The World Bank Implementation Status & Results Report PNG Road Maintenance and Rehabilitation Project II (P119471) PNG Road Maintenance and Rehabilitation Project II (P119471) EAST ASIA AND PACIFIC | Papua New Guinea | Transport Global Practice | IBRD/IDA | Investment Project Financing | FY 2011 | Seq No: 20 | ARCHIVED on 23-Dec-2021 | ISR49668 | Implementing Agencies: Department of Works, The Independent State of Papua New Guinea Key Dates Key Project Dates Bank Approval Date: 03-May-2011 Effectiveness Date: 30-Aug-2011 Planned Mid Term Review Date: 30-Oct-2017 Actual Mid-Term Review Date: 09-Oct-2017 Original Closing Date: 31-Jul-2016 Revised Closing Date: 28-Apr-2023 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The project development objectives are to: (i) improve road transport to project areas through providing satisfactory physicalcondition and safety in selected roads; and (ii) strengthen institutional arrangements for road maintenance including theparticipation ofthe private sector and communities. Has the Project Development Objective been changed since Board Approval of the Project Objective? Yes Board Approved Revised Project Development Objective (If project is formally restructured) The project development objectives are to: (i) improve road transport to project areas through providing satisfactory physical condition and safety in selected roads; and (ii) strengthen institutional arrangements for road maintenance, including the participationof the private sector and communities; and (iii) enhance road-related economic opportunities for women. Components Table Name Component 1 - Rehabilitation, Upgrade and/or Maintenance of Roads and Bridges:(Cost $115.15 M) Component 2 - Technical Assistance for Project Management, Design and Supervision Services, and Capacity Building:(Cost $18.35 M) Component 3 - Contingency for Disaster Risk Response Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions On April 16, 2021, the World Bank approved the project’s restructuring with an extension of the project closing date to April 28, 2023 to allow for the completion of delayed works on Bogia-Awar and Epo-Kerema. The end-targets of the results indicators were also adjusted to reflect the inclusion of these two roads works. 12/23/2021 Page 1 of 5 The World Bank Implementation Status & Results Report PNG Road Maintenance and Rehabilitation Project II (P119471) The project is on-track to achieve its Development Objectives. With the completion of Bogia/Awar and Epo/Kerema road works, four out of the five results indicators will be fully achieved, which include: (i) increased provision of roads with good condition and safety; (ii) increased female participation in economic activities; (iii) increased private sector involvement in road maintenance; and (iv) strengthened institutional capacity in PNG for road maintenance. The fifth indicator (iv) Number of person days worked (by women) in project-related routine road maintenance activities is unlikely to be fully achieved. The contracts for the two new road works on Bogia-Awar and Epo-Kerema have been awarded and the contractor Dekenai has mobilized to both sites. The periodic maintenance on Hiritano Highway, under OPRC, is continuing during the extended project implementation period. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Moderate Moderate Macroeconomic -- Moderate Moderate Sector Strategies and Policies -- Moderate Moderate Technical Design of Project or Program -- Low Low Institutional Capacity for Implementation and -- Substantial Substantial Sustainability Fiduciary -- Substantial Substantial Environment and Social -- Substantial Substantial Stakeholders -- Substantial Substantial Other -- Substantial Substantial Overall -- Substantial Substantial Results PDO Indicators by Objectives / Outcomes Indicator One IN01082786 ►Roads rehabilitated, Rural (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 174.00 174.00 224.00 Date 30-Aug-2011 31-Mar-2021 15-Oct-2021 28-Apr-2023 Indicator Two 12/23/2021 Page 2 of 5 The World Bank Implementation Status & Results Report PNG Road Maintenance and Rehabilitation Project II (P119471) IN01082787 ►Number of persons days worked (by women) as a result of project activities on highways rehabilitation. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 2,100.00 30,000.00 30,000.00 40,000.00 Date 20-Nov-2015 31-Mar-2021 15-Oct-2021 28-Apr-2023 Indicator Three IN01082788 ►Percentage of Hiritano Highway maintained to good condition under PBC (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 30.00 37.00 37.00 42.00 Date 01-Jul-2011 31-Mar-2021 15-Oct-2021 28-Apr-2023 Indicator Four IN01082789 ►Percentage of project roads being maintained by private contractors under PBC. (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 20.00 34.00 34.00 39.00 Date 01-Jul-2011 31-Mar-2021 15-Oct-2021 28-Apr-2023 Indicator Five IN01082790 ►Number of person days worked (by women) in project-related routine road maintenance activities (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 6,782.00 6,782.00 8,500.00 Date 24-Mar-2014 31-Mar-2021 15-Oct-2021 28-Apr-2023 Intermediate Results Indicators by Components Indicator One IN01082793 ►Number of domestic companies trained in bidding and contract management. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 12/23/2021 Page 3 of 5 The World Bank Implementation Status & Results Report PNG Road Maintenance and Rehabilitation Project II (P119471) Value 0.00 8.00 8.00 10.00 Date 30-Aug-2011 31-Mar-2021 15-Oct-2021 28-Apr-2023 Indicator Two IN01082794 ►Number of works contracts tendered. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 9.00 9.00 9.00 Date 01-Jul-2011 31-Mar-2021 15-Oct-2021 28-Apr-2023 Indicator Three IN01082791 ►Number of gender-based violence and HIV/AIDS awareness workshops conducted. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 55.00 55.00 75.00 Date 01-Jul-2011 31-Mar-2021 15-Oct-2021 28-Apr-2023 Indicator Four IN01082792 ►Grievances responded to within the stipulated service standards for response time (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 80.00 80.00 80.00 100.00 Date 15-Oct-2021 31-Mar-2021 15-Oct-2021 28-Apr-2023 Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P119471 IDA-49310 Closed USD 43.00 42.98 0.02 39.74 0.00 100% P119471 IDA-54040 Effective USD 126.50 126.50 0.00 75.68 39.75 66% 12/23/2021 Page 4 of 5 The World Bank Implementation Status & Results Report PNG Road Maintenance and Rehabilitation Project II (P119471) Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P119471 IDA-49310 Closed 03-May-2011 09-Jun-2011 30-Aug-2011 31-Jul-2016 31-Mar-2018 P119471 IDA-54040 Effective 19-Feb-2014 10-Apr-2014 22-Jul-2014 30-Apr-2021 28-Apr-2023 Cumulative Disbursements PBC Disbursement Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC Restructuring History Level 2 Approved on 05-May-2016 ,Level 2 Approved on 15-Apr-2021 Related Project(s) P145120-RMRP II, Additional Financing 12/23/2021 Page 5 of 5