Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) Above US$ 1,000,000 All 3. ICB (Works) Above US$ 5 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 1,500,000 All [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable July 9, 2010 4. Reference to (if any) Project Operational/Procurement Manual: Project Procurement Manual of CJC Project 5. Any Other Special Procurement Arrangements: Not Applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments July 9, 2010 Threshold 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) All 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 200,000 and $300,000 (engineering contracts)_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Ethiopia : Ethiopia Competitiveness and Job Creation Project PLAN General Information Country: Ethiopia 2017-03-08 Bank’s Approval Date of the Original Procurement Plan: 2022-06-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P143302 GPN Date: Project Name: Ethiopia Competitiveness and Job Creation Project Loan / Credit No: IDA / 54510, IDA / 62630 Industrial Parks Development Corporation Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-IPDC-9345-CW-RFB / Con Component 2: Support for In Open - Internationa Single Stage - One E 249,175,403. 245,415,26 2018-03-1 IDA / 54510 Prior Request for Bids Signed 2015-05-22 2015-08-07 2015-08-07 2015-05-27 2016-11-16 2016-12-13 2017-03-14 2017-01-20 2017-01-20 struction of Kilinto Industrial dustrial Infrastructure l nvelope 27 7.83 9 Park CJC/NCB/W-02/08 / Construct Component 4: Project Manag Single Stage - One E Pending Imp 2017-11-1 IDA / 54510 Post Request for Bids Open - National 600,000.00 0.00 2017-02-02 2017-02-04 2017-03-18 2017-04-17 2017-05-22 ion of Kindergarten for Bole L ement and Monitoring and E nvelope lementation 8 emi PAPs valuation IPDC/CJC/NCB/W-02/09 / Con struction of Livestock Develo Component 4: Project Manag pment - Establishing 1 Poultr Single Stage - One E Pending Imp 2018-04-1 IDA / 54510 ement and Monitoring and E Post Request for Bids Open - National 450,000.00 0.00 2017-02-26 2017-07-01 2017-08-12 2017-09-11 2017-10-16 y enterprise nvelope lementation 4 valuation Construction of :1 Poultry s hed 3 Fattening sheds and grai n mills for Kilinto PAPs ET-IPDC-9347-CW-RFB / Con Component 2: Support for In Open - Internationa Single Stage - One E 157,758,001. 127,382,45 2018-09-2 struction of Bole-Lemi Phase IDA / 54510 Prior Request for Bids Signed 2015-05-05 2015-07-21 2015-07-21 2015-05-10 2015-07-21 2016-10-30 2018-09-03 2017-01-20 2016-01-26 dustrial Infrastructure l nvelope 59 3.78 7 II Industrial Park ET-IPDC-165219-NC-DIR / Su Component 2: Support for In 20,000,000.0 13,763,115. 2020-10-2 pply and Installation of Power IDA / 62630 Prior Direct Selection Direct Signed 2020-04-01 2020-05-05 2020-04-06 2020-09-16 2020-04-23 2021-12-09 dustrial Infrastructure 0 12 0 connection to Bole Lemi II an d Qilinto IPs ET-IPDC-251887-CW-RFB / C Request for Bids - onstruction of Cable Trench f Component 2: Support for In Single Stage - One E Small Works SPD 1,335,854.8 2022-02-2 IDA / 62630 Post Request for Bids Open - National 1,588,888.00 Signed 2021-09-08 2021-09-16 2021-09-11 2021-09-16 2021-10-11 2021-10-19 2021-10-21 2021-10-29 2021-10-31 2021-12-14 or Power Supply connection t dustrial Infrastructure nvelope (1 envelope proce 6 8 o Bole Lemi II Industrial Park ss) ET-IPDC-251892-CW-RFB / C Request for Bids - onstruction of Cable Trench f Component 2: Support for In Single Stage - One E Small Works SPD 2022-01-1 IDA / 62630 Post Request for Bids Open - National 1,022,222.00 916,834.15 Signed 2021-09-09 2021-09-16 2021-09-12 2021-09-16 2021-10-12 2021-10-19 2021-10-13 2021-10-29 2021-10-21 2021-12-14 or Power Supply connection t dustrial Infrastructure nvelope (1 envelope proce 9 o Kilinto Industrial Park ss) ET-IPDC-270292-CW-RFQ / C Component 4: Project Manag Request for Quota onstruction of shed floors,toil Request for Quota Single Stage - One E Pending Imp 2022-03-0 IDA / 62630 ement and Monitoring and E Post Limited tions (Non Bank-S 70,000.00 0.00 2022-01-03 2022-01-23 et,road leveling,roof plasterin tions nvelope lementation 9 valuation PD) g and metal works Request for Bids - ET-IPDC-279724-CW-RFB / A Component 2: Support for In Single Stage - One E Small Works SPD Under Imple 2022-05-3 uxiliary small construction W IDA / 62630 Post Request for Bids Open - National 520,000.00 0.00 2022-02-25 2022-02-11 2022-02-28 2022-03-08 2022-03-30 2022-04-06 2022-04-12 dustrial Infrastructure nvelope (1 envelope proce mentation 0 orks for Bole Lemi II & Kilinto ss) Industrial Parks GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CJC/SH/G-01/09 / Goods for s Component 3: Enhancing IZ l Request for Quota Single Stage - One E Pending Impl IDA / 54510 Post