Procurement Plan I. General 1. Project Information Country : Kenya Recipient : Republic of Kenya Project Name : National Agriculture and Rural Inclusive Growth Loan Credit No. : IDA 59000 2. Date of General Procurement Notice : 9th February 2018 3. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services 1. Thresholds for the Method of Procurement: Method of Procurement Thresholds for Method (US$ equivalent) Open International (Goods) Equal to or more than 3 million Open National ( Goods) – Open < $3 million Tender as per PPDA 2015 RFQ (Goods) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Open International (Works) Equal to or more than 15 million Open National (Works) - Open Less than 15 million Tender as per PPDA 2015 RFQ (works) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Method of Procurement Thresholds for Method (US$ equivalent) Open International (Non-consulting Equal to or More than 3 million Services) Open National (Non-consulting Less than 3 million Services) - Open Tender as per PPDA 2015 Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations Prior Review: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection (Project Procurement Risk Rating is “High”): (a) Goods, information technology and Non-consulting Services: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1.5 million (b) Works (including turnkey, supply & installation of plant and equipment and PPP); First procurement under the project irrespective of value and all procurements estimated to cost more than USD 5 million and The prior review thresholds will be reviewed during the implementation of the project and modified, based on the risk assessment. 2. For contracts subject to prior review, the Borrower shall seek the Bank’s no objection before agreeing to: a. an extension of the stipulated time for execution of a contract that has an impact on the planned completion of the project; b. any material modification of the scope of the Works, Goods, Non- consulting services or Consulting Services, or other significant changes to the terms and conditions of the contract; c. any variation order or contract amendment (except in cases of extreme urgency), including due to extension of time, that singly or combined with all previous variation orders or amendments, increases the original contract amount by more than 15% (fifteen percent); or d. the proposed termination of the contract. The Borrower / IA shall provide a copy of all amendments to the contract to the Bank for its records. 3. Prequalification Not Applicable Domestic Preference. The provision of domestic preference shall be applied in the procurement of goods following international market approach in accordance with Annex VI of the Regulations. Domestic preference shall not apply in the procurement of works. 4. Reference to Standard Procurement Documents Bank’s Standard RFB Goods and RFP Consulting Services dated July 2016 will be used as a base and incorporating suitable modifications and the same would be agreed with the Bank subject international competition. 