The World Bank Implementation Status & Results Report Santa Cruz Road Corridor Connector Project (San Ignacio - San Jose) (P152281) Santa Cruz Road Corridor Connector Project (San Ignacio - San Jose) (P152281) LATIN AMERICA AND CARIBBEAN | Bolivia | Transport Global Practice | IBRD/IDA | Investment Project Financing | FY 2017 | Seq No: 10 | ARCHIVED on 03-Aug-2022 | ISR52142 | Implementing Agencies: Administradora Boliviana de Carreteras (ABC), Plurinational State of Bolivia Key Dates Key Project Dates Bank Approval Date: 11-Jan-2017 Effectiveness Date: 21-Dec-2017 Planned Mid Term Review Date: 30-Sep-2020 Actual Mid-Term Review Date: 30-Sep-2020 Original Closing Date: 31-Dec-2021 Revised Closing Date: 30-Nov-2023 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective (PDO) is to improve transport accessibility along the road corridor between San Ignacio de Velasco and San Jose de Chiquitos. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Road Upgrading:(Cost $225.05 M) Technical Studies and Project Management:(Cost $5.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Unsatisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Unsatisfactory Moderately Unsatisfactory Overall Risk Rating Moderate Moderate Implementation Status and Key Decisions Civil works to upgrade the San Ignacio–San Jose road started on the ground in September 2019. After the suspension of civil works due to the COVID-19 pandemic, the contractor restarted the works and progressively increased the pace of execution. The physical progress was 24 percent as of April 2022. The procurement of feasibility and technical design studies for the San Ignacio–San Matias road section has been completed, and the selected consulting firm has started the work and is expected to be concluded by November 2023. 8/3/2022 Page 1 of 7 The World Bank Implementation Status & Results Report Santa Cruz Road Corridor Connector Project (San Ignacio - San Jose) (P152281) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Moderate Moderate Moderate Macroeconomic Moderate Moderate Moderate Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Moderate Moderate Moderate Institutional Capacity for Implementation and High Moderate Moderate Sustainability Fiduciary Substantial Substantial Substantial Environment and Social Substantial Substantial Substantial Stakeholders Moderate Moderate Moderate Other -- Moderate Moderate Overall Substantial Moderate Moderate Results PDO Indicators by Objectives / Outcomes Improve transport accessibility along the San Ignacio-San Jose road corridor IN01161513 ►Travel time along the project area (Hours, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 5.00 4.62 4.62 2.50 Date 16-Dec-2015 08-Apr-2019 08-Apr-2019 29-Dec-2023 IN01161514 ►Vehicle Operating Cost - Cars (Amount(USD), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.37 0.33 0.33 0.21 Date 16-Dec-2015 08-Apr-2019 08-Apr-2019 29-Dec-2023 IN01161515 ►Vehicle Operating Cost - Trucks (Amount(USD), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 2.50 2.39 2.39 1.60 8/3/2022 Page 2 of 7 The World Bank Implementation Status & Results Report Santa Cruz Road Corridor Connector Project (San Ignacio - San Jose) (P152281) Date 16-Dec-2015 08-Apr-2019 08-Apr-2019 29-Dec-2023 Overall Comments PDO As the road is currently under construction, the on-site measurement of these indicators can only be done at their conclusion. The intermediate values indicated are theoretical values evaluated by simulation with HDM-4. Intermediate Results Indicators by Components Road Upgrading IN01161526 ►Roads constructed, non-rural (Kilometers, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 7.00 208.00 Date 31-Dec-2015 24-Dec-2021 31-May-2022 30-Nov-2023 The first 7 km of paved roads have been constructed. Intermediate and end targets were updated in this Comments: ISR. Technical Studies and Project Management IN01161527 ►DBMOT bid documents prepared for San Matias - San Ignacio de Velasco road (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 31-Dec-2015 24-Dec-2021 24-Dec-2021 31-Dec-2021 The consulting firm for this study was hired, and the works are ongoing. However, as decided by ABC, the DBMOT modality is no longer contemplated for this road. This indicator needs to be updated to reflect this Comments: change. IN01161528 ►Direct project beneficiaries (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 125,000.00 125,000.00 125,000.00 135,325.00 Date 31-Dec-2015 08-Apr-2019 30-May-2022 