PROCUREMENT PLAN (Textual Part) Project information: Mauritania Basic Education Support Project – Phase 2 P163143 Project Implementation agency: Direction des Projets Education et Formation Date of the Procurement Plan: February 17, 2020 Period covered by this Procurement Plan: February 19, 2020 – October 30, 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Mauritania : MAURITANIA - Basic Education Sector Support Project - Phase 2 PLAN General Information Country: Mauritania Bank’s Approval Date of the Original Procurement Plan: 2020-02-19 2022-03-13 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163143 GPN Date: Project Name: MAURITANIA - Basic Education Sector Support Project - Phase 2 Loan / Credit No: / , IDA / V3120, IDA / D7360 Mauritania Basic Education Sector Support Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MR-BESSP-222829-CW-RFB / Construction de 56 salles de Component 2: Improving Single Stage - One En cours 2021-12- classe équipées en 5 lots IDA / V3120 education service delivery in A posteriori Appel d'offres Open - National 1,075,697.00 0.00 2021-03-15 2021-06-10 2021-03-20 2021-07-12 2021-05-04 2021-05-19 2021-06-08 Envelope d'exécution 05 indépendants dans la wilaya selected regions du Hodh Echarghi . MR-BESSP-222833-CW-RFB / Construction de 54 salles de Component 2: Improving Single Stage - One En cours 2021-11- classe en 3 lots indépendants IDA / V3120 education service delivery in A posteriori Appel d'offres Open - National 1,038,573.00 0.00 2021-03-15 2021-06-10 2021-03-20 2021-07-12 2021-05-04 2021-05-05 2021-05-20 Envelope d'exécution 16 dans la wilaya du Hodh El selected regions Gharbi. MR-BESSP-222836-CW-RFB / Component 2: Improving Construction de 42 salles de Single Stage - One 2021-12- IDA / V3120 education service delivery in A posteriori Appel d'offres Open - National 852,062.00 656,029.52 Signé 2021-03-15 2021-06-10 2021-03-20 2021-07-12 2021-05-04 2021-07-27 2021-05-19 2021-10-20 2021-06-08 2022-02-08 classe en 4 lots indépendants Envelope 05 selected regions dans la wilaya de l'Assaba, MR-BESSP-222838-CW-RFB / Component 2: Improving Construction de 40 salles de Single Stage - One En cours 2021-12- IDA / V3120 education service delivery in A posteriori Appel d'offres Open - National 742,475.00 0.00 2021-03-15 2021-06-10 2021-03-20 2021-07-12 2021-05-04 2021-05-19 2021-06-08 classe en 4 lots indépendants Envelope d'exécution 05 selected regions dans la wilaya du Guidimagha. MR-BESSP-222840-CW-RFB / Component 2: Improving Construction de 50 salles de Single Stage - One En cours 2021-12- IDA / V3120 education service delivery in A posteriori Appel d'offres Open - National 928,094.00 0.00 2021-03-15 2021-06-10 2021-03-20 2021-07-12 2021-05-04 2021-05-19 2021-06-08 classe en 4 lots indépendants Envelope d'exécution 05 selected regions dans la wilaya du Gorgol. MR-BESSP-223595-CW-RFB / Component 2: Improving Single Stage - One 2021-10- Construction de 10 salles de IDA / V3120 education service delivery in A posteriori Appel d'offres Open - National 170,548.00 138,762.05 Signé 2021-03-24 2021-05-10 2021-03-29 2021-05-10 2021-04-28 2021-06-16 2021-05-19 2021-07-23 2021-06-13 2021-09-07 Envelope 11 classes à Nouckchott-SUD selected regions MR-BESSP-254070-CW-RFB / Request for Bids - Travaux de construction des Component 2: Improving Single Stage - One Small Works SPD En cours 2022-07- salles de classe et clôtures IDA / D7360 education service delivery in A posteriori Appel d'offres Open - National 682,873.00 470,026.60 2021-10-01 2021-10-12 2021-10-06 2021-11-04 2021-11-17 2021-11-16 2021-12-17 2021-12-10 2022-01-21 Envelope (1 envelope d'exécution 20 dans la wilaya de Hodh selected regions process) Echarghi MR-BESSP-254071-CW-RFB / Request for Bids - Travaux de construction des Component 2: Improving Single Stage - One Small Works SPD En cours 2022-07- salles de classe et clôtures IDA / D7360 education service delivery in A posteriori Appel d'offres Open - National 559,116.00 0.00 2021-10-01 2021-10-14 2021-10-06 2021-10-15 2021-11-17 2021-11-25 2021-12-17 2021-12-09 2022-01-21 Envelope (1 envelope d'exécution 20 dans la wilaya de Hodh El selected