PROCUREMENT PLAN (Textual Part) Project information: Timor-Leste Basic Education Strengthening and Transformation Project (P166744) Project Implementation agency: Ministry of Education, Youth and Sport (MOEYS) Date of the Procurement Plan: February 26, 2020. Period covered by this Procurement Plan: July 1, 2020 to December 31, 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, the procedures applicable to the procurement of Goods, Works, Non-Consulting services and Consulting Services under the contracts awarded on the basis of National Open Competitive Procurement shall be those procurement methods set forth in the Timor Leste Procurement Legal Regime Decree Law 10/2005, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When the Borrower uses its own national open competitive procurement arrangements as set forth Timor Leste Procurement Legal Regime Decree Law 10/2005, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. 1. The procurement is open to eligible firms from any country; 2. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; 3. Right for the Bank to review procurement documentation and activities; 4. Maintenance of records of the Procurement process; 5. Procurement Documents acceptable to the Bank shall be used; 6. Bids shall be evaluated using only post-qualification for procurement of goods, works and non-consulting services. 7. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health safety ("ESHS") risks impacts. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables PROCUREMENT Timor-Leste : Basic Education Strengthening and Transformation Project PLAN General Information Country: Timor-Leste 2020-10-28 Bank’s Approval Date of the Original Procurement Plan: 2022-07-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166744 GPN Date: 2020-11-16 Project Name: Basic Education Strengthening and Transformation Project Loan / Credit No: IDA / 65510, TF / B2130 Ministry of Education Youth and Sport Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 001/BEST/TL / 3 packages of new classrooms construction Component 1: Developing 2 Single Stage - One E Pending Imp 2022-08-0 (each package covers differe IDA / 65510 Post Request for Bids Open - National 1,100,000.00 0.00 2021-07-01 2021-07-06 2021-08-17 2021-09-16 2022-02-04 1st Century Learning Spaces nvelope lementation 3 nt municipalities) - 3 schools in 3 different municipalities BEST/WORKS/RFQ01 / PIMU Component 5: Project Manag Request for Quota Single Stage - One E Other (with field f 2022-03-3 TF / B2130 Post Open - National 22,655.50 0.00 Canceled 2021-12-01 2021-12-15 Office Refurbishment ement and Implementation tions nvelope or explanation) 1 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 003/BEST/TL / Provision & In Component 4: Data Driven P Request for Quota Single Stage - One E Under Imple stallation of hardware, includ TF / B2130 lanning, Budgeting, Financin Post Open - National 80,000.00 0.00 2020-11-06 2022-05-19 2022-02-04 2022-08-03 tions nvelope mentation ing servers, software at MoE g and Implementation YS for EMIS 033/BEST/TL / Office electro nic- equipment (computer, pr Component 5: Project Manag Request for Quota Single Stage - One E Under Imple TF / B2130 Post Open - National 20,000.00 0.00 2020-10-09 2022-06-21 2020-12-04 2021-06-02 inter potocopier machine, sc ement and Implementation tions nvelope mentation anner, camera etc) 031/BEST/TL / Furniture and Fixtures for PIMU including Ai Component 5: Project Manag Request for Quota Under Imple TF / B2130 Post 20,000.00 0.00 2020-10-10 2020-12-05 2021-06-03 r conditions, telephones, des ement and Implementation tions mentation ks and chairs and office rack s 030/BEST/TL / Purchasing an Component 3: Improving Te d