PROCUREMENT PLAN (Textual Part) Project information: Sao Tome and Principe - WACA Resilience Investment Project - P162337 Project Implementation agency: Ministry of Public Works and Natural Resources, Directorate General of Environment Date of the Procurement Plan: July 2017 Period covered by this Procurement Plan: July 1st 2017 to June 30th, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Regulamento de Licitação e Contratações Publicas such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information.: Not Applicable PROCUREMENT Western Africa : Investments towards Resilient Management of GCLME PLAN General Information Country: Western Africa Bank’s Approval Date of the Original Procurement Plan: 2018-05-21 2022-01-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162337 GPN Date: 2017-12-29 Project Name: Investments towards Resilient Management of GCLME Loan / Credit No: IDA / V1250, IDA / 62150, IDA / 62120 W Executing Agency(ies): ACCA SENEGAL- Direction de l'Environnement WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 4.4.5 / Maintenance des Component 4: National Single Stage - One 2020-06- équipements et réfection du IDA / V1250 A posteriori Demande de prix Limited 35,735.98 Signé 2019-11-02 2019-11-18 2019-12-28 2019-12-17 Coordination Envelope 25 local du Projet 31308 / Sélection directe du Groupement GIE Eco garde Component 3: Strengthening Passation de pour le reboisement de dix 2020-10- IDA / V1250 National Physical and Social A posteriori marché de gré à Direct 44,174.14 Signé 2020-03-20 2020-04-22 2020-03-25 2020-04-29 2020-04-29 2020-07-20 (10) hectares de filaos dans le 26 Investments gré parc national de la Langue de Barbarie T_2021_32201 / Travaux de construction et d'équipement Component 3: Strengthening en kit solaire d'un atelier de Single Stage - One En cours 2021-11- IDA / 62150 National Physical and Social A posteriori Demande de prix Limited 0.00 2021-04-05 2021-04-29 2021-05-31 couture (lot1) et travaux de Envelope d'exécution 27 Investments construction d'un atelier de coiffure (lot 2) à Diougop T_2021_31309 / Travaux de reboisement de dix (10) ha de Component 3: Strengthening Passation de 2021-10- filao et huit (08) ha de IDA / 62150 National Physical and Social A posteriori marché de gré à Direct 29,533.46 Signé 2021-03-16 2021-03-16 2021-03-21 2021-03-21 2021-04-25 2021-04-09 22 mangrove au PNLB à Saint- Investments gré Louis T_2021_31310 / Travaux de Component 3: Strengthening Passation de 2021-10- reboisement de dix (10) ha de IDA / 62150 National Physical and Social A posteriori marché de gré à Direct 18,325.44 Signé 2021-03-16 2021-03-16 2021-03-21 2021-03-21 2021-04-25 2021-04-21 22 filoas à l'AMP de Saint-Louis Investments gré T_2021_31302 / Travaux de Component 3: Strengthening construction d'une unité de Single Stage - One 2021-11- IDA / 62150 National Physical and Social A posteriori Demande de prix Limited 60,337.70 Signé 2021-04-04 2021-03-22 2021-05-30 2021-04-29 valorisation durables des Envelope 26 Investments arches à Moumbaye (PNLB) F_2021_31302_8 / Travaux Component 3: Strengthening de construction d'un Poste de En cours 2022-04- IDA / 62150 National Physical and Social A posteriori Demande de prix 0.00 2021-08-23 2021-08-09 2021-10-18 Garde au niveau de l'AMP de d'exécution 16 Investments Saint-Louis GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 100 / Acquisition d'un logiciel comptable et mise en Component 4: National Single Stage - One IDA / V1250 A posteriori Demande de prix Limited 25,469.17 Signé 2018-04-17 2018-07-03 2018-06-12 2018-10-11 2018-12-09 place d'un système Coordination Envelope d'information 4.4.7 / Acquisition d'une Component 4: National Single Stage - One IDA / V1250 A posteriori Demande de prix Limited 2,764.60 Signé 2019-11-02 2021-02-27 2019-12-28 2021-06-14 2020-06-25 moto Coordination Envelope DC4-2018 / Acquisition de Component 4: National Single Stage - One IDA / V1250 A posteriori