Third Village Investment Project (P146970) PROCUREMENT Kyrgyz Republic : Third Village Investment Project PLAN General Information Country: Kyrgyz Republic Bank’s Approval Date of the Original Procurement Plan: 2019-12-17 2022-02-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P146970 GPN Date: Project Name: Third Village Investment Project Loan / Credit No: IDA / 56010, IDA / D0410 Community Development and Investment Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IDA-VIP3-HO-CW-16-05 / Construction of a Capacity Building of Local Single Stage - One kindergarten for 100 places in IDA / 56010 Self-Governments and Prior Request for Bids Open - National 0.00 347,529.04 Signed 2016-10-03 2016-09-30 2016-10-19 2016-10-19 Envelope Tosor v., Tamga AO, Jeti- Communities Oguz Raion, Issyk-Kul Region IDA-VIP3-HO-CW-NCB-20-1 / Construction of an additional building for Single Stage - One 2021-01- IDA / D0410 Village Investments Post Request for Bids Open - National 152,173.91 132,012.63 Signed 2020-03-25 2020-04-17 2020-03-30 2020-05-11 2020-05-11 2020-06-10 2020-06-11 2020-07-15 2020-06-30 "Zhetigen" Kindergarten in Envelope 11 Beryu-Bash village, Ak-Suu region, Issyk-Kul oblast IDA-VIP3-HO-CW-NCB-20-2 / Construction of a Single Stage - One 2021-01- kindergarten for 100 places IDA / D0410 Village Investments Post Request for Bids Open - National 143,500.00 468,937.48 Signed 2020-03-25 2020-04-17 2020-03-30 2020-05-11 2020-05-11 2020-06-10 2020-06-11 2020-07-15 2020-07-29 Envelope 11 Ak-Sai village, Ton region, Issyk-Kul oblast IDA-VIP3-HO-CW-NCB-20-3 / Construction of a Single Stage - One 2020-12- kindergarten for 50 places IDA / D0410 Village Investments Post Request for Bids Open - National 254,130.43 222,477.40 Signed 2020-02-21 2020-03-06 2020-02-26 2020-03-06 2020-04-08 2020-05-06 2020-05-08 2020-07-15 2020-06-12 2020-08-11 Envelope 09 Zherge-Tal village, Ak-Tala region, Naryn oblast IDA-VIP3-HO-CW-SH-20-3 / Construction of FAP in Kyzyl- Request for Single Stage - One 2020-10- IDA / D0410 Village Investments Post Limited 28,418.48 31,135.12 Signed 2020-02-26 2020-02-21 2020-04-22 2020-03-16 Zhyldyz village, Zhumgal Quotations Envelope 19 region, Naryn oblast IDA-VIP3-HO-CW-NCB-20-4 / Construction of a Single Stage - One 2020-12- kindergarten for 50 places IDA / D0410 Village Investments Post Request for Bids Open - National 182,608.70 217,340.32 Signed 2020-02-24 2020-03-06 2020-02-29 2020-03-06 2020-04-11 2020-05-06 2020-05-11 2020-06-09 2020-06-15 2020-08-13 Envelope 12 Zher-Kechkyu village, Naryn region, Naryn oblast IDA-VIP3-HO-CW-SH-20-6 / Construction of FAP in Request for Single Stage - One 2020-11- IDA / D0410 Village Investments Post Limited 30,434.78 38,072.83 Signed 2020-03-30 2020-05-07 2020-05-25 2020-07-20 Tamchy-Bulak village, Kara- Quotations Envelope 21 Buura region, Talas oblast IDA-VIP3-HO-CW-NCB-20-5 / Construction of a Single Stage - One 2020-12- IDA / D0410 Village Investments Post Request for Bids Open - National 258,695.65 205,590.46 Signed 2020-02-24 2020-03-06 2020-02-29 2020-03-06 2020-04-11 2020-08-05 2020-05-11 2020-08-13 2020-06-15 2020-08-20 kindergarten Ken-Aral village, Envelope 12 Bakai-Ata region, Talas oblast IDA-VIP3-HO-CW-NCB-20-6 / Construction of a Single Stage - One 2020-12- kindergarten A.Ogonbaev IDA / D0410 Village Investments Post Request for Bids Open - National 227,991.99 226,285.69 Signed 2020-02-24 2020-03-06 2020-02-29 2020-03-06 2020-04-11 2020-05-06 2020-05-11 2020-06-09 2020-06-15 2020-07-20 Envelope 12 village, Talas region, Talas oblast IDA-VIP3-HO-CW-NCB-20-7 / The device of a sewer collector and connection to a Single Stage - One 2021-02- IDA / D0410 Village Investments Post Request for Bids Open - National 259,730.35 204,040.06 Signed 2020-05-04 2020-08-21 2020-05-09 2020-06-20 2020-09-11 2020-07-20 2020-09-23 2020-08-24 2020-10-15 city network in Nijnealarcha Envelope 20 village, Alamudun region, Chui oblast IDA-VIP3-HO-CW-SH-20-7 / Asphalting of the road in Request for Single Stage - One 2020-11- IDA / D0410 Village Investments Post Limited 91,304.35 0.00 Canceled 2020-03-30 2020-05-25 Dayyrbek village, Issyk-Ata Quotations Envelope 21 region, Chui oblast IDA-VIP3-HO-CW-SH-20-5 / Construction of Library in Request for Single Stage - One 2020-11- IDA / D0410 Village Investments Post Limited 45,652.17 0.00 Canceled 2020-03-30 2020-05-25 Ottuk village, Naryn region, Quotations Envelope 21 Naryn oblast IDA-VIP3-HO-CW-SH-20-4 / Construction of FAP in Chon- Request for Single Stage - One 2020-11- IDA / D0410 Village Investments Post Limited 39,565.00 0.00 Canceled 2020-03-30 2020-05-25 Tash village, Tyup region, Quotations Envelope 21 Issyk-Kul oblast IDA-VIP3-HO-CW-NCB-20-8 / Construction of FAP in Chon- Single Stage - One 2020-08- IDA / 56010 Village Investments Post Request for Bids Open - National 76,475.00 79,907.89 Signed 2020-04-24 2020-05-13 2020-04-29 2020-05-12 2020-06-10 2020-06-03 2020-07-10 2020-06-24 2020-07-31 2020-08-03 Tash village, Tyup region, Envelope 15 Issyk-Kul oblast IDA-VIP3-HO-CW-NCB-20-9 / Construction of Library in Single Stage - One 2021-02- IDA / 56010 Village Investments Post Request for Bids Open - National 68,750.00 76,089.19 Signed 2020-04-27 2020-05-13 2020-05-02 2020-05-13 2020-06-13 2020-06-03 2020-07-13 2020-06-24 2020-08-17 2020-08-14 Ottuk village, Naryn region, Envelope 13 Naryn oblast IDA-VIP3-HO-CW-SH-20-1 / Overhaul of school them. Request for Single Stage - One 2020-08- Myrzakmatova in Kozhomkul IDA / 56010 Village Investments Post Open - National 35,431.00 29,222.97 Completed 2020-02-17 2020-04-02 2020-03-25 Quotations Envelope 30 village, Zhaiyl region, Chui oblast Page 1 IDA-VIP3-HO-CW-SH-20-2 / Overhaul of kindergarten in Request for Single Stage - One 2020-09- IDA / 56010 Village Investments Post Open - National 65,625.00 45,323.76 Completed 2020-02-17 2020-04-13 2020-03-27 Kaldyk village, Zhaiyl region, Quotations Envelope 10 Chui oblast IDA-VIP3-HO-CW-NCB-20- 10 / Construction of GSV in Single Stage - One 2021-04- IDA / D0410 Village Investments Post Request for Bids Open - National 102,958.00 91,295.42 Signed 2020-08-26 2020-09-04 2020-08-28 2020-09-18 2020-09-25 2020-10-18 2020-10-15 2020-11-15 2020-10-26 Ak-Dobo village Bakai-Ata Envelope 14 Ragion, Talas Oblast IDA-VIP3-HO-CW-NCB-20- 11 / Construction of Single Stage - One 2021-10- kindergarten for 100 places in IDA / 56010 Village Investments Post Request for Bids Open - National 519,484.00 401,429.27 Signed 2020-11-15 2020-12-02 2020-11-20 2020-12-02 2020-12-11 2020-12-23 2021-01-07 2021-01-26 2021-02-07 2021-02-25 Envelope 05 the Taldy-Suu village, Tup Ragion, Issyk-Kul oblast IDA-VIP3-HO-CW-NCB-20- 12 / Construction of Single Stage - One 2021-09- kindergarten for 50 places in IDA / 56010 Village Investments Post Request for Bids Open - National 225,269.99 216,423.55 Signed 2020-12-09 