Procurement 1. Procurement for the Project will be carried out in accordance with the World Bank’s "Guidelines: Procurement of Goods, Works and Non-consulting Services Under IBRD Loans and IDA Credits and Grants" dated January 2011 and revised as of July, 2014 (Procurement Guidelines); and "Guidelines: Selection and Employment of Consultants Under IBRD Loans and IDA Credits and Grants by World Bank Borrowers" dated January 2011 and revised as of July 2014 (Consultant Guidelines) and the provisions stipulated in the Legal Agreement (LA) and POM. The World Bank Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by IBRD Loans and IDA Credit and Grants dated October 15, 2006 and revised on January 2011, would also apply. Thresholds for Procurement Methods 2. Goods: Goods and equipment estimated to cost US$1,000,000 or more would be procured through International Competitive Bidding (ICB). Goods estimated to cost less than US$1,000,000 and more than US$100,000 would be procured through National Competitive Bidding (NCB). Readily available off-the-shelf goods estimated to cost equal to or less than US$100,000 each would be procured through Shopping (SH) on the basis of at least three written quotations obtained from qualified suppliers. Direct Contracting (DC) may be used in accordance with the requirements outlined in para. 3.7 of the Procurement Guidelines. 3. Works: Works estimated to cost equal to US$5,000,000 or more would be procured through ICB. Works estimated to cost less than US$5,000,000 and equal to or more than US$200,000 would be procured through NCB. Contracts estimated to cost less than US$200,000 each would be procured through Shopping (SH) procedures on the basis of at least three written quotations obtained from qualified contractors. Direct Contracting (DC) for works may be used in accordance with the requirements outlined in para. 3.7 of the Procurement Guidelines. 4. Consultant Services: Consultancy services to be provided by consulting firms estimated to cost more than US$300,000 would be procured through Quality and Cost Based Selection (QCBS) method. Consultancy services to be provided by consulting firms estimated to cost equal to or less than US$300,000 may be procured through Consultants’ Qualifications Selection (CQS) method. Other methods such as Fixed Budget Selection (FBS), Quality Based Selection (QBS), and Least Cost Selection (LCS) shall be made available through the Legal Agreement irrespective of the amount. Individual Consultants (IC) will be selected in accordance with Section V of the Consultant Guidelines. Single Source Selection (SSS) method for firms and individuals will also be specified in the Legal Agreement. For assignments estimated to cost equal to or less than US$300,000, the shortlist may comprise only of national firms according to the paragraph 2.7 of the Consultant Guidelines. However, if foreign firms express interest, they shall be considered. 5. NCB of the Borrower may be used for procurement of goods, works and non-consulting services for the project, provided that the following provisions are complied with: (a) Entities in which the Republic of Armenia owns a majority shareholding shall not be invited to participate in tenders for the government unless they are and can be shown to be legally and financially autonomous and operate under commercial law. (b) Post-qualification criteria shall only pertain to past contract performance, financial, managerial, and technical capabilities of bidders. (c) Joint venture partners shall be jointly and severally liable for their obligations. (d) Estimated contract prices shall not be advertised. (e) Except for late bids, no bids shall be rejected at the bid opening. The opening procedures shall comply with conditions of paragraph 2.45 of the Procurement Guidelines. (f) No bids shall be rejected solely because they exceed the estimated price. Bids can be cancelled and new bids invited, only if the conditions of paragraphs 2.61–2.64 of the Procurement Guidelines are met. (g) All bid evaluation criteria shall be quantifiable in monetary terms or expressed as pass/fail criteria. (h) Without limitation to paragraph 3 of Appendix 1 to the Procurement Guidelines, advance Bank approval is required for any modifications in the contract scope/conditions during implementation. Prior Review Thresholds Type of Procurement Prior Review Threshold Goods $1,000,000 Works First ICB regardless of value and contracts equal to or above $10,000,000 and first NCB IT System & Non-Consulting $1,000,000 Services Direct Contracting* $60,000 Consulting Services (Firm) First QCBS regardless of value and contracts equal to or above $500,000 and first CQS Consulting Services $200,000 (Individual) Single Source Selection** $5,000 *Must comply with the requirements of para. 3.7 of the Procurement Guidelines. ** Must comply with the requirements of paras. 3.8-3.11 of the Consultant Guidelines. 