Procurement Plan dated on January 9, 2020 ODRA-VISTULA FLOOD MANAGEMENT PROJECT I. General 1. Data of General Project information: 2. Borrower: REPUBLIC OF POLAND 3. Project Name: ODRA-VISTULA FLOOD MANAGEMENT PROJECT 4. Loan No.: IBRD 8524–PL POL, Project ID: P147460 5. Coordination Agency: Project Coordination Unit Wroclaw 6. Project Implementing Unit: PGW WP RZGW Wroclaw, PGW WP RZGW Szczecin, PGW WP RZGW Rzeszow, PGW WP RZGW Krakow, IMGW-PIB and PCU. 7. Bank’s approval Date of the Procurement Plan May 07, 2015 - initial approval, August 18,2015; October 27, 2015 February 23, 2016 ; August 18, 2016 February 27,2017 ; August 28, 2017 April 24, 2018 March 29, 2019 ; November 16, 2019 1 Procurement Notice: July 23, 2015, No. WB3345-07/15 Period covered by this procurement plan: 2015-2022 Exchange rate: 1,3 USD = 1 EURO = 4,16 PLN 1Inclusion of a new contracts and exclusion of the contract OVFMP 1A.3 approved by the Steering Committee. Letter no DOLiZK-II-7731-1-39/2019 dated on January 2, 2020 1/4 II. Procurement Method Thresholds 1. Goods and Works and non-consulting services Procurement Method Method Threshold Comments ICB (Open International) 1. ≥ € 1,500,000 Goods, IT and Non-Consultant Services (NCS) NCB (Open National) 2. < € 1,500,000 Goods, IT and Non-Consultant Services (NCS) ICB (Works, Turnkey, S&I of Plant & Equipment 3. ≥ €15,400,000 an PPP) NCB (Works, Turnkey, S&I of Plant & Equipment 4. < €15,400,000 an PPP) Goods, NCS ≤ 5. Shopping (S) €80,000 Works ≤ € 150,000 Each DC contract shall meet the requirement of the 6. Direct Contracting (DC) NA World Bank’s Procurement Guidelines 2/4 III. Prior Review Threshold 1. Goods and Works and non-consulting services Procurement Method Prior Review Threshold Comments ICB (Open International) 1. Goods, IT and Non-Consultant Services ≥ € 3,100,000 (NCS) NCB (Open National) 2. Goods, IT and Non-Consultant Services First contract prior review (NCS) ICB (Works, Turnkey, S&I of Plant & 3. ≥ €15 400,000 Equipment an PPP) NCB (Works, Turnkey, S&I of Plant & 4. First contract prior review Equipment an PPP) 5. Shopping (S) NA All shopping post review Prior review will apply based 6. Direct Contracting (DC) NA on type of procurement 2. Consulting services Selection Method Prior Review Comments Threshold ≥ 1. Consultant (Firms) (CS) €1,500,000 All Individual Consultants contracts shall be subject to ≥€ the Bank’s post-review. 2. Consultant (Individuals) (IC) 300,000 Prior review only under exceptional circumstances (e.g., key positions, long term consultants.) Prior review will apply based on type of procurement Single Source Selection of 3. NA Each SSS contract shall meet the requirement of the Consultants (SSS) World Bank’s Consultants Guidelines 3/4 Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than 380 000 EUR equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 4/4 PROCUREMENT Poland : ODRA-VISTULA FLOOD MANAGEMENT PROJECT PLAN General Information Country: Poland 2019-11-19 Bank’s Approval Date of the Original Procurement Plan: 2022-06-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P147460 GPN Date: Project Name: ODRA-VISTULA FLOOD MANAGEMENT PROJECT Loan / Credit No: IBRD / 85240 Project Coordination Unit Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CANCELLED-ORFPP-A1-11 / Component 1: Flood Protecti CANCELLED-Subsoil strength 20,000,000.0 20,252,482. IBRD / 85240 on of the Middle and Lower Prior Direct Selection Direct Canceled ening by gravel columns with 0 57 Odra embankment construction. OVFMP-3.B.1 / Flood protecti Component 1: Flood Protecti Open - Internationa Single Stage - One E 48,522,527. IBRD / 85240 Prior Request for Bids 0.00 Signed 2017-07-25 2017-08-08 on Sandomierz on of the Middle and Lower l nvelope 28 Odra OVFMP 1A.1 / Chlewice-Porz Component 1: Flood Protecti ecze. Backwater embankmen Single Stage - One E 3,144,673.4 IBRD / 85240 on of the Middle and Lower Prior Request for Bids Open - National 0.00 Signed 2017-04-18 2017-05-15 t of Odra River at Mysla River nvelope 7 Odra and Modernization of Marwic ki polder stage I and II. OVFMP - 1C.1 / 1C.1 Extensi Component 1: Flood Protecti on and construction of flood Open - Internationa Single Stage - One E 30,422,040. IBRD / 85240 on of the Middle and Lower Prior Request for Bids 0.00 Signed 2017-05-31 2017-06-12 embankments and Reconstru l nvelope 92 Odra ction of Czarny Kanal and Ra cza Struga. OVFMP-1B.6 R / Flood protec Component 1: Flood Protecti Open - Internationa Single Stage - One E 62,010,861. tion of Nowa S l and below Kr IBRD / 85240 on of the Middle and Lower Prior Request for Bids 0.00 Signed 2019-08-21 2019-09-20 l nvelope 32 osno Odrza skie Odra OVFMP 1B.1/1(a) / Reconstru ction of the Odra River contr Component 1: Flood Protecti ol infrastructure - adjusting t Open - Internationa Single Stage - One E 31,026,084. IBRD / 85240 on of the Middle and Lower Prior Request for Bids 0.00 Signed 2019-10-21 2019-11-19 o the III class of waterway, o l nvelope 66 Odra n the section from the village of Scinawa to the estuary of t he Nysa Luzycka River Stage II OVFMP-2A.2 / Construction o f Szalej w G rny - a dry flood Component 1: Flood Protecti control reservoir on Bystrzyc Open - Internationa Single Stage - One E 112,739,04 IBRD / 85240 on of the Middle and Lower Prior Request for Bids 0.00 Signed 2018-03-14 2018-04-16 a Dusznicka River and Constr l nvelope 3.78 Odra uction of Krosnowice - a dry f lood control reservoir on Dun a Stream. OVFMP-2A.1/R / Construction of Boboszow - a dry flood con Component 1: Flood Protecti trol reservoir on Nysa Klodzk Open - Internationa Single Stage - One E 113,903,78 IBRD / 85240 on of the Middle and Lower Prior Request for Bids 0.00 Signed 2017-11-22 2017-12-06 a River and Construction of R l nvelope 7.90 Odra oztoki Bystrzyckie - a dry floo d control reservoir on Gowor owka Stream OVFMP-1B.6 / Flood protecti Component 1: Flood Protecti Open - Internationa Single Stage - One E 63,164,916. on of Nowa S l and below Kro IBRD / 85240 on of the Middle and Lower Prior Request for Bids 0.00 Canceled 2019-06-26 l nvelope 74 sno Odrza skie Odra OVFMP-2A.1 / Construction o f Boboszow - a dry flood cont Component 1: Flood Protecti rol reservoir on Nysa Klodzka Open - Internationa Single Stage - One E 81,533,257. IBRD / 85240 on of the Middle and Lower Prior Request for Bids 0.00 Canceled 2017-11-02 River and Construction of Ro l nvelope 18 Odra ztoki Bystrzyckie - a dry flood control reservoir on Goworow ka Stream OVFMP 1C.2 / Extension and construction of flood embank Component 1: Flood Protecti ments and Reconstruction of Open - Internationa Single Stage - One E 31,671,731. 