Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: September 24, 2013] 2. Date of General Procurement Notice: July 12, 2013 3. Period covered by this procurement plan: The procurement period of project covered from year September 2013 to May 2018. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) Above US$ 1,500,000 All 3. ICB (Works) Above US$ 5 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 500,000 All [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Summary of the Procurement Packages planned during the first 18 months after project effectiveness [See Procurement Plan] III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) All 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule [See Procurement Plan] PROCUREMENT Iraq : Transport Corridors Project PLAN General Information Country: Iraq 2017-09-11 Bank’s Approval Date of the Original Procurement Plan: 2022-06-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P131550 GPN Date: Project Name: Transport Corridors Project Loan / Credit No: IBRD / 83220 Ministry of Municipalities and Public Works - Roads & Bridges Directorate Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TCP.W.A1.EW.1.R8 / Rehabili Transport Corridors Improve Open - Internationa Single Stage - One E 95,800,237. IBRD / 83220 Prior Request for Bids Signed 2015-11-22 2015-12-10 tation of Expressway No 1 R8 ments l nvelope 07 TCP.W.A1.EW.1.R7 / Rehabili Transport Corridors Improve Open - Internationa Single Stage - One E 105,953,61 IBRD / 83220 Prior Request for Bids Signed 2015-11-04 2015-12-07 tation of Expressway No.1 R7 ments l nvelope 0.99 TCP.W.A1.EW.1.R8B / Rehabi litation of Expressway No.1S Transport Corridors Improve Open - Internationa Single Stage - One E 2020-05-0 IBRD / 83220 Prior Request for Bids 0.00 Canceled 2019-07-18 2019-09-10 2019-07-23 2019-11-11 2019-09-03 2019-10-03 2019-11-07 ection R8B ments l nvelope 5 from Basra Junction – Safwan (Remaining works) TCP.W.A1.EW.1.R8B /R / Reh abilitation of Expressway No. Transport Corridors Improve Open - Internationa Single Stage - One E 37,157,475. 2020-09-2 IBRD / 83220 Prior Request for Bids Signed 2019-12-03 2019-12-12 2019-12-08 2019-12-17 2020-01-19 2020-02-02 2020-02-18 2020-03-16 2020-03-24 2020-04-30 1 R8/B Basra Junction – Safw ments l nvelope 00 0 an (Remaining works) TCP.W.A1.EW.1.R9A / The co mplete works involve rehabili tation of the sub- section R9 Transport Corridors Improve Open - Internationa Single Stage - One E 2022-03-1 IBRD / 83220 Prior Request for Bids 0.00 Canceled 2020-06-30 2020-07-30 2020-09-10 2020-10-10 2020-12-20 A of the Expressway No. 1 w ments l nvelope 5 hich is the main road axis in I raq. The total length of this s ection is about 63 km Request for B TCP.W.A1.EW.1.R9A/R / Reh ids - Works ( abilitation of part of the sect without preq Transport Corridors Improve Open - Internationa Single Stage - One E 31,683,295. 2023-02-2 ion R9A from the Expressway IBRD / 83220 Prior Request for Bids ualification) Signed 2021-06-11 2021-08-17 2021-07-11 2021-08-25 2021-08-22 2021-11-01 2021-09-21 2022-01-27 2021-12-01 2022-03-30 ments l nvelope 50 4 No. 1 from St. ( 0+970) Bagh SPD - Applyin dad- West to St. ( 40+00) g contractor disqualificiati Request on for B TCP.W.A1.EW.1.A3 / Constru ids - Works ( ction on a pilot basis of a fibe without preq Transport Corridors Improve Open - Internationa Single Stage - One E Under Imple 2024-02-0 r optic cable network along s IBRD / 83220 Prior Request for Bids ualification) 0.00 2021-08-18 2021-09-17 2021-10-29 2021-11-28 2022-02-07 ments l nvelope mentation 7 ection R8B (Rumaila - Safwan SPD - Applyin ) of Expressway (1) for 17 KM g contractor . disqualificiati Request on for B TCP.W.A1.EW.1.R9A-AW / Re ids - Works ( habilitation of part of the sec without preq Transport Corridors Improve Single Stage - One E Under Imple 2023-05-1 tion R9A from the Expresswa IBRD / 83220 Prior Request for Bids Open - National ualification) 0.00 2022-06-10 2022-06-17 2022-06-15 2022-07-15 2022-08-14 2022-09-13 ments nvelope mentation 1 y No. 1 from St. (40+00) Wes SPD - Applyin t to St. (50+00 )- Additional g contractor Works disqualificiati on TCP.W.A1.EW.1.R8-BR / Reh National