PROCUREMENT PLAN Lao PDR Reducing Rural Poverty and Malnutrition Project (P162565) Project information: Lao PDR - Reducing Rural Poverty and Malnutrition (RRPM) Project Project Implementation agency: Ministry of Agriculture and Forestry (MAF) Date of the Procurement Plan: September 11, 2019 Period covered by this Procurement Plan: At least 18 months (for the whole project period) Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Law and the Instruction on Implementation Public Procurement Law, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. 1 a) The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; b) Information related to award of contract including reasons for rejection of unsuccessful bidders shall be published on the implementing agency websites and/or newspaper of wide circulation. c) All complaints on procurement related matters including complaints arising from procurement under Bank financed Projects whilst using National Procurement Procedures shall be dealt with in accordance with Article 33 of the Procurement Decree. Borrower shall put in place an effective complaints review mechanism for dealing with procurement related complaints, and shall disclose the details in all the bidding documents. All complaints shall be recorded by the Borrower in the appropriate tracking and monitoring system, as agreed between the Bank and the Borrower. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information. I. Works and Goods and Non-Consultant Services 2 1.1.Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Annex II of the Procurement Regulations: Category Procurement Method Prior Review Thresholds Thresholds Applicable Remarks Applicable Remarks thresholds thresholds (US$) (US$) Works RFB through ≥ 2.0 million – Above 10 million This has not been Open foreseen at the International project preparation market stage. approach RFB through ≥ 200,000 < – None This has not been Open National 2.0 million foreseen at the market project preparation approach stage. Request for < 200,000 – None – Quotation Direct Selection None No threshold; Same as for This has not been meet competitive foreseen at the requirements of selection project preparation regulations stage. 7.13-7.15 Goods and Non-Consulting Services RFB through ≥ 0.6 million – Above 2 million This has not been Open foreseen at the International project preparation market stage. approach RFB through ≥ 100,000 < - None Risk-based approach Open National 0.6 million market approach Request for < 100,000 None Quotation Direct Selection None No threshold; Same as for This has not been meet competitive foreseen at the requirements of selection project preparation regulations stage. 7.13-7.15 1.2. Procurement packages for Goods (prior and post reviews) with method and Time Schedule 3 Ref. No. Contract Estimated Procurem Revie Expected Comment (Description) Cost (US$) ent w Bids s Method by Opening Bank Date (Prior / Post) Works Component 3: Coordination, management and evaluation C3-W-01 Office renovation 35,000 RFQ Post Sept 20, Execute by at central 2019 PMU/ DRDC, MAF C3-W-02 Office renovation 20,000 RFQ Post Jan 13, Execute by provincial level 2020 PMU/ DRDC, MAF C3-W-03 Office renovation 60,000 RFQ Post Jan 13, Execute by at district levels 2020 PMU/ DRDC, MAF Goods and non-consulting services Component 1: Developing the building blocks of a social protection system C1-NC-01 Secure connection 250,000 RFB Post Oct 15, Execute by services & wiring (National) 2019 PMU/ DRDC, MAF C1-G-01 Tablets 360,000 RFB Post Oct 15, Goods (National) 2019 delivered given that logistics take two months C1-G-02 Power Bank 30,000 RFQ Post Oct 15, Execute by 2019 PMU/ DRDC, MAF C1-G-03 Wireless routers 7,840 RFQ Post Oct 15, Execute by 2019 PMU/ DRDC, MAF C1-G-04 Desktops 98,000 RFQ Post Oct 15, Execute by 2019 PMU/ DRDC, MAF Component 2. Conditional cash transfer program C2-G-01 ID card equipment 77,200 RFQ Post Nov 2, Execute by 2019 PMU/ DRDC, MAF C2-NC-01 Establishment of 500,000 RFB Post Nov 2, Execute by bare minimum 2020 PMU/ data center and DRDC, MAF 4 backup facility for (Internatio MIS; nal/ National) Component 3: Coordination, management, and evaluation C3-G-01 IT Equipment for 158,700 RFB Post Oct 15, Execute by Central provincial (National) 2019 PMU/ and district and DRDC, MAF MPI C3-G-02 IT Equipment for 96,000 RFQ Post Oct 15, Execute by MPI district, 2019 PMU/ province and DRDC, MAF central levels C3-G-03 Office furniture for 152,000 RFB Post Nov 2, , Execute by central, provincial 2020 PMU/ and district levels. DRDC, MAF C3-G-04 Motorcycles for 180,000 RFB Post Nov 2, , Execute by central, province (National) 2020 PMU/ and district levels DRDC, MAF C3-G-05 Cars 3 SUVs 171,000 RFB Post Nov 2, , Execute by (National) 2020 PMU/ DRDC, MAF C3-G-06 Pickup truck 4 188,000 RFB Post Nov 2, , Execute by picks up (National) 2020 PMU/ DRDC, MAF C3-G-07 Field kits 16,400 RFQ Post Jan 13, Execute by 2020 PMU/ DRDC, MAF C3-G-08 FM software 25,000 RFQ Post Oct 15, Execute by 2019 PMU/ DRDC, MAF Total Goods 2,170,440 Notes: RFQ: Request for quotations RFB: Request for Bids II. Selection of Consultants 2.1 Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Annex II of the Procurement Regulations: Procurement Method Prior Review Thresholds Thresholds Applicable Category Applicable thresholds thresholds Remarks Remarks (US$, (US$) millions) 5 QCBS, QBS, FBS, ≥ 300,000 Shortlist of only ≥ 1.0 million Risk-based LCS (Using the most National approach appropriate market Consultants approach) (Firms) for contract agreed in the PP CQS (Open or < 300,000 QCBS, QBS, FBS, None limited competition LCS) can be through national or applied for international market contracts with approach, specified value under in the PP and agreed $300,000 with the Bank. Direct Selection of None No threshold; Same as for This has not firms meet competitive been foreseen requirements of selection at the project regulations 7.13- preparation 7.15 stage. Individual N/A depending Essential ≥ 300,000 Risk-based Consultants on nature of individual and for the approach services assignments will positions as be defined in the specified in Procurement Plan the PP agreed agreed with the with the Bank Bank and in line with regulations 7.34-7.39 using the most appropriate market approach 2.2 Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 7.1, Section VII of the Procurement Regulations. 2.3 Consultancy Assignments with Selection Methods and Time Schedule Ref. No. Description of Estimated Selection Review by Expected Comments Assignment Cost (US$) Method Bank Proposals (Prior / Submissio Post) n Date Component 1: Developing the building blocks of a social protection system C1-QCBS- Design, development 766,000 QCBS Post Sept 16, Execute by 01 and implementation 2019 PMU/ DRDC, of social and MAF 6 Ref. No. Description of Estimated Selection Review by Expected Comments Assignment Cost (US$) Method Bank Proposals (Prior / Submissio Post) n Date beneficiary integrated MIS C1-IC-01 Provincial database 288,000 IC Post Sept 16, Execute by manager - 4 project 2019 PMU/ DRDC, provinces MAF CI-IC-02 IT expert at central 150,000 IC Post Sept 16, Execute by level 2019 PMU/ DRDC, MAF C1-IC-03 Senior application 36,000 IC Post Apr 18, Execute by developer (GRM) 2020 PMU/ DRDC, MAF C1-IC-04 Senior tablet 54,000 IC Post Apr 18, Execute by application developer 2020 PMU/ DRDC, MAF C1-IC-05 Development of 12,000 IC Post Sept 23, in time for Manual and Training 2019 training pre. material consultant Poverty assessment Component 2: Conditional cash transfer program C2-IC-01 Senior international 45,000 IC Post Sept 30, PMU/DRDC, consultant to support 2019 MAF the setup of the cash transfer at national and district level C2-IC-02 Develop the 8,000 IC Post Jan 3, 2020 PMU/DRDC, grievance system, MAF their operational procedures and training C2-IC-03 Develop training 15,000 IC Post Jan 3, 2020 PMU/DRDC, material for CCT MAF program and testing C2-IC-04 Local consultant for 102,000 IC Post Feb 10, PMU/DRDC, SBCC coordination 2020 MAF C2-QCBS- Payment agent for 488,7961 QCBS Post Jan 20, PMU/DRDC, 01 cash transfer 2020 MAF C2-CQS- Design additional 200,000 CQS Post Nov 30 PMU/DRDC, 01 SBCC modules 2019 MAF Component 3: Coordination, management, and evaluation 1This is an upper bound estimate. 