PROCUREMENT PLAN (Textual Part) Project information: Country: Nigeria Project Name: Multi-Sectoral Crisis Recovery Project for North East Nigeria (MCRP) P- Number: P157891 Project Implementation Agency: MCRP PCU (Federal and States) Date of the Procurement Plan: Updated -December 22, 2017. Period covered by this Procurement Plan: From 01/12/2018 – 30/06/2019. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the FGN Public Procurement Act 2007; such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each: Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. 1. Prior Review Threshold for Goods, Works and Non-Consulting Services: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Prior Review Procurement Method Threshold (US$ Comments equivalent) ICB and LIB (Goods and services other than ≥ 5,000,000 ALL consultancy services) NCB (Goods, IT Systems and Non Consulting Services 100,000 < 5,000,000 NONE (NCB) ICB (Works) ≥ 20,000,000 ALL NCB (Works) 150,000 < 20,000,000 NONE Shopping-Goods ≤ 100,000 NONE Shopping-Works ≤ 150,000 NONE Based on Annual Training, Workshops, Study All Values Work Plans & Tours Budgets 2. Prequalification: Bidders for major works shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines, although it is not expected that there will be need for prequalification in the procurement arrangements for the MCRP. MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 2 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT 3. Proposed Procedures for CDD Components (as per paragraph. 6.52 of the Procurement Regulations): Shall apply. 4. Reference to the Project Implementation Manual: Shall apply. 5. Any Other Special Procurement Arrangements: Not Applicable 6. Procurement Packages (Goods and Works) indicating Bank’s Prior and Post Review. MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 3 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT a. Summary of Procurement of Goods: 1 2 3 4 5 6 Review by Estimated Ref. Packag Bank Commen Description Cost (US$ No. es (Prior / ts Million) Post) Total NCB 12.82 43 Post (Goods) Total RfQ (Goods/Non 0.04 1 Post Consulting Services) Procurement of Goods with Selection Methods and Time Schedule (Please see Annex I). b. Summary of Procurement of Civil Works 1 2 3 4 5 6 Review by Estimated Ref. Bank Commen Description Cost (US$ Packages No. (Prior / ts Million) Post) Total NCB 23.59 64 Post (Works) Total RfQ 2.29 20 Post (Works) Procurement of Civil Works with Selection Methods and Time Schedule (Please see Annex II). c. Summary of Procurement of Non- Consulting Services (TBD) 1 2 3 4 5 6 Review by Estimated Ref. Bank Commen Description Cost (US$ Packages No. (Prior / ts Million) Post) Total NCB 0.175 2 Post MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 4 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT 7. Prior Review Threshold for Consultancies: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Prior Review Selection Method Comments Threshold (USD) Consultant Services-QCBS- International 1. Consulting Services ≥ 300,000 ALL 2. Engineering and Construction ≥ 500,000 Supervision Consultant Services-QCBS < 300,000.00 NONE Consultant Services-CQS < 300,000.00 NONE Consultant Services-lC >300,000.00 ALL Consultant Services-lC <300,000.00 NONE Consultant Services- Single Source All Values ALL Selection Note: All ToRs to be prior review QCBS = Quality and Cost Based Selection SSS = Single Source Selection CQ = Consultant Qualification LCS = Least Cost Selection IC = Individual Consultant 8. Short list comprising entirely of National Consultants: Short list of consultants for services, estimated to cost less than $300,000.00 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. a. Summary of Consultancies 1 2 3 4 5 6 Ref. Description Estimate Package Review by Comment No. d Cost s Bank s (US$ (Prior/Post Million) ) Summary of number of 5.72 7 Prior contracts that will be let under International QCBS Summary of number of 6.45 16 Post contracts that will be let under National QCBS Summary of number of 1.74 30 Post contracts that will be let under CQS Summary of number of 0.35 3 Post contracts that will be let under MOU MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 5 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Summary of number of 0.021 3 Post contracts that will be let under Individual Consultancies MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 6 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Estimated Estimated Prior Number of Amount in Investable or Expected Procureme Pre- USD (Over Amount Post Bid- Description (List of Componen nt Procureme qualificati the Project for 18 Revie Opening Contracts) t/Sector Packages nt Method on Life) months w Date WORKS BORNO Construction Of 18-No Double Classroom Blocks in Ngohi, Biji-Biji, Ngulde, C2/Educati Post Tue-19-Jun- Rumirgo, Chul on 3 NCB No 708,196.72 354,098.36 Review 18 Construction Of 10- No. Double Classroom Block - C2/Educati Post Tue-19-Jun- Bama (Banki Town) on 2 NCB No 393,442.62 314,754.10 Review 18 Reconstruction Of 39- No. Double Classroom Block in C2/Educati Post Damasak, Mobbar on 4 NCB No 575,409.84 71,926.23 Review Tue-24-Jul-18 Construction Of 15- No. Double Classroom Block - C2/Educati Post Gajibo, Logomane (Dikwa) on 2 NCB No 590,163.93 147,540.98 Review Tue-24-Jul-18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 7 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Construction Of 25 No. Double Classroom Block C2/Educati Post GUZAMALA on 2 NCB No 983,606.56 245,901.64 Review Tue-24-Jul-18 Construction Of 20- No. Double Classroom Block - Kukawa Town, Baga, Cross- C2/Educati Post Tue-18-Sep- Kauwa on 2 NCB No 786,885.25 196,721.31 Review 18 Construction Of 10- No. Double Classroom Block - C2/Educati Post Tue-18-Sep- Monguno on 1 NCB No 393,442.62 98,360.66 Review 18 Construction Of 4- No. Double Classroom Block in C2/Educati Post Tue-20-Nov- Ajiri. Mafa on 1 NCB No 157,377.05 39,344.26 Review 18 Renovation Of 20- No. Double Classroom Blockin C2/Educati Post Tue-20-Nov- Damboa Town -Abadam on 2 NCB No 295,081.97 73,770.49 Review 18 Renovation Of 31- No. Double Classroom Block - C2/Educati Post Tue-23-Oct- Bama on 2 NCB No 457,377.05 114,344.26 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 8 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Construction Of 3-No. C2/Educati Post Tue-18-Sep- Educational Office -Kukawa on 1 NCB No 196,721.31 98,360.66 Review 18 Construction Of 2-No. Educational Office - C2/Educati Post Tue-20-Nov- Konduga on 1 NCB No 131,147.54 32,786.89 Review 18 Construction Of 2-No. Educational Office -Hawul C2/Educati Post Tue-23-Oct- Sakwa, Kwajafa on 1 NCB No 131,147.54 32,786.89 Review 18 Construction Of 4-No Vip C2/Educati Post Tue-18-Dec- Toilets -Askira-Uba on 1 RfQ No 59,016.39 47,213.11 Review 18 Construction Of 4-No Vip C2/Educati Post Tue-18-Dec- Toilets -Mafa on 1 RfQ No 59,016.39 47,213.11 Review 18 Construction Of 5-No Vip C2/Educati Post Tue-18-Dec- Toilets -Monguno on 1 RfQ No 73,770.49 59,016.39 Review 18 Renovation Of 1-No. Educational Office - C2/Educati Post Tue-18-Dec- Damboa on 1 RfQ No 18,032.79 4,508.20 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 9 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Renovation Of 1-No. Educational Office and 1- No. Principal's Quarters - Benisheik, Kaga- Benisheik, C2/Educati Post Tue-23-Oct- Kaga on 1 RfQ No 42,622.95 16,803.28 Review 18 Rehabilitation of 66KM C2/Transpo 1,223,144. Prior Tue-27-Feb- Maiduguri to Bama road rt 1 NCB No 9,785,152.68 08 Review 18 Rehabilitation of 1 Ngala C2/Transpo Prior Tue-27-Feb- Bridge rt 1 NCB No 2,295,081.97 483,983.71 Review 18 C2/Transpo Post Tue-27-Feb- Rehabilitation of Biu bridge rt 1 NCB No 902,111.48 73,770.49 Review 18 Construction of galameri- dusuman-zabarmari- C2/Transpo Prior Tue-27-Feb- gongulong feeder road rt 1 NCB No 1,104,625.69 59,016.39 Review 18 RehabilitatIon of 3 General Hospital in ABADAM, ASKIRA UBA, KALA-BALGEe and Rehabilitation of Prior Tue-27-Mar- comprehensive Healthcare C2/Health 3 NCB No 1,555,779.01 986,195.83 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 10 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT center (Civil Works, Solar Borehole, Fence & Security Post) Construction of PHC for 15 2,254,098. Prior Tue-27-Mar- LGAs C2/Health 5 NCB No 3,606,557.38 36 Review 18 Rehabilitation of Borno C2/Educati Post Tue-24-Apr- State Library on 2 NCB No 557,377.05 34,426.23 Review 18 Rehabilitation of Umar Ibn C2/Educati Post Tue-24-Apr- Ibrahim college Bama on 2 NCB No 557,377.05 278,688.52 Review 18 Construction of Solar Powered Boreholes (2Nos) in Umar Ibn Ibrahim college Bama Solar Lighting System to Borno C2/Educati Post Tue-24-Apr- Library on 1 NCB No 196,721.31 98,360.66 Review 18 Rehabilitation of Court Buildings in Bama Gwoza C2/Public Post Tue-22-May- Dikwa Mobbar Buildings 4 RfQ No 393,442.62 49,180.33 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 11 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Local Govt Secretariats in Kukawa, Monguno, biu ,Abadam, Kala-Balge, Marte, C2/Public 1,229,508. Post Tue-05-Jun- Magumeri, Guzamala Buildings 8 RfQ No 1,967,213.11 20 Review 18 Rehabilitation of Traditional Rulers' Konduga , Monguno, Kukawa, Nganzai, Baga, Marte, Ngala, Abadam, Guzamala, C2/Public Post Tue-05-Jun- Kwajafa, Kumshe Buildings 6 RfQ No 1,442,622.95 180,327.87 Review 18 Provision of Community Resource Centres in 20 C2/Public Post LGAs Buildings 10 NCB No 2,295,081.97 860,655.74 Review Thu-05-Jul-18 Construction of Handpump Wells in Bama (3) Chibok (5), Biu (5), Mafa(3), Hawul (5), Askira/Uba(5), Konduga(4), Jere(5) Dikwa Post Fri-03-Aug- (3), Gwoza(5), C2/WASH 10 RfQ No 140,983.61 35,245.90 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 12 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Construction of Solar Powered Boreholes in Askira Uba Gwoza(4),Bama(4), Ngala(3), Damboa(3) Jere(4),Kukawa(3), Biu(2),Konduga(3), Gubio(3), Askira/Uba(3), Magumeri(3), Marte(3), Mobbar(3), Monguno(3), Dikwa(2), Mafa(3), Abadam(3), Nganzai(3), Guzamala(3), Kaga(2), Chibok(2), Kala/Balge(3), Hawul(2)(To include 2Nos 5,000lt Plastic water tanks on a 1.5m raised platform , five fetching points/tap gallery, chain link 3,501,639. Post Wed-25-Jul- perimeter fence) C2/WASH 14 NCB No 4,668,852.46 34 Review 18 REHABILITATION OF LOCAL GOVERNMENT LODGES (Marte, Kaga, Chibok, Magumeri, Gwoza, Kala- Balge, Ngala, Guzamala, Abadam, Hawul, C2/Public Post Tue-21-Aug- Askira/Uba, Bama) Buildings 6 NCB No 1,311,475.41 786,885 Review 18 Rehabilitationof Traditional Rulers' Buildings Bama, Konduga, Gwoza ,Kareto, C2/Public Post Damboa , Monguno, Buildings 11 RfQ No 1,442,622.95 180,327.87 Review Thu-26-Jul-18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 13 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Kukawa, Askira-Uba , Dikwa, Baga, Marte REHABILITATION OF MINISTRY BUILDING (Ngala, C2/Public Post Tue-21-Aug- Monguno) Buildings 2 NCB No 276,577 Review 18 CONSTRUCTION OF SANITATION FACILITIES IN 21 LOCAL GOVERNMENT AREAS.ABADAM (6) ASKIRA(6) BAMA(6) BIU(6) CHIBOK(6) DAMBOA(6) DIKWA(6) GUBIO(6) GWOZA(6) JERE(6) KAGA(6) KALA-BALGE(6) KONDUGA(6) KUKAWA(6) MAFA(5) MOBBAR(6) MONGUNO(6) MARTE(6) NGALA(6) NGANZAI(6) Post Wed-19-Sep- MAGUMERI(6) C2/WASH 21 NCB No 781,517 Review 18 REHABILITATION OF EXISTING NON- FUNCTIONAL BOREHOLES ABADAM (1) ASKIRA UBA (2) BIU (2) DIKWA (1) Post Tue-18-Sep- GUBIO (1) GUZAMALA (1) C2/WASH 6 NCB No 258,525 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 14 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT JERE (2) KALA BALGE (1) MAFA (2) MAGUMERI (1) MARTE (2) MOBBAR (1) NGALA (1) NGANZAI (1) Rehabilitation of 8 blocks of Laborataries (Umar Ibn C1/Educati Post Tue-18-Sep- Ibrahim college Bama) on 1 NCB No 262,295 Review 18 ADAMAWA Rehabilitation of Gulak Post Mon-14-May- Water Supply System C2/Water 1 NCB No 179,190.16 134,392.62 Review 18 Rehabilitation of Hong Post Mon-14-May- Water Supply System C2/Water 1 NCB No 116,646.90 87,485.18 Review 18 Rehabilitation of Michika Post Mon-14-May- Water