Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: May 2018]: Revision of Updated Procurement Plan, July 2018] 2. Date of General Procurement Notice: Aug 13, 2018 3. Period covered by this procurement plan: The procurement period of project covered from year September 2018 to December 2019 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB, NCB, Shopping, and DC (Goods and Above US$ All non-consulting services) 2,000,000 2. ICB, NCB, Shopping, and DC (Works / Above US$ All supply and installation of plant and 10,000,000 equipment) 2. Prequalification. Bidders for Not applicable shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Procurement Management Manual (PMM) 5. Any Other Special Procurement Arrangements: Not applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme August 21, 2018 No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 27 1 No Prior of the NCB (Works) Summary 17.53 6 No Post of the NCB (Works) Summary 5.94 1 No Prior of the NCB (Goods) Summary 2.52 3 No Post of the NCB (Goods) Summary 0.058 1 No Post of the Shopping (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 1,000,000 All 2. Single Source (Firms) Above US$ 1,000,000 All 3. Individual Consultant Above US$ 300,000 All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million August 21, 2018 Summary 2.01 2 Prior of number of contracts that will be let under QCBS Summary 0.97 2 Post of number of contracts that will be let under QCBS Summary 1.44 8 Post CQS of number of contracts that will be let under other methods August 21, 2018 PROCUREMENT China : Anhui Aged Care System Demonstration Project PLAN General Information Country: China 2018-08-23 Bank’s Approval Date of the Original Procurement Plan: 2022-06-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154716 GPN Date: 2018-08-13 Project Name: Anhui Aged Care System Demonstration Project Loan / Credit No: IBRD / 88820 Anhui Aged Care PMO Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned JJYL-LA-C1 / Civil engineering Strengthening Community-b Single Stage - One E Pending Imp 2020-09-0 1 of home-based aged care s IBRD / 88820 ased and Home-based Care Post Request for Bids Open - National 305,600.00 0.00 2018-12-01 2018-12-06 2019-01-17 2019-02-16 2019-03-23 nvelope lementation 1 ervice in Lu'an (Jin'an District Services ) JGYL-NG-C2 / Civil engineeri Strengthening the Delivery a ng of Longevity Fairyland of t Single Stage - One E Pending Imp 2022-09-0 IBRD / 88820 nd Management of Nursing Post Request for Bids Open - National 844,000.00 0.00 2019-10-01 2019-10-06 2019-11-17 2019-12-17 2020-01-21 he Service Center for Social nvelope lementation 1 Care Welfare in Ningguo City JJYL-AQ-C1 / The first A contr Strengthening Community-b act of the renovation and ext Single Stage - One E Pending Imp 2020-12-3 IBRD / 88820 ased and Home-based Care Post Request for Bids Open - National 1,139,857.30 0.00 2019-06-23 2019-06-28 2019-08-09 2019-09-08 2019-10-20 ension project of home-base nvelope lementation 1 Services d aged care service station in Anqing JJYL-LA-C2 / Civil engineering Strengthening Community-b Single Stage - One E Pending Imp 2021-05-1 B of home-based aged care s IBRD / 88820 ased and Home-based Care Post Request for Bids Open - National 341,622.42 0.00 2018-12-01 2019-09-17 2019-10-29 2019-10-29 2019-12-03 nvelope lementation 4 ervice in Lu'an (Yu'an District Services ) JJYL-AQ-C3/4 / The second co Strengthening Community-b ntract of the renovation and Single Stage - One E Pending Imp 2021-07-2 IBRD / 88820 ased and Home-based Care Post Request for Bids Open - National 1,921,626.12 0.00 2019-12-29 2020-01-15 2020-02-26 2020-03-27 2020-05-08 extension project