PROCUREMENT PLAN (Textual Part) P163264 - Cambodia Agricultural Sector Project information: Diversification Project Project Implementation agency: Ministry of Agriculture, Forestry and Fisheries (MAFF) Ministry of Rural Development (MRD), Ministry of Water Resources and Meteorology (MOWRAM), and Ministry of Economy and Finance (MEF) Date of the Procurement Plan: November 19, 2018 Period covered by this Procurement Plan: 18 months procurement plan Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Royal Kingdom of Cambodia’s Updated Procurement Manual for All Externally Financed Projects/Programs (“Procurement Manual”), promulgated through the Sub-decree 74 dated May 22, 2012, which is issued pursuant to Article 3 of the Kingdom of Cambodia’s Law on Public Procurement dated January 14, 2012, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. i. Procurement shall be open to eligible firms from any country; ii. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights as per attached confirming application of, and compliance with, the Bank’s Anti- Corruption Guidelines, including format; iii. Each Project shall put in place an effective complaint review system that includes review by the implementing agency and subsequent review by another party not involved in the in the procurement process, if not satisfied with the review of the implementing agency. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Other Relevant Procurement Information. Except the credit line facilities (tentatively US$30 million) under the sub- component 1.2 Financing Agriculture Diversification of the project that will be administered by the Rural Development Bank acting as the Treasury Bank on behalf of the Government, and channelled through the financial intermediaries (participating financial institutes); all the procurement activities under other components and sub-components including the matching grant facility under Cambodia Agricultural Sector Diversification Project will be governed by World Bank Procurement Regulation for IPF Borrowers, July 2016 (revised November 2017 and Revised August 2018) PROCUREMENT Cambodia : Cambodia Agricultural Sector Diversification Project PLAN General Information Country: Cambodia 2019-07-31 Bank’s Approval Date of the Original Procurement Plan: 2022-05-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163264 GPN Date: Project Name: Cambodia Agricultural Sector Diversification Project Loan / Credit No: IDA / 63660 Ministry of Agriculture, Forestry and Fisheries Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CERC-MAFF-01 / Support inp Component 5: Contingent E 2,433,541.4 2021-06-3 uts for growing the vegetable IDA / 63660 Post Direct Selection Direct 3,193,190.00 Signed 2020-11-22 2021-02-22 2020-11-27 2021-02-23 2021-01-01 2021-09-15 mergency Response 4 0 (net house, vegetable seedli ng, fertilizer, TA) National Procure MAFF-CW-3 / Post entry and Component 3: Improving Agr ment Document - Request for Quota Single Stage - One E Pending Imp 2022-05-1 plant quarantine research sta IDA / 63660 iculture Information Systems Post Open - National 1 Envelope proce 150,000.00 0.00 2021-09-19 2021-11-14 tions nvelope lementation 3 tion (Glasshouse) and Quality Control Manage ss (Non Bank-SPD ment ) MAFF-CW-2 / Renovation of L aboratories of Plant Health L National Procure aboratory for Plant Protection Component 3: Improving Agr