Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan September 28, 2015 2. Date of General Procurement Notice: August 10, 2016 3. Period covered by this procurement plan: The procurement period of project covered from year June 2016 to December 2018. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Prior Review Comments Method Threshold US$ 1. ICB and LIB (Goods) All 2. NCB (Goods) Above US$ 2,000,000 3. ICB (Works) All 4. NCB (Works) Above US$ 10,000,000 2. Pre-qualification. Not applicable. 3. Reference to (if any) Project Operational/Procurement Manual: January 28, 2016. 4. Any Other Special Procurement Arrangement: None 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref Description Estimat Packa Domesti Review Comments . ed ges c by Bank No. Cost Prefere (Prior / US$ nce Post) million (yes/no) 1 Summary of 21.91 1 No Prior the ICB (Works) 2 Summary of 119.12 11 No Prior/Post the NCB (Works) III. Selection of Consultants March 29, 2017 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$1,000,000 2. Single Source (Firms) For SSS, USD50,000 (Para 3.9 of Consultant Guidelines, January 2011) and all other SSS contracts. 3. Individual Individuals ≥ USD 0.3 million; and for essential assignments (procurement / legal consultant). For SSS, USD20,000 (Para 5.6 of Consultant Guidelines, January 2011) 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not applicable. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Descriptio Estimat Package Review Comment n of ed s by s Assignme Cost Bank nt US$ (Prior / million Post) Summary 5.91 5 Prior QCBS of number of contracts that will be let under QCBS Summary 1.04 5 Prior/Po CQS/IC of number st of contracts that will be let under other methods March 29, 2017 March 29, 2017 PROCUREMENT Vietnam : Can Tho Urban Development and Resilience PLAN General Information Country: Vietnam Bank’s Approval Date of the Original Procurement Plan: 2016-08-15 2022-03-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152851 GPN Date: 2016-08-10 Project Name: Can Tho Urban Development and Resilience Loan / Credit No: IDA / 57790, IBRD / 85980, TF / A3723 C Executing Agency(ies): an Tho PMU for ODA funded Construction and Investment Projects WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CT3 PW 1 7 / Construction of tide sluice gates on route Flood risk management, and Single Stage - One 3,931,259.6 2018-08- connection with Cach Mang IDA / 57790 Prior Request for Bids Open - National 6,041,900.00 Signed 2016-10-04 2017-05-23 2016-12-06 2017-01-05 2017-11-29 2017-02-19 2018-05-18 2017-04-20 2018-05-24 environmental sanitation Envelope 6 18 Thang 8 Street to Provincial road 918 CT3 PW 2 1 / Construction of Quang Trung Bridge, module 2 and extension of the span of module 1 and Spatial planning platform and Single Stage - One 16,872,300.0 9,684,289.2 2019-02- reinforcement of existing IBRD / 85980 financial and social Prior Request for Bids Open - National Signed 2016-10-14 2017-04-14 2016-12-16 2017-01-16 2017-05-24 2017-03-02 2017-10-17 2017-05-01 2017-11-08 Envelope 0 8 25 bridge, lighting system and protection instruments architecture rehabilitation of the Quang Trung Bridge, approach roads at the both sides of the Bridge CT3 PW 2 3 / Construction of the parallel road form Tran Hoang Na street to the IC3 Spatial planning platform and Single Stage - One 5,441,627.6 2018-08- intersection and approach IBRD / 85980 financial and social Post Request for Bids Open - National 8,081,800.00 Signed 2016-10-04 2016-12-06 2017-01-05 2017-10-05 2017-02-20 2017-12-08 2017-04-20 2017-12-18 Envelope 7 18 road from intersection to the protection instruments bus station including the intersection with NH1A CT3 PW 2 2 / Construction of Spatial planning platform and Tran Hoang Na road from Single Stage - One 10,927,100.0 8,445,162.0 2018-09- IBRD / 85980 financial and social Prior Request for