PROCUREMENT PLAN (Textual Part) Project information: Country: Nigeria Project Name: Multi-Sectoral Crisis Recovery Project for North East Nigeria (MCRP) P- Number: P157891 Project Implementation Agency: MCRP PCU (Federal and States) Date of the Procurement Plan: Updated -December 22, 2017. Period covered by this Procurement Plan: From 01/12/2018 – 30/06/2019. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the FGN Public Procurement Act 2007; such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each: Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. 1. Prior Review Threshold for Goods, Works and Non-Consulting Services: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Prior Review Procurement Method Threshold (US$ Comments equivalent) ICB and LIB (Goods and services other than ≥ 5,000,000 ALL consultancy services) NCB (Goods, IT Systems and Non Consulting Services 100,000 < 5,000,000 NONE (NCB) ICB (Works) ≥ 20,000,000 ALL NCB (Works) 150,000 < 20,000,000 NONE Shopping-Goods ≤ 100,000 NONE Shopping-Works ≤ 150,000 NONE Based on Annual Training, Workshops, Study All Values Work Plans & Tours Budgets 2. Prequalification: Bidders for major works shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines, although it is not expected that there will be need for prequalification in the procurement arrangements for the MCRP. MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 2 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT 3. Proposed Procedures for CDD Components (as per paragraph. 6.52 of the Procurement Regulations): Shall apply. 4. Reference to the Project Implementation Manual: Shall apply. 5. Any Other Special Procurement Arrangements: Not Applicable 6. Procurement Packages (Goods and Works) indicating Bank’s Prior and Post Review. MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 3 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT a. Summary of Procurement of Goods: 1 2 3 4 5 6 Review by Estimated Ref. Packag Bank Commen Description Cost (US$ No. es (Prior / ts Million) Post) Total NCB 12.82 43 Post (Goods) Total RfQ (Goods/Non 0.04 1 Post Consulting Services) Procurement of Goods with Selection Methods and Time Schedule (Please see Annex I). b. Summary of Procurement of Civil Works 1 2 3 4 5 6 Review by Estimated Ref. Bank Commen Description Cost (US$ Packages No. (Prior / ts Million) Post) Total NCB 23.59 64 Post (Works) Total RfQ 2.29 20 Post (Works) Procurement of Civil Works with Selection Methods and Time Schedule (Please see Annex II). c. Summary of Procurement of Non- Consulting Services (TBD) 1 2 3 4 5 6 Review by Estimated Ref. Bank Commen Description Cost (US$ Packages No. (Prior / ts Million) Post) Total NCB 0.175 2 Post MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 4 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT 7. Prior Review Threshold for Consultancies: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Prior Review Selection Method Comments Threshold (USD) Consultant Services-QCBS- International 1. Consulting Services ≥ 300,000 ALL 2. Engineering and Construction ≥ 500,000 Supervision Consultant Services-QCBS < 300,000.00 NONE Consultant Services-CQS < 300,000.00 NONE Consultant Services-lC >300,000.00 ALL Consultant Services-lC <300,000.00 NONE Consultant Services- Single Source All Values ALL Selection Note: All ToRs to be prior review QCBS = Quality and Cost Based Selection SSS = Single Source Selection CQ = Consultant Qualification LCS = Least Cost Selection IC = Individual Consultant 8. Short list comprising entirely of National Consultants: Short list of consultants for services, estimated to cost less than $300,000.00 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. a. Summary of Consultancies 1 2 3 4 5 6 Ref. Description Estimate Package Review by Comment No. d Cost s Bank s (US$ (Prior/Post Million) ) Summary of number of 5.72 7 Prior contracts that will be let under International QCBS Summary of number of 6.45 16 Post contracts that will be let under National QCBS Summary of number of 1.74 30 Post contracts that will be let under CQS Summary of number of 0.35 3 Post contracts that will be let under MOU MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 5 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Summary of number of 0.021 3 Post contracts that will be let under Individual Consultancies MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 6 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Estimated Estimated Prior Number of Amount in Investable or Expected Procureme Pre- USD (Over Amount Post Bid- Description (List of Componen nt Procureme qualificati the Project for 18 Revie Opening Contracts) t/Sector Packages nt Method on Life) months w Date WORKS BORNO Construction Of 18-No Double Classroom Blocks in Ngohi, Biji-Biji, Ngulde, C2/Educati Post Tue-19-Jun- Rumirgo, Chul on 3 NCB No 708,196.72 354,098.36 Review 18 Construction Of 10- No. Double Classroom Block - C2/Educati Post Tue-19-Jun- Bama (Banki Town) on 2 NCB No 393,442.62 314,754.10 Review 18 Reconstruction Of 39- No. Double Classroom Block in C2/Educati Post Damasak, Mobbar on 4 NCB No 575,409.84 71,926.23 Review Tue-24-Jul-18 Construction Of 15- No. Double Classroom Block - C2/Educati Post Gajibo, Logomane (Dikwa) on 2 NCB No 590,163.93 147,540.98 Review Tue-24-Jul-18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 7 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Construction Of 25 No. Double Classroom Block C2/Educati Post GUZAMALA on 2 NCB No 983,606.56 245,901.64 Review Tue-24-Jul-18 Construction Of 20- No. Double Classroom Block - Kukawa Town, Baga, Cross- C2/Educati Post Tue-18-Sep- Kauwa on 2 NCB No 786,885.25 196,721.31 Review 18 Construction Of 10- No. Double Classroom Block - C2/Educati Post Tue-18-Sep- Monguno on 1 NCB No 393,442.62 98,360.66 Review 18 Construction Of 4- No. Double Classroom Block in C2/Educati Post Tue-20-Nov- Ajiri. Mafa on 1 NCB No 157,377.05 39,344.26 Review 18 Renovation Of 20- No. Double Classroom Blockin C2/Educati Post Tue-20-Nov- Damboa Town -Abadam on 2 NCB No 295,081.97 73,770.49 Review 18 Renovation Of 31- No. Double Classroom Block - C2/Educati Post Tue-23-Oct- Bama on 2 NCB No 457,377.05 114,344.26 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 8 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Construction Of 3-No. C2/Educati Post Tue-18-Sep- Educational Office -Kukawa on 1 NCB No 196,721.31 98,360.66 Review 18 Construction Of 2-No. Educational Office - C2/Educati Post Tue-20-Nov- Konduga on 1 NCB No 131,147.54 32,786.89 Review 18 Construction Of 2-No. Educational Office -Hawul C2/Educati Post Tue-23-Oct- Sakwa, Kwajafa on 1 NCB No 131,147.54 32,786.89 Review 18 Construction Of 4-No Vip C2/Educati Post Tue-18-Dec- Toilets -Askira-Uba on 1 RfQ No 59,016.39 47,213.11 Review 18 Construction Of 4-No Vip C2/Educati Post Tue-18-Dec- Toilets -Mafa on 1 RfQ No 59,016.39 47,213.11 Review 18 Construction Of 5-No Vip C2/Educati Post Tue-18-Dec- Toilets -Monguno on 1 RfQ No 73,770.49 59,016.39 Review 18 Renovation Of 1-No. Educational Office - C2/Educati Post Tue-18-Dec- Damboa on 1 RfQ No 18,032.79 4,508.20 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 9 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Renovation Of 1-No. Educational Office and 1- No. Principal's Quarters - Benisheik, Kaga- Benisheik, C2/Educati Post Tue-23-Oct- Kaga on 1 RfQ No 42,622.95 16,803.28 Review 18 Rehabilitation of 66KM C2/Transpo 1,223,144. Prior Tue-27-Feb- Maiduguri to Bama road rt 1 NCB No 9,785,152.68 08 Review 18 Rehabilitation of 1 Ngala C2/Transpo Prior Tue-27-Feb- Bridge rt 1 NCB No 2,295,081.97 483,983.71 Review 18 C2/Transpo Post Tue-27-Feb- Rehabilitation of Biu bridge rt 1 NCB No 902,111.48 73,770.49 Review 18 Construction of galameri- dusuman-zabarmari- C2/Transpo Prior Tue-27-Feb- gongulong feeder road rt 1 NCB No 1,104,625.69 59,016.39 Review 18 RehabilitatIon of 3 General Hospital in ABADAM, ASKIRA UBA, KALA-BALGEe and Rehabilitation of Prior Tue-27-Mar- comprehensive Healthcare C2/Health 3 NCB No 1,555,779.01 986,195.83 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 10 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT center (Civil Works, Solar Borehole, Fence & Security Post) Construction of PHC for 15 2,254,098. Prior Tue-27-Mar- LGAs C2/Health 5 NCB No 3,606,557.38 36 Review 18 Rehabilitation of Borno C2/Educati Post Tue-24-Apr- State Library on 2 NCB No 557,377.05 34,426.23 Review 18 Rehabilitation of Umar Ibn C2/Educati Post Tue-24-Apr- Ibrahim college Bama on 2 NCB No 557,377.05 278,688.52 Review 18 Construction of Solar Powered Boreholes (2Nos) in Umar Ibn Ibrahim college Bama Solar Lighting System to Borno C2/Educati Post Tue-24-Apr- Library on 1 NCB No 196,721.31 98,360.66 Review 18 Rehabilitation of Court Buildings in Bama Gwoza C2/Public Post Tue-22-May- Dikwa Mobbar Buildings 4 RfQ No 393,442.62 49,180.33 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 11 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Local Govt Secretariats in Kukawa, Monguno, biu ,Abadam, Kala-Balge, Marte, C2/Public 1,229,508. Post Tue-05-Jun- Magumeri, Guzamala Buildings 8 RfQ No 1,967,213.11 20 Review 18 Rehabilitation of Traditional Rulers' Konduga , Monguno, Kukawa, Nganzai, Baga, Marte, Ngala, Abadam, Guzamala, C2/Public Post Tue-05-Jun- Kwajafa, Kumshe Buildings 6 RfQ No 1,442,622.95 180,327.87 Review 18 Provision of Community Resource Centres in 20 C2/Public Post LGAs Buildings 10 NCB No 2,295,081.97 860,655.74 Review Thu-05-Jul-18 Construction of Handpump Wells in Bama (3) Chibok (5), Biu (5), Mafa(3), Hawul (5), Askira/Uba(5), Konduga(4), Jere(5) Dikwa Post Fri-03-Aug- (3), Gwoza(5), C2/WASH 10 RfQ No 140,983.61 35,245.90 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 12 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Construction of Solar Powered Boreholes in Askira Uba Gwoza(4),Bama(4), Ngala(3), Damboa(3) Jere(4),Kukawa(3), Biu(2),Konduga(3), Gubio(3), Askira/Uba(3), Magumeri(3), Marte(3), Mobbar(3), Monguno(3), Dikwa(2), Mafa(3), Abadam(3), Nganzai(3), Guzamala(3), Kaga(2), Chibok(2), Kala/Balge(3), Hawul(2)(To include 2Nos 5,000lt Plastic water tanks on a 1.5m raised platform , five fetching points/tap gallery, chain link 3,501,639. Post Wed-25-Jul- perimeter fence) C2/WASH 14 NCB No 4,668,852.46 34 Review 18 REHABILITATION OF LOCAL GOVERNMENT LODGES (Marte, Kaga, Chibok, Magumeri, Gwoza, Kala- Balge, Ngala, Guzamala, Abadam, Hawul, C2/Public Post Tue-21-Aug- Askira/Uba, Bama) Buildings 6 NCB No 1,311,475.41 786,885 Review 18 Rehabilitationof Traditional Rulers' Buildings Bama, Konduga, Gwoza ,Kareto, C2/Public Post Damboa , Monguno, Buildings 11 RfQ No 1,442,622.95 180,327.87 Review Thu-26-Jul-18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 13 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Kukawa, Askira-Uba , Dikwa, Baga, Marte REHABILITATION OF MINISTRY BUILDING (Ngala, C2/Public Post Tue-21-Aug- Monguno) Buildings 2 NCB No 276,577 Review 18 CONSTRUCTION OF SANITATION FACILITIES IN 21 LOCAL GOVERNMENT AREAS.ABADAM (6) ASKIRA(6) BAMA(6) BIU(6) CHIBOK(6) DAMBOA(6) DIKWA(6) GUBIO(6) GWOZA(6) JERE(6) KAGA(6) KALA-BALGE(6) KONDUGA(6) KUKAWA(6) MAFA(5) MOBBAR(6) MONGUNO(6) MARTE(6) NGALA(6) NGANZAI(6) Post Wed-19-Sep- MAGUMERI(6) C2/WASH 21 NCB No 781,517 Review 18 REHABILITATION OF EXISTING NON- FUNCTIONAL BOREHOLES ABADAM (1) ASKIRA UBA (2) BIU (2) DIKWA (1) Post Tue-18-Sep- GUBIO (1) GUZAMALA (1) C2/WASH 6 NCB No 258,525 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 14 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT JERE (2) KALA BALGE (1) MAFA (2) MAGUMERI (1) MARTE (2) MOBBAR (1) NGALA (1) NGANZAI (1) Rehabilitation of 8 blocks of Laborataries (Umar Ibn C1/Educati Post Tue-18-Sep- Ibrahim college Bama) on 1 NCB No 262,295 Review 18 ADAMAWA Rehabilitation of Gulak Post Mon-14-May- Water Supply System C2/Water 1 NCB No 179,190.16 134,392.62 Review 18 Rehabilitation of Hong Post Mon-14-May- Water Supply System C2/Water 1 NCB No 116,646.90 87,485.18 Review 18 Rehabilitation of Michika Post Mon-14-May- Water supply system C2/Water 1 NCB No 138,193.44 103,645.08 Review 18 Rehabilitation of Uba Water Post Tue-15-May- Supply system C2/Water 1 NCB No 71,967.21 71,967.21 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 15 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of exisitng Water Supply sources in Post Tue-15-May- Gombi C2/Water 1 NCB No 30,475.41 30,475.41 Review 18 Construction of Uba New Post Mon-28-May- Water Supply Project C2/Water 1 NCB No 721,222.95 108,183.44 Review 18 Pella New Water Supply Post Mon-28-May- Project C2/Water 1 NCB No 555,289.34 83,293.40 Review 18 Construction of Hong New Post Mon-28-May- Water supply project C2/Water 1 NCB No 1,256,442.62 188,466.39 Review 18 Construction of Michika Post Tue-29-May- New Water supply project C2/Water 1 NCB No 1,189,261.84 178,389.28 Review 18 Construction GOMBI NEW Post Tue-29-May- WATER SUPPLY PROJECT C2/Water 1 NCB No 915,241.80 137,286.27 Review 18 Installation of 12 nos. Solar Boreholes (in secondary schools)- GSS Gombi, GDSS Garkida, GSS Hong, GDSS Pella, GSSS Uba, Post Thu-10-May- GJSS Uba, GDSS Garaha, C2/Water 1 NCB No 377,609.70 75,521.94 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 16 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT GDSS Kwarhi, GDSS Za'ah, GSS Madagli, GSS Shuwa, GSS Gulak, GCSS Shuwa Installation of 37 Nos Solar Boreholes in 37 Health Centers in 7 Local Post Thu-10-May- Governments Areas C2/Water 4 NCB No 1,164,296.59 291,074.15 Review 18 Construction of 295Nos Hand Powered Bore