Sample Procurement Plan (This is only a sample with the minimum content that is required for disclosure on the Bank’s website in accordance with the guidelines. The Project Team will agree with the Client on a procurement plan which may contain additional information and may be prepared in a different format as desired by the Borrower. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary) I. General 1. Project information: Country: Albania Borrower: Ministry of Health and Social Protection (MOHSP) Project Name: Social Assistance Modernization Project (SAMP)- Additional Financing Loan No.: 8841- AL Project Implementing Agency: Project Management Team – Ministry of Health and Social Protection (MOHSP) 2. Bank’s approval Date of the procurement Plan: Submission: January 16, 2019 Approval: January __, 2019 3. Date of General Procurement Notice: February __, 2019 4. Period covered by this procurement plan: January 2019 to June 2021 II. Goods and Works and non-consulting services. - This section is not applicable for SAMP project 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold 1. ICB and LIB (Goods) 2. NCB (Goods) 3. ICB (Works) 4. NCB (Works) 5. ICB (Non-Consultant Services) [Add other methods if necessary] 2. Prequalification. Bidders for _____________ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank] 4. Reference to (if any) Project Operational/Procurement Manual: 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 6. Procurement Packages with Methods and Time Schedule [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 8 9 Ref. Contract Estimat Procurem Prequali Dome Review Expected Comme No. (Descript ed ent fication stic by Bank Bid- nts ion) Cost Method (yes/no) Prefe (Prior / Opening rence Post) Date (yes/ no) III. Goods, Non-consulting Services and Selection of Consultants 1. Prior Review Threshold: Procurement subject to “Prior Review” by the Bank are defined in accordance with World Bank document named: "Bank Guidance: “Thresholds for procurement approaches and methods by country”, Effective July 01, 2016. Expenditure Contract Procurement Bank Prior Review Category Value (US$) Method Goods, Non- ≥1,000,000 RFB/International All ≥US$4 2 million consulting <1,000,000 RFB/National contracts Services ≤100,000 RFQ/National AllRefer to above n.a. DS threshold QCBS, QBS, FBS, All ≥US$12 million n.a. LCS, and CQSa contracts Consulting All ≥US$3400,000 Services n.a. IC contracts All Refer to above n.a. DS thresholds 1. Note: a. CQS below US$300,000 depending on the nature of assignment. 2. DS = Direct Selection; QCBS = Quality Cost Based Selection; FBS = Fixed Budget Selection; LCS = Least Cost Selection; QBS = Quality Based Selection; CQS = Consultant’s Qualifications Based Selection. All ToRs are subject to Bank’s Prior Review. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $US$300,000 equivalent per contract, may comprise entirely of national consultants. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule IV. Implementing Agency Capacity Building Activities with Time Schedule 1. In this section the agreed Capacity Building Activities (some items could be from CPAR recommendation) are listed with time schedule No. Expected outcome / Estimate Estimate Start Comments Activity Description d Cost d Date Duration PROCUREMENT Albania : Social Assistance Modernization Project PLAN General Information Country: Albania 2018-10-09 Bank’s Approval Date of the Original Procurement Plan: 2022-06-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P122233 GPN Date: 2019-03-07 Project Name: Social Assistance Modernization Project Loan / Credit No: IBRD / 81410, IBRD / 88410 