Proc abilitation of 3 Bridges in Bas urement Doc ra Institutional Strengthening a Single Stage - One E ument - 1 En Pending Imp 2023-04-1 - Underpass Bridge (Berjosse IBRD / 83220 nd Capacity Building in the R Prior Request for Bids Open - National 0.00 2022-06-28 2022-07-03 2022-08-14 2022-09-13 2022-10-18 nvelope velope proce lementation 6 ya) at St.48+700-R8B oad Sector ss (Non Bank - Basra Interchange-Kzeizeh -SPD) (St.31+200) and Railway Brid ge(St.4+250) at R8A GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TCP/G/SH/01 / Supply of Air Project Implementation and Request for Quota Single Stage - One E IBRD / 83220 Post Limited 6,329.00 Signed 2016-04-04 2016-03-30 2016-05-30 2016-04-10 2016-11-26 Conditioner for - New PMT off Monitoring tions nvelope ices TCP/G/SH/02 / Supply of Lap Project Implementation and Request for Quota Single Stage - One E IBRD / 83220 Post Limited 3,420.00 Signed 2016-09-30 2016-08-31 2016-11-25 2016-09-20 2017-05-24 top and printer for PMT TCP Monitoring tions nvelope TCP/G/SH/03 / Supply of Lap Project Implementation and Request for Quota Single Stage - One E IBRD / 83220 Post Limited 2,990.00 Signed 2018-09-29 2019-03-06 2018-11-24 2020-05-05 2019-05-23 top and printer for pmt Monitoring tions nvelope TCP/G/SH/04 / Supply of woo den Deskwith drawers (20 pi eces) ,Metallic cupboard with Project Implementation and Request for Quota Single Stage - One E IBRD / 83220 Post Limited 2,760.00 Signed 2019-08-24 2019-08-26 2019-10-19 2019-09-02 2020-04-16 gloss doers with safety lock ( Monitoring tions nvelope 3 pieces) , Metallic cupboard with safety lock (3 pieces), M etal curtains (35 L.M) TCP.G.SH.06 / Supply of Lapt Project Implementation and Request for Quota Single Stage - One E ops for PMT ,archive system IBRD / 83220 Post Limited 9,520.00 Signed 2020-02-15 2020-11-23 2020-04-11 2020-11-29 2020-05-11 Monitoring tions nvelope and external hard drives TCP.G.SH.07 / Vehicle for pa Transport Corridors Improve Request for Quota Single Stage - One E IBRD / 83220 Post Limited 32,000.00 Signed 2020-11-28 2020-12-18 2021-01-12 2020-12-30 2021-01-12 vement condition survey ments tions nvelope TCP.G.SH.08 / Furniture for Transport Corridors Improve Request for Quota Single Stage - One E HDM4,GIS contract manage IBRD / 83220 Post Limited 2,820.00 Signed 2021-01-10 2021-01-02 2021-02-07 2021-05-09 2021-02-07 ments tions nvelope ment committees TCP.G.SH.09 / Purchase of pr Transport Corridors Improve Request for Quota Single Stage - One E inters for PMT and RBD Depa IBRD / 83220 Post Limited 8,605.00 Signed 2021-04-20 2021-04-18 2021-04-29 2021-05-04 2021-04-29 ments tions nvelope rtments supporting the TCP P MT TCP.G.SH.10 / Supply of Lapt Transport Corridors Improve Request for Quota Single Stage - One E IBRD / 83220 Post Limited 1,200.00 Signed 2021-07-23 2021-08-28 2021-08-15 2021-09-05 2021-08-29 op for one of PMT member ments tions nvelope TCP.G.SH.11 / Purchase of F Transport Corridors Improve Request for Quota Single Stage - One E IBRD / 83220 Post Limited 980.00 Signed 2021-09-20 2021-11-20 2021-10-26 2021-12-05 2021-11-09 urniture for PMT and LED scr ments tions nvelope een Page 1 TCP.G.SH.12 / Furniture for n Transport Corridors Improve Request for Quota Single Stage - One E Pending Impl ew GIS room ( following up th IBRD / 83220 Post Limited 0.00 2021-12-05 2022-01-10 2022-01-24 ments tions nvelope ementation e GIS contract requirements). TCP.G.SH.13 / Shopping for Transport Corridors Improve Request for Quota Single Stage - One E Pending Impl IBRD / 83220 Post Limited 0.00 2022-01-07 2022-02-12 2022-02-26 VISIROAD ( HDM4 software to ments tions nvelope ementation ols ) TCP.G.SH.14 / Purchase 2 la Project Implementation and Request for Quota Single Stage - One E Pending Impl IBRD / 83220 Post Limited 0.00 2022-05-25 2022-06-27 2022-07-27 ptops for GIS Monitoring tions nvelope ementation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TCP.NON-CON.DS.01 / TCP-A Transport Corridors Improve F Geotechnical and Pavemen IBRD / 83220 Post Direct Selection Direct 39,000.00 Completed 2021-04-28 2021-04-26 2021-05-03 2021-05-04 2021-05-17 2021-06-06 2021-06-16 2021-07-15 ments t Testing for PR06A TCP.NON-CON.DS.02 / Additi Transport Corridors Improve Pending Impl onal works for the TCP-AF Ge IBRD / 83220 Post Direct Selection Direct 0.00 2021-11-28 2021-12-03 2021-12-17 2022-01-16 ments ementation otechnical and Pavement Tes ting for PR06A CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TCP.CON.QCBS.C1(a) / Tech Transport Corridors Improve Quality And Cost- Open - Internationa IBRD / 83220 Prior 280,147.50 Terminated 2015-06-15 2015-08-24 2015-10-19 2015-11-30 2016-01-11 2016-11-07 2016-02-22 2016-11-08 2017-03-02 Audit ments Based Selection l TCP.CON.LCS.C1 (b) / Extern Transport Corridors Improve Quality And Cost- Open - Internationa IBRD / 83220 Prior 214,592.00 Completed 2016-04-14 2016-04-18 2021-06-30 al Audit ments Based Selection l TCP.CON.QCBS.R7&R8 / Tec hnical Assistance for constru ction supervision of Expressw Transport Corridors Improve Quality And Cost- Open - Internationa IBRD / 83220 Prior 8,063,012.49 Signed 2013-09-18 2015-05-11 2015-07-05 2015-08-16 2015-09-27 2016-03-03 2015-10-21 2016-03-03 2016-03-08 ay NO.1 section R7: Nasiria-R ments Based Selection l umaila & R8 A: section Ruma ila-Basra , R8 B:Rumaila-Safw an TCP/CON/QCBS/B1/I/01/B / Pr Institutional Strengthening a eparation of ESIA for Safwan- Quality And Cost- Open - Internationa IBRD / 83220 nd Capacity Building in the R Post 0.00 Canceled 2017-07-04 2018-08-06 2017-12-24 2018-05-10 2018-08-02 2018-06-07 2018-07-07 2019-02-10 2018-08-11 2018-09-15 2019-09-15 Umm Qasr and Safwan and Based Selection l oad Sector Safwan - Border Crossing Ro ad Rehabilitation Project TCP/CON/QCBS/B1/I/01/A / Pr eparation of Economic Analy Institutional Strengthening a sis , Detailed Engineering De Quality And Cost- Open - Internationa IBRD / 83220 nd Capacity Building in the R Prior 0.00 Canceled 2017-06-01 2018-06-27 2017-06-22 2017-08-05 2018-09-21 2017-09-02 2018-11-07 2017-10-02 2019-02-21 2017-11-06 2019-06-06 2017-12-11 2018-12-11 sign & Bidding Document for Based Selection l oad Sector Safwan- Umm Qasr and Safw an – Border Crossing Road Rehabilitation Project TCP/CON/QCBS/B1/G / Techn ical Assistance in Analysis a Institutional Strengthening a nd inmprovement /Develome Quality And Cost- Open - Internationa IBRD / 83220 nd Capacity Building in the R Prior 946,733.91 Signed 2017-05-08 2018-08-30 2018-01-15 2018-05-28 2018-09-26 2018-06-25 2019-01-09 2018-07-25 2019-06-01 2018-08-29 2019-07-30 2018-10-03 2019-08-29 2019-10-03 nt of Technical Manual /Spec Based Selection l oad Sector ification for road Miantaenan ce and Superpave implemant ation study TCP/CON/QCBS/B1/D / Techn ical Assistance in developme Institutional Strengthening a nt of ICT including citizens'ro Quality And Cost- Open - Internationa IBRD / 83220 nd Capacity Building in the R Prior 825,689.19 Signed 2018-05-20 2018-08-30 2018-06-10 2019-06-18 2018-07-24 2020-02-25 2018-08-21 2020-02-10 2018-09-20 2020-03-18 2018-10-25 2020-06-01 2018-11-29 2020-06-29 2019-11-29 adway reporting system,esti Based Selection l oad Sector blishment of call center(s),su rveilance system , and axel -l oad limit enforcement for RB D TCP/CON/QCBS/B1/C / Aware Institutional Strengthening a Quality And Cost- Open - Internationa ness raising on routine maint IBRD / 83220 nd Capacity Building in the R Prior 0.00 Canceled 2018-04-11 2018-05-02 2018-06-15 2018-07-13 2018-08-12 2018-09-16 2018-10-21 2019-10-21 Based Selection l enance and improving capaci oad Sector ty for RBD TCP/CON/QCBS/B1/B / Techn Institutional Strengthening a Quality And Cost- Open - Internationa ical assistance in enhanceme IBRD / 83220 nd Capacity Building in the R Prior 0.00 Canceled 2018-04-11 2018-05-02 2018-06-15 2018-07-13 2018-08-12 2018-09-16 2018-10-21 2019-10-21 Based Selection l nt of the road sector governa oad Sector nce for RBD TCP/CON/QCBS/B1/I/ 02 / Te chnical Assistance for the up Institutional Strengthening a Quality And Cost- Open - Internationa grade of the existing GIS IBRD / 83220 nd Capacity Building in the R Prior 1,353,049.34 Signed 2018-11-21 2019-01-09 2018-12-12 2019-01-25 2020-05-12 2019-02-22 2020-05-01 2019-03-24 2020-05-18 2019-04-28 2020-05-19 2019-06-02 2020-06-23 2020-06-01 Based Selection l & the road asset manageme oad