Summarized Procurement Plan I. GENERAL Project information: Borrower: CCARDESA Project Name: Agricultural Productivity Program for Southern Africa Project ID No: P164486 Grant No.: Project Implementing Agency: CCARDESA Bank’s approval Date of the Procurement Plan: February 13, 2019 Date of General Procurement Notice: Period covered by this procurement plan: February 13, 2019 to September 2020 II. Goods and Works and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by IDA as stated in Appendix 1 to the Guidelines for Procurement: Thresholds for Procurement Methods and Prior Review Goods, Works and Non- Consulting Services Procurement Approaches and Methods (US$ Prior millions) Review Category Open Open Request for (US$ millions) International National Quotation (RfQ) Works ≥ 15 ≥7 < 0.2 ≤ 0.2 Goods, IT, and non- ≥6 ≥1 < 0.1 ≤ 0.1 consulting services 2. Reference to (if any) Project Operational/Procurement Manual: The Procurement Plan also forms part of the Project Implementation Manual approved on May 2019. 1 3. Procurement Packages with Methods and Time Schedule Procurement of Goods & Non-consulting Services Summary 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preference by Bank US$ million (yes/no) (Prior / Post) Summary of the ICB NIL NIL NIL NIL NIL (Works) Summary of the NCB NIL NIL NIL NIL NIL (Works) Summary of the ICB NIL NIL No NIL No major goods (Goods) Summary of the NCB NIL NIL NIL NIL NIL (Goods) Summary of the RfQ 0.03 6 No Post Request for (Goods & Non- Quotations Consulting Services) Summary of the DC 0.2million 2 No Post (Non-consulting services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines: Selection and Employment of Consultants: Thresholds for Consultants Selection Methods and Prior Review Thresholds for Consultants Selection Methods and Prior Review for Consulting Services Category Prior Short List of National Consultants (US$ million) 2 Review Consulting Engineering and (US$ Services Construction Supervision millions) Consultants (Firms) ≥4 ≤ 0.3 ≤ 0.3 Individual Consultants ≥ 0.5 NA. NA. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Guidelines: Selection and Employment of Consultants. 3. Terms of Reference (TOR) for all consultancy contracts as well as all single source selections, irrespective of the contract value, will be subject to prior review. 4. Any Other Special Selection Arrangements: N/A 5. Consultancy Assignments with Selection Methods and Time Procurement of Consulting Services Summary 1 2 3 4 5 6 Ref. No. Description of Estimated Package Review Comments Assignment Cost s by Bank (Prior / US$ million Post) Summary of NIL NIL NIL NIL contracts through CQS 3 Summary of 0.2 million 26 Post Individual Consultants (mostly contracts through peer reviewers) IC 4 PROCUREMENT Eastern and Southern Africa : Agricultural Productivity Program for Southern Africa - Angola & Lesotho PLAN General Information Country: Eastern and Southern Africa 2019-05-20 Bank’s Approval Date of the Original Procurement Plan: 2022-07-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164486 GPN Date: Project Name: Agricultural Productivity Program for Southern Africa - Angola & Lesotho Loan / Credit No: IBRD / 89170, IDA / D4150 SADC-CCARDESA Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BW-CCARDESA-99779-GO-R Project management, monit FQ / Office equipment: (comp Request for Quota Single Stage - One E IDA / D4150 oring and evaluation, and re Post Open - National 20,000.00 15,154.82 Signed 2019-06-10 2019-07-12 2019-11-21 2019-08-12 uters, printers, photocopiers, tions nvelope gional coordination