Limited 150,000.00 0.00 2017-06-07 2017-06-07 2017-06-07 kill TrainingCenter inkages to the local econom tions nvelope ementation y Component 1: Institutional a CJC/SH/G-04/09 / Vehicle for Request for Quota Single Stage - One E Pending Impl IDA / 54510 nd Regulatory Framework an Post Limited 200,000.00 0.00 2017-05-23 2017-05-23 2017-05-23 EIC 4WD tions nvelope ementation d Capacity Building CJC/SH/G-02/09 / Uniform for Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl IDA / 54510 Post Limited 5,000.00 0.00 2017-06-07 2017-06-07 2017-06-07 PIU drivers and janitors ement and Monitoring and E tions nvelope ementation valuation CJC/SH/G-01/10 / Stationary i Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl tems, sanitary materials and IDA / 54510 ement and Monitoring and E Post Limited 50,000.00 0.00 2017-10-24 2017-12-19 2018-06-17 tions nvelope ementation other miscellaneous goods fo valuation r PIU CJC/SH/S-01/09 / Printing, pr Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl omotional and branding item IDA / 54510 ement and Monitoring and E Post Limited 75,000.00 0.00 2017-10-23 2017-12-18 2018-06-16 tions nvelope ementation s for IPDC and CJC-PIU valuation ET-IPDC-41013-GO-RFQ / Pro Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl curement of Equipment for B IDA / 54510 ement and Monitoring and E Post Limited 50,000.00 0.00 2018-01-03 2018-02-28 2018-08-27 tions nvelope ementation ole Lemi KG valuation CJC/SH/G-03/09 / Procureme Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl nt of Furniture for Kindergart IDA / 54510 ement and Monitoring and E Post Limited 70,000.00 0.00 2017-10-17 2017-12-12 2018-06-10 tions nvelope ementation en at Bole Lemi PAPs and IP valuation DC ET-IPDC-42523-GO-RFQ / Do cumentation of different indu Component 1: Institutional a Request for Quota Single Stage - One E Pending Impl strial parks (Printing, Binding, IDA / 54510 nd Regulatory Framework an Post Limited 50,000.00 0.00 2018-01-23 2018-03-20 2018-09-16 tions nvelope ementation Scanning, and CD burning of d Capacity Building documents for 9 industrial pa rks) ET-IPDC-65788-GO-RFQ / Pro Component 1: Institutional a Single Stage - One E Pending Impl curement of Furniture for IPD IDA / 54510 nd Regulatory Framework an Post Request for Bids Open - National 150,000.00 0.00 2018-06-15 2018-06-20 2018-08-01 2018-08-31 2018-10-05 2019-04-03 nvelope ementation C d Capacity Building ET-IPDC-40618-GO-RFB / Pro Component 1: Institutional a Single Stage - One E curement of IT equipment an IDA / 54510 nd Regulatory Framework an Post Request for Bids Open - National 150,000.00 0.00 Canceled 2018-06-21 2018-06-26 2018-08-07 2018-09-06 2018-10-11 2019-04-09 nvelope d accessories for IPDC d Capacity Building ET-IPDC-205497-GO-RFQ / A Component 3: Enhancing IZ l udio- Visual ,IT Equipment an Request for Quota Single Stage - One E Pending Impl IDA / 62630 inkages to the local econom Post Limited 15,000.00 0.00 2020-11-30 2021-01-04 2021-02-03 d related goods for Establishi tions nvelope ementation y ng Sustainable Training Cent er at Bole Lemi II Page 1 ET-IPDC-205492-GO-RFQ / Tr Component 3: Enhancing IZ l Request for Quota Single Stage - One E Pending Impl IDA / 62630 Post Limited 50,000.00 0.00 2020-11-30 2021-01-18 2021-02-17 aining Room furniture & Fixtu inkages to the local econom tions nvelope ementation re y ET-IPDC-222085-GO-RFB / S Component 4: Project Manag upply, Install & commissioni Single Stage - One E Under Imple IDA / 62630 ement and Monitoring and E Post Request for Bids Open - National 300,000.00 0.00 2021-05-28 2021-07-29 2021-06-02 2021-08-02 2021-07-17 2021-08-31 2021-08-16 2021-09-16 2021-09-20 2022-03-19 ng Animal Fodder productio nvelope mentation valuation n plant for Qilinto PAP ET-IPDC-264728-GO-RFB / S upply, Installation and commi Component 4: Project Manag Single Stage - One E ssioning of Animal Feed Proc IDA / 62630 ement and Monitoring and E Post Request for Bids Open - National 300,000.00 55,000.48 Signed 2021-11-23 2021-11-07 2021-11-28 2021-12-07 2021-12-07 2021-12-12 2021-12-17 2021-12-18 2022-01-06 2022-03-18 nvelope essing and Molasses Storing, valuation Handling and Utilization Equi pment ET-IPDC-270188-GO-RFQ / Pr Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl ocurement of Office Furniture IDA / 62630 ement and Monitoring and E Post Limited 4,000.00 0.00 2021-12-31 2022-01-16 2022-02-15 tions nvelope ementation Kilinto PAPs Organization valuation ET-IPDC-270194-GO-RFQ / Pr Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl ocurement of Diesel Generati IDA / 62630 ement and Monitoring and E Post Limited 22,000.00 0.00 2022-01-01 2022-01-13 2022-03-14 tions nvelope ementation ng Set and Fire extinguisher valuation ET-IPDC-270270-GO-RFQ / Pr Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl ocurement of Workers unifor IDA / 62630 ement and Monitoring and E Post Limited 1,300.00 0.00 2022-01-02 2022-01-14 2022-02-13 tions nvelope ementation m ,protectives and first aid ki valuation ts ET-IPDC-270274-GO-RFQ / pr Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl ocurement of Processed feed IDA / 62630 ement and Monitoring and E Post Limited 4,500.00 0.00 2022-01-01 2022-01-13 2022-02-12 tions nvelope ementation pp packaging bag valuation ET-IPDC-270279-GO-RFQ / Pr Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl ocurement of IT Equipment f IDA / 62630 ement and Monitoring and E Post Limited 1,700.00 0.00 2022-01-02 2022-01-16 2022-02-15 tions nvelope ementation or Kilinto PAPs Organization valuation ET-IPDC-260887-GO-RFB / Pr Component 1: Institutional a Single Stage - One E ocurement of IT Equipment f IDA / 62630 nd Regulatory Framework an Post Request for Bids Open - National 130,000.00 0.00 Canceled 2021-11-10 2021-11-15 2021-12-15 2021-12-22 2022-01-03 2022-04-03 nvelope or Document Management S d Capacity Building ystem ET-IPDC-272959-GO-RFQ / Pr Component 1: Institutional a Request for Quota Single Stage - One E Under Imple ocurement of IT Equipment f IDA / 62630 nd Regulatory Framework an Post Limited 100,000.00 0.00 2022-01-25 2022-04-20 2022-02-12 2022-04-13 tions nvelope mentation or Document Management S d Capacity Building ystem ET-IPDC-270297-GO-RFQ / F Component 4: Project Manag Request for Quota Single Stage - One E IDA / 62630 Post Limited 80,000.00 0.00 Canceled 2022-02-17 2022-02-27 2022-03-19 eed Ingredient ement and Monitoring and E tions nvelope valuation ET-IPDC-270278-GO-RFQ / Pl Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl ank /pallet for feed ingredien IDA / 62630 ement and Monitoring and E Post Limited 3,000.00 0.00 2022-02-10 2022-02-18 2022-03-10 tions nvelope ementation t and finished product valuation ET-IPDC-279820-GO-RFB / Pr ocurement of Diesel Generati Component 2: Support for In Single Stage - One E Pending Impl IDA / 62630 Post Request for Bids Open - National 350,000.00 0.00 2022-02-24 2022-03-01 2022-03-31 2022-04-05 2022-04-10 2022-05-30 ng Sets for Bole Lemi II & Kili dustrial Infrastructure nvelope ementation nto Industrial Parks ET-IPDC-279813-GO-RFB / S upply and Installation of CCT Component 2: Support for In Single Stage - One E Pending Impl IDA / 62630 Post Request for Bids Open - National 25,000.00 0.00 2022-02-25 2022-03-02 2022-04-01 2022-04-08 2022-05-02 2022-05-30 V System for Bole Lemi II & K dustrial Infrastructure nvelope ementation ilinto Industrial Parks Adminis trative Building ET-IPDC-280654-GO-RFB / Pr Component 4: Project Manag Single Stage - One E Pending Impl IDA / 62630 Post Request for Bids Open - National 100,000.00 0.00 2022-02-25 2022-03-02 2022-04-01 2022-04-04 2022-04-12 2022-05-30 ocurement of feed ingredient ement and Monitoring and E nvelope ementation s valuation ET-IPDC-287496-NC-RFB / Pr Component 1: Institutional a Request for Quota Single Stage - One E Pending Impl ocurement of Promotional Ma IDA / 62630 nd Regulatory Framework an Post Limited 50,000.00 0.00 2022-04-15 2022-06-10 2022-08-31 tions nvelope ementation terials d Capacity Building NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-IPDC-40700-NC-RFP / Pre Component 4: Project Manag Request for Propo Single Stage - Two E paration of Documentary Fil IDA / 54510 ement and Monitoring and E Post Open - National 20,000.00 0.00 Canceled 2018-02-15 2018-02-20 2018-04-03 2018-06-16 2018-07-21 2019-01-17 sals nvelope m for CJC Project achieveme valuation nts. ET-IPDC-153598-NC-RFQ / Pr oduction of a video and phot Component 4: Project Manag ograph documentary on the Request for Quota Single Stage - One E IDA / 62630 ement and Monitoring and E Post Limited 20,000.00 3,720.85 Signed 2020-02-15 2020-11-02 2020-04-11 2020-12-15 2020-10-08 achievements registered tions nvelope valuation By competiveness and job cr eation project office (CJCP) Component 1: Institutional a ET-IPDC-254759-CS-CDS / E Under Imple IDA / 62630 nd Regulatory Framework an Post Direct Selection Direct 215,000.00 0.00 2021-10-26 2021-11-08 2021-10-31 2021-12-05 2022-12-30 RP Cloud Subscription Fee mentation d Capacity Building ET-IPDC-285464-NC-RFQ / Pr Component 1: Institutional a Request for Quota Single Stage - One E Under Imple omotional Video Production f IDA / 62630 nd Regulatory Framework an Post Limited 5,000.00 0.00 2022-04-05 2022-05-31 2022-07-31 tions nvelope mentation or IPDC Marketing and Comm d Capacity Building unication CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-IPDC-11323-CS-QCBS / C onsultancy Service of Detaile d Engineering Design & Tend Component 2: Support for In Quality And Cost- Open - Internationa Under Implement er Document Preparation (LS