PROCUREMENT PLAN (Textual Part) Project information: Preparation of Proposed Sustainable Forests and Livelihood Project Project Implementation agency: Forest Department of Ministry of Environment and Forest, Bangladesh Date of the Procurement Plan: September 13, 2017 Period covered by this Procurement Plan: September 2017 to June 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the People’s Republic of Bangladesh (Public Procurement Act 2006 - PPA, 1st amendment to PPA (2009) and the Public Procurement Rules 2008, as amended in August 2009) , such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions : a) e-GP system of the country for national competitive bidding (NCB) shall be followed using Standard/Model Procurement documents satisfactory to the Bank b) Post bidding negotiations shall not be allowed with the lowest evaluated or any other bidder; c) Bids should be submitted and opened in public in one location immediately after the deadline for submission; d) Lottery in award of contracts shall not be allowed; e) Bidders’ qualification/experience requirement shall be mandatory f) Bids shall not be invited or rejected on the basis of percentage above or below the estimated cost. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). “Not Applicable” PROCUREMENT Bangladesh : Sustainable Forests & Livelihoods (SUFAL) Project PLAN General Information Country: Bangladesh Bank’s Approval Date of the Original Procurement Plan: 2020-10-11 2022-01-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161996 GPN Date: 2019-02-26 Project Name: Sustainable Forests & Livelihoods (SUFAL) Project Loan / Credit No: IDA / 63250 P Executing Agency(ies): ublic Works Department WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned WD 51 / Sub soil investigation for the construction of office building ,green house, staff dormitory Strengthening Collaborative Request for Single Stage - One 2020-12- ,nursery shed with seed IDA / 63250 Forest and Protected Areas Post Limited 10,420.00 3,691.26 Signed 2020-10-21 2020-11-11 2020-11-09 2020-11-24 Quotations Envelope 24 storage at Hathazari SFNTC, Management beat office and staff barrack at Rangunia and Beat office at Rawzan. WD 52 / Sub soil investigation for the construction of range office Strengthening Collaborative Request for Single Stage - One 2020-12- at Bashkhali, officer's IDA / 63250 Forest and Protected Areas Post Limited 5,955.00 3,443.19 Signed 2020-10-21 2020-11-10 2020-11-09 2020-11-12 Quotations Envelope 09 dormitory & staff barrack at Management Chattogram Sadar and staff barrack at Satkania WD 53 / Sub soil investigation for the Strengthening Collaborative Under construction of range office Request for Single Stage - One 2020-12- IDA / 63250 Forest and Protected Areas Post Limited 5,955.00 0.00 Implementat 2020-10-21 2020-10-25 2020-11-09 and beat office at Mirersorai Quotations Envelope 09 Management ion and staff barrack (2 nos) at Sitakundu. WD 54 / Sub soil investigation for the Strengthening Collaborative construction of beat cum Request for Single Stage - One 2020-12- IDA / 63250 Forest and Protected Areas Post Limited 7,442.00 5,336.40 Signed 2020-10-21 2020-12-20 2020-11-09 2020-12-29 check station & staff barrack Quotations Envelope 09 Management at Chokoria and staff barrack, range office at Coxbazar Sadar WD 55 / Sub soil investigation for the Strengthening Collaborative Request for Single Stage - One 2020-12- construction of staff barrack, IDA / 63250 Forest and Protected Areas Post Limited 7,442.00 5,336.40 Signed 2020-10-21 2020-12-20 2020-11-09 2020-12-29 Quotations Envelope 24 beat office at Ramu and Ukhia Management and beat office at Teknaf WD 56 / Sub soil investigation for the Strengthening Collaborative construction of Gazipur Request for Single Stage - One 2021-01- IDA / 63250 Forest and Protected Areas Post Limited 5,955.00 3,630.51 Signed 2020-11-22 2021-06-02 2020-12-10 2021-06-20 SFNTC main bldg, staff Quotations Envelope 10 Management dormitory, nursery shed cum seed storage and green house. WD 57 / Sub soil investigation for the construction of Gazipur SFNTC wildlife staff dormitory, Strengthening Collaborative Request for Single Stage - One 2020-12- kaliakoir range office, beat IDA / 63250 Forest and Protected Areas Post Limited 10,420.00 7,049.04 Signed 2020-10-21 2021-06-10 2020-11-09 2021-06-20 Quotations Envelope 24 office, staff barrack & Gazipur Management Sadar staff barrack , Kapasia camp office and Sripur Staff barrack. WD 58 / Sub soil investigation for the construction of Jassore SFNTC office building, staff Strengthening