Demande de prix Limited 60,771.35 Signé 2018-04-24 2020-01-18 2018-06-19 2020-03-02 2018-12-16 véhicule Coordination Envelope 4.4.1 / Acquisition de Component 4: National Single Stage - One IDA / V1250 A posteriori Demande de prix Limited 25,804.96 Signé 2019-12-04 2019-11-27 2020-01-29 2019-12-19 2020-07-27 mobilier de bureau Coordination Envelope 4.4.8 / Acquisition de Component 4: National Single Stage - One IDA / V1250 A posteriori Demande de prix Limited 21,941.18 Signé 2019-12-04 2019-11-27 2020-01-29 2019-12-17 2020-07-27 matériel de bureau Coordination Envelope 4.4.2 / Acquisition de Component 4: National Single Stage - One IDA / V1250 A posteriori Demande de prix Limited 58,041.90 Signé 2019-11-02 2019-11-27 2019-12-28 2020-03-03 2020-06-25 matériel informatique Coordination Envelope 4.4.4 / Acquisition de fournitures de bureau, Component 4: National Single Stage - One IDA / V1250 A posteriori Demande de prix Limited 26,927.28 Signé 2019-11-02 2020-04-07 2019-12-28 2020-06-02 2020-06-25 consommables informatiques Coordination Envelope et produits d'entretien DC1-2018 / Acquisition de Component 2: Strengthening matériels et équipement Single Stage - One IDA / V1250 the Policy and Institutional A posteriori Demande de prix Limited 0.00 Annulé 2018-04-11 2018-06-06 2018-12-03 (matériel et mobilier de Envelope Framework bureau etc...) pour le SIG DC2-2018 / Achat de données de référence Component 2: Strengthening Single Stage - One (support cartographique, IDA / V1250 the Policy and Institutional A posteriori Demande de prix Limited 0.00 Annulé 2019-11-30 2020-01-25 2020-07-23 Envelope images satellite ....) avec Framework équipement et consommables. 420106 / Acquisition de Component 4: National Single Stage - One IDA / 62150 A posteriori Demande de prix Limited 108,438.77 Signé 2021-01-23 2021-01-20 2021-03-20 2021-03-04 2021-09-16 deux (02) véhicules Coordination Envelope 32201 / Acquisition de denrées alimentaires (Lot 1) Component 3: Strengthening Single Stage - One et de produits divers (Lot 2) IDA / 62150 National Physical and Social A posteriori Demande de prix Limited 19,974.46 Signé 2021-02-13 2021-03-11 2021-04-10 2021-04-02 2021-10-07 Envelope pour la Centrale d'achat de Investments Diougop Page 1 N° F_31302_2021 / Component 3: Strengthening Acquisition de drones suivie Single Stage - One IDA / 62150 National Physical and Social A posteriori Demande de prix Limited 12,972.75 Signé 2021-04-13 2021-03-31 2021-06-08 2021-04-26 2021-12-05 d'une formation sur Envelope Investments l’utilisation du matériel N° F_42104_2021 / Acquisition de fournitures de Component 4: National Single Stage - One bureau (lot1), consommables IDA / 62150 A posteriori Demande de prix Limited 25,388.44 Signé 2021-04-11 2021-03-29 2021-06-06 2021-04-28 2021-12-03 Coordination Envelope informatiques (lot 2) et produits d’entretien (lot 3) F_32102_2021 / Acquisition de fournitures de bureau (lot1), mobilier de bureau (lot Component 3: Strengthening 2), matériel de bureau (lot 3), Single Stage - One En attente IDA / 62150 National Physical and Social A posteriori Demande de prix Limited 0.00 2021-04-10 2021-06-05 2021-12-02 et matériel informatique (lot Envelope d'exécution Investments 4), pour l’appui institutionnel des commissions de gestion des plaintes et des DREEC F_43102_21 / Acquisition et Component 4: National Single Stage - One installation de bornes tactiles IDA / 62150 A posteriori Demande de prix Limited 1,733.32 Signé 2021-07-12 2021-09-03 2021-09-06 2021-10-27 2022-03-05 Coordination Envelope au profit du Projet WACA 42104 / Acquisition de fournitures de bureau, de Component 4: National Single Stage - One En attente consommables informatiques IDA / 62150 A posteriori Demande de prix Limited 0.00 2022-03-02 2022-04-27 2022-10-24 Coordination Envelope d'exécution et de produits d'entretiens pour le projet WACA 31103/F3-2022 / Acquisition Component 3: Strengthening de drones et GPS au profit