PROCUREMENT PLAN Version 2.1 – Date: September 1, 2021 PROGRAM TO ACCELERATE AGRARIAN REFORM (ONE MAP PROJECT) A. Project information: Country: Indonesia Borrower: Republic of Indonesia Project ID: P160661 Financing Agreement IBRD Loan 8897-ID Number: Project Implementation Agency(ies): PMU: Ministry of Agrarian and Spatial Planning (ATR/BPN) PIU: Geospatial Information Agency (BIG) B. Key Dates: 1. Procurement Plan: a. Version 1.0 (for June 4, 2018 negotiation) Bank’s Approval to this June 4, 2018 version: Period covered by this June 4, 2018 – December 31, version: 2023 b. Version 1.9 (previous July 22, 2021 version) Bank’s Approval to this July 29, 2021 version: Period covered by this June 4, 2018 – December 31, version: 2023 c. Version 2.0 (this version) September 1, 2021 Bank’s Approval to this September 8, 2021 version: Period covered by this June 4, 2018 – December 31, version: 2023 d. [next version, if any] [to be updated] 2. General Procurement April 2019 Notice: C. Preamble All Procurement under the Project shall be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers of July 2016, revised November 2017, and the provisions of the Procurement Plan and Project Operations Manual and shall take precedence over any national procurement regulations. In accordance with paragraph 5.9 of the Procurement Regulations, the Bank’s online procurement planning and tracking tools i.e. Systematic Tracking and Exchanges in Procurement (STEP) will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. D. Key Provisions The following conditions apply to all procurement activities in this Procurement Plan. The Bank’s procurement prior review thresholds: The identified procurement risk under this Project is ‘Substantial’. Accordingly, all contracts listed in the Procurement Plan that are at or above the thresholds set out below are subject to the Bank’s prior review. All other contracts are subject to the Bank’s ex-post review. Table 1. Applied Prior Review Threshold Type of procurement Procurement Prior Review Thresholds (US$ millions) Works (including turnkey, supply & installation of 10 plant and equipment, and PPP) Goods, Information Technology and Non- 2 consulting Services Consultants: Firms 1 Consultants: Individuals 0.3 The Bank’s approved selection methods thresholds: The following selection method thresholds shall apply for procurement of goods & information technology, non-consulting services and consulting services of each identified activity. Table 2. Applied Approved Selection Method Threshold Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International Works (including turnkey, supply & installation of plant and equipment, and PPP) (i) Request for Request for at or above $0.2 and at or above $25 Bids (RFB) less than $25 (ii) Request for Quotations less than $0.2 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations Goods, Information Technology and Non-consulting services a. For Goods and Information Technology: (i) Request for Request for at or above $0.1 and at or above $2 Bids (RFB) less than $2 (ii) Request for Quotations less than $0.1 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations b. For Non-consulting Services: (i) Request for Request for at or above $0.1 and at or above $10 Bids (RFB) less than $10 (ii) Request for Quotations less than $0.1 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations Consultants: firms a. For Selection of Consulting Firms (i) Quality Cost Based Shortlist of firms for at or above $0.4 Selection (QCBS), Fixed contracts below $0.4 Budget Based Selection may comprise (FBS), Least Cost Based entirely national Selection (LCS) and firms Quality Based Selection (QBS) (ii) Consultant’s less than $0.3 N/A Qualifications Based Selection (CQS) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 7.13, 7.14 paragraph 7.13, 7.14 and 7.15 of the and 7.15 of the Procurement Procurement Regulations Regulations b. For Selection of Individual Consultants (i) Open Competitive All, no monetary All, no monetary Selection of Individual threshold threshold Consultants and Limited Competitive Selection of Individual Consultants Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International (ii) Direct Selection of On exceptional basis On exceptional basis Individual Consultants if justified as per if justified as per paragraph 7.39 of paragraph 7.39 of the Procurement the Procurement Regulations Regulations Standard Procurement Documents (SPD): The Bank’s SPD shall be used when approaching the international market (specifically for international competitive procurement and those contracts shall be as specified in the Procurement Plan tables in STEP. Use of National Procurement Procedures: In accordance with paragraphs 5.3 of the Procurement Regulations, when approaching the national market all contracts to be procured through open national competitive procurement will follow the GoI’s procurement regulation. The procedures applicable to the procurement of goods and non-consulting services awarded on the basis of open national competitive procurement shall be those of the Tender method as set forth in the Peraturan Presiden No. 16/2018 and its subsequent amendment Peraturan Presiden No. 12/2021) provided that such arrangements continue to meet requirements set forth under paragraph 5.4 of these Regulations and the following conditions: 1. The procurement is open to eligible firms from any country. There shall not any restriction to the bidders’ participation including mandatory requirement to form in joint venture; 2. Any gaps between National Procurement Procedures and the Procurement Regulations will be addressed and incorporated in the harmonized bidding documents acceptable by the Bank. Use of National e-Procurement System (SPSE): Unless informed otherwise by the Bank in writing, SPSE e-procurement system may be used only for procurement of works, goods and non-consulting services under Request for Bids (RFB) method through national open competitive procurement method, applying the harmonized model bidding documents for national open competitive procurement agreed by the Bank. For selection of consulting services through QCBS method, only the modified SPSE (termed by LKPP as SPSE-“ICB”) may be used applying the Bank’s Standard Request for Proposal (RFP) document. The Bank has further accepted GOI’s proposal for use of SPSE-ICB for selection of consulting services through CQS method applying a modified Bank’s Standard RFP. Two consulting services activities (contracts) under other Bank-financed project are being performed as pilot use of SPSE-ICB for CQS method to ensure that the system is working as intended. Since at the present time LKPP has not yet developed the modified SPSE for procurement of goods, works and non-consulting services under international open Competitive method, nor for selection of consulting services under QBS, LCS, FBS, and individual consultant selection methods, therefore procurement of all contract packages under these methods shall be carried out through non- electronic process with manual issuance of specific procurement notice (request for expression of interest or invitation for bids/proposals and receipt of bids/proposals), until such time that the modified SPSE has been completed by LKPP and assessed by the Bank to be acceptable. If the Bank determines the modified SPSE to be acceptable for use under the above- mentioned remaining procurement methods, the Bank will confirm through the Bank’s written no objection to LKPP and will also notify in writing to PMU/PIU. Use of National e-Catalogue System. Based on the Bank’s assessment of the national e-catalogue system, the Bank allows the Project Implementing Units (PIUs) under World Bank financed projects to use the national e- catalogue for procurement of small value of goods in lieu of the Request for Quotations (RFQ) method specified in these Regulations within the parameters as below: a) For Goods (other than medicines) with estimated cost not more than USD 15,000 equivalent per contract. PIUs may use the national e-catalogue for procuring such items of goods within the above-specified threshold, if such goods are required under the project and specified in the Procurement Plan approved by the Bank. b) Goods (other than medicines) with estimated cost greater than USD 15,000 but less than USD 100,000 equivalent per contract. PIUs may use the national e-catalogue for procuring such items of goods if such goods are required under the project subject to fulfilling the following additional procedural requirement as below: PMU and PIU shall carry out a secondary procurement process through mini competition, by comparing the prices of similar goods offered by at least three different suppliers which available in the national e-catalogue and then selecting the Supplier with the lowest evaluated price on the basis of “as delivered" price at final destination (i.e., including inland transportation, insurance, applicable taxes and any other incidental charges for the delivery of the required quantity of goods at final destination). E. Other Relevant Procurement Information • Project Operations Manual (POM) shall set out the operating procedures for procurement and contract implementation matters under the Project written in Bahasa, which shall be consistent with the procedures and rules specified under the Bank’s Procurement Regulations. In case of any difference of interpretation between the POM and the Bank’s Procurement Regulations, the later shall prevail; • PMU and PIU may use its own forms of contract for goods/non-consulting services procured under Request for Quotations (RFQ) method when approaching to national market, acceptable to the Bank; • Advance procurement may be applied under the project and shall be valid by signing of the Loan Agreement. PMU and PIU may commence the procurement process prior to issuance of the DIPA for any anticipated activity to be procured under the Project, while signing of the contract shall be subject to issuance of the DIPA of the respective activity. All contracts shall not be designed as single-year contract, and therefore procurement process shall continue throughout multiple calendar years without limitation of contract period up to end of the GoI’s fiscal year; • Regardless of the Bank’s review requirement (prior or post), the Bank may review technical aspects of procurement documents and other non- procurement matters (terms of reference, statement of works, technical specifications, environmental documents, cost estimate, etc.) related to the procurement activity in question, if needed; • The Bank will continue to provide guidance and support to the PMU and PIU for procurement processing through the STEP. • Project Implementation Support Personnel shall not be included in this Procurement Plan. Their selection and hiring procedures shall continue to apply the GoI’s selection and hiring procedures as further defined in the POM. The Procurement Plan is a living document and can be revised if there are any changes during the implementation of the project. PROCUREMENT Indonesia : Program to Accelerate Agrarian Reform (One Map Project) PLAN General Information Country: Indonesia 2019-04-12 Bank’s Approval Date of the Original Procurement Plan: 2022-07-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160661 GPN Date: Project Name: Program to Accelerate Agrarian Reform (One Map Project) Loan / Credit No: IBRD / 88970, TF / A7044 Ministry of Agrarian and Spatial Planning / National Land Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ID-ATR/BPN-108910-CW-RFB