2022-10-1 IBRD / 85240 on of the Middle and Lower Prior Request for Bids 46.44 Signed 2020-01-24 2020-02-09 2020-01-29 2020-02-12 2020-03-11 2020-05-18 2020-04-10 2020-06-16 2020-05-15 2020-07-21 Czarny Kanał and Racza Stru l nvelope 86 8 Odra ga. Contract managed by PGW WP RZGW Wroclaw. OVFMP 3A.1 / Modernization of Vistula embankments in Cr Component 3: Flood Protecti Open - Internationa Single Stage - One E 32,624,000.0 22,044,796. 2022-06-2 IBRD / 85240 Prior Request for Bids Signed 2020-02-11 2020-02-27 2020-03-20 2020-04-03 2020-07-31 2020-09-18 2020-09-21 2022-05-26 2020-12-07 2021-01-19 acow – Section 1, on of the Upper Vistula l nvelope 0 35 4 Section 2, Section 3 OVFMP 1B.7 / WFS Widawa – the rebuilding of the flood m anagement system of the co Component 1: Flood Protecti Open - Internationa Single Stage - One E 31,109,000.0 21,775,847. Under Revie 2022-02-2 mmunes and municipalities C IBRD / 85240 on of the Middle and Lower Prior Request for Bids 2020-02-13 2020-02-13 2020-02-13 2020-02-13 2020-02-19 2020-03-31 2020-03-19 l nvelope 0 56 w 8 zernica, Długołeka, Wisznia Odra Mała and Wrocław. Contract managed by PGW WP RZGW Wrocław. OVFMP 1B.5/1 / Reconstructi on of bridge to ensure a mini Component 1: Flood Protecti mum clearance - Railway bri Open - Internationa Single Stage - One E 101,660,000. 89,046,903. 2022-11-0 IBRD / 85240 on of the Middle and Lower Prior Request for Bids Signed 2020-02-18 2020-04-01 2020-03-16 2020-11-03 2020-12-21 2020-02-23 2021-01-12 2021-05-14 2021-04-05 2021-08-23 2021-05-10 2021-09-13 dge km 733,7 Regalica River l nvelope 00 23 1 Odra in Szczecin. The Contract ma naged by PGW WP RZGW Szc zecin. OVFMP 3D.2/1 / Construction Component 3: Flood Protecti Single Stage - One E 2,212,268.4 2021-02-1 of the right embankment of t IBRD / 85240 Post Request for Bids Open - National 1,716,000.00 Signed 2020-02-21 2020-02-27 2020-02-21 2020-03-27 2020-05-20 2020-05-18 2020-08-18 2020-06-23 2020-09-10 on of the Upper Vistula nvelope 3 8 he Biala River in the City of T arnow OVFMP 3A.3 / Section 4 - Th e right embankment of the Vi Component 3: Flood Protecti Single Stage - One E 5,021,770.6 2021-05-1 IBRD / 85240 Post Request for Bids Open - National 4,634,458.00 Signed 2020-02-24 2019-07-09 2020-02-29 2020-04-11 2019-09-09 2020-05-11 2019-11-07 2020-06-15 2020-01-21 stula River from the estuary on of the Upper Vistula nvelope 4 8 of Skawinka to the Kosciuszk o barrage OVFMP 3B.1/1 / Flood protec Component 3: Flood Protecti 34,996,000.0 29,257,944. 2020-10-0 tion Sandomierz - completion IBRD / 85240 Prior Direct Selection Direct Signed 2020-02-26 2021-09-02 2020-03-02 2021-09-02 2020-04-06 2020-01-29 on of the Upper Vistula 0 73 3 of tasks 3 and 4 Page 1 OVFMP 1A.4 / Implementatio n of works involving the com Component 1: Flood Protecti pletion of flood embankment Single Stage - One E 5,664,931.0 2021-09-2 IBRD / 85240 on of the Middle and Lower Post Request for Bids Open - National 5,421,000.00 Completed 2020-04-03 2020-03-30 2020-04-03 2020-04-27 2020-04-30 2020-05-15 2020-06-15 2020-07-30 2020-06-29 2020-08-20 Chlewice, Marwice – Krajnik, nvelope 0 7 Odra Mniszki - Gryfino. Contract managed by PGW W P RZGW Szczecin. OVFMP 1B.4/2 / Dredging of Component 1: Flood Protecti Single Stage - One E 6,848,250.3 2021-12-3 Klucz-Ustowo ditch. Contract IBRD / 85240 on of the Middle and Lower Post Request for Bids Open - National 3,302,000.00 Signed 2020-04-03 2020-02-28 2020-04-03 2020-05-03 2020-04-27 2020-06-17 2020-07-01 2020-07-01 2020-07-16 nvelope 8 1 managed by PGW WP RZGW Odra Szczecin. OVFMP 3D.3 / Łęg IV – exten sion of the left river embank ment at chainage km 0+082- Component 3: Flood Protecti Single Stage - One E 23,972,000.0 16,534,065. 2022-12-3 5+030 within the Commune IBRD / 85240 Post Request for Bids Open - National Signed 2020-06-30 2020-10-05 2020-07-05 2020-10-19 2020-08-16 2021-01-18 2020-09-15 2021-04-19 2020-12-21 2021-05-14 on of the Upper Vistula nvelope 0 65 0 of Gorzyce, and of the right e mbankment at chainage km 0+000-5+236 within the Co mmune of Gorzyce OVFMP 1B.8 / Flood protecti Component 1: Flood Protecti Open - Internationa Single Stage - One E 27,339,000.0 32,270,283. 2022-12-1 on of Krosno Odrzańskie. Con IBRD / 85240 on of the Middle and Lower Prior Request for Bids Signed 2020-04-30 2020-06-15 2020-07-26 2020-06-29 2020-09-20 2020-09-28 2020-11-15 2020-11-04 2020-12-27 2020-12-01 l nvelope 0 86 8 tract managed by PGW WP R Odra ZGW Wrocław. OVFMP 4B.1/2 / Modernisatio n and implementation of hyd Component 4: Institutional s rological, control and teletec Open - Internationa Single Stage - One E 40,001,000.0 2022-12-1 IBRD / 85240 trengthening and Enhanced Prior Request for Bids 0.00 Canceled 2020-05-31 2020-06-05 2020-07-26 2020-10-11 2020-11-15 hnical measurement systems l nvelope 0 8 Forecasting at hydrotechnical facilities of RZGW Krakow and RZGW Wr oclaw. OVFMP 1B.2 / Modernization Component 1: Flood Protecti works on boundary sections Open - Internationa Single Stage - One E 161,018,000. 64,425,594. 