PROCUREMENT PLAN Project information: Federal Democratic Republic of Ethiopia Resilient landscape and Livelihood, Project [P163383] Project Implementation agency: Ministry of Agriculture and Livestock Resource Date of the Procurement Plan: October 25, 2018 Period covered by this Procurement Plan: October 2018- December 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Procurement and Property Administration Proclamation No 649/2009, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable PROCUREMENT Ethiopia : Ethiopia Resilient Landscapes and Livelihoods Project PLAN General Information Country: Ethiopia 2018-10-29 Bank’s Approval Date of the Original Procurement Plan: 2022-06-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163383 GPN Date: 2018-10-25 Project Name: Ethiopia Resilient Landscapes and Livelihoods Project Loan / Credit No: IDA / 63120, TF / A9048 Ministry of Agriculture and Livestock Resources Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOALR-83767-GO-RFB / Office equipment for woreda Green Infrastructure and Re Open - Internationa Single Stage - One E IDA / 63120 Prior Request for Bids 1,987,791.00 922,381.33 Completed 2018-11-12 2018-12-19 2018-11-17 2019-01-03 2019-01-01 2019-02-14 2019-01-15 2019-07-15 2019-02-08 2020-08-10 2019-06-08 2020-08-10 s, regions and Federal projec silient Livelihoods l nvelope t implementing units ET-MOALR-84714-GO-RFB / Hand Held GPS for new wore das land administration and watershade (260 units, 130 f Green Infrastructure and Re Single Stage - One E IDA / 63120 Post Request for Bids Open - National 295,498.00 261,956.45 Completed 2019-01-31 2019-02-01 2019-02-05 2019-03-07 2019-06-27 2019-03-17 2019-07-10 2019-04-03 2019-07-25 2019-07-02 2019-10-23 or watershed and 130 for Lan silient Livelihoods nvelope d administration),Total Statio n 3 units (for Amhara, Oromi a and SNNP Watershade) an d Edelman Auger (51 units) ET-MOALR-84728-GO-RFB / Back Up Server (Synology) a nd workstation computer wit h UPS for Land administratio Green Infrastructure and Re Single Stage - One E IDA / 63120 Post Request for Bids Open - National 354,085.00 106,383.38 Completed 2019-03-12 2019-09-02 2019-03-17 2019-04-16 2019-10-01 2019-05-01 2019-11-10 2019-05-22 2019-12-16 2019-08-20 2020-04-15 n and M&E and Mid-range Se silient Livelihoods nvelope rver for Gambela (1 units) an d server computer for M&E ( 1 unit) and Large format Plot ter (6 units) for six regions ET-MOALR-84738-GO-RFQ / Project Management and Re Request for Quota Single Stage - One E Stationary and office consum IDA / 63120 Post Limited 10,500.00 3,448.36 Completed 2019-01-06 2020-06-12 2019-01-30 2020-07-28 2019-03-01 2020-09-08 porting tions nvelope able items for 2019 ET-MOALR-84742-GO-RFQ / Project Management and Re Request for Quota Single Stage - One E Tire and inner tube for federa IDA / 63120 Post Limited 12,250.00 13,628.27 Completed 2019-10-06 2019-07-23 2019-11-06 2019-07-31 2019-12-06 2019-08-12 porting tions nvelope l seven vehicles ET-MOALR-85715-GO-RFB / Woreda information center e Investing in Institutions and I Single Stage - One E IDA / 63120 Post Request for Bids Open - National 250,000.00 192,759.68 Completed 