Summarized Procurement Plan I. General 1. Project Name: Integrated Cities and Urban Development Project ( ICUD) 2. Period covered by this procurement plan: First 18 months II. Goods and Non-consulting Services 1. Procurement Methods and Prior Review Thresholds: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Category Method of Threshold (US$ Prior Review Threshold (US$ Procurement Equivalent) Equivalent) Goods ICB No threshold All contracts above $1,000,000 NCB <500,000 None Shopping <100,000 None Direct No threshold All contracts Contracting Non- ICB No threshold All contracts above $1,000,000 consulting services NCB <1,000,000 None Shopping <100,000 None Direct No threshold All contracts Contracting III. Selection of Consultants 1. Selection Methods and Prior Review Thresholds: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Category Selection Threshold Prior Review Threshold Method (US$ Equivalent) (US$ Equivalent) Consulting QCBS/QBS No threshold All contracts above $500,000 Services Firms FBS/CQS/LCS <200,000 None Sole Source No threshold All contracts Individuals IC No threshold All contracts above $200,000 Sole Source No threshold All contracts 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. All Terms of Reference shall be subject to the World Bank’s clearance. PROCUREMENT West Bank and Gaza : GZ-Integrated Cities and Urban Development Project PLAN General Information Country: West Bank and Gaza 2016-08-17 Bank’s Approval Date of the Original Procurement Plan: 2022-06-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150991 GPN Date: 2016-08-17 Project Name: GZ-Integrated Cities and Urban Development Project Loan / Credit No: / , TF / A2846 Municipal Development and Lending Fund Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-MDLF-246049-CW-RFQ / Request for Construction of cardboard an Component No. 1: Planning f Request for Quota Single Stage - One E Quotations ( 2022-01-2 TF / A2846 Post Limited 86,450.00 Terminated 2021-08-27 2021-08-26 2021-10-22 2021-09-26 d paper sorting facility - Beth or Sustainable Urban Growth tions nvelope Non Bank-SP 0 lehem Urban area D) GZ-MDLF-271214-CW-RFQ / Other (with fi Rehabilitation of Pedestrian - Component No. 1: Planning f Request for Quota Single Stage - One E 2022-05-1 TF / A2846 Post Open - National eld for expla 0.00 Canceled 2022-01-26 2022-02-15 Friendly Street in Ramallah a or Sustainable Urban Growth tions nvelope 6 nation) nd Al-Bireh Urban Area GZ-MDLF-271210-CW-RFQ / Other (with fi Component No. 1: Planning f Request for Quota Single Stage - One E 2022-05-1 Rehabilitation of Internal Ro TF / A2846 Post Open - National eld for expla 179,540.00 Signed 2022-01-26 2022-02-15 2022-03-20 or Sustainable Urban Growth tions nvelope 6 ads and Traffic Lights in Heb nation) ron Urban Area Other (with fi GZ-MDLF-271208-CW-RFQ / Component No. 1: Planning f Request for Quota Single Stage - One E 2022-05-2 TF / A2846 Post Open - National eld for expla 196,650.00 Signed 2022-01-30 2022-02-19 2022-03-31 Rehabilitation of Gaza City C or Sustainable Urban Growth tions nvelope 0 nation) entral Park GZ-MDLF-271215-CW-RFQ / Other (with fi Component No. 1: Planning f Request for Quota Single Stage - One E 2022-05-2 Construction of Bus-Stops in TF / A2846 Post Open - National eld for expla 206,363.75 Signed 2022-01-30 2022-02-19 2022-03-28 or Sustainable Urban Growth tions nvelope 0 Nablus Urban Area nation) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component No. 2: Project Im GZ-MDLF-841-GO-RFQ / Sup Request for Quota Single Stage - One E / plementation Support and M Post Limited 3,109.96 Completed 2016-10-06 2017-03-16 2016-12-01 