2020-12-16 2020-12-10 2020-12-16 2020-12-31 2021-01-06 2021-01-30 2021-02-01 2021-02-28 2021-02-22 Envelope 26 the Dobolu village, Naryn Ragion, Naryn oblast IDA-VIP3-HO-CW-NCB-20- 13 / Construction of Single Stage - One 2021-08- kindergarten for 50 places in IDA / 56010 Village Investments Post Request for Bids Open - National 225,707.41 215,418.47 Signed 2020-12-09 2020-12-16 2020-12-10 2020-12-16 2020-12-31 2021-01-06 2021-01-30 2021-02-05 2021-02-02 2021-02-19 Envelope 31 the Maymak village, Kara-Bura Ragion, Talas oblas IDA-VIP3-HO-CW-NCB-20- 14 / Repair of school in the Single Stage - One 2021-08- IDA / 56010 Village Investments Post Request for Bids Open - National 194,077.52 198,757.36 Signed 2020-12-16 2020-12-25 2020-12-18 2020-12-28 2021-01-08 2021-01-15 2021-02-07 2021-02-03 2021-03-14 2021-02-17 village Stavropolovka, Zhayil Envelope 11 rayon, Chui oblast IDA-VIP3-HO-CW-NCB-20- 15 / Repair of the drinking Single Stage - One 2021-09- water supply system in the IDA / 56010 Village Investments Post Request for Bids Open - National 67,751.00 62,516.80 Signed 2021-02-10 2021-02-12 2021-02-11 2021-02-11 2021-03-04 2021-03-05 2021-04-03 2021-04-02 2021-04-29 2021-04-26 Envelope 26 village. Kadyraly, Ak-Tala rayon, Naryn oblast IDA-VIP3-HO-CW-NCB-20- 16 / Installation of lighting on the streets in the villages Zher- Single Stage - One 2021-11- IDA / 56010 Village Investments Post Request for Bids Open - National 42,730.00 48,268.97 Signed 2021-03-19 2021-03-19 2021-03-19 2021-04-09 2021-05-09 2021-05-09 2021-05-06 2021-06-09 2021-05-21 Kazar, Nizhniy-Nooruz, Envelope 06 Druzhba Villages, Issyk-Ata Raion, Chuy Oblast IDA-VIP3-HO-CW-NCB-20- 17 / Major Repair drinking Single Stage - One 2021-11- water system in the village IDA / 56010 Village Investments Post Request for Bids Open - National 417,114.69 356,317.58 Signed 2021-04-09 2021-04-09 2021-04-09 2021-04-09 2021-04-30 2021-04-30 2021-05-30 2021-05-25 2021-06-28 2021-06-21 Envelope 25 Jyrgalan Ak-Suu raijon Issyk- Kul oblast IDA-VIP3-HO-CW-NCB-20- 18 / Major repair of Single Stage - One 2021-11- kindergarten "ALENKA" in the IDA / 56010 Village Investments Post Request for Bids Open - National 294,029.83 0.00 Canceled 2021-04-02 2021-04-09 2021-04-02 2021-04-09 2021-04-23 2021-05-04 2021-05-23 2021-05-24 2021-06-23 Envelope 20 village Predtechenka Moscow rajion Chui oblast IDA-VIP3-HO-CW-NCB-20- 19 / Construction of FAPs`in the village Min-Bulak Bakai- Single Stage - One 2021-12- IDA / 56010 Village Investments Post Request for Bids Open - National 134,529.40 89,501.47 Signed 2021-04-15 2021-04-23 2021-04-15 2021-04-23 2021-05-06 2021-05-14 2021-06-05 2021-06-23 2021-07-06 2021-08-24 Ata raijion Talas oblast and in Envelope 03 the village Min-Bulak Typ rajion Issyk-Kul oblast IDA-VIP3-HO-CW-NCB-20- 20 / Construction of FAPs`in Request for Bids - the village Ak-Bulun Tup Single Stage - One Small Works SPD 2021-12- IDA / 56010 Village Investments Post Request for Bids Open - National 106,382.00 92,992.83 Signed 2021-04-30 2021-05-21 2021-04-30 2021-05-21 2021-06-11 2021-06-20 2021-07-16 2021-07-21 2021-07-18 raijion Issyk-Kul oblast and in Envelope (1 envelope 18 the village Kaiyndy-Bulak Ak- process) Talaa rajion Naryn oblast IDA-VIP3-HO-CW-NCB-20- Request for Bids - 18/RT / Major repair of Single Stage - One Small Works SPD 2022-02- kindergarten "ALENKA" in the IDA / 56010 Village Investments Post Request for Bids Open - National 294,029.93 341,823.93 Signed 2021-05-27 2021-05-28 2021-06-01 2021-06-22 2021-06-22 2021-07-22 2021-07-21 2021-08-18 2021-08-25 Envelope (1 envelope 14 village Predtechenka Moscow process) rajion Chui oblast IDA-VIP3-HO-CW-NCB-20- 21 / Construction of FAPs`in the village Jar-Bashy Request for Bids - International AA Isyk-Ata Single Stage - One Small Works SPD 2022-03- IDA / 56010 Village Investments Post Request for Bids Open - National 114,282.76 53,199.76 Signed 2021-07-16 2021-07-16 2021-07-16 2021-08-06 2021-08-06 2021-09-05 2021-08-12 2021-10-06 2021-09-09 district Chui oblast and in the Envelope (1 envelope 05 village Besh-Koruk process) Aleksandrovski AA Moscow district Chui oblast IDA-VIP3-HO-CW-NCB-20- National 22 / Overhaul of the FAP Procurement Single Stage - One 2022-05- building in the village IDA / 56010 Village Investments Post Request for Bids Open - National Document - 1 55,895.17 57,767.93 Signed 2021-09-07 2021-09-10 2021-09-07 2021-09-28 2021-10-01 2021-11-27 2021-10-20 2021-12-28 2021-11-16 Envelope 27 Ozgorush Ozgorush AO Bakai- Envelope process Ata rayon of Talas oblast (Non Bank-SPD) IDA-VIP3-HO-CW-NCB-20- 23 / Overhaul of the FAP National building and improvement of Procurement the sanitary and hygienic Single Stage - One 2022-05- IDA / 56010 Village Investments Post Request for Bids Open - National Document - 1 51,029.51 0.00 Canceled 2021-09-07 2021-09-10 2021-09-07 2021-09-28 2021-11-27 2021-12-28 conditions of the kindergarten Envelope 27 Envelope process in the village. Konorchok of (Non Bank-SPD) Konorchok AO Ak-Tala rayon Naryn oblast IDA-VIP3-HO-CW-NCB-20- National 24 / Renovation of high Procurement Single Stage - One 2022-05- school sanitary facilities. in IDA / 56010 Village Investments Post Request for Bids Open - National Document - 1 56,713.16 56,418.69 Signed 2021-09-08 2021-09-10 2021-09-10 2021-10-01 2021-10-01 2021-11-30 2021-10-19 2021-12-31 2021-11-16 Envelope 30 with. Kyz-Molo Moscow rayon Envelope process Chui oblast (Non Bank-SPD) IDA-VIP3-HO-CW-SH-20-25 / Installation of sanitary Request for facilities in schools of villages Request for Single Stage - One 2022-04- IDA / D0410 Village Investments Post Open - National Quotations (Non 48,625.00 0.00 Canceled 2021-10-08 2021-11-28 Ken-Suu, Sary-Tologoi, San- Quotations Envelope 27 Bank-SPD) Tash of the San-Tash AA Tup district Issyk-Kul oblast Page 2 IDA-VIP3-HO-CW-NCB-20- 23/RT / Installation of National sanitary facilities in schools of Procurement Single Stage - One 2022-05- villages Ken-Suu, Sary- IDA / D0410 Village Investments Post Request for Bids Open - National Document - 1 51,029.51 0.00 Canceled 2021-10-11 2021-10-11 2021-11-01 2021-11-29 2021-12-05 Envelope 04 Tologoi, San-Tash of the San- Envelope process Tash AA Tup district Issyk-Kul (Non Bank-SPD) oblast IDA-VIP3-HO-CW-SH-20- 25/RT2 / Installation of Request for sanitary facilities in schools of Quotations - Small Request for Single Stage - One 2022-05- villages Ken-Suu, Sary- IDA / 56010 Village Investments Post Open - National Works 48,625.00 38,108.87 Signed 2021-11-15 2021-12-20 2021-12-15 Quotations Envelope 19 Tologoi, San-Tash of the San- (Emergency) SPD - Tash AA Tup district Issyk-Kul Competitive oblast IDA-VIP3-HO-CW-NCB-20- 23/RT2 / Overhaul of the FAP building and improvement of Request for Bids - the sanitary and hygienic Single Stage - One Small Works SPD 2022-06- IDA / 56010 Village Investments Post Request