PROCUREMENT PLAN (Textual Part) Project information: Country: Bangladesh Project name: Local Governance Support Project-3 (P159683) Project Implementation agency: Local Government Division, Ministry of Local Government, Rural Development and Cooperatives. Date of the Procurement Plan: July 13, 2017 Period covered by this Procurement Plan: July 2017 to December 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act, 2006 - PPA, 1st amendment to PPA (2009) and the Public Procurement Rules, 2008, as amended in August 2009) of the People’s Republic of Bangladesh such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a) Post bidding negotiations shall not be allowed with the lowest evaluated or any other bidder; b) Bids should be submitted and opened in public in one location immediately after the deadline for submission; c) Lottery in award of contracts shall not be allowed; d) Bidders’ qualification/experience requirement shall be mandatory e) Bids shall not be invited or rejected on the basis of percentage above or below the estimated cost. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables – Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. Prior Review Thresholds Type of Procurement Method Prior Review Thresholds Remarks Procurement (Estimated Cost of the Contract/Package) Works (including RFB, RFP, Direct Selection >=US$ 10,000,000 turnkey, supply & RFQ None installation of plant and equipment, and PPP) Goods, information RFB, RFP, Direct Selection >=US$ 2,000,000 technology and non- RFQ None consulting services Consultants: firms QCBS, QBS, FBS, CQS, >=US$ 1,000,000 Consultants for the LCS, Direct Selection project related Consultants: >=US$ 300,000 procurement Individual IC (Open, Limited), Direct activities will be Selection prior reviewed by the Bank Notes: 1. Irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: a. procurement processes involving contract negotiations as, described in paragraphs 6.34-36 of Section VI of the Procurement Regulation for Borrowers; b. competitive dialogue; c. sustainable procurement; and d. best and final offer. 2. All contracts at or above the mandatory procurement prior review thresholds are subject to international advertising; 3. Use of Standard Procurement Documents: For all procurements under the project, the Bank’s Standard Procurement Documents (or other documents agreed with the Bank) shall be used; PROCUREMENT Bangladesh : Local Governance Support Project - 3 PLAN General Information Country: Bangladesh 2017-07-17 Bank’s Approval Date of the Original Procurement Plan: 2022-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P159683 GPN Date: 2017-08-01 Project Name: Local Governance Support Project - 3 Loan / Credit No: IDA / 59460 Local Government Division Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual G-04 / Supply & Installation Audits and Performance Ass of Desktop Computers, Laser Open - Internationa Single Stage - One E IDA / 59460 essments, and Management Prior Request for Bids 5,783,380.00 3,424,039.70 Signed 2018-10-11 2018-10-23 2018-10-18 2019-01-23 2018-12-02 2019-02-06 2019-01-01 2019-07-15 2019-02-05 2019-08-25 2019-08-04 Printers, Scanners and UPS w l nvelope Information Systems ith software and all accessori es G-05 / Supply & Installation Capacity Development and P Single Stage - One E of Laptop Computers with all IDA / 59460 roject Implementation Supp Post Request for Bids Open - National 75,570.00 58,802.92 Terminated 2019-02-20 2018-09-03 2019-03-22 2019-05-03 2019-09-19 2019-06-02 2019-09-19 2019-07-07 2019-11-18 2019-10-05 nvelope accessories ort G-15 / Printing & Supply of I Capacity Development and P Single Stage - One E IDA / 59460 Post Request for Bids Open - National 62,970.00 0.00 Canceled 2018-10-14 2018-11-05 2018-11-13 2018-12-04 2018-12-03 2019-01-03 2018-12-03 2019-02-21 2019-04-22 EC Materials roject Implementation Supp nvelope ort G-12 / Printing of Union Paris Capacity Development and P Single Stage - One E IDA / 59460 Post Request for Bids Open - National 52,900.00 52,887.41 Signed 2018-04-20 2018-03-14 2018-05-20 2018-06-10 2018-04-02 2018-07-10 2018-07-23 2018-08-28 2018-09-10 2018-10-27 had(UP) Operational Manual roject Implementation Supp nvelope ort G-19 / Supply and Installatio Capacity Development and P Single Stage - One E IDA / 59460 Post Request for Bids Open - National 125,940.00 0.00 Canceled 2018-11-13 2019-07-01 2019-01-12 2019-02-02 2019-03-04 2019-04-22 2019-06-21 n of Goods to Setup Standar roject Implementation Supp nvelope d Office. ort G-07 / Supply & Installation Capacity Development and P Single Stage - One E IDA / 59460 Post Request for Bids Open - National 31,486.15 4,943.28 Signed 2019-02-12 2019-09-19 2019-03-14 2019-04-04 2019-10-07 2019-05-04 2019-11-11 2019-06-21 2019-12-01 2019-08-20 of Photocopiers roject Implementation Supp nvelope ort G-24 / Printing and Supply of Capacity Development and P Request for Quota Single Stage - One E IDA / 59460 Post Open - National 6,250.00 0.00 Canceled 2018-01-24 2018-02-13 2018-02-23 Wall Calendar of 2018 roject Implementation Supp tions nvelope ort Capacity Development and P Single Stage - One E G-02 / Supply of Microbus IDA / 59460 Post Request for Bids Open - National 62,970.00 0.00 Canceled 2017-08-20 2017-09-19 2017-10-10 2017-11-09 2017-12-14 2018-06-12 roject Implementation Supp nvelope ort G-03 / Supply of Motor Cycle Capacity Development and P Single Stage - One E IDA / 59460 Post Request for Bids Open - National 188,920.00 0.00 Canceled 2018-01-25 2018-02-24 2018-04-07 2018-05-07 2018-06-11 2018-12-08 s roject Implementation Supp nvelope ort G-01 / Supply of Cross Count Capacity Development and P IDA / 59460 Post Direct Selection Direct 100,760.00 0.00 Canceled 2017-08-13 2017-09-12 