2017-03-30 2017-05-30 2017-04-12 ply of Office Furniture. tions nvelope anagement Cost Component No. 2: Project Im GZ-MDLF-840-GO-RFQ / Sup Request for Quota Single Stage - One E / plementation Support and M Post Limited 20,518.00 Completed 2016-10-05 2017-03-01 2016-11-30 2017-03-20 2017-05-29 2017-05-03 ply of Hardware tions nvelope anagement Cost GZ-MDLF-2666-GO-RFQ / Su Component No. 1: Planning f Request for Quota Single Stage - One E pply of Hardware for the Tec / Post Limited 1,767.00 Completed 2016-10-23 2016-10-25 2016-12-18 2016-11-03 2017-06-16 2016-11-08 or Sustainable Urban Growth tions nvelope hnical Supervisor. GZ-MDLF-5595-GO-RFQ / Pro Component No. 2: Project Im Request for Quota Single Stage - One E vision of Adobe Design Packa TF / A2846 plementation Support and M Post Open - National 0.00 Canceled 2017-03-06 2017-05-01 2017-10-28 tions nvelope ge and GIS software for the p anagement Cost roject. GZ-MDLF-33859-GO-RFQ / S Component No. 1: Planning f Request for Quota Single Stage - One E upply of Total Station for Gaz TF / A2846 Post Limited 0.00 Terminated 2017-11-10 2017-12-03 2018-01-05 2017-12-26 2018-07-04 or Sustainable Urban Growth tions nvelope a Municipality GZ-MDLF-41088-GO-RFQ / S Component No. 1: Planning f Request for Quota Single Stage - One E upply of Hardware for the Te TF / A2846 Post Limited 1,487.00 Completed 2018-01-01 2018-01-30 2018-02-19 2018-02-12 2018-03-21 2018-03-06 or Sustainable Urban Growth tions nvelope chnical Coordinator at MOLG GZ-MDLF-842-GO-RFQ / Sup Component No. 1: Planning f Request for Quota Single Stage - One E / Post Limited 0.00 Canceled 2016-10-05 2016-11-30 2017-05-29 ply of Hardware for Gaza or Sustainable Urban Growth tions nvelope GZ-MDLF-57568-GO-RFQ / S upply of hardware to support Component No. 1: Planning f Request for Quota Single Stage - One E TF / A2846 Post Limited 29,991.00 Completed 2018-06-06 2018-06-24 2018-08-01 2018-08-08 2018-09-30 2018-10-31 development of Integrated GI or Sustainable Urban Growth tions nvelope S database/Hebron Urban Ar ea GZ-MDLF-57569-GO-RFQ / S Component No. 1: Planning f Request for Quota Single Stage - One E upply of Hardware to support TF / A2846 Post Limited 13,990.00 Completed 2018-04-25 2018-07-23 2018-06-20 2018-08-28 2018-08-19 2019-01-13 or Sustainable Urban Growth tions nvelope Integrated Planning in Gaza Municipality GZ-MDLF-67743-GO-RFQ / S Component No. 1: Planning f upply of Tow Total Stations f TF / A2846 Post Direct Selection Direct 37,324.00 Completed 2018-06-25 2018-07-15 2018-06-30 2018-07-17 2018-08-04 2018-07-24 2019-01-31 2018-08-02 or Sustainable Urban Growth or Gaza Municipality GZ-MDLF-185208-GO-RFQ / Component No. 1: Planning f Request for Quota Single Stage - One E Supply of a Central Cardboar TF / A2846 Post Open - National 0.00 Canceled 2021-02-20 2021-04-17 2021-08-15 or Sustainable Urban Growth tions nvelope d Baler Machine for Bethlehe m Urban Area GZ-MDLF-164011-GO-DIR / S Component No. 1: Planning f TF / A2846 Post Direct Selection Direct 87,472.10 Completed 2020-09-01 2020-04-19 2020-09-06 2020-11-23 2020-10-11 2020-12-20 2021-04-09 2021-04-29 upply of Software for Traffic or Sustainable Urban Growth Modelling GZ-MDLF-201708-GO-RFQ / Component No. 2: Project Im Request for Quota Single Stage - One E Supply of hardware for the IC TF / A2846 plementation Support and M Post Limited 10,575.00 Completed 2020-11-09 2020-11-30 2021-01-04 2021-02-02 2021-02-03 2021-03-30 tions nvelope UD team anagement Cost GZ-MDLF-222287-GO-RFQ / Component No. 1: Planning f Request for Quota Single Stage - One E Acquisition of an aerial photo TF / A2846 Post Limited 58,800.00 Signed 