2019-02-05 2019-10-03 2019-02-10 2019-10-10 2019-03-12 2019-10-24 2019-03-26 2019-11-25 2019-04-19 2019-12-16 2019-07-18 2020-04-03 stablishment materials (com nformation for Resilience nvelope puters, network cables and o ther related equipment ET-MOALR-85717-GO-RFB / P rocurement of equipment for National Rural Land Administ Rural Land Administration a Single Stage - One E IDA / 63120 Post Request for Bids Open - National 125,700.00 262,399.80 Completed 2019-01-31 2020-01-01 2019-02-05 2020-01-22 2019-03-07 2020-01-28 2019-03-28 2020-03-13 2019-05-02 2020-04-06 2019-07-31 2020-08-21 ration Information System (N nd Use nvelope RLAIS) for all RLLP woredas ( Network Cables, Rawters, fis her and related materials) ET-MOALR-86952-GO-RFB / Software procurement and In Green Infrastructure and Re Single Stage - One E IDA / 63120 Post Request for Bids Open - National 70,000.00 0.00 Canceled 2019-02-28 2019-03-05 2019-04-04 2019-04-18 2019-05-12 2019-07-11 stallation for data collection ( silient Livelihoods nvelope SPSS,SAS.Arc GIS collector) f or 152 watersheds ET-MOALR-84721-GO-RFB / Unmanned Aerial Vehicle (U Rural Land Administration a Single Stage - One E IDA / 63120 Post Request for Bids Open - National 385,415.00 0.00 Canceled 2019-01-31 2019-02-05 2019-03-07 2019-03-21 2019-04-18 2019-09-15 AV)/ Drone with its accessori nd Use nvelope es and software (6 units) ET-MOALR-83764-GO-DIR / V Green Infrastructure and Re UN Agencies (Dire ehicles Station Wagon Vehicl IDA / 63120 Prior Direct 2,180,000.00 1,571,421.57 Completed 2018-12-17 2019-01-22 2018-12-31 2019-03-12 2019-02-04 2019-04-24 2019-08-03 2020-01-06 silient Livelihoods ct) es (20 units) and Motor bicy cles (276 units) ET-MOALR-142397-GO-RFQ / Green Infrastructure and Re Request for Quota Single Stage - One E IDA / 63120 Post Limited 22,000.00 17,747.01 Completed 2019-11-05 2019-11-20 2019-12-03 2019-11-30 2020-01-02 2020-01-27 Procurement of laptops silient Livelihoods tions nvelope ET-MOALR-86957-GO-RFB / I nstallation and training of N Rural Land Administration a Single Stage - One E ational Rural Land Administra IDA / 63120 Post Request for Bids Open - National 195,000.00 0.00 Canceled 2019-02-25 2019-03-02 2019-04-01 2019-04-15 2019-05-05 2019-08-03 nd Use nvelope tion Information System (NRL AIS) software at woreda, Zon e and region level ET-MOALR-188900-GO-RFQ / Investing in Institutions and I Request for Quota Single Stage - One E Procurement of Sanitary mat TF / A9048 Post Limited 68,000.00 65,974.11 Completed 2020-09-01 2020-08-18 2020-10-23 2020-08-25 2020-12-22 2020-08-25 nformation for Resilience tions nvelope erials to protect COVID-19 ET-MOALR-197465-GO-UN / Green Infrastructure and Re UN Agencies (Dire Procurement of 4 vehicles an IDA / 63120 Prior Direct 300,000.00 0.00 Canceled 2020-11-24 2020-11-29 2021-01-03 2021-07-02 silient Livelihoods ct) d 54 motorcycles for GAC wo redas ET-MOALR-199731-GO-RFB / Office equipment for Land Ad Investing in Institutions and I Single Stage - One E IDA / 63120 Post Request for Bids Open - National 550,000.00 295,197.56 Signed 2020-11-01 2020-11-09 2020-12-01 2020-11-09 2020-12-16 2020-12-03 2021-01-06 2021-01-27 2021-02-03 2021-03-26 