Ministry of Health and Social Protection of Albania Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SAMP/G/RFQ/01-2019 / Supp Technical Assistance to Stre Request for Quota Single Stage - One E ly of one air conditioner for P IBRD / 88410 ngthen Implementation Cap Post Limited 550.00 Completed 2019-09-03 2019-08-27 2019-10-29 2019-10-07 2020-04-26 2019-10-18 tions nvelope MT office acity for Social Assistance Pr ograms SAMP/G/RFQ/02-2019 / Desi Technical Assistance to Stre Request for Quota Single Stage - One E gn and printing of thematic IBRD / 88410 ngthen Implementation Cap Post Limited 1,070.85 Completed 2019-10-21 2019-10-14 2019-11-04 2019-11-05 2019-12-02 2019-11-20 tions nvelope maps and posters acity for Social Assistance Pr ograms SAMP/G/RFQ/03-2020 / Printi Technical Assistance to Stre Request for Quota Single Stage - One E ng medical manuals for DA e IBRD / 88410 ngthen Implementation Cap Post Limited 17,089.80 Completed 2020-11-06 2020-12-04 2021-01-01 2021-01-25 2021-06-30 2021-02-24 tions nvelope valuation of adults and childr acity for Social Assistance Pr en ograms NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SAMP/G/SH/04-2014 / Bus R Strengthening the Implemen Request for Quota Open - Internationa ental for Communication Ca IBRD / 81410 tation and Performance of S Prior 13,067.95 Signed 2014-06-06 tions l mpaign Activities ocial Assistance Programs CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SAMP/CS/CQ/04-2014 / Tech nical Supervision of Disability Strengthening the Implemen Assistance MIS development Consultant Qualifi Open - Internationa IBRD / 81410 tation and Performance of S Prior 73,821.05 Signed 2016-03-08 2016-03-10 and implementation through cation Selection l ocial Assistance Programs Independent Verification and Validation (IV&V) Process SAMP/CS/CQ/2-2014 / Techni Strengthening the Implemen cal Assistance for Implement Consultant Qualifi Open - Internationa IBRD / 81410 tation and Performance of S Prior 54,584.54 Signed 2014-05-20 2014-05-22 ation of the Communications cation Selection l ocial Assistance Programs Campaign Activities for NE re forms (first phase) SAMP/CS/QCBS/03-2013 / De Strengthening the Implemen sign and Implementation of P Quality And Cost- Open - Internationa IBRD / 81410 tation and Performance of S Prior 132,675.65 Signed 2013-10-31 2014-12-18 2014-12-01 rocess Evaluation for Pilot Ph Based Selection l ocial Assistance Programs ase for NE reforms SAMP/CS/CQ/01-2014 / Deve Strengthening the Implemen Consultant Qualifi Open - Internationa lopment of Functional Requir IBRD / 81410 tation and Performance of S Prior 52,402.35 Signed 2014-07-29 2014-07-30 cation Selection l ements for Disability Assista ocial Assistance Programs nce MIS SAMP/CS/CQ/01-2019 / TA to Technical Assistance to Stre support the development of ngthen Implementation Cap Consultant Qualifi an exit strategy for NE benefi IBRD / 88410 Post Open - National 48,685.10 Completed 2019-03-26 2019-02-13 2019-04-16 2019-05-30 2019-04-30 2019-06-29 2019-07-04 2019-08-03 2019-07-22 2020-01-30 2019-11-30 acity for Social Assistance Pr cation Selection ciaries based on innovative ograms model and international evid ence on what works SAMP/CS/CQ/09-2019 / TA to Technical Assistance to Stre Consultant Qualifi conduct an assessment of th IBRD / 88410 ngthen Implementation Cap Post Open - National 19,120.00 Completed 2019-04-10 2019-04-17 2019-05-01 2019-06-14 2019-08-06 2019-07-14 2019-09-02 2019-08-18 2019-09-23 2020-02-14 2019-12-15 cation Selection e situation of working invalid acity for Social Assistance Pr s ograms SAMP/CS/CQ/04-2019 / Stren Technical Assistance to