2021-03-15 2021-03-24 2021-05-10 2021-06-16 2021-09-07 or Sustainable Urban Growth tions nvelope for Gaza city GZ-MDLF-222290-GO-RFQ / Supply of IT hardware for Ga Component No. 1: Planning f Request for Quota Single Stage - One E TF / A2846 Post Limited 44,085.00 Completed 2021-03-15 2021-03-15 2021-05-10 2021-04-15 2021-08-08 2021-09-14 za city Infrastructure manage or Sustainable Urban Growth tions nvelope ment and planning optimizati on GZ-MDLF-222293-GO-RFQ / Component No. 1: Planning f Request for Quota Single Stage - One E SCADA system software for TF / A2846 Post Limited 0.00 Canceled 2021-03-15 2021-05-10 2021-08-08 or Sustainable Urban Growth tions nvelope water maintenance and moni toring Page 1 GZ-MDLF-233807-GO-RFQ / Component No. 1: Planning f Request for Quota Single Stage - One E Supply and Install of Solar Ph TF / A2846 Post Limited 42,184.00 Signed 2021-08-21 2021-11-29 2021-10-16 2021-12-27 2022-01-14 or Sustainable Urban Growth tions nvelope otovoltaic Systems for Gaza Urban Area GZ-MDLF-233805-GO-RFB / Supply and Install of Solar Ph Component No. 1: Planning f Single Stage - One E TF / A2846 Post Request for Bids Open - National 243,935.00 Signed 2021-09-15 2021-12-06 2021-09-20 2021-12-07 2021-11-01 2022-01-06 2021-12-01 2022-01-13 2022-01-05 2022-02-02 2022-05-05 otovoltaic Systems for Target or Sustainable Urban Growth nvelope ed Urban Areas in West Bank " GZ-MDLF-185237-GO-DIR / S Component No. 1: Planning f upply of Software for Traffic TF / A2846 Post Direct Selection Direct 43,333.00 Completed 2021-07-27 2021-06-15 2021-08-03 2021-06-21 2021-08-18 2021-07-07 2022-02-14 2021-07-25 or Sustainable Urban Growth Modelling-Ramallah & Al Bire h Urban Area GZ-MDLF-274842-GO-RFQ / Purchasing Cloud storage sp Component No. 1: Planning f Request for Quota Single Stage - One E TF / A2846 Post Limited 49,450.00 Signed 2022-04-20 2022-04-11 2022-05-14 2022-05-10 2022-06-13 ace reserved for 3 years (Virt or Sustainable Urban Growth tions nvelope ual Machines for web App+D atabase) GZ-MDLF-274848-GO-RFQ / Component No. 1: Planning f Request for Quota Single Stage - One E TF / A2846 Post Limited 17,500.00 Signed 2022-02-10 2022-03-06 2022-03-02 2022-03-15 2022-05-01 Supply and Install of Energy or Sustainable Urban Growth tions nvelope Multimeters NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-MDLF-79395-NC-RFQ / G Component No. 1: Planning f Request for Quota Single Stage - One E eographic Information Syste TF / A2846 Post Limited 15,070.70 Completed 2018-10-25 2018-10-07 2018-12-20 2018-10-31 2019-02-03 2019-01-31 or Sustainable Urban Growth tions nvelope m (GIS) Training GZ-MDLF-78354-NC-RFQ / B Component No. 1: Planning f Request for Quota Single Stage - One E TF / A2846 Post Open - National 18,453.00 Completed 2018-10-20 2018-12-15 2019-01-17 2019-04-14 2019-05-12 eit Sahour Photogrammetry or Sustainable Urban Growth tions nvelope GZ-MDLF-112708-NC-RFQ / Training Courses for IT officer Component No. 1: Planning f Request for Quota Single Stage - One E s (Administrator & Developer TF / A2846 Post Limited 10,892.60 Completed 2019-05-14 2019-05-21 2019-07-09 2019-06-17 2019-10-07 2019-09-12 or Sustainable Urban Growth tions nvelope s ): To Manage and Develop t he Urban Performance Tool GZ-MDLF-843-NC-RFQ / Sup Component No. 1: Planning f Request for Quota Single Stage - One E ply of Updated Areal Photogr / Post Limited 0.00 Canceled 2017-04-06 2017-06-01 2017-11-28 or Sustainable Urban Growth tions nvelope ammetric or Satellite Images for Gaza City GZ-MDLF-185216-NC-RFQ / Public Awareness Campaign Component No. 1: Planning f Request for Quota Single Stage - One E TF / A2846 Post