7 Ref. No. Description of Estimated Selection Review by Expected Comments Assignment Cost (US$) Method Bank Proposals (Prior / Submissio Post) n Date C3-IC-01 Project manager at 156,000 IC Post Sept 15, PMU/DRDC, PMU 2019 MAF C3-IC-02 FM Consultant for 130,000 IC Post Sept 15, PMU/DRDC, central* 2019 MAF C3-IC-03 Procurement 32,500 IC Post Sept 15, PMU/DRDC, Consultant 2019 MAF C3-IC-04 M&E Consultant for 120,000 IC Post Nov 1, PMU/DRDC, PMU 2019 MAF C3-IC-05 Commu. And 96,000 IC Post Nov 1, PMU/DRDC, safeguards 2019 MAF C3-IC-06 Accountant 14,700 IC Post Sept 15, PMU/DRDC, assistance 2019 MAF C3-IC-07 Admin assistance 14,700 IC Post Sept 15, PMU/DRDC, 2019 MAF C3-IC-09 Drivers central 46,800 IC Post Sept 15, PMU/DRDC, 2019 MAF C3-IC-10 Provincial coordinator 184,000 IC Post Nov 15, PMU/DRDC, 2019 MAF C3-IC-11 Prov FM 142,800 IC Post Nov 15, PMU/DRDC, 2019 MAF C3-IC-12 Drivers prov. 57,600 IC Post Nov 15, PMU/DRDC, 2019 MAF C3-IC-13 District FM 612,000 IC Post Nov 15, PMU/DRDC, 2019 MAF C3-IC-14 M&E consultant 612,000 IC Post Nov 15, PMU/DRDC, district 2019 MAF C3-IC-15 Community 453,600 IC Post Jan, 2020 PMU/DRDC, Mobilization officers MAF C3-IC-16 M&E Training short 9,000 IC Post Nov 15, PMU/DRDC, term Consultant 2019 MAF C3-IC-17 Impact evaluation 9,000 IC Post Nov 15, PMU/DRDC, training short term 2019 MAF Consultant C3-IC-18 M&E expert for MPI 150,000 IC Post Sept 1615, PMU/DRDC, 2019 MAF C3-CQS- Project Audits* 180,000 CQS Post Oct 5, 2020 PMU/DRDC, 01 MAF C3-CQS- CCT Process 60,000 CQS Post Oct 30, PMU/DRDC, 02 evaluation 2020 MAF C3- CQS- Iterative Beneficiary 80,000 CQS Post Oct 30, PMU/DRDC, 03 monitoring survey 2020 MAF 8 Ref. No. Description of Estimated Selection Review by Expected Comments Assignment Cost (US$) Method Bank Proposals (Prior / Submissio Post) n Date C3- CQS- Village score card 120,000 CQS Post Nov 15, PMU/DRDC, 04 development and 2019 MAF monitoring C3- CQS- Spot-check 112,000 CQS Post Nov 15, PMU/DRDC, 05 2019 MAF C3- Harmonized surveys 600,000 CQS Post Sept 16, PMU/DRDC, QCBS-01 2019 MAF Total consulting services 6,157,49 6 Total Works, Goods, Non- 8,327,93 Consulting Services and 6 Consulting Services Notes: QCBS: Quality Cost Based Selection CQS: Consultant’s Qualifications Based Selection IC: Individual Consultant * Although these packages are subject to procurement Post Review, the World Bank will do prior technical review or the EOI evaluation reports and draft negotiated contracts. To select external financial audit, project implementing agencies shall send their REOIs to all three qualified firms namely PwC, KPMG and EY; that are acceptable audit firms for bank financed projects in the Lao PDR. Means advertising for this package is not required. 9 PROCUREMENT Lao People's Democratic Republic : Reducing Rural Poverty and Malnutrition Project PLAN General Information Country: Lao People's Democratic Republic Bank’s Approval Date of the Original Procurement Plan:2019-09-20 2022-08-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162565 GPN Date: 2019-09-09 Project Name: Reducing Rural Poverty and Malnutrition Project Loan / Credit No: IDA / 63740 Department of Rural Development Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 3: Coordination, C3-W-01 / Office renovation Request for Quota Single Stage - One E 2020-05-2 IDA / 63740 management, monitoring an Post Limited 35,000.00 34,965.48 Completed 2019-09-27 2019-11-15 2019-11-22 2019-12-06 at central level tions nvelope 0 d evaluation Component 3: Coordination, C3-W-03 / Office renovation Request for Quota Single Stage - One E 2020-09-1 IDA / 63740 management, monitoring an Post Limited 60,000.00 0.00 Canceled 2020-01-18 2019-11-21 2020-03-14 at the district level tions nvelope 0 d evaluation Component 3: Coordination, C3-W-03.1 / Office renovatio Request for Quota Single Stage - One E 2021-01-2 IDA / 63740 management, monitoring an Post Open - National 25,000.00 35,005.47 Completed 2020-06-06 2020-08-01 2019-12-06 n at Hauphan province tions nvelope 8 d evaluation Component 3: Coordination, C3-W-03.2 / Office renovatio Request for Quota Single Stage - One E 2021-01-2 IDA / 63740 management, monitoring an Post Open - National 15,000.00 15,155.85 Completed 2020-05-30 2020-07-25 2020-07-23 n at Xiengkhuang province tions nvelope 1 d evaluation Component 3: Coordination, C3-W-03.3 / Office renovatio Request for Quota Single Stage - One E 2021-01-2 IDA / 63740 management, monitoring an Post Open - National 15,000.00 15,009.50 Completed 2020-06-06 2020-08-01 2020-07-15 n at Oudomxay province tions nvelope 8 d evaluation Component 3: Coordination, C3-W-03.4 / Office renovatio Request for Quota Single Stage - One E 2021-01-1 IDA / 63740 management, monitoring an Post Open - National 25,000.00 25,365.86 Completed 2020-05-25 2020-07-20 2020-07-03 n at Phongsaly province tions nvelope 6 d evaluation Component 3: Coordination, C3-W-02 / Office renovation Request for Quota Single Stage - One E 2020-09-1 IDA / 63740 management, monitoring an Post Limited 20,000.00 0.00 Canceled 2020-01-18 2020-03-14 at the provincial level tions nvelope 0 d evaluation GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Developing th C1-G-01 / Tablets for Social Single Stage - One E IDA / 63740 e building blocks of a social Post Request for Bids Open - National 360,000.00 360,000.00 Completed 2019-10-15 2020-03-20 2019-10-20 2019-12-01 2020-03-24 2019-12-31 2020-04-20 2020-02-04 2020-05-08 2020-08-02 2020-07-17 Registry nvelope protection system Component 1: Developing th C1-G-04 / Desktops for a dat Request for Quota Single Stage - One E IDA / 63740 e building blocks of a social Post Open - National 98,000.00 0.00 Canceled 2019-10-20 2019-12-15 2020-06-12 a access point tions nvelope protection system Component 2: Conditional ca Request for Quota Single Stage - One E C2-G-01 / ID card equipment IDA / 63740 Post Open - National 77,200.00 40,598.87 Completed 2019-11-08 2020-01-03 2020-12-14 2020-07-01 2020-12-25 sh transfer program tions nvelope C3-G-02 / IT equipment for Component 3: Coordination, Request for Quota Single Stage - One E MPI district, provincial and ce IDA / 63740 management, monitoring an Post Open - National 96,000.00 87,953.94 Completed 2019-10-20 2019-12-15 2020-07-22 2020-06-12 2020-08-31 tions nvelope ntral level d evaluation C3-G-03 / Office furniture for Component 3: Coordination, Single Stage - One E central, provincial and distric IDA / 63740 management, monitoring an Post Request for Bids Limited 113,000.00 0.00 Canceled 2019-11-03 2019-11-08 2019-12-20 2020-01-19 2020-02-23 2020-08-21 nvelope t levels d evaluation C3-G-04 / Motorcycles for ce Component 2: Conditional ca Single Stage - One E IDA / 63740 Post Request for Bids Open - National 180,000.00 136,354.00 Signed 2019-11-03 2020-02-24 2019-11-08 2019-12-20 2020-03-24 2020-01-19 2020-03-26 2020-02-23 2020-04-20 2020-08-21 ntral, provincial and district l sh transfer program nvelope evels Component 3: Coordination, C3-G-05 / 3 Vehicles for cent Single Stage - One E IDA / 63740 management, monitoring an Post Request for Bids Open - National 171,000.00 0.00 Canceled 2019-11-03 2020-07-29 2019-11-08 2019-12-20 2020-08-31 2020-01-19 2020-02-23 2020-08-21 ral level nvelope d evaluation Component 3: Coordination, Request for Quota Single Stage - One E C3-G-07 / Field kits IDA / 63740 management, monitoring an Post Limited 16,400.00 17,321.21 Completed 2020-01-18 2021-06-24 2020-03-14 2021-07-28 2020-09-10 2021-10-18 tions nvelope d evaluation Component 3: Coordination, Request for Quota Single Stage - One E C3-G-08 / FM software IDA / 63740 management, monitoring an Post Limited 25,000.00 35,286.76 Completed 2019-10-02 2020-12-03 2019-11-27 2021-01-20 2020-05-25 2021-03-16 tions nvelope d evaluation C3-G-01 / IT