5. Any Other Special Procurement Arrangements A. Procurement approach under CDD Approach by Communities: Applicable if stipulated in the PAD. B. When approaching the national market, as agreed in the Procurement Plan, the Open Tender procedure of Public Procurement and Asset Disposal Act 2015 and Regulations 2017 may be used. The specific Requirements for national open competitive procurement include the following: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. Other national procurement arrangements (other than national open competitive procurement), that may be applied by the Borrower (such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti-Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. In all cases, the national procurement procedures to be used shall give due attention to quality aspects. 6. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Selection methods of procurement of Consultants' Services (Firms): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Quality and Cost Based As per requirements of para 7.3 of the Selection (QCBS) Regulations Quality Based Selection As per requirements of para 7.8 to 7.10 (QBS) of the Regulations Selection based on a Fixed As per requirements of para 7.4 and 7.5 of the Budget (FBS) Regulations Selection Based on Least As per requirements of para 7.6 and 7.7 of the Cost Basis (LCS) Regulations Selection based on As per requirements of para 7.11 and 7.12 of Consultant’s Qualification the Regulations (CQ) Direct Must meet the requirements of Para 7.13 to 7.15 of the Regulations, and with prior agreement in PP with the Bank. The short list may consist of all National consultants in case the estimated cost is less than USD 300,000 Procurement methods for Selection of Individual Consultants (IC): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Open Competitive As per requirements of para 7.36 and 7.37 of Selection the Regulations Limited Competitive As per requirements of para 7.38 of the Selection Regulations Direct Must meet the requirements of Para 7.39 of the Regulations, and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Regulations Prior Review Thresholds: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 0.5 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.2 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. PROCUREMENT Kenya : National Agricultural and Rural Inclusive Growth Project PLAN General Information Country: Kenya 2019-06-11 Bank’s Approval Date of the Original Procurement Plan: 2022-06-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153349 GPN Date: 2018-02-09 Project Name: National Agricultural and Rural Inclusive Growth Project Loan / Credit No: IDA / 59000, IDA / Q9870 Bungoma County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-BUNGOMA COUNTY-1106 Project Coordination and Ma Request for Quota Single Stage - One E 2019-12-1 IDA / 59000 Post Limited 20,000.00 17,481.98 Completed 2019-04-22 2020-03-04 2019-06-17 2019-08-28 15-CW-RFQ / renovation of pr nagement tions nvelope 4 oject office KE-BUNGOMA COUNTY-1763 Supporting County Communi Request for Quota Single Stage - One E 2020-10-0 62-CW-RFQ / PROTECTION OF IDA / 59000 Post Limited 4,000.00 0.00 Canceled 2020-06-12 2020-07-06 ty-Led Development tions nvelope 4 NANGATA AND WAMBOKA SP RINGS KE-BUNGOMA COUNTY-1663 14-CW-RFB / CONSTRUCTION Strengthening Producer Org Request for Quota Single Stage - One E 2020-12-0 OF KAPTAMA DAIRY RESOUR IDA / 59000 anizations and Value Chain Post Limited 110,000.00 0.00 Canceled 2020-05-05 2020-06-09 tions nvelope 6 CE CENTRE FOR KAPTAMA D Development AIRY FARMERS COOPERATIVE SOCIETY. KE-BUNGOMA COUNTY-2106 Supporting County Communi