Procurement Plan (Textual Part) I. General 1. Project Information Country: Senegal Project Name: Saint-Louis Emergency Recovery and Resilience Project Project Id: P166538 Project Implementation Agency: Municipal Development Agency Date of the Procurement Plan: Septembre 2018 2. Period Covered by this procurement plan: Septembre 2018 to March 31,2020 II. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. III. Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. IV. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in decree n° 2014-1212 of 22 September 2014 of The Senegal Public Procurement Regulations, such 1 arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: (the “Procurement Guidelines”), and the additional provisions in the following paragraphs: (a) Eligibility: Eligibility to participate in a procurement process and to be awarded an Association-financed contract shall be as defined under Section I of the Procurement Guidelines; accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Association for reasons other than those provided in Section I of the Procurement Guidelines. No restriction based on nationality of bidders and/or origin of goods shall apply, and foreign bidders shall be allowed to participate in NCB without application of restrictive conditions, such as, but not limited to, mandatory partnering or subcontracting with national entities. (b) Domestic Preference: No margins of preference of any sort shall be applied in the bid evaluation. (c) Bidding Documents: Procuring entities shall use bidding documents acceptable to the Association. (d) Bid validity: An extension of bid validity, if justified by exceptional circumstances, may be requested in accordance with Appendix 1 of the Procurement Guidelines. A corresponding extension of any bid guarantee shall be required in all cases of extension of bid validity. A bidder may refuse a request for extension of bid validity without forfeiting its bid guarantee. (e) Qualification: Qualification criteria shall be clearly specified in the bidding documents. All criteria so specified, and only such specified criteria, shall be used to determine whether a bidder is qualified. Qualification shall be assessed on a “pass or fail” basis, and merit points shall not be used. Such assessment shall be based entirely upon the bidder’s or prospective bidder’s capability and resources to effectively perform the contract, taking into account objective and measurable factors, including: (i) relevant general and specific experience, and satisfactory past performance and successful completion of similar contracts over a given period; (ii) financial position; and where relevant (ii) capability of construction and/or manufacturing facilities (f) Prequalification procedures and documents acceptable to the Association shall be used for large, complex and/or specialized works. Verification of the information upon which a bidder was prequalified, including current commitments, shall be carried out at the time of contract award, along with the bidder’s capability with respect to personnel and equipment. Where pre- qualification is not used, the qualification of the bidder who is recommended for award of contract shall be assessed by post-qualification, applying the qualification criteria stated in the bidding documents. (g) Bid Evaluation: All bid evaluation criteria other than price shall be quantifiable in monetary terms. Merit points shall not be used, and no minimum point or percentage value shall be assigned to the evaluation 2 criteria or significance of price in bid evaluation. No negotiations shall be permitted. (h) Guarantees: Guarantees shall be in the format, shall have the period of validity and shall be submitted when and as specified in the bidding documents. (i) Cost Estimates: Detailed cost estimates shall be confidential and shall not be disclosed to prospective bidders. No bids shall be rejected on the basis of comparison with the cost estimates without the Association’s prior written concurrence. (j) Rejection of bids and re-bidding: No bid shall be rejected solely because it falls outside of a predetermined price range or exceeds the estimated cost. All bids (or the sole bid if only one bid is received) shall not be rejected, the procurement process shall not be cancelled, and new bids shall not be solicited without the Association’s prior written concurrence. (k) Fraud and corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the Association’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines. (l) Inspection and audit rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the submission of bids and contract performance. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. V. Prequalification: Not applicable VI. Leased Assets: Not applicable VII. Procurement of Second Hand Goods: Not applicable 3 VIII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). (a) Goods: Non- identified for now (b) Works: Non- identified for now Domestic preference is not applicable for National Open Competitive Procurement IX. Other Relevant Procurement Information 4 X. Procurement Prior Review Thresholds (US$) Valeur seuil Contrats soumis à examen Nature des dépenses Méthode de passation de marchés du préalable de l’IDA march é $EU AOI ≥ Tous les contrats de plus 15.000. $10,000,000 USD 000 AON < Tous les contrats de plus 15.000. $10,000,000 USD 1. Travaux 000 Demande de cotation – au moins 3 offres < Aucun 200.00 0 Entente Directe Pas de Tous les contrats de plus seuil $10,000,000 USD AOI ≥1 Tous les contrats de $2,000,000 000.00 et plus 0 AON < Aucun 1000.0 00 2. Fournitures et Consultation de Fournisseurs locaux au < Aucun services assimilés moins 3 offres 100.00 0 Consultation de Fournisseurs locaux < Aucun (véhicules et carburant) 500.00 0 Entente directe Pas de Tous les contrats de $2,000,000 seuil et plus 5 Post Review: All contracts not subject to prior review shall be subject to post review. 6 XI. Thresholds for Procurement Approaches and Method (US$) Nature de Méthode de passation de Valeur seuil du Contrats soumis à examen dépenses marchés contrat $EU préalable Tous contrats de $1,000,000 EU SBQC1; SBQ2; SCM3; SBF4 ou plus Consultants SQC5 < 300 000 Aucun Firmes Tous contrats de $1,000,000 EU Entente directe Pas de seuil ou plus Consultant individuel (CI) 6 ≥ 100.000 (AMI)7 Tous contrats de 300.000 $ EU ou plus Consultants Consultant individuel (CI) (3CV) < 100.000 Individuels Tous contrats de 300.000 $ EU Entente directe Pas de seuil ou plus Tous les TDRs, quel que soit la valeur du contrat, sont soumis à examen préalable. 1 Sélection Basée sur la Qualité et le Coût 2 Sélection Basée sur la qualité du Consultant 3 Sélection au coût minimum 4 Sélection à Budget fixe 5 Sélection basée sur les qualifications des consultants 6 Consultant Individuel 7 Avis à Manifestation d’Intérêt 7 8 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines8 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed 8Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 9 contract, financially or in any other manner;9 (ii) to be a nominated10 sub- contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension about an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect11 all accounts, records, and other 9 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 10 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 11 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 10 documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 11 PROCUREMENT Senegal : Senegal - Saint-Louis Emergency Recovery and Resilience Project PLAN General Information Country: Senegal Bank’s Approval Date of the Original Procurement Plan: 2018-09-04 2022-02-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166538 GPN Date: Project Name: Senegal - Saint-Louis Emergency Recovery and Resilience Project Loan / Credit No: IDA / 62730, IDA / 67600 MUNICIPAL DEVELOPMENT AGENCY Executing Agency(ies): WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SN-ADM-02-T-AONR / Component 1: Meeting Single Stage - One 2019-02- Travaux d'aménagement du IDA / 62730 Immediate Needs of the A posteriori Appel d'offres Limited 457,123.94 Signé 2018-08-31 2018-12-07 2018-09-05 2018-04-10 2018-09-19 2018-12-17 2018-10-03 2018-12-26 2018-10-31 2019-01-24 Envelope 28 site de relogement provisoire Disaster Affected Population SN-ADM-04-CS-ED / Sélection par entente directe d’une entreprise pour la Component 2: Planned réalisation de travaux Relocation of Populations Passation de 2020-02- complémentaires pour IDA / 62730 Living in the Highest Risk A posteriori marché de gré à Direct 605,481.76 Signé 2019-11-12 2019-10-25 2019-11-15 2020-01-08 2019-11-29 2020-04-02 27 l’aménagement du site de Zones in the Langue de gré relogement provisoire de Barbarie Djougob - Avec l’entreprise CSTP SN-ADM-01-T-AON / Component 3: Strengthening Travaux d’aménagement pour Single Stage - One En attente 2025-07- IDA / 62730 Urban and Coastal Resilience A posteriori Appel d'offres Open - National 0.00 2024-03-28 2024-04-02 2024-05-02 2024-06-01 2024-07-06 la requalification de la zone Envelope d'exécution 06 Planning libérée SN-ADM-02-T-AON / Réalisation des travaux de Component 3: Strengthening Single Stage - One En attente 2025-03- démolition, de nettoyage et IDA / 62730 Urban and Coastal Resilience A posteriori Appel d'offres Open - National 0.00 2022-12-13 2022-12-18 2023-01-17 2023-02-16 2023-03-23 Envelope d'exécution 22 de sécurisation de la bande Planning des 20 m Component 2: Planned SN-ADM-191231-CW-RFQ / Relocation of Populations Travaux complémentaires de Single Stage - One 2020-12- IDA / 62730 Living in the Highest Risk A posteriori Demande de prix Limited 217,305.90 Signé 2020-09-03 2020-09-17 2020-09-18 2020-11-10 la phase 2 de l'aménagement Envelope 17 Zones in the Langue de provisoire de Diougop Barbarie SN-ADM-196346-CW-RFB / Component 