regions process) Gharbi MR-BESSP-254072-CW-RFB / Request for Bids - Component 2: Improving Travaux de construction des Single Stage - One Small Works SPD 2022-07- IDA / D7360 education service delivery in A posteriori Appel d'offres Open - National 502,099.00 437,250.96 Signé 2021-10-01 2021-10-12 2021-10-06 2021-11-04 2021-11-17 2021-11-16 2021-12-17 2021-12-01 2022-01-21 2022-02-22 salles de classe et clôtures Envelope (1 envelope 20 selected regions dans la wilaya de l'ASSABA process) MR-BESSP-254073-CW-RFB / Request for Bids - Component 2: Improving Travaux de construction des Single Stage - One Small Works SPD En cours 2022-07- IDA / D7360 education service delivery in A posteriori Appel d'offres Open - National 503,204.00 0.00 2021-10-01 2021-10-14 2021-10-06 2021-10-15 2021-11-17 2021-11-18 2021-12-17 2022-01-21 salles de classe et clôtures Envelope (1 envelope d'exécution 20 selected regions dans la wilaya du Gorgol process) MR-BESSP-254074-CW-RFB / Request for Bids - Component 2: Improving Travaux de construction des Single Stage - One Small Works SPD En cours 2022-07- IDA / D7360 education service delivery in A posteriori Appel d'offres Open - National 516,022.00 0.00 2021-10-01 2021-10-14 2021-10-06 2021-10-15 2021-11-17 2021-11-25 2021-12-17 2022-02-04 2022-01-21 salles de classe et clôtures Envelope (1 envelope d'exécution 20 selected regions dans la wilaya du Guidimagha process) MR-BESSP-254075-CW-RFB / Request for Bids - Travaux de construction des Component 2: Improving Single Stage - One Small Works SPD En cours 2022-07- salles de classe et clôtures IDA / D7360 education service delivery in A posteriori Appel d'offres Open - National 1,077,348.00 0.00 2021-10-01 2021-10-14 2021-10-06 2021-10-15 2021-11-17 2021-11-18 2021-12-17 2022-01-21 Envelope (1 envelope d'exécution 20 dans la wilaya de Nouakchott selected regions process) Sud MR-BESSP-280056-CW-RFB / Travaux de construction de Component 1: Transforming Request for Bids - salles de classe pour les teacher management using Single Stage - One Small Works SPD En attente 2023-03- IDA / D7360 A posteriori Appel d'offres Open - National 600,000.00 0.00 2022-03-25 2022-03-30 2022-05-11 2022-06-10 2022-07-15 écoles d'applications relevant accountability frameworks Envelope (1 envelope d'exécution 12 des ENIs de Kaédi et d'Akjoujt and new technology process) en deux lots indépendants. GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-BESSP-161843-GO-RFQ Component 1: Transforming / Un onduleur pour la teacher management using Single Stage - One plateforme du SIGE à la / A posteriori Demande de prix Limited 5,000.00 0.00 Annulé 2020-03-20 2020-05-15 2020-11-11 accountability frameworks Envelope DIGTEC, Un logiciel Backup et and new technology point d'accès wifi MR-BESSP-159784-GO-DIR / Connexion internet et accès WIFI, pour DREN et IDEN à Component 3: Strengthening Passation de Nouakchott, et administration / management of the A posteriori marché de gré à Direct 30,000.00 0.00 Annulé 2020-03-24 2020-03-29 2020-04-16 2020-04-19 du SIGE, et Installation de la education sector gré connexion aux DREN et IDEN et formation. Page 1 Component 3: Strengthening MR-BESSP-175882-GO-RFQ Single Stage - One En attente IDA / V3120 management of the A posteriori Demande de prix Limited 13,514.00 0.00 2020-06-17 2020-07-13 2020-08-12 / Location de voitures Envelope d'exécution education sector MR-BESSP-175893-GO-RFQ Component 3: Strengthening / Duplication des items de Single Stage - One En attente IDA / V3120 management of the A posteriori Demande de prix Limited 33,713.00 0.00 2020-06-13 2020-06-30 2020-07-30 l'évaluation des enseignants Envelope d'exécution education sector du fondamental. MR-BESSP-175899-GO-RFQ Component 3: Strengthening / Matériel de passation des Single Stage - One En attente IDA / V3120 management of the A posteriori Demande de prix Limited 10,034.00 0.00 2020-06-20 2020-07-11 2020-07-26 épreuves de l'évaluation des Envelope d'exécution education sector enseignants du fondamental MR-BESSP-204844-GO-RFB / Component 3: Strengthening Single Stage - One Acquisition de 18 véhicules IDA / V3120 management of the A posteriori Appel