land Selection Titling MLMUPC-CS-38 / Consulting Consultant Component 2: Community Pending Firm for Technical Design and IDA / 67060 Post Qualification Open - National 230,000.00 0.00 2021-06-30 2021-07-21 2021-09-03 2021-10-03 2021-11-07 2022-05-06 Infrastructure Development Implementation Supervision for clean water Selection MLMUPC-CS-39 / Consulting Firm for Technical Design and Component 2: Community Quality And Cost- Under IDA / 67060 Post Open - National 572,000.00 0.00 2021-06-30 2021-10-07 2021-07-21 2021-09-03 2021-10-01 2021-10-31 2021-12-05 2022-01-09 2023-01-09 Supervision for Public Infrastructure Development Based Selection Implementation Infrastructure Component 1: Selection and MLMUPC-CS-04 / Development Planning of Formulation of Commune Quality And Cost- IDA / 67060 Social Land Concession and Post Open - International 750,000.00 0.00 Canceled 2021-03-18 2021-06-15 2021-04-08 2021-08-12 2021-05-22 2021-06-19 2021-07-19 2021-08-23 2021-09-27 2022-09-27 Land Use Plan in the Project Based Selection Indigenous Communal Land Areas Titling Component 1: Selection and MLMUPC-CS-41 / Consulting Development Planning of Firm for Formulation of Quality And Cost- Under IDA / 67060 Social Land Concession and Post Open - International 375,000.00 0.00 2021-09-15 2021-09-15 2021-09-30 2021-09-24 2021-11-13 2021-12-11 2022-01-10 2022-02-14 2022-03-21 2023-03-21 Commune Land Use Plan Based Selection Implementation Indigenous Communal Land (Region 2) Titling Component 1: Selection and MLMUPC-CS-40 / Consulting Development Planning of Firm for Formulation of Quality And Cost- Under IDA / 67060 Social Land Concession and Post Open - International 375,000.00 0.00 2021-09-15 2021-09-15 2021-09-30 2021-09-24 2021-11-13 2021-12-11 2022-01-10 2022-02-14 2022-03-21 2023-03-21 Commune Land Use Plan Based Selection Implementation Indigenous Communal Land (Region 1) Titling Component 1: Selection and MLMUPC-CS-42 / Consulting Development Planning of Firm for Formulation of Quality And Cost- Under IDA / 67060 Social Land Concession and Post Open - International 375,000.00 0.00 2021-09-15 2021-09-15 2021-09-30 2021-09-24 2021-11-13 2021-12-11 2022-01-10 2022-02-14 2022-03-21 2023-03-21 Commune Land Use Plan Based Selection Implementation Indigenous Communal Land (Region 3) Titling Component 1: Selection and MLMUPC-CS-23 / Development Planning of Consultant Environmental and Social IDA / 67060 Social Land Concession and Post Qualification Open - International 50,000.00 0.00 Canceled 2021-02-01 2021-02-05 2021-02-22 2021-02-19 2021-04-07 2021-05-07 2021-06-11 2021-12-08 Assessment (ESA) Indigenous Communal Land Selection Titling Component 1: Selection and MLMUPC-CS-23R / Development Planning of Consultant Under Environmental and Social IDA / 67060 Social Land Concession and Post Qualification Open - National 50,000.00 0.00 2021-09-30 2021-09-30 2021-10-21 2021-10-01 2021-12-04 2021-12-25 2022-01-11 2022-04-11 Implementation Assessment (ESA) Indigenous Communal Land Selection Titling INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Selection and MLMUPC-CS-15 / National Development Planning of Individual Under Communication & Outreach IDA / 67060 Social Land Concession and Post Consultant Open 60,000.00 0.00 2021-01-29 2021-05-02 2021-03-19 2021-04-09 2021-05-14 2021-11-10 Implementation Consultant at EA/MLMUPC Indigenous Communal Land Selection Titling Component 4: Project Individual MLMUPC-CS-09 / National IDA / 67060 Management, Coordination Post Consultant Open 60,000.00 0.00 Canceled 2021-01-04 2021-03-14 2021-02-22 2021-03-15 2021-04-19 2021-10-16 Operation Consultant and M&E Selection Page 2 Component 1: Selection and Development Planning of Individual MLMUPC-CS-12 / Safeguard IDA / 67060 Social Land Concession and Post Consultant Open 38,400.00 0.00 Canceled 2021-01-15 2021-03-05 2021-03-26 2021-04-30 2021-10-27 