ment Document - Sanitary and Phytosanitary ( iculture Information Systems Single Stage - One E Pending Imp 2022-06-0 IDA / 63660 Post Request for Bids Open - National 1 Envelope proce 431,500.00 0.00 2021-08-17 2021-08-22 2021-10-03 2021-11-02 2021-12-07 GDA-4 places), Renovation of and Quality Control Manage nvelope lementation 5 ss (Non Bank-SPD national and regional laborat ment ) ories for GDAHP (6 places), R enovation of Laboratory roo ms for DAI -(3 Lots) National Procure Component 3: Improving Agr ment Document - MAFF-CW-4 / Animal Quaran Single Stage - One E Pending Imp 2022-05-1 IDA / 63660 iculture Information Systems Post Request for Bids Open - National 1 Envelope proce 1,000,000.00 0.00 2021-07-30 2021-08-04 2021-09-15 2021-10-15 2021-11-19 tine/Check point (2 Places) nvelope lementation 8 and Quality Control Manage ss (Non Bank-SPD ment ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MAFF-G-5 / Motorcycles for Component 4: Project Manag UN Agencies (Dire MAFF (Central and Provicnica IDA / 63660 ement, Coordination, Monito Post Direct 136,800.00 0.00 Canceled 2019-08-15 2019-08-20 2019-10-04 2019-12-31 ct) l) ring & Evaluation Component 4: Project Manag MAFF-G-4 / Vehicles (Station UN Agencies (Dire IDA / 63660 ement, Coordination, Monito Post Direct 118,000.00 149,583.82 Signed 2019-08-15 2020-05-21 2019-08-20 2020-06-02 2019-10-04 2020-09-03 2019-12-31 Wagon and Minivan) ct) ring & Evaluation Component 4: Project Manag MAFF-G-7 / Vehicles (Pick-up Single Stage - One E IDA / 63660 ement, Coordination, Monito Post Request for Bids Open - National 196,000.00 168,700.00 Signed 2020-07-14 2020-07-16 2020-07-19 2020-07-30 2020-08-30 2020-09-01 2020-09-29 2020-09-03 2020-11-03 2020-09-22 2021-05-02 ) nvelope ring & Evaluation Component 4: Project Manag MAFF-G-13 / Video Conferen Request for Quota Single Stage - One E IDA / 63660 ement, Coordination, Monito Post Open - National 80,000.00 78,500.00 Signed 2020-07-27 2020-09-21 2020-10-05 2021-03-20 ce and Accessories tions nvelope ring & Evaluation Component 4: Project Manag Single Stage - One E MAFF-G-5-R / Motorcycles IDA / 63660 ement, Coordination, Monito Post Request for Bids Open - National 136,800.00 140,600.00 Signed 2020-07-29 2020-07-16 2020-08-03 2020-07-30 2020-09-14 2020-09-01 2020-10-14 2020-09-09 2020-11-18 2020-09-22 2021-05-17 nvelope ring & Evaluation CERC-MAFF-04 / Support inp Component 5: Contingent E uts for raising chicken/duck ( IDA / 63660 Post Direct Selection Direct 1,911,910.00 3,075,303.55 Signed 2020-11-24 2021-03-02 2020-11-29 2021-03-31 2021-01-03 2021-09-30 2021-07-02 mergency Response set up farms for chick/duck, v accine, feed, TA) CERC-MAFF-05 / Support inp Component 5: Contingent E uts for raising fish/frogs (pre IDA / 63660 Post Direct Selection Direct 1,309,198.00 1,036,602.18 Signed 2020-11-29 2021-02-22 2020-12-04 2021-02-23 2021-01-08 2021-09-20 2021-07-07 mergency Response paring plastic tents/tanks an d fingerling, TA) Component 3: Improving Agr MAFF-G-14 / Firewall and Ha Request for Quota Single Stage - One E Pending Impl IDA / 63660 iculture Information Systems Post Limited 2,000.00 0.00 2021-06-18 2021-08-13 2022-02-09 rd Disk for AIDOC tions nvelope ementation and Quality Control Manage ment MAFF-G-15 / Mobile Lab (4 V Component 3: Improving Agr Single Stage - One E ehicles-Van and 2 Vehicles-Pi IDA / 63660 iculture Information Systems