Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: January 10, 2017 (Original procurement plan). 2. Date of General Procurement Notice: NA 3. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. Goods Above US$ 4 million All 2. Works Above US$ 15 million All 3. Non-Consultant Services Above US$ 4 million All 2. Prequalification. NA. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: The Project Implementation Manual (PIM) makes reference to all applicable procurement guidelines and manuals including the Commune/Sangkat Fund PIM for small-scale infrastructure activities carried out by the sub-national levels (Commune/Sangkat), has been developed for this project. 4. Any Other Special Procurement Arrangements: 5 packages (goods) would be financed under retroactive financing 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness. 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comments No. on ed stic by Bank Cost Prefe (Prior / US$ rence Post) million (yes/ no) Communi 5.48 60 No Post procured by ty Communes/ June 12, 2017 infrastruc Sangkats tures individually for the whole life of the project Procure 0.92 8 No Post will be ment of procured vehicles, centrally at office the beginning of equipme project nt, office implementa furniture, tion motorcyc (shopping les, etc. method) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Selection of Consulting firms Above US$ 2 million All 2. Selection of Individual Above US$ All Consultant 400,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: 11 individual consultants would be financed through retroactive financing. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 6 7 Ref. Description Estimate Pac Review Comments No. d kag by Bank Cost es (Prior / US$ Post) million Producer Group 0.34 1 Post QCBS method Mobilization for June 12, 2017 Siem Reap (NGO package) Self-help Group 0.27 1 Post QCBS method Mobilization for SRP (NGO) Human Resources 0.92 2 Post QBS method Development Services Provider (HRDSP) for Siem Reap (NGO/Firm) Consulting firms for 0.175 1 Post CQS method baseline survey, impact survey, and final impact survey, and External financial auditing Individual 2.93 126 Post Selection of consultants for individual supporting the consultant. national level and sub-national level project entities (finance, procurement, infrastructure, community development, micro-finance experts, livelihood specialists, etc.) June 12, 2017 PROCUREMENT Cambodia : KH - Livelihood Enhancement and Association of the Poor Project (LEAP) PLAN General Information Country: Cambodia Bank’s Approval Date of the Original Procurement Plan: 2017-06-12 2022-03-11 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153591 GPN Date: Project Name: KH - Livelihood Enhancement and Association of the Poor Project (LEAP) Loan / Credit No: IDA / 59600 Ministry of Interior Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Document Amount Amount Document / and Recommendation Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion Type (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Pending KH-MOI-99874-CW-RFQ / Component 3: Project Request for Single Stage - One 2019-03- 2019-04- 2019-05- IDA / 59600 Post Open - National 30,000.00 0.00 Implementa Office Renovation at PCO-MOI Management Quotations Envelope 06 17 17 tion KH-MOI-99875-CW-CDD / The rehabilitation laterite Component 1: Improving Pending road (Length 2400m, Width Community Driven 2019-04- 2019-05- 2019-05- 2019-05- 2019-06- 2019-09- IDA / 59600 Livelihoods for Rural Poor Post Open - National 28,341.00 0.00 Implementa 4.00m, 0.15m thick) and Development 30 07 21 28 11 09 and Vulnerable Households tion Single Pipe Culvert Ø 1.0m (2 units) for Anlong Samnar, Chi Kraeng. KH-MOI-99886-CW-CDD / The rehabilitation laterite road ( Length 1500m, Width Component 1: Improving Pending Community Driven 2019-03- 2019-03- 2019-04- 2019-05- 2019-05- 2019-08- 4.00m, 0.15m Thick) and IDA / 59600 Livelihoods for Rural Poor Post Open - National 29,208.00 0.00 Implementa Development 01 08 30 07 21 19 Construction of Box Culver and Vulnerable Households tion heigth 2m with Stop Log (1 unit) for Doun Kaev, Puok. KH-MOI-99878-CW-CDD / The rehabilitation laterite Component 1: Improving Pending Community Driven 2019-03- 2019-03- 2019-03- 2019-03- 2019-04- 2019-07- road (Length 2419m, Width IDA / 59600 Livelihoods for Rural Poor Post Open - National 25,921.00 0.00 Implementa Development 01 08 22 29 12 11 3.50m, 0.15m thick) for Chi and Vulnerable Households tion Kraeng, Chi Kraeng. KH-MOI-99880-CW-CDD / The rehabilitation laterite road (Length 2090m, Width 4.00m, 0.15m thick) and Component 1: Improving Pending Community Driven 2019-03- 2019-03- 2019-03- 2019-03- 2019-04- 2019-07- Construction of Single Pipe IDA / 59600 Livelihoods for Rural Poor Post Open - National 30,721.00 0.00 Implementa Development 01 08 22 29 12 11 Culvert Ø 0.6m (1 unit), and Vulnerable Households tion Single Pipe Culvert Ø 0.8m (1 unit) and Single Pipe Culvert Ø 1.0m (1unit) for Dan Run, Soutr Nikom. KH-MOI-99881-CW-CDD / The rehabilitation laterite road (Length 1550m, Width Component 1: Improving Pending 4.00m, 0.15m thick), Single Community Driven 2019-03- 2019-03- 2019-04- 2019-05- 2019-06- 2019-09- IDA / 59600 Livelihoods for Rural Poor Post Open - National 29,965.00 0.00 Implementa Pipe Culvert Ø 1.0m (1unit) Development 01 06 17 17 21 19 and Vulnerable Households tion and Construction of Double Pipe Culvert Ø 0.8m (5units), for Ballangk, Prasat Bakong. KH-MOI-99887-CW-CDD / Construction of Box Culvert heigth 2m with stop Log (1unit), Box Culvert heigth Component 1: Improving Pending Community Driven 2019-04- 2019-05- 2019-05- 2019-05- 2019-06- 2019-09- 1.5m with stop Log (1unit) IDA / 59600 Livelihoods for Rural Poor Post Open - National 29,896.00 0.00 Implementa Development 30 07 21 28 11 09 Pipe Culver Ø 0.8m with Stop and Vulnerable Households tion Log (1unit) and Single Pipe Culvert Ø 0.8m (4 unit) for Sasar Sdam, Puok. KH-MOI-99888-CW-CDD / Construction of Reinforced Component 1: Improving Pending Concrete Road (Lengh 260m, Community Driven 2019-04- 2019-05- 2019-05- 2019-05- 2019-06- 2019-09- IDA / 59600 Livelihoods for Rural Poor Post Open - National 30,417.00 0.00 Implementa width 5.00m, 0.15m thick) for Development 30 07 21 28 11 09 and Vulnerable Households tion Kampong Thkov, Kralanh. Total: 0.260 km KH-MOI-99890-CW-CDD / The rehabilitation ponds size (60mx30mx5m), Component 1: Improving Pending (30mx25mx5m), Community Driven 2019-03- 2019-03- 2019-03- 2019-03- 2019-04- 2019-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 29,949.00 0.00 Implementa (40mx20mx5m), Development 01 08 22 29 12 11 and Vulnerable Households tion (50mx50mx5m) for Slaeng Spean, Srei Snam. Total:4 Places KH-MOI-99891-CW-CDD / The rehabilitation laterite Component 1: Improving Pending Community Driven 2019-04- 2019-05- 2019-05- 2019-05- 2019-06- 2019-09- road (1.450km) and Single IDA / 59600 Livelihoods for Rural Poor Post Open - National 32,660.00 0.00 Implementa Development 30 07 21 28 11 09 Pipe Culvert Ø 1.0m (3 units) and Vulnerable Households tion for Svay Chek, Angkor Thum. KH-MOI-99892-CW-CDD / The rehabilitation laterite road ( Length 2520m, Width Component 1: Improving Pending Community Driven 2019-04- 2019-05- 2019-05- 2019-05- 2019-06- 2019-09- 4.00m, 0.15 Thick) and IDA / 59600 Livelihoods for Rural Poor Post Open - National 34,064.00 0.00 Implementa Development 30 07 21 28 11 09 Construction of Single Pipe and Vulnerable Households tion Culvert Ø 1.0m (2 unit) for Leang Dai, Angkor Thum. KH-MOI-99893-CW-CDD / The rehabilitation laterite road (Length 1080m, Width Component 1: Improving Pending 4.00m, 0.15m thick) and Community Driven 2019-03- 2019-03- 2019-03- 2019-03- 2019-05- 2019-08- IDA / 59600 Livelihoods for Rural Poor Post Open - National 27,869.20 0.00 Implementa Construction of Single Pipe Development 01 08 22 29 07 05 and Vulnerable Households tion Culvert Ø 0.8m (1 unit) and Triple Pipe Culvert, Ø 1.0m (3 unit) for Ta Siem, Svay Leu. KH-MOI-99894-CW-CDD / Construction of Reinforced Component 1: Improving Pending Community Driven 2019-04- 2019-05- 2019-05- 2019-05- 2019-06- 2019-09- Concrete Road (Length IDA / 59600 Livelihoods for Rural Poor Post Open - National 48,510.00 0.00 Implementa Development 30 07 21 28 11 09 445m, Width 3.50m, 0.15m and Vulnerable Households tion thick) for khnang Phnum, Svay Leu. KH-MOI-99889-CW-CDD / The rehabilitation laterite Component 1: Improving Pending Community Driven 2019-04- 2019-05- 2019-05- 2019-05- 2019-06- 2019-09- road (Length 2600m, Width IDA / 59600 Livelihoods for Rural Poor Post Open - National 29,932.00 0.00 Implementa Development 30 07 21 28 11 09 5.00m, 0.15m thick) for and Vulnerable Households tion Klang Hay, Srei Snam. Total: 2.600 km KH-MOI-110153-CW-CDD / Construction:1- Reinforcement concrete road:(L353m, W 4m, T0.15m) Component 1: Improving Pending Community Driven 2019-04- 2019-05- 2019-05- 2019-05- 2019-06- 2019-09- and drainage system (L353m, IDA / 59600 Livelihoods for Rural Poor Post Open - National 89,712.00 0.00 Implementa Development 30 07 21 28 11 09 0.6m ) and 2-Reinforcement and Vulnerable Households tion concrete road (L357m, W 4m, T 0.15m) in Sangkat Dangkao, Khan Dangkao KH-MOI-110154-CW-CDD / Construction of Reinforcement concrete road and Drainage System: 1- Component 1: Improving Pending Road (100m) , 2-Road (171m Community Driven 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-09- IDA / 59600 Livelihoods for Rural Poor Post Open - National 98,080.00 0.00 Implementa ), 3-Road (52m), 4- Development 15 22 05 12 26 24 and Vulnerable Households tion Road(88m) ,5- Road (90m), 6- Road (93m) and 7-Road (L128m) in Sangkat Prey Veaeng, Khan Dangkao Page 1 KH-MOI-110159-CW-CDD / Construction of reinforcement concrete road:(466m, width 5m, thickness 0.15m ), 2- Component 1: Improving Pending Community Driven 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-09- Road:(312m, width 4m, IDA / 59600 Livelihoods for Rural Poor Post Open - National 105,204.00 0.00 Implementa Development 15 22 05 12 26 24 thickness 0.15m ) and and Vulnerable Households tion drainage system:(312m,cross section 0.6m) in Sangkat Kork Roka, Khan Preak Pnov KH-MOI-110165-CW-CDD / Construction of reinforcement concrete road and and drainage system in Prey Component 1: Improving Pending Spueu & Prey Sandaek, Community Driven 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- 2019-10- IDA / 59600 Livelihoods for Rural Poor Post Open - National 84,579.00 0.00 Implementa Sangkat Chaom Chau 2, Khan Development 30 06 20 27 11 09 and Vulnerable Households tion Por Sen Chey (663m) and drainage system (523m) in Sangkat Chaom Chau 2, Khan Por Sen Chey KH-MOI-110174-CW-CDD / Construction of reinforcement concrete: 1- Road(124m), 2- Road (137m). 3- Road (117m Component 1: Improving Pending Community Driven 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- 2019-10- ). 4-Installation of Sola street IDA / 59600 Livelihoods for Rural Poor Post Open - National 30,250.00 0.00 Implementa Development 30 06 20 27 11 09 lighting and poles (117m), and Vulnerable Households tion and (139m ) in Sangkat Chbar Ampov Ti Pir, Khan Chbar Ampov KH-MOI-110155-CW-CDD / Construction of reinforcement concrete: 1- Road (99m) ,1- Road(101m), 2-Road(60m), 3- Drainage system:(9m), 4- Component 1: Improving Pending Community Driven 2019-08- 2019-08- 2019-09- 2019-09- 2019-09- 2019-12- Installation of Sola street IDA / 59600 Livelihoods for Rural Poor Post Open - National 28,703.49 0.00 Implementa Development 15 22 05 12 26 25 lighting and poles and Vulnerable Households tion (120m),(439m),(439m) and (98m) in Sangkat Chrang Chamreas Ti Muoy,Khan Russey Keo KH-MOI-110151-CW-CDD / Construction: 1- Reinforcement concrete road (340m) and drainage system:(448m), 2-Road Component 1: Improving Pending (L130m) and drainage system Community Driven 2019-08- 2019-08- 2019-09- 2019-09- 2019-09- 2019-12- IDA / 59600 Livelihoods for Rural Poor Post Open - National 171,670.08 0.00 Implementa (130m), 3-Road (120m) and Development 15 22 05 12 26 25 and Vulnerable Households tion drainage system:(250m), 4- Road (238m) and drainage system (238m) in Sangkat Trapeang Krasang, Khan Por Sen Chey KH-MOI-110147-CW-CDD / Construction:1- Reinforcement concrete road, Drainage (L171m),Installation of Sola street lighting and Component 1: Improving Pending poles(171m), 2- Community Driven 2019-08- 2019-08- 2019-09- 2019-09- 2019-09- 2019-12- IDA / 59600 Livelihoods for Rural Poor Post Open - National 43,476.23 0.00 Implementa Reinforcement concrete Development 15 22 05 12 26 25 and Vulnerable Households tion road(147m),drainage(48m), Installation of Sola street lighting and poles (147m) in Sangkat Khmuonh, Khan Saen Sokh KH-MOI-110144-CW-CDD / Construction: 1- Reinforcement concrete road:(L262m, w 2.6m, T 0.12m) ,Drainage Component 1: Improving Pending system:(262m,0.6m), 2- Community Driven 2019-08- 