PROCUREMENT PLAN (Textual Part) Project information: Solomon Islands, Solomon Islands Roads and Aviation Project (SIRAP), P166622 Project Implementation agency: The Ministry of Communication and Aviation (MCA) and the Ministry of Infrastructure Development (MID) Date of the Procurement Plan: May 2020 Period covered by this Procurement Plan: May 2020 – December 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements In accordance with paragraph 5.3 of the Procurement Regulations: not applicable. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: not applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: not applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations: not applicable. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: not applicable. Procurement Thresholds: Goods and Works and non-consulting services. Procurement Method Prior Review Comments Threshold Works (including turnkey, US$2,000,000 Contracts at or above the supply & installation of thresholds are subject to plant and equipment, and the Bank’s procurement PPP) prior review. Goods, information US$500,000 Contracts at or above the technology and non- thresholds are subject to consulting services the Bank’s procurement prior review. Force Account (FA) Only apply to All FA works subject to emergency repair prior review. works, with the total amount not exceeding US$50,000 Selection of Consultants Selection Method Prior Review Comments Threshold Consultants: firms USD$500,000 Contracts at or above the (applicable to all market thresholds are subject to approach options) the Bank’s procurement prior review. Consultants: individuals USD$300,000 Contracts at or above the (applicable to all market thresholds are subject to approach options) the Bank’s procurement prior review. PROCUREMENT Solomon Islands : Solomon Islands Roads and Aviation Project PLAN General Information Country: Solomon Islands 2018-09-03 Bank’s Approval Date of the Original Procurement Plan: 2022-08-03 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166622 GPN Date: 2018-10-23 Project Name: Solomon Islands Roads and Aviation Project Loan / Credit No: IDA / V1670, IDA / 63780, IDA / D4370 Project Support Team Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MCA-MID/RFQW/SI/A13 / Ren Component A: Honiara and Request for Quota Single Stage - One E 2020-07-0 ovations works for Control To IDA / 63780 Munda Airports Infrastructur Post Open - National 200,000.00 68,746.16 Completed 2019-11-05 2019-10-31 2020-01-10 2019-12-12 tions nvelope 8 wer e Investments Component A: Honiara and MCA-MID/QCBS/SI/A10 / Ter Request for Propo Open - Internationa Single Stage - Two E 2021-04-2 IDA / 63780 Munda Airports Infrastructur Prior 6,375,000.00 0.00 Canceled 2019-11-03 2020-03-17 2019-11-17 2020-03-18 2020-01-07 2020-05-20 2020-03-21 2020-04-25 minal Building Design & Build sals l nvelope 0 e Investments MCA-MID/RFBW/SI/B01 / Res Component B: Malaita Road Open - Internationa Single Stage - One E 2021-09-2 ealing of existing sealed secti IDA / 63780 Improvement and Maintenan Prior Request for Bids 2,932,500.00 0.00 Canceled 2020-03-01 2020-04-19 2020-06-25 2020-07-12 2020-10-02 l nvelope 7 on (Airport-Auki) (17km) ce Program MCA-MID/RFBW/SI/A01/2 / R Component A: Honiara and Open - Internationa Single Stage - One E 2021-11-2 unway Resurfacing MUN - Ru IDA / 63780 Munda Airports Infrastructur Prior Request for Bids 7,935,000.00 0.00 Canceled 2020-04-30 2020-06-18 