2023-03-1 IBRD / 85240 on of the Middle and Lower Prior Request for Bids Signed 2020-06-30 2020-07-07 2020-08-31 2020-08-19 2020-10-26 2021-03-29 2020-12-30 2021-09-10 2021-02-15 2021-09-27 of Odra River, Stage I To pro l nvelope 00 52 7 Odra vide Good Condition for Ice – breaking OVFMP 1A.2 / Flood protecti on of Gryfino, Ognica and Pia Component 1: Flood Protecti Single Stage - One E 8,163,701.6 2022-12-2 sek village on Odra River. Mo IBRD / 85240 on of the Middle and Lower Post Request for Bids Open - National 7,410,000.00 Signed 2020-07-23 2020-12-29 2020-07-30 2020-09-18 2021-04-08 2020-10-23 2021-08-09 2020-11-13 2021-09-07 nvelope 0 1 dernization of Marwicki polde Odra r stage III – pump station Kraj nik. OVFMP 1B.3/1 / Stage I – Mo Component 1: Flood Protecti Single Stage - One E 5,903,846.8 2022-03-3 IBRD / 85240 Post Request for Bids Open - National 9,607,000.00 Signed 2020-07-08 2020-08-24 2020-07-31 2020-08-31 2020-12-18 2020-10-30 2021-04-12 2020-11-30 2021-05-07 oring base for icebreakers on of the Middle and Lower nvelope 9 0 Odra OVFMP 1B.3/2 / Stage II - Th e construction of docking-mo Component 1: Flood Protecti Single Stage - One E 4,807,265.3 2022-03-1 oring infrastructure on Lower IBRD / 85240 on of the Middle and Lower Post Request for Bids Open - National 6,682,000.00 Signed 2020-07-19 2020-11-06 2020-07-29 2020-09-30 2021-03-16 2020-11-20 2021-05-24 2020-12-18 2021-07-12 nvelope 0 9 Odra River and on boundary Odra sections of Odra River as well as new aids to navigation OVFMP 1B.5/2 / Reconstructi Component 1: Flood Protecti on of bridge to ensure a mini Open - Internationa Single Stage - One E 33,787,000.0 26,494,844. 2022-12-2 IBRD / 85240 on of the Middle and Lower Prior Request for Bids Signed 2020-07-08 2020-07-21 2020-08-30 2020-10-01 2020-10-30 2021-02-08 2020-12-27 2021-06-01 2021-02-21 2021-07-16 mum clearance - Road bridge l nvelope 0 23 5 Odra km 2,45 Warta River, Kostrzy n n/Odra OVFMP 1B.5/3 / Reconstructi on of bridge to ensure a mini Component 1: Flood Protecti Single Stage - One E 6,060,479.1 2022-12-2 mum clearance (Railway brid IBRD / 85240 on of the Middle and Lower Post Request for Bids Open - National 8,060,000.00 Signed 2020-09-20 2020-12-16 2020-10-18 2020-12-20 2021-02-10 2021-02-14 2021-06-08 2021-02-28 2021-07-06 nvelope 5 0 ge at km 615.1 of the Odra R Odra iver in Kostrzyn nad Odrą) OVFMP 1B.1/1(B) / Reconstr Component 1: Flood Protecti Open - Internationa Single Stage - One E 11,700,000.0 18,233,113. 2023-05-2 uction of the road bridge in K IBRD / 85240 on of the Middle and Lower Post Request for Bids Signed 2020-07-31 2020-08-31 2020-08-18 2020-08-31 2020-10-29 2020-10-28 2020-11-28 2020-12-02 2021-01-29 2021-01-12 l nvelope 0 15 3 rosno Odrzańskie with access Odra road. OVFMP 4A,3,1 / POLRAD We Component 4: Institutional s Open - Internationa Single Stage - One E 27,950,000.0 27,718,698. 2023-07-1 IBRD / 85240 Prior Request for Bids Signed 2020-08-26 2020-08-26 2020-08-26 2020-08-27 2020-09-22 2020-10-21 2020-11-06 ather Radar Modernization trengthening and Enhanced l nvelope 0 74 0 Forecasting OVFMP 3D.2/2 / Expansion o f the left and right embankm Component 3: Flood Protecti Single Stage - One E 28,236,000.0 11,600,398. 2022-06-3 IBRD / 85240 Post Request for Bids Open - National Signed 2020-09-15 2020-09-10 2020-09-20 2020-10-15 2020-11-01 2021-02-05 2021-01-13 2021-05-24 2021-03-10 2021-06-29 ent of the Biala River in the T on of the Upper Vistula nvelope 0 32 0 arnow Municipality and the C ity of Tarnow OVFMP 3A.2/1, 3A.2/2 / Floo Component 3: Flood Protecti Single Stage - One E 10,530,000.0 4,701,044.2 2022-06-3 d protection in Serafa Valley IBRD / 85240 Post Request for Bids Open - National Signed 2020-09-30 2020-10-04 2020-10-05 2020-10-19 2020-11-16 2021-05-07 2021-02-09 2021-07-23 2021-04-05 2021-08-05 on of the Upper Vistula nvelope 0 5 0 - Malinowka 1reservoir, Malin owka 2 reservoir OVFMP 3A.2/4 / Flood protec Component 3: Flood Protecti Open - Internationa Single Stage - One E 1,568,534.5 2022-04-0 IBRD / 85240 Post Request for Bids 2,379,000.00 Signed 2020-12-16 2020-12-21 2020-12-23 2021-02-24 2021-05-17 2021-03-26 2021-08-27 2021-05-04 2021-10-27 tion in Serafa Valley – Serafa on of the Upper Vistula l nvelope 8 5 2 reservoir OVFMP 3A.6 / Construction o Component 3: Flood Protecti Open - Internationa Single Stage - One E 1,643,533.4 2022-02-2 f a pumping station for mobil IBRD / 85240 Post Request for Bids 1,404,000.00 Signed 2020-12-03 2020-11-18 2020-12-08 2021-01-19 2021-06-07 2021-02-18 2021-11-08 2021-03-25 2022-01-28 on of the Upper Vistula l nvelope 5 3 e pumps to drain the Lesisko complex OVFMP 3A.2/3 / Flood protec Component 3: Flood Protecti Open - Internationa Single Stage - One E 2,569,156.3 2022-03-2 tion in Serafa Valley - Malinó IBRD / 85240 Post Request for Bids 3,315,000.00 Signed 2020-12-03 2020-12-21 2020-12-08 2021-02-16 2021-05-24 2021-03-31 2021-12-06 2021-05-12 2022-02-11 on of the Upper Vistula l nvelope 0 4 wka 3 reservoir OVFMP 3A.5 / Development of a flood gate at the left floo Component 3: Flood Protecti Open - Internationa Single Stage - One E 2022-05-0 IBRD / 85240 Post Request for Bids 6,279,000.00 0.00 Canceled 2020-12-03 2020-12-12 2020-12-08 2021-01-19 2021-05-10 2021-02-18 2021-03-25 d embankment in the area of on of the Upper Vistula l nvelope 9 water intakes for the Sendzi mira Steel Mill in Cracow OVFMP 3A.4 / Extension of a section of the right embankm Component 3: Flood Protecti Open - Internationa Single Stage - One E 7,840,841.1 2022-05-0 ent downstream of the Dąbie IBRD / 85240 Post Request for Bids 8,307,000.00 Signed 2020-12-03 2020-11-25 2020-12-08 2021-01-19 2021-06-08 2021-02-18 2021-07-27 2021-03-25 2021-08-05 on of the Upper Vistula l nvelope 9 9 Barrage, including developm ent of a flood gate in the are a of a repair yard OVFMP 2B.2/1 / Flood protec Component 1: Flood Protecti Open - Internationa Single Stage - One E 14,300,000.0 Under Imple 2023-05-2 tion of cities along Biała Ląde IBRD / 85240 on of the Middle and Lower Post Request for Bids 0.00 2021-04-15 2021-10-22 2021-05-16 2021-10-22 2021-07-20 2021-10-17 2021-12-07 l nvelope 0 mentation 8 cka river: Stronie Śląskie, Ląd Odra ek Zdrój OVFMP 3 A.5 / Development National Procure of a flood gate at the left floo ment Document - Component 3: Flood Protecti Single Stage - One E 6,774,170.7 2023-02-0 d embankment in the area of IBRD / 85240 Post Request for Bids Open - National 1 Envelope proce 8,866,000.00 Signed 2021-08-26 2021-09-03 2021-08-31 2021-10-12 2021-11-15 2021-11-11 2021-12-30 2021-12-22 2022-01-27 on of the Upper Vistula nvelope 4 5 water intakes for the Sendzi ss (Non Bank-SPD mira Steel