Consultant Indigenous Communal Land Selection Titling Component 4: Project Individual MLMUPC-CS-10 / National IDA / 67060 Management, Coordination Post Consultant Open 60,000.00 0.00 Canceled 2021-01-15 2021-03-05 2021-03-26 2021-04-30 2021-10-27 M&E Specialist and M&E Selection Component 1: Selection and Development Planning of Individual MLMUPC-CS-14 / Under IDA / 67060 Social Land Concession and Post Consultant Open 60,000.00 0.00 2021-01-04 2021-02-18 2021-02-22 2021-03-15 2021-04-19 2021-10-16 Procurement Consultant Implementation Indigenous Communal Land Selection Titling Component 4: Project Individual MLMUPC-CS-16 / Gender Pending IDA / 67060 Management, Coordination Post Consultant Open 36,000.00 0.00 2021-09-15 2021-11-03 2021-11-24 2021-12-29 2022-06-27 Assessment Implementation and M&E Selection Component 1: Selection and Development Planning of Individual MLMUPC-CS-06 / National Under IDA / 67060 Social Land Concession and Post Consultant Open 60,000.00 0.00 2021-09-13 2021-09-08 2021-11-01 2021-11-22 2021-12-27 2022-06-25 GIS Consultant Implementation Indigenous Communal Land Selection Titling Component 1: Selection and Development Planning of Individual MLMUPC-CS-11 / FM Under IDA / 67060 Social Land Concession and Post Consultant Open 60,000.00 0.00 2021-01-04 2021-02-18 2021-02-22 2021-03-15 2021-04-19 2021-10-16 Constultant Implementation Indigenous Communal Land Selection Titling Component 1: Selection and Development Planning of Individual MLMUPC-CS-13 / IT Under IDA / 67060 Social Land Concession and Post Consultant Open 60,000.00 0.00 2021-06-15 2021-06-15 2021-08-03 2021-08-24 2021-09-28 2022-03-27 Consultant at EA/MLMUPC Implementation Indigenous Communal Land Selection Titling Component 1: Selection and Development Planning of Individual MLMUPC-CS-18 / Safeguard IDA / 67060 Social Land Concession and Post Consultant Open 38,400.00 0.00 Canceled 2021-01-15 2021-03-05 2021-03-26 2021-04-30 2021-10-27 Consultant Indigenous Communal Land Selection Titling Component 1: Selection and Development Planning of Individual MLMUPC-CS-19 / Safeguard IDA / 67060 Social Land Concession and Post Consultant Open 38,400.00 0.00 Canceled 2021-01-15 2021-03-05 2021-03-26 2021-04-30 2021-10-27 Consultant Indigenous Communal Land Selection Titling Component 1: Selection and Development Planning of Individual MLMUPC-CS20 / Safeguard IDA / 67060 Social Land Concession and Post Consultant Open 38,400.00 0.00 Canceled 2021-01-15 2021-03-05 2021-03-26 2021-04-30 2021-10-27 Consultant Indigenous Communal Land Selection Titling Component 1: Selection and Development Planning of Individual MLMUPC-CS-21 / Safeguard IDA / 67060 Social Land Concession and Post Consultant Open 38,400.00 0.00 Canceled 2021-01-15 2021-03-05 2021-03-26 2021-04-30 2021-10-27 Consultant Indigenous Communal Land Selection Titling Component 1: Selection and Development Planning of Individual MLMUPC-CS-22 / Safeguard IDA / 67060 Social Land Concession and Post Consultant Open 38,400.00 0.00 Canceled 2021-01-15 2021-03-05 2021-03-26 2021-04-30 2021-10-27 Consultant Indigenous Communal Land Selection Titling MLMUPC-CS-08 / Component 4: Project Individual International Operation IDA / 67060 Management, Coordination Post Consultant Open 72,000.00 0.00 Canceled 2021-01-15 2021-03-05 2021-03-26 2021-04-30 2021-10-27 Consultant and M&E Selection Component 1: Selection and MLMUPC-CS-07 / IP Development Planning of Individual TECHNICAL ASSISTANT IDA / 67060 Social Land Concession and Post Consultant Open 43,200.00 0.00 Canceled 2021-02-15 2021-02-18 2021-04-05 2021-04-26 2021-05-31 2021-11-27 CONSULTANT based at Indigenous Communal Land Selection MLMUPC Titling Component 1: Selection and Development Planning of Individual MLMUPC-CS-05 / National IP IDA / 67060 Social Land Concession and Post Consultant Open 60,000.00 0.00 Canceled 2021-02-15 