Stre gthening the implementation ngthen Implementation Cap Consultant Qualifi capacity of LGU, ROs, and SS IBRD / 88410 Post Open - National 0.01 Completed 2019-07-15 2019-06-28 2019-08-05 2019-09-18 2019-10-18 2019-10-18 2019-11-11 2019-11-22 2019-12-10 2020-05-20 2020-08-10 acity for Social Assistance Pr cation Selection S for coordination of social se ograms rvices (case management) fo r people with disability SAMP/CS/CQ/07-2019 / A sec Technical Assistance to Stre Consultant Qualifi ond-stage communication ca IBRD / 88410 ngthen Implementation Cap Post Open - National 0.01 Completed 2019-08-14 2019-08-20 2019-09-04 2019-10-18 2019-10-22 2019-11-17 2019-12-24 2019-12-22 2020-01-30 2020-06-19 2021-05-30 cation Selection mpaign in the three selected acity for Social Assistance Pr regions ograms SAMP/CS/CQ/10-2019 / Train Technical Assistance to Stre ing of social inspectors on im ngthen Implementation Cap Consultant Qualifi proved DA inspection metho IBRD / 88410 Post Open - National 13,960.00 Completed 2019-11-15 2020-04-27 2019-12-06 2020-01-19 2020-07-22 2020-02-18 2020-08-26 2020-03-24 2020-09-01 2020-09-20 2021-01-13 acity for Social Assistance Pr cation Selection dology and development of t ograms he technical specifications fo r additional DA MIS module SAMP/CS/CQ/02-2019 / Upda te and delivery of training m odule of disability evaluation Technical Assistance to Stre staff of regional directories, S ngthen Implementation Cap Consultant Qualifi IBRD / 88410 Post Open - National 97,642.00 Completed 2020-02-17 2020-02-19 2020-03-09 2020-04-22 2020-05-19 2020-05-22 2020-07-02 2020-06-26 2020-08-03 2020-12-23 2021-03-11 SS, Regional Directories, MH acity for Social Assistance Pr cation Selection SP staff, family, and specialis ograms t doctors on scale-up implem entation of the disability eval uation reform Page 1 SAMP/CS/CQ/03-2020 / Estab Technical Assistance to Stre lishment of a new referral me ngthen Implementation Cap Consultant Qualifi IBRD / 88410 Post Open - National 35,020.00 Completed 2020-12-01 2020-12-17 2020-12-22 2021-02-04 2021-03-08 2021-03-06 2021-04-23 2021-04-10 2021-05-14 2021-10-07 2021-12-21 chanism for supervising and l acity for Social Assistance Pr cation Selection eading the Disability Reform ograms SAMP/CS/CQ/01-2021 / Deve lopment of training strategy ( complemented by an action Technical Assistance to Stre plan) for nationwide impleme ngthen Implementation Cap Consultant Qualifi ntation of DA evaluation refo IBRD / 88410 Post Open - National 44,926.00 Signed 2021-11-15 2021-11-10 2021-12-06 2022-01-19 2021-12-30 2022-02-18 2021-12-30 2022-03-25 2022-04-07 2022-09-21 acity for Social Assistance Pr cation Selection rm, updating and delivery of ograms training modules to the disab ility evaluation staff of SSS R egional Directories, social ad ministrators, fami SAMP/CS/CQ/01-2022 / PSIA (Poverty and Social Impact A nalysis) follow up survey to Technical Assistance to Stre measure and track the inclus ngthen Implementation Cap Consultant Qualifi Under Implement IBRD / 88410 Post Open - National 0.00 2022-05-18 2022-05-19 2022-06-08 2022-07-22 2022-08-21 2022-09-25 2023-03-24 ion and exclusion errors of th acity for Social Assistance Pr cation Selection ation e DA reform once it is rolled ograms out at least to half of the cou ntry including a beneficiary a ssessment survey for the DA beneficiaries INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SAMP/CS/SSS/018-2015 / Pre paration of Bio-Psycho-Social Strengthening the Implemen Criteria for the Evaluation an IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 1,370.65 Signed 2015-03-20 d Determination of