Holes (in 2 primary schools per 35 wards, 35 Markets, 35 Motor parls and 155 Communities across 7 Post Thu-03-May- LGAs) C2/Water 4 NCB No 1,257,377.05 503,483.61 Review 18 Construction of VIP Latrines of 3-Comp (2 Blks Post Tue-14-Aug- in 24 pri sch) C2/WASH 3 RfQ No 212,459.02 79,672.13 Review 18 VIP Latrine of 3-Comp (2 Post Tue-14-Aug- Blks in 26 Markets) C2/WASH 3 RfQ No 230,163.93 92,065.57 Review 18 VIP Latrine of 3-Comp (2 Post Tue-14-Aug- Blks in 26 Motor Parks) C2/WASH 3 RfQ No 230,163.93 92,065.57 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 17 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Lokwa C2/Transpo Post Mon-11-Jun- Bridge Mubi rt 1 NCB No 475,143.96 356,357.97 Review 18 Reconstruction of Main Road - Bangshika Road C2/Transpo Prior Mon-11-Jun- 2.5Km rt 1 NCB No 1,019,295.08 127,411.89 Review 18 Rehabilitation of Mubi Bazza Road with a spur to C2/Transpo 1,255,469. Prior Mon-11-Jun- Mayo Bani 45Km rt 1 NCB No 8,369,796.72 51 Review 18 Rehabilitation of PHC, Construction of Perimeter Fence and Staff Quarters (Civil Works, Solar Borehole, Fence & Security C2/Educati Prior Tue-10-Apr- Post) in 7 Communities on 7 NCB No 1,139,130.43 451,779.49 Review 18 Rehabilitation of Cottage Post Tue-10-Apr- Hospital C2/Health 1 NCB No 451,768.85 192,001.76 Review 18 Establishment of Trauma Post Thu-17-May- Center @ general hospital C2/Health 1 RfQ No 65,194.96 65,194.96 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 18 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Renovation of GSS in 10 Towns (Gombi, Hong, Uba, Shuwa, Michika, Bazza, Mubi 1, Maiha, Madagali, C2/Educati Post Mubi North) on 10 NCB No 2,305,292.65 442,327.22 Review Tue-10-Jul-18 Renovation of 25Nos C2/Educati Post Primary School over 7 LGAs on 4 NCB No 865,747.88 324,655.45 Review Tue-10-Jul-18 Rehabilitation of Local Government Secretariat - C2/Public Post Thu-07-Jun- Song Buildings 1 NCB No 288,590.56 144,295.28 Review 18 Rehabilitation of Local Government Secretariat - C2/Public Post Thu-07-Jun- Madagali Buildings 1 NCB No 315,082.89 157,541.44 Review 18 Rehabilitation of District Head's Palace in 5 Communities (Uba, Gella, Gombi, Maiha/Pakka, C2/Public Post Thu-07-Jun- Gulak) Buildings 5 NCB No 422,463.57 158,423.84 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 19 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT YOBE Conversion of Motorised Boreholes (28 Communities in Gulani and Damaturu) into Solar Post Mon-26-Mar- Powered C2/Water 1 NCB No 334,013.66 250,510.24 Review 18 Conversion of existing Motorized powered Borehole without Overhead tank into solar powered (Gujba, Gulani, Yunusari, Damaturu,& Post Mon-26-Mar- Geidam ) C2/Water 1 NCB No 277,532.56 208,149.42 Review 18 Conversion of existing Motorized powered Borehole into solar powered and construction of New Overhead tank (Gujba, Gulani, Yunusari, Post Mon-26-Mar- Damaturu,& Geidam) C2/Water 2 NCB No 542,490.73 406,868.05 Review 18 Drilling of New Solar Powered Boreholes in Gujba, Gulani, Yunusari, Damaturu, Fika, Potiskum, Post Mon-02-Apr- Geidam & Fune C2/Water 2 NCB No 878,917.25 329,593.97 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 20 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Solar Powered Boreholes in Gulani, Gujba and Post Mon-02-Apr- Damaturu C2/Water 1 NCB No 244,228.65 183,171.49 Review 18 Construction & Upgrade of Post Wed-24-Oct- 33 nos. PHC Centres C2/Health 5 NCB No 5,386,554.10 538,655.41 Review 18 Reconstruction of Vandalized 3 Nos Post Wed-09-May- Immunization Offices C2/Health 1 RfQ No 68,618.27 68,618.27 Review 18 Renovation of 1No. General Post Mon-03-Sep- Hospital in Buni Yadi C2/Health 1 RfQ No 88,524.59 44,262.30 Review 18 Construction of 1No. Student Hostel each in College of Nursing and Midwifery Damaturu and College of Health Sciences Post Wed-22-Aug- and Technology, Nguru C2/Health 2 NCB No 983,606.56 245,901.64 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 21 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Renovation of Govt Secondary Schools in Goniri,Bara, Bularafa, ,Kananma, Damagum, Buni Yadi, Kukuwa, Gujba and C2/Educati Post Mon-09-Apr- Best Center in Goniri on 5 NCB No 2,001,760.77 800,704.31 Review 18 Renovation of Dokshi C2/Educati Post Mon-09-Apr- Primary school, Gulani on 1 NCB No 168,034.42 67,213.77 Review 18 Rehabilitation of Local Government Office Secretariat in Gujba and C2/Public Post Wed-09-May- Potiskum Buildings 2 NCB No 472,529.40 75,459.62 Review 18 Rehabilitation of Development Offices in Gujba , Gulani, Yunusari & C2/Public Post Wed-09-May- Geidam Buildings 1 RfQ No 62,203.18 15,550.80 Review 18 Provision of Community Resource Centres in all 17 C2/Public Post Wed-23-May- LGAs Buildings 5 NCB No 1,950,819.67 731,557.38 Review 18 Rehabilitation of Audit C2/Public Post Wed-26-Sep- Office Buildings 1 RfQ No 63,078.12 15,769.53 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 22 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Zonal C2/Public Post Wed-26-Sep- Statistical Office Buildings 1 RfQ No 50,491.80 25,245.90 Review 18 Rehabilitation ofCultural Buildings (District Head's Palace) in Buni Yadi and C2/Public Post Mon-27-Aug- Damagum Buildings 2 NCB No 446,682.62 111,670.66 Review 18 Rehabilitation of Government Buildings; C2/Public Post Mon-11-Jun- Agency for Mass Literacy Buildings 1 RfQ No 121,445.24 60,722.62 Review 18 Rehabilitation of Government Buildings; C2/Public Post Mon-11-Jun- Town Engineers Office Buildings 1 RfQ No 121,445.24 60,722.62 Review 18 GOODS BORNO Supply of Returnee C1/Transiti Resettlement Kits Bama, onal 2,216,737. Tue-13-Feb- Dikwa, Gwoza, Ngala, Support 4 NCB No 2,216,737.30 30 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 23 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Monguno, Damboa, Gudumbali, Mobbar, Kala Balge) Supply of Agricultural Support kits with Seeds, Fertilizers and Small Work Farm Tools (Bama, Biu, Gwoza, Ngala, Monguno, C1/Transiti Damboa, Askira, Mobbar, onal Tue-13-Feb- Kukawa) Support 3 NCB No 681,729.10 681,729.10 Post 18 Supply of Small Animals (Bama, Mafa, Gwoza, Ngala, Monguno, Damboa, C1/Transiti Chibok, Nganzai, Kala onal Tue-20-Feb- Balge) Support 3 NCB No 788,935.25 788,935.25 Post 18 Supply of Non-agricultural Livelihood Kits (Bama, Dikwa, Gwoza, Ngala, C1/Transiti Monguno, Damboa, Chibok, onal Tue-13-Feb- Mobbar, Hawul Support 2 NCB No 227,377.05 227,377.05 Post 18 C1/Transiti Supply of Skills Acquisition onal Tue-20-Feb- Start up Kits Support 3 NCB No 737,704.92 387,295.08 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 24 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Supply of solar electrification to 3 GENERAL HOSPITALS in ABADAM, GWOZA and KALA-BALGE and five Comprehensive Health Centre in Abadam, 2 in Gwoza, Kala-Balge, Askira - Tue-01-Jan- Uba C2/Health 3 NCB No 670,553.40 516,770.59 Post 19 Supply of Medical Equipment For 3General Hospitals in ABADAM, ASKIRA UBA, and KALA- Tue-15-Jan- BALGE C2/Health 3 NCB No 590,163.93 73,770.49 Post 19 Supply of Essential Drugs/Medical Consumables For 3 General Hospitals in HAWUL, Tue-05-Mar- MOBBAR AND DAMBOA C2/Health 3 NCB No 472,131.15 59,016.39 Post 19 Supply of Medical Equipment for Comprehensive Health Wed-09-Jan- Centers (Gwoza- Izge) C2/Health 1 NCB No 245,901.64 30,737.70 Post 19 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 25 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Supply of Essential Drugs/Medical Consumables for Comprehensive Health Tue-05-Feb- Center (Gwoza-izge) C2/Health 1 NCB No 236,065.57 29,508.20 Post 19 Supply of Medical Equipment to 15 PHCs to (Ngala, Nganzai Kukawa, Biu, Konduga, Gubio, Askira/Uba, Guzamala, Bama, Jere, Marte, Mobbar, Dikwa, Tue-15-Jan- Mafa, Abadam) C2/Health 2 NCB No 983,606.56 122,950.82 Post 19 Supply of Essential Drugs to 15 PHCs (Ngala, Nganzai Kukawa, Biu, Konduga, Gubio, Askira/Uba, Guzamala, Bama, Jere, Marte, Mobbar, Dikwa, Tue-05-Feb- Mafa, Abadam) C2/Health 2 NCB No 786,885.25 98,360.66 Post 19 Supply and Installation of Solar Inverters in 15 PHCs in (Ngala, Nganzai Kukawa, Biu, Konduga, Gubio, Askira/Uba, Guzamala, Bama, Jere, Marte, Mobbar, Tue-06-Mar- Dikwa, Mafa, Abadam) C2/Health 1 NCB No 262,295.08 65,573.77 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 26 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Furniture for Library/ Offices in the Borno State Library and Furniture for 15 blocks of classrooms in Umar Ibn ibrahim college C2/Educati Tue-19-Mar- Bama on 2 NCB No 491,803.28 245,901.64 Post 19 Books and other learning Materials including elibrary C2/Educati Tue-19-Mar- in the Borno State library on 1 NCB No 262,295.08 131,147.54 Post 19 Suppy of Computers and other accessories to the Borno State Library , Maiduguri and Umar Ibn C2/Educati Tue-19-Mar- ibrahim college Bama on 2 RfQ No 81,967.21 40,983.61 Post 19 Supply of Medical Equipment TO 3 Comprehensive Health centers IN HAWUL, MOBBAR AND DAMBOA Tue-06-Mar- (Kwajafa, Kareto, Damboa) C2/Health 1 NCB No 196,721.31 49,180.33 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 27 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Installation of solar inverters for PHC Gwoza( Tue-06-Mar- Izge) C2/Health 1 NCB No 13,114.75 13,114.75 Post 18 ADAMAWA C1/Transiti Supply of Returnee onal Mon-19-Mar- Resettlement Kits Support 2 NCB No 490,780.33 490,780.33 Post 18 Supply of Agricultural Support kits with Seeds, C1/Transiti Fertilizers and Small Work onal 1,496,508. Mon-19-Mar- Farm Tools Support 7 NCB No 1,496,508.20 20 Prior 18 C1/Transiti onal Thu-19-Apr- Supply of Small Animals Support 1 NCB No 182,950.82 182,950.82 Post 18 C1/Transiti Supply of Non-agricultural onal Mon-19-Mar- Livelihood Kits Support 1 NCB No 213,442.62 213,442.62 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 28 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C1/Transiti Start up kits for quick to onal Mon-19-Mar- market trading Support 1 NCB No 114,754.10 114,754.10 Post 18 Housing Refurbishment Returnee Packs for Voluntary Returnees across C1/Transiti the 7 LGAs being onal Thu-14-Jun- rehabilitated. Support 2 NCB No 390,163.93 331,639.34 Post 18 Supply of Medical Equipment to PHCs in 7 communities and Cottage Hospital in Gulak C2/Health 2 NCB No 344,262.30 43,032.79 Post Thu-19-Jul-18 Supply of Essential Drugs/Medical Consumable to PHCs in 7 Communities and Cottage Hospital in Thu-01-Nov- Gulak C2/Health 2 NCB No 452,459.02 108,196.72 Post 18 Installation of Solar Inverters in 7 Rehabilitated PHCs, Cottage Hospital in Mon-06-Aug- Gulak C2/Health 3 NCB No 268,861.16 18,852.46 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 29 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Equipping of Trauma Center @ Michika General Mon-06-Aug- hospital C2/Health 1 NCB No 214,142.46 80,303.42 Post 18 Supply of Furniture to C2/Educati Thu-29-Mar- Primary Schools in 7 LGAs on 1 NCB No 245,901.64 30,737.70 Post 18 Supply of Books and Teaching/Learning Materials to Primary C2/Educati Thu-29-Mar- Schools in 7 LGAs on 1 NCB No 327,868.85 122,950.82 Post 18 Establishment of spare part supply chain/buffer Mon-16-Apr- stock for Water Facilities C2/WASH 1 NCB No 114,754.10 86,065.57 Post 18 Train the Trainer/User Workshops (i.e. 2 per LGA) for VLOM (Village Level Operation and Maintenance) WASHCOMS, (WASH Committees at LGA Level, WASH Units @ LGAs, VHPs (Voluntary Hygiene Promoters) State/LGA Govt Tue-24-Apr- Officials. C2/WASH 1 NCB No 72,131.15 54,098.36 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 30 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT YOBE C1/Transiti Supply of Non Food Items onal Wed-21-Mar- (NFIs) Kits Support 3 NCB No 559,213.11 559,213.11 Post 18 C1/Transiti Supply of Agricultural kits onal 1,048,940. Wed-21-Mar- with seeds, oil, small tools Support 3 NCB No 1,048,940.98 98 Post 18 C1/Transiti onal Mon-23-Apr- Supply of Small Animals Support 3 NCB No 688,524.59 688,524.59 Post 18 C1/Transiti Non-agricultural Livelihood onal Mon-26-Mar- kits Support 2 NCB No 352,295.08 352,295.08 Post 18 C1/Transiti Supply of Skills Acquisition onal Wed-21-Mar- Start up Kits Support 3 NCB No 786,885.25 550,819.67 Post 18 Procure and distribute Plumpy Nuts for Wed-25-Apr- malnourished children in C2/Health 1 NCB No 215,438.65 32,315.80 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 31 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Gujba, Geidam and Yunusari LGAs Equipping of Trauma Mon-12-Feb- Center C2/Health 1 NCB No 214,147.54 53,536.89 Post 18 Supply of Students Textbooks and Teachers' C2/Educati Mon-17-Sep- Guides on 1 NCB No 284,062.30 71,015.57 Post 18 Supply of Laboratory Equipment Physics. C2/Educati Mon-17-Sep- Chemistry & Biology on 1 NCB No 213,114.75 53,278.69 Post 18 C2/Educati Mon-17-Sep- Supply of School Furniture on 3 NCB No 804,885.25 201,221.31 Post 18 CONSULTING SERVICES BORNO Skills Acquisition Training C1/Transiti (3Nos Consultancies across onal Mon-09-Jul- 10 LGAs) Support 3 QCBS No 491,803.28 258,196.72 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 32 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Specialized psycho-social support responding to C1/Commu needs (3Nos Consultancies nity Wed-28-Mar- across 10 LGAs) Resilience 3 QCBS No 826,229.51 619,672.13 Post 18 Consultancy for the Mobilisation and Organisation of Civic Education with Cultural and Recreational activities at Community Level with programs that respond to needs as prioritized by community based diagnosis (3Nos C1/Commu Consultancies across 10 nity Wed-11-Apr- LGAs) Resilience 3 QCBS No 442,622.95 265,573.77 Post 18 Consultancy for Sensitization, Community