2020-08-27 2020-11-11 2020-12-01 l nvelope 6 nway, taxiway and Apron Res e Investments urfacing Component A: Honiara and MCA-MID/RFBW/SI/A01/1 / R Open - Internationa Single Stage - One E 11,710,000.0 2021-11-2 IDA / 63780 Munda Airports Infrastructur Prior Request for Bids 0.00 Canceled 2020-04-30 2020-06-18 2020-08-27 2020-11-11 2020-12-01 unway Resurfacing HIR l nvelope 0 6 e Investments MCA-MID/RFP/SI/A10-2 / Desi Component A: Honiara and Request for Propo Single Stage - Two E 7,250,420.0 2022-11-2 gn and Build of Munda Termi IDA / 63780 Munda Airports Infrastructur Prior Limited 6,375,000.00 Signed 2020-08-02 2020-08-12 2020-08-07 2020-08-30 2020-08-21 2020-08-27 2020-12-08 2020-11-13 sals nvelope 0 8 nal e Investments Component B: Malaita Road MCA-MID/RFP/SI/B02/1 / Desi Request for Propo Open - Internationa Single Stage - Two E 2021-07-0 IDA / 63780 Improvement and Maintenan Prior 5,100,000.00 0.00 Canceled 2020-07-31 2020-08-05 2020-09-16 2021-01-03 gn and Build of Fiu bridge sals l nvelope 2 ce Program MCA-MID/RFBW/SI/A03/A01. 1/A01.2/B01 / Honiara runwa Component A: Honiara and Open - Internationa Single Stage - One E 23,727,500.0 2023-03-1 y overlay and AGL, Munda ru IDA / 63780 Munda Airports Infrastructur Prior Request for Bids 0.00 Canceled 2020-11-23 2020-11-28 2021-01-09 2021-02-08 2021-03-15 l nvelope 0 5 nway, taxiway and apron ove e Investments rlay, and Malaita road reseali ng Component B: Malaita Road MCA-MID/RFP/S-B02.1 / Desi Request for Propo Open - Internationa Single Stage - Two E 2023-06-1 IDA / 63780 Improvement and Maintenan Prior 5,100,000.00 0.00 Canceled 2021-02-20 2020-12-21 2021-02-25 2021-01-04 2021-04-08 2021-03-03 2021-07-26 gn and Build of Fiu bridge sals l nvelope 6 ce Program MCA-MID/RFBW/SI/B03/04/0 6 / Routine maintenance and Component B: Malaita Road regravelling of Malaita main r Single Stage - One E 2022-03-1 IDA / 63780 Improvement and Maintenan Prior Request for Bids Open - National 6,205,774.00 0.00 Canceled 2020-11-23 2021-03-25 2020-11-28 2021-04-06 2021-01-09 2021-05-03 2021-02-08 2021-08-30 2021-03-15 oad network (59 km), includi nvelope 0 ce Program ng Spot Upgrading for Climat e Resiliency and Road Safety Improvements MCA-MID/RFBW/SI/B02 / Upg Component B: Malaita Road rading of bridges on the Auki Open - Internationa Single Stage - One E 2022-05-2 IDA / 63780 Improvement and Maintenan Post Request for Bids 5,920,344.00 0.00 Canceled 2021-02-08 2021-03-21 2021-02-13 2021-03-27 2021-04-26 2021-05-31 -Dala section (North Road) (2 l nvelope 6 ce Program log bridges, 1 steel truss brid ge) MCA-MID/RFBW/SI/B02.1 / U pgrading of bridges on the A Component B: Malaita Road Open - Internationa Single Stage - One E 9,514,953.0 2022-07-2 uki-Dala section (North Road) IDA / 63780 Improvement and Maintenan Prior Request for Bids 5,920,344.00 Signed 2021-04-05 2021-04-16 2021-04-10 2021-04-20 2021-05-22 2021-07-29 2021-06-21 2021-10-29 2021-07-26 2021-11-22 l nvelope 0 1 (replacement of existing 2 lo ce Program g bridges and 1 steel truss br idge) Request for Bids - MCA-MID/RFBW/SI/A01.2/B0 Component A: Honiara and Open - Internationa Single Stage - One E Works (without pr 12,220,000.0 15,259,525. 