2: Planned Réalisation des travaux de Relocation of Populations terrassements généraux et de Single Stage - One 9,263,077.4 En cours 2021-07- IDA / 62730 Living in the Highest Risk A priori Appel d'offres Open - International 2020-10-05 2020-12-03 2020-10-10 2020-12-09 2020-11-21 2021-01-26 2020-12-21 2021-02-26 2021-01-25 2021-04-29 VRD primaires dans le cadre Envelope 6 d'examen 24 Zones in the Langue de de l’aménagement du site de Barbarie relogement définitif SN-ADM-202773-CW-RFQ / TRAVAUX D’AMENAGEMENT D’ABRI POUR LE PROSE Component 2: Planned CENTRALE D’ACHAT Relocation of Populations Single Stage - One 2021-02- COMMUNAUTAIRE, ET DE IDA / 62730 Living in the Highest Risk A posteriori Demande de prix Limited 18,882.97 Signé 2020-11-11 2020-11-05 2021-01-06 2020-12-03 Envelope 15 REALISATION D’UNE CLOTURE Zones in the Langue de EN GRILLAGE POUR LE MICRO- Barbarie JARDINAGE A DIOUGOP SN-ADM-195764-CW-RFQ / Travaux dans le cadre de la Component 2: Planned réalisation d'un PROSE de Relocation of Populations Single Stage - One 2021-06- première génération sur le IDA / 62730 Living in the Highest Risk A posteriori Demande de prix Limited 0.00 Annulé 2020-10-27 2020-12-22 Envelope 20 site de relogement provisoire Zones in the Langue de (Travaux aménagement Barbarie parking arrêt bus) Component 2: Planned Request for SN-ADM-234573-CW-RFB / Relocation of Populations Bids - Works Single Stage - One En attente 2024-02- Travaux de réalisation des IDA / 62730 Living in the Highest Risk A posteriori Appel d'offres Open - National French Civil 0.00 2021-11-15 2021-11-20 2021-12-20 2022-01-19 2022-02-23 Envelope d'exécution 23 équipements socio-collectifs Zones in the Langue de Law (French) Barbarie SPD SN-ADM-195740-CW-RFB / Component 2: Planned Request for Réalisation des travaux Relocation of Populations Bids - Works complémentaires de voiries et Single Stage - One En attente 2023-02- IDA / 62730 Living in the Highest Risk A posteriori Appel d'offres Open - National French Civil 0.00 2021-10-11 2021-10-16 2021-11-29 2021-12-29 2022-02-02 réseaux divers dans le cadre Envelope d'exécution 02 Zones in the Langue de Law (French) de l'aménagement du site de Barbarie SPD relogement définitif Component 2: Planned Request for SN-ADM-280022-CW-RFB / Relocation of Populations Bids - Works Single Stage - One En attente 2024-12- Construction de logements IDA / 62730 Living in the Highest Risk A priori Appel d'offres Open - International French Civil 0.00 2022-02-23 2022-02-28 2022-04-11 2022-05-11 2022-06-15 Envelope d'exécution 01 définitifs à Diougop Zones in the Langue de Law (French) Barbarie SPD Component 2: Planned Request for SN-ADM-180401-CW-RFB / Relocation of Populations Bids - Works Single Stage - One 2024-09- Travaux de construction des IDA / 62730 Living in the Highest Risk A priori Appel d'offres Open - International French Civil 0.00 Annulé 2021-12-06 2021-12-11 2022-01-22 2022-02-21 2022-03-28 Envelope 13 logements définitifs en 4 lots Zones in the Langue de Law (French) Barbarie SPD GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SN-ADM-O1-F-UN / Acquisition et installation de Passation de Component 1: Meeting matériels et équipements marchés auprès IDA / 62730 Immediate Needs of the A priori Direct 2,313,214.00 Signé 2018-08-14 2018-08-19 2018-09-02 2018-09-13 2019-06-29 (unités mobiles etc. pour le des agences de Disaster Affected Population relogement temporaire - l'ONU Avec UNOPS Page 1 SN-ADM-02-F-DC / Fourniture d'équipements pour les experts du SERRP Component 5: Project basés à l'ARD de Saint-Louis - Single Stage - One IDA / 62730 Management, Monitoring and A posteriori Demande de prix Limited 4,310.49 Signé 2019-03-13 2019-03-28 2019-04-17 2019-05-14 2019-05-17 Lot unique comportant une Envelope Evaluation imprimante, du mobilier de bureau, un split et une Fontaine à eau SN-ADM-03-F-DC / Fourniture de matériels informatiques et de mobiliers Component 5: Project Single Stage - One de bureau dans le cadre de l' IDA / 62730 Management, Monitoring and A posteriori Demande de prix Limited 25,471.05 Signé 2019-03-13 2018-12-24 2019-04-10 2019-03-15 2019-05-10 Envelope appui à la commune et à Evaluation l'ARD de saint-louis en deux (02) lots separes SN-ADM-05-F-DC / Acquisition d'équipements Component 2: Planned ménagers pour les mesures Relocation of Populations Single Stage - One d'aide au relogement IDA / 62730 Living in the Highest Risk A posteriori Demande de prix Limited 50,087.21 Signé 2019-06-15 2019-07-02 2019-07-20 2019-08-08 2019-08-19 Envelope provisoire des familles Zones in the Langue de sinistrées de la langue de Barbarie barbarie. SN-ADM-12-CS-CI / Component 5: Project Fourniture de matériels Single Stage - One IDA / 62730 Management, Monitoring and A posteriori Demande de prix Limited 36,992.91 Signé 2019-08-27 2019-07-15 2019-10-22 2019-09-13 2019-11-21 informatiques pour la Envelope Evaluation commune de Gandon SN-ADM-161657-GO-RFQ / Acquisition