FEDERAL REPUBLIC OF NIGERIA Nigeria Erosion and Watershed Management Project (NEWMAP) PROCUREMENT PLAN I. GENERAL 1. Project information: Country: Nigeria Borrower: Federal Government of Nigeria Project Name: Nigeria Erosion and Watershed Management Project-(NEWMAP) Loan / Credit No.: PIA: National NEWMAP Coordinating Unit. 2. Bank’s approval Date of the procurement Plan: March, 2012 3. Date of General Procurement Notice: 4. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold (US$ equivalent) 1. ICB and LIB (Goods and services > 750,000.00 ALL other than consultancy services) 2. NCB 50,000.00 ≤ NONE 750,000.00 3. ICB (Works) > 5,000,000.00 ALL 4. NCB (Works) 200,000 ≤ NONE 5,000,000.00 5 Shopping-Goods < 50,000.00 NONE 6 Shopping-Works < 100,000.00 NONE 7 Training, Workshops, Study All Values Based on Tours Annual Work Plans & Budgets 2. Prequalification. Bidders for major works shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Shall apply 4. Reference to (if any) Project Operational/Procurement Manual: shall apply 5. Any Other Special Procurement Arrangements: Not Applicable 6. Procurement Packages with Methods and Time Schedule Procurement of Goods : 1 2 3 4 5 6 7 8 9 R Contract Estima Procur Prequalific Domesti Review Expecte Comment ef. (Description) ted ement ation c by Bank d s N Cost Method (yes/no) Preferen (Prior / Post) Bid- o. US$’0 ce Opening 00 (yes/no) Date 1 Computer Systems, Office, software and Accessories Computers and 684 NCB NO NO POST June 7, Procure Accessories, (see 2012 ment by remark each of software Colum) the 7 packages, Photo- SPMU & copiers, UPS, FPMU is Printers and estimate Scanners, Fax d at ( Machines, USD Laptops, 85.5) Stationeries, Consumables, LAN, Telephony,Lasers Software Licenses and Application,. 2 Office Furniture’s and Equipment Computer 680 NCB NO NO PRIOR June 7, Procure workstations and (see 2012 ment by remark each of Office Furniture Colum) the 7 Water Dispenser, SPMU & Refrigerators, FPMU is estimate Airconditioners, d at ( Tables, Chairs, etc USD 85) 3 Operational Vehicles 4-WD Vehicles (32 1440 NCB NO NO PRIOR June 7, Procure units) (see 2012 ment by remark each of Colum) the 7 SPMU & FPMU is estimate d at (180USD 4 Generator 40KVA Sound-Proof 240 NS NO NO PRIOR June 7, Procure Electricity (see 2012 ment by Generating Set- remark each of Purchase and Colum) the 7 Installation (8 SPMU & units) FPMU is estimate d at (30 USD 5 Training Communication, Presentation, Media Equipment and materials, etc Multimedia 364 NS NO NO PRIOR June 7, Procure Projectors, (see 2012 ment by remark each of Flip Chart Colum) the 7 Stands, Boards, SPMU & GSM FPMU is TV/Video/Radio/R estimate ecorders and d at Digital Cameras, (45.5 Internet Facilities, USD GPS, Raincoats and Enumerators bags, Program information kit, Program posters Community oriented Implementation manual 6 Field Equipment Purchase of 2,400 NCB NO NO PRIOR June 7, Procure Weather (see 2012 ment by Monitoring remark each of Stations, GPSs, Colum) the 7 Laser Measures, SPMU & Measuring Wheels, FPMU is 1-2km Range estimate Radios and other d at (300 survey equipment USD and tools to gauge and trace watershed, terrestrial carbon and water flow 7 Geographic Information System Purchase of GIS 3520 NCB NO NO PRIOR June 7, Procure data/Satellite (see 2012 ment by Imagery,, remark each of Overhead Colum) the 7 photography, etc SPMU & FPMU is estimate d at (440 USD Sub Total 9,328. 00 Procurement of Civil Works 1 2 3 4 5 6 7 8 9 Ref Contract Estimat Procur Prequalific Domesti Review Expecte Comment . (Description) ed ement ation c by Bank d s No. Cost Metho (yes/no) Preferen (Prior / Post) Bid- US$’00 d ce Opening 0 (yes/no) Date 1 Civil works, and 252,000. ICB NO YES PRIOR October Procure maintenance of 00 12, ment by flood and gully 2012 ICB for erosion sites all 7 SPMU 2 Office 240,000 NS NO NO PRIOR July, accommodation 2012 for 7 SPMU & FPCU SUB TOTAL 252,240 .00 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1 Consultant Services-QCBS- All Values ALL International 2 Consultant Services-QCBS- > 200,000.00 ALL National 3 Consultant Services-CQS < 200,000.00 NONE 4 Consultant Services-lC > 50,000.00 ALL 5 Consultant Services-lC < 50,000.00 ToR only but ALL 6 Consultant Services- Single All Values ALL Source Selection Note: All ToRs to be prior review QCBS = Quality and Cost Based Selection SSS = Single Source Selection CQ = Consultant Qualification LCS = Least Cost Selection IC = Individual Consultant 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $200,000.00 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: NA 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 7 Ref Description of Estimat Selecti Review Expected Comment . Assignment ed on by Bank Proposal s No. Metho (Prior / s Cost. d Post) Submissi US$’0 on 00 Date 1 Consultancy for the 3,395.24 QCBS Prior On-going Consultancy detailed Engineering (see for Priority designs and data remark sites by each collation for 35 sites Colum of the 7 SPMU (see each State Proc. Plan). 2 Consultancy for the 6,824.47 QCBS Prior September Consultancy supervision of Civil (see 2012 for Priority Works for 35sites remark sites by each Colum of the 7 SPMU (see each State Proc. Plan). 