2019-08- 2019-09- 2019-09- 2019-09- 2019-12- IDA / 59600 Livelihoods for Rural Poor Post Open - National 71,818.97 0.00 Implementa Installation:(18 Sola street Development 15 22 05 12 26 25 and Vulnerable Households tion lighting and poles for 262m) and 3-Concrete bridge: (L206m, width1.50m, T0.07m) in Sangkat Srah Chak, Khan Daun Penh KH-MOI-110162-CW-CDD / Construction of reinforcement concrete:1- road:(L102m, width 2.5m, thickness 0.12m) Component 1: Improving Pending and drainage Community Driven 2019-08- 2019-08- 2019-09- 2019-09- 2019-09- 2019-12- IDA / 59600 Livelihoods for Rural Poor Post Open - National 37,878.83 0.00 Implementa system:(114m).2- Development 15 22 05 12 26 25 and Vulnerable Households tion road:(169m, width 3.5m, thickness 0.15m) and drainage system:(169m) in Sangkat Boeng Kak 1, Khan Tuol Kork KH-MOI-110173-CW-CDD / Construction of reinforcement concrete: 1- Road(110m, Component 1: Improving Pending width 4m, thickness 0.15m), Community Driven 2019-08- 2019-08- 2019-09- 2019-09- 2019-09- 2019-12- IDA / 59600 Livelihoods for Rural Poor Post Open - National 30,281.06 0.00 Implementa 2- Road(100m),2-Installation Development 15 22 05 12 26 25 and Vulnerable Households tion of Sola street lighting and poles (250m) in Khtor,Sangkat Preak Leap, Khan Chroy Changvar KH-MOI-110168-CW-CDD / Construction of reinforcement concrete:1- road(158m) and drainage (138m), 2-Road and drainage system (77m),3- Component 1: Improving Pending Community Driven 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- 2019-10- road(261m) and drainage IDA / 59600 Livelihoods for Rural Poor Post Open - National 73,334.73 0.00 Implementa Development 30 06 20 27 11 09 (207m),4-Installation of Sola and Vulnerable Households tion street lighting and poles(158m), (77m)and (261m) in Sangkat Chak Angrae Leu, Khan Mean Chey KH-MOI-140916-CW-CDD / Repair Dike 78 for Sangkat Component 1: Improving Pending Krabei Riel, Siem Reap Community Driven 2019-10- 2019-10- 2019-11- 2019-11- 2019-11- 2020-02- IDA / 59600 Livelihoods for Rural Poor Post Open - National 30,005.00 0.00 Implementa Municipality ( Size 2.95Km Development 18 25 08 15 29 27 and Vulnerable Households tion length, 4.00m width, 2.00m height) KH-MOI-140917-CW-CDD / Construction of Reinforced Concrete Road for Kampong Component 1: Improving Pending Community Driven 2019-10- 2019-10- 2019-11- 2019-11- 2019-11- 2020-02- Khleang Commune, Sotr IDA / 59600 Livelihoods for Rural Poor Post Open - National 30,248.00 0.00 Implementa Development 18 25 08 15 29 27 Nikom District ( Size 0.25Km and Vulnerable Households tion length, 5.00m width, 0.15m thick) KH-MOI-140918-CW-CDD / Upgrade Earth Road to Laterite Pavement for Sangkat Chong Khneas, Siem Reap Component 1: Improving Pending Community Driven 2019-10- 2019-10- 2019-11- 2019-11- 2019-11- 2020-02- Municipality ( Size 0.80Km IDA / 59600 Livelihoods for Rural Poor Post Open - National 27,191.00 0.00 Implementa Development 18 25 08 15 29 27 length, 4.00m width, 0.15m and Vulnerable Households tion thick), including 1 unit of culvert construction, 0.60m Diameter, 16.00m length. KH-MOI-146743-CW-CDD / Digging Community Pond one place (size 100mx75mx6.00m) including fence construction and Earth Component 1: Improving Pending Community Driven 2019-12- 2019-12- 2019-12- 2020-01- 2020-01- 2020-04- Dam with laterite pavement IDA / 59600 Livelihoods for Rural Poor Post Open - National 45,730.00 0.00 Implementa Development 06 13 27 03 17 16 4.00 meter width, 2.00 meter and Vulnerable Households tion heigh surrounding the pond and 2 reinforced concrete stairs, access laterite road 170m length, 4.00m wid Page 2 KH-MOI-146745-CW-CDD / Unlined Earth Canal Rehabilitation with 1500m Length, 2m bed, 1.60m Depth including the Construction of Component 1: Improving Pending Community Driven 2019-12- 2019-12- 2019-12- 2020-01- 2020-01- 2020-04- Cented Causeway with pipe IDA / 59600 Livelihoods for Rural Poor Post Open - National 41,288.00 0.00 Implementa Development 06 13 27 03 17 16 0.80m diameter, 8m length, and Vulnerable Households tion 4m width 5 places and Construction of Trapezoidal Section Lined Concrete canal with 16m length, 2 KH-MOI-162028-CW-CDD / Earth Road Repair and Laterite Pavement 2 lines for Sangkat Svay Dangkum, Siem Component 1: Improving Pending Reap Municipality (For line 1: Community Driven 2020-03- 2020-03- 2020-03- 2020-04- 2020-04- 2020-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 22,511.00 0.00 Implementa 0.87 Km length, 4.00 m Development 10 17 31 07 21 20 and Vulnerable Households tion width, 0.15m thick including 1 unit of single culvert construction, 1.00m Diameter, 7.00m length ( For line 2: 0.60 Km le KH-MOI-162399-CW-CDD / Reinforced Concrete Road for Component 1: Improving Pending Kampong Thkov Commune, Community Driven 2020-03- 2020-03- 2020-03- 2020-04- 2020-04- 2020-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 29,950.00 0.00 Implementa Kralanh District ( 0.26 Km Development 10 17 31 07 21 20 and Vulnerable Households tion length,4.50m Width, 0.15 thick). KH-MOI-162400-CW-CDD / Earth Road Repair and Laterite Pavement for Svay Leu Commune, Svay Leu Component 1: Improving Pending Community Driven 2020-03- 2020-03- 2020-03- 2020-04- 2020-04- 2020-07- District ( 3.70 Km length, IDA / 59600 Livelihoods for Rural Poor Post Open - National 55,881.00 0.00 Implementa Development 10 17 31 07 21 20 4.00 m width, 0.15m thick), and Vulnerable Households tion including 2 units of double culvert construction, 1.00 m Diameter, 6.00 m length. KH-MOI-162401-CW-CDD / Earth Road Repair and Laterite Pavement for Ta Siem Commune, Svay Leu District ( Component 1: Improving Pending Community Driven 2020-03- 2020-03- 2020-03- 2020-04- 2020-04- 2020-07- 2.335 Km length, 4.50 m IDA / 59600 Livelihoods for Rural Poor Post Open - National 35,980.00 0.00 Implementa Development 10 17 31 07 21 20 width, 0.15m thick), including and Vulnerable Households tion 1 unit of single culvert construction, 1.00m Diameter, 6.00 m length. KH-MOI-162402-CW-CDD / Earth Road Repair and Laterite Pavement for Boeng Mealea Commune, Svay Leu Component 1: Improving Pending Community Driven 2020-03- 2020-03- 2020-03- 2020-04- 2020-04- 2020-07- District ( 2.80 Km length, IDA / 59600 Livelihoods for Rural Poor Post Open - National 44,027.00 0.00 Implementa Development 10 17 31 07 21 20 5.00 m width, 0.15m thick), and Vulnerable Households tion including 2 units of single culvert construction, 0.60m&0.80 Diameter, 6.00 m length. KH-MOI-162403-CW-CDD / Earth Road Repair and Laterite Pavement 3 lines for Peak Snaeng Commune, Angkor Thom District ( For Component 1: Improving Pending Community Driven 2020-03- 2020-03- 2020-03- 2020-04- 2020-04- 2020-07- Line1: 1.95 Km length, 4.00 IDA / 59600 Livelihoods for Rural Poor Post Open - National 54,983.00 0.00 Implementa Development 10 17 31 07 21 20 m width, 0.15m thick and Vulnerable Households tion including 2 units of single culvert construction, 1.00 m Diameter, 5.00 m length & 1 unit of single culver KH-MOI-162406-CW-CDD / Earth Road Repair and Laterite Pavement 5 lines for Kampong Kdei Commune, Chi Component 1: Improving Pending Community Driven 2020-03- 2020-03- 2020-04- 2020-04- 2020-05- 2020-07- kraeng District, ( Total length IDA / 59600 Livelihoods for Rural Poor Post Open - National 59,812.00 0.00 Implementa Development 20 27 10 17 01 30 3190m, 4.00m width, 0.15 and Vulnerable Households tion thick including 1 unit of Double box culvert 2.00m heigh, 6.00m length) KH-MOI-162407-CW-CDD / Earth Road Repair and Literate Pavement 3 lines for Chi kraeng Commune, Chi kraeng District, ( Total length Component 1: Improving Pending Community Driven 2020-03- 2020-03- 2020-04- 2020-04- 2020-05- 2020-07- 1680m, 4.00m, 0.15 thick IDA / 59600 Livelihoods for Rural Poor Post Open - National 39,802.00 0.00 Implementa Development 20 27 10 17 01 30 width including 2 units of and Vulnerable Households tion single pipe culvert 0.60m diameter, 6.00m length and 3 units of single pipe culvert 1.00m diam KH-MOI-162408-CW-CDD / Reinforced Concrete Bridge Component 1: Improving Pending Construction for Tram Sasar Community Driven 2020-03- 2020-03- 2020-04- 2020-04- 2020-05- 2020-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 30,100.00 0.00 Implementa Commune, Srei Snam District Development 20 27 10 17 01 30 and Vulnerable Households tion ( 4.00m Heigh, 11.00m length, 4.00m width). KH-MOI-162409-CW-CDD / Earth Road Repair and Laterite Pavement for Mean Chey Commune, Brasat Component 1: Improving Pending Community Driven 2020-03- 2020-03- 2020-04- 2020-04- 2020-05- 2020-07- Bakong District ( Length IDA / 59600 Livelihoods for Rural Poor Post Open - National 31,649.00 0.00 Implementa Development 20 27 10 17 01 30 1800m, 4.00m width, 0.15 and Vulnerable Households tion thick and 1 unit of single box culvert with water gate, 2.50m heigh, 5.90m length ) KH-MOI-162410-CW-CDD / Earth Road Repair and Laterite Pavement for Roluos Commune, Brasat Bakong District, ( Length 4625m, Component 1: Improving Pending Community Driven 2020-03- 2020-03- 2020-04- 2020-04- 2020-05- 2020-07- 4.00m width, 0.15 thick IDA / 59600 Livelihoods for Rural Poor Post Open - National 49,078.00 0.00 Implementa Development 20 27 10 17 01 30 including 1 units of single and Vulnerable Households tion pipe culvert 0.60m diameter, 6.00m length and 2 units of single pipe culvert 0.80m diameter, 6.00m len KH-MOI-162412-CW-CDD / Earth Road Repair and Laterite Pavement 2 lines for Kantreang Commune, Brasat Component 1: Improving Pending Community Driven 2020-03- 2020-03- 2020-04- 2020-04- 2020-05- 2020-07- Bakong District, ( Total length IDA / 59600 Livelihoods for Rural Poor Post Open - National 19,225.00 0.00 Implementa Development 20 27 10 17 01 30 1500m, 4.00m width, 0.15 and Vulnerable Households tion thick including 1 unit of single pipe culvert 0.80m diameter, 5.00m length) KH-MOI-162414-CW-CDD / Earth Road Repair and Laterite Pavement for Ballangk Commune, Brasat Component 1: Improving Pending Community Driven 2020-03- 2020-03- 2020-04- 2020-04- 2020-05- 2020-07- Bakong District, ( Length IDA / 59600 Livelihoods for Rural Poor Post Open - National 20,670.00 0.00 Implementa Development 20 27 10 17 01 30 985m, 4.00m width, 0.15 and Vulnerable Households tion thick including 3 units of single pipe culvert 0.60m diameter, 5.00m length) KH-MOI-162415-CW-CDD / Earth Road Repair and Component 1: Improving Pending Laterite Pavement for Dan Community Driven 2020-03- 2020-03- 2020-04- 2020-04- 2020-05- 2020-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 26,913.00 0.00 Implementa Run Commune, Sotr Nikom Development 20 27 10 17 01 30 and Vulnerable Households tion District, ( Length 2600m, 4.00m width, 0.15m thick ) Page 3 KH-MOI-162416-CW-CDD / Laterite Road Construction for Prey Chruk Commune, Pouk District ( 3614 m length, Component 1: Improving Pending 4.00m width, 0.15 thick Community Driven 2020-03- 2020-03- 2020-04- 2020-04- 2020-05- 2020-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 62,129.00 0.00 Implementa including 5 units of single Development 20 27 10 17 01 30 and Vulnerable Households tion pipe culvert, 0.60m Diameter, length 6.00m and 1 unit of single pipe culvert 0.80m diameter, length 6.00m ) KH-MOI-162417-CW-CDD / Laterite Road Construction for Doun Kaev Commune, Pouk District ( 2500 m length, Component 1: Improving Pending 4.00m width, 0.15 thick Community Driven 2020-03- 2020-03- 2020-04- 2020-04- 2020-05- 2020-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 49,293.00 0.00 Implementa including 1 unit of single pipe Development 20 27 10 17 01 30 and Vulnerable Households tion culvert,0.80m Diameter length 6.00m and 1 unit of single pipe culvert 1.00m diameter, length 6.00m ) KH-MOI-162418-CW-CDD / Digging Community Pond 2 places for Kdei Run Component 1: Improving Pending Commune, Pouk District Community Driven 2020-03- 2020-03- 2020-04- 2020-04- 2020-05- 2020-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 34,396.00 0.00 Implementa including fence construction Development 20 27 10 17 01 30 and Vulnerable Households tion surrounding the pond and 2 doors ( Size: 60mx33mx5m and 60mx24mx5m) KH-MOI-162419-CW-CDD / Reinforced Concrete Road Construction for Khnat Commune, Pouk District ( Component 1: Improving Pending 400m length, 5.00m width, Community Driven 2020-03- 2020-03- 2020-04- 2020-04- 2020-05- 2020-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 57,625.00 0.00 Implementa 0.15m thick including 1 unit Development 20 27 10 17 01 30 and Vulnerable Households tion of single pipe culvert 0.60 diameter, 6.00m length and 1 unit of single pipe culvert 0.80 diameter, 6.00m length KH-MOI-162420-CW-CDD / Laterite Road Construction for Sasar Sdam Commune, Pouk Component 1: Improving Pending District ( 1500m length, Community Driven 2020-03- 2020-03- 2020-04- 2020-04- 2020-05- 2020-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 39,060.00 0.00 