PROCUREMENT PLAN (Textual Part) Project information: Mozambique, Economic Linkages for Diversification (P171664) Project Implementation agency: Ministry of Economy and Finance Date of the Procurement Plan: December 8, 2020 Period covered by this Procurement Plan: December 15, 2020 – June 30, 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Decree 5/2016, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations –Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable PROCUREMENT Mozambique : Economic Linkages for Diversification PLAN General Information Country: Mozambique 2020-12-08 Bank’s Approval Date of the Original Procurement Plan: 2022-06-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171664 GPN Date: 2021-09-16 Project Name: Economic Linkages for Diversification Loan / Credit No: IDA / D8100, / , IDA / V3550 Ministry of Economy and Finance - DNT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - MZ-MEF-DNT-278774-CW-RF Enabling elements to suppor Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2025-07-0 B / Construction of Integrated IDA / D8100 Post Request for Bids 3,000,000.00 0.00 2023-12-15 2023-12-20 2024-03-04 2024-05-03 2024-07-01 t economic linkages l nvelope (1 envelope proce lementation 1 Market for fish, vegetables a ss) nd fruits of Tete GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-MEF-DNT-208405-GO-RF Request for Quota Single Stage - One E IDA / D8100 Project Management Post Limited 50,000.00 170,880.81 Signed 2021-02-20 2021-10-08 2021-04-17 2022-01-31 2021-10-14 Q / IT and Electronic Equipme tions nvelope nt MZ-MEF-DNT-208408-GO-RF Request for Quota Single Stage - One E / Project Management Post Limited 25,000.00 0.00 Canceled 2021-03-05 2021-09-24 2021-04-30 2021-10-27 Q / Office Furniture tions nvelope MZ-MEF-DNT-208407-GO-RF Single Stage - One E Under Imple IDA / D8100 Project Management Post Request for Bids Open - National 120,000.00 261,899.00 2021-02-15 2021-12-14 2021-02-20 2021-12-14 2021-04-03 2022-01-20 2021-05-03 2022-04-19 2021-06-07 2021-12-04 B / Vehicle purchase nvelope mentation MZ-MEF-DNT-261314-GO-RF Request for Quota Single Stage - One E IDA / D8100 Project Management Post Limited 30,000.00 26,010.86 Signed 2021-11-10 2021-11-07 2022-01-03 2022-01-28 2022-03-04 Q / Supply of Office Furniture tions nvelope NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-MEF-DNT-248096-NC-RF Enabling elements to suppor Single Stage - One E Under Imple P / Design image of IPEME an IDA / D8100 Post Request for Bids Open - National 120,000.00 0.00 2021-10-31 2022-05-06 2021-11-05 2022-05-06 2021-12-17 2022-06-20 2022-01-16 2022-02-20 2022-08-19 t economic linkages nvelope mentation d communication campaign MZ-MEF-DNT-278783-NC-RF Request for Quota Single Stage - One E Pending Impl IDA / D8100 Project Management Post Limited 25,000.00 0.00 2022-07-20 2022-10-28 2023-10-28 Q / Translation services tions nvelope ementation MZ-MEF-DNT-296756-NC-RF B / Human resources and pay Enabling elements to suppor Single Stage - One E Pending Impl IDA / D8100 Post Request for Bids Open - National 100,000.00 0.00 2022-06-28 2022-07-03 2022-09-01 2022-10-16 2022-11-29 2023-11-29 roll agency to support the hir t economic linkages nvelope ementation ing of technical assistants to IPEME CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-MEF-DNT-232323-CS-QC Developing economic