of home-ba nvelope lementation 0 Services sed aged care service station in Anqing JJYL-AQ-C2 / The first B contr Strengthening Community-b act of the renovation and ext Single Stage - One E Pending Imp 2020-12-3 IBRD / 88820 ased and Home-based Care Post Request for Bids Open - National 1,496,021.52 0.00 2019-06-23 2019-06-28 2019-08-09 2019-09-08 2019-10-20 ension project of home-base nvelope lementation 1 Services d aged care service station in Anqing JGYL-LA-C1 / Main works of t Strengthening Community-b Single Stage - One E 22,585,500.0 2023-10-0 he medical synthesis building IBRD / 88820 ased and Home-based Care Prior Request for Bids Open - National 0.00 Canceled 2020-06-26 2020-07-17 2020-07-11 2020-07-21 2020-08-22 2020-08-25 2020-09-21 2020-09-28 2020-10-26 nvelope 0 5 of Lu'an Chinese Medicine Ho Services spital JGYL-LA-C1A / Main works of Strengthening Community-b Single Stage - One E 22,585,500.0 2024-01-0 the medical synthesis buildin IBRD / 88820 ased and Home-based Care Prior Request for Bids Open - National 0.00 Canceled 2020-09-30 2020-09-30 2020-10-15 2020-10-23 2020-11-26 2020-11-11 2020-12-26 2020-11-19 2021-01-30 nvelope 0 9 g of Lu'an Chinese Medicine Services Hospital JGYL-LA-C1B / Main works of Strengthening Community-b Single Stage - One E 22,585,500.0 23,773,244. 2024-03-1 the medical synthesis buildin IBRD / 88820 ased and Home-based Care Prior Request for Bids Open - National Signed 2020-12-08 2020-12-09 2020-12-23 2020-12-09 2021-02-03 2020-12-10 2021-03-05 2020-12-17 2021-04-09 2020-12-31 nvelope 0 05 8 g of Lu'an Chinese Medicine Services Hospital JGYL-AQ-C1 / Nursing Home Strengthening the Delivery a Single Stage - One E Pending Imp 2022-01-1 of Anqing No.1 People's Hosp IBRD / 88820 nd Management of Nursing Post Request for Bids Open - National 7,801,502.00 0.00 2021-03-31 2021-04-05 2021-05-17 2021-06-16 2021-07-21 nvelope lementation 7 ital's -- decoration works Care JGYL-AQ-C2 / Nursing Home Strengthening Community-b Single Stage - One E Pending Imp 2022-01-2 of Anqing No.1 People's Hosp IBRD / 88820 ased and Home-based Care Post Request for Bids Open - National 1,239,253.00 0.00 2021-04-30 2021-05-15 2021-06-12 2021-06-26 2021-07-31 nvelope lementation 7 ital's — Municipal greening w Services ork JGYL-NG-C1 / Civil engineeri Request for Bids - Strengthening the Delivery a ng of "upgrading project of S Single Stage - One E Small Works SPD Pending Imp 2022-03-0 IBRD / 88820 nd Management of Nursing Post Request for Bids Open - National 4,034,400.00 0.00 2021-10-15 2021-10-20 2021-12-01 2021-12-31 2022-02-04 ervice Center for Social Welf nvelope (1 envelope proce lementation 6 Care are in Ningguo City" ss) JGYL-XZ-C1 / Xuancheng Xua Request for Bids - Strengthening the Delivery a nzhou District Social Welfare Single Stage - One E Small Works SPD 10,048,500.0 Under Imple 2022-12-2 IBRD / 88820 nd Management of Nursing Post Request for Bids Open - National 0.00 2021-11-09 2021-11-15 2021-11-14 2021-12-26 2021-12-17 2022-01-25 2021-12-17 2022-03-01 Home relocation and reconst nvelope (1 envelope proce 0 mentation 6 Care ruction project - civil works ss) Request for Bids - JGYL-AQ-C1A / Nursing Home Strengthening the Delivery a Single Stage - One E Works (without pr 6,219,762.8 Under Imple 2022-09-1 of Anqing No.1 People's Hosp IBRD / 88820 nd Management of Nursing Post Request for Bids Open - National 9,222,400.00 2021-11-26 2021-12-10 2021-12-01 2022-01-12 2022-01-15 2022-02-11 2022-01-15 2022-03-18 nvelope equalification) SP 8 mentation 4 ital's -- decoration works Care D GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual JJYL-AQ-G1 / Equipment 1 of Strengthening Community-b