for Bids Open - National 51,029.51 60,733.39 Signed 2021-11-19 2021-11-19 2021-11-19 2021-12-10 2021-11-19 2021-12-24 2022-01-11 2022-01-16 2022-01-28 conditions of the kindergarten Envelope (1 envelope 15 in the village. Konorchok of process) Konorchok AO Ak-Tala rayon Naryn oblast GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-VIP3-HO-GOODS-SH-20- 3 / personal protective Request for Single Stage - One IDA / D0410 Village Investments Post Limited 99,800.00 88,621.41 Signed 2020-04-24 2020-05-06 2020-05-08 2020-05-18 2020-05-29 2020-05-20 equipment for work in the Quotations Envelope centers of COVID-19 IDA-VIP3-HO-EQ-NCB-20-7 / Purchase of special Single Stage - One IDA / 56010 Village Investments Post Request for Bids Open - National 91,304.00 117,736.29 Signed 2020-11-05 2020-11-06 2020-11-05 2020-11-06 2020-11-26 2020-11-27 2020-12-17 2020-12-09 2021-01-17 2020-12-28 2021-05-17 equipment for the removal of Envelope SHW Tuz AA, Chui oblast IDA-VIP3-HO-EQ-NCB-20-8 / Purchase of special Single Stage - One equipment for loading and IDA / 56010 Village Investments Post Request for Bids Open - National 87,296.00 72,307.85 Signed 2020-11-05 2020-11-06 2020-11-05 2020-11-06 2020-11-26 2020-11-27 2020-12-17 2020-12-10 2021-01-17 2020-12-28 2021-05-17 Envelope transporting goods Nurjanov AA, Talas oblast IDA-VIP3-HO-EQ-NCB-20-9 / Purchase of electrical Single Stage - One equipment for the IDA / 56010 Village Investments Post Request for Bids Open - National 68,500.00 0.00 Canceled 2020-11-04 2020-11-27 2020-11-04 2020-11-25 2020-12-18 2020-12-16 2020-12-29 2021-01-16 2021-03-17 Envelope reconstruction of VL-6-0,4 kV Kabak AA, Naryn oblast IDA-VIP3-HO-EQ-NCB-20- 9/RT1 / Purchase of electrical Single Stage - One equipment for the IDA / 56010 Village Investments Post Request for Bids Open - National 68,500.00 0.00 Canceled 2021-01-18 2021-01-20 2021-02-10 2021-03-12 2021-04-14 2021-06-13 Envelope reconstruction of VL-6-0,4 kV Kabak AA, Naryn oblast NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-VIP3-S-CQ-20-4 / Development of detailed design estimates for the Consultant installation of lighting on the IDA / D0410 Village Investments Post Qualification Open - National 15,000.00 31,208.89 Signed 2020-07-13 2020-07-14 2020-08-03 2020-09-07 2020-10-13 2020-09-14 2020-12-07 2020-09-28 2020-12-10 2020-12-27 streets of Zher-Kazar, Nizhniy- Selection Nooruz, Druzhba Villages, Issyk-Ata Raion, Chuy Oblast IDA-VIP3-S-CQ-20-5 / development of detailed design estimates for the capital repair of the drinking Consultant water sup-ply system in IDA / D0410 Village Investments Post Qualification Open - National 30,000.00 12,277.54 Signed 2020-07-13 2020-08-13 2020-08-03 2020-09-07 2020-09-11 2020-09-14 2020-10-28 2020-09-28 2020-10-28 2020-12-27 Zhyrgalan Village, Ak-Suy Selection Raion, Issyk-Kul Oblast and in Kadyraly Village, Ak-Talaa Raion, Naryn Oblast IDA-VIP3-S-CQ-20-6 / development of detailed design estimates for the Consultant capital repair of the building IDA / D0410 Village Investments Post Qualification Open - National 15,000.00 12,026.61 Signed 2020-07-13 2020-08-17 2020-08-03 2020-09-07 2020-10-15 2020-09-14 2020-11-16 2020-09-28 2020-12-07 2020-12-27 of the Alen-ka kindergarten in Selection the village of Predtechenka, Moskovskiy Raion, Chuy Oblast IDA-VIP3-V-CQ-2020-16 / Capacity Building of Local Consultant Preparing Audio and Video IDA / D0410 Self-Governments and Post Qualification Open - National 2,000.00 3,713.63 Signed 2020-08-18 2020-10-26 2020-09-08 2020-10-13 2020-10-23 2020-10-18 2020-11-17 2020-10-28 2020-12-07 2021-01-26 Lessons Communities Selection IDA-VIP-S-CQ-20-7 / development of detailed design estimates for the Consultant construction of the building IDA / D0410 Village Investments Post Qualification Open - National 15,000.00 0.00 Canceled 2020-07-24 2020-08-07 2020-09-13 2020-09-16 2020-09-18 2020-12-17 for the GFD (Group of Family Selection Doctors) in Ak-Dobo Village, Bakai-Ata Raion, Talas Oblast Page 3 Capacity Building of Local Consultant IDA-VIP3-V-CQ-2021-1 / IDA / D0410 Self-Governments and Post Qualification Open - National 6,000.00 13,895.36 Signed 2021-03-29 2021-04-30 2021-04-19 2021-05-17 2021-06-21 2021-05-20 2021-08-11 2021-05-26 2021-09-07 2021-08-24 Information Compaign Communities Selection IDA-VIP3-CQ-2021-2 / AF Capacity Building of Local Consultant VIP-3 Baseline survey and VIP- IDA / D0410 Self-Governments and Post Qualification Open - National 60,000.00 68,415.27 Signed 2021-05-28 2021-05-31 2021-06-11 2021-07-14 2021-07-09 2021-07-19 2021-10-14 2021-07-25 2021-12-13 2021-11-22 3 Impact Assessment Communities Selection ARIS-AUDIT-LCS-2021-1 / Least Cost Under IDA / 56010 Project Management Post Open - International 42,589.00 0.00 2021-08-10 2021-08-16 2021-08-24 2021-09-24 2021-09-21 2021-10-12 2021-10-19 2021-11-05 2021-11-26 2023-12-31 Audit Selection Implementation IDA-VIP3-CQ-2021-3 / Capacity Building of Local Consultant Conducting Market and Value Under IDA / 56010 Self-Governments and Post Qualification Open - National 60,000.00 0.00 2021-10-04 2021-10-05 2021-10-18 2021-11-17 2021-11-22 2021-12-02 2022-04-01 Chain Analysis research in the Implementation Communities Selection target areas of the Project INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-VIP3-T-IC-2020-1 / Technical Supervision Individual Engineer (TSE) for subproject IDA / D0410 Village Investments Post Consultant Open 5,600.00 2,888.23 Signed 2020-02-26 2020-02-24 2020-04-15 2020-05-29 2020-05-06 2020-05-29 2020-06-10 2020-06-11 2020-12-07 ‘Construction of FAP in Kyzyl- Selection Zhyldyz village, Zhumgal region, Naryn oblast’ IDA-VIP3-T-IC-2020-2 / Technical Supervision Engineer (TSE) for subproject Individual ‘Overhaul of school them. IDA / D0410 Village Investments Post Consultant Open 5,600.00 0.00 Canceled 2020-02-21 2020-02-18 2020-04-10 2020-05-01 2020-06-05 2020-12-02 Myrzakmatova in Kozhomkul Selection village, Zhaiyl region, Chui oblast’ IDA-VIP3-T-IC-2020-3 / Technical Supervision Individual Engineer (TSE) for subproject IDA / D0410 Village Investments Post Consultant Open 5,600.00 2,888.31 Signed 2020-02-21 2020-02-18 2020-04-10 2020-05-22 2020-05-01 2020-06-04 2020-06-05 2020-06-05 2020-12-02 ‘Overhaul of kindergarten in Selection Kaldyk village, Zhaiyl region, Chui oblast’ IDA-VIP3-T-IC-2020-4 / Technical Supervision Engineer (TSE) for subproject Individual “Construction of a IDA / D0410 Village Investments Post Consultant Open 5,600.00 2,954.24 Signed 2020-03-18 2020-03-16 2020-05-06 2020-08-03 2020-05-27 2020-08-03 2020-07-01 2020-08-05 2020-12-28 kindergarten Ken-Aral village, Selection Bakai-Ata region, Talas oblast” IDA-VIP3-T-IC-2020-5 / Technical Supervision Engineer (TSE) for subproject Individual “Construction of a IDA / D0410 Village Investments Post Consultant Open 5,600.00 3,211.66 Signed 2020-03-18 