PROCUREMENT PLAN (Textual Part) Project information: Tonga, Climate Resilience Project P161539 Project Implementation agency: Ministry of Infrastructure Date of the Procurement Plan: March 12, 2018 Period covered by this Procurement Plan: [March – December] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in N/A, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). N/A Goods: is not applicable Works: is not applicable Hands-on Expanded Implementation Support (HEIS) N/A Other Relevant Procurement Information. The project is proposed as an Agile Project covered by the Agile Pilots waiver memorandum issued by the World Bank’s Senior Vice President, Operations. The request to have this initiation memorandum instead of a project concept note and a concept review meeting has been approved by the Practice Manager of the Task Team Leader and by OPCS Vice-Presidency on December 4, 2017. Estimated Activity Reference Review Market Category Amount No. / Description: Type Approach (US$) MOI/TCRTPPST/IC06B Consultant / Social Safeguards Post Open 35,000.00 Services Specialist MOI/TCRRPPST/IC06A / Environment Consultant Post Open 45,000.00 Safeguards Services Specialist MOI/TCRTPPST/IC06C Consultant / Local Safeguards Post Open 20,000.00 Services Specialist MOI/TCRTO-PST/SSS- Consultant Post Direct 79,697.00 01 / Project Manager Services MOI/TCRTP-PST/SSS- Consultant 02 / Contracts Post Direct 39,223.00 Services Manager MOI/TCRTP-PST/SSS- Consultant 03 / Project Post Direct 26,213.00 Services Accountant MOI/TCRTP-PST/SSS- Consultant 04 / Procurement Post Direct 27,606.00 Services Officer MOI/TCRTP-PST/SSS- Consultant 05 / Administrative Post Direct 14,290.00 Services Assistance Estimated Activity Reference Review Market Category Amount No. / Description: Type Approach (US$) MOI/TCRTP-LTD/CF- 07 / Feasibility Study, Detail Engineering Design Bid Evaluation and Consultant Open - Prior 500,000.00 Construction Services International Supervision of Tongatapu and Outer Island Roads Works in Tonga TAL/TCRTP/CF-08 / Design, Procurement and Supervision Services: Consultant Open - Post 150,000.00 Resurfacing of Services International Runway at Salote Pilolevu Airport, Ha'apai, Tonga PROCUREMENT Tonga : Tonga Climate Resilient Transport Project PLAN General Information Country: Tonga Bank’s Approval Date of the Original Procurement Plan: 2018-03-12 2021-11-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161539 GPN Date: 2018-03-22 Project Name: Tonga Climate Resilient Transport Project Loan / Credit No: IDA / D3890, / M Executing Agency(ies): inistry of Infrastructure WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOI-WK-1 / Resurfacing Component 2: Climate Single Stage - One 4,077,720.9 2019-11- works on the Ha'apai Airport IDA / D3890 Resilient Infrastructure Prior Request for Bids Open - International Signed 2019-04-01 2019-11-27 2019-04-06 2019-12-02 2019-05-18 2020-02-10 2019-06-17 2020-04-22 2019-07-22 2020-08-03 Envelope 0 19 Runway Solutions MOI-WK-2 / Port works in Component 2: Climate Single Stage - One 2019-09- the outer islands: Lot 1 Eua IDA / D3890 Resilient Infrastructure Prior Request for Bids Open - National 0.00 Canceled 2018-10-15 2019-01-09 2018-10-30 2019-01-10 2019-01-14 2019-03-05 2019-02-13 2019-03-20 2019-03-20 Envelope 16 Lot 2: Niuas Solutions MOI-WK-2-2 / Port Works in Component 2: Climate Single Stage - One 2,317,999.9 2020-03- the Outer Island: Lot No. 1 IDA / D3890 Resilient Infrastructure Prior Request for Bids Open - National Signed 2019-04-29 2019-04-30 2019-05-06 2019-05-08 2019-05-27 2019-06-13 2019-06-17 2020-02-05 2019-07-29 2020-01-24 Envelope 2 29 Eua and Lot No. 2 Niuas Solutions MOI-WK-3-PB-1 / Rehabilitation and Upgrade Component 2: Climate Single Stage - One 3,076,953.2 2025-09- and Routine Maintenance of IDA / D3890 Resilient Infrastructure Prior Request for Bids Open - National Signed 2020-04-20 2020-08-13 2020-05-11 2020-08-21 2020-06-22 2020-09-30 2020-08-21 2021-01-11 2020-09-29 2021-04-26 Envelope 7 28 Priority Roads in Vava'u North Solutions West MOI-WK-3-PB-2 / Rehabilitation and Upgrade Component 2: Climate Single Stage - One 2025-08- and Routine Maintenance of IDA / D3890 Resilient Infrastructure Post Request for Bids Open - National 0.00 Canceled 2020-04-20 2020-08-06 2020-05-11 2020-06-22 2020-09-30 2020-07-23 2021-05-20 2020-08-31 Envelope 30 Priority Roads in Vava'u South Solutions West MOI-WK-3-PB-3 / Rehabilitation of Priority Component 2: Climate Single Stage - One 3,428,071.2 2025-10- Roads and Network Wide IDA / D3890 Resilient Infrastructure Post Request for Bids Open - National Signed 2020-05-20 2020-08-06 2020-06-10 2020-07-22 2020-09-30 2020-09-20 2021-01-11 2020-10-29 Envelope 0 28 Performance Based Solutions Maintenance (PBM-3), 'Eua MOI-WK-3-TR-C2 / Component 2: Climate Under Single Stage - One 2024-02- Rehabilitation and Upgrading IDA / D3890 Resilient Infrastructure Prior Request for Bids Open - National 0.00 Implementat 2020-10-19 2021-06-16 2020-11-09 2021-06-27 2020-12-18 2021-01-15 2021-02-23 Envelope 23 of Priority Roads in Tongatapu Solutions ion MOI-WK-3-TR-C1 / Component 2: Climate Single Stage - One 2023-08- Rehabilitation and Upgrading IDA / D3890 Resilient Infrastructure Prior Request for Bids Open - International 0.00 Canceled 2020-10-19 2020-11-09 2020-12-18 2021-01-15 2021-02-23 Envelope 25 Road Works on Tongatapu Solutions MOI-WK-3-TRC-1 / Component 2: Climate Rehabilitation and Upgrading Single Stage - One 2021-11- IDA / D3890 Resilient Infrastructure Prior Request for Bids Open - International 0.00 Canceled 2021-01-29 2021-02-03 2021-03-17 2021-04-16 2021-05-21 Road Works on Tongatapu Envelope 17 Solutions Liku Road MOI-WK-3-PB-2-2 / Request for REHABILITATION OF ROAD Component 2: Climate Bids - Small Under SECTIONS V2 & V12 AND Single Stage - One 2027-03- IDA / D3890 Resilient Infrastructure Prior Request for Bids Open - National Works SPD (1 0.00 Implementat 2021-09-15 2021-09-14 2021-10-25 2021-10-28 2021-12-06 2022-01-25 2022-03-11 MAINTENANCE SERVICES OF Envelope 10 Solutions envelope ion ROADS IN SOUTH WEST, process) VAVA'U Request for MOI-WK2-01 / Rehabilitation Component 2: Climate Bids - Small Pending Single Stage - One 2024-11- of Liku Road (Fua'amotu - IDA / D3890 Resilient Infrastructure Prior Request for Bids Open - National Works SPD (1 0.00 Implementat 2022-03-15 2022-04-18 2022-05-18 2022-07-13 2022-09-27 Envelope 08 'Utulau) Tongatapu 3 Lots Solutions envelope ion process) Request for MOI-WK-2-3 / Safety Component 2: Climate Bids - Small Pending Single Stage - One 2022-11- Improvement Works at Futu IDA / D3890 Resilient Infrastructure Post Request for Bids Open - National Works SPD (1 0.00 Implementat 2021-12-17 2022-01-01 2022-02-12 2022-03-25 2022-05-06 Envelope 02 Port, Niuafo'ou Solutions envelope ion process) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOI-GO-1 / Transport Sector Component 3: Strengthening Request for Single Stage - One / Post Limited 0.00 Canceled 2019-10-06 2019-12-01 2020-01-30 Safety Campaign the Enabling Environment Quotations Envelope MOI-GO-2 / Laboratory Component 3: Strengthening Request for Single Stage - One IDA / D3890 Post Limited 100,290.32 Signed 2019-08-24 2019-12-02 2019-11-02 2019-12-31 2020-01-31 Testing Equipment the Enabling Environment Quotations Envelope NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 MOI/TCRTP-LTD/CF-07 / Feasibility Study, Detail Engineering Design Bid Component 2: Climate Quality And Cost- Evaluation and Construction IDA / D3890 Resilient Infrastructure Prior Open - International 2,625,579.57 Under Review 2018-03-08 2018-03-08 2018-05-16 2018-03-23 2018-05-18 2018-05-04 2018-08-06 2018-05-18 2018-09-05 2018-06-01 2018-11-26 2018-06-15 2018-12-13 2020-12-14 Based Selection Supervision of Tongatapu and Solutions Outer Island Roads Works in Tonga Consultant MOI-CS-FIRM-4 / Obstacle Component 1: Sectoral and IDA / D3890 Post Qualification Open - International 0.00 Canceled 2019-04-01 2019-03-18 2019-04-22 2019-06-05 2019-07-05 2019-08-09 2020-02-05 Limitation Study - Eua Airport Spatial Planning Tools Selection MOI-CS-FIRM-5 / Consultant Vulnerability Assessment of Component 1: Sectoral and / Post Qualification Open - International 0.00 Canceled 2018-10-15 2019-04-12 2018-11-05 2019-05-01 2018-12-19 2019-01-18 2019-02-22 2019-08-21 Road Networks in Outer Spatial Planning Tools Selection Islands TAL/TCRTP/CF-08 / Design, Procurement and Supervision Component 2: Climate Quality And Cost- Services: Resurfacing of IDA / D3890 Resilient Infrastructure Post Open - International 342,247.86 Signed 2018-03-08 2017-12-05 2018-03-20 2019-04-09 2018-04-17 2018-06-21 2018-05-15 2018-08-01 2018-05-29 2018-08-22 2018-06-12 2018-09-13 2018-06-26 2018-11-20 2019-09-24 Based Selection Runway at Salote Pilolevu Solutions Airport, Ha'apai, Tonga Component 2: Climate Consultant MOI-CS-FIRM-7 / Detailed IDA / D3890 Resilient Infrastructure Post Qualification Open - National 0.00 Canceled 2019-10-01 2019-10-22 2019-12-05 2020-01-04 2020-02-08 2020-04-28 Design for Road Safety Works Solutions Selection MOI-CS-FIRM-1 / Component 2: Climate Consultant Supervision of Safety IDA / D3890 Resilient Infrastructure Post Qualification Open - National 112,791.13 Signed 2018-10-16 2019-01-02 2018-11-06 2019-04-11 2018-12-20 2019-01-15 2019-01-19 2019-03-29 2019-02-23 2019-04-17 2019-08-22 Improvement Works in Eua Solutions Selection Port MOI-CS-FIRM-2 / Component 2: Climate Consultant Supervision of Safety IDA / D3890 Resilient Infrastructure Post Qualification Open - National 144,967.23 Signed 2018-10-15 2018-01-02 2018-11-05 2019-04-11 2018-12-19 2019-01-15 2019-01-18 2019-03-28 2019-02-22 2019-04-23 2019-08-21 Improvement Works in Solutions Selection Niuatoputapu Port MOI-CS-FIRM-5-2 / Vulnerability assessment of Component 1: Sectoral and Quality And Cost- IDA / D3890 Post Open - International 383,635.66 Signed 2019-07-10 2019-07-10 2019-07-31 2019-09-13 2019-08-22 2019-10-11 2019-10-04 2019-11-10 2019-11-15 2019-12-15 2019-12-12 2020-01-19 2019-12-20 2021-01-18 the road networks in Vavau Spatial Planning Tools Based Selection and Eua MOI-CS-FIRM-8 / Active Consultant Component 1: Sectoral and Transportation Opportunities IDA / D3890 Post