6. All TORs are subject to the Bank’s prior review irrespective of the prior or post review status of the consulting assignment in the procurement plan. Post Review Ratio 7. Contracts not subject to Bank’s prior review will be post reviewed by Bank’s supervision missions. Procurement Plan 8. All contracts to be financed under the project, the various procurement or consultant selection methods, the estimated costs, prior review requirements, and time frame have been agreed between the Borrower and the Bank and presented in the Procurement Plan (see below). The Procurement Plan will be updated as required to reflect the actual Project implementation needs and improvements in institutional capacity. The Procurement Plan its updates or modifications, shall be subject to the Bank’s prior review and no objection before implementation. The final version of the Procurement Plan will be disclosed (without cost estimates) and posted in the Bank’s external website in accordance with paragraph 1.18 of Procurement Guidelines and paragraph 1.25 of the Consultants Guidelines, ATDF’s database, and www.procurement.am. 32. Works contracts to be procured under the project include rehabilitation of heritage hubs, construction of tourism facilities and improvement of access roads and parking areas. There is no prequalification anticipated under the project and works are to be procured using NCB procedure. 33. Consultants to be selected under the project include services for preliminary assessment of buildings to undergo rehabilitation, preparation of detailed designs for the rehabilitation of heritage hubs and author’s supervision, technical supervision of works, destination management, marketing and promotion, audit services, monitoring and evaluation, training and site management plan. UNESCO will be contracted under Single Source Selection for advisory services for cultural heritage. 34. Goods to be procured under the project include vehicles, furniture, and equipment for the rehabilitated sites and tourism facilities. 35. A General Procurement Notice (GPN) will be published in UNDB on-line and in its printed version after negotiations. Specific Procurement Notices (SPN) for all ICB packages and consulting contracts each with cost estimate above US$300,000 will also be published in the UNDB. In addition, the SPNs for civil works contracts will be provided to the Union of Builders of Armenia. Filing and Record Keeping 36. ATDF will keep complete files of all procurement packages under the project to facilitate post review and Project audit. 37. The procurement related risks are summarized in Table 3.1 below. 38. Procurement Plan Table 3.1: Summary Risk Assessment Rating of Rating of Description of Risk Mitigation Measures Residual Risk Risk Current procurement Substantial ATDF will hire additional qualified Moderate staff is not able to cope procurement staff or procurement with the increased consultant. workload under LEIDP. High turnover of High ATDF will hire additional qualified Substantial procurement staff due to procurement staff or procurement low salary. consultant. Newly procurement staff Substantial ATDF’s procurement staff should Moderate may not have sufficient continuously improve their knowledge and knowledge of Bank’s procurement experience in Bank procedures by attending procurement. training/workshops offered by the World Bank, familiarizing themselves with the Procurement and Consultant Guidelines and on- the-job training. Given the multi- Substantial (a) Educate stakeholders about Moderate stakeholder environment, the POM through ATDF’s possibility of unnecessary Institutional Support intervention and Department. (b) Ensure pressures resulting in transparent decision making implementation delays based on evaluation criteria disclosed in bidding documents and proposal documents. Inadequate capacity in Substantial (a) DFA will apply additional Moderate the DFA to prepare TORs efforts to improve the and technical technical parts of procurement specifications and documents and quality of implement Bank-financed TORs for consulting services. Project. (b) Project to finance consulting services to build capacity in the DFA. PROCUREMENT Armenia : Local Economy and Infrastructure Development Project PLAN General Information Country: Armenia 2017-03-23 Bank’s Approval Date of the Original Procurement Plan: 2022-06-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150327 GPN Date: Project Name: Local Economy and Infrastructure Development Project Loan / Credit No: TF / A1063, IBRD / 85720 Armenian Territorial Development Fund Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned TUR-01-1 / Rehabilitation of Heritage Hub and Tourism Ci Single Stage - One E 2019-05-0 IBRD / 85720 Post Request for Bids Open - National 1,200,000.00 0.00 Canceled 2017-10-11 2017-10-16 2017-11-03 2017-11-13 2017-12-01 2017-12-13 2017-12-29 2018-01-10 road leading to Garni Stone S rcuit Development nvelope 5 ymphony TUR-01-01-1 / Rehabilitation Heritage Hub and Tourism Ci Single Stage - One E 1,496,995.5 2019-09-3 of road leading to Garni Ston IBRD / 85720 Post Request for Bids Open - National 1,427,000.00 Completed 2018-02-22 2018-03-05 2018-02-27 2018-03-19 2018-03-27 2018-04-16 2018-04-26 2018-05-07 2018-06-07 2018-06-19 rcuit Development nvelope 9 0 e Symphony TUR-06 / Rehabilitation of Ro Heritage Hub and Tourism Ci Single Stage - One E 1,901,802.7 2019-04-2 IBRD / 85720 Post Request for Bids Open - National 2,029,309.00 Completed 2018-05-11 2018-05-20 2018-05-16 2018-05-24 2018-06-13 2018-06-21 2018-07-13 2018-07-11 2018-08-24 2018-07-27 ad Segment Leading to Tatev rcuit Development nvelope 6 1 Monastery TUR-07 / Streets Rehabilitati on of Kumayri Historical Cent Heritage Hub and Tourism Ci Single Stage - One E 2,108,291.7 2019-03-2 IBRD / 85720 Post Request for Bids Open - National 2,146,640.88 Completed 2018-07-16 2018-07-12 2018-07-19 2018-07-12 2018-08-16 