12 MONTHS PROCUREMENT PLAN Project information: P163782 - Integrated Water Management and Development Project Project Implementation agency: National Water And Sewerage Corporation AND Ministry of Water and Environment Date of the Procurement Plan: July 2018 Period covered by this Procurement Plan: One year Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, recvised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: Paragraph 5.3 of the Procurement Regulations will not apply. When approaching the national market, the country’s own procurement procedures shall not be used due to restrictions on eligibility of otherwise eligible firms to participate in NCB. The Regulations will apply. However, the Borrower may use its own procurement arrangements as set forth in the Public Procurement and Disposal Act, 2003 Request for Quotation such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods : Applicable for those contracts identified in the Procurement Plan tables Works: applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information:- (a). Prior Procurement Arrangements: The Procurement Arrangements as indicated in the below table and within the thresholds indicated in the below tables will be used. The thresholds for the Bank’s prior review requirements are also provided in the table below: Table: Thresholds*, Procurement Arrangements, and Prior Review (The table below depicts the Thresholds and Procurement Methods to be used under the IWMDP ): Thresholds*, Procurement Methods, and Prior Review Contract (C) Expenditure Value Procurement Contracts Subject to No Category Threshold* Method Prior Review /[eq. US$] [eq. USD] All contracts at or above USD 10 million are Open Competition subject to international advertising and the International Market use of the Bank’s SPDs (or other C ≥ 10,000,000 Approach and Direct documents agreed with the Bank), as well Contracting as the first contract under Open Competition 1 Works Open Competition 200,000 < C < National Market None except if it is the first contract under 10,000,000 Approach Open Competition. C ≤ 200,000 RfQ None All contracts at or above USD 2 million are Open Competition subject to international advertising and the Goods, IT and International Market use of the Bank’s SPDs (or other 2 non-consulting C ≥ 2,000,000 Approach and Direct documents agreed with the Bank), as well services as the first contract under Open Contracting Competition. Contract (C) Expenditure Value Procurement Contracts Subject to No Category Threshold* Method Prior Review /[eq. US$] [eq. USD] Open Competition : National Market None except if it is the first contract under 100,000 < C < Approach Open Competition. 2,000,000 C ≤ 100,000 RfQ None All contracts at or above USD 300,000 are for subject to international advertising and the C < 300,000 Consulting Services use of the Bank’s SPDs (or other selection of documents agreed with the Bank). 3 consultant firms All contracts at or above USD 300,000 are For Engineering and subject to international advertising and the C ≤ 300,000 Construction Supervision use of the Bank’s SPDs (or other documents agreed with the Bank). Selection of ≥ 300,000 ≥ 300,000 4 Individual All Approaches consultants Training, Workshops, Based on approved This line activity is not subject to 5 Study Tours All Values Annual Work Plan & procurement Review. Budgets (AWPB) by TTL * All contracts not subject to prior review will be post-reviewed. ** Short lists of consultants for services estimated to cost less US$300,000 equivalent per contract may be composed entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. However, if foreign firms have expressed interest, they will not be excluded from consideration. Prior review Thresholds High Substantial Procurement Type Risk Risk Works 5.0 10.0 Goods, It & Non-Consulting 1.5 2.0 Services Consultants (Firms) 0.5 1.0 Individual Consultants 0.2 0.3 Prequalification. Not expected for any works or goods packages in the procurement plan. Proposed Procedures for CDD Components: Applicable Reference to (if any) Project Operational/Procurement Manual: the IWMDP team will prepare a Procurement manuals, which will also be part of the Project Implementation Manual. Any Other Special Procurement Arrangements: None Procurement Packages/PLAN with Procurement Arrangements and Time Schedule: as per the Table below: Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Uganda : Integrated Water Management and Development Project PLAN General Information Country: Uganda 2018-07-10 Bank’s Approval Date of the Original Procurement Plan: 2022-08-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163782 GPN Date: 2018-05-31 Project Name: Integrated Water Management and Development Project Loan / Credit No: IDA / 62760, / Ministry of Water and Environment Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned UG-MWE-65387-CW-RFB / W orks for Construction of Busia Component 1: WSS in Small Municipality Water Supply an Towns and RGCs and Suppor Open - Internationa Single Stage - One E 10,366,641.0 9,605,671.7 2021-04-3 IDA / 62760 Prior Request for Bids Signed 2018-10-15 2020-02-29 2018-11-15 2020-07-10 2018-12-27 2020-09-07 2019-02-15 2021-01-04 2019-04-30 2021-02-09 d Sanitation/Facilities System t to Districts Hosting Refuge l nvelope 0 7 0 , Source Protection Measures es and Sanitation Facilities in Ku mi-Nyero-Ngora UG-MWE-107851-CW-RFB / Construction of 12 monitorin Component 3: Water Resour Single Stage - One E Under Imple 2019-11-0 g stations (5No. Ground Wat IDA / 62760 Post Request for Bids Open - National 391,000.00 0.00 2019-04-12 2020-10-12 2019-04-24 2020-10-12 2019-06-05 2019-07-05 2019-08-09 ce Management nvelope mentation 8 er, 5No. Surface water, 2No. automatic weather stations). UG-MWE-107829-CW-RFB / Works for Construction of: Lot 1 : Namasale Water Supp Component 1: WSS in Small ly and Sanitation System and Towns and RGCs and Suppor Open - Internationa Single Stage - One E Under Revie 2022-01-2 Sanitation and Koboko Sanita IDA / 62760 Prior Request for Bids 7,543,256.00 0.00 2019-07-31 2021-07-23 2019-08-24 2021-07-28 2019-10-05 2021-09-28 2019-11-17 2020-01-25 t to Districts Hosting Refuge l nvelope w 5 tion works es Lot 2: Kaliro - Namungalwe Water Supply and Sanitation System Lot 3: Sanitation works for Ru kungiri Municipality UG-MWE-162979-CW-DIR / Component 1: WSS in Small Under Imple 2020-10-2 Works for drilling and Testing IDA / 62760 Towns and RGCs and Suppor Post Direct Selection Direct 186,285.00 0.00 2020-03-10 2020-03-09 2020-03-15 2020-04-30 mentation 7 of 17No. wells in RGCs t to Districts Hosting Refuge es UG-MWE-173602-CW-RFB / Works for drilling and test pu Component 1: WSS in Small mping of production borehol Towns and RGCs and Suppor Single Stage - One E Pending Imp 2021-03-0 es for 20 sites in the refugee IDA / 62760 Post Request for Bids Open - National 438,947.00 0.00 2020-05-25 2020-06-11 2020-07-02 2020-08-03 2020-09-07 t to Districts Hosting Refuge nvelope lementation 6 s settlements and host com es munities in the districts of Kir yandongo, Arua, Moyo, Adju mani, Lamwo and Yumbe UG-MWE-211703-CW-RFB / Contract for Dredging and Fl Component 3: Water Resour Single Stage - One E 2021-04-1 IDA / 62760 Post Request for Bids Limited 