2017-11-30 2018-05-29 ry Vehicle (4WD) roject Implementation Supp ort G-15-1 / Printing & Supply of Capacity Development and P Single Stage - One E IDA / 59460 Post Request for Bids Open - National 62,970.00 47,512.43 Signed 2019-08-20 2019-10-15 2019-09-09 2019-09-30 2019-10-31 2019-10-14 2019-11-05 2019-11-11 2019-12-23 2019-12-23 IEC Materials roject Implementation Supp nvelope ort G-27 / Printing and Supply of Capacity Development and P Single Stage - One E Grievance Redress Mechanis IDA / 59460 roject Implementation Supp Post Request for Bids Open - National 78,715.36 28,793.95 Signed 2019-09-15 2019-10-14 2019-09-22 2019-10-13 2019-10-30 2019-10-20 2019-11-07 2019-11-24 2020-01-15 2019-12-22 nvelope m (GRM) Handout ort G-08 / Supply & Installation Capacity Development and P Single Stage - One E of ICT Networking with acces IDA / 59460 roject Implementation Supp Post Request for Bids Open - National 12,590.00 0.00 Canceled 2021-02-02 2021-02-22 2021-03-15 2021-04-14 2021-06-02 2021-08-31 nvelope sories(PMU & LGD) ort G-09 / Supply & Installation Capacity Development and P Single Stage - One E IDA / 59460 Post Request for Bids Open - National 25,190.00 0.00 Canceled 2021-02-04 2021-03-04 2021-03-25 2021-04-24 2021-06-12 2021-09-10 of Computer Accessories roject Implementation Supp nvelope ort G-10 / Supply & Installation Capacity Development and P Single Stage - One E of Furniture(Chairs, Tables, A IDA / 59460 roject Implementation Supp Post Request for Bids Open - National 25,190.00 0.00 Canceled 2021-02-08 2021-03-10 2021-03-31 2021-04-30 2021-06-18 2021-09-16 nvelope lmirahs, File Cabinates etc.) ort G-21 / Supply and Installatio Capacity Development and P Single Stage - One E n of Computer, Furniture and IDA / 59460 roject Implementation Supp Post Request for Bids Open - National 75,570.00 0.00 Canceled 2021-02-18 2021-03-04 2021-03-25 2021-04-24 2021-06-12 2021-07-24 nvelope Networking Equipments for M ort IS Help Desk G-11 / Supply & Installation Capacity Development and P Request for Quota Single Stage - One E IDA / 59460 Post Open - National 6,300.00 0.00 Canceled 2020-12-20 2021-01-10 2021-02-07 of Air Coolers roject Implementation Supp tions nvelope ort G-26 / Supply of Office Stati Capacity Development and P Request for Quota Single Stage - One E IDA / 59460 Post Open - National 6,250.00 0.00 Canceled 2021-01-25 2021-02-14 2021-03-16 onery roject Implementation Supp tions nvelope ort G-25 / Printing of Pourashav Capacity Development and P Request for Quota Single Stage - One E IDA / 59460 Post Open - National 6,250.00 0.00 Canceled 2020-12-20 2021-01-09 2021-02-06 a Operational Manual roject Implementation Supp tions nvelope ort G-16 / Supply of Antivirus for Capacity Development and P Request for Quota Single Stage - One E IDA / 59460 Post Open - National 6,300.00 0.00 Canceled 2021-03-02 2021-03-23 2021-04-20 Desktops & Laptops roject Implementation Supp tions nvelope ort G-30 / Printing & Supply of A Capacity Development and P Request for Quota Single Stage - One E nnual Diary, Annual Calendar IDA / 59460 roject Implementation Supp Post Open - National 2,982.56 0.00 Canceled 2020-11-19 2020-12-05 2020-12-26 tions nvelope & Desk Calendar ort G-17 / Printing & Supply of M Capacity Development and P Request for Quota Single Stage - One E IDA / 59460 Post Open - National 6,300.00 0.00 Canceled 2019-08-04 2019-08-25 2019-09-08 id-Term Review Report roject Implementation Supp tions nvelope ort G-14 / Supply of Office Satio Capacity Development and P Single Stage - One E IDA / 59460 Post Request for Bids Open - National 37,780.00 0.00 Canceled 2019-07-17 2019-08-16 2019-09-06 2019-10-06 2019-11-24 2020-01-23 nery-2 roject Implementation Supp nvelope ort G-20 / Supply and installatio Capacity Development and P Request for Quota Single Stage - One E IDA / 59460 Post Open - National 6,297.23 0.00 Canceled 2021-01-24 2021-02-14 2021-02-28 n of Accounting Software -ER roject Implementation Supp tions nvelope P. ort Page 1 G-23 / Supply and installatio Capacity Development and P Single Stage - One E IDA / 59460 Post Request for Bids Open - National 12,594.46 0.00 Canceled 2021-02-09 2021-02-23 2021-03-16 2021-04-15 2021-06-03 2021-08-02 n of Audit Management Soft roject Implementation Supp nvelope ware. ort G-28 / Printing, Publication, Capacity Development and P Single Stage - One E Under Imple IDA / 59460 Post Request for Bids Open - National 29,192.00 0.00 2020-11-15 2021-04-04 2020-11-22 2020-12-13 2021-04-21 2020-12-20 2021-07-01 2021-01-24 2021-12-31 and Supply of LGSP-3 Newsle roject Implementation Supp nvelope mentation tter ort G-29 / Printing and Supply of Capacity Development and P Single Stage - One E Under Imple Union Parishad Development IDA / 59460 roject Implementation Supp Post Request for Bids Open - National 78,200.45 0.00 2021-08-22 2021-10-21 2021-08-29 2021-09-19 2021-11-07 2021-09-26 2021-12-06 2021-10-31 2021-12-30 nvelope mentation Assistance Utilization Guideli ort nes G-06 / Supply & Installation Capacity Development and P Single Stage - One E IDA / 59460 Post Request for Bids Open - National 18,890.00 0.00 Canceled 2021-09-01 2021-09-06 2021-09-27 2021-10-11 2021-11-01 2021-12-13 of Video Conferencing Syste roject Implementation Supp nvelope m ort G-07-2 / Supply & Installatio Capacity Development and P Single Stage - One E Under Imple IDA / 59460 Post Request for Bids Open - National 23,568.23 0.00 2021-08-26 2021-11-25 2021-09-02 2021-09-23 2021-12-13 2021-10-07 2021-11-11 2021-12-23 n of Photocopier roject Implementation Supp nvelope mentation ort G-22 / Supply & Installation Capacity Development and P Request for Quota Single Stage - One E IDA / 59460 Post Open - National 1,890.00 0.00 Canceled 2021-09-03 2021-09-26 2021-10-10 of Color