Implementa 5.00m width, 0.15 thick Development 20 27 10 17 01 30 and Vulnerable Households tion including 2 units of single pipe culvert,0.80m Diameter length 6.00m) KH-MOI-162421-CW-CDD / Laterite Road Construction for Lvea Commune, Pouk District Component 1: Improving Pending Community Driven 2020-03- 2020-03- 2020-04- 2020-04- 2020-05- 2020-07- ( 2200m length, 4.00m width, IDA / 59600 Livelihoods for Rural Poor Post Open - National 38,419.00 0.00 Implementa Development 20 27 10 17 01 30 0.15 thick including 3 units and Vulnerable Households tion of single pipe culvert,0.60m Diameter length 6.00m) KH-MOI-162422-CW-CDD / Unlined Earth Canal Rehabilitation for Spean Component 1: Improving Pending Tnoat Commune, Chi Kraeng Community Driven 2020-03- 2020-03- 2020-04- 2020-04- 2020-05- 2020-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 33,487.00 0.00 Implementa District ( 2100m length, Development 20 27 10 17 01 30 and Vulnerable Households tion 1.20m bed, 1.20 Depth including of 6 units of single pipe culvert with water gate) KH-MOI-162423-CW-CDD / Reinforced Concrete Bridge upgrade in Phum 2, Sangkat Srah Chak, Khan Daun Pend ( Total length 73m, 1.20m Component 2: Improving Pending Community Driven 2020-03- 2020-04- 2020-04- 2020-04- 2020-05- 2020-08- width, 1.50 heigh, 0.07m IDA / 59600 Livelihoods for Urban Poor Post Open - National 65,309.00 0.00 Implementa Development 30 06 20 27 11 09 thickness), Reinforced and Vulnerable Households tion Concrete Road in Phum 20, Sangkat Srah Chak, Khan Daun Penh ( Total length 60m, 2.40m widt, 0.15m thi KH-MOI-162424-CW-CDD / Reinforced Concrete Road in Phum 3, Sangkat Boeung Kak 1, Khan Toul Kork( Total length 46m, 2m width, 0.15m Component 2: Improving Pending Community Driven 2020-03- 2020-04- 2020-04- 2020-04- 2020-05- 2020-08- thickness) and Drainage IDA / 59600 Livelihoods for Urban Poor Post Open - National 9,333.00 0.00 Implementa Development 30 06 20 27 11 09 system (Total length 34m, and Vulnerable Households tion 0.6m diameter). Reinforced concrete road in Phum 4, Sangkat Boeung Kak 1, Khan Toul kork(Total le KH-MOI-162425-CW-CDD / Reinforced Concrete Road in Talei Village, Sangkat Dangkao, Khan Dangkao( Total length 149m, 3.5m Component 2: Improving Pending Community Driven 2020-04- 2020-04- 2020-04- 2020-05- 2020-05- 2020-08- width, 0.15m thickness) and IDA / 59600 Livelihoods for Urban Poor Post Open - National 50,729.00 0.00 Implementa Development 06 13 27 04 18 16 Drainage system (Total length and Vulnerable Households tion 67m, 0.6m diameter). Reinforced concrete road in Khva Village, Sangkat Dangkao, Khan Dangkao(Total KH-MOI-162426-CW-CDD / Reinforced Concrete Road in Component 2: Improving Pending Toap Boss Village, Sangkat Community Driven 2020-04- 2020-04- 2020-04- 2020-05- 2020-05- 2020-08- IDA / 59600 Livelihoods for Urban Poor Post Open - National 40,542.00 0.00 Implementa Prey Veang, Khan Dangkao( Development 06 13 27 04 18 16 and Vulnerable Households tion Total length 310m, 4m width, 0.15m thickness) KH-MOI-162428-CW-CDD / Reinforced Concrete Road in Preak Leap Village, Sangkat Component 2: Improving Pending Preak Leap, Khan Chroy Community Driven 2020-03- 2020-04- 2020-04- 2020-04- 2020-05- 2020-08- IDA / 59600 Livelihoods for Urban Poor Post Open - National 55,323.00 0.00 Implementa Changvar( Total length 287m, Development 30 06 20 27 11 09 and Vulnerable Households tion 3.5m width, 0.15m thickness) and drainage system (Total length 287m, 0.6m diameter) KH-MOI-162429-CW-CDD / Reinforced Concrete Road in Sen Sok Ty Mouy Village, Component 2: Improving Pending Sangkat Khmounh, Khan Sen Community Driven 2020-04- 2020-04- 2020-04- 2020-05- 2020-05- 2020-08- IDA / 59600 Livelihoods for Urban Poor Post Open - National 111,552.00 0.00 Implementa Sok( Total length 547m, 4m Development 03 10 24 01 15 13 and Vulnerable Households tion width, 0.15m thickness) and drainage system (Total length 550m, 0.6m diameter) KH-MOI-162430-CW-CDD / Reinforced Concrete Road in Samaki 5 Village, Sangkat Trapeang Krasang, Khan Pou Sen Chey( Total length 196m, Component 2: Improving Pending Community Driven 2020-04- 2020-04- 2020-04- 2020-05- 2020-05- 2020-08- 6m width, 0.15m thickness) IDA / 59600 Livelihoods for Urban Poor Post Open - National 64,039.00 0.00 Implementa Development 03 10 24 01 15 13 Reinforced Concrete Road in and Vulnerable Households tion Samaki 6 Village, Sangkat Trapeang Krasang, Khan Pou Sen Chey( Total length 121m, 4m & 5m Page 4 KH-MOI-162432-CW-CDD / Reinforced Concrete Road in Chrey Koang Village, Sangkat Choam Chau 2, Khan Pou Sen Chey( Total length 287m, 5m Component 2: Improving Pending Community Driven 2020-04- 2020-04- 2020-04- 2020-05- 2020-05- 2020-08- width, 0.15m thickness) and IDA / 59600 Livelihoods for Urban Poor Post Open - National 177,610.00 0.00 Implementa Development 03 10 24 01 15 13 Drainage System(Total Length and Vulnerable Households tion 287, 0.6m diameter) , Reinforced Concrete Road in Prey Lvea Village, Sangkat Choam Ch KH-MOI-162433-CW-CDD / Reinforced Concrete Road in Andong 1 & Andong 2 Villages, Sangkat Kork Roka, Component 2: Improving Pending Community Driven 2020-04- 2020-04- 2020-04- 2020-05- 2020-05- 2020-08- Khan Peeak Phnov( Total IDA / 59600 Livelihoods for Urban Poor Post Open - National 42,245.00 0.00 Implementa Development 03 10 24 01 15 13 length 211m, 4m width, and Vulnerable Households tion 0.15m thickness) and Drainage System(Total Length 211m, 0.6m diameter) KH-MOI-162435-CW-CDD / Reinforced Concrete Road in Component 2: Improving Pending Daeum Sleng Village, Sangkat Community Driven 2020-04- 2020-04- 2020-05- 2020-05- 2020-05- 2020-08- IDA / 59600 Livelihoods for Urban Poor Post Open - National 28,928.00 0.00 Implementa Chbar Ampov 2, Khan Chbar Development 10 17 01 08 22 20 and Vulnerable Households tion Ampov ( Total length 234m, 3.4m width, 0.15m thickness) KH-MOI-169345-CW-CDD / Solar LED Power Street lighting in Phum 2, Sangkat Srah Chak, Khan Daun Pend ( Component 2: Improving Pending Total sets 22 sets), Solar LED Community Driven 2020-05- 2020-05- 2020-05- 2020-06- 2020-06- 2020-09- IDA / 59600 Livelihoods for Urban Poor Post Open - National 13,469.00 0.00 Implementa Power Street lighting in Phum Development 05 12 26 02 16 14 and Vulnerable Households tion 22, Sangkat Srah Chak, Khan Daun Pend ( Total sets 11 sets), Solar LED Power Street lighting in Phum 24, Sangkat KH-MOI-169346-CW-CDD / Solar LED Power street Component 2: Improving Pending Community Driven 2020-05- 2020-05- 2020-05- 2020-06- 2020-06- 2020-09- lighting in Phum 8, Sangkat IDA / 59600 Livelihoods for Urban Poor Post Open - National 3,613.00 0.00 Implementa Development 05 12 26 02 16 14 Boeung Kak 1, Khan Toul and Vulnerable Households tion Kork( Total sets 11 sets) KH-MOI-169347-CW-CDD / Solar LED Power street lighting in Khva Village, Sangkat Dangkao, Khan Component 2: Improving Pending Community Driven 2020-05- 2020-05- 2020-05- 2020-06- 2020-06- 2020-09- Dangkao( Total sets 26 sets), IDA / 59600 Livelihoods for Urban Poor Post Open - National 15,774.00 0.00 Implementa Development 05 12 26 02 16 14 Solar LED Power street and Vulnerable Households tion lighting in Mol Village, Sangkat Dangkao, Khan Dangkao(Total sets 23 sets) KH-MOI-169348-CW-CDD / Solar LED Power street Component 2: Improving Pending Community Driven 2020-05- 2020-05- 2020-05- 2020-06- 2020-06- 2020-09- lighting in Phum 3, Sangkat IDA / 59600 Livelihoods for Urban Poor Post Open - National 5,495.00 0.00 Implementa Development 05 12 26 02 16 14 Chrang Chamreas Ty Mouy, and Vulnerable Households tion Khan Russei Kao( Total sets 17 sets) KH-MOI-169349-CW-CDD / Solar LED Power street Component 2: Improving Pending Community Driven 2020-05- 2020-05- 2020-05- 2020-06- 2020-06- 2020-09- lighting in Khtor Village, IDA / 59600 Livelihoods for Urban Poor Post Open - National 9,674.00 0.00 Implementa Development 06 13 27 03 17 15 Sangkat Preak Leap, Khan and Vulnerable Households tion Chroy Chang Var( Total sets 30 sets) KH-MOI-169350-CW-CDD / Solar LED Power street lighting in Svay Ckek Thmei Component 2: Improving Pending Community Driven 2020-05- 2020-05- 2020-05- 2020-06- 2020-06- 2020-09- Village, Dandong 1&2 IDA / 59600 Livelihoods for Urban Poor Post Open - National 15,064.00 0.00 Implementa Development 06 13 27 03 17 15 Villages, Sangkat Kork Roka, and Vulnerable Households tion Khan Preak Phnov( Total sets 47 sets) KH-MOI-169351-CW-CDD / Solar LED Power street lighting in Daeum Sleng, Component 2: Improving Pending Community Driven 2020-05- 2020-05- 2020-05- 2020-06- 2020-06- 2020-09- Daeum Sleng I, Daeum Chan I IDA / 59600 Livelihoods for Urban Poor Post Open - National 21,978.00 0.00 Implementa Development 06 13 27 03 17 15 Villages, Sangkat Chbar and Vulnerable Households tion Ampov 2, Khan Chbar Ampov( Total sets 69 sets) KH-MOI-191867-CW-CDD / Reinforced Concrete Road Construction for Khnang Component 1: Improving Pending Community Driven 2020-09- 2020-09- 2020-10- 2020-10- 2020-10- 2020-12- Phnum Commune,Svay Leu IDA / 59600 Livelihoods for Rural Poor Post Open - National 20,181.00 0.00 Implementa Development 15 22 06 13 27 26 District, Siem Reap Province ( and Vulnerable Households tion Length: 0.18 Km, Width 5.00 m, 0.15m thick) KH-MOI-191856-CW-CDD / Earth Road Repair and Laterite Pavement for Anlong Component 1: Improving Pending Samnar, Siem Reap Province ( Community Driven 2021-04- 2021-04- 2021-05- 2021-05- 2021-05- 2021-08- IDA / 59600 Livelihoods for Rural Poor Post Open - National 27,338.00 0.00 Implementa Length 1.80 Km, Width 4.00 Development 15 22 06 13 27 25 and Vulnerable Households tion m, 0.15m thick including 2 units of single culvert construction, Ø0.80m, length 6.00m) KH-MOI-191857-CW-CDD / Earth Road Repair and Laterite Pavement two lines for Sangkat Krabei Riel, Siem Reap Municipality, Siem Reap Component 1: Improving Pending Community Driven 2021-03- 2021-03- 2021-04- 2021-04- 2021-04- 2021-07- Province ( For line1: Length: IDA / 59600 Livelihoods for Rural Poor Post Open - National 45,396.00 0.00 Implementa Development 15 22 05 12 26 25 1.868 Km, Width 5.00m, 0.15 and Vulnerable Households tion thick including 2 units of single culverts, Ø 0.80m, length 7.00m and Ø1.00m, length 7.0 KH-MOI-191859-CW-CDD / Earth Road Repair and Laterite Pavement for Sangkat Tuek Vil ,Siem Reap Component 1: Improving Pending Municipality, Siem Reap Community Driven 2021-03- 2021-03- 2021-04- 2021-04- 2021-04- 2021-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 64,903.00 0.00 Implementa Province ( Length: 2.325 Km , Development 15 22 05 12 26 25 and Vulnerable Households tion Width: 5.00 m, 0.15m thick), including 5 units of single culvert construction, 1 Unit Ø1.00 m, length 6.00 m, 4 units Ø1.00 m, l KH-MOI-191860-CW-CDD / Reinforced Concrete Road Construction for Kampong Component 1: Improving Pending Community Driven 2021-03- 2021-03- 2021-04- 2021-04- 2021-04- 2021-06- Khleang Commune, Sotr IDA / 59600 Livelihoods for Rural Poor Post Open - National 33,774.00 0.00 Implementa Development 15 22 05 12 26 25 Nikom District, Siem Reap and Vulnerable Households tion Province ( Length 0.25 Km, Width 5.00 m, 0.15m thick) KH-MOI-162413-CW-CDD / Earth Road Repair and Laterite Pavement for Bakong Commune, Brasat Bakong Component 1: Improving Pending Community Driven 2021-03- 2021-03- 2021-04- 2021-04- 2021-04- 2021-07- District, ( Length 1.60 Km, IDA / 59600 Livelihoods for Rural Poor Post Open - National 42,032.00 0.00 Implementa Development 15 22 05 12 26 25 4.00m width, 0.15 thick and Vulnerable Households tion including 3 units of double pipe culvert 1.00m diameter, 5.00m length) KH-MOI-191861-CW-CDD / Reinforced Concrete Road Construction for Kampong Component 1: Improving Pending Community Driven 2021-03- 2021-03- 2021-04- 2021-04- 2021-04- 2021-06- Phluk Commune, Brasat IDA / 59600 Livelihoods for Rural Poor Post Open - National 39,635.00 0.00 Implementa Development 15 22 05 12 26 25 Bakong District, Siem Reap and Vulnerable Households tion Province ( Length 0.23 Km, Width 6.00 m, 0.15m thick) Page 5 KH-MOI-191862-CW-CDD / Earth Road Repair and Laterite Pavement 2 lines for Trapeang Thum Commune Component 1: Improving Pending Community Driven 2021-03- 2021-03- 2021-04- 2021-04- 2021-04- 2021-07- ,Brasat Bakong District, Siem IDA / 59600 Livelihoods for Rural Poor Post Open - National 36,380.00 0.00 Implementa Development 15 22 05 12 26 25 Reap Province ( For line1: and Vulnerable Households tion Length 0.50 Km, Width 4.00m, 0.15 thick , For line 2: Length 3.05 Km, Width 4.00m, 0.15 thick) KH-MOI-191863-CW-CDD / Laterite Road Construction 2 lines for Reul Commune ,Pouk Component 1: Improving Pending District, Siem Reap Province Community Driven 2021-03- 2021-03- 2021-04- 2021-04- 2021-04- 2021-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 31,787.00 0.00 Implementa (For line Length 2.09 Km, Development 15 22 05 12 26 25 and Vulnerable Households tion Width 