2020-03-16 2020-05-06 2020-08-03 2020-05-27 2020-08-04 2020-07-01 2020-08-05 2020-12-28 kindergarten A.Ogonbaev Selection village, Talas region, Talas oblast” IDA-VIP3-T-IC-2020-6 / Technical Supervision Engineer (TSE) for subproject Individual “Construction of a IDA / D0410 Village Investments Post Consultant Open 5,600.00 4,002.26 Signed 2020-03-18 2020-03-16 2020-05-06 2020-08-03 2020-05-27 2020-08-04 2020-07-01 2020-08-05 2020-12-28 kindergarten for 50 places Selection Zherge-Tal village, Ak-Tala region, Naryn oblast” IDA-VIP3-T-IC-2020-7 / Technical Supervision Engineer (TSE) for subproject Individual “Construction of a IDA / D0410 Village Investments Post Consultant Open 5,600.00 4,126.04 Signed 2020-03-18 2020-03-16 2020-05-06 2020-08-03 2020-05-27 2020-08-04 2020-07-01 2020-08-05 2020-12-28 kindergarten for 50 places Selection Zher-Kechkyu village, Naryn region, Naryn oblast” IDA-VIP3-T-IC-2020-8 / Technical Supervision Engineer (TSE) for subproject Individual “Construction of a IDA / D0410 Village Investments Post Consultant Open 7,100.00 4,628.29 Signed 2020-05-19 2020-05-18 2020-07-07 2020-08-03 2020-07-28 2020-08-04 2020-09-01 2020-08-05 2021-02-28 kindergarten for 100 places Selection Ak-Sai village, Ton region, Issyk-Kul oblast” IDA-VIP3-T-IC-2020-9 / Technical Supervision Engineer (TSE) for subproject Individual “Construction of an additional IDA / D0410 Village Investments Post Consultant Open 7,100.00 5,133.08 Signed 2020-05-19 2020-05-18 2020-07-07 2020-08-03 2020-07-28 2020-08-04 2020-09-01 2020-08-05 2021-02-28 building for "Zhetigen" Selection Kindergarten in Beryu-Bash village, Ak-Suu region, Issyk- Kul oblast” IDA-VIP3-T-IC-2020-10 / Technical Supervision Individual Engineer (TSE) for subproject IDA / D0410 Village Investments Post Consultant Open 5,600.00 3,201.81 Signed 2020-05-19 2020-05-18 2020-07-07 2020-08-03 2020-07-28 2020-08-04 2020-09-01 2020-08-05 2021-02-28 “Construction of FAP in Selection Tamchy-Bulak village, Kara- Buura region, Talas oblast” IDA-VIP3-T-IC-2020-11 / Technical Supervision Individual Engineer (TSE) for subproject IDA / D0410 Village Investments Post Consultant Open 5,600.00 3,460.08 Completed 2020-05-20 2020-05-18 2020-07-08 2020-08-03 2020-07-29 2020-08-04 2020-09-02 2020-08-05 2021-03-01 2020-12-31 “Construction of FAP in Chon- Selection Tash village, Tyup region, Issyk-Kul oblast” IDA-VIP3-T-IC-2020-12 / Technical Supervision Individual Engineer (TSE) for subproject IDA / D0410 Village Investments Post Consultant Open 5,600.00 4,126.04 Signed 2020-05-20 2020-05-18 2020-07-08 2020-08-03 2020-07-29 2020-08-04 2020-09-02 2020-08-05 2021-03-01 “Construction of Library in Selection Ottuk village, Naryn region, Naryn oblast” Page 4 IDA-VIP3-T-IC-2020-13 / Technical Supervision Engineer (TSE) for subproject Individual “The device of a sewer IDA / D0410 Village Investments Post Consultant Open 5,600.00 2,617.09 Signed 2020-06-16 2020-05-20 2020-08-04 2020-10-19 2020-08-25 2020-10-19 2020-09-29 2020-10-20 2021-03-28 collector and connection to a Selection city network in Nijnealarcha village, Alamudun region, Chui oblast” VIP-S-CQ-20-2 / The geo- referencing to the area design documents (DDE), calculation of the estimated cost of works and materials, and conducting IDA / D0410 Village Investments Post Direct Selection Direct 5,000.00 0.00 Canceled 2020-05-22 2020-08-13 2020-05-29 2020-06-03 2020-08-02 supervision of the facility of Construction of a kindergarten for 50 children in the village of Maimak, Kara- Buura Raion IDA-VIP3-IC-20-13 / Development Cost Estimate Individual for the Capital Repair of the IDA / D0410 Village Investments Post Consultant Open 2,000.00 869.57 Signed 2020-07-13 2020-08-18 2020-08-17 2020-10-14 2020-08-20 2020-10-14 2020-08-26 2020-10-20 2020-11-24 building of School Selection Stravopolovka of Jaiyl Ragion, Chui Region IDA-VIP-S-DC-20-3 / The geo-referencing to the area of deteiled design documents (DDE), calculation of the estimated cost of works and IDA / D0410 Village Investments Post Direct Selection Direct 13,500.00 12,195.12 Completed 2020-07-20 2020-07-23 2020-07-27 2020-08-03 2020-08-01 2020-08-15 2020-09-30 2020-10-30 materials, and conducting supervision of the facility of Construction of a kindergarten for 100 children in the village of Taldy-Suu,IK IDA-VIP-S-DC-20-8 / author's supervision Construction of an additional building for "Zhetigen" IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 1,460.18 Signed 2020-07-24 2020-08-13 2020-08-03 2020-08-19 2020-08-07 2020-08-26 2021-03-05 Kindergarten in Beryu-Bash village, Ak-Suu region, Issyk- Kul oblast IDA-VIP-S-DC-20-9 / Author's supervision of Construction of FAP in IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 730.09 Signed 2020-07-24 2020-08-13 2020-08-03 2020-08-19 2020-08-06 2020-08-26 2021-01-03 Tamchy-Bulak village, Kara- Buura region, Talas oblast IDA-VIP-S-DC-20-10 / Author's supervision of construction of a kindergarten IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 878.40 Signed 2020-07-24 2020-08-13 2020-08-03 2020-08-19 2020-08-06 2020-08-26 2021-01-03 A.Ogonbaev village, Talas region, Talas oblast IDA-VIP-S-DC-20-11 / Author's supervision of construction of a kindergarten IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 1,169.07 Signed 2020-07-24 2020-08-13 2020-08-03 2020-08-19 2020-08-06 2020-08-26 2021-01-03 Ken-Aral village, Bakai-Ata region, Talas oblast IDA-VIP-S-DC-20-12 / Author's supervision of сonstruction of a kindergarten IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 1,226.87 Signed 2020-07-24 2020-08-13 2020-07-30 2020-08-19 2020-08-07 2020-08-26 2021-01-04 Zher-Kechkyu village, Naryn region, Naryn oblast IDA-VIP-S-DC-20-13 / Author's supervision of Construction of a IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 1,746.01 Signed 2020-07-24 2020-08-13 2020-07-30 2020-08-19 2020-08-07 2020-08-26 2021-01-04 kindergarten Zherge-Tal village, Ak-Tala region, Naryn oblast IDA-VIP-S-DC-20-14 / Author's supervision of Construction of a IDA / D0410 Village Investments Post Direct Selection Direct 1,322.00 1,155.89 Signed 2020-07-24 2020-08-13 2020-07-30 2020-08-19 2020-08-07 2020-08-27 2021-03-05 kindergarten Ak-Sai village, Ton region, Issyk-Kul oblast IDA-VIP-S-DC-20-15 / Author's supervision of Construction of FAP in Chon- IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 1,469.34 Signed 2020-07-24 2020-08-13 2020-07-30 2020-08-19 2020-08-07 2020-08-27 2021-01-04 Tash village, Tyup region, Issyk-Kul oblast IDA-VIP-S-DC-20-16 / Author's supervision of Construction of Library in IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 1,130.53 Signed 2020-07-24 2020-08-13 2020-07-30 2020-08-19 2020-08-07 2020-08-27 2021-01-04 Ottuk village, Naryn region, Naryn oblast IDA-VIP-S-DC-20-1 / The geo-referencing to the area of deteiled design documents (DDE), calculation