PROCUREMENT PLAN (Textual Part) Project Country: Kyrgyz Republic information Full Project Name: Regional Economic Development Project (RED) Total Finance ($): USD 60,000,000 Project Number: P167428 Project Implementation agency Community Development and Investment Agency of the Kyrgyz Republic (ARIS) Date of the Procurement Plan February 5, 2020 Period covered by this Procurement September 2020 – December, 2026 Plan: Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), procurement under World Bank financed operations may be carried out in accordance with “Single-Stage Bidding” method set forth in the Public Procurement Law of the Kyrgyz Republic dated April 3, 2015 № 72 (the “PPL”) with amendments dated November 18, 2016 No. 182, December 10, 2016 No. 195, February 14, 2017 No. 25, May 30, 2017 No. 93, March 29, 2018 No. 32, January 11, 2019 No. 4, June 26, 2019 No. 76, provided that such arrangements continue to meet requirements of the paragraph 5.4 of the Procurement Regulations and the following conditions: • The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; • Bidding documents, including contract forms, acceptable to the Bank shall be used. Bidding documents shall include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social, health and safety (“ESHS”) risks and impacts. • The Bidding process shall not be cancelled solely on the reason that minimum bid price is larger than the amount allocated by procuring entity for the procurement. • There shall be no preference applied during procurement of goods and works. • Implementing agency shall have an option to publish procurement notice without disclosing cost estimate. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Other national procurement arrangements such as “Simplified Method” (Request for Quotation) may be applied on the same conditions stated above for procuring limited quantities of readily available off-the-shelf goods or simple civil works of small value. In addition, not less than three quotations shall be requested to ensure competition. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable. PROCUREMENT Kyrgyz Republic : Kyrgyz Republic Regional Economic Development Project PLAN General Information Country: Kyrgyz Republic 2021-03-03 Bank’s Approval Date of the Original Procurement Plan: 2022-06-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167428 GPN Date: 2020-09-16 Project Name: Kyrgyz Republic Regional Economic Development Project Loan / Credit No: IDA / 65580 Community Development and Investment Agency Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-REDP-W-RFQ-2021-1 / O Improving Regional Economi Request for Quota Single Stage - One E Pending Imp 2023-07-2 ffice repair for Osh technical IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2021-06-10 2021-07-23 tions nvelope lementation 3 agricultural college unctions IDA-REDP-W-RFQ-2021-2 / O Improving Regional Economi Request for Quota Single Stage - One E Pending Imp 2022-07-2 IDA / 65580 Post Open - National 0.00 2021-06-10 2021-07-23 ffice repair of Laboratory IST c Planning and Regulatory F tions nvelope lementation 3 A unctions IDA-REDP-W-RFQ-2021-3 / R Improving Regional Economi Request for Quota Single Stage - One E Pending Imp 2022-07-2 econstruction of driving field IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2021-06-10 2021-07-16 tions nvelope lementation 3 s for Osh technical agricultur unctions al college IDA-REDP-W-RFB-2021-4 / Pr Catalyzing Investments for T ovision of tourism services a Single Stage - One E Pending Imp 2023-09-1 IDA / 65580 ourism and Urban Developm Post Request for Bids Open - National 0.00 2021-06-10 2021-06-10 2021-07-15 2021-08-05 2021-08-22 nd amenities (eg. rest stops) nvelope lementation 1 ent along the main circuits IDA-REDP-W-RFQ-2021-8 / O Improving Regional Economi Request for Quota Single Stage - One E Pending Imp 2023-01-2 ffice repair for Osh technolog IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2021-12-17 2022-01-22 tions nvelope lementation 9 ical university unctions IDA-REDP-W-RFB-2021-6 / S uleiman-Too Museum and Co mplex upgrading and Uzgen Catalyzing Investments for T Open - Internationa Single Stage - Two E Pending Imp 2023-11-0 Museum and grounds upgrad IDA / 65580 ourism and Urban Developm Prior Request for Bids 0.00 2021-06-13 2021-06-18 2021-07-30 2021-10-12 2021-11-16 l nvelope lementation 6 ing (including infra, services, ent exhibition organization, mus eum site and visitor manage ment plan etc.) IDA-REDP-W-RFB-2021-7 / A Catalyzing Investments for T Single Stage - One E Pending Imp 2023-12-2 bshir-Ata: Kara-Shoro Park Ky IDA / 65580 ourism and Urban Developm Post Request for Bids Open - National 0.00 2021-06-13 2021-06-13 2021-08-01 2021-08-22 2021-09-11 nvelope lementation 0 rgyz-Ata: infrastructure impr ent ovement IDA-REDP-W-RFQ-2022-9 / O Improving Regional Economi Request for Quota Single Stage - One E Pending Imp 2023-07-3 IDA / 65580 Post Open - National 0.00 2022-06-17 2022-07-30 ffice repair of