4,008,000.00 0.00 Canceled 2021-01-07 2021-01-12 2021-02-05 2021-02-26 2021-04-02 ood Protection Works in uppe ce Management nvelope 2 r mid stream River Nyamwa mba UG-MWE-211704-CW-RFB / Contract for Dredging and Fl Component 3: Water Resour Single Stage - One E 2021-07-3 IDA / 62760 Post Request for Bids Limited 3,592,500.00 0.00 Canceled 2021-01-07 2021-01-12 2021-02-05 2021-02-26 2021-04-02 ood Protection Works in lowe ce Management nvelope 1 r River Nyamwamba UG-MWE-244336-CW-RFB / E mergency Maintenance of Ri Request for Bids - ver Nyamwamba for Flood Mi Component 3: Water Resour Single Stage - One E Small Works SPD Under Imple 2022-08-0 IDA / 62760 Post Request for Bids Limited 4,400,000.00 0.00 2021-08-23 2021-08-27 2021-10-08 2021-11-07 2021-12-12 tigation against Damage of C ce Management nvelope (1 envelope proce mentation 9 ritical Infrastructure and Loss ss) of Livelihoods in Kasese Distr ict UG-MWE-291887-CW-RFB / CONSTRUCTION OF WATER S Request for Bids - UPPLY AND SANITATION SYST Component 1: WSS in Small Works (without pr EMS IN : LOT 1- TIRINYI, KIBU Towns and RGCs and Suppor Open - Internationa Single Stage - One E equalification) SP 17,000,000.0 Under Revie 2023-12-2 IDA / 62760 Prior Request for Bids 0.00 2022-04-29 2022-05-23 2022-07-04 2022-08-26 2022-09-30 KU, KADAMA AND BUDAKA W t to Districts Hosting Refuge l nvelope D - Applying contr 0 w 4 ATER SUPPLY AND SANITATIO es actor disqualificia N SYSTEM & LOT 2- BUTALEJ tion A AND BUSOLWE WATER SUP PLY AND SANITATION SYSTE M Request for Bids - UG-MWE-272612-CW-RFB / Component 1: WSS in Small Works (without pr Construction of Tirinyi, Kibuk Towns and RGCs and Suppor Open - Internationa Single Stage - One E equalification) SP 17,000,000.0 2023-11-2 IDA / 62760 Prior Request for Bids 0.00 Canceled 2022-01-17 2022-02-14 2022-03-28 2022-04-27 2022-06-01 u, Kadama, Budaka, Butaleja, t to Districts Hosting Refuge l nvelope D - Applying contr 0 3 and Busolwe Water Supply a es actor disqualificia nd Sanitation System tion Request for Bids - UG-MWE-307952-CW-RFB / Component 1: WSS in Small Works (without pr Construction of Bitsya Water Towns and RGCs and Suppor Open - Internationa Single Stage - One E equalification) SP Pending Imp 2024-12-3 IDA / 62760 Prior Request for Bids 7,000,000.00 0.00 2022-08-15 2022-08-25 2022-10-06 2022-11-05 2022-12-10 Supply and Sanitation Syste t to Districts Hosting Refuge l nvelope D - Applying contr lementation 1 m in Buhweju District es actor disqualificia tion GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MWE-65595-GO-RFB / Su pply and Installation under th Component 1: WSS in Small e Umbrella Authorities of: Towns and RGCs and Suppor Open - Internationa Single Stage - One E Pending Impl Lot 1: Pipes and Fittings (150 / Post Request for Bids 1,869,000.00 0.00 2018-12-31 2019-02-01 2019-03-15 2019-04-28 2019-06-02 2019-11-29 t to Districts Hosting Refuge l nvelope ementation ,000m) es Lot 2: 500 Bulk and 30,000 d omestic meters UG-MWE-65550-GO-RFB / Su pply and Installation of: Lot 1: hydrometric equipmen t namely (5No. Ground Water Component 3: Water Resour Open - Internationa Single Stage - One E , 5No. Surface water, 2No. au IDA / 62760 Post Request for Bids 1,345,000.00 610,549.00 Signed 2019-04-15 2020-07-16 2019-05-02 2020-07-28 2019-06-13 2020-08-25 2019-07-19 2020-09-22 2019-09-06 2020-12-22 2020-09-04 ce Management l nvelope tomatic weather stations). Lot 2: Establishment of 3no. automatic precipitation and 2 no. dry deposition monitoring stations Page 1 UG-MWE-107838-GO-RFB / P Component 4: Project Imple Request for Quota Single Stage - One E Under Imple rocurement of Project Vehicl IDA / 62760 mentation and Institutional Post Limited 624,000.00 387,480.33 2019-04-30 2019-07-04 2019-07-09 2020-01-05 tions nvelope mentation es- 13N0. - 4WD pickup truck Strengthening s UG-MWE-107841-GO-RFQ / P rocurement of IT equipment f Component 4: Project Imple or Project Implementation : 2 Request for Quota Single Stage - One E Pending Impl IDA / 62760 mentation and Institutional Post Limited 98,000.00 0.00 2019-04-25 2019-07-12 2019-10-11 0No.Laptops, 2No.Printers, 2 tions nvelope ementation Strengthening No.Projectors, 1No. Photocop ier, 4No. still cameras and 25 No. GPS machines UG-MWE-130166-GO-RFB / S Component 1: WSS in Small upply of 25,000 micro and Bu Towns and RGCs and Suppor Single Stage - One E Under Imple lk Water Meters for Umbrella IDA / 62760 Post Request for Bids Open - National 551,000.00 0.00 2019-09-13 2020-07-15 2019-09-23 2020-07-20 2019-10-16 2019-11-15 2019-12-20 2022-12-19 t to Districts Hosting Refuge nvelope mentation s of Water and Sanitation un es der Framework Agreement UG-MWE-113671-GO-RFQ / S Component 1: WSS in Small upply and Installation of 60 u Towns and RGCs and Suppor Single Stage - One E nits of Electro-Mechanical eq IDA / 62760 Post Request for Bids Open - National 496,000.00 0.00 Canceled 2019-05-20 2019-05-31 2019-07-01 2019-07-24 2019-08-28 2022-08-26 t to Districts Hosting Refuge nvelope uipment for Umbrella Water es and Sanitation Authority und er Framework Agreement UG-MWE-113661-GO-RFB / S Component 1: WSS in Small upply of 200,000m Pipes and Towns and RGCs and Suppor Single Stage - One E IDA / 62760 Prior Request for Bids Open - National 1,700,000.00 0.00 Canceled 2020-02-24 2020-04-24 2020-03-09 2020-07-24 2020-04-09 2020-08-26 2020-05-09 2020-06-13 2023-06-13 Fittings for Umbrellas of Wat t to Districts Hosting Refuge nvelope er and Sanitation under Fram es e Work Agreement. UG-MWE-113654-GO-DIR / S Component 1: WSS in Small upply of 25,000 Micro and Bu Towns and RGCs and Suppor lk Water Meters for Umbrella IDA / 62760 Post Direct Selection Direct 551,000.00 0.00 Canceled 2019-05-20 2019-05-31 2019-08-09 2022-08-08 t to Districts Hosting Refuge s of Water and Sanitation un es der Framework Agreement UG-MWE-164748-GO-RFB / S upply of Technical Equipmen t for Regional Laboratories: Lot 1:Assorted Laboratory An alytical Equipment Component 3: Water Resour Open - Internationa Single Stage - One E Lot 2:Assorted Laboratory Pr IDA / 62760 Post Request for Bids 800,000.00 911,092.83 Signed 2020-04-09 2020-09-03 2020-07-19 2021-03-31 2021-01-15 ce Management l nvelope ocessing,Containment &Stor age Equipment Lot 3:Assorted Field Equipme nt Lot 4:Assorted Laboratory Ap paratus & Glassware UG-MWE-183001-GO-RFB / S upply, Installation, Upgrading , Commissioning and Maintai Component 3: Water Resour IDA / 62760 Prior Direct Selection Direct 2,900,000.00 3,189,374.00 Signed 2020-07-13 2020-08-31 2020-08-03 2020-11-23 2020-10-15 2021-08-25 2024-03-28 ning the Water Information S ce Management ystem phase II for the Gover nment of the Republic of Uga nda. UG-MWE-186158-GO-RFQ / P Component 4: Project Imple Request for Quota Single Stage - One E Pending Impl rocurement of Video Confere IDA / 62760 mentation and Institutional Post Limited 60,000.00 0.00 2020-08-12 2020-09-21 2020-12-20 tions nvelope ementation ncing equipment Strengthening UG-MWE-211705-GO-DIR / S Component 3: Water Resour Pending Impl upply and Installation of floo IDA / 62760 Post Direct Selection Direct 60,000.00 0.00 2021-01-07 2021-01-12 2021-02-16 2021-06-16 ce Management ementation d early warning systems on River Nyamwamba UG-MWE-228573-GO-RFB / S upply of Pipes and Fittings fo r Umbrella Authorities under: Component 1: WSS in Small Towns and RGCs and Suppor Open - Internationa Single Stage - One E Under Imple Lot 1(498,000m of pipes for IDA / 62760 Prior Request for Bids 2,400,000.00 0.00 2021-04-16 2021-06-01 2021-04-28 2021-06-11 2021-06-09 2021-07-15 2021-07-09 2021-10-21 2021-08-13 2024-08-12 t to Districts Hosting Refuge l nvelope mentation Wakiso & Kyenjojo) , Lot 2(49 es 8,000m of pipe for Lira & Mb ale), Lot 3 (249,000m of pipe s for Kabale) and Lot 4 (Supp ly of fittings for the five Umbr ella Authorities) UG-MWE-241168-GO-RFB / S upply and Installation of: Lot 1: hydrometric equipment(5 Component 3: Water Resour Open - Internationa Single Stage - One E Under Imple No. Ground Water, 5No. Surf IDA / 62760 Post Request for Bids 735,000.00 0.00 2021-08-06 2021-11-30 2021-08-11 2021-11-30 2021-09-08 2021-10-01 2021-11-05 2022-11-05 ce Management l nvelope mentation ace water, 2No. automatic w eather stations). Lot 2: Hydro met Modeling Unit and Securi ty Equipment(Assorted) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MWE-65819-NC-RFB / Im plementation of priority WRM measures in: Component 3: Water Resour Open - Internationa Single Stage - One E Under Imple Lot 1: Lwakhakha sub-catch IDA / 62760 Prior Request for Bids 9,094,000.00 0.00 2019-01-15 2020-09-30 2019-02-15 2020-10-08 2019-03-29 2020-11-23 2019-05-10 2021-09-29 2019-07-05 2020-12-31 ce Management l nvelope mentation ment Lot 2: Aswa II sub-catchment Lot 3: Kochi sub-catchment Lot 4: Middle Awoja sub-catc hment UG-MWE-130162-NC-RFP / N Component 1: WSS in Small on Consultancy Services for Towns and RGCs and Suppor Request for Propo Single Stage - Two E Pending Impl IDA / 62760 Post Limited 50,000.00 0.00 2019-09-13 2019-09-18 2019-10-10 2019-12-09 2020-01-13 2020-05-12 Development of an Online M t to Districts Hosting Refuge sals nvelope ementation &E Progress Reporting Syste es m UG-MWE-113664-NC-RFB / L abor requirement for the inst allation of pipes, fittings and Component 1: WSS in Small water meters for Umbrella W Towns and RGCs and Suppor Single Stage - One E Pending Impl IDA / 62760 Post Request for Bids Open - National 619,000.00 0.00 2019-05-31 2019-06-12 2019-07-17 2019-08-16 2019-09-20 2022-09-19 ater & Sanitation Authorities t to Districts Hosting Refuge nvelope ementation under Framework Agreement es s in : Lo1: Central, Lot 2: East ern, Lot 3: South Western, Lo t 4: Mid-Western and Lot 5: N orthern UG-MWE-162982-NC-RFQ / N Component 1: WSS in Small on Consulting services to und Towns and RGCs and Suppor Request for Quota Single Stage - One E Pending Impl er take the printing and bindi IDA / 62760 Post Limited 30,000.00 0.00 2020-03-14 2020-04-14 2020-10-11 t to Districts Hosting Refuge tions nvelope ementation ng of the bidding and other r es elated documents under IWM DP. Page 2 UG-MWE-211654-NC-RFB / I mplementation of priority cat Component 3: Water Resour Single Stage - One E Under Imple IDA / 62760 Post Request for Bids Limited 1,300,000.00 0.00 2021-01-07 2021-02-25 2021-01-12 2021-02-25 2021-02-04 2021-02-25 2021-04-01 2021-10-28 chment management measu ce Management nvelope mentation res in upstream Nyamwamba UG-MWE-211697-NC-RFB / I mplementation of priority cat Component 3: Water Resour Single Stage - One E Under Imple IDA / 62760 Post Request for Bids Limited 1,500,000.00 0.00 2021-01-07 2021-02-25 2021-01-12 2021-02-25 2021-02-04 2021-02-25 2021-04-01 2021-10-28 chment management measu ce Management nvelope mentation res in Midstream Nyamwamb a UG-MWE-211698-NC-RFB / I mplementation of priority cat Component 3: Water Resour Single Stage - One E Under Imple IDA / 62760 Post Request for Bids Limited 1,200,000.00 0.00 2021-01-07 2021-02-25 2021-01-12 2021-02-25 2021-02-04 2021-02-25 2021-04-01 2021-10-28 chment management measu ce Management nvelope mentation res in downstream Nyamwa mba CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MWE-65575-CS-QCBS / P Component 3: Water Resour Quality And Cost- Open - Internationa Under Implement reparation of Albert WMZ Wa / Prior 1,500,000.00 0.00 2018-09-28 2019-06-11 2018-10-26 2019-08-02 2018-12-21 2020-04-03 2019-01-18 2020-06-29 2019-02-17 2021-02-22 2019-03-28 2022-01-07 2019-05-08 2020-05-07 ce Management Based Selection l ation ter Resources Strategy and A ction Plan UG-MWE-65391-CS-QCBS / C Component 1: WSS in Small onsultancy Services for Const Towns and RGCs and Suppor Quality And Cost- Under Implement IDA / 62760 Prior Open - National 490,000.00 0.00 2018-10-25 2018-08-25 2018-11-22 2018-10-29 2019-01-05 2019-05-16 2019-02-06 2019-09-05 2019-03-08 2020-08-06 2019-04-12 2021-06-09 2019-06-07 2020-12-07 ruction Supervision of Water t to Districts Hosting Refuge Based Selection ation Supply and Sanitation Syste es ms in Busia UG-MWE-107835-CS-QCBS / Consultancy Services for Fea Component 1: WSS in Small sibility, Detailed Engineering Towns and RGCs and Suppor Quality And Cost- Open - Internationa Under Implement IDA / 62760 Prior 650,000.00 0.00 2019-05-17 2019-07-21 2019-06-14 2019-08-14 2019-07-28 2021-03-14 2019-08-25 2020-08-06 2019-09-24 2021-03-15 2019-10-29 2021-08-26 2019-12-03 2021-12-02 Design and Construction Sup t to Districts Hosting Refuge Based Selection l ation ervision of Water Supply and es Sanitation System in Kyegeg wa-Mpara-Ruyonza UG-MWE-65546-CS-QCBS / L OT 1: Preparation of 2 Catch Component 3: Water Resour Quality And Cost- Open - Internationa Under Implement IDA / 62760 Prior 2,850,000.00 0.00 2019-05-17 2019-06-11 2019-06-14 2019-08-02 2019-08-09 2020-04-27 2019-09-06 2020-06-29 2019-10-06 2021-02-15 2019-11-14 2021-08-18 2019-12-25 2020-12-24 ment Management Plans for ce Management Based Selection l ation Nyamugasani & Kafu in Albe rt WMZ. UG-MWE-113265-CS-QCBS / LOT 2: Preparation of 2 Catch Component 3: Water Resour Quality And Cost- Open - Internationa Under Implement IDA / 62760 Prior 2,850,000.00 0.00 2019-05-17 2019-06-11 2019-06-14 2019-08-04 2019-07-28 2022-01-13 2019-08-25 2020-06-29 2019-09-24 2022-01-13 2019-10-29 2022-01-13 2019-12-03 2020-12-02 ment Management Plans for ce Management Based Selection l ation Sezibwa and Okweng in Kyog a WMZ UG-MWE-113859-CS-CQS / L ot 1: Feasibility Study, Detail Component 1: WSS in Small ed Engineering Design and C Towns and RGCs and Suppor Quality And Cost- Open - Internationa onstruction Supervision of So IDA / 62760 Prior 642,000.00 0.00 Canceled 2019-05-13 2019-05-22 2019-05-27 2019-08-14 2019-07-10 2020-07-26 2019-07-31 2020-09-03 2019-08-30 2021-06-10 2019-10-04 2022-05-03 2019-11-08 2022-02-07 t to Districts Hosting Refuge Based Selection l lar Powered Piped Water Sup es ply Systems and Sanitation F acilities in Refugee Settleme nts and Host Districts Arua a nd Moyo UG-MWE-113876-CS-QCBS / Lot 2: Feasibility Study, Detai Component 1: WSS in Small led Engineering Design and C Towns and RGCs and Suppor Quality And Cost- Open - Internationa onstruction Supervision of So IDA / 62760 Prior 735,000.00 0.00 Under Review 2019-05-13 2019-05-22 2019-05-27 2019-08-14 2019-07-10 2020-07-26 2019-07-31 2020-09-03 2019-08-30 2021-06-10 2019-10-04 2019-11-08 2022-02-07 t to Districts Hosting Refuge Based Selection l lar Powered Piped Water Sup es ply Systems and