Disability, ocial Assistance Programs Immunodeficiency Diseases f rom HIV SAMP/CS/SSS/021-2015 / Pre Strengthening the Implemen paration of Bio-Psycho-Social IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 1,027.98 Signed 2015-03-20 Criteria for the Evaluation an ocial Assistance Programs d Determination of Disability, Oncology diseases SAMP/CS/SSS/017-2015 / Pre Strengthening the Implemen paration of Bio-Psycho-Social IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 342.66 Signed 2015-03-20 Criteria for the Evaluation an ocial Assistance Programs d Determination of Disability SAMP/CS/SSS/02-2015 / Prep aration of Bio-Psycho-Social Strengthening the Implemen Criteria for the Evaluation an IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 1,713.31 Signed 2015-03-20 d Determination of Disability, ocial Assistance Programs Psychiatric impairments No.2 SAMP/CS/SSS/013-2015 / Pre paration of Bio-Psycho-Social Strengthening the Implemen Criteria for the Evaluation an IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 1,484.87 Signed 2015-03-20 d Determination of Disability, ocial Assistance Programs Dermatology Diseases SAMP/CS/SSS/015-2015 / Pre paration of Bio-Psycho-Social Strengthening the Implemen Criteria for the Evaluation an IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 685.32 Signed 2015-03-20 d Determination of Disability, ocial Assistance Programs Allergologic impairments SAMP/CS/SSS/04-2015 / Prep Strengthening the Implemen aration of Bio-Psycho-Social IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 799.54 Signed 2015-03-20 Criteria for the Evaluation an ocial Assistance Programs d Determination of Disability, Neurology Diseases SAMP/CS/SSS/08-2015 / Prep Strengthening the Implemen aration of Bio-Psycho-Social IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 1,142.21 Canceled Criteria for the Evaluation an ocial Assistance Programs d Determination of Disability, Cardiology Diseases SAMP/CS/SSS/06-2015 / Prep Strengthening the Implemen aration of Bio-Psycho-Social IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 571.10 Signed 2015-03-20 Criteria for the Evaluation an ocial Assistance Programs d Determination of Disability, O.R.L. Diseases SAMP/CS/SSS/03-2015 / Prep aration of Bio-Psycho-Social Strengthening the Implemen Criteria for the Evaluation an IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 342.66 Signed 2015-03-20 d Determination of Disability, ocial Assistance Programs Psychiatric impairments No.3 SAMP/CS/SSS/07-2015 / Prep Strengthening the Implemen aration of Bio-Psycho-Social IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 1,027.98 Signed 2015-03-20 Criteria for the Evaluation an ocial Assistance Programs d Determination of Disability, Ophthalmic diseases SAMP/CS/SSS/01-2015 / Prep aration of Bio-Psycho-Social Strengthening the Implemen Criteria for the Evaluation an IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 1,597.38 Signed 2015-03-20 d Determination of Disability, ocial Assistance Programs Psychiatric impairments No.1 SAMP/CS/SSS/05-2015 / Prep aration of Bio-Psycho-Social Strengthening the Implemen Criteria for the Evaluation an IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 799.54 Signed 2015-03-20 d Determination of Disability, ocial Assistance Programs Neurosurgical Diseases SAMP/CS/SSS/011-2015 / Pre paration of Bio-Psycho-Social Strengthening the Implemen Criteria for the Evaluation an IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 1,027.98 Signed 2015-03-20 d Determination of Disability ocial Assistance Programs - Orthopedic Diseases SAMP/CS/SS/08a-2015 / Prep Strengthening