Procurement Plan I. General 1. Project Information Country: Tanzania Project Name: Second Water Sector Support Project (WSSP II) Project ID: P150361 2. Project Implementation Agency: Ministry of Water and Irrigation Dar es Salaam Water Supply and Sewerage Authority Dar es Salaam Water Supply ans Sewerage Corporation 3. Date of the Procurement Plan: April 2017 4. Period Covered by this Procurement Plan: First 18 Months II. Thresholds for Prior Review, Procurement Approaches and Methods A. Goods, Works and Non-Consulting Services Procurement Approaches and Methods (US$ Prior Review millions) Category (US$ Open Open Request for millions) International National Quotation (RfQ) Works ≥ 10 ≥ 15.0 < 15 ≤ 0.2 Goods, IT, and non- ≥2 ≥5 <5 ≤ 0.1 consulting services B. Consulting Services Category Prior Review Short List of National Consultants (US$ (US$ million) millions) Consulting Engineering and Services Construction Supervision Consultants ≥1 ≤ 0.3 ≤ 0.3 (Firms) Individual ≥ 0.3 NA. NA. Consultants [Overall Project Procurement Risk is SUBSTANTIAL] Notes: 1 Terms of Reference: Terms of Reference for all contracts shall be cleared by the Bank, regardless of whether the assignment is for prior or post review. Advertisement: Consultancy Service for Contracts estimated to cost US$ 300,000 equivalent and above per contract shall be advertised in UNDB online in addition to advertising in National News Paper(s) of wide circulation and/or Regional News Paper(s). 2 PROCUREMENT Tanzania : Second Tanzania Water Sector Support Project PLAN General Information Country: Tanzania 2017-04-13 Bank’s Approval Date of the Original Procurement Plan: 2022-06-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150361 GPN Date: Project Name: Second Tanzania Water Sector Support Project Loan / Credit No: IDA / 59490, IDA / V0310 Ministry of Water and Irrigation Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned TZ-MOW-12669-CW-RFB / Dr Component 1: Integrated W illing Works for Ground Water Single Stage - One E Pending Imp 2018-06-2 IDA / 59490 ater Resources Management Post Request for Bids Open - National 1,000,000.00 0.00 2017-09-01 2017-09-06 2017-10-18 2017-11-17 2017-12-22 Monitoring Network in Wami- nvelope lementation 0 (IWRM) Ruvu and Internal Drainage B asins TZ-MOW-12671-CW-RFB / Ci Component 1: Integrated W vil Works Construction and In Single Stage - One E Pending Imp 2019-04-2 IDA / 59490 ater Resources Management Post Request for Bids Open - National 2,750,000.00 0.00 2018-07-02 2018-07-07 2018-08-18 2018-09-17 2018-10-22 stallation of Water Resources nvelope lementation 0 (IWRM) Monitoring Gauges in all the nine Basins in Tanzania TZ-MOW-12670-CW-RFB / Co nstruction of office and water laboratory buildings for Wam i-Ruvu Basin Water Board (B Component 1: Integrated W Single Stage - One E 2019-03-2 WB) Headquarter at Morogor IDA / 59490 ater Resources Management Post Request for Bids Open - National 1,000,000.00 0.00 Canceled 2018-06-04 2018-06-09 2018-07-21 2018-08-20 2018-09-24 nvelope 3 o and Water Users Associatio (IWRM) n (WUA) Offices at Msowero and rehabilitation and extens ion of office building for Wam i-Ruvu BWB in Dodoma. TZ-MOW-12673-CW-RFB / Co Component 1: Integrated W nstruction of Office Block for Single Stage - One E Under Imple 2019-12-2 IDA / 59490 ater Resources Management Post Request for Bids Open - National 800,000.00 816,064.67 2019-03-04 2020-06-18 2019-03-09 2020-08-06 2019-04-20 2020-09-08 2019-05-20 2020-10-15 2019-06-24 the Proposed Water Resourc nvelope mentation 1 (IWRM) es Centre of Excellency (COE ) in Dodoma TZ-MOW-259632-CW-RFB / Request for Bids - Component 1: Integrated W Drilling works for ground wat Single Stage - One E Small Works SPD Pending Imp 2022-09-1 IDA / 59490 ater Resources Management Post Request for Bids Open - National 2,810,000.00 0.00 2021-11-22 2021-11-27 2021-12-27 2022-01-17 2022-03-14 er monitoring in 4 Basins- Wa nvelope (1 envelope proce lementation 0 (IWRM) mi-Ruvu, Pangani, Rufiji, and ss) Internal drainage GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MOW-12602-GO-RFB / Su Component 1: Integrated W Single Stage - One E pply of Motorbikes and Bicycl IDA / 