Collaborative Request for Single Stage - One 2020-12- dormitory, Nursery shed with IDA / 63250 Forest and Protected Areas Post Limited 10,420.00 1,586.18 Signed 2020-10-21 2020-11-04 2020-11-09 2020-12-21 Quotations Envelope 24 seed storage, DFO office Management building, Residence, and Jassore Sadar staff barrack, Green house. WD 59 / Sub soil investigation for the Strengthening Collaborative Request for Single Stage - One 2020-12- construction of Officer's IDA / 63250 Forest and Protected Areas Post Limited 2,980.00 2,903.12 Signed 2020-10-21 2021-09-28 2020-11-09 2021-10-07 Quotations Envelope 03 dormitory and Staff Barrack at Management Barishal Sadar. WD 61 / Sub soil investigation for the construction of range office, Strengthening Collaborative beat office, staff barrack at Request for Single Stage - One 2020-12- IDA / 63250 Forest and Protected Areas Post Limited 8,930.00 4,316.90 Signed 2020-10-21 2021-01-04 2020-11-09 2021-01-25 Charfasion & Doulatkhan Quotations Envelope 24 Management range office & Monpura Camp office and Tajimuddin Camp office. WD 62 / Sub soil investigation for the Strengthening Collaborative Pending Request for Single Stage - One 2020-11- construction of Panchagar- IDA / 63250 Forest and Protected Areas Post Limited 1,490.00 0.00 Implementat 2020-10-21 2020-11-09 Quotations Envelope 29 Debigonj Range office, Management ion Debigonj. WD 63 / Sub soil investigation for the Strengthening Collaborative Under Request for Single Stage - One 2020-12- construction of Jhinaigati IDA / 63250 Forest and Protected Areas Post Limited 2,980.00 0.00 Implementat 2020-10-21 2020-12-14 2020-11-09 Quotations Envelope 03 range office and Sribordi staff Management ion barrack. WD 64 / Sub soil Strengthening Collaborative investigation for the Request for Single Stage - One 2020-12- IDA / 63250 Forest and Protected Areas Post Limited 5,955.00 566.00 Signed 2020-10-21 2020-11-02 2020-11-09 2020-11-12 construction of staff barrack Quotations Envelope 09 Management (2 nos) at Shapaher, Naogaon. Page 1 WD 65 / Sub soil investigation for the Strengthening Collaborative Request for Single Stage - One 2020-12- construction of , kamalganj IDA / 63250 Forest and Protected Areas Post Limited 5,955.00 2,936.49 Signed 2020-10-21 2021-01-18 2020-11-09 2021-02-04 Quotations Envelope 09 camp office, beat office and Management Juri staff barrack. WD 66 / Sub soil investigation for the construction of Ghatail range Strengthening Collaborative Request for Single Stage - One 2020-12- office & Shakhipur camp IDA / 63250 Forest and Protected Areas Post Limited 7,442.00 1,874.83 Signed 2020-10-21 2020-10-28 2020-11-09 2020-12-08 Quotations Envelope 09 office, staff barrack , beat Management office and Modhupur staff barrack WD 67 / Sub soil Strengthening Collaborative investigation of Thakurgaon Request for Single Stage - One 2020-11- IDA / 63250 Forest and Protected Areas Post Limited 1,490.00 1,122.48 Signed 2020-10-21 2020-12-07 2020-11-09 2020-12-15 Sadar - Pirgonj Beat office, Quotations Envelope 29 Management Thakurgaon Sadar. WD 68 / Sub soil investigation for the Strengthening Collaborative construction of Sadar officer's Request for Single Stage - One 2020-12- IDA / 63250 Forest and Protected Areas Post Limited 7,442.00 7,098.88 Signed 2020-10-21 2020-11-12 2020-11-09 2020-11-30 dormitory, DFO office & beat Quotations Envelope 09 Management office and Fulbaria staff barrack WD 69 / Sub soil Strengthening Collaborative Pending investigation for the Request for Single Stage - One 2020-11- IDA / 63250 Forest and Protected Areas Post Limited 1,490.00 0.00 Implementat 2020-10-21 2020-11-09 construction of Laksmipur Quotations Envelope 29 Management ion sadar-Bhabanigonj Beat office. WD 70 / Sub soil investigation for the Strengthening Collaborative Under construction of Noakhali Request for Single Stage - One 2020-12- IDA / 63250 Forest and Protected Areas Post Limited 5,955.00 0.00 Implementat 2020-10-21 2020-10-18 2020-11-09 Sadar DFO residence & Hatia Quotations Envelope 09 Management ion Camp office (2 nos) and Hatia staff barrack. WD 71 / Sub soil investigation for the Strengthening Collaborative Pending Request for Single Stage - One 2020-12- construction of Patuakhali IDA / 63250 Forest and Protected Areas Post Limited 4,465.00 0.00 Implementat 2020-10-21 2020-11-09 Quotations Envelope 03 camp office, Sadar DFO Management ion building and Staff barrack. WD 72 / Sub soil investigation for the Strengthening Collaborative Pending Request for Single Stage - One 2020-12- construction of Amtoli camp IDA / 63250 Forest and