Printer with all acces roject Implementation Supp tions nvelope sories ort G-05-1 / Supply & Installatio Capacity Development and P Single Stage - One E Under Imple n of Laptop Computers with IDA / 59460 roject Implementation Supp Post Request for Bids Open - National 69,979.01 0.00 2021-12-10 2022-01-23 2021-12-24 2022-01-07 2022-01-21 2022-03-04 2022-04-15 nvelope mentation all accessories ort G-35 / Printing and Publicati Capacity Development and P Single Stage - One E Under Imple on of Book on 'Union, Village IDA / 59460 roject Implementation Supp Post Request for Bids Open - National 19,326.39 0.00 2022-01-31 2022-04-11 2022-02-05 2022-02-26 2022-03-05 2022-04-09 2022-05-07 nvelope mentation and Historical Places of Bangl ort adesh' G-36 / Supply & Installation Capacity Development and P Single Stage - One E Pending Impl IDA / 59460 Post Request for Bids Open - National 20,547.95 0.00 2022-06-10 2022-06-17 2022-07-08 2022-07-15 2022-08-15 2022-09-19 of Photocopiers roject Implementation Supp nvelope ementation ort NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NS 04 / Supply of Support St Capacity Development and P aff Services by a Firm Throug IDA / 59460 roject Implementation Supp Prior Direct Selection Direct 2,000,755.67 2,388,232.23 Signed 2017-09-14 2017-09-26 2017-09-21 2017-11-09 2017-11-07 2021-12-31 h Outsourcing ort NS-04 / Supply of Support St Capacity Development and P Single Stage - One E aff Services by a Firm Throug IDA / 59460 roject Implementation Supp Prior Request for Bids Open - National 2,096,977.33 0.00 Canceled 2017-08-30 2017-09-29 2017-10-20 2017-11-17 2018-02-13 2022-01-03 nvelope h Outsourcing ort NS-01 / Appointment of C&F Capacity Development and P Request for Quota Single Stage - One E IDA / 59460 Post Open - National 6,300.00 3,540.23 Signed 2018-09-09 2018-09-30 2020-01-05 2018-10-14 Agent for clearing Goods at P roject Implementation Supp tions nvelope ort of Entry. ort NS-02 / Appointment of a Se Capacity Development and P Single Stage - One E rvice Provider for Manageme IDA / 59460 roject Implementation Supp Post Request for Bids Open - National 629,720.00 0.00 Canceled 2018-11-01 2019-07-01 2018-12-01 2018-12-22 2019-01-21 2019-03-11 2020-03-05 nvelope nt of Foreign Tours ort NS-05 / Hiring a Media Firm f Capacity Development and P Single Stage - One E IDA / 59460 Post Request for Bids Open - National 117,647.06 0.00 Canceled 2018-10-09 2018-09-30 2018-10-11 2018-10-17 2018-10-22 2018-10-20 2018-11-01 2019-04-29 2018-11-15 2021-12-31 or Production of Training Vid roject Implementation Supp nvelope eos ort NS-05-2 / Hiring a Firm for Pr Capacity Development and P Single Stage - One E IDA / 59460 Post Request for Bids Open - National 117,647.06 0.00 Canceled 2020-11-17 2020-11-22 2020-12-13 2020-12-27 2021-01-24 2021-05-24 oduction of Training Videos roject Implementation Supp nvelope ort NS-05-1 / Hiring a Firm for Pr Capacity Development and P Single Stage - One E IDA / 59460 Post Request for Bids Open - National 117,647.06 0.00 Canceled 2019-08-01 2019-10-27 2019-08-06 2019-08-27 2019-11-18 2019-09-10 2019-10-08 2021-12-31 oduction of Training Videos roject Implementation Supp nvelope ort NS-03 / Appointment of a Se Capacity Development and P Single Stage - One E IDA / 59460 Post Request for Bids Open - National 440,810.00 0.00 Canceled 2018-09-12 2018-10-12 2018-11-02 2018-12-02 2019-01-20 2019-03-06 rvice Provider for Event Mana roject Implementation Supp nvelope gement ort NS-08 / Holding Workshops, Capacity Development and P Single Stage - One E Under Imple Publication of Feature & Awa IDA / 59460 roject Implementation Supp Post Request for Bids Open - National 188,403.19 0.00 2021-09-02 2021-12-09 2021-09-07 2021-09-28 2021-10-12 2021-11-16 2022-08-13 nvelope mentation rd for Best Reporting & Photo ort graphy NS-06 / Production and Broa Capacity Development and P Single Stage - One E IDA / 59460 Post Request for Bids Open - National 303,194.92 0.00 Canceled 2021-09-07 2021-12-09 2021-09-12 2021-10-03 2021-12-30 2021-10-17 2021-11-21 2022-05-20 dcasting of TV & Radio Adver roject Implementation Supp nvelope tisement ort NS-07 / Production and Broa Capacity Development and P dcasting of Drama and Video Single Stage - One E IDA / 59460 roject Implementation Supp Post Request for Bids Open - National 277,483.17 0.00 Canceled 2021-08-31 2021-12-09 2021-09-05 2021-09-26 2021-12-30 2021-10-10 2021-11-14 2022-08-11 Documentary, Talk Show in T nvelope ort V & Community Radio NS-02-1 / Appointment of a Capacity Development and P Under Imple Service Provider for Manage IDA / 59460 roject Implementation Supp Post Request for Bids 246,482.43 0.00 2021-10-17 2021-11-14 2021-10-31 2021-11-21 2021-12-12 2022-01-16 2022-12-31 mentation ment of Foreign Tours ort CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual S-19 / Selection & Employm ent of Audit Firm for Annual E xternal Financial Audit and P Audits and Performance Ass Fixed Budget Sele erformance & Safeguards Co IDA / 59460 essments, and Management Post Open - National 144,840.00 99,154.93 Signed 2017-09-14 2017-08-27 2017-10-14 2017-09-13 2017-11-25 2017-11-26 2017-12-23 2017-12-26 2018-02-03 2018-01-29 2018-03-10 2018-02-11 2018-04-21 2018-03-08 2021-12-31 ction mpliance Assessment of Unio Information Systems n Parishads and Pourashavas (if applicable) of Jhalokathi, P irojpur & Barisal Districts S-20 / Selection & Employm ent of Audit Firm for Annual E xternal Financial Audit and P Audits and Performance Ass Fixed Budget Sele erformance & Safeguards Co IDA / 59460 essments, and Management Post Open - National 144,840.00 113,608.51 Signed 2017-09-14 2017-08-27 2017-10-14 2017-10-26 2017-11-25 2017-11-26 2017-12-23 2017-12-26 2018-02-03 2018-01-29 2018-03-10 2018-02-11 