de Single Stage - One En attente IDA / 62150 National Physical and Social A posteriori Demande de prix Limited 0.00 2022-03-27 2022-05-22 2022-11-18 l'UGP WACA, pour la Envelope d'exécution Investments surveillance 31302/F1-2022 / Acquisition Component 3: Strengthening et Dotation d'une embarcation En attente IDA / 62150 National Physical and Social A posteriori Demande de prix 0.00 2022-04-10 2022-06-05 2022-12-02 motorisée à l'AMP-SL pour les d'exécution Investments balades écotouristiques 31302/F2-2022 / Acquisition Component 3: Strengthening de deux (02) quads et d'un Single Stage - One En attente IDA / 62150 National Physical and Social A posteriori Demande de prix Limited 0.00 2022-04-10 2022-06-05 2022-12-02 (01) tricycle au profit de l'AMP Envelope d'exécution Investments et du PNLB 31302/F4-2022 / Acquisition d'équipements les postes de Component 3: Strengthening Single Stage - One En attente garde de l'AMP et du PNLB IDA / 62150 National Physical and Social A posteriori Demande de prix Limited 0.00 2022-04-10 2022-06-05 2022-12-02 Envelope d'exécution (réserve d'eau, équipements Investments solaire, etc.) 32101/F1-2021 / Acquisition et dotation en équipements Component 3: Strengthening Single Stage - One En attente d'aménagement et d'entretien IDA / 62150 National Physical and Social A posteriori Demande de prix Limited 0.00 2022-03-23 2022-05-18 2022-11-14 Envelope d'exécution de la plage de Pilote Bar Investments (Gandiol) NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual S_2021_42105 / Maintenance Component 4: National Single Stage - One des équipements du Projet IDA / 62150 A posteriori Demande de prix Limited 0.00 Annulé 2021-03-29 2021-05-24 2021-11-20 Coordination Envelope WACA CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CF7-2018 / Sélection d'un cabinet d'étude pour Sélection fondée l'élaboration des TDRs Component 3: Strengthening sur les d'études techniques et IDA / V1250 National Physical and Social A posteriori Open - National 48,356.12 Signé 2018-04-10 2018-05-16 2018-05-01 2018-06-14 2018-10-09 2018-07-14 2019-01-04 2018-08-18 2019-02-12 2019-02-14 qualifications des l'assistance au recrutement Investments consultants des Cabinets devant réaliser ces études. CF5-2018 / Sélection d'un cabinet pour l'élaboration des Component 3: Strengthening Sélection fondée études de faisabilités et du IDA / V1250 National Physical and Social A priori sur la qualité et le Open - International 0.00 Annulé 2019-11-29 2019-12-20 2020-02-02 2020-03-01 2020-03-31 2020-05-05 2020-06-09 2021-06-09 plan d'adaptation des îles de Investments coût l'estuaire du Fleuve Casamance CF8-2018 / Sélection d'un Component 2: Strengthening Sélection fondée cabinet pour l'élaboration du IDA / V1250 the Policy and Institutional A posteriori sur la qualité et le Open - International 0.00 Annulé 2019-11-20 2020-03-30 2019-12-11 2020-03-30 2020-01-24 2020-02-21 2020-03-22 2020-04-26 2020-05-31 2021-05-31 Plan national GIZC et du Plan Framework coût local de Ziguinchor 2.2.2 / Sélection d'un cabinet Sélection fondée chargé de l'étude de faisabilité Component 2: Strengthening sur les et design de l'Organe National IDA / V1250 the Policy and Institutional A posteriori Limited 0.00 Annulé 2019-10-31 2019-11-14 2019-12-14 2020-01-18 2020-07-16 qualifications des de Gestion Intégré du Littoral Framework consultants (ONGIL) Sélection fondée 31102 / Sélection d'un Component 3: Strengthening sur les cabinet pour l'EIES et PAR IDA / V1250 National Physical and Social A posteriori Open - National 0.00 Annulé 2020-04-22 2020-07-03 2020-05-13 2020-06-26 2020-07-26 2020-08-30 2021-02-26 qualifications des pour Gorée et Corniches Investments consultants Page 2 3111 / Sélection d'un Cabinet pour les études techniques (APS, APD, DAO) et l’élaboration des Termes de Component 3: Strengthening Sélection fondée Référence pour le contrôle des IDA / V1250 National Physical and Social A posteriori sur la