Request for Quota Single Stage - One E 2021-04-3 67-CW-RFQ / FENCING OF WA IDA / 59000 Post Limited 2,500.00 0.00 Canceled 2021-01-02 2021-04-28 2021-01-30 ty-Led Development tions nvelope 0 TER PONDS AT WABUKHONYI KE-BUNGOMA COUNTY-2513 Request for Quota Supporting County Communi Request for Quota Single Stage - One E Under Imple 2022-01-1 18-CW-RFQ / FENCING OF WA IDA / 59000 Post Limited tions (Non Bank-S 10,662.00 0.00 2021-09-15 2021-10-20 ty-Led Development tions nvelope mentation 8 TER PONDS AT WABUKHONYI PD) WATER PAN. KE-BUNGOMA COUNTY-2676 Request for Bids - 22-CW-RFB / PROCUREMENT Supporting County Communi Single Stage - One E Small Works SPD Under Imple 2022-06-2 IDA / 59000 Post Request for Bids Open - National 231,342.00 0.00 2021-12-28 2022-04-29 2022-01-02 2022-05-02 2022-02-01 2022-03-03 2022-03-31 OF CONSTRUCTION WORKS F ty-Led Development nvelope (1 envelope proce mentation 9 OR WABUKHONYI CONCRETE ss) DAM Request for Bids - KE-BUNGOMA COUNTY-2676 Supporting County Communi Single Stage - One E Small Works SPD Under Imple 2022-06-2 23-CW-RFB / PROCUREMENT IDA / 59000 Post Request for Bids Open - National 559,198.00 0.00 2021-12-28 2022-01-24 2022-01-02 2022-02-01 2022-02-01 2022-03-03 2022-03-31 ty-Led Development nvelope (1 envelope proce mentation 9 OF CIVIL WORKS FOR KABKA ss) RA EARTH DAM KE-BUNGOMA COUNTY-2749 Request for Quota 28-CW-RFQ / Procurement of Supporting County Communi Request for Quota Single Stage - One E 2022-06-1 IDA / 59000 Post Limited tions (Non Bank-S 6,010.00 0.00 Canceled 2022-02-05 2022-03-19 excavation of 20no. farm pon ty-Led Development tions nvelope 7 PD) ds at Kabkara watershed KE-BUNGOMA COUNTY-2796 Request for Quota 89-CW-RFQ / Procurement of Supporting County Communi Request for Quota Single Stage - One E Pending Imp 2022-06-1 IDA / 59000 Post Limited tions (Non Bank-S 52,628.00 0.00 2022-02-25 2022-03-21 excavation and construction ty-Led Development tions nvelope lementation 9 PD) of 20no. farm ponds at Kabk ara watershed GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-BUNGOMA COUNTY-1385 Supporting Community-Driv Single Stage - One E 41-GO-RFB / procurement of IDA / Q9870 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2019-10-30 2019-10-04 2019-11-04 2019-10-04 2019-12-04 2019-10-04 2020-01-03 2019-10-04 2020-02-07 2020-03-08 en Development nvelope motorcycles KE-BUNGOMA COUNTY-1454 Project Coordination and Ma Request for Quota Single Stage - One E 82-GO-RFQ / PURCHASE OF S IDA / 59000 Post Limited 11,429.00 9,141.81 Completed 2019-12-06 2020-05-26 2020-01-17 2020-07-24 2020-04-16 2020-08-03 nagement tions nvelope IX (6 NO) LAPTOPS FOR CPCU KE-BUNGOMA COUNTY-1455 25-GO-RFQ / purchase of 12 Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 5,238.00 5,582.63 Completed 2019-12-04 2020-05-26 2020-01-15 2020-07-17 2020-04-14 2020-07-20 NO mobile phones and 10 N nagement tions nvelope O hard discs for project staff KE-BUNGOMA COUNTY-1398 Supporting County Communi Request for Quota Single Stage - One E 32-GO-RFQ / Purchase of soil IDA / 59000 Post Limited 70,853.00 36,290.19 Completed 2020-03-11 2020-07-14 2020-04-08 2020-09-07 2020-07-07 2020-10-28 ty-Led Development tions nvelope testing equipment KE-BUNGOMA COUNTY-1604 55-GO-RFQ / PURCHASE OF T Supporting County Communi Request for Quota Single Stage - One E REE SEEDLINGS FOR WABUK IDA / 59000 Post