d'offres Open - National 814,547.00 518,259.91 Achevé 2020-12-05 2021-01-18 2021-02-17 2021-06-17 2021-08-16 2021-08-25 Envelope pour 6 régions education sector MR-BESSP-205324-GO-RFB / Acquisition de tablettes au Component 1: Transforming profit de 4000 responsables teacher management using Single Stage - One En attente IDA / V3120 A posteriori Appel d'offres Open - National 427,000.00 0.00 2020-12-07 2020-12-12 2021-01-11 2021-01-26 2021-02-19 2021-02-25 de l'Enseignement accountability frameworks Envelope d'exécution Fondamental and new technology (Opérationnalisation du SIGE) MR-BESSP-205597-GO-RFQ / Location de véhicules pour Component 3: Strengthening Single Stage - One En attente l'évaluation des acquis des IDA / V3120 management of the A posteriori Demande de prix Limited 20,826.00 0.00 2020-11-29 2020-12-29 2020-12-30 Envelope d'exécution élèves de la 1ère AF et 1ère education sector AS par la CNE MR-BESSP-205598-GO-RFQ / Fournitures et duplicata des Component 3: Strengthening Single Stage - One En cours instruments pour l'évaluation IDA / V3120 management of the A posteriori Demande de prix Limited 9,000.00 0.00 2020-11-29 2020-12-10 2020-12-12 Envelope d'exécution des acquis des élèves de 1ère education sector AF et 1ère AS par la CNE MR-BESSP-223592-GO-RFB / Component 2: Improving Single Stage - One En cours Acquisition des kits pour filles IDA / V3120 education service delivery in A posteriori Appel d'offres Open - National 571,500.00 0.00 2021-03-25 2021-06-24 2021-03-30 2021-07-30 2021-04-29 2021-05-20 2021-06-09 2021-08-08 Envelope d'exécution et enseignants selected regions MR-BESSP-229837-GO-RFQ Component 1: Transforming / Acquisition de matériels teacher management using Single Stage - One En attente informatique au profit de la IDA / D7360 A posteriori Demande de prix Limited 53,000.00 0.00 2021-04-27 2021-05-27 2021-06-11 accountability frameworks Envelope d'exécution Cellule inspecteurs, CNE et and new technology unité de gestion du projet MR-BESSP-229838-GO-RFQ Component 1: Transforming / Acquisition de 240 tables et teacher management using Single Stage - One IDA / D7360 A posteriori Demande de prix Limited 17,000.00 14,097.24 Achevé 2021-05-03 2021-05-31 2021-06-13 2021-09-09 2021-06-28 2021-09-20 chaises individuelles pour accountability frameworks Envelope l’ENS and new technology MR-BESSP-234175-GO-RFB / Component 1: Transforming Acquisition de matériels teacher management using Single Stage - One informatiques pour les ENI IDA / D7360 A posteriori Appel d'offres Open - National 480,000.00 413,900.04 Signé 2021-05-31 2021-08-04 2021-06-05 2021-08-12 2021-07-05 2021-09-14 2021-07-25 2021-10-20 2021-08-29 2022-01-07 2021-12-27 accountability frameworks Envelope dans le cadre de contrat de and new technology performance MR-BESSP-234176-GO-RFB / Component 1: Transforming Acquisition des mobiliers teacher management using Single Stage - One En cours pour les ENI (tables bureaux, IDA / D7360 A posteriori Appel d'offres Open - National 200,000.00 0.00 2021-05-31 2021-06-16 2021-06-05 2021-06-08 2021-07-26 2021-06-10 2021-07-15 2021-11-12 accountability frameworks Envelope d'exécution climatiseurs…) dans le cadre and new technology de contrat de performance ; MR-BESSP-234178-GO-RFQ Component 3: Strengthening / Acquisitions d’équipements Single Stage - One En attente IDA / D7360 management of the A posteriori Demande de prix Open - National 45,000.00 0.00 2021-05-25 2021-07-09 2021-07-19 bureautiques pour l’unité de Envelope d'exécution education sector Projet PASEB 2 MR-BESSP-254076-GO-RFQ Component 3: Strengthening / Acquisition d'équipements Single Stage - One En attente IDA / D7360 management of the A posteriori Demande de prix Open - National 19,337.00 0.00 2021-10-06 2021-12-01 2021-12-31 Internet et câblage de bureau Envelope d'exécution education sector de la DPEF MR-BESSP-159785-GO-RFB / Component 1: Transforming Acquisition d'équipements teacher management using Single Stage - One En attente IDA / D7360 A posteriori Appel d'offres Open - National 400,000.00 0.00 2021-10-01 2021-10-03 2021-11-02 2021-11-17 2021-12-07 2022-01-06 SIGE pour l'Administration accountability