2021-05-04 2021-07-07 ministration and Woreda info nformation for Resilience nvelope rmation Centers ET-MOALR-203863-GO-RFQ / Green Infrastructure and Re Request for Quota Single Stage - One E Microsoft Windows 2019 and TF / A9048 Post Limited 15,800.00 7,460.04 Completed 2020-11-21 2020-12-03 2020-12-29 2021-01-15 2021-02-12 2021-04-21 silient Livelihoods tions nvelope Microsoft SQL Server Govern ment License ET-MOALR-210313-GO-UN / Green Infrastructure and Re UN Agencies (Dire Procurement of 4 vehicles an IDA / 63120 Post Direct 335,000.00 412,368.89 Completed 2020-12-18 2020-12-21 2020-12-23 2020-12-22 2021-01-27 2020-12-24 2021-05-27 2021-06-30 silient Livelihoods ct) d 54 motorcycles for GAC wo redas Page 1 ET-MOALR-212923-GO-RFQ / Desktop (20 units) and lapto Rural Land Administration a Request for Quota Single Stage - One E IDA / 63120 Post Limited 52,000.00 32,927.84 Completed 2021-05-28 2021-05-24 2021-06-23 2021-07-07 2021-07-13 2021-08-10 p computers (20 units) for La nd Use tions nvelope nd administration (18 GAC W oredas) ET-MOALR-234546-GO-RFQ / Project Management and Re Request for Quota Single Stage - One E Procurement of tire and inner IDA / 63120 Post Limited 15,000.00 0.00 Canceled 2021-06-06 2021-07-25 2021-08-24 porting tions nvelope tube for NPCU vehicles ET-MOALR-236818-GO-RFQ / Procurement of office equip ment for Sidama Region (Des Project Management and Re Request for Quota Single Stage - One E IDA / 63120 Post Limited 40,000.00 17,946.68 Completed 2021-06-12 2021-08-26 2021-07-10 2021-09-27 2021-08-09 2021-10-27 ktop Computers (7), Laptop C porting tions nvelope omputers (12), Printers (8), C opiers (2), hard disks (12), sc anners (2) and projectors (2)) . ET-MOALR-236820-GO-RFQ / Project Management and Re Request for Quota Single Stage - One E Office furniture (Tables, chair IDA / 63120 Post Limited 11,000.00 5,536.63 Completed 2021-06-15 2021-06-10 2021-07-13 2021-06-30 2021-08-12 2021-08-10 porting tions nvelope , shelf, gust chairs and safe b ox) ET-MOALR-240017-GO-RFQ / Green Infrastructure and Re Request for Quota Single Stage - One E Soil acidity measurement or IDA / 63120 Post Limited 42,000.00 37,831.50 Completed 2021-07-05 2021-06-10 2021-08-02 2021-08-19 2021-09-01 2021-12-01 silient Livelihoods tions nvelope PH test devices ET-MOALR-244510-GO-RFB / Procurement of desktop com puters (91 units), Laptop co Rural Land Administration a Single Stage - One E IDA / 63120 Post Request for Bids Open - National 120,000.00 149,617.85 Signed 2021-08-12 2021-09-08 2021-08-17 2021-09-08 2021-09-28 2021-10-14 2021-10-12 2021-11-16 2021-11-16 2021-12-03 2022-02-14 2021-12-27 mputers (15 units), UPS (91 nd Use nvelope Units), External Hard Disk (6 6 units) and network material s (network cable, switch and Rj-45). ET-MOALR-255790-GO-RFQ / COVID-19 protection material Project Management and Re Request for Quota Single Stage - One E Under Imple s for Amhara 9 displaced proj TF / A9048 Post Limited 35,600.00 36,024.28 2021-10-12 2021-10-07 2021-11-16 2021-10-15 2021-12-16 2021-10-20 porting tions nvelope mentation ect woreda communities due to conflict (Sanitazer, soap, a nd facemask) ET-MOALR-285997-GO-RFB / Scientific