Mill in Cracow. ) Page 2 National Procure OVFMP 1B.9 / Modernisation Component 1: Flood Protecti ment Document - Single Stage - One E Under Imple 2022-12-1 of flood embankment along t IBRD / 85240 on of the Middle and Lower Post Request for Bids Open - National 1 Envelope proce 4,121,000.00 0.00 2021-09-12 2021-12-29 2021-10-31 2021-11-29 2022-03-11 2021-12-13 2021-12-29 nvelope mentation 7 he Ślęzoujście Street with ro Odra ss (Non Bank-SPD ad infrastructure ) OVFMP 2B.1/1 / Flood protec Request for Bids - Component 1: Flood Protecti tion of cities along Nysa Kłod Open - Internationa Single Stage - One E Works (without pr 27,820,000.0 Under Imple 2023-10-2 IBRD / 85240 on of the Middle and Lower Prior Request for Bids 0.00 2021-10-29 2021-12-24 2021-11-30 2022-02-02 2022-02-21 2022-02-28 2022-03-30 zka river: Kłodzko, Bystrzyca l nvelope equalification) SP 0 mentation 2 Odra Kłodzka,Długopole Zdrój, Mię D dzylesie OVFMP 2B.2/2 / Flood protec Request for Bids - Component 1: Flood Protecti tion of cities along Bystrzyca Open - Internationa Single Stage - One E Works (without pr 32,734,000.0 Pending Imp 2023-11-3 IBRD / 85240 on of the Middle and Lower Prior Request for Bids 0.00 2022-03-04 2022-04-07 2022-05-19 2022-06-09 2022-06-30 Dusznicka river: Polanica Zdr l nvelope equalification) SP 0 lementation 0 Odra ój, Szczytna, Duszniki Zdrój. D Request for Quota OVFMP 2B.2/2 (B) / Intervent Component 2: Flood Protecti Request for Quota Single Stage - One E Pending Imp 2022-06-3 IBRD / 85240 Post Open - National tions (Non Bank-S 54,600.00 0.00 2022-03-20 2022-04-29 ion felling of trees in Szczytn on of the Nysa Kłodzka Valle tions nvelope lementation 0 PD) a y Request for Quota OVFMP 2B.1/1 (A) / Intervent Component 2: Flood Protecti Request for Quota Single Stage - One E Pending Imp 2022-06-3 IBRD / 85240 Post Open - National tions (Non Bank-S 169,000.00 0.00 2022-03-20 2022-04-29 ion felling of trees in Kłodzko on of the Nysa Kłodzka Valle tions nvelope lementation 0 PD) y Request for Quota OVFMP 2B.1/1 (C) / Intervent Component 2: Flood Protecti Request for Quota Single Stage - One E Pending Imp 2022-06-3 IBRD / 85240 Post Open - National tions (Non Bank-S 6,500.00 0.00 2022-03-20 2022-04-29 ion felling of trees in Długopo on of the Nysa Kłodzka Valle tions nvelope lementation 0 PD) le Zdrój y Request for Quota OVFMP 2B.2/1 (B) / Intervent Component 2: Flood Protecti Request for Quota Single Stage - One E Pending Imp 2022-06-3 IBRD / 85240 Post Open - National tions (Non Bank-S 107,900.00 0.00 2022-03-20 2022-04-29 ion felling of trees in Lądek Z on of the Nysa Kłodzka Valle tions nvelope lementation 0 PD) drój y Request for Quota OVFMP 2B.2/2 (A) / Intervent Component 2: Flood Protecti Request for Quota Single Stage - One E Pending Imp 2022-06-3 IBRD / 85240 Post Open - National tions (Non Bank-S 11,700.00 0.00 2022-03-20 2022-04-29 ion felling of trees in Polanica on of the Nysa Kłodzka Valle tions nvelope lementation 0 PD) Zdrój y Request for Quota OVFMP 2B.2/2 (C) / Intervent Component 2: Flood Protecti Request for Quota Single Stage - One E Pending Imp 2022-06-3 IBRD / 85240 Post Open - National tions (Non Bank-S 49,400.00 0.00 2022-03-20 2022-04-29 ion felling of trees in Duszniki on of the Nysa Kłodzka Valle tions nvelope lementation 0 PD) Zdrój y Request for Quota OVFMP 2B.2/1 (A) / Intervent Component 2: Flood Protecti Request for Quota Single Stage - One E Pending Imp 2022-06-3 IBRD / 85240 Post Open - National tions (Non Bank-S 31,200.00 0.00 2022-03-20 2022-04-28 ion felling of trees in Stronie on of the Nysa Kłodzka Valle tions nvelope lementation 0 PD) Śląskie y Request for Quota OVFMP 2B.1/1 (B) / Intervent Component 2: Flood Protecti Request for Quota Single Stage - One E Pending Imp 2022-06-3 IBRD / 85240 Post Open - National tions (Non Bank-S 169,000.00 0.00 2022-03-20 2022-04-29 ion felling of trees in Bystrzy on of the Nysa Kłodzka Valle tions nvelope lementation 0 PD) ca Kłodzka y Request for Quota OVFMP 2B.1/1 (D) / Intervent Component 2: Flood Protecti Request for Quota Single Stage - One E Pending Imp 2022-06-3 IBRD / 85240 Post Open - National tions (Non Bank-S 126,100.00 0.00 2022-03-20 2022-04-29 ion felling of trees in Międzyl on of the Nysa Kłodzka Valle tions nvelope lementation 0 PD) esie y GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OVFMP 4B.1/1 / Modernisatio n and implementation of IT s ystems supporting the operat Component 4: Institutional s ional work of the Operational Open - Internationa Single Stage - One E IBRD / 85240 trengthening and Enhanced Prior Request for Bids 20.05 13,811,185.23 Signed 2020-01-24 2020-04-01 2020-01-29 2020-07-09 2020-03-11 2021-01-22 2020-03-31 2021-09-07 2020-04-20 2021-10-07 2022-12-02 Centers in Krakow and Wrocl l nvelope Forecasting aw together with supplies of necessary hardware and soft ware. Contract managed by PGW W P RZGW Wrocław. OVFMP 4A.1.1 / Modernizatio n and extension of the Telem Component 4: Institutional s Open - Internationa Single Stage - One E etry System for hydrological IBRD / 85240 trengthening and Enhanced Prior Request for Bids 49,647,000.00 29,913,591.30 Signed 2020-03-18 2020-06-17 2020-03-23 2020-06-29 2020-05-04 2020-11-05 2020-06-03 2021-05-06 2020-07-08 2021-06-02 2021-01-04 l nvelope modeling and forecasting, in Forecasting cluding radiative data and co nnection provision OVFMP 4A.4.3A / Personal Pr Component 4: Institutional s Open - Internationa Single Stage - One E IBRD / 85240 Post Request for Bids 3,250,000.00 415,436.88 Signed 2020-03-10 2020-03-30 2020-03-15 2020-03-31 2020-04-26 2020-06-19 2020-05-26 2020-12-04 2020-06-30 2021-01-19 2021-01-31 oductivity and Office Equipm trengthening and Enhanced l nvelope ent - Part 1 Forecasting OVFMP 4A.3.2 / Modernizatio Component 4: Institutional s n of the lightning detection n IBRD / 85240 trengthening and Enhanced Post Direct Selection Direct 1,365,000.00 2,142,290.61 Signed 2020-02-26 2020-05-13 2020-03-02 2020-11-02 2020-07-07 2021-09-10 2022-11-30 etwork (PERUN) Forecasting OVFMP 4B.1/3 / Operational Component 4: Institutional s Centers in Krakow and Wrocl Open - Internationa Single Stage - One E IBRD / 85240 trengthening and Enhanced Prior Request for Bids 4,758,000.00 8,376,693.02 Signed 2020-05-24 2020-06-16 2020-05-29 2020-07-07 2020-06-28 2020-11-27 2020-08-23 2021-03-01 2020-09-27 2021-03-30 2022-01-31 aw - Telecommunication con l nvelope Forecasting nections to hydrotechnical fa cilities OVFMP 4B.1/4 / Operational Component 4: Institutional s Centers in Krakow and Wrocl Open - Internationa Single Stage - One E IBRD / 85240 trengthening and Enhanced Post Request for Bids 702,000.00 1,154,813.60 Signed 2020-05-17 2020-05-21 2020-05-22 2020-05-21 2020-06-30 2020-08-24 2020-08-30 2020-12-16 2020-09-30 2020-12-16 2022-04-19 aw - Digital dispatching com l nvelope Forecasting munication system for hydrot echnical facilities OVFMP 4A.1.9 / Modernizatio Component 4: Institutional s Open - Internationa Single Stage - One E n of the Aerological Measure IBRD / 85240 trengthening and Enhanced Post Request for Bids 4,810,000.00 1,368,417.38 Signed 2020-03-10 2020-06-22 2020-03-15 2020-06-22 2020-04-26 2020-08-17 2020-05-26 2020-12-07 2020-06-30 2021-01-08 2020-12-27 l nvelope ment Stations Forecasting OVFMP 4A.4.3B / Personal Pr Component 4: Institutional s Open - Internationa Single Stage - One E IBRD / 85240 Post Request for Bids 650,000.00 598,924.55 Signed 2020-07-28 2020-08-21 2020-07-31 2020-08-21 2020-09-11 2020-11-03 2020-10-11 2021-03-15 2020-11-15 2021-04-14 2021-10-29 oductivity and Office Equipm trengthening and Enhanced l nvelope ent - Part 2 Forecasting OVFMP 4A.4.2 / Modernizatio Component 4: Institutional s Open - Internationa Single Stage - One E IBRD / 85240 Post Request for Bids 3,965,000.00 4,301,635.71 Signed 2020-07-31 2021-04-07 2020-08-05 2021-04-15 2020-09-16 2021-07-06 2020-10-16 2021-11-08 2020-11-20 2021-12-07 2021-09-30 n of ICT Infrastructure trengthening and Enhanced l nvelope Forecasting OVFMP 4B.1/2. / Modernisati on and implementation of hy Component 4: Institutional s drological, control and telete Open - Internationa Single Stage - One E IBRD / 85240 trengthening and Enhanced Prior Request for Bids 43,745,000.00 46,175,012.29 Signed 2020-08-14 2020-09-10 2020-08-26 2021-03-19 2020-10-26 2021-09-10 2020-12-21 2022-03-21 2021-01-25 2022-04-29 2022-12-28 chnical measurement system l nvelope Forecasting s at hydrotechnical facilities of RZGW Krakow and RZGW Wroclaw. OVFMP 4A.1.10A / New work Component 4: Institutional s stations for checking/calibrati Single Stage - One E Pending Impl IBRD / 85240 trengthening and Enhanced Post Request for Bids Open - National 650,000.00 0.00 2020-09-30 2020-10-05 2021-01-06 2021-03-10 2021-04-14 2022-12-30 ons of sensors and moderniz nvelope ementation Forecasting ation of the current equipme nt of CLAP IMGW-PIB OVFMP 4A.2 / Modernization and expansion of the monitor Component 4: Institutional s Open - Internationa Single Stage - One E ing and forecasting system t IBRD / 85240 trengthening and Enhanced Post Request for Bids 2,730,000.00 0.00 Canceled 2020-11-24 2020-12-09 2021-04-05 2021-07-08 2021-08-12 2022-12-30 l nvelope o enhance the hydro meteor Forecasting ological flood protection of th e coastal areas Page 3 OVFMP 4A.4.3C / Personal Pr Component 4: Institutional s Request for Propo Open - Internationa Single Stage - One E oductivity and Office Equipm IBRD / 85240 trengthening and Enhanced Post 2,743,000.00 1,955,380.57 Signed 2021-03-10 2021-03-16 2021-03-15 2021-03-17 2021-04-26 2021-05-13 2021-05-26 2021-07-26 2021-06-30 2021-08-23 2022-04-20 sals l nvelope ent - Part 1 (Lot 1) Forecasting 4A. 2 / Modernization and ex pansion of the monitoring an Component 4: Institutional s Open - Internationa Single Stage - One E Under Imple d forecasting system to enha IBRD / 85240 trengthening and Enhanced Prior Request for Bids 4,680,000.00 0.00 2021-09-24 2021-12-24 2021-09-29 2022-01-07 2021-11-10 2022-04-13 2021-12-10 2022-01-14 2023-07-27 l nvelope mentation nce the hydro meteorological Forecasting flood protection of the coasta l areas 4A.1.4 / Provision of hydrom Component 4: Institutional s Open - Internationa Single Stage - One E IBRD / 85240 Post Request for Bids 2,860,000.00 1,974,677.60 Signed 2021-10-30 2022-01-14 2021-11-04 2022-01-14 2021-12-16 2022-02-24 2022-01-15 2022-04-29 2022-02-19 2022-06-17 2022-08-18 etric measurements equipme trengthening and Enhanced l nvelope nt Forecasting 4A.1.5 / Provision of water tr Component 4: Institutional s Open - Internationa Single Stage - One E Under Imple IBRD / 85240 Post Request for Bids 650,000.00 0.00 2021-11-30 2022-02-22 2021-12-05 2022-02-22 2022-01-16 2022-04-21 2022-04-04 2022-05-09 2023-05-09 ansport means for river meas trengthening and Enhanced l nvelope mentation urements Forecasting 4A.1.6 / Provision of land sur Component 4: Institutional s Open - Internationa Single Stage - One E IBRD / 85240 Post Request for Bids 832,000.00 656,432.91 Signed 2021-10-29 2021-10-21 2021-11-03 2021-10-22 2021-12-15 2021-12-09 2022-01-14 2022-03-16 2022-02-18 2022-04-15 2022-06-18 veying equipment trengthening and Enhanced l nvelope Forecasting 4A.1.8 / Modernization of uni nterrupted power supply syst Component 4: Institutional s ems at the hydrometeorologi Open - Internationa Single Stage - One E IBRD / 85240 trengthening and Enhanced Post Request for Bids 650,000.00 0.00 Canceled 2021-10-29 2021-12-17 2021-11-03 2021-12-20 2021-12-15 2022-01-28 2022-02-23 2022-03-21 2022-04-06 2023-04-07 cal stations, the weather rad l nvelope Forecasting ars and the Central Laborator y of IMGW-PIB for Measuring Instruments OVFMP 4A.1.1A / Modernizat ion and extension of the Tele Component 4: Institutional s Request for Propo Open - Internationa Single Stage - One E Under Imple metry System for hydrologic IBRD / 85240 trengthening and Enhanced Prior 9,373,000.00 0.00 2021-11-30 2022-01-24 2021-12-05 2022-02-15 2022-01-02 2022-04-25 2022-01-31 2022-02-28 2022-08-31 sals l nvelope mentation al modeling and forecasting, Forecasting including radiative data and connection provision (Lot 3) OVFMP 4A.1.8 / Modernizatio n of uninterrupted power sup Component 4: Institutional s ply systems at the hydromet