Limited 13,592.00 15,762.99 Completed 2020-03-18 2020-03-31 2020-04-15 2020-04-27 2020-07-14 2020-05-04 ty-Led Development tions nvelope HONYI SUSTAINABLE LAND M ANAGEMENT ACTIVITES KE-BUNGOMA COUNTY-1604 57-GO-RFQ / PURCHASE OF MOTORCYCLES FOR THE 20 Project Coordination and Ma Request for Quota Single Stage - One E WARDS IMPLEMENTING NARI IDA / 59000 Post Limited 80,000.00 54,775.27 Completed 2020-05-01 2020-06-03 2020-06-12 2020-07-28 2020-09-10 2020-08-04 nagement tions nvelope GP PROJECT IN BUNGOMA CO UNTY. PISTON CAPACITY OF T HE SAID MOTORCYCLES WILL BE OF 100CC- 130CC. KE-BUNGOMA COUNTY-1663 18-GO-RFQ / PURCHASE AND Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 12,500.00 15,742.79 Completed 2020-04-17 2020-07-14 2020-05-29 2020-09-07 2020-11-25 2020-11-24 INSTALLATION OF 25 UNITS ty-Led Development tions nvelope OF SOLAR PUMPS FOR FISH P ONDS. KE-BUNGOMA COUNTY-1663 53-GO-RFQ / PURCHASE OF P OND LINERS G 0.8mm HDPE l Supporting County Communi Request for Quota Single Stage - One E iners 15,220 pcs IDA / 59000 Post Limited 58,000.00 61,624.22 Completed 2020-04-17 2020-05-27 2020-05-13 2020-08-03 2020-08-11 2020-09-08 ty-Led Development tions nvelope PURCHASE OF POND LINERS G 1mm HDPE liners 704 pc s For Wabukhonyi SLM Project. Page 1 KE-BUNGOMA COUNTY-1705 99-GO-RFB / SUPPLY AND INS TALLATION OF HIGH SPEED B Project Coordination and Ma Single Stage - One E ROADBAND INTERNET CONN IDA / 59000 Post Request for Bids Limited 163,000.00 0.00 Canceled 2020-05-07 2020-05-21 2020-05-28 2020-06-11 2020-07-02 2020-09-30 nagement nvelope ECTIVITY, IP BASED AUDIO-VI SUAL TELECONFERENCE SYS TEM, NETWORK FIREWALL A ND NETWORK ROUTER. KE-BUNGOMA COUNTY-1728 Project Coordination and Ma Request for Quota Single Stage - One E 33-GO-RFQ / supply and insta IDA / 59000 Post Limited 80,000.00 68,384.06 Completed 2020-06-05 2020-10-09 2020-07-03 2020-11-23 2020-10-01 2020-12-23 nagement tions nvelope llation of video conferencing equipment. KE-BUNGOMA COUNTY-1738 Supporting County Communi Request for Quota Single Stage - One E 64-GO-RFQ / purchase of ferti IDA / 59000 Post Limited 1,000.00 894.09 Completed 2020-05-31 2020-05-20 2020-06-24 2020-07-17 2020-09-22 2020-07-20 ty-Led Development tions nvelope lizer for Wabukhonyi SLM pro ject. KE-BUNGOMA COUNTY-1763 Supporting County Communi Request for Quota Single Stage - One E 63-GO-RFQ / PURCHASE OF S IDA / 59000 Post Limited 10,000.00 5,942.23 Completed 2020-06-10 2020-07-14 2020-07-04 2020-09-11 2020-10-02 2020-11-23 ty-Led Development tions nvelope URVEY EQUIPMENTS KE-BUNGOMA COUNTY-1815 Project Coordination and Ma Request for Quota Single Stage - One E 18-GO-RFQ / PURCHASE OF F IDA / 59000 Post Limited 20,000.00 18,198.36 Completed 2019-04-04 2019-06-13 2019-05-30 2019-08-04 2019-11-26 2019-09-02 nagement tions nvelope URNITURE KE-BUNGOMA COUNTY-1834 12-GO-RFQ / PURCHASE AND Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 8,750.00 0.00 Canceled 2020-07-31 2020-08-24 2020-11-22 INSTALLATION OF 5000LITRE ty-Led Development tions nvelope S CAPACITY WATER TANKS KE-BUNGOMA COUNTY-1834 15-GO-RFQ / PURCHASE AND Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 9,450.00 0.00 Canceled 2020-07-31 2020-08-28 2020-11-26 INSTALLATION OF POND NET ty-Led Development tions nvelope TING FOR PONDS KE-BUNGOMA COUNTY-1930 Project Coordination and Ma Request for Quota Single Stage - One E 