Sanitation F acilities in Refugee Settleme nts and Host District of Yumb e UG-MWE-113877-CS-QCBS / Lot 3: Feasibility Study, Detai led Engineering Design and C Component 1: WSS in Small onstruction Supervision of So Towns and RGCs and Suppor Quality And Cost- Open - Internationa Under Implement IDA / 62760 Prior 730,000.00 0.00 2019-05-13 2019-05-22 2019-05-27 2020-01-31 2019-07-10 2020-07-26 2019-07-31 2020-09-03 2019-08-30 2021-06-11 2019-10-04 2022-03-01 2019-11-08 2022-02-07 lar Powered Piped Water Sup t to Districts Hosting Refuge Based Selection l ation ply Systems and Sanitation F es acilities in Refugee Settleme nts and Host Districts of Adju mani and Lamwo UG-MWE-107833-CS-QCBS / Consultancy Services for Con Component 1: WSS in Small struction Supervision of Wate Towns and RGCs and Suppor Quality And Cost- Open - Internationa r Supply and Sanitation Syste IDA / 62760 Prior 500,000.00 0.00 Under Review 2019-05-24 2019-06-19 2019-06-21 2019-08-02 2019-08-04 2020-12-22 2019-09-01 2021-01-28 2019-10-01 2021-11-08 2019-11-05 2019-12-10 2021-12-09 t to Districts Hosting Refuge Based Selection l ms in (a) Namasale and Sanit es ation Facilities in koboko (b)K aliro-Namungalwe and (c) Sa nitation Facilities in Rukungiri UG-MWE-115609-CS-CQS / C Component 1: WSS in Small onsultancy Services for Desig Towns and RGCs and Suppor Consultant Qualifi Open - Internationa Under Implement n Review and construction se IDA / 62760 Post 314,000.00 0.00 2019-05-27 2019-06-05 2019-06-10 2019-06-24 2019-07-24 2020-01-23 2019-08-23 2019-09-27 2021-09-26 t to Districts Hosting Refuge cation Selection l ation rvices for Bitsya Water Suppl es y and Sanitation system UG-MWE-65450-CS-QCBS / L Component 1: WSS in Small OT 1: Consultancy Services f Towns and RGCs and Suppor Quality And Cost- Open - Internationa IDA / 62760 Prior 730,000.00 0.00 Canceled 2019-05-10 2019-05-26 2019-07-09 2019-08-11 2019-09-12 2019-10-17 2019-11-21 2021-11-20 or design review and Constru t to Districts Hosting Refuge Based Selection l ction Supervision for Nyamug es asani GFS UG-MWE-117147-CS-QCBS / Component 1: WSS in Small Consultancy Services for desi Towns and RGCs and Suppor Quality And Cost- Open - Internationa Under Implement IDA / 62760 Prior 730,000.00 0.00 2019-06-04 2019-06-05 2019-06-11 2019-06-28 2019-07-25 2020-07-26 2019-08-26 2020-09-01 2019-09-25 2021-04-15 2019-10-23 2021-08-19 2019-11-27 2021-11-26 gn review and Construction S t to Districts Hosting Refuge Based Selection l ation upervision for Nyamugasani es GFS UG-MWE-113032-CS-CQS / L Component 1: WSS in Small OT 2: Consultancy Services f Towns and RGCs and Suppor Consultant Qualifi Open - Internationa or Design Review and constr IDA / 62760 Post 314,000.00 0.00 Canceled 2019-05-09 2019-05-07 2019-05-30 2019-07-13 2019-08-12 2019-09-16 2021-09-15 t to Districts Hosting Refuge cation Selection l uction services for Bitsya Wa es ter Supply and Sanitation sys tem UG-MWE-113883-CS-QCBS / Lot 4: Feasibility Study, Detai Component 1: WSS in Small led Engineering Design and C Towns and RGCs and Suppor Consultant Qualifi Open - Internationa onstruction Supervision of So IDA / 62760 Post 345,000.00 0.00 Canceled 2019-05-13 2019-05-21 2019-05-27 2019-07-10 2019-07-31 2019-09-04 2022-02-07 t to Districts Hosting Refuge cation Selection l lar Powered Piped Water Sup es ply Systems and Sanitation F acilities in Refugee Settleme nts and Host Districts of Kiry andongo Page 3 UG-MWE-117157-CS-CQS / C onsultancy services for Feasi bility Study, Detailed Enginee Component 1: WSS in Small ring Design and Construction Towns and RGCs and Suppor Consultant Qualifi Open - Internationa Under Implement IDA / 62760 Post 345,000.00 0.00 2019-06-04 2019-06-05 2019-06-11 2019-08-14 2019-07-25 2020-01-24 2019-08-24 2019-09-28 2021-09-27 Supervision of Solar Powered t to Districts Hosting Refuge cation Selection l ation Piped Water Supply Systems es and Sanitation Facilities in Re fugee Settlements and Host Districts of Kiryandongo UG-MWE-117161-CS-QCBS / Consultancy Services for qua Component 3: Water Resour Quality And Cost- Open - Internationa Under Implement ntification of the available gr IDA / 62760 Prior 2,000,000.00 0.00 2019-06-17 2019-08-01 2019-07-01 2019-10-29 2019-08-14 2020-06-09 2019-09-11 2020-08-04 2019-10-04 2020-12-17 2019-11-01 2021-07-12 2019-12-06 2020-12-05 ce Management Based Selection l ation oundwater and assessment o f sustainability of groundwat er development UG-MWE-113950-CS-CQS / C onsultancy Services to condu ct Sanitation & giene Promoti Component 1: WSS in Small on/Training on O & M of Sanit Towns and RGCs and Suppor Consultant Qualifi ation Facilities in Busia, Ku IDA / 62760 Post Open - National 250,000.00 0.00 Canceled 2019-05-14 2019-05-20 2019-05-28 2019-07-04 2019-07-29 2019-09-02 2020-09-02 t to Districts Hosting Refuge cation Selection mi-Ngora-Nyero, Rukungiri, K es oboko, Namungalwe-Kaliro, Namasale, Kyegegwa-Mpara- Ruyonza &Towns of Busolwe- Kadama-Tirinyi-Kibuku-Butal eja UG-MWE-127198-CS-QCBS / Consultancy Services to cond Component 1: WSS in Small uct community engagement, Towns and RGCs and Suppor Quality And Cost- IDA / 62760 Prior Open - National 600,000.00 0.00 Canceled 2019-08-19 2019-09-02 2019-11-15 2019-12-13 2020-01-12 2020-02-16 2020-03-22 2022-12-12 Sanitation & hygiene Promoti t to Districts Hosting Refuge Based Selection on/Training on O & M of Sanit es ation Facilities in small towns under IWMDP UG-MWE-127207-CS-CQS / C Component 1: WSS in Small onsultancy services for prepa Towns and RGCs and Suppor Consultant Qualifi IDA / 62760 Post Open - National 450,000.00 0.00 Canceled 2019-08-20 2019-09-04 2019-09-03 2019-10-17 2019-11-16 2019-12-21 2020-06-18 ration of Towns Sanitation pl t to Districts Hosting Refuge cation Selection ans for Small towns(18 No) u es nder IWMDP UG-MWE-127221-CS-QCBS / Component 1: WSS in Small Consultancy Services for Con Towns and RGCs and Suppor Quality And Cost- Open - Internationa Under Implement struction Supervision of Larg IDA / 62760 Prior 1,500,000.00 0.00 2019-08-19 2019-09-27 2019-09-09 2020-08-30 2019-11-06 2021-10-06 2019-12-04 2021-11-11 2020-01-03 2020-02-07 2020-03-13 2021-03-08 t to Districts Hosting Refuge Based Selection l ation e Solar Powered Water Suppl es y and Sanitation Systems in 32 RGCS UG-MWE-118949-CS-CQS / C Component 1: WSS in Small onsultancy Services for Devel Towns and RGCs and Suppor Consultant Qualifi IDA / 62760 Post Open - National 50,000.00 0.00 Canceled 2019-07-22 2019-08-05 2019-09-18 2019-10-18 2019-11-22 2020-05-20 opment of an Online M&E Pro t to Districts Hosting Refuge cation Selection gress Reporting System es UG-MWE-121827-CS-CQS / C Component 1: WSS in Small onsultancy Services for the P Towns and RGCs and Suppor Consultant Qualifi Open - Internationa IDA / 62760 Prior 750,000.00 0.00 Canceled 2019-07-31 2019-08-21 2019-10-04 2019-11-03 2019-12-08 2020-12-07 rofessionalization of Umbrell t to Districts Hosting Refuge cation Selection l as of Water and Sanitation es UG-MWE-130406-CS-CQS / C onsultancy Services for Stake Component 1: WSS in Small holder Engagement, Environ Towns and RGCs and Suppor Quality And Cost- Under Implement IDA / 62760 Prior Open - National 1,150,000.00 0.00 2019-09-16 2020-07-13 2019-10-07 