Procurement Plan (P 155350) Sindh Resilience Project I. General 1. Bank’s approval Date of the procurement Plan [Original: February 28, 2016]: Revision of Updated Procurement Plan, May 2017 ] 2. Date of General Procurement Notice: August 2016 3. Period covered by this procurement plan: The procurement period of project covered from year May 2017 to December 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project issued by SID 4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 July 9, 2010 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] July 9, 2010 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Pakistan : Sindh Resilience Project PLAN General Information Country: Pakistan Bank’s Approval Date of the Original Procurement Plan: 2016-11-03 2022-01-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155350 GPN Date: 2016-10-28 Project Name: Sindh Resilience Project Loan / Credit No: IDA / 58880, IDA / 67940 Sindh Irrigation Department Executing Agency(ies): WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SID-2961-CW-RFP / Providing stone pitching between BU Bund from mile 13/3 to 35/3 and indo bund Improving Infrastructure and Single Stage - One 5,024,100.3 2017-10- IDA / 58880 Prior Request for Bids Open - International Signed 2016-11-25 2017-06-02 2016-12-09 2017-06-08 2017-01-23 2017-07-24 2017-02-22 2017-10-02 2017-04-07 2017-10-27 from mile 0/0 to 15/6 total Systems for Resilience Envelope 6 04 15 miles and 7 furlongs in Sakro Division Mirpursakro. (Baghar Circle Hyderabad). PK-SID-2963-CW-RFP / CONSTRUCTION OF BHANSAR Improving Infrastructure and Single Stage - One 2018-01- SMALL/RECHARGE DAM IN IDA / 58880 Post Request for Bids Open - National 0.00 Canceled 2017-03-01 2017-03-16 2017-04-27 2017-05-29 2017-07-12 Systems for Resilience Envelope 08 NAGARPARKAR AREA (THAR REGION) PK-SID-2964-CW-RFP / CONSTRUCTION OF SABUSAN Improving Infrastructure and Single Stage - One 2018-01- SMALL/RECHARGE DAM IN IDA / 58880 Post Request for Bids Open - National 0.00 Canceled 2017-03-01 2017-03-16 2017-04-27 2017-05-29 2017-07-12 Systems for Resilience Envelope 08 NAGARPARKAR AREA (THAR REGION) PK-SID-2965-CW-RFP / CONSTRUCTION OF SANKAR Improving Infrastructure and Single Stage - One 2018-01- SMALL/RECHARGE DAM IN IDA / 58880 Post Request for Bids Open - National 0.00 Canceled 2017-03-01 2017-03-16 2017-04-27 2017-05-29 2017-07-12 Systems for Resilience Envelope 08 NAGARPARKAR AREA (THAR REGION) PK-SID-2967-CW-RFP / CONSTRUCTION OF KONKAR Improving Infrastructure and Single Stage - One 2018-06- IDA / 58880 Post Request for Bids Open - National 0.00 Canceled 2017-08-01 2017-08-16 2017-09-27 2017-10-27 2017-12-08 RECHARGE/SMALL DAM IN Systems for Resilience Envelope 06 LOWER KOHISTAN PK-SID-2968-CW-RFP / CONSTRUCTION OF Improving Infrastructure and Single Stage - One 2018-06- KARMATIANI IDA / 58880 Post Request for Bids Open - National 0.00 Canceled 2017-08-01 2017-08-16 2017-09-27 2017-10-27 2017-12-08 Systems for Resilience Envelope 06 RECHARGE/SMALL DAM IN LOWER KOHISTAN PK-SID-2960-CW-RFP / Recoupment of stone Apron along S.H Bund mile 1/6 to 2/1 and Repair to damage stone pitching along S.H Bund Improving Infrastructure and Single Stage - One 1,042,222.8 2017-11- mile 1/0 to 3/0 (Different IDA / 58880 Prior Request for Bids Open - National Signed 2017-01-21 2017-06-29 2017-01-26 2017-07-07 2017-03-09 2017-08-07 2017-04-08 2017-09-21 2017-05-13 2017-10-16 Systems for Resilience Envelope 4 09 Reaches) and widening of S.H Bund from mile 0/4 to 3/2 in Kalri Baghar Division Thatta.(Baghar Circle Hyderabad). PK-SID-2962-CW-RFP / Stone pitching and Toe Wall along M.S Bund mile 29/2 to 29/5, 36/0 to 40/0, 45/0 to Improving Infrastructure and Single Stage - One 2017-11- 58/2, Raising and IDA / 58880 Prior Request for Bids Open - National 0.00 Canceled 2017-01-21 2017-06-29 2017-01-26 2017-03-09 2017-04-08 2017-05-13 Systems for Resilience Envelope 09 strengthening along M.S Bund mile 55/4 to 58/2 in Lower Pinyari Division Sujawal. (Pinyari Circle Hyderabad). PK-SID-20260-CW-RFB / Providing Stone Pitching along Under M.S Bund mile 29/2 to 29/5, Improving Infrastructure and Single Stage - One 3,557,787.4 2018-03- IDA / 58880 Post Request for Bids Open - National Implementat 2017-07-21 2017-05-20 2017-07-21 2017-08-07 2017-08-21 2017-08-07 2017-08-28 2017-09-22 2017-10-02 2017-10-17 36/0 to 40/0 to 58/2 and Systems for Resilience Envelope 6 31 ion Raising and Strengthening of M.S Bund mile 55/4 to 58/2. PK-SID-29036-CW-RFB / Providing Stone Pitching along Improving Infrastructure and Single Stage - One 4,146,864.0 2018-11- PB Bund from mile 0/0 to 8/5 IDA / 58880 Post Request for Bids Open - National Signed 2017-09-19 2018-04-08 2017-09-22 2018-04-10 2017-10-23 2018-05-10 2017-10-30 2018-06-04 2017-11-06 2018-07-05 Systems for Resilience Envelope 3 05 and 11/4 to 15/0 in Kalri Baghar Division Thatta. PK-SID-29042-CW-RFB / Earthwork & Repair Damaged Stone Pitching along up Improving Infrastructure and Single Stage - One 2018-11- 2019- Stream left side guide bund IDA / 58880 Post Request for Bids Open - National 791,521.35 Completed 2017-09-19 2018-04-08 2017-09-22 2018-04-10 2017-10-23 2018-05-10 2017-10-30 2018-06-04 2017-11-06 2018-07-09 Systems for Resilience Envelope 05 04-02 from RD 0+000 to RD 5+700 in Kotri