Procurement Plan for Punjab RWSS (P150520) I. General 1. Bank’s approval Date of the procurement Plan 2012 2. Date of General Procurement Notice: [October 01, 2014 ] 3. Period covered by this procurement plan: January 2020 onwards II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as per the Procurement Risk Rating of the Project: 2. Procurement Method Prior Review Threshold US$ 1. ICB and LIB (Goods) Above US$ 2M 2. NCB (Goods) Above US$ 1M 3. ICB (Works) Above US$ 40 million 4. NCB (Works) Above US$ 10 million 5. (Non-Consultant Services) Above US$ 1M 2. Prequalification for Bidders _Not applicable_ 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P150520 5. Any Other Special Procurement Arrangements: In addition, the justification for all contracts to be issued on the basis of LIB, single-source or direct contracting (except for contracts less than US$50,000 in value) will be subject to prior review. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold 1. Competitive Methods (Firms) Above US$ 1M 2. Single Source (Firms) Above US$ 500,000 3. Individual Above US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. PROCUREMENT India : Punjab Rural Water and Sanitation Sector Improvement Project PLAN General Information Country: India 2018-08-16 Bank’s Approval Date of the Original Procurement Plan: 2022-08-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150520 GPN Date: Project Name: Punjab Rural Water and Sanitation Sector Improvement Project Loan / Credit No: IBRD / 84870 Division No. 1, Muktsar Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned DIV48-4684-87-75-4720-480 6/PSF/RBD / Prov. Inst, testin g & comm of 5 No. Pressure Type Filtration Plant of capac Transformation - Improved L Request for Quota Single Stage - One E 2019-05-0 IBRD / 84870 Post Open - National 80,100.00 65,649.19 Completed 2018-09-08 2018-11-03 2018-11-22 ity 20 Cum/ Hr 2 Nos. &. Plan ivability of Villages tions nvelope 2 ts of 30 Cum/hr 3 Nos along with O&M for 3 Months (min) and other work completed u nder component 1A(i) of PRW SSIP DIV48-4679-81-82-83-4718- 21/PSF/RBD / Prov, Ins, testin g & comm of 6 No. Pressure Type Filtration Plant of capac Transformation - Improved L Request for Quota Single Stage - One E 2019-05-0 IBRD / 84870 Post Open - National 85,200.00 78,563.05 Completed 2018-09-08 2018-11-03 2018-11-19 ity 20 Cum/ Hr along with O ivability of Villages tions nvelope 2 & M for Pressure Type Filtrati on Plants forf 3 Months(min) and other work completed un der component 1A(i) under P RWSSIP DIV48-4640-80-86-4719-22- 39/PSF/RBD / Prov, Inst, testi ng & comm of 6 No. Pressure Type Filtration Plant of capac Transformation - Improved L Request for Quota Single Stage - One E 2019-05-0 IBRD / 84870 Post Open - National 85,200.00 78,522.95 Completed 2018-09-08 2018-11-03 2018-11-19 ity 20 Cum/Hr along with On ivability of Villages tions nvelope 2 & M for Pressure Type Filtrati on Plants for3 Months (Min) a nd other completed works un der component 1A(i) DWSS-W-DIV48-4677-1/RRS / WSS VILL BHANGEWALA DIS T MUKTSAR SAHIB: REPAIR O F EXISTING S&S TANKS, PC, Transformation - Improved L Single Stage - Two E 2019-09-0 OHSR CONST. OF SCS WELL, IBRD / 84870 Post Request for Bids Open - National 155,500.00 152,549.20 Completed 2018-10-01 2018-08-27 2018-10-06 2018-11-17 