equipment for c Component 3: Coordination, Single Stage - One E entral, provincial and district IDA / 63740 management, monitoring an Post Request for Bids Open - National 158,700.00 0.00 Canceled 2019-10-31 2019-11-05 2019-12-17 2020-01-16 2020-02-20 2020-08-18 nvelope levels d evaluation Component 1: Developing th C1-G-02 / Power Banks for S Request for Quota Single Stage - One E IDA / 63740 e building blocks of a social Post Open - National 30,000.00 50,515.84 Completed 2019-11-05 2019-12-31 2020-07-16 2020-06-28 2020-08-17 ocial Registry tions nvelope protection system Component 1: Developing th C1-G-04.1 / Desktops & Lapt Request for Quota Single Stage - One E IDA / 63740 e building blocks of a social Post Open - National 24,000.00 32,305.24 Completed 2020-12-08 2021-02-02 2020-07-16 2021-08-01 2020-09-02 ops for Center & Provinces tions nvelope protection system Component 1: Developing th C1-G-04.2 / Desktops for Dis Request for Quota Single Stage - One E IDA / 63740 e building blocks of a social Post Open - National 74,000.00 87,288.64 Completed 2020-12-25 2021-02-19 2020-07-28 2021-08-18 2020-07-31 trict tions nvelope protection system Component 3: Coordination, C3-G-01.1 / IT Equipment for Request for Quota Single Stage - One E IDA / 63740 management, monitoring an Post Open - National 60,000.00 51,158.53 Completed 2020-02-06 2020-04-02 2020-02-27 2020-09-29 2020-04-20 MAF central tions nvelope d evaluation Component 3: Coordination, C3-G-01.2 / IT Equipment for Request for Quota Single Stage - One E IDA / 63740 management, monitoring an Post Open - National 98,700.00 80,232.64 Completed 2020-03-04 2020-04-29 2020-03-12 2020-10-26 2020-05-26 Provinces & Districts tions nvelope d evaluation Page 1 Component 3: Coordination, C3-G-01.3 / IT Equipment for Request for Quota Single Stage - One E IDA / 63740 management, monitoring an Post Open - National 55,000.00 49,317.69 Completed 2020-04-08 2020-06-03 2020-04-30 2020-11-30 2020-06-05 Provinces & Districts tions nvelope d evaluation C3-G-02.1 / IT Equipment for Component 3: Coordination, Request for Quota Single Stage - One E MPI district, province and cen IDA / 63740 management, monitoring an Post Open - National 78,000.00 77,922.70 Completed 2020-10-14 2020-12-09 2020-07-22 2021-06-07 2020-10-16 tions nvelope tral levels d evaluation C3-G-02.2 / Furniture for MPI Component 3: Coordination, Request for Quota Single Stage - One E district, province and central IDA / 63740 management, monitoring an Post Open - National 18,000.00 20,522.88 Signed 2020-10-23 2020-12-18 2020-07-08 2021-06-16 tions nvelope levels d evaluation Component 3: Coordination, C3-G-03.1 / Office furniture f Request for Quota Single Stage - One E IDA / 63740 management, monitoring an Post Open - National 53,000.00 36,915.48 Completed 2020-01-13 2020-03-09 2020-02-27 2020-09-05 2020-03-26 or MAF central. tions nvelope d evaluation C3-G-03.2 / Office furniture f Component 3: Coordination, Request for Quota or provincial and district leve IDA / 63740 management, monitoring an Post 99,000.00 87,044.28 Completed 2020-01-19 2020-03-15 2020-03-03 2020-09-11 2020-05-21 tions ls d evaluation Component 1: Developing th Request for Quota Single Stage - One E C1-G-03 / Wireless Routers IDA / 63740 e building blocks of a social Post Open - National 7,840.00 0.00 Canceled 2019-11-05 2019-12-31 2020-06-28 tions nvelope protection system Component 3: Coordination, C3-G-06 / 4 Vehicles for prov Single Stage - One E IDA / 63740 management, monitoring an Post Request for Bids Open - National 188,000.00 0.00 Canceled 2019-11-03 2020-07-29 2019-11-08 2019-12-20 2020-08-31 2020-01-19 2020-02-23 2020-08-21 inces nvelope d evaluation C2-G-01.2 / IT Equipment for Component 2: Conditional ca Request for Quota Single Stage - One E IDA / 63740 Post Open - National 16,400.00 15,828.52 Completed 2020-08-04 2020-09-29 2020-08-18 2021-03-28 2020-11-20 Backup & Monitoring sh transfer program tions nvelope Component 1: Developing th C1-G-01.6 / Secure connecti Request for Quota Single Stage - One E IDA / 63740 e building blocks of a social Post Open - National 41,000.00 32,547.84 Completed 2020-10-05 2020-11-30 2020-08-18 2021-05-29 2020-10-12 on services & wiring tions nvelope protection system C2-G-01.1 / Server room ren Component 2: Conditional ca Single Stage - One E ovation, New server, Network IDA / 63740 Post Request for Bids Open - National 383,600.00 492,593.23 Completed 2020-11-15 2020-10-15 2020-11-20 2021-01-01 2020-11-17 2021-01-31 2021-01-19 2021-03-07 2021-02-12 2021-09-03 2021-10-04 sh transfer program nvelope ing System, Power supply an d Backup Component 3: Coordination, Request for Quota Single Stage - One E C3-G-09 / VC Equipment IDA / 63740 management, monitoring an Post Open - National 20,900.00 20,000.06 Completed 2021-04-04 2021-05-30 2021-08-27 2021-11-26 2021-10-08 tions nvelope d evaluation C1-G-01.1 / Equipment for S Component 1: Developing th Request for Quota Single Stage - One E ecure connection services & IDA / 63740 e building blocks of a social Post Open - National 29,000.00 27,544.67 Completed 2020-09-20 2020-11-15 2020-06-18 2021-05-14 2020-07-22 tions nvelope wiring protection system Component 3: Coordination, C3-G-05.1 / Cars 3 SUVs and Single Stage - One E IDA / 63740 management, monitoring an Post Request for Bids Open - National 359,000.00 383,058.87 Completed 2021-06-11 2020-10-29 2021-06-16 2021-07-28 2020-11-11 2021-08-27 2020-12-04 2021-10-01 2021-02-02 2022-03-30 2021-10-04 Pickup truck 4 picks up nvelope d evaluation Component 1: Developing th C1-G06 / CCT Communicatio Request for Quota Single Stage - One E IDA / 63740 e building blocks of a social Post Open - National 30,000.00 20,446.18 Completed 2021-08-09 2021-10-04 2021-08-27 2022-04-02 2021-10-18 n tool kits tions nvelope protection system C2-G02 / Toner for ID Cards Component 2: Conditional ca Request for Quota Single Stage - One E IDA / 63740 Post Open - National 15,000.00 12,888.74 Completed 2021-09-15 2021-11-10 2021-10-13 2022-05-09 2021-11-11 Printing sh transfer program tions nvelope C1-G-01.2 / Secure connecti Component 1: Developing th on services & wiring (RRPMP, IDA / 63740 e building blocks of a social Post Direct Selection Direct 55,000.00 30,838.08 Completed 2021-09-12 2021-08-20 2021-09-17 2021-09-27 2021-10-22 2021-10-12 2022-04-20 2022-02-01 NAFRI, Provinces & Districts) protection system C2-G03 / PVC Cards use for Component 2: Conditional ca Request for Quota Single Stage - One E IDA / 63740 Post Open - National 20,000.00 16,817.32 Completed 2021-11-15 2022-01-10 2021-12-10 2022-07-09 2021-12-22 printer ID card sh transfer program tions nvelope Component 3: Coordination, C3.2-G-10 / Motorbike for MP Request for Quota Single Stage - One E IDA / 63740 management, monitoring an Post Open - National 27,400.00 28,969.75 Signed 2022-07-20 2022-09-14 2022-07-25 2023-03-13 I tions nvelope d evaluation Component 1: Developing th C1-G-07 / CCT Poster Printin Request for Quota Single Stage - One E IDA / 63740 e building blocks of a social Post Open - National 30,000.00 25,158.57 Signed 2022-07-20 2022-09-14 2022-07-25 2023-03-13 g tions nvelope protection system NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Developing th C1-NC-01 / Secure connectio Single Stage - One E IDA / 63740 e building blocks of a social Post Request for Bids Open - National 250,000.00 0.00 Canceled 2019-10-15 2019-10-20 2019-12-01 2019-12-31 2020-02-04 2020-08-02 n services and wiring nvelope protection system C2-NC-01 / Establishment of Component 2: Conditional ca Open - Internationa Single Stage - One E a bare minimum data center IDA / 63740 Post Request for Bids 500,000.00 0.00 Canceled 2019-10-15 2019-11-29 2019-10-20 2019-12-01 2019-12-31 2020-02-04 2020-08-02 sh transfer program l nvelope and backup facility for MIS Component 1: Developing th C1-G-05 / Cloud Server & Ho IDA / 63740 e building blocks of a social Post Direct Selection Direct 10,000.00 9,900.00 Completed 2020-05-05 2020-06-06 2020-05-10 2020-08-03 2020-06-14 2020-06-30 