4.00m, 0.15 thick , For line 2: Length 0.75 Km, Width 4.00m, 0.15 thick) KH-MOI-191865-CW-CDD / Drilled wells Construction Component 1: Improving Pending Community Driven 2021-03- 2021-03- 2021-04- 2021-04- 2021-04- 2021-06- with Afridev Pump for Yeang IDA / 59600 Livelihoods for Rural Poor Post Open - National 11,429.00 0.00 Implementa Development 15 22 05 12 26 25 Commune ,Pouk District, and Vulnerable Households tion Siem Reap Province for 5 places KH-MOI-191864-CW-CDD / Laterite Road Construction 2 lines for Trei Nhoar Commune ,Pouk District, Component 1: Improving Pending Siem Reap Province ( For line Community Driven 2021-03- 2021-03- 2021-04- 2021-04- 2021-04- 2021-07- IDA / 59600 Livelihoods for Rural Poor Post Open - National 35,805.00 0.00 Implementa 1: Length 1.20 Km, Width Development 15 22 05 12 26 25 and Vulnerable Households tion 4.00m, 0.15 thick , For line 2: Length 1.45 Km, Width 4.00m, 0.15 thick including 1 unit of double culvert Ø0.60m, length 6.0 KH-MOI-191866-CW-CDD / Drilled wells with solar Pump and Water Distributed Component 1: Improving Pending Community Driven 2021-03- 2021-03- 2021-04- 2021-04- 2021-04- 2021-07- Connection 4 places for IDA / 59600 Livelihoods for Rural Poor Post Open - National 47,530.00 0.00 Implementa Development 15 22 05 12 26 25 Chrouy Neang and Vulnerable Households tion NguonCommune ,Srei Snam District, Siem Reap Province KH-MOI-162411-CW-CDD / Construction of Community Shelter for Ampil Commune, Brasat Bakong District ( Size: 8mx12m, with steel frame, Component 1: Improving Pending Community Driven 2021-05- 2021-05- 2021-06- 2021-06- 2021-06- 2021-09- reinforced concrete slab IDA / 59600 Livelihoods for Rural Poor Post Open - National 15,377.00 0.00 Implementa Development 14 21 04 11 25 23 0.10m thick and zinc roof ) and Vulnerable Households tion including one latrine construction with 4 separated rooms and installation of one unit of wa KH-MOI-251230-CW-RFQ / Laterite Road Construction for Mukh Paen Commune, Pouk District, Siem Reap Province ( Component 1: Improving Request for Pending Request for Single Stage - One 2021-09- 2021-10- 2022-01- 2 lines, for line1: Length= IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 26,739.00 0.00 Implementa Quotations Envelope 11 16 14 1.20 Km, Width= 5.00m, and Vulnerable Households Bank-SPD) tion Thick=0.15m , For line 2: Length= 0.85 Km, Width= 4.00m, Thick=0.15m) KH-MOI-251231-CW-RFQ / Laterite Road Construction for Samraong Yea Commune, Pouk District, Siem Reap Component 1: Improving Request for Pending Province (04 Lines, Total Request for Single Stage - One 2021-09- 2021-10- 2022-01- IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 36,214.00 0.00 Implementa Length= 3.16 Km, Width= Quotations Envelope 11 16 14 and Vulnerable Households Bank-SPD) tion 4.00m, Thick=0.15m including 1 unit of double culvert construction, Ø0.60 m, length 6.00m) KH-MOI-253012-CW-RFQ / Earth Road Repair and Laterite Pavement for Kandeak Commune, Brasat Component 1: Improving Request for Pending Bakong District, Siem Reap Request for Single Stage - One 2021-09- 2021-10- 2022-01- IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 32,966.00 0.00 Implementa Province ( 5 lines, Total Quotations Envelope 22 27 25 and Vulnerable Households Bank-SPD) tion Length=2.77 Km, Width= 4.00 m, Thick=0.15m including 1 unit of single culvert construction, Ø1.00m, length 6.00m KH-MOI-253013-CW-RFQ / Laterite Road Construction for Kaev Poar Commune, Pouk District, Siem Reap Province ( 2 lines, For line1: Length= Component 1: Improving Request for Pending Request for Single Stage - One 2021-09- 2021-10- 2022-01- 0.53 Km, Width= 4.00m, IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 30,147.00 0.00 Implementa Quotations Envelope 22 27 25 Thick=0.15 m , For line 2: and Vulnerable Households Bank-SPD) tion Length 1.15 Km, Width: 4.00m, 0.15 thick including 4 units of single culvert construction, KH-MOI-253014-CW-RFQ / Earth Road Repair and Laterite Pavement for Svay Chek Commune, Angkor Component 1: Improving Request for Pending Thum District, Siem Reap Request for Single Stage - One 2021-09- 2021-10- 2022-01- IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 33,360.00 0.00 Implementa Province (Length= 2.10 Km, Quotations Envelope 22 27 25 and Vulnerable Households Bank-SPD) tion Width= 5.00 m, Thick=0.15m including 1 unit of single culvert construction, Ø1.00m, length= 7.00m) KH-MOI-253015-CW-RFQ / Earth Road Repair and Laterite Pavement for Leang Dai Commune, Angkor Thum District, Siem Reap Province ( Component 1: Improving Request for Pending For line one, Length= 0.922 Request for Single Stage - One 2021-09- 2021-10- 2022-01- IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 37,682.00 0.00 Implementa Km, Width= 4.00 m, Quotations Envelope 22 27 25 and Vulnerable Households Bank-SPD) tion Thick=0.15m including 3 units of single culvert construction, Ø0.80m, length= 6.00m, 1 units of sing KH-MOI-253016-CW-RFQ / Earth Road Repair and Laterite Pavement for Sangkat Svay Dangkum , Siem Reap Municipality, Siem Reap Component 1: Improving Request for Pending Request for Single Stage - One 2021-09- 2021-10- 2022-01- Province (Total Length= IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 61,110.00 0.00 Implementa Quotations Envelope 22 27 25 1.799 Km, Width= 5.00 m, and Vulnerable Households Bank-SPD) tion Thick=0.15m including 1 unit of single culvert construction, Ø1.00m, length= 7.00m and 1 unit of double c KH-MOI-253017-CW-RFQ / Earth Road Repair and Laterite Pavement for Sangkat Component 1: Improving Request for Pending Request for Single Stage - One 2021-09- 2021-10- 2022-01- Krabei Riel , Siem Reap IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 9,885.00 0.00 Implementa Quotations Envelope 22 27 25 Municipality, Siem Reap and Vulnerable Households Bank-SPD) tion Province ( Total Length= 0.315 Km, Width= 5.00 m, Thick=0.15m ) Page 6 KH-MOI-253018-CW-RFQ / Earth Road Repair and Laterite Pavement for Sangkat Tuek Vil , Siem Reap Component 1: Improving Request for Pending Request for Single Stage - One 2021-09- 2021-10- 2022-01- Municipality, Siem Reap IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 20,757.00 0.00 Implementa Quotations Envelope 22 27 25 Province ( Total Length= 0.54 and Vulnerable Households Bank-SPD) tion Km, Width= 5.00 m, Thick=0.15m including 1 unit of single culvert construction, Ø1.00m, length= 7.00m ) KH-MOI-253019-CW-RFQ / Earth Road Repair and Laterite Pavement for Bakong Commune , Brasat Bakong District, Siem Reap Province ( Component 1: Improving Request for Pending Request for Single Stage - One 2021-09- 2021-10- 2022-01- Total Length= 1.015 Km, IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 24,131.00 0.00 Implementa Quotations Envelope 22 27 25 Width= 4.00 m, Thick=0.15m and Vulnerable Households Bank-SPD) tion including 6 unist of single culvert construction, Ø0.60m, Length= 5.00m, 1 unist of single culver KH-MOI-253020-CW-RFQ / Earth Road Repair and Laterite Pavement for Component 1: Improving Request for Pending Request for Single Stage - One 2021-09- 2021-10- 2022-01- Kantreang Commune , Brasat IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 37,561.00 0.00 Implementa Quotations Envelope 22 27 25 Bakong District, Siem Reap and Vulnerable Households Bank-SPD) tion Province ( Total Length= 3.695 Km, Width= 4.00 m, Thick=0.15m) KH-MOI-253021-CW-RFQ / Reinforced Concrete Road Construction for Kandeak Component 1: Improving Request for Pending Request for Single Stage - One 2021-09- 2021-10- 2022-01- Commune, Brasat Bakong IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 32,469.00 0.00 Implementa Quotations Envelope 22 27 25 District, Siem Reap Province ( and Vulnerable Households Bank-SPD) tion Total Length= 0.265 Km, Width= 4.00 m, Thick=0.15m) KH-MOI-253022-CW-RFQ / Earth Road Repair and Laterite Pavement for Roluos Component 1: Improving Request for Pending Request for Single Stage - One 2021-09- 2021-10- 2022-01- Commune, Brasat Bakong IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 37,913.00 0.00 Implementa Quotations Envelope 22 27 25 District, Siem Reap Province ( and Vulnerable Households Bank-SPD) tion Total Length= 3.892 Km, Width= 4.00 m, Thick=0.15m) KH-MOI-253023-CW-RFQ / Drilled Wells with Pump 8 Component 1: Improving Request for Pending places for Sasar Sdam Request for Single Stage - One 2021-09- 2021-10- 2022-01- IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 16,174.00 0.00 Implementa Commune, Pouk District, Quotations Envelope 22 27 25 and Vulnerable Households Bank-SPD) tion Siem Reap Province (Depth=5m, Ø150mm) KH-MOI-253024-CW-RFQ / Drilled Wells with Pump 3 Component 1: Improving Request for Pending places for Doun Kaev Request for Single Stage - One 2021-09- 2021-10- 2022-01- IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 6,065.00 0.00 Implementa Commune, Pouk District, Quotations Envelope 22 27 25 and Vulnerable Households Bank-SPD) tion Siem Reap Province (Depth=5m, Ø150mm) KH-MOI-253025-CW-RFQ / Earth Road Repair and Laterite Pavement for Khnat Commune, Pouk District, Component 1: Improving Request for Pending Request for Single Stage - One 2021-09- 2021-10- 2022-01- Siem Reap Province ( Total IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 27,381.00 0.00 Implementa Quotations Envelope 22 27 25 Length= 1.617 Km, Width= and Vulnerable Households Bank-SPD) tion 4.00 m, Thick=0.15m including 1 single culvert construction, Ø0.60m, length= 6.00m ) KH-MOI-253026-CW-RFQ / Earth Road Repair and Laterite Pavement for Lvea Commune, Pouk District, Component 1: Improving Request for Pending Siem Reap Province ( Total Request for Single Stage - One 2021-09- 2021-10- 2022-01- IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 46,633.00 0.00 Implementa Length= 2.225 Km, Width= Quotations Envelope 22 27 25 and Vulnerable Households Bank-SPD) tion 4.00 m, Thick=0.15m including 3 places of double culvert construction, Ø1.00m, length= 6.00m ) KH-MOI-253027-CW-RFQ / Drilled Wells with Pump 21 Component 1: Improving Request for Pending places for Mukh Paen Request for Single Stage - One 2021-09- 2021-10- 2022-01- IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 42,456.00 0.00 Implementa Commune, Pouk District, Quotations Envelope 22 27 25 and Vulnerable Households Bank-SPD) tion Siem Reap Province, (Depth=5m, Ø150mm) KH-MOI-253028-CW-RFQ / Drilled Wells with Pump 11 Component 1: Improving Request for Pending places for Prey Chruk Request for Single Stage - One 2021-09- 2021-10- 2022-01- IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 22,239.00 0.00 Implementa Commune, Pouk District, Quotations Envelope 22 27 25 and Vulnerable Households Bank-SPD) tion Siem Reap Province, (Depth=5m, Ø150mm) KH-MOI-253029-CW-RFQ / Earth Road Repair and Laterite Pavement for Reul Commune, Pouk District, Component 1: Improving Request for Pending Siem Reap Province ( Total Request for Single Stage - One 2021-09- 2021-10- 2022-01- IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 47,248.00 0.00 Implementa Length= 1.60 Km, Width= Quotations Envelope 22 27 25 and Vulnerable Households Bank-SPD) tion 4.00 m, Thick=0.15m including 4 places of single culvert construction, Ø0.80m, length= 6.00m ) KH-MOI-253030-CW-RFQ / Earth Road Repair and Laterite Pavement for Samraong Yea Commune, Component 1: Improving Request for Pending Pouk District, Siem Reap Request for Single Stage - One 2021-09- 2021-10- 2022-01- IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 45,144.00 0.00 Implementa Province ( Total Length= 2.10 Quotations Envelope 22 27 25 and Vulnerable Households Bank-SPD) tion Km, Width= 4.00 m, Thick=0.15m including 4 places of single culvert construction, Ø0.60m, length= 6.00m ) KH-MOI-253031-CW-RFQ / Earth Road Repair and Laterite Pavement for Chob Ta Trav Commune, Angkor Thum District, Siem Reap Component 1: Improving Request for Pending Request for Single Stage - One 2021-09- 2021-10- 2022-01- Province ( Total Length= IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 41,040.00 0.00 Implementa Quotations Envelope 22 27 25 1.772 Km, Width= 4.00 m, and Vulnerable Households Bank-SPD) tion Thick=0.15m including 2 places of single culvert construction, Ø1.00m, length= 6.00m and 1double culvert KH-MOI-253032-CW-RFQ / Water gate Construction 2 Component 1: Improving Request for Pending Request for Single Stage - One 2021-09- 2021-10- 2022-01- places for Chob Ta Trav IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 45,000.00 0.00 Implementa Quotations Envelope 22 27 25 Commune, Angkor Thum and Vulnerable Households Bank-SPD) tion District, Siem Reap Provincial KH-MOI-253033-CW-RFQ / Earth Road Repair and Laterite Pavement for Leang Dai Commune, Angkor Thum Component 1: Improving Request for Pending District, Siem Reap Province ( Request for Single Stage - One 2021-09- 2021-10- 2022-01- IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 22,163.00 