frameworks Envelope d'exécution centrale , DREN et IDEN. and new technology MR-BESSP-261532-GO-RFQ / Impression de cahiers de Component 1: Transforming préparation en 1ère et 2ème teacher management using Single Stage - One IDA / D7360 A posteriori Demande de prix Open - National 127,000.00 78,731.16 Achevé 2021-11-11 2021-11-12 2021-12-06 2021-12-16 2021-12-21 2022-01-10 AF en langues et en accountability frameworks Envelope mathématiques au premier and new technology cycle du fondamental MR-BESSP-280047-GO-RFB / L'acquisition des véhicules Component 3: Strengthening Single Stage - One En attente pour la supervision et le IDA / D7360 management of the A posteriori Appel d'offres Open - National 400,000.00 0.00 2022-04-04 2022-04-09 2022-05-21 2022-06-20 2022-07-25 2022-10-23 Envelope d'exécution suivi des Tavaux de education sector construction. MR-BESSP-255365-GO-RFB / Component 2: Improving Single Stage - One Acquisition de 35000 tables- IDA / D7360 education service delivery in A priori Appel d'offres Open - National 2,940,000.00 0.00 Annulé 2021-10-04 2021-10-09 2021-11-20 2021-12-20 2022-01-24 2022-07-23 Envelope bancs selected regions MR-BESSP-222847-GO-RFB / Acquisition de tables bancs au Component 2: Improving profit des wilayas du Hodh Single Stage - One IDA / V3120 education service delivery in A posteriori Appel d'offres Open - National 641,026.00 0.00 Annulé 2021-03-15 2021-06-24 2021-03-20 2021-06-30 2021-05-04 2021-05-19 2021-06-13 2021-12-10 Charghi, Hodh El Gharbi, Envelope selected regions Assaba, Gorgol, Guidimaha et Nouakchott- SUD MR-BESSP-282489-GO-RFB / Acquisition et installation de Component 2: Improving 45000 tables-bancs pour les Single Stage - One En attente IDA / D7360 education service delivery in A priori Appel d'offres Open - International 4,000,000.00 0.00 2022-03-25 2022-03-30 2022-05-11 2022-06-10 2022-07-15 2023-02-10 élèves du fondamental dans Envelope d'exécution selected regions les six wilaya d'intervention du PASEB2 NON CONSULTING SERVICES Page 2 Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-BESSP-254069-NC-DIR / Component 1: Transforming Appui pour le développement Passation de teacher management using En attente d'une application SIGE pour le IDA / D7360 A posteriori marché de gré à Direct 639,785.00 0.00 2021-10-04 2021-10-09 2021-11-13 2022-03-13 accountability frameworks d'exécution Ministère de l’Éducation gré and new technology Nationale MR-BESSP-280058-NC-RFQ Component 3: Strengthening / Assistance médicale au Single Stage - One En attente IDA / D7360 management of the A posteriori Demande de prix Limited 20,000.00 0.00 2022-03-06 2022-05-01 2022-07-30 personnel de la DPEF durant la Envelope d'exécution education sector vague actuelle de COVID-19 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-BESSP-159797-NC-RFP / Component 3: Strengthening Sélection fondée En attente Formulation du plan sectoriel / management of the A posteriori sur la qualité et le Open - International 600,000.00 0.00 2020-04-20 2020-05-11 2020-06-24 2020-07-22 2020-08-21 2020-09-25 2020-10-30 2021-10-30 d'exécution et réformes éducatives education sector coût MR-BESSP-166467-CS-CQS / Recrutement d'un cabinet Sélection fondée Component 3: Strengthening pour un appui au Ministère de sur les IDA / V3120 management of the A posteriori Open - National 166,320.00 0.00 Annulé 2020-04-06 2020-04-21 2020-05-20 2020-06-19 2020-07-24 2020-10-22 l'Enseignement Fondamental qualifications des education sector et de la réforme du Secteur de consultants l'éducation Nationale zone 2 MR-BESSP-166468-CS-CQS / Recrutement d'un cabinet Sélection fondée Component 3: Strengthening pour un appui au Ministère de sur les IDA / V3120 management of the A posteriori Open - National 166,320.00 0.00 Annulé 2020-04-13 2020-04-28 2020-05-27 2020-06-26 2020-07-31 2020-10-29 l'Enseignement Fondamental qualifications des education sector et de la réforme du Secteur de consultants l'éducation Nationale zone 3 Sélection fondée MR-BESSP-175876-CS-CQS / Component 3: Strengthening sur les Recrutement d'un expert IDA / V3120 management of the A posteriori Open - International 55,140.00 0.00 Annulé 