Project Management, Institut Request for Quota Single Stage - One E 2019-12-1 / Renovation of Archive Buildi IBRD / 88970 ional Development and Moni Post Open - National 165,866.00 0.00 Canceled 2019-04-27 2019-06-22 tions nvelope 9 ng/Modern Archive toring National Procure ID-ATR/BPN-256537-CW-DIR ment Document - Participatory Mapping and A 2022-01-0 / Renovation of Archive Buildi IBRD / 88970 Post Direct Selection Direct 1 Envelope proce 310,000.00 326,900.66 Signed 2021-10-05 2021-09-22 2021-10-10 2021-10-28 2021-11-07 2021-11-30 grarian Reform 6 ng/Modern Archive (Construc ss (Non Bank-SPD tion) ) ID-ATR/BPN-272977-CW-RFQ Request for Quota Participatory Mapping and A Request for Quota Single Stage - One E 2022-09-3 / Renovation Land office at Kl IBRD / 88970 Post Open - National tions (Non Bank-S 198,000.00 0.00 Canceled 2022-02-06 2022-04-03 grarian Reform tions nvelope 0 aten district - Central Java Pr PD) ovince FY2022 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-ATR/BPN-108911-GO-RFB / Procurement of hardware fo Participatory Mapping and A Open - Internationa Single Stage - One E r strengthening Land Informa IBRD / 88970 Prior Request for Bids 6,652,975.00 0.00 Canceled 2019-04-08 2020-02-19 2020-02-14 2020-04-30 2020-03-30 2020-05-19 2020-05-08 2020-06-29 2020-12-26 grarian Reform l nvelope tion System (Data Center / Di saster Recovery Center infra structure) ID-ATR/BPN-194098-GO-RFB / Retender: Procurement of H Participatory Mapping and A Open - Internationa Single Stage - One E ardware for Strengthening La IBRD / 88970 Prior Request for Bids 6,170,000.00 6,023,182.50 Signed 2020-09-21 2020-10-12 2020-09-26 2020-10-14 2020-11-07 2020-12-07 2020-12-07 2021-01-22 2021-01-11 2021-02-25 2021-04-11 grarian Reform l nvelope nd Information System (Data Center/Disaster Recovery Ce nter Infrastructure) ID-ATR/BPN-108912-GO-RFB Project Management, Institut Single Stage - One E / Procurement of upgrade offi IBRD / 88970 ional Development and Moni Post Request for Bids Open - National 1,990,639.00 0.00 Canceled 2019-04-08 2019-04-13 2019-05-25 2019-06-24 2019-07-29 2020-01-25 nvelope ce equipment (7 Lots) toring ID-ATR/BPN-228382-GO-RFB Participatory Mapping and A Single Stage - One E Under Imple / Procurement of upgrade offi IBRD / 88970 Post Request for Bids Open - National 254,000.00 0.00 2021-04-08 2021-04-14 2021-04-13 2021-05-25 2021-06-08 2021-07-13 2021-09-28 grarian Reform nvelope mentation ce equipment Jambi FY2021 ID-ATR/BPN-228383-GO-RFB Participatory Mapping and A Single Stage - One E / Procurement of upgrade offi IBRD / 88970 Post Request for Bids Open - National 302,431.00 295,667.17 Signed 2021-04-08 2021-10-13 2021-04-13 2021-05-25 2021-11-08 2021-06-08 2021-12-07 2021-07-13 2021-12-29 2021-10-11 grarian Reform nvelope ce equipment West Kalimant an FY2021 ID-ATR/BPN-228384-GO-RFB Participatory Mapping and A Single Stage - One E / Procurement of upgrade offi IBRD / 88970 Post Request for Bids Open - National 273,336.00 251,198.51 Signed 2021-04-08 2020-10-07 2021-04-13 2021-05-25 2021-11-11 2021-06-08 2021-11-11 2021-07-13 2021-12-01 2021-10-11 grarian Reform nvelope ce equipment South Kalimant an FY 2021 ID-ATR/BPN-228385-GO-RFB Participatory Mapping and A Single Stage - One E / Procurement of upgrade offi IBRD / 88970 Post Request for Bids Open - National 322,586.00 307,075.01 Signed 2021-04-08 2020-10-13 2021-04-13 2021-05-25 2021-11-03 2021-06-08 2021-11-11 2021-07-13 2022-02-07 2021-10-11 grarian Reform nvelope ce equipment Central Kalima ntan FY2021 ID-ATR/BPN-228386-GO-RFB Participatory Mapping and A Single Stage - One E / Procurement of upgrade offi IBRD / 88970 Post Request for Bids Open - National 250,300.00 231,717.32 Signed 2021-04-08 2021-10-25 2021-04-13 2021-05-25 2021-10-25 2021-06-08 2021-11-05 2021-07-13 2021-11-29 2021-10-11 grarian Reform nvelope ce equipment East Kalimanta n FY2021 ID-ATR/BPN-228387-GO-RFB Participatory Mapping and A Single Stage - One E / Procurement of upgrade offi IBRD / 88970 Post Request for Bids Open - National 236,432.00 221,260.40 Signed 2021-04-08 2021-09-16 2021-04-13 2021-05-25 2021-10-18 2021-06-08 2021-10-18 2021-07-13 2021-11-10 2021-10-11 grarian Reform nvelope ce equipment Riau FY2021 ID-ATR/BPN-228388-GO-RFB Participatory Mapping and A Single Stage - One E / Procurement of upgrade offi IBRD / 88970 Post Request for Bids Open - National 351,490.00 278,004.39 Signed 2021-04-08 2021-08-19 2021-04-13 2021-05-25 2021-09-20 2021-06-08 2021-10-08 2021-07-13 2021-11-11 2021-10-11 grarian Reform nvelope ce equipment South Sumater a FY2021 ID-ATR/BPN-254537-GO-RFB / Procurement of Scanner for Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 462,100.00 0.00 Canceled 2021-09-28 2021-10-03 2021-10-17 2021-10-31 2021-11-28 2021-12-28 Support Land Offices Operati grarian Reform nvelope onal in 7 provinces ID-ATR/BPN-254541-GO-RFB Participatory Mapping and A Single Stage - One E Pending Impl / Equipment for The New Ren IBRD / 88970 Post Request for Bids Open - National 365,500.00 0.00 2021-09-28 2021-10-03 2021-10-17 2021-10-31 2021-11-28 2021-12-28 grarian Reform nvelope ementation ovated Archieve Building/ Mo dern Archieve ID-ATR/BPN-258411-GO-DIR / Procurement of Scanner for Participatory Mapping and A IBRD / 88970 Post Direct Selection Direct 443,000.00 449,492.72 Signed 2021-10-15 2021-09-28 2021-10-20 2021-11-11 2021-11-06 2021-11-18 2022-01-05 Support Land Offices Operati grarian Reform onal in 7 provinces ID-ATR/BPN-272971-GO-RFB Participatory Mapping and A Single Stage - One E Pending Impl / Strengthening for Security S IBRD / 88970 Post Request for Bids Open - National 1,900,000.00 0.00 2022-01-16 2022-01-21 2022-02-11 2022-02-25 2022-03-18 2022-06-16 grarian Reform nvelope ementation ystem FY2022 ID-ATR/BPN-272972-GO-RFB Participatory Mapping and A Single Stage - One E Pending Impl / Hardware for Network and P IBRD / 88970 Post Request for Bids Open - National 1,900,000.00 0.00 2022-01-16 2022-01-21 2022-02-11 2022-02-25 2022-03-18 2022-06-16 grarian Reform nvelope ementation erformance Monitoring FY202 2 ID-ATR/BPN-272986-GO-RFB Participatory Mapping and A Single Stage - One E Pending Impl / Development of Archive Ma IBRD / 88970 Post Request for Bids Open - National 1,300,000.00 0.00 2022-03-01 2022-03-06 2022-03-27 2022-04-10 2022-05-01 2022-06-30 grarian Reform nvelope ementation nagement in (10 Provinces) F Y2020 NON CONSULTING SERVICES Page 1 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-ATR/BPN-103258-NC-RFB / Pilot Project Fit For Purpose : Project Management, Institut Single Stage - One E Project to Accelerate Agraria IBRD / 88970 ional Development and Moni Post Request for Bids Open - National 383,802.00 233,441.69 Signed 2019-03-15 2019-04-08 2019-03-20 2019-04-10 2019-05-09 2019-04-24 2019-05-17 2019-05-15 2019-06-20 2019-10-12 nvelope n Reform in Kalimantan Timu toring r and Kalimantan Selatan Pro vince Methods: Participatory Mappi ng (PM) and Collaborative (C ID-ATR/BPN-106238-NC-RFB O) PTSL / Pilot Project Fit For Purpose Project Management, Institut Single Stage - One E : IBRD / 88970 ional Development and Moni Post Request for Bids Open - National 170,968.00 69,189.96 Signed 2019-03-25 2019-04-09 2019-03-30 2019-05-11 2019-05-09 2019-06-10 2019-05-31 2019-07-15 2019-06-19 2020-01-11 nvelope Project to Accelerate Agraria toring n Reform in Jambi Province Method: General PTSL ID-ATR/BPN-106239-NC-RFB / Pilot Project Fit For Purpose : Project Management, Institut Single Stage - One E Project to Accelerate Agraria IBRD / 88970 ional Development and Moni Post Request for Bids Open - National 426,863.00 233,043.91 Signed 2019-03-25 2019-04-09 2019-03-30 2019-05-11 2019-05-09 2019-06-10 2019-05-31 2019-07-15 2019-06-20 2020-01-11 nvelope n Reform in Kalimantan Teng toring ah and Kalimantan Barat Pro vince Methods: Community Driven (CD) and Collaborative (CO) ID-ATR/BPN-106240-NC-RFB PTSL / Pilot Project Fit For Purpose Project to Accelerate Agraria Project Management, Institut n Reform in Riau and Sumate Single Stage - One E IBRD / 88970 ional Development and Moni Post Request for Bids Open - National 342,880.00 232,948.36 Signed 2019-03-25 2019-04-08 2019-03-30 2019-05-11 2019-05-09 2019-06-10 2019-05-17 2019-07-15 2019-06-18 2020-01-11 ra Selatan Province nvelope toring Methods: Participatory Mappi ng (PM) and Community Driv en (CD) PTSL ID-ATR/BPN-108465-NC-RFB / Participatory Mapping with Survey (PTSL): 7 lot (South S Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 9,356,886.00 5,970,438.52 Signed 2019-06-15 2019-08-13 2019-06-20 2019-08-01 2019-09-30 2019-08-31 2019-10-09 2019-10-05 2020-10-23 2020-03-03 umatera, Riau, Jambi, West K grarian Reform nvelope alimantan, Central Kalimanta n, East Kalimantan, South Kal imantan) ID-ATR/BPN-108475-NC-RFB / Quality Control for Participa tory Mapping with Survey (PT Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 1,053,482.00 693,358.15 Signed 2019-06-15 2019-11-01 2019-06-20 2019-08-01 2019-11-29 2019-08-31 2019-12-17 2019-10-05 2020-02-18 2020-04-02 SL): 7 lot (South Sumatera, R grarian Reform nvelope iau, Jambi, West Kalimantan, South Kalimantan, East Kalim antan, Central Kalimantan) ID-ATR/BPN-108601-NC-RFB / Event Organizer for Technic Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 176,407.00 74,358.34 Signed 2019-04-08 2019-05-22 2019-04-13 2019-05-25 2019-05-22 2019-06-24 2019-05-22 2019-07-29 2019-07-24 2020-01-25 al Assessment of Forest Boun grarian Reform nvelope dary Demarcation ID-ATR/BPN-108603-NC-RFB Participatory Mapping and A Single Stage - One E Pending Impl / Event Organizer for Technic IBRD / 88970 Post Request for Bids Open - National 96,429.00 0.00 2019-04-08 2019-04-13 2019-05-25 2019-06-24 2019-07-29 2020-01-25 grarian Reform nvelope ementation al Assessment of Document Digitation ID-ATR/BPN-108605-NC-RFB / Procurement of IT Support f Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 1,060,979.00 767,041.41 Signed 2019-06-01 2019-11-11 2019-06-06 2019-07-18 2019-12-06 2019-08-17 2019-12-11 2019-09-21 2020-02-12 2020-03-19 or Scanning and Digital Filing grarian Reform nvelope (Digitalization): 7 lots ID-ATR/BPN-108606-NC-RFB Project Management, Institut / Event Organizer for Worksh Single Stage - One E IBRD / 88970 ional Development and Moni Post Request for Bids Open - National 140,601.00 0.00 Canceled 2019-06-01 2019-06-06 2019-07-18 2019-08-17 2019-09-21 2020-03-19 op Procurement, Financial M nvelope toring anagement and Project Mana gement ID-ATR/BPN-108607-NC-RFB Project Management, Institut / Event Organizer for Worksh Single Stage - One E IBRD / 88970 ional Development and Moni Post Request for Bids Open - National 71,429.00 0.00 Canceled 2019-06-01 2019-06-06 2019-07-18 2019-08-17 2019-09-21 2020-03-19 op International Experience o nvelope toring n Single Land Administration ID-ATR/BPN-108628-NC-RFB Project Management, Institut Single Stage - One E / Event Organizer for Worksh IBRD / 88970 ional Development and Moni Post Request for Bids Open - National 54,739.00 0.00 Canceled 2019-06-01 2019-06-06 2019-07-18 2019-08-17 2019-09-21 2020-03-19 nvelope op Geospatial Industry toring ID-ATR/BPN-108602-NC-RFB Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 1,505,248.00 1,104,413.53 Signed 2019-06-01 2020-03-09 2020-02-20 2020-03-20 2020-08-06 2020-03-31 2020-08-25 2020-04-27 2020-09-22 2020-10-24 / Forest Boundary Demarcati grarian Reform nvelope on: 5 lots ID-ATR/BPN-202001-NC-RFB / Participatory Mapping with Participatory Mapping and A Single Stage - One E IBRD / 88970 Prior