Limited 0.00 Canceled 2020-08-15 2021-03-18 2021-09-14 Cardboard and paper sorting- or Sustainable Urban Growth tions nvelope Bethlehem Urban Area CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-MDLF-850-CS-QCBS / Ass essment and Collection of Mi Component No. 1: Planning f Quality And Cost- / Post Open - National 0.00 Canceled 2017-03-01 2017-03-22 2017-05-05 2017-06-02 2017-07-02 2017-08-06 2017-09-10 2018-09-10 ssing Data and Analysis to D or Sustainable Urban Growth Based Selection evelop Urban Growth Footpri nt in Gaza City GZ-MDLF-7705-CS-QCBS / Ur Component No. 1: Planning f Quality And Cost- Open - Internationa TF / A2846 Prior 486,956.17 Signed 2017-03-19 2017-08-14 2017-04-09 2017-08-16 2017-05-23 2017-11-22 2017-06-20 2017-12-31 2017-07-20 2018-02-05 2017-08-24 2018-02-26 2017-09-28 2018-02-22 2018-09-28 ban Growth Scenario Exercis or Sustainable Urban Growth Based Selection l e GZ-MDLF-57571-CS-CQS / Pr epare a Comprehensive Publi c Transportation Plan for Ra Component No. 1: Planning f Quality And Cost- TF / A2846 Post Open - National 0.00 Canceled 2018-07-20 2018-08-06 2018-08-03 2018-08-24 2018-09-23 2018-10-07 2018-10-21 2018-11-25 2019-05-24 mallah and Al Bireh Urban Ar or Sustainable Urban Growth Based Selection ea and Expand the RAB Mobil ity Plan to include Surda Abu Qush Town GZ-MDLF-57572-CS-QCBS / Prepare the Environmental I Component No. 1: Planning f Quality And Cost- TF / A2846 Post Open - National 0.00 Canceled 2018-06-01 2018-06-15 2018-07-06 2018-08-03 2018-08-17 2018-08-31 2018-10-05 2019-04-03 mpact Assessment study /N or Sustainable Urban Growth Based Selection ablus and Bethlehem Area GZ-MDLF-57573-CS-QCBS / Component No. 1: Planning f Quality And Cost- Prepare a Mobility Study/Tra TF / A2846 Post Open - National 81,174.00 Completed 2018-06-01 2018-11-22 2018-06-22 2018-07-13 2019-01-03 2018-08-10 2019-02-10 2018-08-24 2019-02-17 2018-09-28 2019-02-20 2018-11-02 2019-03-10 2019-05-01 2019-10-04 or Sustainable Urban Growth Based Selection ffic study for Hebron and Na blus Urban Areas GZ-MDLF-849-CS-CQS / Cap Component No. 1: Planning f Consultant Qualifi acity Development for LGUs, / Post Open - National 0.00 Canceled 2016-12-01 2016-12-22 2017-02-04 2017-03-06 2017-04-10 2017-10-07 or Sustainable Urban Growth cation Selection MDLF and MoLG GZ-MDLF-226-CS-QCBS / Ass essment and Collection of Exi Component No. 1: Planning f Quality And Cost- Open - Internationa sting Urban Growth Data and / Post 0.00 Canceled 2016-10-01 2016-10-22 2016-12-05 2017-01-02 2017-02-01 2017-03-08 2017-04-12 2017-08-13 or Sustainable Urban Growth Based Selection l Development of Urban Growt h Planning Roadmaps in Wes t Bank and Gaza GZ-MDLF-78337-CS-QCBS / Demographic Change and se Component No. 1: Planning f Quality And Cost- TF / A2846 Post Open - National 0.00 Canceled 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-27 2019-11-23 rvice demand Study for Bethl or Sustainable Urban Growth Based Selection ehem Urban Area GZ-MDLF-105921-CS-QCBS / Prepare a Comprehensive Pu Component No. 1: Planning f Quality And Cost- Open - Internationa TF / A2846 Post 238,480.00 Completed 2019-03-31 2019-06-10 2019-04-21 2019-06-16 2019-06-04 2019-07-15 2019-07-02 2019-09-09 2019-08-01 2019-09-19 2019-09-05 2019-09-25 2019-10-10 2019-11-05 2020-10-09 2021-06-16 blic Transportation Plan for R or Sustainable Urban Growth Based Selection l amallah and Al Bireh Urban A rea GZ-MDLF-105935-CS-CQS / E xtension of the Traffic and Tr Component No. 1: Planning f Consultant Qualifi ansportation Plan for Ramalla TF / A2846 Post Open - National 29,998.00 Completed 2019-03-31 2019-04-30 2019-04-21 2019-06-04 