PROCUREMENT PLAN General 1. Project Information a. Country: Federal Republic of Somalia b. Project Name: Water For Agro-Pastoral and Reselience Productivity c. Project Number: P167826 d. Total Finance: USD 5 Million 2. Project Implementation Agency: South West State of Somalia 3. Date of Project Plan: October 2018 4. Period Covered by this Procurement: January 2019 – June 2020 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Document: The Bank’s standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified into Procurement Plan tables in STEP III. National Procurement Arrangements: Not applicable IV. Prequalification: Not applicable V. Leased Assets: Not Applicable 1 VI. Procurement of Second hand Goods: Not Applicable VII. Domestic Preference: Not Applicable VIII. Hands on Expanded Implementation Support (HEIS): Not Applicable IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Procurement Approaches and Method (US$ millions) Thresholds for Procurement Approaches and Methods (US$ millions)– Goods, Works, and Non-Consulting Services Category Prior Open Open Request for Review Internation Nation Quotation (US$ al al (RfQ) millions) Works all ≥ 5.0 < 5.0 ≤ 0.2 Goods, IT, and all ≥ 0.5 < 0.5 ≤ 0.1 non-consulting services Thresholds for Procurement Approaches and Methods (US$, millions) – Consulting Services Category Prior Short List of National Consultants Review Consulting Engineering and (US$, Services Construction millions) Supervision Consultants n.a n.a. all (Firms) Individual all n.a. n.a. Consultants 2 South West Procurement Plan XI. Packages for Goods, Works and Non-Consulting Services (At Negotiations – to be entered in STEP) R Contract Estimate Revie Market Sel Eval Procure Preq Do Expected Expected ef Description d Cost w by Approac ecti uati ment ualif mes date of date of . (US$) Bank h (Open- on on Process icati tic bid/ Contract N (Prior National Me Opti (Single on Pref proposal Signatur o / / Limited tho ons stage- (Yes/ ere opening e Post) etc.) d (BA single No) nce (RF FO envelop (Yes P, Rat e etc.) /No) RF ed B, Crit RF eria Q etc. etc ) .) GOODS Low est Single G Purchase of 5 Open Eval stage 02/Mar/20 02/Apr/20 $175,000 Prior RFB N/A N/A 1 vehicles National uate One- 19 19 d Envelop Cost Low Office Equipment est Singe (Laptops, G Eval stage 04/Mar/20 04/Apr/20 Desktops, $30,000 Prior Limited RFQ N/A N/A 2 Projector, Printers uate One - 19 19 and accessories) d Envelop Cost 3 Low est Single G Eval Stage 05/May/20 05/Jun/201 GIS Equipment $25,000 Prior Limited RFQ N/A N/A 3 uate One- 19 9 d Envelop Cost Low est Single Hydrological G Eval Stage 15/Oct/20 16/Nov/20 Water Monitoring $12,000 Prior Limited RFQ N/A N/A 4 Tools uate One- 19 19 d Envelop Cost Low est Single G Open Eval Stage 21/Mar/20 22/Apr/20 Vehicle Fuels $80,000 Prior RFQ N/A N/A 6 National uate One- 19 19 d Envelop Cost Low est Single G Office furniture Eval Stage 12/Jun/202 13/Jul/202 $30,000 Prior Limited RFQ N/A N/A 7 (Chairs, Tables, ) uate One- 0 0 d Envelop Cost Total Goods $352,000 WORKS Construction of Low Sand Dams/Sub- est Single W surface Dams Open Eval stage – 09/Nov/20 10/Dec/20 $90,000 Prior RFQ N/A N/A 1 National uate one 19 19 d envelope Cost 4 Construction of Low Earth Dams est Single W Open Eval stage – 01/Oct/20 02/Nov/20 $90,000 Prior RFQ N/A N/A 2 National uate one 19 19 d envelope Cost Construction/Reh Low abilitation of 10 est Single W Berkads Open Eval stage – 01/Sep/20 01/Oct/20 $42,000 Prior RFQ N/A N/A 3 National uate one 19 19 d envelope Cost Rehabilitation of Low Boreholes/Shallow est Single