2021-02-18 2021-04-05 2021-04-26 2021-05-31 2021-11-27 Consultant Indigenous Communal Land Selection Titling Component 1: Selection and Development Planning of Individual MLMUPC-CS-26 / Operations Under IDA / 67060 Social Land Concession and Post Consultant Open 36,000.00 0.00 2021-04-19 2021-03-19 2021-06-07 2021-06-28 2021-08-02 2022-01-29 Secretariat Coordinator Implementation Indigenous Communal Land Selection Titling Component 1: Selection and Development Planning of Individual MLMUPC-CS-27 / Technical Under IDA / 67060 Social Land Concession and Post Consultant Open 36,000.00 0.00 2021-04-19 2021-03-19 2021-06-07 2021-06-28 2021-08-02 2022-01-29 Secretariat Coordinator Implementation Indigenous Communal Land Selection Titling Component 1: Selection and Development Planning of Individual MLMUPC-CS-28 / National Under IDA / 67060 Social Land Concession and Post Consultant Open 72,000.00 0.00 2021-04-19 2021-05-02 2021-06-07 2021-06-28 2021-08-02 2022-01-29 Senior IP Consultant Implementation Indigenous Communal Land Selection Titling Component 1: Selection and Development Planning of Individual MLMUPC-CS-29 / National Under IDA / 67060 Social Land Concession and Post Consultant Open 60,000.00 0.00 2021-04-23 2021-04-08 2021-06-11 2021-07-02 2021-08-06 2022-02-02 CLUP Consultant Implementation Indigenous Communal Land Selection Titling Component 1: Selection and Development Planning of Individual MLMUPC-CS-30 / National Under IDA / 67060 Social Land Concession and Post Consultant Open 60,000.00 0.00 2021-04-23 2021-04-08 2021-06-11 2021-07-02 2021-08-06 2022-02-02 SLC Consultant Implementation Indigenous Communal Land Selection Titling Page 3 Component 1: Selection and Development Planning of Individual MLMUPC-CS-31 / Under IDA / 67060 Social Land Concession and Post Consultant Open 156,000.00 0.00 2021-04-23 2021-05-02 2021-06-11 2021-07-02 2021-08-06 2022-02-02 International Land Consultant Implementation Indigenous Communal Land Selection Titling MLMUPC-CS-32 / National Individual Component 2: Community Under Senior Infrastructure IDA / 67060 Post Consultant Open 72,000.00 0.00 2021-04-23 2021-05-02 2021-06-11 2021-07-02 2021-08-06 2022-02-02 Infrastructure Development Implementation Engineering Consultant Selection Component 1: Selection and Development Planning of Individual MLMUPC-CS-33 / National Under IDA / 67060 Social Land Concession and Post Consultant Open 72,000.00 0.00 2021-04-23 2021-05-02 2021-06-11 2021-07-02 2021-08-06 2022-02-02 Senior Operations Consultant Implementation Indigenous Communal Land Selection Titling Component 1: Selection and MLMUPC-CS-34 / National Development Planning of Individual Under Senior Environmental Risk IDA / 67060 Social Land Concession and Post Consultant Open 72,000.00 0.00 2021-04-23 2021-05-02 2021-06-11 2021-07-02 2021-08-06 2022-02-02 Implementation Management Consultant Indigenous Communal Land Selection Titling Component 1: Selection and MLMUPC-CS-35 / National Development Planning of Individual Under Senior Social Risk IDA / 67060 Social Land Concession and Post Consultant Open 72,000.00 0.00 2021-04-23 2021-09-08 2021-06-11 2021-07-02 2021-08-06 2022-02-02 Implementation Management Consultant Indigenous Communal Land Selection Titling Component 1: Selection and MLMUPC-CS-36 / Provincial Development Planning of Individual Environmental Risk IDA / 67060 Social Land Concession and Post Consultant Open 60,000.00 0.00 Under Review 2021-04-23 2021-12-07 2021-06-11 2021-07-02 2021-08-06 2022-02-02 Management Consultant Indigenous Communal Land Selection Titling Component 1: Selection and MLMUPC-CS-37 / Provincial Development Planning of Individual Social Risk Management IDA / 67060 Social Land Concession and Post Consultant Open 60,000.00 0.00 Under Review 2021-04-23 2021-12-07 2021-06-11 2021-07-02 2021-08-06 2022-02-02 Consultant Indigenous Communal