2018-10-03 2019-01-30 2018-10-18 2019-03-06 2018-11-28 ivability of Villages nvelope 2 CWT, PIPE LINE & SITE LAYIN G, PROV. AND INST. OF PUMP ING MACHINERY, WATER CO NN., DIST. SYSTEM & BULK W M, CHLORINATION PLANT, PS F INCLUDING O&M DWSS-W-DIV48-5161-1/RRS / WSS VILL SUKHNA ABLU DIS MUKTSAR: CONST OF COLL. SUMP, PCs , S&S TANK, RCC SCS WELL, RCC CWT, PIPE LI Transformation - Improved L Single Stage - Two E 2019-09-0 IBRD / 84870 Post Request for Bids Open - National 320,300.00 273,891.87 Completed 2018-10-01 2018-08-27 2018-10-06 2018-11-17 2018-10-03 2019-01-30 2018-10-18 2019-03-06 2018-11-28 NE & SITE LAYING . PROV & I ivability of Villages nvelope 2 NSTAL OF PUMPING MACHINE RY, WATER CONN WITH WAT ER METER, DISTR SYSTEM & BULK WM, CHLORINATION P LANT & PSF REPAIR OF OHS R DWSS-W-DIV48-4685-2/RRS/ PSF/RBD / WSS LUBBIANWAL I BLOCK & DISTT. SRI MUKTS AR SAHIB: PROVIDING, INSTA LLING, COMMISSIONING OF P Transformation - Improved L Request for Quota Single Stage - One E 2019-05-1 IBRD / 84870 Post Open - National 14,200.00 12,001.66 Completed 2018-11-14 2018-11-14 2017-12-28 RESSURE SAND FILTRATION ivability of Villages tions nvelope 3 PLANT OF CAPACITY 20 CUM/ HOUR AND OPERATION & MA INTENANCE OF PRESSURE SA ND FILTRATION PLANT OF 3 MONTHS. UNDER COMPONEN T 1A(I) PRWSS-W-DIV48-4901-2/PSF /RBD / WSS Village KOTLI DE WAN BLOCK & DISTT. SRI M UKTSAR SAHI: Providing, Inst Transformation - Improved L Request for Quota Single Stage - One E 2019-05-1 alling, commissioning of Pres IBRD / 84870 Post Open - National 14,200.00 12,001.66 Completed 2018-11-14 2018-11-14 2017-12-28 ivability of Villages tions nvelope 3 sure Sand filtration plant of c apacity 20 Cum/Hour and op eration & maintenance of pre ssure sand filtration plant of 3 months under component 1A(i). PRWSS-W-DIV48-4676-2/PSF /RBD / WSS KOTLI SANGAR A ND HARAJ BLOCK,DISTRICT S RI MUKTSAR SAHIB:Providing Transformation - Improved L Request for Quota Single Stage - One E 2019-05-1 ,Installing,commissioning of IBRD / 84870 Post Open - National 17,300.00 14,857.70 Completed 2018-11-14 2018-11-14 2017-12-28 ivability of Villages tions nvelope 3 Pressure Sand filtration plant of capacity 30 Cum/Hour and operation & maintenance of pressure sand filtration plant of 3 months under componen t 1A(i). DWSS-W-DIV48-4764-2/PSF/ RBD / WSS GILJEWALA, BLOC K GIDDERBAHA DIST: SRI MU KTSAR SAHIB .Prov, Inst,co Transformation - Improved L Request for Quota Single Stage - One E 2019-05-1 IBRD / 84870 Post Open - National 17,300.00 14,773.65 Completed 2018-11-14 2018-11-14 2017-12-28 mmissioning of Pressure San ivability of Villages tions nvelope 3 d filtration plant of capacity3 0 Cum/Hour and O&M of pres sure sand filtration plant of 3 months under component 1A (i). PRWSS-W-DIV48-10135-1 / WSS village Rahurianwali Blo National Procure ck, District Distt Sri Muktsar ment Document - Inclusive Household Water a Request for Quota Single Stage - One E Pending Imp 2023-07-0 Sahib.Providing improved ac IBRD / 84870 Post Open - National 2 Envelope proce 16,500.00 0.00 2022-08-30 2023-01-03 nd Sanitation Services tions nvelope lementation 2 cess to water through house ss (Non Bank-SPD hold connections in existing ) water supply scheme Rahuri anwali Block and Distt Sri Mu ktsar Sahib. GOODS Page 1 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2