2018-04-21 2018-03-08 2021-12-31 ction mpliance Assessment of Unio Information Systems n Parishads and Pourashavas (if applicable) of Barguna, Bh ola & Patuakhali Districts Page 2 S-21 / Selection & Employm ent of Audit Firm for Annual E xternal Financial Audit and P Audits and Performance Ass Fixed Budget Sele erformance & Safeguards Co IDA / 59460 essments, and Management Post Open - National 220,400.00 166,027.34 Signed 2017-09-14 2017-08-27 2017-10-14 2017-11-25 2017-11-26 2017-12-23 2017-12-26 2018-02-03 2018-01-29 2018-03-10 2018-02-11 2018-04-21 2018-03-08 2021-12-31 ction mpliance Assessment of Unio Information Systems n Parishads and Pourashavas (if applicable) of Brahmanbar ia & Comilla Districts S-22 / Selection & Employm ent of Audit Firm for Annual E xternal Financial Audit and P Audits and Performance Ass Fixed Budget Sele erformance & Safeguards Co IDA / 59460 essments, and Management Post Open - National 220,400.00 163,429.76 Signed 2017-09-14 2017-08-27 2017-10-14 2017-11-25 2017-11-26 2017-12-23 2017-12-26 2018-02-03 2018-01-29 2018-03-10 2018-02-11 2018-04-21 2018-03-08 2021-12-31 ction mpliance Assessment of Unio Information Systems n Parishads and Pourashavas (if applicable) of Feni, Laksh mipur & Chandpur Noakhali Districts S-23 / Selection & Employm ent of Audit Firm for Annual E xternal Financial Audit and P Audits and Performance Ass Fixed Budget Sele erformance & Safeguards Co IDA / 59460 essments, and Management Post Open - National 220,400.00 165,623.92 Signed 2017-09-14 2017-08-27 2017-10-14 2017-11-25 2017-11-26 2017-12-23 2017-12-26 2018-02-03 2018-01-29 2018-03-10 2018-02-11 2018-04-21 2018-03-08 2021-12-31 ction mpliance Assessment of Unio Information Systems n Parishads and Pourashavas (if applicable) of Chittagong, Khagrachhari & Rangamati D istricts S-24 / Selection & Employm ent of Audit Firm for Annual E xternal Financial Audit and P Audits and Performance Ass Fixed Budget Sele erformance & Safeguards Co IDA / 59460 essments, and Management Post Open - National 94,460.00 64,431.56 Signed 2017-09-14 2017-08-27 2017-10-14 2017-11-25 2017-11-26 2017-12-23 2017-12-26 2018-02-03 2018-01-29 2018-03-10 2018-02-11 2018-04-21 2018-03-08 2021-12-31 ction mpliance Assessment of Unio Information Systems n Parishads and Pourashavas (if applicable) of Bandarban & Cox's Bazar Districts S-25 / Selection & Employm ent of Audit Firm for Annual E xternal Financial Audit and P Audits and Performance Ass Fixed Budget Sele erformance & Safeguards Co IDA / 59460 essments, and Management Post Open - National 188,920.00 133,843.49 Signed 2017-09-18 2017-08-27 2017-10-18 2017-11-29 2017-11-26 2017-12-27 2017-12-26 2018-02-07 2018-01-29 2018-03-14 2018-02-11 2018-04-25 2018-03-08 2021-12-31 ction mpliance Assessment of Unio Information Systems n Parishads and Pourashavas (if applicable) of Sherpur, Ta ngail & Jamalpur Districts S-26 / Selection & Employm ent of Audit Firm for Annual E xternal Financial Audit and P Audits and Performance Ass Fixed Budget Sele erformance & Safeguards Co IDA / 59460 essments, and Management Post Open - National 188,920.00 134,791.26 Signed 2017-09-18 2017-08-27 2017-10-18 2017-11-29 2017-11-26 2017-12-27 2017-12-26 2018-02-07 2018-01-29 2018-03-14 2018-02-11 2018-04-25 2018-03-08 2021-12-31 ction mpliance Assessment of Unio Information Systems n Parishads and Pourashavas (if applicable) of Netrokona & Mymensingh Districts S-27 / Selection & Employm ent of Audit Firm for Annual E xternal Financial Audit and P Audits and Performance Ass Fixed Budget Sele erformance & Safeguards Co IDA / 59460 essments, and Management Post Open - National 163,730.00 123,116.51 Signed 2017-09-18 2017-08-27 2017-10-18 2017-11-29 2017-11-26 2017-12-27 2017-12-26 2018-02-07 2018-01-29 2018-03-14 2018-02-11 2018-04-25 2018-03-08 2021-12-31 ction mpliance Assessment of Unio Information Systems n Parishads and Pourashavas (if applicable) of Gazipur, Nar singdi & Kishoreganj Districts S-28 / Selection & Employm ent of Audit Firm for Annual E xternal Financial Audit and P Audits and Performance Ass Fixed Budget Sele erformance & Safeguards Co IDA / 59460 essments, and Management Post Open - National 188,920.00 127,922.76 Signed 2017-09-18 2017-08-27 2017-10-18 2017-11-29 2017-11-26 2017-12-27 2017-12-26 2018-02-07 2018-01-29 2018-03-14 2018-02-11 2018-04-25 2018-03-08 2021-12-31 ction mpliance Assessment of Unio Information Systems n Parishads and Pourashavas (if applicable) of Narayanganj , Manikganj, Munshiganj & D haka S-29 / Selection & Employm ent of Audit Firm for Annual E xternal Financial Audit and P Audits and Performance Ass Fixed Budget Sele erformance & Safeguards Co IDA / 59460 essments, and Management Post Open - National 94,460.00 71,658.33 Signed 2017-09-18 2017-08-27 2017-10-18 2017-11-29 2017-11-26 2017-12-27 2017-12-26 2018-02-07 2018-01-29 2018-03-14 2018-02-11 2018-04-25 2018-03-08 2021-12-31 ction mpliance Assessment of Unio Information Systems n Parishads and Pourashavas (if applicable) of Rajbari & Fa ridpur Districts S-30 / Selection & Employm ent of Audit Firm for Annual E xternal Financial Audit and P Audits and Performance Ass Fixed Budget Sele erformance & Safeguards Co IDA / 59460 essments, and Management Post Open - National 151,130.00 111,954.17 Signed 2017-09-18 2017-08-27 2017-10-18 2017-11-29 2017-11-26 2017-12-27 2017-12-26 2018-02-07 2018-01-29 2018-03-14 2018-02-11 2018-04-25 2018-03-08 2021-12-31 ction mpliance Assessment of Unio Information Systems n Parishads and Pourashavas (if applicable) of Madaripur, Gopalganj & Shariatpur Distri cts S-31 / Selection & Employm ent of Audit Firm for Annual E xternal Financial Audit and P Audits and Performance Ass erformance & Safeguards Co Fixed Budget Sele IDA / 59460 