laptops, Phones). Project management, monit BW-CCARDESA-99782-GO-R Request for Quota Single Stage - One E IDA / D4150 oring and evaluation, and re Post Open - National 20,000.00 15,730.64 Signed 2019-07-21 2019-09-15 2020-04-17 2020-03-13 FQ / Finance Software. tions nvelope gional coordination BW-CCARDESA-99780-GO-R Project management, monit Request for Quota Single Stage - One E FQ / Office furniture for additi IDA / D4150 oring and evaluation, and re Post Open - National 12,000.00 20,322.25 Signed 2019-06-29 2019-08-24 2019-11-26 2020-02-20 tions nvelope onal PIU staff. gional coordination Strengthening the Institution BW-CCARDESA-99776-GO-R Request for Quota Single Stage - One E IBRD / 89170 al and Enabling Environment Post Open - National 2,000.00 0.00 Canceled 2019-07-03 2019-08-28 2020-02-24 FQ / Promotional material. tions nvelope for Technology Adoption Strengthening the Institution BW-CCARDESA-99769-GO-R Request for Quota Single Stage - One E IBRD / 89170 al and Enabling Environment Post Open - National 500.00 0.00 Canceled 2019-07-13 2019-09-07 2020-03-05 FQ / Visibility Consumables. tions nvelope for Technology Adoption BW-CCARDESA-304240-GO- Strengthening the Institution Request for Quota Single Stage - One E Under Imple RFQ / Procurement of a Desig IDA / D4150 al and Enabling Environment Post Open - National 5,500.00 0.00 2022-07-26 2022-09-20 2023-03-19 tions nvelope mentation n Laptop and related Softwar for Technology Adoption es BW-CCARDESA-304243-GO- Strengthening the Institution Request for Quota Single Stage - One E Under Imple RFQ / Procurement of Brande IDA / D4150 al and Enabling Environment Post Open - National 1,500.00 0.00 2022-07-26 2022-09-20 2023-03-19 tions nvelope mentation d Clothing Material ( Shirts a for Technology Adoption nd hats) BW-CCARDESA-304248-GO- Strengthening the Institution Request for Quota Single Stage - One E Under Imple RFQ / Procurement of Brandi IDA / D4150 al and Enabling Environment Post Open - National 3,600.00 0.00 2022-07-27 2022-09-21 2023-03-20 tions nvelope mentation ng Materials( Notepads, pen for Technology Adoption drives etc) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Project management, monit BW-CCARDESA-100437-NC- Single Stage - One E IBRD / 89170 oring and evaluation, and re Post Request for Bids Open - National 167,200.00 0.00 Canceled 2019-06-10 2019-06-15 2019-06-30 2019-07-14 2019-07-24 2021-01-22 RFB / Air tickets nvelope gional coordination BW-CCARDESA-99542-NC-RF Strengthening the Institution Q / Consultant to design, prin Request for Quota Single Stage - One E IBRD / 89170 al and Enabling Environment Post Open - National 5,000.00 0.00 Canceled 2019-09-07 2019-11-02 2020-04-30 t and bind knowledge produc tions nvelope for Technology Adoption ts (visibility material). BW-CCARDESA-100452-NC- Technology Generation and IBRD / 89170 Post Direct Selection Direct 10,000.00 0.00 Canceled 2019-06-10 2019-06-17 2019-06-27 2019-12-31 DIR / Interpretation equipme Dissemination nt hire. BW-CCARDESA-251300-NC- Project management, monit Request for Quota Single Stage - One E Under Imple RFQ / Procurement of Portug IDA / D4150 oring and evaluation, and re Post Limited 10,000.00 0.00 2021-09-11 2021-11-06 2022-05-05 tions nvelope mentation uese Training gional coordination BW-CCARDESA-264531-NC- RFQ / Procurement of Flight T Strengthening the Institution Request for Quota Single Stage - One E Pending Impl ickets for APPSA Regional Pla IDA / D4150 al and Enabling Environment Post Open - National 32,000.00 0.00 2021-11-28 2022-01-23 2022-07-22 tions nvelope ementation nning Meeting in