instruments for hyd Investing in Institutions and I Single Stage - One E Under Imple ro - sediment and weather/cli IDA / 63120 Post Request for Bids Open - National 150,000.00 0.00 2022-04-12 2022-04-15 2022-05-12 2022-04-15 2022-06-01 2022-07-01 2022-07-29 2022-10-27 nformation for Resilience nvelope mentation mate measurement for the i mplementation of biophysical impact evaluation ET-MOALR-301460-GO-RFQ / Green Infrastructure and Re Request for Quota Single Stage - One E Pending Impl Procurement of T-Shirt for m IDA / 63120 Post Limited 6,000.00 0.00 2022-07-06 2022-08-03 2022-08-23 silient Livelihoods tions nvelope ementation ass plantation of forest and fr uit seedling NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOALR-86964-NC-RFQ / P Green Infrastructure and Re Request for Quota Single Stage - One E rinting Soil Fertility improve IDA / 63120 Post Limited 3,000.00 4,884.03 Completed 2019-03-17 2019-12-19 2019-04-21 2019-12-31 2019-06-05 2020-03-10 silient Livelihoods tions nvelope ment package of technologie s field manual ET-MOALR-86955-NC-RFQ / P rinting the RLLP Safeguard d Green Infrastructure and Re Request for Quota Single Stage - One E IDA / 63120 Post Limited 25,400.00 14,922.02 Completed 2019-02-17 2019-05-15 2019-03-31 2019-09-16 2019-05-30 2020-01-06 ocument (ESMF, RPF, SA and silient Livelihoods tions nvelope Gender main streming) guide line ET-MOALR-244505-GO-RFB / Rural Land Administration a Single Stage - One E Procurement of satellite imag IDA / 63120 Post Request for Bids Open - National 140,000.00 58,662.87 Completed 2021-08-30 2021-09-08 2021-09-04 2021-09-08 2021-10-04 2021-10-19 2021-10-24 2021-12-03 2021-11-21 2021-12-03 2022-02-19 2022-03-22 nd Use nvelope e (2,500 sq.km) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOALR-85236-CS-LCS / A Project Management and Re Least Cost Selecti udit firm for Financial Audit S IDA / 63120 Post Open - National 22,000.00 3,338.75 Signed 2019-06-03 2019-10-10 2019-06-24 2019-07-29 2019-10-02 2019-08-19 2019-10-02 2019-09-02 2019-10-10 2019-09-23 2019-11-04 2019-10-21 2019-11-11 2019-12-20 2020-01-29 porting on ervice 2019/20 ET-MOALR-85701-CS-LCS / R Investing in Institutions and I Least Cost Selecti IDA / 63120 Post Open - National 17,817.00 0.00 Canceled 2019-01-21 2019-02-11 2019-03-07 2019-03-21 2019-03-31 2019-05-05 2019-05-29 2019-07-28 evision of Financial Manual fo nformation for Resilience on r RLLP ET-MOALR-85702-CS-LCS / U Investing in Institutions and I Least Cost Selecti pdating and revision of Harm IDA / 63120 Post Open - National 20,000.00 0.00 Canceled 2019-06-03 2019-11-28 2019-06-24 2020-06-16 2019-08-07 2019-08-21 2019-08-31 2019-09-20 2019-10-10 2020-01-08 nformation for Resilience on onized Result based M&E gui deline ET-MOALR-85711-CS-QCBS / Green Infrastructure and Re Quality And Cost- Open - Internationa Bamboo for Landscape Resto IDA / 63120 Prior 1,000,000.00 0.00 Canceled 2019-01-31 2019-02-15 2019-03-15 2019-04-14 2019-05-05 2019-06-02 2019-06-30 2023-08-08 silient Livelihoods Based Selection l ration and Livelihood diversifi cation ET-MOALR-85707-CS-QCBS / Investing in Institutions and I Quality And Cost- Independent procurement au IDA / 