2020-06-10 2020-06-25 2020-07-12 2020-07-16 2020-07-23 2021-07-23 qualifications des économiste/planificateur education sector consultants MR-BESSP-166466-CS-CQS / Recrutement d'un cabinet Sélection fondée Component 3: Strengthening pour un appui au Ministère de sur les IDA / V3120 management of the A posteriori Open - National 166,320.00 0.00 Annulé 2020-03-30 2020-04-14 2020-05-13 2020-06-12 2020-07-17 2020-08-31 l'Enseignement Fondamental qualifications des education sector et de la réforme du Secteur de consultants l'éducation Nationale zone 1 MR-BESSP-208483-CS-QCBS Component 1: Transforming / Renforcement des Sélection fondée teacher management using compétences pédagogiques IDA / V3120 A posteriori sur la qualité et le Open - National 210,000.00 0.00 Annulé 2021-05-24 2021-01-18 2021-06-07 2021-06-15 2021-06-22 2021-06-24 2021-07-01 2021-07-06 2031-06-14 accountability frameworks des formateurs (Assistance et coût and new technology formation) MR-BESSP-208742-CS-QCBS / Elaboration des Plans de Component 2: Improving Sélection fondée Développement régionaux IDA / V3120 education service delivery in A posteriori sur la qualité et le Open - National 297,600.00 0.00 Annulé 2020-12-16 2021-01-14 2020-12-23 2021-01-06 2021-01-14 2021-01-16 2021-01-26 2021-02-02 2021-03-19 pour les 6 région selected regions coût d'intervention du Projet MR-BESSP-205407-CS-CQS / Sélection fondée Component 2: Improving Elaboration d'un manuel de sur les IDA / V3120 education service delivery in A posteriori Open - National 58,000.00 0.00 Annulé 2020-12-01 2020-12-22 2021-02-04 2021-03-06 2021-04-10 2021-06-09 procédures pour les COGES et qualifications des selected regions les subventions aux écoles consultants MR-BESSP-213513-CS-CQS / Component 3: Strengthening Sélection au Recrutement d'un auditeur IDA / V3120 management of the A posteriori Open - National 30,000.00 9,237.52 Signé 2021-02-10 2021-01-25 2021-02-25 2021-03-17 2021-07-02 2021-03-22 2021-07-30 2021-03-27 2021-08-02 2021-03-31 2021-08-10 2021-04-12 2021-08-27 2026-04-11 moindre coût externe du Projet PASEB II education sector MR-BESSP-229821-CS-CQS / Recrutement d’une institution Component 1: Transforming Sélection fondée universitaire pour l’appui à teacher management using sur les IDA / D7360 A posteriori Open - International 250,000.00 0.00 Annulé 2021-04-30 2021-04-29 2021-05-21 2021-06-16 2021-07-04 2021-08-03 2021-09-07 2021-11-19 l’ENS dans la mise en accountability frameworks qualifications des place d'une formation des and new technology consultants formateurs des INI MR-BESSP-229827-CS-QCBS / Recrutement d’un bureau de Component 2: Improving Sélection fondée suivi pour les travaux de En cours IDA / D7360 education service delivery in A posteriori sur la qualité et le Open - National 6,800.00 0.00 2021-05-15 2021-05-27 2021-06-05 2021-07-19 2021-08-11 2021-08-16 2021-09-09 2021-09-15 2021-09-20 2021-10-20 2021-11-24 2022-03-24 construction de 10 salles de d'exécution selected regions coût classe dans la wilaya de Nktt- Sud MR-BESSP-229832-CS-QCBS / Recrutement d’un bureau de Component 2: Improving Sélection fondée suivi pour les travaux de En cours IDA / D7360 education service delivery in A posteriori sur la qualité et le Open - National 40,000.00 0.00 2021-05-14 2021-05-27 2021-06-04 2021-07-18 2021-08-15 2021-09-14 2021-10-19 2021-11-23 2022-03-23 construction de 56 salles de d'exécution selected regions coût classe dans la wilaya du Hodh Echarghi MR-BESSP-229833-CS-QCBS / Recrutement d’un bureau de Component 2: Improving Sélection fondée suivi pour les travaux de En cours IDA / D7360 education service delivery in A posteriori sur la qualité et le Open - National 40,000.00 0.00 2021-05-14 2021-05-27 2021-06-04 2021-07-18 2021-08-15 2021-09-14 2021-10-19 2021-11-23 2022-03-23 construction de 54 salles de d'exécution selected regions coût classe dans la wilaya du Hodh El Gharbi MR-BESSP-229834-CS-QCBS / Recrutement d’un bureau de Component 2: Improving Sélection fondée suivi pour les travaux de En cours IDA / D7360 education service delivery in A posteriori sur la qualité et le Open - National 34,000.00 0.00 2021-05-14 2021-05-27 2021-06-04 