SUMMARY O F PROCUREMENT PLAN Project Preparation Advancement (PPA) Project information: Harmonizing and Improving Statistics in West Africa Project -P169265 Project Implementation agency: Liberia Institute of Statistics and Geo- Information Services (LISGIS) Date of the Procurement Plan: February 3, 2020 Period covered by this Procurement Plan: 3rd February to 31st July 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 1, 2016), revised in November 2017, and August 2018 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement and Concessions Act, 2010 of the Republic of Liberia, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable for those contracts identified in the Procurement Plan tables; Works: Not Applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. Other Relevant Procurement Information: - (a). Prior Procurement Arrangements: The Procurement Arrangements as indicated in the below table and within the thresholds indicated in the below tables will be used. The thresholds for the Bank’s prior review requirements are also provided in the table below: Table: Thresholds*, Procurement Arrangements, and Prior Review (The table below depicts the Thresholds and Procurement Methods to be used under the Regional Project for Statistics Thresholds*, Procurement Methods, and Prior Review Contract (C) Value Expenditure Procurement Contracts Subject to No Threshold* [eq. Category Method Prior Review /[eq. US$] USD] All contracts at or above USD Open Competition 5,000,000 are subject to International Market 1 Works C ≥ 5,000,000 Approach and Direct international advertising and the use of the Bank’s SPDs (or other Contracting documents agreed with the Contract (C) Value Expenditure Procurement Contracts Subject to No Threshold* [eq. Category Method Prior Review /[eq. US$] USD] Bank). Open Competition National Market 200,000 < C < 5,000,000 None Approach C ≤ 200,000 RfQ None All contracts at or above USD Open Competition 500,000 are subject to International Market international advertising and the C ≥ 500,000 Approach and Direct use of the Bank’s SPDs (or other Goods, IT and Contracting documents agreed with the 2 non-consulting Bank). services Open Competition 100,000 < C < 500,000 National Market None Approach C ≤ 100,000 RfQ None All contracts at or above USD 100,000 are subject to for international advertising and the C < 100,000 Consulting Services use of the Bank’s SPDs (or other National documents agreed with the shortlist for Bank). 3 selection of All contracts at or above USD consultant firms for 200,000 are subject to Engineering and international advertising and the C ≤ 200,000 Construction use of the Bank’s SPDs (or other Supervision documents agreed with the Bank). Selection of All values ≥ 100,000 4 Individual All Approaches consultants Training, This line activity is not subject to Workshops, Based on approved Procurement Review However, 5 Study Tours All Values Annual Work Plan & each of the activities will be Budgets (AWPB) by TTL cleared with the TTL prior to its implementation. (Special procurement arrangements like direct contracting, use of SOEs, UN Agencies, third party monitors, local NGOs, Force Account, servants needs, results based arrangements. It is not expected that there will be need for prequalification in the procurement arrangements under this Regional Project *These thresholds are for the purposes of the initial procurement plan for the PPA and for first 18 months. The thresholds will be revised periodically based on re- assessment of risks. All contracts not subject to prior review will be post-reviewed. Prequalification. Not expected for the packages of works/goods packages in the