Post Request for Bids Open - National 340,000.00 301,800.00 Completed 2021-06-20 2021-09-09 2021-06-25 2021-09-13 2021-08-06 2021-10-27 2021-09-05 2021-11-05 2021-10-10 2021-12-02 2022-04-08 2022-03-04 nvelope ck up) (2 Lots) and Quality Control Manage ment Component 3: Improving Agr MAFF-G-20 / Generator (1=G Single Stage - One E IDA / 63660 iculture Information Systems Post Request for Bids Open - National 160,000.00 170,000.00 Completed 2021-06-23 2021-08-13 2021-06-28 2021-08-18 2021-08-09 2021-09-15 2021-09-08 2021-11-05 2021-10-13 2021-12-01 2022-04-11 2021-12-27 DA Lab, 1 for GDAHP Lab) nvelope and Quality Control Manage ment MAFF-G-21 / Pest database s Component 3: Improving Agr Request for Quota Single Stage - One E Pending Impl oftware development includi IDA / 63660 iculture Information Systems Post Open - National 72,000.00 0.00 2021-06-21 2021-08-16 2022-02-12 tions nvelope ementation ng training to user for GDA and Quality Control Manage ment MAFF-G-23 / Development of Component 3: Improving Agr Animal Health and Productio iculture Information Systems Request for Quota Single Stage - One E Pending Impl IDA / 63660 Post Open - National 40,000.00 0.00 2021-07-06 2021-08-31 2022-02-27 n Information System (Hardw and Quality Control Manage tions nvelope ementation are software, Server, training ment to user) MAFF-G-22 / Laboratory equi Component 3: Improving Agr pment and material for Gene iculture Information Systems Single Stage - One E Pending Impl IDA / 63660 Post Request for Bids Open - National 394,500.00 0.00 2021-06-27 2021-07-02 2021-08-13 2021-09-12 2021-10-17 2022-04-15 ral Directorate of Animal Hea and Quality Control Manage nvelope ementation lth and Production ment MAFF-G-24 / Printing Poster, Component 3: Improving Agr Request for Quota Single Stage - One E Pending Impl campaign on animal health a IDA / 63660 iculture Information Systems Post Limited 24,000.00 0.00 2021-09-10 2021-11-05 2022-05-04 tions nvelope ementation nd animal production for GD and Quality Control Manage AHP ment Component 4: Project Manag MAFF-G-25 / Publication Proj Request for Quota Single Stage - One E Pending Impl IDA / 63660 ement, Coordination, Monito Post Open - National 70,000.00 0.00 2021-11-03 2021-12-29 2022-06-27 ect Documentation tions nvelope ementation ring & Evaluation Component 4: Project Manag MAFF-G-26 / Motorcycles (40 Request for Quota Single Stage - One E IDA / 63660 ement, Coordination, Monito Post Open - National 74,000.00 72,800.00 Signed 2021-07-09 2021-09-03 2021-10-12 2022-03-02 units) tions nvelope ring & Evaluation Page 1 MAFF-G-17 / Laboratory equi Component 3: Improving Agr Open - Internationa Single Stage - One E Pending Impl pment and material for Depa IDA / 63660 iculture Information Systems Post Request for Bids 916,450.00 0.00 2021-09-20 2021-09-25 2021-11-06 2021-12-06 2022-01-10 2022-07-09 l nvelope ementation rtment of Agro-Industry (3 lot and Quality Control Manage s) ment MAFF-G-18 / Laboratory equi Component 3: Improving Agr Open - Internationa Single Stage - One E Pending Impl pment and material for NAL o IDA / 63660 iculture Information Systems Post Request for Bids 848,650.00 0.00 2021-10-03 2021-10-08 2021-11-19 2021-12-19 2022-01-23 2022-07-22 l nvelope ementation f General Directorate of Agric and Quality Control Manage ulture (2 Lots) ment MAFF-G-19 / Laboratory equi Component 3: Improving Agr