Bids Open - National Signed 2016-10-27 2017-09-11 2016-12-29 2017-02-06 2017-10-17 2017-03-23 2017-12-26 2017-05-14 2017-12-28 Nguyen Van Cu road to Tran Envelope 0 3 11 protection instruments Hoang Na Bridge. CT3 PW 2 5 / Construction of Spatial planning platform and Single Stage - One 16,012,000.0 2018-06- connection road CMT8 to IBRD / 85980 financial and social Prior Request for Bids Open - National 0.00 Canceled 2016-10-14 2016-12-16 2017-01-16 2017-03-01 2017-04-28 Envelope 0 27 Provincial road 918 protection instruments CT3 PW 2 6 / Construction of connection road CMT8 to Spatial planning platform and Provincial road 918: road from Single Stage - One 12,502,890.0 12,014,472. 2020-01- IBRD / 85980 financial and social Prior Request for Bids Open - National Signed 2018-01-27 2017-11-28 2018-02-12 2018-03-19 2018-01-10 2018-04-14 2018-09-06 2018-05-23 2018-09-08 intersection of Vo Van Kiet Envelope 0 55 13 protection instruments Road to Provincial road 918 (Km1+820 - Km 5+ 333). CT3 PW 1 1 / Construction of Flood risk management, and Single Stage - One 7,207,052.0 2020-03- the Can Tho River Revetment IBRD / 85980 Prior Request for Bids Open - National 8,121,572.00 Signed 2018-04-21 2019-02-25 2018-04-26 2018-05-26 2019-03-29 2018-06-30 2019-11-25 2018-07-14 2019-12-05 environmental sanitation Envelope 4 13 from Km 0+00 to Km 1+600 CT3 PW 2 5 / Construction of connection road CMT8 to Spatial planning platform and Provincial road 918: road from Single Stage - One 6,845,270.6 2019-04- IBRD / 85980 financial and social Post Request for Bids Open - National 9,243,973.00 Signed 2017-10-28 2017-10-27 2017-11-14 2017-12-18 2017-11-29 2018-01-13 2018-05-18 2018-02-22 2018-06-14 CMT8 Street to intersection of Envelope 6 18 protection instruments Vo Van Kiet Road (Km0+00 - Km1+820). CT3 PW 1 3 / Construction of Flood risk management, and Single Stage - One 5,523,767.7 2019-02- the Can Tho River Revetment IBRD / 85980 Prior Request for Bids Open - National 9,932,348.00 Signed 2017-03-01 2019-01-30 2017-05-03 2017-06-02 2019-05-28 2017-07-17 2019-07-24 2017-09-15 2019-08-28 environmental sanitation Envelope 0 12 from km 3+00 to end of route CT3 PW 1 4 / Construction of Flood risk management, and Single Stage - One 2019-05- the park at the rear of Can IBRD / 85980 Post Request for Bids Open - National 2,846,400.00 0.00 Canceled 2017-09-29 2017-12-01 2017-12-29 2018-02-12 2018-04-13 environmental sanitation Envelope 13 Tho River Revetment CT3 PW 2 7 / Leveling of An Spatial planning platform and Single Stage - One 3,017,075.6 2020-03- Binh Resettlement Site for IBRD / 85980 financial and social Post Request for Bids Open - National 3,529,309.00 Signed 2019-05-02 2019-07-12 2019-05-17 2019-06-17 2019-08-15 2019-07-31 2019-12-31 2019-08-21 2020-01-09 Envelope 2 06 Phase 1 protection instruments CT3 PW 1 5 / Construction of Flood risk management, and Single Stage - One 4,947,676.5 2022-03- IBRD / 85980 Post Request for Bids Open - National 5,773,353.00 Signed 2020-04-01 2020-09-11 2020-04-19 2020-05-19 2020-10-12 2020-07-02 2020-11-02 2020-07-29 2020-11-16 Dau Sau tide Sluice gate environmental sanitation Envelope 4 30 CT3 PW 2 8 / Construction of the technical infrastructure of Single Stage - One 5,809,214.6 2020-10- IBRD / 85980 Urban corridor development Post Request for Bids Open - National 7,600,245.00 Signed 2019-05-31 2019-10-28 2019-06-21 2019-07-22 2019-11-28 2019-09-03 2019-12-23 2019-09-27 2020-02-12 An Binh Resettlement Site for Envelope 9 12 Phase 1 CT3 PW 1 16 / Improvement Cai Son – Muong Khai canals (area from K1+883 – K4+197) Flood risk management, and Single Stage - One 14,516,125.0 11,648,140. 2022-06- IBRD / 85980 Prior Request for Bids Open - National Signed 2020-03-31 2020-08-11 2020-04-24 2020-05-24 2020-09-28 2020-07-24 2020-12-15 2020-08-26 2020-12-23 and construction tidal sluice environmental sanitation Envelope 0 23 30 gate in Pho Tho and Cay Dua canals CT3 PW 1 2 / Construction of the Can Tho River Revetment, Flood risk management, and Single Stage - One 16,319,594.0 12,936,389. 