distribution of set of age/gr Single Stage - One E Pending Impl TF / B2130 aching-Learning Material an Prior Request for Bids Open - National 741,000.00 0.00 2021-01-19 2021-01-24 2021-03-07 2021-04-06 2021-06-18 2021-12-15 ade appropriate children's b nvelope ementation d Assessment ooks for Cycle 1 and 2 and fa brication of book corners 002/BEST/TL / Provision and Installation of relevant hardw Component 4: Data Driven P Single Stage - One E Pending Impl are and internet connectivity TF / B2130 lanning, Budgeting, Financin Post Request for Bids Open - National 120,000.00 0.00 2021-08-03 2021-08-08 2021-09-19 2021-10-19 2022-06-05 2022-12-02 nvelope ementation in selected municipal offices g and Implementation and selected central schools 004/BEST/TL / Operational v Component 1: Developing 2 Request for Quota Single Stage - One E IDA / 65510 Post Open - National 80,000.00 36,500.00 Signed 2021-12-05 2022-05-18 2022-01-30 2022-03-01 2022-03-31 ehicles for the use of PIMU 1st Century Learning Spaces tions nvelope 057/BEST/TL / Operational M Component 5: Project Manag Request for Quota Single Stage - One E Pending Impl TF / B2130 Post Open - National 2,000.00 0.00 2022-05-03 2022-06-28 2022-12-25 otorcycle for PIMU Office ement and Implementation tions nvelope ementation 062/BEST/TL / PIMU Operatio Component 5: Project Manag Request for Quota Single Stage - One E Pending Impl nal Vehicles (1 Pick-up, 4WD TF / B2130 Post Open - National 43,500.00 0.00 2022-07-01 2022-08-26 2023-02-22 ement and Implementation tions nvelope ementation and 1 sedan for Dili-based op eration) 065/BEST/TL / PIMU Office i Component 5: Project Manag Request for Quota Single Stage - One E Pending Impl TF / B2130 Post Open - National 5,000.00 0.00 2022-06-10 2022-08-05 2023-02-01 mprovement (Work Space im ement and Implementation tions nvelope ementation provement) BEST/GOODS/RFQ032 / PIMU Component 5: Project Manag Request for Quota Single Stage - One E Pending Impl TF / B2130 Post Open - National 22,654.45 0.00 2022-01-15 2022-03-12 2022-09-08 Office Refurbishment ement and Implementation tions nvelope ementation 077/BEST/TL / Tablets for Sc Component 1: Developing 2 Request for Quota Single Stage - One E Pending Impl IDA / 65510 Post Open - National 47,600.00 0.00 2022-07-30 2022-09-24 2023-03-23 hool Census. 1st Century Learning Spaces tions nvelope ementation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 070/BEST/TL / A higher educ ation (University or Institute) to provide 36 junior engineer s for School Infrastructure da Component 1: Developing 2 Request for Quota Single Stage - One E Pending Impl IDA / 65510 Post Open - National 198,508.00 0.00 2022-08-02 2022-09-27 2023-03-26 ta collection including perdie 1st Century Learning Spaces tions nvelope ementation m and supervision managem ent; (Remuniration, Payment Perdiem,Comunication Fees, Rental of Equipment, Other O perational Se CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 006/BEST/TL / Consultant Fir m (Experts) for Quality assur Component 1: Developing 2 Consultant Qualifi Pending Impleme IDA / 65510 Post Open - National 175,000.00 0.00 2021-07-01 2021-07-22 2021-09-04 2021-10-04 2021-11-08 2022-05-07 ance of new construction and 1st Century Learning Spaces cation Selection ntation rehabilitation of school infras tructures Page 1 009/BEST/TL / A Firm to desi Component 3: Improving Te gn the implementation, analy Consultant Qualifi Open - Internationa Pending Impleme TF / B2130 aching-Learning Material an Post 400,000.00 0.00 2021-01-31 2021-02-21 2021-04-06 2021-05-06 2021-06-10 2021-12-07 sis and reporting of EGRA an cation Selection l ntation d Assessment d EGMA and basic capacity b uilding (grades 1,2, 3) 005/BEST/TL / A Firm for sys tem core development for th Component 4: Data Driven P e integrated for Sistema de G Quality And Cost- Open - Internationa Under Implement TF / B2130 lanning, Budgeting, Financin Post 500,000.00 0.00 2021-06-01 2021-12-13 2021-06-22 2021-08-05 2021-09-02 2021-10-02 2021-11-06 2022-02-01 2022-12-29 estao Escolar, PMIS and EMIS Based Selection l ation g and Implementation and other data base system, software development/modifi cation/testing/production 061/BEST/TL / Consultant fir Component 5: Project Manag Consultant Qualifi Open - Internationa Pending Impleme TF / B2130 Post 42,000.00 0.00 2022-04-29 2022-05-20 2022-07-03 2022-08-02 2022-09-06 2023-03-05 m for External Auditors for B ement and Implementation cation Selection l ntation EST Project 036/BEST/TL / Online system and training/orientation of sc Component 1: Developing 2 Consultant Qualifi Pending Impleme IDA / 65510 Post Open - National 45,000.00 0.00 2021-02-01 2021-02-22 2021-04-07 2021-05-07 2021-06-11 2021-12-08 hool infrastructure managem 1st Century Learning Spaces cation Selection ntation ent or module linked to EMIS (Component I) 047/BEST/TL / Consultant Fir Component 3: Improving Te m to design the implementat Consultant Qualifi Pending Impleme TF / B2130 aching-Learning Material an Post Open - National 350,000.00 0.00 2022-04-28 2022-05-19 2022-07-02 2022-08-01 2022-09-05 2023-03-04 ion, analysis and reporting of cation Selection ntation d Assessment EGRA and EGMA (grades 1,2, 3) 060/BEST/TL / Consultant Fir Component 1: Developing 2 Consultant Qualifi Pending Impleme m for school infrastructure su IDA / 65510 Post Open - National 328,385.00 0.00 2022-04-29 2022-05-20 2022-07-03 2022-08-02 2022-09-06 2023-03-05 1st Century Learning Spaces cation Selection ntation pervision and quality control 059/BEST/TL / Consultant Fir m for detailed engineering d Component 1: Developing 2 Quality And Cost- Pending Impleme IDA / 65510 Prior Open - National 900,000.00 0.00 2022-06-19 2022-07-10 2022-08-23 2022-09-20 2022-10-20 2022-11-24 2022-12-29 2023-12-29 esign, bidding document pre 1st Century Learning Spaces Based Selection ntation paration/Works and supervisi on. 034/BEST/TL / Implementati Component 1: Developing 2 Consultant Qualifi Open - Internationa on of school census includin IDA / 65510 Post 450,000.00 0.00 Canceled 2021-01-19 2022-01-20 2021-02-09 2022-07-11 2021-03-25 2022-04-24 2021-04-24 2022-06-10 2021-05-29 2021-11-25 1st Century Learning Spaces cation Selection l g school infrastructure and E MIS census INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 021/BEST/TL / Infrastructure Component 5: Project Manag Individual Consult Development Specialist of 21 IDA / 65510 Post Open 135,000.00 0.00 Canceled 2020-10-09 2020-11-09 2020-11-27 2020-12-18 2021-01-22 2023-07-21 ement and Implementation ant Selection st Century School standards 035/BEST/TL / Consultant for implementation of a school i Component 1: Developing 2 Individual Consult Under Implement nfrastucture survey of a smal IDA / 65510 Post Limited 18,000.00 0.00 2021-02-01 2021-11-04 2021-02-06 2021-02-27 2021-04-03 2021-09-30 1st Century Learning Spaces ant Selection ation l purposive sample of school to test the prioritazation guid elines 037/BEST/TL / Technical exp Component 2: Improving Te Individual Consult Under Implement ert in education (curriculum, TF / B2130 Post Open 205,200.00 205,200.00 2020-10-23 2021-11-11 2020-12-11 2021-12-03 2021-01-01 2022-01-14 2021-02-05 2023-02-20 acher Effectiveness ant Selection ation training, school management ) 022/BEST/TL / TA for enhanci ng the reporting and dashbo ard facilities of the classroom Component 2: Improving Te Individual Consult Under Implement observation module