the home-based aged care s Single Stage - One E Under Imple IBRD / 88820 ased and Home-based Care Post Request for Bids Open - National 986,100.00 0.00 2018-12-01 2018-12-06 2019-01-17 2019-01-04 2019-02-16 2019-01-04 2019-03-23 2021-02-01 ervice station in Anqing (offic nvelope mentation Services e,fitness and entertainment equipment) JJYL-AQ-G2 / Equipment 2 of Strengthening Community-b Single Stage - One E Under Imple the home-based aged care s IBRD / 88820 ased and Home-based Care Post Request for Bids Open - National 768,600.00 0.00 2018-12-01 2018-12-06 2019-01-17 2019-01-04 2019-02-16 2019-03-23 2021-02-01 nvelope mentation ervice station in Anqing (furn Services iture) JJYL-AQ-G3 / Equipment 3 of Strengthening Community-b Single Stage - One E Under Imple the home-based aged care s IBRD / 88820 ased and Home-based Care Post Request for Bids Open - National 768,600.00 0.00 2018-12-01 2018-12-06 2019-01-17 2019-01-04 2019-02-16 2019-03-23 2021-02-01 nvelope mentation ervice station in Anqing (elec Services trical appliance) JGYL-AQ-G1 / Nursing Home Strengthening the Delivery a Request for Quota Single Stage - One E Pending Impl of Anqing No.1 People's Hosp IBRD / 88820 nd Management of Nursing Post Open - National 58,000.00 0.00 2019-06-06 2019-08-01 2019-10-01 tions nvelope ementation ital's -- ambulance Care JGYL-AQ-G2 / Nursing Home Strengthening the Delivery a Single Stage - One E Pending Impl of Anqing No.1 People's Hosp IBRD / 88820 nd Management of Nursing Prior Request for Bids Open - National 5,937,100.00 0.00 2019-06-01 2019-06-06 2019-07-18 2019-08-17 2019-09-21 2022-01-01 nvelope ementation ital's -- medical equipment pr Care ocurement Page 1 JJYL-AQ-G4 / Air conditioners Strengthening Community-b Single Stage - One E of the first batch of 40 home- IBRD / 88820 ased and Home-based Care Post Request for Bids Open - National 186,500.00 0.00 Canceled 2020-06-24 2020-06-29 2020-07-27 2020-08-10 2020-09-07 2021-01-05 nvelope based aged care service stati Services on in Anqing JJYL-AQ-G4A / Air conditioner Strengthening Community-b Request for Quota Single Stage - One E s of the first batch of 40 hom IBRD / 88820 ased and Home-based Care Post Limited 186,500.00 145,625.84 Signed 2021-01-29 2021-06-24 2021-03-26 2021-08-06 2021-07-24 tions nvelope e-based aged care service st Services ation in Anqing JJYL-AQ-G8 / Installation of el evator at the home-based a Strengthening Community-b Single Stage - One E ged care service station of H IBRD / 88820 ased and Home-based Care Post Request for Bids Open - National 43,000.00 0.00 Canceled 2021-04-30 2021-05-05 2021-06-02 2021-06-16 2021-07-14 2021-11-11 nvelope eping community in laofeng t Services own of Anqing Economic Dev elopment Zone JJYL-AQ-G8A / Installation of elevator at the home-based a Strengthening Community-b Request for Quota Single Stage - One E Pending Impl ged care service station of H IBRD / 88820 ased and Home-based Care Post Limited 43,000.00 0.00 2021-05-05 2021-06-30 2021-10-28 tions nvelope ementation eping community in laofeng t Services own of Anqing Economic Dev elopment Zone JJYL-LA-G1 / Indoor equipme nt, office equipment and air c Strengthening Community-b Single Stage - One E Pending Impl onditioning equipment of the IBRD / 88820 ased and Home-based Care Post Request for Bids Open - National 240,600.00 0.00 2021-10-25 2021-10-30 2021-12-11 2022-01-10 2022-02-14 2022-06-14 nvelope ementation first contract of home-based Services aged care service station in L u'an JJYL-AQ-G5-G7 / Office and e ntertainment equipment and Strengthening Community-b Single Stage - One E electrical appliances of the s IBRD / 88820 ased and Home-based Care Post