2022-06- IBRD / 85980 Prior Request for Bids Open - National Signed 2020-03-31 2020-05-08 2020-04-24 2020-05-24 2020-05-08 2020-07-24 2020-08-12 2020-08-26 2020-08-19 road at the rear of revetment environmental sanitation Envelope 0 72 30 from Km 1+600 to Km 3+000 CT3 PW 1 18 / Improvement Pending Dau Sau, Muong Cui, Xeo Flood risk management, and Single Stage - One 2022-06- IBRD / 85980 Post Request for Bids Open - National 9,847,343.00 0.00 Implementat 2020-06-30 2020-07-23 2020-08-22 2020-10-22 2020-11-24 Nhum, Nga Bat and Muong Lo environmental sanitation Envelope 30 ion (91B) canals CT3 PW 1 15 / Improvement Flood risk management, and Single Stage - One 4,888,981.3 2022-04- Cai Son – Muong Khai canals IBRD / 85980 Prior Request for Bids Open - National 8,521,752.00 Signed 2020-03-31 2020-05-08 2020-04-19 2020-05-19 2020-06-11 2020-07-02 2020-08-25 2020-07-30 2020-08-27 environmental sanitation Envelope 1 01 (area from K0 - K1+695) Page 1 CT3 PW 1 19 / Improvement Pending Flood risk management, and Single Stage - One 2022-06- Ong Ta, Xeo La, Cay Me, Ong IBRD / 85980 Post Request for Bids Open - National 6,697,748.00 0.00 Implementat 2020-06-30 2020-07-19 2020-08-18 2020-10-01 2020-10-27 environmental sanitation Envelope 30 Dao, Tu Ho and Sao Canals ion CT3 PW 1 20 / Construction Pending Flood risk management, and Single Stage - One 2022-06- of reservoirs in University IBRD / 85980 Post Request for Bids Open - National 4,615,419.00 0.00 Implementat 2020-09-30 2020-10-19 2020-11-19 2021-01-04 2021-01-30 environmental sanitation Envelope 30 Village and Long Hoa Lakes ion CT3 PW 2 4 / Construction of Bridge over Can Tho River Single Stage - One 37,683,000.0 34,146,921. 2022-06- connection Tran Hoang Na IBRD / 85980 Urban corridor development Prior Request for Bids Open - International Signed 2020-02-17 2020-05-01 2020-02-28 2020-05-04 2020-04-28 2020-05-05 2020-07-14 2020-09-10 2020-09-30 2020-09-17 Envelope 0 12 30 Road with approaching road of Can Tho Bridge. CT3 PW 1 9 / Construction of Flood risk management, and Single Stage - One 9,335,367.3 2022-05- IBRD / 85980 Post Request for Bids Open - National 6,762,200.00 Signed 2020-05-31 2020-11-10 2020-06-18 2020-07-18 2020-12-11 2020-09-01 2020-12-15 2020-09-28 2020-12-23 Hang Bang Water Lock environmental sanitation Envelope 1 29 CT3 PW 1 13 / Improving and upgrading the infrastructure Flood risk management, and Single Stage - One 2,717,020.8 2021-08- of Hoang Quoc Viet Street, IBRD / 85980 Post Request for Bids Open - National 5,612,111.00 Signed 2019-05-15 2019-10-31 2019-06-03 2019-07-03 2019-12-04 2019-08-16 2020-01-22 2020-02-17 2020-02-28 environmental sanitation Envelope 8 20 from Km1 + 952.5 to Km3 + 461 CT3 PW 1 6 / Construction of tide sluice gates on route at Flood risk management, and Single Stage - One 1,833,020.3 2021-06- IBRD / 85980 Post Request for Bids Open - National 2,385,200.00 Signed 2017-03-29 2019-11-01 2017-05-31 2017-06-30 2019-12-05 2017-08-14 2019-12-26 2020-02-18 2020-01-20 the rear of Can Tho River environmental sanitation Envelope 4 04 revetment National Procurement Under CT3 PW 1 8 / Construction of Flood risk management, and Single Stage - One 19,162,592.0 2024-03- IBRD / 85980 Prior Request for Bids Open - National Document - 1 0.00 Implementat 2021-12-14 2022-03-24 2021-12-30 2022-01-30 2022-02-28 2022-03-20 Cai Khe Water Lock environmental sanitation Envelope 0 20 Envelope process ion (Non Bank-SPD) National CT3 PW 1 10 / Improving and Procurement Pending upgrading the infrastructure Flood risk management, and Single Stage - One 2024-05- IBRD / 85980 Post Request for Bids Open - National Document - 1 8,011,590.00 0.00 Implementat 2022-03-22 2022-03-30 