Sector nt HDM-IV system TCP/CON/QCBS/B1/I/02 / upg Institutional Strengthening a Quality And Cost- Open - Internationa rade of the existing database IBRD / 83220 nd Capacity Building in the R Prior 0.00 Canceled 2018-01-02 2018-01-23 2019-02-19 2018-03-08 2018-04-05 2018-05-05 2018-06-09 2018-07-14 2019-07-14 Based Selection l and GIS at RBD oad Sector TCP/CON/QCBS/B1/B/C / Tec hnical assistance in Enhance Institutional Strengthening a Quality And Cost- Open - Internationa ment of the road sector gove IBRD / 83220 nd Capacity Building in the R Prior 0.00 Canceled 2018-11-26 2019-01-30 2018-12-17 2019-01-30 2019-02-27 2019-03-29 2019-05-03 2019-06-07 2020-06-06 Based Selection l rnance And Raising awarenes oad Sector s on routine maintenance TCP/CON/QCBS/B4/A / Traini Institutional Strengthening a Quality And Cost- Open - Internationa ng of local contractors and c IBRD / 83220 nd Capacity Building in the R Prior 0.00 Canceled 2018-11-19 2019-02-20 2018-12-10 2019-01-23 2019-02-20 2019-03-22 2019-04-26 2019-05-31 2020-05-30 Based Selection l onsultants for RBD oad Sector TCP/CON/QCBS/R8B / Techni cal Assistance of Constructio Transport Corridors Improve Quality And Cost- Open - Internationa IBRD / 83220 Prior 13,500.00 Signed 2019-01-28 2019-02-20 2019-02-18 2019-04-24 2019-04-03 2019-09-02 2019-05-01 2019-10-22 2019-05-31 2019-12-30 2019-07-05 2020-03-05 2019-08-09 2020-03-31 2020-08-08 n Supervision for Expresswa ments Based Selection l y No.1 R8B Project (Remainin g Works) TCP.CON.DS.B1(I)-03 / IDEN TIFYING AND ASSESSMENT O Institutional Strengthening a F FINANCING AND MAINTENA Quality And Cost- Open - Internationa IBRD / 83220 nd Capacity Building in the R Post 0.00 Canceled 2019-07-18 2019-07-17 2019-08-08 2019-09-02 2019-09-21 2019-10-19 2019-11-18 2019-12-23 2020-01-27 2021-01-26 NCE OPTIONS FOR ROAD TRA Based Selection l oad Sector DE AND DEVELOPMENT COR RIDORS “TOLLING ROAD STU DY” Page 2 TCP.CON.QCBS.B1(I)-03 / ID ENTIFYING AND ASSESSMENT Institutional Strengthening a OF FINANCING AND MAINTEN Quality And Cost- Open - Internationa IBRD / 83220 nd Capacity Building in the R Prior 470,661.88 Completed 2019-10-27 2019-10-30 2019-11-17 2019-12-31 2020-09-08 2020-01-28 2020-01-09 2020-02-27 2020-09-14 2020-04-02 2020-09-18 2020-05-07 2020-09-29 2021-05-07 2021-02-19 ANCE OPTIONS FOR ROAD TR Based Selection l oad Sector ADE AND DEVELOPMENT CO RRIDORS “TOLLING ROAD ST UDY” TCP/CON/QCBS/B1(A) / Tech Institutional Strengthening a Quality And Cost- Open - Internationa nical assistance in RBD organ IBRD / 83220 nd Capacity Building in the R Prior 0.00 Canceled 2019-11-14 2019-12-05 2020-01-18 2020-02-15 2020-03-16 2020-04-20 2020-05-25 2021-05-25 Based Selection l izational structure and capaci oad Sector ty improvement TCP/CON/QCBS/B4(A) / Traini ng of staff of Road and Bridg Institutional Strengthening a Quality And Cost- Open - Internationa es (RBD) and State owned Co IBRD / 83220 nd Capacity Building in the R Prior 674,265.00 Completed 2019-12-02 2020-01-07 2019-12-23 2020-01-20 2020-02-05 2020-04-25 2020-03-04 2020-06-28 2020-04-03 2020-09-23 2020-05-08 2020-11-24 2020-06-12 2020-12-02 2021-06-12 2021-07-31 Based Selection l nstruction Companies / Enter oad Sector prises SOEs in the Road Sect or TCP.CON.QCBS.B1(I)-04 / Ro Transport Corridors Improve Quality And Cost- Open - Internationa ad Safety Investment Strateg IBRD / 83220 Prior 662,590.00 Signed 2020-01-24 2020-02-11 2020-02-14 2020-03-10 2020-03-29 2020-06-15 2020-04-26 2020-08-18 2020-05-26 2020-09-29 2020-06-30 2021-02-08 2020-08-04 2021-05-02 2021-05-06 ments Based Selection l y and Safety System Projects TCP.CON.QCBS.R9A / superv ision consultant to of the reh abilitation of Expressway No. 1 sec R9A which starts in Abo Transport Corridors Improve Quality And Cost- Open - Internationa IBRD / 83220 Prior 1,871,481.50 Signed 2020-05-31 2020-05-18 2020-06-21 2020-07-13 2020-08-04 2020-11-05 2020-09-01 2021-01-05 2020-10-01 2021-08-01 2020-11-05 2022-01-30 2020-12-20 2022-02-08 2022-03-15 u Ghraib city near Baghdad.T ments Based Selection l he total length is about 63 k m.to implement the project a ccording to specification, wit hin cost and according to tim e schedule