3 Consultancy for the RAP 875.00 IC Prior On-going Consultancy study for 35 sites (see for Priority remark sites by each Colum of the 7 SPMU is estimated at (25 USD. 4 Consultancy for the ESIA 875.00 IC Prior On-going Consultancy study for 35 sites (see for Priority remark sites by each Colum of the 7 SPMU is estimated at (25 USD. 5 Consultancy for the 875.00 IC Prior On-going Consultancy Socio-Economic study 35 (see for Priority sites remark sites by each Colum of the 7 SPMU is estimated at 25 USD per site 6 Consultancy for GIS data 875.00 IC Prior On-going Consultancy collection and Mapping (see for Priority for 35 sites remark sites by each Colum of the 7 SPMU is estimated at 75 USD per site 7 Consultancy for the 3500.00 QCBS Prior August, Consultancy detailed Engineering (see 2012 for 5 designs and data remark additional collation for additional Colum sites by each 35sites of the 7 SPMU is estimated at 100 USD per site 8 Consultancy for the 2625.00 QCBS Prior June, 2013 Consultancy detailed ESIA, RAP and (see for 5 Socio Economic Studies remark additional for additional 35 sites Colum sites by each of the 7 SPMU is estimated at 75 USD per site 9 Environmental 800 QCBS 9 engineering and design consultancy, 10 Procurement consultancy 800 QCBS 10 June 1012 for support of FPMU and SPMUs 11 M&E consultancy 400 QCBS 11 12 Consultancy for the 800.00 QCBS 12 Sept., 2012 Consultancy support of SPMUs and (see by each of FPMU remark the 7 SPMU Colum & FPMU is estimated at (100 USD 13 Consultancy for Legal 800.00 IC 13 Sept., 2012 Consultancy Services (see by each of remark the 7 SPMU Colum & FPMU is estimated at (100 USD 14 Consultancy for 3500.00 14 Sept., 2012 Consultancy valuation and (see by each of resettlement remark the 7 SPMU, implementation Colum to cover all sites is estimated at (500 USD per SPMU 15 Consultancy for Training 1600.00 QCBS Prior August, Consultancy and Capacity Building (see 2012 by each of remark the 7 SPMU Colum & FPMU is estimated at (200 USD 16 Consultancy-External 400.00 QCBS Prior March, Consultancy Auditor (see 2013 by FPMU to remark cover each Colum SPMU 17 Consultancy on 800.00 IC Prior Sept., 2012 Consultancy Community consultation, (see by each of Public Education and remark the 7 SPMU Erosion Management Colum & FPMU is and awareness estimated at Techniques, (100 USD Sub Total 27,744. 71 IV. Implementing Agency Capacity Building Activities with Time Schedule 1. In this section the agreed Capacity Building Activities are listed with time schedule below; No. Expected outcome / Estimated Estimate Start Date Com Activity Description Cost US$ d m ‘000 Duration e n t s A. TRAINING 1 3. Nos. Training courses August Capacity for PMU staff; Project 2012 Building Coordinator, activities for Procurement Specialist, each of the 7 SPMU & FPMU and financial mgt, M&E, is estimated at Environmental (90 USD specialists, Communication, 720.00(see Livelihood, Engineering remark 2WKS, specialists Colum each 2 August Capacity 2012 Building activities for Training of project each of the 7 finance staff(FMS, APA, 160.00(see SPMU & FPMU FO, IA) on flexible remark is estimated at accounting software Colum 1wk (20 USD B. WORKSHOP 3 Septembe Capacity r 2012 Building activities for each of the 7 240.00(see SPMU & FPMU Capacity Building for remark is estimated at key stakeholders Colum 3 days (30 USD 4 Septembe Capacity r, 2012 Building activities for each of the 7 160(see SPMU & FPMU remark is estimated at ICT Training Colum 1 wk (20 USD 5 Various Capacity Building activities for each of the 7 Professional 120.00(see SPMU & FPMU Seminars/Workshops/ remark is estimated at subscriptions Colum Various (15 USD 6 Septembe Capacity r 2012 Building 2 Days Sensitization/ activities for Workshop for State and each of the 7 Local Govt. Officials on 200.00(see SPMU & FPMU erosion and watershed remark is estimated at management Colum 2 days (25 USD 7 October Capacity 2012 Building 3 Day workshop for Line activities for Ministries and MDAs on each of the 7 addressing and 240.00(see SPMU & FPMU prevention of Land remark is estimated at Degradation Colum 3- days (30 USD 8 3 Day workshop for local October Capacity 2012 Building Govt. Focal Persons and activities for Community Erosion each of the 7 watch Dogs on 240.00(see SPMU & FPMU prevention of erosion remark is estimated at and land degradation Colum 3-days (30 USD 9 2013 Capacity Building activities for each of the 7 Capacity Building on use 200.00(see SPMU & FPMU of Metrological and GPS remark is estimated at Equipment Colum 5-days (25 USD C. STUDY/TOURS 10 240.00(see Various October Capacity remark times 2012 Building Colum activities for Baseline survey/ each of the 7 Community needs SPMU & FPMU assessment and is estimated at capacity building (30 USD 11 240.00(see Various August, Capacity remark times 2012 Building Colum activities for each of the 7 Sensitization/ SPMU & FPMU Awareness creation of is estimated at NEWMAP in the 18 LGA (30 USD 12 160.00(see WB and Capacity remark FAO to Building Colum determin activities for Participation in each of the 7 watershed studies