The World Bank Implementation Status & Results Report Reintegration of Ex-combatants Project (P160272) Reintegration of Ex-combatants Project (P160272) WESTERN AND CENTRAL AFRICA | Central African Republic | Social Sustainability and Inclusion Global Practice | IBRD/IDA | Investment Project Financing | FY 2017 | Seq No: 10 | ARCHIVED on 29-Jun-2022 | ISR51691 | Implementing Agencies: DDRR Project Implementation Unit, Ministère de l'Economie, du Plan et de la Coopération Key Dates Key Project Dates Bank Approval Date: 13-Apr-2017 Effectiveness Date: 21-Dec-2017 Planned Mid Term Review Date: 16-Sep-2019 Actual Mid-Term Review Date: 19-Jul-2019 Original Closing Date: 31-Dec-2020 Revised Closing Date: 30-Jun-2023 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective (PDO) is to support the social and economic reintegration of demobilized ex-combatants and improve access to socio-economic infrastructure and economic opportunities for host communities. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Social and Economic Reintegration Support:(Cost $13600000.00 M) Support to At-Risk/Vulnerable Individuals and Host Communities:(Cost $12000000.00 M) Project Management:(Cost $4400000.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions On February 16, 2022, a no-cost extension of the project with 12 months was approved. This extended the closing date to June 30, 2023. The two components of the projects, namely community rehabilitation and socio-economic reintegration of ex-combatants, are moving forward. 300 youth at risk has finished their training in Birao and another 700 will soon conclude their vocational training in Kaga Bandoro. At the time of the mission, 1,036 ex-combatants were coming to an end of their five-month long training program. 6/29/2022 Page 1 of 7 The World Bank Implementation Status & Results Report Reintegration of Ex-combatants Project (P160272) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance High High High Macroeconomic High High High Sector Strategies and Policies Substantial Substantial Substantial Technical Design of Project or Program Moderate Moderate Moderate Institutional Capacity for Implementation and High Substantial Moderate Sustainability Fiduciary Substantial Moderate Moderate Environment and Social Moderate Moderate Moderate Stakeholders Substantial Substantial Substantial Other High High High Overall High Substantial Substantial Results PDO Indicators by Objectives / Outcomes Social and Economic Reintegration Support to Ex-Combatants IN01148888 ►Number of demobilized ex-combatants who have undergone socioeconomic reintegration (disaggregated by age, sex and armed group affiliation) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 835.00 835.00 4,000.00 Date 13-Apr-2017 12-Nov-2021 10-Jun-2022 30-Jun-2023 Number of direct project beneficiaries who are ex-combatants that receive social and economic Comments: reintegration support through the project. IN01148890 ►Number of ex-combatants who were received by the PREC for vocational trainings as part of the socio-economic reintegration package (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 2,346.00 2,367.00 4,000.00 Date 01-May-2017 12-Nov-2021 10-Jun-2022 30-Jun-2023 IN01148893 Of which women (Number, Custom Breakdown) 6/29/2022 Page 2 of 7 The World Bank Implementation Status & Results Report Reintegration of Ex-combatants Project (P160272) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 161.00 161.00 500.00 Date 01-May-2017 12-Nov-2021 12-Nov-2021 30-Jun-2022 IN01148894 ►Percentage of demobilized ex-combatants availing income generation opportunities (disaggregated by age, sex, and type of economic activity) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 25.00 60.00 75.00 Date 13-Apr-2017 12-Nov-2021 10-Jun-2022 30-Jun-2023 IN01148895 ►Percentage of total project beneficiaries who report acceptance to return of demobilized ex-combatants (disaggregated by returnees vis-a- vis local communities) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 85.00 100.00 65.00 Date 13-Apr-2017 21-Jun-2021 21-Jun-2021 30-Jun-2023 IN01148896 ►Percentage of host community members who report social acceptance of ex-combatants (disaggregated by age and sex) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 87.22 87.22 70.00 Date 13-Apr-2017 12-Nov-2021 21-Jun-2021 30-Jun-2023 Support to At-Risk, Vulnerable Individuals and Host Communities IN01148889 ►Number of planned small-scale socioeconomic infrastructure sub-projects successfully completed (construction or rehabilitation) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 69.00 69.00 76.00 Date 13-Apr-2017 12-Nov-2021 10-Jun-2022 30-Jun-2023 IN01148891 ►Number of beneficiaries in target communities with improved access to socioeconomic infrastructure (disaggregated by sex) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 436.00 436,000.00 30,000.00 Date 13-Apr-2017 21-Jun-2021 21-Jun-2021 30-Jun-2023 Number of beneficiaries reported in sub-project proposals and verified by the DDRR-PIU, IP and Local Comments: Authority in charge that are estimated to benefit from the socio-economic infrastructure rehabilitation/construction projects, reported once the work is completed. IN01148892 6/29/2022 Page 3 of 7 The World Bank Implementation Status & Results Report Reintegration of Ex-combatants Project (P160272) ►Percentage of total beneficiaries in local communities reporting higher security and reconciliation (disaggregated by age, sex and armed groups affiliation) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 95.54 95.54 80.00 Date 13-Apr-2017 12-Nov-2021 21-Jun-2021 30-Jun-2023 This indicator will measure feeling of greater security among project beneficiairies, including community Comments: members and ex-combatants. Intermediate Results Indicators by Components Social and Economic Reintegration Support to Ex-Combatants IN01148897 ►Percentage of ex-combatants who successfully completed orientation, counseling and skills training (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 41.75 85.00 90.00 Date 13-Apr-2017 12-Nov-2021 10-Jun-2022 30-Jun-2023 For PREC II Comments: IN01148899 ►Percentage of identified eligible former combatants who received specialized support (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 100.00 Date 13-Apr-2017 13-Aug-2018 13-Aug-2018 30-Jun-2023 This indicator will measure the percentage of those ex-combatants who are identified as vulnerable and Comments: who received specialized support. IN01148901 ►Percentage of ex-combatants who received, from those who requested, additional drop-in reintegration support (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 100.00 Date 13-Apr-2017 13-Aug-2018 13-Aug-2018 30-Jun-2022 This indicator will measure the delivery of the follow-up reintegration support in the 24 months following Comments: orientation, counseling and skills training. IN01148903 ►Percentage of targeted former combatants reporting satisfaction with services provided by this program (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 41.00 93.00 95.00 6/29/2022 Page 4 of 7 The World Bank Implementation Status & Results Report Reintegration of Ex-combatants Project (P160272) Date 13-Apr-2017 12-Nov-2021 21-Jun-2021 30-Jun-2023 IN01148905 ►Percentage of ex-combatants who are satisfied with the start-up reintegration support (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 41.00 93.00 90.00 Date 13-Apr-2017 12-Nov-2021 21-Jun-2021 30-Jun-2023 This sub-component will measure the usefulness of the contents and efficiency in the distribution/delivery Comments: of the start-up kits to the ex-combatants. IN01148907 ►Number ex-combatants who received reintegration start-up support (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 835.00 835.00 4,000.00 Date 13-Apr-2017 12-Nov-2021 10-Jun-2022 30-Jun-2023 Support to At-Risk, Vulnerable Individuals and Host Communities IN01148898 ►Number of host community members participating in community-based decision making/participatory planning exercises (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 840.00 920.00 2,500.00 Date 13-Apr-2017 12-Nov-2021 10-Jun-2022 30-Jun-2023 This indicator will track the number of community members participating in consultation, decision-making Comments: or participatory planning activities under project activities described in Component 2. IN01148900 ►Number of host community members participating in capacity building activities (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 840.00 840.00 6,000.00 Date 13-Apr-2017 12-Nov-2021 12-Nov-2021 30-Jun-2023 This indicator will track the number of people participating in capacity building activities under Component Comments: 2. IN01148902 ►Number of host community members, including at-risk/vulnerable peoples, who completed skills training related to the construction, rehabilitation and maintenance of infrastructures (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 976.00 976.00 5,200.00 Date 13-Apr-2017 12-Nov-2021 12-Nov-2021 30-Jun-2023 6/29/2022 Page 5 of 7 The World Bank Implementation Status & Results Report Reintegration of Ex-combatants Project (P160272) IN01148904 ►Number of members of host communities, including at-risk and vulnerable peoples, employed and paid by the project (disaggregated by age and sex) (Number (Thousand), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 4,646.00 4,646.00 5,200.00 Date 13-Apr-2017 12-Nov-2021 12-Nov-2021 30-Jun-2023 IN01148906 ►Number of host communities (local committees/community councils) members trained in conflict mediation, social cohesion and technical aspects related to the maintenance of infrastructures (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 3,920.00 3,920.00 1,012.00 Date 13-Apr-2017 12-Nov-2021 10-Jun-2022 30-Jun-2023 Out of the 3,290 people trained,1,475 are women. Comments: IN01148908 ►Number of youth-at-risk who received basic and vocational trainings (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 300.00 1,000.00 Date 14-Aug-2020 14-Aug-2020 10-Jun-2022 30-Jun-2023 Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P160272 IDA-D1800 Effective USD 30.00 30.00 0.00 24.41 6.30 79% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P160272 IDA-D1800 Effective 13-Apr-2017 22-Jun-2017 21-Dec-2017 31-Dec-2020 30-Jun-2023 Cumulative Disbursements 6/29/2022 Page 6 of 7 The World Bank Implementation Status & Results Report Reintegration of Ex-combatants Project (P160272) Restructuring History Level 2 Approved on 26-Oct-2018 ,Level 2 Approved on 08-Oct-2020 ,Level Approved on 15-Oct-2020 ,Level 2 Approved on 16-Feb-2022 Related Project(s) There are no related projects. 6/29/2022 Page 7 of 7