linkag Quality And Cost- Open - Internationa Under Implement BS / Master plan services and IDA / V3550 es through skills, finance, an Prior 600,000.00 0.00 2021-05-30 2021-08-27 2021-06-20 2021-09-01 2021-08-03 2022-04-01 2021-08-31 2022-05-31 2021-09-30 2021-11-04 2021-12-09 2022-12-09 Based Selection l ation Jamali for INATUR d quality upgrading MZ-MEF-DNT-232326-CS-QC BS / Consulting services for t Developing economic linkag Quality And Cost- Under Implement he design of materials, imag IDA / V3550 es through skills, finance, an Post Open - National 250,000.00 0.00 2021-05-30 2021-10-17 2021-06-20 2021-10-21 2021-08-03 2022-03-02 2021-08-31 2022-03-29 2021-09-30 2022-05-26 2021-11-04 2021-12-09 2022-12-09 Based Selection ation e, communication tools, and l d quality upgrading ead the awareness campaign efforts MZ-MEF-DNT-208398-CS-QC Enabling elements to suppor Quality And Cost- Open - Internationa Under Implement IDA / V3550 Prior 750,000.00 0.00 2021-06-06 2021-05-18 2021-06-27 2021-08-09 2021-08-10 2022-05-04 2021-09-07 2022-06-10 2021-10-07 2021-11-11 2021-12-16 2022-12-16 BS / Mapping of manufacturi t economic linkages Based Selection l ation ng sector MZ-MEF-DNT-234783-CS-QC Enabling elements to suppor Quality And Cost- BS / APIEX - Technical assista IDA / V3550 Prior Open - National 150,000.00 187,435.21 Signed 2021-05-31 2021-05-24 2021-06-21 2021-06-18 2021-08-04 2021-11-03 2021-09-01 2021-12-13 2021-10-01 2022-02-01 2021-11-05 2022-03-07 2021-12-10 2022-03-31 2022-12-10 t economic linkages Based Selection nce to team revising Investm ent Law MZ-MEF-DNT-246363-CS-QC Enabling elements to suppor Quality And Cost- Open - Internationa Under Implement IDA / D8100 Post 100,000.00 0.00 2021-08-15 2021-09-14 2021-09-05 2021-09-16 2021-10-19 2022-04-05 2021-11-16 2022-05-24 2021-12-16 2022-01-20 2022-02-24 2023-02-24 BS / Strategy and HR review f t economic linkages Based Selection l ation or IPEME MZ-MEF-DNT-246368-CS-QC Developing economic linkag BS / Upstream Stage 1: Deliv Quality And Cost- Open - Internationa Under Implement IDA / D8100 es through skills, finance, an Prior 1,400,000.00 0.00 2021-10-31 2021-11-21 2021-11-21 2021-12-06 2022-01-04 2022-02-01 2022-03-03 2022-04-07 2022-05-12 2023-05-12 ery of skills trainings: operati Based Selection l ation d quality upgrading ons, marketing, financial ma nagement, regulatory MZ-MEF-DNT-246417-CS-QC BS / IPEME - Design, impleme Enabling elements to suppor Quality And Cost- Open - Internationa Under Implement IDA / D8100 Post 300,000.00 0.00 2021-08-23 2021-09-28 2021-09-12 2021-09-30 2021-10-26 2022-04-19 2021-11-23 2022-05-30 2021-12-23 2022-01-27 2022-03-03 2023-03-03 ntation and adoption of SME t economic linkages Based Selection l ation data framework MZ-MEF-DNT-246365-CS-QC BS / Upstream Linkages - Org Developing economic linkag Quality And Cost- Open - Internationa Under Implement anization, filtering, screening IDA / D8100 es through skills, finance, an Prior 1,000,000.00 0.00 2021-08-22 2021-09-22 2021-09-12 2021-09-28 2021-10-26 2022-03-12 2021-11-23 2022-05-11 2021-12-23 2022-01-27 2022-03-03 2023-03-03 Based Selection l ation between stages, relationship d quality upgrading with large investments, MZ-MEF-DNT-246418-CS-QC Developing economic linkag BS / Training on personal initi Quality And Cost- Open - Internationa Under Implement IDA / D8100 es