e SPMU & FPMU organized by the world is estimated at bank and FAO (20 USD 13 240.00(see Various December Capacity remark , 2012 Building Colum activities for each of the 7 SPMU & FPMU Launching of ESIA and is estimated at RAP for priority sites (30 USD 14 160.00(see Various Oct., Capacity remark 2012 Building Colum activities for each of the 7 SPMU & FPMU is estimated at livelihood studies (20 USD 15 160.00(see Various World Capacity remark Bank Building Colum determine activities for Participation in each of the 7 Biodiversity/forest d SPMU & FPMU carbon study organized is estimated at by the World Bank (20 USD 16 120.00(see 4-days July 2012 Capacity remark each Building Colum activities for each of the 7 Recognizance survey of SPMU & FPMU Project sites (Erosion is estimated at and Watershed) (15 USD 17 2480.00(se 4-wks February., Capacity e remark 2013 Building International Training Colum activities for and study tours each of the 7 SPMU & FPMU is estimated at (310 USD 18 Various World Capacity Bank Building determine activities for Attendance of World each of the 7 Bank Organized d 800.00(see SPMU & FPMU training, meetings, remark is estimated at seminar and workshops Colum (100 USD Sub Total 6,880.00 PROCUREMENT Nigeria : Nigeria Erosion and Watershed Management Project PLAN General Information Country: Nigeria 2017-06-12 Bank’s Approval Date of the Original Procurement Plan: 2022-06-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P124905 GPN Date: Project Name: Nigeria Erosion and Watershed Management Project Loan / Credit No: IDA / 51050 EDO SPMU Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-EDO SPMU-17122-CW-RF B / Reclamation, channeling Component 1: Erosion and Open - Internationa Single Stage - One E 52,000,000.0 2019-07-0 and remediation works at NE IDA / 51050 Watershed Management Infr Prior Request for Bids 0.00 Canceled 2012-07-13 2012-07-13 2017-04-25 2017-05-30 2017-04-25 2017-07-04 l nvelope 0 3 W Flood and Gully Erosion Sit astructure Investments es in Edo State-GAPIONA AN D URORA NG-EDO SPMU-17128-CW-RF B / Reclamation, channeling and remediation works at NE Component 1: Erosion and Open - Internationa Single Stage - One E 25,600,000.0 20,913,464. 2019-08-3 W Flood and Gully Erosion Sit IDA / 51050 Watershed Management Infr Prior Request for Bids Signed 2012-07-13 2018-04-26 2012-07-13 2017-07-19 2018-07-09 2017-08-18 2019-08-31 2017-09-01 2019-10-15 l nvelope 0 96 0 es in Edo State-OGISO, EDO astructure Investments COLLEGE, AAU, Emu, Igbe Qu arters and Fugar-Agenebode road NG-EDO SPMU-67669-CW-RF B2 / Reclamation, channeling Component 1: Erosion and Open - Internationa Single Stage - One E 52,000,000.0 2018-12-2 and remediation works at NE IDA / 51050 Watershed Management Infr Prior Request for Bids 0.00 Canceled 2017-08-30 2017-09-04 2017-10-16 2017-11-15 2018-08-29 2017-12-20 l nvelope 0 6 W Flood and Gully Erosion Sit astructure Investments es in Edo State-GAPIONA AN D URORA NG-EDO SPMU-72150-CW-RF Component 1: Erosion and B / Delimitation/Delineation a Single Stage - One E 2019-05-2 IDA / 51050 Watershed Management Infr Post Request for Bids Open - National 1,500,000.00 970,785.38 Signed 2018-08-10 2020-06-18 2018-08-15 2021-02-01 2018-09-26 2020-07-17 2018-10-26 2020-08-18 2018-11-30 2020-10-12 nd construction of perimeter nvelope 9 astructure Investments fences at Queen Ede, Auchi a nd Ekehuan sites NG-EDO SPMU-76211-CW-RF B / Reclamation, channeling Component 1: Erosion and Open - Internationa Single Stage - One E 40,840,000.0 27,034,076. Under Revie 2020-12-1 and remediation works at NE IDA / 51050 Watershed Management Infr Prior Request for Bids 2018-08-30 2018-10-04 2018-09-04 2018-10-08 2018-10-16 2018-12-06 2018-11-15 2019-03-20 2018-12-20 2019-04-25 l nvelope 0 82 w 8 W Flood and Gully Erosion Sit astructure Investments es in Edo State-GAPIONA AN D URORA NG-EDO SPMU-96321-CW-RF Q / Post construction mainte nance works including cleani Component 1: Erosion and Request for Quota Single Stage - One E 2019-11-1 ng of drainage channels at Q IDA / 51050 Watershed Management Infr Post Limited 150,000.00 30,519.48 Signed 2019-03-25 2020-05-13 2019-05-20 2020-06-22 tions nvelope 6 ueen Ede flood and gully Ero astructure Investments sion site, and at Ekehuan Flo od and gully erosion site, Ben in City, Edo State NG-EDO SPMU-96325-CW-RF Q / Post construction mainte Component 1: Erosion and Request for Quota Single Stage - One E 2019-11-1 nance works including cleani IDA / 51050 Watershed Management Infr Post Limited 200,000.00 108,872.66 Completed 2019-03-25 2020-05-13 2019-05-20 2020-06-22 tions nvelope 6 ng of drainage channels at A astructure Investments uchi Flood and gully erosion site, Edo State NG-EDO SPMU-163837-CW-R FQ / Delimitation/Delineation Component 1: Erosion and Request for Quota Single Stage - One E 2020-11-1 and construction of vegetativ IDA / 51050 Watershed Management Infr Post Limited 200,000.00 50,030.76 Completed 2020-03-25 2020-12-28 2020-05-20 2021-01-14 tions nvelope 6 e/wire mesh perimeter fence astructure Investments s at Ibore and Ewu sites NG-EDO SPMU-163836-CW-R Component 1: Erosion and FQ / Extending drainage cha Request for Quota Single Stage - One E 2020-11-1 IDA / 51050 Watershed Management Infr Post Limited 195,000.00 161,370.03 Completed 2020-03-25 2020-11-02 2020-05-20 2020-12-04 nnels to safe disposal points- tions nvelope 6 astructure Investments Honey-G Road-NEW NG-EDO SPMU-163835-CW-R Component 1: Erosion and FQ / Gully Stabilization and la Request for Quota Single Stage - One E 2020-11-1 IDA / 51050 Watershed Management Infr Post Limited 195,000.00 232,676.13 Completed 2020-03-25 2020-11-02 2020-05-20 2020-12-04 ndslide Management activitie tions nvelope 6 astructure Investments s.