de mobilier de Component 5: Project Single Stage - One salle de réunion dans le cadre IDA / 62730 Management, Monitoring and A posteriori Demande de prix Limited 3,671.40 Signé 2019-08-20 2019-08-21 2019-10-15 2019-10-22 2020-04-12 Envelope de l'appui logistique à la Evaluation préfecture de Saint-Louis SN-ADM-168570-GO-RFQ / Plan de renforcement de la résilience des populations Component 1: Meeting Single Stage - One sinistrées installées sur le site IDA / 62730 Immediate Needs of the A posteriori Demande de prix Limited 15,095.20 Signé 2020-04-26 2020-04-22 2020-06-21 2020-05-19 2020-12-18 Envelope de relogement de Djougop Disaster Affected Population face à la maladie à coronavirus (COVID-19) SN-ADM-01-F-AON / Acquisition matériels et Component 3: Strengthening équipements (pluviomètres, Single Stage - One En attente IDA / 62730 Urban and Coastal Resilience A posteriori Appel d'offres Open - National 0.00 2022-02-03 2022-02-08 2022-03-10 2022-03-31 2022-05-05 2022-11-01 limnimètres, balises etc...) Envelope d'exécution Planning pour le système d'Alerte Précoce (SAP etc.) SN-ADM-180403-GO-RFB / Acquisition de matériels, Component 3: Strengthening biens et services dans le cadre Single Stage - One En attente IDA / 62730 Urban and Coastal Resilience A posteriori Appel d'offres Open - National 0.00 2022-01-03 2022-01-08 2022-02-19 2022-03-21 2022-04-25 2022-10-22 du renforcement des Envelope d'exécution Planning capacités au niveau institutionnel et technique SN-ADM-181858-GO-RFQ / Réalisation du PROSE micro jardinage : Fournitures de Component 2: Planned matériels de confection de Relocation of Populations Single Stage - One tables pour le jardinage ; IDA / 62730 Living in the Highest Risk A posteriori Demande de prix Limited 22,389.75 Signé 2020-07-20 2020-08-06 2020-09-14 2020-10-08 2021-03-13 Envelope Fournitures d’intrants de Zones in the Langue de production pour le micro- Barbarie jardinage ; Acquisition de plants pour reboisement SN-ADM-186084-GO-RFQ / Acquisition de kits Component 1: Meeting domestiques (literie, Single Stage - One IDA / 62730 Immediate Needs of the A posteriori Demande de prix Limited 59,746.73 Signé 2020-08-03 2020-08-20 2020-09-28 2020-09-24 2021-03-27 ustensiles, produits Envelope Disaster Affected Population d'entretien, etc.) en appui aux populations relogées (phase 2) SN-ADM-04-F-DC / Acquisition de véhicules dans le cadre du renforcement de capacités au niveaux Component 5: Project institutionnel et technique Single Stage - One IDA / 62730 Management, Monitoring and A posteriori Demande de prix Limited 99,933.81 Signé 2019-04-06 2020-09-08 2019-06-17 2020-11-17 2019-07-17 (1Véhicule 4x4 pour ARD de Envelope Evaluation Saint Louis, 1Pick up pour commune de St Louis et 1Pick up pour commune de GANDON) SN-ADM-234819-GO-RFQ / Acquisition d'équipements Component 3: Strengthening Single Stage - One En attente dans le cadre de la mise en IDA / 62730 Urban and Coastal Resilience A posteriori Demande de prix Limited 0.00 2021-08-21 2021-10-16 2022-04-14 Envelope d'exécution pace d'un dispositif provisoire Planning d'alerte précoce SN-ADM-181841-GO-RFQ / réalisation du PROSE centrale d’achat : Acquisition de Component 2: Planned matériels de production Relocation of Populations Single Stage - One (congélateurs, frigos, kits IDA / 62730 Living in the Highest Risk A posteriori Demande de prix Limited 0.00 Annulé 2020-07-20 2020-09-14 2021-03-13 Envelope solaires, etc.) ; Fournitures de Zones in the Langue de denrées alimentaires, de Barbarie produits ménagers et produits cosmétiques SN-ADM-186122-GO-RFQ / Component 2: Planned réalisation du PROSE coiffure : Relocation of Populations Acquisition de matériels de IDA / 62730 Living in the Highest Risk A posteriori Demande de prix 0.00 Annulé 2020-12-26 2021-02-20 2021-08-19 coiffure ; Acquisition de Zones in the Langue de produits cosmétiques pour la Barbarie coiffure SN-ADM-186125-GO-RFQ / réalisation du PROSE petite enfance : Acquisition Component 2: Planned d’équipement pour les Relocation of Populations Single Stage - One En attente enseignements de la Petite- IDA / 62730 Living in the Highest Risk A posteriori Demande de prix Limited 0.00 2021-09-11 2021-11-06 2022-05-05 Envelope d'exécution enfance ; Fourniture de Zones in the Langue de matériels didactiques pour les Barbarie enseignements de la Petite- enfance Page 2 SN-ADM-186126-GO-RFQ / Component 2: Planned réalisation du PROSE transport Relocation of Populations Single Stage - One En attente : acquisition de 02 bus pour le IDA / 62730 Living in the Highest Risk A posteriori Demande de prix Limited 0.00 2021-09-18 2021-11-13 2022-05-12 Envelope d'exécution transport des résidents de Zones in the Langue de Diougop Barbarie SN-ADM-186111-GO-RFQ / Component 2: Planned réalisation du PROSE couture : Relocation of Populations Single Stage - One Acquisition de matériels de IDA / 62730 Living in the Highest Risk A posteriori Demande de prix Limited 