Request for Bids Open - National 3,100,000.00 2,324,630.07 Signed 2020-04-27 2020-05-04 2020-05-02 2020-06-02 2020-06-29 2020-06-16 2020-08-11 2020-07-07 2020-09-24 2020-12-04 Survey (PTSL) Fase-3 (220.00 grarian Reform nvelope 0 parcel with 5 lots) of South Sumatera 2020 ID-ATR/BPN-202002-NC-RFB / Participatory Mapping with Participatory Mapping and A Single Stage - One E IBRD / 88970 Prior Request for Bids Open - National 5,000,000.00 3,523,222.39 Signed 2020-04-27 2020-05-04 2020-05-02 2020-06-02 2020-06-29 2020-06-16 2020-08-11 2020-07-07 2020-09-28 2020-12-04 Survey (PTSL) Fase-3 (280.00 grarian Reform nvelope 0 parcel with 7 lots) of West Kalimantan 2020 ID-ATR/BPN-202003-NC-RFB / Participatory Mapping with Participatory Mapping and A Single Stage - One E IBRD / 88970 Prior Request for Bids Open - National 5,000,000.00 3,724,942.67 Signed 2020-04-27 2020-05-04 2020-05-01 2020-06-02 2020-06-29 2020-06-16 2020-08-11 2020-07-06 2020-09-11 2020-12-03 Survey (PTSL) Fase-3 (280.00 grarian Reform nvelope 0 parcel with 6 lots) of South Kalimantan 2020 ID-ATR/BPN-202004-NC-RFB / Participatory Mapping with Participatory Mapping and A Single Stage - One E IBRD / 88970 Prior Request for Bids Open - National 3,900,000.00 2,815,680.48 Signed 2020-04-27 2020-05-04 2020-05-02 2020-06-02 2020-06-29 2020-06-16 2020-08-11 2020-07-07 2020-09-23 2020-12-04 Survey (PTSL) Fase-3 (220.00 grarian Reform nvelope 0 parcel with 5 lots) of Centr al Kalimantan 2020 ID-ATR/BPN-177786-NC-RFB / Participatory Mapping with Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 1,670,000.00 1,014,800.07 Signed 2020-03-16 2020-05-06 2020-03-21 2020-05-02 2020-06-10 2020-06-01 2020-07-01 2020-06-29 2020-08-11 2020-10-27 Survey (PTSL) Fase-3 (90.000 grarian Reform nvelope parcel with 2 lots) of Riau 20 20 ID-ATR/BPN-177794-NC-RFB / Participatory Mapping with Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 1,550,000.00 1,103,375.81 Signed 2020-03-16 2020-05-05 2020-03-21 2020-05-02 2020-06-10 2020-06-01 2020-07-01 2020-06-29 2020-08-12 2020-10-27 Survey (PTSL) Fase-3 (110.00 grarian Reform nvelope 0 parcel with 3 lots) of Jambi 2020 ID-ATR/BPN-177789-NC-RFB / Participatory Mapping with Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 1,850,000.00 1,257,319.45 Signed 2020-03-16 2020-05-05 2020-03-21 2020-05-02 2020-06-10 2020-06-01 2020-07-01 2020-06-29 2020-08-04 2020-10-27 Survey (PTSL) Fase-3 (100.00 grarian Reform nvelope 0 parcel with 2 lots) of East K alimantan 2020 Page 2 ID-ATR/BPN-177801-NC-RFB / Quality Control for Participa Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 258,000.00 170,269.09 Signed 2020-04-15 2020-05-27 2020-04-20 2020-06-01 2020-06-24 2020-06-15 2020-07-07 2020-07-06 2020-10-19 2020-11-03 tory Mapping with Survey (PT grarian Reform nvelope SL) of South Sumatera 2020 ID-ATR/BPN-177796-NC-RFB Participatory Mapping and A Single Stage - One E / Quality Control for Participa IBRD / 88970 Post Request for Bids Open - National 106,000.00 65,220.93 Signed 2020-04-15 2020-06-19 2020-04-20 2020-06-01 2020-07-17 2020-06-15 2020-07-24 2020-07-06 2020-10-21 2020-11-03 grarian Reform nvelope tory Mapping with Survey (PT SL) of Riau 2020 ID-ATR/BPN-177803-NC-RFB Participatory Mapping and A Single Stage - One E / Quality Control for Participa IBRD / 88970 Post Request for Bids Open - National 130,000.00 89,775.81 Signed 2020-04-15 2020-05-29 2020-04-20 2020-06-01 2020-06-29 2020-06-15 2020-07-07 2020-07-06 2020-08-28 2020-11-03 grarian Reform nvelope tory Mapping with Survey (PT SL) of Jambi 2020 ID-ATR/BPN-177806-NC-RFB / Quality Control for Participa Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 348,000.00 229,358.50 Signed 2020-04-15 2020-05-27 2020-04-20 2020-06-01 2020-06-24 2020-07-01 2020-07-07 2020-07-29 2020-10-27 2020-11-26 tory Mapping with Survey (PT grarian Reform nvelope SL) of West Kalimantan 2020 ID-ATR/BPN-177799-NC-RFB / Quality Control for Participa Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 348,000.00 241,430.00 Signed 2020-04-15 2020-06-03 2020-04-20 2020-06-01 2020-07-01 2020-06-15 2020-07-08 2020-07-06 2020-10-05 2020-11-03 tory Mapping with Survey (PT grarian Reform nvelope SL) of South Kalimantan 202 0 ID-ATR/BPN-177804-NC-RFB / Quality Control for Participa Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 125,000.00 79,001.42 Signed 2020-04-15 2020-05-29 2020-04-20 2020-06-01 2020-06-29 2020-06-15 2020-07-07 2020-07-06 2020-09-08 2020-11-03 tory Mapping with Survey (PT grarian Reform nvelope SL) of East Kalimantan 2020 ID-ATR/BPN-177809-NC-RFB / Quality Control for Participa Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 273,000.00 179,830.86 Signed 2020-04-15 2020-05-27 2020-04-20 2020-06-01 2020-06-24 2020-06-15 2020-07-07 2020-07-06 2020-10-13 2020-11-03 tory Mapping with Survey (PT grarian Reform nvelope SL) of Central Kalimantan 20 20 ID-ATR/BPN-192782-NC-RFQ / Event Organizer (EO) for For Participatory Mapping and A Request for Quota Single Stage - One E IBRD / 88970 Post Limited 121,000.00 112,552.85 Signed 2020-08-08 2020-08-03 2020-09-19 2020-09-14 2020-11-18 est Boundary Demarcation C grarian Reform tions nvelope oordination Meetings ID-ATR/BPN-204226-NC-RFB / Participatory Mapping with Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 1,689,722.00 1,420,417.69 Signed 2020-11-06 2021-03-05 2020-11-11 2020-12-23 2021-04-12 2021-01-22 2021-05-21 2021-02-26 2021-07-15 2021-07-26 Survey (PTSL) Phase-4 (140.0 grarian Reform nvelope 00 parcel) of Riau 2021 - (3 L ots) ID-ATR/BPN-204231-NC-RFB / Participatory Mapping with Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 1,736,319.00 1,267,942.42 Signed 2020-11-06 2020-11-30 2020-11-11 2020-12-23 2021-01-04 2021-01-22 2021-02-01 2021-02-26 2021-03-09 2021-07-26 Survey (PTSL) Phase (110.00 grarian Reform nvelope 0 parcel) of East Kalimantan 2021 - ( 3 Lots) ID-ATR/BPN-203978-NC-RFB / Participatory Mapping with Participatory Mapping and A Single Stage - One E IBRD / 88970 Prior Request for Bids Open - National 3,620,833.00 2,598,014.35 Signed 2020-11-06 2020-12-01 2020-11-11 2020-12-23 2021-01-20 2021-01-22 2021-04-01 2021-02-26 2021-07-28 2021-07-26 Survey (PTSL) Phase-4 (300.0 grarian Reform nvelope 00 parcel) of South Sumatera 2021 - (7 Lots) ID-ATR/BPN-204229-NC-RFB / Participatory Mapping with Participatory Mapping and A Single Stage - One E IBRD / 88970 Prior Request for Bids Open - National 2,655,277.00 1,889,294.58 Signed 2020-11-06 2020-12-01 2020-11-11 2020-12-23 2021-02-01 2021-01-22 2021-04-01 2021-02-26 2021-05-31 2021-07-26 Survey (PTSL) Phase-2 (220.0 grarian Reform nvelope 00 parcel) of Jambi 2021 - (6 Lots) ID-ATR/BPN-203979-NC-RFB / Participatory Mapping with Participatory Mapping and A Single Stage - One E IBRD / 88970 Prior Request for Bids Open - National 4,735,416.00 3,524,872.55 Signed 2020-11-06 2020-12-01 2020-11-11 2020-12-23 2021-01-20 2021-01-22 2021-04-01 2021-02-26 2021-07-29 2021-07-26 Survey (PTSL) Phase (300.00 grarian Reform nvelope 0 parcel) of South Kalimanta n 2021 (8 Lots) ID-ATR/BPN-204232-NC-RFB / Participatory Mapping with Participatory Mapping and A Single Stage - One E IBRD / 88970 Prior Request for Bids Open - National 3,472,638.00 2,740,609.20 Signed 2020-11-06 2020-12-01 2020-11-11 2020-12-23 2021-01-20 2021-01-22 2021-04-01 2021-02-26 2021-07-14 2021-07-26 Survey (PTSL) phase (220.00 grarian Reform nvelope 0 parcel) of Central Kalimant an 2021 - (5 Lots) ID-ATR/BPN-203977-NC-RFB / Quality Control for Participa Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 1,979,166.00 1,621,810.34 Signed 2021-01-05 2021-01-13 2021-01-10 2021-02-21 2021-02-18 2021-03-23 2021-03-17 2021-04-27 2021-08-23 2021-09-24 tory Mapping with Survey Ph grarian Reform nvelope ase 4 (PTSL) in 7 Provinces F Y 2021 (7 Lots) ID-ATR/BPN-203975-NC-RFB Participatory Mapping and A Single Stage - One E / Procurement of Digitalizatio IBRD / 88970 Prior Request for Bids Open - National 2,975,000.00 0.00 Canceled 2020-12-01 2020-12-06 2021-01-17 2021-02-16 2021-03-23 2021-09-19 grarian Reform nvelope n in 7 Provinces FY2021 (7 Lo ts) ID-ATR/BPN-204227-NC-RFB / Participatory Mapping with Participatory Mapping and A Single Stage - One E IBRD / 88970 Prior Request for Bids Open - National 5,208,958.00 4,015,881.01 Signed 2020-11-23 2020-12-01 2020-11-28 2021-01-09 2021-01-20 2021-02-08 2021-04-01 2021-03-15 2021-06-29 2021-08-12 Survey (PTSL) Phase-4 (330.0 grarian Reform nvelope 00 parcel) of West Kalimanta n 2021 - (7 Lots) ID-ATR/BPN-213581-NC-RFB / Thematic Map of Land and Spatial in the Context of Acc Project Management, Institut Single Stage - One E elerating Land Redistribution IBRD / 88970 ional Development and Moni Post Request for Bids Open - National 303,936.00 259,657.86 Signed 2021-01-13 2021-01-18 2021-01-18 2021-03-01 2021-02-26 2021-03-31 2021-03-16 2021-04-28 2021-04-19 2021-07-17 nvelope of Objects for Agrarian Refor toring m from Forest Area Based on Spatial Planning and Environ ment (Pilot Project) ID-ATR/BPN-188254-NC-RFB Participatory Mapping and A Single Stage - One E / PTPR Thematic Map of Land IBRD / 88970 Post Request for Bids Open - National 1,810,803.33 998,589.67 Signed 2020-08-12 2020-09-29 2020-08-17 2020-09-28 2020-10-27 2020-10-28 2020-11-17 2020-11-25 2020-12-16 2020-12-31 grarian Reform nvelope and Spatial (PTPR) (4 Lots) ID-ATR/BPN-222685-NC-RFB / ID-ATR/BPN-203975-NC-RFB Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 375,000.00 155,851.12 Signed 2021-03-05 2021-08-15 2021-03-10 2021-04-21 2021-10-06 2021-05-21 2021-10-25 2021-06-25 2021-11-24 2021-07-07 / Procurement of Digitalizatio grarian Reform nvelope n in South Sumatera Provinc e FY2021 (7 Lots) ID-ATR/BPN-222924-NC-RFB / ID-ATR/BPN-203975-NC-RFB Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 375,000.00 363,183.16 Signed 2021-03-05 2021-08-15 2021-03-10 2021-04-21 2021-10-18 2021-05-21 2021-10-25 2021-06-18 2021-11-22 2021-09-16 / Procurement of Digitalizatio grarian Reform nvelope n in South Riau FY2021 (5 Lo ts) ID-ATR/BPN-222925-NC-RFB / ID-ATR/BPN-203975-NC-RFB Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 458,333.00 398,824.56 Signed 2021-03-05 2021-07-21 2021-03-10 2021-04-21 2021-08-25 2021-05-21 2021-09-03 2021-06-18 2021-09-28 2021-09-16 / Procurement of Digitalizatio grarian Reform nvelope n in East Kalimantan Provinc e FY2021 (5 Lots) ID-ATR/BPN-222927-NC-RFB / ID-ATR/BPN-203975-NC-RFB Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 375,000.00 329,529.37 Signed 2021-03-05 2021-08-15 2021-03-10 2021-04-21 2021-09-30 2021-05-21 2021-10-29 2021-06-18 2021-11-26 2021-09-16 / Procurement of Digitalizatio grarian Reform nvelope n in Central Kalimantan Provi nce FY2021 (5 Lots) Page 3 ID-ATR/BPN-222928-NC-RFB / ID-ATR/BPN-203975-NC-RFB Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 425,000.00 433,869.70 Signed 2021-03-05 2021-09-02 2021-03-10 2021-04-21 2021-09-30 2021-05-21 2021-10-29 2021-06-18 2021-11-11 2021-09-16 / Procurement of Digitalizatio grarian Reform nvelope n in South Kalimantan Provin ce FY2021 (6 Lots) ID-ATR/BPN-222930-NC-RFB / ID-ATR/BPN-203975-NC-RFB Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 483,333.00 476,563.57 Signed 2021-03-05 2021-09-02 2021-03-10 2021-04-21 2021-09-30 2021-05-21 2021-10-29 2021-06-18 2021-12-23 2021-09-16 / Procurement of Digitalizatio grarian Reform nvelope n in West Kalimantan Provinc e FY2021 (6 Lots) ID-ATR/BPN-222931-NC-RFB / ID-ATR/BPN-203975-NC-RFB Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 483,333.00 321,198.20 Signed 2021-03-05 2021-08-13 2021-03-10 2021-04-21 2021-09-17 2021-05-21 