procurement plan. Proposed Procedures for CDD Components: Not Applicable Reference to (if any) Project Operational/Procurement Manual: The LISGIS Project Management Team will prepare Procurement manuals. The Procurement Plan will also form part of the Project Implementation Manual. Any Other Special Procurement Arrangements: None Procurement Packages/PLAN with Procurement Arrangements and Time Schedule: as per the Table below: b) PROCUREMENT PLAN Works There are no works under the Project Preparation Advance Goods and Non-Consulting Services 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procurement Prequ Nation Revie Expecte Expecte Comment No. (Description) Cost Method alifica al w d bid d s US$ tion Prefer by opening Contrac (yes/n ence Bank date t o) (yes/n (Prior Signatu o) / Post) re Date 1 Procurement of 4 12,100 laptops, 3 No. all- in-1 printers, Limited, RFQ No No Post 28 Feb 4 Mar office desks, a 20 20 projector, metal filing cabinet, and stationery and supplies for project management Consultancy Services 1 2 3 4 5 6 7 8 9 Ref. Description of Estimate Selection Review Expecte Expected Expected Comments No. Assignment d Method/ by Bank d date Contract Completi Cost in Arrangem (Prior / of Signatur on US$ ent Post) proposal e Date submissi Date on 1. Recruitment of a Consultant to draft and validate 10,000 INDV Post 16 Mar 10 Apr 23 Apr ToR to be curricula of the 20 20 20 submitted to IDA Statistics degree & for Review and No CEST Program at Objection. the UL 2. Recruitment of a ToR, performance Financial evaluation, draft Management contract and Officer for Project DS Prior 10 Feb 21 Feb 31 Aug minutes of Management 20 20 20 contract negotiation to be submitted to IDA for Review and No 15,600 Objection. 3. ToR, performance evaluation, draft Recruitment of a contract and Procurement DS Prior 10 Feb 21 Feb 31 Aug minutes of Specialist for 20 20 20 contract Project 18,000 negotiation to be Management submitted to IDA for Review and No Objection. Training and Workshop (Training & Workshop activities are subject to TTL clearance). Estimat Estimated Expected Ref. Training, workshop and ed Cost Duration Training/workshop No. study tours in (Days) Date (US$) Conduct of validation 54,000 workshop and TOT for the GP Feb. 20 to March 1. on the design of 13 2020 questionnaires and enumeration training manual Workshop for cartographic 150,000 Feb. 24 to March 2. field staff training 16 2020 Workshop for enumeration 113,900 3. mapping training April 15, 2020 Study Tours to regional 32,000 countries for first-hand experience on regional March to April 4. harmonization of data 2020 collection, management and communication Workshops on current 50,000 administrative data across 5. April to July 2020 MACs and LISGIS regional offices Workshop to strengthen and 35,000 6. develop institutional capacity April to July 2020 of NSO Workshops for steering 40,000 7. committee on Administrative April to July 2020 Data Workshop for Project 10,000 Steering/Technical 8. Committees for annual work February 2020 plan preparation, review and validation GENERAL NOTES 1. Training and capacity building: Training workshops (including training material and support), conference attendance and study tours, will be carried out based on approved annual training and allied activities plan by the TTL. The beneficiaries, after the training, will be requested to submit a brief report indicating what skills have been acquired and how these skills will contribute to enhance their performance and contribute to the attainment of the Project’s development objective. 