through skills, finance, an Prior 2,800,000.00 0.00 2021-08-31 2021-11-21 2021-09-21 2021-12-16 2021-11-04 2021-12-02 2022-01-01 2022-02-05 2022-03-12 2023-03-12 ative skills for upstream and Based Selection l ation d quality upgrading consumption linkages Page 1 MZ-MEF-DNT-267301-CS-CQ S / Consulting services for th e development of the inform Consultant Qualifi IDA / D8100 Project Management Post Limited 50,000.00 27,301.09 Signed 2021-12-10 2021-12-21 2022-01-24 2022-05-10 2022-02-23 2022-05-26 2022-05-09 2022-06-08 2023-05-09 ation management system of cation Selection the feedback and complaint r esolution mechanism (GRM) MZ-MEF-DNT-246367-CS-QC Developing economic linkag BS / Consumption Linkages – Quality And Cost- Open - Internationa IDA / D8100 es through skills, finance, an Prior 750,000.00 0.00 Canceled 2021-08-15 2021-09-05 2021-10-19 2021-11-16 2021-12-16 2022-01-20 2022-02-24 2023-02-24 Organization, selection, man Based Selection l d quality upgrading agement of beneficiaries MZ-MEF-DNT-246416-CS-QC BS / Technical assistance to c Enabling elements to suppor Quality And Cost- Open - Internationa Under Implement IDA / D8100 Post 400,000.00 0.00 2022-04-29 2022-04-28 2022-05-20 2022-04-28 2022-08-02 2022-10-16 2022-11-15 2022-12-29 2023-02-26 2024-02-26 ompetitive grants for econo t economic linkages Based Selection l ation mic linkages and financial se rvices platforms MZ-MEF-DNT-278777-CS-QC BS / Consulting services for s Developing economic linkag Quality And Cost- Open - Internationa Pending Impleme ustainable and climate resilie IDA / D8100 es through skills, finance, an Prior 500,000.00 0.00 2022-06-23 2022-07-14 2022-10-11 2022-12-10 2023-02-08 2023-04-08 2023-06-06 2024-06-05 Based Selection l ntation nt capabilities for upstream a d quality upgrading nd consumption linkage MZ-MEF-DNT-274414-CS-QC Developing economic linkag BS / Consumption Linkages – Quality And Cost- Open - Internationa Under Implement IDA / D8100 es through skills, finance, an Prior 1,000,000.00 0.00 2022-03-15 2022-03-16 2022-03-30 2022-03-18 2022-07-28 2022-09-26 2022-11-10 2023-01-15 2023-03-31 2024-03-30 Organization, selection, man Based Selection l ation d quality upgrading agement of beneficiaries MZ-MEF-DNT-272472-CS-QC Enabling elements to suppor Consultant Qualifi Open - Internationa Under Implement BS / The development of MIC IDA / D8100 Post 100,000.00 0.00 2022-04-04 2022-03-11 2022-04-25 2022-03-16 2022-07-23 2022-09-21 2022-11-19 2023-11-19 t economic linkages cation Selection l ation E strategy for Mozambique MZ-MEF-DNT-282897-CS-QC Enabling elements to suppor Quality And Cost- Open - Internationa Under Implement BS / Programa Unico Coordin IDA / D8100 Post 250,000.00 0.00 2022-03-15 2022-03-16 2022-04-05 2022-03-23 2022-07-03 2022-09-01 2022-10-16 2022-11-29 2023-02-12 2024-02-12 t economic linkages Based Selection l ation ation and management office support MZ-MEF-DNT-278775-CS-QC Quality And Cost- Open - Internationa Under Implement BS / Consulting services to th IDA / D8100 Project Management Prior 1,500,000.00 0.00 2022-06-15 2022-06-04 2022-07-06 2022-06-24 2022-10-19 2022-12-18 2023-01-17 2023-03-17 2023-05-15 2024-05-14 Based Selection l ation e Gender related interventio n in the Project MZ-MEF-DNT-296750-CS-CQ S / DASP - Certification for th Developing economic linkag e implementation of ISO 900 Consultant