supply system C2/Water 1 NCB No 138,193.44 103,645.08 Review 18 Rehabilitation of Uba Water Post Tue-15-May- Supply system C2/Water 1 NCB No 71,967.21 71,967.21 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 15 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of exisitng Water Supply sources in Post Tue-15-May- Gombi C2/Water 1 NCB No 30,475.41 30,475.41 Review 18 Construction of Uba New Post Mon-28-May- Water Supply Project C2/Water 1 NCB No 721,222.95 108,183.44 Review 18 Pella New Water Supply Post Mon-28-May- Project C2/Water 1 NCB No 555,289.34 83,293.40 Review 18 Construction of Hong New Post Mon-28-May- Water supply project C2/Water 1 NCB No 1,256,442.62 188,466.39 Review 18 Construction of Michika Post Tue-29-May- New Water supply project C2/Water 1 NCB No 1,189,261.84 178,389.28 Review 18 Construction GOMBI NEW Post Tue-29-May- WATER SUPPLY PROJECT C2/Water 1 NCB No 915,241.80 137,286.27 Review 18 Installation of 12 nos. Solar Boreholes (in secondary schools)- GSS Gombi, GDSS Garkida, GSS Hong, GDSS Pella, GSSS Uba, Post Thu-10-May- GJSS Uba, GDSS Garaha, C2/Water 1 NCB No 377,609.70 75,521.94 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 16 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT GDSS Kwarhi, GDSS Za'ah, GSS Madagli, GSS Shuwa, GSS Gulak, GCSS Shuwa Installation of 37 Nos Solar Boreholes in 37 Health Centers in 7 Local Post Thu-10-May- Governments Areas C2/Water 4 NCB No 1,164,296.59 291,074.15 Review 18 Construction of 295Nos Hand Powered Bore Holes (in 2 primary schools per 35 wards, 35 Markets, 35 Motor parls and 155 Communities across 7 Post Thu-03-May- LGAs) C2/Water 4 NCB No 1,257,377.05 503,483.61 Review 18 Construction of VIP Latrines of 3-Comp (2 Blks Post Tue-14-Aug- in 24 pri sch) C2/WASH 3 RfQ No 212,459.02 79,672.13 Review 18 VIP Latrine of 3-Comp (2 Post Tue-14-Aug- Blks in 26 Markets) C2/WASH 3 RfQ No 230,163.93 92,065.57 Review 18 VIP Latrine of 3-Comp (2 Post Tue-14-Aug- Blks in 26 Motor Parks) C2/WASH 3 RfQ No 230,163.93 92,065.57 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 17 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Lokwa C2/Transpo Post Mon-11-Jun- Bridge Mubi rt 1 NCB No 475,143.96 356,357.97 Review 18 Reconstruction of Main Road - Bangshika Road C2/Transpo Prior Mon-11-Jun- 2.5Km rt 1 NCB No 1,019,295.08 127,411.89 Review 18 Rehabilitation of Mubi Bazza Road with a spur to C2/Transpo 1,255,469. Prior Mon-11-Jun- Mayo Bani 45Km rt 1 NCB No 8,369,796.72 51 Review 18 Rehabilitation of PHC, Construction of Perimeter Fence and Staff Quarters (Civil Works, Solar Borehole, Fence & Security C2/Educati Prior Tue-10-Apr- Post) in 7 Communities on 7 NCB No 1,139,130.43 451,779.49 Review 18 Rehabilitation of Cottage Post Tue-10-Apr- Hospital C2/Health 1 NCB No 451,768.85 192,001.76 Review 18 Establishment of Trauma Post Thu-17-May- Center @ general hospital C2/Health 1 RfQ No 65,194.96 65,194.96 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 18 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Renovation of GSS in 10 Towns (Gombi, Hong, Uba, Shuwa, Michika, Bazza, Mubi 1, Maiha, Madagali, C2/Educati Post Mubi North) on 10 NCB No 2,305,292.65 442,327.22 Review Tue-10-Jul-18 Renovation of 25Nos C2/Educati Post Primary School over 7 LGAs on 4 NCB No 865,747.88 324,655.45 Review Tue-10-Jul-18 Rehabilitation of Local Government Secretariat - C2/Public Post Thu-07-Jun- Song Buildings 1 NCB No 288,590.56 144,295.28 Review 18 Rehabilitation of Local Government Secretariat - C2/Public Post Thu-07-Jun- Madagali Buildings 1 NCB No 315,082.89 157,541.44 Review 18 Rehabilitation of District Head's Palace in 5 Communities (Uba, Gella, Gombi, Maiha/Pakka, C2/Public Post Thu-07-Jun- Gulak) Buildings 5 NCB No 422,463.57 158,423.84 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 19 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT YOBE Conversion of Motorised Boreholes (28 Communities in Gulani and Damaturu) into Solar Post Mon-26-Mar- Powered C2/Water 1 NCB No 334,013.66 250,510.24 Review 18 Conversion of existing Motorized powered Borehole without Overhead tank into solar powered (Gujba, Gulani, Yunusari, Damaturu,& Post Mon-26-Mar- Geidam ) C2/Water 1 NCB No 277,532.56 208,149.42 Review 18 Conversion of existing Motorized powered Borehole into solar powered and construction of New Overhead tank (Gujba, Gulani, Yunusari, Post Mon-26-Mar- Damaturu,& Geidam) C2/Water 2 NCB No 542,490.73 406,868.05 Review 18 Drilling of New Solar Powered Boreholes in Gujba, Gulani, Yunusari, Damaturu, Fika, Potiskum, Post Mon-02-Apr- Geidam & Fune C2/Water 2 NCB No 878,917.25 329,593.97 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 20 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Solar Powered Boreholes in Gulani, Gujba and Post Mon-02-Apr- Damaturu C2/Water 1 NCB No 244,228.65 183,171.49 Review 18 Construction & Upgrade of Post Wed-24-Oct- 33 nos. PHC Centres C2/Health 5 NCB No 5,386,554.10 538,655.41 Review 18 Reconstruction of Vandalized 3 Nos Post Wed-09-May- Immunization Offices C2/Health 1 RfQ No 68,618.27 68,618.27 Review 18 Renovation of 1No. General Post Mon-03-Sep- Hospital in Buni Yadi C2/Health 1 RfQ No 88,524.59 44,262.30 Review 18 Construction of 1No. Student Hostel each in College of Nursing and Midwifery Damaturu and College of Health Sciences Post Wed-22-Aug- and Technology, Nguru C2/Health 2 NCB No 983,606.56 245,901.64 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 21 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Renovation of Govt Secondary Schools in Goniri,Bara, Bularafa, ,Kananma, Damagum, Buni Yadi, Kukuwa, Gujba and C2/Educati Post Mon-09-Apr- Best Center in Goniri on 5 NCB No 2,001,760.77 800,704.31 Review 18 Renovation of Dokshi C2/Educati Post Mon-09-Apr- Primary school, Gulani on 1 NCB No 168,034.42 67,213.77 Review 18 Rehabilitation of Local Government Office Secretariat in Gujba and C2/Public Post Wed-09-May- Potiskum Buildings 2 NCB No 472,529.40 75,459.62 Review 18 Rehabilitation of Development Offices in Gujba , Gulani, Yunusari & C2/Public Post Wed-09-May- Geidam Buildings 1 RfQ No 62,203.18 15,550.80 Review 18 Provision of Community Resource Centres in all 17 C2/Public Post Wed-23-May- LGAs Buildings 5 NCB No 1,950,819.67 731,557.38 Review 18 Rehabilitation of Audit C2/Public Post Wed-26-Sep- Office Buildings 1 RfQ No 63,078.12 15,769.53 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 22 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Zonal C2/Public Post Wed-26-Sep- Statistical Office Buildings 1 RfQ No 50,491.80 25,245.90 Review 18 Rehabilitation ofCultural Buildings (District Head's Palace) in Buni Yadi and C2/Public Post Mon-27-Aug- Damagum Buildings 2 NCB No 446,682.62 111,670.66 Review 18 Rehabilitation of Government Buildings; C2/Public Post Mon-11-Jun- Agency for Mass Literacy Buildings 1 RfQ No 121,445.24 60,722.62 Review 18 Rehabilitation of Government Buildings; C2/Public Post Mon-11-Jun- Town Engineers Office Buildings 1 RfQ No 121,445.24 60,722.62 Review 18 GOODS BORNO Supply of Returnee C1/Transiti Resettlement Kits Bama, onal 2,216,737. Tue-13-Feb- Dikwa, Gwoza, Ngala, Support 4 NCB No 2,216,737.30 30 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 23 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Monguno, Damboa, Gudumbali, Mobbar, Kala Balge) Supply of Agricultural Support kits with Seeds, Fertilizers and Small Work Farm Tools (Bama, Biu, Gwoza, Ngala, Monguno, C1/Transiti Damboa, Askira, Mobbar, onal Tue-13-Feb- Kukawa) Support 3 NCB No 681,729.10 681,729.10 Post 18 Supply of Small Animals (Bama, Mafa, Gwoza, Ngala, Monguno, Damboa, C1/Transiti Chibok, Nganzai, Kala onal Tue-20-Feb- Balge) Support 3 NCB No 788,935.25 788,935.25 Post 18 Supply of Non-agricultural Livelihood Kits (Bama, Dikwa, Gwoza, Ngala, C1/Transiti Monguno, Damboa, Chibok, onal Tue-13-Feb- Mobbar, Hawul Support 2 NCB No 227,377.05 227,377.05 Post 18 C1/Transiti Supply of Skills Acquisition onal Tue-20-Feb- Start up Kits Support 3 NCB No 737,704.92 387,295.08 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 24 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Supply of solar electrification to 3 GENERAL HOSPITALS in ABADAM, GWOZA and KALA-BALGE and five Comprehensive Health Centre in Abadam, 2 in Gwoza, Kala-Balge, Askira - Tue-01-Jan- Uba C2/Health 3 NCB No 670,553.40 516,770.59 Post 19 Supply of Medical Equipment For 3General Hospitals in ABADAM, ASKIRA UBA, and KALA- Tue-15-Jan- BALGE C2/Health 3 NCB No 590,163.93 73,770.49 Post 19 Supply of Essential Drugs/Medical Consumables For 3 General Hospitals in HAWUL, Tue-05-Mar- MOBBAR AND DAMBOA C2/Health 3 NCB No 472,131.15 59,016.39 Post 19 Supply of Medical Equipment for Comprehensive Health Wed-09-Jan- Centers (Gwoza- Izge) C2/Health 1 NCB No 245,901.64 30,737.70 Post 19 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 25 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Supply of Essential Drugs/Medical Consumables for Comprehensive Health Tue-05-Feb- Center (Gwoza-izge) C2/Health 1 NCB No 236,065.57 29,508.20 Post 19 Supply of Medical Equipment to 15 PHCs to (Ngala, Nganzai Kukawa, Biu, Konduga, Gubio, Askira/Uba, Guzamala, Bama, Jere, Marte, Mobbar, Dikwa, Tue-15-Jan- Mafa, Abadam) C2/Health 2 NCB No 983,606.56 122,950.82 Post 19 Supply of Essential Drugs to 15 PHCs (Ngala, Nganzai Kukawa, Biu, Konduga, Gubio, Askira/Uba, Guzamala, Bama, Jere, Marte, Mobbar, Dikwa, Tue-05-Feb- Mafa, Abadam) C2/Health 2 NCB No 786,885.25 98,360.66 Post 19 Supply and Installation of Solar Inverters in 15 PHCs in (Ngala, Nganzai Kukawa, Biu, Konduga, Gubio, Askira/Uba, Guzamala, Bama, Jere, Marte, Mobbar, Tue-06-Mar- Dikwa, Mafa, Abadam) C2/Health 1 NCB No 262,295.08 65,573.77 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 26 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Furniture for Library/ Offices in the Borno State Library and Furniture for 15 blocks of classrooms in Umar Ibn ibrahim college C2/Educati Tue-19-Mar- Bama on 2 NCB No 491,803.28 245,901.64 Post 19 Books and other learning Materials including elibrary C2/Educati Tue-19-Mar- in the Borno State library on 1 NCB No 262,295.08 131,147.54 Post 19 Suppy of Computers and other accessories to the Borno State Library , Maiduguri and Umar Ibn C2/Educati Tue-19-Mar- ibrahim college Bama on 2 RfQ No 81,967.21 40,983.61 Post 19 Supply of Medical Equipment TO 3 Comprehensive Health centers IN HAWUL, MOBBAR AND DAMBOA Tue-06-Mar- (Kwajafa, Kareto, Damboa) C2/Health 1 NCB No 196,721.31 49,180.33 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 27 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Installation of solar inverters for PHC Gwoza( Tue-06-Mar- Izge) C2/Health 1 NCB No 13,114.75 13,114.75 Post 18 ADAMAWA C1/Transiti Supply of Returnee onal Mon-19-Mar- Resettlement Kits Support 2 NCB No 490,780.33 490,780.33 Post 18 Supply of Agricultural Support kits with Seeds, C1/Transiti Fertilizers and Small Work onal 1,496,508. Mon-19-Mar- Farm Tools Support 7 NCB No 1,496,508.20 20 Prior 18 C1/Transiti onal Thu-19-Apr- Supply of Small Animals Support 1 NCB No 182,950.82 182,950.82 Post 18 C1/Transiti Supply of Non-agricultural onal Mon-19-Mar- Livelihood Kits Support 1 NCB No 213,442.62 213,442.62 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 28 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C1/Transiti Start up kits for quick to onal Mon-19-Mar- market trading Support 1 NCB No 114,754.10 114,754.10 Post 18 Housing Refurbishment Returnee Packs for Voluntary Returnees across C1/Transiti the 7 LGAs being onal Thu-14-Jun- rehabilitated. Support 2 NCB No 390,163.93 331,639.34 Post 18 Supply of Medical Equipment to PHCs in 7 communities and Cottage Hospital in Gulak C2/Health 2 NCB No 344,262.30 43,032.79 Post Thu-19-Jul-18 Supply of Essential Drugs/Medical Consumable to PHCs in 7 Communities and Cottage Hospital in Thu-01-Nov- Gulak C2/Health 2 NCB No 452,459.02 108,196.72 Post 18 Installation of Solar Inverters in 7 Rehabilitated PHCs, Cottage Hospital in Mon-06-Aug- Gulak C2/Health 3 NCB No 268,861.16 18,852.46 