pment and material for PPSP iculture Information Systems Open - Internationa Single Stage - One E Pending Impl IDA / 63660 Post Request for Bids 652,320.00 0.00 2021-09-06 2021-09-11 2021-10-23 2021-11-22 2021-12-27 2022-06-25 SD of General Directorate of and Quality Control Manage l nvelope ementation Agriculture (2 Lots) ment NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MAFF-CON-1 / Consultant fir ms/NGOs for DPr and BPr pr eparation training and hands Component 1: Enabling Agri Quality Based Sel -on implementation support IDA / 63660 Post Open - National 632,833.00 931,453.43 Signed 2019-07-31 2019-09-18 2019-08-21 2019-10-24 2019-10-04 2020-01-17 2019-11-01 2020-03-25 2019-12-01 2020-05-05 2019-12-31 2020-07-22 2020-02-04 2020-08-07 2024-06-30 culture Diversification ection (preparation and evaluation of disersification and Busines s Proposals and Plant ) for re gion 1 MAFF-CON-2 / Consultant fir ms/NGOs for DPr and BPr pre paration training and hands- Component 1: Enabling Agri Quality Based Sel Open - Internationa IDA / 63660 Post 632,833.00 928,530.70 Signed 2019-07-22 2019-09-18 2019-08-12 2019-10-24 2019-09-25 2020-01-17 2019-10-23 2020-03-25 2019-11-22 2020-05-05 2019-12-22 2020-07-22 2020-01-26 2020-08-07 2024-06-30 on implementation support ( culture Diversification ection l Preparation and evaluation of Diversification and Business Proposals and Plan) for regio n2 MAFF-CON-3 / Consultant fir ms/NGOs for DPr and BPr pre paration training and hands- Component 1: Enabling Agri Quality Based Sel IDA / 63660 Post Open - National 632,388.00 920,165.60 Signed 2019-07-22 2019-10-01 2019-08-12 2019-10-24 2019-09-25 2020-01-17 2019-10-23 2020-03-25 2019-11-22 2020-05-05 2019-12-22 2020-05-26 2020-01-26 2020-07-31 2024-06-30 on implementation support ( culture Diversification ection Preparation and evaluation of Diversification and Business Proposals and Plan) for regio n3 MAFF-CON-7 / Consulting fir m for Project monitoring and Component 4: Project Manag evaluation (General baseline Consultant Qualifi Open - Internationa Under Implement IDA / 63660 ement, Coordination, Monito Post 153,000.00 0.00 2019-08-12 2021-04-06 2019-09-02 2021-05-06 2019-10-31 2019-11-30 2020-01-04 2024-06-28 survey, mid-term survey, pro cation Selection l ation ring & Evaluation ject completion survey, selec t technical surveys and studi es, and project reporting) MAFF-CON-5 / Consultant Fir Component 3: Improving Agr m for Development of websit iculture Information Systems Quality And Cost- Open - Internationa e (AMIS&Agriculture Statistic IDA / 63660 Post 550,000.00 0.00 Canceled 2019-08-30 2020-05-21 2019-09-20 2020-06-08 2019-11-03 2019-12-01 2019-12-31 2020-02-04 2020-03-10 2021-06-30 and Quality Control Manage Based Selection l Information (ASI), apps, and ment initial database for MAFF MAFF-CON-4 / Consultant fir Component 1: Enabling Agri Quality And Cost- Open - Internationa m for specialized assistance IDA / 63660 Prior 1,624,800.00 0.00 Under Review 2019-07-26 2021-01-27 2019-08-16 2021-02-09 2019-09-29 2021-08-23 2019-10-27 2021-10-12 2019-11-26 2019-12-31 2020-02-04 2024-06-28 culture Diversification Based Selection l supporting MAFF with project implementation Component 3: Improving Agr MAFF-CON-6 / Consulting Fir Quality And Cost- Open - Internationa Pending Impleme IDA / 63660 iculture Information Systems Post 732,000.00 0.00 2019-08-15 2019-09-05 