IDA / 54510 Prior 6,000,000.00 0.00 2014-07-31 2020-04-01 2014-09-25 2014-11-24 2014-12-09 2014-12-19 2015-01-28 2015-04-01 2016-03-31 dustrial Infrastructure Based Selection l ation ) and Supervision & Contract Administration (TB) for Bole-L emi II and Kilinto Industrial P arks CJC/C-04/09 / Consultancy se Component 3: Enhancing IZ l Quality And Cost- Pending Impleme rvice for training provision fo IDA / 54510 inkages to the local econom Post Open - National 200,000.00 0.00 2017-05-19 2017-05-19 2017-05-19 2017-05-19 2017-05-19 2017-05-19 2017-05-19 2017-05-19 Based Selection ntation r the skills center at bole lem y i Industrial Park Page 2 CJC/C-06/09 / Consultancy S Component 1: Institutional a Quality And Cost- Open - Internationa ervice for class one consultin IDA / 54510 nd Regulatory Framework an Post 400,000.00 0.00 Canceled 2017-06-27 2017-06-27 2017-06-27 2017-06-27 2017-06-27 2017-06-27 2017-06-27 2017-06-27 Based Selection l g firm d Capacity Building ET-IPDC-40694-CS-QCBS / St Component 4: Project Manag Quality And Cost- Open - Internationa Under Implement IDA / 54510 Post 100,000.00 0.00 2018-01-29 2018-01-18 2018-02-19 2018-04-04 2018-05-02 2018-06-01 2018-07-06 2018-08-10 2019-08-10 udying Baseline Survey For C ement and Monitoring and E Based Selection l ation JC Project valuation CJC/C-18/08 / B2B Linkage M Component 3: Enhancing IZ l Quality And Cost- Pending Impleme IDA / 54510 Post Open - National 150,000.00 0.00 2016-08-11 2016-08-11 2016-08-11 2016-08-11 2016-08-11 2016-08-11 2016-08-11 2016-08-11 ARKETING FIRM inkages to the local econom Based Selection ntation y ET-IPDC-64114-CS-QCBS / C Component 1: Institutional a onsultancy Service for Prepar Quality And Cost- Open - Internationa Under Implement IDA / 54510 nd Regulatory Framework an Post 300,000.00 320,000.00 2018-05-25 2019-08-04 2018-06-15 2019-08-06 2018-07-29 2019-09-30 2018-08-26 2019-11-15 2018-09-25 2019-12-16 2018-10-30 2020-01-02 2018-12-04 2019-12-04 ation of Road Map and 10 ye Based Selection l ation d Capacity Building ars Strategic Plan ET-IPDC-40726-CS-QCBS / C Component 2: Support for In Quality And Cost- Open - Internationa Under Implement onsultancy Service for Desig IDA / 54510 Post 50,000.00 0.00 2018-06-15 2018-06-15 2018-06-15 2018-06-15 2018-06-15 2018-06-15 2018-06-15 2018-06-15 dustrial Infrastructure Based Selection l ation n of Industrial Parks Housing Project ET-IPDC-73825-CS-LCS / Co Component 4: Project Manag Least Cost Selecti Pending Impleme mpetitiveness and Job Creati IDA / 54510 ement and Monitoring and E Post Open - National 40,000.00 0.00 2018-08-21 2018-09-11 2018-10-25 2018-11-22 2018-12-22 2019-01-26 2019-03-02 2019-08-29 on ntation on Project Financial Stateme valuation nt Audit ET-IPDC-93273-CS-QCBS / C onsultancy Services for provi Component 3: Enhancing IZ l Quality And Cost- sion of Sourcing, Screening , IDA / 54510 inkages to the local econom Post Open - National 200,000.00 186,871.73 Signed 2018-12-31 2019-01-28 2019-01-21 2019-03-06 2019-05-25 2019-04-03 2019-07-05 2019-05-03 2019-08-02 2019-06-07 2019-08-08 2019-07-12 2019-09-06 2020-07-11 Based Selection Training and allocation for y Bole Lemi industrial Park ET-IPDC-97530-CS-CQS / Pro Component 1: Institutional a Consultant Qualifi Open - Internationa curement of Consulting firm f IDA / 54510 nd Regulatory Framework an Post 200,000.00 0.00 Canceled 2019-01-31 2019-02-21 2019-04-06 2019-05-06 2019-06-10 2019-12-07 cation Selection l or Pharmaceutical IP-Kilinto d Capacity Building ET-IPDC-108081-CS-CQS / C onsultancy procurement for Component 1: Institutional a Transaction Advisory Service Quality And Cost- Open - Internationa IDA / 62630 nd Regulatory Framework an Prior 500,000.00 743,159.89 Signed 2019-04-08 2019-05-21 2019-04-29 2019-06-12 2020-05-29 2019-07-10 2020-07-01 2019-08-09 2020-10-14 2019-09-13 2020-12-07 2019-10-18 2020-12-10 2020-10-17 s-PPP for Operations and Man Based Selection l d Capacity Building agement of Bole Lemi and Kil into Industrial Parks and affili ated services. CJC/ICB/G-07/08 / Developm Component 1: Institutional a Quality And Cost- Open - Internationa ent of CRM and ERP for EIC a IDA / 54510 nd Regulatory Framework an Prior 1,000,000.00 0.00 Canceled 2017-09-20 2017-09-20 2017-07-19 2017-09-20 2018-08-03 2017-09-20 2017-09-20 2019-01-17 2017-09-20 2017-09-20 2017-09-20 Based Selection l nd IPDC d Capacity Building ET-IPDC-110945-CS-QCBS / Component 1: Institutional a Quality And Cost- Open - Internationa Supply, Installation and Com IDA / 54510 nd Regulatory Framework an Prior 600,000.00 858,201.31 Signed 2019-05-06 2019-10-22 2019-05-27 2019-11-06 2019-07-10 2020-03-09 2019-08-07 2020-04-28 2019-09-06 2020-07-30 2019-10-11 2020-09-27 2019-11-15 2020-09-28 2020-11-14 Based Selection l missioning of ERP