PHILIPPINE RURAL DEVELOPMENT PROJECT LN 8421-PH ORIGINAL LOAN Procurement Plan As of June 2018 I. General 1. Bank’s approval Date of the Procurement Plan : September 9, 2014 2. Date of General Procurement Notice : September 25, 2012 3. Period covered by this procurement plan : July 2018 – June 2019 II. Goods and Works and non-consulting services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Method Threshold Prior Review No. Procurement Method US$ Threshold US$ International Competitive 1. 3M and above All contracts Bidding (ICB) (Goods) National Competitive Bidding 2. less than 3M 2M and above (NCB) (Goods) packages 3. Shopping (Goods) less than 0.2M None 4. ICB (Works) packages 15M and above All contracts 5. NCB (Works) packages less than 15M 10M and above 6. Shopping (Works) less than 0.2M None Subject to justification in accordance with para. 3.7 of 5. Direct Contracting (Goods) 2M and above Procurement Guidelines at the Procurement Plan stage 6. Commercial Practice less than 0.1M None 7. Community Participation less than 0.05M None 2. Reference to Project Operational/Procurement Manual including Community Participation: Original version dated : May 2014 To be updated by : July 2018 (Revised Operations Manual submitted September 4, 2017) 3. Summary of the Procurement Packages (with international competition, direct contracting, requiring Bank’s prior review): PHILIPPINE RURAL DEVELOPMENT PROJECT Summary of the Procurement Packages LN 8421 PH Procurement Plan Updated June 2018 (with International Competition, Direct Contracting requiring Bank’s prior review) 1 2 3 4 5 6 7 8 9 10 Domest Estimated ic Expected Procurin Procurem Cost Funding Prefere Review Bid Comment Ref. No. Description g ent US$1= Source nce by Bank Opening s Agency Method Php 50) (yes/no Date ) No subprojects for Bank’s prior review III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines on Selection and Employment of Consultants: Prior Review No. Selection Method Method Threshold US$ Threshold US$ 1. Competitive Methods 0.3M & above (may be used for 1m and above (QCBS, QBS, FBS) also less than 0.3M) (Firms) 2. Competitive Method less than 0.3M None CQS (Firms) 3. Individuals Competitive regardless of amount 0.3M and above 2. Single Source (Firms & on exceptional basis subject to Firms: 1M and Individuals) justification in accordance with above; paras. 3.9 and 5.4 respectively of Individuals 0.3M and Consultant Guidelines at the above. Procurement Plan stage 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Summary of the Consultancy Assignments/Packages (using international competition, single/sole source selection, requiring Bank’s prior review): PHILIPPINE RURAL DEVELOPMENT PROJECT Summary of the Procurement Packages (with International Competition) 1 2 3 4 5 6 7 8 Ref Description of Procurin Expected Bid Estimated Cost (USD Funding Selection Comm . Contract g Opening million) Source Method ents No. Package Agency Date Various PRDP Technical Consultant and Staff (provided with No Objection December 22, 2017) US$1,042,75 Single Source NPCO ( Php53.178 LP/GoP Selection million) US$1,042,75 Single Source Luzon A ( Php59.152 LP/GoP Selection million) LN 8421 PH Procurement Plan Updated June 2018 US$1,042,75 Single Source Luzon B ( Php48.614 LP/GoP Selection million) US$1,042,75 Single Source Visaya ( Php29.612 LP/GoP Selection million) US$1,042,75 Single Source Mindanao ( Php million) LP/GoP Selection Prepared by: Reviewed by: ENGR. ROMEO L. MALONG ENGR. CHRISTOPHER V. MORALES Alternate Procurement Unit Head Procurement Unit Head LN 8421 PH Procurement Plan Updated June 2018 PROCUREMENT Philippines : Philippine Rural Development Project PLAN General Information Country: Philippines Bank’s Approval Date of the Original Procurement Plan: 2019-03-11 Revised Plan Date(s): (comma delineated, leave blank if none)2022-01-26 Project ID: P132317 GPN Date: Project Name: Philippine Rural Development Project Loan / Credit No: IBRD / 88160, IBRD / 84210, IBRD / 92710, TF / B5756 Executing Agency(ies):PRDP PSO Mindanao, Dept of Agriculture WORKS Activity Reference No. / Procurement Estimated Actual Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalificatio High SEA/SH Process Prequalification Specific Procurement Bidding Documents Proposal Submission Contract Description Component Review Type Method Document Amount Amount qualification Document / and Signed Contract No. Approach Process n (Y/N) Risk Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Completion Type (US$) (US$) Documents Justification Recommendation for Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PlannedAwardActual Planned Actual Planned PRDP-IB-RO10-MOC-020- Component 2: 000-000-2015-AF / Single Stage - One 1,325,039. 1,402,781 2018-11- 2019-02- 2018-11- 2019-01- 2019-03- 2019-02- 2019-06- 2019-03- 2020-02- 2019-09- IBRD / 88160 Infrastructure Post Request for Bids Open - National Signed Concreting of Bato, Plaridel Envelope 22 .57 20 21 25 06 26 05 29 12 24 08 Development - Sinian, Baliangao FMR PRDP-IB-RO10-MOC-022- 000-000-2016-AF / Component 2: Concreting of Zamora – Single Stage - One 3,366,843. 3,569,046 2018-11- 2019-02- 2018-11- 2019-01- 2019-03- 2019-02- 2019-06- 2019-03- 2020-02- 2019-09- IBRD / 88160 Infrastructure Post Request for Bids Open - National Signed Culpan – Balintonga – Envelope 14 .20 20 01 25 06 26 05 29 12 20 08 Development Sinampongan Farm to Market Road PRDP-IB-R011-DOC-003- Component 2: Pending 000-000-2017-AF / Single Stage - One 2,144,411. 2018-09- 2018-09- 2018-10- 2018-11- 2019-01- 2019-07- IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Implement Rehabilitation of San Envelope 76 12 17 29 28 02 01 Development ation Agustin - Mamacao - Tanglad FMR PRDP-IB-R011-DDS-015- 000-000-2017-AF / Component 2: Under Single Stage - One 3,330,607. 2018-08- 2018-08- 2018-08- 2018-09- 2018-09- 2018-10- 2018-11- 2019-05- Rehabilitation of San Isidro, IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Implement Envelope 84 09 09 14 25 14 25 29 28 Hagonoy - Km67, Matanao Development ation FMR PRDP-IB-R013-DII-002- Component 2: Single Stage - One 2,124,333. 2,223,577 2018-08- 2018-08- 2018-08- 2018-09- 2018-09- 2018-10- 2018-10- 2018-12- 2018-12- 2019-06- 000-000-2015-AF / IBRD / 88160 Infrastructure Post Request for Bids Open - National Signed Envelope 33 .17 13 06 18 29 12 29 05 03 28 01 Concreting of R. Ecleo to Development Upper Laguna FMR PRDP-IB-RO13-ADS-010- ROS-001-2016-AF / Component 2: Single Stage - One 1,051,798 2018-09- 2018-09- 2018-09- 2018-10- 2018-10- 2018-11- 2018-11- 2019-01- 2018-12- 2019-06- Construction of 4.760 Km. IBRD / 88160 Infrastructure Post Request for Bids Open - National 990,450.98 Signed Envelope .39 11 11 16 28 11 27 12 01 28 30 Main Canal with Structures Development of Limbatangan CIS PRDP-IB-RO13-ADN-007- Component 2: BUT-002-2015-AF / Single Stage - One 3,116,529. 3,276,225 2018-10- 2018-11- 2018-10- 2018-11- 2018-12- 2018-12- 2019-02- 2019-01- 2019-10- 2019-07- IBRD / 88160 Infrastructure Post Request for Bids Open - National Signed Concreting of Lauan - Tud- Envelope 41 .95 09 16 14 25 17 25 26 29 04 28 Development ol Farm to Market Road PRDP-IB-RO10-MOR-013- VIL-001-2016-AF / Component 2: Single Stage - One 1,380,725. 1,446,471 2018-10- 2018-10- 2018-10- 2018-11- 2018-11- 2018-12- 2019-01- 2019-01- 2019-07- 2019-07- Concreting of Dayawan- IBRD / 88160 Infrastructure Post Request for Bids Open - National Signed Envelope 49 .35 10 22 15 26 22 26 09 30 26 29 Lokong-Crossing Development Mambuaya Farm to Market Road PRDP-IB-R009-ZDN-003- 000-000-2015-A-AF / Rehabilitation/Concreting Component 2: of NRJ Gatas, Kalawit- Single Stage - Two 2,603,862. 3,036,312 2018-09- 2018-08- 2018-09- 2018-10- 2018-10- 2019-01- 2018-11- 2019-02- 2019-07- 2019-08- IBRD / 88160 Infrastructure Post Request for Bids Open - National Signed Batayan-Poblacion Envelope 75 .79 14 08 19 31 24 13 23 17 25 16 Development (Pagkaing Bayan)-Daniel Maing-Gabu,Labason- Lawigan Osukan Farm-to- Market Road (Road Segment 1) PRDP-IB-R009-ZDN-003- 000-000-2015-B-AF / Rehabilitation/Concreting Component 2: of NRJ Gatas, Kalawit- Single Stage - Two 6,032,607. 7,042,689 2018-09- 2018-08- 2018-09- 2018-10- 2018-10- 2019-01- 2018-11- 2019-02- 2019-08- 2019-08- IBRD / 88160 Infrastructure Post Request for Bids Open - National Signed Batayan-Poblacion Envelope 84 .82 14 08 19 31 24 13 23 17 01 16 Development (Pagkaing Bayan)-Daniel Maing-Gabu,Labason- Lawigan Osukan Farm-to- Market Road (Road Segment 2) PRDP-IB-R009-ZDN-003- 000-000-2015 / Rehabilitation/Concreting Component 2: Pending of NRJ Gatas, Kalawit- Single Stage - One 2,505,604. 2019-02- 2019-02- 2019-03- 2019-04- 2019-05- 2019-11- IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Implement Batayan-Poblacion Envelope 00 02 07 21 20 25 21 Development ation (Pagkaing Bayan)-Daniel Maing-Gabu,Labason- Lawigan Osukan Farm-to- Market Road (Road Segment 1) PRDP-IB-R010-BUK-018- MAN-004-2016 / Component 2: Construction of Warehouse Request for Single Stage - One 2019-07- 2019-02- 2019-08- 2019-10- 2020-02- IBRD / 88160 Infrastructure Post Limited 68,660.00 72,265.16 Signed with Multi Purpose Drying Quotations Envelope 03 06 28 16 24 Development Pavement (MPDP) (Brgy Kalugmanan) PRDP-IB-R010-BUK-023- MAN-009-2016 / Component 2: Construction of Warehouse Request for Single Stage - One 2019-07- 2019-02- 2019-08- 2019-10- 2020-02- IBRD / 88160 Infrastructure Post Limited 66,509.00 72,884.13 Signed with Multi Purpose Drying Quotations Envelope 03 06 28 16 24 Development Pavement (MPDP) (Brgy Minsuro) PRDP-IB-R010-BUK-024- MAN-010-2016 / Component 2: Construction of Warehouse Request for Single Stage - One 2019-07- 2020-02- 2019-08- 2020-11- 2020-02- IBRD / 88160 Infrastructure Post Limited 68,264.00 72,983.12 Signed with Multi Purpose Drying Quotations Envelope 03 25 28 23 24 Development Pavement (MPDP) (Brgy Sto. Nino) PRDP-IB-R010-BUK-022- MAN-008-2016 / Component 2: Construction of Warehouse Request for Single Stage - One 2019-07- 2019-02- 2019-08- 2019-10- 2020-02- IBRD / 88160 Infrastructure Post Limited 67,264.00 72,265.16 Signed with Multi Purpose Drying Quotations Envelope 03 06 28 16 24 Development Pavement (MPDP) (Brgy Mambatangan) PRDP-IB-R010-MOC-021- PAN-002-2015 / Component 2: Pending Rehabilitation and Single Stage - One 2,720,755. 2019-04- 2019-04- 2019-06- 2019-07- 2019-08- 2020-02- IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Implement Concreting of 11.187 km Envelope 00 16 21 02 02 06 02 Development ation Sumasap-Salimpono- Magsaysay-Bangko-San Juan FMR PRDP-IB-R010-MOC-018- Component 2: ORO-001-2015 / Single Stage - One 1,045,895. 1,139,483 2019-02- 2018-10- 2019-02- 2019-04- 2018-11- 2019-05- 2018-12- 2019-06- 2019-06- 2019-12- IBRD / 88160 Infrastructure Post Request for Bids Open - National Signed Concreting of Dolipos Alto- Envelope 00 .19 15 10 20 03 13 03 17 07 04 04 Development Dullan Norte Road PRDP-IB-R010-MOR-013- Component 2: Under VIL-001-2016 / Single Stage - One 1,328,623. 1,464,717 2019-02- 2018-10- 2019-02- 2019-04- 2018-11- 2019-05- 2018-11- 2019-06- 2019-12- IBRD / 88160 Infrastructure Post Request for Bids Open - National Implement Construction of Dayawan- Envelope 00 .38 16 22 21 04 22 04 22 08 05 Development ation Lokong-Crossing Mambuaya FMR PRDP-IB-R011-DDN-011- Component 2: Under 000-000-2015 / Single Stage - One 3,793,264. 2019-02- 2018-07- 2019-02- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Implement Rehabilitation of Sonlon - Envelope 00 17 29 22 05 05 09 06 Development ation Camansa FMR PRDP-IB-R011-DDN-011- Component 2: Pending 000-000-2017 / Single Stage - One 2,062,930. 2019-02- 2019-02- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Implement Rehabilitation of San Envelope 00 18 23 06 06 10 07 Development ation Agustin - Mamacao - Tanglad FMR PRDP-IB-R011-DDN-015- 000-000-2017 / Component 2: Pending Single Stage - One 3,274,856. 2019-02- 2019-02- 2019-04- 2019-05- 2019-06- 2019-12- Rehabilitation of San Isidro, IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Implement Envelope 00 19 24 07 07 11 08 Hagonoy - Km67, Matanao Development ation FMR PRDP-IB-R011-CVP-015- 000-000-2017 / Component 2: Pending Single Stage - One 3,606,019. 2019-02- 2019-02- 2019-04- 2019-05- 2019-06- 2019-12- Rehabilitation of IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Implement Envelope 00 22 27 10 10 14 11 Cabinuangan-Magangit Development ation FMR with Three (3) units Bridge Retrofitting Work PRDP-IB-RO10-MOC-018- ORO-001-2015-AF / Component 2: Under Single Stage - One 1,088,078. 2018-10- 2018-10- 2018-10- 2018-12- 2018-11- 2018-12- 2019-02- 2019-08- Concreting of Dolipos Alto IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Implement Envelope 43 15 10 20 01 13 31 04 03 to Dullan Norte Farm to Development ation Market Road PRDP-IB-RO13-ADS-012- SAL-001-2016-AF / Component 2: Construction of 2.711 kms. Single Stage - One 436,197.4 2018-08- 2018-08- 2018-09- 2018-10- 2018-09- 2018-11- 2018-10- 2018-12- 2019-02- 2019-06- IBRD / 88160 Infrastructure Post Request for Bids Open - National 416,862.75 Signed Main Canal & Laterals and Envelope 3 28 28 02 14 27 13 29 18 28 16 Development Structures of Laminga Communal Irrigation Project PRDP-IB-R009-ZAS-012- Component 2: TIT-001-2015 / Concreting Single Stage - Two 1,135,156. 2018-11- 2018-11- 2018-12- 2019-03- 2019-04- 2019-10- IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Canceled of San Antonio-Balocon - Envelope 86 05 10 22 06 10 07 Development San Isidro Farm to Market Road PRDP-IB-R009-ZAS-013- Component 2: BUU-002-2017 / Road Single Stage - Two 1,800,411. 2018-11- 2019-01- 2018-11- 2018-12- 2019-03- 2019-04- 2019-10- IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Canceled Concreting of Agutayan Envelope 76 05 15 10 22 06 10 07 Development Farm to Market Road PRDP-IB-R011-DDN-011- Component 2: 000-000-2015-AF / Single Stage - One 3,942,019. 2018-08- 2018-08- 2018-09- 2018-10- 2018-11- 2019-05- IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Canceled Rehabilitation of Sonlon - Envelope 61 02 07 18 18 22 21 Development Camansa FMR PRDP-IB-RO10-MOC-021- PAN-002-2015-AF / Component 2: Rehabilitation and Single Stage - One 2,788,450. 2018-11- 2018-11- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Canceled Concreting of Sumasap – Envelope 98 20 25 06 05 12 08 Development Salimpono – Magsaysay – Bangko – San Juan Farm to Market Road PRDP-IB-R011-DDS-014- Component 2: 000-000-2017 / Single Stage - One 4,877,392. 2018-11- 2018-11- 2018-12- 2019-01- 2019-02- 2019-08- IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Canceled Rehabilitation of Waterfall- Envelope 16 05 10 22 21 25 24 Development Osmeña FMR with PSCG Bridge PRDP-IB-R011-CVP-015- 000-000-2017-AF / Component 2: Single Stage - One 3,747,431. 2018-08- 2018-08- 2018-09- 2018-10- 2018-11- 2019-05- Rehabilitation of IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Canceled Envelope 37 09 14 25 25 29 28 Cabinuangan-Magangit Development FMR with Three (3) units Bridge Retrofitting Work PRDP-IB-R012-NCO-017- Component 2: Single Stage - Two 2,930,274. 2018-11- 2018-11- 2018-12- 2019-03- 2019-04- 2019-10- KID-002-2017 / IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Canceled Envelope 51 05 10 22 06 10 07 Concreting of Sumbac- Development Onica FMR PRDP-IB-R012-SAR-012- GLA-001-2015 / Component 2: Improvement of NHW Jct. Single Stage - Two 4,857,274. 2018-11- 2018-11- 2018-12- 2019-03- 2019-04- 2019-10- IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Canceled Calabanit - E. Alegado (New Envelope 51 05 10 22 06 10 07 Development Aklan - Kaltuad - E. Alegado Road Section) FMR Phase 2 PRDP-IB-R012-SAR-016- Component 2: 000-000-2018 / Single Stage - Two 1,117,372. 2018-11- 2018-11- 2018-12- 2019-03- 2019-04- 2019-10- IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Canceled Concreting of Kanalo- Envelope 55 05 10 22 06 10 07 Development Nomoh Farm-Market Road PRDP-IB-R012-SOC-009- Component 2: TAM-002-2015 / Single Stage - Two 2,240,745. 2018-11- 2018-11- 2018-12- 2019-03- 2019-04- 2019-10- IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Canceled Concreting of Lampitak- Envelope 10 05 10 22 06 10 07 Development Albagan Farm to Market Road PRDP-IB-R012-SUK-017- Component 2: ESP-007-2017 / Single Stage - Two 3,133,607. 2018-11- 2018-11- 2018-12- 2019-03- 2019-04- 2019-10- IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Canceled Concreting of Saliao- Envelope 84 05 10 22 06 10 07 Development Daladap-Guiamalia Farm to Market Road PRDP-IB-RARM-MAG-017- Component 2: Single Stage - One 3,541,627. 2018-11- 2020-01- 2018-11- 2018-12- 2019-01- 2019-02- 2019-08- TAL-001-2017 / IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Canceled Envelope 45 05 31 10 22 21 25 24 Concreting of Tamar-Fukol Development FMR PRDP-IB-RARM-SUL-001- LUG-001-2017 / Component 2: Single Stage - One 2,646,960. 2018-11- 2019-09- 2018-11- 2018-12- 2019-01- 2019-02- 2019-08- Concreting of Barangay IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Canceled Envelope 78 05 05 10 22 21 25 24 Parian Kayawan- Pait- Development Rugasan-Kutah Parang - Mantan Farm to Market Road PRDP-IB-RO10-BUK-023- MAN-009-2016-AF / Component 2: Single Stage - One 2018-11- 2018-11- 2018-12- 2019-01- 2019-02- 2019-08- Proposed Construction of IBRD / 88160 Infrastructure Post Request for Bids Open - National 69,176.47 0.00 Canceled Envelope 06 11 23 22 26 25 Warehouse with Solar Dryer Development (Zone 2, Brgy. Minsuro) Page 1 PRDP-IB-RO10-BUK-024- MAN-010-2016-AF / Component 2: Single Stage - One 2018-11- 2018-11- 2018-12- 2019-01- 2019-02- 2019-08- Proposed Construction of IBRD / 88160 Infrastructure Post Request for Bids Open - National 70,941.18 0.00 Canceled Envelope 06 11 23 22 26 25 Warehouse with Solar Dryer Development (Brgy. Proper, Sto. Niño) PRDP-IB-R009-ZDN-005- Component 2: SIB-001-2017 / Concreting Single Stage - Two 3,330,607. 5,161,860 2018-11- 2019-01- 2018-11- 2018-12- 2019-02- 2019-03- 2019-04- 2019-04- 2019-08- 2019-10- IBRD / 88160 Infrastructure Post Request for Bids Open - National Signed of Poblacion-Sto. Niño - Envelope 84 .56 05 16 10 22 21 06 01 10 30 07 Development (Sitio Log Deck) Tangarak FMR PRDP-IB-R009-ZAS-013- Component 2: BUU-002-2017-AF1 / Road Single Stage - One 1,800,411. 1,888,590 2019-01- 2019-01- 2019-01- 2019-02- 2019-02- 2019-03- 2019-03- 2019-04- 2019-08- 2019-10- IBRD / 88160 Infrastructure Post Request for Bids Open - National Signed Concreting of Agutayan Envelope 00 .18 08 17 13 24 19 26 22 30 29 27 Development Farm to Market Road PRDP-IB-R009-ZAS-012- Component 2: TIT-001-2015-AF1 / Single Stage - One 1,135,156. 1,202,299 2019-01- 2019-05- 2019-01- 2019-02- 2019-06- 2019-03- 2019-07- 2019-05- 2019-11- 2019-10- IBRD / 88160 Infrastructure Post Request for Bids Open - National Signed Concreting of San Antonio- Envelope 00 .41 09 21 14 25 26 27 29 01 14 28 Development Balocon - San Isidro Farm to Market Road PRDP-IB-R009-ZAS-014- Component 2: OLU-001-2017-AF1 / Single Stage - One 2,058,460. 2,270,858 2019-09- 2019-09- 2019-09- 2019-10- 2019-10- 2019-11- 2019-11- 2020-01- 2020-06- 2020-06- IBRD / 88160 Infrastructure Post Request for Bids Open - National Signed Concreting og Gandaan- Envelope 00 .13 11 02 16 28 23 27 20 01 26 29 Development San Jose Farm to Market Road PRDP-IB-R011-DDS-014- 000-000-2017-AF1 / Component 2: Pending Single Stage - One 2,353,120. 2018-01- 2018-01- 2018-02- 2018-03- 2018-05- 2018-10- Rehabilitation of Waterfall- IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Implement Envelope 00 10 15 26 28 02 29 Osmeña FMR with PSCG Development ation Bridge Package 2 PRDP-IB-R012-SUK-017- Component 2: ESP-007-2017-AF1 / Single Stage - One 3,133,607. 3,323,500 2019-09- 2019-09- 2019-09- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-12- 2020-06- IBRD / 88160 Infrastructure Post Request for Bids Open - National Signed Concreting of Saliao- Envelope 00 .20 03 02 08 20 04 19 11 24 23 21 Development Daladap-Guiamalia Farm to Market Road PRDP-IB-R012-SAR-016- Component 2: 000-000-2018-AF1 / Single Stage - One 1,117,372. 1,169,954 Terminate 2019-01- 2019-02- 2019-01- 2019-03- 2019-03- 2019-04- 2019-05- 2019-05- 2019-09- 2019-11- IBRD / 88160 Infrastructure Post Request for Bids Open - National Concreting of Kanalo- Envelope 00 .03 d 22 18 27 10 22 09 07 14 13 10 Development Nomoh Farm-Market Road PRDP-IB-R012-NCO-017- Component 2: KID-002-2017-AF1 / Single Stage - One 2,930,274. 2,679,903 2019-01- 2019-03- 2019-02- 2019-03- 2019-04- 2019-04- 2019-05- 2019-05- 2019-09- 2019-11- IBRD / 88160 Infrastructure Post Request for Bids Open - National Signed Concreting of Sumbac- Envelope 00 .08 31 11 05 19 23 18 07 23 12 19 Development Onica FMR PRDP-IB-RARM-MAG-017- Component 2: TAL-001-2017-AF1 / Single Stage - One 3,541,672. 4,143,413 2020-01- 2020-01- 2020-01- 2020-03- 2020-03- 2020-04- 2020-04- 2020-05- 2020-10- 2020-11- IBRD / 88160 Infrastructure Post Request for Bids Open - National Signed Concreting of Tamar-Fukol Envelope 00 .62 21 31 26 08 03 07 06 12 26 08 Development FMR PRDP-IB-RARM-SUL-001- LUG-001-2017-AF1 / Component 2: Under Concreting of Barangay Single Stage - One 2,646,960. 2019-09- 2019-09- 2019-09- 2019-11- 2019-10- 2019-12- 2019-11- 2020-01- 2020-07- IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Implement Parian Kayawan- Pait- Envelope 00 19 05 24 05 09 05 04 09 07 Development ation Rugasan-Kutah Parang - Mantan Farm to Market Road PRDP-IB-R011-DDS-014- 000-000-2017-AF / Component 2: Pending Single Stage - One 2,262,755. 2019-02- 2019-02- 2019-04- 2019-05- 2019-06- 2019-12- Rehabilitation of Waterfall- IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Implement Envelope 00 20 25 08 08 12 09 Osmeña FMR with PSCG Development ation Bridges (Package 1) PRDP-IB-R010-MOC-022- 000-000-2016 / Component 2: Single Stage - One 3,239,792. 2019-02- 2019-02- 2019-04- 2019-05- 2019-06- 2019-12- Concreting of Zamora- IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Canceled Envelope 00 15 20 03 03 07 04 Culpan-Balintonga- Development Sinampongan Farm to Market Road PRDP-IB-R013-DII-002- Component 2: Single Stage - One 2,044,170. 