0.00 Annulé 2020-12-26 2021-02-20 2021-08-19 Envelope couture ; Acquisition de Zones in the Langue de fournitures pour la couture Barbarie SN-ADM-181829-GO-RFQ / Acquisition de fournitures et services dans le cadre de la Component 2: Planned réalisation du PIC SANTE Relocation of Populations Equipement Unité provisoire Single Stage - One En attente IDA / 62730 Living in the Highest Risk A posteriori Demande de prix Limited 0.00 2021-09-18 2021-11-13 2022-05-12 de santé : Fournitures Envelope d'exécution Zones in the Langue de d’équipements et de matériels Barbarie médicaux ; Fournitures de médicaments et produits phytosanitaires NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SN-ADM-161586-NC-RFQ / ENTRETIEN DU SYSTEME D’ASSAINISSEMENT ET LA Component 1: Meeting Single Stage - One VIDANGE DE FOSSES IDA / 62730 Immediate Needs of the A posteriori Demande de prix Limited 14,393.55 Signé 2020-03-10 2020-03-27 2020-05-05 2020-05-27 2021-05-05 Envelope SEPTIQUES, DU SITE DE Disaster Affected Population RECASEMENT PROVISOIRE DE DIOUGOP CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SN-ADM-02-CS-SQC / Sélection d'un Cabinet pour la Component 2: Planned Sélection fondée Facilitation sociale du Relocation of Populations sur les programme de récasement IDA / 62730 Living in the Highest Risk A posteriori Open - National 424,512.59 Signé 2018-08-14 2018-03-19 2018-08-28 2018-09-25 2018-09-28 2018-10-09 2018-10-09 2018-11-13 2018-12-04 2021-10-28 qualifications des définitif des familles Zones in the Langue de consultants déplacées de la langue de Barbarie barbarie SN-ADM-06-CS-SFQC / Élaboration d'un cadre de financement du risque de Sélection fondée Component 3: Strengthening catastrophe pour guider la sur les En attente IDA / 62730 Urban and Coastal Resilience A posteriori Open - National 0.00 2021-11-01 2021-11-22 2021-12-13 2021-12-27 2022-01-17 2022-07-16 reconstruction de logements qualifications des d'exécution Planning et/ou la réinstallation des consultants ménages affectés par la catastrophe SN-ADM-02-CS-SFQC / Sélection d'un Cabinet pour la Component 3: Strengthening Sélection fondée En attente préparation du Plan de IDA / 62730 Urban and Coastal Resilience A posteriori sur la qualité et le Open - National 0.00 2021-12-01 2021-12-22 2022-02-04 2022-03-04 2022-04-03 2022-05-08 2022-06-12 2023-01-08 d'exécution résilience de l'agglomération Planning coût de Saint-Louis SN-ADM-180402-CS-LCS / Component 5: Project Sélection d'un Cabinet d'audit Sélection au En attente IDA / 62730 Management, Monitoring and A posteriori Open - National 0.00 2022-02-21 2022-03-14 2022-04-27 2022-05-25 2022-06-24 2022-07-29 2022-09-02 2023-03-01 financier du projet (Par la moindre coût d'exécution Evaluation DCFE) Sélection fondée SN-ADM-180399-CS-CQS / Component 5: Project sur les En attente Sélection d'un Cabinet d'audit IDA / 62730 Management, Monitoring and A posteriori Open - National 0.00 2022-01-26 2022-02-16 2022-04-01 2022-05-01 2022-06-05 2022-12-02 qualifications des d'exécution technique du projet Evaluation consultants SN-ADM-204356-CS-QCBS / Component 2: Planned Sélection d’un Cabinet pour la Relocation of Populations Sélection fondée En attente supervision des travaux de IDA / 62730 Living in the Highest Risk A priori sur la qualité et le Open - International 0.00 2021-09-06 2021-09-27 2021-11-10 2021-12-08 2022-01-07 2022-02-11 2022-03-18 2024-02-16 d'exécution construction des logements Zones in the Langue de coût définitifs Barbarie SN-ADM-180398-CS-QCBS / Component 2: Planned Firme pour la supervision des Relocation of Populations Sélection fondée travaux d'aménagement du En cours IDA / 62730 Living in the Highest Risk A priori sur la qualité et le Open - International 0.00 2021-01-23 2020-11-18 2021-02-13 2020-12-03 2021-03-29 2021-05-29 2021-04-26 2021-04-30 2021-05-26 2021-09-24 2021-06-30 2021-12-06 2021-08-04 2024-01-21 site définitif et de d'exécution Zones in the Langue de coût construction de logement et Barbarie d'équipement collectifs SN-ADM-05-CS-SFQC / Sélection d'un Cabinet pour Component 3: Strengthening Sélection fondée l'élaboration et la mise œuvre IDA / 62730 Urban and Coastal Resilience A posteriori sur la qualité et le Open - National 0.00 Annulé 2020-08-03 2020-08-24 2020-10-07 2020-11-04 2020-12-04 2021-01-08 2021-02-12 2024-01-28 du plan de renforcement de Planning coût capacités des structures parties prenantes du projet SN-ADM-234597-CS-QCBS / Elaboration des PUD des Component 3: Strengthening Sélection fondée En cours communes de Saint-Louis, IDA / 67600 Urban and Coastal Resilience A priori sur la qualité et le Open - International 0.00 2021-07-19 2022-02-04 2021-08-09 2022-02-17 2021-09-22 2021-10-20 2021-11-19 2021-12-24 2022-01-28 2023-01-28 d'exécution Ndiébène-Gandiol et Gandon Planning coût (en 3 lots) SN-ADM-01-CS-SFQC / Sélection d'un Cabinet pour la Component 3: Strengthening Sélection fondée conception , IDA / 62730 Urban