-Honey-G Road-NEW NG-EDO SPMU-163834-CW-R FQ / Post construction mainte Component 1: Erosion and Request for Quota Single Stage - One E 2020-11-1 nance works including cleani IDA / 51050 Watershed Management Infr Post Limited 100,000.00 38,321.66 Signed 2020-03-25 2020-12-28 2020-05-20 2021-01-14 tions nvelope 6 ng of drainage channels at Ib astructure Investments ore and Ewu sites-NEW NG-EDO SPMU-163833-CW- DIR / Emergency Reclamatio Component 1: Erosion and 2020-07-0 n, channeling and remediatio IDA / 51050 Watershed Management Infr Post Direct Selection Direct 1,000,000.00 828,026.66 Signed 2020-03-24 2020-03-22 2020-03-27 2020-03-24 2020-04-07 2020-08-18 3 n works at Iguosa flood and g astructure Investments ully Erosion site, Benin City, Edo State NG-EDO SPMU-171909-CW-R FB / Reclamation, channeling Component 1: Erosion and Single Stage - One E 3,618,328.4 2021-05-2 and Parmanent remediation IDA / 51050 Watershed Management Infr Post Request for Bids Open - National 5,500,000.00 Signed 2020-05-14 2020-06-18 2020-05-19 2021-02-01 2020-06-19 2020-07-17 2020-07-05 2020-08-17 2020-07-17 2020-10-16 nvelope 9 8 works at Iguosa flood and gul astructure Investments ly Erosion site, Benin City, Ed o State NG-EDO SPMU-199998-CW-R FB / Reclamation, channeling Component 1: Erosion and Single Stage - One E 9,297,878.0 2021-06-0 and remediation works at Ug IDA / 51050 Watershed Management Infr Post Request for Bids Limited 7,650,000.00 Signed 2020-10-22 2020-12-09 2020-10-27 2020-12-09 2020-11-10 2020-12-23 2020-11-17 2021-01-18 2020-12-08 2021-02-15 nvelope 0 6 boha-Uzogban flood and gull astructure Investments y Erosion site, Central Senato rial district of Edo State NG-EDO SPMU-17119-CW-RF B / Reclamation, channeling Component 1: Erosion and and remediation works at Ek Single Stage - One E 2020-01-1 IDA / 51050 Watershed Management Infr Prior Request for Bids Open - National 2,500,000.00 0.00 Canceled 2017-06-06 2017-06-06 2018-09-10 2018-12-30 2019-01-15 ehuan Road Gully/West Moat nvelope 4 astructure Investments Flood and Gully Erosion catch ment area Phase 1 in Benin C ity NG-EDO SPMU-17125-CW-RF B / Reclamation, channeling Component 1: Erosion and Single Stage - One E 18,700,000.0 2018-09-2 and remediation works at NE IDA / 51050 Watershed Management Infr Prior Request for Bids Open - National 0.00 Canceled 2012-07-13 2012-07-13 2017-01-09 2017-02-21 2017-03-24 nvelope 0 1 W Flood and Gully Erosion Sit astructure Investments es in Edo State-EWU and IBO RE Page 1 NG-EDO SPMU-17126-CW-RF Component 1: Erosion and B / Reclamation, channeling Single Stage - One E 2017-12-1 IDA / 51050 Watershed Management Infr Post Request for Bids Open - National 2,500,000.00 0.00 Canceled 2012-07-13 2012-07-13 2017-04-10 2017-06-08 2017-07-04 and remediation works at Ikp nvelope 9 astructure Investments oba Hill Gully Erosion site NG-EDO SPMU-17112-CW-RF B / Reclamation, channeling Component 1: Erosion and Single Stage - One E 19,850,000.0 2016-03-1 and remediation works at Qu IDA / 51050 Watershed Management Infr Prior Request for Bids Open - National 0.00 Canceled 2012-07-13 2012-07-13 2014-07-22 2014-08-20 2014-09-22 nvelope 0 8 een Ede Secondary School Fl astructure Investments ood and Gully Erosion catch ment area in Benin City NG-EDO SPMU-96317-CW-RF B / Reclamation, channeling and remediation works at Ug boha-Uzogban flood and gull Component 1: Erosion and Open - Internationa Single Stage - One E 20,000,000.0 2021-04-2 y Erosion site, Central Senato IDA / 51050 Watershed Management Infr Prior Request for Bids 0.00 Canceled 2020-04-24 2020-04-29 2020-06-10 2020-07-10 2020-08-14 l nvelope 0 3 rial district of Edo State AND astructure Investments Complete Reclamation, chan neling and remediation work s at Iguosa flood and gully Er osion site, Benin City, Edo St ate NG-EDO SPMU-171910-CW-R FB / Reclamation, channeling Component 1: Erosion and Single Stage - One E 10,000,000.0 2021-06-1 and remediation works at Ug IDA / 51050 Watershed Management Infr Prior Request for Bids Open - National 0.00 Canceled 2020-07-10 2020-07-15 2020-08-14 2020-08-25 2020-09-18 nvelope 0 7 boha-Uzogban flood and gull astructure Investments y Erosion site, Central Senato rial district of Edo State NG-EDO SPMU-17117-CW-RF Component 1: Erosion and B / Reclamation, channeling Open - Internationa Single Stage - One E 42,500,000.0 2017-01-2 IDA / 51050 Watershed Management Infr Prior Request for Bids 0.00 Canceled 2012-07-13 2012-07-13 2014-08-27 2014-12-18 2015-01-22 and remediation works at Os l nvelope 0 0 astructure Investments