2020-11-25 2019-11-20 2019-12-18 2020-01-17 2020-02-21 2020-03-27 2022-03-27 ment and Social Risk Manage t to Districts Hosting Refuge Based Selection ation ment for Nyamugasani and B es istya Gravity Flow Schemes UG-MWE-130593-CS-CQS / C onsultancy Services for Devel Component 3: Water Resour Consultant Qualifi opment and Implementation IDA / 62760 Post Open - National 240,000.00 0.00 Canceled 2019-09-12 2019-10-03 2019-11-16 2019-12-16 2020-01-20 2020-07-18 ce Management cation Selection of Micro-Catchment Manage ment Plans for Refugee Settl ements UG-MWE-145127-CS-CQS / L OT 1: Preparation of 2 Micro Catchment Management Plan Component 3: Water Resour Quality And Cost- Open - Internationa Under Implement IDA / 62760 Post 335,000.00 0.00 2019-11-15 2019-11-19 2019-12-06 2020-02-20 2020-01-19 2020-02-16 2020-03-17 2020-04-21 2020-05-26 2020-11-22 s for Selected Micro Catchme ce Management Based Selection l ation nt around Water Sources in O ra and Anyau Sub Catchment s UG-MWE-145128-CS-CQS / L OT 2: Preparation of 2 Micro Catchment Management Plan Component 3: Water Resour Quality And Cost- Open - Internationa Under Implement IDA / 62760 Post 335,000.00 0.00 2019-11-15 2019-11-19 2019-12-06 2020-02-20 2020-01-19 2020-02-16 2020-03-17 2020-04-21 2020-05-26 2020-11-22 s for Selected Micro Catchme ce Management Based Selection l ation nt around Water Sources in L aropi and Ayugi Sub Catchm ents UG-MWE-145129-CS-CQS / L OT 3: Preparation of 2 Micro Catchment Management Plan Component 3: Water Resour Quality And Cost- Open - Internationa Under Implement IDA / 62760 Post 335,000.00 0.00 2019-11-15 2019-11-19 2019-12-06 2020-02-20 2020-01-19 2020-02-16 2020-03-17 2020-04-21 2020-05-26 2020-11-22 s for Selected Micro Catchme ce Management Based Selection l ation nt around Water Sources in N yimur and Mutunda Sub Catc hments UG-MWE-146154-CS-FBS / L ot 1: Consultancy Services to Conduct Community Engage Component 1: WSS in Small ment, Town Sanitation Planni Towns and RGCs and Suppor Quality And Cost- Open - Internationa ng, Sanitation and Hygiene P IDA / 62760 Post 350,000.00 245,306.13 Signed 2019-11-22 2020-07-30 2019-12-13 2020-10-14 2020-01-26 2021-03-10 2020-02-23 2021-04-01 2020-03-24 2021-05-19 2020-04-28 2021-07-06 2020-06-02 2021-11-25 2022-06-02 t to Districts Hosting Refuge Based Selection l romotion, Training on Operati es on and Maintenance of Sanit ation Facilities in Small Town s of: Koboko, Namasale, and cluster of Kumi-Ngora-Nyero. UG-MWE-146193-CS-QCBS / Lot 2: Consultancy Services t o Conduct Community Engag Component 1: WSS in Small ement, Town Sanitation Plan Towns and RGCs and Suppor Quality And Cost- Open - Internationa ning, Sanitation and Hygiene IDA / 62760 Post 350,000.00 221,137.43 Signed 2019-11-22 2020-07-30 2019-12-13 2020-10-14 2020-01-26 2021-03-10 2020-02-23 2021-04-01 2020-03-24 2021-05-19 2020-04-28 2021-07-06 2020-06-02 2021-11-25 2022-05-23 t to Districts Hosting Refuge Based Selection l Promotion, Training on Opera es tion and Maintenance of Sani tation Facilities in Small Tow ns of: Rukungiri and the clust er of Kyegegwa-Mpara-Ruyon za UG-MWE-146194-CS-QCBS / Lot 3: Conduct Community E ngagement, Town Sanitation Component 1: WSS in Small Planning, Sanitation and Hygi Towns and RGCs and Suppor Quality And Cost- Open - Internationa ene Promotion, Training on O IDA / 62760 Post 350,000.00 217,442.12 Signed 2019-11-22 2020-07-30 2019-12-13 2020-10-14 2020-01-26 2021-03-10 2020-02-23 2021-04-01 2020-03-24 2021-05-19 2020-04-28 2021-07-06 2020-06-02 2021-11-25 2022-05-23 t to Districts Hosting Refuge Based Selection l peration and Maintenance of es Sanitation Facilities in Small Towns of: Busia, Namungalw e-Kaliro, Busolwe, Butaleja, K adama-Tirinyi-Kibuku- Budak a Page 4 UG-MWE-160277-CS-CQS / L OT 1: Consultancy Services f Component 3: Water Resour Consultant Qualifi Under Implement or Technical Supervision of I IDA / 62760 Post Open - National 218,500.00 0.00 2020-02-24 2020-09-28 2020-03-09 2020-10-19 2020-04-22 2020-05-22 2020-06-26 2020-12-23 ce Management cation Selection ation mplementation of Catchment Management Measures in Lw akhakha Sub Catchment UG-MWE-160279-CS-CQS / L OT 2: Consultancy Services f Component 3: Water Resour Consultant Qualifi Under Implement or Technical Supervision of I IDA / 62760 Post Open - National 293,254.00 0.00 2020-02-24 2020-09-28 2020-03-09 2020-10-19 2020-04-22 2020-05-22 2020-06-26 2020-12-23 ce Management cation Selection ation mplementation of Catchment Management Measures in As wa II Sub Catchment UG-MWE-160280-CS-CQS / L OT 3: Consultancy Services f Component 3: Water Resour Consultant Qualifi Under Implement or Technical Supervision of I IDA / 62760 Post Open - National 297,254.00 0.00 2020-02-24 2020-09-28 2020-03-09 2020-10-19 2020-04-22 2020-05-22 2020-06-26 2020-12-23 ce Management cation Selection ation mplementation of Catchment Management Measures in Ko chi Sub Catchment UG-MWE-160281-CS-CQS / L OT 4: Consultancy Services f or Technical Supervision of I Component 3: Water Resour Consultant Qualifi Under Implement IDA / 62760 Post Open - National 296,378.00 0.00 2020-02-24 2020-09-28 2020-03-09 2020-10-19 2020-04-22 2020-05-22 2020-06-26 2020-12-23 mplementation of Catchment ce Management cation Selection ation Management Measures in Mi ddle/lower Awoja Sub Catch ment UG-MWE-182398-CS-CQS / C Component 4: Project Imple onsultancy Services for stren Consultant Qualifi Under Implement IDA / 62760 mentation and Institutional Post Open - National 160,000.00 0.00 2020-07-13 2020-07-16 2020-07-27 2020-09-09 2020-10-09 2020-11-13 2021-05-12 gthening and capacity buildi cation Selection ation Strengthening ng for the Regional Water Uti lity Regulation Units UG-MWE-130191-CS-QCBS / Component 1: WSS in Small Quality And Cost- Open - Internationa Consultancy Services for Prof IDA / 62760 Towns and RGCs and Suppor Prior 2,225,000.00 0.00 Canceled 2019-09-16 2019-12-13 2019-10-07 2019-11-20 2019-12-18 2020-01-17 2020-02-21 2020-03-27 2024-03-26 Based Selection l essionalization of Umbrella A t to Districts Hosting Refuge uthorities es UG-MWE-193868-CS-QCBS / Component 1: WSS in Small Quality And Cost- Open - Internationa Under Implement Consultancy Services for Prof IDA / 62760 Towns and RGCs and Suppor Prior 2,225,000.00 0.00 2020-09-30 2020-09-28 2020-10-02 2020-09-30 2020-11-15 2021-07-27 2020-12-13 2021-09-20 2021-01-12 2022-02-14 2021-02-16 2022-05-06 2021-03-23 2023-03-23 Based Selection l ation essionalization of Umbrella A t to Districts Hosting Refuge uthorities es UG-MWE-196155-CS-CQS / L OT 1: Consultancy Services f or Stakeholder Engagement, Component 1: WSS in Small Environment and Social Risk Towns and RGCs and Suppor Consultant Qualifi IDA / 62760 Post Open - National 342,000.00 0.00 Canceled 2020-09-30 2020-10-27 2020-10-21 2020-12-04 2021-01-03 2021-02-07 2023-02-07 Management for Large Solar t to Districts Hosting Refuge cation Selection Powered Water Supply and S es anitation Systems in Rural Gr owth Centres - Western regio n (12 solar powered water su pply systems) UG-MWE-196157-CS-CQS / L ot 2: Consultancy Services fo r Stakeholder Engagement, E Component 1: WSS in Small nvironment and Social Risk M Towns and RGCs and Suppor Consultant Qualifi IDA / 62760 Post