Open - Internationa Single Stage - One E Pending Impl IBRD / 85240 trengthening and Enhanced Post Request for Bids 650,000.00 0.00 2022-04-13 2022-04-18 2022-05-30 2022-06-29 2022-08-03 2023-08-31 eorological stations, the weat l nvelope ementation Forecasting her radars and the Central La boratory of IMGW-PIB for Mea suring Instruments OVFMP 4B.1/5 / Delivery of Component 4: Institutional s Pending Impl IBRD / 85240 Post Direct Selection Direct 364,000.00 0.00 2022-06-24 2022-07-10 2022-07-24 2022-08-31 DHI Mike 11 modelling softw trengthening and Enhanced ementation are Forecasting NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OVFMP 4A.3.1 / POLRAD We Component 4: Institutional s Open - Internationa Single Stage - One E IBRD / 85240 Prior Request for Bids 27,664,000.00 0.00 Canceled 2020-02-27 2020-03-16 2020-03-03 2020-04-14 2020-05-14 2020-06-18 2020-12-15 ather Radar Modernization trengthening and Enhanced l nvelope Forecasting OVFMP 1A.6 / Security servic Component 1: Flood Protecti Single Stage - One E IBRD / 85240 Post Request for Bids Open - National 70,200.00 25,214.52 Signed 2020-05-28 2019-11-15 2020-06-02 2020-07-14 2019-11-22 2020-08-13 2020-01-19 2020-09-17 2020-01-20 2021-03-16 es for Construction Site. on of the Middle and Lower nvelope Odra 4A.4.1 / High Performance C Component 4: Institutional s Open - Internationa Single Stage - One E Under Imple IBRD / 85240 Prior Request for Bids 14,794,000.00 0.00 2021-10-31 2021-11-05 2021-12-17 2022-01-16 2022-02-20 2023-01-31 omputer trengthening and Enhanced l nvelope mentation Forecasting OVFMP 1B.3/1(A) / Stage I – Component 1: Flood Protecti Request for Quota Single Stage - One E Pending Impl Mooring base for icebreakers IBRD / 85240 on of the Middle and Lower Post Open - National 29,900.00 0.00 2022-05-09 2022-09-08 2023-06-30 tions nvelope ementation – compensatory planting Odra CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 5.4 / Design and Constructio n Supervision for works, Proj Component 1: Flood Protecti ect Management, Technical A Quality And Cost- Open - Internationa IBRD / 85240 on of the Middle and Lower Prior 0.00 36,732,800.12 Signed 2016-11-07 2016-11-09 ssistance and Training, Tech Based Selection l Odra nical Support for the Project and Strengthening of PIU?s In stitutional Capacity 5.3 / Design and Constructio n Supervision for works, Proj Component 1: Flood Protecti ect Management, Technical A Quality And Cost- Open - Internationa IBRD / 85240 on of the Middle and Lower Prior 0.00 7,203,890.85 Signed 2017-03-07 2017-03-16 ssistance and Training, Tech Based Selection l Odra nical Support for the Project and Strengthening of PIU?s In stitutional Capacity 5.2 / Design and Constructio n Supervision for works, Proj Component 1: Flood Protecti ect Management, Technical A Quality And Cost- Open - Internationa IBRD / 85240 on of the Middle and Lower Prior 0.00 16,887,334.63 Signed 2017-07-18 2017-07-19 ssistance and Training, Tech Based Selection l Odra nical Support for the Project and Strengthening of PIU?s In stitutional Capacity. OVFMP 5.7.1 / A concept for implementing the FRMP in th Component 1: Flood Protecti Quality And Cost- Open - Internationa e Upper Vistula sub-basin in t IBRD / 85240 on of the Middle and Lower Prior 0.00 3,120,856.20 Signed 2019-04-24 2019-04-25 Based Selection l erms of prioritization of inves Odra tments, including flood prote ction of the city of Krak w. OVFMP 5.6 / The Master Plan for the B br River catchment area -The concept of implem Component 1: Flood Protecti Quality And Cost- Open - Internationa enting the FRMP in the B br R IBRD / 85240 on of the Middle and Lower Prior 0.00 1,162,618.70 Signed 2018-11-28 2018-12-07 Based Selection l iver catchment area in terms Odra of the identification of invest ment priorities in the water r egion of the Middle Odra Riv er. OVFMP 5.8.1 / Katy-Myscowa . Update of the technical solu tions concept for the constru Component 5: Project mana Quality And Cost- ction of a reservoir, including IBRD / 85240 Post Open - National 1,300,000.00 0.00 Canceled 2020-04-30 2020-05-21 2020-07-04 2020-08-01 2020-08-31 2020-10-05 2020-11-09 2021-05-31 gement and studies Based Selection e.g.: results of hydraulic mod elling dated 2019, previously identified geological conditio ns, and their potential updat e. Page 4 OVFMP 5.8.2 / Katy-Myscowa . Development of surface arc haeological survey, including Component 5: Project mana Consultant Qualifi determination of a potential r IBRD / 85240 Post Open - National 377,000.00 0.00 Canceled 2020-07-30 2020-08-20 2020-10-03 2020-11-02 2021-01-30 2021-06-30 gement and studies cation Selection ange of archaeological recov ery excavations prior to impl ementation of the investmen t, along with sapper survey OVFMP 5.8.3 / Kąty-Myscowa . Development of local spatia l development plans for the a rea covering the reservoir’s b Component 5: Project mana Consultant Qualifi owl and areas needed for res IBRD / 85240 Post Open - National 624,000.00 0.00 Canceled 2020-09-01 2020-09-22 2020-11-05 2020-12-05 2020-12-30 2022-05-30 gement and studies cation Selection ettlements within the Comm une of Nowy Żmigród and th e Commune of Krempna, or o f a decision on location of the pp investment, OVFMP 5.8.4 / Kąty-Myscowa . Development of the Land A cquisition and Resettlement Component 5: Project mana Least Cost Selecti IBRD / 85240 Post Open - National 1,248,000.00 0.00 Canceled 2021-01-13 2021-02-03 2021-03-19 2021-04-16 2021-05-16 2021-06-20 2021-07-25 2022-06-30 Action Plan with estimated e gement and studies on valuation of land properties a nd vegetation, and with land replacement documentation OVFMP 5.8.5 / Kąty-Myscowa . Development of a cost and Component 5: Project mana Consultant Qualifi IBRD / 85240 Post Open - National 468,000.00 0.00 Canceled 2022-04-20 2022-05-11 2022-06-24 2022-07-24 2022-10-20 2023-06-22 benefits analysis for impleme gement and studies cation Selection ntation of the investment OVFMP 5.8.6 / Kąty-Myscowa Component 5: Project mana Consultant Qualifi . Development of the Environ IBRD / 85240 Post Open - National 468,000.00 