Protected Areas Post Limited 4,465.00 0.00 Implementat 2020-10-21 2020-11-09 Quotations Envelope 03 office and Pathorghata camp Management ion office, staff barrack. WD 73 / Sub soil investigation for the Strengthening Collaborative Pending Request for Single Stage - One 2020-12- construction of Madhabpur IDA / 63250 Forest and Protected Areas Post Limited 4,465.00 0.00 Implementat 2020-10-21 2020-11-09 Quotations Envelope 03 beat office and Chunarughat Management ion staff barrack (2 nos). WD 74 / Sub soil Strengthening Collaborative investigation for the Request for Single Stage - One 2020-11- IDA / 63250 Forest and Protected Areas Post Limited 1,490.00 1,283.94 Signed 2020-10-21 2020-12-09 2020-11-09 2021-01-10 construction of Shunamgonj- Quotations Envelope 29 Management Chatak Beat office. WD 75 / Sub soil Strengthening Collaborative investigation for the Request for Single Stage - One 2020-11- IDA / 63250 Forest and Protected Areas Post Limited 1,490.00 1,389.72 Signed 2020-10-21 2021-06-13 2020-11-09 2021-06-20 construction of CCF's Quotations Envelope 29 Management Banglow. WD 77 / Digital survey for the construction of office bldg, green house, staff dormitory, Strengthening Collaborative nursery shed with seed Request for Single Stage - One 2020-11- IDA / 63250 Forest and Protected Areas Post Limited 2,085.00 530.69 Signed 2020-10-21 2020-11-11 2020-11-09 2020-11-24 storage at Hathazari & beat Quotations Envelope 19 Management office, staff barrack at Rangunia and beat office at Rawzan WD 78 / Digital survey for the construction of range office Strengthening Collaborative at Bashkhali & officer's Request for Single Stage - One 2020-11- IDA / 63250 Forest and Protected Areas Post Limited 1,192.00 472.23 Signed 2020-10-21 2020-11-04 2020-11-09 2020-11-11 dormitory, staff barrack at Quotations Envelope 19 Management Chattogram Sadar and staff barrack at Satkania WD 79 / Digital survey for the constructionof range office, Strengthening Collaborative Request for Single Stage - One 2020-11- beat office at Mirersorai and IDA / 63250 Forest and Protected Areas Post Limited 1,192.00 872.69 Signed 2020-10-21 2021-01-14 2020-11-09 2021-02-02 Quotations Envelope 19 staff barrack (2 nos) at Management Sitakundu WD 80 / Digital survey for the construction of beat cum check station, staff barrack at Strengthening Collaborative Chokoria, staff barrack, range Request for Single Stage - One 2020-11- IDA / 63250 Forest and Protected Areas Post Limited 2,980.00 2,358.63 Signed 2020-10-21 2020-12-01 2020-11-09 2020-12-14 office at Coxbazar Sadar, staff Quotations Envelope 19 Management barrack, beat office at Ramu and Ukhia and beat office at Teknaf. WD 81 / Digital survey for Gazipur SFNTC main bldg, staff dormitory, nursery shed, green house, Gazipur SFNTC Strengthening Collaborative wildlife staff dormitory, Request for Single Stage - One 2020-12- IDA / 63250 Forest and Protected Areas Post Limited 3,275.00 2,846.00 Signed 2020-11-22 2021-06-10 2020-12-10 2021-06-20 kaliakoir range office, beat Quotations Envelope 20 Management office, staff barrack, Gazipur Sadar staff barrack, Kapasia camp Office and Sripur Staff barrack. Page 2 WD 82 / Digital survey for the construction of Jassore SFNTC office building, staff Strengthening Collaborative dormitory, Nursery shed with Request for Single Stage - One 2020-11- IDA / 63250 Forest and Protected Areas Post Limited 2,085.00 386.10 Signed 2020-10-21 2020-11-04 2020-11-09 2020-12-21 seed storage, DFO office Quotations Envelope 19 Management building, Residence and Jassore Sadar staff barrack, Green house. WD 83 / Digital survey for the Strengthening Collaborative construction of Officer's Request for Single Stage - One 2020-11- IDA / 63250 Forest and Protected Areas Post Limited 597.00 583.41 Signed 2020-10-21 2021-10-03 2020-11-09 2021-10-17 dormitory and Staff Barrack at Quotations Envelope 19 Management Barishal Sadar WD 85 / Digital survey for the construction of range office, beat office, staff barrack at Strengthening Collaborative Request for Single Stage - One 2020-11- Charfasion & Doulatkhan IDA / 63250 Forest and Protected Areas Post Limited 1,786.00 764.08 Signed 2020-10-21 2021-01-04 2020-11-09 2021-01-25 Quotations Envelope 19 range office & Monpura Camp Management office and Tajimuddin Camp office WD 86 / Digital survey for the Strengthening Collaborative construction of Jhinaigati Request for Single Stage - One 2020-11- IDA / 63250 Forest and Protected Areas Post Limited 597.00 479.04 Signed 2020-10-21 2020-12-14 2020-11-09 2020-12-30 range office and Sribordi staff Quotations