2018-08-09 2018-09-15 2018-08-24 2018-10-27 2018-09-04 er in Gyumri rcuit Development nvelope 8 6 (consist of 2 Lots) TUR-08 / Reconstruction of t Heritage Hub and Tourism Ci Single Stage - One E 2019-07-1 IBRD / 85720 Post Request for Bids Open - National 495,000.00 412,795.18 Completed 2018-11-05 2018-11-05 2018-11-10 2018-11-08 2018-12-08 2018-12-06 2019-01-07 2018-12-12 2019-02-18 2018-12-27 he Road Leading to "Sochut" rcuit Development nvelope 8 Dendropark TUR-02-01 / Improvement of Heritage Hub and Tourism Ci Single Stage - One E 2020-05-0 IBRD / 85720 Post Request for Bids Open - National 224,000.00 193,024.76 Completed 2019-07-26 2019-07-25 2019-07-29 2019-08-02 2019-08-26 2019-08-23 2019-09-25 2019-09-06 2019-11-06 2019-09-20 Khor Virap Monastery Area rcuit Development nvelope 4 TUR-PPI-01 / Provision of Util ity Infrastructure for Areni Wi ne Hotel: Lot 1 Gas Supply System for Heritage Hub and Tourism Ci Single Stage - One E 1,154,118.7 2021-03-2 IBRD / 85720 Post Request for Bids Open - National 1,337,000.00 Completed 2019-12-10 2019-12-10 2019-12-15 2019-12-11 2020-01-19 2020-01-14 2020-02-18 2020-02-14 2020-03-31 2020-04-06 Areni Wine Hotel; rcuit Development nvelope 0 6 Lot 2 Water supply and sewa ge system of Areni Wine Hot el ; Lot 3 Electricity and interne t Supply System for Areni Wi TUR-03 ne / Goris Hub Regener Hotel. ation Lot 1: Restoration of the right bank of Vararakn River, Heritage Hub and Tourism Ci Single Stage - One E 1,851,790.8 2021-07-2 Lot 2: Restoration of the hist IBRD / 85720 Post Request for Bids Open - National 4,714,000.00 Completed 2019-12-15 2019-12-17 2019-12-20 2019-12-17 2020-01-24 2020-01-21 2020-02-23 2020-02-14 2020-04-05 2020-04-07 rcuit Development nvelope 9 9 orical-cultural environment o f the central part of Goris tow n, Lot 3: Renovation of historica l residential houses in the ce ntral part of Goris TUR-04-1 / Partial restoratio Heritage Hub and Tourism Ci Single Stage - One E 2020-11-2 n and reinforcement of monu IBRD / 85720 Post Request for Bids Open - National 309,000.00 0.00 Canceled 2020-02-12 2020-02-12 2020-02-17 2020-02-15 2020-03-16 2020-03-13 2020-04-15 2020-05-27 rcuit Development nvelope 3 ments in the historical capita l of Armenia Dvin TUR-03-2 / Restoration of th Heritage Hub and Tourism Ci Single Stage - One E 2021-09-2 e historical-cultural environm IBRD / 85720 Post Request for Bids Open - National 2,390,000.00 0.00 Canceled 2020-02-21 2020-02-25 2020-02-26 2020-02-27 2020-03-25 2020-03-25 2020-04-24 2020-05-12 2020-06-05 rcuit Development nvelope 8 ent of the central part of Gori s town TUR-04-1-2 / Partial restorati on and reinforcement of mon Heritage Hub and Tourism Ci Single Stage - One E 2021-01-0 IBRD / 85720 Post Request for Bids Open - National 309,000.00 0.00 Canceled 2020-03-30 2020-03-30 2020-04-04 2020-05-02 2020-04-27 2020-06-01 2020-04-27 2020-07-13 uments in the historical capit rcuit Development nvelope 9 al of Armenia Dvin TUR-04-1-3 / Partial restorati on and reinforcement of mon Heritage Hub and Tourism Ci Single Stage - One E 2021-03-0 IBRD / 85720 Post Request for Bids Open - National 305,000.00 0.00 Canceled 2020-05-22 2020-05-21 2020-05-27 2020-06-24 2020-06-18 2020-07-24 2020-06-22 2020-09-04 uments in the historical capit rcuit Development nvelope 3 al of Armenia Dvin TUR-04-1-4 / Partial restorati on and reinforcement of mon Heritage Hub and Tourism Ci Single Stage - One E 2021-05-2 IBRD / 85720 Post Request for Bids Open - National 305,000.00 246,929.67 Signed 2020-07-10 2020-07-21 2020-07-15 2020-07-22 2020-08-12 2020-08-19 2020-09-11 2020-09-07 2020-10-23 2020-11-25 uments in the historical capit rcuit Development nvelope 1 al of Armenia Dvin ТUR-12 / Reconstruction of Y Heritage Hub and Tourism Ci Single Stage - One E 3,962,375.4 2022-04-1 IBRD / 85720 Post Request for Bids Open - National 5,108,000.00 Signed 2020-07-06 2020-07-06 2020-07-08 2020-07-09 2020-08-12 2020-08-10 2020-09-10 2020-08-21 2020-10-22 2020-11-06 erevan-Lanjazat-Garni road rcuit Development nvelope 5 5 ТUR-01-2 / Reconstruction of Heritage Hub and Tourism Ci Single Stage - One E 2021-11-2 IBRD / 85720 Post Request for Bids Open - National 450,000.00 438,562.85 Signed 2020-12-21 2021-03-26 2020-12-26 2021-03-26 2021-01-23 2021-04-23 2021-02-22 2021-05-05 2021-03-27 2021-06-18 the road to Khosrov Forest rcuit Development nvelope 2 TUR-11.6 / Improvement of Heritage Hub and Tourism Ci Single Stage - One E 2022-01-2 IBRD / 85720 Post Request for Bids Open - National 122,000.00 0.00 Canceled 2021-04-16 2021-04-09 2021-04-21 2021-04-09 2021-05-19 2021-05-07 2021-06-18 2021-05-17 2021-07-30 Gndevank Hiking Trail rcuit Development nvelope 6 TUR-11.2 / Rehabilitation, Re storation of Shahumyan, V. V Heritage Hub and Tourism Ci Single Stage - One E 2022-09-2 ardanyan, Myasnikyan, Melik IBRD / 85720 Post Request for Bids Open - National 1,612,000.00 0.00 Canceled 2021-04-15 2021-04-09 2021-04-20 2021-04-09 2021-05-18 2021-05-10 2021-06-17 2021-07-29 rcuit Development nvelope 2 Adamyan and Charents Stree ts and Construction of the All ey Leading to “Qarayts” Request for Bids - TUR-11.2.3.6 / TUR 11.2.3.6 Heritage Hub and Tourism Ci Single Stage - One E Small Works SPD 3,021,754.4 2022-11-2 Reconstruction of the Roads IBRD / 85720 Post Request for Bids Open - National 3,072,000.00 Signed 2021-05-31 2021-05-25 2021-06-05 2021-05-25 2021-07-17 2021-07-06 2021-08-16 2021-07-21 2021-09-27 2021-08-11 