Mobilization and formation of peace groups within 7 Communities(establishmen t of community platforms to discuss community needs, grievances; and C1/Commu redress mechanisms. (1No nity Mon-30-Apr- Consultancy) Resilience 1 QCBS No 531,147.54 318,688.52 Prior 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 33 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Consultancy for Post- C1/Commu Conflict Transitional Justice nity Mon-21-May- and Accountability Resilience 1 QCBS No 147,540.98 88,524.59 Post 18 Statewide sponsorship for Radio Programming for Peacebuilding Campaign and Content for dissemination (focusing on deradicalisation, grievance C1/Commu redress and peacebuilding nity Mon-04-Jun- outreach themes) Resilience 1 CQS No 475,409.84 178,278.69 Prior 18 Consultancy for Educational campaigns for the prevention of mine and unexploded ordinance accidents /Mobilisation and Sensitization Campaign on Mine Action (Unexploded C1/Commu Ordnances) (1No nity Mon-04-Jun- Consultancy) Resilience 1 QCBS No 442,622.95 354,098.36 Prior 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 34 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Consultancy for Leadership Accountability and Transparency Training Programme (NELATTP) Targeting 20 LGA Staff and State Ministry Personal per LGA - Development of a transparency and accountability Local Governance Model through community participation C1/Commu (social accountability nity Fri-25-May- mechanisms) Resilience 1 CQS No 88,524.59 55,327.87 Post 18 Consultancy for Registration, Mapping and C1/Strengt Profiling of all local hening government structures and Local existing capacities State Governanc Fri-25-May- Wide e 1 CQS No 49,180.33 30,737.70 Post 18 Consultancy to provide C1/Strengt Capacity building of LG hening Officers for economic Local planning and policy Governanc Fri-25-May- development e CQS No 88,524.59 55,327.87 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 35 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C1/Strengt hening Capacity building for LG Local officials on programme Governanc Fri-25-May- design and implementation e CQS No 88,524.59 55,327.87 Post 18 Capacity building of LG C1/Strengt Officers for local hening governments on budget Local planning and execution, Governanc Fri-25-May- monitoring and reporting e 1 CQS No 88,524.59 55,327.87 Post 18 Capacity building of LG Officers for strategic communications C1/Strengt (Legislative Advocacy, hening Media relations, Local Stakeholder Management Governanc Fri-25-May- etc). e CQS No 88,524.59 55,327.87 Post 18 Capacity Building for 10 Local Government C1/Strengt Emergency Management hening Responders in Displaced Local and Transitional Local Governanc Fri-25-May- Government Officials e 1 CQS No 203,278.69 152,459.02 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 36 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Sensitization, training (especially on Identification, Documentation, Tracing and Reunification and follow up) and coaching for state and non-state partners on case management of UASC C1/Program (Unaccompanied and Support to Fri-25-May- Separated Children) UASC 1 MOU No 73,770.49 59,016.39 Post 18 Training for officials of relevant State MDAs on C1/Program effective approaches to Support to Thu-28-Jun- UASC UASC 1 IC No 16,393.44 13,114.75 Post 18 Teacher Training and C1/Educati Fri-25-May- Recertification on 1 MOU No 442,622.95 77,459.02 Post 18 Training of Community Health Workers (CHeWs, VHWs, Midwives) to Staff Targeted Health Facilities (3Nos consultancies across the state. Amount Inclusive of Workshop and per diem Mon-29-Apr- payments) C1/Health 3 QCBS No 796,721.31 298,770.49 Post 19 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 37 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Sensitization and Mobilisation for Health (Outreach Programs) in 27 LGAs (Over 10 Fri-25-May- engagements) C1/Health 10 CQS No 708,196.72 265,573.77 Post 18 Identification and training of Village Levels Mechanics and Local Area Mechanics on Operation and Maintenance of existing Hand Pump and Solar powered Borehole for effective utilization and Fri-25-May- management. C2/WASH 1 CQS No 98,360.66 73,770.49 Post 18 ADAMAWA Refresher Training of Existing Extension Workers C1/Transiti to support Livelihoods onal Thu-10-May- Projects Support 1 CQS No 65,573.77 65,573.77 Post 18 Training of affected farmers to apply inputs and access targeted C1/Transiti agricultural value chains onal Thu-21-Jun- and agribusiness skills Support 1 CQS No 167,216.39 167,216.39 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 38 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Establishment of Returnees Resettlement Registry at each LGA for Sensitization, Mobilisation and Logistics support for Safe and C1/Transiti Voluntary returns to 7 onal Thu-24-May- LGAs being rehabilitated Support 1 CQS No 61,565.57 49,252.46 Post 18 Consultancy to provide C1/Transiti Training for Bio Data onal Thu-10-May- Registration Support Support 1 IC No 1,377.05 1,101.64 Post 18 Consultancy for Sensitization, Community Mobilization and formation of peace groups within 7 Communities(establishmen t of community platforms to discuss community C1/Commu needs, grievances; and nity Mon-04-Jun- redress mechanisms Resilience 1 QCBS No 344,262.30 206,557.38 Prior 18 Diagnosis of community- specific reconciliation, peacebuilding and social C1/Commu cohesion needs and nity Thu-03-May- consequent development Resilience 2 QCBS No 344,262.30 206,557.38 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 39 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT of Civil Education Programs using Cultural and Recreational activities at Community Level (2Nos Consultancies) Provision of specialized psycho-social assessment and support responding to needs through group support, recreational, customary and socializing activities, referrals etc C1/Commu (3Nos Consultancies across nity Mon-11-Jun- the affected areas) Resilience 3 QCBS No 642,622.95 481,967.21 Post 18 Sensitization and Mobilisation Programs for Awareness against Stigmatization of Woman and Children associated C1/Commu with armed groups. (1No nity Mon-04-Jun- Consultancy) Resilience 1 QCBS No 413,114.75 247,868.85 Prior 18 Consultancy for Mediation and Alternate Dispute Resolution Capacity C1/Commu Building within the nity Mon-18-Jun- Community Leadership and Resilience 3 QCBS No 425,960.66 255,576.39 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 40 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Governance Structures (3Nos Consultancies acrossthe state) C1/Citizen- Consultancy for Leadership Governmen Accountability and t Transparency Training Relationshi Thu-10-May- Programme p Building 1 CQS No 72,131.15 45,081.97 Post 18 Registration, Mapping and C1/Strengt Profiling of all local hening government structures and Local existing capacities State Governanc Mon-28-May- Wide e 1 CQS No 39,344.26 24,590.16 Post 18 C1/Strengt Capacity building of LG hening Officers for economic Local planning and policy Governanc Mon-28-May- development e 1 CQS No 72,131.15 45,081.97 Post 18 C1/Strengt hening Capacity building for Local programme design and Governanc Mon-28-May- implementation e 1 CQS No 72,131.15 45,081.97 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 41 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Capacity building of LG C1/Strengt Officers for local hening governments on budget Local planning and execution, Governanc Mon-28-May- monitoring and reporting e 1 CQS No 72,131.15 45,081.97 Post 18 Capacity building of LG Officers for strategic communications C1/Strengt (Legislative Advocacy, hening Media relations, Local Stakeholder Management Governanc Thu-21-Jun- etc). e 1 CQS No 72,131.15 45,081.97 Post 18 Hygiene Promotion Mon-17-Sep- Sensitization/Mobilization C2/WASH 1 IC No 9,180.33 6,885.25 Post 18 Hygiene Promotion Mon-12-Nov- Campaign C2/WASH 1 CQS No 85,677.59 64,258.20 Post 18 Training of Community Health Workers (CHeWs) to Staff Targeted Health Thu-13-Dec- Facilities C2/Health 1 CQS No 68,852.46 55,081.97 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 42 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Sensitization and Mobilisation for Health Mon-17-Sep- (Outreach Programs) C2/Health 1 CQS No 183,606.56 146,885.25 Post 18 Mobilization and Sensitization for Children C2/Educati Thu-31-May- Education on 1 CQS No 206,557.38 206,557.38 Post 18 Teacher Training and Recertification ( Primary C2/Educati Thu-13-Dec- and Secondary Schools ) on 1 CQS No 360,655.74 360,656.74 Prior 18 YOBE Skills Acquisition Training C1/Transiti 3 Nos Consultancies across onal Wed-25-Apr- 8 LGAs) Support 3 QCBS No 524,590.16 367,213.11 Post 18 Consultancy for Sensitization, Community Mobilization and formation of peace groups within 15 C1/Peace Wed-23-May- Communities Building 1 QCBS No 491,803.28 319,672.13 Prior 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 43 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Diagnosis of community- specific reconciliation, peacebuilding and social cohesion needs and consequentt development of Civil Education Programs using Cultural and Recreational activities at C1/Peace Mon-04-Jun- Community Level Building 1 CQS No 49,180.33 31,967.21 Post 18 Consultancy for Mediation and Alternate Dispute Resolution Capacity Building within the Community Leadership and C1/Peace Mon-04-Jun- Governance Structures Building 1 CQS No 177,049.18 115,081.97 Post 18 Radio programs on mine awareness, dispute resolution in Hausa, Kanuri C1/Peace Wed-25-Jul- and Fulfulde Building 1 CQS No 280,719.92 105,269.97 Post 18 Provision of specialized psycho-social assessment and support responding to needs (3 Nos Consultancies C1/Peace Wed-20-Jun- across 8 LGAs) Building 3 QCBS No 625,822.95 438,076.07 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 44 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Mapping and profiling of local government C1/Strengt structures and hening communities in places of Local both displacement and Governanc Thu-28-Jun- origin e 1 CQS No 39,344.26 39,344.26 Post 18 Establishment of C1/Strengt community platforms to hening discuss community needs, Local grievances; and building a Governanc Wed-06-Jun- bottom-up planning model e 1 CQS No 74,948.93 59,959.14 Post 18 Development of a transparency and accountability model C1/Strengt through community hening participation (social Local accountability Governanc Wed-06-Jun- mechanisms) e 1 CQS No 47,377.05 37,901.64 Post 18 C1/Strengt Capacity building of LG hening Officers for economic Local planning and policy Governanc Thu-28-Jun- development e 1 CQS No 55,737.70 44,590.16 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 45 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C1/Strengt hening Capacity building for Local programme design and Governanc Thu-28-Jun- implementation e 1 CQS No 55,737.70 44,590.16 Post 18 Capacity building of LG C1/Strengt Officers for local hening governments on budget Local planning and execution, Governanc Thu-28-Jun- monitoring and reporting e 1 CQS No 55,737.70 44,590.16 Post 18 Capacity building of LG Officers for strategic communications C1/Strengt (Legislative Advocacy, hening Media relations, Local Stakeholder Management Governanc etc). e 1 CQS No 55,737.70 44,590.16 Post Thu-26-Jul-18 Sensitization, training (especially on Identification, Documentation, Tracing and Reunification and follow up) and coaching for state and non-state C1/Program partners on case Support on Thu-07-Jun- management of UASC UASC 1 CQS No 52,459.02 41,967.21 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 46 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Training for officials of C1/Program relevant MDAs on effective Support on Thu-28-Jun- approaches to UASC UASC 1 CQS No 8,196.72 6,557.38 Post 18 Menstrual Hygiene Management to support Women and Girls of productive ages to effectively maintain their Thu-17-May- menstrual hygiene C2/WASH 1 QCBS No 110,163.93 41,311.48 Post 18 Community Led Total Sanitation (CLTS) Implementation in Thu-31-May- communities C2/WASH 1 QCBS No 220,327.87 82,622.95 Post 18 Community Management training of entire Communities in the 8 proposed LGAs to effectively manage their Water, Sanitation and Mon-18-Jun- Hygiene Facilities C2/WASH 3 QCBS No 293,770.49 110,163.93 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 47 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Identification and training of Village Levels Mechanics and Local Area Mechanics on Operation and Maintenance of existing Hand Pump and Solar powered Borehole for effective utilization and Thu-17-May- management. C2/WASH 1 CQS No 98,360.66 61,475.41 Post 18 Water Safety Plan implementation in the entire Communities of the Mon-16-Jul- four LGAs. C2/WASH 1 CQS No 112,459.02 84,344.26 Post 18 Integrated Outreach Services (Up to 5 activities Thu-17-May- envisaged) C2/Health 5 QCBS No 344,262.30 129,098.36 Post 18 Training of Community Health Workers (CHeWs, VHWs, Midwives) to Staff Thu-15-Nov- Targeted Health Facilities C2/Health 1 QCBS No 501,639.34 376,229.51 Prior 18 Teacher Training and C2/Educati Mon-26-Nov- Recertification in all LGAs on 1 MOU No 278,688.52 209,016.39 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 48 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT PCNI NERSP PMC CELL Project Wide Project C3/Technic Management Consultancy al 2,000,000. Wed-11-Apr- Firm Assistance 1 QCBS No 3,000,000.00 00 Prior 18 Consultancy services for immediate- and medium- term