0.00 Implementa Total Length= 0.974Km, Quotations Envelope 22 27 25 and Vulnerable Households Bank-SPD) tion Width= 4.00 m, Thick=0.15m including 3 places of single culvert construction, Ø1.00m, length= 5.00m) Page 7 KH-MOI-253034-CW-RFQ / Earth Road Repair and Laterite Pavement for Peak Snaeng Commune, Angkor Component 1: Improving Request for Pending Thum District, Siem Reap Request for Single Stage - One 2021-09- 2021-10- 2022-01- IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 35,005.00 0.00 Implementa Province ( Total Length= 0.98 Quotations Envelope 22 27 25 and Vulnerable Households Bank-SPD) tion Km, Width= 4.00 m, Thick=0.15m including 1 place of single culvert construction, Ø1.00m, length= 6.00m, 1triple culvert KH-MOI-253035-CW-RFQ / Earth Road Repair and Laterite Pavement for Svay Chek Commune, Angkor Component 1: Improving Request for Pending Thum District, Siem Reap Request for Single Stage - One 2021-09- 2021-10- 2022-01- IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 24,196.00 0.00 Implementa Province ( Total Length= Quotations Envelope 22 27 25 and Vulnerable Households Bank-SPD) tion 0.943 Km, Width= 4.00 m, Thick=0.15m including 1 place of single culvert construction, Ø1.00m, length= 7.00m) KH-MOI-253036-CW-RFQ / Earth Road Repair and Laterite Pavement for Boeng Mealea Commune, Svay Leu Component 1: Improving Request for Pending District, Siem Reap Province ( Request for Single Stage - One 2021-09- 2021-10- 2022-01- IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 23,729.00 0.00 Implementa Total Length= 1.15 Km, Quotations Envelope 22 27 25 and Vulnerable Households Bank-SPD) tion Width= 4.00 m, Thick=0.15m including 2 places of single culvert construction, Ø1.00m, length= 6.00m) KH-MOI-253037-CW-RFQ / Earth Road Repair and Laterite Pavement for Svay Leu Commune, Svay Leu District, Siem Reap Province ( Component 1: Improving Request for Pending Request for Single Stage - One 2021-09- 2021-10- 2022-01- Total Length= 1.05 Km, IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 38,068.00 0.00 Implementa Quotations Envelope 22 27 25 Width= 5.00 m, Thick=0.15m and Vulnerable Households Bank-SPD) tion including 1 place of single culvert construction, Ø1.00m, length= 7.00m, 2 places of double culvert con KH-MOI-253038-CW-RFQ / Earth Road Repair and Laterite Pavement for Ta Siem Commune, Svay Leu District, Siem Reap Province ( Total Component 1: Improving Request for Pending Request for Single Stage - One 2021-09- 2021-10- 2022-01- Length= 0.771 Km, Width= IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 22,587.00 0.00 Implementa Quotations Envelope 22 27 25 5.00 m, Thick=0.15m and Vulnerable Households Bank-SPD) tion including 1 single culvert , Ø0.80m, length= 6.00m, 1 single and double culvert,Ø1.00m KH-MOI-253039-CW-RFQ / Reinforced Concrete Road upgrade in Trapeang Krasang, Khan Pou Sen Chey ( Total length 275m, 4m width, Component 2: Improving Request for Pending Request for Single Stage - One 2021-09- 2021-10- 2022-01- 0.15m thickness) and IDA / 59600 Livelihoods for Urban Poor Post Open - National Quotations (Non 86,535.67 0.00 Implementa Quotations Envelope 16 21 19 Reinforced Concrete Road in and Vulnerable Households Bank-SPD) tion Sangkat Trapeang Krasang, Khan Pou Sen Chey ( Total length 178m, 4m width, 1.50) with Drainage System KH-MOI-253040-CW-RFQ / Reinforced Concrete Road in Phum Andong 1 & Phum Andong 2, Sangkat Kork Component 2: Improving Request for Pending Request for Single Stage - One 2021-09- 2021-10- 2022-01- Roka, Khan Preak Phnov ( IDA / 59600 Livelihoods for Urban Poor Post Open - National Quotations (Non 78,963.02 0.00 Implementa Quotations Envelope 16 21 19 Total length 561m, 4m width, and Vulnerable Households Bank-SPD) tion 0.15m thickness) and Drainage system (Total length 244m, 0.6m diameter). KH-MOI-253041-CW-RFQ / Reinforced Concrete Road in Sangkat Choam Chau 2, Khan Pou Sen Chey (Total length Component 2: Improving Request for Pending 60m, 4.50m width, 0.15m Request for Single Stage - One 2021-09- 2021-10- 2022-01- IDA / 59600 Livelihoods for Urban Poor Post Open - National Quotations (Non 59,825.69 0.00 Implementa thickness, 89m, 4m width, Quotations Envelope 16 21 19 and Vulnerable Households Bank-SPD) tion 0.15m thickness, 223m, 3m length, 0.15m thickness) and Drainage System ( Total length 377m, 0.6m diameter) KH-MOI-253042-CW-RFQ / Reinforced Concrete Road in Sangkat Prey Vaeng, Khan Dangkao ( Total length 104m, 5m width, 0.15m thickness, Component 2: Improving Request for Pending Request for Single Stage - One 2021-09- 2021-10- 2022-01- 82m, 4m width, 0.15m IDA / 59600 Livelihoods for Urban Poor Post Open - National Quotations (Non 56,055.11 0.00 Implementa Quotations Envelope 16 21 19 thickness, 128m, 3m length, and Vulnerable Households Bank-SPD) tion 0.15m thickness) and Drainage System ( Total length 190m, 0.6m diameter, 135m, 0.4m diameter). KH-MOI-259610-CW-RFQ / Reinforced Concrete Road Construction for Pou Treay Component 1: Improving Request for Pending Request for Single Stage - One 2021-11- 2021-12- 2022-03- Commune ,Pouk District, IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 42,895.00 0.00 Implementa Quotations Envelope 07 12 12 Siem Reap Province ( Total and Vulnerable Households Bank-SPD) tion Length=0.23 Km, Width= 5.00 m, Thick=0.15m) KH-MOI-259611-CW-RFQ / Construction of ring concrete water storage system with mesh fence surrounding, steel frame building with Component 1: Improving Request for Pending Request for Single Stage - One 2021-11- 2021-12- 2022-03- plastics zinc roof , water pipe IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 27,159.00 0.00 Implementa Quotations Envelope 07 12 12 distributed connection, and and Vulnerable Households Bank-SPD) tion installation of automatic solar pump 340W, for Khnang Phnum Commune, Svay Leu District KH-MOI-259612-CW-RFQ / Construction of livestock building and Chicken Component 1: Improving Request for Pending Request for Single Stage - One 2021-12- 2022-01- 2022-04- Incubator 2 places for Anlong IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 16,422.00 0.00 Implementa Quotations Envelope 06 10 10 Samnar Commune ,Chi and Vulnerable Households Bank-SPD) tion Kraeng District, Siem Reap Province, (Size: 4mx8m, 4mx8m) KH-MOI-259613-CW-RFQ / Construction of livestock building and Chicken Component 1: Improving Request for Pending Request for Single Stage - One 2021-12- 2022-01- 2022-04- Incubator 3 places for IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 24,633.00 0.00 Implementa Quotations Envelope 06 10 10 Kampong Kdei Commune ,Chi and Vulnerable Households Bank-SPD) tion Kraeng District, Siem Reap Province, (Size: 5mx8m) KH-MOI-259614-CW-RFQ / Construction of livestock building and Chicken Component 1: Improving Request for Pending Request for Single Stage - One 2021-12- 2022-01- 2022-04- Incubator 1 place for Chrouy IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 8,211.00 0.00 Implementa Quotations Envelope 06 10 10 Neang Nguon Commune ,Srei and Vulnerable Households Bank-SPD) tion Snam District, Siem Reap Province, (Size: 5mx8m) Page 8 KH-MOI-267134-CW-RFQ / Earth Road Repair and Laterite Pavement for Sambuor Commune, Kralanh Component 1: Improving Request for Pending Request for Single Stage - One 2022-01- 2022-02- 2022-05- District, Siem Reap Province IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 20,000.00 0.00 Implementa Quotations Envelope 05 09 10 (Length= 1.05 Km, Width= and Vulnerable Households Bank-SPD) tion 4.00 m, Thick=0.15m including 1 unit of single culvert construction, Ø0.80m, length 7.00m) KH-MOI-267135-CW-RFQ / Unlined Earth Canal Rehabilitation for Khlang Hay Commune, Srei Snam District,Siem Reap Province ( Component 1: Improving Request for Pending Request for Single Stage - One 2022-01- 2022-02- 2022-05- Length=3.35 Km, Depth= IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 63,783.00 0.00 Implementa Quotations Envelope 05 09 10 1.50 m including 2 units of and Vulnerable Households Bank-SPD) tion single culvert with gate, Ø1.00m,length 6.00m,1 unit of single culvert with gate, Ø0.60m, length= 6.0m KH-MOI-267137-CW-RFQ / Earth Road Repair and Laterite Pavement for Slaeng Spean Commune, Srei Snam Component 1: Improving Request for Pending District, Siem Reap Province ( Request for Single Stage - One 2022-01- 2022-02- 2022-05- IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 61,875.00 0.00 Implementa Length= 3.35 Km, Width= Quotations Envelope 05 09 10 and Vulnerable Households Bank-SPD) tion 4.00 m, Thick=0.15m including 1 unit of double culvert construction, Ø1.00m, length 6.00m.. KH-MOI-267138-CW-RFQ / Rehabilitation of Community Component 1: Improving Request for Pending Request for Single Stage - One 2022-01- 2022-02- 2022-05- Pond 2 places for Chi Kraeng IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 28,518.00 0.00 Implementa Quotations Envelope 05 09 10 Commune, Chi Kraeng and Vulnerable Households Bank-SPD) tion District, Siem Reap Province KH-MOI-267140-CW-RFQ / Rehabilitation of Community Pond and Construction of Component 1: Improving Request for Pending Request for Single Stage - One 2022-01- 2022-02- 2022-05- water tank's support 2 places IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 16,184.00 0.00 Implementa Quotations Envelope 05 09 10 for Kouk Thlork Kraom and Vulnerable Households Bank-SPD) tion Commune, Chi Kraeng District, Siem Reap Province. KH-MOI-267141-CW-RFQ / Drilled Wells Construction Component 1: Improving Request for Pending Request for Single Stage - One 2022-01- 2022-02- 2022-05- with Pump 1 place for Spean IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 7,998.00 0.00 Implementa Quotations Envelope 05 09 10 Tnoat Commune, Chi Kraeng and Vulnerable Households Bank-SPD) tion District, Siem Reap Province. KH-MOI-267142-CW-RFQ / Earth Road Repair and Laterite Pavement for Dan Run Commune , Sotr Nikom District, Siem Reap Province ( Component 1: Improving Request for Pending Request for Single Stage - One 2022-01- 2022-02- 2022-05- Total Length= 1.60 Km, IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 20,199.00 0.00 Implementa Quotations Envelope 05 09 10 Width= 5.00 m, Thick=0.15m and Vulnerable Households Bank-SPD) tion including 1 unit of double culvert construction with water gate, Ø1.00m, Length= 5.00m ) KH-MOI-267143-CW-RFQ / Rehabilitation of Community Ponds two place for Component 1: Improving Request for Pending Request for Single Stage - One 2022-01- 2022-02- 2022-05- Kampong Khleang Commune IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 25,234.00 0.00 Implementa Quotations Envelope 05 09 10 , Sotr Nikom District, Siem and Vulnerable Households Bank-SPD) tion Reap Province (Size:35mx35mx5m & 40mx40mx5m ) KH-MOI-267144-CW-RFQ / Earth Road Repair and Laterite Pavement for Ballangk Commune , Brasat Component 1: Improving Request for Pending Bakong District, Siem Reap Request for Single Stage - One 2022-01- 2022-02- 2022-05- IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 32,490.00 0.00 Implementa Province ( Total Length= Quotations Envelope 05 09 10 and Vulnerable Households Bank-SPD) tion 1.240 Km, Width= 4.00 m, Thick=0.15m including 3 unist of single culvert construction, Ø1.00m, Length= 6.00m, . KH-MOI-267145-CW-RFQ / Unlined Earth Canal Rehabilitation for Mean Chey Commune, Brasat Bakong Component 1: Improving Request for Pending District, Siem Reap Province ( Request for Single Stage - One 2022-01- 2022-02- 2022-05- IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 29,031.00 0.00 Implementa Total Length= 1.25 Km, Quotations Envelope 05 09 10 and Vulnerable Households Bank-SPD) tion Width= 1.50 m, Depth=2.00m including one place of box culvert with water gate 3mx2.50mx5m) KH-MOI-267146-CW-RFQ / Digging Community Pond 2 Component 1: Improving Request for Pending places for Kaev Poar Request for Single Stage - One 2022-01- 2022-02- 2022-05- IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 52,270.00 0.00 Implementa Commune, Pouk District, Quotations Envelope 05 09 10 and Vulnerable Households Bank-SPD) tion Siem Reap Province, (Size: 60mx50mx5m) KH-MOI-267147-CW-RFQ / Dike Rehabilitation for Trapeang Thum Commune, Brasat Bakong District, Siem Component 1: Improving Request for Pending Request for Single Stage - One 2022-01- 2022-02- 2022-05- Reap Province ( Total Length= IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 38,935.00 0.00 Implementa Quotations Envelope 05 09 10 0.80 Km, Depth=1.50m and Vulnerable Households Bank-SPD) tion including six place of single culvert with water gate, Ø1.00m, Length= 6.00m) KH-MOI-267149-CW-RFQ / Reinforced Concrete Road Construction for Pou Treay Component 1: Improving Request for Pending Request for Single Stage - One 2022-01- 2022-02- 2022-05- Commune ,Pouk District, IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 39,500.00 0.00 Implementa Quotations Envelope 05 09 10 Siem Reap