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 29 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Equipping of Trauma Center @ Michika General Mon-06-Aug- hospital C2/Health 1 NCB No 214,142.46 80,303.42 Post 18 Supply of Furniture to C2/Educati Thu-29-Mar- Primary Schools in 7 LGAs on 1 NCB No 245,901.64 30,737.70 Post 18 Supply of Books and Teaching/Learning Materials to Primary C2/Educati Thu-29-Mar- Schools in 7 LGAs on 1 NCB No 327,868.85 122,950.82 Post 18 Establishment of spare part supply chain/buffer Mon-16-Apr- stock for Water Facilities C2/WASH 1 NCB No 114,754.10 86,065.57 Post 18 Train the Trainer/User Workshops (i.e. 2 per LGA) for VLOM (Village Level Operation and Maintenance) WASHCOMS, (WASH Committees at LGA Level, WASH Units @ LGAs, VHPs (Voluntary Hygiene Promoters) State/LGA Govt Tue-24-Apr- Officials. C2/WASH 1 NCB No 72,131.15 54,098.36 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 30 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT YOBE C1/Transiti Supply of Non Food Items onal Wed-21-Mar- (NFIs) Kits Support 3 NCB No 559,213.11 559,213.11 Post 18 C1/Transiti Supply of Agricultural kits onal 1,048,940. Wed-21-Mar- with seeds, oil, small tools Support 3 NCB No 1,048,940.98 98 Post 18 C1/Transiti onal Mon-23-Apr- Supply of Small Animals Support 3 NCB No 688,524.59 688,524.59 Post 18 C1/Transiti Non-agricultural Livelihood onal Mon-26-Mar- kits Support 2 NCB No 352,295.08 352,295.08 Post 18 C1/Transiti Supply of Skills Acquisition onal Wed-21-Mar- Start up Kits Support 3 NCB No 786,885.25 550,819.67 Post 18 Procure and distribute Plumpy Nuts for Wed-25-Apr- malnourished children in C2/Health 1 NCB No 215,438.65 32,315.80 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 31 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Gujba, Geidam and Yunusari LGAs Equipping of Trauma Mon-12-Feb- Center C2/Health 1 NCB No 214,147.54 53,536.89 Post 18 Supply of Students Textbooks and Teachers' C2/Educati Mon-17-Sep- Guides on 1 NCB No 284,062.30 71,015.57 Post 18 Supply of Laboratory Equipment Physics. C2/Educati Mon-17-Sep- Chemistry & Biology on 1 NCB No 213,114.75 53,278.69 Post 18 C2/Educati Mon-17-Sep- Supply of School Furniture on 3 NCB No 804,885.25 201,221.31 Post 18 CONSULTING SERVICES BORNO Skills Acquisition Training C1/Transiti (3Nos Consultancies across onal Mon-09-Jul- 10 LGAs) Support 3 QCBS No 491,803.28 258,196.72 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 32 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Specialized psycho-social support responding to C1/Commu needs (3Nos Consultancies nity Wed-28-Mar- across 10 LGAs) Resilience 3 QCBS No 826,229.51 619,672.13 Post 18 Consultancy for the Mobilisation and Organisation of Civic Education with Cultural and Recreational activities at Community Level with programs that respond to needs as prioritized by community based diagnosis (3Nos C1/Commu Consultancies across 10 nity Wed-11-Apr- LGAs) Resilience 3 QCBS No 442,622.95 265,573.77 Post 18 Consultancy for Sensitization, Community Mobilization and formation of peace groups within 7 Communities(establishmen t of community platforms to discuss community needs, grievances; and C1/Commu redress mechanisms. (1No nity Mon-30-Apr- Consultancy) Resilience 1 QCBS No 531,147.54 318,688.52 Prior 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 33 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Consultancy for Post- C1/Commu Conflict Transitional Justice nity Mon-21-May- and Accountability Resilience 1 QCBS No 147,540.98 88,524.59 Post 18 Statewide sponsorship for Radio Programming for Peacebuilding Campaign and Content for dissemination (focusing on deradicalisation, grievance C1/Commu redress and peacebuilding nity Mon-04-Jun- outreach themes) Resilience 1 CQS No 475,409.84 178,278.69 Prior 18 Consultancy for Educational campaigns for the prevention of mine and unexploded ordinance accidents /Mobilisation and Sensitization Campaign on Mine Action (Unexploded C1/Commu Ordnances) (1No nity Mon-04-Jun- Consultancy) Resilience 1 QCBS No 442,622.95 354,098.36 Prior 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 34 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Consultancy for Leadership Accountability and Transparency Training Programme (NELATTP) Targeting 20 LGA Staff and State Ministry Personal per LGA - Development of a transparency and accountability Local Governance Model through community participation C1/Commu (social accountability nity Fri-25-May- mechanisms) Resilience 1 CQS No 88,524.59 55,327.87 Post 18 Consultancy for Registration, Mapping and C1/Strengt Profiling of all local hening government structures and Local existing capacities State Governanc Fri-25-May- Wide e 1 CQS No 49,180.33 30,737.70 Post 18 Consultancy to provide C1/Strengt Capacity building of LG hening Officers for economic Local planning and policy Governanc Fri-25-May- development e CQS No 88,524.59 55,327.87 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 35 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C1/Strengt hening Capacity building for LG Local officials on programme Governanc Fri-25-May- design and implementation e CQS No 88,524.59 55,327.87 Post 18 Capacity building of LG C1/Strengt Officers for local hening governments on budget Local planning and execution, Governanc Fri-25-May- monitoring and reporting e 1 CQS No 88,524.59 55,327.87 Post 18 Capacity building of LG Officers for strategic communications C1/Strengt (Legislative Advocacy, hening Media relations, Local Stakeholder Management Governanc Fri-25-May- etc). e CQS No 88,524.59 55,327.87 Post 18 Capacity Building for 10 Local Government C1/Strengt Emergency Management hening Responders in Displaced Local and Transitional Local Governanc Fri-25-May- Government Officials e 1 CQS No 203,278.69 152,459.02 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 36 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Sensitization, training (especially on Identification, Documentation, Tracing and Reunification and follow up) and coaching for state and non-state partners on case management of UASC C1/Program (Unaccompanied and Support to Fri-25-May- Separated Children) UASC 1 MOU No 73,770.49 59,016.39 Post 18 Training for officials of relevant State MDAs on C1/Program effective approaches to Support to Thu-28-Jun- UASC UASC 1 IC No 16,393.44 13,114.75 Post 18 Teacher Training and C1/Educati Fri-25-May- Recertification on 1 MOU No 442,622.95 77,459.02 Post 18 Training of Community Health Workers (CHeWs, VHWs, Midwives) to Staff Targeted Health Facilities (3Nos consultancies across the state. Amount Inclusive of Workshop and per diem Mon-29-Apr- payments) C1/Health 3 QCBS No 796,721.31 298,770.49 Post 19 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 37 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Sensitization and Mobilisation for Health (Outreach Programs) in 27 LGAs (Over 10 Fri-25-May- engagements) C1/Health 10 CQS No 708,196.72 265,573.77 Post 18 Identification and training of Village Levels Mechanics and Local Area Mechanics on Operation and Maintenance of existing Hand Pump and Solar powered Borehole for effective utilization and Fri-25-May- management. C2/WASH 1 CQS No 98,360.66 73,770.49 Post 18 ADAMAWA Refresher Training of Existing Extension Workers C1/Transiti to support Livelihoods onal Thu-10-May- Projects Support 1 CQS No 65,573.77 65,573.77 Post 18 Training of affected farmers to apply inputs and access targeted C1/Transiti agricultural value chains onal Thu-21-Jun- and agribusiness skills Support 1 CQS No 167,216.39 167,216.39 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 38 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Establishment of Returnees Resettlement Registry at each LGA for Sensitization, Mobilisation and Logistics support for Safe and C1/Transiti Voluntary returns to 7 onal Thu-24-May- LGAs being rehabilitated Support 1 CQS No 61,565.57 49,252.46 Post 18 Consultancy to provide C1/Transiti Training for Bio Data onal Thu-10-May- Registration Support Support 1 IC No 1,377.05 1,101.64 Post 18 Consultancy for Sensitization, Community Mobilization and formation of peace groups within 7 Communities(establishmen t of community platforms to discuss community C1/Commu needs, grievances; and nity Mon-04-Jun- redress mechanisms Resilience 1 QCBS No 344,262.30 206,557.38 Prior 18 Diagnosis of community- specific reconciliation, peacebuilding and social C1/Commu cohesion needs and nity Thu-03-May- consequent development Resilience 2 QCBS No 344,262.30 206,557.38 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 39 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT of Civil Education Programs using Cultural and Recreational activities at Community Level (2Nos Consultancies) Provision of specialized psycho-social assessment and support responding to needs through group support, recreational, customary and socializing activities, referrals etc C1/Commu (3Nos Consultancies across nity Mon-11-Jun- the affected areas) Resilience 3 QCBS No 642,622.95 481,967.21 Post 18 Sensitization and Mobilisation Programs for Awareness against Stigmatization of Woman and Children associated C1/Commu with armed groups. (1No nity Mon-04-Jun- Consultancy) Resilience 1 QCBS No 413,114.75 247,868.85 Prior 18 Consultancy for Mediation and Alternate Dispute Resolution Capacity C1/Commu Building within the nity Mon-18-Jun- Community Leadership and Resilience 3 QCBS No 425,960.66 255,576.39 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 40 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Governance Structures (3Nos Consultancies acrossthe state) C1/Citizen- Consultancy for Leadership Governmen Accountability and t Transparency Training Relationshi Thu-10-May- Programme p Building 1 CQS No 72,131.15 45,081.97 Post 18 Registration, Mapping and C1/Strengt Profiling of all local hening government structures and Local existing capacities State Governanc Mon-28-May- Wide e 1 CQS No 39,344.26 24,590.16 Post 18 C1/Strengt Capacity building of LG hening Officers for economic Local planning and policy Governanc Mon-28-May- development e 1 CQS No 72,131.15 45,081.97 Post 18 C1/Strengt hening Capacity building for Local programme design and Governanc Mon-28-May- implementation e 1 CQS No 72,131.15 45,081.97 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 41 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Capacity building of LG C1/Strengt Officers for local hening governments on budget Local planning and execution, Governanc Mon-28-May- monitoring and reporting e 1 CQS No 72,131.15 45,081.97 Post 18 Capacity building of LG Officers for strategic communications C1/Strengt (Legislative Advocacy, hening Media relations, Local Stakeholder Management Governanc Thu-21-Jun- etc). e 1 CQS No 72,131.15 45,081.97 Post 18 Hygiene Promotion Mon-17-Sep- Sensitization/Mobilization C2/WASH 1 IC No 9,180.33 6,885.25 Post 18 Hygiene Promotion Mon-12-Nov- Campaign C2/WASH 1 CQS No 85,677.59 64,258.20 Post 18 Training of Community Health Workers (CHeWs) to Staff Targeted Health Thu-13-Dec- Facilities C2/Health 1 CQS No 68,852.46 55,081.97 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 42 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Sensitization and Mobilisation for Health Mon-17-Sep- (Outreach Programs) C2/Health 1 CQS No 183,606.56 146,885.25 Post 18 Mobilization and Sensitization for Children C2/Educati Thu-31-May- Education on 1 CQS No 206,557.38 206,557.38 Post 18 Teacher Training and Recertification ( Primary C2/Educati Thu-13-Dec- and Secondary Schools ) on 1 CQS No 360,655.74 360,656.74 Prior 18 YOBE Skills Acquisition Training C1/Transiti 3 Nos Consultancies across onal Wed-25-Apr- 8 LGAs) Support 3 QCBS No 524,590.16 367,213.11 Post 18 Consultancy for Sensitization, Community Mobilization and formation of peace groups within 15 C1/Peace Wed-23-May- Communities Building 1 QCBS No 491,803.28 319,672.13 Prior 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 43 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Diagnosis