2021-09-28 2021-06-18 2021-11-01 2021-09-16 / Procurement of Digitalizatio grarian Reform nvelope n in Jambi Province FY2021 ( 5 Lots) ID-ATR/BPN-203980-NC-RFB Participatory Mapping and A Single Stage - One E / Forest Area Boundary Situat IBRD / 88970 Post Request for Bids Open - National 1,433,938.00 949,903.51 Signed 2021-01-05 2021-06-10 2021-01-10 2021-02-21 2021-07-16 2021-03-23 2021-08-05 2021-04-27 2021-09-07 2021-07-13 grarian Reform nvelope ion Map FY 2021 (multi Lots) ID-ATR/BPN-177811-NC-RFB / Procurement of IT Support f Participatory Mapping and A Single Stage - One E or Scanning and Digital Filing IBRD / 88970 Post Request for Bids Open - National 1,698,472.00 0.00 Canceled 2020-04-27 2020-05-02 2020-06-13 2020-07-13 2020-08-10 2020-12-08 grarian Reform nvelope (Digitalization) 2020 7 (seven ) Provinces / 7 (seven) Lot ID-ATR/BPN-108631-NC-RFB Project Management, Institut Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 714,286.00 0.00 Canceled 2019-06-01 2019-06-06 2019-07-18 2019-08-17 2019-09-21 2020-03-19 / Event Organizer for Public C ional Development and Moni nvelope ampaign toring ID-ATR/BPN-108632-NC-RFB / Event Organizer for Implem Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 142,857.00 0.00 Canceled 2019-06-01 2019-06-06 2019-07-18 2019-08-17 2019-09-21 2020-03-19 entation Assessment on Pres grarian Reform nvelope Decree No. 86/2018 ID-ATR/BPN-232937-NC-RFQ Participatory Mapping and A Request for Quota Single Stage - One E / Event Organizer for Coordin IBRD / 88970 Post Limited 55,918.00 47,605.34 Signed 2021-05-09 2021-11-29 2021-06-27 2021-12-13 2021-08-11 grarian Reform tions nvelope ation Meeting Forest Area Bo undary FY 2021 ID-ATR/BPN-251188-NC-RFQ Project Management, Institut Request for Quota Single Stage - One E / Film Documenter Productio IBRD / 88970 ional Development and Moni Post Limited 82,600.00 73,440.44 Signed 2021-09-05 2021-10-22 2021-10-31 2021-11-09 2021-12-30 tions nvelope n for Pilot Project Land Redist toring ribution ID-ATR/BPN-260468-NC-RFB Participatory Mapping and A Single Stage - One E Under Imple / Forest Area Boundary Situat IBRD / 88970 Post Request for Bids Open - National 1,945,000.00 0.00 2021-11-01 2022-05-09 2021-11-06 2021-12-18 2022-05-20 2022-01-17 2022-02-21 2022-05-22 grarian Reform nvelope mentation ion Map FY 2022 (multi Lots) ID-ATR/BPN-270081-NC-RFB / Fase-5 Participatory Mappin Participatory Mapping and A Single Stage - One E Under Imple IBRD / 88970 Prior Request for Bids Open - National 31,000,000.00 0.00 2022-01-14 2022-02-15 2022-04-01 2022-06-16 2022-04-01 2022-01-19 2022-04-22 2022-05-22 2022-06-26 2023-12-18 g with Survey (PTSL-PM) usin grarian Reform nvelope mentation g Framework Agreement (3 l ots) ID-ATR/BPN-271713-NC-RFB Participatory Mapping and A Single Stage - One E Pending Impl / PTPR Thematic Map of Land IBRD / 88970 Post Request for Bids Open - National 1,021,762.00 0.00 2022-01-05 2022-01-10 2022-01-31 2022-03-02 2022-03-30 2022-07-13 grarian Reform nvelope ementation and Spatial (PTPR) (4 Lots) F Y2022 ID-ATR/BPN-272948-NC-RFB Participatory Mapping and A Single Stage - One E Pending Impl / Procurement of Digitalizatio IBRD / 88970 Post Request for Bids Open - National 630,500.00 0.00 2022-01-16 2022-01-21 2022-02-11 2022-02-12 2022-03-05 2022-05-04 grarian Reform nvelope ementation n Jambi Province FY2022 (9 L ots) ID-ATR/BPN-272950-NC-RFB Participatory Mapping and A Single Stage - One E Pending Impl / Procurement of Digitalizatio IBRD / 88970 Post Request for Bids Open - National 900,000.00 0.00 2022-01-16 2022-01-21 2022-02-11 2022-02-12 2022-03-12 2022-05-11 grarian Reform nvelope ementation n Riau Province FY2022 (10 L ots) ID-ATR/BPN-272952-NC-RFB Participatory Mapping and A Single Stage - One E Pending Impl / Procurement of Digitalizatio IBRD / 88970 Post Request for Bids Open - National 1,060,000.00 0.00 2022-01-16 2022-01-21 2022-02-11 2022-02-25 2022-03-18 2022-05-17 grarian Reform nvelope ementation n West Kalimantan Province FY2022 (14 Lots) ID-ATR/BPN-272962-NC-RFB Participatory Mapping and A Single Stage - One E Pending Impl / Procurement of Digitalizatio IBRD / 88970 Post Request for Bids Open - National 508,000.00 0.00 2022-01-16 2022-01-21 2022-02-11 2022-02-25 2022-03-18 2022-05-17 grarian Reform nvelope ementation n Central Kalimantan Provinc e FY2022 (9 Lots) ID-ATR/BPN-272963-NC-RFB Participatory Mapping and A Single Stage - One E Pending Impl / Procurement of Digitalizatio IBRD / 88970 Post Request for Bids Open - National 439,000.00 0.00 2022-01-16 2022-01-21 2022-02-11 2022-02-25 2022-03-11 2022-05-10 grarian Reform nvelope ementation n East Kalimantan Province F Y2022 (11 Lots) ID-ATR/BPN-272966-NC-RFB Participatory Mapping and A Single Stage - One E Pending Impl / Procurement of Digitalizatio IBRD / 88970 Post Request for Bids Open - National 608,000.00 0.00 2022-01-16 2022-01-21 2022-02-11 2022-02-25 2022-03-18 2022-05-17 grarian Reform nvelope ementation n South Kalimantan Province FY2022 (11 Lots) ID-ATR/BPN-272970-NC-RFB / Procurement of Digitalizatio Participatory Mapping and A Single Stage - One E Pending Impl IBRD / 88970 Post Request for Bids Open - National 220,000.00 0.00 2022-01-16 2022-01-21 2022-02-11 2022-02-25 2022-03-18 2022-05-17 n West Java, Central Java & E grarian Reform nvelope ementation ast Java Province FY2022 (3 L ots) ID-ATR/BPN-272997-NC-RFQ Participatory Mapping and A Request for Quota Single Stage - One E Pending Impl / Quality Control for PTSL-PM IBRD / 88970 Post Open - National 71,000.00 0.00 2022-03-20 2022-05-01 2022-07-30 grarian Reform tions nvelope ementation FY2022 South Sumatera Prov inces ID-ATR/BPN-272998-NC-RFQ Participatory Mapping and A Request for Quota Single Stage - One E Pending Impl / Quality Control for PTSL-PM IBRD / 88970 Post Open - National 54,000.00 0.00 2022-03-20 2022-05-01 2022-07-30 grarian Reform tions nvelope ementation FY2022 Riau Provinces ID-ATR/BPN-273000-NC-RFQ Participatory Mapping and A Request for Quota Single Stage - One E Pending Impl / Quality Control for PTSL-PM IBRD / 88970 Post Open - National 83,000.00 0.00 2022-03-21 2022-05-02 2022-07-31 grarian Reform tions nvelope ementation FY2022 Jambi Provinces ID-ATR/BPN-273001-NC-RFQ Participatory Mapping and A Request for Quota Single Stage - One E Pending Impl / Quality Control for PTSL-PM IBRD / 88970 Post Open - National 51,000.00 0.00 2022-03-21 2022-05-02 2022-07-31 grarian Reform tions nvelope ementation FY2022 West Kalimantan Pro vinces ID-ATR/BPN-273002-NC-RFQ Participatory Mapping and A Request for Quota Single Stage - One E Pending Impl / Quality Control for PTSL-PM IBRD / 88970 Post Open - National 100,000.00 0.00 2022-03-21 2022-05-02 2022-07-31 grarian Reform tions nvelope ementation FY2022 South Kalimantan Pr ovinces ID-ATR/BPN-273005-NC-RFQ Participatory Mapping and A Request for Quota Single Stage - One E Pending Impl / Quality Control for PTSL-PM IBRD / 88970 Post Open - National 87,500.00 0.00 2022-03-21 2022-05-02 2022-07-31 grarian Reform tions nvelope ementation FY2022 East Kalimantan Prov inces ID-ATR/BPN-273007-NC-RFQ Participatory Mapping and A Request for Quota Single Stage - One E Pending Impl / Quality Control for PTSL-PM IBRD / 88970 Post Open - National 56,000.00 0.00 2022-03-21 2022-05-02 2022-07-31 grarian Reform tions nvelope ementation FY2022 Central Kalimantan P rovinces Page 4 ID-ATR/BPN-273008-NC-RFB Participatory Mapping and A Single Stage - One E Pending Impl / Quality Control for PTSL-PM IBRD / 88970 Post Request for Bids Open - National 590,000.00 0.00 2022-03-16 2022-03-21 2022-04-11 2023-02-09 2023-03-02 2023-05-31 grarian Reform nvelope ementation FY2022 West Java Provinces ID-ATR/BPN-273009-NC-RFB Participatory Mapping and A Single Stage - One E Pending Impl / Quality Control for PTSL-PM IBRD / 88970 Post Request for Bids Open - National 411,000.00 0.00 2022-03-16 2022-03-21 2022-04-11 2022-04-25 2022-05-16 2022-08-14 grarian Reform nvelope ementation FY2022 Central Java Province s ID-ATR/BPN-273011-NC-RFB Participatory Mapping and A Single Stage - One E Pending Impl / Quality Control for PTSL-PM IBRD / 88970 Post Request for Bids Open - National 563,000.00 0.00 2022-03-16 2022-03-21 2022-04-11 2022-04-25 2022-05-16 2022-08-14 grarian Reform nvelope ementation FY2022 East Java Provinces ID-ATR/BPN-272949-NC-RFB Participatory Mapping and A Single Stage - One E Pending Impl / Procurement of Digitalizatio IBRD / 88970 Post Request for Bids Open - National 1,100,000.00 0.00 2022-01-16 2022-01-21 2022-02-11 2022-02-25 2022-03-18 2022-05-17 grarian Reform nvelope ementation n South Sumatera Province F Y2022 (16 Lots) ID-ATR/BPN-289856-NC-RFB / Quality Control for Participa Participatory Mapping and A Single Stage - One E IBRD / 88970 Post Request for Bids Open - National 269,000.00 204,930.00 Signed 2021-03-15 2021-04-08 2021-03-20 2021-05-01 2021-06-02 2021-05-31 2021-06-14 2021-07-05 2021-08-12 2022-01-01 tion Mapping with Survey Ph grarian Reform nvelope ase 4 (PTSL) in Central Kalim antan FY 2021 ID-ATR/BPN-306030-NC-RFB Project Management, Institut / Land and Spatial Thematic Single Stage - One E Pending Impl IBRD / 88970 ional Development and Moni Post Request for Bids Open - National 1,120,000.00 0.00 2022-07-29 2022-08-03 2022-09-14 2022-10-14 2022-11-18 2023-05-17 Map (PTPR) Labuan Bajo - Fl nvelope ementation toring ores NTT 4 Lots FY 2022 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-ATR/BPN-106571-CS-QCB Project Management, Institut S / Method Analysis and Qual Quality And Cost- Under Implement IBRD / 88970 ional Development and Moni Post Open - National 128,571.00 0.00 2019-06-03 2019-07-10 2019-06-24 2019-08-07 2019-07-10 2019-09-04 2019-07-11 2019-10-04 2019-11-08 2019-12-13 2020-12-12 ity Control of Pilot Project Fit Based Selection ation toring For Purpose Cadastral Mappi ng ID-ATR/BPN-108901-CS-QCB S / Consulting Services for De Participatory Mapping and A Quality And Cost- Open - Internationa Pending Impleme IBRD / 88970 Prior 2,331,034.00 0.00 2019-04-08 2019-04-29 2019-06-12 2019-07-10 2019-08-09 2019-09-13 2019-10-18 2020-10-17 velopment of Land Informatio grarian Reform Based Selection l ntation n System, portal and e-Servic es ID-ATR/BPN-108903-CS-QCB Project Management, Institut Quality And Cost- Pending Impleme S / Legal and Institutional Fra IBRD / 88970 ional Development and Moni Post Open - National 85,714.00 0.00 2019-05-01 2019-05-22 2019-07-05 2019-08-02 2019-09-01 2019-10-06 2019-11-10 2020-11-09 Based Selection ntation mework Consulting Services toring ID-ATR/BPN-108907-CS-QCB Project Management, Institut S / Consulting Services for Pr Quality And Cost- Pending Impleme IBRD / 88970 ional Development and Moni Post Open - National 142,857.00 0.00 2019-05-05 2019-05-26 2019-07-09 2019-08-06 2019-09-05 2019-10-10 2019-11-14 2020-11-13 oject Management Informatio Based Selection ntation toring n System Development ID-ATR/BPN-108908-CS-QCB Project Management, Institut Quality And Cost- Open - Internationa Pending Impleme S / Consulting Services for Co IBRD / 88970 ional Development and Moni Post 607,143.00 0.00 2019-05-05 2019-05-26 2019-07-09 2019-08-06 2019-09-05 2019-10-10 2019-11-14 2020-11-13 Based Selection l ntation mmunication and Public Rela toring tions ID-ATR/BPN-116152-CS-QCB Geospatial Data Infrastructu S / Consulting Services for Re Quality And Cost- Pending Impleme TF / A7044 re for Environmental and Na Post Open - National 107,143.00 0.00 2019-06-24 2019-07-15 2019-07-29 2019-08-26 2019-09-02 2019-09-12 2019-10-03 2020-03-31 view Geospatial Data Infrastr Based Selection