qualité et le Open - International 687,372.85 Signé 2019-12-18 2019-12-18 2020-01-08 2020-02-21 2020-05-06 2020-03-20 2020-06-25 2020-04-19 2020-08-13 2020-05-24 2020-09-17 2020-06-28 2020-11-17 2021-06-28 travaux des corniches Est et Investments coût Ouest de Dakar et l’île de Gorée et élaboration des tdrs pour le contrôle des travaux 221011 / Sélection d'un Component 2: Strengthening Sélection fondée Cabinet pour SNGIZC,PNGIZC IDA / V1250 the Policy and Institutional A posteriori sur la qualité et le Open - International 459,445.87 Signé 2020-03-23 2020-03-23 2020-04-13 2020-05-27 2020-07-02 2020-06-24 2020-08-18 2020-07-24 2020-08-27 2020-08-28 2020-10-28 2020-10-02 2020-12-09 2021-10-02 et ONGIL Framework coût 22101 / Sélection Firme : (i) l’actualisation de la SNGIZC, (ii) l’élaboration du PNGIZC, (iii) la déclinaison du PNGIZC Component 2: Strengthening Sélection fondée dans les documents de IDA / V1250 the Policy and Institutional A posteriori sur la qualité et le Open - International 0.00 Annulé 2020-04-10 2020-03-23 2020-05-01 2020-04-09 2020-06-14 2020-06-30 2020-07-12 2020-08-18 2020-08-11 2020-08-27 2020-09-15 2020-10-20 2021-10-20 planification et Framework coût d’aménagement du territoire,locaux (iv) l’étude de faisabilité de l’Organe National de Gestion Intégré 3.1.1 / Sélection d'un Cabinet pour les études techniques (APS, APD, DAO) et Component 3: Strengthening Sélection fondée l’élaboration des Termes de IDA / V1250 National Physical and Social A posteriori sur la qualité et le Open - International 0.00 Annulé 2020-01-07 2019-12-18 2020-01-28 2020-01-08 2020-03-12 2020-05-14 2020-04-09 2020-06-25 2020-05-09 2020-08-13 2020-06-13 2020-07-18 2021-07-18 Référence pour le contrôle des Investments coût travaux des corniches Est et Ouest de Dakar et l’île de Gorée Sélection fondée 461075 / Assurances Component 4: National sur les En cours IDA / 62150 A posteriori Limited 0.00 2020-12-31 2021-01-20 2021-01-14 2021-02-13 2021-03-20 2021-09-16 maladie Coordination qualifications des d'exécution consultants 31104 / Sélection d’un Consultant//Cabinet pour la Sélection fondée Component 3: Strengthening réalisation de l’étude d’impact sur les IDA / 62150 National Physical and Social A posteriori Open - National 95,204.83 Signé 2020-06-30 2020-07-13 2020-07-21 2020-09-03 2020-09-01 2020-10-03 2021-01-04 2020-11-07 2021-01-04 2021-05-06 environnemental et social des qualifications des Investments travaux de protection au consultants niveau de l’ile de Gorée 311103 / Sélection d’un Consultant/Cabinet pour la Sélection fondée réalisation de l’étude d’impact Component 3: Strengthening sur les environnemental et social des IDA / 62150 National Physical and Social A posteriori Open - National 131,720.47 Signé 2020-06-30 2020-07-03 2020-07-21 2020-09-03 2020-09-01 2020-10-03 2021-01-04 2020-11-07 2021-01-04 2021-05-06 qualifications des travaux de stabilisation des Investments consultants corniches Est et Ouest de Dakar 313026 / SELECTION D’UN CONSULTANT POUR LA FORMATION ET L’ENCADREMENT DES Sélection fondée Component 3: Strengthening MARAICHERS DE L’AIRE sur les IDA / 62150 National Physical and Social A posteriori Limited 2,688.98 Signé 2020-09-21 2020-08-28 2020-10-05 2020-09-01 2020-11-04 2021-01-25 2020-12-09 2021-01-25 2021-06-07 MARINE PROTEGEE qualifications des Investments COMMUNAUTAIRE DE SAINT- consultants LOUIS SUR LES TECHNIQUES DE MARAICHAGE AGROECOLOGIQUE 3.1.4.1 / Sélection d'un cabinet pour la réalisation de Component 3: Strengthening Sélection fondée l'étude de faisabilité pour IDA / V1250 National Physical and Social A posteriori sur la qualité et le Open - National 0.00 Annulé 2019-11-29 2019-12-20 2020-02-02 2020-03-01 2020-03-31 2020-05-05 2020-06-09 2021-06-09 l'investissement pour la petite Investments coût côte et la grande côte 31501 / Sélection d'un consultant en charge de la Sélection fondée réalisation des études Component 3: Strengthening sur les En cours