of community- specific reconciliation, peacebuilding and social cohesion needs and consequentt development of Civil Education Programs using Cultural and Recreational activities at C1/Peace Mon-04-Jun- Community Level Building 1 CQS No 49,180.33 31,967.21 Post 18 Consultancy for Mediation and Alternate Dispute Resolution Capacity Building within the Community Leadership and C1/Peace Mon-04-Jun- Governance Structures Building 1 CQS No 177,049.18 115,081.97 Post 18 Radio programs on mine awareness, dispute resolution in Hausa, Kanuri C1/Peace Wed-25-Jul- and Fulfulde Building 1 CQS No 280,719.92 105,269.97 Post 18 Provision of specialized psycho-social assessment and support responding to needs (3 Nos Consultancies C1/Peace Wed-20-Jun- across 8 LGAs) Building 3 QCBS No 625,822.95 438,076.07 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 44 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Mapping and profiling of local government C1/Strengt structures and hening communities in places of Local both displacement and Governanc Thu-28-Jun- origin e 1 CQS No 39,344.26 39,344.26 Post 18 Establishment of C1/Strengt community platforms to hening discuss community needs, Local grievances; and building a Governanc Wed-06-Jun- bottom-up planning model e 1 CQS No 74,948.93 59,959.14 Post 18 Development of a transparency and accountability model C1/Strengt through community hening participation (social Local accountability Governanc Wed-06-Jun- mechanisms) e 1 CQS No 47,377.05 37,901.64 Post 18 C1/Strengt Capacity building of LG hening Officers for economic Local planning and policy Governanc Thu-28-Jun- development e 1 CQS No 55,737.70 44,590.16 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 45 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C1/Strengt hening Capacity building for Local programme design and Governanc Thu-28-Jun- implementation e 1 CQS No 55,737.70 44,590.16 Post 18 Capacity building of LG C1/Strengt Officers for local hening governments on budget Local planning and execution, Governanc Thu-28-Jun- monitoring and reporting e 1 CQS No 55,737.70 44,590.16 Post 18 Capacity building of LG Officers for strategic communications C1/Strengt (Legislative Advocacy, hening Media relations, Local Stakeholder Management Governanc etc). e 1 CQS No 55,737.70 44,590.16 Post Thu-26-Jul-18 Sensitization, training (especially on Identification, Documentation, Tracing and Reunification and follow up) and coaching for state and non-state C1/Program partners on case Support on Thu-07-Jun- management of UASC UASC 1 CQS No 52,459.02 41,967.21 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 46 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Training for officials of C1/Program relevant MDAs on effective Support on Thu-28-Jun- approaches to UASC UASC 1 CQS No 8,196.72 6,557.38 Post 18 Menstrual Hygiene Management to support Women and Girls of productive ages to effectively maintain their Thu-17-May- menstrual hygiene C2/WASH 1 QCBS No 110,163.93 41,311.48 Post 18 Community Led Total Sanitation (CLTS) Implementation in Thu-31-May- communities C2/WASH 1 QCBS No 220,327.87 82,622.95 Post 18 Community Management training of entire Communities in the 8 proposed LGAs to effectively manage their Water, Sanitation and Mon-18-Jun- Hygiene Facilities C2/WASH 3 QCBS No 293,770.49 110,163.93 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 47 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Identification and training of Village Levels Mechanics and Local Area Mechanics on Operation and Maintenance of existing Hand Pump and Solar powered Borehole for effective utilization and Thu-17-May- management. C2/WASH 1 CQS No 98,360.66 61,475.41 Post 18 Water Safety Plan implementation in the entire Communities of the Mon-16-Jul- four LGAs. C2/WASH 1 CQS No 112,459.02 84,344.26 Post 18 Integrated Outreach Services (Up to 5 activities Thu-17-May- envisaged) C2/Health 5 QCBS No 344,262.30 129,098.36 Post 18 Training of Community Health Workers (CHeWs, VHWs, Midwives) to Staff Thu-15-Nov- Targeted Health Facilities C2/Health 1 QCBS No 501,639.34 376,229.51 Prior 18 Teacher Training and C2/Educati Mon-26-Nov- Recertification in all LGAs on 1 MOU No 278,688.52 209,016.39 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 48 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT PCNI NERSP PMC CELL Project Wide Project C3/Technic Management Consultancy al 2,000,000. Wed-11-Apr- Firm Assistance 1 QCBS No 3,000,000.00 00 Prior 18 Consultancy services for immediate- and medium- term implementation capacity building (4 C3/Technic separate Consultancies al Thu-03-May- Envisaged) Assistance 4 CQS No 536,393.44 268,196.72 Prior 18 Consultancy Services for C3/Technic Monitoring and Evaluation al Baseline Study Assistance 1 QCBS No 177,049.18 177,049.18 Post Fri-27-Apr-18 Consultancy services for setting up citizen engagement and third C3/Technic party monitoring al mechanisms Assistance 1 CQS No 177,049.00 59,016.33 Post Fri-06-Apr-18 Consultancy Services for C3/Technic Environmental Impact al Assessment Assistance 1 QCBS No 39,344.26 39,344.26 Post Fri-13-Apr-18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 49 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT NON- CONSULTING SERVICES ADAMAWA Door to Door Collection of Thu-24-May- Solid waste in 7 LGAs C2/WASH 1 NCB No 236,065.57 88,524.59 Post 18 Disposal of Waste from Door to Door Collection in Tue-13-Feb- 7 LGAs C2/WASH 1 NCB No 229,508.20 86,065.57 Post 18 OPERATIONAL COSTS PCNI NERSP PMC CELL PMC Software, Intranet and C3/Operati Tools onal Costs 3 RfQ No 159,240.16 159,240.16 Post Fri-27-Apr-18 Video Conferencing C3/Operati Thu-25-Jan- Equipment onal Costs 1 RfQ No 131,147.54 131,147.54 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 50 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C3/Operati Tue-27-Mar- Office Vehicles onal Costs 1 RfQ No 344,265.00 344,265.00 Post 18 BORNO STATE Procurement of 12 laptop computers, 12 laserjet printers, 4 photocopiers, 3 desktops, 15 desktops for work stations, 2 deskjet printers, HP Scanjet C3/Operati scanner onal Costs 1 RfQ No 159,240.16 159,240.16 Post Fri-27-Apr-18 Procurement of video conference equipment and C3/Operati internet connectivity onal Costs 1 RfQ No 65,574.00 65,574.00 Post Fri-27-Apr-18 Procurement of Office C3/Operati Tue-27-Mar- Furniture onal Costs 1 NCB No 32,786.89 32,786.89 Post 18 Procurement of 1 Video C3/Operati Wed-28-Mar- Camera, 2 DLSR Cameras, onal Costs 1 RfQ No 7,000.00 7,000.00 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 51 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of 100KVA sound proof Generator, C3/Operati Sun-20-May- 10KVA Inverter System onal Costs 1 RfQ No 42,623.00 42,623.00 Post 18 Procurement of Office Vehicles - 2 Toyota Prado Jeep, 3 Toyota Hilux, 1 C3/Operati Wed-14-Mar- Toyota Corolla onal Costs 1 NCB No 448,525.00 448,525.00 Post 18 ADAMAWA STATE Procurement of computers, printers and other C3/Operati Wed-28-Mar- accessories onal Costs 1 RfQ No 24,131.15 24,131.15 Post 18 Procurement of video conference equipment and C3/Operati Wed-28-Mar- internet connectivity onal Costs 1 RfQ No 65,574.00 65,574.00 Post 18 Procurement of Office C3/Operati Tue-27-Mar- Furniture onal Costs 1 NCB No 32,786.89 32,786.89 Post 18 Procurement of 1 Video C3/Operati Wed-28-Mar- Camera, 2 DLSR Cameras, onal Costs 1 RfQ No 20,327.87 20,327.87 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 52 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of 100KVA sound proof Generator, C3/Operati Mon-26-Mar- 10KVA Inverter System onal Costs 1 RfQ No 42,623.00 42,623.00 Post 18 Procurement of Office Vehicles - 2 Toyota Prado Jeep, 3 Toyota Hilux, 1 C3/Operati Tue-27-Mar- Toyota Corolla onal Costs 1 RfQ No 518,033.00 518,033.00 Post 18 YOBE STATE Procurement of computers, printers and other C3/Operati Wed-28-Mar- accessories onal Costs 1 RfQ No 24,131.15 24,131.15 Post 18 Procurement of video conference equipment and C3/Operati Wed-28-Mar- internet connectivity onal Costs 1 RfQ No 65,574.00 65,574.00 Post 18 Procurement of Office C3/Operati Tue-27-Mar- Furniture onal Costs 1 NCB No 32,786.89 32,786.89 Post 18 Procurement of 1 Video C3/Operati Wed-28-Mar- Camera, 2 DLSR Cameras, onal Costs 1 RfQ No 20,327.87 20,327.87 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 53 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of 100KVA sound proof Generator, C3/Operati Mon-26-Mar- 10KVA Inverter System onal Costs 1 RfQ No 42,623.00 42,623.00 Post 18 Procurement of Office C3/Operati Tue-27-Mar- Vehicles onal Costs 1 RfQ No 468,852.46 468,852.46 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 54 PROCUREMENT Nigeria : Multi-Sectoral Crisis Recovery Project for North Eastern Nigeria PLAN General Information Country: Nigeria 2018-12-04 Bank’s Approval Date of the Original Procurement Plan: 2022-06-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157891 GPN Date: Project Name: Multi-Sectoral Crisis Recovery Project for North Eastern Nigeria Loan / Credit No: IDA / 59880, IDA / 66490 YOBE MCRP Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual YB/MCRP/CW004/2019 / Reh Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-11-2 2020-09 abilitation and Upgrading of IDA / 59880 and Service Delivery Restora Post Limited 171,609.40 Completed 2019-03-30 2019-08-09 2019-05-25 2019-08-30 tions nvelope 1 -14 1 No. Trauma Centre Damatu tion & Improvement ru NG-YOBE MCRP-96306-CW-R FQ / Rehabilitation of 21 No. Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 2019-10-1 solar power Boreholes with r IDA / 59880 and Service Delivery Restora Post Limited 0.00 2019-02-21 2019-12-03 2019-04-18 tions nvelope mentation 5 eticulation at Bursari, Damat tion & Improvement uru, Fune, Giedam, Gulani, P otiskum and Tarmuwa YB/MCRP/CW005/2019 / Reh Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-09-1 2020-09 abilitation of Ministry of Agric IDA / 59880 and Service Delivery Restora Post Limited 160,060.55 Completed 2019-01-24 2019-08-09 2019-03-21 2019-08-30 tions nvelope 7 -14 ulture Office Complex tion & Improvement NG-YOBE MCRP-82243-CW-R FQ / Rehabilitation of Cultural Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-07-2 2020-03 Buildings (District Head's Pal IDA / 59880 and Service Delivery Restora Post Limited 176,602.87 Completed 2018-11-26 2019-08-09 2019-01-21 2019-08-30 tions nvelope 0 -30 ace) in Gujba Buni Yadi and T tion & Improvement armuwa Babbangida LGA YB/MCRP/CW001/2019 / Ren Infrastructure Rehabilitation ovation of GSS (Including Pe Request for Quota Single Stage - One E 2019-12-0 2021-02 IDA / 59880 and Service Delivery Restora Post Limited 320,869.71 Completed 2019-04-15 2020-05-12 2019-06-10 2020-06-11 rimeter fence), Bara and Bula tions nvelope 7 -24 tion & Improvement rafa at Gulani LGA YB/MCRP/CW002/2019 / Ren Infrastructure Rehabilitation ovation of GSS (Including per Request for Quota Single Stage - One E 2019-11-0 2020-09 IDA / 59880 and Service Delivery Restora Post Open - National 223,254.63 Completed 2019-03-16 2019-05-11 2019-08-30 imeter fence) Jajere, Fune LG tions nvelope 7 -14 tion & Improvement A and GGSS Buni Gari in Gujb a LGA YB/MCRP/CW008/2019 / Drill ing of 5 No. New Solar (Hybri Infrastructure Rehabilitation d) Powered Boreholes (where Request for Quota Single Stage - One E 2019-10-0 2021-10 IDA / 59880 and Service Delivery Restora Post Limited 150,878.51 Completed 2019-02-12 2020-01-24 2019-04-09 2020-02-21 it is completely destroyed) at tions nvelope 6 -18 tion & Improvement Fune, Fika, Yusufari, Gujba, G ulani, Damaturu, Nguru, Bad e and Nangere LGAs. NG-YOBE MCRP-82202-CW-R Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-07-2 FQ / Rehabilitation of Zonal S IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2018-12-01 2019-01-26 tions nvelope 5 tatistical Office tion & Improvement NG-YOBE MCRP-109279-CW- RFQ / Rehabilitation and Upg Infrastructure Rehabilitation rading of 18 nos. PHC Centr Single Stage - Two E 2020-02-0 IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 0.00 Canceled 2019-03-10 2019-03-15 2019-04-26 2019-07-09 2019-08-13 es to Comprehensive PHC ce nvelope 9 tion & Improvement nter (Must include Solar elec trification, solar powered bor eholes) - Phase I NG-YOBE MCRP-109281-CW- Infrastructure Rehabilitation RFQ / Provision of community Request for Quota Single Stage - One E Under Imple 2019-06-1 IDA / 59880 and Service Delivery Restora Post Limited 0.00 2018-10-21 2018-12-16 town center for peace buildin tions nvelope mentation 4 tion & Improvement g and social cohesion NG-YOBE MCRP-109314-CW- RFQ / Rehabilitation of 11 No. Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 2019-10-1 Solar Powered Boreholes wit IDA / 59880 and Service Delivery Restora Post Limited 0.00 2019-02-21 2019-04-18 tions nvelope mentation 5 h live stock drinking trough a tion & Improvement t Bursari, Damaturu, Fune, G eidam, Gulani and Potiskum NG-YOBE MCRP-82257-CW-R Infrastructure Rehabilitation FQ / Rehabilitation of Solar P Request for Quota Single Stage - One E 2019-07-2 IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2018-11-28 2019-01-23 owered Boreholes in Gulani, tions nvelope 2 tion & Improvement Gujba and Damaturu YB/MCRP/CW003/2019 / Reh abilitation and Upgrading of Infrastructure Rehabilitation 18 nos. PHC Centres to Comp Single Stage - One E 2020-01-0 IDA / 59880 and Service Delivery Restora Prior Request for Bids Open - National 0.00 Canceled 2019-03-15 2019-03-20 2019-05-01 2019-05-31 2019-07-05 rehensive PHC center (Must i nvelope 1 tion & Improvement nclude Solar electrification, s olar powered boreholes) - Ph ase I NG-YOBE MCRP-80657-CW-R Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-06-2 FQ / Rehabilitation of Govern IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2018-11-05 2018-12-31 tions nvelope 9 ment Buildings; Agency for tion & Improvement Mass Literacy YB/MCRP/CW007/2019 / Reh abilitation of solar power Bor Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-10-1 eholes with reticulation at Bu IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2019-02-21 2019-04-18 tions nvelope 5 rsari, Damaturu, Fune, Gieda tion & Improvement m, Gulani, Potiskum and Tar muwa NG-YOBE MCRP-82250-CW-R Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-07-0 FQ / Rehabilitation of Govern IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2018-11-13 2019-01-08 tions nvelope 7 ment Buildings; Town Engin tion & Improvement eers Office NG-YOBE MCRP-82212-CW-R Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-04-1 FQ / Rehabilitation of Ministry IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2018-08-25 2018-10-20 tions nvelope 8 of Agriculture Office Complex tion & Improvement NG-YOBE MCRP-82190-CW-R Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-07-2 FQ / Renovation of 1No. Gen IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2018-12-02 2019-01-27 tions nvelope 6 eral Hospital in Buni Yadi tion & Improvement Page 1 NG-YOBE MCRP-82188-CW-R Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-07-0 FQ / Reconstruction of Vanda IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2018-11-07 2019-01-02 tions nvelope 1 lized 3 Nos Immunization Offi tion & Improvement ces NG-YOBE MCRP-82249-CW-R Infrastructure Rehabilitation FQ / Rehabilitation of Develo Request for Quota Single Stage - One E 2019-07-0 IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2018-11-13 2019-01-08 pment Offices in Gujba , Gula tions nvelope 7 tion & Improvement ni, Yunusari & Geidam NG-YOBE MCRP-81311-CW-R Infrastructure Rehabilitation FQ / Rehabilitation of Local G Request for Quota Single Stage - One E 2019-07-2 IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2018-12-03 2019-01-28 overnment Office Secretariat tions nvelope 7 tion & Improvement in Gujba and Potiskum NG-YOBE MCRP-80668-CW-R Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-08-0 FQ / Renovation of Dokshi Pri IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2018-12-12 2019-02-06 tions nvelope 5 mary school, Gulani tion & Improvement NG-YOBE MCRP-135036-CW- RFB / Rehabilitation and Upgr Infrastructure Rehabilitation ading of 18 nos. PHC Centre Single Stage - One E 2020-09-1 IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 0.00 Canceled 2019-11-29 2019-12-15 2019-12-04 2020-01-15 2020-02-14 2020-03-20 s to Comprehensive PHC cent nvelope 6 tion & Improvement er (Must include Solar electri fication, solar powered boreh oles) - Phase I NG-YOBE MCRP-146315-CW- Infrastructure Rehabilitation Single Stage - One E 16,585,698. 2021-03-1 RFB / Rehabilitation of 40km IDA / 59880 and Service Delivery Restora Prior Request for Bids Open - National Signed 2020-01-06 2020-05-01 2020-01-11 2020-05-06 2020-02-22 2020-06-09 2020-03-23 2020-10-05 2020-04-27 2020-11-13 nvelope 03 7 Gujba - Ngalda Road tion & Improvement NG-YOBE MCRP-154019-CW- RFB / Rehabilitation and Upgr Infrastructure Rehabilitation ading of 11 nos. PHC Centre Single Stage - One E Under Imple 2020-11-0 IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 0.00 2020-01-20 2020-01-17 2020-01-25 2020-01-30 2020-03-07 2020-02-19 2020-04-06 2020-03-30 2020-05-11 s to Comprehensive PHC cent nvelope mentation 7 tion & Improvement er (Must include Solar electri fication, solar powered boreh oles) - Phase I YBMCRP-2020-CW-003 / Reh Infrastructure Rehabilitation abilitation and Upgrading of Single Stage - One E Under Imple 2021-03-2 IDA / 59880 and Service Delivery Restora Post Request for Bids Limited 0.00 2020-06-07 2020-10-30 2020-06-12 2020-11-13 2020-07-24 2020-08-23 2020-09-27 Primary Health Centers to C nvelope mentation 6 tion & Improvement omprehensive Primary Healt h Care Center YBMCRP-2020-CW-005 / Reh Infrastructure Rehabilitation abiltation and Upgrading of P Single Stage - One E Under Imple 2021-03-2 IDA / 59880 and Service Delivery Restora Post Request for Bids Limited 0.00 2020-06-07 2020-12-24 2020-06-12 2020-07-24 2020-08-23 2020-09-27 HC Bara to General Hospital ( nvelope mentation 6 tion & Improvement due to influx of peoples) YBMCRP-2020-CW-001 / Drill Infrastructure Rehabilitation ing of New Solar (Hybrid) Po Request for Quota Single Stage - One E 2021-01-3 IDA / 59880 and Service Delivery Restora Post Limited 238,053.30 Signed 2020-06-08 2020-12-23 2020-08-03 2021-01-15 wered Boreholes (where it is tions nvelope 0 tion & Improvement completely destroyed) YBMCRP-2020-CW-002 / Reh Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-01-2 abilitation of Solar Powered B IDA / 59880 and Service Delivery Restora Post Limited 184,507.92 Signed 2020-06-06 2020-12-23 2020-08-01 2021-01-15 tions nvelope 8 oreholes with live stock drink tion & Improvement ing trough YBMCRP-2020-CW-006 / Con Infrastructure Rehabilitation struction and furnishing of 2 Request for Quota Single Stage - One E 2021-02-2 2021-03 IDA / 59880 and Service Delivery Restora Post Limited 90,093.04 Completed 2020-07-05 2020-12-31 2020-08-30 2021-02-01 Unit of semi-detached staff q tions nvelope 6 -12 tion & Improvement uarters - Immunization office YBMCRP-2020-CW-007 / Rec Infrastructure Rehabilitation onstruction of vandalised St Request for Quota Single Stage - One E 2021-02-2 IDA / 59880 and Service Delivery Restora Post Limited 467,149.10 Signed 2020-07-05 2020-12-31 2020-08-30 2021-02-01 udent Hostel at Yobe State C tions nvelope 6 tion & Improvement ollege of Nursing & Midwifery Damaturu. YBMCRP-2020-CW-008 / Rec Infrastructure Rehabilitation onstruction of vandalised St Request for Quota Single Stage - One E 2021-01-3 IDA / 59880 and Service Delivery Restora Post Limited 467,149.10 Signed 2020-06-08 2020-12-31 2020-08-03 2021-02-01 udent Hostel at Yobe State C tions nvelope 0 tion & Improvement ollege of Science and Health Technology, Nguru YBMCRP-2020-CW-009 / Ren ovation of vandalised central medical store to support gov Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-02-1 ernment efforst for sustainab IDA / 59880 and Service Delivery Restora Post Limited 334,908.57 Signed 2020-06-19 2020-12-31 2020-08-14 2021-02-01 tions nvelope 0 le and stable supple chain m tion & Improvement anagement of drugs and con sumables in response to reco very. YBMCRP-2020-CW-010 / Ren Infrastructure Rehabilitation Request for Quota Single Stage - One E Pending Imp 2021-01-2 ovation of GSS Goniri, Gujba IDA / 59880 and Service Delivery Restora Post Limited 0.00 2020-06-04 2020-07-30 tions nvelope lementation 6 LGA(Including Perimeter fenc tion & Improvement e) YBMCRP-2020-CW-011 / Reh Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-01-2 abilitation of Cultural Buildin IDA / 59880 and Service Delivery Restora Post Limited 63,051.80 Signed 2020-06-07 2021-07-02 2020-08-02 2021-08-03 tions nvelope 9 gs (Emir's Palace) - Buni Yadi tion & Improvement Infrastructure Rehabilitation YBMCRP-2020-CW-012 / Rec Request for Quota Single Stage - One E 2021-01-3 2021-11 IDA / 59880 and Service Delivery Restora Post Limited 904,008.44 Completed 2020-06-08 2020-12-31 2020-08-03 2021-02-01 onstruction of rural markets tions nvelope 0 -29 tion & Improvement YBMCRP-2020-CW-013 / Reh Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-02-0 2021-11 abilitation of VIP toilets and IDA / 59880 and Service Delivery Restora Post Limited 273,605.43 Completed 2020-06-15 2020-12-31 2020-08-10 2021-02-01 tions nvelope 6 -08 dump sites at rural market tion & Improvement YBMCRP-2020-CW-014 / Pro Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-02-2 vision of community town hal IDA / 59880 and Service Delivery Restora Post Limited 549,926.47 Signed 2020-07-05 2021-07-02 2020-08-30 2021-08-03 tions nvelope 6 ls for peace building and soci tion & Improvement al cohesion YBMCRP-2020B-CW-001 / Up grading of existing Laboratori Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-01-3 2021-03 es at State Teaching Hospital IDA / 59880 and Service Delivery Restora Post Limited 53,528.37 Completed 2020-06-08 2020-08-28 2020-08-03 2020-09-24 tions nvelope 0 -05 Damaturu to accommodate t tion & Improvement he new testing facilities YBMCRP-2020B-CW-002 / Re Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-04-0 2022-03 habilitation of Doctors quarte IDA / 59880 and Service Delivery Restora Post Limited 403,673.97 Completed 2020-08-08 2020-10-06 2020-10-03 2022-03-03 tions nvelope 1 -23 rs at YSUTH Damaturu tion & Improvement Page 2 YBMCRP-2020B-CW-004 / Ra habilitation and equipment of Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-01-3 molecular lab at Federal Med IDA / 59880 and Service Delivery Restora Post Limited 94,597.95 Signed 2020-06-08 2020-08-28 2020-08-03 2020-09-24 tions nvelope 0 ical Center Nguru to serve as tion & Improvement additional testing center YBMCRP-2020B-CW-005 / Re Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 2021-04-0 habilitation of existing Hand IDA / 59880 and Service Delivery Restora Post Limited 0.00 2020-08-08 2020-10-03 tions nvelope mentation 1 Pump across 17 LGAs 170 n tion & Improvement o. YBMCRP-2020B-CW-006 / Re habilitation/reconstructional Infrastructure Rehabilitation of additional classes, hostels Request for Quota Single Stage - One E 2021-04-0 IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2020-08-08 2020-10-03 laborotories, Exam and multi tions nvelope 1 tion & Improvement purspose hall and peremeter fencing at Government Highe r College Nguru YBMCRP-2020B-CW-007 / Ra Infrastructure Rehabilitation habilitation of 3 No. skill aqui Request for Quota Single Stage - One E 1,117,981.2 2021-03-1 IDA / 59880 and Service Delivery Restora Post Limited Signed 2020-08-08 2021-07-02 2020-09-18 2021-08-03 sation centers at Damaturu, tions nvelope 0 7 tion & Improvement Potiskum and Bade YBMCRP-2020B-CW-008 / Re Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-04-1 habilitation of 1.5km Buni Ga IDA / 59880 and Service Delivery Restora Post Limited 969,360.04 Signed 2020-08-20 2020-11-27 2020-10-15 2021-01-06 tions nvelope 3 ri Township Raod in Gujba LG tion & Improvement A YBMCRP-2020B-CW-009 / Re Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-04-1 habilitation of 1.5km Babban IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2020-08-20 