hiobugie Flood and Gully Ero sion site at Auchi NG-EDO SPMU-72150B-CW-R FB / Preventive erosion interv ention/bioremediation activiti Component 1: Erosion and Single Stage - One E 2019-05-2 es for incipient gullies includi IDA / 51050 Watershed Management Infr Post Request for Bids Open - National 585,000.00 0.00 Canceled 2018-08-20 2018-08-25 2018-09-21 2018-10-21 2018-11-25 nvelope 4 ng enhancement of greening astructure Investments /vegetative cover/tree planti ng at queen ede, Auchi and E kehuan NG-EDO SPMU-299812-CW-R Component 4: Project Manag Request for Quota Single Stage - One E Other (with field f Pending Imp 2022-06-2 FQ / Renovation of NEWMAP/ IDA / 51050 Post Limited 200,000.00 0.00 2022-04-14 2022-05-02 ement tions nvelope or explanation) lementation 1 Agency Building GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-EDO SPMU-17135-GO-RF Q / Procurement of Computer Component 4: Project Manag Request for Quota Single Stage - One E Systems, Office, software, IC IDA / 51050 Post Open - National 20,000.00 4,213.07 Completed 2017-06-11 2017-07-09 2017-04-13 2017-08-29 2017-06-19 ement tions nvelope T equiment, Inverter and batt ery bank, and office Consum ables NG-EDO SPMU-17138-GO-RF Q / Office furniture's and Equi Component 4: Project Manag Request for Quota Single Stage - One E IDA / 51050 Post Open - National 5,000.00 5,294.76 Completed 2017-06-11 2017-07-09 2021-01-12 2017-07-20 2021-07-06 pment, and electrical and ele ement tions nvelope ctronics equipment NG-EDO SPMU-17143-GO-RF Component 4: Project Manag Request for Quota Single Stage - One E Q / procurement of 2 N0S.4- IDA / 51050 Post Open - National 400,000.00 289,183.13 Completed 2017-03-26 2017-04-14 2017-06-23 2017-05-26 2017-08-24 ement tions nvelope WD Pick up Vehicle and SUV. NG-EDO SPMU-17146-GO-RF Q / Procurement of Training Communication, Presentation Component 4: Project Manag Request for Quota Single Stage - One E , Media Equipment and mate IDA / 51050 Post Open - National 30,000.00 31,046.34 Signed 2017-06-11 2017-07-07 2021-01-12 2017-08-20 ement tions nvelope rials, etc Raincoats, PPE and Enumerators bags, P IEC mat erials, Community oriented I mplementation manuals. NG-EDO SPMU-96311-GO-RF Component 4: Project Manag Request for Quota Single Stage - One E Q / Procurement of Office fur IDA / 51050 Post Limited 10,000.00 7,391.53 Completed 2019-04-15 2020-12-18 2019-06-10 2021-01-12 2019-12-07 2021-06-29 ement tions nvelope nitures and Equipment NG-EDO SPMU-96302-GO-RF Q / Procurement of Personal Component 4: Project Manag Request for Quota Single Stage - One E Protective Equipment (PPE) a IDA / 51050 Post Limited 10,000.00 5,356.05 Signed 2019-04-15 2019-09-23 2019-06-10 2019-10-21 2019-12-07 ement tions nvelope nd Information, Education an d Communication (IEC)materi als- NG-EDO SPMU-96307-GO-RF Q / Office Equipment: Compu ter Accessories-laptops, Tabl ets,memory stck, External Ha Component 4: Project Manag Request for Quota Single Stage - One E rd Drive; Electrical and Electr IDA / 51050 Post Limited 35,000.00 17,262.15 Signed 2019-04-15 2019-08-02 2019-06-10 2019-08-20 2019-12-07 ement tions nvelope onics Equipment-Stabilizers, Deep cycle batteries: Trainin g, Communication and Prese ntation Equipment-Cameras, projectors, recorders NG-EDO SPMU-163839-GO-R FQ / Office Equipment: Comp uter Accessories-laptops, Tab lets,memory stck, External H Component 1: Erosion and Request for Quota Single Stage - One E ard Drive; Electrical and Elec IDA / 51050 Watershed Management Infr Post Limited 5,000.00 5,327.35 Completed 2020-04-13 2020-07-20 2020-05-25 2020-08-06 2020-06-25 2020-09-10 tions nvelope tronics Equipment-Stabilizers astructure Investments , Deep cycle batteries: Traini ng, Communication and Pres entation Equipment-Cameras , projectors, recorders NG-EDO SPMU-171914-GO-R Component 1: Erosion and FQ / Fish and Cassava Proces Request for Quota Single Stage - One E IDA / 51050 Watershed Management Infr Post Limited 100,000.00 98,633.63 Signed 2020-05-07 2020-06-01 2020-05-19 2020-06-12 2020-05-28 sing Plant using Renewable S tions nvelope astructure Investments olar Power Solution NG-EDO SPMU-171913-GO-R Component 1: Erosion and FQ / Ice Block and Ice Cubes Request for Quota Single Stage - One E IDA / 51050 Watershed Management Infr Post Limited 100,000.00 88,210.64 Signed 2020-05-07 2020-06-01 2020-05-17 2020-06-12 2020-05-28 Production Plant for women p tions nvelope astructure Investments owered by Renewable Solar P ower Solution Page 2 NG-EDO SPMU-171912-GO-R Component 1: Erosion and Request for Quota Single Stage - One E FQ / Renewable Solar Power IDA / 51050 Watershed Management Infr Post Limited 100,000.00 96,862.43 Signed 2020-05-08 2020-06-01 2020-05-22 2020-06-12 2020-05-29 tions nvelope Solution for PHC type B astructure Investments NG-EDO SPMU-165594-GO-R Component 1: Erosion and FB / Renewable Solar Power Single Stage - One E IDA / 51050 Watershed Management Infr Post Request for Bids Open - National 300,000.00 241,948.93 Signed 2020-06-14 2020-03-23 2020-06-15 2020-07-15 2020-04-22 2020-07-20 2020-04-30 2020-07-23 2020-05-04 2020-07-27 Solution for CIGs and reclaim nvelope