system for d Capacity Building IPDC ET-IPDC-113651-CS-QCBS / Component 4: Project Manag Environmental and Social Au Quality And Cost- IDA / 54510 ement and Monitoring and E Post Open - National 100,000.00 16,230.74 Signed 2019-05-07 2019-05-19 2019-05-28 2019-07-11 2019-08-30 2019-08-08 2019-10-02 2019-09-07 2019-10-18 2019-10-12 2019-10-28 2019-11-16 2019-11-06 2020-11-15 dit for Bole Lemi II & Kilinto I Based Selection valuation Ps and sector specific ESSA f or each tenant ET-IPDC-113653-CS-QCBS / Component 4: Project Manag Quality And Cost- Environmental and Social Au IDA / 54510 ement and Monitoring and E Post Open - National 50,000.00 31,133.02 Signed 2019-05-07 2019-05-23 2019-05-28 2019-07-11 2019-09-09 2019-08-08 2019-10-10 2019-09-07 2019-10-31 2019-10-12 2019-11-11 2019-11-16 2019-11-19 2020-11-15 Based Selection dit for B2B linkage beneficia valuation ry companies ET-IPDC-162111-CS-QCBS / Component 3: Enhancing IZ l Consultancy service for "Com Quality And Cost- Open - Internationa IDA / 62630 inkages to the local econom Post 450,000.00 149,471.95 Signed 2020-03-12 2020-03-24 2020-03-27 2020-03-24 2020-04-21 2020-05-27 2020-05-19 2020-07-14 2020-06-03 2020-09-21 2020-06-20 2020-10-06 2020-07-12 2020-09-08 2020-08-08 pliance, nomination, system Based Selection l y development and certificatio n support to SMEs" ET-IPDC-162127-CS-QCBS / Component 3: Enhancing IZ l Consultancy Service to "Mark Quality And Cost- Open - Internationa IDA / 62630 inkages to the local econom Post 300,000.00 303,542.50 Signed 2020-03-12 2020-03-24 2020-03-27 2020-03-24 2020-04-16 2020-05-27 2020-05-14 2020-07-14 2020-05-24 2020-08-24 2020-06-10 2020-08-31 2020-06-27 2020-09-15 2021-03-24 eting Support to SMEs to enh Based Selection l y ance B2B linkages with FDIs" ET-IPDC-162119-CS-QCBS / Component 3: Enhancing IZ l Quality And Cost- Open - Internationa Consultancy service “Trainin IDA / 62630 inkages to the local econom Post 350,000.00 116,865.79 Signed 2020-03-12 2020-03-25 2020-03-27 2020-03-24 2020-04-21 2020-05-27 2020-05-19 2020-07-14 2020-05-29 2020-08-27 2020-06-15 2020-09-16 2020-07-13 2020-09-25 2021-04-09 Based Selection l g and Enhancing Productivity y of SMEs" ET-IPDC-161854-CS-QCBS / Component 1: Institutional a ASSESSMENT ON PREVENTIO Consultant Qualifi IDA / 62630 nd Regulatory Framework an Post Open 20,000.00 0.00 Canceled 2020-03-12 2020-03-18 2020-03-27 2020-04-19 2020-04-16 2020-04-26 2020-05-12 2020-08-10 N AND MANAGEMENT OF GE cation Selection d Capacity Building NDER BASED VIOLENCE IN IN DUSTRIAL PARKS (IPs) ET-IPDC-218695-CS-CQS / A SSESSMENT ON PREVENTION Component 1: Institutional a Consultant Qualifi AND MANAGEMENT OF GEND IDA / 62630 nd Regulatory Framework an Post Open - National 70,000.00 79,107.41 Signed 2021-02-22 2021-03-11 2021-03-09 2021-03-26 2021-05-06 2021-04-05 2021-06-22 2021-05-04 2021-07-01 2021-08-02 cation Selection ER BASED VIOLENCE AND GE d Capacity Building NDER ANALYSIS IN INDUSTRI AL PARKS (IPs) ET-IPDC-229929-CS-LCS / Au Component 4: Project Manag Least Cost Selecti Under Implement dit Services for two years (2 IDA / 62630 ement and Monitoring and E Post Open - National 30,000.00 0.00 2021-04-23 2021-07-23 2021-05-03 2021-06-16 2021-07-14 2021-08-13 2021-09-17 2021-10-22 2022-04-20 on ation 020/21-2021/22 Budget year valuation s) ET-IPDC-188725-CS-QCBS / Component 4: Project Manag Quality And Cost- IDA / 62630 Post Open - National 250,000.00 0.00 Canceled 2020-08-14 2020-10-12 2020-08-29 2020-10-22 2020-09-27 2020-10-25 2020-11-04 2020-11-24 2020-12-25 2021-12-25 Document Management Syst ement and Monitoring and E Based Selection em (DMS) valuation ET-IPDC-188728-CS-QCBS / F easibility Study and Develop a Strategy on the Storm Wat Component 2: Support for In Quality And Cost- IDA / 62630 Post Open - National 50,000.00 0.00 Canceled 2020-08-14 2020-08-31 2020-09-04 2020-10-03 2020-10-31 2020-11-15 2020-12-05 2020-12-27 2021-12-27 er and Effluent Discharge fro dustrial Infrastructure Based Selection m Waste Water Treatment Pl ants (WWTP) of KIlinto and B ole Lemi II Industrial Parks ET-IPDC-250259-CS-QCBS / Component 4: Project Manag Quality And Cost- Under Implement IDA / 62630 Post Open - National 250,000.00 0.00 2021-09-07 2021-10-02 2021-09-22 2021-10-07 2021-10-09 2021-11-06 2021-11-16 2021-11-28 2021-12-15 2022-03-15 CJC Project Completion Evalu ement and Monitoring and E Based Selection ation ation valuation ET-IPDC-255580-CS-QCBS / Consultancy Service for Impl Component 3: Enhancing IZ l Quality And Cost- Open - Internationa ementation of Generic Versat IDA / 62630 inkages to the local econom Post 80,000.00 0.00 Canceled 2021-10-06 2021-10-20 2021-10-30 2021-11-27 2021-12-04 2021-12-09 2021-12-15 2022-01-14 Based Selection l ile Enterprise Automated Sys y tem Solutions – Software