Interdistrict La c Planning and Regulatory F tions nvelope lementation 0 boratories unctions IDA-REDP-W-RFB-2021-5 / " Osh City downtown and key and Uzgen City urban regen Catalyzing Investments for T Open - Internationa Single Stage - Two E 2023-11-0 eration (roads, parks and oth IDA / 65580 ourism and Urban Developm Prior Request for Bids 0.00 Canceled 2021-06-13 2021-06-18 2021-07-30 2021-10-12 2021-11-16 l nvelope 6 er public spaces, utilities, etc ent .) (roads, parks and other pu blic spaces, pedestrian bridges a cross river, utilities, etc.)" IDA-REDP-W-RFB-2022-11 / Catalyzing Investments for T Other (with fi Open - Internationa Single Stage - One E Pending Imp 2023-04-0 Construction works: Coastal z IDA / 65580 ourism and Urban Developm Post Request for Bids eld for expla 0.00 2022-06-17 2022-07-06 2022-08-05 2022-08-26 2022-10-20 l nvelope lementation 3 one of the Ak-Buura river. ent nation) IDA-REDP-W-RFB-2022-10 / Catalyzing Investments for T Other (with fi Construction works: Open - Internationa Single Stage - One E Pending Imp 2023-04-0 IDA / 65580 ourism and Urban Developm Post Request for Bids eld for expla 0.00 2022-06-17 2022-07-06 2022-08-05 2022-08-15 2022-10-05 Theater park, Toktogul theat l nvelope lementation 3 ent nation) er and Navoi park. IDA-REDP-W-RFB-2022-12 / Construction works: Zones b Catalyzing Investments for T Other (with fi Open - Internationa Single Stage - One E Pending Imp 2023-07-0 etween residential quarters / IDA / 65580 ourism and Urban Developm Post Request for Bids eld for expla 0.00 2022-09-15 2022-10-04 2022-10-24 2022-11-23 2023-01-03 l nvelope lementation 2 blocks, wall painting (mosaic) ent nation) , northern part of Lenin stree t. IDA-REDP-W-RFB-2022-13 / Catalyzing Investments for T Other (with fi Construction works: Street a Open - Internationa Single Stage - One E Pending Imp 2023-07-1 IDA / 65580 ourism and Urban Developm Post Request for Bids eld for expla 0.00 2022-09-27 2022-10-16 2022-12-06 2022-12-11 2023-01-15 nd road networks (5 streets) l nvelope lementation 4 ent nation) and extension of Dostuk park . IDA-REDP-W-RFB-2022-14 / Catalyzing Investments for T Other (with fi Construction works: Tynchtyk Open - Internationa Single Stage - One E Pending Imp 2023-09-0 IDA / 65580 ourism and Urban Developm Post Request for Bids eld for expla 0.00 2022-11-15 2022-12-04 2023-01-03 2023-01-24 2023-03-05 park, park near the stadium, l nvelope lementation 1 ent nation) stadium, park bridge. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-REDP-GOODS-RFQ-2020 Improving Regional Economi Request for Quota Single Stage - One E Pending Impl -1 / PCs for the office of infor IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2020-12-20 2021-02-16 2021-08-15 tions nvelope ementation mation market system unctions IDA-REDP-GOODS-RFQ-2021 -3 / Printing of materials for d evelopment of information m Improving Regional Economi arket system and for MinAgri, Request for Quota Single Stage - One E Pending Impl IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2021-08-10 2021-09-18 2021-12-17 Osh obl administration and 7 tions nvelope ementation unctions laborotories, market fairs, 6 border control points, soil agr ochemical map and its e-cad astre and 7 centers IDA-REDP-GOODS-RFQ-2021 Improving Regional Economi Request for Quota Single Stage - One E Pending Impl IDA / 65580 Post Open - National 0.00 2021-12-15 2022-01-23 2022-04-23 -5 / Tractor with equipment c Planning and Regulatory F tions nvelope ementation unctions Page 1 IDA-REDP-GOODS-RFQ-2022 Improving Regional Economi Request for Quota Single Stage - One E Pending Impl -11 / Special vehicle for testi IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2022-02-23 2022-04-23 2022-10-20 tions nvelope ementation ng points of expertise of crop unctions s IDA-REDP-GOODS-RFB-2022- 8 / Office equipment, furnitur e for laboratory (ISTA) for on Improving Regional Economi testing points of expertise of Open - Internationa Single Stage - One E Pending Impl IDA / 65580 c Planning and Regulatory F Post Request for Bids 0.00 2022-02-23 2022-02-28 2022-04-11 2022-05-11 2022-06-15 2022-12-12 crops; Office equipment, furn l nvelope ementation unctions iture for 7 sampling points fo r laboratory testing; Office eq uipment, furniture for 7 bord er control points and etc. IDA-REDP-GOODS-RFB-2022- 12 / Abshir-Ata, Kara-Shoro P ark, Kyrgyz-Ata: goods for to Catalyzing Investments for T Open - Internationa Single Stage - One E Pending Impl urist infrastructure upgrading IDA / 65580 ourism and Urban Developm Post Request for Bids 0.00 2022-01-13 2022-01-18 2022-03-01 2022-03-31 2022-05-05 2023-04-30 l nvelope ementation and solid waste management ent improvements ; Trucks and b ins for Kyrgyz-Ata, Abshyr-At a, Karashoroo IDA-REDP-GOODS-RFB-2022- Improving Regional Economi 9 / Mechanization and electrif Single Stage - One E Pending Impl IDA / 65580 c Planning and Regulatory F Post Request for Bids Open - National 0.00 2022-08-11 2022-08-11 2022-08-25 2022-08-28 2022-09-16 