techniques APS, APD, DAO et IDA / 62150 National Physical and Social A posteriori Open - National 0.00 2021-11-30 2021-12-16 2021-12-21 2022-02-03 2022-03-05 2022-04-09 2022-10-06 qualifications des d'exécution le contrôle des travaux de Investments consultants protection côtière du littoral de Mbao. 31107 / Sélection d'une entreprise Chargé du contrôle Component 3: Strengthening Sélection fondée En attente des travaux de stabilisation IDA / 62150 National Physical and Social A posteriori sur la qualité et le Open - International 0.00 2022-02-01 2022-02-22 2022-04-07 2022-05-05 2022-06-04 2022-07-09 2022-08-13 2023-08-13 d'exécution des Corniches Est et Ouest de Investments coût Dakar 21302 / Sélection d'un Sélection fondée Cabinet pour la mise en Component 2: Strengthening sur les En attente œuvre du plan de IDA / 62150 the Policy and Institutional A posteriori Open - National 0.00 2022-03-15 2022-04-05 2022-05-19 2022-06-18 2022-07-23 2023-01-19 qualifications des d'exécution renforcement des capacités Framework consultants (Comité de pilotage, comité technique, UGP...) 22101-2022 / Sélection d'un Sélection fondée Cabinet pour élaborer Component 2: Strengthening sur les En attente l'Evaluation Environnementale, IDA / 62150 the Policy and Institutional A posteriori Open - National 0.00 2022-03-01 2022-03-22 2022-05-05 2022-06-04 2022-07-09 2023-01-05 qualifications des d'exécution Sociale Stratégique de la Framework consultants SNGIZC 31103/C1-2022 / Sélection d'un Cabinet pour la formation des acteurs Sélection fondée impliqués dans le CT de suivi: Component 3: Strengthening sur les En attente i)suivi biologique, (ii) IDA / 62150 National Physical and Social A posteriori Open - National 0.00 2022-02-13 2022-03-06 2022-04-19 2022-05-19 2022-06-23 2022-12-20 qualifications des d'exécution techniques de détection et Investments consultants d'utilisation des capteurs, ii) plongée sous-marine et iii) instruments de sauvegardes E& S de la Banque mondiale 32201/C1-2022 / Sélection Sélection fondée d'un Cabinet pour la Component 3: Strengthening sur les En attente réalisation des études de IDA / 62150 National Physical and Social A posteriori Open - National 0.00 2022-08-22 2022-09-12 2022-10-26 2022-11-25 2022-12-30 2023-06-28 qualifications des d'exécution faisabilité technique des sous- Investments consultants projets socio-économiques 31107/C1 / Sélection d'un Component 3: Strengthening Sélection fondée Cabinet chargé du contrôle En attente IDA / 62150 National Physical and Social A posteriori sur la qualité et le Open - International 0.00 2022-02-01 2022-02-22 2022-04-07 2022-05-05 2022-06-04 2022-07-09 2022-08-13 2023-08-13 des travaux de protection de d'exécution Investments coût l'île de Gorée Page 3 CI-32102-22 / Sélection d'un cabinet pour la conception et Sélection fondée Component 3: Strengthening la production des supports de sur les En attente IDA / 62150 National Physical and Social A posteriori Open - National 0.00 2022-01-25 2022-02-15 2022-03-31 2022-04-30 2022-06-04 2022-12-01 communication sur le qualifications des d'exécution Investments mécanisme de gestion des consultants plaintes 31502/C-2022 / Sélection d'un cabinet chargé de la Sélection fondée Component 3: Strengthening réalisation des études sur les En attente IDA / 62150 National Physical and Social A posteriori Limited 0.00 2022-03-15 2022-03-29 2022-04-28 2022-06-02 2022-11-29 d'impact environnementales qualifications des d'exécution Investments et sociale (EIES) pour la consultants protection du littoral de MBAO INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI1-2017 / PSélection d'un(e) Consultant(e) individuel(le) pour élaborer un Cadres De Gestion Environnementale et Sociale (CGES) sur la zone Component 4: National IDA / V1250 A posteriori Individuel Limited 50,075.58 Signé 2017-09-04 2017-06-12 2017-09-09 2017-06-23 2017-09-30 2017-07-10 2017-11-04 2017-07-10 2018-05-03 côtière et une étude d'impact