2022-04-29 2022-05-15 2022-05-19 of Hoang Quoc Viet Street, environmental sanitation Envelope 19 Envelope process ion from Km0+000 to (Non Bank-SPD) Km1+952,5 National CT3 PW 1 17 / Improvement Procurement Pending Ba Bo, Dau Sau and Hang Bang Flood risk management, and Single Stage - One 17,061,422.0 2024-03- IBRD / 85980 Prior Request for Bids Open - National Document - 1 0.00 Implementat 2022-03-22 2022-03-30 2022-04-29 2022-05-15 2022-05-19 canals as well as Hang Bang environmental sanitation Envelope 0 19 Envelope process ion canal's branch (Non Bank-SPD) National CT3 PW 1 11 / Improving Procurement Pending Water Drainage system at Flood risk management, and Single Stage - One 12,644,455.0 2024-01- IBRD / 85980 Post Request for Bids Open - National Document - 1 0.00 Implementat 2022-03-22 2022-03-30 2022-04-29 2022-05-15 2022-05-19 Central area in Ninh Kieu environmental sanitation Envelope 0 19 Envelope process ion District (Non Bank-SPD) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Spatial planning platform and CT3 PG 3 1 / Spatial Planning Single Stage - One TF / A3723 financial and social Prior Request for Bids Open - National 1,633,435.00 1,489,322.25 Signed 2019-05-10 2019-12-02 2019-06-03 2019-07-05 2020-05-15 2019-08-20 2020-08-13 2019-09-20 2020-08-19 2021-03-26 Platform (SPP) Envelope protection instruments CT3 PG 3 2 / The Design, Spatial planning platform and Development and Single Stage - One TF / A3723 financial and social Post Request for Bids Open - National 273,000.00 210,777.66 Signed 2019-05-10 2019-07-16 2019-05-24 2019-06-24 2019-08-19 2019-08-08 2019-10-03 2019-08-29 2019-10-31 2020-06-03 Implementation of Integrated Envelope protection instruments Social Assistance (ISA) System Spatial planning platform and Pending CT3 PG 3 4 / Collection and Single Stage - One IDA / 57790 financial and social Prior Request for Bids Open - National 2,250,000.00 0.00 Implementati 2020-09-01 2020-09-24 2020-10-29 2020-12-14 2021-01-06 2022-05-23 shopping data Envelope protection instruments on CT3 PG 3 5 / Shopping Spatial planning platform and Pending Single Stage - One Information Communication IDA / 57790 financial and social Prior Request for Bids Open - National 2,500,000.00 0.00 Implementati 2020-09-01 2020-09-24 2020-10-29 2020-12-11 2021-01-06 2022-05-23 Envelope Technology (ICT) protection instruments on Pending Flood risk management, and Single Stage - One CT3 PG 3 6 / SCADA IDA / 57790 Prior Request for Bids Open - National 2,150,066.00 0.00 Implementati 2020-09-01 2020-09-24 2020-10-29 2020-12-11 2021-01-06 2022-06-30 environmental sanitation Envelope on CT3 PG 3 7 / Equipment for Pending Flood risk management, and Single Stage - One supporting and establishing IDA / 57790 Post Request for Bids Open - National 1,724,000.00 0.00 Implementati 2020-09-01 2020-09-24 2020-10-29 2020-12-11 2021-01-06 2022-06-30 environmental sanitation Envelope FRMIS Center on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CT3 NC 3 3 / Survey to Spatial planning platform and develop a household database Single Stage - One IDA / 57790 financial and social Post Request for Bids Open - National 101,633.00 85,401.26 Signed 2019-05-20 2019-07-16 2019-06-03 2019-07-05 2019-08-19 2019-08-19 2019-10-03 2019-09-10 2019-11-13 2020-05-18 in response to flood risks and Envelope protection instruments climate change impacts. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CT3 CS TV03 / Construction supervision and contract Spatial planning platform and Consultant Pending management Consultant for IDA / 57790 financial and social Post Qualification Open - National 175,500.00 0.00 2016-10-24 2016-11-01 2016-12-26 2017-02-16 2017-04-03 2018-01-27 Implementation of Resettlement area phase 1 protection instruments Selection (CT3-PW-2.7) Page 2 CT3 CS TV01 / Construction Supervision and contract management Consultant for packages under Component 1 Flood risk management, and Quality And Cost- (Can Tho River Revetment: IDA / 57790 Prior Open - International 3,804,300.00 3,178,673.71 Signed 2016-07-15 2016-08-30 2016-07-20 2016-11-21 2016-10-13 2017-09-06 2016-12-13 2017-10-09 2017-01-24 2018-05-15 2017-02-20 2018-07-12 2017-05-05 2018-07-27 2019-07-04 environmental sanitation Based Selection CT3-PW-1.1, CT3-PW-1.2, CT3-PW-1.3, CT3-PW-1.4, CT3-PW-1.5, CT3-PW-1.6, CT3-PW-1.8 and CT3-PW- 1.9) CT3 CS TV05 / Independent Consultant Flood risk management, and consultant for monitoring IDA / 57790 Post Qualification Open - National 200,000.00 160,207.10 Signed 2016-10-13 2017-04-12 2016-10-21 2016-12-16 2018-03-02 2017-02-06 2018-04-20 2017-03-22 2018-04-24 2021-10-21 environmental sanitation environment on project Selection Consultant CT3 CS TV07 / Independent Flood risk management, and IDA / 57790 Prior Qualification Open - National 250,000.00 51,854.28 Signed 2016-08-29 2017-01-24 2016-09-05 2016-10-31 2018-04-26 2016-12-21 2018-07-08 2017-02-06 2018-07-13 2020-01-31 Consultant for auditing environmental sanitation Selection CT3 CS TV11 / Construction Supervision and contract management Consultant for packages of Improving and Consultant upgrading the infrastructure Flood risk management, and Pending IDA / 57790 Post Qualification Open - National 295,800.00 0.00 2017-02-06 2017-02-13 2017-04-10 2017-05-24 2017-07-10 2019-05-06 of Hoang Quoc Viet Street and environmental sanitation Implementation Selection Improving Water Drainage system at Central area in Ninh Kieu District: CT3-PW-1.10, CT3-PW-1.11. CT3 CS TV12 / Assistant technical (TA) for doing Bidding documents and Bid Consultant evaluation for all packages Flood risk management, and IDA / 57790 Prior Qualification Open - National 280,000.00 196,533.63 Signed 2016-07-24 2016-12-13 2016-07-31 2016-12-18 2018-03-06 2017-05-23 2018-04-26 2017-07-23 2018-05-14 2019-07-23 under the procurement plan environmental sanitation Selection for the first 18 months and Bidding documents for Phase 2 CT3 CS TV02 / Construction Supervision and contract management Consultant for packages under Component 2 and tide sluice gates on route Flood risk management, and Quality And Cost- IDA / 57790 Prior Open - International 3,381,800.00 2,783,739.97 Signed 2016-07-15 2016-08-30 2016-07-21 2016-11-21 2016-10-13 2017-09-09 2016-11-10 2017-10-18 2016-12-22 2018-04-07 2017-02-20 2018-05-28 2017-04-20 2018-05-31 2020-04-19 connection with Cach Mang environmental sanitation Based Selection Thang 8 Street to Provincial road 918 (CT3-PW-2.1, CT3- PW-2.2, CT3-PW-2.3, CT3- PW-2.4, CT3-PW-2.5 and CT3- P CT3 CS TV06 / Independent Consultant Flood risk management, and Under consultant for resettlement IBRD / 85980 Post Qualification Open - National 150,000.00 132,155.49 2016-08-24 2018-08-15 2016-08-31 2016-10-26 2018-02-26 2018-04-16 2018-04-18 2018-04-28 2022-04-27 environmental sanitation Implementation supervision on project Selection CT3-CS-TV08 / Establishing Spatial planning platform and Flood Risk Management Quality And Cost- TF / A3723 financial and social Prior Open - International 1,700,000.00 1,657,588.00 Signed 2018-04-26 2018-12-04 2018-07-12 2019-01-06 2018-10-19 2019-08-12 2018-12-14 2019-08-02 2019-03-06 2019-11-27 2019-04-20 2020-05-11 2019-05-23 2020-05-18 2021-01-20 Information System (FRMIS) Based Selection protection instruments for can Tho City CT3 CS TV04 / Consulting Consultant service for monitoring and Flood risk management, and IDA / 57790 Post Qualification Open - National 150,000.00 0.00 Canceled 2016-08-24 2016-09-01 2016-10-27 2016-12-17 2017-02-06 2022-02-05 evaluation on implementation environmental sanitation Selection of project Consultancy CT3-CS-TV09 / Sustainable Urban Public Transport & Spatial planning platform and Quality And Cost- Central Area Traffic IDA / 57790 financial and social