essments, and Management Post Open - National 151,130.00 109,359.48 Signed 2017-09-25 2017-08-27 2017-10-25 2017-12-06 2017-11-26 2018-01-03 2017-12-26 2018-02-14 2018-01-29 2018-03-21 2018-02-11 2018-05-02 2018-03-08 2021-12-31 mpliance Assessment of Unio ction Information Systems n Parishads and Pourashavas (if applicable)of Meherpur, C huadanga, Kushtia & Jhenida ha Districts S-32 / Selection & Employm ent of Audit Firm for Annual E xternal Financial Audit and P Audits and Performance Ass Fixed Budget Sele erformance & Safeguards Co IDA / 59460 essments, and Management Post Open - National 138,540.00 97,571.09 Signed 2017-09-25 2017-08-27 2017-10-25 2017-12-06 2017-11-26 2018-01-03 2017-12-26 2018-02-14 2018-01-29 2018-03-21 2018-02-11 2018-05-02 2018-03-08 2021-12-31 ction mpliance Assessment of Unio Information Systems n Parishads and Pourashavas (if applicable) of Magura, Nar ail & Jessore Districts S-33 / Selection & Employm ent of Audit Firm for Annual E xternal Financial Audit and P Audits and Performance Ass Fixed Budget Sele erformance & Safeguards Co IDA / 59460 essments, and Management Post Open - National 176,320.00 128,741.20 Signed 2017-09-25 2017-08-27 2017-10-25 2017-12-06 2017-11-26 2018-01-03 2017-12-26 2018-02-14 2018-01-29 2018-03-21 2018-02-11 2018-05-02 2018-03-08 2021-12-31 ction mpliance Assessment of Unio Information Systems n Parishads and Pourashava(i f applicable) of Khulna, Bager hat & Shatkhira Districts S-34 / Selection & Employm ent of Audit Firm for Annual E xternal Financial Audit and P Audits and Performance Ass Fixed Budget Sele erformance & Safeguards Co IDA / 59460 essments, and Management Post Open - National 157,430.00 117,036.97 Signed 2017-09-25 2017-08-27 2017-10-25 2017-12-06 2017-11-26 2018-01-03 2017-12-26 2018-02-14 2018-01-29 2018-03-21 2018-02-11 2018-05-02 2018-03-08 2021-12-31 ction mpliance Assessment of Unio Information Systems n Parishads and Pourashavas (if applicable) of Thakurgaon, Dinajpur & Panchagarh Distri cts Page 3 S-35 / Selection & Employm ent of Audit Firm for Annual E xternal Financial Audit and P Audits and Performance Ass erformance & Safeguards Co Fixed Budget Sele IDA / 59460 essments, and Management Post Open - National 201,510.00 147,913.94 Signed 2017-09-25 2017-08-27 2017-10-25 2017-12-06 2017-11-26 2018-01-03 2017-12-26 2018-02-14 2018-01-29 2018-03-21 2018-02-11 2018-05-02 2018-03-08 2021-12-31 mpliance Assessment of Unio ction Information Systems n Parishads and Pourashavas (if applicable) of Kurigram, La lmonirhat, Nilphamari & Ran gpur Districts S-36 / Selection & Employm ent of Audit Firm for Annual E xternal Financial Audit and P Audits and Performance Ass Fixed Budget Sele erformance & Safeguards Co IDA / 59460 essments, and Management Post Open - National 176,320.00 129,246.15 Signed 2017-10-05 2017-08-27 2017-11-04 2017-12-16 2017-11-26 2018-01-13 2017-12-26 2018-02-24 2018-01-29 2018-03-31 2018-02-11 2018-05-12 2018-03-08 2021-12-31 ction mpliance Assessment of Unio Information Systems n Parishads and Pourashavas (if applicable) of Joypurhat, B ogra & Gaibandha Districts S-37 / Selection & Employm ent of Audit Firm for Annual E xternal Financial Audit and P Audits and Performance Ass Fixed Budget Sele erformance & Safeguards Co IDA / 59460 essments, and Management Post Open - National 163,730.00 125,867.88 Signed 2017-10-05 2017-08-27 2017-11-04 2017-12-16 2017-11-26 2018-01-13 2017-12-26 2018-02-24 2018-01-29 2018-03-31 2018-02-11 2018-05-12 2018-03-08 2021-12-31 ction mpliance Assessment of Unio Information Systems n Parishads and Pourashavas (if applicable) of Chapainawa bga, Naogaon & Rajshahi Dis tricts S-38 / Selection & Employm ent of Audit Firm for Annual E xternal Financial Audit and P Audits and Performance Ass Fixed Budget Sele erformance & Safeguards Co IDA / 59460 essments, and Management Post Open - National 163,730.00 121,845.29 Signed 2017-10-05 2017-08-27 2017-11-04 2017-12-16 2017-11-26 2018-01-13 2017-12-26 2018-02-24 2018-01-29 2018-03-31 2018-02-11 2018-05-12 2018-03-08 2021-12-31 ction mpliance Assessment of Unio Information Systems n Parishads and Pourashavas (if applicable) of Natore, Pab na & Sirajganj Districts S-39 / Selection & Employm ent of Audit Firm for Annual E xternal Financial Audit and P Audits and Performance Ass Fixed Budget Sele erformance & Safeguards Co IDA / 59460 essments, and Management Post Open - National 151,130.00 115,645.93 Signed 2017-10-05 2017-08-27 2017-11-04 2017-12-16 2017-11-26 2018-01-13 2017-12-26 2018-02-24 2018-01-29 2018-03-31 2018-02-11 2018-05-12 2018-03-08 2021-12-31 ction mpliance Assessment of Unio Information Systems n Parishads and Pourashavas (if applicable) of Sylhet & Su namganj Districts S-40 / Selection & Employm ent of Audit Firm for Annual E xternal Financial Audit and P Audits and Performance Ass Fixed Budget Sele erformance & Safeguards Co IDA / 59460 essments, and Management Post Open - National 113,350.00 74,089.48 Signed 2017-10-05 2017-08-27 2017-11-04 2017-12-16 2017-11-26 2018-01-13 2017-12-26 2018-02-24 2018-01-29 2018-03-31 2018-02-11 2018-05-12 2018-03-08 2021-12-31 ction mpliance Assessment of Unio Information Systems n Parishads and Pourashavas (if applicable) of Moulvibazar & Habiganj Districts S-41 / Selection & Employm Audits and Performance Ass Fixed Budget Sele ent of UP and Pourashavas(if IDA / 59460 essments, and Management Post Open - National 125,940.00 116,617.47 Signed 2017-09-14 2017-08-20 2017-10-14 2017-09-13 2017-11-25 2017-12-04 2017-12-23 2018-02-03 2018-04-05 2018-03-10 2018-04-10 2018-04-21 2018-05-09 2021-12-31 ction applicable) Audit Review Fir Information Systems m- Dhaka Division S-42 / Selection & Employm Audits and Performance Ass ent of UP and Pourashavas(if Fixed Budget Sele