implementation capacity building (4 C3/Technic separate Consultancies al Thu-03-May- Envisaged) Assistance 4 CQS No 536,393.44 268,196.72 Prior 18 Consultancy Services for C3/Technic Monitoring and Evaluation al Baseline Study Assistance 1 QCBS No 177,049.18 177,049.18 Post Fri-27-Apr-18 Consultancy services for setting up citizen engagement and third C3/Technic party monitoring al mechanisms Assistance 1 CQS No 177,049.00 59,016.33 Post Fri-06-Apr-18 Consultancy Services for C3/Technic Environmental Impact al Assessment Assistance 1 QCBS No 39,344.26 39,344.26 Post Fri-13-Apr-18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 49 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT NON- CONSULTING SERVICES ADAMAWA Door to Door Collection of Thu-24-May- Solid waste in 7 LGAs C2/WASH 1 NCB No 236,065.57 88,524.59 Post 18 Disposal of Waste from Door to Door Collection in Tue-13-Feb- 7 LGAs C2/WASH 1 NCB No 229,508.20 86,065.57 Post 18 OPERATIONAL COSTS PCNI NERSP PMC CELL PMC Software, Intranet and C3/Operati Tools onal Costs 3 RfQ No 159,240.16 159,240.16 Post Fri-27-Apr-18 Video Conferencing C3/Operati Thu-25-Jan- Equipment onal Costs 1 RfQ No 131,147.54 131,147.54 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 50 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C3/Operati Tue-27-Mar- Office Vehicles onal Costs 1 RfQ No 344,265.00 344,265.00 Post 18 BORNO STATE Procurement of 12 laptop computers, 12 laserjet printers, 4 photocopiers, 3 desktops, 15 desktops for work stations, 2 deskjet printers, HP Scanjet C3/Operati scanner onal Costs 1 RfQ No 159,240.16 159,240.16 Post Fri-27-Apr-18 Procurement of video conference equipment and C3/Operati internet connectivity onal Costs 1 RfQ No 65,574.00 65,574.00 Post Fri-27-Apr-18 Procurement of Office C3/Operati Tue-27-Mar- Furniture onal Costs 1 NCB No 32,786.89 32,786.89 Post 18 Procurement of 1 Video C3/Operati Wed-28-Mar- Camera, 2 DLSR Cameras, onal Costs 1 RfQ No 7,000.00 7,000.00 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 51 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of 100KVA sound proof Generator, C3/Operati Sun-20-May- 10KVA Inverter System onal Costs 1 RfQ No 42,623.00 42,623.00 Post 18 Procurement of Office Vehicles - 2 Toyota Prado Jeep, 3 Toyota Hilux, 1 C3/Operati Wed-14-Mar- Toyota Corolla onal Costs 1 NCB No 448,525.00 448,525.00 Post 18 ADAMAWA STATE Procurement of computers, printers and other C3/Operati Wed-28-Mar- accessories onal Costs 1 RfQ No 24,131.15 24,131.15 Post 18 Procurement of video conference equipment and C3/Operati Wed-28-Mar- internet connectivity onal Costs 1 RfQ No 65,574.00 65,574.00 Post 18 Procurement of Office C3/Operati Tue-27-Mar- Furniture onal Costs 1 NCB No 32,786.89 32,786.89 Post 18 Procurement of 1 Video C3/Operati Wed-28-Mar- Camera, 2 DLSR Cameras, onal Costs 1 RfQ No 20,327.87 20,327.87 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 52 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of 100KVA sound proof Generator, C3/Operati Mon-26-Mar- 10KVA Inverter System onal Costs 1 RfQ No 42,623.00 42,623.00 Post 18 Procurement of Office Vehicles - 2 Toyota Prado Jeep, 3 Toyota Hilux, 1 C3/Operati Tue-27-Mar- Toyota Corolla onal Costs 1 RfQ No 518,033.00 518,033.00 Post 18 YOBE STATE Procurement of computers, printers and other C3/Operati Wed-28-Mar- accessories onal Costs 1 RfQ No 24,131.15 24,131.15 Post 18 Procurement of video conference equipment and C3/Operati Wed-28-Mar- internet connectivity onal Costs 1 RfQ No 65,574.00 65,574.00 Post 18 Procurement of Office C3/Operati Tue-27-Mar- Furniture onal Costs 1 NCB No 32,786.89 32,786.89 Post 18 Procurement of 1 Video C3/Operati Wed-28-Mar- Camera, 2 DLSR Cameras, onal Costs 1 RfQ No 20,327.87 20,327.87 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 53 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of 100KVA sound proof Generator, C3/Operati Mon-26-Mar- 10KVA Inverter System onal Costs 1 RfQ No 42,623.00 42,623.00 Post 18 Procurement of Office C3/Operati Tue-27-Mar- Vehicles onal Costs 1 RfQ No 468,852.46 468,852.46 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 54 PROCUREMENT Nigeria : Multi-Sectoral Crisis Recovery Project for North Eastern Nigeria PLAN General Information Country: Nigeria 2018-06-05 Bank’s Approval Date of the Original Procurement Plan: 2022-07-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157891 GPN Date: Project Name: Multi-Sectoral Crisis Recovery Project for North Eastern Nigeria Loan / Credit No: IDA / 59880 Borno MCRP Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-BORNO MCRP-57818-CW Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-01-0 2021-03 -RFQ / Rehabilitation of Court IDA / 59880 and Service Delivery Restora Post Open - National 80,642.16 Completed 2018-05-12 2021-10-14 2018-07-07 2020-07-24 tions nvelope 3 -11 Buildings in Bama Gwoza Di tion & Improvement kwa Mobbar NG-BORNO MCRP-58804-CW -RFQ / Rehabilitation of Existi ng Non-Functional Boreholes Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-05-1 2019-12 Abadam (1) Askira Uba (2) Bi IDA / 59880 and Service Delivery Restora Post Open - National 22,161.59 Completed 2018-09-17 2018-11-12 2019-12-10 tions nvelope 1 -30 u (2) Dikwa (1) Gubio (1) Guz tion & Improvement amala (1) Jere (2) Kala Balge (1) Mafa (2) Magumeri (1) Ma rte (2) Mobbar (1) Ngala (1) Nganzai (1) NG-BORNO MCRP-58797-CW Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-04-1 -RFQ / Reconstruction of Post IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2018-08-20 2018-10-15 tions nvelope 3 Office (Bama) tion & Improvement NG-BORNO MCRP-58769-CW Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-08-0 -RFQ / Construction Of 5-No IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2018-12-08 2019-02-02 tions nvelope 1 Vip Toilets -Monguno tion & Improvement NG-BORNO MCRP-58402-CW Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-08-0 -RFQ / Renovation Of 1-No. E IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2018-12-08 2019-02-02 tions nvelope 1 ducational Office -Damboa tion & Improvement NG-BORNO MCRP-55929-CW -RFQ / Construction of Handp Infrastructure Rehabilitation ump Wells in Bama (3) Chibo Request for Quota Single Stage - One E 2019-03-1 IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2018-07-24 2018-09-18 k (5), Biu (5), Mafa(3), Hawul tions nvelope 7 tion & Improvement (5), Askira/Uba(5), Konduga( 4), Jere(5) Dikwa (3), Gwoza( 5), NG-BORNO MCRP-58026-CW Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-07-0 -RFQ / Construction Of 4- No. IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2018-11-10 2019-01-05 tions nvelope 4 Double Classroom Block in Aj tion & Improvement iri. Mafa NG-BORNO MCRP-55956-CW Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-05-0 -RFQ / Construction Of 3-No. IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2018-09-08 2018-11-03 tions nvelope 2 Educational Office -Kukawa tion & Improvement NG-BORNO MCRP-58801-CW -RFQ / Construction of Solar P Infrastructure Rehabilitation Request for Quota Single Stage - One E 2018-12-0 owered Boreholes (2Nos) in IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2018-04-14 2018-06-09 tions nvelope 6 Umar Ibn Ibrahim college Ba tion & Improvement ma Solar Lighting System to Borno Library NG-BORNO MCRP-58893-CW Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-08-0 -RFQ / Construction Of 4-No IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2018-12-08 2019-02-02 tions nvelope 1 Vip Toilets -Mafa tion & Improvement NG-BORNO MCRP-56416-CW Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-06-0 -RFQ / Construction Of 2-No. IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2018-10-13 2018-12-08 tions nvelope 6 Educational Office -Hawul Sa tion & Improvement kwa, Kwajafa NG-BORNO MCRP-57851-CW Infrastructure Rehabilitation -RFB / Construction of new S Request for Quota Single Stage - One E 2019-05-1 2020-04 IDA / 59880 and Service Delivery Restora Post Open - National 5,552.31 Completed 2018-09-17 2018-11-12 2019-09-23 olar Powered Boreholes in 27 tions nvelope 1 -16 tion & Improvement Local Government Areas of B orno State NG-BORNO MCRP-58350-CW Infrastructure Rehabilitation -RFB / REHABILITATION OF 1 Request for Quota Single Stage - One E 2019-05-0 2019-07 IDA / 59880 and Service Delivery Restora Post Open - National 257,374.29 Completed 2018-09-12 2018-11-07 2018-10-12 0 LOCAL GOVERNMENT LOD tions nvelope 6 -04 tion & Improvement GES in Borno State NG-BORNO MCRP-56722-CW Infrastructure Rehabilitation -RFQ / Renovation Of 1-No. E Request for Quota Single Stage - One E 2019-08-0 2019-09 IDA / 59880 and Service Delivery Restora Post Limited 104,759.75 Completed 2018-12-15 2019-06-03 2019-02-09 2019-06-25 ducational Office in Mafa Loc tions nvelope 8 -05 tion & Improvement al Government Area of Borno State NG-BORNO MCRP-58891-CW -RFB / Rehabilitation of Prima Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-06-1 2019-10 ry Health Care Center in 15 L IDA / 59880 and Service Delivery Restora Post Open - National 106,943.98 Completed 2018-10-21 2021-10-14 2018-12-16 2019-06-28 tions nvelope 4 -11 ocal Government Areas of th tion & Improvement e 3 Senatorial districts of Bor no State NG-BORNO MCRP-58035-CW Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-05-1 2020-03 -RFB / Rehabilitation of Borno IDA / 59880 and Service Delivery Restora Post Open - National 287,546.62 Completed 2018-09-22 2018-11-17 2019-07-24 tions nvelope 6 -26 State Library in Maiduguri tion & Improvement NG-BORNO MCRP-58768-CW Infrastructure Rehabilitation -RFQ / Construction Of 18-No. Request for Quota Single Stage - One E 2019-05-1 2019-05 IDA / 59880 and Service Delivery Restora Post Open - National 133,222.10 Completed 2018-09-24 2018-11-19 2018-10-24 Double Classroom Blocks in tions nvelope 8 -20 tion & Improvement Askira/Uba Local Governmen t Area of Borno State NG-BORNO MCRP-73721-CW Infrastructure Rehabilitation -RFQ / Reconstruction of Loc Request for Quota Single Stage - One E 2019-05-1 2019-09 IDA / 59880 and Service Delivery Restora Post Open - National 100,066.50 Completed 2018-09-17 2018-11-12 2019-06-27 al Education Authorities Offic tions nvelope 1 -04 tion & Improvement es in 9 Local Governments of Borno State NG-BORNO MCRP-58400-CW Infrastructure Rehabilitation -RFQ / Renovation of 1-No. Pr Request for Quota Single Stage - One E 2019-09-0 2019-10 IDA / 59880 and Service Delivery Restora Post Open - National 20,565.87 Completed 2019-06-01 2019-07-05 2019-07-05 incipal's Quarters in Kaga Loc tions nvelope 3 -24 tion & Improvement al Government Area of Borno State Page 1 NG-BORNO MCRP-58394-CW Infrastructure Rehabilitation -RFQ / Construction Of 12-No Request for Quota Single Stage - One E 2020-04-0 2020-09 IDA / 59880 and Service Delivery Restora Post Open - National 59,741.05 Completed 2019-08-11 2019-10-06 2019-07-05 Vip Toilets Mafa (4), Askira-U tions nvelope 3 -08 tion & Improvement ba (4), Monguno (4) (3LOTS) NG-BORNO MCRP-58024-CW -RFQ / Reconstruction Of 18- Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-05-2 2019-10 No. Double Classroom Blocks IDA / 59880 and Service Delivery Restora Post Open - National 771,542.71 Completed 2018-10-02 2018-11-27 2019-07-26 tions nvelope 6 -14 in Bama and Mafa Local Gov tion & Improvement ernment Areas of Borno Stat e BOMCRP/RFB/CW/004/019 / Infrastructure Rehabilitation Single Stage - One E 2021-04-0 Rehabilitation of 66KM Maidu IDA / 59880 and Service Delivery Restora Prior Request for Bids Open - National 0.00 Canceled 2019-08-05 2020-01-22 2019-08-10 2020-01-29 2019-09-09 2020-03-03 2019-09-23 2019-10-07 nvelope 7 guri to Bama Road tion & Improvement NG-BORNO MCRP-52157-CW Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-05-1 2019-09 -RFB / Rehabilitation of Com IDA / 59880 and Service Delivery Restora Post Open - National 645,978.75 Completed 2018-09-17 2018-11-12 2019-06-27 tions nvelope 1 -17 munity Resource Centres in tion & Improvement Borno State NG-BORNO MCRP-130217-C Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-12-1 2019-10 W-RFQ / Rehabilitation of Libr IDA / 59880 and Service Delivery Restora Post Limited 76,005.59 Completed 2019-09-25 2019-06-03 2019-10-18 2019-06-20 tions nvelope 7 -14 ary at Umar Ibn Ibrahim Colle tion & Improvement ge Bama NG-BORNO MCRP-130225-C Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-12-2 2020-01 W-RFQ / Rehabilitation of 1 of IDA / 59880 and Service Delivery Restora Post Limited 422,961.00 Completed 2019-09-29 2019-04-04 2019-10-21 2019-04-24 tions nvelope 0 -08 3 General Hospital tion & Improvement NG-BORNO MCRP-130234-C Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-11-1 2019-10 W-RFQ / Supply of Medical Eq IDA / 59880 and Service Delivery Restora Post Limited 521,591.33 Completed 2019-09-19 2019-07-12 2019-10-11 2019-08-01 tions nvelope 0 -10 uipment to 3 General Hospita tion & Improvement ls NG-BORNO MCRP-133224-C Infrastructure Rehabilitation Request for Quota Single Stage - One E 2020-01-2 2020-10 W-RFQ / Rehabilitation of Cou IDA / 59880 and Service Delivery Restora Post Limited 56,074.13 Completed 2019-11-06 2020-07-03 2019-11-28 2020-07-24 tions nvelope 7 -20 rt Building tion & Improvement NG-BORNO MCRP-133225-C Infrastructure Rehabilitation Request for Quota Single Stage - One E 2020-01-0 2020-01 W-RFQ / Rehabilitation of Tra IDA / 59880 and Service Delivery Restora Post Limited 264,975.56 Completed 2019-10-13 2019-10-04 2019-11-04 2019-10-24 tions nvelope 3 -07 ditional Rulers Building (11 L tion & Improvement GAs) NG-BORNO MCRP-133227-C Infrastructure Rehabilitation Request