Johannesbu for Technology Adoption rg from different countries. BW-CCARDESA-264532-NC- Strengthening the Institution RFQ / Procurement of Confer Request for Quota Single Stage - One E Pending Impl IDA / D4150 al and Enabling Environment Post Open - National 9,000.00 0.00 2021-11-28 2022-01-23 2022-07-22 encing Facility for APPSA Reg tions nvelope ementation for Technology Adoption ional Planning Meeting in Joh annesburg. BW-CCARDESA-281262-NC- Project management, monit RFQ / Procurement of Confer Request for Quota Open - Internationa Single Stage - One E Pending Impl IDA / D4150 oring and evaluation, and re Post 20,000.00 0.00 2022-03-03 2022-04-28 2022-10-25 encing Facility for APPSA Scie tions l nvelope ementation gional coordination ntists Dissemination Meeting in RSA BW-CCARDESA-281263-NC- Project management, monit RFQ / Procurement of Air tick Request for Quota Single Stage - One E Pending Impl IDA / D4150 oring and evaluation, and re Post Open - National 20,000.00 0.00 2022-03-03 2022-04-28 2022-10-25 ets for PIU staff and Scientist tions nvelope ementation gional coordination s to attend Dissemination me eting in RSA BW-CCARDESA-305123-NC- RFQ / Procurement of 37 retu Strengthening the Institution rn air tickets for APPSA Angol Request for Quota Single Stage - One E Pending Impl IDA / D4150 al and Enabling Environment Post Open - National 38,700.00 0.00 2022-07-26 2022-09-20 2023-03-19 a Scientists, APPSA Lesotho S tions nvelope ementation for Technology Adoption cientists, and CCARDESA Tea m to participate in a Write sh op in RSA Page 1 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Project management, monit BW-CCARDESA-100419-CS-Q Least Cost Selecti IDA / D4150 oring and evaluation, and re Post Open - National 8,500.00 0.00 Canceled 2019-07-29 2019-09-22 2019-08-19 2019-10-02 2019-10-30 2019-11-29 2020-01-03 2020-02-07 2020-08-05 CBS / Internal Auditing. on gional coordination Project management, monit BW-CCARDESA-100416-CS-Q Least Cost Selecti IDA / D4150 oring and evaluation, and re Post Open - National 15,000.00 0.00 Canceled 2019-10-01 2019-10-09 2019-10-22 2019-12-05 2020-01-02 2020-02-01 2020-03-07 2020-04-11 2020-10-08 CBS / External Auditing. on gional coordination BW-CCARDESA-100487-CS-Q Strengthening the Institution Consultant Qualifi CBS / Consultancy services fo IDA / D4150 al and Enabling Environment Post Open - National 35,000.00 0.00 Canceled 2019-06-17 2019-07-08 2019-08-21 2019-09-20 2019-10-25 2020-04-22 cation Selection r English Language training. for Technology Adoption BW-CCARDESA-100483-CS-Q Strengthening the Institution Consultant Qualifi Open - Internationa CBS / Consultancy services fo IDA / D4150 al and Enabling Environment Post 30,000.00 0.00 Canceled 2019-06-17 2019-07-08 2019-08-21 2019-09-20 2019-10-25 2020-04-22 cation Selection l r Portuguese Language traini for Technology Adoption ng. BW-CCARDESA-178921-CS-Q CBS / The consultancy to und Technology Generation and Quality And Cost- Open - Internationa ertake an assessment of the IDA / D4150 Post 500,000.00 499,969.00 Signed 2020-07-30 2020-07-30 2020-08-20 2020-08-03 2020-10-03 2020-09-14 2020-10-31 2020-11-13 2020-11-30 2020-11-23 2021-01-04 2021-01-27 2021-02-08 2021-02-16 2022-02-08 Dissemination Based Selection l extent of digitalization of AR 4D technologies in the SADC region. BW-CCARDESA-202555-CS-L Project management, monit Least Cost Selecti Under Implement CS / The Firm to undertake e IDA / D4150 oring and evaluation, and re Post Open - National 45,000.00 0.00 2020-11-04 2020-11-02 2020-11-25 2021-01-08 2021-02-05 2021-03-07 2021-04-11 