IDA / 59460 essments, and Management Post Open - National 100,760.00 91,082.10 Signed 2017-09-14 2017-08-20 2017-10-14 2017-11-25 2017-12-04 2017-12-23 2018-02-03 2018-04-05 2018-03-10 2018-04-10 2018-04-21 2018-05-09 2021-12-31 applicable) Audit Review Fir ction Information Systems m - Chittagong Division S-43 / Selection & Employm Audits and Performance Ass ent of UP and Pourashavas(if Fixed Budget Sele IDA / 59460 essments, and Management Post Open - National 113,350.00 105,094.73 Signed 2017-09-14 2017-08-20 2017-10-14 2017-11-25 2017-12-04 2017-12-23 2018-02-03 2018-04-05 2018-03-10 2018-04-10 2018-04-21 2018-05-09 2021-12-31 applicable) Audit Review Fir ction Information Systems m- Rajshahi & Rangpur Divisi ons S-44 / Selection & Employm Audits and Performance Ass ent of UP and Pourashavas(if Fixed Budget Sele IDA / 59460 essments, and Management Post Open - National 138,540.00 121,679.48 Signed 2017-09-14 2017-08-27 2017-10-14 2017-11-25 2017-12-04 2017-12-23 2018-02-03 2018-04-05 2018-03-10 2018-04-10 2018-04-21 2018-05-09 2021-12-31 applicable) Audit Review Fir ction Information Systems m- Khulna, Barisal & Sylhet D ivision S-49 / Selection and Employ ment of a Firm for Upgradati Audits and Performance Ass Quality And Cost- on & maintenance of existing IDA / 59460 essments, and Management Post Open - National 251,500.00 308,417.47 Signed 2018-06-20 2018-09-30 2018-07-11 2018-10-17 2018-11-08 2018-12-26 2018-12-06 2019-01-03 2019-01-05 2019-04-23 2019-02-09 2019-05-14 2019-03-16 2019-05-30 2021-12-31 Based Selection MIS, development of Offline Information Systems & Smart Mobile Tech and ens uring O&M Support S-50 / Selection of Audit Fir m for Annual External Financi Audits and Performance Ass Fixed Budget Sele al Audit and Performance & S IDA / 59460 essments, and Management Post Open - National 54,110.11 28,874.70 Signed 2018-10-21 2019-01-23 2018-11-20 2019-01-01 2019-04-16 2019-01-29 2019-05-13 2019-03-12 2019-05-13 2019-04-16 2019-05-14 2019-05-28 2019-05-30 2021-12-31 ction afeguards Compliance Asses Information Systems sment of Pilot Pourashavas S-18 / Selection and Employ Capacity Development and P ment of a Firm for Informatio Quality And Cost- IDA / 59460 roject Implementation Supp Post Open - National 472,241.00 0.00 Canceled 2018-11-15 2019-06-30 2018-12-15 2019-01-26 2019-10-10 2019-02-23 2019-04-06 2019-05-11 2019-06-22 2020-06-21 n, Education and Communica Based Selection ort tion (IEC) activities. S-48 / Selection & Employm Capacity Development and P ent of a Firm for developmen Quality And Cost- IDA / 59460 roject Implementation Supp Post Open - National 62,970.00 0.00 Canceled 2017-08-14 2017-09-28 2017-11-18 2017-12-16 2018-01-15 2018-02-19 2018-04-11 2021-12-31 t of a mobile based on-line re Based Selection ort al time Smart Monitoring Sys tem S-47 / Selection and Employ ment of a Firm for (i) Support & maintenance of MIS Softwa Audits and Performance Ass Quality And Cost- re, (ii) Production of Offline T IDA / 59460 essments, and Management Post Open - National 226,700.00 0.00 Canceled 2017-09-14 2017-10-05 2017-11-18 2017-12-16 2018-01-15 2018-02-19 2018-03-26 2021-12-31 Based Selection ools for MIS system in UPs, a Information Systems nd (iii) Software Developmen t, Operation and Maintenanc e of MIS Help Desk. S-45 / Selection & Employm Capacity Development and P Quality And Cost- ent of a Firm for Mid-term an IDA / 59460 roject Implementation Supp Post Open - National 125,950.00 0.00 Canceled 2018-10-16 2019-05-13 2018-10-30 2018-11-09 2019-06-24 2018-12-07 2019-07-29 2018-12-14 2019-07-30 2018-12-19 2019-01-20 2021-12-31 Based Selection d Final Evaluation of LGSP-3 ort S-46 / Selection & Employm Capacity Development and P Quality And Cost- IDA / 59460 Post Open - National 75,570.00 0.00 Canceled 2020-04-08 2020-05-08 2020-06-19 2020-07-17 2020-08-28 2020-10-02 2020-11-13 2021-03-13 ent of Final Evaluation Firm roject Implementation Supp Based Selection ort S-45-1 / Selection & Employ Capacity Development and P ment of a Firm for Final Evalu Quality And Cost- Under Implement IDA / 59460 roject Implementation Supp Post Open - National 294,637.60 0.00 2021-02-18 2022-02-17 2021-02-28 2021-03-10 2021-04-07 2021-04-14 2021-04-19 2021-05-21 2021-09-18 ation of Local Governance Su Based Selection ation ort pport Project-3 (LGSP-3) S-53 / Selection and Employ Capacity Development and P ment of a Firm reviewing Proj Quality And Cost- IDA / 59460 roject Implementation Supp Post Open - National 176,782.56 0.00 Canceled 2020-04-15 2020-04-29 2020-05-09 2020-06-06 2020-06-13 2020-06-18 2020-07-20 2021-12-31 ect Experiences of Local Gov Based Selection ort ernance Support Project-3 (L GSP-3) Page 4 S-51 / Selection of Audit Rev iew Firm for review of Report Audits and Performance Ass s of Financial Audits, Perform Fixed Budget Sele IDA / 59460 essments, and Management Post Open - National 8,862.18 0.00 Canceled 2018-10-21 2019-05-05 2018-11-20 2019-01-01 2019-01-29 2019-03-12 2019-04-16 2019-05-28 2021-12-31 ance Assessments and Fiduci ction Information Systems ary & Safeguard Compliance Assessments of Pilot Pourash avas S-54 / Selection and Employ Capacity Development and P ment of a Firm for Preparatio Consultant Qualifi Under Implement IDA / 59460 roject Implementation Supp Post Open - National 28,596.72 0.00 2021-01-21 2021-02-09 2021-02-11 2021-03-27 2021-04-26 2021-05-31 2021-09-28 n, Printing & Publication of G cation Selection ation ort ood Practice Compendium INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual S-05 / Selection & Employm Capacity Development and P Individual Consult IDA / 59460 Prior Open 302,270.00 364,486.17 Signed 2017-07-10 2017-08-24 2017-09-22 2017-12-28 2017-10-13 2018-01-05 2017-11-24 2018-01-08 2021-12-31 