The World Bank Implementation Status & Results Report Cambodia Road Connectivity Improvement (P169930) Cambodia Road Connectivity Improvement (P169930) EAST ASIA AND PACIFIC | Cambodia | Transport Global Practice | IBRD/IDA | Investment Project Financing | FY 2021 | Seq No: 4 | ARCHIVED on 31-Jan-2022 | ISR49609 | Implementing Agencies: Kingdom of Cambodia, Ministry of Public Works and Transport, Ministry of Rural Development Key Dates Key Project Dates Bank Approval Date: 16-Jul-2020 Effectiveness Date: 26-Oct-2020 Planned Mid Term Review Date: 01-May-2024 Actual Mid-Term Review Date: Original Closing Date: 31-Jul-2027 Revised Closing Date: 31-Jul-2027 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The project development objective is to improve climate resilient road access to economic and human development facilities in targeted provinces. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component 1: National and Provincial Roads Improvement:(Cost $47.00 M) Component 2: Rural Roads Improvement:(Cost $47.00 M) Component 3: Institutional Development and Project Management:(Cost $6.00 M) Component 4: Contingent Emergency Response Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions Ministry of Public Works and Transport (MPWT) and Ministry of Rural Development (MRD), two implementing agencies, have achieved good progress during the first year of the project implementation. MPWT is targeting to complete procurement of three Output and Performance Based Road Contracts packages in June-July 2022. MRD is at the completion stage for the procurement process for the design and supervision consultant for rural roads. The Project Implementation Teams at two ministries are fully mobilized from relevant departments. The Project Steering Committee has been established comprising representatives of MRD, MPWT and Ministry of Economy and Finance. The next World Bank implementation support mission is planned in June 2022. 1/31/2022 Page 1 of 8 The World Bank Implementation Status & Results Report Cambodia Road Connectivity Improvement (P169930) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Substantial Substantial Moderate Macroeconomic Moderate Moderate Moderate Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Moderate Moderate Moderate Institutional Capacity for Implementation and Substantial Substantial Substantial Sustainability Fiduciary Substantial Substantial Substantial Environment and Social Substantial Substantial Substantial Stakeholders Moderate Moderate Moderate Other -- Moderate Moderate Overall Substantial Substantial Substantial Results PDO Indicators by Objectives / Outcomes Economic and human development facilities in the project area are made accessible for all seasons IN01080836 ►Facilities with improved climate resilient road access (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 75.00 Date 16-Jul-2020 04-Oct-2021 03-Dec-2021 31-Dec-2027 Measures cumulative number of critical economic and human development facilities that have become accessible all year round as a result of the project. Economic facilities include local markets; human Comments: development facilities include schools and health facilities. IN01080839 Market (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 15.00 Date 16-Jul-2020 04-Oct-2021 03-Dec-2021 31-Dec-2027 IN01080840 1/31/2022 Page 2 of 8 The World Bank Implementation Status & Results Report Cambodia Road Connectivity Improvement (P169930) Hospitals (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 10.00 Date 16-Jul-2020 04-Oct-2021 03-Dec-2021 31-Dec-2027 IN01080841 Schools (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 16-Jul-2020 04-Oct-2021 03-Dec-2021 31-Dec-2027 Travel time reduction along project-financed national and provincial roads IN01080837 ►Travel time reduction along project-financed national and provincial roads (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 Date 16-Jul-2020 04-Oct-2021 03-Dec-2021 31-Dec-2027 Measures average travel time saving after improvement of roads compared with baseline travel time along Comments: each project-financed national and provincial roads. People from the project area spend less time to reach the economic and human development facilities IN01080838 ►Direct beneficiaries with reduced travel time to reach the closet facilities (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 600,000.00 Date 16-Jul-2020 04-Oct-2021 03-Dec-2021 31-Dec-2027 Measures cumulative number of people with reduced travel time compared with before project condition Comments: by at least 10 minutes to reach the closest economic and human development facilities. Project-financed assets have a sustained resilience with service levels maintained under OPBRC IN01080830 ►Project-financed assets (road and bridges) have a sustained resilience with service level maintained under the OPBRC (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 100.00 Date 16-Jul-2020 04-Oct-2021 03-Dec-2021 31-Dec-2027 1/31/2022 Page 3 of 8 The World Bank Implementation Status & Results Report Cambodia Road Connectivity Improvement (P169930) Measures the share of project financed assets (NRs, PRs, rural roads, and bridges) transferred to Comments: maintenance phase under OPBRC after completion of road construction. The OPBRC has specific performance requirements and indicators for resilience. Intermediate Results Indicators by Components Component 1: National and Provincial Roads Improvement IN01080842 ►National and provincial roads improved with climate resilience measures (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 130.00 Date 16-Jul-2020 04-Oct-2021 03-Dec-2021 31-Dec-2027 Measures cumulative kilometers of NRs and PRs upgraded with climate