0.00 Canceled 2021-10-18 2021-11-08 2021-12-27 2022-01-11 2022-02-21 2023-02-21 gement and studies cation Selection mental Management Plan OVFMP 5.8.7 / Kąty-Myscowa Component 5: Project mana Quality And Cost- IBRD / 85240 Prior Open - National 6,253,000.00 0.00 Canceled 2021-11-16 2021-12-07 2022-01-20 2022-02-17 2022-03-19 2022-04-23 2022-05-28 2023-06-23 . Development of a constructi gement and studies Based Selection on design. OVFMP 5.2/KR / Design and Construction Supervision for works, Project Management, Component 5: Project mana Quality And Cost- Open - Internationa IBRD / 85240 Prior 12,233,000.00 6,624,550.76 Signed 2020-11-04 2020-11-04 2020-11-04 2020-11-04 2020-11-04 2020-11-04 2022-04-12 2020-11-04 2017-07-20 2023-07-16 Technical Assistance and Trai gement and studies Based Selection l ning, Technical Support for t he Project and Strengthening of PIU’s Institutional Capacity . OVFMP 5.2/RZ / Design and Construction Supervision for works, Project Management, Component 5: Project mana Quality And Cost- Open - Internationa IBRD / 85240 Prior 10,829,000.00 5,059,982.01 Signed 2020-11-04 2020-11-04 2020-11-04 2020-11-04 2020-11-04 2020-11-04 2022-04-12 2020-11-04 2017-07-20 2023-07-16 Technical Assistance and Trai gement and studies Based Selection l ning, Technical Support for t he Project and Strengthening of PIU’s Institutional Capacity . OVFMP 5.2/KI / Design and C onstruction Supervision for w orks, Project Management, T Component 5: Project mana Quality And Cost- Open - Internationa IBRD / 85240 Prior 3,757,000.00 4,623,504.38 Signed 2020-11-04 2020-11-04 2020-11-04 2020-11-04 2020-11-04 2020-11-04 2022-04-12 2020-11-04 2017-07-19 2023-07-16 echnical Assistance and Train gement and studies Based Selection l ing, Technical Support for the Project and Strengthening of PIU’s Institutional Capacity. OVFMP 5.3/WR / Design and Construction Supervision for works, Project Management, Component 5: Project mana Quality And Cost- Open - Internationa IBRD / 85240 Prior 5,538,000.00 4,701,895.20 Signed 2020-11-04 2020-11-04 2020-11-04 2020-11-04 2020-11-04 2020-11-04 2022-05-19 2020-11-04 2017-03-20 2023-08-16 Technical Assistance and Trai gement and studies Based Selection l ning Technical Support for th e Project and Strengthening of PIU's Institutional Capacity . OVFMP 5.3/SZ / Design and Construction Supervision for works, Project Management, Component 5: Project mana Quality And Cost- Open - Internationa IBRD / 85240 Prior 2,756,000.00 3,206,497.49 Signed 2020-11-04 2020-11-04 2020-11-04 2020-11-04 2020-11-04 2020-11-04 2022-04-06 2020-11-04 2017-03-16 2023-08-16 Technical Assistance and Trai gement and studies Based Selection l ning Technical Support for th e Project and Strengthening of PIU's Institutional Capacity . OVFMP 5.4/SZ / Design and Construction Supervision for works, Project Management, Component 5: Project mana Quality And Cost- Open - Internationa IBRD / 85240 Prior 19,916,000.00 13,728,303.31 Signed 2020-11-04 2020-11-04 2020-11-04 2020-11-04 2020-11-04 2020-11-04 2021-12-10 2020-11-04 2016-11-10 2023-05-16 Technical Assistance and Trai gement and studies Based Selection l ning Technical Support for th e Project and Strengthening of PIU's Institutional Capacity . OVFMP 5.4/WR / Design and Construction Supervision for works, Project Management, Component 5: Project mana Quality And Cost- Open - Internationa IBRD / 85240 Prior 27,353,047.50 29,194,999.99 Signed 2020-11-04 2020-11-04 2020-11-04 2020-11-04 2020-11-04 2020-11-04 2021-10-13 2020-11-04 2016-11-09 2023-05-16 Technical Assistance and Trai gement and studies Based Selection l ning Technical Support for th e Project and Strengthening of PIU's Institutional Capacity . OVFMP-5.8.1 / Katy-Myscow a Support at the stage of the bidding procedure for the de velopment of bid documentat Component 5: Project mana Consultant Qualifi Open - Internationa Pending Impleme IBRD / 85240 Post 182,000.00 0.00 2021-02-28 2021-03-21 2021-05-04 2021-05-19 2021-05-31 2021-12-30 ion for the implementation of gement and studies cation Selection l ntation complete technical documen tation (including construction and executive design) and pr eparation of necessary docu ments OVFMP-5.8.2A / Katy-Mysco wa Development of surface a rchaeological survey, includi Component 5: Project mana Consultant Qualifi Open - Internationa IBRD / 85240 Post 65,000.00 0.00 Canceled 2021-03-10 2021-09-29 2021-03-19 2021-12-06 2021-04-20 2022-01-10 2021-05-15 2021-05-31 2021-12-30 ng determination of a potenti gement and studies cation Selection l al range of archaeological re covery excavations prior to i mplementation of the invest ment OVFMP-5.8.2B / Katy-Mysco Component 5: Project mana Consultant Qualifi Open - Internationa wa IBRD / 85240 Post 208,000.00 0.00 Canceled 2021-03-03 2021-06-22 2021-03-17 2021-07-19 2021-04-21 2021-09-17 2021-05-13 2021-05-31 2023-06-30 gement and studies cation Selection l Geological and geotechnical services OVFMP-5.8.2C / Kąty-Mysco Component 5: Project mana Consultant Qualifi Open - Internationa IBRD / 85240 Post 208,000.00 0.00 Canceled 2021-03-08 2021-03-15 2021-04-22 2021-05-12 2021-05-31 2021-12-30 wa gement and studies cation Selection l Sapper survey OVFMP-5.8.3A / Kąty-Mysco Component 5: Project mana Consultant Qualifi Open - Internationa wa IBRD / 85240 Post 312,000.00 236,277.89 Signed 2021-03-09 2021-06-02 2021-03-19 2021-06-29 2021-04-21 2021-07-23 2021-05-01 2021-10-29 2021-05-27 2021-11-08 2022-12-30 gement and studies cation Selection l Informational activities, infor mation point Page 5 OVFMP-5.8.6 / Katy-Myscow a Development of a construc tion design and of a detailed design, including bills of qua Component 5: Project mana Quality And Cost- Open - Internationa IBRD / 85240 Prior 6,253,000.00 0.00 Canceled 2021-11-02 2021-11-23 2022-01-06 2022-02-03 2022-03-05 2022-04-09 2022-05-14 2023-06-30 ntities and estimates for the gement and studies Based Selection l reservoir, along with: protecti on of landslips, design of a fis h pass, access roads, design for demolition of buildings OVFMP 5.7.2 / Retention acti vities program as an element of flood