and Coastal Resilience A posteriori sur la qualité et le Open - National 0.00 Annulé 2018-11-07 2019-12-18 2018-11-21 2019-01-04 2019-02-01 2019-03-03 2019-04-07 2019-05-12 2020-05-06 opérationnalisation du Planning coût Système d'alerte précoce local (SAPL) INDIVIDUAL CONSULTANTS Page 3 Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Planned SN-ADM-04-CS-CI / Relocation of Populations Recrutement d'un expert IDA / 62730 Living in the Highest Risk A posteriori Individuel Open 0.00 Annulé 2018-08-16 2018-04-10 2018-10-04 2018-10-25 2018-11-29 2022-11-08 social pour assister l'équipe Zones in the Langue de du projet basée à St Louis Barbarie SN-ADM-05-CS-CI / Recrutement d'un spécialiste Component 5: Project en sauvegarde IDA / 62730 Management, Monitoring and A posteriori Individuel Open 0.00 Annulé 2018-08-20 2018-03-30 2018-10-08 2018-10-29 2018-12-03 2022-11-12 environnementale et sociale Evaluation pour assister l'équipe du projet basée à St Louis SN-ADM-06-CS-CI / Component 5: Project Recrutement d'un assistant en IDA / 62730 Management, Monitoring and A posteriori Individuel Open 0.00 Annulé 2018-09-12 2018-04-25 2018-10-31 2018-11-21 2018-12-26 2022-12-05 suivi et évaluation pour Evaluation assister l'ADM SN-ADM-07-CS-CI / Recrutement d'un expert en Component 5: Project En attente génie civil avec une expertise IDA / 62730 Management, Monitoring and A posteriori Individuel Open 0.00 2018-08-29 2018-10-17 2018-11-07 2018-12-12 2022-11-21 d'exécution en génie côtier pour assister Evaluation l'ADM SN-ADM-01-CS-ED / Sélection d'un Cabinet pour les Études Techniques (APS) environnementale et sociale Component 3: Strengthening Sélection de pour la proposition d'une IDA / 62730 Urban and Coastal Resilience A priori consultants par Direct 2,018,523.72 Signé 2018-09-07 2019-03-08 2018-09-17 2019-03-05 2018-11-05 2020-01-16 2020-04-28 solution de protection durable Planning entente directe du littoral au niveau de la langue de Barbarie et le Plan Directeur de Drainage. Avec le Groupement EGIS/DELTARES SN-ADM-03-CS-ED / Sélection d'un Cabinet Component 5: Project Sélection de assistant technique IDA / 62730 Management, Monitoring and A priori consultants par Direct 537,399.86 Signé 2019-03-04 2020-07-08 2019-03-14 2020-07-10 2019-05-18 2021-05-05 2020-05-12 international au projet avec Evaluation entente directe Cabinet CREOCEAN Component 2: Planned SN-ADM-04-CS-CIB / Relocation of Populations Recrutement d'un expert IDA / 62730 Living in the Highest Risk A posteriori Individuel Open 2,818.16 Signé 2018-04-10 2019-05-05 2019-06-14 2019-08-15 2019-07-14 2019-09-12 2019-09-16 2019-09-16 2020-09-15 social pour assister l'équipe Zones in the Langue de du projet basée à Saint Louis Barbarie SN-ADM-06-CS-CIB / Component 5: Project Recrutement d'un assistant en IDA / 62730 Management, Monitoring and A posteriori Individuel Open 113,790.19 Signé 2018-04-25 2018-10-01 2018-11-01 2019-01-02 2018-12-16 2019-02-16 2019-02-20 2019-02-01 2022-12-31 suivi et évaluation pour Evaluation assister l'ADM SN-ADM-13-CS-CI / Component 5: Project Sélection d'un Spécialiste en IDA / 62730 Management, Monitoring and A posteriori Individuel Open 295,691.28 Signé 2019-12-13 2020-01-14 2020-01-06 2020-05-26 2020-01-11 2020-05-29 2020-01-19 2020-06-19 2023-07-02 Passation de Marchés Evaluation SN-ADM-01-CI-ED / Sélection Directe d'un Component 5: Project consultant Individuel IDA / 62730 Management, Monitoring and A posteriori Individuel Direct 191,233.79 Signé 2019-12-16 2020-02-14 2019-12-24 2020-02-24 2019-12-26 2020-02-28 2019-12-30 2020-04-01 2023-06-30 Assistant Technique National Evaluation en Ingénierie Sociale. Avec Mouhamadou BA SN-ADM-06-CI-ED / Sélection Directe d'un Component 5: Project En cours consultant Individuel Expert IDA / 62730 Management, Monitoring and A posteriori Individuel Direct 0.00 2019-12-16 2018-08-03 2019-12-24 2019-12-26 2019-12-30 2023-06-30 d'exécution Environnementaliste. Avec Evaluation Insa FALL SN-ADM-05-CI-ED / Sélection Directe d'un Component 5: Project consultant Individuel IDA / 62730 Management, Monitoring and A posteriori Individuel Direct 188,599.45 Signé 2019-12-16 2020-02-14 2019-12-24 2020-02-24 2019-12-26 2020-02-28 2019-12-30 2020-04-01 2023-06-30 Spécialiste en sauvegarde Evaluation sociale. Avec Marie Solange NDIONE SN-ADM-03-CI-ED / Sélection Directe d'un consultant Individuel Component 5: Project Spécialiste en Hygiène, Santé, IDA / 62730 Management, Monitoring and A posteriori Individuel Direct 59,560.23 Signé 2019-12-16 2018-10-02 2019-12-24 2018-08-14 2019-12-26 2019-03-08 2019-12-30 2019-04-22 2023-06-30 Sécurité Environnement & Evaluation Social (HESSS). Avec Lala Youssou NDIAYE SN-ADM-04-CI-ED / Sélection Directe d'un Component 5: Project consultant Individuel IDA / 62730 Management, Monitoring and A posteriori Individuel Direct 90,839.21 Signé 2019-12-16 2020-02-13 2019-12-24 2020-02-24 2019-12-26 2020-02-28 2019-12-30 2020-04-01 