TCP.CON.QCBS.B1(I)-05 / Te chnical assistance for the de velopment and implementati Transport Corridors Improve Quality And Cost- Open - Internationa IBRD / 83220 Prior 0.00 Canceled 2020-11-23 2021-01-18 2020-12-14 2021-02-17 2021-01-27 2021-07-27 2021-02-24 2021-03-26 2021-04-30 2021-06-04 2022-06-04 on of Bridge Inventory and In ments Based Selection l spection System (BIIS) for Ba ghdad 13 Bridges over Tigris River TCP.CON.QCBS.A5 / Enginee Transport Corridors Improve Quality And Cost- Open - Internationa Under Implement ring supervision for installati IBRD / 83220 Post 0.00 2021-01-28 2021-03-06 2021-02-11 2021-03-11 2021-03-25 2021-04-24 2021-05-22 2021-06-29 2023-04-20 ments Based Selection l ation on of fiber optics network for Expressway 1 TCP.CON.QCBS.B1(I)-06 / Pre paration of Economic Analysi Transport Corridors Improve Quality And Cost- Open - Internationa Under Implement s, Detailed Engineering Desig IBRD / 83220 Prior 0.00 2021-05-14 2021-08-24 2021-06-04 2021-08-03 2021-08-31 2021-09-30 2021-11-04 2021-12-09 2022-07-21 ments Based Selection l ation n for Package 1 Roads: Kut – Ammara Road and Ammara Basra Road TCP.CON.QCBS.B1(I)-06A / P Transport Corridors Improve Quality And Cost- Open - Internationa reparation of (ESIA) and(RAP) IBRD / 83220 Post 0.00 Canceled 2021-06-10 2021-07-01 2021-08-30 2021-09-27 2021-10-27 2021-12-01 2022-01-05 2022-07-27 ments Based Selection l Studies for Hwy 6-Kut-Amara h-Basra Road TCP.CON.CQS.B1.I.01 / Struc Transport Corridors Improve Consultant Qualifi Open - Internationa tural Evaluation for Five Brid IBRD / 83220 Post 0.00 Canceled 2021-08-20 2021-08-12 2021-09-10 2021-10-24 2021-11-23 2021-12-28 2022-04-07 ments cation Selection l ges Located on Expressway No. 1 TCP.CON.QCBS.B1(I)-05/R / T Transport Corridors Improve Quality And Cost- Open - Internationa Under Implement echnical assistance for Inspe IBRD / 83220 Prior 0.00 2021-10-27 2021-11-01 2021-11-17 2021-11-09 2021-12-31 2021-12-23 2022-01-28 2022-02-21 2022-02-27 2022-04-11 2022-04-03 2022-05-08 2022-09-05 ments Based Selection l ation ction of Baghdad 13 Bridges over Tigris River TCP.CON.LCS.C1(B-2) / Exter Transport Corridors Improve Least Cost Selecti IBRD / 83220 Post Open - National 36,000.00 Signed 2022-02-28 2022-02-24 2022-03-21 2022-05-04 2022-03-14 2022-06-01 2022-03-24 2022-07-01 2022-04-03 2022-08-05 2022-04-13 2022-09-09 2022-06-14 2023-03-08 nal Financial Auditor ments on TCP.CON.CQS.C1(A) / Techni Transport Corridors Improve Consultant Qualifi Open - Internationa Under Implement IBRD / 83220 Post 0.00 2022-03-10 2022-03-07 2022-03-24 2022-04-21 2022-05-26 2022-05-05 2022-06-02 2023-03-29 cal Audit for R8B and R9A ments cation Selection l ation TCP.CON.QCBS.B1(B-C) / rais ing awareness on routine mai Institutional Strengthening a Quality And Cost- Open - Internationa Under Implement ntenance and Preparation of IBRD / 83220 nd Capacity Building in the R Prior 0.00 2022-06-10 2022-06-08 2022-07-01 2022-06-19 2022-08-14 2022-09-11 2022-10-11 2022-11-15 2022-12-20 2023-06-18 Based Selection l ation Performance-Based Maintena oad Sector nce bid documents for Expre ssway No. 1 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TCP.CON.IC.C1(c) / Contract Transport Corridors Improve Individual Consult IBRD / 83220 Prior Open 672,225.00 Signed 2016-04-11 2016-05-31 Management Specialist ments ant Selection TCP.CON.IC.C1 (c).01-04 / Tr Transport Corridors Improve IBRD / 83220 Prior Direct Selection Direct 12,000.00 Signed 2015-09-29 anslation Services ments TCP.CON.IC.C.01 / Procurem Transport Corridors Improve Individual Consult IBRD / 83220 Prior Open 99,615.00 Signed 2015-07-30 2015-08-11 ent Expert ments ant Selection TCP/CON/IC/C1/C/01/02 / En Project Implementation and Individual Consult IBRD / 83220 Post Open 73,280.00 Signed 2015-02-26 2016-09-28 2015-04-16 2016-05-15 2015-05-07 2016-12-19 2015-06-11 2016-10-27 2015-12-08 vironmental Specialist Monitoring ant Selection TCP/CON/IC/C1/C/01/06 / Dis pute Board for Rehabilitation Project Implementation and Individual Consult IBRD / 83220 Post Direct 80,250.00 Signed 2016-10-24 2018-09-15 2016-11-03 2016-11-29 2016-11-24 2017-04-23 2016-12-29 2017-06-06 2017-06-27 of Expressway