2019-02- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- 000-000-2015 / IBRD / 88160 Infrastructure Post Request for Bids Open - National 0.00 Canceled Envelope 00 28 05 16 16 20 17 Concreting of R. Ecleo - Development Upper Laguna FMR PRDP-IB-RO10-BUK-018- MAN-004-2016-AF / Component 2: Proposed Construction of Single Stage - One 2018-11- 2018-11- 2018-12- 2019-01- 2019-02- 2019-08- IBRD / 88160 Infrastructure Post Request for Bids Open - National 71,352.94 0.00 Canceled Warehouse with Solar Dryer Envelope 06 11 23 22 26 25 Development (Sitio Balakbakan, Brgy. Kalugmanan) PRDP-IB-RO10-BUK-022- MAN-008-2016-AF / Component 2: Proposed Construction of Single Stage - One 2018-11- 2018-11- 2018-12- 2019-01- 2019-02- 2019-08- IBRD / 88160 Infrastructure Post Request for Bids Open - National 70,862.75 0.00 Canceled Warehouse with Solar Dryer Envelope 06 11 23 22 26 25 Development (Sitio Viga, Brgy. Mambatangan) National PRDP-IB-R009-ZDN-006- Procurement Component 2: Pending SIA-001-2018-EU / Single Stage - One Document - 1 1,711,140. 2021-12- 2021-12- 2022-02- 2022-03- 2022-04- 2022-10- IBRD / 92710 Infrastructure Post Request for Bids Open - National 0.00 Implement Rehab/Conc. of NRJ Envelope Envelope 00 15 22 02 04 08 05 Development ation Gonayen-Balunokan FMR process (Non Bank-SPD) National PRDP-IB-R009-ZDN-007- Procurement Component 2: Pending RIZ-001-2018-EU / Single Stage - One Document - 1 1,056,440. 2021-12- 2021-12- 2022-02- 2022-03- 2022-04- 2022-11- IBRD / 92710 Infrastructure Post Request for Bids Open - National 0.00 Implement Rehab/Concreting of Envelope Envelope 00 15 22 02 04 08 30 Development ation Mapang - Mabuhay FMR process (Non Bank-SPD) National PRDP-IB-R009-ZDN-008- Procurement Component 2: Pending RIZ-002-2018-EU / Single Stage - One Document - 1 1,581,040. 2021-12- 2021-12- 2021-12- 2022-01- 2022-03- 2023-02- IBRD / 92710 Infrastructure Post Request for Bids Open - National 0.00 Implement Rehab/Concreting Of NRJ Envelope Envelope 00 15 22 26 25 01 17 Development ation San Roque - Rizalina FMR process (Non Bank-SPD) National PRDP-IB-R010-MOC-014- Procurement BON-002-2019-EU / Component 2: Pending Single Stage - One Document - 1 3,340,000. 2022-03- 2022-03- 2022-05- 2022-06- 2022-07- 2023-01- Concreting of Buracan – IBRD / 92710 Infrastructure Post Request for Bids Open - National 0.00 Implement Envelope Envelope 00 20 25 06 05 10 06 Dimalco – Dapagan – Masay Development ation process (Non FMR Bank-SPD) National PRDP-IB-R010-MOR-014- Procurement NAA-001-2018-EU / Component 2: Pending Single Stage - One Document - 1 1,880,000. 2021-12- 2021-12- 2022-02- 2022-03- 2022-04- 2022-10- Construction of Mapulog- TF / B5756 Infrastructure Post Request for Bids Open - National 0.00 Implement Envelope Envelope 00 15 22 02 04 08 05 Tuboran FMR with Arch Development ation process (Non Bridges Bank-SPD) National PRDP-IB-R010-BUK-026- Component 2: Procurement Pending Single Stage - One 3,140,000. 2021-12- 2021-12- 2022-02- 2022-03- 2022-04- 2022-10- VAL-002-2018-EU / TF / B5756 Infrastructure Post Request for Bids Open - National Document - 1 0.00 Implement Envelope 00 15 22 02 04 08 05 Concreting of Mt. Nebo- Development Envelope ation Sitio Migtulod FMR process (Non Bank-SPD) National PRDP-IB-R010-BUK-023- Procurement LAN-001-2017-EU / Component 2: Pending Single Stage - One Document - 1 1,880,000. 2021-12- 2021-12- 2022-01- 2022-02- 2022-03- 2022-09- Concreting of Road and IBRD / 92710 Infrastructure Post Request for Bids Open - National 0.00 Implement Envelope Envelope 00 08 15 14 13 28 24 Drainage at Purok 3 to Development ation process (Non Purok 5, Kulasihan Bank-SPD) Lantapan, Bukidnon National PRDP-IB-R010-BUK-029- Procurement VAL-003-2018-EU / Component 2: Pending Single Stage - One Document - 1 5,000,000. 2021-12- 2021-12- 2022-02- 2022-03- 2022-04- 2022-10- Concreting of Jct. Brgy. IBRD / 92710 Infrastructure Post Request for Bids Open - National 0.00 Implement Envelope Envelope 00 15 22 02 04 08 05 Mabuhay to Brgy. Banlag Development ation process (Non Proper to Sitio Pantaron Bank-SPD) FMR National PRDP-IB-R011-DDS-016- Procurement Component 2: Pending 000-000-2018-EU / Single Stage - One Document - 1 2,054,460. 2021-12- 2021-12- 2022-01- 2022-03- 2022-04- 2023-05- IBRD / 92710 Infrastructure Post Request for Bids Open - National 0.00 Implement Rehabilitation of Ibo-Pitu, Envelope Envelope 00 15 20 31 02 06 12 Development ation Malalag FMR process (Non Bank-SPD) National PRDP-IB-R012-SOC-009- Procurement Component 2: Pending TAM-002-2015-AF2 / Single Stage - One Document - 1 2,006,040. 2021-12- 2021-12- 2022-02- 2022-03- 2022-04- 2023-05- IBRD / 92710 Infrastructure Post Request for Bids Open - National 0.00 Implement Concreting of Lampitak- Envelope Envelope 00 15 22 02 04 08 11 Development ation Albagan Farm to Market process (Non Road Bank-SPD) PRDP-IB-R012-SUK-037- Component 2: Request for Pending ISU-006-2021-EU / Request for Single Stage - One 2021-12- 2022-01- 2022-07- IBRD / 92710 Infrastructure Post Open - National Quotations (Non 70,500.00 0.00 Implement Construction of Impao Quotations Envelope 15 29 28 Development Bank-SPD) ation Potable Water System Level II PRDP-IB-R012-SUK-038- Component 2: Request for Pending ISU-007-2021-EU / Request for Single Stage - One 2021-12- 2022-02- 2022-08- IBRD / 92710 Infrastructure Post Open - National Quotations (Non 143,377.00 0.00 Implement Construction of Kolambog Quotations Envelope 15 09 08 Development Bank-SPD) ation Potable Water System Level II PRDP-IB-R012-SUK-039- Component 2: Request for Pending ISU-008-2021-EU / Request for Single Stage - One 2021-12- 2022-02- 2022-08- IBRD / 92710 Infrastructure Post Open - National Quotations (Non 71,300.00 0.00 Implement Construction of Kudanding Quotations Envelope 15 09 08 Development Bank-SPD) ation Potable Water System Level II PRDP-IB-R012-SUK-040- Component 2: Request for Pending ISU-009-2021-EU / Request for Single Stage - One 2021-12- 2022-02- 2022-08- IBRD / 92710 Infrastructure Post Open - National Quotations (Non 155,877.00 0.00 Implement Construction of Laguilayan Quotations Envelope 15 09 08 Development Bank-SPD) ation Potable Water System Level II PRDP-IB-R012-SUK-041- Component 2: Request for Pending ISU-010-2021-EU / Request for Single Stage - One 2021-12- 2022-02- 2022-08- IBRD / 92710 Infrastructure Post Open - National Quotations (Non 140,988.00 0.00 Implement Construction of Mapantig Quotations Envelope 15 09 08 Development Bank-SPD) ation Potable Water System Level II PRDP-IB-R012-SUK-042- Component 2: Request for Pending ISU-011-2021-EU / Request for Single Stage - One 2021-12- 2022-02- 2022-08- IBRD / 92710 Infrastructure Post Open - National Quotations (Non 170,846.00 0.00 Implement Construction of New Egana Quotations Envelope 15 09 08 Development Bank-SPD) ation Potable Water System Level II PRDP-IB-R012-SUK-043- Component 2: Request for Pending ISU-012-2021-EU / Request for Single Stage - One 2021-12- 2022-02- 2022-08- IBRD / 92710 Infrastructure Post Open - National Quotations (Non 143,746.00 0.00 Implement Construction of Tayugo Quotations Envelope 15 09 08 Development Bank-SPD) ation Potable Water System Level II National PRDP-IB-R013-SDS-004- Procurement Component 2: Pending SAN-004-2018-EU / Single Stage - One Document - 1 1,690,880. 2021-12- 2021-12- 2022-02- 2022-03- 2022-04- 2022-10- TF / B5756 Infrastructure Post Request for Bids Open - National 0.00 Implement Construction/Concreting of Envelope Envelope 00 15 22 02 04 08 05 Development ation Buhisan-Manumnum FMR process (Non Bank-SPD) National PRDP-IB-R013-ADS-012- Component 2: Procurement Pending Single Stage - One 1,219,757. 2022-03- 2022-03- 2022-05- 2022-06- 2022-07- 2023-01- 000-000-2018-EU / IBRD / 92710 Infrastructure Post Request for Bids Open - National Document - 1 0.00 Implement Envelope 00 20 25 06 05 10 06 Concreting of Bucac- Development Envelope ation Marcelina FMR process (Non Bank-SPD) PRDP-IB-RARM-TAW-013- SOU-003-2016-EU / Component 2: Request for Pending Request for Single Stage - One 2021-12- 2022-03- 2022-09- Construction of Tampakan IBRD / 92710 Infrastructure Post Open - National Quotations (Non 99,969.00 0.00 Implement Quotations Envelope 15 28 24 Dampong Warehouse with Development Bank-SPD) ation Solar Drier PRDP-IB-RARM-TAW-012- Component 2: Request for Pending SOU-002-2016-EU / Request for Single Stage - One 2021-12- 2022-03- 2022-09- IBRD / 92710 Infrastructure Post Open - National Quotations (Non 120,000.00 0.00 Implement Construction of Lahad Quotations Envelope 15 28 24 Development Bank-SPD) ation Dampong Fish Landing National PRDP-IB-RARM-TAW-015- Procurement Component 2: Pending TAN-007-2016-EU / Single Stage - One Document - 1 2021-12- 2021-12- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Infrastructure Post Request for Bids Open - National 200,000.00 0.00 Implement Construction of Sallangan Envelope Envelope 08 15 14 13 10 06 Development ation Potable Water Supply Level process (Non II Bank-SPD) National PRDP-IB-RARM-BAS-003- Procurement LAM-001-2017-EU / Component 2: Pending Single Stage - One Document - 1 1,102,660. 2021-12- 2021-12- 2022-01- 2022-02- 2022-03- 2022-09- Concreting of Barangay Lo- IBRD / 92710 Infrastructure Post Request for Bids Open - National 0.00 Implement Envelope Envelope 00 08 15 14 13 10 06 ok -Barangay Arco Farm to Development ation process (Non Market Road Bank-SPD) National PRDP-IB-RARM-LDS-002- Component 2: Procurement Pending Single Stage - One 1,584,000. 2021-12- 2021-12- 2022-01- 2022-02- 2022-03- 2022-09- PIA-001-2017-EU / IBRD / 92710 Infrastructure Post Request for Bids Open - National Document - 1 0.00 Implement Envelope 00 08 15 14 13 28 24 Concreting of Barangay Development Envelope ation Pantar process (Non Bank-SPD) National PRDP-IB-RARM-LDS-003- Procurement GAN-001-2017-EU / Component 2: Pending Single Stage - One Document - 1 1,320,000. 2021-12- 2021-12- 2022-01- 2022-02- 2022-03- 2022-09- Construction of Campong IBRD / 92710 Infrastructure Post Request for Bids Open - National 0.00 Implement Envelope Envelope 00 08 15 14 13 28 24 Sabala to Sogod Madaya, Development ation process (Non Gannassi, Lanao Del Sur Bank-SPD) PRDP-IB-RARM-TAW-017- Component 2: Request for Pending TAN-008-2021 / Request for Single Stage - One 2021-12- 2022-03- 2022-09- IBRD / 92710 Infrastructure Post Open - National Quotations (Non 120,000.00 0.00 Implement Construction of Kepeng Quotations Envelope 15 28 24 Development Bank-SPD) ation Warehouse with Solar Dryer National PRDP-IB-RARM-TAW-018- Procurement TAN-009-2021 / Component 2: Pending Single Stage - One Document - 1 2021-12- 2021-12- 2022-01- 2022-02- 2022-03- 2022-09- Construction of Kepeng IBRD / 92710 Infrastructure Post Request for Bids Open - National 300,000.00 0.00 Implement Envelope Envelope 08 13 24 13 28 24 Fish Landing with Concrete Development ation process (Non Footbridge Bank-SPD) PRDP-IB-RARM-TAW-019- Component 2: Request for Pending TAN-010-2021 / Request for Single Stage - One 2021-12- 2022-03- 2022-09- IBRD / 92710 Infrastructure Post Open - National Quotations (Non 120,000.00 0.00 Implement Construction of Quotations Envelope 15 28 24 Development Bank-SPD) ation Tongbangkaw Fish Landing National PRDP-IB-RARM-TAW-020- Procurement TAN-011-2021 / Component 2: Pending Single Stage - One Document - 1 2021-12- 2021-12- 2022-01- 2022-02- 2022-03- 2022-09- Construction of Tapian IBRD / 92710 Infrastructure Post Request for Bids Open - National 240,000.00 0.00 Implement Envelope Envelope 08 13 14 13 28 24 Sokah Fish Landing with Development ation process (Non Concrete Footbridge Bank-SPD) Page 2 PRDP-IB-RARM-MAG-019- SOU-002-2021 / Component 2: Request for Pending Request for Single Stage - One 2021-12- 2022-03- 2022-09- Construction of Brgy IBRD / 92710 Infrastructure Post Open - National Quotations (Non 120,000.00 0.00 Implement Quotations Envelope 15 28 24 Romangaob Warehouse Development Bank-SPD) ation with Solar Dryer PRDP-IB-RARM-MAG-020- Component 2: Request for Pending SOU-003-2021 / Request for Single Stage - One 2021-12- 2022-03- 2022-09- IBRD / 92710 Infrastructure Post Open - National Quotations (Non 132,800.00 0.00 Implement Rehabilitation of Brgy. San Quotations Envelope 15 28 24 Development Bank-SPD) ation Jose Water System Level II National PRDP-IB-RARM-MAG-022- Procurement Component 2: Pending NOR-001-2021 / Single Stage - One Document - 1 3,300,000. 2021-12- 2021-12- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Infrastructure Post Request for Bids Open - National 0.00 Implement Concreting of Brgy. Rempes- Envelope Envelope 00 08 15 14 13 28 24 Development ation Darugao-Rempes Farm to process (Non Market Road Bank-SPD) National PRDP-IB-RARM-MAG-023- Component 2: Procurement Pending Single Stage - One 2021-12- 2021-12- 2022-01- 2022-02- 2022-03- 2022-09- DAT-001-2021 / IBRD / 92710 Infrastructure Post Request for Bids Open - National Document - 1 804,000.00 0.00 Implement Envelope 08 15 14 13 28 24 Concreting of Banaba- Development Envelope ation Paitan FMR process (Non Bank-SPD) PRDP-IB-RARM-SUL-003- Component 2: Request for Pending MAI-001-2021 / Request for Single Stage - One 2021-12- 2022-03- 2022-09- IBRD / 92710 Infrastructure Post Open - National Quotations (Non 120,000.00 0.00 Implement Construction of Batu Ugis Quotations Envelope 15 28 24 Development Bank-SPD) ation Warehouse with Solar Drier PRDP-IB-RARM-SUL-004- Component 2: Request for Pending MAI-002-2021 / Request for Single Stage - One 2021-12- 2022-03- 2022-09- IBRD / 92710 Infrastructure Post Open - National Quotations (Non 120,000.00 0.00 Implement Construction of Lapa Quotations Envelope 15 28 24 Development Bank-SPD) ation Warehouse with Solar Drier PRDP-IB-RARM-SUL-005- Component 2: Request for Pending MAI-003-2021 / Request for Single Stage - One 2021-12- 2022-03- 2022-09- IBRD / 92710 Infrastructure Post Open - National Quotations (Non 120,000.00 0.00 Implement Construction of Brgy Quotations Envelope 15 20 16 Development Bank-SPD) ation Lagasan Asibih Warehouse with Solar Dryer PRDP-IB-RARM-SUL-006- Component 2: Request for Pending MAI-004-2021 / Request for Single Stage - One 2021-12- 2022-03- 2022-09- IBRD / 92710 Infrastructure Post Open - National Quotations (Non 120,000.00 0.00 Implement Construction of Laud Kulasi Quotations Envelope 15 28 24 Development Bank-SPD) ation Warehouse with Solar Drier National PRDP-IB-RARM-SUL-007- Procurement Component 2: Pending OMA-001-2021 / Single Stage - One Document - 1 1,600,000. 2021-12- 2021-12- 2022-01- 2022-02- 2022-03- 2022-09- IBRD / 92710 Infrastructure Post Request for Bids Open - National 0.00 Implement Construction of Niangkaan Envelope Envelope 00 08 15 14 13 28 24 Development ation Proper FMR process (Non Bank-SPD) GOODS Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalificatio Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification Recommendation for Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PlannedAwardActual Planned Actual Planned Actual PRDP-PSO-GOODS-001- Pending Component 4: Project Request for Single Stage - One 2021-10- 2021-12- 2021-12- ADM-001-2022-EU / TF / B5756 Post Open - National 60,000.00 0.00 Implementa Implementation Support Quotations Envelope 20 01 16 Laptop Computers tion PRDP-PSO-GOODS-003- Pending Component 4: Project Request for Single Stage - One 2021-10- 2021-12- 2021-12- ADM-003-2022-EU / TF / B5756 Post Open - National 24,000.00 0.00 Implementa Implementation Support Quotations Envelope 20 01 16 Desktop Computer tion PRDP-PSO-GOODS-004- Pending Component 4: Project Request for Single Stage - One 2021-10- 2021-12- 2021-12- ADM-004-2022-EU / TF / B5756 Post Open - National 8,000.00 0.00 Implementa Implementation Support Quotations Envelope 20 01 16 Colored Printer (3in1) A3 tion size PRDP-PSO-GOODS-006- Pending Component 4: Project Request for Single Stage - One 2021-10- 2021-12- 2021-12- ADM-006-2022-EU / TF / B5756 Post Open - National 2,000.00 0.00 Implementa Implementation Support Quotations Envelope 20 01 16 Smartphone 4K tion PRDP-PSO-GOODS-007- Pending Component 4: Project Request for Single Stage - One 2021-11- 2022-01- 2022-07- ADM-007-2022-EU / TF / B5756 Post Open - National 1,400.00 0.00 Implementa Implementation Support Quotations Envelope 20 15 14 GeoPhoto 360 deg tion PRDP-PSO-GOODS-008- Pending Component 4: Project Request for Single Stage - One 2021-10- 2021-12- 2021-12- ADM-008-2022-EU / Rotor TF / B5756 Post Open - National 3,000.00 0.00 Implementa Implementation Support Quotations Envelope 20 01 16 Type Drone tion PRDP-PSO-GOODS-009- Pending Component 4: Project Request for Single Stage - One 2021-10- 2021-12- 2021-12- ADM-009-2022-EU / TF / B5756 Post Open - National 300.00 0.00 Implementa Implementation Support Quotations Envelope 20 01 16 Heavy Duty Multi-paper tion Shredder PRDP-PSO-GOODS-010- Pending Component 4: Project Request for Single Stage - One 2021-10- 2021-12- 2021-12- ADM-010-2022-EU / TF / B5756 Post Open - National 300.00 0.00 Implementa Implementation Support Quotations Envelope 20 01 16 Colored Printer - tion (Continuous Ink) PRDP-PSO-GOODS-011- Pending Component 4: Project Request for Single Stage - One 2021-10- 2021-12- 2021-12- ADM-011-2022-EU / Fax TF / B5756 Post Open - National 600.00 0.00 Implementa Implementation Support Quotations Envelope 20 01 16 Machine tion PRDP-PSO-GOODS-012- Pending Component 4: Project Request for Single Stage - One 2021-10- 2021-12- 2021-12- ADM-012-2022-EU / Laser TF / B5756 Post Open - National 2,000.00 0.00 Implementa Implementation Support Quotations Envelope 20 01 16 Printer (Black) tion PRDP-PSO-GOODS-013- Pending Component 4: Project Request for Single Stage - One 2021-10- 2021-12- 2021-12- ADM-013-2022-EU / TF / B5756 Post Open - National 4,080.00 0.00 Implementa Implementation Support Quotations Envelope 20 01 16 Tablet Device tion PRDP-PSO-GOODS-014- Pending Component 4: Project Request for Single Stage - One 2021-10- 2021-12- 2022-06- ADM-014-2022-EU / Sim TF / B5756 Post Open - National 2,400.00 0.00 Implementa Implementation Support Quotations Envelope 20 15 13 Module for GRM Platform tion PRDP-PSO-GOODS-015- Pending Component 4: Project Request for Single Stage - One 2021-10- 2021-12- 2021-12- ADM-015-2022-EU / TF / B5756 Post Open - National 2,400.00 0.00 Implementa Implementation Support Quotations Envelope 20 01 16 Television 60in tion PRDP-PSO-GOODS-016- Pending Component 4: Project Request for Single Stage - One 2021-10- 2021-12- 2021-12- ADM-016-2022-EU / Steel TF / B5756 Post Open - National 960.00 0.00 Implementa Implementation Support Quotations Envelope 20 01 16 Cabinet lateral 4 drawers tion PRDP-PSO-GOODS-017- Pending ADM-017-2022-EU / Component 4: Project Request for Single Stage - One 2021-10- 2021-12- 2021-12- TF / B5756 Post Open - National 1,200.00 0.00 Implementa Container Van (including Implementation Support Quotations Envelope 20 01 16 tion installation/freight charges) PRDP-PSO-GOODS-018- Pending Component 4: Project Request for Single Stage - One 2021-10- 2021-12- 2021-12- ADM-018-2022-EU / TF / B5756 Post Open - National 400.00 0.00 Implementa Implementation Support Quotations Envelope 20 01 16 Vertical Safety Vault tion Cabinet PRDP-PSO-GOODS-019- Pending Component 4: Project Request for Single Stage - One 2021-10- 2021-12- 2021-12- ADM-019-2022-EU / Sala TF / B5756 Post Open - National 800.00 0.00 Implementa Implementation Support Quotations Envelope 20 01 16 Set tion PRDP-PSO-GOODS-020- Pending Component 4: Project Request for Single Stage - One 2021-10- 2021-12- 2021-12- ADM-020-2022-EU / TF / B5756 Post Open - National 2,400.00 0.00 Implementa Implementation Support Quotations Envelope 20 01 16 Refrigerator tion PRDP-PSO-GOODS-021- Pending Component 4: Project Request for Single Stage - One 2021-10- 2021-12- 2021-12- ADM-021-2022-EU / TF / B5756 Post Open - National 1,000.00 0.00 Implementa Implementation Support Quotations Envelope 20 01 16 Condenser USB Microphone tion PRDP-PSO-GOODS-022- Pending Component 4: Project Request for Single Stage - One 2021-10- 2021-12- 2021-12- ADM-022-2022-EU / HDMI TF / B5756 Post Open - National 600.00 0.00 Implementa Implementation Support Quotations Envelope 20 01 16 Splitter tion PRDP-PSO-GOODS-024- Pending Component 4: Project Request for Single Stage - One 2021-10- 2021-12- 2021-12- ADM-024-2022-EU / TF / B5756 Post Open - National 40,000.00 0.00 Implementa Implementation Support Quotations Envelope 20 01 16 Airconditioner Units - tion Refrigerator Type PRDP-PSO-GOODS-025- Pending Component 4: Project Request for Single Stage - One 2021-10- 2021-12- 2021-12- ADM-025-2022-EU / LCD TF / B5756 Post Open - National 1,200.00 0.00 Implementa Implementation Support Quotations Envelope 20 01 16 projector tion PRDP-PSO-GOODS-026- Pending Component 4: Project Request for Single Stage - One 2021-10- 2021-12- 2021-12- ADM-026-2022-EU / TF / B5756 Post Open - National 1,400.00 0.00 Implementa Implementation Support Quotations Envelope 20 01 16 Customized Tent tion PRDP-PSO-GOODS-023- Pending Component 4: Project Request for Single Stage - One 2021-10- 2021-12- 2021-12- ADM-023-2022-EU / TF / B5756 Post Open - National 1,000.00 0.00 Implementa Implementation Support Quotations Envelope 20 01 16 Portable Printer tion NON CONSULTING SERVICES Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalificatio Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification Recommendation for Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PlannedAwardActual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Short List and Draft Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Process Expression of Request for Opening of Technical Evaluation of Description Component Review Type Method Terms of Reference Request for Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Status Interest Notice Proposals as Issued Proposals / Minutes Technical Proposal Proposals Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Process Draft Negotiated Description Component Review Type Method Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Status Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRDP-IS-MIN-IB-001-000- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 2018-AF / Component Implementation Support Implementation 01 11 15 14 Head PRDP-IS-MIN-IB-002-000- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 2018-AF / Irrigation Implementation Support Implementation 01 11 15 14 Specialist PRDP-IS-MIN-IB-003-001- Component 4: Project Under 2018-09- 2020-11- 2018-09- 2018-11- 2019-05- 2018-AF / Roads and IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Implementation Support Implementation 01 20 11 15 14 Bridges Specialist PRDP-IS-MIN-IB-003-002- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 2018-AF / Roads and IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Implementation Support Implementation 01 11 15 14 Bridges Specialist