2023-06-30 Assistant de Projet. Avec Evaluation Khady Manel FALL SN-ADM-07-CI-ED / Sélection Directe d'un Component 5: Project Sélection de En cours consultant Individuel Expert IDA / 62730 Management, Monitoring and A posteriori consultants par Direct 0.00 2019-12-19 2018-08-03 2019-12-23 2019-12-29 2023-06-30 d'exécution en Développement urbain. Evaluation entente directe Avec Amadou Diouldé DIALLO SN-ADM-12-CONS-CI / Sélection d’un consultant pour la réalisation de l’Étude d’Impact Environnemental et Component 3: Strengthening Social (EIES) de IDA / 62730 Urban and Coastal Resilience A posteriori Individuel Limited 46,126.08 Signé 2020-01-17 2019-11-05 2020-01-20 2019-11-11 2020-01-23 2019-12-23 2020-01-28 2020-01-21 2020-02-27 l’aménagement définitif du Planning site de relogement de Djougop et de la libération de la bande des 20m sur la langue de Barbarie. SN-ADM-160320-CS-INDV / Component 5: Project Recrutement d’un comptable IDA / 62730 Management, Monitoring and A posteriori Individuel Open 121,394.45 Signé 2020-02-24 2020-02-20 2020-04-13 2021-02-12 2020-05-04 2021-03-24 2020-06-08 2021-04-05 2023-06-30 dans le cadre du SERRP Evaluation Page 4 SN-ADM-160526-CS-INDV / Component 2: Planned Recrutement d’un Géomètre Relocation of Populations agréé pour la délimitation de IDA / 62730 Living in the Highest Risk A posteriori Individuel Limited 2,208.10 Signé 2020-03-02 2020-03-12 2020-03-07 2020-04-23 2020-03-28 2020-05-22 2020-05-02 2020-07-03 2020-05-08 l’assiette foncière de la bande Zones in the Langue de des 20 mètres de la Langue Barbarie de Barbarie à Saint Louis. SN-ADM-161658-CS-INDV / Conception et opérationnalisation d'un Component 4: Contingent système d'alerte précoce (SAP) IDA / 62730 Emergency Response A posteriori Individuel Open 37,384.88 Signé 2019-11-21 2019-10-17 2020-01-09 2020-01-10 2020-01-30 2020-02-07 2020-03-05 2020-02-14 2020-09-01 provisoire pour faire face aux Component impacts du changement climatique sur la LANGUE DE BARBARIE SN-ADM-161660-CS-INDV / Sélection Directe d'un Component 5: Project consultant Individuel IDA / 62730 Management, Monitoring and A posteriori Individuel Direct 182,547.87 Signé 2020-02-14 2020-02-14 2020-02-24 2020-02-26 2020-03-16 2020-02-28 2020-04-20 2020-04-01 2023-06-30 Ingénieur Génie Civil Evaluation spécialisé en Hydraulique SN-ADM-165141-CS-INDV / Supervision des travaux Component 1: Meeting d'aménagement du site de IDA / 62730 Immediate Needs of the A posteriori Individuel Open 55,621.04 Signé 2020-03-20 2020-03-19 2020-05-08 2020-05-05 2020-05-29 2020-05-11 2020-07-03 2020-06-04 2020-12-30 relogement provisoire (2e Disaster Affected Population phase) SN-ADM-165134-CS-INDV / SÉLECTION DIRECTE D’UN CONSULTANT EN CHARGE DE PRÉPARER UNE ANNEXE DU Component 5: Project MANUEL DE PROCEDURES IDA / 62730 Management, Monitoring and A posteriori Individuel Direct 34,000.00 Signé 2020-03-19 2020-03-15 2020-03-23 2020-03-18 2020-03-25 2020-03-23 2020-03-27 2020-04-09 2020-05-11 EXISTANT, PORTANT SUR LE Evaluation CYCLE DE GESTION ET DE SUIVI DES PROCESSUS DE PASSATION ET D’EXECUTION DES MARCHES DE L’ADM SN-ADM-168569-CS-INDV / RECRUTEMENT D’UN(E) CONSULTANT(E) Component 3: Strengthening INDIVIDUEL(LE) POUR IDA / 62730 Urban and Coastal Resilience A posteriori Individuel Open 88,265.18 Signé 2020-04-20 2020-04-08 2020-06-08 2020-06-09 2020-06-29 2020-06-15 2020-08-03 2020-07-22 2021-01-30 L’ÉLABORATION ET L’APPUI A Planning LA MISE EN ŒUVRE DU PLAN DE FORMATION DES ACTEURS DU SERRP SN-ADM-01-CS-CI / Component 2: Planned Sélection d'un Consultant Relocation of Populations individuel pour l'étude et le IDA / 62730 Living in the Highest Risk A posteriori Individuel Open 69,335.05 Signé 2020-06-17 2019-11-22 2020-08-05 2020-01-16 2020-08-26 2020-07-08 2020-09-30 2020-08-07 2022-12-19 suivi architectural des travaux Zones in the Langue de de construction de logements Barbarie et d'équipement sociaux SN-ADM-183283-CS-INDV / SELECTION D’UN ASSISTANT TECHNIQUE SPECIALISTE DES Component 5: Project VILLES DURABLES ET IDA / 62730 Management, Monitoring and A priori Individuel Open 296,489.78 Signé 2020-07-15 2020-07-21 2020-09-02 2021-02-19 2020-09-23 2021-04-05 2020-10-28 2021-04-28 2021-04-26 RESILIENTES POUR APPUYER Evaluation LA MISE EN ŒUVRE DES ACTIVITES PREVUES DANS LE SERRP SN-ADM-191242-CS-INDV / ELABORATION DE L’AUDIT DE LA MISE EN ŒUVRE DU PLAN Component 2: Planned D’ACTIONS DE Relocation of Populations REINSTALLATION DE IDA / 62730 Living in the Highest Risk A posteriori Individuel Open 29,464.45 Signé 2020-09-03 2020-09-07 2020-10-22 2020-03-19 2020-11-12 2020-03-19 2020-12-17 2020-04-02 2021-06-15 L’AMENAGEMENT PROVISOIRE Zones in the Langue de DU SITE DE DJOUGOP ET DU Barbarie DEPLACEMENT DES PERSONNES AFFECTEES PAR LE PROJET SN-ADM-11-CS-CI / Élaboration d'une stratégie Component 5: Project visant les modalités IDA / 62730 Management, Monitoring and A posteriori Individuel Open 0.00 Annulé 2020-11-02 2020-12-21 