PROCUREMENT PLAN Project information: Democratic Republic of Congo – Kinshasa Multisector Dev and Urban Res (P171141) Project Implementation agency: Ministry of Public Works – Cellule Infrastructures Date of the Procurement Plan: March 2020- Period covered by this Procurement Plan: March 2020 – Sept 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the DRC Procurement code of April 27, 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Standard Bidding Documents. All Standard Bidding Documents to be used for the project under NCB shall be found acceptable to the World Bank before their use during the implementation of the project. (b) Eligibility. Eligibility of bidders and acceptability of their goods and services shall not be based on their nationality and/or their origin, and association with a national firm shall not be a condition for participation in a bidding process. Therefore, except for the ineligibility situations referred to in paragraphs 1.10(a) (i) and 1.10(a) (ii) of the Procurement Guidelines, the eligibility of bidders must be based solely on their qualification, experience, and capacity to carry out the contract related to the specific bidding process. (c) Advertising and bid preparation time. Bidding opportunities shall be advertised at least in a national newspaper of wide circulation and on the website of the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics), and bidders should be given at least 30 days from the date of invitation to bid or the date of availability of the bidding documents, whichever is later. (d) Criteria for qualification of bidders. Qualification criteria shall only concern the bidder’s capability and resources to perform the contract, taking into account objective and measurable factors. Such criteria for qualification of bidders shall be clearly specified in the bidding documents. (e) Evaluation and contract award. A contract shall be awarded to the substantially responsive and lowest evaluated bidder provided that such bidder meets the qualification criteria specified in the bidding documents. No scoring system shall be allowed for the evaluation of bids, and no ‘blanket’ limitation to the number of lots which can be awarded to a bidder shall apply. The criteria for bid evaluation and the contract award conditions shall be clearly specified in the bidding documents; (f) Preferences. No preference shall be given to domestic/regional bidders, to domestically/regionally manufactured goods, and to bidders forming a joint venture with a national firm or proposing national subcontractors or carrying out economic activities in the territory of the recipient. (g) Publication of contract award. Information on all contract awards shall be published in at least a national newspaper of wide circulation or in the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) website. (h) Fraud and corruption. In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines. (i) Inspection and audit rights. In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy with respect to inspection and audit of accounts, records, and other documents relating to the bid submission and contract performance. (j) Requirement for administrative documents and/or tax clearance certificate. The bidding documents shall not require foreign bidders to produce any administrative or tax-related certificates before confirmation of awarding a contract. (k) Modifications of a signed contract. Any change in the contract amount which, singly or combined with