2021-05-16 2021-11-12 on ation xternal audit function for CC gional coordination ARDESA BW-CCARDESA-227496-CS-L Project management, monit CS / Engagement of the Firm Least Cost Selecti IDA / D4150 oring and evaluation, and re Post Open - National 25,000.00 21,673.13 Signed 2021-04-01 2021-04-01 2021-04-22 2021-06-05 2019-11-08 2021-07-03 2019-11-22 2021-08-02 2019-11-29 2021-09-06 2021-05-04 2021-10-11 2021-04-26 2022-04-09 to Provide Internal Audit Serv on gional coordination ices to CCARDESA INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BW-CCARDESA-99473-CS-IN Strengthening the Institution DV / Independent Reviewer Individual Consult IBRD / 89170 al and Enabling Environment Post Open 1,600.00 0.00 Canceled 2019-08-12 2019-09-19 2019-09-29 2019-10-27 2020-10-26 #1 to strengthen technical b ant Selection for Technology Adoption ackstopping in the implemen ting countries. BW-CCARDESA-99499-CS-IN Strengthening the Institution Individual Consult DV / Scoping studies Consult IDA / D4150 al and Enabling Environment Post Open 8,000.00 0.00 Canceled 2019-08-05 2019-09-23 2019-10-14 2019-11-18 2020-11-17 ant Selection ant #1. for Technology Adoption BW-CCARDESA-99481-CS-IN Strengthening the Institution DV / Independent Reviewer Individual Consult IBRD / 89170 al and Enabling Environment Post Open 1,600.00 0.00 Canceled 2019-06-14 2019-07-22 2019-08-01 2019-09-05 2020-09-04 #3 to strengthen technical b ant Selection for Technology Adoption ackstopping in the implemen ting countries. BW-CCARDESA-99479-CS-IN Strengthening the Institution DV / Independent Reviewer Individual Consult IBRD / 89170 al and Enabling Environment Post Open 1,600.00 0.00 Canceled 2019-06-21 2019-07-29 2019-08-08 2019-09-05 2020-09-04 #2 to strengthen technical b ant Selection for Technology Adoption ackstopping in the implemen ting countries. BW-CCARDESA-99567-CS-IN Project management, monit Individual Consult DV / Facilitator for the region IDA / D4150 oring and evaluation, and re Post Open 1,200.00 0.00 Canceled 2019-08-26 2019-10-14 2019-11-04 2019-12-09 2020-07-31 ant Selection al seed dialogue for 3 days. gional coordination BW-CCARDESA-99500-CS-IN Strengthening the Institution Individual Consult DV / Scoping Studies Consult IDA / D4150 al and Enabling Environment Post Open 8,000.00 0.00 Canceled 2019-07-15 2019-09-02 2019-09-23 2019-10-28 2020-10-27 ant Selection ant #2. for Technology Adoption BW-CCARDESA-99517-CS-IN Strengthening the Institution DV / Consultant to review RC Individual Consult IBRD / 89170 al and Enabling Environment Post Open 800.00 0.00 Canceled 2019-08-22 2019-10-10 2019-10-31 2019-12-05 2020-12-04 oLs communication and tech ant Selection for Technology Adoption nology dissemination strategi es. BW-CCARDESA-98228-CS-IN Technology Generation and Individual Consult DV / Facilitator fees for proje IDA / D4150 Post Open 4,000.00 2,000.00 Signed 2019-06-17 2019-06-13 2019-07-22 2019-07-03 2019-08-05 2019-07-04 2019-09-09 2019-07-04 2020-09-08 Dissemination ant Selection ct operationalization worksho p BW-CCARDESA-99574-CS-IN Project management, monit Individual Consult DV / Facilitator for the M&E tr IBRD / 89170 oring and evaluation, and re Post Open 2,000.00 0.00 Canceled 2019-06-24 2019-07-27 2019-08-03 2019-08-17 2021-02-20 ant Selection aining for scientists. gional coordination BW-CCARDESA-99375-CS-IN DV / Consultant #1 for the re Technology Generation and Individual Consult gional peer review of R&D Co IBRD / 89170 Post Open 4,000.00 0.00 Canceled 2019-07-02 2019-08-20 2019-09-10 2019-10-15 2020-04-12 Dissemination ant Selection ncept Notes and