Province ( Total and Vulnerable Households Bank-SPD) tion Length=0.23 Km, Width= 5.00 m, Thick=0.15m) KH-MOI-267151-CW-RFQ / Digging Community Pond for Component 1: Improving Request for Pending Request for Single Stage - One 2022-01- 2022-02- 2022-05- Trei Nhoar Commune, Pouk IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 47,500.00 0.00 Implementa Quotations Envelope 05 09 10 District, Siem Reap Province, and Vulnerable Households Bank-SPD) tion 4 places (Size: 50mx30mx5m) KH-MOI-267152-CW-RFQ / Digging Community Pond for Component 1: Improving Request for Pending Request for Single Stage - One 2022-01- 2022-02- 2022-05- Yeang Commune, Pouk IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 34,016.00 0.00 Implementa Quotations Envelope 05 09 10 District, Siem Reap Province, and Vulnerable Households Bank-SPD) tion 1 places (Size:100mx50mx5m) KH-MOI-267153-CW-RFQ / Earth Road Repair and Laterite Pavement for Sambuor Commune, Kralanh Component 1: Improving Request for Pending District, Siem Reap Province ( Request for Single Stage - One 2022-01- 2022-02- 2022-05- IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 21,086.00 0.00 Implementa Total Length= 0.95Km, Quotations Envelope 05 09 10 and Vulnerable Households Bank-SPD) tion Width= 4.00 m, Thick=0.15m including 1 place of single culvert construction, Ø1.00m, length= 7.00m ) Page 9 KH-MOI-267154-CW-RFQ / Earth Road Repair and Laterite Pavement for Tram Sasar Commune, Srei Snam Component 1: Improving Request for Pending District, Siem Reap Province ( Request for Single Stage - One 2022-01- 2022-02- 2022-05- IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 58,347.00 0.00 Implementa Total Length= 2.00Km, Quotations Envelope 05 09 10 and Vulnerable Households Bank-SPD) tion Width= 4.00 m, Thick=0.15m including 1 place of single culvert construction, Ø0.80m, length= 7.00m, . KH-MOI-267156-CW-RFQ / Earth Road Repair and Laterite Pavement for Kouk Component 1: Improving Request for Pending Thlork Kraom Commune, Request for Single Stage - One 2022-01- 2022-02- 2022-05- IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 50,569.00 0.00 Implementa Kouk Chi Kraeng District, Quotations Envelope 05 09 10 and Vulnerable Households Bank-SPD) tion Siem Reap Province ( Total Length= 2.385 Km, Width= 4.00 m, Thick=0.15m .. KH-MOI-267157-CW-RFQ / Construction of safe place for community evacuation for Sangkat Chong Khneas, Siem Component 1: Improving Request for Pending Request for Single Stage - One 2022-01- 2022-02- 2022-05- Reap Municilpality, Siem Reap IDA / 59600 Livelihoods for Rural Poor Post Open - National Quotations (Non 57,605.00 0.00 Implementa Quotations Envelope 05 09 10 Province (Length=0.52Km, and Vulnerable Households Bank-SPD) tion Width=20m) including1 unit of latrine construction with 4 rooms. KH-MOI-267160-CW-RFQ / Solar LED Power Street Component 2: Improving Request for Pending lighting in Phum Trapeang Request for Single Stage - One 2022-01- 2022-03- 2022-05- IDA / 59600 Livelihoods for Urban Poor Post Open - National Quotations (Non 2,523.40 0.00 Implementa Anhchanh 6, Sangkat Quotations Envelope 05 02 01 and Vulnerable Households Bank-SPD) tion Trapeang krasang, Khan Pou Sen Chey (Total Set 12 sets) KH-MOI-267165-CW-RFQ / Solar LED Power Street Component 2: Improving Request for Pending Request for Single Stage - One 2022-01- 2022-03- 2022-05- lighting in Phum Saen Sok 1, IDA / 59600 Livelihoods for Urban Poor Post Open - National Quotations (Non 7,610.90 0.00 Implementa Quotations Envelope 05 02 01 Sangkat Khmounh, Khan Saen and Vulnerable Households Bank-SPD) tion Sok (Total Set 37 sets) KH-MOI-267219-CW-RFQ / Solar LED Power Street Component 2: Improving Request for Pending lighting in Phum Andong1, Request for Single Stage - One 2022-01- 2022-03- 2022-05- IDA / 59600 Livelihoods for Urban Poor Post Open - National Quotations (Non 7,817.00 0.00 Implementa Phum Andong 2, Sangkat Quotations Envelope 05 02 01 and Vulnerable Households Bank-SPD) tion Kork Roka, Khan Prek Phnov (Total set 38 sets) KH-MOI-267220-CW-RFQ / Solar LED Power Street Component 2: Improving Request for Pending Request for Single Stage - One 2022-01- 2022-03- 2022-05- lighting in Phum Talei, IDA / 59600 Livelihoods for Urban Poor Post Open - National Quotations (Non 2,317.70 0.00 Implementa Quotations Envelope 05 02 01 Sangkat Dangkao, Khan and Vulnerable Households Bank-SPD) tion Dangkao (Total set 11 sets) KH-MOI-267223-CW-RFQ / Solar LED Power Street Component 2: Improving Request for Pending Request for Single Stage - One 2022-01- 2022-03- 2022-05- lighting in Phum 3 & 4 , IDA / 59600 Livelihoods for Urban Poor Post Open - National Quotations (Non 5,403.20 0.00 Implementa Quotations Envelope 05 02 01 Sangkat Boeung Kak 1, Khan and Vulnerable Households Bank-SPD) tion Toul Kork (Total set 26 sets) KH-MOI-267224-CW-RFQ / Solar LED Power Street Component 2: Improving Request for Pending Request for Single Stage - One 2022-01- 2022-03- 2022-05- lighting in Phum 2, Sangkat IDA / 59600 Livelihoods for Urban Poor Post Open - National Quotations (Non 6,637.40 0.00 Implementa Quotations Envelope 05 02 01 Chrang Chamreas 1, Khan and Vulnerable Households Bank-SPD) tion Russei Kao (Total set 32 sets) KH-MOI-267260-CW-RFQ / Solar LED Power Street Component 2: Improving Request for Pending Request for Single Stage - One 2022-01- 2022-03- 2022-05- lighting in Phum Prek Leap, IDA / 59600 Livelihoods for Urban Poor Post Open - National Quotations (Non 3,757.60 0.00 Implementa Quotations Envelope 05 02 01 Sankat Prek Leap, Khan Chroy and Vulnerable Households Bank-SPD) tion Changvar (Total set 18 Sets) KH-MOI-267261-CW-RFQ / Solar LED Power Street Component 2: Improving Request for Pending Request for Single Stage - One 2022-01- 2022-03- 2022-05- lighting in Phum 15 & 16, IDA / 59600 Livelihoods for Urban Poor Post Open - National Quotations (Non 10,340.00 0.00 Implementa Quotations Envelope 05 02 01 Sangkat Srah Chak, Khan and Vulnerable Households Bank-SPD) tion Daun Penh (Total set 50 sets) KH-MOI-267262-CW-RFQ / Solar LED Power Street Component 2: Improving Request for Pending Request for Single Stage - One 2022-01- 2022-03- 2022-05- lighting in Phum Prek Tanou, IDA / 59600 Livelihoods for Urban Poor Post Open - National Quotations (Non 6,431.70 0.00 Implementa Quotations Envelope 05 02 01 Sangkat Chak Angrae Leu, and Vulnerable Households Bank-SPD) tion Khan Mean Chey (Total set 31 sets) KH-MOI-267263-CW-RFQ / Reinforced concrete road in Phum Saen Sok 1, Sangkat Component 2: Improving Request for Pending Khmounh, Khan Saen Sok Request for Single Stage - One 2022-01- 2022-03- 2022-05- IDA / 59600 Livelihoods for Urban Poor Post Open - National Quotations (Non 18,925.00 0.00 Implementa (Total length 148m, 4m Quotations Envelope 05 02 01 and Vulnerable Households Bank-SPD) tion width, 0,15m thickness) Pipe culvert (Total length 6m, Ǿ80 Diameter) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-14029-GO-RFQ / Pending Component 3: Project Request for Single Stage - One 2017-07- 2017-09- 2017-10- Office Furniture for National IDA / 59600 Post Open - National 27,380.00 0.00 Implementati Management Quotations Envelope 14 03 18 Level and Sub National Level on KH-MOI-14017-GO-RFQ / Pending Component 3: Project Request for Single Stage - One 2017-07- 2017-09- 2017-11- Softwares ( Accounting) for IDA / 59600 Post Open - National 10,000.00 0.00 Implementati Management Quotations Envelope 31 20 19 PCO-MOI 1 unit on KH-MOI-26199-GO-RFB / Component 1: Improving Pending Motorcycles plus helmets for Single Stage - One 2017-10- 2017-10- 2017-11- 2017-12- 2018-01- 2018-03- IDA / 59600 Livelihoods for Rural Poor Post Request for Bids Open - National 226,100.00 0.00 Implementati National level and Sub- Envelope 02 16 15 06 03 04 and Vulnerable Households on National (Total 133 Units) KH-MOI-26827-GO-RFB / Lot1: Develop Management Information System (MIS) Pending Component 3: Project Single Stage - One 2017-11- 2017-11- 2017-12- 2018-01- 2018-02- 2018-04- System Lot2: Server, IDA / 59600 Post Request for Bids Open - National 140,000.00 0.00 Implementati Management Envelope 01 15 15 05 02 03 Network, Tablet, website, on etc.) Lot 3:MIS webside maintenance for PCO-MOI KH-MOI-33988-GO-RFQ / 4 Pending Component 3: Project Request for Single Stage - One 2017-11- 2017-12- 2017-12- Laptop Computers for IDA / 59600 Post Open - National 9,200.00 0.00 Implementati Management Quotations Envelope 05 05 20 Management on KH-MOI-34259-GO-RFB / Under Component 3: Project Single Stage - One 2017-11- 2019-01- 2017-11- 2017-12- 2019-02- 2018-01- 2018-02- 2018-04- Office Equipment for National IDA / 59600 Post Request for Bids Open - National 132,200.00 0.00 Implementati Management Envelope 08 10 13 15 15 14 18 19 and Sub National Leve on KH-MOI-36613-GO-UN / Lot1:Vehicles (Station Wagon) 3 units for -PCO-MOI and 1 units for MEF, Component 1: Improving Pending UN Agencies 2017-11- 2017-11- 2017-12- 2018-02- Lot2:Vehicles (Pick up Cars) IDA / 59600 Livelihoods for Rural Poor Post Direct 330,000.00 0.00 Implementati (Direct) 17 22 25 23 for 1units for GDA-MAFF, 3 and Vulnerable Households on units for Siem Reap and 2 units for PPM. The total Vehicles: 10 Units Page 10 KH-MOI-34266-GO-UN / Vehicles (Station Wagon) 3 Component 1: Improving UN Agencies 2017-11- 2017-11- 2017-12- 2018-02- units for -PCO-MOI and 1 IDA / 59600 Livelihoods for Rural Poor Post Direct 132,000.00 0.00 Canceled (Direct) 08 13 25 23 units for MEF, Total Vehicles: and Vulnerable Households 4 Units KH-MOI-11051-GO-RFB / Vehicles (Pick up Cars) for Component 1: Improving Single Stage - One 2017-10- 2017-10- 2017-11- 2017-12- 2018-01- 2018-05- 1units for GDA-MAFF, 3 units IDA / 59600 Livelihoods for Rural Poor Post Request for Bids Open - National 198,000.00 0.00 Canceled Envelope 02 16 15 15 07 07 for Siem Reap and 2 units for and Vulnerable Households PPM. Total Vehicles: 6 Units KH-MOI-99858-GO-RFQ / Pending Component 3: Project Request for Single Stage - One 2019-03- 2019-04- 2019-04- Total 7 Air Conditioners for IDA / 59600 Post Open - National 4,900.00 0.00 Implementati Management Quotations Envelope 06 03 17 PCO and MAFF on Pending KH-MOI-99860-GO-RFQ / Component 3: Project Request for Single Stage - One 2019-03- 2019-04- 2019-05- IDA / 59600 Post Open - National 20,000.00 0.00 Implementati Office Furniture for MOI-PCO Management Quotations Envelope 06 03 03 on KH-MOI-99861-GO-RFQ / Printing Material and Component 1: Improving Pending Thumbprint pad for Request for Single Stage - One 2019-03- 2019-04- 2019-05- IDA / 59600 Livelihoods for Rural Poor Post Open - National 22,644.00 0.00 Implementati SHG/producer Quotations Envelope 06 03 03 and Vulnerable Households on group/commune federation for 2019 KH-MOI-99863-GO-RFQ / Material for SHG/producer Component 1: Improving Pending Request for Single Stage - One 2019-03- 2019-04- 2019-05- group/commune federation IDA / 59600 Livelihoods for Rural Poor Post Open - National 31,250.00 0.00 Implementati Quotations Envelope 06 24 24 (Boxes for keeping and Vulnerable Households on documents and cash) KH-MOI-99865-GO-RFQ / Equipment for Component 1: Improving Pending Request for Single Stage - One 2019-03- 2019-04- 2019-04- Commune/Sangkat IDA / 59600 Livelihoods for Rural Poor Post Open - National 10,000.00 0.00 Implementati Quotations Envelope 06 03 18 Investment Projects (SRP and and Vulnerable Households on PPCH) KH-MOI-99868-GO-RFQ / Component 1: Improving Pending 72 Tablets for MIS (3 MoI, 3 Request for Single Stage - One 2019-04- 2019-05- 2019-06- IDA / 59600 Livelihoods for Rural Poor Post Open - National 24,840.00 0.00 Implementati GDA, 3 PPCH, 3 Pro. S_Reap, Quotations Envelope 06 04 03 and Vulnerable Households on 47 commune, 13 Sangkat) KH-MOI-99869-GO-RFQ / Printing Materials (Logos, Component 1: Improving Pending Request for Single Stage - One 2019-05- 2019-06- 2019-06- Printed Folder, Factsheets, IDA / 59600 Livelihoods for Rural Poor Post Open - National 20,250.00 0.00 Implementati Quotations Envelope 06 03 24 Newsletters, Brochures, and Vulnerable Households on Posters and Standing Poster) KH-MOI-99871-GO-RFQ / Printing Materials for Component 1: Improving Under Request for Single Stage - One 2019-12- 2020-01- 2020-02- SHG/producer IDA / 59600 Livelihoods for Rural Poor Post Open - National 20,145.00 0.00 Implementati Quotations Envelope 06 04 03 group/commune federation and Vulnerable Households on for 2020 KH-MOI-26829-GO-RFB / Material for SHG/Poducer group/commune Component 1: Improving federation(books keeping, Single Stage - One 2017-11- 2017-11- 2017-12- 2018-01- 2018-02- 2018-04- IDA / 59600 Livelihoods for Rural Poor Post Request for Bids Open - National 126,250.70 0.00 Canceled cash book, pay and loan Envelope 01 15 15 05 02 03 and Vulnerable Households record book, SHG box for keeping docs. And Thumprint pad) for SRP KH-MOI-121052-GO-RFQ / Pending Component 3: Project Request for Single Stage - One 