to gener TF / B2130 Post Open 20,000.00 0.00 2021-08-02 2021-09-20 2021-10-11 2021-11-15 2022-05-14 acher Effectiveness ant Selection ation ate and display aggregate da ta on results of classroom ob servations by indicator, scho ol, cluster and municipal offic e 015/BEST/TL / Review and U Component 2: Improving Te Individual Consult Pending Impleme pgrade training materials for TF / B2130 Post Open 20,000.00 0.00 2020-12-15 2021-02-02 2021-02-23 2021-03-30 2021-09-26 acher Effectiveness ant Selection ntation school leaders training 016/BEST/TL / Upgrading/De Component 2: Improving Te Individual Consult Pending Impleme velop teacher training monit TF / B2130 Post Open 20,000.00 0.00 2021-01-01 2021-02-19 2021-03-12 2021-04-16 2021-10-13 acher Effectiveness ant Selection ntation oring/observation tool for INF ORDEPE 017/BEST/TL / Training obser Component 2: Improving Te Individual Consult Pending Impleme vation/evaluation report on t TF / B2130 Post Open 20,000.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 acher Effectiveness ant Selection ntation eachers training quality 011/BEST/TL / Curriculum sp Component 3: Improving Te ecialist for reviewing and qu Individual Consult Pending Impleme TF / B2130 aching-Learning Material an Post Limited 25,000.00 0.00 2021-01-29 2021-02-03 2021-02-24 2021-03-31 2021-09-27 ality checks for 3rd cycle boo ant Selection ntation d Assessment ks (language and social scien ces) 018/BEST/TL / Curriculum sp Component 3: Improving Te ecialist for reviewing and qu Individual Consult Pending Impleme TF / B2130 aching-Learning Material an Post Open 15,000.00 0.00 2021-01-29 2021-03-19 2021-04-09 2021-05-14 2021-11-10 ality assurance for 3rd cycle ant Selection ntation d Assessment TLM (natural sciences) 027/BEST/TL / Curriculum sp Component 3: Improving Te Individual Consult Pending Impleme ecialist for revision and qualit TF / B2130 aching-Learning Material an Post Open 15,000.00 0.00 2021-01-29 2021-03-19 2021-04-09 2021-05-14 2021-11-10 ant Selection ntation y assurance for 3rd cycle TL d Assessment M (mathematics) 007BEST/TL / A consultant to Component 3: Improving Te Individual Consult Pending Impleme develop Physical Education B TF / B2130 aching-Learning Material an Post Open 38,400.00 0.00 2020-11-13 2021-01-01 2021-01-22 2021-02-26 2022-02-25 ant Selection ntation ook and Manual for Grade 7 ( d Assessment Third Cycle) 020/BEST/TL / Financial Man Component 5: Project Manag Individual Consult TF / B2130 Post Open 151,200.00 151,200.00 Signed 2020-10-04 2020-11-09 2020-11-22 2022-06-03 2020-12-13 2022-06-03 2021-01-17 2021-10-18 2023-01-17 agement Specialist ement and Implementation ant Selection 023/BEST/TL / Procurement Component 5: Project Manag Individual Consult TF / B2130 Post Open 151,200.00 40,650.00 Terminated 2020-10-02 2020-11-09 2020-11-20 2021-10-13 2020-12-11 2021-10-25 2021-01-15 2021-10-18 2023-01-15 Specialist ement and Implementation ant Selection 013/BEST/TL / Environmenta Component 5: Project Manag Individual Consult TF / B2130 Post Open 124,200.00 124,200.00 Signed 2020-12-01 2020-11-09 2021-01-19 2022-01-11 2021-02-09 2021-10-18 2021-03-16 2021-10-18 2023-03-16 l and Social safeguard specia ement and Implementation ant Selection list 024/BEST/TL / M&E Specialis Component 5: Project Manag Individual Consult TF / B2130 Post Open 108,000.00 0.00 Canceled 2020-12-01 2020-11-09 2021-01-19 2021-02-09 2021-03-16 2023-03-16 t for PIMU ement and Implementation ant Selection Page 2 012/BEST/TL / ICT specialist Component 5: Project Manag Individual Consult Under Implement TF / B2130 Post Open 118,000.00 0.00 2020-10-29 2020-11-09 2020-12-17 2021-10-18 2021-01-07 2021-10-18 2021-02-11 2023-02-10 for PIMU ement and