2020-12-11 2020-08-18 sting protection system Component 3: Coordination, Request for Quota Single Stage - One E C3-NC-02 / Translation IDA / 63740 management, monitoring an Post Open - National 20,000.00 11,772.62 Signed 2021-03-03 2021-04-28 2021-01-20 2021-10-25 tions nvelope d evaluation Component 1: Developing th C1-G-05.1 / Cloud Server & IDA / 63740 e building blocks of a social Post Direct Selection Direct 22,000.00 23,004.09 Completed 2021-06-30 2021-05-06 2021-07-05 2021-05-21 2021-08-09 2021-06-30 2022-02-05 2021-08-12 Hosting protection system Component 3: Coordination, C3-NC-11 / Translation servi Request for Quota Single Stage - One E IDA / 63740 management, monitoring an Post Open - National 20,000.00 6,642.00 Signed 2022-08-20 2022-10-15 2022-07-25 2023-04-13 ce provider tions nvelope d evaluation CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Page 2 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C1-QCBS-01 / Design, develo Component 1: Developing th Quality And Cost- Open - Internationa pment, and implementation IDA / 63740 e building blocks of a social Post 703,800.00 796,400.00 Signed 2019-09-27 2019-11-26 2019-10-18 2019-11-26 2019-12-01 2020-02-25 2019-12-29 2020-03-26 2020-01-28 2020-05-25 2020-03-03 2020-06-15 2020-04-07 2020-08-05 2021-04-07 Based Selection l of social and beneficiary inte protection system grated MIS C2-QCBS-01 / payment agen Component 2: Conditional ca Quality And Cost- IDA / 63740 Post Open - National 488,796.00 364,773.75 Signed 2019-11-24 2020-04-10 2019-12-15 2020-01-28 2020-06-12 2020-02-25 2020-07-17 2020-03-26 2020-08-12 2020-04-30 2021-01-14 2020-06-04 2021-02-24 2021-06-04 t for cash sh transfer program Based Selection C3- CQS-04 / Village score c Component 3: Coordination, Consultant Qualifi ard development and monito IDA / 63740 management, monitoring an Post Open - National 120,000.00 0.00 Canceled 2019-11-15 2019-12-06 2020-01-19 2020-02-18 2020-03-24 2020-09-20 cation Selection ring d evaluation Component 3: Coordination, Consultant Qualifi C3- CQS-05 / Spot-check IDA / 63740 management, monitoring an Post Open - National 112,000.00 0.00 Canceled 2019-11-15 2019-12-06 2020-01-19 2020-02-18 2020-03-24 2020-09-20 cation Selection d evaluation Component 3: Coordination, C3- QCBS-01 / Harmonized s Consultant Qualifi IDA / 63740 management, monitoring an Post Open - National 200,000.00 199,144.00 Completed 2019-10-27 2019-11-13 2019-11-17 2019-11-26 2019-12-31 2020-02-16 2020-01-30 2020-04-01 2020-03-05 2020-05-06 2020-09-01 2021-11-01 urveys - baseline cation Selection d evaluation Component 3: Coordination, C3-CQS-6.2 / Harmonized Su Consultant Qualifi IDA / 63740 management, monitoring an Post Open - National 200,000.00 0.00 Canceled 2021-05-02 2021-05-23 2021-07-06 2021-08-05 2021-09-09 2022-03-08 rvey - Midterm cation Selection d evaluation Component 3: Coordination, C3-CQS-6.3 / Harmonized su Consultant Qualifi Pending Impleme IDA / 63740 management, monitoring an Post Open - National 200,000.00 0.00 2023-05-01 2023-05-22 2023-07-05 2023-08-04 2023-09-08 2024-03-06 rvey - impact evaluation cation Selection ntation d evaluation C2-CQS-01 / Design addition Component 2: Conditional ca Consultant Qualifi IDA / 63740 Post Open - National 200,000.00 194,282.00 Signed 2019-12-08 2021-04-07 2019-12-29 2020-02-11 2021-08-16 2020-03-12 2021-11-03 2020-04-16 2021-11-30 2020-10-13 al SBCC modules sh transfer program cation Selection Component 3: Coordination, Consultant Qualifi C3-CQS-01 / Project Audits IDA / 63740 management, monitoring an Post Open - National 180,000.00 68,134.00 Signed 2021-01-31 2021-01-22 2021-02-21 2021-04-06 2021-05-20 2021-05-06 2021-06-02 2021-06-10 2021-06-22 2021-12-07 cation Selection d evaluation Component 3: Coordination, C3- CQS-03 / Iterative Benefi Consultant Qualifi Under Implement IDA / 63740 management, monitoring an Post Open - National 80,000.00 0.00 2022-02-01 2022-01-28 2022-02-22 2022-02-03 2022-04-07 2022-06-16 2022-05-07 2022-06-11 2022-12-08 ciary monitoring survey cation Selection ation d evaluation Component 3: Coordination, C3-CQS-02 / CCT Process ev Consultant Qualifi Pending Impleme IDA / 63740 management, monitoring an Post Open - National 60,000.00 0.00 2022-08-15 2022-09-05 2022-10-19 2022-11-18 2022-12-23 2023-06-21 aluation cation Selection ntation d evaluation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Coordination, C3-IC-02 / FM Consultant for Individual Consult IDA / 63740 management, monitoring an Post Open 130,000.00 34,200.00 Completed 2019-09-27 2019-10-13 2019-11-15 2019-12-03 2019-12-06 2019-12-17 2020-01-10 2019-12-20 2020-07-08 2020-12-30 central ant Selection d evaluation Component 3: Coordination, C3-IC-03 / Procurement Cons Individual Consult IDA / 63740 management, monitoring an Post Open 32,500.00 32,400.00 Completed 2019-09-27 2019-10-13 2019-11-15 2019-11-26 2019-12-06 2019-12-03 2020-01-10 2019-12-20 2020-07-08 2021-02-28 ultant ant Selection d evaluation Component 3: Coordination, C3-IC-01 / Project manager a Individual Consult IDA / 63740 management, monitoring an Post Open 156,000.00 39,600.00 Signed 2019-09-27 2019-10-13 2019-11-15 2019-12-03 2019-12-06 2019-12-04 2020-01-10 2019-12-20 2020-07-08 t PMU ant Selection d evaluation Component 1: Developing th C1-IC-02 / IT expert at centr Individual Consult IDA / 63740 e building blocks of a social Post Open 150,000.00 61,560.00 Signed 2019-09-27 2019-10-13 2019-11-15 2019-12-13 2019-12-06 2019-12-27 2020-01-10 2019-12-30 2020-07-08 al level ant Selection protection system Component 1: Developing th C1-IC-03 / Senior Application Individual Consult IDA / 63740 e building blocks of a social Post Open 36,000.00 0.00 Canceled 2020-03-23 2020-05-11 2020-06-01 2020-07-06 2021-01-02 Developer (GRM) ant Selection protection system Component 1: Developing th C1-IC-04 / senior tablet appli Individual Consult IDA / 63740 e building blocks of a social Post Open 54,000.00 0.00 Canceled 2020-03-23 2020-05-11 2020-06-01 2020-07-06 2021-01-02 cation developer ant Selection protection system Component 1: Developing th C1-IC-05 / Development of tr Individual Consult IDA / 63740 e building blocks of a social Post Open 12,000.00 0.00 Canceled 2019-09-27 2019-11-15 2019-12-06 2020-01-10 2020-07-08 aining material consultant ant Selection protection system C2-IC-01 / Senior internation al consultant to support the s Component 2: Conditional ca Individual Consult IDA / 63740 Post Open 45,000.00 0.00 Canceled 2019-09-27 2019-11-15 2019-12-06 2020-01-10 2020-07-08 etup of the cash transfer at n sh transfer program ant Selection ational, provincial and distric t levels. C2-IC-02 / Develop the griev Component 2: Conditional ca Individual Consult ance system, their operation IDA / 63740 Post Open 8,000.00 0.00 Canceled 2020-01-05 2020-02-23 2020-03-15 2020-04-19 2020-10-16 sh transfer program ant Selection al procedures, and training C2-IC-03 / Develop training Component 2: Conditional ca Individual Consult IDA / 63740 Post Open 15,000.00 0.00 Canceled 2020-01-05 2020-02-23 2020-03-15 2020-04-19 2020-10-16 material for CCT program an sh transfer program ant Selection d test C2-IC-04 / Local consultant f Component 2: Conditional ca Individual Consult IDA / 63740 Post Open 102,000.00 0.00 Canceled 2020-01-05 2021-03-21 2020-02-23 2020-03-15 2020-04-19 2020-10-16 or SBCC coordination sh transfer program ant Selection Component 3: Coordination, C3-IC-04 / M&E consultant fo Individual Consult IDA / 63740 management, monitoring an Post Open 120,000.00 158,400.00 Signed 2019-10-20 2020-03-12 2019-12-08 2020-07-28 2019-12-29 2020-08-10 2020-02-02 2020-08-10 2020-07-31 r PMU ant Selection d evaluation Component 3: Coordination, C3-IC-05 / Communication a Individual Consult IDA / 63740 management, monitoring an Post Open 96,000.00 19,800.00 Signed 2019-11-17 2021-05-25 2020-01-05 2021-07-21 2020-01-26 2021-07-21 2020-03-01 2021-08-01 2020-08-28 nd Safeguards Consultant ant Selection d evaluation Component 3: Coordination, C3-IC-10 / Provincial coordin Individual