The World Bank Implementation Status & Results Report Dhaka City Neighborhood Upgrading Project (P165477) Dhaka City Neighborhood Upgrading Project (P165477) SOUTH ASIA | Bangladesh | Urban, Resilience and Land Global Practice | IBRD/IDA | Investment Project Financing | FY 2019 | Seq No: 7 | ARCHIVED on 20-Jun-2022 | ISR51900 | Implementing Agencies: Dhaka South City Corporation, People’s Republic of Bangladesh Key Dates Key Project Dates Bank Approval Date: 29-Mar-2019 Effectiveness Date: 01-Jul-2019 Planned Mid Term Review Date: 05-Sep-2022 Actual Mid-Term Review Date: Original Closing Date: 30-Jun-2024 Revised Closing Date: 30-Jun-2024 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) To enhance public spaces and improve urban services in selected neighborhoods in Dhaka. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Public space enhancements:(Cost $97.30 M) Place management, urban planning and project implementation support:(Cost $8.70 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Unsatisfactory Moderately Unsatisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions There has been significant progress in the preparation of sub-project appraisal reports and detailed engineering designs. The PIU plans to advertise the Invitation for Bids for 12 sub-projects by April 2022. Risks 6/20/2022 Page 1 of 6 The World Bank Implementation Status & Results Report Dhaka City Neighborhood Upgrading Project (P165477) Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance High High High Macroeconomic Moderate Moderate Moderate Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Moderate Moderate Moderate Institutional Capacity for Implementation and Substantial Substantial Substantial Sustainability Fiduciary High High High Environment and Social Substantial Substantial Substantial Stakeholders Substantial Substantial Substantial Other -- -- -- Overall Substantial Substantial Substantial Results PDO Indicators by Objectives / Outcomes Enhanced public spaces in selected neighborhoods in Dhaka IN01154663 ►Percentage increase in the number of people accessing enhanced public spaces (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 Date 30-Jun-2019 28-Feb-2022 28-Feb-2022 30-Jun-2024 No sub-projects have yet been completed. Based on the 13 appraised sub-projects, the 20% increase is Comments: attainable. IN01154665 Percentage increase in the number of women accessing enhanced public spaces (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 Date 30-Jun-2019 28-Feb-2022 28-Feb-2022 30-Jun-2024 Improved urban services in selected neighborhoods in Dhaka IN01154664 ►People provided with improved urban living conditions (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target 6/20/2022 Page 2 of 6 The World Bank Implementation Status & Results Report Dhaka City Neighborhood Upgrading Project (P165477) Value 0.00 0.00 0.00 1,000,000.00 Date 30-Jun-2019 28-Feb-2022 28-Feb-2022 30-Jun-2024 No sub-projects have yet been completed. The estimated population that will benefit from the 13 Comments: appraised sub-projects is 1.2 million people. IN01154846 People provided with improved urban living conditions - Female (RMS requirement) (Number, Corporate Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 500,000.00 Intermediate Results Indicators by Components Public space enhancements IN01154847 ►Total area of public spaces improved (Hectare(Ha), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 30.00 Date 30-Jun-2019 28-Feb-2022 28-Feb-2022 30-Jun-2024 Due to the pandemic and lockdown in the country, progress to date is behind the planned implementation Comments: schedule no update at this stage. IN01154849 ►Number of people consulted under participatory sessions for subproject design and implementation (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 2,118.00 1,200.00 Date 30-Jun-2019 28-Feb-2022 28-Feb-2022 30-Jun-2024 More than 2,000 people have been consulted under the participatory design process for subproject design Comments: and implemenation. IN01154850 ►Percentage of citizens in selected neighborhoods who consider that their views have been taken into account in the subproject designs (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 35.00 60.00 Date 30-Jun-2019 28-Feb-2022 28-Feb-2022 30-Jun-2024 While the project is making progress to reaching the end target of 60%, the PIU has been advised to raise Comments: its efforts to ensure more citizens feel that their views are considered in the subproject designs. IN01154851 6/20/2022 Page 3 of 6 The World Bank Implementation Status & Results Report Dhaka City Neighborhood Upgrading Project (P165477) Percentage of women in selected neighborhoods who consider that their views have been taken into account in the subproject designs (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 20.00 60.00 Date 30-Jun-2019 28-Feb-2022 28-Feb-2022 30-Jun-2024 IN01154852 ►Percentage of women who report feeling safe in public spaces in the selected neighborhood locations (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 60.00 Date 30-Jun-2019 28-Feb-2022 28-Feb-2022 30-Jun-2024 No results yet to be reported. Comments: IN01154853 ►Roads rehablitated (Kilometers, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 30.00 Date 30-Jun-2019 28-Feb-2022 28-Feb-2022 30-Jun-2024 No sub-projects have been completed yet. Road sub-projects appraised to date target 8 kilometers for Comments: improvement. IN01154854 ►Number of intersection management strategies developed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 5.00 Date 30-Jun-2019 23-Sep-2021 23-Sep-2021 30-Jun-2024 No results yet to be reported. Outputs are to be produced in June 2022 by the consulting firm conducting Comments: the Traffic Study. Place management, urban planning and project implementation support IN01154848 ►Share of improved public spaces with approved plans for operation, management, programming and community outreach (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 100.00 Date 02-Jul-2018 28-Feb-2022 28-Feb-2022 30-Jun-2024 No results yet to be reported. Outputs will be produced by the Asset Management consulting firm to be Comments: engaged by the PIU. 6/20/2022 Page 4 of 6 The World Bank Implementation Status & Results Report Dhaka City Neighborhood Upgrading Project (P165477) Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P165477 IDA-63610 Effective USD 100.50 100.50 0.00 12.85 85.46 13% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P165477 IDA-63610 Effective 29-Mar-2019 29-May-2019 01-Jul-2019 30-Jun-2024 30-Jun-2024 Cumulative Disbursements 6/20/2022 Page 5 of 6 The World Bank Implementation Status & Results Report Dhaka City Neighborhood Upgrading Project (P165477) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 6/20/2022 Page 6 of 6