No.1 section R Monitoring ant Selection 7 (Nasiria-Rumaila) TCP/CON/IC/C1/C/01/07 / Dis pute Board for Rehabilitation Project Implementation and Individual Consult IBRD / 83220 Post Direct 80,250.00 Signed 2016-10-24 2016-09-15 2016-11-03 2016-11-29 2016-11-24 2017-04-23 2017-05-16 2017-04-25 2020-01-15 Of Expressway Section R8 (R Monitoring ant Selection umaila – Basra & Safwan) TCP/CON/IC/C1/C/01/08 / Dis pute Board for Rehabilitation Project Implementation and Individual Consult IBRD / 83220 Post Direct 80,250.00 Signed 2016-08-18 2016-09-15 2016-08-28 2017-04-18 2016-09-18 2017-04-23 2016-10-23 2017-04-25 2017-04-21 of Expressway No.1 section R Monitoring ant Selection 7 (Nasiria-Rumaila) TCP/CON/IC/C1/C/01/09 / Dis pute Board for Rehabilitation Project Implementation and Individual Consult IBRD / 83220 Post Direct 80,250.00 Signed 2016-08-18 2016-09-15 2016-08-28 2017-04-18 2016-09-18 2017-04-23 2016-10-23 2017-04-23 2017-04-21 Of Expressway Section R8 (R Monitoring ant Selection umaila – Basra & Safwan) Page 3 TCP/CON/IC/C1/C/01/10 / Dis pute Board for Rehabilitation Project Implementation and Individual Consult IBRD / 83220 Post Direct 80,250.00 Signed 2017-03-07 2016-09-15 2017-03-17 2017-03-13 2017-04-07 2017-04-23 2017-05-12 2017-04-23 2017-11-08 of Expressway No.1 section R Monitoring ant Selection 7 (Nasiria-Rumaila) TCP/CON/IC/C1/C/01/11 / Dis pute Board for Rehabilitation Project Implementation and Individual Consult IBRD / 83220 Post Direct 80,250.00 Signed 2017-03-07 2016-09-15 2017-03-17 2017-03-13 2017-04-07 2017-03-13 2017-05-12 2017-06-06 2017-11-08 Of Expressway Section R8 (R Monitoring ant Selection umaila – Basra & Safwan) TCP/CON/IC/C1/C/01/12 / Ro ot Cause Analysis and Occup Project Implementation and Individual Consult ational Health and Safety(OH IBRD / 83220 Post Open 0.00 Canceled 2018-11-19 2019-01-07 2019-01-28 2019-03-04 2019-08-31 Monitoring ant Selection S) Audit for Iraq Transport Co rridors Project (TCP Segment R7 and R8) TCP/CON/IC/C1/C/ 01-12 / Ro ot Cause Analysis and Occup Project Implementation and ational Health and Safety(OH IBRD / 83220 Post Direct Selection Direct 22,000.00 Signed 2018-12-16 2018-12-26 2019-03-01 2018-12-31 2019-08-28 Monitoring S) Audit for Iraq Transport Co rridors Project (TCP Segment R7 and R8) TCP/CON/IC/C1/C/01/13 / Ro ad Safety Audit of traffic man Project Implementation and agement plan IBRD / 83220 Post Direct Selection Direct 20,000.00 Signed 2018-12-16 2018-12-26 2019-03-01 2018-12-31 2019-08-28 Monitoring for Iraq Transport Corridors p roject (TCP segment R7 and R8) TCP/CON/DS/B1/I/03 / Identif ying and assessment of finan Project Implementation and IBRD / 83220 Post Direct Selection Direct 0.00 Canceled 2019-02-26 2019-03-08 2019-05-12 2019-11-08 cing and maintenance option Monitoring s for road trade and develop ment corridors TCP-CON-IC-C1-C -01-16 / Di spute Board for Rehabilitatio Project Implementation and Individual Consult IBRD / 83220 Post Direct 13,600.00 Signed 2020-01-12 2020-02-06 2020-01-17 2020-02-01 2020-02-07 2020-02-01 2020-03-13 2020-02-09 2021-05-12 n of Expressway No.1 section Monitoring ant Selection R7 (Nasiria-Rumaila) TCP-CON-IC-C1-C -01-17 / Di spute Board for Rehabilitatio Project Implementation and Individual Consult IBRD / 83220 Post Direct 13,600.00 Signed 2020-01-12 2020-02-01 2020-01-17 2020-02-01 2020-02-07 2020-03-13 2020-02-09 2021-04-04 n Of Expressway Section R8 ( Monitoring ant Selection Rumaila – Basra & Safwan) TCP.CON.IC.C1(C ).01-18 / P Project Implementation and Individual Consult IBRD / 83220 Post Direct 45,600.00 Completed 2020-01-30 2020-02-09 2020-02-09 2020-02-01 2020-02-12 2020-02-01 2020-02-15 2020-02-09 2021-02-09 2021-06-09 avement Expert/ Prof. Ham Monitoring ant Selection ed Hamdou TCP.CON.DC.BI(E AND H,F)-0 Institutional Strengthening a 1 / PPP Training and Certifica IBRD / 83220 nd Capacity Building in the R Post Direct Selection Direct 34,760.00 Signed 2020-03-01 2020-01-23 2020-03-02 2020-03-03 2020-03-25 2020-02-06 2020-04-29 tion (CP3P Foundation)/Beirut oad Sector TCP.CON.DC.B1(e and h,f)-01 TCP.CON.IC.C1(C ).01-19 / U pdate the ESIA, ESMP and AR AP/RAP in accordance with th e WB safeguards policies