22-GO-RFQ / PURCHASE OF 2 IDA / 59000 Post Limited 6,000.00 5,459.51 Completed 2020-09-30 2021-06-14 2020-10-28 2021-06-30 2021-01-26 2021-10-01 nagement tions nvelope 0NO. RIDING GEARS. KE-BUNGOMA COUNTY-1995 17-GO-RFQ / PURCHASE OF D Supporting Community-Driv Request for Quota Single Stage - One E IDA / 59000 Post Limited 12,000.00 11,116.26 Completed 2020-11-09 2021-04-28 2020-12-03 2021-06-24 2021-03-03 2021-08-30 ESKTOP COMPUTERS AND PR en Development tions nvelope INTERS FOR CDDCs KE-BUNGOMA COUNTY-1995 Supporting Community-Driv Request for Quota Single Stage - One E 38-GO-RFQ / PURCHASE OF 2 IDA / 59000 Post Limited 7,000.00 6,375.23 Completed 2020-11-09 2021-04-23 2020-12-03 2021-06-24 2021-03-03 2021-09-24 en Development tions nvelope 0NO. STEEL CABINETS FOR C DDCs KE-BUNGOMA COUNTY-2106 69-GO-RFQ / PURCHASE OF T Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 1,700.00 1,537.07 Completed 2020-12-31 2021-01-28 2021-01-24 2021-04-20 2021-04-24 2021-09-01 -SHIRTS, ROLL UP BANNER, B ty-Led Development tions nvelope RONCHURES AND FLIERS. KE-BUNGOMA COUNTY-2106 Supporting County Communi Request for Quota Single Stage - One E 68-GO-RFQ / PROVIDE AND I IDA / 59000 Post Limited 8,500.00 0.00 Canceled 2020-12-31 2021-01-28 2021-04-28 ty-Led Development tions nvelope NSTALL DRIP IRRIGATION KIT S KE-BUNGOMA COUNTY-2007 Supporting County Communi Request for Quota Single Stage - One E 91-GO-RFQ / PURCHASE OF P IDA / 59000 Post Limited 5,000.00 0.00 Canceled 2020-11-09 2020-12-03 2021-03-03 ty-Led Development tions nvelope LAN PLOTTER KE-BUNGOMA COUNTY-2513 Supporting County Communi Request for Quota Single Stage - One E 21-GO-RFQ / SUPPLY AND DE IDA / 59000 Post Limited 4,000.00 3,466.20 Signed 2021-09-13 2021-10-27 2021-10-11 2022-01-25 2022-01-09 ty-Led Development tions nvelope LIVERY OF SEEDLINGS. KE-BUNGOMA COUNTY-2646 61-GO-RFQ / Supply and deli Supporting County Communi Request for Quota Single Stage - One E Under Imple IDA / 59000 Post Limited 700.00 0.00 2021-12-03 2022-01-10 2022-04-10 very of shade nets for farm p ty-Led Development tions nvelope mentation onds at Wabukhonyi water p an. KE-BUNGOMA COUNTY-2773 Strengthening Producer Org 11-GO-DIR / Purchase of web Pending Impl IDA / 59000 anizations and Value Chain Post Direct Selection Direct 8,100.00 0.00 2022-05-04 2023-05-04 -based dashboard and analyt ementation Development ics App for Oakar services (D AT) KE-BUNGOMA COUNTY-2776 Strengthening Producer Org 28-GO-DIR / Purchase of an o Pending Impl IDA / 59000 anizations and Value Chain Post Direct Selection Direct 9,396.00 0.00 2022-02-25 2022-03-04 2022-04-08 2022-10-05 perating digital platform for ementation Development Agripreneurs for KUZA biasha ra DAT KE-BUNGOMA COUNTY-2776 Strengthening Producer Org Pending Impl 31-GO-DIR / Purchase of micr IDA / 59000 anizations and Value Chain Post Direct Selection Direct 6,786.00 0.00 2022-02-25 2022-03-02 2022-04-06 2022-10-03 ementation o projectors Development KE-BUNGOMA COUNTY-2779 Strengthening Producer Org Pending Impl 70-GO-DIR / Purchase of 15n IDA / 59000 anizations and Value Chain Post Direct Selection Direct 3,480.00 0.00 2022-02-25 2022-03-02 2022-03-30 2022-09-26 ementation o. Android tablets for Kuza D Development AT cohort KE-BUNGOMA COUNTY-2670 Supporting County Communi Request for Quota Single Stage - One E 93-GO-RFQ / PURCHASE AND IDA / 59000 Post