rcuit Development nvelope (1 envelope proce 9 1 and Tourism Infrastructure of ss) Jermuk Request for Bids - ТUR-10.1 / Improvement of t Heritage Hub and Tourism Ci Single Stage - One E Small Works SPD 1,119,224.9 2023-02-0 IBRD / 85720 Post Request for Bids Open - National 1,106,000.00 Signed 2021-07-01 2021-06-24 2021-07-06 2021-06-24 2021-08-03 2021-07-22 2021-09-02 2021-08-05 2021-10-14 2021-08-17 he nearest area of the Garni rcuit Development nvelope (1 envelope proce 3 6 temple ss) Request for Bids - TUR-03.2-3 / Restoration of t Heritage Hub and Tourism Ci Single Stage - One E Small Works SPD 2,884,340.8 2023-02-2 he Historical-Cultural Environ IBRD / 85720 Post Request for Bids Open - National 2,796,000.00 Signed 2021-07-22 2021-07-09 2021-07-27 2021-07-23 2021-08-24 2021-08-06 2021-09-23 2021-09-10 2021-11-04 2021-09-15 rcuit Development nvelope (1 envelope proce 2 7 ment of the Central part of G ss) oris Town Request for Bids - TUR-05 / Improvement of th Heritage Hub and Tourism Ci Single Stage - One E Small Works SPD 2022-04-0 e Area Near the “Zorats Qare IBRD / 85720 Post Request for Bids Open - National 278,000.00 279,178.91 Signed 2021-07-22 2021-06-29 2021-07-27 2021-06-29 2021-08-24 2021-07-27 2021-09-23 2021-08-23 2021-11-04 2021-09-14 rcuit Development nvelope (1 envelope proce 3 r” Historical and Cultural Res ss) erve Page 1 Request for Bids - TUR-13.2 / Preparatory Work Heritage Hub and Tourism Ci Single Stage - One E Small Works SPD 1,801,475.1 2022-09-2 for the Reconstruction of the IBRD / 85720 Post Request for Bids Open - National 1,600,000.00 Signed 2021-07-22 2021-07-19 2021-07-27 2021-07-19 2021-08-24 2021-08-16 2021-09-23 2021-09-03 2021-11-04 2021-10-07 rcuit Development nvelope (1 envelope proce 6 0 "Barekamutyun" Town Park i ss) n Gyumri TUR-11.6-2 / Improvement o Heritage Hub and Tourism Ci Single Stage - One E Other (with field f 2022-06-0 IBRD / 85720 Post Request for Bids Open - National 130,000.00 0.00 Canceled 2021-08-27 2021-08-02 2021-09-01 2021-08-02 2021-09-29 2021-08-30 2021-10-29 2021-12-03 f Gndevank Hiking Trail rcuit Development nvelope or explanation) 1 TUR-09 / Rehabilitation of th Heritage Hub and Tourism Ci Single Stage - One E 2022-02-1 IBRD / 85720 Post Request for Bids Open - National 1,056,000.00 0.00 Canceled 2020-11-04 2020-11-03 2020-11-09 2020-11-03 2020-12-07 2020-12-01 2021-01-06 2020-12-21 2021-02-17 e road leading to old Khndzor rcuit Development nvelope 2 esk TUR-11.6-3 / Improvement o Heritage Hub and Tourism Ci Request for Quota Single Stage - One E Other (with field f 2022-05-0 IBRD / 85720 Post Open - National 130,000.00 0.00 Canceled 2021-09-28 2021-11-02 f Gndevank hiking trail rcuit Development tions nvelope or explanation) 1 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PLEID C- 2.2 / Rehabilitation of Goris Central Parks ; redev elopment of the Right Bank o f Goris River; restoration of H Heritage Hub and Tourism Ci Consultant Qualifi Open - Internationa TF / A1063 Prior 0.00 142,629.48 Signed 2016-10-21 2016-10-14 istorical and Architectural En rcuit Development cation Selection l vironment of the Central Part of Goris and development a Management Model for upgra ded infrastructures LPD-01 / Development of Pro ject Design and Author's Sup Heritage Hub and Tourism Ci Consultant Qualifi ervision for the Rehabilitation IBRD / 85720 Post Open - National 50,000.00 44,049.21 Completed 2017-11-22 2017-12-06 2017-12-06 2017-12-08 2018-01-10 2017-12-28 2018-01-17 2018-01-13 2018-02-07 2018-01-12 2019-06-22 2019-08-04 rcuit Development cation Selection of Road Segment Leading to Tatev Monastery Sub-project LV-01 / Detailed Measureme Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 800.00 686.43 Completed 2018-01-09 2018-01-09 2018-01-19 2018-01-17 2018-02-16 2018-02-16 2018-02-23 2018-02-20 2018-03-16 2018-02-23 2018-05-15 2018-04-06 nt, Assets Inventory and Valu rcuit Development cation Selection ation LTS-01 / Technical supervisi on of construction for Rehabil Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 18,560.00 26,806.60 Completed 2018-04-13 2018-04-09 2018-04-27 2018-04-09 2018-05-25 2018-05-04 2018-06-15 2018-05-18 2018-07-06 2018-05-18 2019-10-29 2021-05-21 itation of road leading to Gar rcuit Development cation Selection ni Stone Symphony LTS-02 / Technical supervisi on of construction for Rehabil Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 24,360.00 24,136.16 Completed 2018-05-17 2018-05-23 2018-05-24 2018-05-30 2018-06-21 2018-06-19 2018-07-12 2018-07-06 2018-08-02 2018-07-06 2019-03-30 2019-08-04 itation of Road Segment Lea rcuit Development cation Selection ding to Tatev Monaster LTS-03 / Technical Supervisi on of construction for "Stree Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 23,700.00 33,893.03 Signed 2018-08-02 2018-07-27 2018-08-16 2018-07-27 2018-09-13 2018-08-27 2018-10-04 2018-08-31 2018-10-25 2018-09-03 2019-03-24 ts Rehabilitation of Kumayri rcuit Development cation Selection Historical Center in Gyumri LTS-04 / Technical Supervisi Heritage Hub and Tourism Ci Consultant Qualifi on for "Reconstruction of the IBRD / 85720 Post Open - National 7,800.00 7,745.90 Completed 2018-11-21 2018-11-29 2018-11-28 2018-12-20 2018-12-24 2019-01-25 2019-01-14 2019-02-04 2019-02-04 2019-02-07 2019-07-04 2019-09-16 rcuit Development cation Selection Road Leading to "Sochut" De ndropark" AUD-18 / AUDIT OF THE LOC AL ECONOMY AND INFRASTR