2022-12-15 ication of agriculture for Osh nvelope ementation unctions technical agricultural college IDA-REDP-GOODS-RFQ-2022 Improving Regional Economi Request for Quota Single Stage - One E Pending Impl -10 / Promotion materials for IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2022-06-26 2022-07-30 2022-11-06 tions nvelope ementation National Stakeholders platfor unctions m IDA-REDP-GOODS-RFB-2022- Catalyzing Investments for T 13 / Furniture, goods and exi Open - Internationa Single Stage - One E Pending Impl IDA / 65580 ourism and Urban Developm Post Request for Bids 0.00 2022-08-10 2022-08-15 2022-09-26 2022-10-26 2022-11-30 2023-05-29 bition equipment for Suleimq l nvelope ementation ent n-Too and Uzgen museums IDA-REDP-GOODS-RFB-2021- 2 / Laboratory equipment (for 7 sampling points for laborat ory testing, for 7 border cont Improving Regional Economi Open - Internationa Single Stage - Two E Pending Impl rol points, for 2 phytosanitar IDA / 65580 c Planning and Regulatory F Prior Request for Bids 0.00 2021-12-12 2021-12-17 2022-01-28 2022-04-12 2022-05-17 2022-11-13 l nvelope ementation y laboratories under GosStan unctions dard, food kaboratory (Sanep idnadzor), Venerinary Service and CoCommerse and small f ood laboratories etc... IDA-REDP-GOODS-RFQ-2021 Improving Regional Economi Request for Quota Single Stage - One E Pending Impl -6 / Software for information IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2021-12-12 2022-01-20 2022-04-20 tions nvelope ementation market system unctions IDA-REDP-GOODS-RFB-2023- 18 / Purchase of goods (traini ng materials, printed materia Supporting Tourism and Rur Single Stage - Two E Pending Impl ls, etc.) for training in the hos IDA / 65580 al Development through Sm Post Request for Bids Open - National 0.00 2022-01-02 2022-01-07 2022-02-18 2022-05-03 2022-06-07 2022-12-04 nvelope ementation pitality industry for tour guid all Grants es, tour operators and mana gers / accommodation perso nnel. Technical support IDA-REDP-GOODS-RFB-2023- Improving Regional Economi Single Stage - One E 15 / Goods for Implementatio IDA / 65580 c Planning and Regulatory F Post Request for Bids Open - National 0.00 Canceled 2023-01-10 2023-01-17 2023-01-31 2023-02-21 2023-03-10 2023-09-06 nvelope n of acitivities suggested by t unctions he REDP IDA-REDP-GOODS-RFB-2023- Improving Regional Economi Single Stage - One E 16 / Goods for regional onlin IDA / 65580 c Planning and Regulatory F Post Request for Bids Open - National 0.00 Canceled 2023-01-10 2023-01-17 2023-01-31 2023-02-21 2023-03-10 2023-09-06 nvelope e platform development unctions IDA-REDP-GOODS-RFB-2021- Catalyzing Investments for T Open - Internationa Single Stage - One E 7 / Goods for Branding, mark IDA / 65580 ourism and Urban Developm Post Request for Bids 0.00 Canceled 2021-10-01 2021-10-06 2021-11-17 2021-12-17 2022-01-21 2022-04-21 l nvelope eting and promotion activitie ent s for Osh region IDA-REDP-GOODS-RFB-2022- Catalyzing Investments for T Open - Internationa Single Stage - One E Pending Impl 17 / Goods for Branding,mark IDA / 65580 ourism and Urban Developm Post Request for Bids 0.00 2022-01-23 2022-01-28 2022-03-11 2022-04-10 2022-05-15 2022-11-11 l nvelope ementation eting and promotion activitie ent s for Osh region IDA-REDP-GOODS-RFB-2022- 14 / Ensuring the product de Catalyzing Investments for T Open - Internationa Single Stage - One E velopment at the regional lev IDA / 65580 ourism and Urban Developm Post Request for Bids 0.00 Canceled 2022-03-10 2022-03-13 2022-04-24 2022-05-24 2022-06-28 2022-12-25 l nvelope el (fairs, exhibitions, PR, med ent ia campaigns, cultural events , forums) IDA-REDP-GOODS-RFB-2022- 15 / Ensuring the product de Catalyzing Investments for T Open - Internationa Single Stage - One E Pending Impl velopment at the regional lev IDA / 65580 ourism and Urban Developm Post Request for Bids 0.00 2022-03-10 2022-03-15 2022-04-24 2022-05-24 2022-06-26 2022-12-25 l nvelope ementation el (fairs, exhibitions, PR, med ent ia campaigns, cultural events , forums). IDA-REDP-GOODS-RFB-2023- Improving Regional Economi Single Stage - One E Pending Impl 20 / Goods for regional onlin IDA / 65580 c Planning and Regulatory F Post Request for Bids Open - National 0.00 2023-01-10 2023-01-15 2023-02-04 2023-02-24 2023-03-10 2023-09-06 nvelope ementation e platform development unctions IDA-REDP-GOODS-RFB-2023- Improving Regional Economi Open - Internationa Single Stage - One E Pending Impl 19 / Goods for Implementatio IDA / 65580 c Planning and Regulatory F Post Request for Bids 0.00 2023-01-10 2023-01-15 2023-01-30 2023-02-14 2023-03-21 2023-09-17 l nvelope ementation n of acitivities suggested by t unctions he REDP IDA-REDP-GOODS-RFQ-2021 -4 / Printing of education mat erials on veterinary, artificial Improving Regional Economi Request for Quota Single Stage - One E Pending Impl insemination, mechanization IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2022-07-05 2022-08-13 2022-11-11 tions nvelope ementation and electrification