Proposals o ver 5 days respectively. BW-CCARDESA-99727-CS-IN Technology Generation and Individual Consult IBRD / 89170 Post Open 13,600.00 0.00 Canceled 2019-06-24 2019-07-23 2019-08-02 2019-09-06 2020-03-04 DV / Portuguese Interpreter Dissemination ant Selection # 2. BW-CCARDESA-99719-CS-IN Technology Generation and Individual Consult IBRD / 89170 Post Open 13,600.00 2,997.17 Signed 2019-07-01 2019-06-27 2019-07-30 2019-07-08 2019-08-09 2019-07-09 2019-09-13 2019-07-10 2020-03-11 DV / Portuguese Interpreter Dissemination ant Selection #1. BW-CCARDESA-99534-CS-IN Strengthening the Institution Individual Consult DV / Development of knowle IBRD / 89170 al and Enabling Environment Post Open 1,500.00 0.00 Canceled 2019-06-24 2019-08-12 2019-09-02 2019-10-07 2020-10-06 ant Selection dge products Consultant #3. for Technology Adoption BW-CCARDESA-99532-CS-IN Strengthening the Institution Individual Consult DV / Development of knowle IBRD / 89170 al and Enabling Environment Post Open 1,500.00 0.00 Canceled 2019-06-24 2019-08-12 2019-09-02 2019-10-07 2020-10-06 ant Selection dge products Consultant #2. for Technology Adoption BW-CCARDESA-99389-CS-IN DV / Consultant #4 for the re Technology Generation and Individual Consult gional peer review of R&D Pr IBRD / 89170 Post Open 4,000.00 0.00 Canceled 2019-07-02 2019-08-20 2019-09-10 2019-10-15 2020-04-12 Dissemination ant Selection oject Concept Notes and Pro posals, 5 days respectively. Page 2 BW-CCARDESA-99391-CS-IN DV / Consultant #6 for the re Technology Generation and Individual Consult gional peer review of R&D Pr IBRD / 89170 Post Open 4,000.00 0.00 Canceled 2019-06-17 2019-07-25 2019-08-04 2019-09-08 2020-09-07 Dissemination ant Selection oject Concept Notes and Pro posals, 5 days respectively. BW-CCARDESA-99390-CS-IN DV / Consultant #5 for region Technology Generation and Individual Consult al peer review of R&D Project IBRD / 89170 Post Open 4,000.00 0.00 Canceled 2019-07-02 2019-08-20 2019-09-10 2019-10-15 2020-04-12 Dissemination ant Selection Concept Notes and Proposals , 5 days respectively. BW-CCARDESA-99381-CS-IN DV / Consultant #2 for region Technology Generation and Individual Consult al peer review of R&D Project IBRD / 89170 Post Open 4,000.00 0.00 Canceled 2019-07-02 2019-08-20 2019-09-10 2019-10-15 2020-04-12 Dissemination ant Selection Concept Notes and Proposals , 5 days respectively. BW-CCARDESA-99503-CS-IN Strengthening the Institution Individual Consult DV / Scoping Studies Consult IDA / D4150 al and Enabling Environment Post Open 8,000.00 0.00 Canceled 2019-07-08 2019-08-26 2019-09-16 2019-10-21 2020-10-20 ant Selection ant #4. for Technology Adoption BW-CCARDESA-99502-CS-IN Strengthening the Institution Individual Consult DV / Scoping Studies Consult IDA / D4150 al and Enabling Environment Post Open 8,000.00 0.00 Canceled 2019-08-08 2019-09-26 2019-10-17 2019-11-21 2020-11-20 ant Selection ant #3. for Technology Adoption BW-CCARDESA-99530-CS-IN Strengthening the Institution Individual Consult DV / Development of knowle IBRD / 89170 al and Enabling Environment Post Open 1,500.00 0.00 Canceled 2019-07-08 2019-08-26 2019-09-16 2019-10-21 2020-10-20 ant Selection dge products Consultant #1. for Technology Adoption BW-CCARDESA-99386-CS-IN DV / Consultant #3 for the re Technology Generation and Individual Consult gional peer review for R&D P IBRD / 89170 Post Open 4,000.00 0.00 Canceled 2019-07-02 2019-08-20 2019-09-10 2019-10-15 2020-04-12 Dissemination ant Selection roject Concept Notes and Pro posal, 5 days respectively. BW-CCARDESA-117893-CS-I Project management, monit Individual