Coordination environnementale et sociale (EIES) sur la repress and replication of the textbooks for schools CI2-2018 / Recrutement d'un(e) Consultant(e) Component 4: National individuel(le) pour élaborer un IDA / V1250 A posteriori Individuel Limited 30,045.35 Signé 2017-10-05 2017-07-04 2017-10-10 2017-07-03 2017-10-31 2017-07-10 2017-12-05 2018-02-20 2018-06-03 Coordination Cadre de Politique de Réinstallation (CPR) CI4-2017 / Sélection d'un consultant individuel Component 4: National IDA / V1250 A posteriori Individuel Limited 64,711.65 Signé 2017-11-17 2017-09-05 2017-11-22 2017-07-04 2017-12-13 2017-12-06 2018-01-17 2017-12-06 2018-07-16 spécialiste en passation de Coordination marchés (au temps passé) CI3-2018 / Sélection d'un consultant pour l'élaboration du manuel d'exécution du Component 4: National IDA / V1250 A posteriori Individuel Limited 19,553.16 Signé 2017-12-06 2017-12-28 2017-12-11 2017-12-23 2018-01-01 2018-01-22 2018-02-05 2018-01-22 2018-08-04 projet et du manuel de Coordination procédures financières et administratives CI14-2018 / Sélection d'un Consultant Individuel pour le Diagnostic Institutionnel, technique et organisationnel Component 4: National IDA / V1250 A posteriori Individuel Limited 17,832.00 Signé 2018-05-15 2019-02-22 2018-05-20 2019-03-14 2018-06-10 2019-03-15 2018-07-15 2019-05-06 2019-01-11 de l'Inspection du Ministère Coordination de l'Environnement et du Développement Durable (MEED) CI13-2018 / Sélection d'un Component 3: Strengthening Consultant Individuel pour IDA / V1250 National Physical and Social A posteriori Individuel Limited 14,567.44 Signé 2018-05-08 2018-02-05 2018-05-13 2018-06-13 2018-06-03 2018-06-21 2018-07-08 2018-06-21 2019-01-04 l'Elaboration d'un Manuel de Investments Suivi-Evaluation 3141 / Etude de faisabilité pour une solution Component 3: Strengthening Sélection de d'adaptation aux Direct - IDA / V1250 National Physical and Social A posteriori consultants par 0.00 Annulé 2019-05-23 2018-10-31 2019-05-30 2019-06-14 2019-07-14 changements climatiques en International Investments entente directe zone côtière pour la grande Côte et la petite Côte 4.1.4 / Sélection d'un Component 2: Strengthening consultant individuel en suivi- IDA / V1250 the Policy and Institutional A posteriori Individuel Limited 37,840.94 Signé 2019-07-18 2019-11-29 2019-07-23 2020-07-27 2019-08-13 2020-01-02 2019-09-17 2020-01-02 2020-03-15 évaluation Framework 2.1.3 / Élaboration du plan Component 2: Strengthening de renforcement des IDA / V1250 the Policy and Institutional A posteriori Individuel Limited 0.00 Annulé 2019-10-21 2019-10-26 2019-11-16 2019-12-21 2020-06-18 capacités Framework 4.1.8 / Sélection d'un Component 4: National consultant individuel en Génie IDA / V1250 A posteriori Individuel Limited 47,177.28 Signé 2020-01-31 2020-05-13 2020-02-05 2020-05-19 2020-02-26 2020-06-23 2020-04-01 2020-06-26 2020-09-28 Coordination Civil 41110 / Sélection d'un Component 4: National Consultant Individuel en IDA / V1250 A posteriori Individuel Direct 32,129.10 Signé 2020-01-07 2017-07-04 2020-01-17 2020-01-02 2020-02-07 2020-01-02 2020-03-13 2020-01-02 2020-09-09 Coordination Passation des Marchés 31303 / Sélection d'un Consultant Individuel en vue Component 3: Strengthening de l'évaluation IDA / V1250 National Physical and Social A posteriori Individuel Limited 14,279.60 Signé 2020-04-15 2020-07-20 2020-04-20 2020-07-30 2020-05-11 2020-08-17 2020-06-15 2020-08-19 2020-12-12 environnementale pour la Investments relance de l'écotourisme 21501 / Sélection d'un Consultant Individuel pour la Component 2: Strengthening revue du cadre réglementaire IDA / V1250 the Policy and Institutional A posteriori Individuel Limited 35,342.01 Signé 2020-05-06 2020-12-07 2020-05-11 2020-07-23 2020-06-01 2020-09-02 2020-07-06 2020-09-07 2021-01-02 relativement aux protocoles Framework additionnels de la Convention d'Abidjan 41509 / Sélection directe pour l’acquisition