all previous changes, increases the original contract amount by 15 percent or more must be done through an amendment to the signed contract instead of signing a new contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable Works: is not applicable PROCUREMENT Congo, Democratic Republic of : Kinshasa Multisector Development and Urban Resilience Project PLAN General Information Country: Congo, Democratic Republic of 2017-12-08 Bank’s Approval Date of the Original Procurement Plan: 2022-06-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171141 GPN Date: 2021-11-03 Project Name: Kinshasa Multisector Development and Urban Resilience Project Loan / Credit No: IDA / 68580, IDA / V3360, IDA / D7940 Urban Water Supply Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned A-1-1 / Construction et équip ement d'un complexe de trai Resilient Infrastructure and Open - Internationa Single Stage - Two E 47,200,000.0 71,429,146. 2019-11-1 IDA / 68580 A priori Appel d'offres Signé 2017-11-16 2018-01-25 2017-11-21 2018-01-26 2017-11-21 2018-03-13 2017-11-17 2018-01-30 2018-04-30 2018-03-31 2019-10-19 2018-05-21 2019-12-11 tement (captage, conduite d Services l nvelope 0 23 2 e refoulement, station de trai tement,) ZR-CEP-263793-CW-RFB / Fo urniture et pose des conduite Request for Bids - s de transferts et distribution Resilient Infrastructure and Open - Internationa Single Stage - One E Works French Civi 52,000,000.0 En cours d'e 2024-01-2 en aval de l’usine de traitem IDA / V3360 A priori Appel d'offres 0.00 2021-12-06 2022-01-03 2022-03-04 2022-04-01 2022-06-08 Services l nvelope l Law (French) SP 0 xécution 9 ent d’eau d’Ozone et achève D ment des travaux de pose de s canalisations de Kinshasa- Ouest ZR-CEP-263811-CW-RFB / Co Request for Bids - nstruction d'une ligne électri Resilient Infrastructure and Single Stage - One E Works French Civi En attente d 2023-11-2 que pour l'alimentation de la IDA / V3360 A posteriori Appel d'offres Open - National 2,500,000.00 0.00 2022-01-10 2022-01-25 2022-03-11 2022-04-10 2022-05-31 Services nvelope l Law (French) SP 'exécution 2 nouvelle station de pompage D et du réservoir de KISENSO ZR-PEMU-220163-CW-RFB / " Fourniture, pose des conduit es et construction de deux ré servoirs de stockage : Lot 1 : Fourniture et pose des Resilient Infrastructure and Open - Internationa Single Stage - One E 57,000,000.0 2023-06-0 IDA / V3360 A priori Appel d'offres 0.00 Annulé 2021-05-28 2021-06-02 2021-08-01 2021-08-22 2021-10-12 conduites de transferts et dis Services l nvelope 0 4 tribution aval Ozone Lot 2 : Construction de deux réservoirs (Gombele et Jelo- Binza) ZR-CEP-263838-CW-RFB / Fo Request for Bids - urniture et pose du réseau d Resilient Infrastructure and Open - Internationa Single Stage - One E Works French Civi 17,000,000.0 En attente d 2024-03-0 e distribution d'eau secondai IDA / V3360 A priori Appel d'offres 0.00 2022-03-10 2022-04-09 2022-06-08 2022-07-08 2022-09-16 Services l nvelope l Law (French) SP 0 'exécution 9 re et tertiaire pour permettre D la réalisation des brancheme nts particuliers ZR-PEMU-220190-CW-RFB / Réhabilitation, extension du r Resilient Infrastructure and Single Stage - One E 38,000,000.0 2022-05-0 IDA / V3360 A priori Appel d'offres Open - National 0.00 Annulé 2021-07-15 2021-07-20 2021-08-31 2021-09-21 2021-11-04 éseau et branchements socia Services nvelope 0 3 ux dans la zone ( plusieurs lo ts) Request for Bids - ZR-CEP-266776-CW-RFB / Co Resilient Infrastructure and Open - Internationa Single Stage - One E Works French Civi 12,500,000.0 En attente d 2024-01-2 nstruction de deux réservoirs IDA / V3360 A priori Appel d'offres 0.00 2022-02-04 2022-03-04 2022-05-03 2022-05-31 2022-08-07 Services l nvelope l Law (French) SP 0 'exécution 9 de stockage à DJELO BINZA e D t à KISENSO ZR-CEP-289256-CW-RFQ / Tr Request for Quota Resilient Infrastructure and Single Stage - One E En attente d 2022-10-0 avaux de sectorisation d'une IDA / V3360 A posteriori Demande de prix Limited tions (Non Bank-S 116,000.00 0.00 2022-06-04 2022-07-28 Services nvelope 'exécution 6 zone pilote du réseau de dist PD) ribution d'eau ZR-PEMU-220195-CW-CP / C onstruction de la station pilot Resilient Infrastructure and Pratiques commer Open - Internationa Single Stage - Two E 2022-12-0 IDA / V3360 A posteriori 3,500,000.00 0.00 Annulé 2021-09-15 2021-09-20 2021-11-19 2022-01-09 2022-02-08 e de traitement des boues de Services ciales l nvelope 5 vidange sur le site de l’ITA M ombele GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CEP-263837-GO-RFB / Fo urniture des compteurs et kit s de matériels de brancheme nt particulier pour 50 000 ab Resilient Infrastructure and Open - Internationa Single Stage - One E En cours d'ex IDA / V3360 A priori Appel d'offres 10,000,000.00 0.00 2022-01-10 2022-02-09 2022-04-10 2022-05-10 2022-07-19 2023-07-19 onnés Services l nvelope amen - Lot 1 : Fourniture de 50 000 compteurs - Lot 2 : Fourniture des kits d e matériels de branchement particulier ZR-CEP-263854-GO-RFQ / Ac quisition des fournitures de b Single Stage - One E En attente d' IDA / V3360 Project Management A posteriori Demande de prix Limited 14,800.00 0.00 2021-12-11 2022-01-21 2023-01-21 ureau, petits matériels de bu nvelope exécution reau et consommables infor matiques ZR-CEP-263856-GO-RFQ / Re Single Stage - One E En attente d' production et reliure des DA IDA / V3360 Project Management A posteriori Demande de prix Limited 20,000.00 0.00 2021-12-11 2022-01-21 2023-01-21 nvelope exécution O et autres rapports ZR-CEP-263866-GO-RFQ / Ac quisition des mobiliers de bur Single Stage - One E En attente d' IDA / V3360 Project Management A posteriori Demande de prix Limited 61,750.00 0.00 2021-12-25 2022-02-19 2022-08-18 eau (tables, chaise de burea nvelope exécution u et autres accessoires) pour la CEP-O ZR-PEMU-220203-GO-RFQ / Fourniture des matériels info Resilient Infrastructure and Single Stage - One E rmatiques (ordinateurs, impri IDA / V3360 A posteriori Demande de prix Limited 100,000.00 0.00 Annulé 2021-06-26 2021-08-21 2022-01-18 Services nvelope mantes et accessoires) pour l es micro-caisses de la REGID ESO ZR-CEP-289146-GO-RFQ / Ac quisition de matériel informa Resilient Infrastructure and Single Stage - One E En attente d' IDA / V3360 A posteriori Demande de prix Limited 113,500.00 0.00 2022-05-31 2022-07-22 2022-08-31 tique en trois (03) lots au bé Services nvelope exécution néfice de la REGIDESO et de l a CEP-O Page 1 ZR-CEP-289179-GO-RFQ / Ac quisition d'une plateforme (lo Resilient Infrastructure and Single Stage - One E En attente d' giciel, licence et déploiement IDA / V3360 A posteriori Demande de prix Limited 25,000.00 0.00 2022-05-31 2022-07-11 2022-09-09 Services nvelope exécution ) pour le paiement par mobil e des factures d'eau de la RE GIDESO ZR-CEP-289182-GO-RFQ / Im pression et affichage des gra nds panneaux, impression de Resilient Infrastructure and Single Stage - One E En attente d' IDA / V3360 A posteriori Demande de prix Limited 84,500.00 0.00 2022-06-04 2022-07-15 