ntation tural Resource Management ucture an Services ID-ATR/BPN-219895-CS-CQS Participatory Mapping and A Consultant Qualifi Under Implement / Preparation of Archive Build IBRD / 88970 Post Open - National 8,621.00 0.00 2021-02-26 2021-04-30 2021-03-19 2021-04-16 2021-05-16 2021-06-13 2021-09-11 grarian Reform cation Selection ation ing/Modern Archive (DED - Pl anning) ID-ATR/BPN-108906-CS-QCB Project Management, Institut Quality And Cost- S / Vulnerability Mapping, soc IBRD / 88970 ional Development and Moni Post Open - National 321,429.00 0.00 Canceled 2019-05-05 2019-05-26 2019-07-09 2019-08-06 2019-09-05 2019-10-10 2019-11-14 2020-11-13 Based Selection ial monitoring and impact as toring sessment ID-ATR/BPN-108902-CS-QCB Project Management, Institut S / Pilot Project Analysis Cons Quality And Cost- IBRD / 88970 ional Development and Moni Post Open - National 128,571.00 0.00 Canceled 2019-04-08 2019-04-29 2019-06-12 2019-07-10 2019-08-09 2019-09-13 2019-10-18 2020-10-17 ultant and Data Quality Contr Based Selection toring ol for Participatory Mapping ID-ATR/BPN-296881-CS-CQS / Consultant Communication Project Management, Institut Consultant Qualifi Under Implement supporting for strengthening IBRD / 88970 ional Development and Moni Post Open - National 145,000.00 0.00 2022-06-15 2022-05-24 2022-07-06 2022-08-19 2022-09-18 2022-10-23 2023-04-21 cation Selection ation communication policy in publ toring ic relations bureau FY 2022 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-ATR/BPN-108917-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 30,000.00 90,248.70 Signed 2019-04-24 2019-06-09 2019-06-12 2019-07-11 2019-07-03 2019-07-12 2019-08-07 2019-08-01 2020-02-03 / Safeguards Coordinator ional Development and Moni ant Selection toring ID-ATR/BPN-108918-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 25,000.00 15,917.45 Signed 2019-04-24 2019-03-01 2019-06-12 2019-03-08 2019-07-03 2019-03-08 2019-08-07 2019-06-12 2020-02-03 / Monitoring and Evaluation S ional Development and Moni ant Selection pecialist toring ID-ATR/BPN-108920-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 22,500.00 2,003.10 Signed 2019-04-24 2019-08-01 2019-06-12 2019-10-25 2019-07-03 2019-10-24 2019-08-07 2019-10-30 2020-02-03 / ICT specialist ional Development and Moni ant Selection toring ID-ATR/BPN-108921-CS-INDV Project Management, Institut Individual Consult Pending Impleme / Legal expert ( consultant on IBRD / 88970 ional Development and Moni Post Open 25,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 ant Selection ntation land law policy) toring ID-ATR/BPN-108922-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 56,000.00 41,790.00 Signed 2019-04-24 2019-07-10 2019-06-12 2019-08-06 2019-07-03 2019-08-14 2019-08-07 2019-10-01 2020-02-03 / Liasion PCC ional Development and Moni ant Selection toring ID-ATR/BPN-108923-CS-INDV Project Management, Institut Individual Consult / Strategic Planning Specialis IBRD / 88970 ional Development and Moni Post Open 125,000.00 19,502.00 Signed 2019-04-24 2021-01-20 2019-06-12 2021-02-02 2019-07-03 2021-02-04 2019-08-07 2021-02-11 2020-02-03 ant Selection t (International) toring Page 5 ID-ATR/BPN-108924-CS-INDV Project Management, Institut Individual Consult Pending Impleme / Social and Environmental S IBRD / 88970 ional Development and Moni Post Open 25,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 ant Selection ntation pecialist for Pilot Participator toring y Mapping ID-ATR/BPN-108925-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 12,500.00 8,698.75 Signed 2019-04-24 2019-05-16 2019-06-12 2019-07-12 2019-07-03 2019-07-12 2019-08-07 2021-08-01 2020-02-03 / FM Assistant ional Development and Moni ant Selection toring ID-ATR/BPN-108926-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 12,500.00 52,486.00 Signed 2019-04-24 2019-05-01 2019-06-12 2019-07-22 2019-07-03 2019-07-22 2019-08-07 2019-08-01 2020-02-03 / Procurement Assistant ional Development and Moni ant Selection toring ID-ATR/BPN-108927-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 12,500.00 20,955.74 Signed 2019-04-24 2019-05-01 2019-06-12 2021-07-12 2019-07-03 2019-07-29 2019-08-07 2019-08-01 2020-02-03 / Junior Public Awareness Spe ional Development and Moni ant Selection cilaist toring ID-ATR/BPN-108928-CS-INDV Project Management, Institut Individual Consult Pending Impleme IBRD / 88970 Post Open 52,500.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 / Junior Public Awareness Spe ional Development and Moni ant Selection ntation cilaist toring ID-ATR/BPN-108929-CS-INDV Project Management, Institut Individual Consult Pending Impleme IBRD / 88970 Post Open 140,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 / Regional Project Technical A ional Development and Moni ant Selection ntation dvisor toring ID-ATR/BPN-108930-CS-INDV Project Management, Institut Individual Consult Pending Impleme IBRD / 88970 Post Open 140,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 / Regional Project Operations ional Development and Moni ant Selection ntation Advisor toring ID-ATR/BPN-108931-CS-INDV Project Management, Institut Individual Consult Pending Impleme IBRD / 88970 Post Open 20,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 / Project Administrator ional Development and Moni ant Selection ntation toring ID-ATR/BPN-108915-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 30,000.00 0.00 Canceled 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 / Financial Management Spec ional Development and Moni ant Selection ialist toring ID-ATR/BPN-116146-CS-INDV Project Management, Institut Individual Consult TF / A7044 Post Open 26,786.00 177,784.78 Signed 2018-12-03 2018-10-01 2018-12-22 2018-12-19 2018-12-24 2018-12-21 2019-01-01 2019-01-03 2019-05-31 / Project Management Adviso ional Development and Moni ant Selection r toring ID-ATR/BPN-116153-CS-INDV Project Management, Institut Individual Consult TF / A7044 Post Open 14,286.00 75,930.91 Signed 2019-02-01 2019-01-23 2019-02-23 2019-02-06 2019-03-02 2019-02-08 2019-03-15 2019-02-11 2019-05-31 / Communication Specialist ional Development and Moni ant Selection toring ID-ATR/BPN-116154-CS-INDV Project Management, Institut Individual Consult TF / A7044 Post Open 8,571.00 3,219.13 Signed 2019-01-02 2019-03-17 2019-01-19 2019-04-08 2019-01-22 2019-04-09 2019-02-01 2019-04-16 2019-05-31 / Safeguards Coordinator ional Development and Moni ant Selection toring ID-ATR/BPN-116151-CS-INDV Project Management, Institut Individual Consult TF / A7044 Post Open 7,500.00 78,450.61 Signed 2019-02-18 2019-02-10 2019-02-26 2019-03-06 2019-02-27 2019-03-08 2019-03-01 2019-03-14 2019-05-31 / Monitoring & Evaluation Sp ional Development and Moni ant Selection ecilaist toring ID-ATR/BPN-116148-CS-INDV Project Management, Institut Individual Consult TF / A7044 Post Open 10,714.00 0.00 Canceled 2019-05-24 2019-06-23 2019-06-04 2019-06-06 2019-06-10 2019-12-07 / PCC Liaison Officer ional Development and Moni ant Selection toring ID-ATR/BPN-116147-CS-INDV Project Management, Institut Individual Consult Pending Impleme TF / A7044 Post Open 12,857.00 0.00 2019-05-24 2019-06-04 2019-06-06 2019-06-10 2019-12-07 / Legal Advisor ional Development and Moni ant Selection ntation toring ID-ATR/BPN-116149-CS-INDV Project Management, Institut Individual Consult TF / A7044 Post Open 3,750.00 8,425.20 Signed 2019-05-24 2018-12-09 2019-06-07 2019-01-15 2019-06-09 2019-01-15 2019-06-13 2019-02-01 2019-11-30 / Assistant Safeguard Coordin ional Development and Moni ant Selection ator toring ID-ATR/BPN-177834-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Direct 37,250.00 0.00 Canceled 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 / Financial Management Spec ional Development and Moni ant Selection ialist toring ID-ATR/BPN-178294-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Direct 28,200.00 0.00 Canceled 2019-12-20 2019-03-01 2019-12-23 2019-12-24 2020-01-01 2020-12-31 / Monitoring and Evaluation C ional Development and Moni ant Selection onsultant toring ID-ATR/BPN-178144-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Direct 16,600.00 0.00 Canceled 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 / Public Awareness Specialist ional Development and Moni ant Selection 3 (Riau) toring ID-ATR/BPN-178122-CS-INDV Project Management, Institut Individual Consult Pending Impleme / Public Awareness Specialist IBRD / 88970 ional Development and Moni Post Direct 16,600.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 ant Selection ntation 5 (Kalteng) toring ID-ATR/BPN-178141-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Direct 16,600.00 0.00 Canceled 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 / Public Awareness Specialist ional Development and Moni ant Selection 7 (Kalsel) toring ID-ATR/BPN-178299-CS-INDV Project Management, Institut Individual Consult / Program Officer (5 Person) IBRD / 88970 ional Development and Moni Post Direct 40,000.00 0.00 Canceled 2020-01-15 2020-01-18 2020-01-19 2020-01-27 2020-12-31 ant Selection and Access Reform Officer (1 toring Person) ID-ATR/BPN-178296-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Direct 33,100.00 0.00 Canceled 2019-12-20 2019-08-01 2019-12-23 2019-12-24 2020-01-01 2020-12-31 / PCC Liaison Adviser ional Development and Moni ant Selection toring ID-ATR/BPN-178302-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Direct 21,000.00 0.00 Canceled 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 / PCC liaison Officer ional Development and Moni ant Selection toring ID-ATR/BPN-177836-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Direct 21,000.00 0.00 Canceled 2019-12-20 2019-05-01 2019-12-23 2019-12-24 2020-01-01 2020-12-31 / Financial Management Assis ional Development and Moni ant Selection tant toring ID-ATR/BPN-177831-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 13,800.00 10,798.04 Signed 2019-12-20 2020-08-02 2020-02-07 2020-09-21 2020-02-28 2020-09-21 2020-03-27 2020-11-02 2020-12-31 / Project Management Assista ional Development and Moni ant Selection nt toring ID-ATR/BPN-181543-CS-INDV Project Management, Institut Individual Consult Pending Impleme IBRD / 88970 Post Open 11,750.00 0.00 2020-07-01 2020-08-04 2020-08-11 2020-09-01 2021-02-28 / Survey and Mapping Special ional Development and Moni ant Selection ntation ist toring ID-ATR/BPN-178301-CS-INDV Project Management, Institut Individual Consult Under Implement / Transformation Digital Spec IBRD / 88970 ional Development and Moni Post Direct 6,200.00 0.00 2020-01-15 2020-01-03 2020-01-18 2020-01-19 2020-01-27 2020-07-25 ant Selection ation ialist [National] toring ID-ATR/BPN-178298-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 10,400.00 0.00 Canceled 2020-01-15 2020-06-02 2020-03-04 2020-03-18 2020-04-22 2020-10-19 / Land Tenure Expert (Nation ional Development and Moni ant Selection al) toring ID-ATR/BPN-178297-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 51,800.00 0.00 Canceled 2020-01-15 2020-03-04 2020-03-18 2020-04-22 2020-10-19 / Land Tenure Expert (Interna ional Development and Moni ant Selection tional ) toring ID-ATR/BPN-178150-CS-INDV Project Management, Institut Individual Consult / Knowledge Management & IBRD / 88970 ional Development and Moni Post Open 10,400.00 10,019.52 Signed 2020-01-15 2020-03-02 2020-03-04 2020-04-09 2020-03-18 2020-04-15 2020-04-08 2020-05-04 2020-12-31 ant Selection Data Officer toring ID-ATR/BPN-187783-CS-INDV Project Management, Institut Individual Consult Pending Impleme IBRD / 88970 Post Open 51,800.00 0.00 