2019-10-19 2019-11-16 2019-12-16 2020-01-20 2020-02-24 2021-04-30 m for AIS database concepts Based Selection l ntation and Quality Control Manage ment MAFF-CON-5-R / Consultant Component 3: Improving Agr Firm for Development of web iculture Information Systems Quality And Cost- Open - Internationa Under Implement site (AMIS&Agriculture Statis IDA / 63660 Post 550,000.00 0.00 2021-02-14 2021-02-08 2021-03-07 2021-02-17 2021-04-20 2021-05-18 2021-06-17 2021-07-22 2021-08-26 2022-08-26 and Quality Control Manage Based Selection l ation tic Information (ASI), apps, a ment nd initial database for MAFF MAFF-CON-9 / Consulting fir Component 3: Improving Agr m for pest identification and iculture Information Systems Quality And Cost- Open - Internationa Pending Impleme IDA / 63660 Post 538,000.00 0.00 2021-09-13 2021-10-04 2021-11-17 2021-12-15 2022-01-14 2022-02-18 2022-03-25 2023-03-25 Awareness raising on phytos and Quality Control Manage Based Selection l ntation anitary (PS) measures ment MAFF-CON-10 / Evaluator Co Component 5: Contingent E Consultant Qualifi Pending Impleme IDA / 63660 Post Open - National 20,000.00 0.00 2022-06-01 2022-06-22 2022-08-05 2022-09-04 2022-10-09 2023-04-07 nsultant /Firm of CERC activit mergency Response cation Selection ntation y INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MAFF-CS-15 / National FM Co Component 1: Enabling Agri Individual Consult IDA / 63660 Post Open 54,000.00 14,117.64 Signed 2019-07-22 2019-09-12 2019-09-09 2020-03-18 2019-09-30 2020-03-19 2019-11-04 2020-04-20 2021-05-31 nsultant culture Diversification ant Selection Component 4: Project Manag MAFF-CS-16 / National Procu Individual Consult IDA / 63660 ement, Coordination, Monito Post Open 54,000.00 39,528.00 Signed 2019-07-22 2019-09-11 2019-09-09 2019-11-13 2019-09-30 2019-11-27 2019-11-04 2019-12-06 2021-05-31 rement Consultant ant Selection ring & Evaluation Component 4: Project Manag MAFF-CS-12 / International O Individual Consult IDA / 63660 ement, Coordination, Monito Prior Open 756,000.00 0.00 Canceled 2019-07-24 2019-09-26 2019-09-11 2020-04-24 2019-10-02 2019-11-06 2024-12-31 peration Consultant ant Selection ring & Evaluation Component 4: Project Manag MAFF-CS-13 / Senior Nationa Individual Consult IDA / 63660 ement, Coordination, Monito Post Open 198,000.00 39,529.44 Signed 2019-07-23 2019-09-12 2019-09-10 2020-01-15 2019-10-01 2020-01-21 2019-11-05 2020-02-17 2024-12-31 l Operations Consultant ant Selection ring & Evaluation MAFF-CS-2 / National Project Component 1: Enabling Agri Individual Consult IDA / 63660 Post Open 204,000.00 38,117.64 Signed 2019-07-24 2021-04-26 2019-09-11 2021-09-23 2019-10-02 2021-09-27 2019-11-06 2021-10-11 2024-12-31 Coordination Support Consult culture Diversification ant Selection ant Page 2 Component 4: Project Manag MAFF-CS-14 / National Senio Individual Consult IDA / 63660 ement, Coordination, Monito Post Open 189,000.00 38,117.64 Signed 2019-07-25 2019-09-11 2019-09-12 2020-01-15 2019-10-03 2020-01-21 2019-11-07 2020-02-17 2024-12-31 r M&E Specialist ant Selection ring & Evaluation MAFF-CS-6 / International Co Component 3: Improving Agr nsultant for Development an iculture Information Systems Individual Consult Pending Impleme IDA / 63660 Post Open 54,000.00 0.00 2019-07-26 2019-09-20 2019-10-11 2019-12-27 2020-03-31 d Finalization of Law on Quali and Quality Control Manage ant