Request for Bids Open - National 1,236,600.00 1,089,545.08 Signed 2022-01-08 2021-04-15 2022-01-13 2022-02-10 2021-09-28 2022-03-12 2021-09-28 2022-04-16 2021-10-20 2022-10-13 nvelope econd batch of home-based Services aged care service station in Anqing JJYL-AQ-G6 / Furniture of the Strengthening Community-b Single Stage - One E second batch of home-based IBRD / 88820 ased and Home-based Care Post Request for Bids Open - National 432,800.00 330,062.22 Signed 2022-01-08 2021-07-29 2022-01-13 2022-02-10 2021-09-28 2022-03-12 2021-09-28 2022-04-16 2021-10-27 2022-10-13 nvelope aged care service station in Services Anqing NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual JJYL-AQ-NS1 / Audit of civil e Project Management, Monito Request for Quota Single Stage - One E Pending Impl ngineering project of Anqing IBRD / 88820 Post Open - National 21,160.00 0.00 2020-06-28 2020-08-23 2021-06-19 ring and Evaluation tions nvelope ementation home care service station JGYL-AQ-NS1 / Project audit Project Management, Monito Request for Quota Single Stage - One E Pending Impl of Nursing Home of Anqing N IBRD / 88820 Post Open - National 45,202.00 0.00 2021-04-05 2021-05-31 2021-06-24 ring and Evaluation tions nvelope ementation o.1 People's Hospital's JJYL-AQ-NS4 / Anqing Munici pal government purchases lo w-income home-based aged Project Management, Monito Request for Quota Single Stage - One E Pending Impl IBRD / 88820 Post Limited 31,200.00 0.00 2021-07-28 2021-09-22 2022-09-22 care service and third-party ring and Evaluation tions nvelope ementation acceptance services of visitin g service for the elderly, emp ty nest and living alone FWZC-NS3 / Pilot Ability Ass Supporting the Development Request for Quota Pending Impl essment and Needs Assessm IBRD / 88820 of Government Stewardship Post 22,335.00 0.00 2022-06-20 2022-07-04 2022-08-15 tions ementation ent for the Elderly (Xuanchen Capacity g) FWZC-NS2 / Pilot Ability Ass Supporting the Development Request for Quota Single Stage - One E Pending Impl essment and Needs Assessm IBRD / 88820 of Government Stewardship Post Open - National 22,335.00 0.00 2022-06-20 2022-07-04 2022-08-15 tions nvelope ementation ent for the Elderly (Hefei) Capacity FWZC-NS4 / Pilot Ability Ass Supporting the Development Request for Quota Single Stage - One E Pending Impl essment and Needs Assessm IBRD / 88820 of Government Stewardship Post Open - National 22,335.00 0.00 2022-06-20 2022-08-15 2023-02-11 tions nvelope ementation ent for the Elderly (Anqing) Capacity FWZC-NS5 / Pilot Ability Ass Supporting the Development Request for Quota Single Stage - One E Pending Impl essment and Needs Assessm IBRD / 88820 of Government Stewardship Post Open - National 22,335.00 0.00 2022-06-20 2022-07-06 2022-08-15 tions nvelope ementation ent for the Elderly (Chuzhou) Capacity FWZC-NS6 / Pilot Ability Ass Supporting the Development Request for Quota Single Stage - One E Pending Impl essment and Needs Assessm IBRD / 88820 of Government Stewardship Post Open - National 22,335.00 0.00 2022-06-17 2022-07-04 2022-08-15 tions nvelope ementation ent for the Elderly (Fuyang) Capacity CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FWZC-S3 / Capacity building Supporting the Development Consultant Qualifi Pending Impleme IBRD / 88820 Post Open - National 217,500.00 0.00 2018-11-01 2018-11-22 2019-01-05 2019-02-04 2019-03-11 2020-12-01 of aged care professionals 1 of Government Stewardship cation Selection ntation Capacity FWZC-S4 / Capacity building Supporting the Development Consultant Qualifi Pending Impleme IBRD / 88820 Post Open - National 217,500.00 0.00 2019-01-01 2019-01-22 2019-03-07 2019-04-06 2019-05-11 