Qualifi Pending Impleme IDA / D8100 es through skills, finance, an Post Open - National 80,000.00 0.00 2022-07-31 2022-08-21 2022-11-18 2023-01-17 2023-03-09 2024-03-08 1/15 Management Quality Sy cation Selection ntation d quality upgrading stem in One-Stop-Shops (BA Us) in Maputo, Tete, Nampul a and Cabo Delgado MZ-MEF-DNT-296753-CS-CQ S / Design of a Corporate Ima Enabling elements to suppor Consultant Qualifi Pending Impleme ge in x One-Stop-Shops (BA IDA / D8100 Post Open - National 50,000.00 0.00 2022-08-16 2022-09-06 2022-11-19 2023-01-18 2023-03-10 2023-05-09 t economic linkages cation Selection ntation Us) located in Cabo Delgado, Nampula, Tete Provinces MZ-MEF-DNT-267305-CS-QC Enabling elements to suppor Quality And Cost- Open - Internationa Pending Impleme BS / Feasibility study and det IDA / D8100 Post 300,000.00 0.00 2022-08-05 2022-08-20 2022-12-03 2023-02-01 2023-03-18 2023-05-01 2023-07-15 2024-07-14 t economic linkages Based Selection l ntation ailed design for an integrated market of Tete MZ-MEF-DNT-299237-CS-CQ S / Preparation of environme Enabling elements to suppor Consultant Qualifi IDA / D8100 Post Limited 50,000.00 0.00 Canceled 2022-06-13 2022-08-12 2022-09-26 2022-12-10 2023-12-10 ntal and social project tools f t economic linkages cation Selection or access to financing and ec onomic opportunities INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-MEF-DNT-208325-CS-IND Individual Consult IDA / D8100 Project Management Post Open 100,000.00 112,500.00 Signed 2020-12-22 2021-01-18 2021-02-09 2021-04-15 2021-03-02 2021-06-18 2021-04-06 2021-06-30 2021-10-03 V / Project Coordinator ant Selection MZ-MEF-DNT-208370-CS-IND Individual Consult IDA / D8100 Project Management Post Open 70,000.00 72,000.00 Signed 2021-02-15 2021-01-18 2021-04-05 2021-04-15 2021-04-26 2021-06-18 2021-05-31 2021-06-30 2021-11-27 V / Financial Management Sp ant Selection ecialist MZ-MEF-DNT-208376-CS-IND Individual Consult IDA / D8100 Project Management Post Open 40,000.00 48,000.00 Signed 2021-01-28 2021-01-22 2021-03-18 2021-04-26 2021-04-08 2021-06-18 2021-05-13 2021-06-30 2021-11-09 V / Accountant ant Selection MZ-MEF-DNT-208332-CS-IND Individual Consult IDA / D8100 Project Management Prior Open 50,000.00 72,000.00 Signed 2021-01-25 2021-01-19 2021-03-15 2021-04-26 2021-04-05 2021-06-18 2021-05-10 2021-06-30 2021-11-06 V / Procurement Specialist ant Selection MZ-MEF-DNT-208372-CS-IND Individual Consult V / Environmental Safeguard IDA / D8100 Project Management Post Open 50,000.00 63,000.00 Signed 2021-01-25 2021-01-22 2021-03-15 2021-04-15 2021-04-05 2021-06-18 2021-05-10 2021-06-30 2021-11-06 ant Selection s Specialist MZ-MEF-DNT-208381-CS-IND Individual Consult V / Specialist to Support Fir IDA / D8100 Project Management Post Open 50,000.00 60,000.00 Signed 2021-02-10 2021-05-10 2021-03-31 2022-01-10 2021-04-21 2022-01-14 2021-05-26 2022-01-31 2021-11-22 ant Selection m Capabilities for Economic L inkages MZ-MEF-DNT-208399-CS-IND Individual Consult IDA / D8100 Project Management Post Open 50,000.00 60,000.00 Signed 2021-02-15 2021-01-22 2021-04-05 2021-04-15 2021-04-26 2021-06-11 2021-05-31 2021-06-30 2021-11-27 V / Social Safeguards Speciali ant Selection st MZ-MEF-DNT-208378-CS-IND Individual Consult IDA / D8100 Project Management Post Open 40,000.00 48,000.00 Signed 2021-01-31 2021-05-10 2021-03-21 2021-12-08 