Open - National 313,000.00 0.00 Canceled 2020-09-30 2020-10-27 2020-10-21 2020-12-04 2021-01-03 2021-02-07 2023-02-07 anagement for Large Solar P t to Districts Hosting Refuge cation Selection owered Water Supply and Sa es nitation Systems in Rural Gro wth Centres -Central region ( 11 solar powered water suppl y systems) UG-MWE-196161-CS-CQS / L ot 3: Consultancy Services fo r Stakeholder Engagement, E Component 1: WSS in Small nvironment and Social Risk M Towns and RGCs and Suppor Consultant Qualifi IDA / 62760 Post Open - National 255,000.00 0.00 Canceled 2020-09-30 2020-10-27 2020-10-21 2020-12-04 2021-01-03 2021-02-07 2023-02-07 anagement for Large Solar P t to Districts Hosting Refuge cation Selection owered Water Supply and Sa es nitation Systems in Rural Gro wth Centres - Eastern region (9 solar powered water suppl y systems) UG-MWE-223396-CS-CQS / C onsultancy Services to under Component 1: WSS in Small take the Stakeholder engage Towns and RGCs and Suppor Consultant Qualifi Under Implement ment , Environment and Risk IDA / 62760 Post Limited 241,211.00 0.00 2021-03-12 2021-08-18 2021-03-26 2021-04-25 2021-05-30 2021-11-26 t to Districts Hosting Refuge cation Selection ation for Solar Powered water supp es ly and sanitation systems in Refugee Hosting District of Ki ryandongo. UG-MWE-228559-CS-QCBS / LOT 1: Consultancy Services for Stakeholder Engagement, Component 1: WSS in Small Environment and Social Risk Towns and RGCs and Suppor Quality And Cost- Management for Large Solar IDA / 62760 Prior Open - National 964,845.00 0.00 Under Review 2021-04-16 2021-09-29 2021-05-07 2022-01-16 2021-06-20 2021-07-18 2021-08-17 2021-09-21 2021-10-26 2023-10-26 t to Districts Hosting Refuge Based Selection Powered Water Supply and S es anitation Systems in Rural Gr owth Centers - Western regio n (12 solar powered water su pply systems) UG-MWE-228562-CS-QCBS / Lot 2: Consultancy Services f or Stakeholder Engagement, Component 1: WSS in Small Environment and Social Risk Towns and RGCs and Suppor Quality And Cost- IDA / 62760 Prior Open - National 884,442.00 0.00 Under Review 2021-04-16 2021-09-29 2021-05-07 2022-01-16 2021-06-20 2021-07-18 2021-08-17 2021-09-21 2021-10-26 2023-10-26 Management for Large Solar t to Districts Hosting Refuge Based Selection Powered Water Supply and S es anitation Systems in Rural Gr owth Centers -Central region (11 solar powered water sup ply systems) UG-MWE-228563-CS-QCBS / Lot 3: Consultancy Services f or Stakeholder Engagement, Component 1: WSS in Small Environment and Social Risk Towns and RGCs and Suppor Quality And Cost- IDA / 62760 Prior Open - National 723,634.00 0.00 Under Review 2021-04-16 2021-09-29 2021-05-07 2022-01-16 2021-06-20 2021-07-18 2021-08-17 2021-09-21 2021-10-26 2023-10-26 Management for Large Solar t to Districts Hosting Refuge Based Selection Powered Water Supply and S es anitation Systems in Rural Gr owth Centers - Eastern regio n (9 solar powered water sup ply systems) UG-MWE-228575-CS-CQS / C onsultancy Services for Upda te of Environmental and Soci Component 1: WSS in Small al Impact Assessment (ESIA), Towns and RGCs and Suppor Consultant Qualifi Under Implement Source Protection Plan (SPP), IDA / 62760 Post Limited 300,000.00 0.00 2021-04-16 2021-05-18 2021-04-30 2021-05-30 2021-07-04 2021-12-31 t to Districts Hosting Refuge cation Selection ation and Resettlement Action Plan es (RAP) for the Bitsya and Nya mugasani Water Systems in Buhweju and Kasese Districts Respectively UG-MWE-233662-CS-QCBS / Consultancy Services for Sta Component 1: WSS in Small keholder Engagement, Enviro Towns and RGCs and Suppor Quality And Cost- Open - Internationa Pending Impleme IDA / 62760 Prior 1,050,000.00 0.00 2021-05-14 2021-06-04 2021-07-18 2021-08-15 2021-09-14 2021-10-19 2021-11-23 2022-11-23 nment and Social Risk Manag t to Districts Hosting Refuge Based Selection l ntation ement for Ora-Enyau Water S es upply and Sanitation System Page 5 UG-MWE-233666-CS-CQS / C onsultancy Services for Envir Component 1: WSS in Small onmental and Social Impact Towns and RGCs and Suppor Consultant Qualifi Under Implement Assessment (ESIA), Source Pr IDA / 62760 Post Limited 300,000.00 0.00 2021-05-14 2022-03-17 2021-05-28 2021-06-27 2021-08-01 2022-08-01 t to Districts Hosting Refuge cation Selection ation otection Plan (SPP), and Rese es ttlement Action Plan (RAP) fo r Ora-Enyau Water Supply an d Sanitation System UG-MWE-233081-CS-CQS / C Component 1: WSS in Small onsultancy Services for Const Towns and RGCs and Suppor Consultant Qualifi Pending Impleme IDA / 62760 Post Limited 300,000.00 0.00 2021-05-17 2021-05-31 2021-06-30 2021-08-04 2022-08-04 ruction Supervision of Bwera t to Districts Hosting Refuge cation Selection ntation Water Supply System in Kase es se District. UG-MWE-233085-CS-CQS / C Component 1: WSS in Small onsultancy Services for Const Towns and RGCs and Suppor Consultant Qualifi Pending Impleme IDA / 62760 Post Limited 300,000.00 0.00 2021-05-17 2021-05-31 2021-06-30 2021-08-04 2022-08-04 ruction Supervision of Dungul t to Districts Hosting Refuge cation Selection ntation uha Water Supply System in es Kasese District UG-MWE-223390-CS-QCBS / LOT 1: Stakeholder engagem Component 1: WSS in Small ent, Environment and Social Towns and RGCs and Suppor Quality And Cost- Under Implement IDA / 62760 Post Open - National 615,041.00 0.00 2021-03-12 2021-11-15 2021-04-02 2022-01-19 2021-05-16 2021-06-13 2021-07-13 2021-08-17 2021-09-21 2022-09-21 Risk Management for Solar P t to Districts Hosting Refuge Based Selection ation owered water supply and san es itation systems in Refugee H osting Districts of Arua & Mo yo UG-MWE-223391-CS-QCBS / Lot 2: Consultancy Services t Component 1: WSS in Small o undertake Stakeholder eng Towns and RGCs and Suppor Quality And Cost- Under Implement agement, Environment and S IDA / 62760 Post Open - National 404,757.00 0.00 2021-03-12 2021-11-15 2021-04-02 2022-01-19 2021-05-16 2021-06-13 2021-07-13 2021-08-17 2021-09-21 2022-09-21 t to Districts Hosting Refuge Based Selection ation ocial Risk Management for S es olar Powered water supply a nd sanitation systems in Refu gee Hosting Districts of Yum be UG-MWE-253406-CS-QCBS / Lot 3: Consultancy Services t o undertake Stakeholder eng Component 1: WSS in Small agement, Environment and S Towns and RGCs and Suppor Quality And Cost- Under Implement IDA / 62760 Post Open - National 575,770.00 0.00 2021-09-20 2021-11-15 2021-10-11 2022-01-19 2021-11-24 2021-12-22 2022-01-21 2022-02-25 2022-04-01 2023-04-01 ocial Risk Management for S t to Districts Hosting Refuge Based Selection ation olar Powered water supply a es nd sanitation systems in Refu gee Hosting Districts of Adju mani and Lamwo UG-MWE-251069-CS-QCBS / ENVIRONMENTAL AND SOCIA L IMPACT ASSESSMENT (ESIA Component 1: WSS in Small )/ENVIRONMENTAL AND SOCI Towns and RGCs and Suppor Consultant Qualifi Under Implement AL PROJECT BRIEF, RESETTLE IDA / 62760 Post Limited 420,000.00 0.00 2021-10-08 2022-02-01 2021-10-29 2021-11-28 2022-01-02 2022-07-01 t to Districts Hosting Refuge cation Selection ation MENT ACTION PLAN (RAP) AN es D SOURCE PROTECTION PLA Ns (SPP) FOR LARGE SOLAR P OWERED PIPED WATER SUPP LY SYSTEMS AND SANITATIO N FACILITIES IN YUMBE UG-MWE-251067-CS-QCBS / ENVIRONMENTAL AND