2021-07-18 2021-08-15 2021-09-14 2021-10-19 2021-11-23 2022-11-23 construction de 42 salles de d'exécution selected regions coût classe dans la wilaya de l’Assaba Page 3 MR-BESSP-229835-CS-QCBS / Recrutement d’un bureau de Component 2: Improving Sélection fondée suivi pour les travaux de En cours IDA / D7360 education service delivery in A posteriori sur la qualité et le Open - National 37,000.00 0.00 2021-05-14 2021-05-27 2021-06-04 2021-07-18 2021-08-15 2021-09-14 2021-10-19 2021-11-23 2022-03-23 construction 50 salle des d'exécution selected regions coût classe dans la wilaya du Gorgol MR-BESSP-229879-CS-QCBS / Recrutement d’un bureau de Component 2: Improving Sélection fondée suivi pour les travaux de En cours IDA / D7360 education service delivery in A posteriori sur la qualité et le Open - National 30,000.00 0.00 2021-05-14 2021-05-27 2021-06-04 2021-07-18 2021-08-02 2021-08-15 2021-09-15 2021-09-14 2021-10-19 2021-11-23 2022-03-23 construction 40 salles de d'exécution selected regions coût classe dans la wilaya du Guidimagha MR-BESSP-237807-CS-CQS / Sélection fondée Elaboration des Plans de Component 2: Improving sur les En attente Développement régionaux IDA / D7360 education service delivery in A posteriori Open - National 297,600.00 0.00 2021-06-02 2021-06-23 2021-08-06 2021-09-05 2021-09-29 2021-11-13 qualifications des d'exécution pour les 5 régions selected regions consultants d'intervention du Projet INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-BESSP-159783-CS-INDV Component 1: Transforming / Appui au processus de teacher management using En cours / A posteriori Individuel Limited 28,000.00 0.00 2020-03-09 2020-03-14 2020-04-04 2020-05-09 2020-11-05 restructuration des ENIS et de accountability frameworks d'exécution l'ENS and new technology MR-BESSP-159791-CS-INDV Component 3: Strengthening En attente / Manuel de procédure du / management of the A posteriori Individuel Limited 25,000.00 0.00 2020-02-24 2020-02-29 2020-03-21 2020-04-25 2020-10-22 d'exécution Projet education sector MR-BESSP-159793-CS-INDV / Finalisation études Component 2: Improving En attente environnementales et sociales / education service delivery in A posteriori Individuel Limited 27,000.00 0.00 2020-03-12 2020-03-17 2020-04-07 2020-05-12 2020-11-08 d'exécution et Mécanisme de Gestion des selected regions Plaintes (trois consultants) MR-BESSP-159795-CS-INDV Component 3: Strengthening En attente / Manuel d'exécution du / management of the A posteriori Individuel Limited 25,000.00 0.00 2020-02-29 2020-03-05 2020-03-26 2020-04-30 2020-10-27 d'exécution projet education sector Component 1: Transforming MR-BESSP-160153-CS-INDV teacher management using En attente / Appui à la restructuration / A posteriori Individuel Open 25,000.00 0.00 2020-03-09 2020-04-27 2020-05-18 2020-06-22 2020-12-19 accountability frameworks d'exécution des ENIs et ENS II and new technology MR-BESSP-159786-CS-INDV Component 2: Improving / Appui à l'élaboration du / education service delivery in A posteriori Individuel Limited 25,000.00 0.00 Annulé 2020-04-13 2020-04-18 2020-05-09 2020-06-13 2020-12-10 nouveau modèle des cartes selected regions scolaires (central et régional) MR-BESSP-175878-CS-CQS / Component 3: Strengthening recrutement d'un expert en IDA / V3120 management of the A posteriori Individuel Open 55,140.00 0.00 Annulé 2020-06-08 2020-07-07 2020-07-14 2020-07-26 2021-01-22 Education/Formation education sector MR-BESSP-205334-CS-INDV Component 2: Improving / Manuel de procédures pour IDA / V3120 education service delivery in A posteriori Individuel Open 18,000.00 0.00 Annulé 2020-12-02 2020-12-28 2021-01-02 2021-01-10 2021-02-09 les plans de développement selected regions régionnaux MR-BESSP-159788-CS-INDV Component 2: Improving / Elaboration d'un manuel de / education service delivery in A posteriori Individuel Limited 50,000.00 0.00 Annulé 2020-02-25 2020-03-01 2020-03-22 2020-04-26 2020-10-23 procédures pour COGES et selected regions subventions aux écoles MR-BESSP-205542-CS-INDV / Accompagnement pour un Component 1: Transforming appui à la conception , la mise teacher management using En cours IDA / V3120 A