Barrage Division Jamshoro. PK-SID-29051-CW-RFB / Providing Stone Pitching along MS Bund from mile 0/0 to Improving Infrastructure and Single Stage - One 6,072,151.7 2018-11- IDA / 58880 Post Request for Bids Open - National Signed 2017-09-19 2018-04-08 2017-09-22 2018-04-10 2017-10-23 2018-05-10 2017-10-30 2018-06-04 2017-11-06 2018-07-05 14/0 and 22/0 to 24/7 in Systems for Resilience Envelope 7 05 Upper Pinyari Division, Hyderabad PK-SID-29055-CW-RFB / Providing Stone Pitching along Improving Infrastructure and Single Stage - One 2018-11- BU Bund from mile 3/0 to 5/0 IDA / 58880 Post Request for Bids Open - National 969,963.22 Signed 2017-09-19 2018-04-09 2017-09-22 2018-04-10 2017-10-23 2018-05-10 2017-10-30 2018-06-04 2017-11-06 2018-07-05 Systems for Resilience Envelope 05 in Kalri Baghar Division Thatta. Page 1 PK-SID-29086-CW-RFB / Providing Stone Pitching along Kuka Link Bund 0/0 to 20/6, Raising and Strengthening Improving Infrastructure and Single Stage - One 4,924,242.9 2018-11- along Kuka Wari Bund mile IDA / 58880 Post Request for Bids Open - National Signed 2017-09-19 2018-04-08 2017-09-22 2018-04-10 2017-10-23 2018-05-10 2017-10-30 2018-06-04 2017-11-06 2018-07-04 Systems for Resilience Envelope 4 05 3/6 to7/4 and Kuka Wari Retarded Bund mile 0/0 to 3/0 in Lower Pinyari Division Sujawal. PK-SID-37707-CW-RFB / Recoupment of Damaged Stone Pitching & Earth Work along SM Bund from mile Improving Infrastructure and Single Stage - One 2019-04- IDA / 58880 Post Request for Bids Open - National 0.00 Canceled 2018-01-16 2018-01-19 2018-02-21 2018-03-07 2018-04-11 123/0 to 172/0 (Different Systems for Resilience Envelope 10 Reaches) in Hala Irrigation Division Hala. (95 percent from counterpart funding). PK-SID-69711-CW-RFB / Construction of 2Nos: Improving Infrastructure and Single Stage - One 3,757,015.5 2019-11- Small/Recharge Dams in IDA / 58880 Post Request for Bids Open - National Signed 2018-07-16 2018-07-18 2018-07-19 2018-07-19 2018-08-20 2018-08-27 2018-09-19 2018-09-10 2018-11-02 2018-10-01 Systems for Resilience Envelope 9 01 Lower Khoistan Malir namely Karmatiani and Konkar. PK-SID-2969-CW-RFP / CONSTRUCTION OF ARIPIR Improving Infrastructure and Single Stage - One 2,137,362.2 2019-11- IDA / 58880 Post Request for Bids Open - National Signed 2018-07-16 2018-07-18 2018-07-19 2018-07-19 2018-08-20 2018-08-27 2018-09-19 2018-09-13 2018-11-02 2018-10-03 RECHARGE/SMALL DAM IN Systems for Resilience Envelope 9 01 LOWER KOHISTAN. PK-SID-2966-CW-RFP / CONSTRUCTION OF JUNG Improving Infrastructure and Single Stage - One 3,332,375.0 2019-11- IDA / 58880 Post Request for Bids Open - National Signed 2018-07-16 2018-07-18 2018-07-19 2018-07-19 2018-08-20 2018-08-27 2018-09-19 2018-09-10 2018-11-02 2018-10-03 SHAHI RECHARGE/SMALL DAM Systems for Resilience Envelope 8 01 IN LOWER KOHISTAN PK-SID-69710-CW-RFB / Construction of 2Nos: Improving Infrastructure and Single Stage - One 7,044,375.2 2019-11- Small/Recharge Dams in IDA / 58880 Post Request for Bids Open - International Signed 2018-07-16 2018-07-18 2018-07-19 2018-07-20 2018-09-03 2018-09-07 2018-10-03 2018-10-22 2018-11-16 2018-11-26 Systems for Resilience Envelope 8 15 Tharparkar namely Sabusan and Sankar. PK-SID-83933-CW-RFB / Recoupment of Damaged Stone Pitching & Earth Work along SM Bund from mile 123/0 to 172/0 (Different Improving Infrastructure and Single Stage - One 1,063,696.5 2019-10- IDA / 58880 Post Request for Bids Open - National Signed 2018-10-29 2018-12-26 2018-11-01 2019-01-03 2018-12-03 2019-02-04 2019-01-02 2019-06-28 2019-01-30 2019-07-23 Reaches) in Hala Irrigation Systems for Resilience Envelope 1 27 Division Hala. (100 percent payment will be made counterpart funding through Government of Sindh). PK-SID-93082-CW-RFB / Package No: 14 Construction Improving Infrastructure and Single Stage - One 2,950,660.0 2020-03- IDA / 58880 Post Request for Bids Open - National Signed 2018-12-28 2019-01-02 2018-12-31 2019-01-03 2019-01-30 2019-02-04 2019-03-01 2019-03-27 2019-03-29 2019-04-08 of Bhansar/ Rathi Small Systems for Resilience Envelope 1 27 storage Dam. PK-SID-93083-CW-RFB / Package No: 15 Lot No. 1 Construction of Naing-II Small/Recharge Dam. Improving Infrastructure and Single Stage - One 6,109,757.4 2020-03- IDA / 58880 Post Request for Bids Open - National Signed 2018-12-28 2019-01-02 2018-12-31 2019-01-03 2019-01-30 2019-02-04 2019-03-01 2019-03-05 2019-03-29 2019-03-29 Lot No. 2 Systems for Resilience Envelope 1 27 Construction of Gabol and Dhal Dhoro-II Small/Recharge Dams. PK-SID-93084-CW-RFB / Package No: 16 Lot No. 1 Construction of Tikho-II and Improving Infrastructure and Single Stage - One 5,460,536.9 2020-03- Sureshi Small/Recharge Dams. IDA / 58880 Post Request for Bids Open - National Signed 2018-12-28 2019-01-02 2018-12-31 2019-01-03 2019-01-30 2019-02-04 2019-03-01 2019-03-01 2019-03-29 2019-04-24 Systems for Resilience Envelope 5 27 Lot No. 2 Construction of Upper Mole-II Small/Recharge Dam. PK-SID-93086-CW-RFB / Package No: 17 Construction Improving Infrastructure and Single Stage - One 3,549,284.4 2020-03- IDA / 58880 Post Request for Bids Open - National Signed 2018-12-28 2019-01-02 2018-12-31 2019-01-03 2019-01-30 2019-02-04 2019-03-01 2019-05-24 2019-03-29 2019-06-13 of Nali and Qasim Tok Systems for Resilience Envelope 2 27 Small/Recharge Dams. PK-SID-119972-CW-RFB / Package-I: Construction and Improving Infrastructure and Single Stage - One 1,135,510.3 2020-07- Rehabilitation of Laboratory IDA / 58880 Post Request for Bids Open - National Signed 2019-06-21 2019-07-01 2019-06-24 2019-07-08 2019-07-24 2019-08-09 2019-08-23 2019-09-05 2019-10-11 2019-10-24 Systems for Resilience Envelope 5 07 Building and Trays. 