SOCIA L IMPACT ASSESSMENT (ESIA )/ENVIRONMENTAL AND SOCI Component 1: WSS in Small AL PROJECT BRIEF, RESETTLE Towns and RGCs and Suppor Consultant Qualifi Under Implement IDA / 62760 Post Limited 350,000.00 0.00 2021-10-08 2022-02-01 2021-10-29 2021-11-28 2022-01-02 2022-07-01 MENT ACTION PLAN (RAP) AN t to Districts Hosting Refuge cation Selection ation D SOURCE PROTECTION PLA es Ns (SPP) FOR LARGE SOLAR P OWERED PIPED WATER SUPP LY SYSTEMS AND SANITATIO N FACILITIES IN ARUA & MOY O UG-MWE-251070-CS-QCBS / ENVIRONMENTAL AND SOCIA L IMPACT ASSESSMENT (ESIA )/ENVIRONMENTAL AND SOCI Component 1: WSS in Small AL PROJECT BRIEF, RESETTLE Towns and RGCs and Suppor Consultant Qualifi Under Implement IDA / 62760 Post Limited 420,000.00 0.00 2021-10-08 2022-02-01 2021-10-29 2021-11-28 2022-01-02 2022-07-01 MENT ACTION PLAN (RAP) & t to Districts Hosting Refuge cation Selection ation SOURCE PROTECTION PLANs es (SPP) FOR LARGE SOLAR PO WERED PIPED WATER SUPPL Y SYSTEMS AND SANITATION FACILITIES IN AJUMANI & LAM WO UG-MWE-258812-CS-QCBS / Consultancy Services for Sta Component 1: WSS in Small keholder Engagement, Enviro Towns and RGCs and Suppor Quality And Cost- Open - Internationa Under Implement nment and Social Risk Manag IDA / 62760 Prior 1,150,000.00 0.00 2021-10-25 2022-04-07 2021-11-15 2022-06-10 2021-12-29 2022-01-26 2022-02-25 2022-04-01 2022-05-06 2023-10-28 t to Districts Hosting Refuge Based Selection l ation ement for Ora-Ala (Nyagak a es nd Enyau) Water Supply and Sanitation Systems in West N ile of Uganda UG-MWE-258807-CS-QCBS / Component 1: WSS in Small CONSULTANCY SERVICES FO Towns and RGCs and Suppor Quality And Cost- Open - Internationa R CONSTRUCTION SUPERVISI IDA / 62760 Prior 1,500,000.00 0.00 Under Review 2022-04-01 2022-05-02 2022-04-15 2022-05-10 2022-05-22 2022-06-19 2022-07-15 2022-08-19 2022-09-16 2024-12-20 t to Districts Hosting Refuge Based Selection l ON OF ORA- ALA WATER SUP es PLY AND SANITATION SYSTE M UG-MWE-283143-CS-CQS / C onsultancy services for Prepa Component 1: WSS in Small ration Of ESIA, SPP and RAP f Towns and RGCs and Suppor Consultant Qualifi Under Implement or 4No. Solar-Powered Water IDA / 62760 Post Limited 280,000.00 0.00 2022-04-01 2022-03-30 2022-04-15 2022-05-15 2022-06-19 2022-12-16 t to Districts Hosting Refuge cation Selection ation Supply and Sanitation Syste es ms in Busoga (Bulange, Nang o, Itanda (Bubugo) and Kagu mba) UG-MWE-283144-CS-CQS / C onsultancy services for Prepa ration Of ESIA, SPP and RAP f Component 1: WSS in Small or 4No. Solar-Powered Water Towns and RGCs and Suppor Consultant Qualifi Under Implement IDA / 62760 Post Limited 420,000.00 0.00 2022-04-01 2022-03-30 2022-04-15 2022-05-15 2022-06-19 2022-12-16 Supply and Sanitation Syste t to Districts Hosting Refuge cation Selection ation ms in Mid Western Uganda ( es Bubanda, Nankondo, Rwentu ha, Kasaba, Kyampangara an d Nymushojwa ) UG-MWE-288263-CS-CQS / C Component 1: WSS in Small onsultancy services for finaliz Towns and RGCs and Suppor Consultant Qualifi Under Implement ation of engineering designs IDA / 62760 Post Limited 290,000.00 0.00 2022-04-28 2022-04-25 2022-05-12 2022-06-11 2022-07-16 2022-11-13 t to Districts Hosting Refuge cation Selection ation and tender documents for Al es a-Ora water supply and sanit ation system UG-MWE-297840-CS-CQS / C onsultancy Services for Feasi Component 1: WSS in Small bility Study, Detailed Enginee Towns and RGCs and Suppor Consultant Qualifi Under Implement ring Design and Bid Docume IDA / 62760 Post Limited 350,000.00 0.00 2022-06-10 2022-06-08 2022-06-24 2022-07-24 2022-08-28 2023-02-24 t to Districts Hosting Refuge cation Selection ation ntation for Solar Powered Pip es ed Water Supply and Sanitati on Systems in Refugee Hosti ng Districts of Arua and Moyo . Page 6 UG-MWE-298970-CS-CQS / C onsultancy Services for Desig Component 3: Water Resour Quality And Cost- IDA / 62760 Post Open - National 450,000.00 0.00 Under Review 2022-08-12 2022-08-05 2022-09-02 2022-10-16 2022-11-13 2022-12-13 2023-01-17 2023-02-21 2024-02-21 n of River Nyamwamba Maint ce Management Based Selection enance and Flood Protection Works INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MWE-71843-CS-INDV / Pr Component 4: Project Imple ocurement of an individual c Individual Consult Under Implement IDA / 62760 mentation and Institutional Post Open 405,000.00 0.00 2019-03-22 2019-03-20 2019-04-29 2019-05-13 2019-05-31 2025-05-30 onsultant for the position of P ant Selection ation Strengthening roject Technical Officer UG-MWE-71833-CS-INDV / Pr Component 4: Project Imple ocurement of an individual c Individual Consult Under Implement IDA / 62760 mentation and Institutional Post Open 405,000.00 0.00 2019-03-22 2019-03-20 2019-04-29 2019-05-13 2019-05-31 2025-05-30 onsultant for the position of E ant Selection ation Strengthening nvironment Specialist UG-MWE-72025-CS-INDV / Pr Component 4: Project Imple ocurement of an individual c Individual Consult IDA / 62760 mentation and Institutional Prior Open 405,000.00 0.00 Canceled 2019-02-15 2019-03-15 2019-03-25 2019-04-08 2019-04-26 2025-04-25 onsultant for the position of S ant Selection Strengthening ocial Safeguards Specialist UG-MWE-113006-CS-INDV / Component 4: Project Imple Procurement of an individual Individual Consult Under Implement IDA / 62760 mentation and Institutional Post Open 405,000.00 0.00 2019-05-17 2019-05-20 2019-07-03 2019-07-24 2019-08-28 2020-02-24 consultant for the position of ant Selection ation Strengthening Social Safeguards Specialist UG-MWE-71827-CS-INDV / Pr ocurement of an Individual c Component 4: Project Imple Individual Consult onsultant for the position of IDA / 62760 mentation and Institutional Prior Direct 270,000.00 0.00 Canceled 2018-11-23 2018-12-14 2018-12-28 2019-01-18 2025-01-17 ant Selection Assistant Procurement Speci Strengthening alist - Mr Vincent Okurut UG-MWE-113008-CS-INDV / Procurement of an Individual Component 4: Project Imple Individual Consult Under Implement consultant for the position of IDA / 62760 mentation and Institutional Post Direct 270,000.00 0.00 2019-05-07 2019-05-20 2019-05-17 2019-05-24 2019-06-28 2025-06-27 ant Selection ation Assistant Procurement Speci Strengthening alist - Mr Vincent Okurut UG-MWE-71426-CS-INDV / Pr ocurement of an Individual C Component 4: Project Imple Individual Consult onsultant for the position of F IDA / 62760 mentation and Institutional Prior Direct 450,000.00 0.00 Canceled 2018-11-23 2018-12-14 2018-12-28 2019-01-18 2025-01-17 ant Selection inancial Management Special Strengthening ist - Mr Sufiyian Igwahabi UG-MWE-113011-CS-INDV / Procurement of an Individual Component 4: Project Imple Individual Consult Consultant for the position of IDA / 62760 mentation and Institutional Post Direct 450,000.00 303,696.00 Signed 2019-05-07 2019-07-19 2019-05-17 2019-04-18 2019-05-31 2019-07-15 2019-06-28 2019-07-15 2025-06-27 ant Selection Financial Management Speci Strengthening alist - Mr Sufiyian Igwahabi UG-MWE-87286-CS-INDV / Pr ocurement of an Individual C Component 3: Water Resour Individual Consult onsultant for the position of IDA / 62760 Prior Direct 135,000.00 0.00 Canceled 2018-11-23 2018-12-14 2018-12-28 2019-01-18 2021-01-15 ce Management ant Selection Water Information