of agricult unctions ure for Osh agricolledge and printing education materials f or Osh technological universi ty NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 IDA-REDP-CS-CQS-2021-1 / R Improving Regional Economi Consultant Qualifi Pending Impleme egional development platfor IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2021-01-25 2021-01-31 2021-03-16 2021-04-15 2021-05-20 2021-08-18 cation Selection ntation m implementation unctions IDA-REDP-CS-CQS-2021-4 / Consulting company to cond Strengthening Agri-Food Sup Consultant Qualifi Pending Impleme IDA / 65580 Post Open - National 0.00 2021-06-29 2021-07-04 2021-08-17 2021-09-28 2021-10-15 2023-10-05 uct market studies. Methodol ply Chains and SMEs cation Selection ntation ogy for National Stakeholders Platform IDA-REDP-CS-CQS-2021-5 / S urvey on agribusiness value Strengthening Agri-Food Sup Consultant Qualifi IDA / 65580 Post Open - National 52,594.80 Signed 2021-06-29 2021-05-06 2021-06-30 2021-05-18 2021-07-18 2022-04-12 2021-08-17 2022-04-12 2021-10-15 2022-04-13 2022-01-13 chain. Survey on diagnostic s ply Chains and SMEs cation Selection tudies. Consulting company for survey IDA-REDP-CS-CQS-2021-10 / Consulting company for Deve lopment of design document ation and supervision of repa Improving Regional Economi Consultant Qualifi Pending Impleme ir of the office of Osh technic IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2021-12-20 2021-12-25 2022-02-07 2022-03-21 2022-04-02 2022-10-18 cation Selection ntation al agriculture college, (includi unctions ng driving fields) and office o f Osh technological university , warehouses of seed farms a nd plemzavod etc... IDA-REDP-CS-QCBS-2021-7 / Catalyzing Investments for T Quality And Cost- Open - Internationa Under Implement Tech supervision SulaimanT IDA / 65580 ourism and Urban Developm Post 0.00 2021-07-23 2022-06-14 2021-08-07 2021-09-05 2021-10-03 2021-10-23 2021-11-13 2021-12-10 2023-12-30 Based Selection l ation oo and the Uzgen Museum ent IDA-REDP-CS-QCBS-2021-8 / Catalyzing Investments for T Company for Branding,marke Quality And Cost- Open - Internationa Pending Impleme IDA / 65580 ourism and Urban Developm Post 0.00 2021-09-23 2021-09-28 2021-11-14 2021-12-04 2021-12-24 2022-01-14 2022-02-10 2022-10-06 ting and promotion activities Based Selection l ntation ent for Osh region IDA-REDP-CS-LCS-2021-1 / P Implementation Support and Least Cost Selecti Open - Internationa IDA / 65580 Post 0.00 Canceled 2021-10-15 2021-11-05 2021-12-19 2022-01-16 2022-02-15 2022-03-22 2022-04-26 2026-08-23 roject audit (financial audit) Monitoring and Evaluation on l IDA-REDP-CS-QCBS-2021-9 / Tourism Product developmen Catalyzing Investments for T Quality And Cost- Open - Internationa Pending Impleme t at the regional level (fairs, IDA / 65580 ourism and Urban Developm Post 0.00 2022-07-23 2022-08-13 2022-09-26 2022-10-24 2022-11-23 2022-12-28 2023-02-01 2023-07-01 Based Selection l ntation exhibitions, PR, media campa ent igns, cultural events, forums) IDA-REDP-CS-QCBS-2021-10 / Сonsulting company for M& E to conduct a baseline surve Implementation Support and Quality And Cost- Open - Internationa Pending Impleme y, focus group interviews, etc IDA / 65580 Prior 0.00 2022-10-10 2022-10-31 2022-12-14 2023-01-11 2023-02-10 2023-03-17 2023-04-21 2024-04-20 Monitoring and Evaluation Based Selection l ntation . collect quantitive and qualit ative data through the projec t and then at closing provide the summary with the impact results IDA-REDP-CS-QCBS-2021-4 / Consulting company for feasi Improving Regional Economi bilty studies for SPS investm Quality And Cost- Open - Internationa IDA / 65580 c Planning and Regulatory F Post 158,295.00 Signed 2021-07-17 2021-05-01 2021-08-07 2021-05-18 2021-09-20 2021-08-25 2021-10-18 2021-09-23 2021-11-17 2022-02-08 2021-12-22 2022-02-24 2022-01-26 2022-03-31 2022-07-25 ents and design of technical Based Selection l unctions specifications for equipment of laboratories, centers and p oints IDA-REDP-CS-CQS-2021-25 / Catalyzing Investments for T Consultant Qualifi Regional Tourism Strategy C IDA / 65580 ourism and Urban Developm Post Open - National 90,744.99 Signed 2021-10-27 2021-09-22 2021-11-17 2021-12-31 2022-05-11 2022-01-30 2022-05-11 2022-03-06 2022-05-11 2022-09-02 cation Selection onsultant for Osh Oblast ent IDA-REDP-CS-QCBS-2021-11 / Consulting company to iden Strengthening Agri-Food Sup Quality And Cost- Open - Internationa tify specific supply chain acto IDA / 65580 Post 0.00 Canceled 2021-07-23 2021-07-28 2021-09-01 2021-10-03 2021-10-23 2021-11-13 2021-12-10 2022-04-09 ply Chains and SMEs Based Selection l rs for participation and the c ompetitive selection of sub-p rojects IDA-REDP-CS-QCBS-2021-1 / Training in hospitality industr Catalyzing Investments for T Quality And Cost- Open - Internationa y for tour guides, tour operat IDA / 65580 ourism and Urban Developm Prior 0.00 Canceled 2021-08-25 2021-09-15 2021-10-29 2021-11-26 2021-12-26 2022-01-30 2022-03-06 2023-03-06 Based Selection