Post Open - International 475,000.00 410,263.00 Signed 2018-06-12 2018-10-08 2018-07-16 2018-10-15 2018-10-23 2019-05-13 2018-12-19 2019-06-28 2019-03-13 2019-08-26 2019-04-26 2019-09-25 2019-05-28 2019-12-12 2021-01-25 Based Selection Management Study for Can protection instruments Tho City CT3 CS TV04 / Consulting Consultant service for monitoring and Flood risk management, and IBRD / 85980 Post Qualification Open - National 220,000.00 264,483.47 Signed 2018-12-12 2019-02-18 2018-12-27 2019-02-09 2019-07-30 2019-03-11 2019-09-14 2019-03-29 2019-10-17 2021-09-25 evaluation on implementation environmental sanitation Selection of project Consultancy Spatial planning platform and CT3-CS-TV10 / Spatial Quality And Cost- TF / A3723 financial and social Prior Open - International 1,634,000.00 0.00 Canceled 2018-07-05 2018-08-08 2018-11-15 2019-01-11 2019-04-05 2019-05-20 2019-06-20 2020-12-18 Planning Platform (SPP) Based Selection protection instruments CT3-CS-TV14 / Consultancy Service for the Design, Spatial planning platform and Consultant Development and IDA / 57790 financial and social Post Qualification Open - National 267,000.00 0.00 Canceled 2018-06-30 2018-08-03 2018-11-16 2019-01-14 2019-02-15 2019-11-15 Implementation of Integrated protection instruments Selection Social Assistance (ISA) System CT3-CS-TV15 / Consulting Service to carry out a Geo- Spatial planning platform and Referenced Households Quality And Cost- Pending IDA / 57790 financial and social Post Open - National 295,000.00 0.00 2018-07-06 2018-07-27 2018-11-05 2018-12-12 2019-02-08 2019-03-25 2019-04-29 2021-12-28 Vulnerability Survey and data Based Selection Implementation protection instruments update against Flood in Can Tho City CT3 CS TV13 / Consultant of Consultant communication on the IBRD / 85980 Urban corridor development Post Qualification Open - National 93,761.00 89,091.66 Signed 2019-05-02 2019-04-17 2019-05-06 2019-07-05 2019-07-26 2019-10-21 2019-09-09 2019-11-08 2019-10-17 2021-04-29 project. Selection CT3 CS TV17 / Spatial planning platform and Transportation system Quality And Cost- Pending IDA / 57790 financial and social Prior Open - International 1,000,000.00 0.00 2020-05-18 2020-06-17 2020-09-18 2020-11-06 2020-12-16 2021-03-04 2021-04-13 2022-06-30 improvement and research Based Selection Implementation protection instruments Consultant - Phase 2 CT3 CS TV16 / Construction Supervision and contract Flood risk management, and Quality And Cost- management Consultant for IBRD / 85980 Post Open - International 356,675.00 0.00 Canceled 2020-02-28 2020-03-29 2020-05-18 2020-06-17 2020-07-17 2020-08-30 2020-09-30 2022-04-06 environmental sanitation Based Selection packages under Component 1 for Phase II CT3-CS-TV19 / Independent Consultant Flood risk management, and Consultant for auditing for IBRD / 85980 Post Qualification Open - National 100,517.00 39,678.87 Signed 2020-09-30 2021-05-04 2020-10-03 2020-10-23 2021-07-13 2020-11-24 2021-08-26 2020-11-28 2021-08-26 2023-11-28 environmental sanitation Phase 2 Selection Page 3 CT3-CS-TV16 / The Consultancy for construction Consultant supervision and contract Flood risk management, and Pending IBRD / 85980 Post Qualification Open - National 292,178.00 0.00 2020-07-04 2020-10-03 2020-10-23 2020-11-23 2020-11-28 2022-09-28 management for improving environmental sanitation Implementation Selection primary canals and urban drainage improvement. CT3-CS-TV18 / The Consultancy for construction supervision and contract Consultant Flood risk management, and Pending management for improving IBRD / 85980 Post Qualification Open - National 294,896.00 0.00 2020-07-04 2020-10-03 2020-10-23 2020-11-24 2020-11-28 2022-11-28 environmental sanitation Implementation canals and inner city branch Selection canals and lakes and CMT8 road improvement. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 4