PRDP-IS-MIN-IB-003-003- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 2018-AF / Roads and IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Implementation Support Implementation 01 11 15 14 Bridges Specialist PRDP-IS-MIN-IB-003-004- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 2018-AF / Roads and IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Implementation Support Implementation 01 11 15 14 Bridges Specialist PRDP-IS-MIN-IB-004-000- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 2018-AF / Water Specialist Implementation Support Implementation 01 11 15 14 PRDP-IS-MIN-IB-005-000- Component 4: Project Under 2018-09- 2020-11- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 6,352.94 0.00 2018-AF / Rural Infa Implementation Support Implementation 01 20 11 15 14 Engineer PRDP-IS-MIN-IB-006-000- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 4,235.29 0.00 Implementation Support Implementation 01 11 15 14 Development Associate PRDP-IS-MIN-IB-007-000- Individual 2018-AF / Technical Component 4: Project Pending 2018-09- 2018-10- 2018-11- 2018-12- 2019-06- IBRD / 84210 Post Consultant Open 11,764.71 0.00 Consultant for the O & M Implementation Support Implementation 01 20 10 15 13 Selection completed SPs PRDP-IS-MIN-OPD-001- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 000-2018-AF / Executive IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Implementation Support Implementation 01 11 15 14 Assistant PRDP-IS-MIN-OPD-002- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 000-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 4,235.29 0.00 Implementation Support Implementation 01 11 15 14 Development Associate PRDP-IS-MIN-ODPD-001- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 000-2018-AF / Executive IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Implementation Support Implementation 01 11 15 14 Assistant PRDP-IS-MIN-ODPD-002- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 000-2018-AF / Economist Implementation Support Implementation 01 11 15 14 PRDP-IS-MIN-ODPD-003- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 000-2018-AF / Assistant IBRD / 84210 Post Direct Selection Direct 6,352.94 0.00 Implementation Support Implementation 01 11 15 14 Economist Page 3 PRDP-IS-MIN-ODPD-004- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 000-2018-AF / Writer Implementation Support Implementation 01 11 15 14 PRDP-IS-MIN-FIN-001- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 000-2018-AF / Finance Implementation Support Implementation 01 11 15 14 Unit Head PRDP-IS-MIN-FIN-002- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 000-2018-AF / LGU Implementation Support Implementation 01 11 15 14 Finance PRDP-IS-MIN-FIN-003- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 000-2018-AF / Budget Implementation Support Implementation 01 11 15 14 Specialist PRDP-IS-MIN-FIN-004- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 001-2018-AF / Finance Implementation Support Implementation 01 11 15 14 Specialist PRDP-IS-MIN-FIN-004- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 002-2018-AF / Finance Implementation Support Implementation 01 11 15 14 Specialist PRDP-IS-MIN-FIN-004- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 003-2018-AF / Finance Implementation Support Implementation 01 11 15 14 Specialist PRDP-IS-MIN-FIN-004- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 004-2018-AF / Finance Implementation Support Implementation 01 11 15 14 Specialist PRDP-IS-MIN-FIN-005- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 001-2018-AF / Finance Implementation Support Implementation 01 11 15 14 Analyst PRDP-IS-MIN-FIN-005- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 002-2018-AF / Finance Implementation Support Implementation 01 11 15 14 Analyst PRDP-IS-MIN-FIN-006- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 000-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 4,235.29 0.00 Implementation Support Implementation 01 11 15 14 Development Associate PRDP-IS-MIN-PRO-001- Component 4: Project Under 2018-09- 2020-11- 2018-09- 2018-11- 2019-05- 000-2018-AF / IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Implementation Support Implementation 01 20 11 15 14 Procurement Unit Head PRDP-IS-MIN-PRO-002- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 000-2018-AF / IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Implementation Support Implementation 01 11 15 14 Procurement Specialist PRDP-IS-MIN-PRO-003- Component 4: Project Under 2018-09- 2020-11- 2018-09- 2018-11- 2019-05- 000-2018-AF / IBRD / 84210 Post Direct Selection Direct 6,352.94 0.00 Implementation Support Implementation 01 20 11 15 14 Procurement Officer PRDP-IS-MIN-PRO-004- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 001-2018-AF / Associate IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Implementation Support Implementation 01 11 15 14 Procurement Officer PRDP-IS-MIN-PRO-005- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 000-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 4,235.29 0.00 Implementation Support Implementation 01 11 15 14 Development Associate PRDP-IS-MIN-MAE-001- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 000-2018-AF / M&E Unit Implementation Support Implementation 01 11 15 14 Head PRDP-IS-MIN-MAE-002- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 001-2018-AF / M&E Implementation Support Implementation 01 11 15 14 Specialist PRDP-IS-MIN-MAE-002- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 002-2018-AF / M&E Implementation Support Implementation 01 11 15 14 Specialist PRDP-IS-MIN-MAE-002- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 003-2018-AF / M&E Implementation Support Implementation 01 11 15 14 Specialist PRDP-IS-MIN-MAE-003- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 6,352.94 0.00 000-2018-AF / M&E Implementation Support Implementation 01 11 15 14 Officer PRDP-IS-MIN-MAE-004- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 000-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 4,235.29 0.00 Implementation Support Implementation 01 11 15 14 Development Associate PRDP-IS-MIN-SES-001- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 000-2018-AF / SES Unit Implementation Support Implementation 01 11 15 14 Head PRDP-IS-MIN-SES-002- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 000-2018-AF / Social IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Implementation Support Implementation 01 11 15 14 Safeguard Specialist PRDP-IS-MIN-SES-003- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 000-2018-AF / IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Implementation Support Implementation 01 11 15 14 Environmental Safeguards Specialist PRDP-IS-MIN-SES-004- Component 4: Project Under 2018-09- 2020-11- 2018-09- 2018-11- 2019-05- 000-2018-AF / IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Implementation Support Implementation 01 20 11 15 14 Environmental Safeguards Officer PRDP-IS-MIN-SES-005- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 001-2018-AF / Social IBRD / 84210 Post Direct Selection Direct 6,352.94 0.00 Implementation Support Implementation 01 11 15 14 Safeguard Officer PRDP-IS-MIN-SES-005- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 002-2018-AF / Social IBRD / 84210 Post Direct Selection Direct 6,352.94 0.00 Implementation Support Implementation 01 11 15 14 Safeguard Officer PRDP-IS-MIN-SES-006- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 6,352.94 0.00 000-2018-AF / Grievance Implementation Support Implementation 01 11 15 14 Officer PRDP-IS-MIN-SES-007- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 000-2018-AF / IBRD / 84210 Post Direct Selection Direct 6,352.94 0.00 Implementation Support Implementation 01 11 15 14 Environmental Safeguard Officer PRDP-IS-MIN-GGU-001- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 000-2018-AF / IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Implementation Support Implementation 01 11 15 14 Geomapping and Governance Unit Head PRDP-IS-MIN-GGU-002- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 000-2018-AF / GIS Data Implementation Support Implementation 01 11 15 14 Specialist PRDP-IS-MIN-GGU-003- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 6,352.94 0.00 000-2018-AF / GIS Data Implementation Support Implementation 01 11 15 14 Officer PRDP-IS-MIN-GGU-004- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 000-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 4,235.29 0.00 Implementation Support Implementation 01 11 15 14 Development Associate PRDP-IS-MIN-INF-001- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 000-2018-AF / Info Ace Implementation Support Implementation 01 11 15 14 Unit Head PRDP-IS-MIN-INF-002- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 000-2018-AF / Info & IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Implementation Support Implementation 01 11 15 14 Advocacy Specialist PRDP-IS-MIN-INF-003- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 000-2018-AF / Info & IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Implementation Support Implementation 01 11 15 14 Technology Specialist PRDP-IS-MIN-ADM-001- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 000-2018-AF / Admin Unit Implementation Support Implementation 01 11 15 14 Head PRDP-IS-MIN-ADM-002- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 000-2018-AF / Admin Implementation Support Implementation 01 11 15 14 Officer III PRDP-IS-MIN-ADM-003- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 000-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 4,235.29 0.00 Implementation Support Implementation 01 11 15 14 Development Associate PRDP-IS-MIN-ADM-005- Component 4: Project Pending 2018-09- 2018-09- 2018-11- 2019-05- 000-2018-AF / Admin IBRD / 84210 Post Direct Selection Direct 2,823.53 0.00 Implementation Support Implementation 01 11 15 14 Staff/Computer Maintenance PRDP-IS-MIN-003-IB-003- Component 2: Individual Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 2019-AF / Rural IBRD / 88160 Infrastructure Post Consultant Open 13,585.00 0.00 Implementation 02 21 11 16 12 Infrastructure Specialist Development Selection PRDP-IS-MIN-004-IB-004- Component 2: Individual Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 2019-AF / Rural IBRD / 88160 Infrastructure Post Consultant Open 13,585.00 0.00 Implementation 02 21 11 16 12 Infrastructure Specialist Development Selection PRDP-IS-MIN-005-IB-005- Component 2: Individual Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 2019-AF / Rural IBRD / 88160 Infrastructure Post Consultant Open 13,585.00 0.00 Implementation 02 21 11 16 12 Infrastructure Specialist Development Selection PRDP-IS-MIN-007-IB-007- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 2019-AF / Program IBRD / 88160 Post Consultant Open 8,151.00 0.00 Implementation Support Implementation 02 21 11 16 12 Development Associate Selection PRDP-IS-MIN-008-OPD- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / IBRD / 88160 Post Consultant Open 6,792.00 0.00 Implementation Support Implementation 02 21 11 16 12 Administrative Officer I Selection PRDP-IS-MIN-009-DPD- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / IBRD / 88160 Post Consultant Open 13,585.00 0.00 Implementation Support Implementation 02 21 11 16 12 Compliance/Legal Officer Selection PRDP-IS-MIN-010-DPD- Individual Component 4: Project Under 2019-04- 2020-11- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / IBRD / 88160 Post Consultant Open 8,151.00 0.00 Implementation Support Implementation 02 20 21 11 16 12 Administrative Officer II Selection PRDP-IS-MIN-011-DPD- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / IBRD / 88160 Post Consultant Open 6,792.00 0.00 Implementation Support Implementation 02 21 11 16 12 Administrative Officer II Selection Individual PRDP-IS-MIN-013-DPD- Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- IBRD / 88160 Post Consultant Open 12,226.00 0.00 001-2019-AF / Economist Implementation Support Implementation 02 21 11 16 12 Selection PRDP-IS-MIN-016-DPD- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / IBRD / 88160 Post Consultant Open 13,585.00 0.00 Implementation Support Implementation 02 21 11 16 12 Information Specialist Selection Individual PRDP-IS-MIN-017-DPD- Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- IBRD / 88160 Post Consultant Open 10,868.00 0.00 001-2019-AF / Writer Implementation Support Implementation 02 21 11 16 12 Selection PRDP-IS-MIN-018-DPD- Individual Component 4: Project Under 2019-04- 2020-11- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Media IBRD / 88160 Post Consultant Open 9,509.00 0.00 Implementation Support Implementation 02 20 21 11 16 12 Production Officer Selection PRDP-IS-MIN-034-FIN- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Finance IBRD / 88160 Post Consultant Open 13,585.00 0.00 Implementation Support Implementation 02 21 11 16 12 Analyst III Selection PRDP-IS-MIN-035-FIN- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Finance IBRD / 88160 Post Consultant Open 13,585.00 0.00 Implementation Support Implementation 02 21 11 16 12 Analyst III Selection PRDP-IS-MIN-039-FIN- Component 4: Project Under 2019-01- 2020-11- 2019-01- 2019-03- 2019-09- IBRD / 88160 Post Direct Selection Direct 12,226.00 0.00 001-2019-AF / Finance Implementation Support Implementation 03 20 13 19 15 Analyst II PRDP-IS-MIN-044-MNE- Component 4: Project Pending 2019-01- 2019-01- 2019-03- 2019-09- IBRD / 88160 Post Direct Selection Direct 12,226.00 0.00 001-2019-AF / M&E Implementation Support Implementation 03 13 19 15 Officer PRDP-IS-MIN-047-PRO- Component 4: Project Under 2019-01- 2020-11- 2019-01- 2019-03- 2019-09- 001-2019-AF / IBRD / 88160 Post Direct Selection Direct 12,226.00 0.00 Implementation Support Implementation 03 20 13 19 15 Procurement Officer PRDP-IS-MIN-050-SES- 001-2019-AF / Social and Component 4: Project Under 2019-01- 2020-11- 2019-01- 2019-03- 2019-09- IBRD / 88160 Post Direct Selection Direct 17,660.00 0.00 Environmental Safeguards Implementation Support Implementation 03 20 13 19 15 Unit Head PRDP-IS-MIN-052-SES- 001-2019-AF / Social and Component 4: Project Under 2019-01- 2019-01- 2019-03- 2019-09- IBRD / 88160 Post Direct Selection Direct 12,226.00 0.00 Environmental Safeguards Implementation Support Implementation 03 13 19 15 Officer PRDP-IS-MIN-055-R009- Component 2: Individual Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Rural IBRD / 88160 Infrastructure Post Consultant Open 10,868.00 0.00 Implementation 02 21 11 16 12 Infrastructure Engineer Development Selection PRDP-IS-MIN-056-R009- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Program IBRD / 88160 Post Consultant Open 6,792.00 0.00 Implementation Support Implementation 02 21 11 16 12 Development Associate Selection Page 4 PRDP-IS-MIN-062-R009- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Budget IBRD / 88160 Post Consultant Open 9,509.00 0.00 Implementation Support Implementation 02 21 11 16 12 Analyst I Selection PRDP-IS-MIN-065-R009- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Associate IBRD / 88160 Post Consultant Open 9,509.00 0.00 Implementation Support Implementation 02 21 11 16 12 SES Officer Selection PRDP-IS-MIN-068-R010- Component 4: Project Pending 2019-01- 2019-01- 2019-03- 2019-09- 001-2019-AF / Program IBRD / 88160 Post Direct Selection Direct 6,792.00 0.00 Implementation Support Implementation 03 13 19 15 Development Associate Individual PRDP-IS-MIN-069-R010- Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- IBRD / 88160 Post Consultant Open 9,509.00 0.00 001-2019-AF / Writer Implementation Support Implementation 02 21 11 16 12 Selection PRDP-IS-MIN-076-R010- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Project IBRD / 88160 Post Consultant Open 6,792.00 0.00 Implementation Support Implementation 02 21 11 16 12 Development Associate- Selection DPD PRDP-IS-MIN-077-R010- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Project IBRD / 88160 Post Consultant Open 6,792.00 0.00 Implementation Support Implementation 02 21 11 16 12 Development Associate- Selection DPD PRDP-IS-MIN-078-R010- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Project IBRD / 88160 Post Consultant Open 6,792.00 0.00 Implementation Support Implementation 02 21 11 16 12 Development Associate- Selection DPD PRDP-IS-MIN-079-R010- Component 4: Project Pending 2019-01- 2019-01- 2019-03- 2019-09- IBRD / 88160 Post Direct Selection Direct 9,509.00 0.00 001-2019-AF / Finance Implementation Support Implementation 03 13 19 15 Analyst I PRDP-IS-MIN-083-R010- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Associate IBRD / 88160 Post Consultant Open 9,509.00 0.00 Implementation Support Implementation 02 21 11 16 12 Procurement Officer Selection PRDP-IS-MIN-084-R010- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Associate IBRD / 88160 Post Consultant Open 9,509.00 0.00 Implementation Support Implementation 02 21 11 16 12 SES Officer Selection PRDP-IS-MIN-085-R011- Component 2: Individual Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Rural IBRD / 88160 Infrastructure Post Consultant Open 12,226.00 0.00 Implementation 02 21 11 16 12 Infrastructure Specialist Development Selection Individual PRDP-IS-MIN-093-R011- Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- IBRD / 88160 Post Consultant Open 10,868.00 0.00 001-2019-AF / Economist Implementation Support Implementation 02 21 11 16 12 Selection PRDP-IS-MIN-095-R011- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Finance IBRD / 88160 Post Consultant Open 9,509.00 0.00 Implementation Support Implementation 02 21 11 16 12 Analyst I Selection PRDP-IS-MIN-096-R011- Component 4: Project Pending 2019-01- 2019-01- 2019-03- 2019-09- IBRD / 88160 Post Direct Selection Direct 10,868.00 0.00 001-2019-AF / GIS Officer Implementation Support Implementation 03 13 19 15 PRDP-IS-MIN-098-R011- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Monitoring IBRD / 88160 Post Consultant Open 10,868.00 0.00 Implementation Support Implementation 02 21 11 16 12 and Evaluation Officer Selection PRDP-IS-MIN-099-R011- Individual 001-2019-AF / Associate Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- IBRD / 88160 Post Consultant Open 9,509.00 0.00 Monitoring and Evaluation Implementation Support Implementation 02 21 11 16 12 Selection Officer PRDP-IS-MIN-101-R011- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Associate IBRD / 88160 Post Consultant Open 9,509.00 0.00 Implementation Support Implementation 02 21 11 16 12 Procurement Officer Selection PRDP-IS-MIN-102-R011- Individual 001-2019-AF / Social and Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- IBRD / 88160 Post Consultant Open 10,868.00 0.00 Environmental Safeguards Implementation Support Implementation 02 21 11 16 12 Selection Officer PRDP-IS-MIN-103-R011- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Associate IBRD / 88160 Post Consultant Open 9,509.00 0.00 Implementation Support Implementation 02 21 11 16 12 SES Officer Selection PRDP-IS-MIN-110-R012- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Program IBRD / 88160 Post Consultant Open 6,792.00 0.00 Implementation Support Implementation 02 21 11 16 12 Development Associate Selection PRDP-IS-MIN-111-R012- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / IBRD / 88160 Post Consultant Open 6,792.00 0.00 Implementation Support Implementation 02 21 11 16 12 Administrative Officer II Selection PRDP-IS-MIN-116-R012- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Budget IBRD / 88160 Post Consultant Open 9,509.00 0.00 Implementation Support Implementation 02 21 11 16 12 Analyst I Selection Individual PRDP-IS-MIN-117-R012- Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- IBRD / 88160 Post Consultant Open 10,868.00 0.00 001-2019-AF / Economist Implementation Support Implementation 02 21 11 16 12 Selection PRDP-IS-MIN-118-R012- Component 4: Project Pending 2019-01- 2019-01- 2019-03- 2019-09- IBRD / 88160 Post Direct Selection Direct 9,509.00 0.00 001-2019-AF / Finance Implementation Support Implementation 03 13 19 15 Analyst I Individual PRDP-IS-MIN-120-R012- Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- IBRD / 88160 Post Consultant Open 10,868.00 0.00 001-2019-AF / GIS Officer Implementation Support Implementation 02 21 11 16 12 Selection PRDP-IS-MIN-121-R012- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Associate IBRD / 88160 Post Consultant Open 9,509.00 0.00 Implementation Support Implementation 02 21 11 16 12 M&E Officer Selection PRDP-IS-MIN-122-R012- Individual 001-2019-AF / Social and Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- IBRD / 88160 Post Consultant Open 10,868.00 0.00 Environmental Safeguards Implementation Support Implementation 02 21 11 16 12 Selection Officer PRDP-IS-MIN-123-R012- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Associate IBRD / 88160 Post Consultant Open 9,509.00 0.00 Implementation Support Implementation 02 21 11 16 12 SES Officer Selection Individual PRDP-IS-MIN-136-R013- Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- IBRD / 88160 Post Consultant Open 10,868.00 0.00 001-2019-AF / GIS Officer Implementation Support Implementation 02 21 11 16 12 Selection PRDP-IS-MIN-138-R013- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Associate IBRD / 88160 Post Consultant Open 9,509.00 0.00 Implementation Support Implementation 02 21 11 16 12 M&E Officer Selection PRDP-IS-MIN-139-R013- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Associate IBRD / 88160 Post Consultant Open 9,509.00 0.00 Implementation Support Implementation 02 21 11 16 12 Procurement Officer Selection PRDP-IS-MIN-141-R013- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Associate IBRD / 88160 Post Consultant Open 9,509.00 0.00 Implementation Support Implementation 02 21 11 16 12 SES Officer Selection PRDP-IS-MIN-146-ARMM- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Budget IBRD / 88160 Post Consultant Open 9,509.00 0.00 Implementation Support Implementation 02 21 11 16 12 Analyst I Selection PRDP-IS-MIN-149-ARMM- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Finance IBRD / 88160 Post Consultant Open 19,019.00 0.00 Implementation Support Implementation 02 21 11 16 12 Analyst I Selection Individual PRDP-IS-MIN-150-ARMM- Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- IBRD / 88160 Post Consultant Open 10,868.00 0.00 001-2019-AF / GIS Officer Implementation Support Implementation 02 21 11 16 12 Selection