astructure Investments ed land/park; PHC type A; an d PHC type B NG-EDO SPMU-181084-GO-R FQ / Procurement of Sanitizer Component 4: Project Manag Request for Quota Single Stage - One E s, anti viral diffusers, hand w IDA / 51050 Post Limited 5,000.00 5,233.37 Completed 2020-06-26 2020-06-24 2020-07-06 2020-07-06 2020-07-10 2020-07-23 ement tions nvelope ashing devices and accessori es for prevention of COVID-1 9 Pandemic for SPMU NG-EDO SPMU-179566-GO-R FB / Establishment of Solar P Component 1: Erosion and Single Stage - One E owered Agro-based Processin IDA / 51050 Watershed Management Infr Post Request for Bids Limited 600,000.00 366,961.02 Signed 2020-06-15 2020-06-15 2020-06-18 2020-06-15 2020-06-19 2020-06-19 2020-06-22 2020-06-22 2020-06-24 2020-06-24 2020-06-29 nvelope g/Livelihood enhancement Cl astructure Investments usters in Auchi, Benin and Ub iaja NG-EDO SPMU-179560-GO-R Component 1: Erosion and FB / Establishment of Solar P Single Stage - One E IDA / 51050 Watershed Management Infr Post Request for Bids Limited 350,000.00 182,213.62 Signed 2020-06-15 2020-06-15 2020-06-18 2020-06-15 2020-06-19 2020-06-19 2020-06-22 2020-06-22 2020-06-24 2020-06-24 2020-06-27 owered Recycling/Waste Man nvelope astructure Investments agement CIG clusters in Beni n, Auchi and Ekpoma NG-EDO SPMU-17150-GO-RF Q / Procurement of Weather Monitoring Stations, GPSs, La Component 4: Project Manag Request for Quota Single Stage - One E IDA / 51050 Post Open - National 10,000.00 0.00 Canceled 2017-06-11 2017-07-07 2017-08-18 ser Measures and Measuring ement tions nvelope Wheels, 1-2km Range Radios and other survey equipment and tools to gauge and NG-EDO SPMU-163840-GO-R FB / Procurement, Installation , Training and Commissionin Component 2: Erosion and g of Hydromet/Automatic Flo Watershed Management Inst Single Stage - One E od Early Warning System-AF IDA / 51050 Post Request for Bids Open - National 1,000,000.00 0.00 Canceled 2020-04-10 2020-04-15 2020-05-27 2020-06-26 2020-07-31 2021-01-27 itutions and Information Ser nvelope EWS at Agenebode and Ilushi vices , 3 units of Automatic Weath er Stations and DCP-Data Co llection Platform for River ga uging at Ikpoba River NG-EDO SPMU-299816-GO-R Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl FQ / Procurement of Furnitur IDA / 51050 Post Limited 100,000.00 0.00 2022-05-06 2022-05-23 2022-06-22 ement tions nvelope ementation e and Fittings NG-EDO SPMU-299813-GO-R FQ / Procurement of GNSS Dr Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl IDA / 51050 Post Limited 100,000.00 0.00 2022-05-06 2022-05-24 2022-06-23 one Hardware and equipmen ement tions nvelope ementation t for Engineering Design NG-EDO SPMU-299836-GO-R FQ / Procurement of LAN , Wi Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl IDA / 51050 Post Limited 50,000.00 0.00 2022-05-06 2022-05-24 2022-06-23 relesss Network, Server and ement tions nvelope ementation Telephony for NEWMAP/Agen cy NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-EDO SPMU-96167-NC-RF Component 4: Project Manag Request for Quota Single Stage - One E Q / Procurement of Broadban IDA / 51050 Post Limited 35,000.00 2,981.95 Signed 2019-04-15 2020-10-30 2019-06-10 2020-11-16 2019-12-07 ement tions nvelope d Internet Service CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-EDO SPMU-17077-CS-CQ Component 1: Erosion and Consultant Qualifi S / Consultancy for Water Ha IDA / 51050 Watershed Management Infr Post Open - National 150,000.00 146,004.86 Signed 2016-02-05 2016-01-11 2016-02-05 2016-02-05 2016-12-01 2016-02-26 2017-03-29 2017-02-16 2017-07-12 2017-05-16 cation Selection rvesting-ONGOING astructure Investments NG-EDO SPMU-17069-CS-CQ S / Consultancy for the gener Component 1: Erosion and ation of Land Resources Inve Consultant Qualifi IDA / 51050 Watershed Management Infr Post Open - National 95,000.00 93,773.32 Completed 2015-02-05 2015-12-11 2015-02-05 2016-02-05 2016-11-24 2016-02-26 2017-06-02 2017-02-16 2017-07-18 2017-05-16 2020-06-01 ntory Data (LRID) for erosion cation Selection astructure Investments sites, infrastructure, watersh eds, wetlands (GIS survey)-O NGOING NG-EDO SPMU-72134-CS-QC Component 1: Erosion and Quality And Cost- Open - Internationa BS / Supervision of civil work IDA / 51050 Watershed Management Infr Prior 2,600,000.00 1,764,478.40 Signed 2018-08-20 2018-08-12 2018-09-10 2018-08-16 2018-10-24 2019-02-26 2018-11-21 2019-04-03 2018-12-21 2019-06-20 2019-01-25 2019-09-04 2019-03-01 2019-09-19 2020-02-29 Based Selection l s at New Flood and gully eros astructure Investments ion Sites NG-EDO SPMU-72151-CS-CQ Component 1: Erosion and Consultant Qualifi S / Engagement of Focal NGO IDA / 51050 Watershed Management Infr Post Open - National 200,000.00 229,969.12 Signed 2018-08-20 2018-11-08 2018-09-10 2018-10-15 2019-03-26 2018-11-01 2019-07-24 2018-12-06 2019-08-14 2020-12-04 cation Selection to support project impliment astructure Investments ation-new NG-EDO SPMU-96301-CS-CQ Component 1: Erosion and S / Consultancy for the Engin Consultant Qualifi IDA / 51050 Watershed Management Infr Post Open - National 100,000.00 91,542.40 Completed 2019-02-10 2018-11-08 