Heritage Hub and Tourism Ci Consultant Qualifi UCTURE DEVELOPMENT PROJ IBRD / 85720 Post Open - National 6,443.00 24,124.85 Completed 2018-12-04 2018-11-30 2018-12-11 2019-01-06 2018-12-24 2019-01-27 2018-12-28 2019-02-17 2018-12-28 2019-08-16 2019-06-27 rcuit Development cation Selection ECT (LEID) FOR THE PERIOD FROM DECEMBER 29, 2016 TO DECEMBER 31, 2018 LPD-06 / Design and Author' s Supervision for the Utility In Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 28,070.00 0.00 Completed 2019-03-27 2019-03-21 2019-04-10 2019-04-04 2019-05-15 2019-04-29 2019-05-22 2019-05-14 2019-06-12 2019-05-14 2019-07-12 2019-12-03 frastructure of "Areni Wine h rcuit Development cation Selection otel" in Areni community LGS-01 / The geological and geophysical surveys of the ro Heritage Hub and Tourism Ci Consultant Qualifi ad section bypassing the la IBRD / 85720 Post Open - National 20,760.00 22,832.32 Completed 2019-05-14 2019-05-08 2019-05-21 2019-06-14 2019-06-27 2019-07-25 2019-07-27 2019-08-14 2019-08-17 2019-08-14 2019-09-26 2020-02-24 rcuit Development cation Selection ndslide of road leading to T atev monastery sub-project LTS-05 / Technical Supervisi Heritage Hub and Tourism Ci Consultant Qualifi on of construction for "Khor V IBRD / 85720 Post Open - National 3,680.00 3,677.73 Signed 2019-08-26 2019-08-16 2019-09-02 2019-08-26 2019-09-28 2019-09-18 2019-10-19 2019-09-27 2019-11-09 2019-09-30 2020-05-07 rcuit Development cation Selection irap Monastery Area Landsca ping". LTS-06 / Technical Supervisi on of Construction for Provisi Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 16,000.00 15,801.97 Completed 2019-12-15 2019-12-16 2019-12-22 2019-12-23 2020-01-17 2020-03-23 2020-02-07 2020-04-10 2020-02-28 2020-04-13 2021-02-22 2021-01-29 on of Utility Infrastructure for rcuit Development cation Selection “Areni Wine Hotel” LTS-07 / Technical Supervisi Heritage Hub and Tourism Ci Consultant Qualifi on of Construction for Goris IBRD / 85720 Post Open - National 48,000.00 41,188.69 Signed 2019-12-15 2019-12-16 2019-12-22 2019-12-23 2020-01-17 2020-02-15 2020-02-07 2020-03-26 2020-02-28 2020-03-31 2021-06-22 rcuit Development cation Selection Hub Regeneration LPD-09 / Design for the “Im Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 35,500.00 31,187.16 Signed 2019-12-30 2019-12-30 2020-01-20 2020-01-30 2020-03-04 2020-03-23 2020-04-03 2020-04-10 2020-05-08 2020-04-16 2020-10-05 2020-11-18 provement of Garni Temple a rcuit Development cation Selection rea” LPD-08 / Design for the “Re Heritage Hub and Tourism Ci Consultant Qualifi habilitation of the road leadi IBRD / 85720 Post Open - National 38,000.00 229,192.15 Signed 2019-12-30 2020-01-30 2020-01-20 2020-02-26 2020-03-11 2020-04-06 2020-04-10 2020-04-20 2020-05-15 2020-04-21 2020-08-15 2020-07-22 rcuit Development cation Selection ng to Old Khndzoresk” Page 2 LCD-01 / Development of Co ncept Design for the Heritag Heritage Hub and Tourism Ci Quality Based Sel Open - Internationa IBRD / 85720 Post 114,815.00 178,779.00 Completed 2020-01-20 2020-01-09 2020-02-10 2020-01-23 2020-04-10 2020-04-06 2020-05-08 2020-06-19 2020-06-07 2020-07-28 2020-07-07 2020-07-28 2020-08-11 2020-12-21 2020-11-09 2021-09-27 e hub regeneration in Areni v rcuit Development ection l illage and adjacent villages LTS-08 / Technical supervisi on of the "Partial restoration Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 3,039.00 5,443.18 Signed 2020-02-13 2020-02-07 2020-02-27 2020-02-26 2020-04-02 2020-04-20 2020-04-23 2020-05-21 2020-05-14 2020-05-27 2020-11-10 and reinforcement of monum rcuit Development cation Selection ents in the historical capital o f Armenia Dvin". LS-02 / International Visitor Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 246,000.00 0.00 Canceled 2020-02-14 2020-02-27 2020-03-06 2020-02-27 2020-04-19 2020-05-19 2020-06-09 2021-11-01 Exit Survey on National Level rcuit Development cation Selection AUD-19 / "AUDIT OF THE AR MENIAN TERRITORIAL DEVEL OPMENT FUND and AUDIT OF Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 30,918.00 23,973.29 Completed 2020-03-13 2020-03-09 2020-03-20 2020-03-18 2020-04-29 2020-04-10 2020-05-20 2020-05-05 2020-06-10 2020-05-06 2020-09-18 2020-07-28 THE LOCAL ECONOMY AND I rcuit Development cation Selection NFRASTRUCTURE DEVELOPM ENT (LEID) PROJECT FOR THE YEAR ENDED DECEMBER 31, 2019". LPD-13 / Modification of the sub-project design and autho Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 46,280.00 45,768.21 Completed 2020-04-27 2020-04-23 2020-05-18 2020-04-27 2020-07-01 2020-05-21 2020-07-31 2020-05-27 2020-09-04 2020-05-27 2021-02-01 2020-06-22 r's supervision for the ”Reno rcuit Development cation Selection vation of Garni-Lanjazat road ”. LTS-09 / Technical supervisi Heritage Hub and Tourism Ci Consultant Qualifi on of the ”Reconstruction of IBRD / 85720 Post Open - National 50,780.00 49,189.36 Signed 2020-07-31 2020-08-05 2020-08-21 2020-08-13 2020-10-04 2020-09-24 2020-11-03 2020-10-09 2020-11-24 2020-10-12 2022-05-18 rcuit Development cation Selection Garni-Lanjazat road”. LPD-16 / Design and author' s supervision of Improvemen Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 5,300.00 5,048.87 Signed 2020-09-11 2020-10-14 2020-09-25 2020-10-15 2020-11-08 2020-11-13 2020-12-08 2020-12-16 2021-01-12 2020-12-18 2021-07-18 t of the green zone near Khor rcuit Development cation Selection Virap Monastery, installation of sales pavilions