59490 ater Resources Management Post Request for Bids Open - National 350,000.00 19,504.05 Signed 2017-07-03 2018-10-05 2017-07-08 2017-08-07 2018-10-26 2017-08-21 2018-10-26 2017-09-25 2019-03-22 2017-11-24 nvelope es (100 of each) to support 1 (IWRM) 00 WUAs TZ-MOW-12667-GO-RFB / Su Component 1: Integrated W pply of office data managem Single Stage - One E IDA / 59490 ater Resources Management Post Request for Bids Open - National 1,250,000.00 818,766.58 Signed 2018-03-01 2018-06-26 2018-03-06 2018-04-05 2018-07-20 2018-05-05 2018-09-19 2018-06-09 2019-07-01 2018-09-07 ent tools and equipment incl nvelope (IWRM) uding ICT equipment TZ-MOW-12610-GO-RFP / Su Component 1: Integrated W Single Stage - One E Pending Impl pply of water quality monitori IDA / 59490 ater Resources Management Post Request for Bids Open - National 300,000.00 0.00 2017-07-01 2017-07-06 2017-08-05 2017-09-04 2017-10-09 2018-04-07 nvelope ementation ng equipment and tools (IWRM) TZ-MOW-12605-GO-RFB / Su pply of surface and groundw Component 1: Integrated W Single Stage - One E Pending Impl ater monitoring network gau IDA / 59490 ater Resources Management Prior Request for Bids Open - National 3,200,000.00 0.00 2017-07-03 2017-07-08 2017-08-07 2017-09-06 2017-10-11 2018-04-09 nvelope ementation ges monitoring instruments f (IWRM) or large dams and sediment monitoring equipment TZ-MOW-10924-GO-RFB / Su Component 1: Integrated W Single Stage - One E pply of Water Users Associati IDA / 59490 ater Resources Management Post Request for Bids Open - National 150,000.00 252,960.06 Signed 2017-05-30 2018-08-07 2017-06-04 2017-06-25 2018-08-30 2017-07-25 2018-09-07 2017-08-29 2019-04-18 2017-11-27 nvelope ons Survival Working Kits (IWRM) TZ-MOW-63646-GO-RFQ / Pu rchase of office equipments ( Component 4: Project mana Laptop Desktop, Ups, Netwo Request for Quota Single Stage - One E Pending Impl IDA / 59490 gement and Implementation Post Open - National 40,010.20 0.00 2018-08-06 2018-10-01 2019-03-30 rk Printer, Scanner, Photocop tions nvelope ementation Support ier, Projector, WiFi Router, Pri nter LaserJet pro M402dne, G armin GPS NAVA F 78) TZ-MOW-70318-GO-UN / Sup Component 1: Integrated W ply of eighteen four-Wheel Dr UN Agencies (Dire IDA / 59490 ater Resources Management Prior Direct 1,080,000.00 847,979.00 Signed 2018-08-22 2019-07-09 2018-08-27 2019-07-09 2018-10-01 2019-06-30 2019-03-30 ive Vehicles for the Basin Wa ct) (IWRM) ter Boards and MoWI's Divisi on of WR. TZ-MOW-12668-GO-RFB / Su Component 1: Integrated W Single Stage - One E pply of Communication Strat IDA / 59490 ater Resources Management Post Request for Bids Open - National 200,000.00 0.00 Canceled 2018-09-27 2018-10-02 2018-11-01 2018-12-01 2019-01-05 2019-04-05 nvelope egy Materials (IWRM) TZ-MOW-109251-GO-RFB / S Component 1: Integrated W Single Stage - One E Pending Impl upply and Installation of Dam IDA / 59490 ater Resources Management Post Request for Bids Open - National 240,000.00 0.00 2019-04-12 2019-04-17 2019-05-29 2019-06-28 2019-08-02 2020-01-29 nvelope ementation safety Monitoring Instrument (IWRM) s TZ-MOW-63647-GO-RFQ / Pu Component 4: Project mana Request for Quota Single Stage - One E Pending Impl rchase of office equipment to IDA / 59490 gement and Implementation Post Open - National 17,418.50 0.00 2018-08-20 2018-10-15 2019-04-13 tions nvelope ementation support three consultant of Support WSSP II project TZ-MOW-113290-GO-RFB / P Component 4: Project mana Single Stage - One E urchase of office furniture's f IDA / 59490 gement and Implementation Post Request for Bids Open - National 175,000.00 0.00 Canceled 2019-05-08 2019-05-13 2019-06-23 2019-07-23 2019-08-27 2020-02-23 nvelope or MoW through support of W Support SSP II Project TZ-MOW-109947-GO-RFB / P Component 4: Project mana urchase of three motor vehicl Single Stage - One E IDA / 59490 gement and Implementation Post Request for Bids Open - National 136,363.64 0.00 Canceled 2019-04-23 2019-04-28 2019-06-09 2019-07-09 2019-08-13 2020-02-09 es for PDCU to support WSS nvelope Support P II implementation Page 1 TZ-MOW-118055-GO-UN / Pu Component 4: Project mana rchase of three motor vehicle UN Agencies (Dire IDA / 59490 gement and Implementation Post Direct 136,363.64 108,343.00 Signed 2019-06-13 2019-06-13 2019-06-18 2019-06-11 2019-07-23 2019-09-04 2020-01-19 s for PDCU to support WSSP I ct) Support I implementation TZ-MOW-121119-GO-UN / Su Component 1: Integrated W pply of Five (5) Four Wheel D UN Agencies (Dire IDA / 59490 ater Resources Management Post Direct 350,000.00 217,314.00 Signed 2019-07-05 2019-07-26 2019-07-10 2019-07-26 2019-08-14 2019-11-01 2020-02-10 rive Vehicles for Water Resou ct) (IWRM) rces Center of Excellence (W RCoE) TZ-MOW-136409-GO-RFB / S Component 1: Integrated W Single Stage - One E upply of Dam Safety Working IDA / 59490 ater Resources Management Post Request for Bids Open - National 410,586.00 343,956.94 Signed 2019-10-07 2019-10-15 2019-10-12 2019-11-23 2020-03-03 2019-12-23 2020-05-04 2020-01-27 2020-10-02 2020-07-25 nvelope Tools Equipment and Softwar (IWRM) e TZ-MOW-153185-GO-RFQ / S Component 1: Integrated W Request for Quota Single Stage - One E upply of Communication Stra IDA / 59490 ater Resources Management Post Limited 51,222.00 30,127.31 Signed 2020-01-29 2020-02-14 2020-03-25 2020-05-12 2020-09-21 tions nvelope tegy Materials (IWRM) TZ-MOW-157301-GO-UN / Su Component 1: Integrated W UN Agencies (Dire pply of Four (4) 4Wheel Drive IDA / 59490 ater Resources Management Post Direct 180,000.00 178,774.91 Signed 2020-02-07 2020-02-07 2020-02-12 2020-06-15 2020-03-27 2020-10-27 2020-06-28 ct) Vehicles for the Basin Water (IWRM) Boards TZ-MOW-172132-GO-RFB / S upply of Data Management T ools and Equipments Includin Component 1: Integrated W Single Stage - One E g ICT Equipment- (Heavy Dut IDA / 59490 ater Resources Management Post Request for Bids Open - National 575,000.00 570,440.67 Signed 2020-05-25 2020-07-27 2020-05-30 2020-07-27 2020-07-11 2020-08-18 2020-08-10 2020-09-02 2020-09-14 2021-02-11 2021-01-12 nvelope y Desktop & Laptops, Indoor (IWRM) Electric Display Boards and A ccessories, Multimedia Projec tors and A3 Scanners TZ-MOW-173143-GO-RFQ / S Component 1: Integrated W Request for Quota Single Stage - One E upply of Water Users Associa IDA / 59490 ater Resources Management Post Limited 27,000.00 25,727.62 Signed 2020-05-31 2020-06-17 2020-07-26 2020-09-10 2020-10-24 tions nvelope tion Survival Working Kits - O (IWRM) ffice Cabinets TZ-MOW-173510-GO-RFQ / P Component 4: Project mana Request for Quota Single Stage - One E IDA / 59490 Post Limited 95,000.00 121,437.11 Signed 2019-05-14 2019-05-14 2019-07-02 2019-07-31 2019-08-01 rocurement of Office Furnitur gement and Implementation tions nvelope e for MOW Support TZ-MOW-174173-GO-UN / Su Component 4: Project mana UN Agencies (Dire IDA / 59490 Post Direct 454,300.00 302,502.68 Signed 2020-05-26 2020-05-15 2020-05-31 2020-05-19 2020-07-21 2020-09-25 2021-01-17 pply of Nine (9) Motor Vehicl gement and Implementation ct) es Support TZ-MOW-160562-GO-RFB / S Component 4: Project mana Single Stage - One E upply of ICT Equipment and S IDA / 59490 gement and Implementation Post Request for Bids Open - National 281,080.91 0.00 Canceled 2020-02-28 2020-04-03 2020-03-10 2020-04-03 2020-03-31 2020-04-23 2020-04-14 2020-05-12 2020-05-19 2020-08-22 nvelope oftware for Implementation o Support f WSSP II TZ-MOW-182042-GO-RFB / S Component 4: Project mana upply, Installation and Comm Single Stage - One E IDA / 59490 gement and Implementation Post Request for Bids Open - National 282,000.00 399,861.53 Signed 2020-07-09 2020-07-12 2020-07-13 2020-07-12 2020-08-03 2020-08-03 2020-08-17 2020-08-14 2020-09-03 2021-01-13 2020-10-18 issioning of ICT Equipment a nvelope Support nd Software for WSSP II TZ-MOW-148402-GO-UN / Su Component 1: Integrated W UN Agencies (Dire pply of Four (4) Four Wheel IDA / 59490 ater Resources Management Post Direct 180,000.00 0.00 Canceled 2020-01-08 2020-01-13 2020-02-17 2020-08-15 ct) Motor Vehicles for the Basin (IWRM) Water Boards TZ-MOW-11480-GO-RFB / Su Component 1: Integrated W pply of eighteen four-Wheel Single Stage - One E IDA / 59490 ater Resources Management Post Request for Bids Open - National 1,080,000.00 0.00 Canceled 2017-07-03 2017-07-08 2017-08-07 2017-08-28 2017-10-02 2017-12-31 Drive Vehicles for