d'un logiciel Sélection de Component 4: National de programmation et de suivi- IDA / V1250 A posteriori consultants par Direct 9,562.33 Signé 2020-04-21 2020-02-10 2020-05-01 2020-04-03 2020-07-05 2020-06-08 2021-01-01 Coordination évaluation Multi-Projet « entente directe Ruche » 2.1.5 / Sélection d'un Consultant chargé de l'établissement des critères de Component 2: Strengthening sélection et d'attribution des IDA / V1250 the Policy and Institutional A posteriori Individuel Limited 0.00 Annulé 2019-09-18 2019-09-23 2019-10-14 2019-11-18 2020-05-16 bourses du master GAED pour Framework la gestion des risques liés aux activités pétrolières et gazières Page 4 4.1.15 / Sélection d'un consultant individuel expert Component 4: National social junior en charge du IDA / V1250 A posteriori Individuel Limited 0.00 Annulé 2019-10-10 2020-04-09 2019-10-15 2019-11-05 2019-12-10 2020-06-07 Coordination mécanisme de gestion des plaintes CF2-2018 / Sélection d'un observatoire de référence Component 2: Strengthening Sélection de pour l'accompagnement et la IDA / V1250 the Policy and Institutional A posteriori consultants par Direct 0.00 Annulé 2019-11-27 2020-02-11 2019-12-07 2020-02-10 2020-08-08 mise en place de Framework entente directe l'observatoire national du littoral 41107 / Sélection d'un Consultant Individuel Component 4: National IDA / V1250 A posteriori Individuel Limited 0.00 Annulé 2020-05-04 2020-05-09 2020-05-30 2020-07-04 2020-12-31 spécialiste en gestion Coordination pétrolière et gazière offshore 4.1.9 / Sélection d'un Component 4: National consultant individuel en IDA / V1250 A posteriori Individuel Limited 0.00 Annulé 2019-11-04 2019-11-09 2019-11-30 2020-01-04 2020-07-02 Coordination Développement Institutionnel 41109 / Sélection d'un Consultant Individuel Component 4: National IDA / V1250 A posteriori Individuel Limited 0.00 Annulé 2020-05-18 2020-05-23 2020-06-13 2020-07-18 2021-01-14 spécialiste en développement Coordination institutionnel 31402 / Sélection d'un Consultant Individuel pour Component 3: Strengthening l'élaboration d'un document IDA / V1250 National Physical and Social A posteriori Individuel Limited 0.00 Annulé 2020-05-06 2020-05-11 2020-06-01 2020-07-06 2021-01-02 de projet relatif à la Investments réparation aux investissements additionnel 4110 / Sélection d'un Sélection de Component 4: National consultant individuel en IDA / 62150 A posteriori consultants par Direct 32,672.34 Signé 2021-01-18 2020-12-22 2021-01-28 2020-12-28 2021-04-03 2021-01-04 2021-09-30 Coordination passation des marchés entente directe 313025 / SELECTION D’UN CONSULTANT POUR LA FORMATION DES FEMMES DU PNLB SUR LES TECHNIQUES AMELIOREES DE Component 3: Strengthening TRANSFORMATION DES IDA / 62150 National Physical and Social A posteriori Individuel Limited 2,708.64 Signé 2021-01-19 2021-02-04 2021-01-24 2021-03-03 2021-02-14 2021-06-21 2021-03-21 2021-06-21 2021-09-17 PRODUITS HALIEUTIQUES ET Investments L’APPUI A LA MAITRISE D’ŒUVRE DU PROJET DE VALORISATION DES ARCHES DU VILLAGE DE MOUBAYE CI_2021_32102 / Sélection d'un consultant individuel chargé de l'élaboration d'une Component 3: Strengthening étude sur la situation de IDA / 62150 National Physical and Social A posteriori Individuel Limited 14,341.20 Signé 2021-03-19 2021-04-01 2021-03-24 2021-06-15 2021-04-14 2021-07-15 2021-05-19 2021-07-14 2021-11-15 référence genre dans les Investments zones d'intervention du Projet WACA SD_42109_2021 / Sélection de Acquisition et installation d'un Component 4: National IDA / 62150 A posteriori consultants par Direct 5,371.74 Signé 2021-04-05 2021-04-15 2021-04-15 2021-05-17 2021-06-19 2021-05-20 2021-12-16 Logiciel TOMPRO/Etats Coordination entente directe Financiers SD-32103-1 / Sélection directe avec la RTS2, pour la Component 3: Strengthening Sélection de En cours visibilité et la vulgarisation IDA / 62150 National Physical and Social A posteriori consultants par Direct 0.00 2021-05-24 