the Implemen aration of Bio-Psycho-Social IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 1,157.90 Signed 2015-04-20 Criteria for the Evaluation an ocial Assistance Programs d Determination of Disability Page 2 SAMP/CS/SS/01-2016 / Disab ility International expert to a Strengthening the Implemen ssist MSWY to carry out the a IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 7,013.79 Signed 2016-07-01 ctivities for starting the imple ocial Assistance Programs mentation of pilot phase of t he DA reform SAMP/CS/SS/15-2016 / Local Strengthening the Implemen DA expertise for supervising IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 9,606.15 Signed 2017-01-17 the disability evaluation refor ocial Assistance Programs m implementation in pilot ar ea SAMP/CS/IC/14-2016-B / Tec hnical Advisor for implement Strengthening the Implemen ation of DA reform in pilot ar IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 22,900.00 Canceled ea and Preparation of action ocial Assistance Programs plan for nationwide DA refor m implementation SAMP/CS/SS/21-2018 / Local Strengthening the Implemen DA expertise for supervising IBRD / 81410 tation and Performance of S Post Direct Selection Direct 15,776.78 Signed the disability evaluation refor ocial Assistance Programs m implementation in pilot ar ea Strengthening the Implemen SAMP /CS/IC/11-2015 / Procu Individual Consult IBRD / 81410 tation and Performance of S Prior Open 5,134.39 Signed 2017-01-03 2017-01-03 rement Expert ant Selection ocial Assistance Programs SAMP/CS/IC/06-2013 / Refine Strengthening the Implemen ment of Design of IE (includin Individual Consult IBRD / 81410 tation and Performance of S Prior Open 42,187.00 Signed 2014-02-20 2014-03-22 2014-04-16 2014-03-25 2014-04-25 2014-12-30 g sampling), and analysis of ant Selection ocial Assistance Programs baseline data (study) Strengthening the Implemen SAMP/CS/IC/08-2013 / Monit Individual Consult IBRD / 81410 tation and Performance of S Prior Open 31,420.66 Signed 2014-04-25 2014-05-01 oring & Evaluation Officer ant Selection ocial Assistance Programs SAMP/CS/IC/9-2014 / Design Strengthening the Implemen of new disability eligibility cri Individual Consult IBRD / 81410 tation and Performance of S Prior Open 68,832.75 Signed 2014-07-15 2014-07-17 teria based on the social mo ant Selection ocial Assistance Programs del and international standar ds SAMP/CS/SSS/020-2015 / Pre Strengthening the Implemen paration of Bio-Psycho-Social IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 1,827.53 Signed 2015-03-20 Criteria for the Evaluation an ocial Assistance Programs d Determination of Disability, Pulmonary diseases SAMP/CS/SSS/012-2015 / Pre paration of Bio-Psycho-Social Strengthening the Implemen Criteria for the Evaluation an IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 1,370.65 Signed 2015-04-08 d Determination of Disability, ocial Assistance Programs Endocrinology Diseases SAMP/CS/SSS/09-2015 / Prep aration of Bio-Psycho-Social Strengthening the Implemen Criteria for the Evaluation an IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 1,027.98 Signed 2015-03-20 d Determination of Disability, ocial Assistance Programs Gastrohepatol diseases SAMP/CS/SSS/22-2015 / Prep Strengthening the Implemen aration of Bio-Psycho-Social IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 1,713.31 Signed 2015-03-20 Criteria for the Evaluation an ocial Assistance Programs d Determination of Disability, Medical Supervisor SAMP/CS/SSS/014-2015 / Pre Strengthening the Implemen paration of Bio-Psycho-Social IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 2,115.24 Signed 2015-03-20 