LM-01 / Consultancy Service for the LEID Project Performa Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 291,000.00 260,666.35 Signed 2021-01-18 2021-01-14 2021-02-01 2021-02-01 2021-03-01 2021-02-25 2021-03-15 2021-04-13 2021-04-01 2021-06-23 2023-04-01 nce Monitoring & Evaluation i rcuit Development cation Selection n the selected regions of Arm enia LTS-10 / Technical supervisi Heritage Hub and Tourism Ci Consultant Qualifi on of the “Rehabilitation of t IBRD / 85720 Post Open - National 12,500.00 0.00 Canceled 2020-11-30 2020-12-14 2020-12-21 2021-02-03 2021-03-05 2021-03-26 2022-03-26 rcuit Development cation Selection he road leading to old Khndz oresk” LTS-11 / Technical supervisi on of the construction works for sub-projects of Rehabilita tion of the road leading from Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 20,000.00 20,768.52 Signed 2021-02-02 2021-03-17 2021-02-16 2021-04-29 2021-03-16 2021-05-26 2021-03-30 2021-07-06 2021-04-06 2021-07-06 2021-12-02 "Symphony of Stones" natura rcuit Development cation Selection l monument to "Khosrov Fore st State Reserve" and “Impro vement of the adjacent territ ory of the Garni temple” LTS-12 / Technical supervisi on of construction works for s ub-project "Rehabilitation of t Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 16,300.00 16,855.61 Signed 2021-02-02 2021-03-25 2021-02-16 2021-04-30 2021-03-16 2021-06-01 2021-03-30 2021-07-06 2021-04-06 2021-07-06 2022-04-01 he road leading to old Khndz rcuit Development cation Selection oresk" & "Improvement of th e area near the Zorats Karer monument" AUD-20 / AUDIT OF THE LOC AL ECONOMY AND INFRASTR Consultant Qualifi UCTURE DEVELOPMENT PROJ IBRD / 85720 Institutional Development Post Open - National 42,000.00 28,456.65 Completed 2021-03-29 2021-03-24 2021-04-12 2021-04-23 2021-05-10 2021-04-30 2021-05-15 2021-05-14 2021-05-25 2021-05-14 2021-07-09 2021-07-29 cation Selection ECT (LEID) FOR THE YEAR EN DING DECEMBER 31, 2020 LPD-17 / Design and author' s supervision of Renovation, i mprovement and landscape gardening of the Drinking Gal Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 49,000.00 51,758.75 Signed 2021-04-09 2021-05-07 2021-04-23 2021-05-27 2021-05-21 2021-06-18 2021-05-26 2021-07-06 2021-06-05 2021-07-06 2022-06-05 lery alleys, construction of pa rcuit Development cation Selection vilions and Information Cente r and Construction of the acc ess road to the “Yeghnik” sta tue and to the observation d eck LPD-18 / Design and author' s supervision of the develop ment of design for the recons truction of the 320-meters of Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 10,200.00 11,003.32 Signed 2021-07-05 2021-06-07 2021-07-26 2021-09-23 2021-08-23 2021-10-04 2021-08-28 2021-11-10 2021-09-07 2021-11-10 2022-09-07 not restored landslide sectio rcuit Development cation Selection n of the 6-kilometer road lea ding from the "Devil's Bridge " natural monument to Tatev monastery complex LEX-01-2 / Investigation of t Heritage Hub and Tourism Ci Consultant Qualifi he technical state of the exis IBRD / 85720 Post Open - National 2,600.00 2,618.01 Signed 2021-08-09 2021-08-06 2021-08-23 2021-09-23 2021-09-20 2021-10-07 2021-09-25 2021-12-08 2021-10-05 2021-12-10 2021-11-14 rcuit Development cation Selection ting building of the Drinking Gallery LTS-13 / Technical supervisi on of construction works for Rehabilitation, Restoration of Shahumyan, V. Vardanyan, M Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 40,000.00 36,574.20 Signed 2021-08-11 2021-07-19 2021-08-25 2021-07-29 2021-09-22 2021-08-13 2021-10-06 2021-08-17 2021-10-13 2021-08-17 2022-12-07 yasnikyan, Melik Adamyan a rcuit Development cation Selection nd Charents Streets and Con struction of the Alley, Rehabil itation of Mashtots street, Im provement of Gndevank Hiki ng Trail LEX-01 / Investigation of the Heritage Hub and Tourism Ci Consultant Qualifi technical state of the existin IBRD / 85720 Post Open - National 1,700.00 0.00 Canceled 2021-04-09 2021-03-31 2021-04-23 2021-04-26 2021-05-21 2021-05-10 2021-05-26 2021-06-07 2021-06-05 2021-07-15 rcuit Development cation Selection g building of the Drinking Gal lery LPD-19 / Designing and auth Heritage Hub and Tourism Ci Consultant Qualifi or’s supervision of the works IBRD / 85720 Post Open - National 96,390.00 96,558.53 Signed 2021-08-04 2021-08-06 2021-08-25 2021-09-29 2021-09-22 2021-10-15 2021-09-27 2021-10-25 2021-10-07 2021-10-25 2022-12-01 rcuit Development cation Selection under Component 1 and Com ponent 4. LPD-21 / Designing and auth Heritage Hub and Tourism Ci Consultant Qualifi or’s supervision of the works IBRD / 85720 Post Open - National 114,105.00 14,965.06 Signed 2021-08-04 2021-08-06 2021-08-25 2021-09-10 2021-09-22 2021-10-15 2021-09-27 2021-10-21 2021-10-07 2021-10-22 2023-03-31 rcuit Development cation Selection under Component 5 LTS-14 / Technical supervisi on of Construction of "Prepar Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 18,735.00 18,770.43 Signed 2021-08-04 2021-08-13 2021-08-11 2021-09-03 2021-09-08 2021-10-05 2021-09-15 2021-10-07 2021-09-22 2021-10-07 2022-08-08 atory work for the reconstruc rcuit Development cation Selection tion of the "Barekamutyun" t own park in Gyumri". Page 3 LPD-20 / Designing and auth Heritage Hub and Tourism Ci Consultant Qualifi or’s supervision of the works IBRD / 85720 Post Open - National 68,345.00 67,559.78 Signed 2021-08-04 2021-08-06 