posteriori Individuel Open 86,000.00 0.00 2020-12-14 2021-01-18 2021-02-01 2021-02-22 2021-03-29 2025-03-28 en œuvre et au suivi des accountability frameworks d'exécution Projets d'Etablissement des and new technology ENI. MR-BESSP-205516-CS-INDV Component 3: Strengthening Sélection de En cours / Recrutement Coordinateur IDA / V3120 management of the A posteriori consultants par Direct 192,000.00 0.00 2020-11-19 2021-01-18 2020-11-29 2021-02-02 2026-02-01 d'exécution Technique du Projet PASEB II education sector entente directe MR-BESSP-205408-CS-INDV Component 3: Strengthening Sélection de / Recrutement Directeurs des En cours IDA / V3120 management of the A posteriori consultants par Direct 180,000.00 0.00 2020-11-19 2021-01-18 2020-11-29 2021-02-02 2026-02-01 travaux et superviseurs des d'exécution education sector entente directe Cellules mobiles MR-BESSP-205535-CS-INDV Component 3: Strengthening Sélection de / Recrutement Responsable IDA / V3120 management of the A posteriori consultants par Direct 162,000.00 0.00 Annulé 2020-11-19 2021-01-18 2020-11-29 2021-02-02 2026-02-01 Administratif et Financier education sector entente directe MR-BESSP-205540-CS-INDV Component 3: Strengthening Sélection de / Recrutement Responsable IDA / V3120 management of the A posteriori consultants par Direct 162,000.00 0.00 Annulé 2020-11-19 2021-01-18 2020-11-29 2021-02-02 2026-02-01 Suivi Evaluation education sector entente directe MR-BESSP-205528-CS-INDV Component 3: Strengthening Sélection de / Recrutement Spécialiste IDA / V3120 management of the A posteriori consultants par Direct 162,000.00 0.00 Annulé 2020-11-19 2021-01-18 2020-11-29 2021-02-02 2026-02-01 Passation des Marchés education sector entente directe Component 1: Transforming MR-BESSP-208744-CS-INDV teacher management using En cours / Chef Composante 1 du IDA / V3120 A posteriori Individuel Open 180,000.00 0.00 2020-12-15 2021-01-19 2021-02-02 2021-02-23 2021-03-30 2026-03-29 accountability frameworks d'exécution projet PASEB II and new technology MR-BESSP-205519-CS-INDV Component 3: Strengthening Sélection de / Recrutement Chef IDA / V3120 management of the A posteriori consultants par Direct 180,000.00 0.00 Annulé 2020-11-19 2020-11-29 2021-02-02 2026-02-01 Composante 1 du PASEB II education sector entente directe MR-BESSP-175841-CS-QCBS Component 3: Strengthening / Recrutement d'un Expert en IDA / V3120 management of the A posteriori Individuel Open 55,140.00 0.00 Annulé 2020-06-09 2020-07-08 2020-07-13 2020-08-03 2021-01-30 suivi-évaluation education sector Page 4 MR-BESSP-213551-CS-INDV / Recrutement d'un consultant Component 2: Improving individuel pour l’élaboration En cours IDA / V3120 education service delivery in A posteriori Individuel Open 27,000.00 0.00 2021-01-25 2021-01-14 2021-02-28 2021-03-10 2021-03-17 2021-05-16 d’un manuel de procédure d'exécution selected regions pour les COGES et les subventions aux écoles MR-BESSP-213533-CS-INDV Component 3: Strengthening / Renforcement des capacités IDA / V3120 management of the A posteriori Individuel Open 36,000.00 36,029.89 Signé 2021-01-27 2021-01-18 2021-03-07 2021-05-06 2021-03-17 2021-05-18 2021-03-27 2021-06-07 2022-03-27 de la Cellule Nationale education sector d'Evaluation MR-BESSP-205522-CS-INDV Component 3: Strengthening Sélection de En cours / Recrutement Chef IDA / V3120 management of the A priori consultants par Direct 180,000.00 0.00 2020-11-19 2021-02-17 2020-11-29 2021-02-02 2026-02-01 d'exécution Composante 2 du PASEB II education sector entente directe MR-BESSP-213537-CS-CQS / Component 3: Strengthening Spécialiste en Passation des IDA / V3120 management of the A posteriori Individuel Open 162,000.00 13,204.92 Signé 2021-01-14 2021-01-19 2021-02-02 2021-07-16 2021-02-03 2021-07-28 2021-02-15 2021-09-20 2021-08-14 Marchés education sector Component 1: Transforming MR-BESSP-208741-CS-CDS / Sélection de teacher management using Appui au développement du IDA / V3120 A posteriori consultants par Direct 1,600,000.00 0.00 Annulé 2020-12-15 2021-01-04 2021-01-17 2026-01-16 accountability frameworks SIGE entente directe and new technology MR-BESSP-213511-CS-CQS / Component 3: Strengthening recrutement d'un auditeur IDA / V3120 management of the A posteriori Individuel Open 27,600.00 25,921.78 Signé 2021-01-14 2021-01-25 2021-03-04 2021-07-19 2021-03-14 2021-07-26 2021-03-28 2021-09-09 2026-03-27 interne education sector MR-BESSP-213509-CS-CDS / Component 3: Strengthening Sélection de En cours Expert en Education IDA / V3120 management of the A posteriori consultants par Direct 144,000.00 0.00 2021-01-12 2021-02-03 2021-01-20 2021-02-08 2022-02-08 d'exécution /Formation education sector entente directe MR-BESSP-213292-CS-CDS / Component 3: Strengthening Sélection de Expert IDA / V3120 management of the A posteriori consultants par Direct 60,000.00 0.00 Annulé 2021-01-11 2021-02-03 2021-01-21 2021-02-10 2022-02-10 Economiste/planificateur de education sector entente directe l’Education MR-BESSP-219785-CS-INDV / Responsable du suivi des Component 3: Strengthening questions environnementales En cours IDA / V3120 management of the A posteriori Individuel Open 32,400.00 0.00 2021-02-15 2021-02-24 2021-03-09 2021-03-16 2021-03-22 2022-03-22 et sociales dans l’exécution d'exécution education sector des infrastructures du Projet PASEBII MR-BESSP-219970-CS-INDV Component 4: Contingent / Recrutement spécialiste IDA / V3120 Emergency Response A posteriori Individuel Open 162,000.00 0.00 Annulé 2021-02-16 2021-03-22 2021-04-01 2021-04-11 2026-04-10 Passation des Marchés 2 Component MR-BESSP-223600-CS-INDV Component 2: Improving En cours / Spécialiste de Passation des IDA / V3120 education service delivery in A posteriori Individuel Limited 162,000.00 0.00 2021-03-14 2021-03-16 2021-03-19 2021-04-09 2021-05-14 2021-11-10 d'exécution Marchés selected regions MR-BESSP-222850-CS-INDV Component 3: Strengthening Sélection de / Recrutement d'une IDA / V3120 management of the A posteriori consultants par Direct 16,939.00 16,615.90 Signé 2021-04-01 2021-04-30 2021-04-11 2021-04-26 2021-05-06 2021-07-02 2022-05-01 comptable education sector entente directe MR-BESSP-229836-CS-INDV / Recrutement d’un Consultant Individuel pour Component 2: Improving En cours l’élaboration d’un manuel de IDA / D7360 education service delivery in A posteriori Individuel Limited 33,000.00 0.00 2021-04-30 2021-06-02 2021-05-05 2021-05-20 2021-06-14 2021-07-29 d'exécution procédures pour les plans de selected regions développement Régionaux de l’éducation MR-BESSP-229880-CS-INDV / Recrutement d’un Expert Component 3: Strengthening Économiste/planificateur de IDA / D7360 management of the A posteriori Individuel Limited 40,120.00 40,175.57 Signé 2021-04-19 2021-04-26 2021-04-24 2021-04-22 2021-05-15 2021-05-17 2021-06-13 2021-06-01 2021-10-09 l’Education au profit du education sector Ministère de l’Education MR-BESSP-234173-CS-INDV / Recrutement d’un Component 1: Transforming consultant individuel pour teacher management using En attente l’élaboration des réseaux IDA / D7360 A posteriori Individuel Open 40,000.00 0.00 2021-05-20 2021-07-08 2021-07-29 2021-09-02 2021-09-06 accountability frameworks d'exécution d’échange et de partage pour and new technology la formation initiale et continue des enseignants MR-BESSP-240251-CS-INDV / Recrutement d'un consultant Component 1: Transforming individuel pour l’élaboration teacher management using IDA / D7360 A posteriori Individuel Limited 33,000.00 0.00 Annulé 2021-06-25 2021-06-30 2021-07-03 2021-07-18 2021-08-27 d'un plan de formation accountability frameworks continue pour les enseignants and new technology du fondamental. Component 1: Transforming MR-BESSP-206727-CS-CDS / Sélection de teacher management using Appui pour le développement IDA / V3120 A posteriori consultants par Direct 200,000.00 0.00 Annulé 2020-12-15 2020-12-25 2021-01-03 2022-01-03 accountability frameworks et la mise e place du SIGE entente directe and new technology MR-BESSP-280055-CS-INDV / recrutement d'un architecte Component 3: Strengthening En attente pour l'élaboration d'un plan IDA / D7360 management of the A posteriori Individuel Limited 20,000.00 0.00 2022-04-27 2022-05-02 2022-05-23 2022-06-27 2022-07-31 d'exécution d'aménagement et education sector d'extension du bâtiment de la DPEF Page 5