2022-07-25 s flyers pour la sensibilisation Services nvelope exécution et communication sur l’applic ation pour le paiement par m obile des factures REGIDESO ZR-CEP-289199-GO-RFQ / Ac quisition d'un paquet de 300 Resilient Infrastructure and Single Stage - One E En attente d' 000 SMS pour la relance des IDA / V3360 A posteriori Demande de prix Limited 27,000.00 0.00 2022-06-04 2022-07-13 2022-07-28 Services nvelope exécution abonnés en retard de paieme nt de facture de consommati on ZR-CEP-289229-GO-RFQ / Ac quisition et installation de m atériel de communication (tél Resilient Infrastructure and Single Stage - One E En attente d' IDA / V3360 A posteriori Demande de prix Limited 32,000.00 0.00 2022-05-31 2022-07-11 2022-08-10 évisions, roll-up, etc.) pour la Services nvelope exécution poursuite de l'amélioration d e l'image des 40 secteurs de la REGIDESO ZR-CEP-289233-GO-RFB / Ac quisition et installation des é Resilient Infrastructure and Single Stage - One E En attente d' quipements photovoltaïques IDA / V3360 A posteriori Appel d'offres Open - National 980,000.00 0.00 2022-05-30 2022-06-04 2022-07-19 2022-08-03 2022-08-22 2023-02-18 Services nvelope exécution pour 40 secteurs à Kinshasa et centre informatique centra l de la REGIDESO ZR-CEP-289250-GO-RFQ / Ac quisition du logiciel de gestio Resilient Infrastructure and Single Stage - One E En attente d' n et archivage y compris la f IDA / V3360 A posteriori Demande de prix Limited 89,500.00 0.00 2022-05-31 2022-07-11 2022-09-09 Services nvelope exécution ormation des utilisateurs pou r la numérisation des manuel s de procédures NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PEMU-214701-NC-DIR / R enouvellement du contrat de nettoyage et entretien des b Resilient Infrastructure and Passation de marc ureaux de la CEP-O/REGIDES IDA / 68580 A posteriori Direct 20,880.00 28,880.00 Signé 2021-01-22 2020-12-31 2021-01-23 2020-12-31 2021-01-25 2020-12-31 2021-06-30 Services hé de gré à gré O et de ses alentours imméd iats avec le prestataire GEN ERAL INVESTMENT SERVICES (GIS) au 30 juin 2021. ZR-PEMU-214702-NC-DIR / R enouvellement du contrat d e service de Gardiennage et l Resilient Infrastructure and Passation de marc a sécurisation des bureaux d IDA / 68580 A posteriori Direct 25,800.00 25,800.00 Signé 2021-01-22 2020-12-31 2021-01-23 2020-12-31 2021-01-25 2020-12-31 2021-06-30 Services hé de gré à gré e la CEP-O/REGIDESO et de s es alentours immédiats avec le prestataire NEW PROTECT ION au 30 juin 2021 ZR-CEP-263857-NC-RFQ / En Single Stage - One E tretien & réparation des véhi IDA / V3360 Project Management A posteriori Demande de prix Limited 16,000.00 15,665.00 Signé 2021-12-11 2021-12-29 2022-01-21 2022-03-01 2023-01-21 nvelope cules de la CEP-O ZR-CEP-263860-NC-RFQ / En Single Stage - One E En cours d'ex tretien & réparation du Grou IDA / V3360 Project Management A posteriori Demande de prix Limited 7,800.00 0.00 2021-12-11 2022-01-06 2022-01-21 2023-01-21 nvelope écution pe Électrogène de la CEP-O ZR-CEP-263861-NC-RFQ / En tretien et réparation matériel s, équipements de bureau & Single Stage - One E En attente d' maintenance bâtiment (main IDA / V3360 Project Management A posteriori Demande de prix Limited 6,000.00 0.00 2021-12-11 2022-01-21 2023-01-21 nvelope exécution tenance split, électricité, plo mberie, matériels informatiq ues, frais maintenance bâtim ent, etc.) ZR-CEP-289037-NC-RFQ / Re censement des clients de la Resilient Infrastructure and Single Stage - One E En attente d' REGIDESO dans la