of the estimated cost of works and materials, and conducting IDA / D0410 Village Investments Post Direct Selection Direct 5,500.00 4,728.87 Completed 2020-08-03 2020-08-13 2020-08-09 2020-08-24 2020-08-12 2020-08-26 2020-11-10 2020-11-26 supervision of the facility of Construction of a kindergarten for 50 children in the village of Dobolu, Naryn Raio IDA-VIP-S-DC-20-2 / The geo-referencing to the area design documents (DDE), calculation of the estimated cost of works and materials, IDA / D0410 Village Investments Post Direct Selection Direct 5,500.00 4,728.87 Completed 2020-08-17 2020-08-24 2020-08-27 2020-08-24 2020-09-05 2020-08-26 2020-12-04 2020-11-26 and conducting supervision of the facility of Construction of a kindergarten for 50 children in the village of Maimak, Kara- Buura Raion Page 5 IDA-VIP3-T-IC-2020-14 / Technical supervision consultant for sub projects of Capacity Building of Local Individual the construction of building IDA / D0410 Self-Governments and Post Consultant Open 6,000.00 2,744.40 Signed 2020-10-21 2020-10-22 2020-11-12 2020-11-20 2020-11-13 2020-12-07 2020-11-17 2021-01-04 2021-07-15 for a group of family doctors Communities Selection (FGP) in the village Ak-Dobo Talas oblast(3 cycle) IDA-VIP-S-DC-20-17 / Author's supervision of the construction drainage collector and conection IDA / D0410 Village Investments Post Direct Selection Direct 2,500.00 2,563.50 Signed 2020-10-25 2020-11-13 2020-10-27 2020-10-26 2020-10-30 2021-01-06 2021-03-29 Bishkek City net in the Chui oblast, Alamudun rajion, Nijnee Ala-Archa IDA-VIP-S-DC-20-18 / The geo-referencing to the area of deteiled design documents (DDE), calculation of the estimated cost of works and IDA / D0410 Village Investments Post Direct Selection Direct 18,115.00 14,246.62 Signed 2020-11-04 2020-11-04 2020-11-09 2020-11-05 2020-11-13 2020-12-09 2021-02-26 materials, and conducting supervision of the facility of Construction of feldsher- obstetric station (FAP) in the villages. IDA-VIP3-T-IC-2020-15 / Technical supervision consultant for sub projects of Individual the construction of IDA / D0410 Village Investments Post Consultant Open 5,294.00 0.00 Canceled 2020-11-19 2020-11-20 2020-12-19 2020-12-22 2020-12-27 2021-09-23 Kindergarten for 100 places Selection in the village Taldu-Suu Issyk- Kul (3 cycle) IDA-VIP3-T-IC-2020-16 / Technical supervision consultant for sub project of Individual the сonstruction of IDA / D0410 Village Investments Post Consultant Open 5,294.00 4,265.14 Signed 2020-12-16 2021-02-04 2021-01-14 2021-02-25 2021-01-15 2021-02-26 2021-01-21 2021-03-01 2021-10-18 kindergarten for 50 places in Selection the Dobolu village, Naryn Ragion, Naryn oblast (3 cycle) IDA-VIP3-T-IC-2020-17 / Technical supervision consultant for sub project of Individual the construction of IDA / D0410 Village Investments Post Consultant Open 5,294.00 0.00 Canceled 2020-12-16 2021-02-04 2021-01-01 2021-01-02 2021-01-21 2021-10-18 kindergarten for 50 places in Selection the Maymak village, Kara-Bura Ragion, Talas oblas (3 cycle) IDA-VIP3-IC-2020-18 / Selection of a consultant for the development of design estimates for: Individual "Repair of FAP, purchase of IDA / D0410 Village Investments Post Consultant Open 1,647.00 0.00 Canceled 2020-12-16 2020-12-14 2021-01-14 2021-01-15 2021-01-21 2021-02-20 inventory and equipment" in Selection the village. Zhar-Bashy, International AO, Issyk-Ata rayon, Chui oblast " IDA-VIP3-T-IC-2020-18 / Technical supervision Individual consultant for sub project of IDA / D0410 Village Investments Post Consultant Open 2,994.00 3,271.67 Signed 2021-01-06 2021-01-24 2021-02-08 2021-03-15 2021-02-08 2021-03-15 2021-02-13 2021-03-23 2021-09-11 the Repairing of school in the Selection village Stavropolovka, Zhayil rayon, Chui oblast (3 cycle) Capacity Building of Local Individual IDA-VIP3-IC-2020-17 / IDA / D0410 Self-Governments and Post Consultant Open 5,835.00 0.00 Canceled 2020-11-19 2020-11-25 2020-12-20 2020-12-23 2020-12-25 2021-08-22 Infrastructure Engineer Communities Selection IDA-VIP3-T-IC-2021-1 / Technical supervision Individual consultant for sub project of IDA / D0410 Village Investments Post Consultant Open 2,948.00 3,361.79 Signed 2021-03-02 2021-03-04 2021-03-31 2021-05-13 2021-04-01 2021-05-13 2021-04-03 2021-05-14 2021-09-30 the Repairing water sistem in Selection the Kadyraly village Ak-Tala raijion Naryn oblast IDA-VIP-S-DC-21-1 / Author's supervision of the construction kindergarten for IDA / D0410 Village Investments Post Direct Selection Direct 2,500.00 1,031.56 Signed 2021-03-03 2021-03-03 2021-03-18 2021-03-17 2021-03-21 2021-03-17 2021-10-17 50 places in the Maymak village Kara-Bura Rajion Talas oblast IDA-VIP-S-DC-21-2 / Author's supervision of the construction kindergarten for IDA / D0410 Village Investments Post Direct Selection Direct 2,500.00 990.29 Signed 2021-03-03 2021-03-10 2021-03-18 2021-03-09 2021-03-21 2021-03-17 2021-10-17 50 places in the Dobolu village Naryn Rajion Naryn oblast IDA-VIP-S-DC-21-3 / Author's supervision of the construction kindergarten for IDA / D0410 Village Investments Post Direct Selection Direct 2,500.00 1,325.99 Signed 2021-03-03 2021-03-05 2021-03-18 2021-03-12 2021-03-21 2021-03-15 2021-10-17 100 places in the Taldy-Suu village Tup Rajion Issyk-Kul oblast IDA-VIP-S-DC-21-4 / Author's supervision of Capital Repair Water System in IDA / D0410 Village Investments Post Direct Selection Direct 2,500.00 0.00 Canceled 2021-03-12 2021-03-18 2021-03-17 2021-03-20 2021-08-17 the village Kadyraly Naryn oblast (3 Cicle) Capacity Building of Local Individual IDA-VIP3-IC-2021-1 / IDA / D0410 Self-Governments and Post Consultant Open 3,300.00 0.00 Canceled 2021-03-12 2021-04-12 2021-04-15 2021-04-24 2021-08-22 Buisiness Planning Trainer Communities Selection IDA-VIP3-IC-TR-2021-2 / Capacity Building of Local Individual Business Planning and IDA / D0410 Self-Governments and Post Consultant Open 700.00 1,178.75 Signed 2021-03-29 2021-04-02 2021-04-29 2021-06-21 2021-04-30 2021-08-02 2021-05-02 2021-08-13 2021-08-30 Financial Literacy Trainer in Communities Selection the Naryn oblast Page 6 IDA-VIP3-IC-TR-2021-3 / Capacity Building of Local Individual Business Planning and IDA / D0410 Self-Governments and Post Consultant Open 700.00 1,178.75 Signed 2021-03-29 2021-04-02 2021-04-27 2021-06-21 2021-04-28 2021-06-21 2021-04-30 2021-08-13 2021-08-28 Financial Literacy Trainer in Communities Selection the Talas oblast IDA-VIP3-IC-TR-2021-4 / Capacity Building of Local Individual Business Planning and IDA / D0410 Self-Governments and Post Consultant Open 700.00 1,178.75 Signed 2021-03-29 2021-04-02 2021-04-27 2021-06-21 2021-04-28 2021-08-02 2021-04-30 2021-08-13 2021-08-28 Financial Literacy Trainer in Communities Selection the Issyk-Kul oblast IDA-VIP3-IC-TR-2021-5 / Capacity Building of Local Individual Business