ent of Sr. Procurement Speci roject Implementation Supp ant Selection alist ort S-09 / Selection & Employm Capacity Development and P Individual Consult IDA / 59460 Post Open 226,700.00 188,167.69 Signed 2017-08-10 2017-11-19 2017-10-28 2018-06-12 2017-11-18 2018-06-21 2017-12-30 2018-06-24 2021-12-31 ent of Capacity Building Spec roject Implementation Supp ant Selection ialist ort S-10 / Selection & Employm Capacity Development and P Individual Consult Under Implement IDA / 59460 Post Open 226,700.00 0.00 2017-08-10 2017-08-22 2017-10-28 2017-11-18 2017-12-30 2021-12-31 ent of Audit Specialist roject Implementation Supp ant Selection ation ort S-12 / Selection & Employm Capacity Development and P Individual Consult Under Implement IDA / 59460 Post Open 151,130.00 0.00 2017-07-10 2017-07-27 2017-09-22 2017-10-13 2017-11-24 2021-12-31 ent of Audit Associate roject Implementation Supp ant Selection ation ort S-14 / Selection & Employm Capacity Development and P Individual Consult IDA / 59460 Post Open 151,130.00 139,755.26 Signed 2017-07-10 2017-07-27 2017-09-22 2018-01-08 2017-10-13 2018-01-09 2017-11-24 2018-01-10 2021-12-31 ent of Grant Management As roject Implementation Supp ant Selection sociate ort S-15 / Selection & Employm Capacity Development and P Individual Consult IDA / 59460 Prior Open 60,450.00 72,043.87 Signed 2017-07-10 2017-08-24 2017-09-22 2018-01-18 2017-10-13 2018-01-25 2017-11-24 2018-02-01 2019-11-14 ent of Procurement Associate roject Implementation Supp ant Selection ort S-16 / Selection & Employm Capacity Development and P Individual Consult IDA / 59460 Post Open 151,130.00 112,727.51 Signed 2017-07-10 2017-07-27 2017-09-22 2018-10-29 2017-10-13 2018-10-31 2017-11-24 2018-11-28 2021-12-31 ent of Administrative Associa roject Implementation Supp ant Selection te ort S-06 / Selection & Employm Capacity Development and P Individual Consult Under Implement IDA / 59460 Post Open 261,960.00 287,672.92 2017-09-23 2017-08-20 2017-12-11 2017-11-21 2018-01-08 2017-12-04 2018-03-05 2021-12-31 ent of Sr. Audit Specialist roject Implementation Supp ant Selection ation ort S 01 / Selection and Employ Capacity Development and P Individual Consult ment of Sr. Grant Manageme IDA / 59460 roject Implementation Supp Post Open 261,960.00 265,357.91 Signed 2017-08-23 2017-08-20 2017-11-10 2017-11-09 2017-12-08 2017-11-13 2018-02-02 2017-11-30 2022-01-14 ant Selection nt Specialist ort S 02 / Selection & Employme Capacity Development and P Individual Consult IDA / 59460 Post Open 261,960.00 303,734.37 Signed 2017-08-26 2017-08-01 2017-11-13 2017-11-09 2017-12-11 2017-11-13 2018-02-05 2017-11-16 2021-12-31 nt of Sr. Finance Specialist roject Implementation Supp ant Selection ort S 08 / Selection & Employme Capacity Development and P nt of Sr. Local Government S Individual Consult IDA / 59460 roject Implementation Supp Post Open 261,960.00 101,559.10 Signed 2017-10-31 2017-08-22 2018-01-18 2018-05-08 2018-02-15 2018-07-11 2018-04-12 2018-07-11 2021-12-31 pecialist(Planning, Budgeting ant Selection ort and Institution Development) S 13 / Selection & Employme Capacity Development and P Individual Consult Under Implement IDA / 59460 Post Open 261,960.00 245,709.40 2017-08-26 2017-11-13 2018-01-08 2017-12-11 2018-01-14 2018-02-05 2021-12-31 nt of Finance Associate-2 roject Implementation Supp ant Selection ation ort S-08 / Selection & Employm Capacity Development and P ent of Sr. Local Government Individual Consult IDA / 59460 roject Implementation Supp Prior Open 302,270.00 0.00 Canceled 2017-08-10 2017-08-03 2017-10-28 2017-11-18 2017-12-30 2021-12-31 Specialist(Planning, Budgetin ant Selection ort g and Institution Developmen t) S-02 / Selection & Employm Capacity Development and P Individual Consult IDA / 59460 Prior Open 302,270.00 0.00 Canceled 2017-07-10 2017-08-01 2017-09-22 2017-10-06 2017-11-03 2021-12-31 ent of Sr. Finance Specialist roject Implementation Supp ant Selection ort S-01 / Selection and Employ Capacity Development and P Individual Consult ment of Senior Grant Manage IDA / 59460 roject Implementation Supp Prior Open 302,270.00 0.00 Canceled 2017-07-10 2017-08-03 2017-09-22 2017-10-13 2017-11-24 2021-12-31 ant Selection ment Specialist ort S-13 / Selection & Employm Capacity Development and P Individual Consult IDA / 59460 Prior Open 302,270.00 0.00 Canceled 2017-07-10 2017-08-01 2017-09-22 2017-10-13 2017-11-24 2021-12-31 ent of Finance Associate-2 roject Implementation Supp ant Selection ort S 04 / Selection and Employ Capacity Development and P Individual Consult IDA / 59460 Post Open 261,960.00 256,874.40 Signed 2017-10-15 2018-02-13 2017-12-03 2018-06-21 2017-12-24 2018-06-25 2018-01-28 2018-06-25 2021-12-31 ment of Senior M&E Specialis roject Implementation Supp ant Selection t ort S-03 / Selection & Employm Capacity Development and P Individual Consult IDA / 59460 Prior Open 302,270.00 0.00 Canceled 2017-08-10 2017-10-28 2017-11-18 2017-12-30 2021-12-31 ent of Sr. MIS Specialist roject Implementation Supp ant Selection ort S-04 / Selection & Employm Capacity Development and P Individual Consult IDA / 59460 Prior Open 302,270.00 0.00 Canceled 2017-08-10 2017-10-28 2017-11-18 2017-12-30 2021-12-31 ent of Sr. M&E Specialist roject Implementation Supp ant Selection ort S-07 / Selection & Employm Capacity Development and P Individual Consult ent of Sr. Environment and S IDA / 59460 roject Implementation Supp Prior Open 302,270.00 0.00 Canceled 2017-08-10 2017-08-29 2017-10-28 2017-11-18 2017-12-30 2021-12-31 ant Selection ocial Safegaurds Specialist ort S-17-1 / Selection and Emplo Capacity Development and P Individual Consult IDA / 59460 Post Open 120,907.00 117,413.44 Signed 2018-01-16 2018-01-30 2018-03-06 2018-09-04 2018-03-27 2018-09-06 2018-05-01 