W Wells Open Eval stage – 18/Aug/20 19/Sep/20 $50,000 Prior RFQ N/A N/A 4 National uate one 19 19 d envelope Cost Office Low Construction/Reh est Single W abilitation Open Eval stage – 01/Aug/20 01/Sep/20 $70,000 Prior RFQ N/A N/A 5 National uate one 19 19 d envelope Cost Total Works $342,000 Non -Consulting Services Total Non- Consultant Service Consulting Services 5 Re Contract Estimate Review Market Selecti Shortli Expected Expected f Description d Cost by Bank Approach on sting Date of Date of No (US$) (Prior/Po (Open- Metho (Yes/N Bid Contract . st) National/ d o) Proposal Signatur Limited (QCBS Opening e etc.) , LCBCS , QBS, DS Site selection, geophysical surveying, Open – 16/Mar/201 15/Apr/20 C1 100,000 Prior CQS N/A contracting and National 9 19 engineering support Develop GIS map Prior Open - CQS 08/Aug/20 C2 for potential sites 20,000 N/A 08/Jul/2019 National 19 creation of village livelihood development Open - 13/May/202 10/Jun/202 C3 plans & water 500,000 Prior QCBS N/A International 0 0 budgets implement rural development policies and laws Open 12/Feb/20 C4 to regulate sector 50,000 Prior CQS N/A 15/Jan/2020 and ensure National 20 sustainability technical assistance agency Open 22/Feb/202 19/Mar/20 C5 for training 60,000 Prior CQS N/A assessment, National 0 20 selecting, training 6 and monitoring field service support, acquisition and application of geo-spatial Open – 01/Mar/202 01/Apr/20 C6 imagery for 20,000 Prior CQS N/A before and after National 0 20 satelite photos Procurement 05/Feb/20 C7 50,000 Prior Open INDV N/A 05/Jan/2019 Specialist 19 Open INDV 05/Feb/20 C8 Finance Specialist 50,000 Prior N/A 05/Jan/2019 19 Open INDV 10/Feb/201 10/Mar/20 C9 Project Engineer 72,000 Prior N/A 9 19 C1 Open INDV 31/Oct/20 2 Site Engineers 21,000 Prior N/A 01/Oct/2019 0 19 Total $943,000 Consulting Services $1,637,0 Grand Total 00 7 PROCUREMENT Somalia : Somalia - Water for Agro-pastoral Productivity and Resilience PLAN General Information Country: Somalia 2020-02-18 Bank’s Approval Date of the Original Procurement Plan: 2022-06-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167826 GPN Date: Project Name: Somalia - Water for Agro-pastoral Productivity and Resilience Loan / Credit No: IDA / D4970 Puntland Ministry of Planning, Economic Development and International Cooperation Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SO-MOPIC - PL-174463-CW-R Component 4: Project Manag FB / Construction of Ministry Single Stage - One E 2021-03-1 IDA / D4970 ement, M & E, Knowledge M Prior Request for Bids Open - National 285,000.00 341,801.64 Signed 2020-05-24 2020-10-16 2020-05-29 2020-10-19 2020-07-10 2020-11-25 2020-08-09 2021-01-04 2020-09-13 2021-01-12 of Planning, Economic Develo nvelope 2 anagement and Learning pment and International Coo peration offices. SO-MOPIC - PL-178126-CW-R Component 2. Institutional a Request for Quota Single Stage - One E 2021-02-1 FQ / Rehabilitation and Exten IDA / D4970 Prior Open - National 180,000.00 179,968.80 Completed 2020-06-26 2020-08-21 2020-08-21 2020-10-28 nd Capacity Development tions nvelope 7 ding of MoEACC Office in Gar owe SO-MOPIC - PL-182498-CW-R Component 4: Project Manag Request for Quota Single Stage - One E 2021-03-0 FQ / Construction of MoLAH C IDA / D4970 ement, M & E, Knowledge M Prior Limited 50,000.00 49,139.25 Completed 2020-07-09 2020-09-18 2020-09-03 2020-10-14 tions nvelope 2 onference Hall anagement and Learning SO-MOPIC - PL-178198-CW-R Component 4: Project Manag FQ / Rehabilitation of Meetin Request for Quota Single Stage - One E 2021-02-1 