l ors and accomodation mana ent gers/staff; Technical support in business planning IDA-REDP-CS-CQS-2021-27 / Consulting company providin Strengthening Agri-Food Sup Consultant Qualifi Pending Impleme g training and advice to mem IDA / 65580 Post Open - National 0.00 2022-04-04 2022-04-25 2022-06-08 2022-07-08 2022-08-12 2023-02-08 ply Chains and SMEs cation Selection ntation bers of productive partnershi ps for productivity, quality, m arketing and sales ARIS-AUDIT-LCS-2021-1 / Au Implementation Support and Least Cost Selecti Open - Internationa Under Implement IDA / 65580 Post 0.00 2021-09-01 2021-09-13 2021-09-15 2021-09-24 2021-10-13 2021-10-20 2021-10-27 2021-11-10 2021-12-08 2024-12-07 dit (financial audit) Monitoring and Evaluation on l ation IDA-REDP-CS-QCBS-2021-5 / Implementation Support and Quality And Cost- Open - Internationa Company for Preparation of f IDA / 65580 Prior 0.00 Canceled 2021-05-20 2021-06-10 2021-07-24 2021-08-21 2021-09-20 2021-10-25 2021-11-29 2022-11-29 Monitoring and Evaluation Based Selection l uture projects IDA-REDP-CS-CQS-2021-20 / Conducting an information ca mpaign, social mobilization a Strengthening Agri-Food Sup Consultant Qualifi nd diagnostic study in order t IDA / 65580 Post Open - National 0.00 Canceled 2021-09-20 2021-09-16 2021-10-11 2021-11-24 2021-12-24 2022-01-28 2022-07-27 ply Chains and SMEs cation Selection o build value chains and crea te productive partnerships in Osh oblast and Osh city and t heir further development IDA-REDP-CS-CQS-2021-22 / Conducting an information ca mpaign, social mobilization a Strengthening Agri-Food Sup Consultant Qualifi nd diagnostic study in order t IDA / 65580 Post Open - National 288,773.33 Signed 2021-12-20 2021-10-29 2022-01-10 2022-02-23 2022-04-19 2022-03-25 2022-04-19 2022-04-29 2022-04-19 2024-04-18 ply Chains and SMEs cation Selection o build value chains and crea te productive partnerships in Osh oblast and Osh city and t heir further development IDA-REDP-CS-QCBS-2021-3 / Support to department of To Improving Regional Economi Quality And Cost- Open - Internationa urism and regional/local touri IDA / 65580 c Planning and Regulatory F Prior 0.00 Canceled 2021-06-20 2021-07-11 2021-08-24 2021-09-21 2021-10-21 2021-11-25 2021-12-30 2022-05-29 Based Selection l sm agencies for improved st unctions atistics and data collection IDA-REDP-CS-CQS-2021-21 / Training in hospitality industr Supporting Tourism and Rur Consultant Qualifi y for tour guides, tour operat IDA / 65580 al Development through Sm Post Open - National 0.00 Canceled 2021-09-27 2021-10-18 2021-12-01 2021-12-31 2022-02-04 2022-08-03 cation Selection ors and accomodation mana all Grants gers/staff; Technical support in business planning Page 3 IDA-REDP-CS-QCBS-2021-2 / Comprehensive assessment Catalyzing Investments for T of SulaimanToo and Uzgen m Quality And Cost- Open - Internationa IDA / 65580 ourism and Urban Developm Post 0.00 Canceled 2021-08-25 2021-10-22 2021-09-15 2021-10-29 2021-11-26 2021-12-26 2022-01-30 2022-03-06 2023-08-28 useums complexes Detailed Based Selection l ent designs and Construction Su pervision for SulaimanToo an d the Uzgen Museum IDA-REDP-CS-CQS-2021-3 / Improving Regional Economi Consultant Qualifi Open - Internationa Development of Visitors Man IDA / 65580 c Planning and Regulatory F Post 0.00 Canceled 2021-06-29 2021-07-20 2021-09-02 2021-10-02 2021-11-06 2022-02-04 cation Selection l agement Plans for Suleiman unctions Too and Uzgen IDA-REDP-CS-CQS-2021-23 / Catalyzing Investments for T Consultant Qualifi Open - Internationa Pending Impleme Development of Visitors Man IDA / 65580 ourism and Urban Developm Post 0.00 2021-12-19 2022-01-09 2022-02-12 2022-03-14 2022-04-11 2023-02-02 cation Selection l ntation agement Plans for Suleiman ent Too and Uzgen IDA-REDP-CS-CQS-2021-2 / Improving Regional Economi Development of Visitors Man Consultant Qualifi IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 Canceled 2021-06-17 2021-06-23 2021-08-06 2021-09-05 2021-10-10 2022-01-08 agement Plans for Kyrgyz-At cation Selection unctions a, Abshyr-Ata, Karashoroo IDA-REDP-CS-CQS-2021-24 / Consulting company for the p reparation of the regional ec onomic development progra Strengthening Agri-Food Sup Consultant Qualifi IDA / 65580 Post Open - National 0.00 Canceled 2021-09-26 2021-10-22 2021-10-17 2021-11-30 2021-12-30 2022-02-03 2022-08-02 m of osh oblast and economi ply Chains and SMEs cation Selection c development program of os h city under the implementat ion of the regional economic development project IDA-REDP-CS-CQS-2021-7 / Desing for tourism site touri Catalyzing Investments for T Consultant Qualifi sm services and amenities (e IDA / 65580 ourism and Urban Developm Post Open - National 0.00 Canceled 2021-06-29 2021-10-22 2021-07-06 2021-08-19 2021-09-30 2021-10-12 2022-07-14 cation Selection g Desing Abshir-Ata: Kara-Sh ent oro Park Kyrgyz-Ata: infrastr ucture improvement) IDA-REDP-CS-QCBS-2021-15 / Support to department of T Catalyzing Investments for T Quality