Consult IDA / 63740 management, monitoring an Post Open 184,000.00 0.00 Canceled 2019-11-17 2020-04-10 2020-01-05 2020-01-26 2020-03-01 2020-08-28 ator ant Selection d evaluation Component 3: Coordination, C3-IC-16 / M&E Training shor Individual Consult IDA / 63740 management, monitoring an Post Open 9,000.00 0.00 Canceled 2019-11-17 2020-01-05 2020-01-26 2020-03-01 2020-08-28 t-term consultant ant Selection d evaluation Page 3 Component 3: Coordination, C3-IC-18 / M&E expert for M Individual Consult IDA / 63740 management, monitoring an Post Open 150,000.00 50,000.00 Signed 2019-10-04 2019-10-13 2019-11-22 2020-02-04 2019-12-13 2020-02-05 2020-01-17 2020-02-05 2020-07-15 PI ant Selection d evaluation C1-IC-1.1 / Provincial databa Component 1: Developing th se manager will also act as d Individual Consult IDA / 63740 e building blocks of a social Post Open 72,000.00 0.00 Canceled 2019-11-17 2020-01-05 2020-01-26 2020-03-01 2020-08-28 ata collection for poverty ass ant Selection protection system essment supervisor Component 1: Developing th C1-IC-1.2 / also for poverty d Individual Consult IDA / 63740 e building blocks of a social Post Open 72,000.00 0.00 Canceled 2019-11-17 2020-01-05 2020-01-26 2020-03-01 2020-08-28 ata collection supervisor ant Selection protection system C1-IC-1.3 / will also act as a Component 1: Developing th Individual Consult poverty data collection super IDA / 63740 e building blocks of a social Post Open 72,000.00 0.00 Canceled 2019-11-17 2020-01-05 2020-01-26 2020-03-01 2020-08-28 ant Selection visor protection system C1-IC-1.4 / will also act as a Component 1: Developing th Individual Consult poverty data collection super IDA / 63740 e building blocks of a social Post Open 72,000.00 0.00 Canceled 2019-11-17 2020-01-05 2020-01-26 2020-03-01 2020-08-28 ant Selection visor protection system Component 3: Coordination, C3-IC-13 / District FM consul Individual Consult IDA / 63740 management, monitoring an Post Open 612,000.00 0.00 Canceled 2019-11-17 2020-04-03 2020-01-05 2020-01-26 2020-03-01 2020-08-28 tant (12) ant Selection d evaluation Component 3: Coordination, C3-IC-14 / M&E consultant fo Individual Consult IDA / 63740 management, monitoring an Post Open 612,000.00 0.00 Canceled 2019-11-17 2020-05-22 2020-01-05 2020-01-26 2020-03-01 2020-08-28 r the district ant Selection d evaluation Component 3: Coordination, C3-IC-15 / Community Mobili Individual Consult IDA / 63740 management, monitoring an Post Open 453,600.00 0.00 Canceled 2020-02-02 2020-03-22 2020-04-12 2020-05-17 2020-11-13 sation Office ant Selection d evaluation Component 3: Coordination, C3-IC-06 / Accountance Assi Individual Consult IDA / 63740 management, monitoring an Post Open 14,700.00 0.00 Canceled 2019-09-27 2019-11-15 2019-12-06 2020-01-10 2020-07-08 stance ant Selection d evaluation Component 3: Coordination, C3-IC-07 / Administration as Individual Consult IDA / 63740 management, monitoring an Post Open 14,700.00 0.00 Canceled 2019-09-27 2019-11-15 2019-12-06 2020-01-10 2020-07-08 sistance ant Selection d evaluation Component 1: Developing th C1-IC-01.1 / Provincial IT ass Individual Consult IDA / 63740 e building blocks of a social Post Open 72,000.00 18,000.00 Signed 2020-05-31 2020-03-08 2020-07-19 2020-07-01 2020-08-09 2020-06-02 2020-09-13 2020-07-15 2021-03-12 istants Huaphan provinces ant Selection protection system C1-IC-01.2 / Provincial IT ass Component 1: Developing th Individual Consult istants Xiengkhuang provinc IDA / 63740 e building blocks of a social Post Open 72,000.00 18,000.00 Signed 2020-05-31 2020-03-08 2020-07-19 2020-08-25 2020-08-09 2020-08-28 2020-09-13 2020-08-28 2021-03-12 ant Selection es protection system Component 1: Developing th C1-IC-01.3 / Provincial IT ass Individual Consult IDA / 63740 e building blocks of a social Post Open 72,000.00 18,000.00 Signed 2020-05-31 2020-03-08 2020-07-19 2020-08-28 2020-08-09 2020-08-28 2020-09-13 2020-09-04 2021-03-12 istants Oudomxay provinces ant Selection protection system Component 1: Developing th C1-IC-01.4 / Provincial IT ass Individual Consult IDA / 63740 e building blocks of a social Post Open 72,000.00 18,000.00 Signed 2020-05-31 2020-03-08 2020-07-19 2020-08-25 2020-08-09 2020-08-28 2020-09-13 2020-08-28 2021-03-12 istants Phongsaly provinces ant Selection protection system Component 3: Coordination, C3-IC-20 / Nutrition Converg Individual Consult IDA / 63740 management, monitoring an Post Open 36,000.00 27,600.00 Signed 2020-12-30 2020-10-19 2021-02-17 2021-03-04 2021-03-10 2021-03-10 2021-04-14 2021-03-10 2021-10-11 ence Coordinator ant Selection d evaluation Component 3: Coordination, C3-IC-21 / Procurement Assi Individual Consult IDA / 63740 management, monitoring an Post Open 10,000.00 9,600.00 Signed 2021-02-28 2020-12-17 2021-04-18 2021-07-15 2021-05-09 2021-07-15 2021-06-13 2021-07-23 2021-12-10 stant ant Selection d evaluation Component 3: Coordination, C3-IC-22 / Accountant for MP Individual Consult IDA / 63740 management, monitoring an Post Open 6,000.00 9,600.00 Signed 2021-03-30 2020-12-17 2021-05-18 2021-03-03 2021-06-08 2021-03-04 2021-07-13 2021-03-13 2022-01-09 I ant Selection d evaluation C2-IC-01.1 / National Consult Component 2: Conditional ca IDA / 63740 Post Direct Selection Direct 20,000.00 8,800.00 Signed 2021-03-19 2021-03-22 2021-03-28 2021-05-05 2021-04-21 2021-05-21 2021-10-20 ant on CCT Payment. sh transfer program Component 3: Coordination, C3-IC-11 / Provincial Account Individual Consult IDA / 63740 management, monitoring an Post Open 142,800.00 0.00 Canceled 2019-11-17 2020-01-05 2020-01-26 2020-03-01 2020-08-28 ant ant Selection d evaluation Component 3: Coordination, C3-IC-01.1 / Project manager Individual Consult IDA / 63740 management, monitoring an Post Open 156,000.00 40,800.00 Signed 2021-05-30 2021-06-17 2021-07-18 2021-07-21 2021-08-08 2021-07-21 2021-09-12 2021-08-01 2022-03-11 at PMU ant Selection d evaluation Component 3: Coordination, C3-IC-03.1 / Procurement Co Individual Consult IDA / 63740 management, monitoring an Post Open 32,500.00 31,680.00 Signed 2021-05-25 2021-03-01 2021-07-13 2021-04-08 2021-08-03 2021-03-29 2021-09-07 2021-04-21 2022-03-06 nsultant ant Selection d evaluation Component 3: Coordination, C3-IC-23 / Provincial coordin Individual Consult IDA / 63740 management, monitoring an Post Open 46,000.00 20,400.00 Signed 2021-05-25 2021-01-25 2021-07-13 2021-04-07 2021-08-03 2021-04-23 2021-09-07 2021-04-23 2022-03-06 ator ant Selection d evaluation Component 3: Coordination, C3-IC-24 / District Coordinat Individual Consult IDA / 63740 management, monitoring an Post Open 204,000.00 0.00 Canceled 2021-05-30 2021-07-18 2021-08-08 2021-09-12 2022-03-11 or & M&E consultant district ant Selection d evaluation C3-IC-14.8.1 / District Coordi Component 3: Coordination, Individual Consult nator & M&E consultant for N IDA / 63740 management, monitoring an Post Open 41,000.00 12,000.00 Signed 2021-06-11 2021-05-02 2021-07-30 2021-06-11 2021-08-20 2021-06-08 2021-09-24 2021-07-01 2022-03-23 ant Selection onghad district, Xiengkhaung d evaluation Province. C3-IC-14.1.1 / District Coordi Component 3: Coordination, Individual Consult nator & M&E consultant for M IDA / 63740 management, monitoring an Post Open 42,000.00 12,000.00 Completed 2021-06-11 2021-05-02 2021-07-30 2021-06-11 2021-08-20 2021-06-08 2021-09-24 2021-07-01 2022-03-23 2021-07-27 ant Selection ai district, Phongsaly Provinc d evaluation e C3-IC-14.9.1 / District Coordi Component 3: Coordination, Individual Consult nator & M&E consultant for K IDA / 63740 management, monitoring an Post Open 42,000.00 12,000.00 Signed 2021-06-11 2021-05-02 2021-07-30 2021-06-11 2021-08-20 2021-06-08 2021-09-24 2021-07-01 2022-03-23 ant Selection huan district Huaphan Provin d evaluation ce C3-IC-14.11.1 / District Coor Component 3: Coordination, Individual Consult dinator & M&E consultant for IDA / 63740 management, monitoring an Post Open 42,000.00 12,000.00 Signed 2021-06-11 2021-05-02 2021-07-30 2021-06-11 2021-08-20 2021-06-08 2021-09-24 