ville de Ki IDA / V3360 A posteriori Demande de prix Open - National 575,000.00 0.00 2022-05-14 2022-06-29 2023-04-25 Services nvelope exécution nshasa par 110 Agents recen seurs (dont 100 recenseurs e t 10 Superviseurs) ZR-CEP-289323-NC-DIR / Re crutement par entente direct e de la firme ITEC pour l'acqu Resilient Infrastructure and Passation de marc En attente d' IDA / V3360 A posteriori Direct 300,000.00 0.00 2022-05-13 2022-05-15 2022-06-13 2022-09-21 isition du Cash management, Services hé de gré à gré exécution son intégration dans le modu le Trésorerie de l’ERP et form ation des utilisateurs finaux ZR-CEP-263851-NC-RFQ / As surance médicale en faveur Single Stage - One E IDA / V3360 Project Management A posteriori Demande de prix Limited 48,000.00 0.00 Annulé 2021-12-04 2022-01-09 2023-01-09 du personnel de la CEP-O, de nvelope janvier à décembre 2022 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual B-9-4-1 / Recrutement d'un c Sélection fondée s Resilient Infrastructure and Open - Internationa onsultant (firme) pour le cont IDA / 68580 A priori ur la qualité et le 2,500,000.00 5,285,518.32 Signé 2017-12-11 2018-01-10 2017-12-12 2017-12-14 2018-01-11 2017-12-15 2017-01-24 2017-12-18 2018-01-12 2018-01-22 2018-01-13 2018-02-26 2018-01-15 2020-02-26 Services l rôle et surveillance des trava coût ux d'AEP à KIN ZR-CEP-263798-CS-QCBS / C ontrôle et surveillance des tr avaux de pose des conduites Sélection fondée s Resilient Infrastructure and Open - Internationa En cours d'exame de transferts et distribution e IDA / V3360 A priori ur la qualité et le 2,600,000.00 0.00 2021-12-06 2021-12-16 2022-01-29 2022-02-26 2022-03-28 2022-05-02 2022-06-06 2024-03-27 Services l n n aval de l’usine de traiteme coût nt d’eau d’Ozone et achèvem ent des travaux de pose des canalisations de Kinshasa-Ou est Page 2 ZR-CEP-263803-CS-CQS / Mi se en œuvre du PAR des trav aux de pose des conduites d Sélection fondée s e transferts et distribution en Resilient Infrastructure and En cours d'exame IDA / V3360 A posteriori ur les qualification Open - National 75,000.00 0.00 2021-12-06 2022-03-11 2021-12-27 2022-02-09 2022-03-11 2022-04-15 2022-06-14 aval de l’usine de traitement Services n s des consultants d’eau d’Ozone et achèvemen t des travaux de pose des ca nalisations de Kinshasa-Oues t, y compris indemnisations d es PAP ZR-CEP-263813-CS-QCBS / C ontrôle et surveillance des tr avaux de construction de troi Sélection fondée s s réservoirs à DJELO BINZA, à Resilient Infrastructure and Open - Internationa En cours d'exame IDA / V3360 A priori ur la qualité et le 1,000,000.00 0.00 2021-12-13 2021-12-23 2022-02-05 2022-03-05 2022-04-04 2022-05-05 2022-06-09 2024-01-30 GOMBELE et à KISENSO et d' Services l n coût une ligne électrique pour l'ali mentation de la nouvelle stat ion de pompage et du réserv oir de KISENSO ZR-CEP-263839-CS-QCBS / C ontrôle et surveillance des tr Sélection fondée s avaux de pose du réseau de Resilient Infrastructure and Open - Internationa En attente d'exéc IDA / V3360 A priori ur la qualité et le 1,020,000.00 0.00 2022-01-10 2022-01-20 2022-03-05 2022-04-02 2022-05-02 2022-07-01 2022-08-21 2024-04-12 distribution d'eau secondaire Services l ution coût et tertiaire pour permettre la réalisation des branchement s particuliers ZR-CEP-263847-CS-CQS / Mi se en œuvre du PAR pour la pose du réseau de distributio Sélection fondée s Resilient Infrastructure and En attente d'exéc n d'eau secondaire et tertiair IDA / V3360 A posteriori ur les qualification Open - National 75,000.00 0.00 2022-03-07 2022-03-28 2022-05-27 2022-06-26 2022-08-25 2022-10-24 Services ution e pour permettre la réalisatio s des consultants n des branchements particuli ers, y compris la station de p ompage amont ZR-CEP-289021-CS-CQS / Co nsultant (firme) chargé d'assi ster la REGIDESO à l'élaborat Sélection fondée s Resilient Infrastructure and En cours d'exame ion et la mise en œuvre d'un IDA / V3360 A posteriori ur les qualification Open - National 200,000.00 0.00 2022-05-13 2022-04-18 2022-05-27 2022-07-10 2022-07-24 2022-08-08 2022-10-07 Services n Plan de Gestion Environneme s des consultants ntale et Sociale des Ouvrage s (PGESO) en phase d'exploit ation ZR-CEP-289029-CS-CQS / Co nsultant (firme) pour l'élabor ation du dossier d'appel à pr Sélection fondée s Resilient Infrastructure and Open - Internationa En cours d'exame opositions des travaux de co IDA / V3360 A posteriori ur les qualification 350,000.00 0.00 2022-05-13 2022-04-19 2022-05-27 2022-07-10 2022-07-24 2022-08-21 2023-04-18 Services l n nstruction d'une station de tr s des consultants aitement de boues de vidang es (STBV) et l'appui à l'évalu ation des propositions ZR-CEP-289303-CS-CQS / Co Sélection fondée s nsultant (firme) chargé de la Resilient Infrastructure and En cours d'exame IDA / V3360 A posteriori ur les qualification Open - National 25,000.00 0.00 2022-05-13 2022-05-24 2022-06-03 2022-07-13 2022-07-27 2022-07-30 2022-08-09 formation des Directeurs de l Services n s des consultants a REGIDESO sur le Managem ent et le Leadership ZR-CEP-289333-CS-CQS / Co nsultant (firme) chargé du dé Sélection fondée s veloppement d'un projet de r Resilient Infrastructure and Open - Internationa En attente d'exéc IDA / V3360 A posteriori ur les qualification 300,000.00 0.00 2022-05-13 2022-05-27 2022-07-10 2022-07-20 2022-08-08 2022-12-06 echerche systématique de fui Services l ution s des consultants tes par le recours à des prest ations externes sur la base d e contrats de performance ZR-CEP-O-262369-CS-QCBS / Contrôle et surveillance des t Sélection fondée s Resilient Infrastructure and Open - Internationa ravaux de la station pilote d IDA / V3360 A priori ur la qualité et le 800,000.00 0.00 Annulé 2022-02-28 2022-03-21 2022-05-04 2022-06-01 2022-07-01 2022-08-05 2022-09-09 2024-05-01 Services l e traitement des boues de vi coût dange sur le site de l’ITA MO MBELE ZR-CEP-O-262368-CS-QCBS / Contrôle et surveillance des t Sélection fondée s Resilient Infrastructure and Open - Internationa ravaux de construction de la IDA / V3360 A priori ur la qualité et le 1,000,000.00 0.00 Annulé 2021-12-13 2022-01-03 2022-02-16 2022-03-16 2022-04-15 2022-05-20 2022-06-24 2024-02-14 Services l 3ème phase de l'usine de tra coût itement d'eau au site Ozone/ Kinshasa-Ouest INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CEP-274095-CS-INDV / R ecrutement par ED de Mr PEP IDA / D7940 Project Management A posteriori Individuel Direct 18,000.00 15,450.00 Signé 2022-01-31 2022-01-27 2022-01-31 2022-02-17 2022-02-01 2022-02-18 2022-02-01 2022-02-21 2023-02-01 O MAKE Israël, Caissier de la CEP-O/REGIDESO ZR-CEP-288965-CS-CDS / Re crutement par entente direct e du Groupement IGIP/ANTEA Group/VSI Afrique pour le co Sélection de cons Resilient Infrastructure and En cours d'exécut ntrôle et la surveillance des t IDA / V3360 A priori ultants par entent Direct 3,500,000.00 0.00 2022-05-13 2022-06-16 2022-05-23 2022-06-22 2022-06-17 2024-08-05 Services ion ravaux de construction des p e directe hases 2 