And Cost- Open - Internationa Pending Impleme ourism and regional/local tou IDA / 65580 ourism and Urban Developm Post 0.00 2022-01-11 2022-02-01 2022-03-17 2022-04-14 2022-05-14 2022-06-18 2022-07-23 2023-07-23 Based Selection l ntation rism agencies for improved s ent tatistics and data collection IDA-REDP-CS-CQS-2021-9 / T Catalyzing Investments for T Consultant Qualifi Open - Internationa IDA / 65580 Post 0.00 Canceled 2021-06-29 2021-07-20 2021-09-02 2021-10-02 2021-11-06 2022-03-06 echnical audit ourism and Urban Developm cation Selection l ent IDA-REDP-CS-QCBS-2021-6 / Catalyzing Investments for T Quality And Cost- Open - Internationa Osh City Construction Superv IDA / 65580 ourism and Urban Developm Post 0.00 Canceled 2021-07-23 2021-08-13 2021-09-05 2021-10-03 2021-10-23 2021-11-13 2021-12-10 2023-12-30 Based Selection l ision Services ent IDA-REDP-CS-CQS-2021-6 / P Catalyzing Investments for T reparation of detailed design Consultant Qualifi IDA / 65580 ourism and Urban Developm Post Open - National 0.00 Canceled 2021-06-29 2021-07-04 2021-08-17 2021-09-28 2021-10-10 2022-01-13 packages for Osh and Uzgen cation Selection ent Design packages IDA-REDP-CS-CQS-2021-8 / T echnical supervision for touri Catalyzing Investments for T Consultant Qualifi sm sites (infrastructure impr IDA / 65580 ourism and Urban Developm Post Open - National 0.00 Canceled 2021-06-29 2021-07-06 2021-08-19 2021-09-30 2021-10-17 2022-04-15 cation Selection ovement: Abshir-Ata, park Ka ent ra-Shoro, Kyrgyz-Ata) IDA-REDP-CS-CQS-2021-13 / Catalyzing Investments for T DED: Zones between residen Consultant Qualifi Pending Impleme IDA / 65580 ourism and Urban Developm Post Open - National 0.00 2021-11-21 2021-12-12 2022-01-25 2022-02-24 2022-03-31 2022-09-27 tial quarters/blocks, wall pain cation Selection ntation ent ting (mosaic), the northern p art of Lenin Street. IDA-REDP-CS-CQS-2021-14 / Catalyzing Investments for T Consultant Qualifi Pending Impleme DED: road networks (5 street IDA / 65580 ourism and Urban Developm Post Open - National 0.00 2021-11-21 2021-12-12 2022-01-25 2022-02-24 2022-03-31 2022-09-27 cation Selection ntation s) and extension of Dostuk p ent ark IDA-REDP-CS-QCBS-2021-14 / DED: Development of feasib Catalyzing Investments for T Quality And Cost- Open - Internationa Pending Impleme ility study and DED of infrastr IDA / 65580 ourism and Urban Developm Post 0.00 2021-11-30 2021-12-05 2021-12-15 2021-12-30 2022-01-09 2022-01-29 2022-02-25 2023-02-25 Based Selection l ntation ucture of Sulaiman-Too comp ent lex and Uzgen historical and architectural complex IDA-REDP-CS-CQS-2021-28 / Consulting company for prep Improving Regional Economi Consultant Qualifi aration of a regional economi IDA / 65580 c Planning and Regulatory F Post Open - National 148,095.79 Signed 2021-11-26 2021-12-02 2021-12-06 2021-12-26 2022-05-11 2021-12-31 2022-05-11 2022-01-26 2022-05-11 2022-07-25 cation Selection c development program for t unctions he Osh oblast and Osh city IDA-REDP-CS-CQS-2021-26 / Catalyzing Investments for T Development of Visitors Man Consultant Qualifi Pending Impleme IDA / 65580 ourism and Urban Developm Post Open - National 0.00 2021-12-01 2021-12-11 2021-12-28 2022-01-07 2022-02-10 2022-08-09 agement Plans for Kyrgyz-At cation Selection ntation ent a, Abshyr-Ata, Karashoroo IDA-REDP-CS-CQS-2021-11 / Catalyzing Investments for T Detailed design packages an Consultant Qualifi IDA / 65580 ourism and Urban Developm Post Open - National 49,479.16 Signed 2021-11-30 2022-03-04 2021-12-21 2022-02-03 2022-04-12 2022-03-05 2022-06-01 2022-04-29 2022-06-07 2022-07-28 d author supervision for the s cation Selection ent elected facilities in the city of Osh IDA-REDP-CS-CQS-2021-15 / Detailed design packages for Catalyzing Investments for T : City Park of Culture and Lei Consultant Qualifi IDA / 65580 ourism and Urban Developm Post Open - National 50,868.60 Signed 2021-11-21 2022-03-02 2021-12-12 2022-01-25 2022-04-05 2022-02-24 2022-06-01 2022-03-31 2022-06-07 2022-09-27 sure "Tynchtyk" named after cation Selection ent N. Aznabakieva, park near th e city stadium, city stadium a nd park bridge IDA-REDP-CS-CQS-2021-17 / Design services and author s Catalyzing Investments for T Consultant Qualifi Under Implement upervision for Kara-Shoro an IDA / 65580 ourism and Urban Developm Post Open - National 0.00 2021-11-28 2022-03-18 2021-12-19 2022-03-29 2022-02-01 2022-03-03 2022-04-07 2022-10-04 cation Selection ation d Kyrgyz-Ata national parks a ent nd Abshir-Ata Waterfall IDA-REDP-CS-CQS-2021-12 / Catalyzing Investments for T Consultant Qualifi IDA / 65580 Post Open - National 0.00 Canceled 2021-11-21 2021-12-12 2022-01-25 2022-02-24 2022-03-31 2022-09-27 DED: coastal zone of the Ak- ourism and Urban Developm cation Selection Buura river ent IDA-REDP-CS-QCBS-2021-13 Supporting Tourism and Rur / Consulting company for the Quality And Cost- Open - Internationa Under Implement IDA / 65580 al Development through Sm Post 0.00 2022-05-08 2022-05-11 2022-05-18 2022-06-07 