the Basin nvelope (IWRM) Water Boards and MoWI's Div ision of WR. TZ-MOW-203764-GO-RFB / S upply office furniture (office t Component 4: Project mana Single Stage - One E ables, office chairs, office ca IDA / 59490 gement and Implementation Post Request for Bids Open - National 150,000.00 74,137.96 Signed 2021-01-07 2021-06-21 2021-01-12 2021-02-23 2021-07-13 2021-03-25 2021-07-22 2021-04-29 2021-11-24 2021-10-26 nvelope binets) for WAMI/RUVU and D Support AWASA (DID, OFF GRID, PRO CUREMENT, SAFEGUARD) TZ-MOW-203759-GO-RFQ / S Component 4: Project mana Request for Quota Single Stage - One E Pending Impl upply of Design Software, Sta IDA / 59490 gement and Implementation Post Open - National 73,000.00 0.00 2020-12-09 2021-02-03 2021-08-02 tions nvelope ementation tistical Package, MS Project Support TZ-MOW-228544-GO-RFB / S Component 1: Integrated W upply, Installation and Comm Single Stage - One E IDA / 59490 ater Resources Management Post Request for Bids Open - National 160,000.00 36,790.82 Signed 2021-04-27 2021-06-07 2021-05-02 2021-06-07 2021-05-23 2021-06-28 2021-06-06 2021-07-06 2021-07-11 2022-01-06 2021-11-08 issioning of ICT Equipment in nvelope (IWRM) cluding Video Conference Fa cility TZ-MOW-261343-GO-RFQ / P Component 4: Project mana Request for Quota Single Stage - One E Under Imple IDA / 59490 Post Open - National 24,937.30 0.00 2021-11-20 2022-01-15 2022-07-14 rocurement of Video Confere gement and Implementation tions nvelope mentation nce Support TZ-MOW-261339-GO-RFQ / S upply, installation and commi Component 4: Project mana ssion Cybersecurity Software Request for Quota Single Stage - One E Pending Impl IDA / 59490 gement and Implementation Post Open - National 15,000.00 0.00 2021-11-20 2022-01-15 2022-07-14 (SOPHOS) and Corporate Anti tions nvelope ementation Support virus License Software to sec ure data and information for MoW and WSSP II MoW. TZ-MOW-262387-GO-RFB / S Component 4: Project mana Single Stage - One E Pending Impl upply, Installation and Comm IDA / 59490 gement and Implementation Post Request for Bids Open - National 212,000.00 0.00 2021-11-23 2021-11-28 2021-12-28 2022-01-11 2022-02-15 2022-08-14 nvelope ementation issioning of ICT Equipment a Support nd Software TZ-MOW-265345-GO-RFQ / S Component 4: Project mana Request for Quota Single Stage - One E Pending Impl upply of ICT Equipment for W IDA / 59490 gement and Implementation Post Open - National 17,000.00 0.00 2021-12-17 2022-02-11 2022-08-10 tions nvelope ementation ater Institute Support TZ-MOW-265350-GO-RFQ / S Component 4: Project mana Request for Quota Single Stage - One E Under Imple IDA / 59490 Post Open - National 19,000.00 0.00 2021-12-17 2022-02-11 2022-08-10 upply of Furniture for Water I gement and Implementation tions nvelope mentation nstitute Support TZ-MOW-294826-GO-DIR / Pr Component 4: Project mana Pending Impl ocurement of Five (5) motor IDA / 59490 gement and Implementation Post Direct Selection Direct 160,000.00 0.00 2022-06-03 2022-06-17 2022-07-15 2023-01-11 ementation vehicles for WSSP II Support TZ-MOW-300022-GO-RFB / S Component 1: Integrated W upply, Installation, Commissi Open - Internationa Single Stage - One E Pending Impl IDA / 59490 ater Resources Management Prior Request for Bids 3,000,000.00 0.00 2022-06-22 2022-06-29 2022-07-29 2022-08-19 2022-09-23 2023-03-22 oning and after sales service l nvelope ementation (IWRM) s of water resources monitori ng networks NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 TZ-MOW-153183-NC-DIR / Pr Component 1: Integrated W Under Imple inting of Communication Stra IDA / 59490 ater Resources Management Post Direct Selection Direct 148,778.00 0.00 2020-01-24 2020-02-14 2020-01-29 2020-02-14 2020-03-04 2020-08-31 mentation tegy Materials (IWRM) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MOW-11548-CS-CQS / Co Component 1: Integrated W nsultancy Services for Techni Consultant Qualifi Pending Impleme IDA / 59490 ater Resources Management Post Open - National 100,000.00 0.00 2017-08-30 2017-09-20 2017-11-03 2017-12-03 2018-01-07 2018-07-06 cal Assistance on Preparation cation Selection ntation (IWRM) of Water Resources Use Char ges Regulations