Qualification Open - International 0.00 Canceled 2021-07-01 2021-07-22 2021-09-04 2021-10-04 2021-11-08 2022-05-07 Spatial Planning Tools Study Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual MOI/TCRTO-PST/SSS-01 / Component 3: Strengthening IDA / D3890 Post Consultant Direct 48,418.45 Completed 2018-04-02 2018-05-18 2018-04-12 2018-05-18 2018-05-03 2018-05-23 2018-06-07 2018-06-15 2018-12-04 2019-02-28 Project Manager the Enabling Environment Selection Individual MOI/TCRTP-PST/SSS-02 / Component 3: Strengthening IDA / D3890 Post Consultant Direct 23,866.82 Completed 2018-04-02 2018-05-16 2018-04-12 2018-05-18 2018-05-03 2018-05-23 2018-06-07 2018-06-15 2018-12-04 2019-02-28 Contracts Manager the Enabling Environment Selection Individual MOI/TCRTP-PST/SSS-03 / Component 3: Strengthening IDA / D3890 Post Consultant Direct 15,925.57 Completed 2018-04-02 2018-05-16 2018-04-12 2018-05-18 2018-05-03 2018-05-22 2018-06-07 2018-06-15 2018-12-04 2019-02-28 Project Accountant the Enabling Environment Selection Individual MOI/TCRTP-PST/SSS-04 / Component 3: Strengthening IDA / D3890 Post Consultant Direct 15,950.65 Completed 2018-04-02 2018-05-18 2018-04-12 2018-05-18 2018-05-03 2018-05-23 2018-06-07 2018-06-15 2018-12-04 2019-02-28 Procurement Officer the Enabling Environment Selection Individual MOI/TCRTP-PST/SSS-05 / Component 3: Strengthening IDA / D3890 Post Consultant Direct 8,681.82 Completed 2018-04-02 2018-05-16 2018-04-12 2018-05-18 2018-05-03 2018-05-23 2018-06-07 2018-06-15 2018-12-04 2019-02-28 Administrative Assistance the Enabling Environment Selection Individual MOI/TCRTPPST/IC06B / / Post Consultant Open 0.00 Canceled 2018-03-20 2018-01-29 2018-04-17 2018-04-24 2018-05-02 2018-09-09 Social Safeguards Specialist Selection MOI/TCRRPPST/IC06A / Individual Environment Safeguards / Post Consultant Open 0.00 Canceled 2018-03-22 2018-04-19 2018-04-26 2018-05-04 2018-09-11 Specialist Selection Individual MOI/TCRTPPST/IC06C / Local / Post Consultant Open 0.00 Canceled 2018-03-20 2018-04-17 2018-04-24 2018-05-02 2018-08-09 Safeguards Specialist Selection Individual MOI/TCRTPPST/IC06B/2 / Component 3: Strengthening IDA / D3890 Post Consultant Limited 33,656.00 Completed 2018-03-22 2018-01-29 2018-03-27 2018-03-02 2018-04-17 2018-03-13 2018-05-22 2018-04-27 2018-09-19 2018-07-30 Social Safeguards Specialist the Enabling Environment Selection MOI/TCRRPPST/IC06A /2 / Individual Component 3: Strengthening Environment Safeguards IDA / D3890 Post Consultant Limited 42,323.60 Completed 2018-03-22 2018-01-29 2018-03-27 2018-03-02 2018-04-17 2018-04-27 2018-05-22 2018-04-27 2018-09-19 2018-07-30 the Enabling Environment Specialist Selection MOI/TCRTP/IC-09 / Individual Component 3: Strengthening International Technical IDA / D3890 Post Consultant Limited 28,443.23 Completed 2018-07-24 2018-06-11 2018-07-29 2018-07-17 2018-08-19 2018-08-22 2018-09-23 2018-07-24 2019-01-21 2018-11-26 the Enabling Environment Adviser (Procurement - Selection Roads) MOI/TCRTP/IC-10 / Gender Individual Component 3: Strengthening and Gender Based Violence IDA / D3890 Post Consultant Limited 7,200.00 Completed 2018-07-24 2018-07-09 2018-07-29 2018-07-06 2018-08-19 2018-08-31 2018-09-23 2018-08-31 2018-10-23 2018-09-30 the Enabling Environment Consultant Selection Individual MOI-CS-INDV-1 / Project Component 3: Strengthening / Post Consultant Open 0.00 Canceled 2018-10-22 2018-12-10 2018-12-31 