29-Dec-2023 This indicator hasn´t been updated by the client recently. Comments: IN01161529 Female beneficiaries (Percentage, Corporate Supplement) Baseline Actual (Previous) Actual (Current) End Target 8/3/2022 Page 3 of 7 The World Bank Implementation Status & Results Report Santa Cruz Road Corridor Connector Project (San Ignacio - San Jose) (P152281) Value 50.00 50.00 50.00 50.00 IN01161530 ►Road users satisfied with quality of roads disaggregated by gender and user mode (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 11.30 11.30 11.30 70.00 Date 31-Dec-2015 08-Apr-2019 08-Apr-2019 29-Dec-2023 This indicator has not been measured recently. Comments: IN01161531 Road Users Satisfaction - Male Passengers (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 17.00 17.00 17.00 70.00 Date 31-Dec-2015 08-Apr-2019 08-Apr-2019 29-Dec-2023 IN01161532 Road Users Satisfaction - Female Passengers (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 12.00 12.00 12.00 70.00 Date 31-Dec-2015 08-Apr-2019 08-Apr-2019 29-Dec-2023 IN01161533 Road Users Satisfaction - Male Drivers (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 6.00 6.00 6.00 70.00 Date 31-Dec-2015 08-Apr-2019 08-Apr-2019 29-Dec-2023 IN01161534 ►Social Inclusion and Gender (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 11-Jul-2016 08-Apr-2019 30-May-2022 30-Jun-2023 The indicator is partially completed.  100% of workers have been trained on Gender, Gender-Based Violence, prevention of STD- HIV/AIDS.  The works on the 4 wells for access to drinking water have been delayed. The latter must be carried out within the framework of the PPI. Comments:  Regarding the training of the Ayoreo community, the delegates from each community to be trained have been elected by each of the 3 communities of the Santa Teresita TCO and the San Jose settlement, however, they have not yet received training. In this sense, the indicator has not made any progress. IN01161535 8/3/2022 Page 4 of 7 The World Bank Implementation Status & Results Report Santa Cruz Road Corridor Connector Project (San Ignacio - San Jose) (P152281) Improvement of access to water in indigenous communities (Text, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 4.00 Date 11-Jul-2016 08-Apr-2019 08-Apr-2019 30-Jun-2023 IN01161536 Training of construction workers on gender, gender based violence prevention and HIV/AIDS/STD (Text, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0% 64,7% 100% 100% Date 11-Jul-2016 24-Dec-2021 30-May-2021 30-Jun-2023 IN01161537 Ayoreo women and men trained on HIV/AIDS/STD and Tuberculosis prevention, working in their communities. (Text, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 10.00 Date 11-Jul-2016 31-Dec-2021 31-Dec-2021 29-Dec-2023 IN01161538 ►iRAP surveys completed showing any trends/improvements in road safety along the corridor (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 31-Dec-2015 08-Apr-2019 08-Apr-2019 30-Dec-2022 It is likely that IRAP surveys won't be implemented. Thid indicator needs to be updated. Comments: IN01161539 ►Traffic accidents on the San Ignacio de Velasco - San Jose de Chiquitos road corridor reported (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 03-Aug-2016 07-Dec-2020 30-May-2022 29-Dec-2023 ABC continues to report the accidents on the road corridor. Comments: Overall Comments IR Comments for each indicator are provided in the corresponding section each section. As reported in the previous ISR and in the specific comments of each indicator, some of them would need to be updated. This request was not addressed by the GoB. Performance-Based Conditions 8/3/2022 Page 5 of 7 The World Bank Implementation Status & Results Report Santa Cruz Road Corridor Connector Project (San Ignacio - San Jose) (P152281) Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P152281 IBRD-86480 Effective USD 200.00 200.00 0.00 46.17 153.83 23% P152281 IDA-59030 Effective USD 30.00 30.00 0.00 12.49 17.51 42% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P152281 IBRD-86480 Effective 11-Jan-2017 02-Feb-2017 21-Dec-2017 31-Dec-2021 30-Nov-2023 P152281 IDA-59030 Effective 11-Jan-2017 02-Feb-2017 21-Dec-2017 31-Dec-2021 30-Nov-2023 Cumulative Disbursements Restructuring History Level 2 Approved on 21-Dec-2021 Related Project(s) 8/3/2022 Page 6 of 7 The World Bank Implementation Status & Results Report Santa Cruz Road Corridor Connector Project (San Ignacio - San Jose) (P152281) There are no related projects. 8/3/2022 Page 7 of 7