PRDP-IS-MIN-151-ARMM- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Budget IBRD / 88160 Post Consultant Open 12,226.00 0.00 Implementation Support Implementation 02 21 11 16 12 Analyst I Selection PRDP-IS-MIN-152-ARMM- Component 2: Individual Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Rural IBRD / 88160 Infrastructure Post Consultant Open 10,868.00 0.00 Implementation 02 21 11 16 12 Infrastructure Engineer Development Selection PRDP-IS-MIN-153-ARMM- Component 2: Individual Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Rural IBRD / 88160 Infrastructure Post Consultant Open 10,868.00 0.00 Implementation 02 21 11 16 12 Infrastructure Engineer Development Selection PRDP-IS-MIN-154-ARMM- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Project IBRD / 88160 Post Consultant Open 6,792.00 0.00 Implementation Support Implementation 02 21 11 16 12 Development Associate Selection PRDP-IS-MIN-156-ARMM- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Monitoring IBRD / 88160 Post Consultant Open 10,868.00 0.00 Implementation Support Implementation 02 21 11 16 12 and Evaluation Officer Selection PRDP-IS-MIN-157-ARMM- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Associate IBRD / 88160 Post Consultant Open 9,509.00 0.00 Implementation Support Implementation 02 21 11 16 12 M&E Officer Selection PRDP-IS-MIN-159-ARMM- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Associate IBRD / 88160 Post Consultant Open 9,509.00 0.00 Implementation Support Implementation 02 21 11 16 12 Procurement Officer Selection PRDP-IS-MIN-160-ARMM- Individual 001-2019-AF / Social and Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- IBRD / 88160 Post Consultant Open 10,868.00 0.00 Environmental Safeguards Implementation Support Implementation 02 21 11 16 12 Selection Officer PRDP-IS-MIN-161-ARMM- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2019-AF / Associate IBRD / 88160 Post Consultant Open 9,509.00 0.00 Implementation Support Implementation 02 21 11 16 12 SES Officer Selection PRDP-MIN-001-IB-001- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / I-Build IBRD / 88160 Infrastructure Post Consultant Direct 19,800.00 0.00 Implementation 02 12 02 08 04 Component Head Development Selection PRDP-MIN-002-IB-001- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Rural IBRD / 88160 Infrastructure Post Consultant Direct 14,200.00 0.00 Implementation 02 12 02 08 04 Infrastructure Specialists Development Selection PRDP-MIN-003-IB-001- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Rural IBRD / 88160 Infrastructure Post Consultant Direct 14,200.00 0.00 Implementation 02 12 02 08 04 Infrastructure Specialists Development Selection PRDP-MIN-004-IB-001- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Rural IBRD / 88160 Infrastructure Post Consultant Direct 14,200.00 0.00 Implementation 02 12 02 08 04 Infrastructure Specialists Development Selection PRDP-MIN-005-IB-001- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Rural IBRD / 88160 Infrastructure Post Consultant Direct 14,200.00 0.00 Implementation 02 12 02 08 04 Infrastructure Specialists Development Selection PRDP-MIN-006-IB-001- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Rural IBRD / 88160 Infrastructure Post Consultant Direct 14,200.00 0.00 Implementation 02 12 02 08 04 Infrastructure Specialists Development Selection PRDP-MIN-007-IB-001- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Rural IBRD / 88160 Infrastructure Post Consultant Direct 12,800.00 0.00 Implementation 02 12 02 08 04 Infrastructure Engineer Development Selection PRDP-MIN-008-IB-001- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Project Dev't. IBRD / 88160 Post Consultant Direct 8,500.00 0.00 Implementation Support Implementation 02 12 02 08 04 Associate Selection PRDP-MIN-009-ADM-001- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Administrative IBRD / 88160 Post Consultant Direct 8,500.00 0.00 Implementation Support Implementation 02 12 02 08 04 Officer I Selection PRDP-MIN-010-DPD-001- Individual Component 4: Project Under 2020-01- 2020-11- 2020-02- 2020-03- 2020-04- 2020-10- 2020-AF / IBRD / 88160 Post Consultant Open 14,200.00 0.00 Implementation Support Implementation 02 20 20 12 16 13 Compliance/Legal Officer Selection PRDP-MIN-011-DPD-001- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 2020-AF / Administrative IBRD / 88160 Post Consultant Open 8,500.00 0.00 Implementation Support Implementation 02 21 11 16 12 Officer II Selection PRDP-MIN-012-DPD-001- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Administrative IBRD / 88160 Post Consultant Direct 7,100.00 0.00 Implementation Support Implementation 02 12 02 08 04 Officer I Selection Individual PRDP-MIN-013-DPD-001- Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 12,800.00 0.00 2020-AF / Economist Implementation Support Implementation 02 12 02 08 04 Selection Page 5 Individual PRDP-MIN-014-DPD-001- Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 12,800.00 0.00 2020-AF / Economist Implementation Support Implementation 02 12 02 08 04 Selection Individual PRDP-MIN-015-DPD-001- Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 12,800.00 0.00 2020-AF / GIS Officer Implementation Support Implementation 02 12 02 08 04 Selection Individual PRDP-MIN-016-DPD-001- Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 12,800.00 0.00 2020-AF / GIS Officer Implementation Support Implementation 02 12 02 08 04 Selection PRDP-MIN-017-DPD-001- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Information IBRD / 88160 Post Consultant Direct 14,200.00 0.00 Implementation Support Implementation 02 12 02 08 04 Specialist Selection Individual PRDP-MIN-018-DPD-001- Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,300.00 0.00 2020-AF / Writer Implementation Support Implementation 02 12 02 08 04 Selection PRDP-MIN-019-DPD-001- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-04- 2019-10- 2020-AF / Media IBRD / 88160 Post Consultant Open 9,900.00 0.00 Implementation Support Implementation 03 21 14 18 15 Production Officer Selection PRDP-MIN-020-DPD-001- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Finance Unit IBRD / 88160 Post Consultant Direct 18,400.00 0.00 Implementation Support Implementation 02 12 02 08 04 Head Selection PRDP-MIN-021-DPD-001- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Finance Analyst IBRD / 88160 Post Consultant Direct 14,200.00 0.00 Implementation Support Implementation 02 12 02 08 04 III/Finance Specialist Selection PRDP-MIN-022-DPD-001- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Finance Analyst IBRD / 88160 Post Consultant Direct 14,200.00 0.00 Implementation Support Implementation 02 12 02 08 04 III/Finance Specialist Selection PRDP-MIN-023-DPD-001- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Finance Analyst IBRD / 88160 Post Consultant Direct 12,800.00 0.00 Implementation Support Implementation 02 12 02 08 04 II Selection PRDP-MIN-024-DPD-001- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Finance Analyst IBRD / 88160 Post Consultant Direct 12,800.00 0.00 Implementation Support Implementation 02 12 02 08 04 II Selection PRDP-MIN-025-DPD-001- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Finance Analyst IBRD / 88160 Post Consultant Direct 11,300.00 0.00 Implementation Support Implementation 02 12 02 08 04 I Selection PRDP-MIN-026-DPD-001- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Finance Analyst IBRD / 88160 Post Consultant Direct 12,800.00 0.00 Implementation Support Implementation 02 12 02 08 04 II Selection Individual PRDP-MIN-027-DPD-001- Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,300.00 0.00 2020-AF / Budget Analyst Implementation Support Implementation 02 12 02 08 04 Selection PRDP-MIN-028-DPD-001- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Procurement IBRD / 88160 Post Consultant Direct 18,400.00 0.00 Implementation Support Implementation 02 12 02 08 04 Unit Head Selection PRDP-MIN-029-DPD-001- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Procurement IBRD / 88160 Post Consultant Direct 12,800.00 0.00 Implementation Support Implementation 02 12 02 08 04 Officer Selection PRDP-MIN-030-DPD-001- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Procurement IBRD / 88160 Post Consultant Direct 12,800.00 0.00 Implementation Support Implementation 02 12 02 08 04 Officer Selection PRDP-MIN-031-DPD-001- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Associate IBRD / 88160 Post Consultant Direct 11,300.00 0.00 Implementation Support Implementation 02 12 02 08 04 Procurement Officer Selection Individual PRDP-MIN-032-DPD-001- Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 18,400.00 0.00 2020-AF / M&E Unit Head Implementation Support Implementation 02 20 12 02 08 04 Selection Individual PRDP-MIN-033-DPD-001- Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 12,800.00 0.00 2020-AF / M&E Officer Implementation Support Implementation 02 12 02 08 04 Selection Individual PRDP-MIN-034-DPD-001- Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 12,800.00 0.00 2020-AF / M&E Officer Implementation Support Implementation 02 12 02 08 04 Selection Individual PRDP-MIN-035-DPD-001- Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 18,400.00 0.00 2020-AF / SES Unit Head Implementation Support Implementation 02 12 02 08 04 Selection PRDP-MIN-036-DPD-001- Individual 2020-AF / Social and Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 12,800.00 0.00 Environmental Safegeuards Implementation Support Implementation 02 12 02 08 04 Selection Officer PRDP-MIN-037-DPD-001- Individual 2020-AF / Social and Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 12,800.00 0.00 Environmental Safegeuards Implementation Support Implementation 02 12 02 08 04 Selection Officer PRDP-MIN-038-DPD-001- Individual Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Admin Unit IBRD / 88160 Post Consultant Direct 18,400.00 0.00 Implementation Support Implementation 02 20 12 02 08 04 Head Selection PRDP-MIN-039-DPD-001- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Administrative IBRD / 88160 Post Consultant Direct 8,500.00 0.00 Implementation Support Implementation 02 12 02 08 04 Officer II Selection PRDP-MIN-R009-001-IB- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Rural IBRD / 88160 Infrastructure Post Consultant Direct 11,300.00 0.00 Implementation 02 12 02 08 04 Infrastructure Engineer Development Selection PRDP-MIN-R009-002-IB- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Rural IBRD / 88160 Infrastructure Post Consultant Direct 11,300.00 0.00 Implementation 02 12 02 08 04 Infrastructure Engineer Development Selection PRDP-MIN-R009-003-IB- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Rural IBRD / 88160 Infrastructure Post Consultant Direct 11,300.00 0.00 Implementation 02 12 02 08 04 Infrastructure Engineer Development Selection PRDP-MIN-R009-004-IB- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Project IBRD / 88160 Post Consultant Direct 7,100.00 0.00 Implementation Support Implementation 02 12 02 08 04 Development Associate Selection PRDP-MIN-R009-005-IB- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Budget IBRD / 88160 Post Consultant Direct 9,900.00 0.00 Implementation Support Implementation 02 12 02 08 04 Analyst I Selection Individual PRDP-MIN-R009-006-IB- Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,300.00 0.00 001-2020-AF / GIS Officer Implementation Support Implementation 02 12 02 08 04 Selection PRDP-MIN-R009-007-IB- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,900.00 0.00 Implementation Support Implementation 02 12 02 08 04 Procurement Officer Selection PRDP-MIN-R009-008-IB- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,900.00 0.00 Implementation Support Implementation 02 12 02 08 04 SES Officer Selection PRDP-MIN-R010-001-IB- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Rural IBRD / 88160 Infrastructure Post Consultant Direct 11,300.00 0.00 Implementation 02 12 02 08 04 Infrastructure Engineer Development Selection PRDP-MIN-R010-002-IB- Component 2: Individual Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Rural IBRD / 88160 Infrastructure Post Consultant Direct 11,300.00 0.00 Implementation 02 12 02 08 04 Infrastructure Engineer Development Selection PRDP-MIN-R010-003-IB- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Project IBRD / 88160 Post Consultant Direct 7,100.00 0.00 Implementation Support Implementation 02 12 02 08 04 Development Associate Selection Individual PRDP-MIN-R010-004-IB- Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 9,900.00 0.00 001-2020-AF / Writer Implementation Support Implementation 02 20 12 02 08 04 Selection Individual PRDP-MIN-R010-005-IB- Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,300.00 0.00 001-2020-AF / Economist Implementation Support Implementation 02 12 02 08 04 Selection PRDP-MIN-R010-006-IB- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Project IBRD / 88160 Infrastructure Post Consultant Direct 7,100.00 0.00 Implementation 02 12 02 08 04 Development Associate Development Selection PRDP-MIN-R010-007-IB- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Project IBRD / 88160 Post Consultant Direct 7,100.00 0.00 Implementation Support Implementation 02 12 02 08 04 Development Associate Selection PRDP-MIN-R010-008-IB- Component 2: Individual Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Project IBRD / 88160 Infrastructure Post Consultant Direct 7,100.00 0.00 Implementation 02 20 12 02 08 04 Development Associate Development Selection PRDP-MIN-R010-009-IB- Individual Component 4: Project Pending 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- 001-2020-AF / Finance IBRD / 88160 Post Consultant Open 9,900.00 0.00 Implementation Support Implementation 02 21 11 16 12 Analyst I Selection PRDP-MIN-R010-010-IB- Individual Component 4: Project Under 2019-04- 2020-11- 2019-05- 2019-06- 2019-07- 2020-01- 001-2020-AF / Finance IBRD / 88160 Post Consultant Open 9,900.00 0.00 Implementation Support Implementation 02 20 21 11 16 12 Analyst I Selection Individual PRDP-MIN-R010-01-IB- Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,300.00 0.00 001-2020-AF / GIS Officer Implementation Support Implementation 02 12 02 08 04 Selection Individual PRDP-MIN-R010-012-IB- Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,300.00 0.00 001-2020-AF / GIS Officer Implementation Support Implementation 02 12 02 08 04 Selection PRDP-MIN-R010-013-IB- Individual Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,900.00 0.00 Implementation Support Implementation 02 20 12 02 08 04 Procurement Officer Selection PRDP-MIN-R010-014-IB- Individual Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,900.00 0.00 Implementation Support Implementation 02 20 12 02 08 04 SES Officer Selection PRDP-MIN-R011-00-IB- Component 2: Individual Pending 2020-03- 2020-04- 2020-05- 2020-06- 2020-12- 001-2020-AF / Rural IBRD / 88160 Infrastructure Post Consultant Open 12,800.00 0.00 Implementation 02 20 11 15 12 Infrastructure Specialist Development Selection PRDP-MIN-R011-002-IB- Component 2: Individual Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Rural IBRD / 88160 Infrastructure Post Consultant Direct 11,300.00 0.00 Implementation 02 28 12 02 08 04 Infrastructure Engineer Development Selection PRDP-MIN-R011-003-IB- Component 2: Individual Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Rural IBRD / 88160 Infrastructure Post Consultant Direct 11,300.00 0.00 Implementation 02 28 12 02 08 04 Infrastructure Engineer Development Selection PRDP-MIN-R011-004-IB- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Project IBRD / 88160 Post Consultant Direct 7,100.00 0.00 Implementation Support Implementation 02 12 02 08 04 Development Assistant Selection PRDP-MIN-R011-005-IB- Component 2: Individual Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Budget IBRD / 88160 Infrastructure Post Consultant Direct 9,900.00 0.00 Implementation 02 28 12 02 08 04 Analyst Development Selection Individual PRDP-MIN-R011-006-IB- Component 4: Project Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,300.00 0.00 001-2020-AF / Economist Implementation Support Implementation 02 28 12 02 08 04 Selection Individual PRDP-MIN-R011-008-IB- Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,300.00 0.00 001-2020-AF / GIS Officer Implementation Support Implementation 02 12 02 08 04 Selection PRDP-MIN-R011-009-IB- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / M&E IBRD / 88160 Post Consultant Direct 11,300.00 0.00 Implementation Support Implementation 02 12 02 08 04 Officer Selection PRDP-MIN-R011-010-IB- Individual Component 4: Project Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / IBRD / 88160 Post Consultant Direct 11,300.00 0.00 Implementation Support Implementation 02 28 12 02 08 04 Procurement Officer Selection Page 6 PRDP-MIN-R011-011-IB- Individual 001-2020-AF / SES Officer Component 4: Project Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,300.00 0.00 (Social Safeguards, Implementation Support Implementation 02 28 12 02 08 04 Selection Environmental Safeguards) PRDP-MIN-R011-012-IB- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,900.00 0.00 Implementation Support Implementation 02 12 02 08 04 SES Officer Selection PRDP-MIN-R012-001-IB- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Rural IBRD / 88160 Infrastructure Post Consultant Direct 11,300.00 0.00 Implementation 02 12 02 08 04 Infrastructure Engineer Development Selection PRDP-MIN-R012-002-IB- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Rural IBRD / 88160 Infrastructure Post Consultant Direct 11,300.00 0.00 Implementation 02 12 02 08 04 Infrastructure Engineer Development Selection PRDP-MIN-R012-003-IB- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Rural IBRD / 88160 Infrastructure Post Consultant Direct 11,300.00 0.00 Implementation 02 12 02 08 04 Infrastructure Engineer Development Selection PRDP-MIN-R012-004-IB- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Project IBRD / 88160 Infrastructure Post Consultant Direct 7,100.00 0.00 Implementation 02 12 02 08 04 Development Assistant Development Selection PRDP-MIN-R012-005-IB- Individual Component 4: Project Pending 2020-03- 2020-04- 2020-05- 2020-06- 2020-12- 001-2020-AF / IBRD / 88160 Post Consultant Open 7,100.00 0.00 Implementation Support Implementation 02 20 11 15 12 Administrative Officer II Selection PRDP-MIN-R012-006-IB- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Budget IBRD / 88160 Post Consultant Direct 9,900.00 0.00 Implementation Support Implementation 02 12 02 08 04 Analyst I Selection PRDP-MIN-R012-007-IB- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Finance IBRD / 88160 Post Consultant Direct 9,900.00 0.00 Implementation Support Implementation 02 12 02 08 04 Analyst I Selection PRDP-MIN-R012-008-IB- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Finance IBRD / 88160 Post Consultant Direct 9,900.00 0.00 Implementation Support Implementation 02 12 02 08 04 Analyst I Selection Individual PRDP-MIN-R012-009-IB- Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,300.00 0.00 001-2020-AF / GIS Officer Implementation Support Implementation 02 12 02 08 04 Selection PRDP-MIN-R012-010-IB- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,900.00 0.00 Implementation Support Implementation 02 12 02 08 04 Procurement Officer Selection PRDP-MIN-R012-011-IB- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,900.00 0.00 Implementation Support Implementation 02 12 02 08 04 M&E Officer Selection PRDP-MIN-R012-012-IB- Individual 001-2020-AF / SES Officer Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,300.00 0.00 (Social Safeguards, Implementation Support Implementation 02 12 02 08 04 Selection Environmental Safeguards) PRDP-MIN-R012-013-IB- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,900.00 0.00 Implementation Support Implementation 02 12 02 08 04 SES Officer Selection PRDP-MIN-R013-001-IB- Component 2: Individual 001-2020-AF / Rural Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Infrastructure Post Consultant Direct 12,800.00 0.00 Infrastructure Specialist Implementation 02 20 12 02 08 04 Development Selection (Roads & Bridges, Water, Irrigation) PRDP-MIN-R013-002-IB- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Rural IBRD / 88160 Infrastructure Post Consultant Direct 11,300.00 0.00 Implementation 02 12 02 08 04 Infrastructure Engineer Development Selection PRDP-MIN-R013-003-IB- Component 2: Individual Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Rural IBRD / 88160 Infrastructure Post Consultant Direct 11,300.00 0.00 Implementation 02 20 12 02 08 04 Infrastructure Engineer Development Selection PRDP-MIN-R013-004-IB- Component 2: Individual Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Rural IBRD / 88160 Infrastructure Post Consultant Direct 11,300.00 0.00 Implementation 02 20 12 02 08 04 Infrastructure Engineer Development Selection PRDP-MIN-R013-005-IB- Individual Component 4: Project Under 2020-03- 2020-11- 2020-04- 2020-05- 2020-06- 2020-12- 001-2020-AF / Project IBRD / 88160 Post Consultant Open 7,100.00 0.00 Implementation Support Implementation 02 20 20 11 15 12 Development Associate Selection PRDP-MIN-R013-006-IB- Individual Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Finance IBRD / 88160 Post Consultant Direct 9,900.00 0.00 Implementation Support Implementation 02 20 12 02 08 04 Analyst I Selection Individual PRDP-MIN-R013-007-IB- Component 4: Project Under 2020-03- 2020-11- 2020-04- 2020-05- 2020-06- 2020-12- IBRD / 88160 Post Consultant Open 11,300.00 0.00 001-2020-AF / GIS Officer Implementation Support Implementation 02 20 20 11 15 12 Selection PRDP-MIN-R013-008-IB- Individual Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / M&E IBRD / 88160 Post Consultant Direct 11,300.00 0.00 Implementation Support Implementation 02 20 12 02 08 04 Officer Selection PRDP-MIN-R013-009-IB- Individual Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,900.00 0.00 Implementation Support Implementation 02 20 12 02 08 04 M&E Officer Selection PRDP-MIN-R013-010-IB- Individual Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,900.00 0.00 Implementation Support Implementation 02 20 12 02 08 04 Procurement Officer Selection PRDP-MIN-R013-011-IB- Individual 001-2020-AF / SES Officer Component 4: Project Under 2020-01- 2019-11- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,300.00 0.00 (Social Safeguards, Implementation Support Implementation 02 20 12 02 08 04 Selection Environmental Safeguards) PRDP-MIN-R013-012-IB- Individual