2020-10-15 tions nvelope 3 gida Twonship road and drai tion & Improvement nage GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-YOBE MCRP-81294-GO-R Technical Assistance and Pro Request for Quota Single Stage - One E IDA / 59880 Post Limited 40,021.78 Completed 2018-12-09 2019-02-03 2018-11-07 2019-08-02 2018-11-27 FQ / Renovation of State PCU ject Management Support tions nvelope Office NG-YOBE MCRP-82263-GO-R Infrastructure Rehabilitation Request for Quota Single Stage - One E FQ / Procurement of State PC IDA / 59880 and Service Delivery Restora Post Limited 96,324.00 Completed 2018-12-10 2019-02-04 2018-12-05 2019-08-03 2018-12-17 tions nvelope Us Office Furniture tion & Improvement NG-YOBE MCRP-82183-GO-R Technical Assistance and Pro Request for Quota Single Stage - One E FQ / Procurement of 1 Video IDA / 59880 Post Limited 14,213.58 Completed 2018-11-14 2019-02-01 2019-01-09 2019-03-01 2019-07-08 2019-03-22 ject Management Support tions nvelope Camera, 2 DLSR Cameras, NG-YOBE MCRP-80237-GO-R Technical Assistance and Pro Request for Quota Single Stage - One E FQ / Procurement of 60KVA s IDA / 59880 Post Limited 34,569.00 Completed 2018-12-08 2018-11-14 2019-02-02 2018-12-05 2019-08-01 2018-12-15 ject Management Support tions nvelope ound proof Generator, 5KVA I nverter System NG-YOBE MCRP-82186-GO-R Technical Assistance and Pro Request for Quota Single Stage - One E IDA / 59880 Post Limited 0.00 Canceled 2018-11-07 2019-01-02 2019-07-01 FQ / Insurance of Office Proje ject Management Support tions nvelope ct Vehicles NG-YOBE MCRP-81785-GO-R Technical Assistance and Pro Request for Quota Single Stage - One E Under Imple FQ / M&E working tools Inclu IDA / 59880 Post Limited 0.00 2018-11-24 2019-01-19 2019-07-18 ject Management Support tions nvelope mentation de Soft ware, Data Housing, Hard copy tools NG-YOBE MCRP-81289-GO-R FQ / Procurement of Office V Technical Assistance and Pro Request for Quota Single Stage - One E IDA / 59880 Post Limited 514,533.00 Completed 2018-11-23 2019-01-18 2018-12-11 2019-07-17 2018-12-12 ehicles 1 Prado, 4Hilux, 1Cor ject Management Support tions nvelope olla and one 18Seater Bus NG-YOBE MCRP-81293-GO-R FQ / Procurement of compute Technical Assistance and Pro Request for Quota Single Stage - One E IDA / 59880 Post Limited 20,037.60 Completed 2018-12-09 2019-01-04 2019-02-03 2019-02-15 2019-08-02 2019-03-01 rs, printers and other access ject Management Support tions nvelope ories of state PCUs including fridges and television YB/MCRP/GO001/2019 / Non Strengthening Peace Buildin Request for Quota Single Stage - One E IDA / 59880 Post Open - National 429,343.20 Completed 2019-02-20 2019-04-17 2019-04-10 2019-10-14 2019-04-20 Food Items (NFIs) Kits g, Stability and Social Cohesi tions nvelope on YB/MCRP/GO005/2019 / Proc Infrastructure Rehabilitation ure and distribute essential d Single Stage - Two E IDA / 59880 and Service Delivery Restora Prior Request for Bids Open - National 0.00 Canceled 2019-03-18 2019-03-23 2019-05-04 2019-07-17 2019-08-21 2020-02-17 rugs and consumables to the nvelope tion & Improvement 18 upgraded PHC center YB/MCRP/GO008/2019 / Prov Technical Assistance and Pro Request for Quota Single Stage - One E ision of Office Equipment (lap IDA / 59880 Post Limited 54,148.70 Completed 2019-02-11 2019-02-05 2019-04-08 2019-02-27 2019-10-05 2019-03-07 ject Management Support tions nvelope tops, printers, accessories, fri dge,TV, etc) NG-YOBE MCRP-100448-GO- Strengthening Peace Buildin Single Stage - Two E IDA / 59880 Post Request for Bids Open - National 0.00 Canceled 2018-10-16 2021-04-05 2018-10-21 2018-12-02 2019-02-14 2019-03-21 2019-09-17 RFQ / Non-agricultural Livelih g, Stability and Social Cohesi nvelope ood kits on NG-YOBE MCRP-79974-GO-R FQ / Procurement of video co Technical Assistance and Pro Request for Quota Single Stage - One E IDA / 59880 Post Limited 0.00 Canceled 2018-11-10 2019-01-05 2019-07-04 nference equipment and inte ject Management Support tions nvelope rnet connectivity & subscripti on YB/MCRP/GO007/2019 / Equi Infrastructure Rehabilitation Request for Quota Single Stage - One E pping of Upgraded Trauma C IDA / 59880 and Service Delivery Restora Post Limited 114,898.09 Completed 2019-11-26 2020-05-12 2020-01-21 2020-07-09 2020-07-19 2021-01-20 tions nvelope entre tion & Improvement YB/MCRP/GO002/2019 / Agri Strengthening Peace Buildin Single Stage - One E cultural kits with Improved s IDA / 59880 g, Stability and Social Cohesi Post Request for Bids Open - National 674,506.43 Completed 2019-02-22 2019-04-05 2019-02-27 2019-06-19 2019-04-10 2019-05-06 2019-05-10 2019-05-04 2019-06-14 2019-05-06 2019-12-11 2019-05-17 nvelope eeds, oil, small tools on NG-YOBE MCRP-107931-GO- DIR / Procurement of video c Technical Assistance and Pro IDA / 59880 Post Direct Selection Direct 98,573.35 Completed 2019-03-26 2019-02-11 2019-03-31 2019-02-14 2019-05-05 2019-02-25 2019-11-01 2019-03-21 onference equipment and int ject Management Support ernet connectivity & subscrip tion NG-YOBE MCRP-96308-GO-R Infrastructure Rehabilitation Request for Quota Single Stage - One E FQ / Equipping of Upgraded T IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2019-02-06 2019-04-03 2019-09-30 tions nvelope rauma Centre tion & Improvement NG-YOBE MCRP-82231-GO-R Strengthening Peace Buildin Single Stage - One E FB / Supply of Skills Acquisiti IDA / 59880 g, Stability and Social Cohesi Post Request for Bids Open - National 0.00 Canceled 2018-11-19 2018-11-24 2019-01-05 2019-02-04 2019-03-11 2019-09-07 nvelope on Start up Kits on Page 3 NG-YOBE MCRP-121384-GO- Strengthening Peace Buildin Request for Quota Single Stage - One E RFQ / Small Animals (improv IDA / 59880 g, Stability and Social Cohesi Post Open - National 581,912.55 Completed 2019-07-20 2019-09-14 2019-08-06 2020-03-12 2019-08-30 tions nvelope ed animal inputs, sourcing im on proved breeds) NG-YOBE MCRP-121385-GO- Infrastructure Rehabilitation RFQ / Medical Equipment and Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2019-09-21 2019-11-16 2020-05-14 facility furnitures to 18 focal tions nvelope tion & Improvement ward primary health care cen tres YB/MCRP/GO006/2019 / Medi Strengthening Peace Buildin cal Equipment and facility Fu Single Stage - One E IDA / 59880 g, Stability and Social Cohesi Post Request for Bids Open - National 0.00 Canceled 2019-03-22 2019-03-27 2019-05-08 2019-06-07 2019-07-12 2020-01-08 rniture to 18 focal ward prim nvelope on ary health care centers YB/MCRP/GO003/2019 / Sma ll Animals (Imporved Animal I Strengthening Peace Buildin Single Stage - One E nputs , (Registration of Benef IDA / 59880 g, Stability and Social Cohesi Post Request for Bids Open - National 0.00 Canceled 2019-02-28 2019-03-05 2019-04-16 2019-05-16 2019-06-20 2019-12-17 nvelope iciaries/ Sourcing Improved B on reeds/Provision of Soft Skills f or maximum yield) NG-YOBE MCRP-164770-GO- Strengthening Peace Buildin Request for Quota Single Stage - One E RFQ / Procurement of Machin IDA / 59880 g, Stability and Social Cohesi Post Limited 465,989.56 Completed 2020-03-21 2021-04-05 2020-05-16 2021-04-23 2020-11-12 2021-05-31 tions nvelope es and accessories for softski on lls supports NG-YOBE MCRP-164781-GO- Strengthening Peace Buildin RFQ / Procurement of softskil Request for Quota Single Stage - One E IDA / 59880 g, Stability and Social Cohesi Post Limited 372,279.02 Completed 2020-03-21 2020-04-15 2020-05-16 2020-05-11 2020-11-12 2021-01-01 l local commodities to suppor tions nvelope on t women income generation activities. YBMCRP-2020-GO-002 / Purc Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple hase of Instructional Material IDA / 59880 and Service Delivery Restora Post Limited 0.00 2020-06-03 2021-03-04 2020-07-29 2021-01-25 tions nvelope mentation s: Students Text Books and T tion & Improvement eachers Guides YBMCRP-2020-GO-003 / Purc Infrastructure Rehabilitation hase of Instructional Material Request for Quota Single Stage - One E Under Imple IDA / 59880 and Service Delivery Restora Post Limited 0.00 2020-06-03 2021-03-04 2020-07-29 2021-01-25 s:Laboratory Equipments; Ph tions nvelope mentation tion & Improvement ysics. Chemistry & Biology YBMCRP-2020-GO-004 / Purc Infrastructure Rehabilitation Request for Quota Single Stage - One E hase of Teachers Tables and IDA / 59880 and Service Delivery Restora Post Limited 97,752.56 Completed 2020-06-01 2021-03-04 2020-07-27 2021-03-29 2021-01-23 2021-04-12 tions nvelope Chairs and Student Double S tion & Improvement eater Desk YBMCRP-2020-GO-005 / Purc Infrastructure Rehabilitation Request for Quota Single Stage - One E hase of Student Double Deck IDA / 59880 and Service Delivery Restora Post Limited 96,879.08 Completed 2020-06-02 2021-03-04 2020-07-28 2021-03-29 2021-01-24 2021-04-02 tions nvelope er Beds and Mattrases tion & Improvement YBMCRP-2020-GO-006 / Offic Technical Assistance and Pro Request for Quota Single Stage - One E IDA / 59880 Post Limited 6,073.66 Completed 2020-06-07 2020-05-13 2020-06-29 2020-05-29 2020-07-29 2020-06-23 e Consumables & Stationery ject Management Support tions nvelope (1 Year) YBMCRP-2020-CW-004 / Proc Infrastructure Rehabilitation ure and distribute essential d Single Stage - One E Under Imple IDA / 59880 and Service Delivery Restora Prior Request for Bids Limited 0.00 2020-07-31 2020-08-05 2020-09-16 2020-10-16 2020-11-20 2021-05-19 rugs and consumables to the nvelope mentation tion & Improvement Rehabilitate PHC center Seco ndary facility YBMCRP-2020-GO-001 / Proc Infrastructure Rehabilitation Request for Quota Single Stage - One E urement of Medical Equipme IDA / 59880 and Service Delivery Restora Post Limited 662,603.55 Completed 2020-08-29 2020-04-06 2020-10-24 2020-04-30 2021-04-22 2020-09-28 tions nvelope nt and facility Furniture to Re tion & Improvement habiliated PHCs . YBMCRP-2020B-GO-003 / Pro Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple curement of Molecular Labor IDA / 59880 and Service Delivery Restora Post Limited 0.00 2020-06-08 2020-08-03 2021-01-30 tions nvelope mentation atory Equipment for testing o tion & Improvement f COVID-19 YBMCRP-2020B-GO-004 / Pro Infrastructure Rehabilitation curement of Infection Preven Request for Quota Single Stage - One E Under Imple IDA / 59880 and Service Delivery Restora Post Limited 46,983.54 2020-06-08 2020-07-09 2020-08-03 2021-01-30 tion and Biosafety equipment tions nvelope mentation tion & Improvement for the new testing Laboarat ory YBMCRP-2020B-GO-005 / Pro Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple curement of Bio safety cabin IDA / 59880 and Service Delivery Restora Post Limited 46,295.30 2020-06-08 2020-07-10 2020-08-03 2021-01-30 tions nvelope mentation et Level 3 and 2 tion & Improvement YBMCRP-2020B-GO-006 / Pro Infrastructure Rehabilitation curement of 9000 pcs of N95 Request for Quota Single Stage - One E Under Imple IDA / 59880 and Service Delivery Restora Post Limited 0.00 2020-06-08 2020-07-10 2020-08-03 2021-01-30 face masks and 1000 packet tions nvelope mentation tion & Improvement s of surgical face masks YBMCRP-2020B-GO-007 / Pro Infrastructure Rehabilitation curement of 1500 pcs of Lev Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 238,450.38 Completed 2020-06-08 2020-07-10 2020-08-03 2020-08-30 2021-01-30 2021-04-07 el Personal Protective Equip tions nvelope tion & Improvement ment (PPEs) and googles, fac e shields YBMCRP-2020B-GO-010 / fab Infrastructure Rehabilitation rication and distribution of cu Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 126,634.44 Completed 2020-08-08 2020-07-10 2020-10-03 2020-07-30 2021-04-01 2020-10-21 stomised hand washing equi tions nvelope tion & Improvement pment to all 17 LGAs (100/LG A) YBMCRP-2020B-GO-008 / Pro curement of Medical Waste I Infrastructure Rehabilitation Request for Quota Single Stage - One E ncinerators for isolation cent IDA / 59880 and Service Delivery Restora Post Limited 185,368.76 Completed 2020-06-08 2020-07-09 2020-08-03 2020-08-03 2020-08-12 2021-03-30 tions nvelope ers at the Specialist Hospital tion & Improvement