2020-01-15 2020-03-04 2020-03-18 2020-04-15 2020-12-31 / Spatial Analyst for Land Par ional Development and Moni ant Selection ntation cels Sp. toring ID-ATR/BPN-178295-CS-INDV Project Management, Institut Individual Consult Pending Impleme / Transformation Digital Spec IBRD / 88970 ional Development and Moni Post Open 51,800.00 0.00 2020-01-15 2020-03-04 2020-03-18 2020-04-22 2020-10-19 ant Selection ntation ialist [International] toring Page 6 ID-ATR/BPN-178300-CS-INDV Project Management, Institut Individual Consult Pending Impleme IBRD / 88970 Post Open 2,800.00 0.00 2020-06-05 2020-07-24 2020-08-07 2020-09-11 2020-10-01 / Capacity Building Specialist ional Development and Moni ant Selection ntation toring ID-ATR/BPN-181544-CS-INDV Project Management, Institut Individual Consult Pending Impleme IBRD / 88970 Post Open 21,000.00 0.00 2020-04-15 2020-06-03 2020-06-24 2020-07-29 2020-08-28 / Consultant 3D ional Development and Moni ant Selection ntation toring ID-ATR/BPN-187781-CS-INDV Project Management, Institut Individual Consult Pending Impleme / Legal Specialist (Supporting IBRD / 88970 ional Development and Moni Post Open 10,417.00 0.00 2020-08-03 2020-09-21 2020-10-05 2020-11-02 2020-12-31 ant Selection ntation for Transformation digital) toring ID-ATR/BPN-187780-CS-INDV Project Management, Institut Individual Consult Under Implement / Financial Specialist (Suppor IBRD / 88970 ional Development and Moni Post Open 10,417.00 0.00 2020-08-03 2020-06-30 2020-09-21 2020-10-05 2020-11-02 2020-12-31 ant Selection ation ting for Transformation digita toring l) ID-ATR/BPN-187777-CS-INDV Project Management, Institut Individual Consult Under Implement / IT Specialist (Supporting for IBRD / 88970 ional Development and Moni Post Open 10,417.00 0.00 2020-08-03 2020-06-08 2020-09-21 2020-10-05 2020-11-02 2020-12-31 ant Selection ation Transformation digital) toring ID-ATR/BPN-187797-CS-INDV Project Management, Institut Individual Consult / Feedback and Grievance Re IBRD / 88970 ional Development and Moni Post Open 8,333.00 22,405.60 Signed 2020-08-07 2020-05-29 2020-09-25 2020-07-22 2020-10-16 2020-07-22 2020-11-20 2020-09-01 2020-12-31 ant Selection dress Mechanism (FGRM) Offi toring cer ID-ATR/BPN-187776-CS-INDV Project Management, Institut / Project Planning and Manag Individual Consult IBRD / 88970 ional Development and Moni Post Direct 52,083.00 33,058.25 Signed 2020-08-03 2020-08-24 2020-08-13 2020-06-24 2020-08-27 2020-09-10 2020-09-24 2020-09-11 2020-12-31 ement Specialist (Supporting ant Selection toring for Transformation Digital) ID-ATR/BPN-187772-CS-INDV Project Management, Institut / Project Risk Management S Individual Consult IBRD / 88970 ional Development and Moni Post Direct 52,083.00 33,058.25 Signed 2020-08-03 2020-08-24 2020-08-13 2020-06-24 2020-08-27 2020-09-10 2020-09-24 2020-09-11 2020-12-31 pecialist (Supporting for Tran ant Selection toring sformation Digital) ID-ATR/BPN-187770-CS-INDV Project Management, Institut / Land Information System D Individual Consult IBRD / 88970 ional Development and Moni Post Direct 52,083.00 33,058.25 Signed 2020-08-03 2020-08-24 2020-08-13 2020-06-24 2020-08-27 2020-09-10 2020-09-24 2020-09-11 2020-12-31 evelopment Specialist (Supp ant Selection toring orting for Transformation Dig ital) ID-ATR/BPN-187774-CS-INDV Project Management, Institut / Digital Communication Spec Individual Consult Under Implement IBRD / 88970 ional Development and Moni Post Direct 52,083.00 0.00 2020-08-03 2020-08-24 2020-08-13 2020-08-27 2020-09-24 2020-12-31 ialist (Supporting for Transfor ant Selection ation toring mation Digital) ID-ATR/BPN-187799-CS-INDV Project Management, Institut Individual Consult / Administrator Support at 7 IBRD / 88970 ional Development and Moni Post Open 21,875.00 0.00 Canceled 2020-08-07 2020-06-15 2020-09-25 2020-10-09 2020-11-06 2020-12-31 ant Selection Provinces (7 Packages) toring ID-ATR/BPN-201161-CS-INDV Project Management, Institut Individual Consult Pending Impleme TF / A7044 Post Direct 6,944.00 0.00 2020-10-25 2020-11-02 2020-11-07 2020-11-15 2020-12-30 / Risk Screening Support ional Development and Moni ant Selection ntation toring ID-ATR/BPN-203395-CS-INDV Project Management, Institut Individual Consult / Project Manager for PMO Di IBRD / 88970 ional Development and Moni Post Open 10,417.00 3,339.50 Signed 2020-09-01 2020-09-01 2020-09-27 2020-11-18 2020-10-04 2020-11-18 2020-10-25 2020-12-01 2020-12-31 ant Selection gital Transformation toring ID-ATR/BPN-203397-CS-INDV Project Management, Institut Individual Consult / Safeguard Specialist for Pilo IBRD / 88970 ional Development and Moni Post Open 3,125.00 0.00 Canceled 2020-09-01 2021-03-04 2020-09-27 2020-10-11 2020-11-01 2020-12-31 ant Selection t Project Land Redistribution toring ID-ATR/BPN-203401-CS-INDV Project Management, Institut Individual Consult / Project Management Assista IBRD / 88970 ional Development and Moni Post Open 3,160.00 10,950.28 Signed 2020-09-01 2021-03-04 2020-09-27 2021-04-28 2020-10-11 2021-04-28 2020-11-01 2022-05-05 2020-12-31 ant Selection nt for Pilot Project Land Redis toring tribution ID-ATR/BPN-203400-CS-INDV Project Management, Institut Individual Consult Under Implement / Communication Specialit for IBRD / 88970 ional Development and Moni Post Open 3,125.00 0.00 2020-09-01 2020-11-06 2020-09-27 2020-10-11 2020-11-01 2020-12-31 ant Selection ation Pilot Project Land Redistributi toring on ID-ATR/BPN-203402-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 3,472.00 41,839.00 Signed 2020-10-01 2020-11-27 2020-10-27 2020-12-16 2020-11-10 2020-12-21 2020-12-01 2021-01-04 2020-12-31 / Procurement Assistant-2 (sh ional Development and Moni ant Selection ort term) toring ID-ATR/BPN-204256-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 25,000.00 0.00 Under Review 2020-11-13 2021-01-20 2021-01-01 2021-01-15 2021-02-05 2021-12-22 / Stategic Planner (PMU) ional Development and Moni ant Selection toring ID-ATR/BPN-204250-CS-INDV Project Management, Institut Individual Consult / Community Empowerment IBRD / 88970 ional Development and Moni Post Open 8,160.00 12,383.22 Signed 2021-01-05 2021-03-04 2021-02-23 2021-04-07 2021-03-09 2021-05-05 2021-04-06 2021-10-06 2021-09-03 ant Selection Consultant for Land Redistrib toring ution ID-ATR/BPN-204251-CS-INDV Project Management, Institut Individual Consult / Social Safeguard and Compl IBRD / 88970 ional Development and Moni Post Open 4,896.00 10,161.76 Signed 2021-01-05 2020-11-05 2021-02-23 2021-06-08 2021-03-09 2021-06-08 2021-03-30 2021-06-17 2021-06-28 ant Selection aint Handling for Land Redist toring ribution ID-ATR/BPN-204246-CS-INDV Project Management, Institut / TORA Potential Analysis Con Individual Consult IBRD / 88970 ional Development and Moni Post Open 114,236.00 0.00 Canceled 2020-12-01 2021-01-19 2021-02-02 2021-02-23 2021-12-20 sultant for Land Redistributio ant Selection toring n (7 Consultants) ID-ATR/BPN-204244-CS-INDV Project Management, Institut Individual Consult / Bilingual Secretary for Land IBRD / 88970 ional Development and Moni Post Open 5,347.00 0.00 Canceled 2021-01-05 2021-03-04 2021-02-23 2021-03-16 2021-04-20 2021-11-16 ant Selection Redistribution toring ID-ATR/BPN-204254-CS-INDV Project Management, Institut Individual Consult / Supporting Staffs for Land R IBRD / 88970 ional Development and Moni Post Open 7,778.00 6,720.55 Signed 2021-01-05 2021-03-04 2021-02-23 2021-06-08 2021-03-09 2021-06-08 2021-03-30 2021-07-21 2021-10-26 ant Selection edistribution (2 Consultants) toring ID-ATR/BPN-219903-CS-INDV Participatory Mapping and A Individual Consult Pending Impleme / QC Renovation of Archive B IBRD / 88970 Post Open 5,172.00 0.00 2021-02-19 2021-03-24 2021-04-07 2021-05-05 2021-11-01 grarian Reform ant Selection ntation uilding/Modern Archive ID-ATR/BPN-204257-CS-INDV Project Management, Institut Individual Consult Under Implement IBRD / 88970 Post Open 25,000.00 2,085.90 2021-03-23 2021-02-01 2021-04-25 2021-05-24 2021-05-09 2021-05-24 2021-05-16 2021-08-14 / Strategic Program Officer (2 ional Development and Moni ant Selection ation person) toring ID-ATR/BPN-243281-CS-INDV Participatory Mapping and A Individual Consult IBRD / 88970 Post Direct 66,200.00 51,393.72 Signed 2021-07-13 2021-07-29 2021-07-23 2021-08-05 2021-08-06 2021-08-27 2021-09-03 2021-09-14 2022-03-02 / SPIP Facilitator (4 Positions) grarian Reform ant Selection ID-ATR/BPN-243285-CS-INDV Participatory Mapping and A Individual Consult IBRD / 88970 Post Direct 20,600.00 16,850.40 Signed 2021-07-13 2021-07-29 2021-07-23 2021-08-05 2021-08-06 2021-08-27 2021-09-03 2021-09-14 2022-03-02 / SPIP Coordinator (1 Position grarian Reform ant Selection ) Page 7 ID-ATR/BPN-243302-CS-INDV / Governance, Forestry and E Participatory Mapping and A Individual Consult IBRD / 88970 Post Open 8,100.00 4,622.66 Signed 2021-07-13 2021-07-01 2021-08-31 2021-09-14 2021-09-21 2021-09-21 2021-10-26 2021-10-06 2022-03-25 nvironmental Policy Consulta grarian Reform ant Selection nt for Land Redistribution ID-ATR/BPN-243312-CS-INDV / Data Management Consulta Participatory Mapping and A Individual Consult IBRD / 88970 Post Open 7,500.00 4,327.60 Signed 2021-07-13 2021-07-01 2021-08-31 2021-09-14 2021-09-21 2021-09-21 2021-10-26 2021-10-06 2022-03-25 nt and grarian Reform ant Selection Reporting for Pilot Project La nd Redistribution ID-ATR/BPN-204249-CS-INDV Project Management, Institut Individual Consult / Business Process and Regul IBRD / 88970 ional Development and Moni Post Open 8,000.00 4,583.28 Signed 2021-01-05 2021-07-01 2021-02-23 2021-09-14 2021-03-09 2021-09-21 2021-04-06 2021-10-07 2021-11-02 ant Selection ation Consultant for Land Re toring distribution ID-ATR/BPN-204248-CS-INDV Project Management, Institut Individual Consult / Land Use Planning Consulta IBRD / 88970 ional Development and Moni Post Open 32,400.00 8,065.08 Signed 2021-01-05 2021-07-01 2021-02-23 2021-09-13 2021-03-09 2021-09-21 2021-03-30 2021-10-07 2021-06-28 ant Selection nt for Land Redistribution (4 toring Positions) ID-ATR/BPN-204245-CS-INDV Project Management, Institut / Agrarian Reform Assessmen Individual Consult IBRD / 88970 ional Development and Moni Post Open 32,400.00 7,966.71 Signed 2020-12-01 2021-07-01 2021-01-19 2021-09-17 2021-02-02 2021-09-21 2021-02-23 2021-10-06 2021-12-20 t Consultant for Land Redistri ant Selection toring bution (4 Consultants) ID-ATR/BPN-249707-CS-INDV Project Management, Institut Individual Consult TF / A7044 Post Open 20,833.00 0.00 Canceled 2018-10-01 2018-10-01 2018-11-19 2018-12-18 2018-12-10 2019-02-08 2019-01-14 2019-07-13 / Financial Management Spec ional Development and Moni ant Selection ialist TF toring ID-ATR/BPN-249706-CS-INDV Project Management, Institut Individual Consult TF / A7044 Post Open 17,361.00 166,830.16 Signed 2018-10-01 2018-10-01 2018-11-19 2019-01-15 2018-12-10 2019-01-16 2019-01-14 2019-02-01 2019-07-13 / Procurement Specialist TF ional Development and Moni ant Selection toring ID-ATR/BPN-116145-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 6,429.00 49,138.31 Signed 2019-05-24 2019-06-03 2019-06-04 2019-07-15 2019-06-06 2019-07-15 2019-06-10 2019-08-01 2019-12-07 / Junior Public Awareness Spe ional Development and Moni ant Selection cialist toring ID-ATR/BPN-251250-CS-INDV Project Management, Institut Individual Consult / Knowledge Management Mo IBRD / 88970 ional Development and Moni Post Open 10,625.00 24,902.28 Signed 2021-01-02 2021-01-04 2021-02-20 2021-03-02 2021-03-13 2021-03-03 2021-04-17 2021-03-24 2021-10-14 ant Selection nitoring Officer FY2021 toring ID-ATR/BPN-251240-CS-INDV