2021-06-30 2021-06-03 2021-08-07 2022-02-03 d'exécution des activités du du Projet Investments entente directe WACA SD-32103-2 / Sélection directe avec Le groupe Futurs Component 3: Strengthening Sélection de En cours Médias pour la visibilité et la IDA / 62150 National Physical and Social A posteriori consultants par Direct 0.00 2021-05-24 2021-06-30 2021-06-03 2021-08-07 2022-02-03 d'exécution vulgarisation des activités du Investments entente directe Projet WACA SD-32103-3 / Sélection directe avec la Radio SUD FM Component 3: Strengthening Sélection de En cours pour la visibilité et la IDA / 62150 National Physical and Social A posteriori consultants par Direct 0.00 2021-05-24 2021-06-30 2021-06-03 2021-08-07 2022-02-03 d'exécution vulgarisation des activités du Investments entente directe Projet WACA SD-32103-4 / Sélection Component 3: Strengthening Sélection de directe avec l'Union des En cours IDA / 62150 National Physical and Social A posteriori consultants par Direct 0.00 2021-05-24 2021-06-30 2021-06-03 2021-08-07 2022-02-03 Radios Associatives et d'exécution Investments entente directe Communautaires (URAC) SD-32103-5 / Sélection directe avec la voix du Littoral Component 3: Strengthening Sélection de En cours pour la visibilité et la IDA / 62120 National Physical and Social A posteriori consultants par Direct 0.00 2021-05-24 2021-06-30 2021-06-03 2021-08-07 2022-02-03 d'exécution vulgarisation des activités du Investments entente directe Projet WACA SD-32103-6 / Sélection Component 3: Strengthening Sélection de En cours Directe avec Le site en ligne IDA / 62150 National Physical and Social A posteriori consultants par Direct 0.00 2021-05-24 2021-06-30 2021-06-03 2021-08-07 2022-02-03 d'exécution Dakar actu Investments entente directe SD-32103-7 / Sélection directe avec le Groupe Component 3: Strengthening Sélection de En cours Walfadjri pour la visibilité et la IDA / 62150 National Physical and Social A posteriori consultants par Direct 0.00 2021-05-24 2021-06-30 2021-06-03 2021-08-07 2022-02-03 d'exécution vulgarisation des activités du Investments entente directe Projet WACA CI_2021_45106 / Sélection d'un consultant individuel Component 4: National IDA / 62150 A posteriori Individuel Limited 63,070.70 Signé 2021-06-03 2021-06-04 2021-06-08 2021-06-23 2021-06-29 2021-07-15 2021-08-03 2021-07-15 2022-01-30 pour la revue à mi-parcours Coordination du Projet WACA SD_2021_4117 / Sélection Directe d'un Cabinet chargé Sélection de Component 4: National du recrutement d'un IDA / 62150 A posteriori consultants par Direct 0.00 Annulé 2021-06-09 2021-06-07 2021-06-19 2021-06-15 2021-08-23 2022-02-19 Coordination comptable pour le Projet entente directe WACA Page 5 CI_43102_21 / Sélection d'un Consultant Individuel pour la Component 4: National En cours conception et la mise en IDA / 62150 A posteriori Individuel Limited 0.00 2021-07-07 2001-10-31 2021-07-12 2021-08-02 2021-09-06 2022-03-05 Coordination d'exécution œuvre de la communication digitale SD-41101-2021 / Sélection Sélection de directe d'un cabinet chargé du Component 4: National En attente IDA / 62150 A posteriori consultants par Direct 0.00 2021-12-30 2022-01-09 2022-03-15 2022-09-11 recrutement de quatre experts Coordination d'exécution entente directe de l'UGP du Projet WACA 32102/CI1-2022 / Sélection Component 3: Strengthening d'un consultant individuel En attente IDA / 62150 National Physical and Social A posteriori Individuel Limited 0.00 2022-08-05 2022-08-10 2022-08-31 2022-10-05 2023-04-03 pour la formation des acteurs d'exécution Investments du MGP sur les VBG/HS/EAS CI-32102-21 / Sélection d'un consultant individuel pour la conception et la production Component 3: Strengthening des supports de IDA / 62150 National Physical and Social A posteriori Individuel Limited 0.00 Annulé 2021-05-24 2021-10-31 2021-05-29 2021-06-19 2021-07-24 2022-01-20 communication sur le Investments mécanisme de gestion des plaintes Page 6