2. Operational Costs: These are expenditures incurred by the Recipient to finance: (i) communication technology (including, without limitation, internet and telephone; (ii) per diem and travel expenses of the operational staff performing their responsibilities under the Project; (iii) fuel and vehicle maintenance; (iv) maintenance of equipment; (v) photocopies and publications; (viii) bank commissions; and (ix) utilities and office supplies as defined in the FA. Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Western and Central Africa : Harmonizing and Improving Statistics in West Africa PLAN General Information Country: Western and Central Africa 2020-09-01 Bank’s Approval Date of the Original Procurement Plan: 2022-08-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169265 GPN Date: 2021-05-19 Project Name: Harmonizing and Improving Statistics in West Africa Loan / Credit No: IDA / 65740 Unidade de Gestao de Projectos Especiais Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Regional component: Harmo 06/UGPE/HISWA/2021 / Purc nization, Data Collection, Qu hase of ICT Equipment’s for t Open - Internationa Single Stage - One E Under Imple IDA / 65740 ality Improvement, Dissemin Post Request for Bids 300,000.00 0.00 2021-08-01 2022-06-30 2021-08-06 2022-06-30 2021-09-17 2021-10-17 2021-11-21 2022-05-20 he National Statistical Syste l nvelope mentation ation and Use of Core Social m (NSS) and Economic Statistics Regional component: Harmo 05/UGPE/HISWA/2021 / Purc nization, Data Collection, Qu Open - Internationa Single Stage - One E Pending Impl hase of Equipment for Health IDA / 65740 ality Improvement, Dissemin Post Request for Bids 200,000.00 0.00 2021-08-15 2021-08-20 2021-10-01 2021-10-31 2021-12-05 2022-06-03 l nvelope ementation Infrastructure ation and Use of Core Social and Economic Statistics Regional component: Harmo 08/UGPE/HISWA/2021 / Purc nization, Data Collection, Qu Single Stage - One E Under Imple hase of equipment (Electroni IDA / 65740 ality Improvement, Dissemin Post Request for Bids Open - National 140,000.00 0.00 2021-09-13 2022-04-05 2021-09-18 2021-10-30 2022-05-23 2021-11-29 2022-06-27 2022-01-03 2022-07-02 nvelope mentation c System Infrastructure) ation and Use of Core Social and Economic Statistics Regional component: Harmo 09/UGPE/HISWA/2021 / Purc nization, Data Collection, Qu Request for Quota Single Stage - One E hase of ICT Equipment’s for I IDA / 65740 ality Improvement, Dissemin Post Limited 90,000.00 46,866.50 Signed 2021-09-08 2021-09-13 2021-11-03 2021-12-13 2022-05-02 tions nvelope Mar ation and Use of Core Social and Economic Statistics Regional component: Harmo 20/UGPE/HISWA/2022 / Purc nization, Data Collection, Qu hase of weight balance for IV Request for Quota Single Stage - One E Pending Impl IDA / 65740 ality Improvement, Dissemin Post Open - National 9,500.00 0.00 2022-08-02 2022-09-27 2023-03-26 Household Expenditure and I tions nvelope ementation ation and Use of Core Social ncome Survey and Economic Statistics Regional component: Harmo 037/UGPE/HISWA/2022 / Acq nization, Data Collection, Qu Request for Quota Single Stage - One E Pending Impl uisition of covid-19 kit for fiel IDA / 65740 ality Improvement, Dissemin Post Open - National 27,000.00 0.00 2022-08-22 2022-10-17 2023-04-15 tions nvelope ementation d agents ation and Use of Core Social and Economic Statistics Regional component: Harmo 038/UGPE/HISWA/2022 / Pur nization, Data Collection, Qu chase of ICT Equipment’s for Request for Quota Single Stage - One E Pending Impl IDA / 65740 ality Improvement, Dissemin Post Open - National 70,000.00 0.00 2022-08-29 2022-10-24 2023-04-22 Completion of the Mindelo La tions nvelope ementation ation and Use of Core Social nd Registry Operation and Economic