63120 Prior Open - National 100,000.00 42,991.30 Completed 2020-06-01 2020-06-24 2020-06-15 2020-08-09 2020-07-09 2021-01-02 2020-08-06 2021-02-04 2020-08-16 2021-03-22 2020-09-09 2021-05-05 2020-10-07 2021-05-10 2021-02-04 2022-04-11 nformation for Resilience Based Selection dit for project during mid ter m ET-MOALR-98608-CS-QCBS / Green Infrastructure and Re Quality And Cost- Afforestation/Reforestation/R IDA / 63120 Post Open - National 35,800.00 0.00 Canceled 2019-02-12 2019-03-07 2019-02-26 2019-10-10 2019-03-19 2019-11-14 2019-04-18 2019-04-25 2019-05-09 2019-05-26 2019-07-25 silient Livelihoods Based Selection estoration status assessment for SLMP ET-MOALR-85700-CS-LCS / R evision and Updating of Coun Green Infrastructure and Re Least Cost Selecti IDA / 63120 Post Open - National 20,000.00 0.00 Canceled 2019-02-01 2019-02-22 2019-04-07 2019-05-05 2019-05-19 2019-06-16 2019-07-10 2019-10-08 try Strategy Investment Fram silient Livelihoods on ework For SLM (ESIF) ET-MOALR-85755-CS-LCS / C onduct study on the increme Green Infrastructure and Re Least Cost Selecti ntal base flow potential due t IDA / 63120 Post Open - National 9,000.00 0.00 Canceled 2019-03-12 2019-04-02 2019-05-07 2019-05-21 2019-06-04 2019-06-25 2019-07-23 2019-10-21 silient Livelihoods on o the treated land and propo se utilization of water for sm all holder framing Page 2 ET-MOALR-85704-CS-LCS / D Green Infrastructure and Re Least Cost Selecti eveloping Livelihood Develop IDA / 63120 Post Open - National 21,000.00 0.00 Canceled 2019-04-30 2019-05-21 2019-06-18 2019-07-02 2019-07-12 2019-08-05 2019-08-29 2019-11-27 silient Livelihoods on ment Strategy Document ET-MOALR-85703-CS-LCS / R Investing in Institutions and I Least Cost Selecti evision and Updating Capacit IDA / 63120 Post Open - National 18,500.00 0.00 Canceled 2019-09-03 2019-09-24 2019-10-18 2019-11-01 2019-11-11 2019-12-09 2020-01-02 2020-04-01 nformation for Resilience on y Development Strategy for SLMP ET-MOALR-165074-CS-LCS / Project Management and Re Least Cost Selecti External Financial Audit for t IDA / 63120 Post Open - National 29,000.00 9,422.58 Completed 2020-03-23 2020-04-01 2020-04-06 2020-05-11 2020-04-27 2020-05-25 2020-05-25 2020-07-13 2020-06-08 2020-07-14 2020-06-29 2020-07-13 2020-07-13 2020-08-03 2020-09-11 2021-01-01 porting on he project (July 8, 2019 to Jul y 7, 2020) ET-MOALR-85758-CS-LCS / c onduct value chain analysis a Green Infrastructure and Re Least Cost Selecti IDA / 63120 Post Open - National 24,000.00 0.00 Canceled 2019-04-01 2020-03-03 2019-04-22 2019-05-27 2019-06-24 2019-07-08 2019-08-12 2019-09-16 2019-12-15 nd feasibility study on prioriti silient Livelihoods on zed commodities ET-MOALR-211311-CS-LCS / External financial Audit for R Project Management and Re Least Cost Selecti IDA / 63120 Post Open - National 17,500.00 15,984.37 Completed 2020-12-25 2020-12-21 2021-01-08 2021-01-29 2021-01-28 2021-02-26 2021-02-12 2021-03-12 2021-02-19 2021-04-09 2021-03-01 2021-05-07 2021-03-12 2021-07-06 2021-09-28 LLP for the year 2020/21 (bot porting on h Interim and annual) ET-MOALR-212929-CS-QCBS / RLLP Beneficiary Household Green Infrastructure and Re Quality And Cost- Open - Internationa IDA / 63120 Post 112,500.00 118,000.00 Completed 2021-01-15 2021-01-25 2021-01-29 2021-02-05 2021-02-13 2021-03-17 2021-03-13 2021-04-15 2021-03-24 2021-04-27 2021-04-28 2021-05-17 2021-06-02 2021-06-03 2022-06-02 2021-12-31 s Survey on Selected Results silient Livelihoods Based Selection l Frame Work Indicators ET-MOALR-270486-CS-LCS / External Financial Audit for t Project Management and Re Least Cost Selecti IDA / 63120 Post Open - National 16,000.00 13,226.86 Signed 2021-12-27 2022-01-02 2022-01-10 2022-01-28 2022-02-07 2022-02-07 2022-03-07 2022-02-08 2022-03-21 2022-02-08 2022-04-11 2022-02-08 2022-05-02 2022-02-18 2022-07-31 he budget year 2021/22 for R porting on LLP project implementing ag encies INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOALR-83753-CS-INDV / Project Management and Re Individual Consult Senior Procurement and Cont IDA / 63120 Prior Direct 54,100.00 13,192.74 Signed 2018-10-25 2018-11-21 2018-11-04 2018-11-11 2019-02-28 2018-11-26 2019-02-01 2023-12-31 porting ant Selection ract Management Specialist ET-MOALR-83757-CS-INDV / Project Management and Re Individual Consult Senior Planning, Monitoring a IDA / 63120 Post Direct 54,100.00 13,199.07 Completed 2018-10-25 2018-11-14 2018-11-04 2018-11-09 2019-01-24 2018-11-23 2019-01-01 2023-12-31 2019-12-31 porting ant Selection nd Evaluation Specialist ET-MOALR-83759-CS-INDV / Project Management and Re Individual Consult IDA / 63120 Post Direct 100,100.00 12,977.30 Completed 2018-10-25 2018-11-06 2018-11-04 2018-11-09 2019-01-24 2018-11-24 2019-01-15 2023-12-31 2019-12-31 Senior Accountant (two in nu porting ant Selection mber ET-MOALR-83761-CS-INDV / Project Management and Re Individual Consult Procurement and Contract M IDA / 63120 Prior Direct 52,500.00 12,971.08 Signed 2018-10-25 2019-01-29 2018-11-04 2018-11-09 2019-02-28 2018-11-24 2019-01-01 2023-12-31 porting ant Selection anagement Specialist (natio nal) ET-MOALR-83763-CS-INDV / Project Management and Re Individual Consult IDA / 63120 Post Open 54,100.00 13,205.43 Completed 2018-10-25 2018-11-06 2018-11-25 2018-12-03 2019-02-21 2018-12-25 2019-02-27 2024-01-30 2020-09-01 Data base Manger porting ant Selection ET-MOALR-83736-CS-INDV / Project Management and Re Individual Consult IDA / 63120 Post Direct 69,450.00 14,992.02 Completed 2018-10-25 2019-01-09 2018-11-04 2018-11-09 2019-01-24 2018-11-23 2019-01-01 2023-12-30 2019-12-31 National Program Coordinato porting ant Selection r ET-MOALR-83758-CS-INDV / Project Management and Re Individual Consult Senior Financial Management IDA / 63120 Post Direct 54,100.00 13,205.43 Completed 2018-10-25 2018-11-27 2018-11-04 2019-01-20 2018-11-09 2019-02-21 2018-11-23 2019-02-27 2023-12-31 2019-12-31 porting ant Selection Specialist ET-MOALR-85117-CS-CDS / P Project Management and Re lanning, Monitoring and Eval IDA / 63120 Post Direct Selection Direct 54,100.00 0.00 Canceled 2018-11-12 2018-11-14 2018-11-22 2018-12-11 2023-12-30 porting uation Specialist (National) ET-MOALR-85132-CS-INDV / Project Management and Re Individual Consult IDA / 63120 Post Open 54,100.00 0.00 Canceled 2018-11-12 2018-12-21 2018-12-08 2018-12-15 2018-12-27 2023-12-31 Data Manger