for Quota Single Stage - One E 2020-01-0 2021-07 W-RFQ / Construction of New IDA / 59880 and Service Delivery Restora Post Limited 14,598.54 Completed 2019-10-17 2021-03-01 2019-11-09 2021-03-19 tions nvelope 8 -17 hand Pumps Water Sources tion & Improvement NG-BORNO MCRP-133230-C Infrastructure Rehabilitation Request for Quota Single Stage - One E 2020-01-2 2020-05 W-RFQ / Rehabilitation of Exi IDA / 59880 and Service Delivery Restora Post Limited 56,840.24 Completed 2019-10-30 2019-12-06 2019-11-21 2019-12-27 tions nvelope 0 -18 sting Non-Functional Borehol tion & Improvement es BORNO/MCRP/CW/RFQ/100/2 Infrastructure Rehabilitation 0 / Construction of Double Cl Request for Quota Single Stage - One E 2020-10-2 2020-01 IDA / 59880 and Service Delivery Restora Post Limited 145,301.07 Completed 2020-04-07 2019-10-04 2020-04-28 2019-10-24 assroom Blocks at Askira/Uba tions nvelope 5 -31 tion & Improvement Local Government Area of Bo rno State BORNO/MCRP/CW/RFQ/104/2 Infrastructure Rehabilitation 0 / Construction of Double Cl Request for Quota Single Stage - One E 2020-10-2 IDA / 59880 and Service Delivery Restora Post Limited 381,946.31 Signed 2020-04-08 2020-07-27 2020-04-29 2020-08-13 assroom Blocks at Kukawa Lo tions nvelope 6 tion & Improvement cal Government Area of Born o State BORNO/MCRP/CW/RFQ/105/2 Infrastructure Rehabilitation 0 / Construction of Double Cl Request for Quota Single Stage - One E 2020-10-2 2019-09 IDA / 59880 and Service Delivery Restora Post Limited 57,801.12 Completed 2020-04-11 2019-02-20 2020-05-02 2019-03-11 assroom Blocks at Ajiri Com tions nvelope 9 -16 tion & Improvement munity of Mafa Local Govern ment Area BORNO/MCRP/CW/RFQ/107/2 Infrastructure Rehabilitation 0 / Renovation of Double Clas Request for Quota Single Stage - One E 2020-10-3 2019-06 IDA / 59880 and Service Delivery Restora Post Limited 58,824.15 Completed 2020-04-12 2019-02-20 2020-05-03 2019-03-11 sroom Blocks at Bama Town, tions nvelope 0 -21 tion & Improvement Bama Local Government Are a of Borno State BORNO/MCRP/CW/RFQ/109 / Infrastructure Rehabilitation Renovation of Educational Of Request for Quota Single Stage - One E 2020-11-0 2019-09 IDA / 59880 and Service Delivery Restora Post Limited 92,528.54 Completed 2020-04-19 2019-07-17 2020-05-10 2019-06-25 fice at Damboa Local Govern tions nvelope 6 -06 tion & Improvement ment Area of Borno State BORNO/MCRP/CW/RFQ/111 / Infrastructure Rehabilitation Rehabilitation of Primary Hea Request for Quota Single Stage - One E 2020-11-1 2019-11 IDA / 59880 and Service Delivery Restora Post Limited 82,775.24 Completed 2020-04-23 2019-09-02 2020-05-14 2019-09-23 lthcare Centers in selected L tions nvelope 0 -04 tion & Improvement ocal Government Areas of Bo rno State BORNO/MCRP/CW/RFQ/112/2 0 / Rehabilitation of Court Bui Infrastructure Rehabilitation Request for Quota Single Stage - One E 2020-12-1 2020-12 ldings at Bama, Gwoza, Dikw IDA / 59880 and Service Delivery Restora Post Limited 83,961.86 Completed 2020-05-28 2020-07-06 2020-06-18 2020-07-24 tions nvelope 5 -31 a and Mobbar Local Governm tion & Improvement ent Areas of Borno State BORNO/MCRP/CW/RFQ/113/2 Infrastructure Rehabilitation 0 / Rehabilitation of Tradition Request for Quota Single Stage - One E 2020-12-0 2020-10 IDA / 59880 and Service Delivery Restora Post Limited 69,919.00 Completed 2020-05-14 2020-02-18 2020-06-04 2020-03-10 al Rulers Building in selected tions nvelope 1 -15 tion & Improvement Local Government Areas of B orno State BORNO/MCRP/CW/RFQ/116/2 Infrastructure Rehabilitation 0 / Rehabilitation of existing Request for Quota Single Stage - One E 2020-09-2 2020-12 IDA / 59880 and Service Delivery Restora Post Limited 93,386.86 Completed 2020-06-04 2020-09-29 2020-06-25 2020-10-19 Non-Functional Boreholes in tions nvelope 3 -09 tion & Improvement selected Local Government A reas of Borno State BORNO/MCRP/CW/RFQ/118/2 Infrastructure Rehabilitation 0 / Reconstruction of 60 Nos. Request for Quota Single Stage - One E 1,520,034.1 2020-11-2 2020-12 IDA / 59880 and Service Delivery Restora Post Limited Completed 2020-05-09 2020-12-20 2020-05-30 2020-01-09 Double Classroom Blocks in J tions nvelope 4 6 -24 tion & Improvement ere Local Government Area BORNO/MCRP/CW/RFQ/119/2 Infrastructure Rehabilitation 0 / Reconstruction of 30 Nos. Request for Quota Single Stage - One E 2020-12-0 2021-05 IDA / 59880 and Service Delivery Restora Post Limited 396,674.96 Completed 2020-05-15 2020-07-07 2020-06-05 2020-07-28 Double Classroom Blocks in P tions nvelope 2 -04 tion & Improvement ulka, Gwoza Local Governme nt Area of Borno State BORNO/MCRP/CW/RFQ/120/2 0 / Reconstruction of Perimet Infrastructure Rehabilitation Request for Quota Single Stage - One E 2020-12-0 2020-06 er Fence, Gate and Generato IDA / 59880 and Service Delivery Restora Post Limited 761,174.22 Completed 2020-05-17 2020-03-06 2020-06-07 2020-03-27 tions nvelope 4 -10 rs Houses at Borno State Coll tion & Improvement ege of Basic Studies (BOCOB S) Bama Page 2 BORNO/MCRP/CW/RFQ/126/2 Infrastructure Rehabilitation 0 / Establishment of Vocation Request for Quota Single Stage - One E 1,364,155.1 2020-12-1 2020-12 IDA / 59880 and Service Delivery Restora Post Limited Completed 2020-05-31 2020-01-07 2020-06-21 2020-01-27 al Training Center in Mongun tions nvelope 3 8 -31 tion & Improvement o Local Government Area of Borno State BORNO/MCRP/CW/RFQ/121 / Infrastructure Rehabilitation Establishment of Water Work Request for Quota Single Stage - One E 2020-12-0 2020-11 IDA / 59880 and Service Delivery Restora Post Limited 353,549.05 Completed 2020-05-21 2019-12-23 2020-06-11 2020-01-13 s Facilities at Pulka, Gwoza L tions nvelope 8 -13 tion & Improvement ocal Government Area of Bor no State BORNO/MCRP/CW/RFQ/108/2 Infrastructure Rehabilitation 0 / Construction of Education Request for Quota Single Stage - One E 2020-11-0 2021-01 IDA / 59880 and Service Delivery Restora Post Limited 134,120.37 Completed 2020-04-19 2020-07-09 2020-05-10 2020-07-29 al Office at Kukawa, Hawul a tions nvelope 6 -15 tion & Improvement nd Konduga Local Governme nt Areas of Borno State BORNO/MCRP/CW/RFQ/117/2 Infrastructure Rehabilitation 0 / Rehabilitation of Roads in Request for Quota Single Stage - One E 4,745,074.6 2020-11-0 2021-04 IDA / 59880 and Service Delivery Restora Post Limited Completed 2020-04-15 2020-02-25 2020-05-06 2020-03-13 Jiddari Polo ward of Jere Local tions nvelope 2 2 -28 tion & Improvement Government Area of Borno St ate BORNO/MCRP/CW/RFQ/115,2 0 / Establishment of Sanitatio Infrastructure Rehabilitation Request for Quota Single Stage - One E 2020-12-0 2020-04 n Facilities across Host Com IDA / 59880 and Service Delivery Restora Post Limited 80,455.59 Completed 2020-05-20 2020-01-07 2020-06-10 2020-01-27 tions nvelope 7 -01 munities in selected Local Go tion & Improvement vernment Areas of Borno Sta te BOMCRP/CW/RFB/05/2020 / Infrastructure Rehabilitation Single Stage - One E 2022-09-2 Rehsbilitation of 66Km Maidu IDA / 59880 and Service Delivery Restora Prior Request for Bids Limited 0.00 Canceled 2020-08-17 2020-08-21 2020-08-22 2020-09-21 2020-09-22 2020-10-02 nvelope 2 guri - Bama Road tion & Improvement BOMCRP/CW/DIR/001/20 / R Infrastructure Rehabilitation 12,717,711. 2023-04-2 ehabilitation of 66km Maidug IDA / 59880 and Service Delivery Restora Prior Direct Selection Direct Signed 2020-10-02 2020-09-30 2020-10-04 2020-10-02 2020-10-17 2020-12-24 49 0 uri-Bama Road tion & Improvement BOMCRP/RFB/CW/003/019 / Infrastructure Rehabilitation Single Stage - One E 2020-02-0 Construction of Galameri-Dus IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 0.00 Canceled 2019-08-05 2021-01-13 2019-08-10 2019-09-09 2019-09-23 2019-10-07 nvelope 5 uman-Zabarmari-Gungulong tion & Improvement Feeder Road Request for BOMCRP/CW/DIR/002/2020 / Quotations - Infrastructure Rehabilitation REHABILITATION OF 4.17km Small Works Under Imple 2022-11-1 IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 0.00 2021-05-03 2021-08-10 2021-05-05 2021-05-15 MONGUNO TOWNSHIP ROAD, (Emergency) mentation 3 tion & Improvement IN MONGUNO LOCAL GOVER SPD -Non Co NMENT AREA mpetitive BORNO/MCRP/CW/RFB/122/2 Infrastructure Rehabilitation 0 / Rehabilitation of 4.197k Single Stage - One E 2021-08-0 IDA / 59880 and Service Delivery Restora Prior Request for Bids Limited 0.00 Canceled 2020-10-15 2020-10-20 2020-12-01 2020-12-31 2021-02-04 m Monguno Township Roads, nvelope 3 tion & Improvement Monguno Local Government Area of Borno State BORN/MCRP/CW/RFQ/114/20 Infrastructure Rehabilitation / Construction of Sanitation F Request for Quota Single Stage - One E 2020-12-0 IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2020-05-15 2020-06-05 acilities in selected Local Gov tions nvelope 2 tion & Improvement ernment Areas of Borno Stat e NG-BORNO MCRP-133228-C Infrastructure Rehabilitation Request for Quota Single Stage - One E 2020-01-1 W-RFQ / Construction of Sani IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2019-10-24 2019-11-15 tions nvelope 4 tation Facilities in 21 LGAs tion & Improvement NG-BORNO MCRP-133229-C Infrastructure Rehabilitation W-RFQ / Establishment of Sa Request for Quota Single Stage - One E 2020-01-2 IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2019-11-02 2019-11-23 nitation Facilities across Host tions nvelope 2 tion & Improvement Communities in 11 LGAs BORNO/MCRP/CW/RFQ/110/2 Infrastructure Rehabilitation 0 / Renovation of Educational Request for Quota Single Stage - One E 2020-11-0 IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2020-04-18 2020-05-09 Office Kaga Local Governmen tions nvelope 5 tion & Improvement t Area of Borno State BORNO/MCRP/CW/RFQ/103/2 Infrastructure Rehabilitation 0 / Construction of Double Cl Request for Quota Single Stage - One E 2020-10-2 IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2020-04-08 2020-04-29 assroom Blocks at Damasak tions nvelope 6 tion & Improvement Town of Mobbar Local Gover nment Area BORNO/MCRP/CW/RFQ/101/2 Infrastructure Rehabilitation 0 / Construction of Double Cl Request for Quota Single Stage - One E 2020-10-2 IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2020-04-08 2020-04-29 assroom Blocks at Banki Tow tions nvelope 6 tion & Improvement n of Bama Local Government Area BORNO/MCRP/CW/RFQ/106/2 Infrastructure Rehabilitation 0 / Renovation of Double Clas Request for Quota Single Stage - One E 2020-10-2 IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2020-04-10 2020-05-01 sroom Blocks at Abadam Loc tions nvelope 8 tion & Improvement al Government Area NG-BORNO MCRP-58897-CW Infrastructure Rehabilitation Single Stage - One E 2019-07-2 -RFB / Renovation Of 31- No. IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 0.00 Canceled 2018-10-08 2018-10-13 2018-11-24 2018-12-24 2019-01-28 nvelope 7 Double Classroom Block -Ba tion & Improvement ma NG-BORNO MCRP-58384-CW Strengthening Peace Buildin Request for Quota Single Stage - One E 2019-04-1 -RFQ / Rehabilitation of Minis IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 Canceled 2018-08-20 2018-10-15 tions nvelope 3 try Building (Ngala, Monguno on ) NG-BORNO MCRP-130200-C Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-12-1 W-RFQ / Construction of 15-N IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2019-09-20 2019-10-12 tions nvelope 1 o. Double Classroom Block Di tion & Improvement kwa NG-BORNO MCRP-130206-C Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-12-0 W-RFQ / Renovation of 20-No IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2019-09-18 2019-10-10 tions nvelope 9 . 