2023-10-2 1 / Munda runway, taxiway a IDA / 63780 Munda Airports Infrastructur Prior Request for Bids Signed 2021-07-08 2021-06-29 2021-07-13 2021-07-07 2021-08-24 2021-09-09 2021-09-23 2021-11-05 2021-10-28 2021-12-16 l nvelope equalification) SP 0 62 8 nd apron overlay e Investments D MCA-MID/RFPW/SI/A04 / Desi Component A: Honiara and Request for Propo Open - Internationa Single Stage - Two E 2023-02-0 gn and Build of Rescue Fire S IDA / 63780 Munda Airports Infrastructur Post 1,900,000.00 0.00 Canceled 2022-03-02 2022-03-07 2022-04-18 2022-07-01 2022-08-05 sals l nvelope 1 ervices Station e Investments Component A: Honiara and MCA-MID/RFBW/S-A15 / Fligh Open - Internationa Single Stage - One E 2022-08-2 IDA / 63780 Munda Airports Infrastructur Post Request for Bids 1,100,000.00 0.00 Canceled 2021-11-01 2021-11-06 2021-12-18 2022-01-17 2022-02-21 t Service Tower l nvelope 0 e Investments MCA-MID/RFBW/SI/A03/A01. Component A: Honiara and Open - Internationa Single Stage - One E 15,900,000.0 2023-12-1 1 / Honiara runway overlay a IDA / 63780 Munda Airports Infrastructur Prior Request for Bids 0.00 Canceled 2022-03-07 2022-03-12 2022-04-23 2022-05-23 2022-06-27 l nvelope 0 9 nd AGL. e Investments MCA-MID/RFBW/SI/B03/04/0 6-2 / Routine maintenance a Request for Bids - Component B: Malaita Road nd regravelling of Malaita ma Single Stage - One E Small Works SPD Under Imple 2023-03-2 IDA / 63780 Improvement and Maintenan Post Request for Bids Open - National 2,080,000.00 0.00 2021-11-19 2022-07-18 2021-11-24 2022-07-20 2022-01-19 2022-02-18 2022-03-25 in road network (North Road nvelope (1 envelope proce mentation 0 ce Program – 17km), including Spot Upgr ss) ading for Climate Resiliency and Road Safety Improveme nts MCA-MID/RFBW/SI /B03/04/0 6-3 / Routine maintenance a Request for Bids - Component B: Malaita Road nd regravelling of Malaita ma Single Stage - One E Small Works SPD Under Revie 2023-03-2 IDA / 63780 Improvement and Maintenan Prior Request for Bids Open - National 4,670,000.00 0.00 2021-11-19 2021-11-24 2022-01-19 2022-02-18 2022-03-25 in road network (East Road - nvelope (1 envelope proce w 0 ce Program 21km), including Spot Upgra ss) ding for Climate Resiliency a nd Road Safety Improvement s SB-PST-307625-CW-DIR / Ho Component A: Honiara and Direct - Internation Other (with field f Pending Imp 2023-03-1 niara International Airport Ru IDA / D4370 Munda Airports Infrastructur Post Direct Selection 250,000.00 0.00 2022-08-04 2022-08-09 2022-09-13 al or explanation) lementation 2 nway Pavement Emergency e Investments Repair Works GOODS Page 1 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MCA-MID/RFQG/SI/C14 / 2x P Component C: Institutional S Request for Quota Single Stage - One E IDA / 63780 Post Open - National 115,000.00 100,369.74 Completed 2019-07-05 2019-09-10 2019-08-22 2019-12-09 2019-09-10 roject Vehicles trengthening tions nvelope Component A: Honiara and MCA-MID/RFQG/SI/A07/1 / A Request for Quota Open - Internationa Single Stage - One E IDA / 63780 Munda Airports Infrastructur Post 250,000.00 195,193.87 Signed 2020-02-06 2020-02-01 2020-04-23 2020-03-18 2021-02-17 DS-B Ground Stations tions l nvelope e Investments Component A: Honiara and MCA-MID/RFQG/SI/A06/2 / VS Request for Quota Open - Internationa Single Stage - One E IDA / 63780 Munda Airports Infrastructur Post 195,500.00 271,141.12 Signed 2020-07-14 2020-06-10 2020-09-18 2020-09-09 2021-02-15 AT Hardware Supply tions l nvelope e Investments MCA-MID/RFQG/SI/C2.02 / M Component C: Institutional S Request for Quota Single Stage - One E IDA / D4370 Post Limited 4,000.00 3,587.39 Completed 2020-12-11 2020-12-02 2021-02-05 2021-01-07 2021-03-07 2021-01-15 obile Data Storage Devices trengthening