for Project Implementation and Individual Consult the Expressway No.1–section IBRD / 83220 Post Direct 14,000.00 Signed 2020-04-23 2020-05-19 2020-05-03 2020-06-09 2020-05-24 2020-06-28 2020-07-05 2020-07-06 2020-10-03 Monitoring ant Selection s R9A (63km) and R9B (61km ) Abu Ghraib city in Baghdad at Sta. 0+000 and the City of Hit in the Governate of Al An bar at Sta. 123+000 (123 km ) TCP/CON/IC/C1/C/01/15 / En Project Implementation and Individual Consult IBRD / 83220 Post Direct 0.00 Canceled 2019-03-03 2019-07-17 2019-03-13 2019-04-03 2019-05-08 2019-11-04 vironmental and Social Speci Monitoring ant Selection alist TCP.CON.IC.C1(C ).01-20 / O ccupational Health and Safet Transport Corridors Improve Individual Consult IBRD / 83220 Post Limited 72,000.00 Signed 2020-09-20 2020-09-19 2020-09-25 2020-10-19 2020-10-16 2020-11-03 2020-11-20 2020-11-11 2021-05-19 y Expert for TCP projects Sec ments ant Selection tions R8B (Remaining works), R9A R4 ,R5 and R6. TCP.CON.IC.C1(C ).01-21 / Tr ansportation economist Expe rt to update the feasibility st Transport Corridors Improve Individual Consult udy report prepared by the C IBRD / 83220 Post Limited 24,500.00 Signed 2020-09-20 2020-09-14 2020-09-25 2020-12-16 2020-10-05 2020-12-25 2020-10-17 2020-12-30 2021-02-14 ments ant Selection onsolidated Consultants (CC) 2013 for the Expressway No. 1 – specifically to Sections R 9A and R9B TCP.CON.IC.C1(C).01-22 / ES Transport Corridors Improve Individual Consult MP audit for TCP projects Ex IBRD / 83220 Post Direct 5,500.00 Signed 2020-09-30 2020-10-18 2020-10-19 2020-12-09 2020-10-24 2020-12-22 2020-11-03 2021-01-21 2022-02-26 ments ant Selection pressway No. 1- Sections R4, R5 and R6 TCP.CON.IC.C1(C).01-24 / TC Transport Corridors Improve Individual Consult IBRD / 83220 Post Direct 0.00 Canceled 2020-10-18 2020-10-18 2020-10-25 2020-11-04 2020-11-16 2021-02-08 P-AF / Senior Highway Engine ments ant Selection er TCP.CON.IC.C1(C).01-25 / TC Transport Corridors Improve Individual Consult IBRD / 83220 Post Direct 0.00 Canceled 2020-10-19 2020-10-18 2020-10-26 2020-11-05 2020-11-17 2021-02-09 P-AF /Senior Structural/ Bridg ments ant Selection e Engineer TCP.CON.IC.C1(C).01-26 / Ro Transport Corridors Improve Individual Consult IBRD / 83220 Post Direct 17,000.00 Completed 2020-10-25 2020-10-14 2020-11-01 2020-11-25 2020-11-15 2020-12-04 2020-12-04 2020-12-13 2021-01-29 2021-08-31 ad Maintenance Expert ments ant Selection TCP.CON.IC.C1(C).01-23 / TC Transport Corridors Improve Individual Consult IBRD / 83220 Post Direct 0.00 Canceled 2020-10-22 2020-10-15 2020-10-25 2020-10-30 2020-11-11 2021-01-20 P - AF / Environmental and S ments ant Selection ocial Expert TCP.CON.IC.C1(C).01-27 / Pr eparation of the ESIAs and R APs for the below projects wi thin the TCP-AF priority no.1 Transport Corridors Improve Individual Consult IBRD / 83220 Post Direct 0.00 Canceled 2020-11-08 2020-11-11 2020-11-11 2020-11-14 2020-11-19 2020-12-30 - PR03B: The Rustumiya Brid ments ant Selection ge project. - PR03A: Kut-Baghdad Road s ection (Hwy 6). TCP.CON.IC.C1(C).01-28 / De tailed Engineering Design, Te Transport Corridors Improve Individual Consult IBRD / 83220 Post Limited 0.00 Canceled 2020-11-24 2020-12-09 2020-11-29 2020-12-13 2020-12-23 2021-04-14 nder Document Preparation F ments ant Selection or the widening and rehabilit ation of Kut-Baghdad TCP.CON.IC.C1(C).01-29 / De tailed Engineering Design, Te Transport Corridors Improve Individual Consult nder Document Preparation F IBRD / 83220 Post 95,000.00 Signed 2020-11-26 2020-12-09 2020-12-01 2021-01-06 2020-12-15 2021-04-02 2020-12-25 2021-04-15 2021-04-16 ments ant Selection or Dualization of the Fajr int ersection - Al Bader road Page 4 TCP.CON.IC.C1(C).01-31 / Tr Transport Corridors Improve Individual Consult IBRD / 83220 Post Direct 27,000.00 Completed 2020-11-24 2021-01-19 2020-12-04 2021-03-30 2020-12-09 2021-04-26 2020-12-19 2021-05-05 2021-01-23 2021-08-31 affic Data Collection and Anal ments ant Selection ysis TCP.CON.IC.C1(C).01-30 / De tailed Engineering Design, Te Transport Corridors Improve Individual Consult IBRD / 83220 Post Limited 0.00 Canceled 2020-11-25 2020-12-09 2020-11-30 2020-12-07 2020-12-19 