2019-06-10 2019-07-04 2019-07-01 2019-08-08 2019-07-10 2019-12-06 2019-11-10 or Sustainable Urban Growth cation Selection h, Al-Bireh, and Betunia to in clude Surda-Abu Qush. GZ-MDLF-105937-CS-QCBS / Strategic Environmental and Component No. 1: Planning f Quality And Cost- Open - Internationa TF / A2846 Post 214,704.00 Completed 2019-03-31 2019-06-26 2019-04-21 2019-07-08 2019-06-04 2019-08-26 2019-07-02 2019-10-21 2019-08-01 2019-11-19 2019-09-05 2019-11-14 2019-10-10 2019-12-15 2020-06-06 2021-08-25 Social Assessment for the fiv or Sustainable Urban Growth Based Selection l e targeted urban areas in We st Bank & Gaza Page 2 GZ-MDLF-106015-CS-CQS / Component No. 1: Planning f Consultant Qualifi Development Plan for the Wa TF / A2846 Post Open - National 0.00 Canceled 2020-09-01 2020-09-22 2020-11-05 2020-12-05 2021-01-26 2021-05-26 or Sustainable Urban Growth cation Selection ter Front for Gaza City GZ-MDLF-153610-CS-QCBS / Developing a Sustainable To Component No. 1: Planning f Quality And Cost- Open - Internationa TF / A2846 Post 382,730.44 Signed 2020-06-01 2020-07-29 2020-06-22 2020-08-05 2020-09-09 2020-09-02 2020-11-01 2020-10-02 2020-11-24 2020-11-06 2020-12-24 2020-12-11 2021-02-09 2021-08-08 urism Development Plan for or Sustainable Urban Growth Based Selection l Bethlehem Urban area GZ-MDLF-164003-CS-CQS / L ocal Technical consultant for Component No. 1: Planning f Consultant Qualifi TF / A2846 Post Open - National 19,923.00 Completed 2020-10-01 2020-12-17 2020-10-22 2020-12-05 2021-02-03 2021-01-04 2021-03-23 2021-02-08 2021-03-29 2022-02-07 2021-08-17 Pilot Project for Cardboard an or Sustainable Urban Growth cation Selection d Paper Sorting- Bethlehem Urban Area GZ-MDLF-201725-CS-CQS / Component No. 1: Planning f Consultant Qualifi Assessment of IT-GIS Environ TF / A2846 Post Open - National 17,400.00 Completed 2020-11-04 2020-11-12 2020-11-25 2021-01-08 2020-12-07 2021-02-07 2021-01-10 2021-03-14 2021-01-10 2021-09-10 2021-08-15 or Sustainable Urban Growth cation Selection ment for the ICUD Targeted Urban Areas GZ-MDLF-210299-CS-CQS / P ublic Awareness Campaign C Component No. 1: Planning f Consultant Qualifi TF / A2846 Post Open - National 21,450.00 Completed 2020-12-20 2020-12-27 2021-01-10 2021-02-23 2021-02-02 2021-03-25 2021-05-12 2021-04-29 2021-05-24 2021-07-28 2022-01-09 ardboard and paper sorting-B or Sustainable Urban Growth cation Selection ethlehem Urban Area GZ-MDLF-164006-CS-QCBS / LTC for Sustainable Urban Gr Component No. 1: Planning f Quality And Cost- Open - Internationa TF / A2846 Post 99,931.59 Completed 2020-05-01 2021-01-21 2020-05-22 2020-07-05 2021-03-04 2020-08-02 2021-04-11 2020-09-01 2021-04-26 2020-10-06 2021-04-28 2020-11-10 2021-05-20 2021-07-08 2022-05-17 owth Pilot Projects: Gaza, He or Sustainable Urban Growth Based Selection l bron, Ramallah-Al-Bireh, and Nablus Urban Areas GZ-MDLF-222297-CS-CQS / P Component No. 1: Planning f Consultant Qualifi roviding Capacity Building Tr TF / A2846 Post Open - National 0.00 Canceled 2021-03-10 2021-03-31 2021-05-14 2021-06-13 2021-07-18 2022-01-14 or Sustainable Urban Growth cation Selection aining for ICUD Targeted Urb an Areas GZ-MDLF-222299-CS-QCBS / Component No. 1: Planning f Quality And Cost- TF / A2846 Post Open - National 42,970.00 Signed 2021-03-25 2021-09-12 2021-04-15 2021-05-29 2021-10-06 2021-06-26 2021-11-03 2021-07-26 2021-11-14 2021-08-30 2021-11-17 2021-10-04 2021-12-06 2022-10-04 City center development pla or Sustainable Urban Growth Based Selection n for Gaza GZ-MDLF-222301-CS-QCBS / Component No. 1: Planning f Quality And Cost- Open - Internationa Joint strategic spatial & inves TF / A2846 Post 