Envelope 19 Management barrack. WD 87 / Digital survey for the Strengthening Collaborative Request for Single Stage - One 2020-11- construction of staff barrack IDA / 63250 Forest and Protected Areas Post Limited 1,192.00 235.50 Signed 2020-10-21 2020-11-12 2020-11-09 2020-11-12 Quotations Envelope 19 (2 nos) at Shapaher, Naogaon. Management WD 88 / Digital survey for the Strengthening Collaborative construction of kamaganj Request for Single Stage - One 2020-11- IDA / 63250 Forest and Protected Areas Post Limited 1,192.00 577.23 Signed 2020-10-21 2021-01-21 2020-11-09 2021-02-04 camp office and beat office Quotations Envelope 19 Management and Juri staff barrack. WD 89 / Digital survey for the construction of Ghatail range Strengthening Collaborative office & Shakhipur camp Request for Single Stage - One 2020-11- IDA / 63250 Forest and Protected Areas Post Limited 1,490.00 1,108.56 Signed 2020-10-21 2020-10-28 2020-11-09 2020-12-08 office, staff barrack , beat Quotations Envelope 19 Management office, and Modhupur staff barrack. WD 90 / Digital survey for the construction of Sadar officer's Strengthening Collaborative Request for Single Stage - One 2020-11- dormitory, DFO office gazipur IDA / 63250 Forest and Protected Areas Post Limited 1,490.00 990.51 Signed 2020-10-21 2020-11-23 2020-11-09 2020-11-30 Quotations Envelope 19 sadar, beat office and Fulbaria Management staff barrack. WD 91 / Digital survey for the construction of Noakhali Strengthening Collaborative Request for Single Stage - One 2020-11- Sadar DFO residence & Hatia IDA / 63250 Forest and Protected Areas Post Limited 1,192.00 1,160.74 Signed 2020-10-21 2020-11-03 2020-11-09 2020-12-07 Quotations Envelope 19 Camp office (2 nos) and Hatia Management staff barrack WD 92 / Digital survey for the Strengthening Collaborative Pending construction of Patuakhali Request for Single Stage - One 2020-11- IDA / 63250 Forest and Protected Areas Post Limited 895.00 0.00 Implementat 2020-10-21 2020-11-09 camp office, Sadar DFO Quotations Envelope 19 Management ion building and Staff barrack. WD 93 / Digital survey for the Strengthening Collaborative Pending construction of Amtoli camp Request for Single Stage - One 2020-11- IDA / 63250 Forest and Protected Areas Post Limited 895.00 0.00 Implementat 2020-10-21 2020-11-09 office and Pathorghata camp Quotations Envelope 19 Management ion office and staff barrack. WD 94 / Digital survey for the Strengthening Collaborative construction of Madhabpur Request for Single Stage - One 2020-11- IDA / 63250 Forest and Protected Areas Post Limited 895.00 716.59 Signed 2020-10-21 2020-11-11 2020-11-09 2020-11-17 beat office, Chunarughat staff Quotations Envelope 19 Management barrack (2 nos). WD 47 (CIVIL) / Construction for the Banobhaban HQ Strengthening Collaborative Single Stage - One 1,034,013.8 2022-04- vertical Expansion (2 floors: IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1,170,238.00 Signed 2021-01-25 2021-02-01 2021-02-08 2021-03-10 2021-03-07 2021-03-24 2021-03-31 2021-04-12 2021-05-04 Envelope 5 19 Civil, sanitary and Internal Management Electrification) WD 2 / Construction of Beat office, staff barrack with earth Strengthening Collaborative Single Stage - One 2022-04- work, boundary wall, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 212,517.00 209,558.39 Signed 2021-02-01 2021-06-03 2021-02-08 2021-03-01 2021-06-21 2021-03-22 2021-08-03 2021-04-05 2021-09-28 Envelope 12 approach road, small culvert Management etc at Rangunia,Chattogram. WD 3 / Construction of Beat office with earth work, Strengthening Collaborative Single Stage - One 2022-03- boundary wall, approach road, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 90,828.00 89,224.19 Signed 2021-02-01 2021-06-03 2021-02-08 2021-03-01 2021-06-21 2021-03-03 2021-07-18 2021-03-17 2021-09-26 Envelope 24 small culvert etc at Rawjan, Management Chattogram. WD 4 / Construction of range office with earth work, Strengthening Collaborative Pending Single Stage - One 2022-04- boundary wall, approach road, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 149,323.00 0.00 Implementat 2021-02-01 2021-02-08 2021-03-01 2021-03-22 2021-04-05 Envelope 12 small culvert etc at Bashkhali, Management ion Chattogram. WD 6 / Construction of Staff barrack with earth work, Strengthening Collaborative Single Stage - One 2022-04- boundary wall, approach road, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 128,811.00 117,032.58 Signed 2021-02-01 2021-06-02 2021-02-08 2021-03-01 2021-06-20 2021-03-22 2021-06-20 2021-04-05 2021-09-30 Envelope 12 small culvert