The World Bank Implementation Status & Results Report Strengthening the Statistical System of Uzbekistan (P173450) Strengthening the Statistical System of Uzbekistan (P173450) EUROPE AND CENTRAL ASIA | Uzbekistan | Poverty and Equity Global Practice | IBRD/IDA | Investment Project Financing | FY 2022 | Seq No: 1 | ARCHIVED on 27-Jun-2022 | ISR52015 | Implementing Agencies: State Committee of the Republic of Uzbekistan on Statistics, The Ministry of Finance of Uzbekistan Key Dates Key Project Dates Bank Approval Date: 16-Feb-2022 Effectiveness Date: -- Planned Mid Term Review Date: -- Actual Mid-Term Review Date: Original Closing Date: 15-Jul-2027 Revised Closing Date: 15-Jul-2027 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The PDO is to strengthen the capacity of Uzbekistan’s national statistical system to produce and disseminate statistics. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Institutional Reform and Capacity:(Cost $2.30 M) Data Production:(Cost $30.00 M) Improving Equipment and Dissemination:(Cost $15.70 M) Project Management:(Cost $2.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO -- Satisfactory Overall Implementation Progress (IP) -- Satisfactory Overall Risk Rating -- Moderate Implementation Status and Key Decisions In June 2022, the client published the POM acceptable to the World Bank, and announced the competitive process for selecting PMU team members with ToR's acceptable to the World Bank. These materials are available on the Statistics Committee website: https://stat.uz/en/legal-acts/strengthening-the-statistical-system-of-uzbekistan-project https://stat.uz/en/press-center/news-of-committee/22997-e-lon64567457474-3 The project is not yet effective, as the final effectiveness condition (the formation of the project management unit) is not net complete. 6/27/2022 Page 1 of 4 The World Bank Implementation Status & Results Report Strengthening the Statistical System of Uzbekistan (P173450) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Moderate -- Moderate Macroeconomic Moderate -- Moderate Sector Strategies and Policies Low -- Low Technical Design of Project or Program Low -- Low Institutional Capacity for Implementation and Substantial -- Substantial Sustainability Fiduciary Substantial -- Substantial Environment and Social Moderate -- Moderate Stakeholders Moderate -- Moderate Other -- -- -- Overall Moderate -- Moderate Results PDO Indicators by Objectives / Outcomes Statistical Performance Index IN01162374 ►Statistical Performance Indicators (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 54.90 -- 54.90 72.00 Date 01-Jun-2019 -- 01-Jun-2022 01-Jun-2024 The most recent SPI for Uzbekistan was 54.9 measured in 2019. Comments: Overall Comments PDO The project is not yet effective. The most recent SPI for Uzbekistan is 54.9 in 2019. Intermediate Results Indicators by Components 6/27/2022 Page 2 of 4 The World Bank Implementation Status & Results Report Strengthening the Statistical System of Uzbekistan (P173450) Data Production IN01162431 ►Rounds of modernized household budget survey published online (Number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 6.00 Date 01-Jun-2022 -- 01-Jun-2022 02-Jun-2025 Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed Not P173450 IDA-70380 USD 50.00 50.00 0.00 0.00 50.00 0% Effective Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date Not P173450 IDA-70380 16-Feb-2022 23-Apr-2022 -- 15-Jul-2027 15-Jul-2027 Effective Cumulative Disbursements 6/27/2022 Page 3 of 4 The World Bank Implementation Status & Results Report Strengthening the Statistical System of Uzbekistan (P173450) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 6/27/2022 Page 4 of 4