Land Selection Titling Component 4: Project Individual MLMUPC-CS-44 / National Under IDA / 67060 Management, Coordination Post Consultant Open 72,000.00 0.00 2021-04-22 2021-09-08 2021-06-10 2021-07-01 2021-08-05 2022-02-01 Senior M&E Consultant Implementation and M&E Selection Component 4: Project Individual MLMPUC-CS-45 / Under IDA / 67060 Management, Coordination Post Consultant Open 156,000.00 0.00 2021-05-04 2021-09-08 2021-06-22 2021-07-13 2021-08-17 2022-02-13 International M&E Consultant Implementation and M&E Selection MLMUPC-CS-46 / Component 4: Project Individual Under International Operations IDA / 67060 Management, Coordination Post Consultant Open 156,000.00 0.00 2021-05-04 2021-09-08 2021-06-22 2021-07-13 2021-08-17 2022-02-13 Implementation Consultant and M&E Selection MLMUPC-CS-43 / Component 4: Project Intermittent National IDA / 67060 Management, Coordination Post Direct Selection Direct 20,000.00 16,560.00 Signed 2021-09-12 2021-09-09 2021-09-17 2021-09-26 2021-09-25 2021-10-01 2022-03-24 Procurement and Contract and M&E Management Consultant Component 1: Selection and Development Planning of Individual MLMUPC-CS-47 / Junior FM IDA / 67060 Social Land Concession and Post Consultant Open 36,000.00 0.00 Under Review 2021-11-19 2021-11-25 2021-12-23 2022-01-01 2022-01-13 2024-01-13 Management Consultant Indigenous Communal Land Selection Titling MLMUPC-CS-48 / National Component 4: Project Individual Under Procurement and Contract IDA / 67060 Management, Coordination Post Consultant Open 26,400.00 0.00 2021-11-12 2021-11-25 2021-12-16 2021-12-25 2022-01-06 2024-01-06 Implementation Management Assistant and M&E Selection Component 1: Selection and MLMUPC-CS-50 / Provincial Development Planning of Individual Environmental Risk IDA / 67060 Social Land Concession and Post Consultant Open 60,000.00 0.00 Under Review 2021-12-15 2021-12-07 2022-02-02 2022-02-23 2022-03-30 2024-03-19 Management Consultant Indigenous Communal Land Selection (Region-2) Titling Component 1: Selection and MLMUPC-CS-51 / Provincial Development Planning of Individual Environmental Risk IDA / 67060 Social Land Concession and Post Consultant Open 60,000.00 0.00 Under Review 2021-12-15 2021-12-07 2022-02-02 2022-02-23 2022-03-30 2024-03-19 Management Consultant Indigenous Communal Land Selection (Region 3) Titling Component 1: Selection and MLMUPC-CS-52 / Provincial Development Planning of Individual Social Risk Management IDA / 67060 Social Land Concession and Post Consultant Open 60,000.00 0.00 Under Review 2021-12-15 2021-12-07 2022-02-02 2022-02-23 2022-03-30 2024-03-19 Consultant (Region 2) Indigenous Communal Land Selection Titling Component 1: Selection and MLMUPC-CS-53 / Provincial Development Planning of Individual Social Risk Management IDA / 67060 Social Land Concession and Post Consultant Open 60,000.00 0.00 Under Review 2021-12-15 2021-12-07 2022-02-02 2022-02-23 2022-03-30 2024-03-19 Consultant (Regional 3) Indigenous Communal Land Selection Titling Component 1: Selection and MLMUPC-CS-54 / Indigenous Development Planning of Individual Pending Peoples (IPs) Development IDA / 67060 Social Land Concession and Post Consultant Open 14,400.00 0.00 2021-12-24 2022-01-24 2022-02-07 2022-02-28 2024-02-28 Implementation Facilitator Indigenous Communal Land Selection Titling Component 4: Project Individual MLMUPC-CS-49 / Pending IDA / 67060 Management, Coordination Post Consultant Open 21,600.00 0.00 2021-12-24 2022-02-20 2022-03-06 2022-03-20 2024-03-19 Administrative Assistant Implementation and M&E Selection Component 1: Selection and MLMUPC-CS-55 / Development Planning of Individual Pending Community Development IDA / 67060 Social Land Concession and Post Consultant Open 14,400.00 0.00 2022-01-07 2022-03-06 2022-03-20 2022-04-10 2024-04-09 Implementation Facilitators Indigenous Communal Land Selection Titling Page 4