2021-01-11 2021-02-15 2025-01-25 d'allocation de logements en Evaluation complément du PAR SN-ADM-205155-CS-INDV / RECRUTEMENT D’UN Component 2: Planned CONSULTANT CHARGE DE Relocation of Populations L’ELABORATION DU PLAN DE IDA / 62730 Living in the Highest Risk A posteriori Individuel Open 20,575.85 Signé 2020-11-20 2020-11-16 2021-01-08 2021-01-08 2021-01-29 2021-01-18 2021-03-05 2021-02-09 2021-09-01 RESTAURATION DES MOYENS Zones in the Langue de DE SUBSISTANCE (PRMS) DES Barbarie PERSONNES AFFECTEES DE LA LANGUE DE BARBARIE SN-ADM-234572-CS-INDV / Component 5: Project Recrutement d’un (e) Expert(e) IDA / 62730 Management, Monitoring and A posteriori Individuel Open 288,515.65 Signé 2021-05-24 2021-05-21 2021-07-12 2021-07-12 2021-08-02 2021-07-15 2021-09-06 2021-08-11 2022-03-05 en intermédiation sociale dans Evaluation le cadre du SERRP SN-ADM-234596-CS-INDV / Component 2: Planned Sélection d'un Consultant Relocation of Populations En attente pour l'étude de démolition IDA / 62730 Living in the Highest Risk A posteriori Individuel Limited 0.00 2021-10-18 2021-10-21 2021-10-24 2021-10-29 2021-11-28 d'exécution des maisons au niveau de la Zones in the Langue de LB Barbarie SN-ADM-09-CS-CI / Component 5: Project Recrutement d'un comptable IDA / 62730 Management, Monitoring and A posteriori Individuel Open 0.00 Annulé 2019-04-01 2020-02-20 2019-05-20 2019-06-10 2019-07-15 2023-06-24 basé à St Louis Evaluation SN-ADM-08-CS-CI / Component 5: Project Recrutement d'un assistant à IDA / 62730 Management, Monitoring and A posteriori Individuel Open 0.00 Annulé 2018-11-07 2019-12-31 2018-12-26 2019-01-16 2019-02-20 2023-01-30 la coordination du projet Evaluation SN-ADM-02-CI-ED / Sélection Directe d'un Component 5: Project consultant Individuel IDA / 62730 Management, Monitoring and A posteriori Individuel Open 0.00 Annulé 2019-12-16 2020-02-14 2019-12-25 2019-12-27 2019-12-31 2023-06-30 Ingénieur Génie Civil Evaluation spécialisé en Hydraulique. Avec Lamine Doumbouya Page 5 SN-ADM-234880-CS-INDV / Component 2: Planned Recrutement d'un expert Relocation of Populations social pour assister l'équipe IDA / 62730 Living in the Highest Risk A posteriori Individuel Open 190,951.02 Signé 2021-05-24 2021-06-01 2021-07-12 2021-10-22 2021-08-02 2021-09-08 2021-09-06 2021-12-01 2022-03-05 du projet basée à St Louis Zones in the Langue de (remplacement/démission) Barbarie SN-ADM-206510-CS-INDV / Recrutement d’un (e) Expert(e) Component 5: Project en médiation sociale et lutte IDA / 62730 Management, Monitoring and A posteriori Individuel Open 0.00 Annulé 2020-12-03 2020-11-25 2021-01-21 2021-02-11 2021-03-18 2021-09-14 contre les violences basées Evaluation sur le genre dans le cadre du SERRP SN-ADM-10-CS-CI / Component 5: Project Recrutement d'un expert de la IDA / 62730 Management, Monitoring and A posteriori Individuel Open 0.00 Annulé 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2023-06-24 résilience urbaine Evaluation SN-ADM-05-CS-CIB / Recrutement d'un spécialiste Component 3: Strengthening en sauvegarde IDA / 62730 Urban and Coastal Resilience A posteriori Individuel Open 0.00 Annulé 2018-03-30 2018-05-02 2018-06-20 2018-08-04 2018-10-01 2023-12-31 environnementale et sociale Planning pour assister l'équipe du projet basée à St Louis Component 2: Planned SN-ADM-02-CS-CI / Relocation of Populations Sélection d'un Consultant IDA / 62730 Living in the Highest Risk A posteriori Individuel Limited 49,774.27 Signé 2021-08-09 2021-06-22 2021-08-14 2021-07-15 2021-08-28 2021-08-24 2021-09-18 2021-11-10 2021-12-17 individuel pour l'étude de plan Zones in the Langue de béton armé des logements Barbarie Component 2: Planned SN-ADM-03-CS-CI / Relocation of Populations Sélection d'un Consultant IDA / 62730 Living in the Highest Risk A posteriori Individuel Limited 20,595.24 Signé 2021-08-09 2021-06-30 2021-08-14 2021-07-13 2021-09-04 2021-08-16 2021-10-09 2021-10-12 2022-01-07 individuel pour l'étude des Zones in the Langue de lots techniques des logements Barbarie SN-ADM-247450-CS-INDV / SELECTION D’UN CONSULTANT INDIVIDUEL Component 2: Planned POUR LES ETUDES Relocation of Populations ARCHITECTURALES DU IDA / 67600 Living in the Highest Risk A posteriori Individuel Limited 32,457.93 Signé 2021-08-16 2021-08-10 2021-08-21 2021-08-24 2021-09-11 2021-10-11 2021-10-16 2021-11-09 2022-04-14 MARCHE, DU POSTE DE Zones in the Langue de SANTE, DU COLLEGE DU Barbarie PROJET DE RELOGEMENT DES POPULATIONS SUR LE SITE DE DIOUGOP SN-ADM-02-CS-ED / Sélection d'un Cabinet pour les Etudes Techniques d'APD et DAO pour la proposition Component 3: Strengthening Sélection de d'une solution de protection IDA / 62730 Urban and Coastal Resilience A posteriori consultants par Direct 0.00 Annulé 2020-03-05 2020-06-17 2020-03-15 2018-10-22 2020-05-10 2021-05-05 durable du littoral au niveau Planning entente directe de la langue de Barbarie et le Plan Directeur de Drainage. Avec le Groupement EGIS/DELTARES Page 6