etc at Satkania, Management Chattogram. WD 26 / Construction of staff barrack (2 nos) with Earth Strengthening Collaborative Single Stage - One 2022-04- work, boundary wall, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 240,476.00 153,860.26 Signed 2021-02-01 2021-03-09 2021-02-08 2021-03-01 2021-03-25 2021-03-22 2021-05-19 2021-04-05 2021-06-10 Envelope 12 approach road, small culvert Management etc at Shapaher, Naogaon. WD 32 / Construction of Beat office with Earth work, Strengthening Collaborative Pending Single Stage - One 2022-04- boundary wall, approach road, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 94,581.00 0.00 Implementat 2021-02-01 2021-02-08 2021-03-01 2021-03-22 2021-04-05 Envelope 12 small culvert etc at Management ion Thakurgaon Sadar. Page 3 WD 7 / Construction of Range office, Beat office with Strengthening Collaborative Single Stage - One 2022-04- earth work, boundary wall, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 228,788.00 228,217.31 Signed 2021-02-01 2021-05-11 2021-02-08 2021-03-01 2021-05-31 2021-03-22 2021-06-28 2021-04-05 2021-07-19 Envelope 12 approach road, small culvert Management etc at Mirersorai, Chattogram. WD 8 / Construction of Sitakundu Staff barrack and Strengthening Collaborative Foujdarhat Staff barrack with Single Stage - One 2022-04- IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 239,514.00 234,914.83 Signed 2021-02-01 2021-05-11 2021-02-08 2021-03-01 2021-05-31 2021-03-22 2021-06-24 2021-04-05 2021-07-26 earth work, boundary wall, Envelope 12 Management approach road, small culvert etc at Sitakundu ,Chattogram. WD 30 / Construction of Range office at Ghatail and Strengthening Collaborative Camp office, Staff barrack at Single Stage - One 2022-04- IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 438,523.00 431,593.81 Signed 2021-02-01 2021-05-05 2021-02-08 2021-03-01 2021-06-03 2021-03-22 2021-07-11 2021-04-05 2021-08-23 Shakhipur with Earth work, Envelope 12 Management boundary wall, approach road, small culvert etc in Tangail WD 16 / Construction of Staff National barrack with Earth work, Strengthening Collaborative Procurement Pending Single Stage - One 2022-10- boundary wall, approach road, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 129,894.00 0.00 Implementat 2021-08-16 2021-08-23 2021-09-13 2021-10-04 2021-10-18 Envelope 25 small culvert etc at Gazipur Management Envelope process ion sadar. (Non Bank-SPD) WD 17 / Construction of National Camp office at Kapasia and Strengthening Collaborative Procurement Pending Staff barrack at Sripur with Single Stage - One 2022-10- IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 217,397.00 0.00 Implementat 2021-08-16 2021-08-23 2021-09-13 2021-10-04 2021-10-18 Earth work, boundary wall, Envelope 25 Management Envelope process ion approach road, small culvert (Non Bank-SPD) etc in Gazipur. WD 24 / Construction of National Range office with Earth work, Strengthening Collaborative Procurement Under Single Stage - One 2022-10- boundary wall, approach road, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 144,335.00 0.00 Implementat 2021-08-16 2021-08-31 2021-08-23 2021-09-13 2021-10-04 2021-10-18 Envelope 25 small culvert etc at Jhinaigati, Management Envelope process ion Sherpur. (Non Bank-SPD) WD 25 / Construction of Staff National barrack with Earth work, Strengthening Collaborative Procurement Pending Single Stage - One 2022-10- boundary wall, approach road, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 123,605.00 0.00 Implementat 2021-08-16 2021-08-23 2021-09-13 2021-10-04 2021-10-18 Envelope 25 small culvert etc at Sribordi, Management Envelope process ion Sherpur. (Non Bank-SPD) WD 28 / Construction of National Camp office and beat office Strengthening Collaborative Procurement Pending with Earth work, boundary Single Stage - One 2022-10- IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 179,069.00 0.00 Implementat 2021-08-16 2021-08-23 2021-09-13 2021-10-04 2021-10-18 wall, approach road, small Envelope 25 Management Envelope process ion culvert etc. at Komolgonj, (Non Bank-SPD) Moulovibazar. WD 29 / Construction of Staff National barrack with Earth work, Strengthening Collaborative Procurement Pending Single Stage - One 2022-10- boundary wall, approach road, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 128,363.00 0.00 Implementat 2021-08-16 2021-08-23 2021-09-13 2021-10-04 2021-10-18 Envelope 25 small culvert etc. at Juri, Management Envelope process ion Moulovibazar. (Non Bank-SPD) WD 35 / Construction of Staff National barrack with Earth