2021-03-13 nder Document Preparation F ments ant Selection or PR03B- Rustumiya Bridge TCP.CON.DS.B1.I.06 / Geote chnical and Pavement Testin Transport Corridors Improve IBRD / 83220 Post Direct Selection Direct 0.00 Canceled 2020-12-20 2021-04-11 2020-12-30 2021-01-11 2021-03-22 g along PR03A, PR03B &PR06 ments A road corridors subprojects TCP.CON.IC.C1(C).01-32 / TC Transport Corridors Improve Individual Consult IBRD / 83220 Post Limited 20,000.00 Signed 2020-12-31 2020-12-26 2021-01-14 2021-04-01 2021-01-19 2021-04-23 2021-02-14 2021-05-05 2021-06-20 P-AF Road Safety Auditor ments ant Selection TCP.CON.IC.C1(C).01-33 / AF Transport Corridors Improve Individual Consult IBRD / 83220 Post Limited 22,000.00 Signed 2020-12-31 2021-01-19 2021-01-14 2021-04-05 2021-01-19 2021-01-29 2021-05-09 2021-06-18 -TCP Transport Economist Ex ments ant Selection pert TCP.CON.IC.C1(C).01-34 / Di Transport Corridors Improve Individual Consult spute Board Sole Member for IBRD / 83220 Post Limited 19,800.00 Signed 2021-01-27 2021-01-22 2021-02-10 2021-04-02 2021-02-15 2021-01-05 2021-02-25 2021-06-28 2023-02-15 ments ant Selection R8B remaining works TCP.CON.IC.C1(C).01-35 / En Transport Corridors Improve Individual Consult vironmental and Social Exper IBRD / 83220 Post Direct 42,455.00 Signed 2021-04-14 2021-04-15 2021-04-24 2021-05-10 2021-05-01 2021-06-10 2021-05-11 2021-06-13 2021-08-10 ments ant Selection t for R9A and Al -Fajer Al-Bed er. TCP.CON.DS.C1 (B) / Externa Transport Corridors Improve IBRD / 83220 Post Direct Selection Direct 0.00 Canceled 2021-05-08 2021-05-20 2021-06-30 2023-06-30 l financial audit contract ments TCP.CON.IC.C1(C).01-36 / Ba Transport Corridors Improve Individual Consult IBRD / 83220 Post Limited 22,000.00 Signed 2021-05-11 2021-05-05 2021-05-25 2022-01-20 2021-05-30 2022-02-13 2021-06-25 2022-02-28 2021-09-03 ghdad 13 Bridges Road Safet ments ant Selection y Auditor TCP.CON.IC.C1(C).01-37 / 13 Transport Corridors Improve Individual Consult Under Implement Bridges package no.1 - Envir IBRD / 83220 Post Limited 0.00 2021-06-03 2021-06-25 2021-06-24 2021-07-01 2021-07-09 2021-11-26 ments ant Selection ation onmental and Social Speciali st TCP.CON.IC.C1(C).01-38 / Ro ad Safety Investment Strateg Transport Corridors Improve Individual Consult IBRD / 83220 Post Limited 37,400.00 Signed 2021-07-22 2021-06-30 2021-07-27 2021-12-17 2021-08-17 2021-09-13 2021-09-21 2021-09-15 2022-03-20 y and Safety System Projects ments ant Selection - Roads Safety Auditor RSA. TCP.CON.DS.C1(B)/R / Exter Transport Corridors Improve IBRD / 83220 Post Direct Selection Direct 0.00 Canceled 2021-07-27 2021-06-28 2021-08-08 2021-09-18 2024-01-01 nal financial audit contract- Ir ments aq Branch TCP.CON.DS.C1(B)/R-2 / Exte Transport Corridors Improve IBRD / 83220 Post Direct Selection Direct 77,900.00 Terminated 2022-01-17 2022-01-16 2022-01-29 2022-01-17 2022-03-11 2022-02-01 2024-06-23 rnal Financial Audit ments TCP.CON.DS.B1 (D) / RBD CR RS and ICT systems for a seg Project Implementation and Under Implement IBRD / 83220 Post Direct Selection Direct 0.00 2022-03-31 2022-04-18 2022-04-10 2022-06-06 2022-05-04 2022-11-23 ment of Expressway No. 1 – Monitoring ation Section R5 including fiber opt ic TCP.CON.IC.C1(C).01-39 / Pr eparation of Environmental a nd Social Impact Assessment Transport Corridors Improve Individual Consult Under Implement (ESIA) Studies for IBRD / 83220 Post Direct 0.00 2022-03-31 2022-03-27 2022-04-10 2022-04-15 2022-04-27 2023-05-17 ments ant Selection ation the maintenance of 13 Bridg es over the Tigris River and r emoval of Sunken Parts from the River TCP.CON.DS.B1.(E AND H,F)- Institutional Strengthening a Under Implement 02 / Workshop – Road Perfor IBRD / 83220 nd Capacity Building in the R Post Direct Selection Direct 0.00 2022-06-10 2022-06-01 2022-06-20 2022-08-24 2022-10-23 ation mance Based Maintenance oad Sector TCP.CON.IC.C1(C).01- 40 / Br idge Engineer Reviewer- For Transport Corridors Improve Individual Consult Pending Impleme the Tender document Mainte IBRD / 83220 Post Limited 0.00 2022-06-30 2022-07-05 2022-07-26 2022-08-30 2023-02-26 ments ant Selection ntation nance works of (13) bridges in the City of Baghdad Page 5