and Teaching Hospital in Da maturu YBMCRP-2020B-GO-009 / Eq Infrastructure Rehabilitation Request for Quota Single Stage - One E upping of 3 No. skill aquisatio IDA / 59880 and Service Delivery Restora Post Limited 370,036.37 Completed 2020-06-08 2022-03-16 2020-08-03 2022-04-07 2021-01-30 2022-04-26 tions nvelope n centers at Damaturu, Potis tion & Improvement kum, Bade LGAs YBMCRP-2020B-GO-002 / Su pport for Animal Tractions - ( Strengthening Peace Buildin Request for Quota Single Stage - One E Pending Impl Provision of 890 No. of Anima IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 2020-06-30 2020-08-25 2020-10-24 tions nvelope ementation l Tractions - 1 Cart, 1 Ox Plou on gh and pair of Oxen per hous ehold) YBMCRP-2020B-GO-001 / Su pport for women-led small bu siness development for the i Strengthening Peace Buildin Request for Quota Single Stage - One E Pending Impl dentified women headed hou IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 2020-06-30 2020-08-25 2020-11-23 tions nvelope ementation seholds (Provision of Local Sp on aghetti Machine for 1000 ben eficiaries and Home Grinding Machine for 1000 beneficiari es) Page 4 YB/MCRP/GO005/2019/A / Pr Infrastructure Rehabilitation Request for Quota Single Stage - One E ocurement of medical equip IDA / 59880 and Service Delivery Restora Post Limited 1,052,050.71 Completed 2020-07-07 2020-07-06 2020-09-01 2020-07-27 2020-11-30 2020-12-08 tions nvelope ment to PHCs tion & Improvement YB/MCRP/GO005/2019/B / Pr Infrastructure Rehabilitation Request for Quota Single Stage - One E ocurement of Essential Drugs IDA / 59880 and Service Delivery Restora Post Limited 727,000.69 Completed 2020-07-07 2020-07-06 2020-09-01 2020-07-27 2020-11-30 2021-03-05 tions nvelope to PHCs tion & Improvement YB/MCRP/GO005/2019/C / Pr Infrastructure Rehabilitation Request for Quota Single Stage - One E ocurement of Medical Consu IDA / 59880 and Service Delivery Restora Post Limited 230,471.17 Completed 2020-07-07 2020-07-06 2020-09-01 2020-07-27 2020-11-30 2021-03-05 tions nvelope mables to PHCs tion & Improvement YBMCRP/AF/GO/2021/002 / P Strengthening Peace Buildin rovision of Starter Packs for b Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2022-02-07 2022-04-04 2022-10-01 eneficiaries of the entrepren tions nvelope ementation on eurship for unskilled youth pr ogram YBMCRP/AF/GO/2021/003 / P Strengthening Peace Buildin Request for Quota Single Stage - One E Pending Impl IDA / 66490 Post Limited 0.00 2022-02-07 2022-04-04 2022-10-01 romotion of Economic Trees i g, Stability and Social Cohesi tions nvelope ementation n 10LGAs on YBMCRP/AF/GO/2021/004 / P Infrastructure Rehabilitation rovision, Training and distrib Request for Quota Single Stage - One E Pending Impl IDA / 66490 and Service Delivery Restora Post Limited 0.00 2022-02-07 2022-04-04 2022-10-01 ution of small farming equip tions nvelope ementation tion & Improvement ment for crop production to 1 6 farmer Groups Trained YBMCRP/AF/GO/2021/005 / V Infrastructure Rehabilitation alue Chain Expansion throug Request for Quota Single Stage - One E Pending Impl IDA / 66490 and Service Delivery Restora Post Limited 0.00 2022-02-07 2022-04-04 2022-10-01 h Distribution of processing e tions nvelope ementation tion & Improvement quipment for cooperatives YBMCRP/AF/GO/2021/001 / P Strengthening Peace Buildin rovision of improved seedling Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Request for Bids Limited 0.00 2022-06-07 2022-06-12 2022-07-24 2022-08-23 2022-09-27 2023-03-26 for Rice, Maize, Millet, Sorgh nvelope ementation on um, Beans - durig year 1 of the projects NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-YOBE MCRP-82187-CS-Q CBS / Consultancy for Sensiti Strengthening Peace Buildin Quality And Cost- zation, Community Mobilizati IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 Under Review 2018-12-03 2019-02-08 2018-12-24 2019-06-27 2019-02-06 2019-03-06 2019-04-05 2019-05-10 2019-06-14 2020-06-13 Based Selection on and formation of peace gr on oups within 15 Communities NG-YOBE MCRP-79981-CS-C QS / Diagnosis of community- specific reconciliation, peace Strengthening Peace Buildin building and social cohesion Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 Canceled 2018-10-20 2018-11-10 2018-12-24 2019-01-23 2019-02-27 2019-08-26 needs and consequentt deve cation Selection on lopment of Civil Education Pr ograms using Cultural and Re creational activities at Comm unity Level NG-YOBE MCRP-82239-CS-C Strengthening Peace Buildin QS / Radio programs on mine Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 Canceled 2018-11-09 2018-11-30 2019-01-13 2019-02-12 2019-03-19 2019-09-15 awareness, dispute resolutio cation Selection on n in Hausa, Kanuri and Fulful de NG-YOBE MCRP-82222-CS-C QS / Identification and trainin g of Village Levels Mechanics Infrastructure Rehabilitation Consultant Qualifi Under Implement and Local Area Mechanics on IDA / 59880 and Service Delivery Restora Post Open - National 0.00 2018-12-03 2019-03-29 2018-12-24 2019-02-06 2019-03-08 2019-04-12 2019-10-09 cation Selection ation Operation and Maintenance o tion & Improvement f existing Hand Pump and Sol ar powered Borehole for effe ctive utilization and manage ment. NG-YOBE MCRP-82096-CS-C QS / Consultancy for Educati onal campaigns for the preve Strengthening Peace Buildin Consultant Qualifi ntion of mine and unexplode IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 Canceled 2018-11-15 2018-12-06 2019-01-19 2019-02-18 2019-03-25 2019-09-21 cation Selection d ordinance accidents /Mobili on sation and Sensitization Cam paign on Mine Action (Unexpl oded Ordnances) NG-YOBE MCRP-96314-CS-C QS / Yobe State Civic Educati on Program (See The North E Strengthening Peace Buildin Consultant Qualifi ast Civic Education Program IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 Canceled 2019-03-01 2019-03-22 2019-05-05 2019-06-04 2019-07-09 2020-01-05 cation Selection me (NECEP) Pg 287 TBP - Dia on gnosis of community-specific reconciliation, peacebuilding and social cohesion needs NG-YOBE MCRP-96312-CS-C QS / Mapping and profiling of local government structures Strengthening Peace Buildin and communities in places of Consultant Qualifi Under Implement IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 2019-05-10 2020-01-24 2019-05-31 2019-07-14 2019-08-13 2019-09-17 2020-03-15 both displacement and origin cation Selection ation on (Registration, Mapping and P rofiling of all local governme nt structures and existing ca pacities 8 LGA) NG-YOBE MCRP-96410-CS-C QS / Capacity building for 8 l Strengthening Peace Buildin Consultant Qualifi ocal government areas (base IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 Under Review 2019-04-10 2022-04-17 2019-05-01 2019-06-14 2019-07-14 2019-08-18 2020-02-14 cation Selection d on results of mapping and on profiling assessment) NG-YOBE MCRP-100451-CS- CQS / Consultancy support fo Strengthening Peace Buildin Consultant Qualifi Under Implement r Non Food Items, Agricultura IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 2019-02-26 2019-03-19 2019-05-02 2019-06-01 2019-07-06 2020-01-02 cation Selection ation l kits, Small Animals and Non on -agricultural Livelihood kits Page 5 NG-YOBE MCRP-109006-CS- Infrastructure Rehabilitation CQS / Consultancy to support Consultant Qualifi Under Implement IDA / 59880 and Service Delivery Restora Post Open - National 0.00 2019-04-10 2019-03-29 2019-05-01 2022-06-25 2019-06-14 2019-07-14 2019-08-18 2020-02-14 the development of BoQ and cation Selection ation tion & Improvement designs for C2 intervention in Education. NG-YOBE MCRP-109010-CS- Infrastructure Rehabilitation CQS / Consultancy to support Consultant Qualifi Under Implement IDA / 59880 and Service Delivery Restora Post Open - National 0.00 2019-04-17 2019-03-29 2019-05-08 2019-06-21 2019-07-21 2019-08-25 2020-02-21 the development of BoQ and cation Selection ation tion & Improvement designs for C2 intervention in Health Sector. NG-YOBE MCRP-109020-CS- Infrastructure Rehabilitation CQS / Consultancy to support Consultant Qualifi Under Implement IDA / 59880 and Service Delivery Restora Post Open - National 0.00 2019-04-24 2019-03-29 2019-05-15 2019-06-28 2019-07-28 2019-09-01 2020-02-28 the development of BoQ and cation Selection ation tion & Improvement designs for C2 intervention in Public Building. NG-YOBE MCRP-109021-CS- Infrastructure Rehabilitation CQS / Consultancy to support Consultant Qualifi Under Implement IDA / 59880 and Service Delivery Restora Post Open - National 0.00 2019-04-19 2019-03-29 2019-05-10 2019-06-23 2019-07-23 2019-08-27 2020-02-23 the development of BoQ and cation Selection ation tion & Improvement designs for C2 intervention in Water Sector. NG-YOBE MCRP-82213-CS-C QS / Consultancy for Mediatio Strengthening Peace Buildin n and Alternate Dispute Reso Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 Canceled 2018-11-10 2018-12-01 2019-01-14 2019-02-13 2019-03-20 2019-09-16 lution Capacity Building withi cation Selection on n the Community Leadership and Governance Structures NG-YOBE MCRP-80670-CS-C QS / Mapping and profiling of Strengthening Peace Buildin Consultant Qualifi local government structures IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 Canceled 2018-11-05 2018-11-26 2019-01-09 2019-02-08 2019-03-15 2019-09-11 cation Selection and communities in places of on both displacement and origin NG-YOBE MCRP-82097-CS-C Strengthening Peace Buildin Consultant Qualifi QS / Yobe State Civic Educati IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 Canceled 2018-11-23 2018-12-14 2019-01-27 2019-02-26 2019-04-02 2019-09-29 cation Selection on Program on NG-YOBE MCRP-81787-CS-Q CBS / Community Manageme Infrastructure Rehabilitation nt training of entire Commun Quality And Cost- IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2018-11-02 2018-11-23 2019-01-06 2019-02-03 2019-03-05 2019-04-09 2019-05-14 2020-05-13 ities in the 8 proposed LGAs t Based Selection tion & Improvement o effectively manage their W ater, Sanitation and Hygiene Facilities NG-YOBE MCRP-121202-CS- CQS / Safeguards Screening: Deployment of Screening che Infrastructure Rehabilitation Consultant Qualifi Under Implement cklists Preparation of site spe IDA / 59880 and Service Delivery Restora Post Open - National 0.00 2019-07-01 2019-06-07 2019-07-22 2019-09-04 2019-07-19 2019-10-04 2019-11-08 2020-05-06 cation Selection ation cific Safeguards Instruments tion & Improvement Safeguards Compliance Moni toring GRM compliance feed back INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-YOBE MCRP-146402-CS- CDS / Consultancy for screeni Infrastructure Rehabilitation ng and development of safeg IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 42,757.63 Signed 2019-11-22 2019-12-09 2019-12-02 2019-12-20 2020-02-05 2019-12-27 2020-08-03 uard tools for Rehabilitation tion & Improvement of 40km Gujba - Ngalda Road NG-YOBE MCRP-146410-CS- Infrastructure Rehabilitation CDS / Consultancy for Design Under Implement IDA / 59880 and Service Delivery Restora Prior Direct Selection Direct 0.00 2020-01-06 2020-01-15 2020-01-16 2020-01-21 2020-03-21 2021-02-08 and Supervision and Rehabili ation tion & Improvement tation of 40km Gujba - Ngald a Road YBMCRP-2020-CS-001 / Refr esher training and soft skills f Strengthening Peace Buildin or re-orientation on quick to IDA / 59880 g, Stability and Social Cohesi Post Direct Selection Direct 149,439.25 Completed 2020-05-11 2020-12-22 2020-05-21 2021-03-29 2020-07-25 2021-04-26 2021-01-21 2021-06-23 market trading (Women to c on onstitute a minimum of 60% of the Beneficiaries) - Phase I I YBMCRP-2020-CS-002 / Supp Strengthening Peace Buildin IDA / 59880 Post Direct Selection Direct 0.00 Canceled 2020-05-11 2020-05-21 2020-07-25 2021-01-21 ort for peace group activities g, Stability and Social Cohesi on YBMCRP-2020-CS-004 / Provi sion of community based psy Strengthening Peace Buildin cho-social services and corre Under Implement IDA / 59880 g, Stability and Social Cohesi Post Direct Selection Direct 