Criteria for the Evaluation an ocial Assistance Programs d Determination of Disability SAMP/CS/SSS/019-2015 / Pre Strengthening the Implemen paration of Bio-Psycho-Social IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 913.76 Canceled Criteria for the Evaluation an ocial Assistance Programs d Determination of Disability, Pediatric Diseases SAMP/CS/SSS/010-2015 / Th e preparation of Bio-Psycho-S Strengthening the Implemen ocial Criteria for the Evaluati IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 961.19 Signed 2015-03-20 on and Determination of Disa ocial Assistance Programs bility, Rheumatology disease s SAMP/CS/SSS/016-2015 / Pre paration of Bio-Psycho-Social Strengthening the Implemen Criteria for the Evaluation an IBRD / 81410 tation and Performance of S Prior Direct Selection Direct 1,370.65 Signed 2015-03-20 d Determination of Disability, ocial Assistance Programs Oncohematology Diseases Technical Assistance to Stre SAMP/CS/SS/01-2019 / Proje Individual Consult IBRD / 88410 ngthen Implementation Cap Post Direct 48,234.11 Signed 2019-03-26 2019-01-11 2019-04-05 2019-01-15 2019-04-26 2019-01-15 2019-05-31 2019-01-17 2019-11-27 ct Manager ant Selection acity for Social Assistance Pr ograms SAMP/CS/SS/02-2019 / Finan Technical Assistance to Stre Individual Consult cial Management Specialist ( IBRD / 88410 ngthen Implementation Cap Post Direct 2,232.50 Signed 2019-03-26 2019-01-22 2019-04-05 2019-10-22 2019-04-26 2019-01-22 2019-05-31 2019-01-30 2019-11-27 ant Selection part time remote basis contr acity for Social Assistance Pr act) ograms Technical Assistance to Stre SAMP/CS/IC/03-2019 / Financ Individual Consult IBRD / 88410 ngthen Implementation Cap Post Open 32,118.33 Signed 2019-03-26 2019-04-04 2019-05-14 2019-02-26 2019-06-04 2019-03-01 2019-07-09 2019-03-04 2020-01-05 ial Management Specialist ant Selection acity for Social Assistance Pr ograms Technical Assistance to Stre SAMP/CS/IC/02-2019 / Procur Individual Consult IBRD / 88410 ngthen Implementation Cap Post Open 0.00 Canceled 2019-03-26 2019-05-14 2019-06-04 2019-07-09 2020-01-05 ement Expert ant Selection acity for Social Assistance Pr ograms SAMP/CS/IC/02-2019-D / Pro Technical Assistance to Stre Individual Consult Under Implement curement Expert (part-time) - IBRD / 88410 ngthen Implementation Cap Post Limited 0.00 2019-04-25 2019-04-30 2019-04-30 2019-05-07 2019-05-21 2019-07-22 2019-06-25 2019-12-22 ant Selection ation Rebid acity for Social Assistance Pr ograms SAMP/CS/IC/09-2019 / Stren gthening the MHSP (or SSS) Technical Assistance to Stre M&E capacity for data analys ngthen Implementation Cap Individual Consult IBRD / 88410 Post Open 0.01 Completed 2019-06-10 2019-08-02 2019-07-29 2020-10-02 2019-08-19 2019-10-15 2019-09-23 2019-11-01 2020-03-21 2020-12-21 is, to manage and update the acity for Social Assistance Pr ant Selection scoring formula (not publicly ograms disclosed) (statistic local exp ert) Page 3 SAMP/CS/IC/12-2019 / TA act Technical Assistance to Stre ivities to ensure quality of re ngthen Implementation Cap Individual Consult IBRD / 88410 Post Open 7,940.00 Completed 2020-01-30 2020-02-17 2020-03-19 2020-04-27 2020-04-09 2021-04-05 2020-05-14 2020-05-28 2020-11-10 2021-08-31 habilitation works of ROs in E acity for Social Assistance Pr ant Selection lbasan Region (audit consult ograms ancy) SAMP/CS/IC/10-2019 / TA act Technical Assistance to Stre ivities to ensure quality of re ngthen Implementation Cap Individual Consult IBRD / 88410 Post Open 0.01 Completed 2019-09-05 2019-09-26 2019-10-24 2019-11-05 2019-11-14 2019-11-14 2019-12-19 2019-12-10 2020-06-16 2021-01-31 habilitation