1 PK-SID-178002-CW-RFB / Construction of Jaganwari Improving Infrastructure and Single Stage - One 1,785,852.7 2021-10- IDA / 58880 Post Request for Bids Open - National Signed 2020-07-01 2020-09-10 2020-07-02 2020-09-10 2020-08-03 2020-10-15 2020-09-02 2021-03-18 2020-10-14 2021-04-14 Small/Recharge Dam in Systems for Resilience Envelope 4 13 Khairpur Mirs'. PK-SID-178003-CW-RFB / Construction of Tungwari Improving Infrastructure and Single Stage - One 2,032,490.0 2021-10- IDA / 58880 Post Request for Bids Open - National Signed 2020-07-01 2020-09-10 2020-07-02 2020-09-10 2020-08-03 2020-10-15 2020-09-02 2021-03-18 2020-10-14 2021-04-20 Small/Recharge Dam in Systems for Resilience Envelope 7 13 Khairpur Mirs'. PK-SID-178008-CW-RFB / Construction of Darig Improving Infrastructure and Single Stage - One 2,075,865.1 2021-10- IDA / 58880 Post Request for Bids Open - National Signed 2020-07-01 2020-09-10 2020-07-02 2020-09-10 2020-08-03 2020-10-15 2020-09-02 2021-04-28 2020-10-14 2021-06-09 Small/Recharge Dam in Systems for Resilience Envelope 8 13 Khairpur Mirs'. PK-SID-178009-CW-RFB / Construction of Samlee Improving Infrastructure and Single Stage - One 3,431,427.1 2021-10- IDA / 58880 Post Request for Bids Open - National Signed 2020-07-01 2020-09-10 2020-07-02 2020-09-10 2020-08-03 2020-10-15 2020-09-02 2021-03-18 2020-10-14 2021-04-16 Small/Recharge Dam in Systems for Resilience Envelope 5 13 Nagarparkar (Thar Region). PK-SID-178010-CW-RFB / Construction of Paro Jo Improving Infrastructure and Single Stage - One 2,288,220.0 2021-10- IDA / 58880 Post Request for Bids Open - National Signed 2020-07-01 2020-09-10 2020-07-02 2020-09-10 2020-08-03 2020-10-15 2020-09-02 2021-03-18 2020-10-14 2021-04-06 Wandhio Small/Recharge Dam Systems for Resilience Envelope 3 13 in Nagarparkar (Thar Region). PK-SID-178011-CW-RFB / Construction of Sehriyoon Improving Infrastructure and Single Stage - One 2,466,385.3 2021-10- IDA / 58880 Post Request for Bids Open - National Signed 2020-07-01 2020-09-10 2020-07-02 2020-09-10 2020-08-03 2020-10-15 2020-09-02 2021-03-18 2020-10-14 2021-04-28 Small/Recharge Dam in Systems for Resilience Envelope 2 13 Nagarparkar (Thar Region). Page 2 PK-SID-182665-CW-RFB / Reconstruction of Soil Improving Infrastructure and Single Stage - One 2021-10- IDA / 58880 Post Request for Bids Open - National 310,844.81 Signed 2020-07-01 2020-07-17 2020-07-03 2020-07-17 2020-08-02 2020-08-19 2020-09-01 2020-11-02 2020-10-06 2020-12-08 Mechanics Laboratory and Systems for Resilience Envelope 05 Office Building at Karachi. PK-SID-220119-CW-RFB / Improving Infrastructure and Single Stage - One 2,405,200.2 2022-06- CONSTRUCTION OF BHATTA IDA / 67940 Post Request for Bids Open - National Signed 2021-02-17 2021-02-19 2021-02-22 2021-02-26 2021-03-26 2021-03-25 2021-04-26 2021-04-30 2021-06-09 2021-06-10 Systems for Resilience Envelope 9 08 SIRO DAM IN NAGARPARKAR. PK-SID-220128-CW-RFB / Improving Infrastructure and Single Stage - One 1,746,755.0 2022-06- CONSTRUCTION OF SOHRIO IDA / 67940 Post Request for Bids Open - National Signed 2021-02-17 2021-02-19 2021-02-22 2021-02-26 2021-03-26 2021-03-25 2021-04-26 2021-04-30 2021-06-09 2021-06-10 Systems for Resilience Envelope 6 08 WAH DAM IN NAGARPARKAR. PK-SID-220131-CW-RFB / Improving Infrastructure and Single Stage - One 3,139,491.1 2022-06- CONSTRUCTION OF NAMARO IDA / 67940 Post Request for Bids Open - National Signed 2021-02-17 2021-02-19 2021-02-22 2021-02-26 2021-03-26 2021-03-25 2021-04-26 2021-04-28 2021-06-09 2021-06-10 Systems for Resilience Envelope 6 08 DAM IN NAGARPARKAR. PK-SID-220132-CW-RFB / Improving Infrastructure and Single Stage - One 3,246,751.3 2022-06- CONSTRUCTION OF VIAKASAR IDA / 67940 Post Request for Bids Open - National Signed 2021-02-17 2021-02-19 2021-02-22 2021-02-26 2021-03-26 2021-03-25 2021-04-26 2021-05-04 2021-06-09 2021-06-10 Systems for Resilience Envelope 1 08 DAM IN NAGARPARKAR. PK-SID-220136-CW-RFB / Improving Infrastructure and Single Stage - One 4,215,473.4 2022-06- CONSTRUCTION OF GORDHRO- IDA / 67940 Post Request for Bids Open - National Signed 2021-02-17 2021-02-19 2021-02-22 2021-02-26 2021-03-26 2021-03-25 2021-04-26 2021-05-17 2021-06-09 2021-07-05 Systems for Resilience Envelope 1 08 2 DAM IN NAGARPARKAR. PK-SID-220140-CW-RFB / Improving Infrastructure and Single Stage - One 2,405,858.3 2022-06- CONSTRUCTION OF SUDRAN IDA / 67940 Post Request for Bids Open - National Signed 2021-02-17 2021-02-19 2021-02-22 2021-02-26 2021-03-26 2021-03-25 2021-04-26 2021-06-14 2021-06-09 2021-08-05 Systems for Resilience Envelope 5 08 DAM IN NAGARPARKAR. PK-SID-220141-CW-RFB / CONSTRUCTION OF ADHIGAM- Improving Infrastructure and Single Stage - One 1,990,269.1 2022-06- IDA / 67940 Post Request for Bids Open - National Signed 2021-02-17 2021-02-19 2021-02-22 2021-02-26 2021-03-26 2021-03-25 2021-04-26 2021-08-02 2021-06-09 2021-09-15 SYED ALAM DAM IN Systems