Consult NDV / FINANCE OFFICER - PIU IBRD / 89170 oring and evaluation, and re Post Open 298,319.00 298,319.00 Signed 2019-06-04 2019-06-12 2019-07-15 2019-10-07 2019-07-20 2019-10-18 2019-07-30 2019-10-21 2023-07-29 ant Selection staff - 4 years contract gional coordination BW-CCARDESA-117903-CS-I Project management, monit Individual Consult NDV / Procurement Officer - IBRD / 89170 oring and evaluation, and re Post Open 298,319.00 298,319.00 Signed 2019-06-04 2019-06-27 2019-07-15 2019-10-14 2019-07-20 2019-11-15 2019-07-30 2019-11-22 2023-07-29 ant Selection PIU staff - 4 year contract gional coordination BW-CCARDESA-117905-CS-I Project management, monit Individual Consult NDV / Programme Officer - PI IBRD / 89170 oring and evaluation, and re Post Open 298,319.00 298,319.00 Signed 2019-06-04 2019-06-12 2019-07-15 2019-08-26 2019-07-20 2019-10-11 2019-07-30 2019-10-28 2023-07-29 ant Selection U Staff - 4 year contract gional coordination BW-CCARDESA-117906-CS-I Project management, monit Individual Consult NDV / Monitoring and Evaluat IDA / D4150 oring and evaluation, and re Post Open 334,131.00 334,131.00 Terminated 2019-06-04 2019-06-12 2019-07-15 2019-08-26 2019-07-20 2019-08-30 2019-07-30 2019-09-09 2023-07-29 ant Selection ion Officer - 4 year contract gional coordination BW-CCARDESA-117908-CS-I NDV / Information Communic Technology Generation and Individual Consult IBRD / 89170 Post Open 298,319.00 298,319.00 Signed 2019-06-04 2019-06-12 2019-06-26 2019-08-26 2019-07-01 2019-09-27 2019-07-11 2019-10-07 2023-07-10 ation and Knowledge Manage Dissemination ant Selection ment (ICKM) Officer - PIU staf f - 4 year contract BW-CCARDESA-217590-CS-I Project management, monit Individual Consult Under Implement NDV / Employment Contract f IDA / D4150 oring and evaluation, and re Post Open 356,406.00 0.00 2021-02-03 2021-02-04 2021-03-24 2021-04-14 2021-05-19 2021-11-15 ant Selection ation or M& E Officer gional coordination BW-CCARDESA-217598-CS-I Project management, monit Individual Consult Under Implement NDV / Employment Contract f IDA / D4150 oring and evaluation, and re Post Open 445,249.00 0.00 2021-02-03 2021-02-04 2021-03-24 2021-04-14 2021-05-19 2021-11-15 ant Selection ation or Project Coordinator gional coordination BW-CCARDESA-217615-CS-C Project management, monit DS / Consultancy for facilitati IDA / D4150 oring and evaluation, and re Post Direct Selection Direct 15,000.00 14,981.93 Signed 2021-02-08 2021-02-05 2021-02-18 2021-02-08 2021-04-24 2021-06-07 2021-10-21 ng regional write shop and e gional coordination ndorsement workshop. BW-CCARDESA-234922-CS-I Project management, monit NDV / Engagement of M&E c Individual Consult IDA / D4150 oring and evaluation, and re Post Open 12,600.00 14,000.00 Signed 2021-05-19 2021-05-17 2021-07-07 2021-07-16 2021-07-28 2021-07-20 2021-09-01 2021-07-23 2022-02-28 onsultant to Support the impl ant Selection gional coordination ementation of APPSA Region al Activities BW-CCARDESA-251935-CS-I Strengthening the Institution Individual Consult Under Implement NDV / Consultancy for Finaliz IDA / D4150 al and Enabling Environment Post Open 6,000.00 0.00 2021-09-07 2021-09-22 2021-10-26 2021-11-16 2021-12-21 2022-06-19 ant Selection ation ation of the RCol Communica for Technology Adoption tion Strategy BW-CCARDESA-264147-CS-I NDV / Engagement of an Ind Technology Generation and Individual Consult Under Implement IDA / D4150 Post Open 3,000.00 0.00 2021-11-22 2021-11-22 2022-01-10 2022-01-31 2022-03-07 2022-09-03 ependent Peer Reviewer for Dissemination ant Selection ation Production Systems and Man agement (One) BW-CCARDESA-264152-CS-I NDV / Engagement of an Ind Technology Generation and Individual Consult Under Implement IDA / D4150 Post Open 3,000.00 0.00 2021-11-22 2021-11-22 2022-01-10 2022-01-31 2022-03-07 2022-09-03 ependent Peer Reviewer for Dissemination ant Selection ation Production Systems and Man agement (Two) BW-CCARDESA-264153-CS-I NDV / Engagement of Indepe Technology Generation and Individual Consult Under Implement ndent Reviewer for Agricultur IDA / D4150 Post Open 3,000.00 0.00 2021-11-22 2021-11-22 2022-01-10 2022-01-31 2022-03-07 2022-09-03 Dissemination ant Selection ation al extension, dissemination T ransfer and Technology Prop osals BW-CCARDESA-264154-CS-I NDV / Engagement of an Ind Technology Generation and Individual Consult Under Implement ependent Reviewer for Crop IDA / D4150 Post Open 3,000.00 0.00 2021-11-22 2021-11-22 2022-01-10 2022-01-31 2022-03-07 2022-09-03 Dissemination ant Selection ation Genetic Diversity, breeding a nd Improvements Proposals ( one) BW-CCARDESA-264155-CS-I NDV / Engagement of an Ind Technology Generation and Individual Consult Under Implement ependent Reviewer for Crop IDA / D4150 Post Open 3,000.00 0.00 2021-11-22 2021-11-22 2022-01-10 2022-01-31 2022-03-07 2022-09-03 Dissemination ant Selection ation Genetic Diversity, breeding a nd Improvements Proposals ( Two) BW-CCARDESA-264156-CS-I NDV / Engagement of an Ind Technology Generation and Individual Consult Under Implement IDA / D4150 Post Open 3,000.00 0.00 2021-11-22 2021-11-22 2022-01-10 2022-01-31 2022-03-07 2022-09-03 ependent Reviewer for Post Dissemination ant Selection ation Harvest Management and Pr ocess Proposals Page 3 BW-CCARDESA-264158-CS-I NDV / Engagement of an Ind Technology Generation and Individual Consult Under Implement IDA / D4150 Post Open 3,000.00 0.00 2021-11-22 2021-11-22 2022-01-10 2022-01-31 2022-03-07 2022-09-03 ependent Reviewer for Social Dissemination ant Selection ation and Environmental Safeguar ds Proposals BW-CCARDESA-264159-CS-I NDV / Engagement of an Ind Technology Generation and Individual Consult Under Implement IDA / D4150 Post Open 3,000.00 0.00 2021-11-22 2021-11-22 2022-01-10 2022-01-31 2022-03-07 2022-09-03 ependent Reviewer for Monit Dissemination ant Selection ation oring and Evaluation Proposa ls BW-CCARDESA-280907-CS-C Project management, monit DS / Peer Review of the 8 R& Under Implement IDA / D4150 oring and evaluation, and re Post Direct Selection Direct 1,350.00 0.00 2022-02-25 2022-02-25 2022-03-07 2022-05-11 2022-11-07 D subprojects under impleme ation gional coordination ntation- Social Safety Guards BW-CCARDESA-280911-CS-C Project management, monit DS / Peer review of the 8 R& Under Implement IDA / D4150 oring and evaluation, and re Post Direct Selection Direct 1,350.00 0.00 2022-02-25 2022-02-25 2022-03-07 2022-05-11 2022-11-07 D Sub projects under implem ation gional coordination entation - Plant Breeding and Agronomy BW-CCARDESA-280914-CS-C Project management, monit DS / Peer review of the 8 R& Under Implement IDA / D4150 oring and evaluation, and re Post Direct Selection Direct 1,350.00 0.00 2022-02-25 2022-02-25 2022-03-07 2022-05-11 2022-11-07 D sub projects under implem ation gional coordination entation- Legumes BW-CCARDESA-286849-CS-I Strengthening the Institution NDV / Consultancy for Situati Individual Consult Under Implement IDA / D4150 al and Enabling Environment Post Open 15,000.00 0.00 2022-03-29 2022-04-06 2022-05-17 2022-06-07 2022-07-12 2023-01-08 on Analysis Report on Domes ant Selection ation for Technology Adoption tication of the SADC and CO MESA HSRS Page 4