Project Management, Institut Individual Consult / Financial Management Spec IBRD / 88970 ional Development and Moni Post Open 25,000.00 25,128.00 Signed 2020-12-01 2020-12-01 2021-01-19 2020-12-29 2021-02-09 2020-12-29 2021-03-16 2021-01-04 2021-09-12 ant Selection ialist FY2021 toring ID-ATR/BPN-251241-CS-INDV Project Management, Institut Individual Consult / Public Awareness Specialist IBRD / 88970 ional Development and Moni Post Open 16,000.00 12,443.10 Signed 2021-01-02 2020-12-28 2021-02-20 2021-01-08 2021-03-13 2021-03-12 2021-04-17 2021-03-12 2021-10-14 ant Selection East Kalimantan Province FY toring 2021 ID-ATR/BPN-2021-13-CS-IND Project Management, Institut Individual Consult V / Public Awareness Speciali IBRD / 88970 ional Development and Moni Post Open 4,200.00 46,855.04 Signed 2019-06-01 2019-06-03 2019-07-20 2019-09-05 2019-08-10 2019-09-09 2019-09-14 2021-10-01 2019-11-13 ant Selection st South Sumatera Province F toring Y2019 ID-ATR/BPN-2021-14-CS-IND Project Management, Institut Individual Consult V / Public Awareness Speciali IBRD / 88970 ional Development and Moni Post Open 4,200.00 18,390.76 Signed 2019-06-01 2019-06-03 2019-07-20 2019-09-02 2019-08-10 2019-09-04 2019-09-14 2019-10-01 2019-12-13 ant Selection st West Kalimantan Province toring FY2019 ID-ATR/BPN-251246-CS-INDV Project Management, Institut Individual Consult / Public Awareness Specialist IBRD / 88970 ional Development and Moni Post Open 14,500.00 3,026.70 Signed 2021-01-02 2020-12-28 2021-02-20 2021-01-07 2021-02-23 2021-03-04 2021-03-01 2021-03-04 2021-05-30 ant Selection West Kalimantan Province FY toring 2021 ID-ATR/BPN-251249-CS-INDV Project Management, Institut Individual Consult / Public Awareness Specialist IBRD / 88970 ional Development and Moni Post Open 4,200.00 49,277.02 Signed 2019-06-01 2019-06-10 2019-07-20 2019-08-12 2019-07-27 2019-08-23 2019-08-10 2019-10-14 2019-11-08 ant Selection Central Kalimantan Province toring FY2019 ID-ATR/BPN-251251-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 9,400.00 47,337.75 Signed 2019-06-01 2019-06-09 2019-07-20 2019-08-08 2019-07-27 2019-08-09 2019-08-10 2019-10-01 2019-11-08 / Legal Specialist PMU FY201 ional Development and Moni ant Selection 9 toring ID-ATR/BPN-251243-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 3,200.00 40,930.20 Signed 2019-06-01 2019-07-23 2019-07-20 2019-09-11 2019-08-10 2019-09-11 2019-09-14 2019-10-07 2019-12-13 / Graphic Designer PMU FY20 ional Development and Moni ant Selection 19 toring ID-ATR/BPN-251252-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 10,500.00 10,470.00 Signed 2019-06-01 2019-07-19 2019-07-20 2019-09-24 2019-07-27 2019-09-24 2019-08-10 2019-10-01 2019-11-08 / Senior Policy Advisor FY201 ional Development and Moni ant Selection 9 toring ID-ATR/BPN-251258-CS-INDV Project Management, Institut Individual Consult / Digital Transformation Spec IBRD / 88970 ional Development and Moni Post Open 10,500.00 10,134.00 Signed 2020-01-02 2020-01-06 2020-02-20 2020-02-27 2020-02-27 2020-03-02 2020-03-12 2020-03-02 2020-06-10 ant Selection ialist FY2020 toring ID-ATR/BPN-254529-CS-INDV Project Management, Institut Individual Consult / Public Specialist Awareness IBRD / 88970 ional Development and Moni Post Open 12,000.00 550,979.55 Signed 2021-09-28 2021-10-01 2021-10-15 2021-10-27 2021-10-20 2021-11-08 2021-11-03 2021-11-15 2022-02-01 ant Selection Java Province FY2021 toring ID-ATR/BPN-254533-CS-INDV Project Management, Institut / Public Specialist Awareness Individual Consult IBRD / 88970 ional Development and Moni Post Open 12,000.00 5,138.98 Signed 2021-06-30 2022-01-10 2021-07-24 2022-07-04 2021-07-31 2022-07-04 2021-08-21 2022-07-12 2021-11-19 West Kalimantan Province (T ant Selection toring hird Recruitment) ID-ATR/BPN-116150-CS-INDV Project Management, Institut Individual Consult Pending Impleme IBRD / 88970 Post Open 10,500.00 0.00 2019-05-24 2019-06-04 2019-06-06 2019-06-10 2019-12-31 / Spatial Land Data Analysis f ional Development and Moni ant Selection ntation or PMO toring ID-ATR/BPN-108914-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 37,500.00 0.00 Canceled 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 / Project Management Adviso ional Development and Moni ant Selection r toring ID-ATR/BPN-177827-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Direct 59,600.00 0.00 Canceled 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 / Project Management Adviso ional Development and Moni ant Selection r toring ID-ATR/BPN-108916-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 30,000.00 0.00 Canceled 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 / Procurement Specialist ional Development and Moni ant Selection toring ID-ATR/BPN-177837-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Direct 45,500.00 0.00 Canceled 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 / Procurement Specialist ional Development and Moni ant Selection toring ID-ATR/BPN-108919-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 25,000.00 0.00 Canceled 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 / Communication Specialist ional Development and Moni ant Selection toring ID-ATR/BPN-177840-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Direct 29,000.00 0.00 Canceled 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 / Communication Specialist ional Development and Moni ant Selection toring ID-ATR/BPN-177839-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Direct 21,000.00 0.00 Canceled 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 / Procurement Assistant ional Development and Moni ant Selection toring Page 8 ID-ATR/BPN-177842-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Direct 24,900.00 0.00 Canceled 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 / Safeguards Coordinator ional Development and Moni ant Selection toring ID-ATR/BPN-178145-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Direct 16,600.00 0.00 Canceled 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 / Public Awareness Specialist ional Development and Moni ant Selection 2 (Jambi) toring ID-ATR/BPN-178140-CS-INDV Project Management, Institut Individual Consult / Public Awareness Specialist IBRD / 88970 ional Development and Moni Post Direct 16,600.00 0.00 Canceled 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 ant Selection 6 (Kaltim) toring ID-ATR/BPN-177843-CS-INDV Project Management, Institut Individual Consult / Public Awareness Specialist IBRD / 88970 ional Development and Moni Post Direct 16,600.00 0.00 Canceled 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 ant Selection 1 (Sumsel) toring ID-ATR/BPN-178143-CS-INDV Project Management, Institut Individual Consult / Public Awareness Specialist IBRD / 88970 ional Development and Moni Post Direct 16,600.00 0.00 Canceled 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 ant Selection 4 (Kalbar) toring ID-ATR/BPN-178148-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Direct 12,500.00 0.00 Canceled 2019-12-20 2019-08-01 2019-12-23 2019-12-24 2020-01-01 2020-12-31 / Graphic Designer ional Development and Moni ant Selection toring ID-ATR/BPN-178119-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Direct 37,250.00 0.00 Canceled 2019-12-20 2019-12-26 2019-12-28 2020-01-02 2020-12-31 / Legal Specialist ional Development and Moni ant Selection toring ID-ATR/BPN-263514-CS-INDV Project Management, Institut Individual Consult TF / A7044 Post Open 20,833.00 48,846.36 Signed 2018-10-01 2018-10-01 2018-11-19 2018-12-18 2018-11-26 2019-12-19 2018-12-31 2019-01-03 2019-12-31 / Financial Management Spec ional Development and Moni ant Selection ialist (TF) toring ID-ATR/BPN-263509-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 21,000.00 20,895.00 Signed 2019-12-20 2019-06-02 2020-01-15 2019-12-09 2020-01-20 2019-12-11 2020-02-08 2020-01-06 2020-12-30 / PCC Liaison Officer FY2020 ional Development and Moni ant Selection toring ID-ATR/BPN-263510-CS-INDV Project Management, Institut Individual Consult / Financial Management Assis IBRD / 88970 ional Development and Moni Post Open 21,000.00 65,119.20 Signed 2019-12-20 2019-12-20 2020-01-22 2020-01-22 2020-01-29 2020-01-23 2020-02-19 2020-01-27 2020-12-30 ant Selection tant FY2020 toring ID-ATR/BPN-263507-CS-INDV Project Management, Institut Individual Consult / Public Awareness Specialist IBRD / 88970 ional Development and Moni Post Open 16,600.00 40,296.75 Signed 2019-12-20 2019-07-01 2020-01-10 2020-01-10 2020-01-13 2020-01-10 2020-02-03 2020-01-27 2020-11-29 ant Selection South Kalimantan Province F toring Y2020 ID-ATR/BPN-263508-CS-INDV Project Management, Institut Individual Consult / Public Awareness Specialist IBRD / 88970 ional Development and Moni Post Open 16,600.00 26,131.05 Signed 2019-12-20 2019-07-01 2020-01-13 2019-10-24 2020-01-16 2019-10-25 2020-02-02 2020-01-06 2021-01-27 ant Selection Riau Province FY2020 toring ID-ATR/BPN-263348-CS-INDV Participatory Mapping and A Individual Consult / Project Management Assista IBRD / 88970 Post Open 21,000.00 13,887.72 Signed 2021-11-16 2021-11-16 2022-01-04 2022-01-04 2022-01-25 2022-01-06 2022-03-01 2022-01-31 2022-12-26 grarian Reform ant Selection nt PMU FY2022 (new hired) ID-ATR/BPN-263360-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 34,000.00 5,404.80 Signed 2019-12-01 2019-12-01 2020-01-03 2019-12-30 2020-01-10 2019-12-30 2020-01-31 2020-02-03 2020-07-29 / Program Officer FY2020 (5 ional Development and Moni ant Selection Persons) toring ID-ATR/BPN-263512-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 5,900.00 800.40 Signed 2020-01-15 2020-03-03 2020-02-14 2019-10-30 2020-02-19 2019-10-30 2020-03-09 2020-06-02 2020-12-31 / Access Reform Officer FY20 ional Development and Moni ant Selection 20 toring ID-ATR/BPN-272980-CS-INDV / Planning Consultant for Ren Participatory Mapping and A Individual Consult IBRD / 88970 Post Open 7,000.00 0.00 Canceled 2022-01-23 2022-02-25 2022-03-04 2022-03-25 2022-04-24 ovation Land office at Klaten grarian Reform ant Selection district - Central Java Provinc e FY 2022 ID-ATR/BPN-272982-CS-INDV / Monitoring Consultant for R Participatory Mapping and A Individual Consult IBRD / 88970 Post Open 7,000.00 0.00 Canceled 2022-02-06 2022-03-11 2022-03-18 2022-04-08 2022-10-05 enovation Land office at Klat grarian Reform ant Selection en district - Central Java Prov ince FY2022 ID-ATR/BPN-273171-CS-INDV Project Management, Institut / Feedback and Grievance Re Individual Consult IBRD / 88970 ional Development and Moni Post Open 16,600.00 8,004.00 Signed 2022-01-17 2022-04-07 2022-02-19 2022-06-30 2022-02-26 2022-06-30 2022-03-19 2022-07-06 2022-12-31 dress Mechanism (FGRM) Offi ant Selection toring cer FY2022 (new hire) ID-ATR/BPN-273172-CS-INDV Project Management, Institut Individual Consult Under Implement / Strategic Planner (Planning IBRD / 88970 ional Development and Moni Post Open 25,000.00 0.00 2022-01-24 2022-04-24 2022-02-26 2022-03-05 2022-03-26 2022-09-22 ant Selection ation Bureau) FY2022 toring ID-ATR/BPN-273173-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 16,600.00 13,581.96 Signed 2022-01-17 2022-01-06 2022-02-19 2022-01-27 2022-02-26 2022-01-28 2022-03-12 2022-02-14 2022-12-31 / Safeguard Officer/Assistant ional Development and Moni ant Selection toring ID-ATR/BPN-273174-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open 20,800.00 0.00 Canceled 2022-01-17 2022-02-19 2022-02-26 2022-03-19 2022-12-31 / Land Tenure (National) FY2 ional Development and Moni ant Selection 022 toring ID-ATR/BPN-273175-CS-INDV Project