20 Double Classroom Block tion & Improvement at Abadam NG-BORNO MCRP-58781-CW Infrastructure Rehabilitation -RFQ / Rehabilitation of Umar Request for Quota Single Stage - One E 2019-05-1 IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2018-09-17 2018-11-12 Ibn Ibrahim college Library in tions nvelope 1 tion & Improvement Bama Local Government Are a of Borno State BOMCRP/RFB/CW/001/019 / Infrastructure Rehabilitation Single Stage - One E 2019-08-3 Rehabilitation of 1 Ngala Brid IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 0.00 Canceled 2019-03-05 2019-03-10 2019-04-09 2019-04-19 2019-05-03 nvelope 1 ge tion & Improvement Infrastructure Rehabilitation BOMCRP/RFB/CW/002/019 / Single Stage - One E 2020-03-1 IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 0.00 Canceled 2019-09-12 2019-09-17 2019-10-17 2019-10-31 2019-11-14 Rehabilitation of Biu bridge nvelope 3 tion & Improvement Page 3 NG-BORNO MCRP-58803-CW Infrastructure Rehabilitation -RFB / RehabilitatIon of 3 Ge Request for Quota Single Stage - One E 2019-06-1 IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2018-10-17 2018-12-12 neral Hospital in (ABADAM, A tions nvelope 0 tion & Improvement SKIRA UBA & KALA-BALGE) NG-BORNO MCRP-130253-C W-RFQ / Rehabilitation of Co Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-12-1 mprehensive Health Care Ce IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2019-09-27 2019-10-20 tions nvelope 9 nter (CivilWorks, Solar Boreh tion & Improvement ole, Fence & Security Post) at CHC Izge, Gwoza NG-BORNO MCRP-57567-CW Infrastructure Rehabilitation -RFQ / Solar Lighting System Request for Quota Single Stage - One E 2019-05-2 IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2018-10-02 2018-11-27 to Umar Ibrahim College Libr tions nvelope 6 tion & Improvement ary Bama and Borno State Li brary Maiduguri NG-BORNO MCRP-130211-C Infrastructure Rehabilitation W-RFQ / Rehabilitation of 8 Bl Request for Quota Single Stage - One E 2019-12-1 IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2019-09-21 2019-10-13 ocks of Laboratories at Umar tions nvelope 2 tion & Improvement Ibn Ibrahim College Bama NG-BORNO MCRP-130219-C Infrastructure Rehabilitation W-RFQ / Construction of Sola Request for Quota Single Stage - One E 2019-12-2 IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2019-09-29 2019-10-21 r Powered Boreholes (2No.) a tions nvelope 0 tion & Improvement t Umar Ibn Ibrahim College B ama NG-BORNO MCRP-130203-C Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-12-1 W-RFQ / Construction of 20-N IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2019-09-22 2019-10-14 tions nvelope 3 o.Double Classroom Block at tion & Improvement Kukawa BOMCRP/RFB/CW/035/019 / Infrastructure Rehabilitation Single Stage - One E 2020-01-1 Rehabilitation of Comprehen IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 0.00 Canceled 2019-05-15 2019-05-20 2019-06-19 2019-07-03 2019-07-17 nvelope 3 sive Health Center in (CHC) i tion & Improvement n 15 LGAs NG-BORNO MCRP-58871-CW Infrastructure Rehabilitation -RFB / Rehabilitation of Local Request for Quota Single Stage - One E 2019-05-1 IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2018-09-17 2018-11-12 Govt Secretariats of 8 Local tions nvelope 1 tion & Improvement Government Areas of Borno State BOMCRP-AF/CW/RFQ/001 / R econstruction of 1 Bedroom s Request for Infrastructure Rehabilitation emi detached staff quarters f Request for Quota Single Stage - One E Quotations ( 2022-08-1 IDA / 59880 and Service Delivery Restora Post Limited 43,803.64 Signed 2021-12-19 2022-03-15 2022-02-13 2022-04-04 or the 18 PHCs Konduga (2), tions nvelope Non Bank-SP 2 tion & Improvement Bayo (1), A/Uba (2), MMC (3), D) Hawul (1), Gwoza (1), Chibok (2), Shani (1) and Marte (1) BOMCRP-AF/CW/RFQ/002 / R Request for econstruction of 2 Bedroom s Quotations - Infrastructure Rehabilitation emi detached staff quarters f Request for Quota Single Stage - One E Small Works 2022-08-2 IDA / 59880 and Service Delivery Restora Post Limited 59,332.50 Signed 2022-01-04 2022-03-31 2022-03-01 2022-04-05 or the 18 PHCs Konduga (4), tions nvelope (Emergency) 8 tion & Improvement Bayo (1), A/Uba (3), MMC (3), SPD -Compet Hawul (1), Gwoza (1), Chibok itive (2), Shani (1) and Marte (1) BOMCRP-AF/CW/RFQ/003 / R Request for Infrastructure Rehabilitation ehabilitation of Local Govern Request for Quota Single Stage - One E Quotations ( Pending Imp 2022-08-1 IDA / 59880 and Service Delivery Restora Post Limited 0.00 2021-12-17 2022-02-11 emnt Lodges at Kukawa, Guz tions nvelope Non Bank-SP lementation 0 tion & Improvement amala and Marte Local Gover D) nment Areas BOMCRP-AF/CW/RFQ/004 / R Request for ehabilitation of Traditional Ru Infrastructure Rehabilitation Request for Quota Single Stage - One E Quotations ( Pending Imp 2022-09-0 lers Buildings Dikwa, Kaga, K IDA / 59880 and Service Delivery Restora Post Limited 0.00 2022-01-12 2022-03-09 tions nvelope Non Bank-SP lementation 5 ala Balge, Abadam, Kukawa tion & Improvement D) and Guzamla Local Governm ent Areas BOMCRP-AF/CW/RFQ/005 / R Request for Infrastructure Rehabilitation ehabilitation of Court Buildin Request for Quota Single Stage - One E Quotations ( Pending Imp 2022-07-2 IDA / 59880 and Service Delivery Restora Post Limited 0.00 2022-01-05 2022-01-25 gs Ngala, Mobbar, A/Uba, Mo tions nvelope Non Bank-SP lementation 4 tion & Improvement nguno and konduga Local Go D) vernment Areas BOMCRP-AF/CW/RFQ/006 / R Request for Infrastructure Rehabilitation ehabilitation of Local Govern Request for Quota Single Stage - One E Quotations ( Pending Imp 2022-07-2 IDA / 59880 and Service Delivery Restora Post Limited 0.00 2022-01-08 2022-01-28 ment Secretariats Kukawa, G tions nvelope Non Bank-SP lementation 7 tion & Improvement uzamala and Marte Local Go D) vernment Areas Request for BOMCRP-AF/CW/RFQ/007 / R Infrastructure Rehabilitation Request for Quota Single Stage - One E Quotations ( Pending Imp 2022-07-1 esuscitation of Damasak Irrig IDA / 59880 and Service Delivery Restora Post Limited 0.00 2021-12-29 2022-01-18 tions nvelope Non Bank-SP lementation 7 ation Scheme tion & Improvement D) Request for BOMCRP-AF/CW/RFQ/008 / R Infrastructure Rehabilitation Request for Quota Single Stage - One E Quotations ( 2022-09-1 esuscitation of Monguno Irrig IDA / 59880 and Service Delivery Restora Post Limited 205,529.18 Signed 2022-02-22 2021-12-28 2022-03-14 2022-01-17 tions nvelope Non Bank-SP 0 ation Scheme tion & Improvement D) BOMCRP-AF/CW/RFQ/009 / E Request for Infrastructure Rehabilitation stablishment of Monguno Liv Request for Quota Single Stage - One E Quotations ( Pending Imp 2022-08-2 IDA / 59880 and Service Delivery Restora Post Limited 0.00 2022-02-04 2022-02-24 estock Investigation and Bre tions nvelope Non Bank-SP lementation 3 tion & Improvement eding Center (LIBC) D) BOMCRP-AF/CW/RFQ/010 / E stablishment of agro-logistic hubs in some selected LGAs Request for Infrastructure Rehabilitation across the state to enhance Request for Quota Single Stage - One E Quotations ( 2022-08-0 2022-06 IDA / 59880 and Service Delivery Restora Post Limited 75,498.65 Completed 2022-01-20 2022-03-14 2022-02-09 2022-04-04 production, processing, pack tions nvelope Non Bank-SP 8 -28 tion & Improvement aging and marketing of farm D) produce, fruits and vegetable s, livestocks and poultry prod ucts. Dikwa, Kukawa, Gubio a nd Mobbar BOMCRP-AF/CW/RFQ/011 / 5 00,000ltr corrugated overhea d tanks with 25m high steel s Request for Infrastructure Rehabilitation tanchion complete with conn Request for Quota Single Stage - One E Quotations ( Pending Imp 2022-07-2 IDA / 59880 and Service Delivery Restora Post Limited 0.00 2022-01-06 2022-01-26 ection accessories Monguno ( tions nvelope Non Bank-SP lementation 5 tion & Improvement 2), Gubio (2), Magumari (2), D) Marte (2), Guzamala (2), Mob bar (2), Kukawa (2), Abadam (2), Kala Balge (2) and Dikwa (2) BOMCRP-AF/CW/RFQ/012 / R Request for ehabilitation of Double Classr Infrastructure Rehabilitation Request for Quota Single Stage - One E Quotations ( Pending Imp 2022-08-1 oom Blocks MMc (10), Jere (1 IDA / 59880 and Service Delivery Restora Post Limited 0.00 2022-01-28 2022-02-17 tions nvelope Non Bank-SP lementation 6 0), Monguno (5), Marte (5), D tion & Improvement D) ikwa (5), Konduga (10), Kuka wa (5) and Baga (5) Page 4 BOMCRP-AF/CW/RFQ/015 / R Request for Infrastructure Rehabilitation ehabilitation of Laboratory M Request for Quota Single Stage - One E Quotations ( Pending Imp 2022-08-2 IDA / 59880 and Service Delivery Restora Post Limited 0.00 2022-02-03 2022-02-23 MC (7), Jere (7), Biu (3), Haw tions nvelope Non Bank-SP lementation 2 tion & Improvement ul (2), A/Uba (2), Bayo (1) an D) d Dikwa (2) Request for BOMCRP-AF/CW/RFQ/013 / R Quotations - econstruction of Double Clas Infrastructure Rehabilitation Request for Quota Single Stage - One E Small Works Pending Imp 2022-09-0 sroom Blocks Mafa (5), Guza IDA / 59880 and Service Delivery Restora Post Limited 0.00 2022-01-15 2022-03-12 tions nvelope (Emergency) lementation 8 mala (5), Kala Balge (5), Dik tion & Improvement SPD -Compet wa (5), MMC (8), Jere (7) and itive Marte (5) BOMCRP-AF/CW/RFQ/014 / R Request for econstruction of VIP Toilets in Infrastructure Rehabilitation Request for Quota Single Stage - One E Quotations ( Pending Imp 2022-08-0 Schools MMC (5), Jere (5), Gu IDA / 59880 and Service Delivery Restora Post Limited 0.00 2022-01-21 2022-02-10 tions nvelope Non Bank-SP lementation 9 bio (3), Monguno (3), Marte ( tion & Improvement D) 4), Mafa (4), Dikwa (4), Gwoz a (4) and Konduga (1) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-BORNO MCRP-55919-GO Strengthening Peace Buildin -RFB / Supply of non food ite Request for Quota Single Stage - One E IDA / 59880 g, Stability and Social Cohesi Post Open - National 414,196.65 Completed 2018-08-29 2018-10-24 2019-02-05 2019-04-22 2018-10-24 m Kits for household support tions nvelope on for 9 Local Government Area s of Borno State NG-BORNO MCRP-58782-GO -RFB / Supply of Agricultural Strengthening Peace Buildin Request for Quota Single Stage - One E Support kits with Seeds, Ferti IDA / 59880 g, Stability and Social Cohesi Post Open - National 190,176.53 Completed 2018-08-29 2018-10-24 2018-09-05 2019-04-22 2018-09-10 tions nvelope lizers and Small Work Farm T on ools for 9 Local Government Areas of Borno State NG-BORNO MCRP-55925-GO Strengthening Peace Buildin -RFB / Supply of Small Animal Request for Quota Single Stage - One E IDA / 59880 g, Stability and Social Cohesi Post Open - National 352,563.75 Completed 2018-08-29 2018-10-24 2018-10-15 2019-04-22 2018-10-30 s for 9 Local Government Are tions nvelope on as of Borno State NG-BORNO MCRP-58006-GO Strengthening Peace Buildin -RFB / Supply of Non-agricult Request for Quota Single Stage - One E IDA / 59880 g, Stability and Social Cohesi Post Open - National 487,381.13 Completed 2018-08-29 2018-10-24 2018-10-11 2019-04-22 2018-10-17 ural Livelihood Kits to 9 Local tions nvelope on Government Areas of Borno State NG-BORNO MCRP-58404-GO -RFB / Procurement of 2 Toyo Technical Assistance and Pro Single Stage - One E IDA / 59880 Post Request for Bids Open - National 0.00 Canceled 2018-04-16 2019-02-06 2018-04-21 2018-06-02 2018-07-18 2018-07-02 2019-02-06 2018-08-06 2019-02-02 ta Prado Jeep, 3 Toyota Hilux, ject Management Support nvelope 1 Toyota Corolla NG-BORNO MCRP-58381-GO -RFQ / Procurement of 100KV Technical Assistance and Pro Request for Quota Single Stage - One E IDA / 59880 Post Open - National 0.00 Canceled 2018-04-14 2018-06-09 2018-12-06 A sound proof Generator, 10 ject Management Support tions nvelope KVA Inverter System NG-BORNO MCRP-58351-GO -RFB / Supply of broadcasting equipment to selected Radio Strengthening Peace Buildin Single Stage - One E Station for content dissemina IDA / 59880 g, Stability and Social Cohesi Post Request for Bids Open - National 0.00 Canceled 2018-04-20 2018-04-25 2018-06-06 2018-07-06 2018-08-10 2019-02-06 nvelope tion towards deradicalisation, on grievance redress and peace building media outreach cam paign to target LGAs. NG-BORNO MCRP-58380-GO Technical Assistance and Pro Request for Quota Single Stage - One E -RFQ / Procurement of 1 Vide IDA / 59880 Post Open - National 0.00 Canceled 2018-04-18 2018-06-13 2018-12-10 ject Management Support tions nvelope o Camera, 2 DLSR Cameras, NG-BORNO MCRP-52708-GO -RFB / Furniture for Library/ O Infrastructure Rehabilitation Single Stage - Two E ffices in the Borno State Libr IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 0.00 Canceled 2019-07-16 2019-07-21 2019-09-01 2019-11-14 2019-12-19 2020-06-16 nvelope ary and Furniture for 15 bloc tion & Improvement ks of classrooms in Umar Ibn ibrahim college Bama NG-BORNO MCRP-58807-GO -RFQ / Rehabilitation of Comp Infrastructure Rehabilitation rehensive Healthcare Center Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Open - National 67,027.47 Completed 2018-11-05 2018-12-31 2019-04-29 2019-06-29 2019-12-05 (Civil Works, Solar Borehole, tions nvelope tion & Improvement Fence & Security Post) in Izg e town of Gwoza Local Gover nment Area of Borno State. NG-BORNO MCRP-58008-GO -RFQ / Statewide sponsorship for Radio Programming for Pe Strengthening Peace Buildin Request for Quota Single Stage - One E acebuilding Campaign/Conte IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 Canceled 2018-10-24 2018-12-19 2019-06-17 tions nvelope nt on deradicalisation, grieva on nce redress and cultural/relig ious tolerance in 27 Local Go vernment Areas of Borno Sta te. NG-BORNO MCRP-130187-G Infrastructure Rehabilitation Request for Quota Single Stage - One E O-RFQ / Supply of Teaching IDA / 59880 and Service Delivery Restora Post Limited 967,362.59 Completed 2019-09-11 2019-06-04 2019-10-02 2019-06-24 2019-12-31 2019-07-03 tions nvelope Materials (22 Communities) tion & Improvement NG-BORNO MCRP-130192-G Infrastructure Rehabilitation Request for Quota Single Stage - One E O-RFQ / Supply of First aid Kit IDA / 59880 and Service Delivery Restora Post Limited 133,307.89 Completed 2019-09-14 2019-12-27 2019-10-05 2020-01-17 2019-12-04 2020-02-18 tions nvelope s tion & Improvement NG-BORNO MCRP-130193-G Infrastructure Rehabilitation Request for Quota Single Stage - One E O-RFQ / Procurement of Furni IDA / 59880 and Service Delivery Restora Post Limited 401,290.82 Completed 2019-09-18 2019-07-05 2019-10-11 2019-07-26 2019-12-10 2020-02-20 tions nvelope ture tion & Improvement NG-BORNO MCRP-130209-G Infrastructure Rehabilitation O-RFQ / Furniture for 15 Bloc Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 479,285.03 Completed 2019-09-22 2020-01-07 2019-10-14 2020-01-29 2019-12-13 2020-03-20 ks of Classrooms at Umar Ibn tions nvelope tion & Improvement Ibrahim College Bama NG-BORNO MCRP-130227-G Infrastructure Rehabilitation Request for Quota Single Stage - One E O-RFQ / Provisions for Solar e IDA / 59880 and Service Delivery Restora Post Limited 544,223.65 Completed 2019-09-26 2019-07-16 2019-10-17 2019-08-05 2019-11-26 2019-08-22 tions nvelope lectrification to 3 General Ho tion & Improvement spitals NG-BORNO MCRP-130243-G Infrastructure Rehabilitation O-RFQ / Supply of Essential D Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 405,142.20 Completed 2019-09-28 2019-07-29 2019-10-21 2019-08-15 2019-11-20 2019-09-09 rugs/Medical Consumables to tions nvelope tion & Improvement 3 General Hospitals Page 5 NG-BORNO MCRP-133079-G Infrastructure Rehabilitation Request for Quota Single Stage - One E O-RFQ / Supply of Medical eq IDA / 59880 and Service Delivery Restora Post Limited 48,000.86 Completed 