Planning and IDA / D0410 Self-Governments and Post Consultant Open 700.00 1,178.75 Signed 2021-03-29 2021-04-02 2021-04-27 2021-06-21 2021-04-28 2021-08-02 2021-04-30 2021-08-13 2021-08-28 Financial Literacy Trainer in Communities Selection the Chui oblst (1) IDA-VIP3-IC-TR-2021-6 / Capacity Building of Local Individual Business Planning and IDA / D0410 Self-Governments and Post Consultant Open 700.00 1,178.75 Signed 2021-03-29 2021-04-02 2021-04-27 2021-06-21 2021-04-28 2021-08-02 2021-04-30 2021-08-13 2021-08-28 Financial Literacy Trainer in Communities Selection the Chui oblst (2) IDA-VIP3-IC-2021-2 / Senior Capacity Building of Local Individual Economist (Local Markets and IDA / D0410 Self-Governments and Post Consultant Open 4,400.00 8,414.76 Signed 2021-03-31 2021-03-30 2021-04-30 2021-04-28 2021-05-02 2021-04-30 2021-05-07 2021-05-01 2021-11-03 Buisiness Expert) Communities Selection IDA-VIP3-IC-2021-3 / Consultant for the Capacity Building of Local development of Project IDA / D0410 Self-Governments and Post Direct Selection Direct 4,000.00 5,212.56 Signed 2021-03-31 2021-04-15 2021-04-03 2021-04-16 2021-04-12 2021-04-19 2021-07-11 Operational Manual for VIP-3 Communities AF IDA-VIP3-IC-SSS-TR-2021-7 Capacity Building of Local / Trainer for basic trainings of IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-24 2021-04-30 2021-05-24 2021-07-29 Operational Manual of Project Communities in the Naryn oblast (1) IDA-VIP3-IC-SSS-TR-2021-8 Capacity Building of Local / Trainer for basic trainings of IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-08-23 2021-04-30 2021-05-24 2021-07-29 Operational Manual of Project Communities in the Chui oblast (1) IDA-VIP3-IC-SSS-TR-2021-9 Capacity Building of Local / Trainer for basic trainings of IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-23 2021-04-30 2021-05-24 2021-07-29 Operational Manual of Project Communities in the Chui oblast (2) IDA-VIP3-IC-SSS-TR-2021- 10 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.31 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-24 2021-07-29 Manual of Project in the Chui Communities oblast (3) IDA-VIP3-IC-SSS-TR-2021- 11 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.31 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-24 2021-07-29 Manual of Project in the Issyk- Communities Kul oblast (1) IDA-VIP3-IC-SSS-TR-2021- 12 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.31 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-24 2021-07-29 Manual of Project in the Naryn Communities oblast (2) IDA-VIP3-IC-SSS-TR-2021- 13 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.31 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-24 2021-07-29 Manual of Project in the Chui Communities oblast (4) IDA-VIP3-IC-SSS-TR-2021- 14 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-24 2021-07-29 Manual of Project in the Issyk- Communities Kul oblast (2) IDA-VIP3-IC-SSS-TR-2021- 15 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 722.33 Signed 2021-04-19 2021-04-29 2021-04-24 2021-06-08 2021-04-30 2021-07-19 2021-07-29 Manual of Project in the Chui Communities oblast (5) IDA-VIP3-IC-SSS-TR-2021- 17 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-29 2021-05-24 2021-07-28 Manual of Project in the Chui Communities oblast (7) IDA-VIP3-IC-SSS-TR-2021- 18 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-24 2021-07-29 Manual of Project in the Chui Communities oblast (8) IDA-VIP3-IC-SSS-TR-2021- 19 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-24 2021-07-29 Manual of Project in the Talas Communities oblast (1) IDA-VIP3-IC-SSS-TR-2021- 20 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-05-19 2021-05-24 2021-08-17 Manual of Project in the Chui Communities oblast (9) IDA-VIP3-IC-SSS-TR-2021- 21 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-24 2021-07-29 Manual of Project in the Chui Communities oblast (10) Page 7 IDA-VIP3-IC-SSS-TR-2021- 22 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.38 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-24 2021-07-29 Manual of Project in the Issyk- Communities Kul oblast (3) IDA-VIP3-IC-SSS-TR-2021- 23 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.38 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-24 2021-07-29 Manual of Project in the Talas Communities oblast (2) IDA-VIP3-IC-SSS-TR-2021- 24 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.38 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-24 2021-07-29 Manual of Project in the Naryn Communities oblast (3) IDA-VIP3-IC-SSS-TR-2021- 25 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.38 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-24 2021-07-29 Manual of Project in the Chui Communities oblast (11) IDA-VIP3-IC-SSS-TR-2021- 26 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.38 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-24 2021-07-29 Manual of Project in the Issyk- Communities Kul oblast (4) IDA-VIP3-IC-SSS-TR-2021- 27 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.38 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-24 2021-07-29 Manual of Project in the Naryn Communities oblast (4) IDA-VIP3-IC-SSS-TR-2021- 28 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,591.47 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-24 2021-07-29 Manual of Project in the Naryn Communities oblast (4) IDA-VIP3-IC-SSS-TR-2021- 29 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-24 2021-07-29 Manual of Project in the Talas Communities oblast (3) IDA-VIP3-IC-SSS-TR-2021- 30 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-24 2021-07-29 Manual of Project in the Naryn Communities oblast (5) IDA-VIP3-IC-SSS-TR-2021- 31 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-24 2021-07-29 Manual of Project in the Chui Communities oblast (13) IDA-VIP3-IC-SSS-TR-2021- 32 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-24 2021-07-29 Manual of Project in the Chui Communities oblast (14) IDA-VIP3-IC-SSS-TR-2021- 33 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-24 2021-07-29 Manual of Project in the Talas Communities oblast (4) IDA-VIP3-IC-SSS-TR-2021- 34 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-24 2021-07-29 Manual of Project in the Issyk- Communities Kul oblast (6) IDA-VIP3-IC-SSS-TR-2021- 35 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,591.47 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-24 2021-07-29 Manual of Project in the Chui Communities oblast (14) IDA-VIP3-IC-SSS-TR-2021- 36 / Trainer for basic Capacity Building of Local trainings of Operational IDA / D0410 Self-Governments and Post Direct Selection Direct 1,588.00 1,945.13 Signed 2021-04-19 2021-04-30 2021-04-24 2021-05-10 2021-04-30 2021-05-24 2021-07-29 Manual of Project in the Chui Communities oblast (15) IDA-VIP3-T-IC-2021-2 / Technical supervision Individual consultant for