2019-02-04 2021-03-28 Manager the Enabling Environment Selection Individual MOI-CS-INDV-2 / Contracts Component 3: Strengthening IDA / D3890 Post Consultant Open 116,606.91 Signed 2018-10-22 2019-02-01 2018-12-10 2019-02-04 2018-12-31 2019-06-03 2019-02-04 2019-06-28 2021-03-28 Manager the Enabling Environment Selection Page 2 Individual MOI-CS-INDV-3 / Component 3: Strengthening IDA / D3890 Post Consultant Open 111,523.90 Signed 2018-10-22 2019-04-01 2018-12-10 2019-07-02 2018-12-31 2019-07-08 2019-02-04 2019-07-12 2021-03-28 Procurement Officer the Enabling Environment Selection Individual MOI-CS-INDV-4 / Component 3: Strengthening IDA / D3890 Post Consultant Open 92,857.93 Signed 2018-10-22 2018-12-14 2018-12-10 2019-02-04 2018-12-31 2019-03-11 2019-02-04 2019-02-18 2021-03-28 Accountant the Enabling Environment Selection Individual MOI-CS-INDV-5 / Component 3: Strengthening IDA / D3890 Post Consultant Open 16,533.72 Completed 2018-10-22 2018-12-16 2018-12-10 2019-02-15 2018-12-31 2019-02-15 2019-02-04 2019-02-22 2021-03-28 2020-04-14 Administrative Assistant the Enabling Environment Selection MOI-CS-INDV-6 / Individual Component 3: Strengthening Communications and M & E / Post Consultant Open 52,188.00 Completed 2019-03-01 2018-12-16 2019-04-19 2019-02-28 2019-05-10 2019-02-28 2019-06-14 2019-03-01 2021-08-05 2020-01-07 the Enabling Environment Officer Selection MOI-CS-FIRM-3 / Training Component 3: Strengthening / Post Direct Selection Direct 0.00 Canceled 2019-07-08 2019-07-18 2019-09-21 2020-03-19 and Capacity Building the Enabling Environment Individual MOI-CS-INDV-7 / Safeguards Component 3: Strengthening IDA / D3890 Post Consultant Open 76,560.00 Signed 2019-03-01 2018-12-16 2019-04-19 2019-02-22 2019-05-10 2019-04-03 2019-06-14 2019-07-12 2021-08-05 Specialist the Enabling Environment Selection Individual MOI-CS-INDV-1-2 / Project Component 3: Strengthening IDA / D3890 Post Consultant Direct 130,036.15 Completed 2018-10-29 2018-12-16 2018-11-08 2019-02-22 2018-11-29 2019-02-22 2019-01-03 2019-02-22 2019-09-20 2020-02-28 Manager the Enabling Environment Selection MOI-CS-CDS-1 / Technical Component 3: Strengthening IDA / D3890 Post Direct Selection Direct 45,000.00 Signed 2019-03-06 2019-03-07 2019-03-16 2019-02-19 2019-04-05 2019-03-25 2019-07-14 Maritime Advisor the Enabling Environment Individual MOI/TCRTPPST/IC06C/2 / Component 3: Strengthening IDA / D3890 Post Consultant Limited 8,783.28 Signed 2018-03-22 2018-01-29 2018-03-27 2018-03-02 2018-04-17 2018-04-18 2018-05-22 2018-04-27 2018-09-19 Local Safeguards Specialist the Enabling Environment Selection Individual MOI-CS-INDV-8 / Obstacle Component 1: Sectoral and IDA / D3890 Post Consultant Open 23,135.62 Signed 2019-04-22 2019-06-12 2019-06-24 2019-05-25 2019-07-15 2019-05-25 2019-08-19 2019-06-19 2019-09-08 Limitation Study in Eua Spatial Planning Tools Selection Individual MOI-CS-INDV-9 / Laboratory Component 3: Strengthening IDA / D3890 Post Consultant Open 53,117.00 Signed 2019-04-29 2019-06-20 2019-06-22 2019-09-12 2019-07-06 2019-09-12 2019-07-27 2019-09-23 2019-10-25 Adviser the Enabling Environment Selection MOI-CS-FIRM-6 / Road Component 3: Strengthening Safety Audit Training and / Post Direct Selection Direct 0.00 Canceled 2019-06-03 2019-07-11 2019-06-13 2019-08-17 2019-11-25 the Enabling Environment Monitoring and Attachment Individual MOI-CS-INDV-1-2-2 / Component 3: Strengthening