TZ-MOW-11553-CS-CQS / Co Component 1: Integrated W nsultancy for Development a Consultant Qualifi IDA / 59490 ater Resources Management Post Open - National 150,000.00 222,121.00 Signed 2017-09-20 2017-05-18 2017-10-11 2018-03-20 2017-11-24 2018-06-07 2017-12-24 2018-07-06 2018-01-28 2020-08-14 2018-07-27 nd Implementation of Labora cation Selection (IWRM) tory Information Managemen t System TZ-MOW-11854-CS-QCBS / C Component 1: Integrated W Quality And Cost- Open - Internationa onsultancy services for Natio IDA / 59490 ater Resources Management Prior 1,750,000.00 1,644,924.09 Signed 2017-08-18 2018-01-10 2017-09-08 2018-08-09 2017-10-22 2019-01-11 2017-11-19 2019-03-15 2017-12-19 2019-07-19 2018-01-23 2019-10-08 2018-02-27 2019-12-18 2019-02-27 Based Selection l nal Hydrological Aquifer Map (IWRM) ping TZ-MOW-11857-CS-QCBS / C onsultancy Services for Oper Component 1: Integrated W Quality And Cost- Open - Internationa ational Decision Support Syst IDA / 59490 ater Resources Management Prior 2,500,000.00 3,702,347.25 Signed 2017-10-05 2017-11-04 2018-08-09 2017-12-18 2019-01-18 2018-01-15 2019-03-15 2018-02-14 2019-07-17 2018-03-21 2020-05-04 2018-04-25 2020-09-18 2019-04-25 Based Selection l em Through Enhanced Hydro (IWRM) - Meteorological Services TZ-MOW-11878-CS-CQS / De Component 1: Integrated W Consultant Qualifi sign and Supervision for Cent IDA / 59490 ater Resources Management Post Open - National 250,000.00 47,044.99 Signed 2017-05-25 2019-03-08 2017-06-15 2019-04-16 2017-07-29 2019-07-16 2017-08-28 2019-10-29 2017-10-02 2019-11-05 2018-03-31 cation Selection re of Excellence Building (IWRM) TZ-MOW-10918-CS-QCBS / C Component 1: Integrated W Quality And Cost- Open - Internationa onsultancy Services for Catc IDA / 59490 ater Resources Management Post 750,000.00 541,125.00 Signed 2017-03-30 2018-05-22 2017-04-28 2018-05-22 2017-06-02 2018-08-28 2017-06-30 2018-09-26 2017-07-30 2018-12-04 2017-08-29 2018-12-21 2017-10-03 2019-03-14 2018-10-03 Based Selection l hment Conservation in Wami (IWRM) -Ruvu Basin TZ-MOW-44490-CS-CQS / Co nsultancy services for Consol Component 1: Integrated W idation of Data, Information a Consultant Qualifi IDA / 59490 ater Resources Management Post Open - National 300,000.00 277,090.70 Signed 2018-01-18 2015-02-19 2018-02-08 2018-03-24 2015-10-06 2018-04-23 2016-12-21 2018-05-28 2016-12-23 2018-11-24 nd Models from the IWRMD Pl cation Selection (IWRM) ans and Preparation of Requi rements Specification for WR IS & Web Portal TZ-MOW-54418-CS-QCBS / C Component 1: Integrated W Quality And Cost- Open - Internationa onsultancy Services on Wate IDA / 59490 ater Resources Management Prior 414,000.00 385,210.34 Signed 2015-02-03 2015-02-13 2015-09-23 2015-11-13 2016-02-10 2016-07-01 2018-05-30 2018-12-15 2017-08-07 2019-06-13 Based Selection l r Resources Management Fin (IWRM) ancing Options TZ-MOW-54421-CS-QCBS / C onsultancy Services for Prep Component 1: Integrated W Quality And Cost- Open - Internationa aration of Integrated Water IDA / 59490 ater Resources Management Post 533,000.00 518,435.03 Signed 2015-02-03 2018-03-27 2015-02-13 2015-09-07 2015-09-14 2015-11-12 2015-11-12 2016-04-04 2015-02-15 2016-12-21 2015-11-23 2017-06-01 2017-05-04 2017-11-28 Based Selection l Management and Developme (IWRM) nt Plan for Wami/Ruvu Basin TZ-MOW-64973-CS-QCBS / C Component 4: Project mana onsultancy Service for Projec Quality And Cost- Open - Internationa IDA / 59490 gement and Implementation Prior 1,200,000.00 2,639,045.65 Signed 2018-06-20 2019-05-09 2018-07-11 2019-07-24 2018-08-15 2019-10-27 2018-09-12 2019-12-11 2018-10-12 2020-03-03 2018-11-16 2020-09-30 2018-12-21 2020-11-26 2019-12-21 t Management Firm to Suppo Based Selection l Support rt Implementation of WSSP II TZ-MOW-11389-CS-QCBS / C onsultancy Services for desig n review and supervision of c onstruction of office and labo Component 1: Integrated W Quality And Cost- Open - Internationa ratory buildings for Wami-Ru IDA / 59490 ater Resources Management Post 600,000.00 0.00 Canceled 2017-09-05 2017-09-26 2017-10-24 2017-11-21 2017-12-21 2018-01-25 2018-03-01 2019-03-01 Based Selection l vu Basin Water Boards Head (IWRM) quarter Morogoro