tions nvelope Component A: Honiara and MCA-MID/RFQG/SI/A07/2 / A Request for Quota Open - Internationa Single Stage - One E IDA / 63780 Munda Airports Infrastructur Post 57,500.00 0.00 Canceled 2021-12-06 2022-02-10 2022-03-12 2022-04-11 DS-B EQUIPAGE tions l nvelope e Investments MCA-MID/RFQG/SI/D18 / Purc Component D: Project Imple Request for Quota Single Stage - One E IDA / D4370 Post Open - National 7,500.00 6,053.95 Completed 2021-10-15 2021-11-15 2021-12-10 2022-03-17 2022-06-08 2022-03-28 hase of photocopier mentation Support tions nvelope MCA-MID/RFQG/SI/A05 / Auto Component A: Honiara and Request for Quota Open - Internationa Single Stage - One E mated Weather Observation IDA / 63780 Munda Airports Infrastructur Post 356,500.00 0.00 Canceled 2022-04-05 2022-06-09 2023-06-04 tions l nvelope Station (AWOS) e Investments Component A: Honiara and MCA-MID/RFBG/SI/A08 / Stan Open - Internationa Single Stage - One E IDA / 63780 Munda Airports Infrastructur Prior Request for Bids 764,700.00 0.00 Canceled 2022-03-20 2022-05-08 2022-07-17 2022-08-01 2022-10-20 2023-04-18 d by Generators l nvelope e Investments Component A: Honiara and MCA-MID/RFQG/SI/A12 / Pass Request for Quota Open - Internationa Single Stage - One E IDA / 63780 Munda Airports Infrastructur Post 63,250.00 0.00 Canceled 2022-04-05 2022-06-10 2022-09-08 enger Handling Equipment tions l nvelope e Investments Component A: Honiara and SB-PST-293658-GO-RFQ / AD Request for Quota Open - Internationa Single Stage - One E IDA / D4370 Munda Airports Infrastructur Post 320,000.00 0.00 Canceled 2022-05-14 2022-05-08 2022-07-09 2023-01-05 S-B Equipage tions l nvelope e Investments NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component B: Malaita Road MID/RFQNCS/S/B10 / Mobile Request for Quota Open - Internationa Single Stage - One E IDA / V1670 Improvement and Maintenan Post 100,000.00 0.00 Canceled 2018-10-08 2018-12-13 2019-04-12 mapping survey (PPA) tions l nvelope ce Program Component A: Honiara and MCA/RFQNCS/S/A15 / UXO S Request for Quota Open - Internationa Single Stage - One E IDA / V1670 Munda Airports Infrastructur Post 100,000.00 0.00 Canceled 2018-12-08 2019-02-12 2019-05-13 urvey (MUN & HNI) tions l nvelope e Investments Component A: Honiara and MCA/RFQNCS/S-A13 / UXO S Request for Quota Open - Internationa Single Stage - One E IDA / V1670 Munda Airports Infrastructur Post 115,000.00 132,099.62 Completed 2019-02-25 2019-04-30 2019-03-27 2019-10-27 2020-09-24 urvey (MUN & HIR) tions l nvelope e Investments Component A: Honiara and MCA-MID/NCS/S/A09/1 / HFW Request for Quota Open - Internationa Single Stage - One E IDA / V1670 Munda Airports Infrastructur Post 115,000.00 0.00 Canceled 2019-03-22 2019-05-27 2019-07-26 D Testing tions l nvelope e Investments Component A: Honiara and MCA-MID/NCS/S/A09/1-2 / H Request for Quota Single Stage - One E IDA / V1670 Munda Airports Infrastructur Post Limited 115,000.00 107,800.00 Terminated 2019-11-22 2019-11-11 2020-01-17 2020-01-30 2020-07-15 WFD testing tions nvelope e Investments Component A: Honiara and MCA-MID/RFQNCS/SI/A06/3 / Request for Quota Open - Internationa Single Stage - One E IDA / 63780 Munda Airports Infrastructur Post 172,500.00 146,650.29 Signed 2020-09-01 2020-08-05 2020-11-07 2020-09-25 2021-01-06 VSAT Installation tions l nvelope e Investments Component A: Honiara and MCA-MID/NCS/S/A09/1-3 / H Request for Quota Single Stage - One E IDA / 63780 Munda Airports Infrastructur