work, Strengthening Collaborative Procurement Pending Single Stage - One 2022-10- boundary wall, approach road, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 128,086.00 0.00 Implementat 2021-08-16 2021-08-23 2021-09-13 2021-10-04 2021-10-18 Envelope 25 small culvert etc. at Fulbaria, Management Envelope process ion Mymensing. (Non Bank-SPD) WD 9 / Construction of Beat National cum Check Station & Staff Strengthening Collaborative Procurement Pending barrack with earth work, Single Stage - One 2023-01- IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 237,976.00 0.00 Implementat 2021-10-11 2021-10-18 2021-11-08 2021-11-29 2022-01-03 boundary wall, approach road, Envelope 10 Management Envelope process ion small culvert etc at Chokoria, (Non Bank-SPD) Cox's Bazar WD 11 / Construction of Staff National barrack, Beat office with earth Strengthening Collaborative Procurement Pending Single Stage - One 2023-01- work, boundary wall, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 209,048.00 0.00 Implementat 2021-10-11 2021-10-18 2021-11-08 2021-11-29 2022-01-03 Envelope 10 approach road, small culvert Management Envelope process ion etc at Ramu, Cox's Bazar. (Non Bank-SPD) WD 12 / Construction of Staff National barrack, Beat office with earth Strengthening Collaborative Procurement Pending Single Stage - One 2023-01- work, boundary wall, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 220,952.00 0.00 Implementat 2021-10-11 2021-10-18 2021-11-08 2021-11-29 2022-01-03 Envelope 10 approach road, small culvert Management Envelope process ion etc at Ukhia, Cox's Bazar. (Non Bank-SPD) WD 13 / Construction of National beat Office with earth work, Strengthening Collaborative Procurement Pending 2023-01- boundary wall, approach road, IDA / 63250 Forest and Protected Areas Post Request for Bids Document - 1 98,500.00 0.00 Implementat 2021-10-11 2021-10-18 2021-11-08 2021-11-29 2022-01-03 10 small culvert etc at Teknaf, Management Envelope process ion Cox's Bazar. (Non Bank-SPD) WD 19 / Construction of National Officer's dormitory, staff Strengthening Collaborative Procurement Pending Single Stage - One 2023-01- barrack with Earth work, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 288,298.00 0.00 Implementat 2021-10-11 2021-10-18 2021-11-08 2021-11-29 2022-01-03 Envelope 10 boundary wall, approach road, Management Envelope process ion small culvert etc at Barishal (Non Bank-SPD) WD 31 / Construction of Staff National barrack with Earth work, Strengthening Collaborative Procurement Pending Single Stage - One 2023-01- boundary wall, approach road, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 134,536.00 0.00 Implementat 2021-10-11 2021-10-18 2021-11-08 2021-11-29 2022-01-03 Envelope 10 small culvert etc at Management Envelope process ion Modhupur, Tangail. (Non Bank-SPD) WD 42 / Construction of Beat National office with Earth work, Strengthening Collaborative Procurement Pending Single Stage - One 2023-01- boundary wall, approach road, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 103,214.00 0.00 Implementat 2021-10-11 2021-10-18 2021-11-08 2021-11-29 2022-01-03 Envelope 10 small culvert etc at Management Envelope process ion Madhabpur, Hobigonj. (Non Bank-SPD) WD 44 / Construction of Beat National office with Earth work, Strengthening Collaborative Procurement Pending Single Stage - One 2023-01- boundary wall, approach road, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 96,012.00 0.00 Implementat 2021-10-11 2021-10-18 2021-11-08 2021-11-29 2022-01-03 Envelope 10 small culvert etc at Chatak, Management Envelope process ion Sunamganj (Non Bank-SPD) Page 4 WD 45 / Construction of National CCF's Banglow including Civil Strengthening Collaborative Procurement Pending Works, ESMP, Internal Sanitary Single Stage - One 2023-01- IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 229,595.00 0.00 Implementat 2021-10-11 2021-10-18 2021-11-08 2021-11-29 2022-01-03 and Water Supply and Internal Envelope 10 Management Envelope process ion Electrification work at Mirpur, (Non Bank-SPD) Dhaka WD 37 / Construction of DFO National residence with Earth work, Strengthening Collaborative Procurement Pending Single Stage - One 2023-01- boundary wall, approach road, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 185,571.00 0.00 Implementat 2021-10-11 2021-10-18 2021-11-08 2021-11-29 2022-01-03 Envelope 10 small culvert etc at Noakhali Management Envelope process ion sadar. (Non Bank-SPD) WD 60 / Sub soil investigation for the Strengthening Collaborative construction of DFO office Request for Single Stage - One 2020-12- IDA / 63250 Forest and Protected Areas Post Limited 5,955.00 0.00 Canceled 2020-10-21 2020-11-09 building and Staff Barrack (2 Quotations Envelope 09 Management nos) at Dinajpur Sadar and beat office at Nawabganj. WD 84 / Digital survey for the construction of DFO office Strengthening Collaborative Request for Single Stage - One 2020-11- building and Staff Barrack (2 IDA / 63250 Forest and Protected Areas Post Limited 1,192.00 0.00 Canceled 2020-10-21 2020-11-09 Quotations Envelope 19 nos) at Dinajpur Sadar and Management beat office at Nawabganj. WD 34 / Construction of National Staff barrack, beat office with Strengthening Collaborative Procurement Earth work, boundary wall, Single Stage - One 2022-10- IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 209,790.00 0.00 Canceled 2021-08-16 2021-08-23 2021-09-13 2021-10-04 2021-10-18 approach road, small culvert Envelope 25 Management Envelope process etc. at Muktagacha, (Non Bank-SPD) Mymensing . WD 108 / Digital Survey for the construction of office Strengthening Collaborative Request for Pending Request for Single Stage - One 2022-02- bldg, greenhouse, staff IDA / 63250 Forest and Protected Areas Post Limited Quotations (Non 1,191.00 0.00 Implementat 2021-12-15 2022-01-02 Quotations Envelope 01 dormitory, nursery shed with Management Bank-SPD) ion seed storage at Patiya SFNTC WD 76 / Sub soil Strengthening Collaborative Request for investigation for the Request for Single Stage - One 2020-11- IDA / 63250 Forest and Protected Areas Post Limited Quotations (Non 1,490.00 0.00 Canceled 2020-10-21 2020-11-09 construction of Chattogram Quotations Envelope 29 Management Bank-SPD) Town-Agrabad Staff Quarter. WD 1 / Construction of office building of officer-in-charge, staff dormitory, nursery shed Strengthening Collaborative with seed storage and green Single Stage - One 2022-04- IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 382,535.00 0.00 Canceled 2021-02-01 2021-02-08 2021-03-01 2021-03-22 2021-04-05 house with earth work, Envelope 12 Management boundary wall, approach road, small culvert etc at Olinagar, Hathazari, Chattogram. WD-84 / Digital Survey for the construction of DFO office Strengthening Collaborative Request for Pending building and one Staff Barrack Request for Single Stage - One 2022-02- IDA / 63250 Forest and Protected Areas Post Limited Quotations (Non 1,190.00 0.00 Implementat 2021-12-30 2022-01-17 at Dinajpur Sadar and beat Quotations Envelope 16 Management Bank-SPD) ion office and one Staff Barrack at Birampur, Dinajpur WD 110 / Digital Survey for the construction of Staff Strengthening Collaborative Request for Pending Barrack at Mymensingh Sadar, Request for Single Stage - One 2022-02- IDA / 63250 Forest and Protected Areas Post Limited Quotations (Non 893.00 0.00 Implementat 2021-12-30 2022-01-17 Beat Office at Bhaluka and Quotations Envelope 16 Management Bank-SPD) ion Range Office at Muktagacha, Mymensingh WD-34 / Construction of National Range Office with Earth work, Strengthening Collaborative Procurement Pending Single Stage - One 2023-05- boundary wall, approach road, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 150,393.00 0.00 Implementat 2022-02-20 2022-02-27 2022-03-20 2022-04-10 2022-04-24 Envelope 01 small culvert etc. at Rasulpur, Management Envelope process ion Muktagacha, Mymensing (Non Bank-SPD) WD 101 / Sub soil Strengthening Collaborative Request for Pending investigation for the Request for Single Stage - One 2022-02- IDA / 63250 Forest and Protected Areas Post Limited Quotations (Non 1,488.00 0.00 Implementat 2021-12-30 2022-01-17 construction of range office Quotations Envelope 16 Management Bank-SPD) ion at Rangunia, Chattogram WD 111 / Subsoil Strengthening Collaborative Request for Pending investigation for the Request for Single Stage - One 2022-02- IDA / 63250 Forest and Protected Areas Post Limited Quotations (Non 1,488.00 0.00 Implementat 2021-12-30 2022-01-17 construction of Staff Barrack Quotations Envelope 16 Management Bank-SPD) ion at Hathazari, Chattogram WD-1 / Construction of office building of officer-in-charge, National staff dormitory, nursery shed Strengthening Collaborative Procurement Pending with seed storage and Single Stage - One 2023-05- IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 382,535.00 0.00 Implementat 2022-02-20 2022-02-27 2022-03-20 2022-04-10 2022-04-24 greenhouse with earthwork, Envelope 01 Management Envelope process ion boundary wall, approach road, (Non Bank-SPD) small culvert etc at Patiya, Chattogram. WD-76 / Sub soil investigation for the Strengthening