porting ant Selection ET-MOALR-85695-CS-CDS / B Green Infrastructure and Re Under Implement IDA / 63120 Prior Direct Selection Direct 1,000,000.00 1,072,446.32 2019-01-01 2020-05-25 2019-01-11 2020-07-17 2019-03-08 2024-02-10 io-physical impact evaluation silient Livelihoods ation ET-MOALR-85697-CS-CDS / Green Infrastructure and Re Under Implement Climate Smart Agriculture pr IDA / 63120 Prior Direct Selection Direct 1,000,000.00 0.00 2019-01-01 2020-05-25 2019-01-11 2020-07-28 2019-03-08 2023-11-02 silient Livelihoods ation oductivity impact evaluation ET-MOALR-85699-CS-CDS / S Green Infrastructure and Re ynergies and policy evaluatio IDA / 63120 Prior Direct Selection Direct 500,000.00 0.00 Canceled 2019-01-01 2019-01-11 2019-03-08 2023-11-02 silient Livelihoods n of the biophysical impact e valuations ET-MOALR-85113-CS-CDS / P rocurement and Contract Ma Project Management and Re IDA / 63120 Prior Direct Selection Direct 50,500.00 12,971.08 Signed 2018-11-12 2018-11-22 2018-12-09 2019-01-10 2023-12-30 ng.Specialist (MoALR) procur porting ement Directoret (Seconded) ET-MOALR-97252-CS-INDV / Project Management and Re Individual Consult Planning and monitoring spe IDA / 63120 Post Direct 54,100.00 13,199.07 Completed 2019-01-29 2019-01-01 2019-02-08 2019-02-15 2019-01-15 2019-03-01 2019-12-31 2023-12-31 2019-12-31 porting ant Selection cialist (National) ET-MOALR-98239-CS-INDV / Investing in Institutions and I Individual Consult IDA / 63120 Post Open 7,200.00 0.00 Canceled 2019-02-27 2019-04-02 2019-04-12 2019-05-06 2019-07-05 Update (Re-launch) the SLMP nformation for Resilience ant Selection web portal ET-MOALR-162673-CS-CDS / SLMP Knowledge Manageme Investing in Institutions and I nt Information System (KMIS) IDA / 63120 Prior Direct Selection Direct 500,000.00 0.00 Canceled 2020-03-31 2020-03-19 2020-04-10 2020-06-05 2023-01-01 nformation for Resilience Upgrading, Maintenance and Implementation Training Con sultancy Service ET-MOALR-165707-CS-CDS / SLMP Knowledge Manageme Green Infrastructure and Re nt Information System (KMIS) IDA / 63120 Post Direct Selection Direct 450,000.00 431,470.62 Completed 2020-03-31 2020-03-26 2020-04-10 2020-04-14 2020-06-14 2020-07-17 2023-06-19 2022-02-24 silient Livelihoods Upgrading, Maintenance and Implementation Training Con sultancy Service ET-MOALR-257606-CS-INDV Project Management and Re Individual Consult / Procurement and contract IDA / 63120 Prior Open 25,000.00 5,877.01 Signed 2021-10-11 2021-10-20 2021-11-05 2022-04-01 2021-11-12 2022-05-05 2021-11-26 2022-05-11 2024-04-30 porting ant Selection management specialist for Si dama region Page 3 ET-MOALR-257607-CS-INDV Project Management and Re Individual Consult / Financial Management Spec IDA / 63120 Post Open 25,000.00 221.93 Completed 2021-10-11 2021-10-19 2021-11-09 2021-11-05 2021-11-16 2021-11-08 2021-11-30 2021-11-03 2024-04-30 2021-11-08 porting ant Selection ialist for Sidama Region ET-MOALR-301470-CS-INDV Project Management and Re Individual Consult Pending Impleme / Procurement specialist for S IDA / 63120 Post Open 14,400.00 0.00 2022-07-25 2022-08-27 2022-09-10 2022-09-25 2024-06-30 porting ant Selection ntation outh West Region Page 4