Component 4: Project Pending 2020-03- 2020-04- 2020-05- 2020-06- 2020-12- 001-2020-AF / Associate IBRD / 88160 Post Consultant Open 9,900.00 0.00 Implementation Support Implementation 02 20 11 15 12 SES Officer Selection PRDP-MIN-BARM-001-IB- 001-2020-AF / Rural Component 2: Individual Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- Infrastruture Specialist IBRD / 88160 Infrastructure Post Consultant Direct 12,800.00 0.00 Implementation 02 23 12 02 08 04 (Roads& Bridges, Water, Development Selection Irrigation) PRDP-MIN-BARM-002-IB- Component 2: Individual Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Rural IBRD / 88160 Infrastructure Post Consultant Direct 11,300.00 0.00 Implementation 02 23 12 02 08 04 Infrastruture Engineer Development Selection PRDP-MIN-BARM-003-IB- Component 2: Individual Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Rural IBRD / 88160 Infrastructure Post Consultant Direct 11,300.00 0.00 Implementation 02 23 12 02 08 04 Infrastruture Engineer Development Selection PRDP-MIN-BARM-004-IB- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Project IBRD / 88160 Post Consultant Direct 7,100.00 0.00 Implementation Support Implementation 02 12 02 08 04 Development Associates Selection (PDA) PRDP-MIN-BARM-005-IB- Individual Component 4: Project Pending 2020-03- 2020-04- 2020-05- 2020-06- 2020-12- 001-2020-AF / IBRD / 88160 Post Consultant Open 7,100.00 0.00 Implementation Support Implementation 02 20 11 15 12 Administrative Officer II Selection PRDP-MIN-BARM-006-IB- Individual Component 4: Project Pending 2020-03- 2020-04- 2020-05- 2020-06- 2020-12- 001-2020-AF / Finance IBRD / 88160 Post Consultant Open 9,900.00 0.00 Implementation Support Implementation 02 20 11 15 12 Analyst I Selection PRDP-MIN-BARM-007-IB- Individual Component 4: Project Pending 2020-03- 2020-04- 2020-05- 2020-06- 2020-12- 001-2020-AF / Finance IBRD / 88160 Post Consultant Open 9,900.00 0.00 Implementation Support Implementation 02 20 11 15 12 Analyst I Selection PRDP-MIN-BARM-008-IB- Individual Component 4: Project Under 2020-03- 2020-12- 2020-04- 2020-05- 2020-06- 2020-12- 001-2020-AF / Budget IBRD / 88160 Post Consultant Open 9,900.00 0.00 Implementation Support Implementation 02 23 20 11 15 12 Analyst I Selection Individual PRDP-MIN-BARM-009-IB- Component 4: Project Pending 2020-03- 2020-04- 2020-05- 2020-06- 2020-12- IBRD / 88160 Post Consultant Open 11,300.00 0.00 001-2020-AF / GIS Officer Implementation Support Implementation 02 20 11 15 12 Selection PRDP-MIN-BARM-010-IB- Individual Component 4: Project Pending 2020-03- 2020-04- 2020-05- 2020-06- 2020-12- 001-2020-AF / M&E IBRD / 88160 Post Consultant Open 11,300.00 0.00 Implementation Support Implementation 02 20 11 15 12 Officer Selection PRDP-MIN-BARM-011-IB- Individual Component 4: Project Pending 2020-03- 2020-04- 2020-05- 2020-06- 2020-12- 001-2020-AF / Associate IBRD / 88160 Post Consultant Open 9,900.00 0.00 Implementation Support Implementation 02 20 11 15 12 M&E Officer Selection PRDP-MIN-BARM-012-IB- Individual Component 4: Project Under 2020-03- 2020-12- 2020-04- 2020-05- 2020-06- 2020-12- 001-2020-AF / Associate IBRD / 88160 Post Consultant Open 9,900.00 0.00 Implementation Support Implementation 02 23 20 11 15 12 Procurement Officer Selection PRDP-MIN-BARM-013-IB- Individual 001-2020-AF / SES Officer Component 4: Project Under 2020-03- 2020-12- 2020-04- 2020-05- 2020-06- 2020-12- IBRD / 88160 Post Consultant Open 11,300.00 0.00 (Social Safegaurds, Implementation Support Implementation 02 23 20 11 15 12 Selection Environmental Safeguards) PRDP-MIN-BARM-014-IB- Individual Component 4: Project Pending 2020-03- 2020-04- 2020-05- 2020-06- 2020-12- 001-2020-AF / Associate IBRD / 88160 Post Consultant Open 9,900.00 0.00 Implementation Support Implementation 02 20 11 15 12 SES Officer Selection PRDP-IS-MIN-001-IB-001- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF1 / Rural IBRD / 88160 Infrastructure Post Consultant Direct 7,200.00 0.00 Implementation 01 11 01 07 03 Infrastructure Specialist Development Selection PRDP-IS-MIN-002-IB-002- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF1 / Rural IBRD / 88160 Post Consultant Direct 7,200.00 0.00 Implementation Support Implementation 01 11 01 07 03 Infrastructure Specialist Selection PRDP-IS-MIN-003-IB-003- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF1 / Rural IBRD / 88160 Infrastructure Post Consultant Direct 7,200.00 0.00 Implementation 01 11 01 07 03 Infrastructure Specialist Development Selection PRDP-IS-MIN-004-IB-004- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF1 / Rural IBRD / 88160 Infrastructure Post Consultant Direct 7,200.00 0.00 Implementation 01 11 01 07 03 Infrastructure Specialist Development Selection PRDP-IS-MIN-005-IB-005- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF1 / Rural IBRD / 88160 Infrastructure Post Consultant Direct 7,200.00 0.00 Implementation 01 11 01 07 03 Infrastructure Specialist Development Selection PRDP-IS-MIN-006-IB-006- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF1 / Rural IBRD / 88160 Infrastructure Post Consultant Direct 6,480.00 0.00 Implementation 01 11 01 07 03 Infrastructure Engineer Development Selection PRDP-IS-MIN-007-IB-007- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF1 / Program IBRD / 88160 Post Consultant Direct 4,320.00 0.00 Implementation Support Implementation 01 11 01 07 03 Development Associate Selection PRDP-IS-MIN-008-IB-008- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF1 / IBUILD IBRD / 88160 Infrastructure Post Consultant Direct 10,080.00 0.00 Implementation 01 11 01 07 03 Component Head Development Selection PRDP-IS-MIN-009-OPD- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-04- 2020-10- 001-2020-AF1 / IBRD / 88160 Post Consultant Open 3,600.00 0.00 Implementation Support Implementation 01 19 11 15 12 Administrative Officer I Selection PRDP-IS-MIN-010-DPD- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 003-2020-AF1 / IBRD / 88160 Post Consultant Direct 7,200.00 0.00 Implementation Support Implementation 01 11 01 07 03 Compliance/Legal Officer Selection PRDP-IS-MIN-011-DPD- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 003-2020-AF1 / IBRD / 88160 Post Consultant Direct 4,320.00 0.00 Implementation Support Implementation 01 11 01 07 03 Administrative Officer II Selection PRDP-IS-MIN-012-DPD- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 004-2020-AF1 / IBRD / 88160 Post Consultant Direct 3,600.00 0.00 Implementation Support Implementation 01 11 01 07 03 Administrative Officer I Selection Individual PRDP-IS-MIN-013-DPD- Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 6,480.00 0.00 005-2020-AF1 / Economist Implementation Support Implementation 01 20 11 01 07 03 Selection Individual PRDP-IS-MIN-014-DPD- Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 6,480.00 0.00 006-2020-AF1 / Economist Implementation Support Implementation 01 20 11 01 07 03 Selection PRDP-IS-MIN-015-DPD- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 007-2020-AF1 / GIS IBRD / 88160 Post Consultant Direct 6,480.00 0.00 Implementation Support Implementation 01 11 01 07 03 Officer Selection Page 7 PRDP-IS-MIN-016-DPD- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 008-2020-AF1 / GIS IBRD / 88160 Post Consultant Direct 6,480.00 0.00 Implementation Support Implementation 01 11 01 07 03 Officer Selection PRDP-IS-MIN-017-DPD- Individual Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- 009-2020-AF1 / IBRD / 88160 Post Consultant Direct 7,200.00 0.00 Implementation Support Implementation 01 20 11 01 07 03 Information Specialist Selection Individual PRDP-IS-MIN-018-DPD- Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 5,760.00 0.00 010-2020-AF1 / Writer Implementation Support Implementation 01 11 01 07 03 Selection PRDP-IS-MIN-019-DPD- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-04- 2020-10- 011-2020-AF1 / Media IBRD / 88160 Post Consultant Open 5,040.00 0.00 Implementation Support Implementation 01 19 11 15 12 Production Officer Selection PRDP-IS-MIN-020-ADM- Individual Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF1 / IBRD / 88160 Post Consultant Direct 9,360.00 0.00 Implementation Support Implementation 01 20 11 01 07 03 Administrative Unit Head Selection PRDP-IS-MIN-021-ADM- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF1 / IBRD / 88160 Post Consultant Direct 4,320.00 0.00 Implementation Support Implementation 01 11 01 07 03 Administrative Officer II Selection PRDP-IS-MIN-022-FIN- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF1 / Finance IBRD / 88160 Post Consultant Direct 9,360.00 0.00 Implementation Support Implementation 01 11 01 07 03 Unit Head Selection PRDP-IS-MIN-023-FIN- Individual Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF1 / Finance IBRD / 88160 Post Consultant Direct 7,200.00 0.00 Implementation Support Implementation 01 20 11 01 07 03 Analyst III Selection PRDP-IS-MIN-024-FIN- Individual Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- 003-2020-AF1 / Finance IBRD / 88160 Post Consultant Direct 7,200.00 0.00 Implementation Support Implementation 01 20 11 01 07 03 Analyst III Selection PRDP-IS-MIN-025-FIN- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 004-2020-AF1 / Finance IBRD / 88160 Post Consultant Direct 6,480.00 0.00 Implementation Support Implementation 01 11 01 07 03 Analyst II Selection PRDP-IS-MIN-026-FIN- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 005-2020-AF1 / Finance IBRD / 88160 Post Consultant Direct 5,760.00 0.00 Implementation Support Implementation 01 11 01 07 03 Analyst I Selection PRDP-IS-MIN-027-FIN- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 006-2020-AF1 / Finance IBRD / 88160 Post Consultant Direct 6,480.00 0.00 Implementation Support Implementation 01 11 01 07 03 Analyst II Selection PRDP-IS-MIN-028-FIN- Individual Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- 007-2020-AF1 / Finance IBRD / 88160 Post Consultant Direct 6,480.00 0.00 Implementation Support Implementation 01 20 11 01 07 03 Analyst II Selection PRDP-IS-MIN-029-FIN- Individual Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- 008-2020-AF1 / Budget IBRD / 88160 Post Consultant Direct 6,480.00 0.00 Implementation Support Implementation 01 20 11 01 07 03 Analyst Selection PRDP-IS-MIN-030-MNE- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF1 / M&E Unit IBRD / 88160 Post Consultant Direct 9,360.00 0.00 Implementation Support Implementation 01 11 01 07 03 Head Selection PRDP-IS-MIN-031-MNE- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF1 / M&E IBRD / 88160 Post Consultant Direct 6,480.00 0.00 Implementation Support Implementation 01 11 01 07 03 Officer Selection PRDP-IS-MIN-032-MNE- Individual Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF1 / M&E IBRD / 88160 Post Consultant Direct 6,480.00 0.00 Implementation Support Implementation 01 20 11 01 07 03 Officer Selection PRDP-IS-MIN-033-PRO- Individual Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF1 / IBRD / 88160 Post Consultant Direct 9,360.00 0.00 Implementation Support Implementation 01 20 11 01 07 03 Procurement Unit Head Selection PRDP-IS-MIN-034-PRO- Individual Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF1 / IBRD / 88160 Post Consultant Direct 9,360.00 0.00 Implementation Support Implementation 01 20 11 01 07 03 Procurement Officer Selection PRDP-IS-MIN-035-PRO- Individual Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- 003-2020-AF1 / IBRD / 88160 Post Consultant Direct 6,480.00 0.00 Implementation Support Implementation 01 20 11 01 07 03 Procurement Officer Selection PRDP-IS-MIN-036-PRO- Individual Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- 004-2020-AF1 / Associate IBRD / 88160 Post Consultant Direct 5,760.00 0.00 Implementation Support Implementation 01 20 11 01 07 03 Procurement Officer Selection PRDP-IS-MIN-037-SES- Individual 001-2020-AF1 / Social and Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 9,360.00 0.00 Environmental Safeguards Implementation Support Implementation 01 11 01 07 03 Selection Unit Head PRDP-IS-MIN-038-SES- Individual 002-2020-AF1 / Social and Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 6,480.00 0.00 Environmental Safeguards Implementation Support Implementation 01 11 01 07 03 Selection Officer PRDP-IS-MIN-039-SES- Individual 003-2020-AF1 / Social and Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 6,480.00 0.00 Environmental Safeguards Implementation Support Implementation 01 11 01 07 03 Selection Officer PRDP-IS-MIN-040-R009- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF1 / Rural IBRD / 88160 Infrastructure Post Consultant Direct 2,880.00 0.00 Implementation 01 11 01 07 03 Infrastructure Engineer Development Selection PRDP-IS-MIN-041-R009- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF1 / Rural IBRD / 88160 Infrastructure Post Consultant Direct 2,880.00 0.00 Implementation 01 11 01 07 03 Infrastructure Engineer Development Selection PRDP-IS-MIN-042-R009- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 003-2020-AF1 / Rural IBRD / 88160 Infrastructure Post Consultant Direct 2,880.00 0.00 Implementation 01 11 01 07 03 Infrastructure Engineer Development Selection PRDP-IS-MIN-043-R009- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 004-2020-AF1 / Program IBRD / 88160 Post Consultant Direct 1,800.00 0.00 Implementation Support Implementation 01 11 01 07 03 Development Associate Selection PRDP-IS-MIN-044-R009- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 005-2020-AF1 / IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 11 01 07 03 Administrative Officer II Selection PRDP-IS-MIN-045-R009- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 006-2020-AF1 / Budget IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 11 01 07 03 Analyst I Selection PRDP-IS-MIN-046-R009- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 007-2020-AF1 / Associate IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 11 01 07 03 SES Officer Selection PRDP-IS-MIN-047-R009- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 008-2020-AF1 / Associate IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 11 01 07 03 Procurement Officer Selection PRDP-IS-MIN-048-R009- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 009-2020-AF1 / GIS IBRD / 88160 Post Consultant Direct 2,880.00 0.00 Implementation Support Implementation 01 11 01 07 03 Officer Selection PRDP-IS-MIN-050-R010- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF1 / Rural IBRD / 88160 Infrastructure Post Consultant Direct 2,880.00 0.00 Implementation 01 11 01 07 03 Infrastructure Engineer Development Selection PRDP-IS-MIN-051-R010- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF1 / Rural IBRD / 88160 Infrastructure Post Consultant Direct 2,880.00 0.00 Implementation 01 11 01 07 03 Infrastructure Engineer Development Selection PRDP-IS-MIN-052-R010- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 003-2020-AF1 / Program IBRD / 88160 Post Consultant Direct 1,800.00 0.00 Implementation Support Implementation 01 11 01 07 03 Development Associate Selection Individual PRDP-IS-MIN-053-R010- Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 2,880.00 0.00 004-2020-AF1 / Economist Implementation Support Implementation 01 11 01 07 03 Selection PRDP-IS-MIN-054-R010- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 005-2020-AF1 / Finance IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 11 01 07 03 Analyst II Selection PRDP-IS-MIN-055-R010- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 006-2020-AF1 / Finance IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 11 01 07 03 Analyst II Selection PRDP-IS-MIN-056-R010- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 007-2020-AF1 / Associate IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 11 01 07 03 Procurement Officer Selection PRDP-IS-MIN-057-R010- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 008-2020-AF1 / Project IBRD / 88160 Post Consultant Direct 1,800.00 0.00 Implementation Support Implementation 01 11 01 07 03 Development Associate Selection PRDP-IS-MIN-058-R010- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 009-2020-AF1 / Project IBRD / 88160 Post Consultant Direct 1,800.00 0.00 Implementation Support Implementation 01 11 01 07 03 Development Associate Selection PRDP-IS-MIN-059-R010- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 010-2020-AF1 / Associate IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 11 01 07 03 SES Officer Selection PRDP-IS-MIN-060-R010- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 011-2020-AF1 / GIS Data IBRD / 88160 Post Consultant Direct 2,880.00 0.00 Implementation Support Implementation 01 11 01 07 03 Officer Selection PRDP-IS-MIN-061-R010- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 012-2020-AF1 / GIS Data IBRD / 88160 Post Consultant Direct 2,880.00 0.00 Implementation Support Implementation 01 11 01 07 03 Officer Selection PRDP-IS-MIN-062-R010- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 013-2020-AF1 / Project IBRD / 88160 Post Consultant Direct 1,800.00 0.00 Implementation Support Implementation 01 11 01 07 03 Development Associate Selection Individual PRDP-IS-MIN-063-R010- Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 2,520.00 0.00 014-2020-AF1 / Writer Implementation Support Implementation 01 11 01 07 03 Selection PRDP-IS-MIN-061-R011- Component 2: Individual Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF1 / Rural IBRD / 88160 Infrastructure Post Consultant Direct 2,880.00 0.00 Implementation 01 28 11 01 07 03 Infra Engineer Development Selection PRDP-IS-MIN-062-R011- Component 2: Individual Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF1 / Rural IBRD / 88160 Infrastructure Post Consultant Direct 2,880.00 0.00 Implementation 01 28 11 01 07 03 Infra Engineer Development Selection PRDP-IS-MIN-063-R011- Component 2: Individual Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- 003-2020-AF1 / Rural IBRD / 88160 Infrastructure Post Consultant Direct 2,880.00 0.00 Implementation 01 28 11 01 07 03 Infra Engineer Development Selection PRDP-IS-MIN-064-R011- Component 2: Individual Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- 004-2020-AF1 / Rural IBRD / 88160 Infrastructure Post Consultant Direct 2,880.00 0.00 Implementation 01 28 11 01 07 03 Infra Engineer Development Selection PRDP-IS-MIN-065-R011- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 005-2020-AF1 / Program IBRD / 88160 Post Consultant Direct 1,800.00 0.00 Implementation Support Implementation 01 11 01 07 03 Development Associate Selection PRDP-IS-MIN-066-R011- Individual Component 4: Project Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- 006-2020-AF1 / IBRD / 88160 Post Consultant Direct 2,880.00 0.00 Implementation Support Implementation 01 28 11 01 07 03 Monitoring and Evaluation Selection Officer PRDP-IS-MIN-067-R011- Individual Component 4: Project Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- 007-2020-AF1 / Finance IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 28 11 01 07 03 Analyst I Selection PRDP-IS-MIN-068-R011- Individual Component 4: Project Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- 008-2020-AF1 / Finance IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 28 11 01 07 03 Analyst I Selection PRDP-IS-MIN-069-R011- Individual Component 4: Project Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- 009-2020-AF1 / Budget IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 28 11 01 07 03 Analyst Selection PRDP-IS-MIN-070-R011- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 010-2020-AF1 / GIS IBRD / 88160 Post Consultant Direct 2,880.00 0.00 Implementation Support Implementation 01 11 01 07 03 Officer Selection Page 8 PRDP-IS-MIN-071-R011- Individual Component 4: Project Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- 011-2020-AF1 / SES IBRD / 88160 Post Consultant Direct 2,880.00 0.00 Implementation Support Implementation 01 28 11 01 07 03 Officer Selection PRDP-IS-MIN-072-R011- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 012-2020-AF1 / Associate IBRD / 88160 Post Consultant Direct 250.00 0.00 Implementation Support Implementation 01 11 01 07 03 SES Officer Selection Individual PRDP-IS-MIN-073-R011- Component 4: Project Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 2,880.00 0.00 013-2020-AF1 / Economist Implementation Support Implementation 01 28 11 01 07 03 Selection PRDP-IS-MIN-074-R012- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF1 / Rural IBRD / 88160 Infrastructure Post Consultant Direct 2,880.00 0.00 Implementation 01 11 01 07 03 Infrastructure Engineer Development Selection PRDP-IS-MIN-075-R012- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF1 / Rural IBRD / 88160 Infrastructure Post Consultant Direct 2,880.00 0.00 Implementation 01 11 01 07 03 Infrastructure Engineer Development Selection PRDP-IS-MIN-076-R012- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 003-2020-AF1 / Rural IBRD / 88160 Infrastructure Post Consultant Direct 2,880.00 0.00 Implementation 01 11 01 07 03 Infrastructure Engineer Development Selection PRDP-IS-MIN-077-R012- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 004-2020-AF1 / Program IBRD / 88160 Post Consultant Direct 1,800.00 0.00 Implementation Support Implementation 01 11 01 07 03 Development Associate Selection PRDP-IS-MIN-078-R012- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 005-2020-AF1 / Finance IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 11 01 07 03 Analyst I Selection PRDP-IS-MIN-079-R012- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 006-2020-AF1 / Finance IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 11 01 07 03 Analyst I Selection PRDP-IS-MIN-080-R012- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 007-2020-AF1 / GIS IBRD / 88160 Post Consultant Direct 2,880.00 0.00 Implementation Support Implementation 01 11 01 07 03 Officer Selection PRDP-IS-MIN-081-R012- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 008-2020-AF1 / Associate IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 11 01 07 03 Procurement Officer Selection PRDP-IS-MIN-082-R012- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 009-2020-AF1 / SES IBRD / 88160 Post Consultant Direct 2,880.00 0.00 Implementation Support Implementation 01 11 01 07 03 officer Selection PRDP-IS-MIN-083-R012- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 010-2020-AF1 / Associate IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 11 01 07 03 SES Officer Selection