and Water Users Associations Offices at Msowero and rehabilitation and extension at Dodoma TZ-MOW-12527-CS-QCBS / I Component 1: Integrated W Quality And Cost- Open - Internationa nstitutional development sup IDA / 59490 ater Resources Management Prior 1,000,000.00 0.00 Canceled 2017-10-20 2017-11-10 2017-12-24 2018-01-21 2018-02-20 2018-03-27 2018-05-01 2019-05-01 Based Selection l port technical assistance CO (IWRM) E TZ-MOW-10915-CS-QCBS / C Component 1: Integrated W onsultancy Services for Mode Quality And Cost- Open - Internationa IDA / 59490 ater Resources Management Prior 1,750,000.00 0.00 Canceled 2017-03-30 2017-04-28 2017-06-02 2017-06-30 2017-07-30 2017-08-29 2017-10-03 2019-11-30 rnizing Hydrological and Met Based Selection l (IWRM) eorological Monitoring Syste ms TZ-MOW-10921-CS-QCBS / C onsultancy Services for Oper Component 1: Integrated W Quality And Cost- Open - Internationa ational Decision Support Syst IDA / 59490 ater Resources Management Prior 2,500,000.00 0.00 Canceled 2017-04-11 2018-01-10 2017-05-12 2018-03-22 2017-06-16 2017-07-14 2017-08-13 2017-09-12 2017-10-17 2018-10-17 Based Selection l em through Enhanced Hydro- (IWRM) Meteorological Services TZ-MOW-11875-CS-CQS / Co Component 1: Integrated W nsultancy Services for the st Consultant Qualifi IDA / 59490 ater Resources Management Post Open - National 50,000.00 0.00 Canceled 2017-05-25 2017-06-15 2017-07-29 2017-08-28 2017-10-02 2018-03-31 udy of institutional set up for cation Selection (IWRM) water Resources Centre of Ex cellence TZ-MOW-12529-CS-CQS / Co Component 1: Integrated W Consultant Qualifi Open - Internationa nsultancy Services for prepa IDA / 59490 ater Resources Management Prior 300,000.00 0.00 Canceled 2017-07-03 2017-07-24 2017-08-21 2017-09-04 2017-10-09 2018-04-07 cation Selection l ration of future investments (IWRM) TZ-MOW-11533-CS-CQS / Te Component 1: Integrated W chnical Assistance for strengt Consultant Qualifi Pending Impleme IDA / 59490 ater Resources Management Post Open - National 100,000.00 0.00 2017-08-10 2017-08-31 2017-10-14 2017-11-13 2017-12-18 2018-06-16 hening Ground water Resour cation Selection ntation (IWRM) ces Development and Manag ement in Tanzania TZ-MOW-79016-CS-QCBS / C onsultancy Services for Prep aration of Strategic Environm Component 1: Integrated W Quality And Cost- Open - Internationa ental and Social Appraisal (S IDA / 59490 ater Resources Management Prior 600,000.00 744,682.34 Signed 2018-11-14 2018-11-29 2018-12-05 2018-12-17 2019-01-18 2019-04-11 2019-02-15 2019-05-17 2019-03-17 2019-09-30 2019-04-21 2020-02-04 2019-05-26 2020-03-25 2020-05-25 Based Selection l ESA) for Integrated Water Re (IWRM) sources Management and De velopment (IWRMD) Plans for Five Basins in Tanzania. TZ-MOW-64970-CS-CQS / Co Component 4: Project mana Consultant Qualifi nsultancy Services for Project IDA / 59490 gement and Implementation Post Open - National 150,000.00 0.00 Canceled 2018-10-16 2019-07-26 2018-11-06 2018-11-15 2018-12-11 2019-01-05 2019-02-09 2019-08-08 cation Selection Manager Consultancy for Sup Support port of WSSP II Page 3 TZ-MOW-11545-CS-CQS / Te Component 1: Integrated W chnical Assistance on Suppor Consultant Qualifi IDA / 59490 ater Resources Management Post Open - National 100,000.00 0.00 Canceled 2017-08-30 2017-09-20 2017-11-03 2017-12-03 2018-01-07 2018-07-06 ting Implementation of IWRM cation Selection (IWRM) D at National and Basin Level s TZ-MOW-11558-CS-CQS / Te chnical Assistance for Conce Component 1: Integrated W Consultant Qualifi ptualisation, Strategic Planni IDA / 59490 ater Resources Management Post Open - National 200,000.00 0.00 Canceled 2017-11-30 2017-12-21 2018-02-03 2018-03-05 2018-04-09 2018-10-06 cation Selection ng and Opertionslisation of t (IWRM) he Water Resources Centre o f Excellence (WRCoE) TZ-MOW-195725-CS-CQS / C onsultancy Services for Upda Component 1: Integrated W Consultant Qualifi ting ESIA for Implementation IDA / 59490 ater Resources Management Post Open - National 200,000.00 175,497.60 Signed 2020-10-15 2020-11-09 2020-11-05 2021-01-07 2020-12-19 2021-03-12 2021-01-18 2021-08-04 2021-02-22 2021-11-05 2021-08-21 cation Selection of Water Supply and