2022-06-17 2022-06-27 2022-07-17 2022-08-11 2025-02-18 preparation and implementat Based Selection l ation all Grants ion of the Small Grants Progr am IDA-REDP-CS-CQS-2021-18 / Catalyzing Investments for T Consultant Qualifi Technical Supervision of Civil IDA / 65580 ourism and Urban Developm Post Open - National 0.00 Under Review 2022-06-20 2022-06-16 2022-07-11 2022-08-24 2022-09-23 2022-11-07 2024-07-05 cation Selection Works under the RED-1 ent Page 4 IDA-REDP-CS-CQS-2021-31 / Selection of consulting comp any for assessment of the sol Implementation Support and Consultant Qualifi IDA / 65580 Post Open - National 0.00 Canceled 2022-03-01 2022-03-04 2022-03-22 2022-05-05 2022-06-04 2022-07-09 2023-01-05 id waste management syste Monitoring and Evaluation cation Selection ms in selected towns and the identification of priority secto r investments IDA-REDP-CS-CQS-2021-31- RT / Selection of consulting c ompany for assessment of th Implementation Support and Consultant Qualifi Open - Internationa Under Implement IDA / 65580 Post 0.00 2022-06-17 2022-06-17 2022-07-08 2022-08-21 2022-09-20 2022-10-25 2023-04-23 e solid waste management s Monitoring and Evaluation cation Selection l ation ystems in selected towns an d the identification of priority sector investments INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-REDP-CS-IC-2021-11 / Lo Improving Regional Economi Individual Consult Pending Impleme cal consultant for review of le IDA / 65580 c Planning and Regulatory F Post Open 0.00 2021-12-21 2022-01-23 2022-02-25 2022-03-22 2023-03-17 ant Selection ntation gal acts for exports 3 unctions IDA-REDP-CS-IC-2021-12 / Lo Improving Regional Economi Individual Consult Pending Impleme cal consultant for review of le IDA / 65580 c Planning and Regulatory F Post Open 0.00 2021-12-21 2022-01-23 2022-01-25 2022-03-26 2023-03-21 ant Selection ntation gal acts for exports 4 unctions IDA-REDP-CS-IC-2021-13 / C Improving Regional Economi onsultant for Development of Individual Consult Pending Impleme IDA / 65580 c Planning and Regulatory F Post Open 0.00 2021-12-21 2022-01-23 2022-01-25 2022-03-26 2023-03-21 legal documents of 7 samplin ant Selection ntation unctions g points for laboratory testin g IDA-REDP-CS-IC-2021-3 / Co Improving Regional Economi Individual Consult Pending Impleme nsultant for sowtfare desing IDA / 65580 c Planning and Regulatory F Post Open 0.00 2020-11-25 2020-12-25 2020-12-30 2021-02-28 2022-02-23 ant Selection ntation and on-job training unctions IDA-REDP-CS-IC-2021-4 / Co Improving Regional Economi nsultant for Development of Individual Consult Pending Impleme IDA / 65580 c Planning and Regulatory F Post Open 0.00 2020-11-25 2020-12-25 2020-12-30 2021-02-28 2022-02-23 education materials for Osh t ant Selection ntation unctions echnical agricultural college and Osh university IDA-REDP-CS-IC-2021-8 / Int Improving Regional Economi Individual Consult Pending Impleme ernational consultant for revi IDA / 65580 c Planning and Regulatory F Post Open 0.00 2020-12-21 2021-01-20 2021-01-25 2021-03-26 2022-03-21 ant Selection ntation ew of legal acts for exports unctions IDA-REDP-CS-IC-2021-10 / Lo Improving Regional Economi Individual Consult Pending Impleme cal consultant for review of le IDA / 65580 c Planning and Regulatory F Post Open 0.00 2020-12-21 2021-01-20 2021-01-25 2021-03-26 2022-03-21 ant Selection ntation gal acts for exports 2 unctions IDA-REDP-CS-IC-2021-9 / Loc Improving Regional Economi Individual Consult Pending Impleme al consultant for review of le IDA / 65580 c Planning and Regulatory F Post Open 0.00 2020-12-21 2021-01-20 2021-01-25 2021-03-26 2021-05-01 ant Selection ntation gal acts for exports 1 unctions IDA-REDP-CS-IC-2021-20 / C Supporting Tourism and Rur onsultant to provide support Individual Consult IDA / 65580 al Development through Sm Post Open 16,421.51 Signed 2021-10-21 2021-08-19 2021-12-09 2022-04-15 2021-12-30 2022-04-15 2022-02-03 2022-04-15 2022-08-02 to ARIS with Small Grants Pro ant Selection all Grants gram and Public and Private Cooperation initiative IDA-REDP-CS-IC-2021-1 / Co Improving Regional Economi Individual Consult nsultant for Regional Econom IDA / 65580 c Planning and Regulatory F Post Open 0.00 Canceled 2020-11-25 2020-12-25 2020-12-30 2021-02-28 2022-02-23 ant Selection ic Development Plan for Osh unctions region IDA-REDP-CS-IC-2021-2 / Co Improving Regional Economi Individual Consult nsultant for Development of t IDA / 65580 c Planning and Regulatory F Post Open 0.00 Canceled 2021-09-27 2021-05-18 2021-10-27 2021-11-01 2021-12-31 2022-12-26 ant Selection he Regional tourism strategy unctions for Osh region IDA-REDP-CS-IC-2021-21 / Fo r the Consultancy to provide Implementation Support and Individual Consult IDA / 65580 Post Open 0.00 Canceled 2021-12-12 2021-10-07 2022-01-30 2022-02-20 2022-03-27 2022-09-23 support to ARIS with Social Is Monitoring and Evaluation ant Selection sues for RED Project IDA-REDP-CS-IC-2021-22 / Fo r the Consultancy to provide Implementation Support and