2019-09-29 2020-06-24 2019-10-21 2020-07-14 2019-12-20 2020-08-06 tions nvelope uipment to Izge CHC, Gwoza tion & Improvement LGA NG-BORNO MCRP-133090-G Infrastructure Rehabilitation O-RFQ / Supply Essential Dru Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 179,495.82 Completed 2019-10-06 2020-03-04 2019-10-28 2020-03-24 2019-12-12 2020-04-08 gs/Medical Consumables to 3 tions nvelope tion & Improvement Comprehensive Health Cente rs NG-BORNO MCRP-133095-G Infrastructure Rehabilitation Request for Quota Single Stage - One E O-RFQ / Supply of Medical Eq IDA / 59880 and Service Delivery Restora Post Limited 636,589.86 Completed 2019-10-09 2020-07-10 2019-10-31 2020-08-03 2019-12-30 2020-08-20 tions nvelope uipment to 15 PHCs tion & Improvement NG-BORNO MCRP-133221-G Infrastructure Rehabilitation Request for Quota Single Stage - One E O-RFQ / Supply of Essential D IDA / 59880 and Service Delivery Restora Post Limited 94,876.36 Completed 2019-10-13 2020-10-13 2019-11-04 2020-11-02 2020-01-03 2020-11-19 tions nvelope rugs to 15 PHCs tion & Improvement BORNO/MCRP/GO/RFQ/50/20 Infrastructure Rehabilitation Request for Quota Single Stage - One E / Procurement of Furniture fo IDA / 59880 and Service Delivery Restora Post Limited 320,175.05 Completed 2020-04-12 2020-02-20 2020-05-02 2020-03-10 2020-06-01 2020-04-02 tions nvelope r Library/Offices in Maiduguri tion & Improvement BORNO/MCRP/GO/RFQ/55/20 / Supply of Medical Equipmen Infrastructure Rehabilitation Request for Quota Single Stage - One E t to Primary Healthcare Cent IDA / 59880 and Service Delivery Restora Post Limited 284,337.26 Completed 2020-05-02 2020-09-30 2020-05-23 2020-10-20 2020-07-22 2020-11-06 tions nvelope ers in selected Local Govern tion & Improvement ment Areas of Borno State BORNO/MCRP/GO/RFQ/56/20 Infrastructure Rehabilitation / Supply of Essential Drugs to Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 427,444.16 Completed 2020-04-30 2019-11-01 2020-05-21 2019-11-22 2020-06-30 2019-12-17 Primary Healthcare Centers i tions nvelope tion & Improvement n selected Local Government Areas of Borno State BORNO/MCRP/GO/RFQ/57/20 / Installation of Solar Inverter Infrastructure Rehabilitation Request for Quota Single Stage - One E s in Primary Healthcare Cent IDA / 59880 and Service Delivery Restora Post Limited 187,371.86 Completed 2020-04-30 2020-02-25 2020-05-20 2020-03-16 2020-06-29 2020-04-02 tions nvelope ers in selected Local Govern tion & Improvement ment Areas of Borno State BORNO/MCRP/GO/RFQ/59/20 Infrastructure Rehabilitation Request for Quota Single Stage - One E / Provision of Instructional Ma IDA / 59880 and Service Delivery Restora Post Limited 782,803.01 Completed 2020-05-28 2020-12-11 2020-06-18 2020-12-31 2020-12-15 2021-01-15 tions nvelope terials to Schools in Borno St tion & Improvement ate BORNO/MCRP/GO/RFQ/61/20 Infrastructure Rehabilitation Request for Quota Single Stage - One E / Provision of Furniture for Sc IDA / 59880 and Service Delivery Restora Post Limited 120,500.42 Completed 2020-05-31 2020-08-11 2020-06-21 2020-09-01 2020-12-18 2020-09-18 tions nvelope hools in Borno State tion & Improvement BORNO/MCRP/GO/RFQ/62/20 Infrastructure Rehabilitation / Provision of Hospital Equip Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 941,856.67 Completed 2020-05-28 2021-03-11 2020-06-18 2021-03-31 2020-12-15 2021-04-26 ment for Tertiary Health Cent tions nvelope tion & Improvement er (Borno State University) BORNO/MCRP/GO/RFQ/63/20 Infrastructure Rehabilitation Request for Quota Single Stage - One E / Provision of Furniture to Pri IDA / 59880 and Service Delivery Restora Post Limited 623,855.70 Completed 2020-05-28 2020-05-08 2020-06-18 2020-06-01 2020-12-15 2020-06-23 tions nvelope mary Healthcare Centers in B tion & Improvement orno State BORNO/MCRP/GO/RFQ/58/20 Strengthening Peace Buildin Request for Quota Single Stage - One E IDA / 59880 Post Limited 162,792.85 Completed 2020-04-22 2020-10-27 2020-05-14 2020-11-16 2020-08-12 2020-12-07 / Supply of non Food item Kit g, Stability and Social Cohesi tions nvelope s on BORNO/MCRP/GO/RFQ/54/20 Infrastructure Rehabilitation Request for Quota Single Stage - One E / Installation of Solar Lighting IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2020-04-17 2020-05-08 2020-06-27 tions nvelope System for Library at Maidug tion & Improvement uri Borno State NG-BORNO MCRP-133085-G Infrastructure Rehabilitation O-RFQ / Supply of Essential D Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2019-09-29 2019-10-21 2019-12-20 rugs/Medical Consumables to tions nvelope tion & Improvement CHC Izge,Gwoza LGA NG-BORNO MCRP-133222-G Infrastructure Rehabilitation Request for Quota Single Stage - One E O-RFQ / Installation of Solar I IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2019-10-02 2019-10-24 2019-12-23 tions nvelope nverters to 15 PHCs tion & Improvement NG-BORNO MCRP-52158-GO -RFQ / Supply and Installation of Solar Inverters in 15 Prima Infrastructure Rehabilitation Request for Quota Single Stage - One E ry Health Cares in (Ngala, Ng IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2019-02-24 2019-04-21 2019-10-18 tions nvelope anzai Kukawa, Biu, Konduga, tion & Improvement Gubio, Askira/Uba, Guzamala , Bama, Jere, Marte, Mobbar, Dikwa, Mafa, Abadam) NG-BORNO MCRP-58872-GO Infrastructure Rehabilitation -RFQ / Books and other learni Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2019-03-09 2019-05-04 2019-10-31 ng Materials including elibrar tions nvelope tion & Improvement y in the Borno State library NG-BORNO MCRP-133078-G Infrastructure Rehabilitation Request for Quota Single Stage - One E O-RFQ / Installation of Solar I IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2019-10-02 2019-10-24 2019-12-03 tions nvelope nverters at CHC Izge, Gwoza tion & Improvement LGA BORNO/MCRP/GO/RFQ/51/20 Infrastructure Rehabilitation / Procurement of Books and o Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2020-04-08 2020-04-29 2020-05-29 ther learning materials includ tions nvelope tion & Improvement ing E-Library at Maiduguri, B orno State NG-BORNO MCRP-130215-G Infrastructure Rehabilitation O-RFQ / Supply of Computers Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2019-09-25 2019-10-17 2019-11-16 and other accessories to Um tions nvelope tion & Improvement ar Ibn Ibrahim College Bama BORNO/MCRP/GO/RFQ/53/20 Infrastructure Rehabilitation Request for Quota Single Stage - One E / Procurement of Computers IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2020-04-15 2020-05-06 2020-06-15 tions nvelope and accessories tion & Improvement NG-BORNO MCRP-130189-G Infrastructure Rehabilitation Request for Quota Single Stage - One E O-RFQ / Supply of Laboratory IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2019-09-14 2019-10-06 2020-01-04 tions nvelope Equipment tion & Improvement BOMCRP/RFQ/CW/034/019 / Infrastructure Rehabilitation Request for Quota Single Stage - One E Supply of Medical equipment IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2019-03-02 2019-04-06 2019-04-20 tions nvelope to 1 of 3 (Lassa) General Hos tion & Improvement pitals Page 6 NG-BORNO MCRP-133088-G Infrastructure Rehabilitation O-RFQ / Supply of Medical eq Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2019-09-25 2019-10-16 2019-11-30 uipment to 3 Comprehensive tions nvelope tion & Improvement Health Centers (Hawul, Mobb ar and Damboa) NG-BORNO MCRP-58049-GO -RFQ / Suppy of Computers a Infrastructure Rehabilitation Request for Quota Single Stage - One E nd other accessories to the B IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2019-03-09 2019-05-04 2019-10-31 tions nvelope orno State Library , Maidugur tion & Improvement i and Umar Ibn ibrahim colle ge Bama BOMCRP-AF/GO/RFQ/001 / S Contingent Emergency Resp Request for Quota Single Stage - One E Pending Impl upply of Medical Equipment t IDA / 59880 Post Limited 0.00 2021-12-15 2022-02-09 2022-08-08 onse tions nvelope ementation o Magumeri and Gubio BOMCRP-AF/GO/RFQ/002 / S Contingent Emergency Resp Request for Quota Single Stage - One E Pending Impl upply of Essential Drugs/Medi IDA / 59880 Post Limited 0.00 2021-12-18 2022-02-12 2022-08-11 onse tions nvelope ementation cal Consumables to Magume ri and Gubio BOMCRP-AF/GO/RFQ/003 / Pr ovision of Vocational Training Infrastructure Rehabilitation Centre Equipments to Mafa, Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 996,264.31 Completed 2022-02-03 2022-02-15 2022-02-23 2022-03-07 2022-05-24 2022-03-21 Magumeri, Jere, Gubio, Mong tions nvelope tion & Improvement uno, Ngala, Bama, A/Uba, Dik wa and Gwoza Local Govern ment Areas BOMCRP-AF/GO/RFQ/004 / Pr ovision of Classroom Furnitur Infrastructure Rehabilitation Request for Quota Single Stage - One E Pending Impl es Mafa (4), Gubio (4), Guza IDA / 59880 and Service Delivery Restora Post Limited 0.00 2022-07-24 2022-09-18 2023-03-17 tions nvelope ementation mala (4), Kaga (4), Marte (4), tion & Improvement Kala Balge (4) Magumeri (4) and Dikwa (4) BOMCRP-AF/GO/RFQ/009 / Pr ocurement of Strategic Com Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl IDA / 59880 Post Limited 0.00 2022-03-09 2022-03-29 2022-09-25 munications Equipment (Cam ject Management Support tions nvelope ementation eras, Vioce Recorders, Camc orders, CUGS etc) BOMCRP-AF/GO/RFQ/010 / Pr Technical Assistance and Pro Request for Quota Single Stage - One E ocurement of Fire Protective IDA / 59880 Post Limited 8,149.51 Completed 2022-03-10 2022-05-09 2022-03-30 2022-05-27 2022-09-26 2022-06-07 ject Management Support tions nvelope & Prevention Equipments BOMCRP-AF/GO/RFQ/011 / Pr Strengthening Peace Buildin Request for Quota Single Stage - One E ovision of Agric kits and Impl IDA / 59880 g, Stability and Social Cohesi Post Limited 786,674.15 Completed 2021-12-23 2021-10-04 2022-01-12 2021-10-22 2022-07-11 2021-11-10 tions nvelope ements (plought, ridgers,pla on nters,sprayers) BOMCRP-AF/GO/RFQ/012 / Pr Strengthening Peace Buildin ovision of Non-Agricultural Li Request for Quota Single Stage - One E Pending Impl IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 2022-03-17 2022-04-06 2022-10-03 velihood Kits (Knitting Machi tions nvelope ementation on ne, Sewing Machines, Oil Extr action Machines) BOMCRP-AF/GO/RFQ/014 / Pr Strengthening Peace Buildin Request for Quota Single Stage - One E ocurement of Agricultural inp IDA / 59880 g, Stability and Social Cohesi Post Limited 251,566.42 Completed 2022-05-01 2021-10-04 2022-05-21 2021-10-22 2022-06-20 2021-11-09 tions nvelope uts (Seeds, Pesticides etc) on BOMCRP-AF/GO/RFQ/006 / Pr Technical Assistance and Pro Request for Quota Single Stage - One E IDA / 59880 Post Limited 0.00 Canceled 2022-03-10 2022-03-30 2022-09-26 ocurement of Office Utilities ject Management Support tions nvelope BOMCRP-AF/GO/RFQ/50/021 Infrastructure Rehabilitation / PROCUREMENT OF WATER Request for Quota Single Stage - One E Pending Impl IDA / 59880 and Service Delivery Restora Post Limited 0.00 2022-06-15 2022-07-05 2022-08-04 PURIFIERS TO MAIDUGURI W tions nvelope ementation tion & Improvement ATER TREATMENT PLANT NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-BORNO MCRP-58894-CS- QCBS / Specialized psycho-so Strengthening Peace Buildin cial support responding to ra Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Open - National 374,263.02 Completed 2018-09-21 2019-07-01 2018-10-12 2019-10-17 2018-11-25 2019-07-03 2018-12-25 2019-07-23 2019-01-29 2019-07-29 2019-07-28 2019-10-11 pid assessment needs/gaps a cation Selection on nd pop to intervene in 27 Loc al Government Areas of Born o State. NG-BORNO MCRP-58895-CS- CQS / Consultancy for the Mo Strengthening Peace Buildin bilisation and Organisation of Consultant Qualifi Pending Impleme IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 2018-09-21 2018-10-12 2018-11-25 2018-12-25 2019-01-29 2019-07-28 Civic Education with Cultural cation Selection ntation on and Recreational activities wi th 27 Local Government Area s of Borno State NG-BORNO MCRP-53660-CS- CQS / Consultancy for Sensiti Strengthening Peace Buildin zation, Community Mobilizati Consultant Qualifi Under Implement IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 2018-09-21 2018-10-12 2018-11-25 2018-12-25 2019-01-29 2019-07-28 on and formation of peace gr cation Selection ation on oups within affected Commu nities in 7 Local Government Areas of Borno State NG-BORNO MCRP-58889-CS- CQS / Capacity Building for 1 Strengthening Peace Buildin 0 Local Government Emerge Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 Canceled 2019-04-18 2019-04-18 2019-04-18 2019-04-18 2019-04-18 2019-04-18 ncy Management Responder cation Selection on s in Displaced and Transition al Local Government Officials NG-BORNO MCRP-58864-CS- Strengthening Peace Buildin CQS / Training for officials of Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 Canceled 2018-06-11 2018-07-02 2018-08-15 2018-09-14 2018-10-19 2019-04-17 relevant State MDAs on effec cation Selection on tive approaches to UASC Page 7 NG-BORNO MCRP-58382-CS- CQS / Consultancy to provide Strengthening Peace Buildin Consultant Qualifi Capacity building of LG Offic IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 Canceled 2018-07-02 2018-07-23 2018-09-05 2018-10-05 2018-11-09 2019-05-08 cation Selection ers for economic planning an on d policy development NG-BORNO MCRP-58040-CS- CQS / Capacity building of L Strengthening Peace Buildin Consultant Qualifi G Officers for local governme IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 Canceled 2018-05-25 2018-06-15 2018-07-29 2018-08-28 