PRDP-IS-MIN-084-R012- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 011-2020-AF1 / IBRD / 88160 Post Consultant Direct 1,800.00 0.00 Implementation Support Implementation 01 11 01 07 03 Administrative Officer II Selection Individual PRDP-IS-MIN-085-R012- Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 2,880.00 0.00 012-2020-AF1 / Economist Implementation Support Implementation 01 11 01 07 03 Selection PRDP-IS-MIN-086-R012- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 013-2020-AF1 / Associate IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 11 01 07 03 Procurement Officer Selection PRDP-IS-MIN-87-R013- Component 2: Individual Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF1 / Rural IBRD / 88160 Infrastructure Post Consultant Direct 3,240.00 0.00 Implementation 01 20 11 01 07 03 Infra Specialist Development Selection PRDP-IS-MIN-88-R013- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF1 / Rural IBRD / 88160 Infrastructure Post Consultant Direct 2,880.00 0.00 Implementation 01 11 01 07 03 Infrastructure Engineer Development Selection PRDP-IS-MIN-89-R013- Component 2: Individual Under 2020-01- 2019-11- 2020-01- 2020-02- 2020-03- 2020-09- 003-2020-AF1 / Rural IBRD / 88160 Infrastructure Post Consultant Direct 2,880.00 0.00 Implementation 01 20 11 01 07 03 Infrastructure Engineer Development Selection PRDP-IS-MIN-90-R013- Individual Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-04- 2020-10- 004-2020-AF1 / Project IBRD / 88160 Post Consultant Open 1,800.00 0.00 Implementation Support Implementation 01 19 11 15 12 Development Associate Selection PRDP-IS-MIN-92-R013- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 005-2020-AF1 / Finance IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 11 01 07 03 Analyst I Selection PRDP-IS-MIN-93-R013- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 006-2020-AF1 / Associate IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 11 01 07 03 Procurement Officer Selection PRDP-IS-MIN-94-R013- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 007-2020-AF1 / M&E IBRD / 88160 Post Consultant Direct 2,880.00 0.00 Implementation Support Implementation 01 11 01 07 03 Officer Selection PRDP-IS-MIN-95-R013- Individual Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- 008-2020-AF1 / Associate IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 20 11 01 07 03 M&E Officer Selection PRDP-IS-MIN-96-R013- Individual 009-2020-AF1 / Social and Component 4: Project Pending 2020-01- 2020-02- 2020-03- 2020-04- 2020-10- IBRD / 88160 Post Consultant Open 2,880.00 0.00 Environmental Safeguards Implementation Support Implementation 01 19 11 15 12 Selection Officer PRDP-IS-MIN-97-R013- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 010-2020-AF1 / GIS IBRD / 88160 Post Consultant Direct 2,880.00 0.00 Implementation Support Implementation 01 11 01 07 03 Officer Selection Individual PRDP-IS-MIN-98-R013- Component 4: Project Under 2020-01- 2020-11- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 2,520.00 0.00 011-2020-AF1 / Writer Implementation Support Implementation 01 20 11 01 07 03 Selection PRDP-IS-MIN-99-BARMM- Component 2: Individual Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF1 / Rural IBRD / 88160 Infrastructure Post Consultant Direct 3,240.00 0.00 Implementation 01 11 01 07 03 Infra Specialist Development Selection PRDP-IS-MIN-100-BARMM- Component 2: Individual Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF1 / Rural IBRD / 88160 Infrastructure Post Consultant 2,880.00 0.00 Implementation 01 23 11 01 07 03 Infrastructure Engineer Development Selection PRDP-IS-MIN-101-BARMM- Component 2: Individual Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- 003-2020-AF1 / Rural IBRD / 88160 Infrastructure Post Consultant Direct 2,880.00 0.00 Implementation 01 23 11 01 07 03 Infrastructure Engineer Development Selection PRDP-IS-MIN-102-BARMM- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 004-2020-AF1 / Project IBRD / 88160 Post Consultant Direct 1,800.00 0.00 Implementation Support Implementation 01 11 01 07 03 Development Associate Selection PRDP-IS-MIN-103-BARMM- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 005-2020-AF1 / IBRD / 88160 Post Consultant Direct 1,800.00 0.00 Implementation Support Implementation 01 11 01 07 03 Administrative Officer II Selection Individual PRDP-IS-MIN-104-BARMM- Component 4: Project Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 2,880.00 0.00 006-2020-AF1 / Economist Implementation Support Implementation 01 23 11 01 07 03 Selection PRDP-IS-MIN-105-BARMM- Individual Component 4: Project Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- 007-2020-AF1 / Associate IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 23 11 01 07 03 Procurement Officer Selection PRDP-IS-MIN-106-BARMM- Individual Component 4: Project Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- 008-2020-AF1 / Finance IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 23 11 01 07 03 Analyst I Selection PRDP-IS-MIN-107-BARMM- Individual Component 4: Project Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- 009-2020-AF1 / Budget IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 23 11 01 07 03 Analyst I Selection PRDP-IS-MIN-108-BARMM- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 010-2020-AF1 / GIS IBRD / 88160 Post Consultant Direct 2,880.00 0.00 Implementation Support Implementation 01 11 01 07 03 Officer Selection PRDP-IS-MIN-109-BARMM- Individual Component 4: Project Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- 011-2020-AF1 / IBRD / 88160 Post Consultant Direct 2,880.00 0.00 Implementation Support Implementation 01 23 11 01 07 03 Monitoring and Evaluation Selection Officer PRDP-IS-MIN-110-BARMM- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 012-2020-AF1 / Associate IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 11 01 07 03 M&E Officer Selection PRDP-IS-MIN-111-BARMM- Individual 013-2020-AF1 / Social and Component 4: Project Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 5,760.00 0.00 Environmental Safeguards Implementation Support Implementation 01 23 11 01 07 03 Selection Officer PRDP-IS-MIN-112-BARMM- Individual Component 4: Project Pending 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 014-2020-AF1 / Associate IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 11 01 07 03 SES Officer Selection PRDP-IS-MIN-113-BARMM- Individual Component 4: Project Under 2020-01- 2020-12- 2020-01- 2020-02- 2020-03- 2020-09- 015-2020-AF1 / Finance IBRD / 88160 Post Consultant Direct 2,520.00 0.00 Implementation Support Implementation 01 23 11 01 07 03 Analyst I Selection PRDP-IS-MIN-ADM-007- Component 4: Project 2018-09- 2020-11- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 4,235.29 0.00 Canceled 002-2018-AF / Cash Clerk Implementation Support 01 20 11 15 14 PRDP-IS-MIN-ADM-008- Component 4: Project 2018-09- 2020-11- 2018-09- 2018-11- 2019-05- 006-2018-AF / Chauffeur IBRD / 84210 Post Direct Selection Direct 2,823.53 0.00 Canceled Implementation Support 01 20 11 15 14 (Driver/Mechanic) PRDP-IS-MIN-ADM-008- Component 4: Project 2018-09- 2020-11- 2018-09- 2018-11- 2019-05- 008-2018-AF / Chauffeur IBRD / 84210 Post Direct Selection Direct 2,823.53 0.00 Canceled Implementation Support 01 20 11 15 14 (Driver/Mechanic) PRDP-IS-MIN-ADM-006- Component 4: Project 2018-09- 2018-09- 2018-11- 2019-05- 000-2018-AF / IBRD / 84210 Post Direct Selection Direct 3,529.41 0.00 Canceled Implementation Support 01 11 15 14 Administrative Assistant PRDP-IS-MIN-ADM-007- Component 4: Project 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 4,235.29 0.00 Canceled 001-2018-AF / Cash Clerk Implementation Support 01 11 15 14 PRDP-IS-MIN-ADM-008- Component 4: Project 2018-09- 2018-09- 2018-11- 2019-05- 001-2018-AF / Chauffeur IBRD / 84210 Post Direct Selection Direct 2,823.53 0.00 Canceled Implementation Support 01 11 15 14 (Driver/Mechanic) PRDP-IS-MIN-ADM-008- Component 4: Project 2018-09- 2018-09- 2018-11- 2019-05- 002-2018-AF / Chauffeur IBRD / 84210 Post Direct Selection Direct 2,823.53 0.00 Canceled Implementation Support 01 11 15 14 (Driver/Mechanic) PRDP-IS-MIN-ADM-008- Component 4: Project 2018-09- 2018-09- 2018-11- 2019-05- 005-2018-AF / Chauffeur IBRD / 84210 Post Direct Selection Direct 2,823.53 0.00 Canceled Implementation Support 01 11 15 14 (Driver/Mechanic) PRDP-IS-MIN-ADM-008- Component 4: Project 2018-09- 2018-09- 2018-11- 2019-05- 004-2018-AF / Chauffeur IBRD / 84210 Post Direct Selection Direct 2,823.53 0.00 Canceled Implementation Support 01 11 15 14 (Driver/Mechanic) PRDP-IS-MIN-ADM-008- Component 4: Project 2018-09- 2018-09- 2018-11- 2019-05- 007-2018-AF / Chauffeur IBRD / 84210 Post Direct Selection Direct 2,823.53 0.00 Canceled Implementation Support 01 11 15 14 (Driver/Mechanic) PRDP-IS-MIN-ADM-008- Component 4: Project 2018-09- 2018-09- 2018-11- 2019-05- 003-2018-AF / Chauffeur IBRD / 84210 Post Direct Selection Direct 2,823.53 0.00 Canceled Implementation Support 01 11 15 14 (Driver/Mechanic) PRDP-IS-MIN-ADM-004- Component 4: Project 2018-09- 2018-09- 2018-11- 2019-05- 000-2018-AF / Chief IBRD / 84210 Post Direct Selection Direct 4,235.29 0.00 Canceled Implementation Support 01 11 15 14 Automotive Mechanic PRDP-IS-MIN-ADM-009- Component 4: Project 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 2,117.65 0.00 Canceled 001-2018-AF / Implementation Support 01 11 15 14 Utility/Messenger PRDP-IS-MIN-ADM-009- Component 4: Project 2018-09- 2018-09- 2018-11- 2019-05- IBRD / 84210 Post Direct Selection Direct 2,117.65 0.00 Canceled 002-2018-AF / Implementation Support 01 11 15 14 Utility/Messenger Individual PRDP-PSO-001-IP-001- Component 1: Local and Under 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- TF / B5756 Post Consultant Open 13,440.00 0.00 2022-EU / Planning Officer National Level Planning Implementation 15 01 17 08 28 31 Selection PRDP-PSO-008-IP-008- Individual Component 1: Local and Under 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 2022-EU / Project TF / B5756 Post Consultant Open 7,680.00 0.00 National Level Planning Implementation 15 01 17 08 28 31 Development Associate Selection Page 9 PRDP-PSO-009-IR-001- Individual Component 3. Enterprise Under 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 2022-EU / Business Devt TF / B5756 Post Consultant Open 12,000.00 0.00 Development Implementation 15 01 17 08 28 31 Officer Selection Individual PRDP-PSO-010-IS-ODP- Component 4: Project Pending 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- TF / B5756 Post Consultant Open 13,440.00 0.00 001-2022-EU / Economist Implementation Support Implementation 15 17 08 28 31 Selection PRDP-PSO-013-IS-ODP- Individual Component 4: Project 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 004-2022-EU / Web TF / B5756 Post Consultant Open 14,880.00 0.00 Canceled Implementation Support 15 17 08 28 31 Developer Selection PRDP-PSO-014-IS-ODP- Individual Component 4: Project 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 005-2022-EU / GIS TF / B5756 Post Consultant Open 14,880.00 0.00 Canceled Implementation Support 15 17 08 28 31 Specialist/Programmer Selection PRDP-PSO-015-IS-ODP- Individual Component 4: Project Pending 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 006-2022-EU / Digitization TF / B5756 Post Consultant Open 7,680.00 0.00 Implementation Support Implementation 15 17 08 28 31 of Knowledge Product Selection Officer PRDP-PSO-016-IS-FIN- Individual Component 4: Project Pending 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-EU / Finance TF / B5756 Post Consultant Open 13,440.00 0.00 Implementation Support Implementation 15 17 08 28 31 Analyst II Selection PRDP-PSO-017-IS-FIN- Individual Component 4: Project Pending 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 002-2022-EU / Finance TF / B5756 Post Consultant Open 12,000.00 0.00 Implementation Support Implementation 15 17 08 28 31 Analyst I Selection PRDP-PSO-018-IS-MNE- Individual Component 4: Project Pending 2021-10- 2021-12- 2021-12- 2021-12- 2022-12- 001-2022-EU / M&E TF / B5756 Post Consultant Open 13,440.00 0.00 Implementation Support Implementation 15 03 24 28 31 Officer Selection Individual PRDP-PSO-019-IS-SES- Component 4: Project Pending 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- TF / B5756 Post Consultant Open 13,440.00 0.00 001-2022-EU / SES Officer Implementation Support Implementation 15 17 08 28 31 Selection Individual PRDP-PSO-020-IS-SES- Component 4: Project Pending 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- TF / B5756 Post Consultant Open 13,440.00 0.00 002-2022-EU / SES Officer Implementation Support Implementation 15 17 08 28 31 Selection PRDP-PSO-021-IS-ADM- Individual Component 4: Project 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-EU / Admin TF / B5756 Post Consultant Open 7,680.00 0.00 Under Review Implementation Support 15 20 17 08 28 31 Officer I Selection PRDP-PSO-022-IS-ADM- Individual Component 4: Project 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-EU / Admin TF / B5756 Post Consultant Open 7,680.00 0.00 Under Review Implementation Support 15 20 17 08 28 31 Officer I Selection PRDP-RO09-023-IR-001- Individual Component 3. Enterprise Under 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 2022-EU / Business Devt TF / B5756 Post Consultant Open 12,000.00 0.00 Development Implementation 15 01 17 08 28 31 Officer Selection PRDP-RO09-024-IS-PRO- Individual Component 4: Project Under 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-EU / Associate TF / B5756 Post Consultant Open 10,560.00 0.00 Implementation Support Implementation 15 01 17 08 31 30 Procurement Officer Selection PRDP-RO09-025-IS-ODP- Individual Component 4: Project Pending 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-EU / Project TF / B5756 Post Consultant Open 7,680.00 0.00 Implementation Support Implementation 15 17 08 28 31 Development Associate Selection PRDP-RO09-026-IS-FIN- Individual Component 4: Project Under 2021-10- 2021-12- 2021-11- 2021-12- 2022-01- 2022-12- 001-2022-EU / Fnance TF / B5756 Post Consultant Open 10,560.00 0.00 Implementation Support Implementation 15 01 17 08 03 30 Analyst I Selection Individual PRDP-RO09-027-IS-ODP- Component 4: Project Under 2021-10- 2021-12- 2021-11- 2021-12- 2022-01- 2022-12- TF / B5756 Post Consultant Open 10,560.00 0.00 002-2022-EU / Writer Implementation Support Implementation 15 01 17 08 03 30 Selection Individual PRDP-RO10-028-IS-ODP- Component 4: Project Under 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- TF / B5756 Post Consultant Open 12,000.00 0.00 001-2022-EU / Economist Implementation Support Implementation 15 12 17 08 28 31 Selection PRDP-RO10-029-IS-PRO- Individual Component 4: Project 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-EU / Associate TF / B5756 Post Consultant Open 10,560.00 0.00 Under Review Implementation Support 15 22 17 08 28 31 Procurement Officer Selection PRDP-RO10-030-IS-001- Individual Component 4: Project Pending 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-EU / Project Devt TF / B5756 Post Consultant Open 7,680.00 0.00 Implementation Support Implementation 15 17 08 28 31 Associate Selection PRDP-RO10-031-IS-FIN- Individual Component 4: Project 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-EU / Budget TF / B5756 Post Consultant Open 10,560.00 0.00 Under Review Implementation Support 15 22 17 08 28 31 Analyst Selection PRDP-RO11-032-IR-001- Individual Component 3. Enterprise Under 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 2022-EU / Business Devt TF / B5756 Post Consultant Open 12,000.00 0.00 Development Implementation 15 01 17 08 28 31 Officer Selection PRDP-RO11-033-IR-002- Individual Component 3. Enterprise Under 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-EU / Business Devt TF / B5756 Post Consultant Open 12,000.00 0.00 Development Implementation 15 11 17 08 28 31 Officer Selection PRDP-RO11-034-IR-003- Individual Component 3. Enterprise Under 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-EU / Business Devt TF / B5756 Post Consultant Open 12,000.00 0.00 Development Implementation 15 11 17 08 28 31 Officer Selection PRDP-RO11-035-IS-PRO- Individual Component 4: Project Under 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-EU / Associate TF / B5756 Post Consultant Open 10,560.00 0.00 Implementation Support Implementation 15 01 17 08 28 31 Procurement Officer Selection PRDP-RO12-036-IR-001- Individual Component 3. Enterprise Under 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 2022-EU / Business Devt TF / B5756 Post Consultant Open 12,000.00 0.00 Development Implementation 15 01 17 08 28 31 Officer Selection PRDP-RO12-037-IS-PRO- Individual Component 4: Project Under 2021-10- 2021-12- 2021-11- 2021-12- 2022-01- 2022-12- 001-2022-EU / Associate TF / B5756 Post Consultant Open 10,560.00 0.00 Implementation Support Implementation 15 01 17 08 03 30 Procurement Officer Selection PRDP-RO13-038-IR-001- Individual Component 3. Enterprise 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-EU / Business TF / B5756 Post Consultant Open 12,000.00 0.00 Under Review Development 15 22 17 08 28 31 Development Officer Selection PRDP-RO13-039-IR-002- Individual Component 3. Enterprise 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-EU / Enterprise Devt TF / B5756 Post Consultant Open 13,440.00 0.00 Under Review Development 15 22 17 08 28 31 And Mktg Specialist Selection PRDP-RO13-040-IR-003- Individual Component 3. Enterprise Under 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-EU / Project Devt TF / B5756 Post Consultant Open 7,680.00 0.00 Development Implementation 15 22 17 08 28 31 Associate Selection PRDP-RO13-041-IS-PRO- Individual Component 4: Project 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-EU / Associate TF / B5756 Post Consultant Open 10,560.00 0.00 Under Review Implementation Support 15 22 17 08 28 31 Procurement Officer Selection PRDP-BARM-042-IR-001- Individual Component 3. Enterprise 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 2022-EU / Business TF / B5756 Post Consultant Open 12,000.00 0.00 Under Review Development 15 01 17 08 28 31 Development Officer Selection PRDP-BARM-043-IR-001- Individual Component 3. Enterprise Under 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-EU / Business TF / B5756 Post Consultant Open 12,000.00 0.00 Development Implementation 15 11 17 08 28 31 Development Officer Selection PRDP-BARM-044-IR-002- Individual Component 3. Enterprise Under 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 2022-EU / Project Devt TF / B5756 Post Consultant Open 7,680.00 0.00 Development Implementation 15 01 17 08 28 31 Associate Selection PRDP-BARM-045-IS-PRO- Individual Component 4: Project Under 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-EU / Associate TF / B5756 Post Consultant Open 10,560.00 0.00 Implementation Support Implementation 15 01 17 08 28 31 Procurement Officer Selection Individual PRDP-BARM-046-IS-ODP- Component 4: Project Under 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- TF / B5756 Post Consultant Open 12,000.00 0.00 001-2022-EU / GIS Officer Implementation Support Implementation 15 01 17 08 28 31 Selection PRDP-BARM-047-IS-MNE- Individual Component 4: Project Under 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-EU / M&E TF / B5756 Post Consultant Open 12,000.00 0.00 Implementation Support Implementation 15 01 17 08 28 31 Officer Selection PRDP-PSO-001-IP-001- Individual Component 1: Local and 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / IPLAN Planning IBRD / 92710 Post Consultant Direct 20,640.00 0.00 Under Review National Level Planning 08 17 18 09 28 31 Component Head Selection PRDP-PSO-002-IP-002- Individual Component 1: Local and Under 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Planning IBRD / 92710 Post Consultant Open 14,880.00 0.00 National Level Planning Implementation 15 17 17 08 28 31 Specialist Selection PRDP-PSO-003-IP-003- Individual Component 1: Local and 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Planning IBRD / 92710 Post Consultant Direct 13,440.00 0.00 Under Review National Level Planning 08 15 18 09 28 31 Officer Selection PRDP-PSO-004-IP-004- Individual Component 1: Local and 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Planning IBRD / 92710 Post Consultant Direct 13,440.00 0.00 Under Review National Level Planning 08 15 18 09 28 31 Officer Selection PRDP-PSO-005-IP-005- Individual Component 1: Local and 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Project IBRD / 92710 Post Consultant Open 9,120.00 0.00 Under Review National Level Planning 15 15 23 14 28 31 Development Associate Selection PRDP-PSO-006-IB-001- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / IBUILD IBRD / 92710 Infrastructure Post Consultant Direct 20,640.00 0.00 Under Review 08 15 18 09 28 31 Component Head Development Selection PRDP-PSO-007-IB-002- Component 2: Individual 2022-AF2 / Rural 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- IBRD / 92710 Infrastructure Post Consultant Direct 14,880.00 0.00 Under Review Infrastructure Specialist 08 15 18 09 28 31 Development Selection (Roads and Bridges, Water and Irrigation) PRDP-PSO-008-IB-003- Component 2: Individual 2022-AF2 / Rural 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- IBRD / 92710 Infrastructure Post Consultant Direct 14,880.00 0.00 Under Review Infrastructure Specialist 08 15 18 09 28 31 Development Selection (Roads and Bridges, Water and Irrigation) PRDP-PSO-009-IB-004- Component 2: Individual 2022-AF2 / Rural 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- IBRD / 92710 Infrastructure Post Consultant Direct 14,880.00 0.00 Under Review Infrastructure Specialist 08 15 18 09 28 31 Development Selection (Roads and Bridges, Water and Irrigation) PRDP-PSO-010-IB-005- Component 2: Individual 2022-AF2 / Rural 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- IBRD / 92710 Infrastructure Post Consultant Direct 14,880.00 0.00 Under Review Infrastructure Specialist 08 15 18 09 28 31 Development Selection (Roads and Bridges, Water and Irrigation) PRDP-PSO-011-IB-006- Component 2: Individual 2022-AF2 / Rural 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- IBRD / 92710 Infrastructure Post Consultant Direct 14,880.00 0.00 Under Review Infrastructure Specialist 08 15 18 09 28 31 Development Selection (Roads and Bridges, Water and Irrigation) PRDP-PSO-012-IB-007- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural IBRD / 92710 Infrastructure Post