2021-07-01 2022-03-23 ant Selection Huamueang district Huaphan d evaluation Province Component 3: Coordination, C3-IC-11.1 / Provincial Accou Individual Consult IDA / 63740 management, monitoring an Post Open 16,800.00 8,400.00 Signed 2021-07-01 2021-02-19 2021-08-19 2021-08-12 2021-09-09 2021-08-13 2021-10-14 2021-08-20 2022-04-12 ntant for Phongsaly ant Selection d evaluation Page 4 Component 3: Coordination, C3-IC-11.2 / Provincial Accou Individual Consult IDA / 63740 management, monitoring an Post Open 16,800.00 8,400.00 Signed 2021-07-01 2021-02-19 2021-08-19 2021-08-12 2021-09-09 2021-08-13 2021-10-14 2021-08-20 2022-04-12 ntant for Udomxay ant Selection d evaluation Component 3: Coordination, C3-IC-11.3 / Provincial Accou Individual Consult IDA / 63740 management, monitoring an Post Open 16,800.00 8,400.00 Signed 2021-07-01 2021-02-19 2021-08-19 2021-08-12 2021-09-09 2021-08-13 2021-10-14 2021-08-20 2022-04-12 ntant for Xiengkhua ant Selection d evaluation Component 3: Coordination, C3-IC-11.4 / Provincial Accou Individual Consult IDA / 63740 management, monitoring an Post Open 16,800.00 8,400.00 Signed 2021-07-01 2021-02-19 2021-08-19 2021-08-12 2021-09-09 2021-08-13 2021-10-14 2021-08-20 2022-04-12 ntant for Huaphanh ant Selection d evaluation C3-IC-15.25.1 / Community Component 3: Coordination, Individual Consult Mobilization Officer, Namor D IDA / 63740 management, monitoring an Post Open 8,400.00 3,600.00 Signed 2021-06-11 2021-02-01 2021-07-30 2021-03-24 2021-08-20 2021-03-23 2021-09-24 2021-03-29 2022-03-23 ant Selection is, UDX d evaluation C3-IC-15.40.1 / Community Component 3: Coordination, Individual Consult Mobilization Officer, Khuan Di IDA / 63740 management, monitoring an Post Open 8,400.00 3,600.00 Signed 2021-06-11 2021-02-01 2021-07-30 2021-03-24 2021-08-20 2021-03-23 2021-09-24 2021-03-29 2022-03-23 ant Selection s, HPH d evaluation C3-IC-15.36.1 / Community Component 3: Coordination, Individual Consult Mobilization Officer, Khuan Di IDA / 63740 management, monitoring an Post Open 8,400.00 0.38 Signed 2021-07-08 2021-06-01 2021-08-26 2021-07-20 2021-09-16 2021-07-16 2021-10-21 2021-07-23 2022-04-19 ant Selection strict, Huaphanh Province d evaluation C3-IC-14.1.1.1 / District Coor Component 3: Coordination, Individual Consult dinator & M&E consultant for IDA / 63740 management, monitoring an Post Limited 42,000.00 12,000.00 Terminated 2021-08-02 2021-01-20 2021-08-07 2021-08-12 2021-08-28 2021-08-13 2021-10-02 2021-08-25 2022-03-31 ant Selection Mai district Phongsaly Provin d evaluation ce C3-IC-14.3.1 / District Coordi Component 3: Coordination, Individual Consult nator & M&E consultant for S IDA / 63740 management, monitoring an Post Limited 39,000.00 12,000.00 Signed 2021-08-10 2020-02-20 2021-08-15 2021-08-12 2021-09-05 2021-08-13 2021-10-10 2021-08-20 2022-04-08 ant Selection amphanh district, Phongsaly d evaluation Province C3-IC-15.5.1 / Community M Component 3: Coordination, Individual Consult obilization Officer, Mai Dis, P IDA / 63740 management, monitoring an Post Open 5,700.00 3,600.00 Signed 2021-10-20 2020-03-12 2021-12-08 2021-10-29 2021-12-29 2021-10-20 2022-02-02 2021-11-01 2022-08-01 ant Selection SL d evaluation C3-IC-13.10.1 / District Acco Component 3: Coordination, Individual Consult untant for Khuan District, Ha IDA / 63740 management, monitoring an Post Open 40,500.00 9,600.00 Signed 2021-10-29 2021-11-04 2021-12-17 2021-11-23 2022-01-07 2021-11-25 2022-02-11 2021-12-01 2022-08-10 ant Selection uphan province d evaluation C3-IC-15.46.1 / Community Component 3: Coordination, Individual Consult Mobilization Officer, Huameu IDA / 63740 management, monitoring an Post Open 3,900.00 3,600.00 Signed 2021-11-01 2021-11-04 2021-12-20 2021-11-25 2022-01-10 2021-11-25 2022-02-14 2021-12-01 2022-08-13 ant Selection ng Dis, HPH d evaluation C3-IC-15.25.2 / Community Component 3: Coordination, Individual Consult Mobilization Officer, Namor D IDA / 63740 management, monitoring an Post Open 3,600.00 3,600.00 Signed 2021-11-01 2021-11-01 2021-12-20 2021-11-25 2022-01-10 2021-11-25 2022-02-14 2021-12-01 2022-08-13 ant Selection is, UDX d evaluation C3-IC-15.55 / Community Mo Component 3: Coordination, Individual Consult bilization Officer in Khua Dis, IDA / 63740 management, monitoring an Post Open 7,200.00 3,600.00 Signed 2022-01-25 2022-01-20 2022-03-15 2022-02-18 2022-04-05 2022-02-21 2022-05-10 2022-03-01 2022-11-06 ant Selection PSL d evaluation C3-IC-15.56 / Community Mo Component 3: Coordination, Individual Consult bilization Officer, Mai Dis, PS IDA / 63740 management, monitoring an Post Open 7,200.00 3,600.00 Signed 2022-01-25 2022-01-20 2022-03-15 2022-02-18 2022-04-05 2022-02-21 2022-05-10 2022-03-01 2022-11-06 ant Selection L d evaluation C3-IC-15.57 / Community Mo Component 3: Coordination, Individual Consult bilization Officer, Huameuan IDA / 63740 management, monitoring an Post Open 7,200.00 3,600.00 Signed 2022-01-25 2022-01-20 2022-03-15 2022-02-18 2022-04-05 2022-02-21 2022-05-10 2022-03-01 2022-11-06 ant Selection g Dis, HPH d evaluation C3-IC-15.58 / Community Mo Component 3: Coordination, Individual Consult bilization Officer, Xamtai Dis, IDA / 63740 management, monitoring an Post Open 7,200.00 3,600.00 Signed 2022-01-25 2022-01-20 2022-03-15 2022-02-18 2022-04-05 2022-02-21 2022-05-10 2022-03-01 2022-11-06 ant Selection HPH d evaluation C3-IC-15.59 / Community Mo Component 3: Coordination, Individual Consult bilization Officer, Kuan Dis, H IDA / 63740 management, monitoring an Post Open 7,200.00 3,600.00 Signed 2022-01-25 2022-01-20 2022-03-15 2022-02-18 2022-04-05 2022-02-21 2022-05-10 2022-03-01 2022-11-06 ant Selection PH d evaluation C3-IC-15.60 / Community Mo Component 3: Coordination, Individual Consult bilization Officer, Nonghead IDA / 63740 management, monitoring an Post Open 7,200.00 3,600.00 Signed 2022-01-25 2022-01-20 2022-03-15 2022-02-18 2022-04-05 2022-02-21 2022-05-10 2022-03-01 2022-11-06 ant Selection Dis, XKH d evaluation C3-IC-17 / Impact evaluation Component 3: Coordination, Individual Consult training short term Consultan IDA / 63740 management, monitoring an Post Open 9,000.00 0.00 Canceled 2019-11-15 2020-01-03 2020-01-24 2020-02-28 2020-08-26 ant Selection t d evaluation C3-IC-14.3.1.1 / District Coor Component 3: Coordination, Individual Consult dinator & M&E consultant for IDA / 63740 management, monitoring an Post Open 51,000.00 12,000.00 Signed 2022-03-01 2022-02-10 2022-04-19 2022-03-17 2022-05-10 2022-03-25 2022-06-14 2022-04-01 2022-12-11 ant Selection Samphanh district, Phongsal d evaluation y Province Component 3: Coordination, C3.2-IC-23 / Admin Officer fo Individual Consult IDA / 63740 management, monitoring an Post Open 11,400.00 7,200.00 Signed 2022-03-01 2022-02-11 2022-04-19 2022-03-17 2022-05-10 2022-03-28 2022-06-14 2022-04-01 2022-12-11 r DIC, MPI ant Selection d evaluation C3.2-IC-24 / Technical Assist Component 3: Coordination, Individual Consult Under Implement ance for M&E Nutrition Conve IDA / 63740 management, monitoring an Post Open 18,000.00 0.00 2022-04-01 2022-06-16 2022-05-20 2022-06-10 2022-07-15 2023-01-11 ant Selection ation rgence d evaluation Component 3: Coordination, C3-IC-013.12 / District Accou Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 9,600.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-07-22 2020-05-30 2020-07-22 2020-11-26 ntant ant Selection d evaluation Component 3: Coordination, C3-IC-13.11 / District Accoun Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 9,600.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-07-22 2020-05-30 2020-07-21 2020-11-26 tant ant Selection d evaluation Component 3: Coordination, C3-IC-13.10 / District Accoun Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 9,600.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-07-22 2020-05-30 2020-07-22 2020-11-26 tant ant Selection d evaluation Component 3: Coordination, C3-IC-13.9 / District Account Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 9,600.