for Resilience Envelope 5 08 NAGARPARKAR. PK-SID-220143-CW-RFB / Improving Infrastructure and Single Stage - One 1,559,990.3 2022-06- CONSTRUCTION OF LAYARI-1 IDA / 67940 Post Request for Bids Open - National Signed 2021-02-17 2021-02-19 2021-02-22 2021-02-26 2021-03-26 2021-03-25 2021-04-26 2021-07-12 2021-06-09 2021-08-26 Systems for Resilience Envelope 8 08 DAM IN NAGARPARKAR. PK-SID-220144-CW-RFB / Improving Infrastructure and Single Stage - One 1,955,535.6 2022-06- CONSTRUCTION OF JHANJHOO IDA / 67940 Post Request for Bids Open - National Signed 2021-02-17 2021-02-19 2021-02-22 2021-02-26 2021-03-26 2021-03-25 2021-04-26 2021-05-18 2021-06-09 2021-06-29 Systems for Resilience Envelope 3 08 DAM IN NAGARPARKAR. PK-SID-220145-CW-RFB / Improving Infrastructure and Single Stage - One 2,135,050.9 2022-06- CONSTRUCTION OF PATHAR IDA / 67940 Post Request for Bids Open - National Signed 2021-02-17 2021-02-19 2021-02-22 2021-02-26 2021-03-26 2021-03-25 2021-04-26 2021-05-04 2021-06-09 2021-06-15 Systems for Resilience Envelope 7 08 DAM IN NAGARPARKAR. PK-SID-220147-CW-RFB / CONSTRUCTION OF TARGAAM Improving Infrastructure and Single Stage - One 1,983,545.0 2022-06- IDA / 67940 Post Request for Bids Open - National Signed 2021-02-17 2021-02-19 2021-02-22 2021-02-26 2021-03-26 2021-03-25 2021-04-26 2021-06-07 2021-06-09 2021-07-27 BUDHESAR DAM IN Systems for Resilience Envelope 3 08 NAGARPARKAR. Request for PK-SID-178000-CW-RFB / Bids - Small Construction of Sangchat Jo Improving Infrastructure and Single Stage - One 2022-09- IDA / 67940 Post Request for Bids Open - National Works SPD (1 0.00 Canceled 2021-05-31 2021-05-31 2021-07-01 2021-07-31 2021-09-11 Tarr Small/Recharge Dam in Systems for Resilience Envelope 10 envelope Lower Kohistan. process) PK-SID-177999-CW-RFB / Package No: 04 Lot No. 1 Construction of Request for Gurrand Small/ Recharge Dam Bids - Small Under Improving Infrastructure and Single Stage - One 2022-09- in Lower Kohistan. IDA / 67940 Post Request for Bids Open - National Works SPD (1 0.00 Implementat 2021-05-31 2021-05-31 2021-05-31 2021-05-31 2021-07-01 2021-07-07 2021-07-31 2021-09-11 Systems for Resilience Envelope 10 Lot No. 2 Construction of envelope ion Sangchat Jo Tarr Small/ process) Recharge Dam in Lower Kohistan. PK-SID-235601-CW-RFB / Package No: 01 Lot No. 1 Construction of Bandhaka Request for Dam in Central Kohistan. Bids - Small Improving Infrastructure and Single Stage - One 5,780,916.6 2022-09- IDA / 67940 Post Request for Bids Open - National Works SPD (1 Signed 2021-05-31 2021-05-31 2021-05-31 2021-05-31 2021-07-01 2021-07-07 2021-07-31 2021-07-23 2021-09-11 2021-09-30 Lot No. 2 Systems for Resilience Envelope 1 10 envelope Construction of Baaro Dam in process) Central Kohistan. Lot No. 3 Construction of Chakhri Dam in Central Kohistan. Request for PK-SID-235602-CW-RFB / Bids - Small Improving Infrastructure and Single Stage - One 2022-09- Construction of Baaro Dam in IDA / 67940 Post Request for Bids Open - National Works SPD (1 0.00 Canceled 2021-05-31 2021-05-31 2021-07-01 2021-07-31 2021-09-11 Systems for Resilience Envelope 10 Central Kohistan. envelope process) Request for PK-SID-235603-CW-RFB / Bids - Small Improving Infrastructure and Single Stage - One 2022-09- Construction of Chakhri Dam IDA / 67940 Post Request for Bids Open - National Works SPD (1 0.00 Canceled 2021-05-31 2021-05-31 2021-07-01 2021-07-31 2021-09-11 Systems for Resilience Envelope 10 in Central Kohistan. envelope process) PK-SID-235604-CW-RFB / Package No: 02 Request for Lot No .1 Construction of Bids - Small Under Improving Infrastructure and Single Stage - One 2022-09- Churlo Dam in Central IDA / 67940 Post Request for Bids Open - National Works SPD (1 0.00 Implementat 2021-05-31 2021-05-31 2021-05-31 2021-05-31 2021-07-01 2021-07-07 2021-07-31 2021-08-31 2021-09-11 Systems for Resilience Envelope 10 Kohistan. envelope ion Lot No. 2 Construction of process) Sunn-2 Dam in Central Kohistan. Request for PK-SID-235605-CW-RFB / Bids - Small Improving Infrastructure and Single Stage - One 2022-09- Construction of Sunn-2 Dam IDA / 67940 Post Request for Bids Open - National Works SPD (1 0.00 Canceled 2021-05-31 2021-05-31 2021-07-01 2021-07-31 2021-09-11 Systems for Resilience Envelope 10 in Central Kohistan. envelope process) Page 3 PK-SID-235606-CW-RFB / Package No: 03 Lot No. 1 Construction of Request for Gadap-2 Dam in Lower Bids - Small Under Kohistan. Improving Infrastructure and Single Stage - One 2022-09- IDA / 67940 Post Request for Bids Open - National Works SPD (1 0.00 Implementat 2021-05-31 2021-05-31 2021-05-31 2021-05-31 2021-07-01 2021-07-07 2021-07-31 2021-07-30 2021-09-11 Lot No. 2 Construction of Lat- Systems for Resilience Envelope 10 envelope ion 2 Dam in Lower Kohistan. process) Lot No. 3 Construction of Khuda Bux Dam in Lower Kohistan. Request for PK-SID-235609-CW-RFB / Bids - Small Improving Infrastructure and Single Stage - One 2022-09- Construction of Khuda Bux IDA / 67940 Post Request for Bids Open - National Works SPD (1 0.00 Canceled 2021-05-31 2021-05-31 2021-07-01 2021-07-31 2021-09-11 Systems for Resilience Envelope 10 Dam in Lower Kohistan. envelope process) Request for PK-SID-235611-CW-RFB / Bids - Small Improving Infrastructure and Single Stage - One 2022-09- Construction of Lat-2 