Selection ntation ty and Safety of Agricultural ment Products MAFF-CS-7 / National Consul Component 3: Improving Agr tant for Development and Fin iculture Information Systems Individual Consult Pending Impleme IDA / 63660 Post Open 18,000.00 0.00 2019-07-29 2019-09-16 2019-10-07 2019-12-31 2021-03-31 alization of Law on Quality an and Quality Control Manage ant Selection ntation d Safety of Agricultural Produ ment cts MAFF-CS-8 / International Co Component 3: Improving Agr Individual Consult Pending Impleme nsultant for GAP guidelines d IDA / 63660 iculture Information Systems Post Open 126,000.00 0.00 2019-07-29 2019-09-16 2019-10-07 2020-01-01 2022-03-31 ant Selection ntation evelopment and Quality Control Manage ment MAFF-CS-9 / International Co Component 3: Improving Agr Individual Consult Pending Impleme nsultant for Organic farming IDA / 63660 iculture Information Systems Post Open 56,000.00 0.00 2019-07-31 2019-09-18 2019-10-09 2019-12-25 2022-01-31 ant Selection ntation guidelines development and Quality Control Manage ment MAFF-CS-3 / TWGAW co-chai Component 1: Enabling Agri Individual Consult IDA / 63660 Post Open 102,000.00 0.00 Canceled 2019-08-01 2019-09-19 2019-10-10 2019-12-02 2024-12-31 r assistant culture Diversification ant Selection MAFF-CS-4 / International te Component 1: Enabling Agri Individual Consult Pending Impleme chnical assistance on Cambo IDA / 63660 Post Open 234,000.00 0.00 2019-08-01 2019-09-19 2019-10-10 2019-11-29 2021-05-28 culture Diversification ant Selection ntation dian brand and GI developm ent MAFF-CS-5 / National technic Component 1: Enabling Agri Individual Consult Pending Impleme al assistance on Cambodian IDA / 63660 Post Open 24,000.00 0.00 2019-08-05 2019-09-23 2019-10-14 2019-12-31 2020-08-31 culture Diversification ant Selection ntation brand and GI development Component 4: Project Manag MAFF-CON-8 / External Finan IDA / 63660 ement, Coordination, Monito Post Direct Selection Direct 120,000.00 0.00 Canceled 2019-12-02 2019-12-12 2020-02-15 2024-06-28 ce Auditor ring & Evaluation MAFF-CS-10 / International C Component 3: Improving Agr Individual Consult Pending Impleme onsultant for pest identificati IDA / 63660 iculture Information Systems Post Open 168,000.00 0.00 2020-03-27 2020-05-15 2020-06-05 2020-07-10 2022-04-11 ant Selection ntation on and Quality Control Manage ment Component 3: Improving Agr MAFF-CS-11 / National Cons Individual Consult Pending Impleme IDA / 63660 iculture Information Systems Post Open 72,000.00 0.00 2020-03-31 2020-05-19 2020-06-09 2020-07-14 2024-08-30 ultant for pest identification ant Selection ntation and Quality Control Manage ment Component 4: Project Manag MAFF-CS-29 / Procurement A Individual Consult IDA / 63660 ement, Coordination, Monito Post Open 14,400.00 12,000.00 Signed 2020-06-08 2021-01-04 2020-07-27 2021-05-31 2020-08-17 2021-06-03 2020-09-21 2021-06-07 2021-03-20 ssistant ant Selection ring & Evaluation Component 3: Improving Agr MAFF-CS-18 / National TA f Individual Consult IDA / 63660 iculture Information Systems Post Open 18,000.00 0.00 Canceled 2020-08-10 2020-09-28 2020-10-19 2020-11-23 2021-05-22 or ISO 17025 accreditation ant Selection and Quality Control Manage ment Component 3: Improving Agr MAFF-CS-19 / International T Individual Consult IDA / 63660 iculture Information Systems Post Open 28,000.00 0.00 Canceled 2020-09-11 2020-10-30 2020-11-20 