System Sp ecialist- Mr Kirunda Deusdedi t UG-MWE-113012-CS-INDV / Procurement of an Individual Component 3: Water Resour Individual Consult Consultant for the position of IDA / 62760 Post Direct 135,000.00 230,134.80 Signed 2019-05-07 2019-05-20 2019-05-17 2019-04-18 2019-05-31 2019-07-15 2019-06-28 2019-07-15 2020-06-27 ce Management ant Selection Water Information System Sp ecialist- Mr Kirunda Deusdedi t UG-MWE-71820-CS-INDV / Pr ocurement of an Individual C Component 4: Project Imple Individual Consult onsultant for the position of IDA / 62760 mentation and Institutional Prior Direct 405,000.00 0.00 Canceled 2018-11-23 2018-12-14 2018-12-28 2019-01-18 2025-01-17 ant Selection Monitoring and Evaluation Sp Strengthening ecialist - Mr. Tonny Emmy A meny UG-MWE-113013-CS-INDV / Procurement of an Individual Component 4: Project Imple Individual Consult Consultant for the position of IDA / 62760 mentation and Institutional Post Direct 360,000.00 230,134.80 Signed 2019-05-09 2019-05-20 2019-05-19 2019-04-18 2019-06-02 2019-06-30 2019-07-15 2025-06-29 ant Selection Monitoring and Evaluation Sp Strengthening ecialist - Mr. Tonny Emmy A meny UG-MWE-71810-CS-INDV / Pr Component 4: Project Imple ocurement of an Individual C Individual Consult Under Implement IDA / 62760 mentation and Institutional Prior Open 405,000.00 0.00 2019-02-15 2019-07-21 2019-03-25 2020-02-24 2019-04-08 2019-04-26 2025-04-25 onsultant for the Position of a ant Selection ation Strengthening Procurement Specialist UG-MWE-117193-CS-CDS / P Component 1: WSS in Small reparation of Resettlement A Towns and RGCs and Suppor IDA / 62760 Post Direct Selection Direct 100,000.00 0.00 Canceled 2019-07-22 2019-08-01 2019-10-05 2020-04-02 ction Plans for the 16 large s t to Districts Hosting Refuge olar powered water supply sy es stems UG-MWE-130212-CS-CDS / P Component 1: WSS in Small reparation of Resettlement A Towns and RGCs and Suppor Under Implement IDA / 62760 Post Direct Selection Direct 200,000.00 0.00 2019-09-10 2019-10-21 2019-09-27 2019-12-01 2020-05-29 ction Plans for the 32 large s t to Districts Hosting Refuge ation olar powered water supply sy es stems UG-MWE-162976-CS-CDS / C Component 1: WSS in Small onsultancy services to carry Towns and RGCs and Suppor Under Implement out Geophysical Survey and IDA / 62760 Post Direct Selection Direct 32,589.00 0.00 2020-03-10 2020-03-10 2020-03-20 2020-05-19 2020-11-15 t to Districts Hosting Refuge ation Drilling Supervision of Produc es tion Wells In RGCs under IW MDP UG-MWE-180334-CS-INDV / Procurement of individual co Component 4: Project Imple nsultant for the position of Pr Individual Consult Under Implement IDA / 62760 mentation and Institutional Post Direct 365,000.00 0.00 2020-06-22 2020-10-14 2020-06-29 2020-07-13 2020-07-27 2024-12-31 oject Advisor/Project Manage ant Selection ation Strengthening ment Specialist for the Integr ated Water Management & D evelopment Project. UG-MWE-117178-CS-CDS / C onsultancy Services for Quali Component 3: Water Resour Under Implement ty Assurance of the roll out of IDA / 62760 Post Direct Selection Direct 300,000.00 0.00 2019-06-17 2020-10-07 2019-06-27 2019-08-31 2021-08-30 ce Management ation Water Information System in Victoria, Upper Nile, Albertin e and Kyoga WMZs Page 7 UG-MWE-187888-CS-CDS / C onsultancy Services for Envir onmental and Social Impact Component 1: WSS in Small Assessment (ESIA), RAP & So Towns and RGCs and Suppor Under Implement urce Protection Plans (SSP) fo IDA / 62760 Post Direct Selection Direct 60,000.00 0.00 2020-08-11 2021-01-22 2020-08-21 2020-10-25 2021-04-23 t to Districts Hosting Refuge ation r Large Solar Powered Piped es Water Supply Systems and S anitation Facilities in Refugee Settlement and Host Commu nities in Kiryandongo UG-MWE-211700-CS-CDS / C onsultancy for undertaking S Component 3: Water Resour Under Implement ocial and Environment Asses IDA / 62760 Post Direct Selection Direct 60,000.00 0.00 2021-01-07 2022-06-13 2021-01-17 2021-03-08 2021-03-14 ce Management ation sment for River Nyamwamba flood risk management activ ities UG-MWE-215916-CS-CDS / C onsultancy for Environmental and Social Impact Assessmen Component 1: WSS in Small t (ESIA), RAP & Source Protec Towns and RGCs and Suppor Under Implement tion Plans (SSP) for Large Sol IDA / 62760 Post Direct Selection Direct 100,000.00 0.00 2021-02-08 2021-06-18 2021-02-18 2021-04-24 2021-10-21 t to Districts Hosting Refuge ation ar Powered Piped Water Sup es ply Systems and Sanitation i n 5 RGCS of Bugomolwa, Kik onge-Nakasero, Lubaali ,Dam ba-Kalyambuzi and Kikooge UG-MWE-173608-CS-CQS / E nvironmental and Social Imp act Assessment (ESIA), RAP Component 1: WSS in Small & Source Protection Plans (S Towns and RGCs and Suppor Under Implement IDA / 62760 Post Direct Selection Direct 120,000.00 0.00 2021-02-08 2021-06-18 2021-02-22 2021-04-16 2021-10-13 SP) for Large Solar Powered t to Districts Hosting Refuge ation Piped Water Supply Systems es and Sanitation Facilities in 6 RGCS of Bugwara, Kabamba, Kikoora, Mwitanzige, Kasese and Lwentulege. UG-MWE-215886-CS-CDS / C onsultancy for Environmental and Social Impact Assessmen Component 1: WSS in Small t (ESIA), RAP & Source Protec Towns and RGCs and Suppor Under Implement IDA / 62760 Post Direct Selection Direct 100,000.00 0.00 2021-02-05 2021-06-18 2021-02-15 2021-04-21 2021-10-18 tion Plans (SSP) for Large Sol t to Districts Hosting Refuge ation ar Powered Piped Water Sup es ply Systems and Sanitation F acilities in 5 RGCS of Igwaya, Kidera, Kitenga, Lugala and B ukizibu UG-MWE-223407-CS-INDV / Component 4: Project Imple Procurement of an Individual Individual Consult Under Implement IDA / 62760 mentation and Institutional Post Open 147,000.00 0.00 2021-03-12 2021-04-27 2021-05-10 2021-05-31 2021-07-05 2024-12-16 consultant for the position of ant Selection ation Strengthening Assistant Procurement Speci alist for IWMDP UG-MWE-255501-CS-CDS / C onsultancy Services for carryi Component 1: WSS in Small ng out Engineering re-design Towns and RGCs and Suppor Under Implement IDA / 62760 Post Direct Selection Direct 298,000.00 0.00 2021-10-05 2021-10-01 2021-10-15 2021-12-19 2022-06-17 of Bwera and Dunguluha wat t to Districts Hosting Refuge ation er supplys for emergency rec es onstruction and rehabilitation UG-MWE-267736-CS-CDS / C onsultancy Services for Const Component 3: Water Resour Under Implement ruction Supervision of River IDA / 62760 Post Direct Selection Direct 150,000.00 0.00 2021-12-17 2021-12-15 2021-12-27 2022-03-02 2023-08-24 ce Management ation Nyamwamba Emergency Mai ntenance and Flood Protectio n Works UG-MWE-283152-CS-INDV / Component 4: Project Imple Procurement of an Individual Individual Consult Under Implement IDA / 62760 mentation and Institutional Post Open 168,750.00 0.00 2022-03-14 2022-03-13 2022-05-02 2022-05-23 2022-06-27 2024-12-31 Consultant for the position of ant Selection ation Strengthening Monitoring and Evaluation Sp ecialist. UG-MWE-211701-CS-CDS / C onsultancy for Design and Co Component 3: Water Resour nstruction Supervision of Dr IDA / 62760 Post Direct Selection Direct 450,000.00 0.00 Canceled 2021-01-07 2021-10-27 2021-01-17 2021-03-09 2021-07-07 ce Management edging and Flood Protection Works for River Nyamwamba Page 8