Dam in IDA / 67940 Post Request for Bids Open - National Works SPD (1 0.00 Canceled 2021-05-31 2021-05-31 2021-07-01 2021-07-31 2021-09-11 Systems for Resilience Envelope 10 Lower Kohistan. envelope process) Request for PK-SID-235613-CW-RFB / Bids - Small Improving Infrastructure and Single Stage - One 2022-09- Construction of Jharando-2 IDA / 67940 Post Request for Bids Open - National Works SPD (1 0.00 Canceled 2021-05-31 2021-05-31 2021-07-01 2021-07-31 2021-09-11 Systems for Resilience Envelope 10 Dam in Lower Kohistan. envelope process) PK-SID-235618-CW-RFB / Package No: 06 Request for Lot No. 1 Construction of Bids - Small Gorban Bhutti Dam in Lower Improving Infrastructure and Single Stage - One 7,212,691.7 2022-09- IDA / 67940 Post Request for Bids Open - National Works SPD (1 Signed 2021-05-31 2021-05-31 2021-05-31 2021-05-31 2021-07-01 2021-07-07 2021-07-31 2021-08-23 2021-09-11 2021-10-05 Kohistan. Systems for Resilience Envelope 3 10 envelope Lot No. 2Construction of process) Dahri Sharif Dam in Lower Kohistan. Request for PK-SID-235624-CW-RFB / Bids - Small Improving Infrastructure and Single Stage - One 2022-09- Construction of Dahri Sharif IDA / 67940 Post Request for Bids Open - National Works SPD (1 0.00 Canceled 2021-05-31 2021-05-31 2021-07-01 2021-07-31 2021-09-11 Systems for Resilience Envelope 10 Dam in Lower Kohistan. envelope process) PK-SID-235630-CW-RFB / Package No: 05 Request for Lot No. 1 Construction of Bids - Small Jharando-1 Dam in Lower Improving Infrastructure and Single Stage - One 4,962,412.0 2022-09- IDA / 67940 Post Request for Bids Open - National Works SPD (1 Signed 2021-05-31 2021-05-31 2021-05-31 2021-05-31 2021-07-01 2021-07-07 2021-07-31 2021-08-06 2021-09-11 2021-09-03 Kohistan. Systems for Resilience Envelope 4 10 envelope Lot No. 2 Construction of process) Jharando-2 Dam in Lower Kohistan. Request for PK-SID-235632-CW-RFB / Bids - Small Improving Infrastructure and Single Stage - One 2,739,368.9 2022-09- Construction of Gaib Janan IDA / 67940 Post Request for Bids Open - National Works SPD (1 Signed 2021-05-31 2021-05-31 2021-05-31 2021-05-31 2021-07-01 2021-07-07 2021-07-31 2021-08-06 2021-09-11 2021-09-03 Systems for Resilience Envelope 5 10 Dam in Lower Kohistan. envelope process) Request for PK-SID-252668-CW-RFB / Bids - Small Under CONSTRUCTION OF NARANI Improving Infrastructure and Single Stage - One 2022-12- IDA / 67940 Post Request for Bids Open - National Works SPD (1 0.00 Implementat 2021-09-09 2021-09-09 2021-09-14 2021-09-10 2021-10-15 2021-10-12 2021-11-15 2021-12-27 DAM IN DISTRICT QAMBER Systems for Resilience Envelope 26 envelope ion SHAHDADKOT. process) Request for PK-SID-252670-CW-RFB / Bids - Small Under CONSTRUCTION OF BUZEH Improving Infrastructure and Single Stage - One 2022-12- IDA / 67940 Post Request for Bids Open - National Works SPD (1 0.00 Implementat 2021-09-09 2021-09-09 2021-09-14 2021-09-10 2021-10-15 2021-10-12 2021-11-15 2021-12-27 DAM IN DISTRICT QAMBER Systems for Resilience Envelope 26 envelope ion SHAHDADKOT. process) Request for PK-SID-252671-CW-RFB / Bids - Small Under CONSTRUCTION OF KHAR Improving Infrastructure and Single Stage - One 2022-12- IDA / 67940 Post Request for Bids Open - National Works SPD (1 0.00 Implementat 2021-09-09 2021-09-09 2021-09-14 2021-09-10 2021-10-15 2021-10-12 2021-11-15 2021-12-27 GANI DAM IN DISTRICT Systems for Resilience Envelope 26 envelope ion QAMBER SHAHDADKOT. process) Request for PK-SID-252673-CW-RFB / Bids - Small Under CONSTRUCTION OF TOOPI Improving Infrastructure and Single Stage - One 2022-12- IDA / 67940 Post Request for Bids Open - National Works SPD (1 0.00 Implementat 2021-09-09 2021-09-09 2021-09-14 2021-09-10 2021-10-15 2021-10-12 2021-11-15 2021-12-27 DAM IN DISTRICT QAMBER Systems for Resilience Envelope 26 envelope ion SHAHDADKOT. process) Request for PK-SID-252674-CW-RFB / Bids - Small Under CONSTRUCTION OF KHINJI Improving Infrastructure and Single Stage - One 2022-12- IDA / 67940 Post Request for Bids Open - National Works SPD (1 0.00 Implementat 2021-09-09 2021-09-09 2021-09-14 2021-09-10 2021-10-15 2021-10-12 2021-11-15 2021-12-27 DAM IN DISTRICT QAMBER Systems for Resilience Envelope 26 envelope ion SHAHDADKOT. process) Request for PK-SID-252677-CW-RFB / Bids - Small Under CONSTRUCTION OF TUNNI Improving Infrastructure and Single Stage - One 2022-12- IDA / 67940 Post Request for Bids Open - National Works SPD (1 0.00 Implementat 2021-09-09 2021-09-09 2021-09-14 2021-09-10 2021-10-15 2021-10-12 2021-11-15 2021-12-27 DAM IN DISTRICT QAMBER Systems for Resilience Envelope 26 envelope ion SHAHDADKOT. process) Request for PK-SID-252679-CW-RFB / Bids - Small Under CONSTRUCTION OF GAARELO Improving Infrastructure and Single Stage - One 2022-12- IDA / 67940 Post Request for Bids Open - National Works SPD (1 0.00 Implementat 2021-09-09 2021-09-09 2021-09-14 2021-09-10 2021-10-15 2021-10-12 2021-11-15 2021-12-27 DAM IN DISTRICT QAMBER Systems for Resilience Envelope 26 envelope ion SHAHDADKOT. process) Request for PK-SID-252681-CW-RFB / Bids - Small Under CONSTRUCTION OF Improving Infrastructure and Single Stage - One 2022-12- IDA / 67940 Post Request for Bids Open - National Works SPD (1 0.00 Implementat 2021-09-09 2021-09-09 2021-09-14 2021-09-10 2021-10-15 2021-10-12 2021-11-15 2021-12-27 