Mo dules for SMEs INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 CJC/C-08/09 / Construction M Component 2: Support for In Individual Consult Pending Impleme anagement Consultant for Bo IDA / 54510 Post Limited 100,000.00 0.00 2017-03-02 2017-03-02 2017-03-02 2017-03-02 2017-03-02 dustrial Infrastructure ant Selection ntation le Lemi 2 and Killinto Industri al Parks CJC/H-08/09 / Environment S Component 4: Project Manag Individual Consult Pending Impleme IDA / 54510 Post Open 100,000.00 0.00 2017-02-10 2017-02-10 2017-02-10 2017-02-10 2017-02-10 pecialist ement and Monitoring and E ant Selection ntation valuation CJC/C-09/09 / Individual Con Component 4: Project Manag sultant -Data Analyst- ( organ Individual Consult Pending Impleme IDA / 54510 ement and Monitoring and E Post Limited 5,000.00 0.00 2017-04-15 2017-04-15 2017-04-15 2017-04-15 2017-04-15 izing and documenting procu ant Selection ntation valuation rement documents). CJC/C-07/09 / Skill Training C Component 3: Enhancing IZ l Individual Consult Pending Impleme IDA / 54510 Post Limited 50,000.00 0.00 2017-02-24 2017-02-24 2017-02-24 2017-02-24 2017-02-24 oordinator inkages to the local econom ant Selection ntation y Component 1: Institutional a ET-IPDC-19013-CS-INDV / Na Individual Consult Under Implement IDA / 54510 nd Regulatory Framework an Post Limited 100,000.00 0.00 2017-06-01 2017-06-30 2017-07-21 2017-08-25 2018-08-25 tional Financial Consultant ant Selection ation d Capacity Building ET-IPDC-19014-CS-INDV / Re Component 4: Project Manag Individual Consult Under Implement cruitment of assistant Project IDA / 54510 ement and Monitoring and E Post Open 25,000.00 0.00 2017-06-24 2017-07-20 2017-08-12 2017-09-02 2017-10-07 2018-10-07 ant Selection ation Engineer for Kilinto valuation ET-IPDC-19016-CS-INDV / Re Component 4: Project Manag Individual Consult Under Implement cruitment of assistant Project IDA / 54510 ement and Monitoring and E Post Open 25,000.00 0.00 2017-06-24 2017-08-12 2017-09-02 2017-10-07 2018-10-07 ant Selection ation Engineer for Bole Lemi II valuation CJC/M-03/07 / Individual Con Component 4: Project Manag Individual Consult IDA / 54510 Prior Open 100,000.00 0.00 Canceled 2017-04-15 2017-04-15 2017-09-25 2017-04-15 2017-04-15 2017-04-15 sultant -Procurement Speciali ement and Monitoring and E ant Selection st valuation ET-IPDC-31289-CS-INDV / Pr Component 4: Project Manag Individual Consult Under Implement IDA / 54510 Prior Open 100,000.00 0.00 2017-01-12 2017-10-26 2017-03-02 2017-03-23 2017-04-27 2017-10-24 ocurement Specialist ement and Monitoring and E ant Selection ation valuation CJC/SSS/C-01/10 / Audit Serv Component 4: Project Manag Under Implement ices for CJC project Account f IDA / 54510 ement and Monitoring and E Post Direct Selection Direct 20,000.00 0.00 2017-10-27 2017-11-06 2018-01-10 2018-07-09 ation or the year ended July 8, 201 valuation 7. ET-IPDC-40708-CS-INDV / Na Component 1: Institutional a Individual Consult tional Procurement Consulta IDA / 54510 nd Regulatory Framework an Prior Open 50,000.00 17,225.54 Under Review 2018-01-10 2018-02-08 2018-02-28 2018-03-21 2018-04-14 2018-04-25 2018-10-17 2018-10-22 ant Selection nt for IPDC d Capacity Building ET-IPDC-40715-CS-INDV / Re Component 4: Project Manag Individual Consult Under Implement IDA / 54510 Post Open 15,000.00 0.00 2018-01-15 2019-01-30 2018-03-05 2019-01-30 2018-03-26 2018-04-30 2018-10-27 cruitment of Communication ement and Monitoring and E ant Selection ation Specialist valuation ET-IPDC-40737-CS-INDV / Na Component 1: Institutional a Individual Consult tional Consultant for the form IDA / 54510 nd Regulatory Framework an Post Open 100,000.00 0.00 Canceled 2018-02-27 2018-04-17 2018-05-08 2018-06-12 2018-12-09 ant Selection ulation of SPV at IPDC d Capacity Building ET-IPDC-49425-CS-INDV / Co Component 4: Project Manag Individual Consult Pending Impleme ntract Administration and Cla IDA / 54510 ement and Monitoring and E Post Open 50,000.00 0.00 2018-03-15 2018-05-03 2018-05-24 2018-06-28 2019-06-27 ant Selection ntation im Consultant valuation ET-IPDC-64119-CS-INDV / Re Component 4: Project Manag Individual Consult IDA / 54510 Prior Open 20,000.00 1,159.65 Signed 2018-06-15 2018-08-13 2018-08-03 2019-05-06 2018-08-24 2019-11-19 2018-09-28 2019-06-06 2019-03-27 cruitment of Assistant Procur ement and Monitoring and E ant Selection ement valuation ET-IPDC-81199-CS-INDV / E Component 4: Project Manag Individual Consult mployment of Procurement S IDA / 54510 ement and Monitoring and E Prior Limited 35,000.00 0.00 Canceled 2018-10-19 2018-11-02 2018-10-24 2018-11-02 2018-11-14 2018-12-19 2019-06-17 ant Selection pecialist for CJCP valuation ET-IPDC-81199-CS-INDV-2 / Component 4: Project Manag Individual Consult Under Implement Hiring