risk management in t Component 5: Project mana Quality And Cost- Open - Internationa IBRD / 85240 Prior 6,253,000.00 0.00 Under Review 2021-11-25 2022-03-14 2021-12-16 2022-04-06 2022-01-29 2022-02-26 2022-03-28 2022-05-02 2022-07-01 2023-12-03 he Upper Western Vistula an gement and studies Based Selection l d Upper Eastern Vistula wate r region between Kraków and Zawichost – STAGE I OVFMP-5.8.5 / Construction of the Katy-Myscowa water r eservoir on the Wisloka River . Component 5: Project mana Consultant Qualifi Open - Internationa Pending Impleme IBRD / 85240 Post 364,000.00 0.00 2021-06-01 2021-06-22 2021-08-05 2021-09-04 2021-09-30 2023-08-31 Adjustment of a cost and ben gement and studies cation Selection l ntation efits analysis for implementa tion of the investment to the standards, including standar ds of financing institution OVFMP-5.8.4 / Construction of the Katy-Myscowa water r eservoir on the Wisloka River Component 5: Project mana Quality And Cost- Open - Internationa Pending Impleme IBRD / 85240 Post 1,560,000.00 0.00 2022-01-12 2022-02-02 2022-03-18 2022-04-15 2022-05-15 2022-06-19 2022-07-24 2023-07-31 . Development of environme gement and studies Based Selection l ntation ntal and social standards bas ed on the standards of the W orld Bank/financial institution . OVFMP-5.8.3 / Construction of the Katy-Myscowa water r eservoir on the Wisloka River Component 5: Project mana Consultant Qualifi Open - Internationa Pending Impleme . IBRD / 85240 Post 468,000.00 0.00 2022-04-13 2022-05-04 2022-06-27 2022-07-27 2022-08-26 2023-08-31 gement and studies cation Selection l ntation Development of local spatial development plans for the ar ea covering the reservoir’s b owl and areas needed for res ettlements. OVFMP_5.8.6 / Construction of the Katy-Myscowa water r eservoir on the Wisloka River Component 5: Project mana Quality And Cost- Open - Internationa . Development of a constructi IBRD / 85240 Prior 14,062,500.00 0.00 Under Review 2022-04-25 2022-05-16 2022-05-31 2022-06-08 2022-06-16 2022-06-24 2022-07-31 2023-11-30 gement and studies Based Selection l on design and of a detailed d esign, including bills of quant ities and estimates for the re servoir. OVFMP_5.8.2A / Constructio n of the Katy-Myscowa water reservoir on the Wisloka Rive r. Development of surface ar Component 5: Project mana Consultant Qualifi Open - Internationa Pending Impleme IBRD / 85240 Post 104,000.00 0.00 2022-04-19 2022-04-28 2022-05-25 2022-06-10 2022-07-15 2023-04-18 chaeological survey, includin gement and studies cation Selection l ntation g determination of a potentia l range of archaeological rec overy excavations prior to im plementation of the investme nt. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 1/19/2019 / PROJECT DIRECT OR AT THE ODRA-VISTULA FL OOD MANAGEMENT PROJECT Component 1: Flood Protecti Individual Consult COORDINATION UNIT UNDER IBRD / 85240 on of the Middle and Lower Prior Open 0.00 779,003.70 Signed 2019-04-22 2019-05-06 ant Selection THE ODRA RIVER BASIN FLO Odra OD PROTECTION PROJECT AN D THE ODRA-VISTULA FLOOD MANAGEMENT PROJECT OVFMP 5.1 (31) / Assistant t Component 5: Project mana Individual Consult IBRD / 85240 Post Open 143,000.00 132,170.29 Signed 2020-06-02 2020-06-01 2020-07-21 2020-07-24 2020-08-11 2020-09-21 2020-09-15 2020-09-21 2023-12-18 o the Project Director and Se gement and studies ant Selection cretary OVFMP 5.1 (10.1) / Resettle Component 5: Project mana Individual Consult IBRD / 85240 Post Open 208,000.00 183,568.99 Signed 2020-06-02 2020-06-01 2020-07-21 2020-07-23 2020-08-11 2020-08-27 2020-09-15 2020-08-27 2023-12-11 ment and Land Acquisition S gement and studies ant Selection pecialist OVFMP 5.1 (6.1) / Financial a Component 5: Project mana Individual Consult IBRD / 85240 Post Direct 207,156.00 253,666.05 Signed 2020-06-17 2020-06-01 2020-06-27 2020-09-07 2020-07-04 2020-09-04 2020-08-01 2020-09-04 2023-12-15 nd Accounting Specialist gement and studies ant Selection OVFMP 5.1 (27.1) / IPE - Me Component 5: Project mana Individual Consult IBRD / 85240 Post Open 50,138.00 56,371.50 Signed 2020-06-30 2020-07-30 2020-09-03 2020-10-01 2020-09-24 2020-11-30 2020-10-29 2020-11-30 2023-12-15 mbers of Panel Expert gement and studies ant Selection OVFMP 5.1 (27.2) / IPE - Me Component 5: Project mana Individual Consult IBRD / 85240 Post Open 58,138.00 18,767.52 Signed 2020-06-30 2020-07-30 2020-09-03 2020-10-01 2020-09-24 2020-11-30 2020-10-29 2020-11-30 2023-12-15 mbers of Panel Expert gement and studies ant Selection OVFMP 5.1 (12.1) / Hydrotec Component 5: Project mana Individual Consult IBRD / 85240 Post Open 247,000.00 0.00 Canceled 2020-09-06 2021-03-23 2020-10-18 2020-10-19 2020-10-25 2023-12-11 hnic Specialist gement and studies ant Selection OVFMP 5.1 (4.1) / Financial C Component 5: Project mana Individual Consult Under Implement IBRD / 85240 Post Open 182,000.00 0.00 2020-11-22 2020-11-24 2021-02-08 2021-02-09 2021-03-07 2023-12-15 ontroll Specialist gement and studies ant Selection ation OVFMP 5.1 (32) / Specialist f or coordinating the process o Component 5: Project mana Individual Consult IBRD / 85240 Post Open 182,000.00 167,478.89 Signed 2020-11-22 2021-06-23 2021-02-15 2021-06-21 2021-03-08 2021-08-02 2021-03-21 2021-08-02 2023-12-15 f proceedings of the 4B Subc gement and studies ant Selection omponent as part of the imp lementation of OVFMP OVFMP 5.1 (18.1) / New PR S Component 5: Project mana Individual Consult IBRD / 85240 Post Open 183,375.00 99,363.94 Signed 2021-07-11 2021-06-22 2021-08-22 2021-09-29 2021-09-12 2021-11-02 2021-09-18 2021-11-02 2023-12-15 pecialist gement and studies ant Selection OVFMP 5.1 (12.1') / Contract Component 5: Project mana Individual Consult Under Implement IBRD / 85240 Post Open 208,000.00 0.00 2021-07-18 2021-07-26 2021-09-12 2021-09-22 2021-09-30 2023-12-15 s Specialist gement and studies ant Selection ation OVFMP 5.3(A) / Author's sup Component 5: Project mana IBRD / 85240 Post Direct Selection Direct 76,700.00 121,007.92 Signed 2021-08-17 2021-08-22 2021-09-12 2019-04-24 2023-03-07 ervision for the Contract 1C.1 gement and studies Page 6