Sanitati (IWRM) on Improvement Projects for Tanga UWASA TZ-MOW-195742-CS-CQS / C onsultancy Services for Revie Component 1: Integrated W w and Update for the Detaile Consultant Qualifi IDA / 59490 ater Resources Management Post Open - National 150,000.00 2,366,720.00 Signed 2020-10-05 2020-11-09 2020-10-26 2021-01-07 2020-12-09 2021-03-12 2021-01-08 2021-06-18 2021-02-12 2022-01-13 2021-08-11 d Engineering Designs and C cation Selection (IWRM) onstruction Supervision of th e proposed Waste Water Infr astructure for Tanga City TZ-MOW-198503-CS-QCBS / Consultancy Services for Ass Component 1: Integrated W Quality And Cost- Open - Internationa essment of Feasibility, Desig IDA / 59490 ater Resources Management Prior 2,200,000.00 0.00 Canceled 2019-12-04 2020-12-04 2019-12-25 2020-02-07 2020-03-06 2020-04-05 2020-05-10 2020-06-14 2021-06-14 Based Selection l n and Construction Supervisi (IWRM) on of a Managed Aquifer Rec harge (MAR) System TZ-MOW-195738-CS-CQS / C onsultancy Services for Envir onmental and Social Impact Component 1: Integrated W Consultant Qualifi Pending Impleme Assessment and Resettlemen IDA / 59490 ater Resources Management Post Open - National 270,000.00 0.00 2020-10-05 2020-10-26 2020-12-09 2021-01-08 2021-02-12 2021-08-11 cation Selection ntation t Action Plan of the proposed (IWRM) managed Aquifer recharge s ystem to increase Water Resi lience for the City of Dodoma TZ-MOW-262954-CS-CQS / C Component 1: Integrated W onsultancy Services for Desig Consultant Qualifi Open - Internationa Under Implement IDA / 59490 ater Resources Management Post 500,000.00 0.00 2021-11-22 2021-12-11 2021-12-07 2021-12-16 2022-01-20 2022-04-22 2022-02-03 2022-03-10 2023-03-10 n of Water Transfer Scheme f cation Selection l ation (IWRM) rom Mtera Reservoir to Dodo ma City TZ-MOW-279737-CS-CQS / C onsultancy for the assessme nt of the feasibility, design a Component 1: Integrated W Consultant Qualifi nd construction supervision o IDA / 59490 ater Resources Management Post Open - National 400,000.00 0.00 Canceled 2022-03-03 2022-03-23 2022-04-02 2022-05-23 2022-04-30 2022-05-14 2022-06-18 2024-12-04 cation Selection f a Managed Aquifer Recharg (IWRM) e (MAR) system to increase water resilience of the City of Dodoma TZ-MOW-293240-CS-CQS / C onsultancy Services Envirom Component 1: Integrated W Consultant Qualifi Under Implement ental and Social Impact Asse IDA / 59490 ater Resources Management Post Open - National 200,000.00 0.00 2022-05-10 2022-05-25 2022-06-09 2022-07-14 2022-07-15 2022-08-19 2023-02-15 cation Selection ation ssment (ESIA) of the propose (IWRM) d Mtera to Dodoma Water Su pply Project INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MOW-12593-CS-INDV / C Component 4: Project mana onsultancy Service for updati Individual Consult IDA / V0310 gement and Implementation Post Open 30,000.00 0.00 Canceled 2017-04-20 2017-04-27 2017-05-01 2017-05-03 2017-05-17 ng, upgrading, refining and i ant Selection Support mprovement of the PIM, work shops TZ-MOW-11864-CS-IND / Co Component 1: Integrated W Individual Consult Under Implement nsultancy Services for Moder IDA / 59490 ater Resources Management Prior Open 300,000.00 0.00 2018-09-10 2018-09-24 2018-10-29 2019-04-01 2018-11-19 2018-12-24 2019-06-22 ant Selection ation nizing Hydrological and Monit (IWRM) oring Systems TZ-MOW-63683-CS-INDV / C Component 4: Project mana onsultancy Service for Techni Individual Consult IDA / 59490 gement and Implementation Post Open 80,000.00 100,800.00 Signed 2018-10-16 2018-11-08 2018-11-25 2019-03-25 2018-12-17 2019-04-17 2019-01-21 2019-05-23 2019-07-20 cal Advisor for Financial Man ant Selection Support agement Support to WSSP II TZ-MOW-63691-CS-INDV / C Component 4: Project mana onsultancy Service for Techni Individual Consult IDA / 59490 gement and Implementation Post Open 80,000.00 0.00 Canceled 2018-10-16 2019-07-26 2018-11-19 2018-11-30 2019-01-04 2019-07-03 cal Advisor for Procurement ant Selection Support and Contract Management S upport to WSSP II TZ-MOW-87731-CS-INDV / C Component 4: Project mana Individual Consult Under Implement onsultancy Service for Projec IDA / 59490 gement and Implementation Post Open 150,000.00 