sub project of IDA / D0410 Village Investments Post Consultant Open 3,800.00 3,932.67 Signed 2021-05-03 2021-05-06 2021-06-03 2021-09-02 2021-06-06 2021-09-02 2021-06-10 2021-10-01 2022-01-06 the Major repair kindergarten Selection Alenka in the Predtechenka village Chui oblast (3 cycle) IDA-VIP3-T-IC-2021-3 / Technical supervision Individual consultant for sub project of IDA / D0410 Village Investments Post Consultant Open 4,800.00 0.00 Canceled 2021-05-03 2021-06-07 2021-06-08 2021-06-10 2022-03-07 the Repairing water sistem in Selection the Jyrgalan village Tup raijion Issyk-Kul oblast (3 cycle) IDA-VIP3-T-IC-2021-4 / Technical supervision Individual consultant for sub project of IDA / D0410 Village Investments Post Consultant Open 3,200.00 0.00 Canceled 2021-05-04 2021-06-04 2021-06-07 2021-06-09 2021-12-06 the сonstruction of FAP`in the Selection village Min-Bulak Bakai-Ata raijion Talas oblast (3 cycle) Page 8 IDA-VIP3-T-IC-2021-5 / Technical supervision Individual consultant for sub project of IDA / D0410 Village Investments Post Consultant Open 3,200.00 0.00 Canceled 2021-05-03 2021-06-05 2021-06-06 2021-06-08 2021-12-05 the сonstruction of FAP`in the Selection village Min-Bulak Typ rajion Issyk-Kul oblast (3 cycle) IDA-VIP3-T-IC-2021-6 / Technical supervision consultant for sub project Individual Installation of lighting on the IDA / 56010 Village Investments Post Consultant Open 2,948.00 1.00 Signed 2021-05-17 2021-05-05 2021-06-17 2021-06-30 2021-06-20 2021-06-30 2021-06-24 2021-07-01 2021-12-21 streets in villages Zher-Kazar, Selection Nizhniy-Nooruz, Druzhba Villages, Issyk-Ata Raion, Chuy Oblast IDA-VIP3-T-IC-2021-7 / Technical supervision Individual consultant for sub project of IDA / 56010 Village Investments Post Consultant Open 2,948.00 2,368.93 Signed 2021-05-17 2021-05-06 2021-06-17 2021-07-23 2021-06-20 2021-07-23 2021-06-24 2021-07-26 2021-12-21 the Construction of FAP in the Selection village Min-Bulak Bakai-Ata raijion Talas oblast IDA-VIP3-IC-2020-19 / Naryn Regional Specialist for Capacity Building of Local Individual Social Mobilization, Capacity IDA / D0410 Self-Governments and Post Consultant Open 6,000.00 4,291.43 Signed 2021-06-01 2021-05-25 2021-06-30 2021-07-26 2021-07-01 2021-07-27 2021-07-03 2021-08-02 2021-12-31 Building and Gender Communities Selection Development IDA-VIP-S-DC-21-5 / Author's supervision of the Installation of lighting on the streets in villages Zher-Kazar, IDA / D0410 Village Investments Post Direct Selection Direct 2,500.00 722.33 Signed 2021-06-01 2021-06-08 2021-06-16 2021-06-08 2021-06-19 2021-07-19 2021-12-16 Nizhniy-Nooruz, Druzhba Villages, Issyk-Ata Raion, Chuy Oblast (3 Cicle) IDA-VIP-S-DC-21-6 / Author's supervision of the Major Repair drinking water IDA / D0410 Village Investments Post Direct Selection Direct 10,700.00 2,058.40 Signed 2021-06-03 2021-06-08 2021-06-18 2021-06-09 2021-06-21 2021-07-15 2022-03-18 system in the village Jyrgalan Ak-Suu raijon Issyk-Kul oblast (3 Cicle) IDA-VIP3-IC-2021-4 / Сonsultant for the development of detailed design estimates for Individual installation of sanitary IDA / D0410 Village Investments Post Consultant Open 1,176.00 1,315.56 Signed 2021-06-15 2021-06-15 2021-07-13 2021-07-12 2021-07-13 2021-07-19 2021-07-18 2021-07-22 2021-08-17 facilities in a secondary school Selection in the villages of Santash 3- ferma, Sary-Tologoi, Ken-Suu, Baizak, Santash AO, Tyup rayon, Issyk-Kul oblast IDA-VIP3-IC-2021-6 / Сonsultant for the development of detailed design estimates for the Individual renovation of a FAP and IDA / D0410 Village Investments Post Consultant Open 1,176.00 1.14 Signed 2021-06-16 2021-06-15 2021-07-14 2021-07-13 2021-07-14 2021-07-12 2021-07-19 2021-07-22 2021-08-18 purchase of inventory in the Selection village of Ozgorush, Ozgurush AO, Bakai-Ata rayon, Talas oblast IDA-VIP3-IC-2021-7 / Сonsultant for the development of detailed design estimates for the Individual repair of sanitary facilities in IDA / D0410 Village Investments Post Consultant Open 1,176.00 825.21 Signed 2021-06-16 2021-06-15 2021-07-14 2021-07-12 2021-07-14 2021-07-22 2021-07-19 2021-07-23 2021-08-18 the secondary school in the Selection village of Kyz-Molo, Tselinniy AO, Moskovskiy rayon, Chuy oblast IDA-VIP3-IC-2021-5 / Consultant for the development of DED for the renovation of a FAP, the purchase of furniture, office Individual equipment, and the IDA / D0410 Village Investments Post Consultant Open 1,176.00 750.97 Signed 2021-06-16 2021-06-14 2021-07-14 2021-07-12 2021-07-14 2021-07-20 2021-07-19 2021-07-22 2021-08-18 installation of a water supply Selection system with sanitary facilities in a kindergarten in the village of Konorchok, Ak-Taala rayon, Naryn obl IDA-VIP3-IC-2021-8 / Technical supervision Individual consultant for sub project of IDA / D0410 Village Investments Post Consultant Open 2,948.00 4,543.90 Signed 2021-07-22 2021-08-05 2021-08-22 2021-09-06 2021-08-25 2021-09-07 2021-08-29 2021-09-08 2022-02-25 the Construction of FAP in the Selection village Ak-Bulun Tup Ragion Issyk-Kul oblast IDA-VIP3-IC-2021-9 / Technical supervision Individual consultant for sub project of IDA / D0410 Village Investments Post Consultant Open 2,948.00 0.00 Canceled 2021-07-22 2021-08-22 2021-08-25 2021-08-29 2022-02-25 the Construction of FAP in the Selection village Min-Bulak Bakai-Ata raijion Talas oblast IDA-VIP3-T-IC-2021-10 / Technical supervision Individual consultant for sub project of IDA / D0410 Village Investments Post Consultant Open 2,948.00 4,131.14 Signed 2021-08-09 2021-08-05 2021-09-08 2021-09-03 2021-09-11 2021-09-06 2021-09-16 2021-09-08 2022-03-15 the Construction of FAP in the Selection village Kaiyndy Bulak Ak-Tala raijion Naryn oblast IDA-VIP3-T-IC-2021-11 / Technical supervision Individual consultant for sub project of IDA / D0410 Village Investments Post Consultant Open 2,948.00 3,361.55 Signed 2021-08-09 2021-08-05 2021-09-08 2021-09-14 2021-09-11 2021-09-16 2021-09-16 2021-09-20 2022-03-15 the Construction of FAP in the Selection village Jar-Bashy Issyk-Ata district Chui oblast Page 9 IDA-VIP-S-DC-21-7 / Author Supervision of Construction of feldsher-obstetric station IDA / D0410 Village Investments Post Direct Selection Direct 5,325.00 2,416.83 Signed 2021-08-12 2021-09-24 2021-08-18 2021-09-27 2021-08-29 2021-12-01 2022-02-25 (FAP) in the villages Ak-Bulun, Min-Bulak, Kaindy-Bulak, Min- Bulak, Besh-kooruk, Jar-Bashy IDA-VIP3-IC-2021-10 / IDA / 56010 Project Management Post Direct Selection Direct 2,625.00 2,589.59 Signed 2021-09-22 2021-10-01 2021-09-28 2021-10-04 2021-10-01 2021-10-04 2021-12-31 Monitoring and MIS specialist Individual IDA-VIP3-T-IC-2020-5/RT1 IDA / D0410 Village Investments Post Consultant Open 5,835.00 6,429.17 Signed 2021-01-28 2021-02-01 2021-03-18 2021-03-17 2021-04-08 2021-04-13 2021-05-13 2021-04-13 2021-11-09 / Infrastructure