Collaborative Request for Pending construction of Staff Quarter Request for Single Stage - One 2022-02- IDA / 63250 Forest and Protected Areas Post Limited Quotations (Non 1,488.00 0.00 Implementat 2021-12-30 2022-01-17 at Chattogram Forest Quotations Envelope 16 Management Bank-SPD) ion Academy, Solosohor, Chattogram WD-60 / Subsoil investigation for the construction of DFO office Strengthening Collaborative Request for Pending Request for Single Stage - One 2022-02- building, one Staff Barrack at IDA / 63250 Forest and Protected Areas Post Limited Quotations (Non 5,952.00 0.00 Implementat 2021-12-30 2022-01-17 Quotations Envelope 16 Dinajpur Sadar and beat Management Bank-SPD) ion office, one Staff Barrack at Birampur, Dinajpur WD 102 / Sub soil Strengthening Collaborative Request for Pending investigation for the Request for Single Stage - One 2022-02- IDA / 63250 Forest and Protected Areas Post Limited Quotations (Non 1,488.00 0.00 Implementat 2021-12-30 2022-01-17 construction of Beat Office at Quotations Envelope 16 Management Bank-SPD) ion Sapaher, Naogaon Page 5 WD 4A / Construction of National range office with earth work, Strengthening Collaborative Procurement Pending Single Stage - One 2023-05- boundary wall, approach road, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 150,393.00 0.00 Implementat 2022-02-20 2022-02-28 2022-03-21 2022-04-11 2022-04-25 Envelope 02 small culvert etc at Rangunia, Management Envelope process ion Chattogram. (Non Bank-SPD) WD 26-A / Construction of National Beat office with earth work, Strengthening Collaborative Procurement Pending Single Stage - One 2023-05- boundary wall, approach road, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 93,524.00 0.00 Implementat 2022-02-20 2022-02-27 2022-03-20 2022-04-10 2022-04-24 Envelope 01 small culvert etc at Shrionti, Management Envelope process ion Shapaher, Naogaon (Non Bank-SPD) WD 105 / Sub soil investigation for the construction of Staff Barrack Strengthening Collaborative Request for Pending Request for Single Stage - One 2022-02- at Mymensingh Sadar, Beat IDA / 63250 Forest and Protected Areas Post Limited Quotations (Non 4,464.00 0.00 Implementat 2021-12-30 2022-01-17 Quotations Envelope 16 Office at Bhaluka and Range Management Bank-SPD) ion Office at Muktagacha, Mymensingh WD 103 / Subsoil investigation for the Strengthening Collaborative Request for Pending construction of office bldg, Request for Single Stage - One 2022-02- IDA / 63250 Forest and Protected Areas Post Limited Quotations (Non 5,952.00 0.00 Implementat 2021-12-30 2022-01-17 greenhouse, staff dormitory, Quotations Envelope 16 Management Bank-SPD) ion nursery shed with seed storage at Patiya SFNTC WD 10 / Construction of Staff Barrack at Cox'sBazar Sadar Forest Colony, Range office at National PM Khali Range, Cox'sBazar Strengthening Collaborative Procurement Pending Single Stage - One 2023-03- Sadar and Beat office at IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 352,155.00 0.00 Implementat 2022-01-05 2022-01-12 2022-02-02 2022-02-23 2022-03-17 Envelope 24 Kosturaghat, Cox'sbazar with Management Envelope process ion earthwork, boundary wall, (Non Bank-SPD) approach road, small culvert etc. WD 14 / Construction of Office Building of Officer-in- National Charge, staff dormitory, Strengthening Collaborative Procurement Pending nursery shed cum seed Single Stage - One 2023-04- IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 383,750.00 0.00 Implementat 2022-01-24 2022-01-31 2022-02-21 2022-03-14 2022-04-05 storage and greenhouse Envelope 12 Management Envelope process ion Earthwork and construction of (Non Bank-SPD) boundary wall, approach road, small culvert, etc at Gazipur WD 23 / Construction of National Range office with Earth work, Strengthening Collaborative Procurement Pending Single Stage - One 2023-04- boundary wall, approach road, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 145,595.00 0.00 Implementat 2022-01-24 2022-02-01 2022-02-22 2022-03-15 2022-04-06 Envelope 13 small culvert etc at Debigonj, Management Envelope process ion Panchagar (Non Bank-SPD) WD 47-E/M / Vertical National extension of lifts (4 nos.) Strengthening Collaborative Procurement Pending Single Stage - One 2023-04- (Electrical works) in IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National Document - 1 101,785.00 0.00 Implementat 2022-01-17 2022-01-24 2022-02-14 2022-03-07 2022-03-29 Envelope 05 BanoBhaban Head Quarter at Management Envelope process ion Agargaon, Dhaka (Non Bank-SPD) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 6