Procurement Manage IDA / 54510 ement and Monitoring and E Prior Limited 35,000.00 0.00 2019-01-31 2019-02-05 2019-02-26 2019-04-02 2019-09-29 ant Selection ation ment Specialist valuation ET-IPDC-18009-CS-INDV / Int Component 1: Institutional a Individual Consult ernational Individual Consult IDA / 54510 nd Regulatory Framework an Prior Limited 150,000.00 0.00 Canceled 2017-06-01 2017-06-06 2017-06-27 2017-08-01 2018-08-01 ant Selection ant for Pharmaceutical Indust d Capacity Building rial Park-- EIC ET-IPDC-108077-CS-INDV / H Component 1: Institutional a Individual Consult iring of International Individu IDA / 54510 nd Regulatory Framework an Post Limited 150,000.00 0.00 Canceled 2019-04-01 2019-04-06 2019-04-27 2019-06-01 2019-11-28 ant Selection al Consultant for Pharmaceut d Capacity Building ical IP -Kilinto ET-IPDC-108085-CS-INDV / H Component 3: Enhancing IZ l iring of International Individu Individual Consult IDA / 62630 inkages to the local econom Post Open 100,000.00 8,000.00 Signed 2019-04-01 2019-06-17 2019-05-20 2019-09-10 2019-06-10 2019-10-08 2019-07-15 2019-10-10 2020-01-11 al Consultant (TA) for SME s ant Selection y upport under B2B linkage ET-IPDC-64132-CS-INDV / Re Component 4: Project Manag Individual Consult IDA / 54510 Post Open 20,000.00 18,914.03 Signed 2019-05-20 2019-05-31 2019-07-08 2019-07-01 2019-07-29 2019-08-01 2019-09-02 2019-08-01 2020-02-29 cruitment of Gender Speciali ement and Monitoring and E ant Selection st valuation ET-IPDC-113658-CS-INDV / H iring of individual Consultant Component 2: Support for In Individual Consult IDA / 62630 Post Open 40,000.00 19,587.70 Signed 2019-10-28 2019-08-21 2019-12-16 2020-02-18 2020-01-06 2019-02-21 2020-02-10 2020-03-01 2020-08-08 for handing over of Bole Lemi dustrial Infrastructure ant Selection II to establish operating pro cedures ET-IPDC-129680-CS-INDV / H iring of individual Consultant Component 2: Support for In Individual Consult IDA / 62630 Post Open 40,000.00 26,410.29 Signed 2019-09-01 2019-08-21 2019-10-20 2020-03-03 2019-11-10 2020-03-10 2019-12-15 2020-03-15 2020-06-12 for handing over of Kilinto IP dustrial Infrastructure ant Selection to establish operating proce dures ET-IPDC-153594-CS-INDV / I Component 1: Institutional a ndividual Consultant for asse Individual Consult IDA / 62630 nd Regulatory Framework an Post Open 20,000.00 7,765.05 Signed 2020-01-24 2020-02-21 2020-02-23 2020-07-07 2020-03-04 2020-07-15 2020-03-24 2020-08-17 2020-05-23 ssing the need for affordable ant Selection d Capacity Building and accessible child care Pro grams In industrial parks ET-IPDC-158064-CS-INDV / R Component 1: Institutional a Individual Consult ecruitment of Senior Adviser IDA / 62630 nd Regulatory Framework an Post Limited 24,000.00 28,308.82 Signed 2020-02-10 2020-02-24 2020-02-15 2020-02-25 2020-03-07 2020-03-01 2020-04-11 2020-03-01 2020-10-08 ant Selection to the IPDC CEO as part of Ca d Capacity Building pacity Building. ET-IPDC-163913-CS-INDV / S Component 4: Project Manag Individual Consult IDA / 62630 Post Open 20,000.00 11,812.89 Signed 2020-03-16 2020-03-24 2020-04-19 2020-07-15 2020-05-04 2020-07-14 2020-05-24 2020-07-15 2020-11-20 ocial Development Specialist ement and Monitoring and E ant Selection valuation ET-IPDC-180941-CS-QCBS / Component 4: Project Manag Individual Consult Consultancy Services for stu IDA / 62630 ement and Monitoring and E Post Open 10,000.00 38,089.09 Signed 2020-08-14 2020-10-07 2020-09-12 2020-12-08 2020-09-19 2021-03-04 2020-10-17 2021-03-05 2021-04-15 ant Selection dy of ESMF for Bole Lemi II & valuation Kilinto IPs ET-IPDC-197653-CS-INDV / P Component 4: Project Manag Individual Consult IDA / 62630 Prior Open 24,000.00 23,554.59 Signed 2020-10-08 2020-10-16 2020-11-06 2021-03-04 2020-11-13 2021-04-14 2020-11-30 2021-05-01 2021-06-30 rocurement Management Sp ement and Monitoring and E ant Selection ecialist valuation Page 4 Component 1: Institutional a ET-IPDC-205548-CS-INDV / H Individual Consult IDA / 62630 nd Regulatory Framework an Post Limited 35,000.00 3,106.78 Signed 2020-11-29 2020-12-08 2020-12-04 2020-12-15 2020-12-25 2020-12-22 2021-01-29 2021-01-01 2021-08-27 uman Resource Advisor ant Selection d Capacity Building ET-IPDC-205551-CS-INDV / C Component 1: Institutional a Individual Consult Under Implement ommunication and Knowledg IDA / 62630 nd Regulatory Framework an Post Limited 35,000.00 0.00 2020-11-29 2020-12-05 2020-12-04 2020-12-14 2021-01-14 2021-08-12 ant Selection ation e Management Specialist d Capacity Building ET-IPDC-205090-CS-INDV / H Component 4: Project Manag iring of Individual Consultant Individual Consult IDA / 62630 ement and Monitoring and E Post Limited 10,000.00 8,550.44 Signed 2020-12-09 2020-12-04 2020-12-11 2020-12-07 2021-01-01 2020-12-28 2021-02-05 2020-12-28 