2020-12-25 2021-06-23 A on risk categorization ant Selection and Quality Control Manage ment MAFF-CS-20 / International T Component 3: Improving Agr Individual Consult A to develop operation manu IDA / 63660 iculture Information Systems Post Open 6,000.00 0.00 Canceled 2020-09-11 2020-10-30 2020-11-20 2020-12-25 2021-06-23 ant Selection al and Quality Control Manage ment MAFF-CS-21 / International T Component 3: Improving Agr echnical assistance to suppor iculture Information Systems Individual Consult IDA / 63660 Post Open 168,000.00 0.00 Canceled 2020-09-11 2020-10-30 2020-11-20 2020-12-25 2021-06-23 t to national and Quality Control Manage ant Selection and regional laboratories" ment MAFF-CS-22 / ITA for Develo Component 3: Improving Agr Individual Consult ping guidelines and conflict r IDA / 63660 iculture Information Systems Post Open 54,000.00 0.00 Canceled 2020-09-15 2020-11-03 2020-11-24 2020-12-29 2021-06-27 ant Selection esolution mechanisms and Quality Control Manage ment MAFF-CS-23 / NTA for Develo Component 3: Improving Agr Individual Consult ping guidelines and conflict r IDA / 63660 iculture Information Systems Post Open 9,000.00 0.00 Canceled 2020-09-15 2020-11-03 2020-11-24 2020-12-29 2021-06-27 ant Selection esolution mechanisms and Quality Control Manage ment MAFF-CS-24 / ITA for study o Component 3: Improving Agr Individual Consult n long term value chain optio IDA / 63660 iculture Information Systems Post Open 42,000.00 0.00 Canceled 2020-06-25 2020-08-13 2020-09-03 2020-10-08 2021-04-06 ant Selection ns and Quality Control Manage ment MAFF-CS-25 / NTA for study Component 3: Improving Agr Individual Consult on long term value chain opti IDA / 63660 iculture Information Systems Post Open 9,000.00 0.00 Canceled 2020-09-16 2020-11-04 2020-11-25 2020-12-30 2021-06-28 ant Selection ons and Quality Control Manage ment MAFF-CS-26 / ITA for Study o Component 3: Improving Agr Individual Consult n nutrition sensitive value ch IDA / 63660 iculture Information Systems Post Open 42,000.00 0.00 Canceled 2020-10-15 2021-07-28 2020-12-03 2020-12-24 2021-01-28 2021-07-27 ant Selection ains and Quality Control Manage ment MAFF-CS-27 / NTA for Study Component 3: Improving Agr Individual Consult Under Implement on nutrition sensitive value c IDA / 63660 iculture Information Systems Post Open 9,000.00 0.00 2020-10-15 2021-07-28 2020-12-03 2020-12-24 2021-01-28 2021-07-27 ant Selection ation hains and Quality Control Manage ment Component 3: Improving Agr MAFF-CS-28 / NTA for Formul Individual Consult IDA / 63660 iculture Information Systems Post Open 45,000.00 0.00 Canceled 2020-10-15 2020-12-03 2020-12-24 2021-01-28 2021-07-27 ation of regulations ant Selection and Quality Control Manage ment MAFF-CS-1 / International co Component 1: Enabling Agri Individual Consult Under Implement nsultant to prepare strategy IDA / 63660 Post Open 24,000.00 0.00 2020-06-15 2020-05-21 2020-08-03 2020-08-24 2020-09-28 2021-03-27 culture Diversification ant Selection ation and implementation plan (Kh mer and English) Component 4: Project Manag MAFF-CS-30 / National Cons Individual Consult IDA / 63660 ement, Coordination, Monito Post Open 108,000.00 35,294.12 Signed 2020-07-09 2020-07-02 2020-08-27 2020-09-02 2020-09-17 2020-09-03 2020-10-22 2020-09-08 2021-04-20 ultant for safeguard ant Selection ring & Evaluation Component 4: Project Manag MAFF-CS-12-R / International Individual Consult IDA / 63660 ement, Coordination, Monito Prior Open 756,000.00 173,442.00 Signed 2020-10-09 2020-10-08 2020-11-27 2021-01-12 2020-12-18 2021-02-25 2021-01-22 2021-03-01 2021-07-21 Operation Consultant ant Selection ring & Evaluation MAFF-CS-31 / International T Component 3: Improving Agr Individual Consult Pending Impleme echnical assistance to suppor IDA / 63660 iculture Information Systems Post Open 168,000.00 0.00 2021-08-25 2021-10-13 2021-11-03 2021-12-08 2022-06-06 ant Selection ntation t to national and regional lab and Quality Control Manage oratories ment Page 3 MAFF-CS-32 / International C Component 3: Improving Agr Individual Consult Pending Impleme onsultant for Development g IDA / 63660 iculture Information Systems Post Open 28,000.00 0.00 2021-08-31 2021-10-19 2021-11-09 2021-12-14 2022-06-12 ant Selection ntation uidelines and conflict resoluti and Quality Control Manage on mechanisms ment MAFF-CS-33 / National Cons Component 3: Improving Agr Individual Consult Pending Impleme ultant for Development guide IDA / 63660 iculture Information Systems Post Open 18,000.00 0.00 2021-08-31 2021-10-19 2021-11-09 2021-12-14 2022-06-12 ant Selection ntation lines and conflict resolution and Quality Control Manage mechanisms ment MAFF-CS-34 / National TA for Component 3: Improving Agr Individual Consult Pending Impleme Formulation of regulations (G IDA / 63660 iculture Information Systems Post Open 45,000.00 0.00 2021-09-12 2021-10-31 2021-11-21 2021-12-26 2022-06-24 ant Selection ntation uideline, Prakas of GAHP, Qu and Quality Control Manage arantine) ment MAFF-CS-35 / National Knowl Component 4: Project Manag Individual Consult edge Management and IDA / 63660 ement, Coordination, Monito Post Open 36,000.00 39,528.00 Signed 2021-07-13 2021-08-05 2021-08-31 2022-01-11 2021-09-21 2022-01-17 2021-10-26 2022-01-28 2022-04-24 ant Selection Communications Consultant ring & Evaluation Component 4: Project Manag MAFF-CS-36 / TA-National Co Individual Consult IDA / 63660 ement, Coordination, Monito Post Open 35,294.00 38,117.64 Signed 2021-07-12 2021-09-13 2021-08-30 2021-12-17 2021-09-20 2021-12-20 2021-10-25 2021-12-30 2022-04-23 nsultant for Social Safeguard ant Selection ring & Evaluation Component 3: Improving Agr MAFF-CS-37 / ITA for Formul Individual Consult Pending Impleme IDA / 63660 iculture Information Systems Post Open 28,000.00 0.00 2021-09-16 2021-11-04 2021-11-25 2021-12-30 2022-06-28 ation of law and regulations ant Selection ntation and Quality Control Manage ment Component 3: Improving Agr MAFF-CS-38 / NTA for Formul Individual Consult Pending Impleme IDA / 63660 iculture Information Systems Post Open 12,000.00 0.00 2021-09-16 2021-11-04 2021-11-25 2021-12-30 2022-06-28 ation of​ law and regulations ant Selection ntation and Quality Control Manage ment Component 4: Project Manag MAFF-CS-39 / National Cons IDA / 63660 ement, Coordination, Monito Post Direct Selection Direct 15,000.00 0.00 Canceled 2021-11-02 2021-12-06 2021-11-12 2022-01-16 2022-07-15 ultant for for Baseline Survey ring & Evaluation MAFF-CS-26-R / ITA for Study Component 3: Improving Agr Individual Consult Pending Impleme on nutrition-sensitive value c IDA / 63660 iculture Information Systems Post Open 42,000.00 0.00 2022-06-01 2022-07-20 2022-08-10 2022-09-14 2023-03-13 ant Selection ntation hains and Quality Control Manage ment Page 4