2021-08-11 2021-09-03 2021-09-08 2021-09-27 2021-09-13 2021-10-18 2021-09-23 2021-10-18 2023-03-02 rcuit Development cation Selection under Component 3 LPD-23 / Designing and auth or’s supervision of the works under Component 2- «Improv ement of Dvin ancient site an Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 43,930.00 0.00 Canceled 2021-09-13 2021-10-08 2021-09-27 2021-10-26 2021-11-26 2021-12-15 2021-12-01 2021-12-11 2023-02-04 d the adjacent area and repl rcuit Development cation Selection enishment with tourist infrast ructure» of «The archeologic al site, historical town Dvin of Armenia» sub-project. LPD-24 / Designing and auth or’s supervision of the works under “Major Rehabilitation o Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 70,770.00 49,971.02 Signed 2021-09-14 2021-09-29 2021-09-21 2021-10-25 2021-11-20 2021-12-10 2021-11-25 2021-12-30 2021-12-05 2022-01-03 2023-01-29 f the Road to Marmashen Mo rcuit Development cation Selection nastic Complex and Improve ment of the Adjacent Area” s ub-project. DMO-01 / Preparation of Des tination Management Organi Quality And Cost- Open - Internationa Under Implement IBRD / 85720 Institutional Development Post 307,000.00 0.00 2021-11-01 2021-10-21 2021-11-29 2021-12-07 2022-01-24 2022-02-04 2022-02-21 2022-03-18 2022-03-21 2022-05-12 2022-04-11 2022-05-24 2022-05-16 2022-11-12 zation (DMO) Development M Based Selection l ation odel for the Republic of Arme nia LPD-26 / Designing and Auth or’s Supervision of the Rehab Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 57,160.00 61,848.38 Signed 2022-03-02 2022-04-07 2022-03-16 2022-05-18 2022-04-20 2022-05-20 2022-05-11 2022-06-15 2022-05-30 2022-06-15 2023-11-26 ilitation of Meghri Pokr Tagh ( rcuit Development cation Selection Small district) Tourism Infrast ructure LEX-02 / Expertise of Archite Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 35,130.00 38,333.09 Signed 2022-03-22 2022-03-25 2022-03-29 2022-04-11 2022-05-03 2022-04-28 2022-05-08 2022-05-12 2022-05-18 2022-05-12 2023-05-18 ctural Design (16 projects). rcuit Development cation Selection LPD-27 / Designing and Auth or’s Supervision of the “Parti al Major Rehabilitation of Das Heritage Hub and Tourism Ci Consultant Qualifi Under Implement IBRD / 85720 Post Open - National 62,130.00 0.00 2022-04-19 2022-05-12 2022-04-26 2022-06-03 2022-05-31 2022-06-21 2022-07-03 2022-12-30 htadem Fortress, Establishm rcuit Development cation Selection ation ent of a Museum and Improv ement of the Area Adjoining t o the Monument”. LPD-29 / Design and Author’ s Supervision of the construc tion works provided under Co Heritage Hub and Tourism Ci Consultant Qualifi Pending Impleme mponent 2 of the “Improvem IBRD / 85720 Post Open - National 98,900.00 0.00 2022-06-21 2022-07-05 2022-08-09 2022-08-30 2022-09-11 2023-09-06 rcuit Development cation Selection ntation ent of the Dvin Ancient Site a nd Adjacent Area and Additio n of Tourism Infrastructure” Subproject. LPD-28 / Design and Author’ s Supervision of the construc tion works provided under “R Heritage Hub and Tourism Ci Consultant Qualifi Pending Impleme IBRD / 85720 Post Open - National 28,800.00 0.00 2022-06-19 2022-07-03 2022-08-07 2022-08-28 2022-09-09 2023-02-06 econstruction and Strengthe rcuit Development cation Selection ntation ning of the Drinking Gallery o f Jermuk City of the RA” com ponent. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LPD-02 / Autors supervision f or Construction For Rehabilit Heritage Hub and Tourism Ci IBRD / 85720 Post Direct Selection Direct 7,140.00 7,141.45 Completed 2018-04-26 2018-04-23 2018-05-06 2018-04-23 2018-05-30 2018-05-10 2019-09-22 2020-04-30 ation Of Road Leading To Gar rcuit Development ni Stone Symphony LPD-03/1 / Author's Supervis ion of construction for "Stree Heritage Hub and Tourism Ci IBRD / 85720 Post Direct Selection Direct 7,300.00 7,242.39 Signed 2018-08-02 2018-08-02 2018-08-12 2018-08-02 2018-09-05 2018-09-03 2019-02-02 ts Rehabilitation of Kumayri rcuit Development Historical Center in Gyumri LPD-04 / Geological researc h and Design development f Heritage Hub and Tourism Ci or the Rehabilitation of landsl IBRD / 85720 Post Direct Selection Direct 15,456.00 15,489.35 Completed 2018-12-14 2018-12-10 2018-12-22 2018-12-20 2019-01-15 2018-12-26 2019-02-04 2019-04-10 rcuit Development ide segment of road leading to Tatev monastery sub-proje ct. LPD-05 / Author's Supervisio Heritage Hub and Tourism Ci n of "Reconstruction of the R IBRD / 85720 Post Direct Selection Direct 1,980.00 1,986.01 Completed 2019-02-05 2019-01-30 2019-02-15 2019-02-18 2019-03-11 2019-02-18 2019-08-08 2019-09-16 rcuit Development oad Leading to "Sochut" Den dropark". LPD-07 / Author’s Supervisio Heritage Hub and Tourism Ci n of Construction of "Khor Vi IBRD / 85720 Post Direct Selection Direct 1,345.00 1,319.48 Completed 2019-09-20 2019-09-16 2019-09-30 2019-09-23 2019-11-09 2019-10-16 2020-05-07 2021-03-16 rcuit Development rap Monastery Area Landsca ping " LS-01 / Monitoring and Supe rvision of Tourism Internation al Visitor Survey on National Heritage Hub and Tourism Ci Individual Consult IBRD / 85720 Post Limited 12,600.00 12,533.21 Signed 2019-11-08 2019-11-04 2019-11-15 2019-11-19 2019-12-06 2019-12-06 2020-01-10 2019-12-06 2021-04-04 Level. rcuit Development ant Selection Baseline Data Assessment of the Armenia Local Economy and Infrastructure Developm ent Project LPD-10 / Author’s