0.00 Canceled 2021-03-31 2021-04-21 2021-06-04 2021-07-02 2021-08-01 2021-09-05 2021-10-10 2022-10-10 or Sustainable Urban Growth Based Selection l tment plan for the targeted u rban areas GZ-MDLF-163991-CS-QCBS / Joint Spatial Framework with Component No. 1: Planning f Quality And Cost- Open - Internationa TF / A2846 Post 0.00 Canceled 2020-10-01 2020-10-22 2020-12-05 2021-01-02 2021-02-01 2021-03-08 2021-04-12 2022-01-07 Capital investment Plans for t or Sustainable Urban Growth Based Selection l he targeted Urban areas GZ-MDLF-242981-CS-CQS / J Component No. 1: Planning f Consultant Qualifi oint strategic spatial & invest TF / A2846 Post Open - National 290,000.00 Signed 2021-07-15 2021-08-05 2021-08-05 2021-09-18 2021-09-01 2021-10-18 2021-09-30 2021-11-22 2021-10-05 2022-06-20 or Sustainable Urban Growth cation Selection ment plan for the targeted ur ban areas GZ-MDLF-246036-CS-CQS / Developing a computerized s Component No. 1: Planning f Consultant Qualifi ystem for the maintenance a TF / A2846 Post Open - National 0.00 Canceled 2021-09-01 2021-09-22 2021-11-05 2021-12-05 2022-01-09 2022-08-07 or Sustainable Urban Growth cation Selection nd operation of water / wast e-water stations in Gaza city GZ-MDLF-246050-CS-CQS / Design and development of s Component No. 1: Planning f Consultant Qualifi TF / A2846 Post Open - National 125,000.00 Signed 2021-08-15 2021-09-01 2021-09-05 2021-10-19 2021-10-05 2021-11-18 2021-11-01 2021-12-23 2021-11-08 2022-08-20 hared urban Geo database fo or Sustainable Urban Growth cation Selection r the targeted four urban are as INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-MDLF-851-CS-INDV / Hiri Component No. 1: Planning f Individual Consult ng of Technical GIS Data Sto / Post Open - National 156,540.00 Signed 2017-01-01 2017-01-01 2017-02-19 2017-01-26 2017-03-12 2017-01-31 2017-04-16 2017-03-01 2017-10-13 or Sustainable Urban Growth ant Selection rage Specialist GZ-MDLF-225-CS-INDV / Tec Component No. 1: Planning f Individual Consult / Post Open - National 32,000.00 Terminated 2016-06-29 2016-06-22 2016-08-16 2016-10-09 2016-09-06 2016-10-10 2016-10-11 2016-10-15 2017-04-09 hnical Supervisor within MOL or Sustainable Urban Growth ant Selection G. GZ-MDLF-844-CS-INDV / Hiri Component No. 1: Planning f Individual Consult ng of Local Coordinator- Beth / Post Open - National 32,775.00 Terminated 2016-11-29 2016-11-17 2017-01-17 2017-02-20 2017-02-07 2017-02-22 2017-03-14 2017-03-01 2017-09-10 or Sustainable Urban Growth ant Selection lehem Urban Area GZ-MDLF-845-CS-INDV / Hiri Component No. 1: Planning f Individual Consult ng of Local Coordinator - Heb / Post Open - National 139,245.00 Signed 2016-11-29 2016-11-17 2017-01-17 2017-01-30 2017-02-07 2017-01-30 2017-03-14 2017-03-01 2017-09-10 or Sustainable Urban Growth ant Selection ron Urban Area GZ-MDLF-848-CS-INDV / Hiri Component No. 1: Planning f Individual Consult ng of Local Coordinator - Nab / Post Open - National 137,550.00 Signed 2016-11-29 2016-11-17 2017-01-17 2017-01-19 2017-02-07 2017-01-26 2017-03-14 2017-02-01 2017-09-10 or Sustainable Urban Growth ant Selection lus Urban Area GZ-MDLF-15955-CS-INDV / I Component No. 1: Planning f Individual Consult nstitutional Assesment of RA TF / A2846 Post Open 3,782.00 Terminated 2017-05-25 2017-07-12 2017-07-13 2017-09-14 2017-08-03 2017-09-14 2017-09-07 2017-09-20 2018-03-06 or Sustainable Urban Growth ant Selection B Joint Cooperation Unit GZ-MDLF-33862-CS-INDV / H Component No. 1: Planning f Individual Consult TF / A2846 Post Open 51,527.00 Terminated 2017-11-05 2017-12-03 2017-12-24 2017-12-03 2018-01-14 2017-12-04 2018-02-18 2017-12-14 2019-02-18 iring