IDA / D4970 ement, M & E, Knowledge M Prior Limited 10,000.00 9,853.76 Completed 2020-06-25 2020-09-14 2020-08-20 2020-10-07 g Room at the Puntland Minis tions nvelope 6 anagement and Learning try of Energy, Mineral and W ater (MoEMW) SO-MOPIC - PL-214242-CW-R Component 1: Support the D FQ / Construction of Subsurfa Request for Quota Single Stage - One E 2021-09-2 IDA / D4970 evelopment of Multiple Use Prior Limited 101,982.95 145,803.65 Signed 2021-01-30 2021-03-11 2021-03-27 2021-04-22 ce Dam in Rabable Village, N tions nvelope 3 Water Sources ugaal Region, Puntland, Som alia SO-MOPIC - PL-218499-CW-R FQ / Rehabilitation of four Co Component 2. Institutional a Request for Quota Single Stage - One E 2021-10-2 mmunity Centers and Rangel IDA / D4970 Prior Limited 135,000.00 135,288.00 Signed 2021-03-04 2021-07-27 2021-04-29 2021-08-17 nd Capacity Development tions nvelope 6 and in Meeladeen, Raydable, Lasodawoco and Xamxama. SO-MOPIC - PL-232616-CW-R Component 1: Support the D Request for Quota FQ / Construction of Arc Grav Request for Quota Single Stage - One E 2022-01-0 IDA / D4970 evelopment of Multiple Use Prior Limited tions (Non Bank-S 120,795.94 146,305.59 Signed 2021-05-13 2021-06-13 2021-07-08 2021-07-19 ity Dam in Ceel Dahir Village, tions nvelope 4 Water Sources PD) Bari Region, Puntland Somali a SO-MOPIC - PL-256301-CW-R Component 1: Support the D Request for Quota FQ / Rehabilitation of Xagar b Request for Quota Single Stage - One E 2022-06-1 IDA / D4970 evelopment of Multiple Use Prior Limited tions (Non Bank-S 75,939.19 0.00 Canceled 2021-10-21 2021-12-16 orehole in Xagar Village, Bari tions nvelope 4 Water Sources PD) Region, Puntland Somalia SO-MOPIC - PL-257543-CW-R Request for Bids - Component 1: Support the D FB / Construction of an Impro Single Stage - One E Small Works SPD 2022-08-0 IDA / D4970 evelopment of Multiple Use Prior Request for Bids Open - National 221,941.28 0.00 Canceled 2021-10-20 2021-11-05 2021-10-25 2021-12-06 2022-01-05 2022-02-09 ved Haffir Dam at Carmoyiin nvelope (1 envelope proce 8 Water Sources Village, Karkaar Region, Puntl ss) and State of Somalia SO-MOPIC - PL-258569-CW-R Component 3: Supporting Su Request for Quota FQ / Rehabilitation of 4 regio stainable Land Management Request for Quota Single Stage - One E 2022-06-2 IDA / D4970 Prior Limited tions (Non Bank-S 125,371.84 94,901.50 Signed 2021-10-28 2021-10-21 2021-12-23 2021-11-29 nal veterinary offices in (Boss and Livelihoods Developmen tions nvelope 1 PD) aso, Qardo, Dhahar and Garo t Around Water Points we HQ) SO-MOPIC - PL-258570-CW-R Component 3: Supporting Su Request for Bids - FB / Construction of 3 veterin stainable Land Management Single Stage - One E Small Works SPD 2022-08-1 ary clinics and 1 Regional Vet IDA / D4970 Prior Request for Bids Open - National 413,648.63 404,861.40 Signed 2021-10-25 2021-11-05 2021-10-30 2021-11-12 2021-12-11 2021-12-20 2022-01-10 2022-01-12 2022-02-14 2022-01-15 and Livelihoods Developmen nvelope (1 envelope proce 3 erinary office in Garowe, Ufe t Around Water Points ss) yn, Baargaal, and Aluula SO-MOPIC - PL-259747-CW-R FQ / Construction of Arc Grav Component 1: Support the D Request for Quota Request for Quota Single Stage - One E 2022-06-2 ity Dam in Barookhle Village, IDA / D4970 evelopment of Multiple Use Prior Limited tions (Non Bank-S 142,861.04 141,958.25 Signed 2021-11-05 2021-11-23 2021-12-31 2021-12-20 tions nvelope 9 Armo District, Bari Region, Pu Water Sources PD) ntland State of Somalia SO-MOPIC - PL-260672-CW-R Component 1: Support the D Request for