Statistics NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Regional component: Harmo 12/UGPE/HISWA/2021 / Com nization, Data Collection, Qu Request for Quota Single Stage - One E Pending Impl munication/divulgation electr IDA / 65740 ality Improvement, Dissemin Post Limited 25,000.00 0.00 2021-09-13 2021-11-08 2022-05-07 tions nvelope ementation onic billing System ation and Use of Core Social and Economic Statistics 13/UGPE/HISWA/2021 / PRO Regional component: Harmo DUCTION OF AUDIOVISUAL A nization, Data Collection, Qu Request for Quota Single Stage - One E Pending Impl ND COMMUNICATION MATERI IDA / 65740 ality Improvement, Dissemin Post Limited 30,000.00 0.00 2021-11-13 2022-01-08 2022-07-07 tions nvelope ementation ALS FOR THE V GENERAL FIS ation and Use of Core Social HERIES CENSUS and Economic Statistics Regional component: Harmo 16/UGPE/HISWA/2021 / Grap nization, Data Collection, Qu hic Materials, Audiovisuals an Request for Quota Single Stage - One E IDA / 65740 ality Improvement, Dissemin Post Limited 30,000.00 10,791.14 Signed 2022-01-16 2022-01-07 2022-03-13 2022-01-31 2022-09-09 d Clothing for the General Sp tions nvelope ation and Use of Core Social orts Census and Economic Statistics Regional component: Harmo 018/UGPE/HISWA/2022 / Pro nization, Data Collection, Qu duction of Audiovisuals Mater Request for Quota Single Stage - One E Pending Impl IDA / 65740 ality Improvement, Dissemin Post Limited 10,000.00 0.00 2022-08-31 2022-10-26 2023-04-24 ials for IV Household Expendi tions nvelope ementation ation and Use of Core Social ture and Income Survey and Economic Statistics 19/UGPE/HISWA/2022 / Prod Regional component: Harmo uction of graphic materials, c nization, Data Collection, Qu Request for Quota Single Stage - One E Pending Impl lothing and gifts for IV House IDA / 65740 ality Improvement, Dissemin Post Limited 100,000.00 0.00 2022-09-04 2022-10-30 2023-04-28 tions nvelope ementation hold Expenditure and Income ation and Use of Core Social Survey and Economic Statistics Regional component: Harmo 22/UGPE/HISWA/2022 / Printi nization, Data Collection, Qu ng service for IV Household E Request for Quota Single Stage - One E Pending Impl IDA / 65740 ality Improvement, Dissemin Post Limited 28,000.00 0.00 2022-09-04 2022-10-30 2023-04-28 xpenditure and Income Surve tions nvelope ementation ation and Use of Core Social y and Economic Statistics Page 1 23/UGPE/HISWA/2022 / Grap hic Materials, Audiovisuals, S Regional component: Harmo pot and Clothing for i) livesto nization, Data Collection, Qu Request for Quota Single Stage - One E Pending Impl ck survey, ii) National Survey IDA / 65740 ality Improvement, Dissemin Post Limited 40,000.00 0.00 2022-08-03 2022-09-28 2023-03-27 tions nvelope ementation on Food and Nutritional Vuln ation and Use of Core Social erability, iii) Annual survey o and Economic Statistics n non-irrigated crops and iv) Irrigated Crops Survey Regional component: Harmo 029/UGPE/HISWA/2022 / Gra nization, Data Collection, Qu phic Materials, Audiovisuals, Request for Quota Single Stage - One E Pending Impl IDA / 65740 ality Improvement, Dissemin Post Limited 10,000.00 0.00 2022-08-05 2022-09-30 2023-03-29 spot and Clothing for dissemi tions nvelope ementation ation and Use of Core Social nation census data and Economic Statistics Regional component: Harmo 036/UGPE/HISWA/2022 / Diff nization, Data Collection, Qu usion of spot for IV Househol Request for Quota Single Stage - One E Pending Impl IDA / 65740 ality Improvement, Dissemin Post Limited 25,000.00 0.00 2022-08-22 2022-10-17 2023-04-15 d Expenditure and Income Su tions nvelope ementation ation and Use of Core Social rvey and Economic