Post Limited 115,000.00 0.00 Canceled 2020-06-20 2020-06-11 2020-08-15 2021-02-11 WFD Testing tions nvelope e Investments CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MCA/CQS/S/C1/04 / Airline St Component C: Institutional S Consultant Qualifi Open - Internationa IDA / V1670 Post 150,000.00 185,681.25 Completed 2018-09-03 2018-10-05 2018-09-17 2018-10-05 2018-11-23 2018-11-15 2019-01-30 2019-01-31 2019-02-28 2019-02-18 2019-06-13 2019-11-25 rategy Review trengthening cation Selection l MCA/CQS/S/C1/05 / Airport M Component C: Institutional S Consultant Qualifi Open - Internationa IDA / V1670 Post 320,000.00 398,421.25 Completed 2018-09-03 2019-02-01 2018-09-17 2018-12-21 2019-04-10 2019-01-20 2019-06-13 2019-02-28 2019-06-20 2019-06-28 2020-04-02 aster Planning Study trengthening cation Selection l MCA-MID/QCBS/S/A02/B07 / Component A: Honiara and Quality And Cost- Open - Internationa Design & Supervision for ALL IDA / V1670 Munda Airports Infrastructur Prior 3,200,000.00 0.00 Canceled 2018-09-03 2018-12-04 2018-09-03 2019-01-01 2018-11-23 2019-01-17 2019-01-17 2019-02-18 2019-03-28 2020-03-27 Based Selection l Aviation Investments, includi e Investments ng Roads MCA-MID/QCBS/S-A02/B07/A Component A: Honiara and Quality And Cost- Open - Internationa 09-2 / Design & supervision f IDA / V1670 Munda Airports Infrastructur Prior 3,795,000.00 3,767,230.98 Signed 2019-02-19 2019-03-12 2019-02-19 2019-03-29 2019-03-28 2019-05-23 2019-05-14 2019-07-02 2019-07-07 2019-08-17 2019-08-21 2019-09-24 2019-09-10 2021-09-13 Based Selection l or all Aviation Investments, i e Investments ncluding roads MCA-MID/CQS/SI/A06/1 / VSA Component A: Honiara and Consultant Qualifi Open - Internationa T Design & supervision, hub IDA / 63780 Munda Airports Infrastructur Post 207,000.00 347,870.72 Signed 2019-06-03 2019-06-24 2019-06-14 2019-07-07 2019-09-19 2019-09-09 2019-11-18 2019-11-10 2019-12-06 2019-11-11 2023-11-15 cation Selection l management e Investments Component A: Honiara and MCA-MID/CQS/SI/A13/1 / Con Consultant Qualifi Open - Internationa IDA / 63780 Munda Airports Infrastructur Post 50,000.00 75,055.39 Completed 2019-07-01 2019-07-11 2019-07-16 2019-07-18 2019-10-06 2019-08-19 2019-11-19 2019-09-09 2019-12-24 2019-09-10 2020-06-21 2020-06-15 trol Tower Adviser cation Selection l e Investments MCA-MID/QCBS/SI/C1/06 / TA Component C: Institutional S Quality And Cost- Open - Internationa IDA / 63780 Post 345,000.00 475,330.61 Signed 2019-06-25 2019-07-16 2019-09-16 2019-07-26 2019-10-15 2019-09-18 2019-11-11 2019-10-31 2019-12-02 2019-11-27 2019-12-12 2020-01-30 2019-12-31 2020-02-14 2020-11-15 : Aviation Sector Strategy trengthening Based Selection l Page 2 MCA-MID/CQS/SI/C2/04 / Add Component C: Institutional S Consultant Qualifi Open - Internationa IDA / 63780 Post 402,500.00 392,004.00 Signed 2019-12-01 2019-11-06 2019-12-22 2019-11-17 2020-02-04 2020-02-18 2020-03-05 2020-03-16 2020-06-18 2020-03-18 2023-06-03 ressing Gender Based Violen trengthening cation Selection l ce MCA-MID/CQS/SI/C2/01 / TA: Component C: Institutional S Consultant Qualifi Open - Internationa Pending Impleme Support for Planning and Ass IDA / 63780 Post 291,750.00 0.00 2022-12-01 2022-12-15 2023-03-22 2023-05-20 2023-06-18 2024-12-09 trengthening cation Selection l ntation et Management MCA-MID/CQS/SI/C1/07 / TA: Component C: Institutional S Consultant Qualifi Open - Internationa Pending Impleme IDA / 63780 Post 230,000.00 0.00 