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-07-21 2020-05-30 2020-07-22 2020-11-26 ant ant Selection d evaluation Component 3: Coordination, C3-IC-13.6 / District Account Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 9,600.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-07-22 2020-05-30 2020-07-23 2020-11-26 ant ant Selection d evaluation Component 3: Coordination, C3-IC-13.5 / District Account Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 9,600.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-07-22 2020-05-30 2020-07-21 2020-11-26 ant ant Selection d evaluation Page 5 Component 3: Coordination, C3-IC-13.3 / District Account Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 9,600.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-07-21 2020-05-30 2020-07-21 2020-11-26 ant ant Selection d evaluation Component 3: Coordination, C3-IC-13.2 / District Account Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 9,600.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-07-22 2020-05-30 2020-07-21 2020-11-26 ant ant Selection d evaluation Component 3: Coordination, C3-IC-13.1 / District Account Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 9,600.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-07-22 2020-05-30 2020-07-21 2020-11-26 ant ant Selection d evaluation Component 3: Coordination, C3-IC-13.4 / District Account Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 9,600.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-07-22 2020-05-30 2020-07-23 2020-11-26 ant ant Selection d evaluation Component 3: Coordination, C3-IC-13.7 / District Account Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 9,600.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-07-22 2020-05-30 2020-07-21 2020-11-26 ant ant Selection d evaluation Component 3: Coordination, C3-IC-13.8 / District Account Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 9,600.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-07-22 2020-05-30 2020-07-21 2020-11-26 ant in Nonghead District ant Selection d evaluation Component 3: Coordination, C3-IC-13.4.1 / District Accou Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 8,400.00 Signed 2020-02-15 2020-03-16 2020-04-04 2021-02-11 2020-04-25 2021-02-19 2020-05-30 2021-02-11 2020-11-26 nts ant Selection d evaluation Component 3: Coordination, C3-IC-15.26 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.27 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.28 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.29 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-20 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.31 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.32 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.33 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.34 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.51 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.52 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.53 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.46 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.47 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.48 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.41 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-17 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.42 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-10 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.43 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.44 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.36 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.37 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.38 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Page 6 Component 3: Coordination, C3-IC-15.19 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.20 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.21 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.22 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-17 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.23 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.15 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.16 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.11 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.12 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-17 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.13 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-17 2020-05-30 2020-07-23 2020-11-26 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.6 / Community Mob Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 ilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.7 / Community Mob Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 ilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.8 / Community Mob Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 ilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.1 / Community Mob Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 ilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.2 / Community Mob Individual Consult IDA / 63740 management, monitoring an Post Open 14,500.00 3,600.00 Signed 2020-02-15 2020-03-12 2020-04-04 2020-07-17 2020-04-25 2020-07-20 2020-05-30 2020-07-23 2020-11-26 ilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.30 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 11,000.00 3,600.00 Signed 2020-08-15 2020-03-12 2020-10-03 2020-11-02 2020-10-24 2020-11-11 2020-11-28 2020-11-30 2021-05-27 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.35 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 11,000.00 3,600.00 Signed 2020-08-15 2020-03-12 2020-10-03 2020-11-02 2020-10-24 2020-11-11 2020-11-28 2020-11-30 2021-05-27 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.54 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 11,000.00 3,600.00 Signed 2020-08-15 2020-03-12 2020-10-03 2020-11-02 2020-10-24 2020-11-11 2020-11-28 2020-12-03 2021-05-27 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.45 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 11,000.00 3,600.00 Signed 2020-08-15 2020-03-12 2020-10-03 2020-11-02 2020-10-24 2020-11-11 2020-11-28 2020-12-03 2021-05-27 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.39 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 11,000.00 3,600.00 Signed 2020-08-15 2020-03-12 2020-10-03 2020-11-02 2020-10-24 2020-11-11 2020-11-28 2020-12-03 2021-05-27 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.40 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 11,000.00 3,600.00 Signed 2020-08-15 2020-03-12 2020-10-03 2020-11-02 2020-10-24 2020-11-11 2020-11-28 2020-12-03 2021-05-27 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.49 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 11,000.00 3,600.00 Signed 2020-08-15 2020-03-12 2020-10-03 2020-12-02 2020-10-24 2020-11-02 2020-11-28 2020-12-03 2021-05-27 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.50 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 11,000.00 3,600.00 Signed 2020-08-15 2020-03-12 2020-10-03 2020-11-02 2020-10-24 2020-11-11 2020-11-28 2020-12-03 2021-05-27 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.24 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 11,000.00 3,600.00 Signed 2020-08-15 2020-03-12 2020-10-03 2020-11-02 2020-10-24 2020-11-11 2020-11-28 2020-11-30 2021-05-27 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.25 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 11,000.00 3,600.00 Signed 2020-08-15 2020-03-12 2020-10-03 2020-11-02 2020-10-24 2020-11-11 2020-11-28 2020-11-30 2021-05-27 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.3 / Community Mob Individual Consult IDA / 63740 management, monitoring an Post Open 11,000.00 3,600.00 Signed 2020-08-15 2020-03-12 2020-10-03 2020-10-29 2020-10-24 2020-11-11 2020-11-28 2020-12-03 2021-05-27 ilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.5 / Community Mob Individual Consult IDA / 63740 management, monitoring an Post Open 11,000.00 3,600.00 Signed 2020-08-15 2020-03-12 2020-10-03 2020-11-02 