Limited 12,600.00 0.00 Canceled 2021-12-25 2022-01-22 2022-04-22 ty-Led Development tions nvelope INSTALLATION OF HDPE PON DLINERS KE-BUNGOMA COUNTY-2670 89-GO-RFQ / PURCHASE AND Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 18,000.00 0.00 Canceled 2021-12-27 2022-01-24 2022-04-24 INSTALLATION OF SOLAR PU ty-Led Development tions nvelope MPING UNITS FOR FARM PON DS KE-BUNGOMA COUNTY-2779 Strengthening Producer Org 72-GO-RFQ / Purchase of 1no Request for Quota Single Stage - One E IDA / 59000 anizations and Value Chain Post Limited 55,000.00 0.00 Canceled 2022-02-25 2022-03-21 2022-09-17 . tractor and implements for tions nvelope Development Kikai Producer Organization KE-BUNGOMA COUNTY-2970 Supporting County Communi 65-GO-DIR / Purchase of DAT IDA / 59000 Post Direct Selection Direct 5,000.00 0.00 Canceled 2022-06-10 2022-06-17 2022-07-01 2022-07-31 ty-Led Development equipments for Agribora DAT Cohort. KE-BUNGOMA COUNTY-3004 Supporting County Communi Request for Quota Single Stage - One E Pending Impl 70-GO-RFQ / Purchase of DAT IDA / 59000 Post Limited 5,000.00 0.00 2022-07-01 2022-08-01 2022-10-30 ty-Led Development tions nvelope ementation items for Agribora DAT cohor t NON CONSULTING SERVICES Page 2 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-BUNGOMA COUNTY-1930 Project Coordination and Ma Request for Quota Single Stage - One E 23-NC-RFQ / BRANDING OF 2 IDA / 59000 Post Limited 5,000.00 4,557.89 Completed 2020-09-28 2021-04-23 2020-10-26 2021-06-22 2021-01-24 2021-08-30 nagement tions nvelope 0NO. MOTOR CYCLES KE-BUNGOMA COUNTY-2106 Supporting County Communi Request for Quota Single Stage - One E 70-NC-RFQ / HIRE OF VEHICL IDA / 59000 Post Limited 1,000.00 4,559.97 Completed 2020-12-31 2021-01-28 2021-01-24 2021-04-30 2021-04-24 2021-06-24 ty-Led Development tions nvelope ES FOR ROADSHOW CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-BUNGOMA COUNTY-1455 Supporting Community-Driv Consultant Qualifi Under Implement 35-CS-LCS / recruitment of se IDA / 59000 Post Open - National 47,619.00 0.00 2020-04-10 2020-10-26 2020-04-17 2020-05-01 2020-05-08 2020-05-29 2021-01-21 en Development cation Selection ation rvice provider for local chicke n value chain. KE-BUNGOMA COUNTY-1495 21-CS-LCS / PROCUREMENT Supporting Community-Driv Consultant Qualifi OF CONSULTANT FOR PROVI IDA / 59000 Post Open - National 47,619.00 22,747.95 Signed 2020-04-07 2020-10-21 2020-04-14 2020-04-28 2020-12-20 2020-05-12 2021-02-26 2020-06-02 2021-08-18 2021-11-21 en Development cation Selection SION OF TRAINING SERVICE FOR BANANA VALUE CHAIN KE-BUNGOMA COUNTY-1495 28-CS-LCS / RECRUITMENT O Supporting Community-Driv Consultant Qualifi Under Implement F FIRMS FOR PROVISION OF IDA / 59000 Post Open - National 47,619.00 0.00 2020-04-10 2020-10-21 2020-04-17 2020-05-01 2020-05-08 2020-05-22 2021-12-23 en Development cation Selection ation SERVICES TO THE DAIRY VAL UE CHAIN IN BUNGOMA COU NTY. KE-BUNGOMA COUNTY-1481 45-CS-LCS / Recruitment of c Supporting Community-Driv Consultant Qualifi onsultancy firms to carryout IDA / 59000 Post Open - National 47,619.00 22,603.98 Signed 2020-04-10 2020-10-21 2020-04-17 2020-05-01 2020-06-22 2020-05-08 2021-02-26 2020-05-29 2021-07-16 2021-12-30 en Development cation Selection training of CIGs on Beans val ue chains in Bungoma county . INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3