2022-12-01 2022-12-15 2023-03-20 2023-05-20 2023-06-08 2024-06-02 Technical Support to CAASI trengthening cation Selection l ntation MCA-MID/CQS/SI/C1/08 / TA: Component C: Institutional S Consultant Qualifi Open - Internationa Pending Impleme IDA / 63780 Post 115,000.00 0.00 2022-12-01 2022-12-15 2023-03-21 2023-05-20 2023-06-20 2024-06-14 Technical Support to SIACL trengthening cation Selection l ntation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MCA/INDV/S/A14 / UXO Speci Component A: Honiara and alist (Preparation of specifica IDA / V1670 Munda Airports Infrastructur Post Direct Selection Direct 35,000.00 53,015.33 Completed 2018-09-03 2018-09-05 2018-09-03 2018-09-25 2018-10-02 2018-10-11 2019-03-31 2020-11-13 tion for UXO survey and rem e Investments oval, oversight of survey) MU N & HIR MCA MID/INDV/S/D01 / Proje Component D: Project Imple Individual Consult IDA / V1670 Prior Open 750,000.00 1,096,141.29 Signed 2018-09-03 2018-09-05 2018-10-17 2018-11-06 2019-03-13 2018-11-16 2019-03-04 2020-11-05 ct Manager mentation Support ant Selection MCA MID/INDV/S/D02 / Natio Component D: Project Imple Individual Consult IDA / V1670 Post Open 150,000.00 391,999.07 Signed 2018-09-03 2018-09-12 2018-10-22 2018-10-22 2018-10-22 2018-10-30 2018-11-16 2018-10-30 2019-11-11 nal Safeguard Specialist mentation Support ant Selection MCA MID/INDV/S/D03 / Com munity Liaison Officer to dev Component D: Project Imple Individual Consult IDA / V1670 Post Open 100,000.00 0.00 Canceled 2018-09-03 2018-09-16 2018-10-22 2018-10-22 2018-11-06 2019-11-01 elop and implement a comm mentation Support ant Selection unity consultation plan MCA MID/INDV/S/D04 / Proje Component D: Project Imple Individual Consult IDA / V1670 Post Open 100,000.00 66,659.00 Completed 2018-09-03 2018-10-01 2018-09-03 2019-01-29 2018-09-13 2019-01-29 2018-09-24 2019-01-29 2019-09-19 2022-04-15 ct Accountant mentation Support ant Selection MCA MID/SS/SI/D03 / Comm Component D: Project Imple IDA / V1670 Post Direct Selection Direct 100,000.00 253,159.70 Signed 2018-09-27 2018-09-13 2018-10-07 2018-10-12 2018-11-06 2018-10-12 2019-11-01 unity Liaison Officer mentation Support Component A: Honiara and MCA/INDV/S/A10 / Airport Te Individual Consult IDA / V1670 Munda Airports Infrastructur Post Open 52,000.00 56,950.00 Completed 2019-02-01 2019-02-03 2019-03-29 2019-03-07 2019-04-19 2019-03-07 2019-05-24 2019-03-19 2019-09-01 2019-10-31 rminal Concept Design ant Selection e Investments MCA-MID/INDV/S-D05 / Admi Component D: Project Imple Individual Consult IDA / V1670 Post Open 57,500.00 71,029.33 Signed 2019-03-01 2019-03-08 2019-05-06 2019-05-23 2019-05-26 2019-05-23 2019-06-05 2019-05-23 2022-05-20 nistrative Assistant mentation Support ant Selection MCA-MID/INDV/SI/C2/03 / TA: Component C: Institutional S Individual Consult IDA / 63780 Post Open 115,000.00 73,587.50 Signed 2019-11-01 2019-12-05 2020-01-05 2020-02-27 2020-01-14 2020-02-27 2020-01-25 2020-02-27 2021-07-18 Road Safety trengthening ant Selection Component B: Malaita Road MCA-MID/INDV/SI/B05 / Tech Individual Consult IDA / 63780 Improvement and Maintenan Post Open 115,000.00 0.00 Canceled 2019-07-01 2019-08-15 2019-09-05 2019-09-16 2019-09-25 2021-09-14 nical Auditor ant Selection ce Program MCA-MID/INDV/SI/C2/02 / TA: Component C: Institutional S Individual Consult IDA / 63780 Post Open 86,250.00 0.00 Canceled 2019-11-01 2020-01-06 2020-01-16 2020-01-27 2021-01-21 Improving Project