Statistics CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Regional component: Harmo 04/UGPE/HISWA/2021 / Stre nization, Data Collection, Qu ngthening of Health Informati Quality And Cost- Open - Internationa IDA / 65740 ality Improvement, Dissemin Post 300,000.00 0.00 Canceled 2021-07-15 2021-09-29 2021-08-05 2021-10-20 2021-09-18 2022-03-01 2021-10-16 2022-04-12 2021-11-15 2021-12-20 2022-01-24 2023-01-24 on Systems and Electronic Pr Based Selection l ation and Use of Core Social escription and Economic Statistics 07/UGPE/HISWA/2021 / Draft Country-Specific Component Consultant Qualifi Pending Impleme ing and implementation of th IDA / 65740 : Improving and modernizing Post Open - National 50,000.00 0.00 2021-07-30 2021-08-20 2021-10-03 2021-11-02 2021-12-07 2022-06-05 cation Selection ntation e ICT Plan 2021-2025 physical and statistical infra structure 03/UGPE/HISWA/2021 / Deve Regional component: Harmo lopment of the single technol nization, Data Collection, Qu Quality And Cost- Open - Internationa Pending Impleme ogical platform of consolidat IDA / 65740 ality Improvement, Dissemin Post 250,000.00 0.00 2021-07-30 2021-08-20 2021-10-03 2021-10-31 2021-11-30 2022-01-04 2022-02-08 2023-02-08 Based Selection l ntation ed indicators of the National ation and Use of Core Social Statistical System(NSS) and Economic Statistics Regional component: Harmo 02/UGPE/HISWA/2021 / Impl nization, Data Collection, Qu Consultant Qualifi Pending Impleme ementation of the MASTERD IDA / 65740 ality Improvement, Dissemin Post Open - National 60,000.00 0.00 2021-08-31 2021-09-21 2021-11-04 2021-12-04 2022-01-08 2022-07-07 cation Selection ntation ATA-INE platform ation and Use of Core Social and Economic Statistics 15/UGPE/HISWA/2021 / Acco unting and Financing audit D evelopment of Financial and Accounting Audits for the DIG Project Management and Mo Least Cost Selecti Open - Internationa Under Implement ITAL CABO VERDE PROJECT (I IDA / 65740 Post 45,000.00 0.00 2021-03-24 2021-04-01 2021-04-14 2021-05-28 2021-06-25 2021-07-25 2021-08-29 2021-10-03 2022-04-01 nitoring and Evaluation on l ation DA CREDITS Ref. V3050 and 6792-CV) and HARMONINZIN G AND IMPROVING STATISTIC S IN WEST AFRICA PROJECT (I DA CREDIT Ref. 6574-CV) Regional component: Harmo nization, Data Collection, Qu 032UGPE/HISWA/2022 / Trai Consultant Qualifi Pending Impleme IDA / 65740 ality Improvement, Dissemin Post Open - National 15,000.00 0.00 2022-08-30 2022-09-20 2022-11-03 2022-12-03 2023-01-07 2023-07-06 ning in English for NSS cation Selection ntation ation and Use of Core Social and Economic Statistics Regional component: Harmo nization, Data Collection, Qu 033/UGPE/HISWA/202 / Train Consultant Qualifi Pending Impleme IDA / 65740 ality Improvement, Dissemin Post Open - National 10,000.00 0.00 2022-08-10 2022-08-31 2022-10-14 2022-11-13 2022-12-18 2023-06-16 ing in French for NSS cation Selection ntation ation and Use of Core Social and Economic Statistics INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 01 UGPE HISWA 2020 / Recr Project Management and Mo Individual Consult IDA / 65740 Post Open 156,655.00 0.00 Canceled 2020-09-02 2020-09-01 2020-10-21 2020-11-20 2020-11-11 2020-12-16 2021-06-14 uitment of Project Manager nitoring and Evaluation ant Selection 01 UGPE HISWA 2021 / Recr Project Management and Mo Individual Consult IDA / 65740 Post Open 156,655.00 64,911.83 Signed 2021-01-08 2021-01-26 2021-02-26 2021-04-07 2021-03-19 2021-04-13 2021-04-23 2021-04-15 2021-10-20 uitment of Project Manager nitoring and Evaluation ant Selection 10/UGPE/HISWA/2021 / Prom Regional component: Harmo otion for Efficient use of Adm nization, Data Collection, Qu Individual