Supervisio Heritage Hub and Tourism Ci n of Construction of "Goris hu IBRD / 85720 Post Direct Selection Direct 18,790.00 18,781.89 Signed 2020-01-20 2020-01-09 2020-02-08 2020-01-21 2020-03-19 2020-02-28 2022-06-27 rcuit Development b regeneration". LPD-11 / Author's supervisio n of the "Partial restoration a Heritage Hub and Tourism Ci IBRD / 85720 Post Direct Selection Direct 1,823.00 1,744.37 Signed 2020-02-13 2020-02-07 2020-03-12 2020-02-25 2020-04-21 2020-03-24 2020-10-18 nd reinforcement of monume rcuit Development nts in the historical capital of Armenia Dvin". LPD-12 / Modification of the Heritage Hub and Tourism Ci subproject design for "Zorat IBRD / 85720 Post Direct Selection Direct 2,235.00 2,165.99 Completed 2020-03-04 2020-03-03 2020-03-14 2020-03-05 2020-05-18 2020-03-24 2020-06-17 2020-12-15 rcuit Development s Qarer Monument Tourism Z one". LNS-01 / Local Individual Co nsultancy Services for Touris Heritage Hub and Tourism Ci Individual Consult m Product Development und IBRD / 85720 Post Open 6,245.00 6,163.30 Signed 2020-03-04 2020-03-06 2020-05-08 2020-04-20 2020-05-29 2020-05-06 2020-07-03 2020-05-06 2020-10-31 rcuit Development ant Selection er the World Bank’s Local Ec onomy and Infrastructure De velopment Project Page 4 LPD-14 / Update of the Desig n and Author’s Supervision of Heritage Hub and Tourism Ci IBRD / 85720 Post Direct Selection Direct 52,165.00 52,060.73 Signed 2020-08-25 2020-08-19 2020-09-04 2020-08-31 2020-11-01 2020-09-08 2021-12-26 Reconstruction of tourism inf rcuit Development rastructure and streets of Jer muk city. LPD-15 / Update of Design a nd Author’s Supervision of Re Heritage Hub and Tourism Ci construction of beginning of t IBRD / 85720 Post Direct Selection Direct 5,150.00 5,235.99 Signed 2020-08-25 2020-09-01 2020-09-04 2020-09-07 2020-11-01 2020-09-15 2021-12-26 rcuit Development he road from Garni Symphon y of Stones monument to Kh osrov Forest State Reserve. LIC-02 / Individual Consultan cy Services for Expertise Engi Heritage Hub and Tourism Ci Individual Consult neer under the World Bank’s IBRD / 85720 Post Open 12,600.00 0.00 Canceled 2020-09-22 2020-09-22 2020-11-10 2020-12-01 2021-01-05 2022-01-05 rcuit Development ant Selection Local Economy and Infrastruc ture Development Project. LIC-03 / Individual Consultan cy Services for Economic ana Heritage Hub and Tourism Ci Individual Consult lysis under the World Bank’s IBRD / 85720 Post Open 11,800.00 13,357.39 Terminated 2020-09-22 2020-09-22 2020-11-10 2020-10-14 2020-12-01 2020-10-15 2021-01-05 2020-10-16 2022-01-05 rcuit Development ant Selection Local Economy and Infrastruc ture Development Project. LIC-04 / Individual Consultan cy Services of Legal assistan Heritage Hub and Tourism Ci Individual Consult ce under the World Bank’s Lo IBRD / 85720 Post Open 11,600.00 11,578.97 Signed 2020-09-22 2020-09-22 2020-11-10 2020-11-25 2020-12-01 2020-12-01 2021-01-05 2020-12-02 2022-01-05 rcuit Development ant Selection cal Economy and Infrastructu re Development Project. LIC-02-2 / Individual Consult ancy Services for Expertise E Heritage Hub and Tourism Ci Individual Consult ngineer under the World Ban IBRD / 85720 Post Open 12,600.00 15,858.30 Signed 2021-03-24 2021-04-23 2021-04-26 2021-06-14 2021-05-03 2021-07-27 2021-05-15 2021-07-29 2022-05-15 rcuit Development ant Selection k’s Local Economy and Infras tructure Development Project LPD-22 / Author’s Supervisio n of Construction of "Prepara Heritage Hub and Tourism Ci IBRD / 85720 Post Direct Selection Direct 10,220.00 9,339.15 Signed 2021-08-04 2021-08-13 2021-08-14 2021-08-22 2021-09-27 2021-09-10 2022-08-13 tory work for the reconstructi rcuit Development on of the "Barekamutyun" to wn park in Gyumri". LIC-05 / Project Coordinator f Individual Consult or the LEID Project within the IBRD / 85720 Institutional Development Post Open 23,000.00 23,853.39 Signed 2021-08-10 2021-08-03 2021-09-12 2021-10-14 2021-10-03 2021-10-27 2021-11-07 2021-10-29 2022-04-09 ant Selection Tourism Committee LPD-25 / Author’s Supervisio n of the ''Improvement of the Heritage Hub and Tourism Ci IBRD / 85720 Post Direct Selection Direct 1,730.00 1,786.90 Signed 2021-09-14 2021-09-22 2021-09-24 2021-09-23 2021-11-07 2021-10-13 2022-04-06 nearest area of the Zorats Q rcuit Development arer monument". LIC-06 / Individual Consultan cy Services for Economic ana Heritage Hub and Tourism Ci Individual Consult lysis under the World Bank’s IBRD / 85720 Post Direct 22,335.00 22,460.72 Terminated 2021-10-19 2021-10-19 2021-10-29 2021-10-20 2021-11-12 2021-10-20 2021-12-01 2021-10-20 2023-03-31 rcuit Development ant Selection Local Economy and Infrastruc ture Development Project LIC-07 / Individual Consultan cy Services for Economic ana Heritage Hub and Tourism Ci Individual Consult lysis under the World Bank’s IBRD / 85720 Post Limited 15,150.00 15,536.74 Signed 2022-04-06 2022-03-31 2022-04-11 2022-04-06 2022-04-16 2022-04-06 2022-05-05 2022-04-11 2023-03-31 rcuit Development ant Selection Local Economy and Infrastruc ture Development Project. LIC-01 / International Individ ual Consultancy Services for Leading Tourism Product Dev Heritage Hub and Tourism Ci Individual Consult IBRD / 85720 Post Open 43,435.00 0.00 Canceled 2020-03-04 2020-03-06 2020-05-08 2020-05-29 2020-07-03 2020-11-30 elopment activities under the rcuit Development ant Selection World Bank’s Local Economy and Infrastructure Developm ent Project. Page 5