works of ROs in T acity for Social Assistance Pr ant Selection irana Region (audit consultan ograms cy) SAMP/CS/IC/11-2019 / TA act Technical Assistance to Stre ivities to ensure quality of re ngthen Implementation Cap Individual Consult IBRD / 88410 Post Open 6,780.00 Completed 2020-03-05 2020-02-17 2020-04-23 2020-04-06 2020-05-14 2020-05-06 2020-06-18 2020-05-28 2020-12-15 2021-08-31 habilitation works of ROs in D acity for Social Assistance Pr ant Selection urres Region (audit consultan ograms cy) SAMP/CS/SS/04-2019 / Stren Technical Assistance to Stre gthening the MHSP (or SSS) ngthen Implementation Cap Individual Consult M&E capacity for data analys IBRD / 88410 Post Direct 6,000.00 Completed 2019-06-05 2019-06-14 2019-06-22 2019-06-21 2019-07-13 2019-07-16 2019-08-17 2019-07-29 2020-02-13 2020-09-29 acity for Social Assistance Pr ant Selection is, to manage and update the ograms scoring formula (not publicly disclosed) (IT local expert) SAMP/CS/SS/05-2019 / TA to Technical Assistance to Stre monitor and support the scal ngthen Implementation Cap IBRD / 88410 Post Direct Selection Direct 25,750.00 Signed 2019-10-25 2019-10-23 2019-11-04 2019-10-30 2020-01-08 2019-11-21 2020-07-06 e-up implementation of the d acity for Social Assistance Pr isability evaluation reform (lo ograms cal expert) SAMP/CS/IC/13-2019 / Hire a Technical Assistance to Stre second local expert on disabi ngthen Implementation Cap Individual Consult IBRD / 88410 Post Open 0.01 Signed 2019-11-08 2019-11-05 2019-12-27 2019-12-18 2020-01-17 2019-12-06 2020-02-21 2020-01-30 2020-08-19 lity to support the main local acity for Social Assistance Pr ant Selection expert with feedback from st ograms akeholders Technical Assistance to Stre SAMP/CS/IC/14-2020 / M&E Individual Consult IBRD / 88410 ngthen Implementation Cap Post Open 0.01 Terminated 2020-03-10 2020-03-11 2020-04-28 2020-05-04 2020-05-19 2020-05-14 2020-06-23 2020-06-03 2020-12-20 Officer (part-time) ant Selection acity for Social Assistance Pr ograms SAMP/CS/IC/01-2021 / Stren Technical Assistance to Stre gthening the MHSP (or SSS) ngthen Implementation Cap Individual Consult M&E capacity for data analys IBRD / 88410 Post Open 6,000.00 Signed 2021-11-15 2021-11-12 2022-01-03 2021-12-13 2022-01-24 2021-12-13 2022-02-28 2022-01-05 2022-08-27 acity for Social Assistance Pr ant Selection is, to manage and update the ograms scoring formula (not publicly disclosed) (IT local expert) SAMP/CS/SS/01-2021 / Stren gthening the MHSP (or SSS) Technical Assistance to Stre M&E capacity for data analys ngthen Implementation Cap IBRD / 88410 Post Direct Selection Direct 6,000.00 Signed 2021-11-15 2021-11-12 2021-11-25 2021-12-03 2022-01-29 2021-12-06 2022-07-28 is, to manage and update the acity for Social Assistance Pr scoring formula (not publicly ograms disclosed) (statistic local exp ert) SAMP/CS/IC/01-2022 / TA to Technical Assistance to Stre support the MHSP for monito ngthen Implementation Cap Individual Consult Under Implement IBRD / 88410 Post Limited 0.00 2022-06-06 2022-06-07 2022-06-11 2022-07-02 2022-08-06 2023-02-02 ring and improving the effect acity for Social Assistance Pr ant Selection ation iveness of social assistance p ograms rograms SAMP/CS/SS/01-2022 / Deliv ery of training modules to th Technical Assistance to Stre e disability evaluation staff of ngthen Implementation Cap Pending Impleme SSS Regional Directories, soc IBRD / 88410 Post Direct Selection Direct 0.00 2022-06-28 2022-07-08 2022-09-11 2023-03-10 acity for Social Assistance Pr ntation ial administrators, family doc ograms tors and medical specialists i n the regions of Lezhe, Shko der, Vlora. Page 4