Consult Pending Impleme inistrative Records and Capa IDA / 65740 ality Improvement, Dissemin Post Open 100,000.00 0.00 2021-09-04 2021-10-23 2021-11-13 2021-12-18 2022-06-16 ant Selection ntation city Building Sessions on Ad ation and Use of Core Social ministrative Records and Economic Statistics Regional component: Harmo 11/UGPE/HISWA/2021 / Tech nization, Data Collection, Qu nical support to Strengthenin Individual Consult Pending Impleme IDA / 65740 ality Improvement, Dissemin Post Open 30,000.00 0.00 2021-09-03 2021-10-22 2021-11-12 2021-12-17 2022-06-15 g Quality Management Syste ant Selection ntation ation and Use of Core Social m and Economic Statistics Regional component: Harmo 14/UGPE/HISWA/2021 / Impr nization, Data Collection, Qu Under Implement ovement of the "Happiness I IDA / 65740 ality Improvement, Dissemin Post Direct Selection Direct 90,000.00 0.00 2022-02-04 2022-02-04 2022-02-14 2022-02-18 2022-04-20 2022-10-17 ation nvoice" Raffle Platform ation and Use of Core Social and Economic Statistics Regional component: Harmo 017/UGPE/HISWA/2022 / Tec nization, Data Collection, Qu hnical support to Strengtheni Individual Consult Pending Impleme IDA / 65740 ality Improvement, Dissemin Post Open - National 30,000.00 0.00 2022-08-30 2022-10-18 2022-11-08 2022-12-13 2023-06-11 ng Quality Management Syst ant Selection ntation ation and Use of Core Social em and Economic Statistics Regional component: Harmo 21/UGPE/HISWA/2022 / Recr nization, Data Collection, Qu uitment of two graduate tech Individual Consult Pending Impleme IDA / 65740 ality Improvement, Dissemin Post Open - National 51,000.00 0.00 2022-07-26 2022-09-13 2022-10-04 2022-11-08 2023-05-07 nicians for IV Household Exp ant Selection ntation ation and Use of Core Social enditure and Income Survey and Economic Statistics Page 2 Regional component: Harmo 028/UGPE/UGPE/2022 / Recr nization, Data Collection, Qu uitment of a Developer/Progr Individual Consult Pending Impleme IDA / 65740 ality Improvement, Dissemin Post Open - National 50,000.00 0.00 2022-07-31 2022-09-18 2022-10-09 2022-11-13 2023-05-12 ammer to Update the Survey ant Selection ntation ation and Use of Core Social Management System and Economic Statistics Regional component: Harmo 030/UGPE/HISWA/2022 / Trai nization, Data Collection, Qu Individual Consult Open - Internationa Pending Impleme ning in Statistical Software - IDA / 65740 ality Improvement, Dissemin Post 14,000.00 0.00 2022-07-31 2022-09-18 2022-10-09 2022-11-13 2023-05-12 ant Selection l ntation STATA for NSS ation and Use of Core Social and Economic Statistics Regional component: Harmo 31/UGPE/HISWA/2022 / Train nization, Data Collection, Qu Individual Consult Pending Impleme ing in Statistical Software (SP IDA / 65740 ality Improvement, Dissemin Post Open - National 10,000.00 0.00 2022-08-30 2022-10-18 2022-11-08 2022-12-13 2023-06-11 ant Selection ntation SS) for NSS ation and Use of Core Social and Economic Statistics Regional component: Harmo nization, Data Collection, Qu 034/UGPE/HISWA/2022 / Trai Individual Consult Pending Impleme IDA / 65740 ality Improvement, Dissemin Post Open - National 7,000.00 0.00 2022-08-30 2022-10-18 2022-11-08 2022-12-13 2023-06-11 ning in Sampling for NSS ant Selection ntation ation and Use of Core Social and Economic Statistics Regional component: Harmo 035/UGPE/HISWA/2022 / Trai nization, Data Collection, Qu Individual Consult Pending Impleme ning in advanced excel traini IDA / 65740 ality Improvement, Dissemin Post Open - National 7,000.00 0.00 2022-07-29 2022-09-16 2022-10-07 2022-11-11 2023-05-10 ant Selection ntation ng for NSS ation and Use of Core Social and Economic Statistics Page 3