Implementation ant Selection ation 032/BEST/TL / Administratio Component 5: Project Manag Individual Consult TF / B2130 Post Open 67,500.00 0.00 Canceled 2020-11-01 2020-11-09 2020-12-20 2021-01-10 2021-02-14 2023-02-14 n assistant to PIMU ement and Implementation ant Selection 028/BEST/TL / Independent v Component 2: Improving Te Individual Consult Pending Impleme TF / B2130 Post Open 15,000.00 0.00 2021-06-30 2021-08-18 2021-09-08 2021-10-13 2022-04-11 erification of DLI achievemen acher Effectiveness ant Selection ntation ts 008/BEST/TL / A consultant t o design a Paper based temp late for supporting the acquis Component 3: Improving Te ition, packaging, and distribu Individual Consult Pending Impleme TF / B2130 aching-Learning Material an Post Open 4,500.00 0.00 2021-02-01 2021-03-22 2021-04-12 2021-05-17 2021-08-31 tion of TLM, estimate the nu ant Selection ntation d Assessment mber of books to be printed each year, and provide the s chools with updates on the st atus on their TLM needs; 038/BEST/TL / A consultant t Component 3: Improving Te Individual Consult Pending Impleme o develop Art Book and Manu TF / B2130 aching-Learning Material an Post Open 38,400.00 0.00 2020-11-13 2021-01-01 2021-01-22 2021-02-26 2022-02-25 ant Selection ntation al for Grade 7th d Assessment 019/BEST/TL / Project manag Component 5: Project Manag Individual Consult TF / B2130 Prior Open 305,100.00 0.00 Canceled 2020-10-08 2020-11-15 2020-11-26 2020-12-17 2021-01-08 2023-01-08 er for PMIU ement and Implementation ant Selection BEST/INDV/005 / Monitoring Component 5: Project Manag Individual Consult Under Implement IDA / 65510 Post Open 119,025.00 0.00 2021-10-15 2021-11-11 2021-11-17 2022-01-11 2021-12-08 2022-01-17 2022-01-12 2024-07-10 and Evaluation Specialist ement and Implementation ant Selection ation BEST/INDV/001 / BEST Proje Component 5: Project Manag Individual Consult Under Implement TF / B2130 Post Open 244,350.00 64,304.46 2021-10-15 2021-12-17 2021-12-03 2021-11-04 2021-12-24 2021-10-25 2022-01-28 2022-07-27 ct Manager ement and Implementation ant Selection ation BEST/INDV/006 / Infrastructu Component 5: Project Manag Individual Consult Under Implement TF / B2130 Post Open 180,675.00 180,675.00 2021-10-15 2021-11-11 2021-12-03 2022-05-14 2021-12-24 2022-01-16 2022-01-28 2022-07-27 re Development Specialist ement and Implementation ant Selection ation BEST/INDV/008 / Administrat Component 5: Project Manag Individual Consult Under Implement TF / B2130 Post Open 56,250.00 0.00 2021-11-15 2021-11-11 2021-12-10 2022-01-18 2021-12-13 2022-01-18 2021-12-14 2022-12-30 ion Assistant to PIMU ement and Implementation ant Selection ation BEST/INDV/003 / Procureme Component 5: Project Manag Individual Consult Under Implement TF / B2130 Post Open 126,000.00 126,000.00 2021-12-05 2021-11-25 2022-01-23 2022-02-28 2022-02-13 2022-03-04 2022-03-20 2022-09-16 nt Specialist (National) ement and Implementation ant Selection ation 025/BEST/TL / Architect to pr Component 1: Developing 2 Individual Consult Under Implement oduce standardized designs IDA / 65510 Post Open 30,000.00 0.00 2020-12-02 2022-05-18 2021-01-20 2021-02-10 2021-03-17 2021-09-13 1st Century Learning Spaces ant Selection ation and infrastructure standards 014/BEST/TL / Quality assura nce consultant for reviewing Component 4: Data Driven P Individual Consult Pending Impleme designing and development TF / B2130 lanning, Budgeting, Financin Post Open 15,000.00 0.00 2021-11-01 2021-12-20 2022-01-10 2022-02-14 2022-08-13 ant Selection ntation of system for infrastructure c g and Implementation omponent in EMIS (in 2020 a nd 2021) 010/BEST/TL / Technical Spe cialist to support the develop ment and finalization of the p Component 1: Developing 