Manageme trengthening ant Selection nt MCA-MID/INDV/SI/D17 / Perio Component D: Project Imple Individual Consult IDA / 63780 Post Direct 9,520.00 0.00 Canceled 2020-02-16 2020-02-26 2020-03-18 2020-04-22 2021-04-17 dic Procurement Specialist mentation Support ant Selection MCA-MID/INDV/SI/D12 / Cont Component D: Project Imple Individual Consult IDA / 63780 Post Open 16,800.00 0.00 Canceled 2020-02-16 2020-02-20 2020-04-05 2020-04-26 2020-05-31 2021-06-13 ract Management Specialist mentation Support ant Selection MCA-MID/INDV/SI/D18 / Econ Component D: Project Imple Individual Consult IDA / 63780 Post Open 42,000.00 0.00 Canceled 2020-03-02 2020-04-20 2020-05-11 2020-06-15 2021-06-30 omist & Financial Specialist mentation Support ant Selection MCA-MID/INDV/SI/D17.1 / Na Component D: Project Imple Individual Consult IDA / 63780 Post Open 30,000.00 122,016.49 Signed 2020-04-30 2020-06-17 2020-06-18 2020-09-10 2020-07-09 2020-09-10 2020-08-13 2020-09-25 2021-02-09 tional Procurement Specialist mentation Support ant Selection MCA-MID/INDV/SI/A05 / Com Component D: Project Imple Individual Consult IDA / 63780 Post Open 50,000.00 41,141.70 Signed 2020-06-30 2020-06-16 2020-08-18 2020-07-01 2020-09-08 2020-08-03 2020-10-13 2020-08-04 2021-04-11 munications Adviser mentation Support ant Selection MCA-MID/DS/S-C1.09 / TA: S Component C: Institutional S olomon Airlines Strategic Pla IDA / 63780 Post Direct Selection Direct 70,000.00 91,253.75 Signed 2021-11-10 2021-11-12 2021-11-20 2021-11-16 2022-01-13 2021-11-22 2022-04-13 trengthening nning Workshop SB-PST-278983-CS-INDV / N Component D: Project Imple Individual Consult IDA / D4370 Post Open 110,000.00 89,250.02 Signed 2022-02-21 2022-03-08 2022-04-11 2022-04-10 2022-05-02 2022-04-13 2022-06-06 2022-04-18 2022-12-03 ational Finance Manager mentation Support ant Selection SB-PST-282373-CS-INDV / N Component D: Project Imple Individual Consult IDA / D4370 Post Open 45,000.00 44,568.00 Signed 2022-03-11 2022-03-08 2022-04-29 2022-04-03 2022-05-20 2022-04-13 2022-06-24 2022-04-24 2022-12-21 ational Project Manager mentation Support ant Selection SB-PST-282374-CS-INDV / Int Component D: Project Imple Individual Consult IDA / D4370 Post Open 190,000.00 0.00 Canceled 2022-03-11 2022-03-08 2022-04-29 2022-04-05 2022-05-20 2022-04-13 2022-06-24 2022-12-21 ernational Project Manager mentation Support ant Selection MCA-MID/INDV/SI/C1/01 / TA: Component C: Institutional S Individual Consult Pending Impleme IDA / 63780 Post Open 57,500.00 0.00 2022-03-11 2022-05-17 2022-05-26 2022-06-07 2022-10-05 Training Needs Analysis trengthening ant Selection ntation SB-PST-291884-CS-INDV / Pr Component D: Project Imple Individual Consult IDA / D4370 Post Open 60,000.00 47,008.20 Signed 2022-04-27 2022-05-04 2022-06-15 2022-06-22 2022-07-06 2022-07-01 2022-08-10 2022-07-01 2023-02-06 oject Accountant mentation Support ant Selection SB-PST-282374-CS-INDV-2 / I Component D: Project Imple Individual Consult Under Implement nternational Project Manager IDA / D4370 Post Open 190,000.00 0.00 2022-06-30 2022-06-30 2022-08-18 2022-09-08 2022-10-13 2023-04-11 mentation Support ant Selection ation (retender) Component A: Honiara and SB-PST-307623-CS-INDV / Ai Individual Consult Direct - Internation Pending Impleme IDA / D4370 Munda Airports Infrastructur Post 30,000.00 0.00 2022-08-04 2022-08-14 2022-09-04 2022-10-09 2023-04-07 rport Pavement Specialist ant Selection al ntation e Investments Page 3