0.00 2020-05-11 2021-06-28 2020-05-21 2020-07-25 2021-01-21 sponding support responding ation on to needs(group support, recr eational, customary and soci alizing activities, referrals). YBMCRP-2020-CS-006 / Cons Infrastructure Rehabilitation ultancy for supervision and d Under Implement IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 0.00 2020-05-12 2020-05-08 2020-05-22 2020-06-02 2020-07-26 2021-01-22 evelopment of Design and Bil ation tion & Improvement l of Quantity for the water wo rks YBMCRP-2020-CS-007 / Cons ultancy for supervision, devel Infrastructure Rehabilitation opment of Design and Bill of IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 146,120.22 Signed 2020-05-12 2020-05-08 2020-05-22 2020-06-02 2020-07-26 2020-07-01 2021-01-22 Quantity for works projects u tion & Improvement nder Health, Education and P ublic Building Sectors YBMCRP-2020-CS-008 / Cons Infrastructure Rehabilitation ultancy for the development IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 41,435.23 Completed 2020-05-12 2020-05-08 2020-05-22 2020-06-02 2020-07-26 2020-06-24 2021-01-22 2020-12-21 of safeguard Instruments for tion & Improvement all sectors works YBMCRP-2020-CS-003 / Radi Strengthening Peace Buildin o programs on mine awarene IDA / 59880 g, Stability and Social Cohesi Post Direct Selection Direct 52,633.16 Signed 2020-06-01 2020-09-02 2020-06-11 2020-11-10 2020-08-15 2021-01-07 2021-02-11 ss, dispute resolution in Haus on a, Kanuri and Fulfulde YBMCRP-2020-CS-005 / Capa Strengthening Peace Buildin city building for 8 local gover IDA / 59880 g, Stability and Social Cohesi Post Direct Selection Direct 0.00 Under Review 2020-06-01 2021-06-28 2020-06-11 2020-08-15 2021-02-11 nment areas (based on result on s of mapping and profiling as sessment) Page 6 YBMCRP-2020B-CS-002 / Co nduct of Intensified Communi Infrastructure Rehabilitation ty Engagement and Dialogue IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 70,631.94 Completed 2020-06-03 2020-09-04 2020-06-13 2020-09-07 2020-08-17 2020-09-22 2021-02-13 2020-11-20 on Prevention and control me tion & Improvement asures across 14 Emirates an d 17 LGAs YBMCRP-2020B-CS-003 / Tra ining of 98 Environmental He alth workers and cleaners on Infrastructure Rehabilitation medical waste disposal, 98 H IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 69,892.61 Completed 2020-06-03 2020-07-22 2020-06-13 2020-09-07 2020-08-17 2020-11-05 2021-02-13 2021-01-05 ealthcare and non healthcare tion & Improvement personnel on infection preve ntion control and 30 Laborot ory Scientists in testing COVI D-19 testing laboratory. YBMCRP-2020B-CS-004 / De Infrastructure Rehabilitation velopment of Strategic Sustai IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 24,031.50 Signed 2020-06-03 2020-09-24 2020-06-13 2020-09-25 2020-08-17 2020-11-09 2021-02-13 nability Plan for WASH tion & Improvement YBMCRP-2020B-CS-005 / Co Infrastructure Rehabilitation nsultancy for raod design an Under Implement IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 0.00 2020-06-03 2020-08-07 2020-06-13 2020-08-17 2021-02-13 d supervision of 1.5km Buni ation tion & Improvement Gari Town and 1.5KM Babban gida Town YBMCRP-2020B-CS-006 / Co nsultancy for development of Infrastructure Rehabilitation Under Implement safeguard tool for rahabilitati IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 0.00 2020-06-03 2020-03-24 2020-06-13 2020-08-17 2021-02-13 ation on of 1.5km Buni Gari Town, tion & Improvement 1.5KM Babbangida roads YBMCRP-2020B-CS-001 / Ma Strengthening Peace Buildin pping and profiling of women IDA / 59880 g, Stability and Social Cohesi Post Direct Selection Direct 42,041.37 Completed 2020-06-26 2020-10-26 2020-07-06 2020-11-30 2020-09-09 2020-12-22 2020-12-08 2021-04-12 headed households across in on surgent affected communitie s YBMCRP/AF/CS/2021/001 / 1- Identification, Sensitisation a nd strengthening of existing Contingent Emergency Resp IDA / 66490 Post Direct Selection Direct 0.00 Under Review 2022-03-06 2022-04-12 2022-03-16 2022-05-20 2022-11-16 cooperatives/farmer groups ( onse 2 cooperatives & 2 farmer gr oups per affected LGAs) - 32 groups YBMCRP/AF/CS/2021/003 / 1 70 No. of Youth training on G Strengthening Peace Buildin AP, CSA and Research Extens Under Implement IDA / 66490 g, Stability and Social Cohesi Post Direct Selection Direct 0.00 2022-01-15 2022-06-27 2022-01-25 2022-03-31 2022-09-27 ion Farmer Inputs Linkage Sy ation on stem (REFILS) for continuous support to farmers. - 10 per L GAs . YBMCRP/AF/CS/2021/020 / S upport for COVID-19 - Grassr oot community sensitization Infrastructure Rehabilitation Pending Impleme of Mai Unguwas, 6 each from IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 2022-02-02 2022-02-12 2022-04-18 2022-10-15 ntation 17 LGAs on COVID-19 Comm tion & Improvement unity case definition, case id entification and channel of re porting - Health Sector YBMCRP/AF/CS/2021/021 / S upport for COVID-19 - Trainin Infrastructure Rehabilitation g of 320 Primary school Head Pending Impleme IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 2022-02-02 2022-02-12 2022-04-18 2022-10-15 Masters for C-19 IPC measur ntation tion & Improvement es and identification of suspe cted cases in schools - Healt h Sector YBMCRP/AF/CS/2021/023 / E nlightenment /Advocacy on H ygiene and sanitation Promot Infrastructure Rehabilitation Pending Impleme ion through production of m IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 2022-02-02 2022-02-12 2022-04-18 2022-10-15 ntation aterials Print and Electronic tion & Improvement media in 4 languages- Englis h, Hausa, Kanuri and Fulfulde - WASH Sector YBMCRP/AF/CS/2021/037 / D Infrastructure Rehabilitation evelopment and deployment IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 Under Review 2022-01-15 2022-05-12 2022-01-25 2022-03-31 2022-09-27 of safeguard tools - Educatio tion & Improvement n Sector YBMCRP/AF/CS/2021/012 / D Infrastructure Rehabilitation Under Implement evelopment of Design, BEME IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 2022-01-15 2022-05-10 2022-01-25 2022-06-07 2022-03-31 2022-09-27 ation and Supervision - Transport S tion & Improvement ector YBMCRP/AF/CS/2021/002 / E Infrastructure Rehabilitation Under Implement stablishment of seed multipli IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 2022-02-18 2022-05-10 2022-02-28 2022-05-04 2022-10-31 ation cation system (10 LGAs) tion & Improvement YBMCRP/AF/CS/2021/004 / W Infrastructure Rehabilitation Under Implement eather Smart Services For Fa IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 2022-02-06 2022-06-27 2022-02-16 2022-04-22 2022-10-19 ation rmers tion & Improvement YBMCRP/AF/CS/2021/005 / S Infrastructure Rehabilitation Pending Impleme kills acquisition and entrepre IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 2022-01-07 2022-01-17 2022-03-23 2022-09-19 ntation neurship for unskilled Wome tion & Improvement n & Youths YBMCRP/AF/CS/2021/006 / C Strengthening Peace Buildin IDA / 66490 Post Direct Selection Direct 0.00 Under Review 2022-05-03 2022-04-12 2022-05-13 2022-07-17 2023-01-13 apacity Building of Women Tr g, Stability and Social Cohesi ade Groups on YBMCRP/AF/CS/2021/007 / S Strengthening Peace Buildin ensitsation and advocacy on Under Implement IDA / 66490 g, Stability and Social Cohesi Post Direct Selection Direct 0.00 2022-01-11 2022-04-12 2022-01-21 2022-03-27 2022-09-23 peace building activities inclu ation on ding radio programmes, jingl es etc YBMCRP/AF/CS/2021/008 / S ensitization and moblization Strengthening Peace Buildin Pending Impleme Meeting with Religious leader IDA / 66490 g, Stability and Social Cohesi Post Direct Selection Direct 0.00 2022-02-10 2022-02-20 2022-04-26 2022-10-23 ntation s on imperativeness of recon on ciliation and peace buliding YBMCRP/AF/CS/2021/009 / F Strengthening Peace Buildin aciilitation of inter and intra Pending Impleme IDA / 66490 g, Stability and Social Cohesi Post Direct Selection Direct 0.00 2022-02-02 2022-02-12 2022-04-18 2022-10-15 Religious dialogue platforms ntation on at local Government levels YBMCRP/AF/CS/2021/010 / D Infrastructure Rehabilitation Pending Impleme evelopment and deployment IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 2022-02-14 2022-02-24 2022-04-30 2022-10-27 ntation of safeguard tools - Agric Infr tion & Improvement astructure Page 7 YBMCRP/AF/CS/2021/011 / 6- Infrastructure Rehabilitation BEMA design and supervision IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 Under Review 2022-01-15 2022-04-20 2022-01-25 2022-03-31 2022-09-27 for works projects under Agri tion & Improvement c Infrastructure sub conpone nt YBMCRP/AF/CS/2021/013 / D Infrastructure Rehabilitation evelopment of Environmental Under Implement IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 2022-02-15 2022-05-12 2022-02-25 2022-05-01 2022-10-28 & Social Safeguards instrume ation tion & Improvement nts - Transport Sector YBMCRP/AF/CS/2021/014 / R Infrastructure Rehabilitation oad Inventory, and Develop Under Implement IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 2022-02-16 2022-05-10 2022-02-26 2022-05-02 2022-10-29 ment of Road Information Sy ation tion & Improvement stem - Transport Sector YBMCRP/AF/CS/2021/015 / S Infrastructure Rehabilitation upport Quarterly intergrated Pending Impleme IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 2022-02-02 2022-02-12 2022-04-18 2022-10-15 MNCH outreach services to h ntation tion & Improvement ard to reach communities - H ealh Sector YBMCRP/AF/CS/2021/016 / S Infrastructure Rehabilitation upport Quaterly data quality Pending Impleme IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 2022-02-02 2022-02-12 2022-04-18 2022-10-15 assessment for quality impr ntation tion & Improvement ovement - Health Sector YBMCRP/AF/CS/2021/017 / D Infrastructure Rehabilitation Under Implement evelopment and deployment IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 2022-02-02 2022-06-25 2022-02-12 2022-04-18 2022-10-15 ation of safeguard tools for - Healt tion & Improvement h section YBMCRP/AF/CS/2021/018 / B Infrastructure Rehabilitation EMA design and supervision f IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 Under Review 2022-02-02 2022-06-25 2022-02-12 2022-04-18 2022-10-15 or - Health sector tion & Improvement YBMCRP/AF/CS/2021/019 / S upport for COVID-19 - Trainin Infrastructure Rehabilitation g of 45 Health care workers f Pending Impleme IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 2022-02-02 2022-02-12 2022-04-18 2022-10-15 rom 13 Tertiary Education ins ntation tion & Improvement titutions in the state on COVI D-19 IPC measures, case det ection and reporting - Health Sector YBMCRP/AF/CS/2021/022 / S upport for COVID-19 - Trainin Infrastructure Rehabilitation Pending Impleme g of 22 No. Lab Scienetist an IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 2022-02-02 2022-02-12 2022-04-18 2022-10-15 ntation d Tecunician on Quality Mana tion & Improvement gement System in the Molec ular Lab - Health Sector YBMCRP/AF/CS/2021/024 / D Infrastructure Rehabilitation Pending Impleme evelopment of sustainability IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 2022-02-02 2022-02-12 2022-04-18 2022-10-15 ntation framework - WASH Sector tion & Improvement YBMCRP/AF/CS/2021/025 / D Infrastructure Rehabilitation evelopment and deployment IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 Under Review 2022-02-02 2022-05-12 2022-02-12 2022-04-18 2022-10-15 of safeguard tools - WASH se tion & Improvement ctor YBMCRP/AF/CS/2021/026 / B Infrastructure Rehabilitation EMA design and supervision - IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 Under Review 2022-02-02 2022-05-12 2022-02-12 2022-04-18 2022-10-15 WASH sector tion & Improvement YBMCRP/AF/CS/2021/038 / B Infrastructure Rehabilitation Under Implement EMA design and supervision IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 2022-02-02 2022-06-25 2022-02-12 2022-04-18 2022-10-15 ation - Education Sector tion & Improvement Page 8