Engineer Selection IDA-VIP3-T-IC-2021-12 / Technical supervision Individual consultant for sub project of IDA / 56010 Village Investments Post Consultant Open 2,948.00 4,670.57 Signed 2021-11-16 2021-11-19 2021-12-13 2021-12-13 2021-12-17 2021-12-13 2021-12-24 2021-12-13 2022-06-22 the Major Repair of Building Selection FAP in the Ozgorysh village Bakai-Ata district Talas oblast IDA-VIP-S-DC-21-8 / Author Supervision of Construction of Major repair of kindergarten Under IDA / 56010 Village Investments Post Direct Selection Direct 5,325.00 0.00 2021-12-07 2021-12-08 2021-12-21 2021-12-26 2022-06-24 "ALENKA" in the village Implementation Predtechenka Moscow rajion Chui oblast IDA-VIP3-AF-IC-2022-1 / Capacity Building of Local Individual Under CDSO for the Alamudun rayon IDA / D0410 Self-Governments and Post Consultant Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 Implementation of the Chui oblast Communities Selection IDA-VIP3-AF-IC-2022-2 / Capacity Building of Local Individual Under CDSO for the Zhayil rayon of IDA / D0410 Self-Governments and Post Consultant Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 Implementation the Chui oblast Communities Selection IDA-VIP3-AF-IC-2022-3 / Capacity Building of Local Individual Under CDSO for the Kemin rayon of IDA / D0410 Self-Governments and Post Consultant Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 Implementation the Chui oblast Communities Selection IDA-VIP3-AF-IC-2022-4 / Capacity Building of Local Individual Under CDSO for the Moskova rayon IDA / D0410 Self-Governments and Post Consultant Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 Implementation of the Chui oblast Communities Selection IDA-VIP3-AF-IC-2022-5 / Capacity Building of Local Individual Under CDSO for the Panfilov rayon of IDA / D0410 Self-Governments and Post Consultant Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 Implementation the Chui oblast Communities Selection IDA-VIP3-AF-IC-2022-6 / Capacity Building of Local Individual Under CDSO for the Sokuluk rayon of IDA / D0410 Self-Governments and Post Consultant Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 Implementation the Chui oblast Communities Selection IDA-VIP3-AF-IC-2022-7 / Capacity Building of Local Individual Under CDSO for the Chui rayon of IDA / D0410 Self-Governments and Post Consultant Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 Implementation the Chui oblast Communities Selection IDA-VIP3-AF-IC-2022-8 / Capacity Building of Local Individual Under CDSO for the Ysyk-Ata rayon IDA / D0410 Self-Governments and Post Consultant Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 Implementation of the Chui oblast Communities Selection IDA-VIP3-AF-IC-2022-9 / Capacity Building of Local Individual Under CDSO for the Ak-Tala rayon of IDA / 56010 Self-Governments and Post Consultant Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 Implementation the Naryn oblast Communities Selection IDA-VIP3-AF-IC-2022-10 / Capacity Building of Local Individual Under CDSO for the At-Bashy rayon IDA / D0410 Self-Governments and Post Consultant Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 Implementation of the Naryn oblast Communities Selection IDA-VIP3-AF-IC-2022-11 / Capacity Building of Local Individual Under CDSO for the Zhumgal rayon IDA / D0410 Self-Governments and Post Consultant Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 Implementation of the Naryn oblast Communities Selection IDA-VIP3-AF-IC-2022-12 / Capacity Building of Local Individual Under CDSO for the Kochkor rayon IDA / D0410 Self-Governments and Post Consultant Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 Implementation of the Naryn oblast Communities Selection IDA-VIP3-AF-IC-2022-13 / Capacity Building of Local Individual Under CDSO for the Naryn rayon of IDA / D0410 Self-Governments and Post Consultant Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 Implementation the Naryn oblast Communities Selection IDA-VIP3-AF-IC-2022-14 / Capacity Building of Local Individual Under CDSO for the Ak-Suu rayon of IDA / D0410 Self-Governments and Post Consultant Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 Implementation the Issyk-Kul oblast Communities Selection IDA-VIP3-AF-IC-2022-15 / Capacity Building of Local Individual Under CDSO for the Jeti-Oguz rayon IDA / D0410 Self-Governments and Post Consultant Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 Implementation of the Issyk-Kul oblast Communities Selection IDA-VIP3-AF-IC-2022-16 / Capacity Building of Local Individual Under CDSO for the Ton rayon of the IDA / D0410 Self-Governments and Post Consultant Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 Implementation Issyk-Kul oblast Communities Selection IDA-VIP3-AF-IC-2022-17 / Capacity Building of Local Individual Under CDSO for the Tup rayon of the IDA / D0410 Self-Governments and Post Consultant Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 Implementation Issyk-Kul oblast Communities Selection IDA-VIP3-AF-IC-2022-18 / Capacity Building of Local Individual Under CDSO for the Issyk-Kul rayon IDA / D0410 Self-Governments and Post Consultant Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 Implementation of the Issyk-Kul oblast Communities Selection IDA-VIP3-AF-IC-2022-19 / Capacity Building of Local Individual Under CDSO for the Talas rayon of IDA / D0410 Self-Governments and Post Consultant Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 Implementation the Talas oblast Communities Selection IDA-VIP3-AF-IC-2022-20 / Capacity Building of Local Individual Under CDSO for the Bakai-Ata rayon IDA / D0410 Self-Governments and Post Consultant Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 Implementation of the Talas oblast Communities Selection Page 10 IDA-VIP3-AF-IC-2022-21 / Capacity Building of Local Individual Under CDSO for the Manas rayon of IDA / D0410 Self-Governments and Post Consultant Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 Implementation the Talas oblast Communities Selection IDA-VIP3-AF-IC-2022-22 / Capacity Building of Local Individual Under CDSO for the Kara-Buura IDA / D0410 Self-Governments and Post Consultant Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 Implementation rayon of the Talas oblast Communities Selection IDA-VIP3-IC-2022-22 / Talas Regional Specialist for Capacity Building of Local Individual Under Social Mobilization, Capacity IDA / D0410 Self-Governments and Post Consultant Open 4,376.00 0.00 2022-01-19 2022-01-14 2022-02-19 2022-02-22 2022-02-28 2022-06-30 Implementation Building and Gender Communities Selection Development Capacity Building of Local Individual IDA-VIP3-AF-IC-2022-57 / Pending IDA / 56010 Self-Governments and Post Consultant Open 2,950.00 0.00 2022-02-18 2022-03-04 2022-03-07 2022-03-13 2022-06-30 Climate Change Specialist Implementation Communities Selection Page 11