2018-10-02 2019-03-31 cation Selection nts on budget planning and e on xecution, monitoring and rep orting NG-BORNO MCRP-58752-CS- Strengthening Peace Buildin Consultant Qualifi CQS / Consultancy for Post-C IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 Canceled 2018-04-02 2018-04-23 2018-06-06 2018-07-06 2018-08-10 2019-02-06 cation Selection onflict Transitional Justice an on d Accountability NG-BORNO MCRP-53657-CS- CQS / Sensitization, training ( especially on Identification, D Strengthening Peace Buildin ocumentation, Tracing and R Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 Canceled 2018-06-11 2018-07-02 2018-08-15 2018-09-14 2018-10-19 2019-04-17 eunification and follow up) a cation Selection on nd coaching for state and no n-state partners on case man agement of UASC (Unaccomp anied and Separated Childre n) NG-BORNO MCRP-58439-CS- Infrastructure Rehabilitation Consultant Qualifi Pending Impleme QCBS / Sensitization and Mob IDA / 59880 and Service Delivery Restora Post Open - National 0.00 2018-09-10 2018-10-01 2018-11-14 2018-12-14 2019-01-18 2019-07-17 cation Selection ntation ilisation for Health (Outreach tion & Improvement Programs) NG-BORNO MCRP-53655-CS- QCBS / Training of Communit y Health Workers (CHeWs, V Infrastructure Rehabilitation Quality And Cost- Under Implement HWs, Midwives) to Staff Targ IDA / 59880 and Service Delivery Restora Post Open - National 0.00 2019-03-18 2019-04-08 2019-05-22 2019-06-19 2019-07-19 2019-08-23 2019-09-27 2020-09-26 Based Selection ation eted Health Facilities (3Nos c tion & Improvement onsultancies across the state . Amount Inclusive of Worksh op and per diem payments) NG-BORNO MCRP-57816-CS- CQS / Consultancy for Educat Strengthening Peace Buildin ional Campaigns, Mobilizatio Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Open - National 225,180.00 Completed 2018-09-03 2019-02-12 2018-09-24 2018-11-07 2019-02-12 2018-12-07 2019-02-12 2019-01-11 2018-10-16 2019-07-10 2018-12-24 n and Sensitization on Mine A cation Selection on ctions & Unexploded Ordinan ces in 27 Local Government Areas of Borno State NG-BORNO MCRP-73783-CS- CQS / Consultancy for Mediat Strengthening Peace Buildin ion and Alternate Dispute Re Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Open - National 139,085.49 Completed 2018-11-05 2019-02-12 2018-11-26 2019-01-09 2019-02-12 2019-02-08 2018-10-16 2019-03-15 2018-10-17 2019-09-11 2018-12-03 solution Capacity Building for cation Selection on peace groups in 27 Local Gov enrment Areas of Borno Stat e BOMCRP/CQS/CS/008/019 / Capacity building of LG Offic Strengthening Peace Buildin Consultant Qualifi ers for Strategic Communicat IDA / 59880 g, Stability and Social Cohesi Post Open - National 37,457.33 Completed 2019-04-09 2019-03-19 2019-04-23 2019-05-03 2019-03-26 2019-05-10 2019-04-15 2019-05-24 2019-04-18 2019-06-07 2019-06-07 cation Selection ions (Legislative Advocacy, M on edia relations, Stakeholder M anagement etc) BOMCRP/CQS/CS/007/019 / Strengthening Peace Buildin Capacity building of LG Offic Consultant Qualifi Under Implement IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 2019-04-09 2019-02-22 2019-04-23 2019-05-07 2019-05-14 2019-05-28 2019-06-11 ers for budget planning, exec cation Selection ation on ution, monitoring and reporti ng BOMCRP/CQS/CS/009/019 / Capacity building for 10 Loca Strengthening Peace Buildin Consultant Qualifi l Government Emergency Ma IDA / 59880 g, Stability and Social Cohesi Post Open - National 86,180.00 Completed 2019-04-09 2018-09-20 2019-04-23 2019-05-07 2018-10-11 2019-05-14 2018-10-14 2019-05-22 2018-10-17 2019-06-05 2019-01-03 cation Selection nagement Res ponders in Dis on placed and Transitional Local Government Officials BOMCRP/CQS/CS/010/019 / Sensitization, training on ide Strengthening Peace Buildin ntification, Documentation, T Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Open - National 81,257.63 Completed 2019-04-09 2019-08-08 2019-04-23 2019-11-21 2019-05-07 2019-10-14 2019-05-14 2019-09-05 2019-05-28 2019-11-07 2019-06-11 2019-12-09 racing, Reunification, Follow cation Selection on up and coaching for case ma nagement of UASC (Unaccom panied and Separated Childr en) BOMCRP/CQS/CS/033/019 / I dentification and training of Village Levels Mechanics and Infrastructure Rehabilitation Local area Mechanics in 21 L Consultant Qualifi Pending Impleme IDA / 59880 and Service Delivery Restora Post Open - National 0.00 2019-10-10 2019-10-24 2019-11-14 2019-11-21 2019-12-05 2019-12-19 GAs on operation and mainte cation Selection ntation tion & Improvement nance of existing Hand pump and Solar powered Borehole f or effective utilization and m anagement NG-BORNO MCRP-73723-CS- CQS / Statewide sponsorship for Radio Programming for Pe Strengthening Peace Buildin Consultant Qualifi acebuilding Campaign/Conte IDA / 59880 g, Stability and Social Cohesi Post Open - National 97,154.27 Completed 2019-03-18 2019-05-09 2019-04-01 2019-04-22 2019-04-03 2019-04-29 2019-04-22 2019-05-13 2019-04-25 2019-11-09 2020-04-08 cation Selection nt on deradicalization, grieva on nce redress and cultural/relig ious tolerance in 27 Local Go vernment Areas of Borno Sta te BOMCRP/CQS/CS/020/019 / T Infrastructure Rehabilitation Consultant Qualifi Under Implement eacher Training and Recertifi IDA / 59880 and Service Delivery Restora Post Open - National 0.00 2019-09-02 2019-10-02 2019-09-16 2019-10-07 2019-10-14 2019-10-28 2019-11-27 cation Selection ation cation tion & Improvement NG-BORNO MCRP-120946-C Infrastructure Rehabilitation S-CQS / Engagement of Cons Consultant Qualifi IDA / 59880 and Service Delivery Restora Post Open - National 261,765.85 Completed 2019-09-02 2019-05-13 2019-09-09 2019-10-16 2019-09-18 2019-05-20 2019-09-19 2019-06-04 2019-09-21 2019-06-05 2019-10-21 2019-08-27 ultant to Design and Supervis cation Selection tion & Improvement e for Borno PCU 66km Maidu guri-Bama Road NG-BORNO MCRP-120952-C S-CQS / Engagement of Safe Infrastructure Rehabilitation Consultant Qualifi Pending Impleme guard Consultant to produce IDA / 59880 and Service Delivery Restora Post Open - National 0.00 2019-09-02 2019-09-09 2019-09-18 2019-09-19 2019-09-21 2019-10-21 cation Selection ntation ESIA for Borno PCU Gongulon tion & Improvement g-Zabarmari-Dusuman-Gala mari-feeder Road NG-BORNO MCRP-120951-C S-CQS / Engagement of Cons Infrastructure Rehabilitation Consultant Qualifi ultant to Design and Supervis IDA / 59880 and Service Delivery Restora Post Open - National 41,510.55 Completed 2019-09-02 2019-05-01 2019-09-09 2019-10-15 2019-09-18 2019-05-14 2019-09-19 2019-06-03 2019-09-21 2019-06-10 2019-10-21 2019-07-08 cation Selection e for Borno PCU Gongulong-Z tion & Improvement abarmari-Duduman-Galamari -feeder Road Page 8 NG-BORNO MCRP-120950-C S-CQS / Engagement of Safe Infrastructure Rehabilitation Consultant Qualifi guard Consultant to produce IDA / 59880 and Service Delivery Restora Post Open - National 109,131.56 Completed 2019-09-02 2019-08-08 2019-09-09 2019-11-21 2019-09-18 2019-09-26 2019-09-19 2019-10-16 2019-09-21 2019-10-21 2019-10-21 2020-06-08 cation Selection ESIAand RAP for Borno PCU 6 tion & Improvement 6km Maiduguri-Bama Road BORNO/MCRP/CS/CQS/59/20 / Training on Value addition f Strengthening Peace Buildin Consultant Qualifi Pending Impleme or Women drying fish, peppe IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 2020-05-04 2020-05-14 2020-05-16 2020-05-21 2020-08-19 cation Selection ntation r, tomato, okro and other pro on ducts using solar tent dryer BORNO/MCRP/CS/CQS/50 / T Strengthening Peace Buildin raining of Community Health Consultant Qualifi Pending Impleme IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 2020-04-20 2020-05-04 2020-05-06 2020-05-11 2020-06-10 Workers (CHeWs, VHWs, Mid cation Selection ntation on wives) of Targeted Health Fa cilities BORN/MCRP/CS/CQS/54/20 / Strengthening Peace Buildin Consultant Qualifi Pending Impleme Silage, Pellet and Concentrat IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 2020-04-27 2020-05-07 2020-05-09 2020-05-14 2020-08-12 cation Selection ntation e Feed Making Technology on BORNO/MCRP/CS/CQS/55/20 Strengthening Peace Buildin Consultant Qualifi Pending Impleme / Pasture Production and hay IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 2020-04-27 2020-05-07 2020-05-09 2020-05-14 2020-08-12 cation Selection ntation making technology on BORNO/MCRP/CS/CQS/56/20 Strengthening Peace Buildin Consultant Qualifi Pending Impleme / Artificial Insemination Tech IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 2020-04-29 2020-05-09 2020-05-11 2020-05-16 2020-08-14 cation Selection ntation nicians Technology on BORNO/MCRP/CS/CQS/57/20 / Training of extension agent Strengthening Peace Buildin s on Climate Smart Agricultur Consultant Qualifi Pending Impleme IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 2020-04-22 2020-05-02 2020-05-04 2020-05-09 2020-08-07 e (CAS) concept to sustainabl cation Selection ntation on y increase productivity, enha nce resilience and reduce/re move green house gas emiss ion BORNO/MCRP/CS/CQS/54/20 Strengthening Peace Buildin Consultant Qualifi Pending Impleme / Regenerative Agriculture an IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 2020-04-24 2020-05-08 2020-05-10 2020-05-15 2020-08-13 cation Selection ntation d Composting Technology on BORNO/MCRP/CS/CQS/60/20 / Provision of Specialized psy Strengthening Peace Buildin Consultant Qualifi Pending Impleme co-social support responding IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 2020-05-04 2020-05-14 2020-05-16 2020-05-21 2020-08-19 cation Selection ntation to needs (group support, recr on eational, customary and soci alizing activities referrals) BORNO/MCRP/CS/CQS/51/20 Strengthening Peace Buildin / Sensitization for Health (Ou Consultant Qualifi Pending Impleme IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 2020-05-04 2020-05-18 2020-05-21 2020-05-27 2020-06-26 treach Programs) in 27 Local cation Selection ntation on Government Areas of Borno State BORNO/MCRP/CS/CQS/58/20 Strengthening Peace Buildin / Capacity Building of Smallh Consultant Qualifi Pending Impleme IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 2020-04-30 2020-05-10 2020-05-12 2020-05-17 2020-08-15 older farmers on Fertilizer an cation Selection ntation on d Pesticides technologies BORNO/MCRP/CS/CQS/52/20 Strengthening Peace Buildin Consultant Qualifi Pending Impleme / Rainwater Harvesting for Dr IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 2020-04-20 2020-04-22 2020-05-02 2020-05-06 2020-08-04 cation Selection ntation y Season Irrigation Farming on BOMCRP-AF/CS/CQS/001 / D evelopment, Intergration & I Strengthening Peace Buildin Consultant Qualifi Pending Impleme nstallation of Computerised IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 2021-12-29 2022-01-12 2022-01-26 2022-01-30 2022-04-30 cation Selection ntation Hospital Management Syste on ms for Major Hospitals in Bor no State BOMCRP-AF/CS/CQS/005 / C Strengthening Peace Buildin Consultant Qualifi Pending Impleme onsultancy for the Coordinati IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 2022-03-23 2022-03-28 2022-04-11 2022-04-15 2022-10-12 cation Selection ntation on of Peace Groups activities on and reporting BOMCRP-AF/CS/CQS/004 / Pr Strengthening Peace Buildin Consultant Qualifi Pending Impleme IDA / 59880 Post Limited 0.00 2022-02-01 2022-02-06 2022-02-20 2022-03-27 2022-09-23 ovision of Psyco social Suppo g, Stability and Social Cohesi cation Selection ntation rt on BOMCRP-AF/CS/CQS/016 / Es Strengthening Peace Buildin Consultant Qualifi Pending Impleme tablishment of cooperative b IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 2022-01-31 2022-02-14 2022-02-28 2022-03-04 2022-05-03 cation Selection ntation ased pasture development c on enter BOMCRP-AF/CS/CQS/017 / D evelopment of weather infor mation that is easily accessib Strengthening Peace Buildin le to farmers in local languag Consultant Qualifi Pending Impleme IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 2022-04-18 2022-05-02 2022-05-05 2022-05-09 2022-11-05 es including leaflets, brochur cation Selection ntation on es,short message system, se nsitization on weather and cli mate change through cinema vans, seminars and worksho ps. BOMCRP-AF/CS/CQS/020/21 Technical Assistance and Pro Consultant Qualifi Pending Impleme / FUNCTIONAL REVIEW OF PC IDA / 59880 Post Limited 0.00 2022-07-22 2022-08-05 2022-08-07 2022-08-11 2023-02-07 ject Management Support cation Selection ntation U CAPACITY AND SYSTEMS BOMCRP-AF/CS/CQS/030 / E Strengthening Peace Buildin NGAGEMENT OF CONSULTIN Consultant Qualifi Pending Impleme IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 2022-08-01 2022-08-15 2022-08-17 2022-08-21 2022-10-20 G FIRM FOR THE RECRUITME cation Selection ntation on NT OF HUMAN RESOURCE FO R HEALTH INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-BORNO MCRP-58865-CS- INDV / Consultancy for Regist Strengthening Peace Buildin ration, Mapping and Profiling Individual Consult Pending Impleme IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 2018-11-05 2018-11-05 2018-11-05 2018-11-05 2018-11-05 of all local government struct ant Selection ntation on ures and existing capacities State Wide in 27 Local Gover nment Areas of Borno State BOMCRP-CS-CDS-02-20 / SU Infrastructure Rehabilitation PERVISION OF REHABILITATI IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 257,593.78 Signed 2021-05-03 2021-08-10 2021-05-08 2021-09-02 2021-05-17 2021-09-24 2023-11-03 ON OF 66KM MAIDUGURI-BA tion & Improvement MA ROAD Page 9