Consultant Direct 13,440.00 0.00 Under Review 08 15 18 09 28 31 Infrastructure Engineer Development Selection PRDP-PSO-013-IB-008- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Project IBRD / 92710 Post Consultant Direct 9,120.00 0.00 Under Review Implementation Support 08 15 18 09 28 31 Development Associate Selection PRDP-PSO-014-IR-001- Individual Component 3. Enterprise Pending 2021-11- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / IREAP IBRD / 92710 Post Consultant Direct 20,640.00 0.00 Development Implementation 08 18 09 28 31 Component Head Selection PRDP-PSO-015-IR-002- Individual Component 3. Enterprise 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Enterprise Devt IBRD / 92710 Post Consultant Direct 14,880.00 0.00 Under Review Development 08 17 18 09 28 31 Specialist Selection PRDP-PSO-016-IR-003- Individual Component 3. Enterprise 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Enterprise Devt IBRD / 92710 Post Consultant Open 14,880.00 0.00 Under Review Development 15 17 17 08 28 31 Specialist Selection PRDP-PSO-017-IR-004- Individual Component 3. Enterprise 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Organizational IBRD / 92710 Post Consultant Open 14,880.00 0.00 Under Review Development 15 01 17 08 28 31 Devt Specialist Selection PRDP-PSO-018-IR-005- Individual Component 3. Enterprise 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Business IBRD / 92710 Post Consultant Direct 13,440.00 0.00 Under Review Development 08 17 18 09 28 31 Development Officer Selection PRDP-PSO-019-IR-006- Individual Component 3. Enterprise 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Business IBRD / 92710 Post Consultant Direct 13,440.00 0.00 Under Review Development 08 17 18 09 28 31 Development Officer Selection Page 10 PRDP-PSO-020-IR-007- Individual Component 3. Enterprise 2021-11- 2021-10- 2021-12- 2021-12- 2022-01- 2022-12- 2022-AF2 / Business IBRD / 92710 Post Consultant Open 13,440.00 0.00 Under Review Development 08 17 26 27 28 31 Development Officer Selection PRDP-PSO-021-IR-008- Individual Component 3. Enterprise 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Business IBRD / 92710 Post Consultant Open 13,440.00 0.00 Under Review Development 15 17 17 08 28 31 Development Officer Selection PRDP-PSO-022-IR-009- Individual Component 3. Enterprise 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Business IBRD / 92710 Post Consultant Open 13,440.00 0.00 Under Review Development 15 17 17 08 28 31 Development Officer Selection PRDP-PSO-023-IR-010- Individual Component 4: Project 2021-11- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Project IBRD / 92710 Post Consultant Direct 9,120.00 0.00 Under Review Implementation Support 08 01 18 09 28 31 Development Associate Selection PRDP-PSO-024-IR-011- Individual Component 3. Enterprise 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Project IBRD / 92710 Post Consultant Open 9,120.00 0.00 Under Review Development 15 01 17 08 28 31 Development Associate Selection PRDP-PSO-025-IS-OPD- Individual Component 4: Project 2021-11- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / IBRD / 92710 Post Consultant Direct 7,680.00 0.00 Under Review Implementation Support 08 20 18 09 28 31 Administrative Officer I Selection PRDP-PSO-026-IS-DPD- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / IBRD / 92710 Post Consultant Direct 14,880.00 0.00 Under Review Implementation Support 08 17 18 09 28 31 Compliance/Legal Officer Selection PRDP-PSO-027-IS-DPD- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 002-2022-AF2 / IBRD / 92710 Post Consultant Direct 9,120.00 0.00 Under Review Implementation Support 08 17 18 09 28 31 Administrative Officer II Selection PRDP-PSO-028-IS-DPD- Individual Component 4: Project 2021-11- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 003-2022-AF2 / IBRD / 92710 Post Consultant Direct 7,680.00 0.00 Under Review Implementation Support 08 20 18 09 28 31 Administrative Officer I Selection Individual PRDP-PSO-029-IS-DPD- Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- IBRD / 92710 Post Consultant Direct 12,960.00 0.00 Under Review 004-2022-AF2 / Economist Implementation Support 08 17 18 09 28 31 Selection Individual PRDP-PSO-030-IS-DPD- Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- IBRD / 92710 Post Consultant Direct 12,960.00 0.00 Under Review 005-2022-AF2 / Economist Implementation Support 08 17 18 09 28 31 Selection PRDP-PSO-031-IS-DPD- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 006-2022-AF2 / GIS IBRD / 92710 Post Consultant Direct 12,960.00 0.00 Under Review Implementation Support 08 20 18 09 28 31 Officer Selection PRDP-PSO-032-IS-DPD- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 007-2022-AF2 / GIS IBRD / 92710 Post Consultant Direct 12,960.00 0.00 Under Review Implementation Support 08 20 18 09 28 31 Officer Selection PRDP-PSO-033-IS-DPD- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 008-2022-AF2 / IBRD / 92710 Post Consultant Direct 14,880.00 0.00 Under Review Implementation Support 08 20 18 09 28 31 Information Specialist Selection Individual PRDP-PSO-034-IS-DPD- Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- IBRD / 92710 Post Consultant Direct 12,960.00 0.00 Under Review 009-2022-AF2 / Writer Implementation Support 08 20 18 09 28 31 Selection PRDP-PSO-035-IS-DPD- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 010-2022-AF2 / Media IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review Implementation Support 08 20 18 09 28 31 Production Officer Selection PRDP-PSO-037-IS-FIN- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 002-2022-AF2 / Finance IBRD / 92710 Post Consultant Direct 14,880.00 0.00 Under Review Implementation Support 08 20 18 09 28 31 Analyst III/Finance Selection Soecialist PRDP-PSO-038-IS-FIN- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 003-2022-AF2 / Finance IBRD / 92710 Post Consultant Direct 14,880.00 0.00 Under Review Implementation Support 08 20 18 09 28 31 Analyst III/Finance Selection Soecialist PRDP-PSO-039-IS-FIN- Individual Component 4: Project Under 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 004-2022-AF2 / Finance IBRD / 92710 Post Consultant Direct 13,440.00 0.00 Implementation Support Implementation 08 20 18 09 28 31 Analyst II Selection PRDP-PSO-040-IS-FIN- Individual Component 4: Project Under 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 005-2022-AF2 / Finance IBRD / 92710 Post Consultant Direct 13,440.00 0.00 Implementation Support Implementation 08 20 18 09 28 31 Analyst II Selection PRDP-PSO-041-IS-FIN- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 006-2022-AF2 / Finance IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review Implementation Support 08 20 18 09 28 31 Analyst I Selection PRDP-PSO-042-IS-FIN- Individual Component 4: Project Under 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 007-2022-AF2 / Finance IBRD / 92710 Post Consultant Direct 13,440.00 0.00 Implementation Support Implementation 08 20 18 09 28 31 Analyst II Selection PRDP-PSO-043-IS-FIN- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 008-2022-AF2 / Budget IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review Implementation Support 08 20 18 09 28 31 Analyst Selection PRDP-PSO-044-IS-PRO- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / IBRD / 92710 Post Consultant Direct 19,200.00 0.00 Under Review Implementation Support 08 21 18 09 28 31 Procurement Unit Head Selection PRDP-PSO-045-IS-PRO- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 002-2022-AF2 / IBRD / 92710 Post Consultant Direct 13,440.00 0.00 Under Review Implementation Support 08 21 18 09 28 31 Procurement Officer Selection PRDP-PSO-046-IS-PRO- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 003-2022-AF2 / IBRD / 92710 Post Consultant Direct 13,440.00 0.00 Under Review Implementation Support 08 21 18 09 28 31 Procurement Officer Selection PRDP-PSO-047-IS-PRO- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 004-2022-AF2 / Associate IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review Implementation Support 08 21 18 09 28 31 Procurement Officer Selection PRDP-PSO-048-IS-MNE- Individual Component 4: Project 2021-11- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / M&E Unit IBRD / 92710 Post Consultant Direct 19,200.00 0.00 Under Review Implementation Support 08 01 18 09 28 31 Head Selection PRDP-PSO-049-IS-MNE- Individual Component 4: Project Under 2021-11- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 002-2022-AF2 / M&E IBRD / 92710 Post Consultant Direct 13,440.00 0.00 Implementation Support Implementation 08 01 18 09 28 31 Officer Selection PRDP-PSO-050-IS-MNE- Individual Component 4: Project 2021-11- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 003-2022-AF2 / M&E IBRD / 92710 Post Consultant Direct 13,440.00 0.00 Under Review Implementation Support 08 01 18 09 28 31 Officer Selection PRDP-PSO-051-IS-SES- Individual Component 4: Project 2021-11- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / SES Unit IBRD / 92710 Post Consultant Direct 19,200.00 0.00 Under Review Implementation Support 08 01 18 09 28 31 Head Selection PRDP-PSO-052-IS-SES- Individual Component 4: Project 2021-11- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 002-2022-AF2 / SES IBRD / 92710 Post Consultant Direct 13,440.00 0.00 Under Review Implementation Support 08 01 18 09 28 31 Officer (Social Safeguards, Selection Envi Safeguards) PRDP-PSO-053-IS-SES- Individual Component 4: Project 2021-11- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 003-2022-AF2 / SES IBRD / 92710 Post Consultant Direct 13,440.00 0.00 Under Review Implementation Support 08 01 18 09 28 31 Officer (Social Safeguards, Selection Envi Safeguards) PRDP-PSO-054-IS-ADM- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / Admin IBRD / 92710 Post Consultant Direct 19,200.00 0.00 Under Review Implementation Support 08 21 18 09 28 31 Unit Head Selection PRDP-PSO-055-IS-ADM- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 002-2022-AF2 / IBRD / 92710 Post Consultant Direct 9,120.00 0.00 Under Review Implementation Support 08 21 18 09 28 31 Administrative Officer II Selection PRDP-RO09-056-IP-001- Individual Component 1: Local and 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Planning IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review National Level Planning 08 19 18 09 28 31 Officer Selection PRDP-RO09-057-IP-002- Individual Component 1: Local and 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Planning IBRD / 92710 Post Consultant Open 12,000.00 0.00 Under Review National Level Planning 15 19 17 08 28 31 Officer Selection PRDP-RO09-058-IB-001- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Direct 36,000.00 0.00 Under Review 08 19 18 09 28 31 Engineers Development Selection PRDP-RO09-059-IB-002- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Direct 36,000.00 0.00 Under Review 08 19 18 09 28 31 Engineers Development Selection PRDP-RO09-060-IB-003- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Direct 36,000.00 0.00 Under Review 08 19 18 09 28 31 Engineers Development Selection PRDP-RO09-061-IB-004- Component 2: Individual 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Open 36,000.00 0.00 Under Review 15 19 17 08 28 31 Engineers Development Selection PRDP-RO09-062-IB-005- Component 2: Individual 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Open 36,000.00 0.00 Under Review 15 19 17 08 28 31 Engineers Development Selection PRDP-RO09-063-IB-006- Component 2: Individual 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Open 36,000.00 0.00 Under Review 15 19 17 08 28 31 Engineers Development Selection PRDP-RO09-064-IB-007- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Project IBRD / 92710 Infrastructure Post Consultant Direct 7,680.00 0.00 Under Review 08 19 18 09 28 31 Development Associate Development Selection PRDP-RO09-065-IR-001- Individual Component 3. Enterprise 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Enterprise Devt IBRD / 92710 Post Consultant Open 13,440.00 0.00 Under Review Development 15 19 17 08 28 31 & Marketing Specialist Selection PRDP-RO09-066-IR-002- Individual Component 3. Enterprise 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Organizational IBRD / 92710 Post Consultant Open 12,000.00 0.00 Canceled Development 15 01 17 08 28 31 Devt Specialist Selection PRDP-RO09-067-IR-003- Individual Component 3. Enterprise 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Business Devt IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review Development 08 19 18 09 28 31 Officer Selection PRDP-RO09-068-IR-004- Individual Component 3. Enterprise 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Project IBRD / 92710 Post Consultant Direct 7,680.00 0.00 Under Review Development 08 21 18 09 28 31 Development Associate Selection PRDP-RO09-069-IS-ADM- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / Admin IBRD / 92710 Post Consultant Direct 7,680.00 0.00 Under Review Implementation Support 08 21 18 09 28 31 Officer II Selection PRDP-RO09-070-IS-FIN- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / Budget IBRD / 92710 Post Consultant Direct 10,560.00 0.00 Under Review Implementation Support 08 21 18 09 28 31 Analyst I Selection PRDP-RO09-071-IS-SES- Individual Component 4: Project 2021-11- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / Associate IBRD / 92710 Post Consultant Direct 10,560.00 0.00 Under Review Implementation Support 08 01 18 09 28 31 SES Officer Selection PRDP-RO09-072-IS-SES- Individual Component 4: Project 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 002-2022-AF2 / Associate IBRD / 92710 Post Consultant Open 10,560.00 0.00 Under Review Implementation Support 15 01 17 08 28 31 SES Officer Selection PRDP-RO09-073-IS-PRO- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / Associate IBRD / 92710 Post Consultant Direct 10,560.00 0.00 Under Review Implementation Support 08 21 18 09 28 31 Procurement Officer Selection PRDP-RO09-074-IS-DPD- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / GIS IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review Implementation Support 08 21 18 09 28 31 Officer Selection PRDP-RO10-075-IP-001- Individual Component 1: Local and 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Planning IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review National Level Planning 08 14 18 09 28 31 Officer Selection PRDP-RO10-076-IP-002- Individual Component 1: Local and 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Planning IBRD / 92710 Post Consultant Open 12,000.00 0.00 Under Review National Level Planning 08 12 17 08 28 31 Officer Selection PRDP-RO10-077-IB-001- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Direct 12,000.00 0.00 Under Review 08 12 18 09 28 31 Engineer Development Selection Page 11 PRDP-RO10-078-IB-002- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Direct 12,000.00 0.00 Under Review 08 14 18 09 28 31 Engineer Development Selection PRDP-RO10-079-IB-003- Component 2: Individual 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Open 12,000.00 0.00 Under Review 15 12 17 08 28 31 Engineer Development Selection PRDP-RO10-080-IB-004- Component 2: Individual 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Open 12,000.00 0.00 Under Review 15 14 17 08 28 31 Engineer Development Selection PRDP-RO10-081-IB-005- Component 2: Individual 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Open 12,000.00 0.00 Under Review 15 14 17 08 28 31 Engineer Development Selection PRDP-RO10-082-IB-006- Component 2: Individual 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Open 12,000.00 0.00 Under Review 15 12 17 08 28 31 Engineer Development Selection PRDP-RO10-083-IB-007- Component 2: Individual 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Open 12,000.00 0.00 Under Review 15 12 17 08 28 31 Engineer Development Selection PRDP-RO10-084-IB-008- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Project IBRD / 92710 Infrastructure Post Consultant Direct 7,680.00 0.00 Under Review 08 18 18 09 28 31 Development Associate Development Selection PRDP-RO10-085-IR-001- Individual Component 3. Enterprise 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Enterprise Devt IBRD / 92710 Post Consultant Open 13,440.00 0.00 Under Review Development 15 12 17 08 28 31 & Marketing Specialist Selection PRDP-RO10-087-IR-003- Individual Component 3. Enterprise 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Business Devt IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review Development 08 12 18 09 28 31 Officer Selection PRDP-RO10-088-IR-004- Individual Component 3. Enterprise 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Business Devt IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review Development 08 12 18 09 28 31 Officer Selection PRDP-RO10-089-IR-005- Individual Component 3. Enterprise 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Project IBRD / 92710 Post Consultant Direct 7,680.00 0.00 Under Review Development 08 17 18 09 28 31 Development Associate Selection Individual PRDP-RO10-090-IS-DPD- Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review 001-2022-AF2 / Economist Implementation Support 08 17 18 09 28 31 Selection PRDP-RO10-091-IS-FIN- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / Finance IBRD / 92710 Post Consultant Direct 10,560.00 0.00 Under Review Implementation Support 08 20 18 09 28 31 Analyst I Selection PRDP-RO10-092-IS-FIN- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 002-2022-AF2 / Finance IBRD / 92710 Post Consultant Direct 10,560.00 0.00 Under Review Implementation Support 08 20 18 09 28 31 Analyst I Selection PRDP-RO10-093-IS-PRO- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / Associate IBRD / 92710 Post Consultant Direct 10,560.00 0.00 Under Review Implementation Support 08 20 18 09 28 31 Procurement Officer Selection PRDP-RO10-094-IS-MNE- Individual Component 4: Project Pending 2021-11- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / Project IBRD / 92710 Post Consultant Direct 7,680.00 0.00 Implementation Support Implementation 08 18 09 28 31 Development Associate Selection PRDP-RO10-095-IS-MNE- Individual Component 4: Project Pending 2021-11- 2021-11- 2021-12- 2021-12- 2022-12- 002-2022-AF2 / Project IBRD / 92710 Post Consultant Direct 7,680.00 0.00 Implementation Support Implementation 08 18 09 28 31 Development Associate Selection PRDP-RO10-096-IS-SES- Individual Component 4: Project 2021-11- 2021-11- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / Associate IBRD / 92710 Post Consultant Direct 10,560.00 0.00 Under Review Implementation Support 08 05 18 09 28 31 SES Officer Selection PRDP-RO10-097-IS-SES- Individual Component 4: Project 2021-10- 2021-11- 2021-11- 2021-12- 2021-12- 2022-12- 002-2022-AF2 / Associate IBRD / 92710 Post Consultant Open 10,560.00 0.00 Under Review Implementation Support 15 05 17 08 28 31 SES Officer (additional) Selection PRDP-RO10-098-IS-DPD- Individual Component 4: Project Pending 2021-11- 2021-11- 2021-12- 2021-12- 2022-12- 002-2022-AF2 / Project IBRD / 92710 Post Consultant Direct 7,680.00 0.00 Implementation Support Implementation 08 18 09 28 31 Development Associate Selection PRDP-RO11-099-IP-001- Individual Component 1: Local and 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Planning IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review National Level Planning 08 19 18 09 28 31 Officer Selection PRDP-RO11-100-IP-002- Individual Component 1: Local and 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Planning IBRD / 92710 Post Consultant Open 12,000.00 0.00 Under Review National Level Planning 15 19 17 08 28 31 Officer Selection PRDP-RO11-101-IB-001- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Direct 12,000.00 0.00 Under Review 08 19 18 09 28 31 Engineer Development Selection PRDP-RO11-102-IB-002- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Direct 12,000.00 0.00 Under Review 08 11 18 09 28 31 Engineer Development Selection PRDP-RO11-103-IB-003- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Direct 12,000.00 0.00 Under Review 08 19 18 09 28 31 Engineer Development Selection PRDP-RO11-104-IB-004- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Direct 12,000.00 0.00 Under Review 08 19 18 09 28 31 Engineer Development Selection PRDP-RO11-105-IB-005- Component 2: Individual 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Open 12,000.00 0.00 Under Review 15 19 17 08 28 31 Engineer Development Selection PRDP-RO11-106-IB-006- Component 2: Individual 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Open 12,000.00 0.00 Under Review 15 19 17 08 28 31 Engineer Development Selection PRDP-RO11-107-IB-007- Component 2: Individual 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Open 12,000.00 0.00 Under Review 15 19 17 08 28 31 Engineer Development Selection PRDP-RO11-108-IB-008- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Project IBRD / 92710 Infrastructure Post Consultant Direct 7,680.00 0.00 Under Review 08 19 18 09 28 31 Development Associate Development Selection PRDP-RO11-109-IR-001- Individual Component 3. Enterprise 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Enterprise Devt IBRD / 92710 Post Consultant Open 13,440.00 0.00 Under Review Development 15 19 17 08 28 31 & Marketing Specialist Selection PRDP-RO11-111-IR-003- Individual Component 3. Enterprise 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Business Devt IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review Development 08 19 18 09 28 31 Officer Selection PRDP-RO11-112-IR-004- Individual Component 3. Enterprise 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Business Devt IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review Development 08 11 18 09 28 31 Officer Selection PRDP-RO11-113-IR-005- Individual Component 3. Enterprise 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Business Devt IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review Development 08 19 18 09 28 31 Officer Selection PRDP-RO11-114-IR-006- Individual Component 3. Enterprise 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Project IBRD / 92710 Post Consultant Direct 7,680.00 0.00 Under Review Development 08 19 18 09 28 31 Development Associate Selection PRDP-RO12-125-IP-001- Individual Component 1: Local and 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Planning IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review National Level Planning 08 21 18 09 28 31 Officer Selection