2021-08-04 for conducting Feasibility stu ant Selection valuation dy & Business Plan for QIP P APs ET-IPDC-208351-CS-INDV / H Component 1: Institutional a Individual Consult Under Implement iring of Technical Advisor fo IDA / 62630 nd Regulatory Framework an Post Limited 24,000.00 0.00 2020-12-14 2020-12-19 2020-12-20 2021-01-10 2021-02-14 2021-08-13 ant Selection ation r Business development and d Capacity Building Private Sector ET-IPDC-234578-CS-INDV / H iring of Assistance B2B spe Component 3: Enhancing IZ l Individual Consult cialist for monitoring and fo IDA / 62630 inkages to the local econom Post Open 5,000.00 0.00 Canceled 2021-05-15 2021-05-31 2021-07-03 2021-07-24 2021-08-28 2022-02-24 ant Selection llowing up the Matching Gra y nt & TA implemented activi ties ET-IPDC-234575-CS-INDV / T echnical Consultancy service Component 4: Project Manag Individual Consult s for the implementation of R IDA / 62630 ement and Monitoring and E Post Open 10,000.00 6,404.27 Signed 2021-05-26 2021-05-31 2021-07-14 2021-06-16 2021-08-04 2020-07-07 2021-09-08 2021-08-05 2022-03-07 ant Selection estoration for Kilinto Industri valuation al Park Project Affected Peop le (PAP) ET-IPDC-98910-CS-INDV / Re Component 1: Institutional a Individual Consult design and Modification of IP IDA / 54510 nd Regulatory Framework an Post Open 30,000.00 0.00 Canceled 2019-02-28 2019-04-18 2019-05-09 2019-06-13 2019-12-10 ant Selection DC Website d Capacity Building ET-IPDC-82663-CS-INDV / In dividual Consultant to Suppor Component 1: Institutional a Individual Consult t ERP, CRM tasks for Ethiopia IDA / 54510 nd Regulatory Framework an Post Direct 100,000.00 0.00 Canceled 2018-11-02 2018-11-12 2018-12-03 2019-01-07 2019-07-06 ant Selection n Investment Commission (EI d Capacity Building C) and Industrial Parks Devel opment Corporation (IPDC) ET-IPDC-98911-CS-INDV / Hir Component 1: Institutional a Individual Consult ing of Transformational advis IDA / 54510 nd Regulatory Framework an Post Limited 100,000.00 0.00 Canceled 2019-02-28 2019-03-05 2019-03-26 2019-04-30 2019-10-27 ant Selection or for IPDC d Capacity Building ET-IPDC-254805-CS-INDV / E Component 2: Support for In Individual Consult IDA / 62630 Post Open 5,600.00 0.00 Canceled 2021-10-05 2021-10-04 2021-11-03 2021-11-10 2021-12-06 2022-06-04 nvironmental Safeguards Spe dustrial Infrastructure ant Selection cialist ET-IPDC-255477-CS-INDV / H Component 2: Support for In Individual Consult andover Engineer for Kilinto I IDA / 62630 Post Limited 12,000.00 14,947.79 Signed 2021-10-26 2021-10-29 2021-10-31 2021-11-05 2021-11-21 2021-11-18 2021-12-26 2021-11-19 2022-05-31 dustrial Infrastructure ant Selection ndustrial Park ET-IPDC-252133-CS-CDS / Or Component 1: Institutional a Under Implement acle Official Implementer Trai IDA / 62630 nd Regulatory Framework an Post Direct Selection Direct 12,000.00 0.00 2021-10-04 2021-11-05 2021-10-14 2021-10-31 2022-04-29 ation ning d Capacity Building ET-IPDC-255472-CS-INDV / C Component 4: Project Manag Individual Consult Under Implement IDA / 62630 Post Open 8,000.00 0.00 2021-10-26 2021-11-02 2021-12-14 2022-05-30 2022-01-04 2022-02-08 2022-05-31 JC Project Coordinator ement and Monitoring and E ant Selection ation valuation ET-IPDC-285466-CS-INDV / R Component 4: Project Manag Individual Consult Pending Impleme IDA / 62630 Post Limited 3,000.00 0.00 2022-03-31 2022-04-05 2022-04-26 2022-05-31 2022-07-31 ecruitment of communication ement and Monitoring and E ant Selection ntation expert valuation ET-IPDC-287494-CS-INDV / P Component 4: Project Manag Individual Consult Pending Impleme rocurement of Contract Mana IDA / 62630 ement and Monitoring and E Post Limited 8,000.00 0.00 2022-04-15 2022-04-20 2022-05-11 2022-06-15 2022-08-26 ant Selection ntation gement specialist valuation ET-IPDC-287656-CS-INDV / R Component 4: Project Manag Individual Consult Under Implement ecruitment of Assistant procu IDA / 62630 ement and Monitoring and E Post Limited 5,000.00 0.00 2022-04-08 2022-04-12 2022-04-13 2022-05-04 2022-06-08 2022-08-19 ant Selection ation rement officer valuation ET-IPDC-284907-CS-QCBS / Procurement of Social Audit Component 4: Project Manag Individual Consult Pending Impleme for the RAP and Livelihood re IDA / 62630 ement and Monitoring and E Post Limited 12,000.00 0.00 2022-04-14 2022-04-19 2022-05-10 2022-06-14 2022-08-31 ant Selection ntation storation plan implementatio valuation n in Bole Lemi-II and Kilinto IPs. ET-IPDC-300388-CS-INDV / R Component 4: Project Manag ecruitment of Individual cons Individual Consult Pending Impleme IDA / 62630 ement and Monitoring and E Post Limited 35,000.00 0.00 2022-06-30 2022-07-05 2022-07-26 2022-08-30 2023-02-26 ultant-Contract Administratio ant Selection ntation valuation n Advisor to CEO Page 5