KHURRAND DAM IN DISTRICT Systems for Resilience Envelope 26 envelope ion SHAHEED BENAZIRABAD. process) Request for PK-SID-252683-CW-RFB / Bids - Small Under CONSTRUCTION OF JAM Improving Infrastructure and Single Stage - One 2022-12- IDA / 67940 Post Request for Bids Open - National Works SPD (1 0.00 Implementat 2021-09-09 2021-09-09 2021-09-14 2021-09-10 2021-10-15 2021-10-12 2021-11-15 2021-12-27 DATAAR DAM IN DISTRICT Systems for Resilience Envelope 26 envelope ion SHAHEED BENAZIRABAD. process) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SID-2980-GO-RFQ / Improving Infrastructure and Request for Single Stage - One IDA / 58880 Prior Open - National 415,398.59 Completed 2016-11-12 2016-12-19 2017-01-07 2017-03-03 2017-07-06 2018-08-10 Vehciles Systems for Resilience Quotations Envelope PK-SID-2979-GO-RFQ / Improving Infrastructure and Request for Single Stage - One IDA / 58880 Post Open - National 47,647.27 Completed 2016-11-11 2017-01-06 2017-04-26 2017-07-05 2017-05-19 Office Furniture Systems for Resilience Quotations Envelope PK-SID-4707-GO-RFQ / Improving Infrastructure and Request for Single Stage - One IDA / 58880 Post Open - National 39,507.07 Completed 2016-12-24 2017-02-18 2017-04-26 2017-08-17 2017-05-19 Office Equipment Systems for Resilience Quotations Envelope Page 4 PK-SID-2978-GO-RFB / Improving Infrastructure and Request for Single Stage - One IDA / 58880 Post Open - National 0.00 Canceled 2016-11-11 2017-01-06 2017-07-05 Office Equipment Systems for Resilience Quotations Envelope PK-SID-15281-GO-RFQ / Improving Infrastructure and Request for Single Stage - One Purchase of Motorcycles upto IDA / 58880 Post Open - National 1,206.08 Completed 2017-05-19 2017-06-12 2017-05-31 2017-07-27 2017-10-16 Systems for Resilience Quotations Envelope 70cc PK-SID-15303-GO-RFQ / Improving Infrastructure and Request for Single Stage - One Purchasing of stabilizer of 11 IDA / 58880 Post Open - National 1,744.00 Completed 2017-05-19 2017-06-12 2017-09-06 2017-07-27 2017-09-13 Systems for Resilience Quotations Envelope Nos: for office use PK-SID-16582-GO-RFQ / Supply, Installation Testing Improving Infrastructure and Request for Single Stage - One IDA / 58880 Post Open - National 12,561.52 Completed 2017-06-02 2017-10-26 2017-06-26 2017-11-16 2017-08-10 2017-12-08 and Commissioning Diesel Systems for Resilience Quotations Envelope Generator 30 to 37 KVA. PK-SID-21212-GO-RFQ / Improving Infrastructure and Request for Single Stage - One IDA / 58880 Post Open - National 17,121.64 Completed 2017-07-20 2017-08-14 2017-10-17 2017-09-28 2017-12-15 Video Conference System Systems for Resilience Quotations Envelope PK-SID-27863-GO-RFQ / Work Station, Chairs, Fixtures and partitions in prayer area. 1. Work Stations 08 Nos. Improving Infrastructure and Request for Single Stage - One 2. Hydraulic Chairs IDA / 58880 Post Open - National 7,528.57 Completed 2017-09-08 2017-10-26 2017-10-12 2017-11-10 2017-12-11 2017-11-18 Systems for Resilience Quotations Envelope 08 Nos. 3. Aluminum Door with Glass 01 No. 4. Fixture/Partitions 01 No. PK-SID-92972-GO-RFQ / Improving Infrastructure and Request for Single Stage - One Procurement of 2Nos: IDA / 58880 Post Open - National 994.49 Signed 2019-01-04 2019-02-18 2019-01-14 2019-03-04 2019-04-14 Systems for Resilience Quotations Envelope Motorcycles for Office use. PK-SID-118848-GO-RFB / Improving Infrastructure and Single Stage - One Hydraulic Laboratory IDA / 58880 Post Request for Bids Open - National 629,524.99 Signed 2019-06-20 2019-06-01 2019-06-27 2019-07-08 2019-07-29 2019-08-09 2019-08-28 2019-09-19 2019-09-30 2019-10-23 2020-03-28 Systems for Resilience Envelope Equipment. PK-SID-171224-GO-RFQ / Procurement of Health Safety Improving Infrastructure and Request for Single Stage - One Products and Disinfectant for IDA / 58880 Post Open - National 6,718.81 Signed 2020-04-30 2020-05-01 2020-05-18 2020-05-11 2020-06-17 Systems for Resilience Quotations Envelope Project Management Team (PMT). PK-SID-189315-GO-RFQ / Improving Infrastructure and Request for Single Stage - One Procurement of I.T Equipment IDA / 58880 Post Open - National 9,058.76 Signed 2020-08-18 2020-08-31 2020-09-09 2020-10-20 2020-10-09 Systems for Resilience Quotations Envelope for office use. PK-SID-197646-GO-RFB / Procurement of Equipment for Improving Infrastructure and Single Stage - One River Morphology Study, Flood IDA / 58880 Post Request for Bids Open - National 748,297.37 Signed 2020-10-04 2020-11-12 2020-11-03 2020-11-13 2020-12-15 2020-12-17 2021-01-14 2021-02-04 2021-02-25 2021-03-17 2021-08-24 Systems for Resilience Envelope Hazard Mapping & Establishment of DSS in Sindh. PK-SID-229375-GO-RFQ / Improving Infrastructure and Request for Single Stage - One IDA / 58880 Post Open - National 283,488.74 Signed 2021-04-16 2021-04-20 2021-05-04 2021-05-06 2021-11-02 Procurement of Vehicles. Systems for Resilience Quotations Envelope NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SID-122451-NC-RFQ / Improving Infrastructure and Request for Single Stage - One IDA / 58880 Post Open - National 86,680.00 Signed 2019-07-12 2019-07-31 2019-08-02 2019-09-04 2020-01-29 Digitization of Data Systems for Resilience Quotations Envelope PK-SID-243394-NC-RFQ / Improving Infrastructure and Request for Single Stage - One Digitalization and IDA / 67940 Post Open - National 88,477.72 Signed 2021-07-14 2021-08-21 2021-08-12 2021-09-14 2022-02-08 Systems for Resilience Quotations Envelope Preservation of Record. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SID-2955-CS-QCBS / Procurement of Project Improving Infrastructure and Quality And Cost- IDA / 58880 Prior Open - International 4,303,336.77 Under Review 2016-11-03 2016-11-03 2016-11-03 2016-12-17 2017-01-04 2017-01-14 2017-02-13 2017-02-13 2017-03-13 2017-03-20 2017-04-28 2017-04-24 2017-05-18 2018-04-24 Implementation Support and Systems for Resilience Based Selection Supervision Consultant (PISSC) PK-SID-38659-CS-CQS / Consultant Organizational Capacity Improving Infrastructure and IDA / 58880 Post Qualification Open - National 244,301.97 Signed 2017-12-04 2017-12-15 2017-12-19 2017-12-18 2018-02-20 2018-02-20 2018-03-23 2018-03-22 2018-05-04 2018-04-16 2018-10-31 Assessment of Sindh Irrigation Systems for Resilience Selection Department. PK-SID-38661-CS-CQS / Consultant Improving Infrastructure and Third Party Monitoring and IDA / 58880 Post Qualification Open - National 348,297.30 Signed 2017-12-04 2017-12-15 2017-12-19 2017-12-18 2018-02-20 2018-02-20 2018-03-23 2018-03-19 2018-05-04 2018-04-13 2021-05-03 Systems for Resilience Validation. Selection PK-SID-56147-CS-QCBS / River Morphological Study, Flood Hazard Mapping and Improving Infrastructure and Quality And Cost- IDA / 58880 Prior Open - International 1,924,831.00 Signed 2018-03-30 2018-05-31 2018-04-06 2018-06-22 2018-06-04 2018-12-04 2018-07-04 2019-10-18 2018-08-03 2020-01-26 2018-08-24 2020-05-10 2018-09-21 2020-06-01 2020-03-14 Establishment of Decision Systems for Resilience Based Selection Support System for Sindh Province PK-SID-61859-CS-QCBS / Feasibility Study of 30 Nos: of Improving Infrastructure and Quality And Cost- IDA / 58880 Prior Open - International 1,019,910.33 Signed 2018-05-08 2018-07-30 2018-05-15 2018-08-10 2018-07-12 2019-04-03 2018-08-11 2019-05-20 2018-09-10 2020-03-12 2018-10-01 2020-04-24 2018-10-29 2020-07-07 2020-04-21 Small Dams in Water Scarce Systems for Resilience Based Selection Areas in Sindh Province. PK-SID-128479-CS-CQS / Consultant Improving Infrastructure and Hydro Metrological Hazard IDA / 58880 Post Qualification Open - National 465,544.39 Signed 2019-08-22 2019-08-23 2019-09-23 2019-08-29 2019-11-08 2019-10-24 2019-12-08 2019-11-18 2020-01-13 2019-11-25 2021-01-12 Systems for Resilience Assessment of Sindh Province. Selection Page 5 PK-SID-128488-CS-CQS / Consultant Performance Evaluation of Improving Infrastructure and IDA / 58880 Post Qualification Open - National 298,863.33 Signed 2019-08-22 2019-08-23 2019-09-23 2019-08-29 2019-11-08 2019-10-24 2019-12-13 2019-11-11 2020-01-20 2019-11-15 2020-07-18 Small Dams in the Sindh Systems for Resilience Selection Province. PK-SID-191831-CS-CQS / Consultant Improving Infrastructure and Risk profile for Sea Level Rise IDA / 58880 Post Qualification Open - National 291,948.18 Signed 2020-09-23 2020-11-03 2020-10-23 2020-11-05 2020-12-23 2021-03-18 2021-01-24 2021-04-26 2021-02-28 2021-05-20 2021-11-25 Systems for Resilience in Sindh Coastal Area. Selection PK-SID-191832-CS-CQS / Feasibility Study for Provision Consultant of Solar Pumps to Small Land Improving Infrastructure and IDA / 58880 Post Qualification Open - National 293,058.35 Signed 2020-09-23 2020-11-03 2020-10-23 2020-11-05 2020-12-23 2021-03-18 2021-01-22 2021-04-12 2021-02-26 2021-04-14 2021-11-23 Holder and Command Area Systems for Resilience Selection Development of Selected Area Sindh. PK-SID-197423-CS-QCBS / Project Implementation Consultant for Design Review Improving Infrastructure and Quality And Cost- IDA / 58880 Prior Open - International 2,808,665.40 Signed 2020-11-05 2020-12-03 2020-11-30 2020-12-07 2021-02-03 2021-02-21 2021-02-05 2021-02-22 2021-03-08 2021-06-08 2021-03-29 2021-06-24 2021-04-14 2021-07-23 2024-10-14 and Resident Supervision of Systems for Resilience Based Selection Construction of Small Dams in Sindh. PK-SID-247635-CS-QCBS / Feasibility Study of 50 Nos. Improving Infrastructure and Quality And Cost- Under Small Dams and Lining of 50 IDA / 67940 Prior Open - International 0.00 2021-08-12 2021-09-27 2021-09-02 2021-09-28 2021-09-15 2022-01-05 2021-10-17 2021-10-31 2021-11-17 2021-12-15 2023-06-12 Systems for Resilience Based Selection Implementation Nos. Ponds/Taraies in Sindh Province. PK-SID-256444-CS-CQS / Consultant Improving Infrastructure and Under Third Party Monitoring & IDA / 67940 Post Qualification Open - National 0.00 2021-10-05 2021-10-06 2021-10-25 2021-10-08 2021-12-24 2022-01-21 2022-02-25 2024-08-13 Systems for Resilience Implementation Validation (TPM&V). Selection PK-SID-257409-CS-QCBS / Preparation of an Inventory Indus Embankments and Breaching Sections, to Improving Infrastructure and Quality And Cost- Under IDA / 67940 Post Open - International 0.00 2021-10-08 2021-10-22 2021-10-29 2021-12-13 2021-11-11 2021-12-13 2021-12-27 2022-01-17 2022-02-14 2023-05-10 Document their Current Systems for Resilience Based Selection Implementation Conditions and for Informed Disaster Risk & Hazard Mapping. PK-SID-257424-CS-CQS / Consultant Improving Infrastructure and Under Capacity Development IDA / 67940 Post Qualification Open - National 0.00 2021-10-22 2021-11-02 2021-11-11 2022-01-12 2022-02-09 2022-03-16 2024-03-05 Systems for Resilience Implementation Program/ Trainings. Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual PK-SID-2970-CS-INDV / Improving Infrastructure and IDA / 58880 Prior Consultant Open 56,401.20 Completed 2016-11-07 2016-11-20 2016-12-27 2016-12-22 2017-01-17 2017-01-25 2017-02-21 2017-01-05 2017-08-20 2017-12-31 Finance Consultant Systems for Resilience Selection Individual PK-SID-2972-CS-INDV / M & Improving Infrastructure and IDA / 58880 Post Consultant Open 134,215.64 Signed 2016-11-07 2016-12-15 2016-12-27 2017-03-22 2017-01-17 2017-05-02 2017-02-21 2017-06-13 2017-08-20 E Consultant Systems for Resilience Selection Individual PK-SID-2973-CS-INDV / Improving Infrastructure and IDA / 58880 Post Consultant Open 117,688.81 Signed 2016-11-07 2016-12-29 2016-12-27 2017-07-03 2017-01-17 2017-07-03 2017-02-21 2017-08-07 2017-08-20 IT/GIS Consultant Systems for Resilience Selection Individual PK-SID-2975-CS-INDV / Improving Infrastructure and IDA / 58880 Post Consultant Open 117,711.82 Signed 2016-11-07 2017-12-15 2016-12-27 2018-02-09 2017-01-17 2018-02-09 2017-02-21 2018-02-08 2017-08-20 Quality Assurance Engineer Systems for Resilience Selection Individual PK-SID-2976-CS-INDV / Improving Infrastructure and IDA / 58880 Post Consultant Open 31,029.60 Terminated 2016-11-07 2016-12-29 2016-12-27 2017-06-23 2017-01-17 2017-06-23 2017-02-21 2017-07-03 2017-08-20 Environmental Consultant Systems for Resilience Selection Individual PK-SID-2981-CS-INDV / Improving Infrastructure and Under IDA / 58880 Post Consultant Open 167,946.39 2016-11-07 2016-12-29 2016-12-27 2017-05-29 2017-01-17 2017-05-30 2017-02-21 2017-07-07 2017-08-20 Social Safeguard Consulatnt Systems for Resilience Implementation Selection PK-SID-7391-CS-INDV / Individual Procurement & Contract Improving Infrastructure and IDA / 58880 Prior Consultant Open 184,464.42 Signed 2017-02-15 2017-02-16 2017-04-05 2017-02-28 2017-04-26 2017-04-03 2017-05-31 2017-04-03 2018-05-31 Consultant (Individual Systems for Resilience Selection Consultant) PK-SID-2971-CS-INDV / Individual Improving Infrastructure and Procurement & Contract IDA / 58880 Prior Consultant Open 0.00 Canceled 2016-11-07 2016-11-17 2016-12-27 2017-01-17 2017-02-21 2017-08-20 Systems for Resilience Consultant Selection PK-SID-27831-CS-INDV / Individual Hiring of Environment Improving Infrastructure and IDA / 58880 Post Consultant Open 150,855.62 Signed 2017-09-08 2017-09-15 2017-10-02 2017-10-27 2017-10-04 2017-10-27 2017-10-06 2017-11-06 2018-10-06 Consultant (Individual Systems for Resilience Selection Consultant) Individual PK-SID-47074-CS-INDV / Improving Infrastructure and IDA / 58880 Prior Consultant Open 201,650.47 Signed 2018-02-01 2018-02-01 2018-02-02 2018-02-01 2018-02-08 2018-02-01 2018-01-01 2018-02-01 Finance Consultant Systems for Resilience Selection Individual PK-SID-92998-CS-INDV / Improving Infrastructure and IDA / 58880 Post Consultant Open 69,170.72 Signed 2019-01-01 2019-02-06 2019-01-28 2019-04-11 2019-02-04 2019-04-23 2019-02-13 2019-04-29 2020-02-12 Fiduciary Monitoring Analyst Systems for Resilience Selection PK-SID-114445-CS-INDV / Individual The Hiring of Improving Infrastructure and IDA / 58880 Post Consultant Open 80,174.08 Signed 2019-05-10 2019-05-13 2019-07-01 2019-05-14 2019-07-22 2019-05-15 2019-08-26 2019-05-16 2020-08-24 Electro/Hydraulic Individual Systems for Resilience Selection Consultant. Page 6 PK-SID-121794-CS-INDV / The Hiring of Individual Consultant for carrying out Individual the Social & Environment Improving Infrastructure and IDA / 58880 Post Consultant Limited 6,403.07 Signed 2019-07-09 2019-07-09 2019-07-09 2019-07-10 2019-07-11 2019-07-10 2019-07-12 2019-08-08 2019-09-10 Impact Assessment of Systems for Resilience Selection Constructed Small Dams in Sindh Province Under Irrigation Department. PK-SID-207688-CS-INDV / Individual Improving Infrastructure and Under Social & Gender Specialist IDA / 58880 Post Consultant Limited 0.00 2020-12-04 2020-12-04 2020-12-19 2020-12-24 2020-12-30 2021-12-30 Systems for Resilience Implementation (Individual Consultant). Selection PK-SID-217159-CS-INDV / Individual Improving Infrastructure and Senior Water Management IDA / 58880 Post Consultant Limited 48,210.72 Signed 2021-02-02 2021-02-03 2021-02-16 2021-02-15 2021-02-19 2021-03-02 2021-02-25 2021-03-08 2022-02-25 Systems for Resilience Specialist. Selection Individual PK-SID-217218-CS-INDV / Improving Infrastructure and IDA / 58880 Post Consultant Limited 33,550.94 Signed 2021-02-02 2021-02-03 2021-02-16 2021-02-15 2021-02-19 2021-03-02 2021-02-25 2021-03-08 2022-02-25 Water Management Specialist. Systems for Resilience Selection PK-SID-263942-CS-CDS / Impact Assessment/ Improving Infrastructure and Under Performance Evaluation of 14 IDA / 67940 Post Direct Selection Direct 0.00 2021-11-18 2021-11-19 2021-11-28 2021-11-22 2022-01-17 2022-07-16 Systems for Resilience Implementation Small Dams in the Sindh Province. PK-SID-273736-CS-INDV / Individual Improving Infrastructure and Pending Structure Safety Engineer IDA / 67940 Post Consultant Open 0.00 2022-01-20 2022-03-09 2022-03-30 2022-05-04 2023-05-03 Systems for Resilience Implementation (Individual Consultant). Selection Page 7