PRDP-RO12-126-IP-002- Individual Component 1: Local and 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Planning IBRD / 92710 Post Consultant Open 12,000.00 0.00 Under Review National Level Planning 15 21 17 08 28 31 Officer Selection PRDP-RO12-127-IB-001- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Direct 36,000.00 0.00 Under Review 08 21 18 09 28 31 Engineers Development Selection PRDP-RO12-128-IB-002- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Direct 36,000.00 0.00 Under Review 08 21 18 09 28 31 Engineers Development Selection PRDP-RO12-129-IB-003- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Direct 36,000.00 0.00 Under Review 08 21 18 09 28 31 Engineers Development Selection PRDP-RO12-130-IB-004- Component 2: Individual 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Open 36,000.00 0.00 Under Review 15 21 17 08 28 31 Engineers Development Selection PRDP-RO12-131-IB-005- Component 2: Individual 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Open 36,000.00 0.00 Under Review 15 21 17 08 28 31 Engineers Development Selection PRDP-RO12-132-IB-006- Component 2: Individual 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Open 36,000.00 0.00 Under Review 15 21 17 08 28 31 Engineers Development Selection PRDP-RO12-133-IB-007- Component 2: Individual 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Open 36,000.00 0.00 Under Review 15 21 17 08 28 31 Engineers Development Selection PRDP-RO12-134-IB-008- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Project IBRD / 92710 Infrastructure Post Consultant Direct 7,680.00 0.00 Under Review 08 21 18 09 28 31 Development Associate Development Selection PRDP-RO12-135-IR-001- Individual Component 3. Enterprise 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Enterprise Devt IBRD / 92710 Post Consultant Open 13,440.00 0.00 Under Review Development 15 21 17 08 28 31 & Marketing Specialist Selection PRDP-RO12-137-IR-003- Individual Component 3. Enterprise 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Business Devt IBRD / 92710 Post Consultant Direct 36,000.00 0.00 Under Review Development 08 21 18 09 28 31 Officer Selection PRDP-RO12-138-IR-004- Individual Component 3. Enterprise 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Business Devt IBRD / 92710 Post Consultant Direct 36,000.00 0.00 Under Review Development 08 21 18 09 28 31 Officer Selection PRDP-RO12-139-IR-005- Individual Component 3. Enterprise 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Business Devt IBRD / 92710 Post Consultant Direct 36,000.00 0.00 Under Review Development 08 21 18 09 28 31 Officer Selection PRDP-RO12-140-IR-006- Individual Component 3. Enterprise 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Project IBRD / 92710 Post Consultant Direct 7,680.00 0.00 Under Review Development 08 21 18 09 28 31 Development Associate Selection PRDP-RO12-141-IS-FIN- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / Finance IBRD / 92710 Post Consultant Direct 21,120.00 0.00 Under Review Implementation Support 08 21 18 09 28 31 Analyst I Selection PRDP-RO12-142-IS-FIN- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 002-2022-AF2 / Finance IBRD / 92710 Post Consultant Direct 21,120.00 0.00 Under Review Implementation Support 08 21 18 09 28 31 Analyst I Selection PRDP-RO12-143-IS-FIN- Individual Component 4: Project 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 003-2022-AF2 / Budget IBRD / 92710 Post Consultant Open 10,560.00 0.00 Under Review Implementation Support 15 21 17 08 28 31 Analyst Selection PRDP-RO12-144-IS-GGU- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / GIS IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review Implementation Support 08 21 18 09 28 31 Officer Selection PRDP-RO12-145-IS-PRO- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / Associate IBRD / 92710 Post Consultant Direct 10,560.00 0.00 Under Review Implementation Support 08 21 18 09 28 31 Procurement Officer Selection PRDP-RO12-146-IS-MNE- Individual Component 4: Project 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / Associate IBRD / 92710 Post Consultant Open 10,560.00 0.00 Under Review Implementation Support 15 21 17 08 28 31 M&E Officer Selection PRDP-RO12-147-IS-SES- Individual 001-2022-AF2 / SES Component 4: Project 2021-11- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review Officer (Social Safeguards, Implementation Support 08 01 18 09 28 31 Selection Environmental Safegeuards) Page 12 PRDP-RO12-148-IS-SES- Individual Component 4: Project 2021-11- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 002-2022-AF2 / Associate IBRD / 92710 Post Consultant Direct 10,560.00 0.00 Under Review Implementation Support 08 01 18 09 28 31 SES Officer Selection PRDP-RO12-149-IS-SES- Individual Component 4: Project 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 003-2022-AF2 / Associate IBRD / 92710 Post Consultant Open 10,560.00 0.00 Under Review Implementation Support 15 01 17 08 28 31 SES Officer Selection PRDP-RO12-150-IS-ADM- Individual Component 4: Project 2021-11- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / Admin IBRD / 92710 Post Consultant Direct 7,680.00 0.00 Under Review Implementation Support 08 01 18 09 28 31 Officer II Selection Individual PRDP-RO12-151-IS-DPD- Component 4: Project 2021-11- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review 001-2022-AF2 / Economist Implementation Support 08 01 18 09 28 31 Selection PRDP-RO13-152-IP-001- Individual Component 1: Local and 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Planning IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review National Level Planning 08 17 18 09 28 31 Officer Selection PRDP-RO13-153-IP-002- Individual Component 1: Local and 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Planning IBRD / 92710 Post Consultant Open 12,000.00 0.00 Under Review National Level Planning 15 17 17 08 28 31 Officer Selection PRDP-RO13-154-IP-003- Individual Component 1: Local and 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Project IBRD / 92710 Post Consultant Open 7,680.00 0.00 Under Review National Level Planning 15 17 17 08 28 31 Development Associate Selection PRDP-RO13-155-IB-001- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Direct 13,440.00 0.00 Under Review 08 17 18 09 28 31 Specialist Development Selection PRDP-RO13-156-IB-002- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Direct 12,000.00 0.00 Under Review 08 17 18 09 28 31 Engineer Development Selection PRDP-RO13-157-IB-003- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Direct 12,000.00 0.00 Under Review 08 17 18 09 28 31 Engineer Development Selection PRDP-RO13-158-IB-004- Component 2: Individual 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Open 12,000.00 0.00 Under Review 15 17 17 08 28 31 Engineer Development Selection PRDP-RO13-159-IB-005- Component 2: Individual 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Open 12,000.00 0.00 Under Review 15 17 17 08 28 31 Engineer Development Selection PRDP-RO13-160-IB-006- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Direct 12,000.00 0.00 Under Review 08 17 18 09 28 31 Engineer Development Selection PRDP-RO13-161-IB-007- Component 2: Individual 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Open 12,000.00 0.00 Under Review 15 17 17 08 28 31 Engineer Development Selection PRDP-RO13-162-IB-008- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Project IBRD / 92710 Infrastructure Post Consultant Direct 7,680.00 0.00 Under Review 08 20 18 09 28 31 Development Associate Development Selection PRDP-RO13-163-IR-001- Individual Component 3. Enterprise 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Enterprise Devt IBRD / 92710 Post Consultant Open 13,440.00 0.00 Under Review Development 15 20 17 08 28 31 & Marketing Specialist Selection PRDP-RO13-165-IR-003- Individual Component 3. Enterprise 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Business Devt IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review Development 08 20 18 09 28 31 Officer Selection PRDP-RO13-166-IR-004- Individual Component 3. Enterprise 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Project IBRD / 92710 Post Consultant Direct 7,680.00 0.00 Under Review Development 08 20 18 09 28 31 Development Associate Selection PRDP-RO13-167-IS-FIN- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / Finance IBRD / 92710 Post Consultant Direct 10,560.00 0.00 Under Review Implementation Support 08 20 18 09 28 31 Analyst I Selection PRDP-RO13-168-IS-PRO- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / Associate IBRD / 92710 Post Consultant Direct 10,560.00 0.00 Under Review Implementation Support 08 20 18 09 28 31 Procurement Officer Selection PRDP-RO13-169-IS-MNE- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / M&E IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review Implementation Support 08 22 18 09 28 31 Officer Selection PRDP-RO13-170-IS-MNE- Individual Component 4: Project 2021-11- 2021-11- 2021-11- 2021-12- 2021-12- 2022-12- 002-2022-AF2 / Associate IBRD / 92710 Post Consultant Direct 10,560.00 0.00 Under Review Implementation Support 08 05 18 09 28 31 M&E Officer Selection PRDP-RO13-171-IS-SES- Individual 001-2022-AF2 / SES Component 4: Project 2021-11- 2021-11- 2021-11- 2021-12- 2021-12- 2022-12- IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review Officer (Social Safeguards, Implementation Support 08 05 18 09 28 31 Selection Environmental Safegeuards) PRDP-RO13-172-IS-SES- Individual Component 4: Project 2021-10- 2021-11- 2021-11- 2021-12- 2021-12- 2022-12- 002-2022-AF2 / Associate IBRD / 92710 Post Consultant Open 10,560.00 0.00 Under Review Implementation Support 15 05 17 08 28 31 SES Officer (additional) Selection PRDP-RO13-173-IS-DPD- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / GIS Data IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review Implementation Support 08 22 18 09 28 31 Officer Selection Individual PRDP-RO13-174-IS-DPD- Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- IBRD / 92710 Post Consultant Direct 10,560.00 0.00 Under Review 002-2022-AF2 / Writer Implementation Support 08 20 18 09 28 31 Selection PRDP-BARMM-175-IP-001- Individual Component 1: Local and 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Planning IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review National Level Planning 08 13 18 09 28 31 Officer Selection PRDP-BARMM-176-IP-002- Individual Component 1: Local and 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Planning IBRD / 92710 Post Consultant Open 12,000.00 0.00 Under Review National Level Planning 15 13 17 08 28 31 Officer Selection PRDP-BARMM-177-IB-001- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Direct 13,440.00 0.00 Under Review 08 13 18 09 28 31 Specialist Development Selection PRDP-BARMM-178-IB-002- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Direct 12,000.00 0.00 Under Review 08 13 18 09 28 31 Engineer Development Selection PRDP-BARMM-179-IB-003- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Direct 12,000.00 0.00 Under Review 08 13 18 09 28 31 Engineer Development Selection PRDP-BARMM-180-IB-004- Component 2: Individual 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Open 12,000.00 0.00 Under Review 15 13 17 08 28 31 Engineer Development Selection PRDP-BARMM-181-IB-005- Component 2: Individual 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Open 12,000.00 0.00 Under Review 15 13 17 08 28 31 Engineer Development Selection PRDP-BARMM-182-IB-006- Component 2: Individual 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Rural Infra IBRD / 92710 Infrastructure Post Consultant Open 12,000.00 0.00 Under Review 15 13 17 08 28 31 Engineer Development Selection PRDP-BARMM-183-IB-007- Component 2: Individual 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Project IBRD / 92710 Infrastructure Post Consultant Direct 7,680.00 0.00 Under Review 08 13 18 09 28 31 Development Associate Development Selection PRDP-BARMM-184-IR-001- Individual Component 3. Enterprise 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Enterprise Devt IBRD / 92710 Post Consultant Open 13,440.00 0.00 Under Review Development 15 25 17 08 28 31 & Marketing Specialist Selection PRDP-BARMM-186-IR-003- Individual Component 3. Enterprise 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Business Devt IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review Development 08 27 18 09 28 31 Officer Selection PRDP-BARMM-187-IR-004- Individual Component 3. Enterprise 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Business Devt IBRD / 92710 Post Consultant Open 12,000.00 0.00 Under Review Development 15 27 17 08 28 31 Officer Selection PRDP-BARMM-188-IR-005- Individual Component 3. Enterprise 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Business Devt IBRD / 92710 Post Consultant Open 12,000.00 0.00 Under Review Development 15 27 17 08 28 31 Officer Selection PRDP-BARMM-189-IR-006- Individual Component 3. Enterprise 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Business Devt IBRD / 92710 Post Consultant Open 12,000.00 0.00 Under Review Development 15 27 17 08 28 31 Officer Selection PRDP-BARMM-190-IR-007- Individual Component 3. Enterprise 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Project IBRD / 92710 Post Consultant Direct 7,680.00 0.00 Under Review Development 08 27 18 09 28 31 Development Associate Selection PRDP-BARMM-191-IS- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- ADM-001-2022-AF2 / IBRD / 92710 Post Consultant Direct 13,440.00 0.00 Under Review Implementation Support 08 27 18 09 28 31 Admin Officer II Selection Individual PRDP-BARMM-192-IS-DPD- Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- IBRD / 92710 Post Consultant Direct 13,440.00 0.00 Under Review 001-2022-AF2 / Economist Implementation Support 08 27 18 09 28 31 Selection PRDP-BARMM-193-IS-PRO- Individual Component 4: Project 2021-11- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / Associate IBRD / 92710 Post Consultant Direct 13,440.00 0.00 Under Review Implementation Support 08 01 18 09 28 31 Procurement Officer Selection PRDP-BARMM-194-IS-FIN- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / Finance IBRD / 92710 Post Consultant Direct 13,440.00 0.00 Under Review Implementation Support 08 27 18 09 28 31 Analyst I Selection PRDP-BARMM-195-IS-FIN- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 002-2022-AF2 / Finance IBRD / 92710 Post Consultant Direct 13,440.00 0.00 Under Review Implementation Support 08 27 18 09 28 31 Analyst I Selection PRDP-BARMM-196-IS-FIN- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 003-2022-AF2 / Budget IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review Implementation Support 08 27 18 09 28 31 Analyst I Selection PRDP-BARMM-197-IS-DPD- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 002-2022-AF2 / GIS IBRD / 92710 Post Consultant Direct 13,440.00 0.00 Under Review Implementation Support 08 27 18 09 28 31 Officer Selection PRDP-BARMM-198-IS-MNE- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / M&E IBRD / 92710 Post Consultant Direct 13,440.00 0.00 Under Review Implementation Support 08 27 18 09 28 31 Officer Selection PRDP-BARMM-199-IS-MNE- Individual Component 4: Project 2021-11- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 002-2022-AF2 / Associate IBRD / 92710 Post Consultant Direct 13,440.00 0.00 Under Review Implementation Support 08 01 18 09 28 31 M&E Officer Selection PRDP-BARMM-200-IS-SES- Individual 001-2022-AF2 / SES Component 4: Project 2021-11- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review Officer (Social Safeguards, Implementation Support 08 01 18 09 28 31 Selection Environmental Safegeuards) PRDP-BARMM-201-IS-SES- Individual Component 4: Project 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 002-2022-AF2 / Associate IBRD / 92710 Post Consultant Open 13,440.00 0.00 Under Review Implementation Support 15 01 17 08 28 31 SES Officer (additional) Selection PRDP-BARMM-202-IS-SES- Individual Component 4: Project 2021-11- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 003-2022-AF2 / Associate IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review Implementation Support 08 01 18 09 28 31 SES Officer Selection Individual PRDP-RO09-002-IP-001- Component 1: Local and Under 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- TF / B5756 Post Consultant Open 12,000.00 0.00 2022-EU / Planning Officer National Level Planning Implementation 15 01 17 08 28 31 Selection Individual PRDP-RO10-003-IP-001- Component 1: Local and 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- TF / B5756 Post Consultant Open 12,000.00 0.00 Under Review 2022-EU / Planning Officer National Level Planning 15 22 17 08 28 31 Selection Individual PRDP-RO11-004-IP-001- Component 1: Local and Under 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- TF / B5756 Post Consultant Open 12,000.00 0.00 2022-EU / Planning Officer National Level Planning Implementation 15 01 17 08 28 31 Selection Individual PRDP-RO12-005-IP-001- Component 1: Local and Under 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- TF / B5756 Post Consultant Open 12,000.00 0.00 2022-EU / Planning Officer National Level Planning Implementation 15 01 17 08 28 31 Selection Page 13 Individual PRDP-RO13-006-IP-001- Component 1: Local and 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- TF / B5756 Post Consultant Open 12,000.00 0.00 Under Review 2022-EU / Planning Officer National Level Planning 15 22 17 08 28 31 Selection Individual PRDP-BARM-007-IP-001- Component 1: Local and Under 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- TF / B5756 Post Consultant Open 12,000.00 0.00 2022-EU / Planning Officer National Level Planning Implementation 15 01 17 08 28 31 Selection PRDP-RO11-115-IS-MNE- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / M&E IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review Implementation Support 08 19 18 09 28 31 Officer Selection PRDP-RO11-116-IS-FIN- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / Finance IBRD / 92710 Post Consultant Direct 10,560.00 0.00 Under Review Implementation Support 08 19 18 09 28 31 Analyst I Selection PRDP-RO11-117-IS-FIN- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 002-2022-AF2 / Finance IBRD / 92710 Post Consultant Direct 10,560.00 0.00 Under Review Implementation Support 08 19 18 09 28 31 Analyst I Selection PRDP-RO11-118-IS-FIN- Individual Component 4: Project 2021-11- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 003-2022-AF2 / Budget IBRD / 92710 Post Consultant Direct 10,560.00 0.00 Under Review Implementation Support 08 01 18 09 28 31 Analyst Selection PRDP-RO11-119-IS-PRO- Individual Component 4: Project 2021-11- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / IBRD / 92710 Post Consultant Direct 10,560.00 0.00 Under Review Implementation Support 08 01 18 09 28 31 Procurement Officer Selection PRDP-RO11-120-IS-DPD- Individual Component 4: Project 2021-11- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / GIS Data IBRD / 92710 Post Consultant Direct 7,680.00 0.00 Under Review Implementation Support 08 19 18 09 28 31 Officer Selection PRDP-RO11-121-IS-SES- Individual 001-2022-AF2 / SES Component 4: Project 2021-11- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- IBRD / 92710 Post Consultant Direct 7,680.00 0.00 Under Review Officer (Social Safeguards, Implementation Support 08 01 18 09 28 31 Selection Environmental Safeguards) PRDP-RO11-122-IS-SES- Individual Component 4: Project 2021-11- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 002-2022-AF2 / Associate IBRD / 92710 Post Consultant Direct 10,560.00 0.00 Under Review Implementation Support 08 01 18 09 28 31 SES Officer Selection PRDP-RO11-123-IS-SES- Individual Component 4: Project 2021-10- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- 003-2022-AF2 / Associate IBRD / 92710 Post Consultant Open 10,560.00 0.00 Under Review Implementation Support 15 01 17 08 28 31 SES Officer (additional) Selection Individual PRDP-RO11-124-IS-DPD- Component 4: Project 2021-11- 2021-12- 2021-11- 2021-12- 2021-12- 2022-12- IBRD / 92710 Post Consultant Direct 12,000.00 0.00 Under Review 002-2022-AF2 / Economist Implementation Support 08 01 18 09 28 31 Selection PRDP-RO10-086-IR-002- Individual Component 3. Enterprise Pending 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Organizational IBRD / 92710 Post Consultant Open 12,000.00 0.00 Development Implementation 15 17 08 28 31 Devt Officer Selection PRDP-RO11-110-IR-002- Individual Component 3. Enterprise Pending 2021-10- 2021-12- 2021-12- 2022-01- 2023-01- 2022-AF2 / Organizational IBRD / 92710 Post Consultant Open 12,000.00 0.00 Development Implementation 15 03 24 12 15 Devt Officer Selection PRDP-RO12-136-IR-002- Individual Component 3. Enterprise Pending 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Organizational IBRD / 92710 Post Consultant Open 12,000.00 0.00 Development Implementation 15 17 08 28 31 Devt Officer Selection PRDP-RO13-164-IR-002- Individual Component 3. Enterprise Pending 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Organizational IBRD / 92710 Post Consultant Open 12,000.00 0.00 Development Implementation 15 17 08 28 31 Devt Officer Selection PRDP-BARMM-185-IR-002- Individual Component 3. Enterprise Pending 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- 2022-AF2 / Organizational IBRD / 92710 Post Consultant Open 12,000.00 0.00 Development Implementation 15 17 08 28 31 Devt Officer Selection PRDP-RO09-066-IR-002- Individual Component 3. Enterprise Pending 2021-12- 2022-01- 2022-02- 2022-02- 2022-12- 2022-AF2-A / IBRD / 92710 Post Consultant Open 12,000.00 0.00 Development Implementation 02 11 01 21 31 Organizational Devt Officer Selection PRDP-PSO-036-IS-FIN- Individual Component 4: Project Pending 2021-11- 2021-11- 2021-12- 2021-12- 2022-12- 001-2022-AF2 / Finance IBRD / 92710 Post Consultant Direct 19,200.00 0.00 Implementation Support Implementation 08 18 09 28 31 Unit Head Selection Individual PRDP-PSO-011-IS-ODP- Component 4: Project Pending 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- TF / B5756 Post Consultant Open 13,920.00 0.00 002-2022-EU / GIS Officer Implementation Support Implementation 15 17 08 28 31 Selection Individual PRDP-PSO-012-IS-ODP- Component 4: Project Pending 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- TF / B5756 Post Consultant Open 13,920.00 0.00 003-2022-EU / GIS Officer Implementation Support Implementation 15 17 08 28 31 Selection Page 14