2021-04-11 2022-01-14 2021-05-16 2022-03-03 2021-11-12 V / M&E Specialist ant Selection MZ-MEF-DNT-232314-CS-IND Developing economic linkag Individual Consult V / Social and environmental IDA / V3550 es through skills, finance, an Post Open 15,000.00 24,000.00 Signed 2021-05-20 2021-05-17 2021-07-08 2022-01-18 2021-07-29 2022-02-17 2021-09-02 2022-03-11 2022-03-01 ant Selection specialist - Nampula d quality upgrading MZ-MEF-DNT-208395-CS-IND V / Capacity Assessment of fi Individual Consult rms in specific sub-sectors a / Project Management Post Open 70,000.00 0.00 Canceled 2021-02-21 2021-04-11 2021-05-02 2021-06-06 2021-12-03 ant Selection nd value chains for potential to economic linkages MZ-MEF-DNT-208402-CS-IND Individual Consult / Project Management Post Open 35,000.00 0.00 Canceled 2021-02-15 2021-04-05 2021-04-26 2021-05-31 2021-11-27 V / Project´s Operations Man ant Selection ual Page 2 MZ-MEF-DNT-232315-CS-IND Individual Consult V / Social and environmental IDA / V3550 Project Management Post Limited 15,000.00 24,000.00 Signed 2021-05-25 2021-05-17 2021-05-30 2022-01-18 2021-06-20 2022-02-18 2021-07-25 2022-03-16 2022-01-21 ant Selection specialist service in Cabo Del gado MZ-MEF-DNT-233916-CS-IND Individual Consult IDA / V3550 Project Management Post Limited 50,000.00 42,000.00 Signed 2021-05-30 2021-08-31 2021-06-04 2021-09-13 2021-06-25 2021-12-16 2021-07-30 2022-01-31 2022-01-26 V / Internal Auditor ant Selection MZ-MEF-DNT-232313-CS-IND Individual Consult V / Social and environmental IDA / V3550 Project Management Post Limited 15,000.00 24,000.00 Signed 2021-05-30 2021-05-20 2021-06-04 2021-12-10 2021-06-25 2021-12-28 2021-07-30 2022-03-03 2022-01-26 ant Selection specialist - Tete MZ-MEF-DNT-246359-CS-IND Individual Consult IDA / D8100 Project Management Post Open 50,000.00 49,800.00 Signed 2021-08-15 2021-08-31 2021-10-03 2022-02-01 2021-10-24 2022-02-22 2021-11-28 2022-03-14 2022-05-27 V / Specialist of Infrastructur ant Selection e MZ-MEF-DNT-246419-CS-CD Developing economic linkag Under Implement S / Personal Initiative design IDA / D8100 es through skills, finance, an Prior Direct Selection Direct 200,000.00 508,036.33 2021-09-30 2021-11-21 2021-10-10 2021-12-13 2021-12-14 2022-06-12 ation and training of trainers d quality upgrading MZ-MEF-DNT-208383-CS-IND Individual Consult / Project Management Post Limited 20,000.00 0.00 Canceled 2021-02-15 2021-02-20 2021-03-13 2021-04-17 2021-10-14 V / Legal Adviser (Short-Term ant Selection ) MZ-MEF-DNT-208396-CS-IND V / Mapping of service provid Individual Consult ers in the targeted regions (i / Project Management Post Open 50,000.00 0.00 Canceled 2021-02-15 2021-04-05 2021-04-26 2021-05-31 2021-11-27 ant Selection ncluding an assessment of d epth of CSOs operating in the provinces of focus) MZ-MEF-DNT-254288-CS-IND Individual Consult IDA / D8100 Project Management Post Open 40,000.00 42,000.00 Signed 2021-10-28 2021-09-28 2022-01-26 2022-02-23 2022-02-25 2022-03-08 2022-05-02 2022-03-31 2023-05-02 V / Communication Specialist ant Selection MZ-MEF-DNT-255139-CS-IND Individual Consult Under Implement IDA / D8100 Project Management Prior Open 30,000.00 0.00 2021-10-15 2021-10-22 2022-01-02 2022-06-02 2022-02-16 2022-06-15 2022-05-02 2023-05-02 V / Procurement Assistant ant Selection ation MZ-MEF-DNT-255138-CS-IND Enabling elements to suppor Individual