2019-03-03 2019-04-16 2019-02-07 2019-05-16 2019-02-25 2019-06-20 2019-03-05 2019-12-17 2020-05-06 eering design for Iguosa floo cation Selection astructure Investments d and gully Erosion site, Beni n City, Edo State NG-EDO SPMU-96298-CS-CQ S / Consultancy for the Engin Component 1: Erosion and Consultant Qualifi eering design for Ugboha-Uz IDA / 51050 Watershed Management Infr Post Limited 100,000.00 70,033.12 Completed 2019-09-10 2019-09-03 2019-09-24 2019-09-17 2019-10-24 2019-10-09 2019-11-28 2019-10-16 2020-05-26 2020-12-09 cation Selection ogban flood and gully Erosio astructure Investments n site, Central Senatorial dist rict of Edo State NG-EDO SPMU-163832-CS-C QS / Consultancy for the prep Component 1: Erosion and Consultant Qualifi aration of catchment manag IDA / 51050 Watershed Management Infr Post Limited 300,000.00 287,027.41 Signed 2020-04-10 2020-05-11 2020-04-24 2020-06-30 2020-05-24 2020-08-05 2020-06-28 2020-08-07 2020-12-25 cation Selection ement plan for flood and gull astructure Investments y erosion sites in Edo State-N EW Page 3 NG-EDO SPMU-17109-CS-QC BS / Procurement of consulta Component 1: Erosion and nts for study/ designs of Ten Quality And Cost- Open - Internationa IDA / 51050 Watershed Management Infr Prior 2,400,000.00 0.00 Canceled 2013-09-06 2013-10-24 2013-12-27 2014-02-04 2014-02-19 2014-03-07 2014-04-09 2016-04-08 (10) additional erosion sites Based Selection l astructure Investments and supervision of civil works +Supervision of Ekehuan, Au chi and Queen ede sites NG-EDO SPMU-17051-CS-CQ Component 1: Erosion and Consultant Qualifi S / Consultancy of Sevices of IDA / 51050 Watershed Management Infr Post Open - National 200,000.00 0.00 Canceled 2014-12-22 2014-12-22 2015-04-10 2015-04-28 2015-05-12 2017-06-20 cation Selection Focal NGO astructure Investments NG-EDO SPMU-17098-CS-QC BS / Procurement of consulta Component 1: Erosion and Quality And Cost- Open - Internationa nts for supervision of civil wo IDA / 51050 Watershed Management Infr Prior 960,000.00 0.00 Canceled 2013-09-07 2013-10-29 2014-01-07 2014-02-04 2014-02-19 2014-03-07 2014-04-09 2017-09-29 Based Selection l rks at Ekehuan, Auchi and Qu astructure Investments een ede sites and new sites NG-EDO SPMU-17096-CS-QC Component 2: Erosion and Quality And Cost- Open - Internationa BS / Urban and Storm Water IDA / 51050 Watershed Management Inst Prior 4,000,000.00 0.00 Canceled 2017-06-30 2017-08-31 2017-10-31 2018-01-08 2018-02-09 2018-03-29 2018-04-27 2018-11-30 Based Selection l Master Plan for larger Benin itutions and Information Ser City vices INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-EDO SPMU-17088-CS-IN Component 4: Project Manag Individual Consult DV / Consultancy for M & E B IDA / 51050 Post Open 60,000.00 47,725.65 Completed 2017-01-13 2017-01-16 2017-01-13 2017-01-16 2017-02-10 2017-02-10 2017-02-20 2017-02-15 2017-05-03 2017-10-13 ement ant Selection aseline data for New Sites-Ga piona and Urora NG-EDO SPMU-17094-CS-CD Component 1: Erosion and S / Consultancy for design of IDA / 51050 Watershed Management Infr Post Direct Selection Direct 100,000.00 74,796.02 Signed 2017-06-06 2016-12-28 2017-06-06 2016-12-29 2017-06-30 2017-07-12 2017-09-22 emergency works for incipien astructure Investments t gullies requiring rapid actio n-several NG-EDO SPMU-17040-CS-IN Component 1: Erosion and DV / Consultancy for M & E B Individual Consult IDA / 51050 Watershed Management Infr Post Open 100,000.00 51,139.00 Completed 2017-01-13 2017-01-16 2017-01-13 2017-01-16 2017-02-10 2017-02-10 2017-02-20 2017-02-15 2017-05-03 2017-11-04 aseline data for New Sites-Ib ant Selection astructure Investments ore, Ewu and Fugar-Agenebo de Road NG-EDO SPMU-17048-CS-IN Component 1: Erosion and DV / Consultancy for M & E B Individual Consult IDA / 51050 Watershed Management Infr Post Open 95,000.00 38,168.96 Completed 2017-02-06 2017-10-04 2017-02-06 2017-10-04 2017-02-24 2017-11-02 2017-02-24 2017-11-13 2017-05-23 2019-12-13 aseline data for New Sites-Ed ant Selection astructure Investments o College and Ogiso-Osunde NG-EDO SPMU-17042-CS-IN Component 1: Erosion and DV / Consultancy for M & E B Individual Consult IDA / 51050 Watershed Management Infr Post Open 95,000.00 58,114.38 Completed 2017-02-06 2017-09-01 2017-02-06 2017-10-23 2017-02-24 2017-11-02 2017-02-24 2017-11-13 2017-05-23 2019-07-17 aseline data for New Sites-E ant Selection astructure Investments mu, AAU and Igbe Quarters NG-EDO SPMU-17029-CS-IN DV / Consultancy for the deta Component 1: Erosion and Individual Consult iled RAP, and Socio-Economic IDA / 51050 Watershed Management Infr Post Open 95,000.00 37,215.75 Completed 2017-02-06 2017-08-30 2017-02-06 2017-09-28 2017-02-24 2017-10-13 2017-02-24 2017-10-31 2017-05-23 2020-02-20 ant Selection Studies for New Sites-Edo Col astructure Investments lege, Ogiso-Osunde and AAU NG-EDO SPMU-17032-CS-IN DV / Consultancy for the deta Component 1: Erosion and Individual Consult iled RAP, and Socio-Economic IDA / 51050 Watershed Management Infr Post Open 95,000.00 36,396.25 Completed 2017-02-06 2017-08-30 2017-02-06 2017-09-28 2017-02-24 2017-10-13 2017-02-24 2017-10-30 2017-05-23 