2020-10-24 2020-11-11 2020-11-28 2020-12-03 2021-05-27 ilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.4 / Community Mob Individual Consult IDA / 63740 management, monitoring an Post Open 11,000.00 3,600.00 Signed 2020-08-15 2020-03-12 2020-10-03 2020-11-02 2020-10-24 2020-11-11 2020-11-28 2020-12-03 2021-05-27 ilization officer ant Selection d evaluation Page 7 Component 3: Coordination, C3-IC-15.9 / Community Mob Individual Consult IDA / 63740 management, monitoring an Post Open 11,000.00 3,600.00 Signed 2020-08-15 2020-03-12 2020-10-03 2020-11-02 2020-10-24 2020-11-11 2020-11-28 2020-12-03 2021-05-27 ilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.10 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 11,000.00 3,600.00 Signed 2020-08-15 2020-03-12 2020-10-03 2020-11-02 2020-10-24 2020-11-11 2020-11-28 2020-12-03 2021-05-27 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.17 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 11,000.00 3,600.00 Signed 2020-08-15 2020-03-12 2020-10-03 2020-11-02 2020-10-24 2020-11-11 2020-11-28 2020-12-03 2021-05-27 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.18 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 11,000.00 3,600.00 Signed 2020-08-15 2020-03-12 2020-10-03 2020-11-02 2020-10-24 2020-11-11 2020-11-28 2020-12-03 2021-05-27 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-15.14 / Community Mo Individual Consult IDA / 63740 management, monitoring an Post Open 11,000.00 3,600.00 Signed 2020-08-15 2020-03-21 2020-10-03 2020-11-02 2020-10-24 2020-11-11 2020-11-28 2020-12-03 2021-05-27 bilization officer ant Selection d evaluation Component 3: Coordination, C3-IC-10.1 / Provincial coordi Individual Consult IDA / 63740 management, monitoring an Post Open 46,000.00 20,400.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-06-29 2020-05-30 2020-07-21 2020-11-26 nator ant Selection d evaluation Component 3: Coordination, C3-IC-10.4 / Provincial coordi Individual Consult IDA / 63740 management, monitoring an Post Open 46,000.00 20,400.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-06-29 2020-05-30 2020-07-21 2020-11-26 nator ant Selection d evaluation Component 3: Coordination, C3-IC-10.3 / Provincial coordi Individual Consult IDA / 63740 management, monitoring an Post Open 46,000.00 20,400.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-06-29 2020-05-30 2020-07-21 2020-11-26 nator ant Selection d evaluation Component 3: Coordination, C3-IC-10.2 / Provincial coordi Individual Consult IDA / 63740 management, monitoring an Post Open 46,000.00 20,400.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-06-29 2020-05-30 2020-07-24 2020-11-26 nator ant Selection d evaluation Component 3: Coordination, C3-IC-14.7 / District Coordin Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 12,000.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-07-21 2020-05-30 2020-07-21 2020-11-26 ator & M&E ant Selection d evaluation Component 3: Coordination, C3-IC-14.8 / District Coordin Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 12,000.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-07-21 2020-05-30 2020-07-21 2020-11-26 ator & M&E ant Selection d evaluation Component 3: Coordination, C3-IC-14.12 / District Coordi Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 12,000.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-07-21 2020-05-30 2020-07-21 2020-11-26 nator & M&E ant Selection d evaluation Component 3: Coordination, C3-IC-14.11 / District Coordi Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 12,000.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-07-21 2020-05-30 2020-07-24 2020-11-26 nator & M&E ant Selection d evaluation Component 3: Coordination, C3-IC-14.10 / District Coordi Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 12,000.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-07-21 2020-05-30 2020-07-21 2020-11-26 nator & M&E ant Selection d evaluation Component 3: Coordination, C3-IC-14.9 / District Coordin Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 12,000.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-07-21 2020-05-30 2020-07-21 2020-11-26 ator & M&E ant Selection d evaluation Component 3: Coordination, C3-IC-14.5 / District Coordin Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 12,000.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-08 2020-04-25 2020-07-21 2020-05-30 2020-07-21 2020-11-26 ator & M&E ant Selection d evaluation Component 3: Coordination, C3-IC-14.6 / District Coordin Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 12,000.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-07-21 2020-05-30 2020-07-17 2020-11-26 ator & M&E ant Selection d evaluation Component 3: Coordination, C3-IC-14.4 / District Coordin Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 12,000.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-07-21 2020-05-30 2020-07-24 2020-11-26 ator & M&E ant Selection d evaluation Component 3: Coordination, C3-IC-14.3 / District Coordin Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 12,000.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-07-21 2020-05-30 2020-07-21 2020-11-26 ator & M&E ant Selection d evaluation Component 3: Coordination, C3-IC-14.2 / District Coordin Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 12,000.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-07-21 2020-05-30 2020-07-24 2020-11-26 ator & M&E ant Selection d evaluation Component 3: Coordination, C3-IC-14.1 / District Coordin Individual Consult IDA / 63740 management, monitoring an Post Open 51,000.00 12,000.00 Signed 2020-02-15 2020-03-16 2020-04-04 2020-07-17 2020-04-25 2020-07-21 2020-05-30 2020-07-21 2020-11-26 ator & M&E ant Selection d evaluation Component 3: Coordination, C3-IC-26 / M&E Officer for P Individual Consult IDA / 63740 management, monitoring an Post Open 120,000.00 42,000.00 Signed 2022-04-15 2022-03-22 2022-06-03 2022-04-28 2022-06-24 2022-05-05 2022-07-29 2022-05-20 2023-01-25 MU ant Selection d evaluation C3-DS-03 / Consulting Firm f Component 3: Coordination, Under Implement or Nutrition Convergence Mo IDA / 63740 management, monitoring an Post Direct Selection Direct 200,000.00 210,000.00 2022-05-01 2022-04-08 2022-05-11 2022-04-19 2022-07-15 2023-01-11 ation nitoring Midline Survey 2022 d evaluation Component 3: Coordination, C3-IC-25 / M&E training shor Individual Consult Pending Impleme IDA / 63740 management, monitoring an Post Direct 9,000.00 0.00 2022-09-01 2022-09-11 2022-10-02 2022-11-06 2023-05-05 t term Consultant ant Selection ntation d evaluation C3-IC-13.9.1 / District FM for Component 3: Coordination, Individual Consult Xamtai District, Hauphan pro IDA / 63740 management, monitoring an Post Open 51,000.00 9,600.00 Signed 2022-06-15 2022-05-27 2022-08-03 2022-06-16 2022-08-24 2022-06-17 2022-09-28 2022-06-17 2023-03-27 ant Selection vince d evaluation C3-IC-13.8.1 / District Accou Component 3: Coordination, Individual Consult Under Implement ntant in Nonghead District, Xi IDA / 63740 management, monitoring an Post Open 51,000.00 0.00 2022-07-29 2022-07-25 2022-09-16 2022-10-07 2022-11-11 2023-05-10 ant Selection ation engkhuang province d evaluation Component 3: Coordination, C3-IC-18.1 / M&E Expert for Individual Consult IDA / 63740 management, monitoring an Post Open 150,000.00 0.00 Under Review 2022-07-31 2022-07-21 2022-09-18 2022-10-09 2022-11-13 2023-05-12 MPI ant Selection d evaluation C3-IC-15.47.1 / Community Component 3: Coordination, Individual Consult Pending Impleme Mobilization Officer, Huameu IDA / 63740 management, monitoring an Post Open - National 10,400.00 0.00 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2023-06-13 ant Selection ntation ng Dis, HPH d evaluation Page 8 Component 3: Coordination, C3-IC-05.1 / Communication Individual Consult Pending Impleme IDA / 63740 management, monitoring an Post Open - National 96,000.00 0.00 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2023-06-13 and Inclusion Specialist ant Selection ntation d evaluation Page 9