Individual Consult IDA / 65580 Post Limited 7,055.99 Signed 2021-12-12 2021-10-12 2021-12-26 2022-04-04 2022-02-20 2022-04-04 2022-03-27 2022-04-05 2022-09-23 support to ARIS with Social Is Monitoring and Evaluation ant Selection sues for RED Project IDA-REDP-CS-IC-2021-19 / C onsultants for the developme Strengthening Agri-Food Sup Individual Consult nt of business plans and proj IDA / 65580 Post Open 0.00 Canceled 2021-10-29 2021-12-17 2022-01-07 2022-02-11 2022-08-10 ply Chains and SMEs ant Selection ect proposals at the stages o f selection of productive part nerships IDA-REDP-CS-IC-2021-24 / C Catalyzing Investments for T onsulting for conducting rese Individual Consult Pending Impleme IDA / 65580 ourism and Urban Developm Post Open 0.00 2021-11-30 2021-12-25 2022-01-04 2022-01-20 2022-04-20 arch on tourism statistics an ant Selection ntation ent d developing recommendatio ns for impoving IDA-REDP-CS-IC-2021-6 / Loc Improving Regional Economi al consultant for for MinAgri, Individual Consult IDA / 65580 c Planning and Regulatory F Post Open 0.00 Canceled 2020-11-25 2020-12-25 2020-12-30 2021-02-28 2022-02-23 Osh oblast administration an ant Selection unctions d other stakeholders 1 IDA-REDP-CS-IC-2021-7 / Loc Improving Regional Economi al consultant for for MinAgri, Individual Consult IDA / 65580 c Planning and Regulatory F Post Open 0.00 Canceled 2020-12-21 2021-01-20 2021-01-25 2021-03-26 2022-03-21 Osh oblast administration an ant Selection unctions d other stakeholders 2 IDA-REDP-CS-IC-2021-25 / C onsultant - trainer for capacit y building of specialists of go Improving Regional Economi vernment bodies and process Individual Consult IDA / 65580 c Planning and Regulatory F Post Open 1,627.02 Signed 2021-12-05 2021-11-25 2022-01-23 2022-04-05 2022-02-13 2022-04-03 2022-03-20 2022-04-13 2022-09-16 ing enterprises on food safet ant Selection unctions y in accordance with internat ional food quality and safety standards (ISO 9001, ISO 220 00, FSSC 22000). Page 5 IDA-REDP-CS-IC-2021-26 / C onsultant-trainer for capacity building of specialists of gove rnment bodies and agricultur Improving Regional Economi Individual Consult al producers on ensuring the IDA / 65580 c Planning and Regulatory F Post Open 1,627.02 Signed 2021-12-05 2021-11-25 2022-01-23 2022-04-01 2022-02-13 2022-04-01 2022-03-20 2022-04-05 2022-09-16 ant Selection safety of agricultural producti unctions on in accordance with intern ational standards (GLOBAL G .A.P., Organic, ISO 14000, etc .) for domestic mar IDA-REDP-CS-CQS-2021-30 / Implementation Support and Individual Consult Pending Impleme IDA / 65580 Post Open 0.00 2023-05-05 2023-06-23 2023-07-14 2023-08-18 2024-02-14 Technical audit Monitoring and Evaluation ant Selection ntation IDA-REDP-CS-IC-2021-28 / In dependent consultant on eva Strengthening Agri-Food Sup Individual Consult Pending Impleme IDA / 65580 Post Open 0.00 2021-12-27 2022-02-14 2022-03-07 2022-04-11 2023-10-03 luation of business plans and ply Chains and SMEs ant Selection ntation Sub-project proposals IDA-REDP-CS-IC-2021-31 / S Implementation Support and Individual Consult election of institutional devel IDA / 65580 Post Limited 9,490.78 Signed 2021-12-05 2021-12-08 2021-12-10 2022-04-05 2021-12-31 2022-04-05 2022-02-04 2022-04-06 2022-08-03 Monitoring and Evaluation ant Selection opment consultant IDA-REDP-CS-IC-2021-29 / In dependent consultant on eva Strengthening Agri-Food Sup Individual Consult Pending Impleme IDA / 65580 Post Open 0.00 2021-12-27 2022-02-14 2022-03-07 2022-04-11 2023-10-03 luation of business plans and ply Chains and SMEs ant Selection ntation Sub-project proposals IDA-REDP-CS-IC-2021-27 / In dependent consultant on eva Strengthening Agri-Food Sup Individual Consult Pending Impleme IDA / 65580 Post Open 0.00 2021-12-27 2022-02-14 2022-03-07 2022-04-11 2023-10-03 luation of business plans and ply Chains and SMEs ant Selection ntation Sub-project proposals IDA-REDP-CS-IC-2021-30 / In dependent consultant on eva Strengthening Agri-Food Sup Individual Consult Pending Impleme IDA / 65580 Post Open 0.00 2021-12-27 2022-02-14 2022-03-07 2022-04-11 2023-10-03 luation of business plans and ply Chains and SMEs ant Selection ntation Sub-project proposals IDA-REDP-CS-IC-2021-32 / C Catalyzing Investments for T Individual Consult Under Implement onsultant to develop a websit IDA / 65580 ourism and Urban Developm Post Open 0.00 2022-04-28 2022-05-13 2022-06-16 2022-07-07 2022-08-11 2023-02-07 ant Selection ation e of the Public-Private Coope ent ration Program IDA-REDP-CS-IC-2021-14 / C onsultant-trainer on capacity building of employees of the Ministry of Agriculture of the Strengthening Agri-Food Sup Individual Consult Under Implement Kyrgyz Republic, specialists o IDA / 65580 Post Open 0.00 2022-05-25 2022-06-06 2022-07-13 2022-08-03 2022-09-07 2023-03-06 ply Chains and SMEs ant Selection ation f the Regional Economic Dev elopment Project of Osh obla st and Osh city, ARIS and the Agribusiness Competitivenes s Center on building a Page 6