2021-02-01 of aged care professionals 2 of Government Stewardship cation Selection ntation Capacity FWZC-S5 / Design of the co Supporting the Development Quality And Cost- Open - Internationa Pending Impleme mprehensive management s IBRD / 88820 of Government Stewardship Post 997,800.00 0.00 2018-12-01 2018-12-22 2019-02-04 2019-03-04 2019-04-03 2019-05-08 2019-06-12 2020-03-01 Based Selection l ntation ystem of the provinical aged Capacity care service JJYL-AQ-S1 / Community-bas Strengthening Community-b Consultant Qualifi Under Implement ed aged care service station i IBRD / 88820 ased and Home-based Care Post Open - National 174,000.00 0.00 2018-09-01 2018-08-28 2018-09-22 2018-11-05 2018-09-25 2018-12-05 2018-11-20 2019-01-09 2021-10-01 cation Selection ation n Anqing -- Design Services NLJQ-S1 / Project pilots revie Project Management, Monito Consultant Qualifi Pending Impleme IBRD / 88820 Post Open - National 145,000.00 0.00 2019-01-01 2019-01-22 2019-03-07 2019-04-06 2019-05-11 2023-06-01 w and experience exchange ( ring and Evaluation cation Selection ntation 1) Project Management, Monito Consultant Qualifi Pending Impleme NLJQ-S4 / Satisfaction survey IBRD / 88820 Post Open - National 101,500.00 0.00 2018-11-01 2018-11-22 2019-01-05 2019-02-04 2019-03-11 2023-06-01 ring and Evaluation cation Selection ntation FWZC-S1 / Functional ability Supporting the Development Quality And Cost- Open - Internationa Pending Impleme IBRD / 88820 Post 623,600.00 0.00 2019-08-09 2019-08-30 2019-10-13 2019-11-10 2019-12-10 2020-01-14 2020-02-18 2022-08-09 and needs assessment for th of Government Stewardship Based Selection l ntation e elderly Capacity Page 2 FWZC-S2 / Aged care service Supporting the Development Quality And Cost- Open - Internationa Pending Impleme IBRD / 88820 Post 348,000.00 0.00 2019-08-09 2019-08-30 2019-10-13 2019-11-10 2019-12-10 2020-01-14 2020-02-18 2023-06-09 standard system of Government Stewardship Based Selection l ntation Capacity JJYL-AQ-S2 / Construction su Strengthening Community-b Consultant Qualifi pervisor of the community-b IBRD / 88820 ased and Home-based Care Post Open - National 135,400.00 0.00 Under Review 2019-06-07 2019-07-26 2019-06-28 2019-08-11 2019-09-10 2019-10-15 2022-10-31 cation Selection ased aged care service statio Services n in Anqing NLJQ-S7 / Compilation of gui Project Management, Monito Consultant Qualifi Under Implement delines for purchasing basic IBRD / 88820 Post Open - National 72,500.00 0.00 2019-06-28 2019-07-08 2019-07-19 2019-09-01 2019-10-01 2019-11-12 2020-12-31 ring and Evaluation cation Selection ation aged care service NLJQ-S6 / Resettlement moni Project Management, Monito Consultant Qualifi Under Implement IBRD / 88820 Post Open - National 116,000.00 0.00 2018-11-01 2019-10-22 2018-11-22 2019-01-05 2019-02-04 2019-03-11 2023-06-01 toring and public consultatio ring and Evaluation cation Selection ation n NLJQ-S5 / Environment moni Project Management, Monito Consultant Qualifi Under Implement IBRD / 88820 Post Open - National 116,000.00 0.00 2018-11-01 2019-10-23 2018-11-22 2019-01-05 2019-02-04 2019-03-11 2023-06-01 toring ring and Evaluation cation Selection ation NLJQ-S3 / Selection of projec Project Management, Monito Quality And Cost- Open - Internationa IBRD / 88820 Prior 696,000.00 0.00 Canceled 2019-07-31 2020-07-07 2019-08-21 2020-07-07 2019-10-04 2020-09-04 2019-11-01 2019-12-01 2020-01-05 2020-02-09 2024-02-28 t management consulting fir ring and Evaluation Based Selection l m NLJQ-S2 / Tracking and Rese arch on the experimental poi Project Management, Monito Consultant Qualifi Under Implement IBRD / 88820 Post Open - National 59,700.00 0.00 