2019-07- 2019-08- 2019-09- Procurement of supply Server IDA / 59600 Post Open - National 20,000.00 0.00 Implementati Management Quotations Envelope 10 04 03 and network for LEAP Project on KH-MOI-136652-GO-RFQ / Component 1: Improving Pending Request for Single Stage - One 2019-10- 2019-11- 2019-11- Office Furniture for Skill IDA / 59600 Livelihoods for Rural Poor Post Open - National 4,400.00 0.00 Implementati Quotations Envelope 16 11 25 Development Activities and Vulnerable Households on KH-MOI-136666-GO-RFQ / Component 1: Improving Pending Motorcycles for Skill Request for Single Stage - One 2019-10- 2019-11- 2019-11- IDA / 59600 Livelihoods for Rural Poor Post Open - National 17,500.00 0.00 Implementati Development Activities (10 Quotations Envelope 16 11 25 and Vulnerable Households on Units) KH-MOI-168855-GO-RFQ / Component 1: Improving Pending Vehicles (VAN) 1 units for - Request for Single Stage - One 2020-04- 2020-06- 2020-07- IDA / 59600 Livelihoods for Rural Poor Post Open 30,000.00 0.00 Implementati PCO-MOI ( Import tax will be Quotations Envelope 29 05 05 and Vulnerable Households on exempted) KH-MOI-168856-GO-RFQ / Component 1: Improving Pending Request for Single Stage - One 2020-05- 2020-05- 2020-06- Office Furniture for Sub IDA / 59600 Livelihoods for Rural Poor Post Open - National 16,915.00 0.00 Implementati Quotations Envelope 02 28 27 National Level (PCO, SRP ) and Vulnerable Households on KH-MOI-168859-GO-RFQ / Study Equipment (Hummer Component 1: Improving Pending Test, DCP Test, Autormatic Request for Single Stage - One 2020-05- 2020-05- 2020-06- IDA / 59600 Livelihoods for Rural Poor Post Open - National 11,000.00 0.00 Implementati Level, GPS…2sets) for Quotations Envelope 06 29 13 and Vulnerable Households on Commnune/Sangkat Investment Projects (SRP) KH-MOI-168860-GO-RFQ / Printing Communication Component 1: Improving Pending Materials (LEAP Newsletters Request for Single Stage - One 2020-06- 2020-07- 2020-08- IDA / 59600 Livelihoods for Rural Poor Post Open - National 12,000.00 0.00 Implementati semi-annual (2time/years) in Quotations Envelope 20 18 08 and Vulnerable Households on Khmer and English 2time/year) KH-MOI-168861-GO-RFQ / Component 1: Improving Pending Printing Communication Request for Single Stage - One 2020-09- 2020-10- 2020-10- IDA / 59600 Livelihoods for Rural Poor Post Open - National 4,000.00 0.00 Implementati Materials ( Success Story 4 Quotations Envelope 06 04 25 and Vulnerable Households on time/year) KH-MOI-168862-GO-RFQ / Component 1: Improving Pending Request for Single Stage - One 2020-09- 2020-09- 2020-10- Video Production of project IDA / 59600 Livelihoods for Rural Poor Post Open - National 7,000.00 0.00 Implementati Quotations Envelope 06 29 29 achievement (15 Minute) and Vulnerable Households on KH-MOI-226724-GO-RFB / Component 1: Improving Under Vehicles (VAN) 1 units for - Single Stage - One 2021-04- 2021-04- 2021-04- 2021-04- 2021-05- 2021-06- 2021-07- 2021-08- IDA / 59600 Livelihoods for Rural Poor Post Request for Bids Open - National 130,000.00 0.00 Implementati PCO-MOI, Vehicles (Pick up Envelope 18 23 23 27 23 22 27 02 and Vulnerable Households on Cars) 2 units for Siem Reap KH-MOI-226726-GO-UN / Component 2: Improving Pending SUV Vehicles 1 units for UN Agencies 2021-04- 2021-04- 2021-06- 2021-08- IDA / 59600 Livelihoods for Urban Poor Post Direct 40,000.00 0.00 Implementati PPCH( Import tax will be (Direct) 18 21 02 31 and Vulnerable Households on exempted) KH-MOI-226728-GO-RFQ / Component 1: Improving Under Request for Single Stage - One 2021-04- 2021-04- 2021-05- 2021-06- Motorcycles( 12 Units for SRP IDA / 59600 Livelihoods for Rural Poor Post Open - National 30,000.00 0.00 Implementati Quotations Envelope 19 27 29 28 and 3 Units for MAFFs) and Vulnerable Households on KH-MOI-226744-GO-RFQ / Office Equipment: (4 Laptops for PCO, 2 Laptops for PPCH Under Component 3: Project Request for Single Stage - One 2021-04- 2021-05- 2021-06- 2021-07- ,5 Laptops for MAFF , 4 Note IDA / 59600 Post Open - National 33,032.00 0.00 Implementati Management Quotations Envelope 26 21 23 23 Book for SC, 2 Desktops for on PPCH, 1 Printer for MAFF, and 15 Tablets for New CF- SRP) KH-MOI-226750-GO-RFQ / Procurement of 1 unit Stability Camera Stand ,1 unit Pending Zoom-Len Camera ,1 Unit Component 3: Project Request for Single Stage - One 2021-05- 2021-06- 2021-07- IDA / 59600 Post Open - National 7,400.00 0.00 Implementati Drone Camera for SRP and Management Quotations Envelope 02 15 15 on 1Unit Zoom-Len Camera,1set Equipment of video conference for PPCH Page 11 KH-MOI-226753-GO-RFQ / Pending Installation Microphone Component 3: Project Request for Single Stage - One 2021-06- 2021-07- 2021-08- IDA / 59600 Post Open - National 20,000.00 0.00 Implementati System for PCO-LEAP meeting Management Quotations Envelope 02 16 15 on room KH-MOI-226767-GO-RFQ / Materials for SHG/producer group (14000 Cash book for SHGs member, 1200 SHGs Component 1: Improving Under Request for Single Stage - One 2021-04- 2021-04- 2021-06- 2021-07- Saving, Loan & Repayment IDA / 59600 Livelihoods for Rural Poor Post Open - National 30,400.00 0.00 Implementati Quotations Envelope 26 27 23 23 Books,1200 SHG minute and Vulnerable Households on books, 4000 SHG minute books and 1200 Thumbprint pad for SHG 2021 KH-MOI-226770-GO-RFQ / Purchase 25 Booth for PGs to Component 1: Improving Under Request for Single Stage - One 2021-05- 2021-06- 2021-07- promote agriculture products IDA / 59600 Livelihoods for Rural Poor Post Open - National 6,875.00 0.00 Implementati Quotations Envelope 04 10 10 for weekend Market for SMT- and Vulnerable Households on SRP KH-MOI-226776-GO-RFQ / Printing Communication Component 1: Improving Under Materials (LEAP Newsletters Request for Single Stage - One 2021-05- 2021-11- 2021-06- 2021-12- IDA / 59600 Livelihoods for Rural Poor Post Open - National 8,500.00 0.00 Implementati semi-annual (2time/years) in Quotations Envelope 08 10 05 02 and Vulnerable Households on Khmer and English 2time/year) 2021 KH-MOI-226782-GO-RFQ / Printing 140 Produce PCV Component 1: Improving Pending Request for Single Stage - One 2021-04- 2021-05- 2021-06- Banner and 11200 leaflets on IDA / 59600 Livelihoods for Rural Poor Post Open - National 9,400.00 0.00 Implementati Quotations Envelope 19 25 15 Skills Development and Vulnerable Households on information for SRP and PPCH KH-MOI-226783-GO-RFQ / Printing Tools to Provide technical training for CAHEWs in Q1 and Q2 on (Chicken Eggs Incubator Making), Component 1: Improving Under Request for Single Stage - One 2021-05- 2021-11- 2021-06- 2021-12- (how to use vaccination kits), IDA / 59600 Livelihoods for Rural Poor Post Open - National 52,500.00 0.00 Implementati Quotations Envelope 04 01 30 27 50 Sets ( chicken raising ) (Pig and Vulnerable Households on Raising) and 50 Sets PCV Banner Training Tools (Fish (rice and vegetable production) KH-MOI-226784-GO-RFQ / Component 1: Improving Pending Design and print out banner Request for Single Stage - One 2021-05- 2021-06- 2021-06- IDA / 59600 Livelihoods for Rural Poor Post Open - National 3,000.00 0.00 Implementati to mainstream information on Quotations Envelope 04 09 30 and Vulnerable Households on gender to target beneficiaries KH-MOI-283063-GO-RFQ / Printing Newsletters semi- Component 1: Improving Pending Request for Single Stage - One 2022-05- 2022-06- 2022-06- annual (2 time/year) and IDA / 59600 Livelihoods for Rural Poor Post Open - National 12,750.00 0.00 Implementati Quotations Envelope 06 03 24 Success Story leaflet (SRP and and Vulnerable Households on PPCH) KH-MOI-283065-GO-RFQ / Printing Material for SHG Component 1: Improving Pending Request for Single Stage - One 2022-04- 2022-05- 2022-06- (SHGs cash, bank book, SHGs IDA / 59600 Livelihoods for Rural Poor Post Open - National 5,500.00 0.00 Implementati Quotations Envelope 20 18 08 saving, loan & repayment and Vulnerable Households on book) total 2000books KH-MOI-283066-GO-RFQ / Design and print out Poster to Component 1: Improving Pending Request for Single Stage - One 2022-04- 2022-05- 2022-06- mainstream information on IDA / 59600 Livelihoods for Rural Poor Post Open - National 3,000.00 0.00 Implementati Quotations Envelope 20 18 08 gender to target beneficiaries and Vulnerable Households on (SHGs1,000) NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-99864-NC-RFQ / Under Component 3: Project Request for Single Stage - One 2019-03- 2019-04- 2019-05- Develop Website for LEAP IDA / 59600 Post Open - National 5,600.00 0.00 Implementati Management Quotations Envelope 06 03 03 Projec on Component 1: Improving Pending KH-MOI-99870-NC-RFQ / Request for Single Stage - One 2019-07- 2019-08- 2019-10- IDA / 59600 Livelihoods for Rural Poor Post Open - National 20,000.00 0.00 Implementati Four (4) Video Spots Quotations Envelope 06 17 16 and Vulnerable Households on KH-MOI-226780-NC-RFQ / Under Component 3: Project Request for Single Stage - One 2021-07- 2021-09- 2021-08- 2021-10- Video Production of project IDA / 59600 Post Open - National 7,000.00 0.00 Implementati Management Quotations Envelope 06 20 17 16 achievement 2021 on KH-MOI-283064-NC-RFQ / Pending Produce short video stories Component 3: Project Request for Single Stage - One 2022-06- 2022-07- 2022-09- IDA / 59600 Post Open - National 7,000.00 0.00 Implementati (15 minutes) on project Management Quotations Envelope 06 18 16 on achievements (PCO) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-39863-CS-CQS / Consultant Impact Survey (3nd year of Component 3: Project Pending 2020-01- 2020-03- 2020-04- 2020-05- 2020-11- IDA / 59600 Post Qualification Open - National 30,000.00 0.00 2020-01-02 the project/Mid-term review) Management Implementation 23 07 06 11 07 Selection (Local Firm) at PCO-MOI KH-MOI-39867-CS-CQS / Final Impact Survey ( (5th year Consultant Component 3: Project Pending 2022-01- 2022-03- 2022-04- 2022-05- 2022-11- of Project evaluation and IDA / 59600 Post Qualification Open - National 40,000.00 0.00 2022-01-03 Management Implementation 24 09 08 13 09 completion report) (Local Selection Firm) at PCO-MOI KH-MOI-82848-CS-CQS / Development of Community Component 1: Improving Consultant Institutions of the Poor for 4 Under 2019-01- 2018-11- 2019-01- 2019-02- 2019-03- 2022-11- IDA / 59600 Livelihoods for Rural Poor Post Qualification Open - National 280,000.00 0.00 2018-10-22 Districts​​  (Angkor Thum, Implementation 18 12 11 10 17 30 and Vulnerable Households Selection Kralanh, Pouk and Srei Snam District) KH-MOI-82083-CS-CQS / Development of Community Component 1: Improving Consultant Institutions of the Poor for 5 Under 2018-12- 2018-11- 2019-01- 2019-03- 2019-02- 2019-03- 2022-12- IDA / 59600 Livelihoods for Rural Poor Post Qualification Open - National 290,000.00 0.00 2018-10-22 Districts ( Chi Kraeng, Prasat Implementation 21 12 11 22 10 17 05 and Vulnerable Households Selection Bakong, Siem Reap, Soutr Nikom and Svay Leu District) KH-MOI-70310-CS-QCBS / Component 1: Improving Human Resource Quality And Cost- Open - 2019-01- 2019-01- 2019-02- 2019-05- 2019-04- 2019-05- 2019-06- 2019-07- 2023-06- IDA / 59600 Livelihoods for Rural Poor Prior 784,000.00 0.00 Canceled 2018-12-14 Development Service Provider Based Selection International 13 16 26 10 12 12 16 21 30 and Vulnerable Households (HRDSP) for SRP and PPCH KH-MOI-39858-CS-QCBS / Human Resources Component 2: Improving Quality And Cost- Open - 2018-01- 2018-03- 2018-04- 2018-05- 2018-06- 2018-07- 2020-12- Development Services IDA / 59600 Livelihoods for Urban Poor Post 367,932.00 0.00 Canceled 2017-12-29 Based Selection International 19 04 01 01 05 10 26 Provider(HRDSP) for PPM and Vulnerable Households (NGO/Firm) KH-MOI-39860-CS-CQS / Consultant Component 3: Project 2018-02- 2018-03- 2018-04- 2018-05- 2018-11- Baseline Survey (1st IDA / 59600 Post Qualification Open - National 30,000.00 0.00 Canceled 2018-01-15 Management 05 21 20 25 21 year)(Local Firm) at PCO-MOI Selection Page 12 KH-MOI-39857-CS-QCBS / Human Resources Component 1: Improving Quality And Cost- Open - 2018-01- 2018-03- 2018-04- 2018-05- 2018-06- 2018-07- 2020-12- Development Services IDA / 59600 Livelihoods for Rural Poor Post 545,936.00 0.00 Canceled 2017-12-29 Based Selection International 19 04 01 01 05 10 26 Provider(HRDSP) for SRP and Vulnerable Households (NGO/Firm) KH-MOI-187154-CS-CQS / Tracer Study Consultant for Component 1: Improving Consultant Under 2020-08- 2020-08- 2020-08- 2020-10- 2020-11- 2020-12- 2022-12- 24 months (one firm IDA / 59600 Livelihoods for Rural Poor Post Qualification Open - National 45,000.00 0.00 2020-08-10 Implementation 07 31 23 14 13 18 08 consultant will be hired for and Vulnerable Households Selection both SRP and PPCH) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-13893-CS-INDV / Component 1: Improving Individual Under 2017-12- 2017-08- 2018-04- 2017-09- 2018-04- 2017-10- 2022-10- Provincial Operation and M&E IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 120,000.00 0.00 2017-06-26 Implementation 07 23 30 06 30 11 10 Specialist for SRP (60 Months) and Vulnerable Households Selection KH-MOI-13901-CS-INDV / Individual Component 3: Project Pending 2017-09- 2017-09- 2017-10- 2020-10- Project Assistant for PCO-MOI IDA / 59600 Post Consultant Open 18,000.00 0.00 2017-07-17 Management Implementation 06 20 25 24 (60 Months) Selection KH-MOI-13903-CS-INDV / Component 2: Improving Individual Pending 2017-08- 2017-09- 2017-10- 2022-10- National Operation and M&E IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 150,000.00 0.00 2017-06-26 Implementation 23 06 11 10 Specialist for PPM (60 Months) and Vulnerable Households Selection KH-MOI-13905-CS-INDV / Component 1: Improving Individual Provincial Finance Pending 2017-08- 2017-09- 2017-10- 2020-10- IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 72,000.00 0.00 2017-06-26 Management Specialist for Implementation 23 06 11 10 and Vulnerable Households Selection SRP (36 Months) KH-MOI-13907-CS-INDV / Component 1: Improving Individual Pending 2017-09- 2017-09- 2017-10- 2022-10- Project Assistant for SRP (60 IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 15,000.00 0.00 2017-07-17 Implementation 06 20 25 24 Months) and Vulnerable Households Selection KH-MOI-13910-CS-INDV / Component 2: Improving Individual Pending 2017-09- 2017-09- 2017-10- 2022-10- Project Assistant for PPM (60 IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 15,000.00 0.00 2017-07-17 Implementation 06 20 25 24 Months) and Vulnerable Households Selection KH-MOI-13913-CS-INDV / Component 2: Improving Individual Pending 2017-09- 2017-09- 2017-11- 2020-10- 01 PPM Infrastructure IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 72,000.00 0.00 2017-07-17 Implementation 13 27 01 31 Specialist at PPM (36 Months) and Vulnerable Households Selection KH-MOI-11055-CS-INDV / Individual National Project Management Component 3: Project Pending 2017-10- 2017-10- 2017-12- 2022-11- IDA / 59600 Post Consultant Open 180,000.00 0.00 2017-08-16 and M&E consultant at PCO- Management Implementation 13 27 01 30 Selection MOI KH-MOI-11263-CS-INDV / Component 1: Improving Individual National Finance Management Pending 2017-10- 2017-10- 2017-12- 2020-11- IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 90,000.00 0.00 2017-08-16 Specialist for MOI/PPM(36 Implementation 13 27 01 30 and Vulnerable Households Selection Months) KH-MOI-13886-CS-INDV / Component 2: Improving Individual Pending 2017-10- 2017-10- 2017-12- 2020-11- National procurement IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 90,000.00 0.00 2017-08-16 Implementation 13 27 01 30 Specialist based at PCO and Vulnerable Households Selection KH-MOI-30826-CS-INDV / Component 1: Improving Individual Provincial Infrastructure Pending 2017-12- 2017-12- 2018-01- 2021-01- IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 72,000.00 0.00 2017-10-16 Specialist (P M & E Engineer) Implementation 04 25 29 13 and Vulnerable Households Selection at SRP (36 Months) KH-MOI-30834-CS-INDV / Provincial Infrastructure Component 1: Improving Individual Pending 2017-12- 2017-12- 2018-01- 2021-01- Specialist (Building IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 72,000.00 0.00 2017-10-16 Implementation 04 25 29 13 Construction Engineer) at SRP and Vulnerable Households Selection (36 Months) KH-MOI-30840-CS-INDV / Provincial Infrastructure Component 1: Improving Individual Pending 2017-12- 2017-12- 2018-01- 2021-01- Specialist (Rural Road IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 72,000.00 0.00 2017-10-16 Implementation 04 25 29 13 Construction Engineer) at SRP and Vulnerable Households Selection (36 Months) KH-MOI-39794-CS-INDV / Individual Component 3: Project Pending 2018-03- 2018-04- 2018-05- 2018-07- International Micro-Finance IDA / 59600 Post Consultant Open 60,000.00 0.00 2018-02-01 Management Implementation 22 12 17 16 Expert at PCO-MOI(60 days) Selection KH-MOI-39797-CS-INDV / Individual National Communication Component 3: Project Pending 2018-03- 2018-03- 2018-04- 2021-04- IDA / 59600 Post Consultant Open 90,000.00 0.00 2018-01-15 Specialist at PCO-MOI (36 Management Implementation 05 26 30 14 Selection Months) KH-MOI-39798-CS-INDV / Individual Component 3: Project Pending 2018-02- 2018-03- 2018-04- 2020-04- National MIS Specialist at PCO- IDA / 59600 Post Consultant Open 60,000.00 0.00 2017-12-29 Management Implementation 16 09 13 02 MOI (24 Months) Selection KH-MOI-39800-CS-INDV / Component 1: Improving Individual National Agriculture Pending 2018-03- 2018-03- 2018-04- 2021-04- IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 90,000.00 0.00 2018-01-15 Likelihood Specialist for GDA- Implementation 05 26 30 14 and Vulnerable Households Selection MAFF (36 Months) KH-MOI-39817-CS-INDV / Component 1: Improving Individual Pending 2018-02- 2018-03- 2018-04- 2020-04- National HR Development IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 48,000.00 0.00 2017-12-29 Implementation 16 09 13 02 Specialist for SRP (24 Months) and Vulnerable Households Selection KH-MOI-39821-CS-INDV / Component 2: Improving Individual National HR Development Pending 2018-03- 2018-04- 2018-05- 2020-05- IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 48,000.00 0.00 2018-02-01 Specialist for PPM ( 24 Implementation 22 12 17 06 and Vulnerable Households Selection Months) KH-MOI-39888-CS-INDV / 7 Component 1: Improving Individual Pending 2018-03- 2018-04- 2018-05- 2022-11- District Facilitators (7 DF x 55 IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 336,000.00 0.00 2018-02-01 Implementation 22 12 17 22 Months) at Siem Reap and Vulnerable Households Selection KH-MOI-40438-CS-INDV / Component 1: Improving Individual Pending 2018-03- 2018-04- 2018-05- 2021-05- Provincial Micro-Finance IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 72,000.00 0.00 2018-02-01 Implementation 22 12 17 01 Specialist for SRP ( 36 and Vulnerable Households Selection Months) KH-MOI-40440-CS-INDV / Component 1: Improving Individual Senior Livelihood/business Pending 2018-03- 2018-04- 2018-05- 2021-05- IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 90,000.00 0.00 2018-02-01 development Specialist for Implementation 22 12 17 01 and Vulnerable Households Selection SRP (36 Months) KH-MOI-40447-CS-INDV / Component 1: Improving Individual Pending 2018-03- 2018-04- 2018-05- 2022-11- 47 Commune Facilitators IDA / 59600 Livelihoods for Rural Poor Prior Consultant Open 564,000.00 0.00 2018-02-01 Implementation 22 12 17 22 (47CFs x55 Months) for SRP and Vulnerable Households Selection KH-MOI-40449-CS-INDV / Component 1: Improving Individual 47 Commune Animal Health Pending 2018-03- 2018-04- 2018-05- 2022-11- IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 338,400.00 0.00 2018-02-01 & Extension Workers (47 Implementation 22 12 17 22 and Vulnerable Households Selection CAHEW x 55 Months) for SRP KH-MOI-40453-CS-INDV / 4 Component 2: Improving Individual Local Coordinator for urban Pending 2018-03- 2018-04- 2018-05- 2022-11- IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 96,000.00 0.00 2018-02-01 poor(4CLUPs x 55 Months) for Implementation 22 12 17 22 and Vulnerable Households Selection PPM Individual KH-MOI-99872-CS-INDV / Component 3: Project Pending 2019-04- 2019-05- 2019-06- 2022-06- IDA / 59600 Post Consultant Open 15,000.00 0.00 2019-03-01 Project Assistant for MAFF Management Implementation 21 05 09 08 Selection Page 13 KH-MOI-99873-CS-INDV / Component 1: Improving Individual 2019-07- 2019-07- 2019-08- 2019-10- Tracer Study Consultant (60 IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 18,000.00 0.00 Canceled 2019-06-03 22 29 12 11 Working Days) and Vulnerable Households Selection KH-MOI-136635-CS-INDV / International Skill Component 1: Improving Individual Development Advisor (120 Under 2019-10- 2019-11- 2019-11- 2019-11- 2020-03- IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 112,800.00 0.00 2019-10-04 days x 1 pax) for (20day- Implementation 18 10 15 28 27 and Vulnerable Households Selection 2019, 80 days-2020 and 20 days-2021) KH-MOI-136641-CS-INDV / Component 2: Improving Individual National Skills Development Pending 2019-11- 2019-11- 2019-11- 2022-09- IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 85,000.00 0.00 2019-10-04 Specialist (34 monthsx1pax) Implementation 10 15 28 13 and Vulnerable Households Selection for PCO-LEAP KH-MOI-136643-CS-INDV / Component 2: Improving Individual Human Resource Pending 2019-11- 2019-11- 2019-11- 2022-09- IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 190,400.00 0.00 2019-10-04 Development Facilitators for Implementation 10 15 28 13 and Vulnerable Households Selection SRP (34month x 7 paxes) KH-MOI-136648-CS-INDV / Component 1: Improving Individual Human Resource Pending 2019-11- 2019-11- 2019-11- 2022-09- IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 81,600.00 0.00 2019-10-04 Development Facilitators for Implementation 10 15 28 13 and Vulnerable Households Selection PPCH (34month x 3 paxes) KH-MOI-168864-CS-INDV / National Consultant for Component 1: Improving Individual Pending 2020-07- 2020-08- 2020-09- 2022-09- Market Linkage Study IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 56,000.00 0.00 2020-05-24 Implementation 12 02 06 06 (Intermittent) for 3 year (2020- and Vulnerable Households Selection 2022) KH-MOI-168866-CS-INDV / National Consultant for Component 1: Improving Individual Pending 2020-06- 2020-07- 2020-08- 2022-08- Sturdy research promote IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 31,200.00 0.00 2020-05-01 Implementation 19 10 14 14 Linkage with formal Financial and Vulnerable Households Selection sector for 3 year (2020- 20220) KH-MOI-220888-CS-INDV / Component 1: Improving Individual Procure to replacement of Ms. Under 2021-02- 2021-04- 2021-04- 2021-04- 2022-04- IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 33,360.00 0.00 2021-03-01 Teng Ratana Resigned on 22 Implementation 23 03 08 22 22 and Vulnerable Households Selection July 2020 KH-MOI-226811-CS-INDV / One National procurement Component 2: Improving Individual Specialist based at PCO (12 Under 2021-04- 2021-06- 2021-06- 2021-07- 2022-07- IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 30,000.00 0.00 2021-04-08 months) to replacement Mr. Implementation 23 05 19 24 24 and Vulnerable Households Selection Chay Ponlork Resigned on 01 Oct 2019 KH-MOI-226812-CS-INDV / Individual One National Independent Component 3: Project Under 2021-10- 2021-06- 2021-07- 2021-08- 2021-10- IDA / 59600 Post Consultant Open 6,000.00 0.00 2021-05-03 auditor for Infrastructure with Management Implementation 25 21 12 16 15 Selection (2 month 2021) Based in PCO KH-MOI-226814-CS-INDV / Component 1: Improving Individual One National Agriculture Under 2021-04- 2021-05- 2021-06- 2021-07- 2022-07- IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 30,000.00 0.00 2021-04-08 Likelihood Specialist for GDA- Implementation 23 27 17 22 22 and Vulnerable Households Selection MAFF (12 Months) KH-MOI-226815-CS-INDV / Provincial Infrastructure Specialist (Rural Road Component 1: Improving Individual Under 2021-04- 2021-05- 2021-06- 2021-07- 2022-07- Construction Engineer) at SRP IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 24,000.00 0.00 2021-04-08 Implementation 23 27 17 22 22 (12 Months) to replacement and Vulnerable Households Selection Mr Set Chamroeun Resigned on 31 Jan 21 KH-MOI-226816-CS-INDV / Individual One Junior Finance/Admin Component 3: Project 2021-05- 2021-06- 2021-07- 2021-08- 2022-08- IDA / 59600 Post Consultant Open 9,600.00 0.00 Under Review 2021-05-03 Officer Based in PCO (12 Management 21 23 07 11 11 Selection Months) KH-MOI-226817-CS-INDV / Component 2: Improving Individual One Junior Finance/Admin 2021-05- 2021-06- 2021-07- 2021-08- 2022-08- IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 9,600.00 0.00 Under Review 2021-05-03 Officer Based in SMT-PPCH 21 23 07 11 11 and Vulnerable Households Selection (12 Months) KH-MOI-226818-CS-INDV / Component 1: Improving Individual One Junior Finance/Admin 2021-05- 2021-06- 2021-07- 2021-08- 2022-08- IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 9,600.00 0.00 Under Review 2021-05-03 Officer Based in SMT- SRP (12 21 23 07 11 11 and Vulnerable Households Selection Months) KH-MOI-226819-CS-INDV / Component 1: Improving Individual One Promote finance linkage Pending 2021-06- 2021-06- 2021-07- 2022-07- IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 9,600.00 0.00 2021-05-03 facilitators Base in SMT-SRP Implementation 09 23 26 26 and Vulnerable Households Selection (1pax x12 Months) KH-MOI-259609-CS-INDV / Individual Component 3: Project Under 2022-02- 2021-12- 2022-01- 2022-02- 2022-03- Gender specialist (20 working IDA / 59600 Post Consultant Open 6,000.00 0.00 2021-11-02 Management Implementation 03 21 11 15 17 days) Selection Page 14