2018-09-20 2021-12-31 yment of MIS Analyst roject Implementation Supp ant Selection ort S-17-2 / Selection and Emplo Capacity Development and P Individual Consult IDA / 59460 Post Open 120,907.00 118,809.68 Signed 2018-01-16 2018-01-30 2018-03-06 2018-09-06 2018-03-27 2018-09-09 2018-05-01 2018-09-10 2021-12-31 yment of MIS Analyst (Resear roject Implementation Supp ant Selection ch) ort S-17-3 / Selection and Emplo Capacity Development and P Individual Consult IDA / 59460 Post Open 120,907.00 118,900.57 Signed 2018-01-16 2018-01-30 2018-03-06 2018-09-04 2018-03-27 2018-09-06 2018-05-01 2018-09-09 2021-12-31 yment of MIS Analyst (GIS) roject Implementation Supp ant Selection ort S-17-4 / Selection and Emplo Capacity Development and P Individual Consult IDA / 59460 Post Open 120,907.00 118,900.57 Signed 2018-01-16 2018-01-30 2018-03-06 2018-09-04 2018-03-27 2018-09-06 2018-05-01 2018-09-09 2021-12-31 yment of MIS Analyst (M&E) roject Implementation Supp ant Selection ort S 07 / Selection & Employm Capacity Development and P Individual Consult ent of Sr. Environment and S IDA / 59460 roject Implementation Supp Post Open 261,960.00 71,871.50 Signed 2018-04-21 2018-02-06 2018-06-09 2018-06-24 2018-06-30 2018-06-25 2018-08-04 2018-06-28 2019-01-31 ant Selection ocial Safegaurds Specialist ort S 07 / Selection and Employ Capacity Development and P Individual Consult ment of Senior Environment IDA / 59460 roject Implementation Supp Post Open 261,960.00 0.00 Canceled 2017-09-13 2017-07-30 2017-10-18 2017-11-08 2017-12-13 2021-12-31 ant Selection and Social Safeguard Speciali ort st Page 5 S 03-1 / Selection and Emplo Capacity Development and P Individual Consult IDA / 59460 Post Limited 261,960.00 236,255.91 Signed 2018-10-11 2018-10-16 2018-10-16 2018-10-25 2018-11-06 2018-10-28 2018-12-11 2018-11-14 2021-12-31 yment of Senior MIS Specialis roject Implementation Supp ant Selection t ort S 13-1 / Selection & Employ Capacity Development and P Individual Consult Under Implement IDA / 59460 Post Open 130,980.00 0.00 2018-10-10 2018-12-28 2018-01-08 2019-01-25 2018-01-14 2019-03-22 2021-12-31 ment of Finance Associate roject Implementation Supp ant Selection ation ort S-17 / Selection & Employm Capacity Development and P Individual Consult IDA / 59460 Prior Open 604,530.00 0.00 Canceled 2017-08-10 2017-10-28 2017-11-18 2017-12-30 2021-12-31 ent of MIS Analyst-4 roject Implementation Supp ant Selection ort S 51 / Selection of Audit Revi ew Firm for review of Reports Audits and Performance Ass of Financial Audits, Performa IDA / 59460 essments, and Management Post Direct Selection Direct 4,050.27 3,996.31 Signed 2019-05-27 2019-05-05 2019-06-02 2019-05-20 2019-06-22 2019-05-30 2021-12-31 nce Assessments and Fiducia Information Systems ry & Safeguard Compliance A ssessments of Selected Pilot Pourashavas. S 04-1 / Selection and Emplo Capacity Development and P Individual Consult Under Implement IDA / 59460 Post Open 156,171.28 0.00 2019-05-28 2019-07-18 2019-07-16 2019-08-06 2019-09-10 2021-12-31 yment of Senior M&E Speciali roject Implementation Supp ant Selection ation st ort S-06-1 / Selection & Employ Capacity Development and P Individual Consult IDA / 59460 Post Direct 156,171.28 181,687.54 Signed 2019-06-19 2019-07-30 2019-06-29 2019-08-20 2019-07-20 2019-08-21 2019-08-24 2019-08-22 2020-02-20 ment of Sr. Audit Specialist roject Implementation Supp ant Selection ort S-17-1-1 / Selection and Em Capacity Development and P Individual Consult Under Implement IDA / 59460 Post Limited 78,085.64 0.00 2019-06-17 2019-08-05 2019-06-22 2019-08-20 2019-07-13 2019-08-21 2019-08-17 2021-12-31 ployment of MIS Analyst roject Implementation Supp ant Selection ation ort S 07-1 / Selection & Employ Capacity Development and P Individual Consult ment of Sr. Environment and IDA / 59460 roject Implementation Supp Post Limited 146,096.00 166,729.62 Signed 2019-08-01 2019-08-25 2019-08-06 2019-09-02 2019-08-27 2019-09-03 2019-10-01 2019-09-04 2021-12-31 ant Selection Social Safegaurds Specialist ort S 08-1 / Selection & Employ Capacity Development and P ment of Sr. Local Governmen Individual Consult IDA / 59460 roject Implementation Supp Post Limited 130,982.36 162,216.88 Signed 2019-10-15 2019-09-29 2019-10-22 2019-10-10 2019-10-27 2019-10-10 2019-11-08 2019-12-11 2021-12-31 t Specialist(Planning, Budgeti ant Selection ort ng and Institution Developme nt) S-52 / Selection & Employm Capacity Development and P Individual Consult IDA / 59460 Post Open 84,855.63 0.00 Canceled 2021-02-15 2021-04-05 2021-04-26 2021-05-31 2021-12-31 ent of Communication Specia roject Implementation Supp ant Selection list ort S-11-1 / Selection and Emplo Capacity Development and P Individual Consult Under Implement IDA / 59460 Post Limited 84,855.63 0.00 2020-11-29 2020-12-21 2020-12-03 2020-12-24 2021-01-28 2022-01-28 yment of Procurement Speci roject Implementation Supp ant Selection ation alist ort S 03 / Selection and Employ Capacity Development and P Individual Consult IDA / 59460 Post Open 261,960.00 0.00 Canceled 2017-10-15 2018-02-13 2017-12-03 2018-07-18 2017-12-24 2018-01-28 2021-12-31 ment of Senior MIS Specialist roject Implementation Supp ant Selection ort S-11 / Selection & Employm Capacity Development and P Individual Consult IDA / 59460 Prior Open 226,700.00 0.00 Canceled 2017-08-10 2017-10-28 2017-11-18 2017-12-30 2021-12-31 ent of Procurement Specialist roject Implementation Supp ant Selection ort S 07-2 / Selection & Employ Capacity Development and P Individual Consult Under Implement ment of Senior Environment IDA / 59460 roject Implementation Supp Post Limited 61,205.27 0.00 2020-12-01 2020-12-24 2020-12-06 2020-12-27 2021-01-06 2021-12-31 ant Selection ation and Social Safeguards Specia ort list Page 6