2020-12-25 2020-12-17 2021-01-08 2021-02-21 2021-03-23 2021-04-27 2025-05-18 nts of reform and design of r ring and Evaluation cation Selection ation ural homes for the aged JGYL-AQ-S1 / Construction su Strengthening Community-b Consultant Qualifi Under Implement pervisor of Nursing Home of IBRD / 88820 ased and Home-based Care Post Open - National 90,400.00 0.00 2021-03-31 2021-04-07 2021-04-21 2021-06-04 2021-07-04 2021-08-08 2022-04-05 cation Selection ation Anqing No.1 People's Hospita Services l's NLJQ-S8 / Evaluation of the i mplementation effect of the Project Management, Monito Consultant Qualifi Under Implement IBRD / 88820 Post Open - National 38,600.00 0.00 2021-03-31 2021-03-16 2021-04-21 2021-06-04 2021-07-04 2021-08-15 2021-10-14 policy of Anhui Province to b ring and Evaluation cation Selection ation uild the Aged Care System (2 018-2020) action plan FWZC-S1A / Development of Strengthening Community-b Consultant Qualifi competency and needs asses IBRD / 88820 ased and Home-based Care Post Open - National 74,000.00 71,781.07 Signed 2021-06-20 2021-05-31 2021-07-11 2021-08-24 2022-06-01 2021-09-23 2021-07-12 2021-10-28 2021-07-13 2022-10-28 cation Selection sment toolkit for the elderly Services FWZC-S5A / The overall desi Strengthening Community-b gn of comprehensive informa Quality And Cost- Under Implement IBRD / 88820 ased and Home-based Care Post Open - National 407,000.00 0.00 2021-06-30 2021-06-02 2021-07-21 2021-09-03 2021-08-11 2021-10-01 2021-11-26 2021-10-31 2021-11-26 2021-12-05 2022-01-09 2022-08-07 tion system for the aged care Based Selection ation Services service in Anhui Province JGYL-NG-S1 / Supervision of Strengthening Community-b Consultant Qualifi the upgrading project of Serv IBRD / 88820 ased and Home-based Care Post Open - National 111,300.00 0.00 Under Review 2021-09-30 2021-11-09 2021-10-21 2021-12-04 2022-01-03 2022-02-07 2023-05-03 cation Selection ice Center for Social Welfare Services in Ningguo City NLJQ-S9 / Preparation of envi ronmental impact assessmen Project Management, Monito Consultant Qualifi Under Implement IBRD / 88820 Post Open - National 39,000.00 0.00 2021-12-12 2021-12-13 2022-01-02 2022-02-15 2022-03-17 2022-04-28 2022-07-27 t report of new projects adjus ring and Evaluation cation Selection ation ted in the medium term NLJQ-S10 / Preparation of fe Project Management, Monito Consultant Qualifi Under Implement asibility study report of new IBRD / 88820 Post Open - National 76,000.00 0.00 2021-12-12 2021-12-13 2022-01-02 2022-02-15 2022-03-17 2022-04-28 2022-05-07 ring and Evaluation cation Selection ation projects for medium-term adj ustment NLJQ-S11 / Preparation of so Project Management, Monito Consultant Qualifi Under Implement cial evaluation report of new IBRD / 88820 Post Open - National 39,000.00 0.00 2021-12-12 2021-12-13 2022-01-02 2022-02-15 2022-03-17 2022-04-28 2022-05-07 ring and Evaluation cation Selection ation projects for medium-term adj ustment JGYL-SZ-S1 / Transformation Strengthening the Delivery a Consultant Qualifi Under Implement and Upgrading Design of Rur IBRD / 88820 nd Management of Nursing Post Open - National 179,280.00 0.00 2022-06-10 2022-06-10 2022-06-18 2022-07-05 2022-07-10 2022-07-15 2023-12-01 cation Selection ation al Nursing Homes in Suzhou Care City NLJQ-S12 / Performance eval Supporting the Development Consultant Qualifi Pending Impleme uation of government purcha IBRD / 88820 of Government Stewardship Post Open - National 71,376.00 0.00 2022-06-23 2022-06-26 2022-07-18 2022-07-19 2022-07-22 2023-12-31 cation Selection ntation se of basic elderly care servic Capacity es INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3