resilience measures. Comments: Disaggregated data at both levels would be gathered, entered and monitored. IN01080846 ►Bridges repaired/upgraded with climate resilient measures (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 13.00 Date 16-Jul-2020 04-Oct-2021 03-Dec-2021 31-Dec-2027 Measures cumulative numbers of bridges along NRs and PRs upgraded with more climate resilient Comments: measures. IN01080849 ►Female employees with paid jobs under OPBRC for national and provincial roads (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 15.00 Date 16-Jul-2020 04-Oct-2021 03-Dec-2021 31-Dec-2027 Measures cumulative numbers of bridges along NRs and PRs upgraded with more climate resilient Comments: measures. IN01080852 ►Number of people with enhanced access to transportation services (Number (Thousand), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 190.00 Date 16-Jul-2020 04-Oct-2021 03-Dec-2021 31-Dec-2027 The number of people with enhanced access to transportation services is measured by multiplying the total number o Comments: 1/31/2022 Page 4 of 8 The World Bank Implementation Status & Results Report Cambodia Road Connectivity Improvement (P169930) IN01080855 ►Road safety assessment of the national and provincial roads (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 2.00 Date 16-Jul-2020 04-Oct-2021 03-Dec-2021 31-Dec-2027 Measures the occurrence of road safety assessment at design stage and at completion of works for NRs Comments: and PRs. Component 2: Rural Roads Improvement IN01080843 ►Rural roads upgraded with climate resilience measures (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 250.00 Date 16-Jul-2020 04-Oct-2021 03-Dec-2021 31-Dec-2027 Measures cumulative kilometers of rural roads upgraded with climate resilience measures. Comments: IN01080850 ►Road safety assessment of the rural roads (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 2.00 Date 16-Jul-2020 04-Oct-2021 03-Dec-2021 31-Dec-2027 Measures the occurrence of road safety assessment at design stage and at construction completion stage Comments: for rural roads. IN01080853 ►Female employees with paid jobs under OPBRC for rural roads (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 15.00 Date 16-Jul-2020 04-Oct-2021 03-Dec-2021 31-Dec-2027 Measures share of female employees with paid jobs in implementing OPBRC for rural roads. Comments: Component 3: Institutional Development and Project Management IN01080844 ►Rural Roads Accessibility and Financing Strategy developed (Yes/No, Custom) 1/31/2022 Page 5 of 8 The World Bank Implementation Status & Results Report Cambodia Road Connectivity Improvement (P169930) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 16-Jul-2020 04-Oct-2021 03-Dec-2021 31-Dec-2027 Measures the completion of the development of Rural Roads Financing Strategy and stakeholder Comments: consultations. IN01080847 ►Georeferenced data registered in the upgraded road crash database (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 16-Jul-2020 04-Oct-2021 03-Dec-2021 31-Dec-2027 Measures the completion of georeferenced data registration in the upgraded road crash database at Comments: MPWT funded by the project. IN01080851 ►Community members trained through road safety awareness campaigns (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 500.00 Date 16-Jul-2020 04-Oct-2021 03-Dec-2021 31-Dec-2027 Measures cumulative number of community members trained through road safety awareness campaigns Comments: provided by the project. IN01080854 Share of men out of total community members trained (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 70.00 IN01080856 ►MRD and MPWT staff trained on OPBRC, disagrgregated by gender (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 33.00 33.00 30.00 Date 16-Jul-2020 04-Oct-2021 03-Dec-2021 31-Dec-2027 Measures the aggregated number of MRD and MPWT staff trained to manage OPBRC for road Comments: construction and maintenance. IN01080857 Disaggregated by gender (number of female staff trained) (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 11.00 11.00 20.00 IN01080858 1/31/2022 Page 6 of 8 The World Bank Implementation Status & Results Report Cambodia Road Connectivity Improvement (P169930) ►Contractors' work force trained on ESHS, OHS and GBV/VAC Code of Conduct (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 100.00 Date 16-Jul-2020 04-Oct-2021 03-Dec-2021 31-Dec-2027 Measures the share of Contractor work force trained on ESHS, OHS and GBV/VAC Code of Conduct. Comments: Citizen engagement IN01080845 ►Grievances registered and addressed in a timely manner (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 16-Jul-2020 04-Oct-2021 03-Dec-2021 20-Dec-2027 Measures grievances registered raising from project activities and resolved within three months time, with Comments: gender disaggregated data. IN01080848 ►Beneficiaries expressing satisfaction with improved road condition and accessibility to facilities (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 70.00 Date 16-Jul-2020 04-Oct-2021 03-Dec-2021 31-Dec-2027 Measures the share of surveyed beneficiaries who expressed satisfaction with improved road condition Comments: and accessibility to facilities. Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P169930 IDA-67670 Effective USD 100.00 100.00 0.00 3.33 98.97 3.3% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P169930 IDA-67670 Effective 16-Jul-2020 05-Aug-2020 26-Oct-2020 31-Jul-2027 31-Jul-2027 1/31/2022 Page 7 of 8 The World Bank Implementation Status & Results Report Cambodia Road Connectivity Improvement (P169930) Cumulative Disbursements PBC Disbursement Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 1/31/2022 Page 8 of 8