2020-03-31 ant Selection Studies for New Sites-EMU, Ig astructure Investments be quarters and Fugar-Agene bode road NG-EDO SPMU-17037-CS-IN Component 1: Erosion and DV / Consultancy for the deta Individual Consult IDA / 51050 Watershed Management Infr Post Open 100,000.00 58,509.00 Completed 2017-01-13 2017-01-12 2017-01-13 2017-01-13 2017-02-10 2017-02-10 2017-02-20 2017-02-15 2017-05-03 2017-07-20 iled ESIA, for Flood and Gully ant Selection astructure Investments Erosion in Edo State-NEW-1- GAPIONA and URORA NG-EDO SPMU-17044-CS-IN Component 1: Erosion and DV / Consultancy for the deta Individual Consult IDA / 51050 Watershed Management Infr Post Open 100,000.00 36,960.00 Completed 2017-01-13 2017-01-12 2017-01-13 2017-01-13 2017-02-10 2017-02-10 2017-02-20 2017-02-15 2017-05-03 2017-10-20 iled ESIA, for Flood and Gully ant Selection astructure Investments Erosion in Edo State-NEW-2-I BORE, EWU NG-EDO SPMU-17038-CS-IN DV / Consultancy for the deta Component 1: Erosion and Individual Consult iled ESIA, for Flood and Gully IDA / 51050 Watershed Management Infr Post Open 90,000.00 51,067.50 Completed 2017-02-06 2017-09-22 2017-02-06 2017-10-06 2017-02-24 2017-10-24 2017-02-24 2017-10-27 2017-05-23 2019-07-23 ant Selection Erosion in Edo State-New Site astructure Investments s-AAU, Edo College and Ogis o-Osunde NG-EDO SPMU-17050-CS-IN DV / Consultancy for the deta Component 1: Erosion and iled ESIA, for Flood and Gully Individual Consult IDA / 51050 Watershed Management Infr Post Open 90,000.00 67,193.50 Completed 2017-02-06 2017-09-12 2017-02-06 2017-10-06 2017-02-24 2017-10-24 2017-02-24 2017-10-27 2017-05-23 2018-12-03 Erosion in Edo State-New Site ant Selection astructure Investments s-Emu-Ohodua, Igbe Quarter s and FUGAR AGENEBODE R OAD NG-EDO SPMU-96184-CS-IN DV / Consultancy for M & E B aseline data for Iguosa flood Component 1: Erosion and Individual Consult and gully Erosion site, Benin IDA / 51050 Watershed Management Infr Post Limited 100,000.00 35,185.63 Completed 2019-08-10 2019-11-29 2019-08-15 2019-12-09 2019-09-05 2019-12-24 2019-10-10 2020-01-07 2020-04-07 2021-06-18 ant Selection City, Edo State and for Ugbo astructure Investments ha-Uzogban flood and gully E rosion site, Central Senatorial district of Edo State NG-EDO SPMU-96179-CS-IN DV / Consultancy for the deta iled RAP, and Socio-Economic Component 1: Erosion and Studies for Iguosa flood and Individual Consult IDA / 51050 Watershed Management Infr Post Limited 50,000.00 38,903.04 Completed 2019-08-10 2019-11-29 2019-08-15 2019-11-29 2019-09-05 2019-12-11 2019-10-10 2019-12-30 2020-04-07 2021-06-29 gully Erosion site, Benin City, ant Selection astructure Investments Edo State and for Ugboha-Uz ogban flood and gully Erosio n site, Central Senatorial dist rict of Edo State NG-EDO SPMU-96187-CS-IN DV / Consultancy for the deta iled ESMP, for Iguosa flood an Component 1: Erosion and Individual Consult d gully Erosion site, Benin Cit IDA / 51050 Watershed Management Infr Post Limited 50,000.00 36,024.17 Completed 2019-08-10 2019-11-29 2019-08-15 2019-12-12 2019-09-05 2020-01-06 2019-10-10 2020-01-17 2020-04-07 2021-05-11 ant Selection y, Edo State and for Ugboha- astructure Investments Uzogban flood and gully Eros ion site, Central Senatorial di strict of Edo State Page 4 NG-EDO SPMU-17062-CS-IN DV / Consultancy for sensitiz Component 4: Project Manag Individual Consult ation on Livelihood, Watersh IDA / 51050 Post Open 90,000.00 0.00 Canceled 2014-05-27 2014-07-07 2014-07-31 2014-08-08 2015-04-27 ement ant Selection ed Management & Engineeri ng designs for Erosion Manag ement-ON GOING NG-EDO SPMU-17064-CS-IN Component 4: Project Manag Individual Consult DV / Consultancy for Liveliho IDA / 51050 Post Open 90,000.00 0.00 Canceled 2014-07-07 2014-07-07 2014-07-31 2014-08-08 2015-04-27 ement ant Selection od Needs Assessment-ON-GO ING NG-EDO SPMU-17081-CS-IN DV / Consultancy for Environ Component 4: Project Manag Individual Consult IDA / 51050 Post Open 90,000.00 0.00 Canceled 2014-05-27 2014-07-07 2014-07-31 2014-08-08 2015-04-27 mental and Social Safeguard ement ant Selection Sensitization on Erosion Cont rol-on going NG-EDO SPMU-96316-CS-IN DV / Consultancy for the prep Component 1: Erosion and Individual Consult aration of catchment manag IDA / 51050 Watershed Management Infr Post Limited 100,000.00 0.00 Canceled 2019-04-10 2019-04-15 2019-05-06 2019-06-10 2019-12-07 ant Selection ement plan for flood and gull astructure Investments y erosion sites in Edo State NG-EDO SPMU-17085-CS-IN Component 1: Erosion and Individual Consult DV / Consultancy on Bioreme IDA / 51050 Watershed Management Infr Post Open 30,000.00 0.00 Canceled 2017-02-06 2017-06-06 2017-06-30 2017-06-30 2017-09-22 ant Selection diation works astructure Investments NG-EDO SPMU-171911-CS-IN DV / Consultancy for the Retr Component 1: Erosion and Individual Consult ofitting of ESMPs to address IDA / 51050 Watershed Management Infr Post Limited 100,000.00 0.00 Canceled 2020-06-10 2020-06-15 2020-07-06 2020-07-24 2020-10-23 ant Selection and include issues of GBV/SE astructure Investments A for flood and gully erosion sites in Edo State Page 5