0.00 2018-11-22 2018-11-19 2018-12-25 2019-01-08 2019-02-12 2019-08-11 ant Selection ation t manager consultancy for su Support pport of WSSP II TZ-MOW-89190-CS-INDV / T Component 1: Integrated W echnical Assistance for suppo Individual Consult IDA / 59490 ater Resources Management Post Open 150,000.00 150,000.00 Signed 2018-12-10 2018-01-04 2019-01-28 2019-03-14 2019-02-18 2019-07-01 2019-03-25 2019-07-16 2019-09-21 rting implementation of IWR ant Selection (IWRM) MD at National and Basin Lev els TZ-MOW-94046-CS-INDV / T echnical Assistance for Conc Component 1: Integrated W Individual Consult eptualisation, Strategic Plann IDA / 59490 ater Resources Management Post Open 200,000.00 115,600.00 Signed 2019-01-09 2019-02-11 2019-02-27 2019-03-19 2019-03-20 2019-06-28 2019-04-24 2019-07-23 2019-10-21 ant Selection ing and Operationslisation of (IWRM) the Water Resources Centre of Excellence (WRCoE) TZ-MOW-70351-CS-INDV / In Component 1: Integrated W dividual consultant to suppor Individual Consult IDA / 59490 ater Resources Management Post Open 200,000.00 96,650.00 Signed 2018-09-19 2019-06-12 2018-11-07 2019-08-29 2018-11-28 2019-10-18 2019-01-02 2020-01-31 2019-07-01 t the COE as the Gis and Re ant Selection (IWRM) mote Sensing Expert TZ-MOW-70349-CS-INDV / In Component 1: Integrated W dividual consultant to suppor Individual Consult IDA / 59490 ater Resources Management Post Open 200,000.00 99,600.00 Signed 2018-09-05 2019-06-12 2018-10-24 2020-04-17 2018-11-14 2020-07-02 2018-12-19 2020-09-11 2019-06-17 t the COE core team as Wate ant Selection (IWRM) r Resources Expert and Mode ller TZ-MOW-70350-CS-INDV / In Component 1: Integrated W dividual consultant to suppor Individual Consult IDA / 59490 ater Resources Management Post Open 200,000.00 100,000.00 Signed 2018-09-12 2019-06-12 2018-10-31 2019-08-29 2018-11-21 2019-10-18 2018-12-26 2020-01-21 2019-06-24 t the COE core team as Grou ant Selection (IWRM) ndwater Expert and Modeller Page 4 TZ-MOW-130152-CS-INDV / Component 4: Project mana Individual Consult Consultancy Services for Pro IDA / 59490 gement and Implementation Post Open 80,000.00 90,200.00 Signed 2019-09-05 2019-09-04 2019-10-08 2019-12-19 2019-11-05 2020-03-27 2019-11-15 2020-05-20 2020-11-14 ant Selection curement Specialist under W Support SSP II TZ-MOW-109248-CS-INDV / I ndividual Consultant to Cond Component 1: Integrated W uct Surveillance Survey, Desi Individual Consult IDA / 59490 ater Resources Management Post Open 178,600.00 0.00 Canceled 2019-04-08 2019-05-11 2019-06-01 2019-07-06 2020-01-02 gn, Tender Preparation and S ant Selection (IWRM) upervision of Installation of D am Safety Monitoring Instru mentation TZ-MOW-12520-CS-INDV / In dividual consultant to suppor Component 1: Integrated W Individual Consult t the COE core team in provi IDA / 59490 ater Resources Management Post Open 200,000.00 0.00 Canceled 2017-10-01 2017-11-12 2017-11-19 2017-12-31 2018-06-29 ant Selection ding multi-sectoral analysis a (IWRM) nd policy support to different Stakeholders TZ-MOW-136426-CS-INDV / I ndividual consultant to suppo Component 1: Integrated W Individual Consult rt the COE core team in provi IDA / 59490 ater Resources Management Prior Open 300,000.00 0.00 Canceled 2019-10-07 2019-11-12 2019-11-25 2019-12-16 2020-01-20 2020-07-18 ant Selection ding multi-sectoral analysis a (IWRM) nd policy support to different Stakeholders TZ-MOW-145207-CS-INDV / I ndividual consultant to suppo Component 1: Integrated W Individual Consult rt the COE core team in provi IDA / 59490 ater Resources Management Post Open 200,000.00 99,996.00 Signed 2019-11-17 2019-11-20 2020-01-05 2020-09-18 2020-01-26 2020-11-19 2020-03-01 2020-12-22 2020-08-28 ant Selection ding multi-sectoral analysis a (IWRM) nd policy support to different Stakeholders TZ-MOW-136407-CS-INDV / I ndividual Consultant to Cond Component 1: Integrated W uct Surveillance Survey, Desi Individual Consult IDA / 59490 ater Resources Management Prior Open 400,000.00 0.00 Canceled 2019-10-07 2019-11-25 2019-12-16 2020-01-20 2020-07-18 gn, Tender Preparation and S ant Selection (IWRM) upervision of Installation of D am Safety Monitoring Instru mentation Page 5