Management, Institut / Land data Expert Analysis F Individual Consult IBRD / 88970 ional Development and Moni Post Open 20,800.00 0.00 Canceled 2022-01-17 2022-02-19 2022-02-26 2022-03-19 2022-12-31 Y2022 for Strengthening the ant Selection toring Land Tenure Policy ID-ATR/BPN-273176-CS-INDV Project Management, Institut Individual Consult / Land and GIS Modeling FY2 IBRD / 88970 ional Development and Moni Post Open 20,800.00 0.00 Canceled 2022-01-17 2022-02-19 2022-02-26 2022-03-19 2022-12-31 ant Selection 022 for Strengthening the La toring nd Tenure Policy ID-ATR/BPN-273177-CS-INDV Project Management, Institut / 3 IC - Land data Analysis FY Individual Consult IBRD / 88970 ional Development and Moni Post Open 37,500.00 0.00 Canceled 2022-01-17 2022-02-19 2022-02-26 2022-03-19 2022-09-15 2022 for Strengthening the L ant Selection toring and Tenure Policy ID-ATR/BPN-273178-CS-INDV Project Management, Institut / Land Modeling Analysis FY2 Individual Consult IBRD / 88970 ional Development and Moni Post Open 4,200.00 0.00 Canceled 2022-01-17 2022-02-19 2022-02-26 2022-03-19 2022-12-31 022 for Strengthening the La ant Selection toring nd Tenure Policy ID-ATR/BPN-273179-CS-INDV Project Management, Institut / Communication Specialist F Individual Consult Pending Impleme IBRD / 88970 ional Development and Moni Post Open 15,000.00 0.00 2022-01-17 2022-02-19 2022-02-26 2022-03-19 2022-12-31 Y2022 for Strengthening the ant Selection ntation toring Communication policy ID-ATR/BPN-273180-CS-INDV Project Management, Institut / Information and Complaints Individual Consult Pending Impleme IBRD / 88970 ional Development and Moni Post Open 12,500.00 0.00 2022-01-17 2022-02-19 2022-02-26 2022-03-19 2022-12-31 Management FY2022 for Stre ant Selection ntation toring ngthening the Communicatio n policy Page 9 ID-ATR/BPN-273181-CS-INDV Project Management, Institut / Public Information and Advo Individual Consult Pending Impleme IBRD / 88970 ional Development and Moni Post Open 12,500.00 0.00 2022-01-17 2022-02-19 2022-02-26 2022-03-19 2022-12-31 cacy FY2022 for Strengtheni ant Selection ntation toring ng the Communication policy ID-ATR/BPN-273182-CS-INDV Project Management, Institut / Access Reform Officer for In Individual Consult Pending Impleme IBRD / 88970 ional Development and Moni Post Open 12,500.00 0.00 2022-01-17 2022-02-06 2022-02-13 2022-03-06 2022-12-18 digenous Laws FY2020 for St ant Selection ntation toring rengthening the Communicat ion policy ID-ATR/BPN-284410-CS-CDS Geospatial Data Infrastructu Individual Consult / 2D and 3D Cadastral Specia IBRD / 88970 re for Environmental and Na Post Direct 113,800.00 110,121.00 Signed 2022-04-01 2022-04-11 2022-04-11 2022-05-13 2022-05-02 2022-05-13 2022-06-06 2022-07-11 2022-12-03 ant Selection list for Smart Land Developm tural Resource Management ent ID-ATR/BPN-284428-CS-INDV Geospatial Data Infrastructu / System / Solution Tester (2 Individual Consult Under Implement IBRD / 88970 re for Environmental and Na Post Open 31,000.00 0.00 2022-06-01 2022-07-01 2022-07-20 2022-08-10 2022-09-14 2023-03-13 persons) supports for Smart ant Selection ation tural Resource Management Land Development ID-ATR/BPN-284409-CS-CDS Geospatial Data Infrastructu Individual Consult / Spatial Data Infrastructure IBRD / 88970 re for Environmental and Na Post Direct 113,800.00 110,121.00 Signed 2022-04-01 2022-04-11 2022-04-11 2022-05-13 2022-05-02 2022-05-13 2022-06-06 2022-07-11 2022-12-03 ant Selection Specialist for Smart Land De tural Resource Management velopment ID-ATR/BPN-284412-CS-CDS Geospatial Data Infrastructu Individual Consult / Land Administration System IBRD / 88970 re for Environmental and Na Post Direct 113,800.00 110,121.00 Signed 2022-04-01 2022-04-11 2022-04-11 2022-05-13 2022-05-02 2022-05-13 2022-06-06 2022-07-11 2022-12-03 ant Selection Specialist tural Resource Management ID-ATR/BPN-284418-CS-CDS Geospatial Data Infrastructu Individual Consult / System Architecture & Infra IBRD / 88970 re for Environmental and Na Post Direct 113,800.00 110,121.00 Signed 2022-04-01 2022-04-11 2022-04-11 2022-05-13 2022-05-02 2022-05-13 2022-06-06 2022-07-11 2022-12-03 ant Selection structure (Cloud) Designer S tural Resource Management pecialist Geospatial Data Infrastructu ID-ATR/BPN-284415-CS-CDS Individual Consult IBRD / 88970 re for Environmental and Na Post Direct 113,800.00 110,121.00 Signed 2022-04-01 2022-04-11 2022-04-11 2022-05-13 2022-05-02 2022-05-13 2022-06-06 2022-07-11 2022-12-03 / Business Analyst Specialist ant Selection tural Resource Management ID-ATR/BPN-284426-CS-INDV Geospatial Data Infrastructu / Spatial Planning / Cadastral Individual Consult Under Implement IBRD / 88970 re for Environmental and Na Post Open 10,400.00 0.00 2022-04-01 2022-07-01 2022-05-20 2022-06-10 2022-07-15 2023-01-11 Analyst support for Smart La ant Selection ation tural Resource Management nd Development ID-ATR/BPN-284457-CS-INDV Geospatial Data Infrastructu Individual Consult Under Implement / Technical Writer support to IBRD / 88970 re for Environmental and Na Post Open 15,500.00 0.00 2022-06-01 2022-07-01 2022-07-20 2022-08-10 2022-09-14 2023-03-13 ant Selection ation Smart Land Development tural Resource Management ID-ATR/BPN-284423-CS-INDV Geospatial Data Infrastructu Individual Consult Under Implement / Business Analyst supports t IBRD / 88970 re for Environmental and Na Post Open 20,700.00 0.00 2022-04-01 2022-07-01 2022-05-20 2022-06-10 2022-07-15 2023-01-11 ant Selection ation o Smart Land Development tural Resource Management ID-ATR/BPN-285755-CS-INDV Project Management, Institut / Land and GIS Modeling Exp Individual Consult IBRD / 88970 ional Development and Moni Post Open 13,700.00 13,800.00 Signed 2022-02-24 2022-03-17 2022-04-14 2022-05-13 2022-05-05 2022-05-13 2022-06-09 2022-05-13 2022-12-06 ert FY 2022 for Strengthenin ant Selection toring g the Land Tenure Policy ID-ATR/BPN-285760-CS-INDV Project Management, Institut / Land Modeling Analysis FY 2 Individual Consult IBRD / 88970 ional Development and Moni Post Open 8,200.00 5,244.00 Signed 2022-02-24 2022-03-17 2022-04-14 2022-05-17 2022-05-05 2022-05-17 2022-06-09 2022-05-17 2022-12-06 022 for Strengthening the La ant Selection toring nd Tenure Policy ID-ATR/BPN-285758-CS-INDV Project Management, Institut / 3 IC - Land Data Analysis FY Individual Consult IBRD / 88970 ional Development and Moni Post Open 24,800.00 16,961.49 Signed 2022-02-24 2022-03-17 2022-04-14 2022-05-13 2022-05-05 2022-05-13 2022-06-09 2022-06-06 2022-12-06 2022 for Strengthening the L ant Selection toring and Tenure Policy ID-ATR/BPN-285754-CS-INDV Project Management, Institut / Land Data Expert Analysis F Individual Consult IBRD / 88970 ional Development and Moni Post Open 13,700.00 13,452.00 Signed 2022-02-24 2022-03-17 2022-04-14 2022-05-13 2022-05-05 2022-05-13 2022-06-09 2022-05-13 2022-12-06 Y 2022 for Strengthening the ant Selection toring Land Tenure Policy ID-ATR/BPN-285756-CS-INDV Project Management, Institut / Land Tenure Expert (Nation Individual Consult IBRD / 88970 ional Development and Moni Post Open 13,700.00 13,800.00 Signed 2022-02-24 2022-03-17 2022-04-14 2022-05-13 2022-05-05 2022-05-12 2022-06-09 2022-05-13 2022-12-06 al) FY 2022 for Strengthening ant Selection toring the Land Tenure Policy ID-ATR/BPN-285759-CS-INDV Project Management, Institut / Land Tenure Expert (Interna Individual Consult IBRD / 88970 ional Development and Moni Post Open 68,900.00 36,674.00 Signed 2022-02-24 2022-03-17 2022-04-14 2022-07-01 2022-05-05 2022-07-01 2022-06-09 2022-07-04 2022-12-06 tional) FY 2022 for Strengthe ant Selection toring ning the Land Tenure Policy ID-ATR/BPN-285757-CS-INDV Project Management, Institut Individual Consult Under Implement / 3 IC - Land Law Expert FY 2 IBRD / 88970 ional Development and Moni Post Open 41,300.00 0.00 2022-02-24 2022-03-17 2022-04-14 2022-05-05 2022-06-09 2022-12-06 ant Selection ation 022 for Strengthening the La toring nd Tenure Policy ID-ATR/BPN-289867-CS-INDV Project Management, Institut Individual Consult / Public Awareness Specialist IBRD / 88970 ional Development and Moni Post Open 15,000.00 4,002.00 Signed 2022-01-01 2022-01-12 2022-02-19 2022-02-15 2022-03-12 2022-02-15 2022-04-16 2022-02-15 2022-10-13 ant Selection for West Jawa Province FY 20 toring 22 ID-ATR/BPN-301247-CS-INDV Project Management, Institut Individual Consult / Public Awareness Specialist IBRD / 88970 ional Development and Moni Post Open 15,500.00 12,346.90 Signed 2022-06-24 2022-01-02 2022-08-12 2022-02-17 2022-09-02 2022-02-16 2022-10-07 2022-03-01 2023-04-05 ant Selection for East Kalimantan FY 2022 toring ID-ATR/BPN-301253-CS-INDV Project Management, Institut Individual Consult / Public Awareness Specialist IBRD / 88970 ional Development and Moni Post Open 15,000.00 4,004.40 Signed 2022-02-01 2022-01-02 2022-03-22 2022-02-22 2022-04-12 2022-02-22 2022-05-17 2022-03-01 2022-11-13 ant Selection for Riau Province FY 2022 toring ID-ATR/BPN-301884-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Limited 5,000.00 2,003.10 Signed 2022-06-28 2021-03-03 2022-07-03 2021-04-13 2022-07-24 2021-05-28 2022-08-28 2021-06-02 2023-02-24 / Strategic Program Officer F ional Development and Moni ant Selection Y 2021 toring ID-ATR/BPN-301921-CS-INDV Project Management, Institut Individual Consult / Program Officer for Vice Min IBRD / 88970 ional Development and Moni Post Limited 15,000.00 3,739.12 Signed 2020-01-01 2020-01-01 2020-01-06 2020-01-30 2020-01-27 2020-01-30 2020-03-02 2020-10-01 2020-08-29 ant Selection ister FY2020 ( 3 person) toring ID-ATR/BPN-303272-CS-INDV / 5 (Five) Risk Management E xperts to Assist the Coordina Participatory Mapping and A Individual Consult Under Implement IBRD / 88970 Post Direct 57,000.00 0.00 2022-07-18 2022-07-18 2022-07-28 2022-08-18 2022-09-22 2023-03-21 tor According to The Scope a grarian Reform ant Selection ation s Assign and Responsible the Assignment as Given (TOR) Page 10 ID-ATR/BPN-303278-CS-INDV / Risk Management Coordinat Participatory Mapping and A Individual Consult Under Implement or as a Supervisor and qualit IBRD / 88970 Post Direct 14,000.00 0.00 2022-07-18 2022-07-18 2022-07-28 2022-08-18 2022-09-22 2023-03-21 grarian Reform ant Selection ation y Assurance for the activities of other risk management ex perts ID-ATR/BPN-305196-CS-INDV Project Management, Institut Individual Consult / Financial Management Assis IBRD / 88970 ional Development and Moni Post Open - National 21,000.00 8,323.75 Signed 2019-12-20 2019-07-01 2020-02-07 2019-07-12 2020-02-28 2019-07-12 2020-04-03 2019-08-01 2020-09-30 ant Selection tant FY 2019 toring ID-ATR/BPN-305194-CS-INDV Project Management, Institut Individual Consult IBRD / 88970 Post Open - National 33,100.00 7,990.80 Signed 2019-12-20 2019-07-23 2020-02-07 2019-08-15 2020-02-28 2019-08-15 2020-04-03 2019-10-01 2020-09-30 / PCC Liaison Adviser FY 201 ional Development and Moni ant Selection 9 toring ID-ATR/BPN-305187-CS-INDV Project Management, Institut Individual Consult / Monitoring and Evaluation C IBRD / 88970 ional Development and Moni Post Open - National 28,200.00 26,405.28 Signed 2019-12-20 2019-12-20 2020-02-07 2019-03-08 2020-02-28 2019-03-08 2020-04-03 2020-01-03 2020-09-30 ant Selection onsultant FY 2019 toring ID-ATR/BPN-305184-CS-INDV Project Management, Institut Individual Consult / Financial Management Spec IBRD / 88970 ional Development and Moni Post Open - National 37,250.00 16,780.68 Signed 2019-12-20 2019-12-20 2020-02-07 2020-01-20 2020-02-28 2020-01-20 2020-04-03 2020-01-27 2020-09-30 ant Selection ialist PMU FY 2019 toring Page 11