Consult Under Implement IDA / D8100 Post Open 50,000.00 0.00 2021-10-08 2021-10-19 2021-12-27 2022-03-21 2022-01-26 2022-04-11 2023-04-11 V / Economic Advisor to IPEM t economic linkages ant Selection ation E MZ-MEF-DNT-246362-CS-IND V / Designing and installing u Individual Consult IDA / D8100 Project Management Post Open 50,000.00 0.00 Canceled 2021-08-31 2021-10-19 2021-11-09 2021-12-14 2022-06-12 pdated Grievance Redress M ant Selection echanism (GRM) MZ-MEF-DNT-266906-CS-IND V / Survey of the needs for R Individual Consult Under Implement IDA / D8100 Project Management Post Open 10,000.00 0.00 2022-01-15 2022-02-01 2022-04-14 2022-05-14 2022-08-12 2023-02-08 ehabilitation and adequacy o ant Selection ation f IPEME Headquarters office MZ-MEF-DNT-272449-CS-IND Individual Consult Under Implement IDA / D8100 Project Management Post Open 50,000.00 0.00 2022-01-14 2022-01-14 2022-04-29 2022-05-10 2022-06-13 2022-08-27 2023-08-27 V / Gender and GBV Specialis ant Selection ation t MZ-MEF-DNT-266909-CS-IND Individual Consult IDA / D8100 Project Management Post Open 50,000.00 0.00 Canceled 2021-12-30 2022-04-14 2022-05-29 2022-08-12 2023-08-12 V / Gender and youth Special ant Selection ist MZ-MEF-DNT-265703-CS-IND V / Environmental and social Enabling elements to suppor Individual Consult Under Implement IDA / D8100 Post Open 25,000.00 0.00 2022-02-18 2022-02-18 2022-06-17 2022-08-01 2022-10-15 2023-06-12 impact study for integrated t economic linkages ant Selection ation market for fish, vegetable an d fruits in Tete MZ-MEF-DNT-246369-CS-IND V / Senior Advisor on Private Enabling elements to suppor Individual Consult IDA / D8100 Post Limited 80,000.00 0.00 Canceled 2021-09-30 2021-10-05 2021-10-26 2021-11-30 2022-05-29 Sector Development to assist t economic linkages ant Selection Prime-Minister’s office MZ-MEF-DNT-278771-CS-IND Individual Consult IDA / D8100 Project Management Post Direct 45,000.00 45,000.00 Signed 2022-02-18 2022-02-18 2022-03-05 2022-02-23 2022-03-26 2022-03-15 2022-06-09 2022-03-31 2023-06-04 V / Accountant ant Selection MZ-MEF-DNT-278779-CS-IND V / Environmental and Social Enabling elements to suppor Individual Consult Pending Impleme Impact Assessment and Envir IDA / D8100 Post Open 50,000.00 0.00 2022-09-30 2023-02-26 2023-04-12 2023-07-11 2024-03-07 t economic linkages ant Selection ntation onmental Licensing of Market in location being identified in Balama or Montepuez MZ-MEF-DNT-296751-CS-IND Enabling elements to suppor Individual Consult Pending Impleme IDA / D8100 Post Open 50,000.00 0.00 2022-08-30 2022-12-03 2023-01-17 2023-04-02 2024-04-01 V / Reform Advisor for DASP t economic linkages ant Selection ntation MZ-MEF-DNT-278773-CS-IND V / Environmental and Social Enabling elements to suppor Individual Consult Pending Impleme Impact Assessment (ESIA) an IDA / D8100 Post Open 50,000.00 0.00 2022-06-30 2022-11-11 2022-12-26 2023-03-11 2023-11-06 t economic linkages ant Selection ntation d Environmental Licensing of the Topuito Eco-Industrial Par k Infrastructure MZ-MEF-DNT-301323-CS-IND V / Preparation of environme Enabling elements to suppor Individual Consult Pending Impleme IDA / D8100 Post Open 50,000.00 0.00 2022-06-26 2022-08-14 2022-09-04 2022-10-09 2023-04-07 ntal and social project tools f t economic linkages ant Selection ntation or access to financing and ec onomic opportunities Page 3