2 Individual Consult Pending Impleme IDA / 65510 Post Open 20,000.00 0.00 2020-10-30 2020-12-18 2021-01-08 2021-02-12 2021-08-11 rioritization methodology , pr 1st Century Learning Spaces ant Selection ntation eparation of prioritization pla n including priority list for sc hool construction 043/BEST/TL / Technical Assi stance to update school lead Component 2: Improving Te Individual Consult Under Implement TF / B2130 Post Open 17,500.00 0.00 2022-05-08 2022-06-26 2022-06-26 2022-07-17 2022-08-21 2023-02-17 ers training package, develo acher Effectiveness ant Selection ation ping of training materials (inc luding the use experts) 039/BEST/TL / Technical Assi stance for school infrastructu Component 1: Developing 2 Individual Consult Under Implement IDA / 65510 Post Open 27,000.00 0.00 2022-04-28 2022-06-23 2022-06-16 2022-07-07 2022-08-11 2023-02-07 re planning and prioritization 1st Century Learning Spaces ant Selection ation guideline development and t esting Component 3: Improving Te 045/BEST/TL / Specialist in b Individual Consult Under Implement TF / B2130 aching-Learning Material an Post Open 60,000.00 0.00 2022-04-28 2022-06-10 2022-06-16 2022-07-07 2022-08-11 2023-02-07 asic Education Curriculum ant Selection ation d Assessment 044/BEST/TL / Technical Assi stance to develop or upgrade Component 2: Improving Te Individual Consult Under Implement TF / B2130 Post Open 20,250.00 0.00 2022-04-28 2022-06-28 2022-06-16 2022-07-07 2022-08-11 2023-02-07 teacher training monitoring/ acher Effectiveness ant Selection ation Observation Tool and module 069/BEST/TL / Polo-based su Component 1: Developing 2 Individual Consult Pending Impleme IDA / 65510 Post Open - National 2,250.00 0.00 2022-07-25 2022-09-12 2022-10-03 2022-11-07 2023-05-06 pervisor for Manufahi Munici 1st Century Learning Spaces ant Selection ntation pality 072/BEST/TL / An Internation Component 1: Developing 2 Individual Consult Open - Internationa Pending Impleme IDA / 65510 Post 63,750.00 0.00 2022-07-25 2022-09-12 2022-10-03 2022-11-07 2023-05-06 al Team Leader for School Ce 1st Century Learning Spaces ant Selection l ntation nsus 073/BEST/TL / Local Technic al Consultant 1 Person (Exp ert for Design the instrument Component 1: Developing 2 Individual Consult Pending Impleme /Questionnaire Format and T IDA / 65510 Post Open - National 22,000.00 0.00 2022-07-25 2022-09-12 2022-10-03 2022-11-07 2023-05-06 1st Century Learning Spaces ant Selection ntation abulation) duration of the co ntract 4 months ( estamate $ 4,400/month incluiding Tax 1 0%) Prepare Questionnaire F orm 078/BEST/TL / Polo Bases Su Component 1: Developing 2 Individual Consult Pending Impleme IDA / 65510 Post Open - National 2,250.00 0.00 2022-07-17 2022-09-04 2022-09-25 2022-10-30 2023-04-28 pervisor for Dili Municipality 1st Century Learning Spaces ant Selection ntation 080/BEST/TL / Polo Bases Su pervisor for Baucau Municip Component 1: Developing 2 Individual Consult Pending Impleme IDA / 65510 Post Open - National 2,250.00 0.00 2022-07-25 2022-09-12 2022-10-03 2022-11-07 2023-05-06 ality (duration of Contract 3 1st Century Learning Spaces ant Selection ntation months $ 750/month) 082/BEST/TL / Polo Bases Su Component 1: Developing 2 Individual Consult Pending Impleme IDA / 65510 Post Open - National 2,250.00 0.00 2022-07-25 2022-09-12 2022-10-03 2022-11-07 2023-05-06 pervisor for Maliana Municipa 1st Century Learning Spaces ant Selection ntation lity 083/BEST/TL / Polo Bases Su Component 1: Developing 2 Individual Consult Pending Impleme IDA / 65510 Post Open - National 2,250.00 0.00 2022-07-25 2022-09-12 2022-10-03 2022-11-07 2023-05-06 pervisor for Oecussi Municipa 1st Century Learning Spaces ant Selection ntation lity Page 3