of Local Coordinator at or Sustainable Urban Growth ant Selection MOLG GZ-MDLF-24713-CS-INDV / I Component No. 1: Planning f Individual Consult TF / A2846 Post Open 0.00 Canceled 2017-08-13 2017-09-17 2017-09-22 2017-10-01 2018-10-01 CUD Technical Supervisor or Sustainable Urban Growth ant Selection GZ-MDLF-57570-CS-INDV / P repare the TOR for a Compre hensive Public Transportation Component No. 1: Planning f Individual Consult TF / A2846 Post Limited 4,200.00 Completed 2018-05-15 2018-05-28 2018-05-20 2018-05-19 2018-05-27 2018-06-11 2018-06-17 2018-07-11 2018-07-17 2018-08-10 Plan for Ramallah and Al Bire or Sustainable Urban Growth ant Selection h Urban Area and Expand the RAB Mobility Plan to include Surda Abu Qush Town GZ-MDLF-63644-CS-INDV / H Component No. 1: Planning f Individual Consult iring of Local Coordinator -Be TF / A2846 Post Open 80,988.00 Signed 2018-05-25 2018-05-29 2018-06-23 2018-06-28 2018-07-14 2018-08-01 2018-08-18 2018-08-01 2019-03-16 or Sustainable Urban Growth ant Selection thlehem Urban Area GZ-MDLF-69297-CS-INDV / P repare a conceptual Spatial F Component No. 1: Planning f Individual Consult TF / A2846 Post Limited 7,680.00 Completed 2018-07-19 2018-07-15 2018-07-24 2018-07-18 2018-08-14 2018-07-22 2018-09-18 2018-07-22 2018-10-18 2018-10-07 ramework for the urban area or Sustainable Urban Growth ant Selection s targeted with ICUD project Page 3 GZ-MDLF-78343-CS-INDV / P Component No. 1: Planning f Individual Consult ersonnel Skills & Team Buildi TF / A2846 Post Limited 1,600.00 Completed 2018-12-01 2019-05-22 2018-12-06 2019-05-29 2018-12-27 2019-07-10 2019-01-31 2019-07-25 2019-03-02 2019-09-24 or Sustainable Urban Growth ant Selection ng Training GZ-MDLF-82654-CS-CDS / In Component No. 1: Planning f troductory Training Course in TF / A2846 Post Direct Selection Direct 11,645.00 Completed 2018-11-01 2018-10-16 2018-11-11 2019-01-15 2018-11-01 2019-03-12 2018-12-20 or Sustainable Urban Growth Transportation Planning GZ-MDLF-82673-CS-CDS / In Component No. 1: Planning f troductory Training Course in TF / A2846 Post Direct Selection Direct 16,440.00 Completed 2018-11-01 2018-10-16 2018-11-11 2019-01-15 2018-11-01 2019-03-12 2018-12-20 or Sustainable Urban Growth Urban Planning GZ-MDLF-153582-CS-CDS / I Component No. 1: Planning f Individual Consult TF / A2846 Post Direct 40,800.00 Completed 2020-02-02 2020-01-22 2020-02-12 2020-01-27 2020-03-04 2020-02-11 2020-04-08 2020-02-15 2020-10-05 2020-12-15 nstitutional Development Ad or Sustainable Urban Growth ant Selection viser GZ-MDLF-163998-CS-CDS / S Component No. 1: Planning f Individual Consult TF / A2846 Post Direct 56,920.00 Signed 2020-05-01 2020-05-27 2020-05-11 2020-06-02 2020-06-01 2020-06-02 2020-07-06 2020-06-15 2021-01-02 enior Urban Adviser or Sustainable Urban Growth ant Selection GZ-MDLF-185235-CS-INDV / Component No. 1: Planning f Individual Consult TF / A2846 Post Limited 15,200.00 Signed 2020-08-01 2020-07-29 2020-08-06 2020-09-02 2020-08-27 2020-08-30 2020-10-01 2020-09-06 2021-06-28 Hiring of Local Coordinator at or Sustainable Urban Growth ant Selection MOLG GZ-MDLF-185236-CS-INDV / Component No. 1: Planning f Individual Consult Communication and Public R TF / A2846 Post Open 5,535.00 Completed 2020-08-01 2020-07-29 2020-09-19 2020-11-05 2020-10-10 2020-11-19 2020-11-14 2020-11-22 2021-08-11 2021-11-08 or Sustainable Urban Growth ant Selection elation Specialist GZ-MDLF-164008-CS-QCBS / Component No. 1: Planning f Individual Consult Prepare the Spatial develop TF / A2846 Post Open 0.00 Canceled 2020-10-01 2020-11-19 2020-12-10 2021-01-14 2021-09-11 or Sustainable Urban Growth ant Selection ment Framework