IDA / D3890 Post Consultant Open 141,563.58 Completed 2020-01-01 2019-12-19 2020-01-23 2020-02-20 2020-01-23 2020-02-21 2020-02-09 2020-02-21 2022-02-08 2021-09-28 TCRTP Project Manager the Enabling Environment Selection MOI/CS/INDV-6-1 / Individual Component 3: Strengthening Communications, Monitoring IDA / D3890 Post Consultant Open 52,763.35 Signed 2020-01-14 2020-01-16 2020-02-14 2020-03-09 2020-02-21 2020-03-05 2020-03-13 2020-03-11 2022-03-13 the Enabling Environment & Evaluation Officer Selection MOI-CS-INDV-10 / Driving Individual Component 3: Strengthening Instructor for commercial IDA / D3890 Post Consultant Open 0.00 Canceled 2020-01-17 2020-01-28 2020-03-06 2020-03-27 2020-05-01 2020-10-28 the Enabling Environment license Selection Individual MOI-CS-INDV-5-1 / Component 3: Strengthening IDA / D3890 Post Consultant Open 26,586.00 Completed 2020-04-14 2020-04-20 2020-05-17 2020-06-15 2020-05-24 2020-06-15 2020-06-13 2020-06-16 2022-06-13 2021-09-30 Administrative Assistant the Enabling Environment Selection Individual MOI-CS-INDV-7-1 / Component 3: Strengthening IDA / D3890 Post Consultant Open 51,791.04 Signed 2020-05-01 2020-06-02 2020-06-19 2020-07-30 2020-07-10 2020-07-30 2020-08-14 2020-08-05 2022-08-14 Safeguards Officer the Enabling Environment Selection Individual MOI-ICS-INDV-12 / Legal Component 3: Strengthening IDA / D3890 Post Consultant 64,838.32 Signed 2020-09-28 2020-09-24 2020-10-08 2020-09-30 2020-10-18 2021-01-22 2020-10-28 2021-01-26 2021-06-25 Consultant the Enabling Environment Selection Individual MOI-ICS-INDV-13 / Component 3: Strengthening IDA / D3890 Post Consultant Open 225,776.42 Signed 2020-11-02 2020-11-13 2020-12-21 2021-02-10 2021-01-11 2021-03-04 2021-02-15 2021-03-22 2022-11-07 Technical Adviser - Roads the Enabling Environment Selection Individual MOI-CS-INDV-4-1 / Project Component 3: Strengthening IDA / D3890 Post Consultant 0.00 Canceled 2020-10-19 2020-12-07 2020-12-28 2021-02-01 2023-02-01 Accountant the Enabling Environment Selection Individual MOI-CS-INDV-5-2 / Component 3: Strengthening Pending IDA / D3890 Post Consultant Open 0.00 2021-10-15 2021-12-13 2021-12-14 2022-01-01 2024-01-01 Administrative Assistant the Enabling Environment Implementation Selection Individual MOI-PMU-SSS-06 / TCRTP Component 3: Strengthening Pending IDA / D3890 Post Consultant Direct 0.00 2021-11-01 2021-11-11 2021-11-25 2021-12-05 2022-12-05 Project Manager the Enabling Environment Implementation Selection Individual MOI-PMU-INDV-4-1 / Project Component 3: Strengthening Pending IDA / D3890 Post Consultant Open 0.00 2021-11-30 2022-01-31 2022-02-07 2022-03-22 2023-12-31 Accountant the Enabling Environment Implementation Selection Individual MOI-PMU-INDV-3-1 / Component 3: Strengthening Pending IDA / D3890 Post Consultant Open 0.00 2021-11-30 2022-01-31 2022-02-21 2022-03-28 2023-12-31 Procurement Officer the Enabling Environment Implementation Selection Individual MOI-PMU-INDV-2-1 / Component 3: Strengthening Pending IDA / D3890 Post Consultant Open 0.00 2021-11-30 2022-01-31 2022-02-21 2022-03-28 2023-12-31 Contracts Manager the Enabling Environment Implementation Selection MOI-PMU-INDV-6-2 / Individual Component 3: Strengthening Pending Communication, Monitoring & IDA / D3890 Post Consultant Open 0.00 2021-11-30 2022-02-05 2022-02-12 2022-03-28 2023-12-31 the Enabling Environment Implementation Evaluation Officer Selection Page 3