et 3 de l'usine d'Ozo ne à Kinshasa-Ouest ainsi qu e des travaux en cours d'ach èvement de la Phase 1 ZR-CEP-289275-CS-INDV / C onsultant individuel pour la p réparation d'un plan pour la Resilient Infrastructure and En attente d'exéc mise en œuvre d'un program IDA / V3360 A posteriori Individuel Open 10,000.00 0.00 2022-05-13 2022-07-01 2022-07-11 2022-07-23 2022-08-02 Services ution me de diversité en termes de genre et sensibilisation du pe rsonnel REGIDESO sur les as pects genre ZR-CEP-289299-CS-INDV / C onsultant individuel chargé d e la révisitation du code d’ét Resilient Infrastructure and En cours d'exame hique du travailleur en renfor IDA / V3360 A posteriori Individuel Open 10,000.00 0.00 2022-05-13 2022-05-24 2022-07-06 2022-07-16 2022-07-28 2022-08-27 Services n çant les aspects sur les viole nces basées sur le genre (VB G) et de la sensibilisation des travailleurs de la REGIDESO ZR-CEP-289328-CS-INDV / C onsultant individuel pour la mise à jour du site web de la Resilient Infrastructure and En cours d'exame REGIDESO et formation des IDA / V3360 A posteriori Individuel Open 10,000.00 0.00 2022-05-13 2022-05-07 2022-07-06 2022-07-16 2022-07-28 2022-08-17 Services n webmasters, en vue de perm ettre la publication des docu ments généraux financiers a ccessibles au grand public Page 3 ZR-PEMU-220213-CS-CDS / Sélection de cons Resilient Infrastructure and Appui à la réforme de la REGI IDA / V3360 A posteriori ultants par entent Direct 1,000,000.00 0.00 Annulé 2021-04-15 2021-04-25 2021-06-14 2022-06-09 Services DESO (COPIREP) e directe ZR-CEP-299852-CS-CDS / Re crutement par Entente direct e de Monsieur Achille BONDO Sélection de cons Resilient Infrastructure and En cours d'exécut pour la mission d'Assistance IDA / V3360 A posteriori ultants par entent Direct 30,500.00 0.00 2022-06-16 2022-06-15 2022-06-19 2022-06-22 2022-08-21 Services ion technique à la REGIDESO et e directe à la CEP-O pour l’élaboration d’un contrat de performance entre l’État et la REGIDESO ZR-CEP-266781-CS-CDS / Re crutement par Entente direct e de Monsieur Achille BONDO Sélection de cons Resilient Infrastructure and pour la mission d'Assistance IDA / V3360 A posteriori ultants par entent Direct 15,000.00 0.00 Annulé 2021-12-20 2022-01-20 2021-12-30 2022-02-18 2022-03-20 Services technique à la REGIDESO et e directe à la CEP-O pour l’élaboration d’un contrat de performance entre l’État et la REGIDESO ZR-PEMU-251401-CS-INDV / Recrutement d'un Assistant e IDA / D7940 Project Management A posteriori Individuel Limited 30,000.00 0.00 Annulé 2021-09-03 2021-06-29 2021-09-08 2021-09-09 2021-09-10 2022-09-10 n Suivi-Évaluation de la CEP- O/REGIDESO ZR-CEP-301493-CS-INDV / R ecrutement par ED de Monsi En cours d'exame eur Patrick YAMBUYA au post IDA / D7940 Project Management A posteriori Individuel Direct 66,000.00 0.00 2022-06-27 2022-06-27 2022-06-27 2022-06-28 2022-06-29 2023-06-29 n e de Responsable de la Passa tion des Marchés de la CEP-O ZR-CEP-301492-CS-INDV / R ecrutement d'un Consultant En attente d'exéc IDA / D7940 Project Management A posteriori Individuel Open 60,000.00 0.00 2022-07-25 2022-09-03 2022-09-24 2022-10-14 2023-10-14 pour occuper le poste d'Ingé ution nieur des Opérations à la CEP -O ZR-CEP-301491-CS-INDV / R ecrutement d'un Consultant En attente d'exéc IDA / D7940 Project Management A posteriori Individuel Open 60,000.00 0.00 2022-07-25 2022-09-03 2022-09-24 2022-10-14 2023-10-14 pour occuper le poste de Spé ution cialiste en Passation des Mar chés à la CEP-O Page 4