for Gaza Cit y GZ-MDLF-201721-CS-INDV / Component No. 1: Planning f Individual Consult TF / A2846 Post Limited 11,550.00 Completed 2020-11-04 2020-11-12 2020-11-09 2020-11-30 2020-11-30 2020-11-30 2021-01-04 2020-12-01 2021-07-03 2021-07-05 Junior Urban Planner @ MOL or Sustainable Urban Growth ant Selection G GZ-MDLF-222304-CS-INDV / Component No. 1: Planning f Individual Consult Practical Training on Market- TF / A2846 Post Direct 17,325.00 Completed 2021-03-15 2021-03-24 2021-03-25 2021-03-31 2021-04-15 2021-03-29 2021-05-20 2021-04-06 2021-11-16 2021-08-31 or Sustainable Urban Growth ant Selection Oriented Urban Planning GZ-MDLF-233801-CS-INDV / Technical Support and Capac Component No. 1: Planning f Individual Consult ity Building for the Pilot Proje TF / A2846 Post Limited 31,200.00 Signed 2021-06-01 2021-05-27 2021-06-06 2021-06-10 2021-06-27 2021-06-14 2021-08-01 2021-06-25 2022-04-28 or Sustainable Urban Growth ant Selection ct "Installation of Solar Photo voltaic Systems for Targeted Urban Areas in West Bank" GZ-MDLF-233803-CS-INDV / Technical Support and Capac Component No. 1: Planning f Individual Consult ity Building for the Pilot Proje TF / A2846 Post Limited 7,000.00 Signed 2021-06-01 2021-05-27 2021-06-06 2021-05-21 2021-06-27 2021-07-11 2021-08-01 2021-07-25 2022-01-28 or Sustainable Urban Growth ant Selection ct "Installation of Solar Photo voltaic Systems for Gaza Urb an Area GZ-MDLF-246031-CS-INDV / Component No. 1: Planning f Individual Consult TF / A2846 Post Limited 9,000.00 Terminated 2021-08-01 2021-08-16 2021-08-06 2021-08-17 2021-08-27 2021-09-15 2021-10-01 2021-09-21 2022-02-28 Institutional Development Co or Sustainable Urban Growth ant Selection nsultant GZ-MDLF-246045-CS-INDV / Component No. 1: Planning f Individual Consult Regional Urban Development TF / A2846 Post Limited 0.00 Canceled 2021-09-08 2021-09-13 2021-10-04 2021-11-08 2022-06-06 or Sustainable Urban Growth ant Selection Adviser-Gaza City Developm ent Plan GZ-MDLF-246048-CS-INDV / Component No. 1: Planning f Individual Consult Urban Development Expert - TF / A2846 Post Limited 10,500.00 Signed 2021-09-01 2021-10-14 2021-09-06 2021-10-17 2021-09-27 2021-10-26 2021-11-01 2021-11-01 2022-05-30 or Sustainable Urban Growth ant Selection Gaza City Development Plan GZ-MDLF-274844-CS-INDV / Component No. 1: Planning f Individual Consult TF / A2846 Post Direct 8,000.00 Signed 2022-02-10 2022-03-01 2022-02-16 2022-03-02 2022-02-23 2022-03-07 2022-03-05 2022-03-20 2022-06-03 Institutional Consultant Expe or Sustainable Urban Growth ant Selection rt GZ-MDLF-274851-CS-INDV / Component No. 1: Planning f Individual Consult Pending Impleme TF / A2846 Post Limited 0.00 2022-03-01 2022-03-04 2022-03-09 2022-03-19 2022-06-17 Hiring of a Graphic Designer or Sustainable Urban Growth ant Selection ntation GZ-MDLF-300103-CS-CDS / S Component No. 1: Planning f Individual Consult Pending Impleme enior Urban Development Ad TF / A2846 Post Direct 0.00 2022-06-30 2022-07-06 2022-07-09 2022-07-19 2022-10-17 or Sustainable Urban Growth ant Selection ntation viser - Phase Two GZ-MDLF-300415-CS-INDV / Component No. 1: Planning f Individual Consult Pending Impleme Urban development expert / TF / A2846 Post Direct 0.00 2022-06-30 2022-07-06 2022-07-27 2022-08-06 2022-11-04 or Sustainable Urban Growth ant Selection ntation Gaza city development plan- phase two GZ-MDLF-300418-CS-INDV / Component No. 1: Planning f Individual Consult Pending Impleme Local Coordinator for Bethleh TF / A2846 Post Direct 0.00 2022-06-30 2022-07-06 2022-07-09 2022-07-19 2022-10-17 or Sustainable Urban Growth ant Selection ntation em and Hebron Urban Areas Page 4