Quota FQ / Construction of Arc Grav Request for Quota Single Stage - One E 2022-07-0 IDA / D4970 evelopment of Multiple Use Prior Limited tions (Non Bank-S 74,912.25 94,032.00 Signed 2021-11-08 2021-11-23 2022-01-03 2021-12-20 ity Dam near Caluula Town, tions nvelope 2 Water Sources PD) Bari Region, Puntland State o f Somalia SO-MOPIC - PL-263230-CW-R Component 1: Support the D Request for Quota FQ / Construction of an Impro Request for Quota Single Stage - One E 2022-07-1 IDA / D4970 evelopment of Multiple Use Prior Limited tions (Non Bank-S 168,391.65 189,065.20 Signed 2021-11-25 2021-11-23 2022-01-20 2021-12-20 ved Haffir Dam at Carmoyiin tions nvelope 9 Water Sources PD) Village, Karkaar Region, Puntl and State of Somalia SO-MOPIC - PL-263900-CW-R FQ / Rehabilitation of Hudun Component 1: Support the D Request for Quota Request for Quota Single Stage - One E 2022-07-2 borehole in Hudun village, G IDA / D4970 evelopment of Multiple Use Prior Limited tions (Non Bank-S 72,202.57 78,332.65 Signed 2021-11-27 2021-11-30 2022-01-22 2021-12-22 tions nvelope 1 obob-jiran District, Nugal Reg Water Sources PD) ion, Puntland State of Somali a SO-MOPIC - PL-263901-CW-R FQ / Rehabilitation of two Bor Component 1: Support the D Request for Quota Request for Quota Single Stage - One E 2022-07-2 eholes in Cagaaran and Goco IDA / D4970 evelopment of Multiple Use Prior Limited tions (Non Bank-S 59,209.36 109,902.21 Signed 2021-11-27 2021-12-03 2022-01-22 2021-12-22 tions nvelope 1 saale villages, Mudug Region Water Sources PD) , Puntland State of Somalia SO-MOPIC - PL-263902-CW-R FQ / Rehabilitation of two bor Component 1: Support the D Request for Quota Request for Quota Single Stage - One E 2022-07-2 eholes in Tuulo-xanan and Tu IDA / D4970 evelopment of Multiple Use Prior Limited tions (Non Bank-S 90,862.54 118,491.69 Signed 2021-11-28 2021-11-30 2022-01-23 2021-12-22 tions nvelope 2 urdibi villages, Galdogob Dist Water Sources PD) rict, Mudug Region, Puntland State of Somalia SO-MOPIC - PL-265621-CW-R Component 1: Support the D Request for Quota FQ / Construction of Subsurfa Request for Quota Single Stage - One E 2022-08-0 IDA / D4970 evelopment of Multiple Use Prior Limited tions (Non Bank-S 114,833.11 135,021.87 Signed 2021-12-10 2021-11-30 2022-02-04 2021-12-26 ce Dam in Washington Villag tions nvelope 3 Water Sources PD) e, Bari Region, Puntland Stat e of Somalia Page 1 SO-MOPIC - PL-271559-CW-R FQ / Rehabilitation of four Co Request for Quota Component 2. Institutional a Request for Quota Single Stage - One E 2022-09-0 mmunity Centers and Rangel IDA / D4970 Prior Limited tions (Non Bank-S 135,616.40 144,690.68 Signed 2022-01-13 2022-02-07 2022-03-10 2022-02-27 nd Capacity Development tions nvelope 6 ands in Rabable, Barookhle, PD) Ceeldaahir and Carmooyin. SO-MOPIC - PL-286566-CW-R Component 1: Support the D Request for Quota FQ / Construction of an Impro Request for Quota Single Stage - One E 2022-11-2 IDA / D4970 evelopment of Multiple Use Prior Limited tions (Non Bank-S 161,805.12 172,079.67 Signed 2022-04-05 2022-04-15 2022-05-31 2022-05-18 ved Haffir Dam near Yidin Yo tions nvelope 7 Water Sources PD) bin Village, Bari Region, Puntl and State of Somalia. SO-MOPIC - PL-286568-CW-R Component 1: Support the D Request for Quota FQ / Construction of an Impro Request for Quota Single Stage - One E 2022-11-2 IDA / D4970 evelopment of Multiple Use Prior Limited tions (Non Bank-S 162,359.77 184,462.76 Signed 2022-04-04 2022-04-15 2022-05-30 2022-05-19 ved Haffir Dam near Xidda Vi tions nvelope 6 Water Sources PD) llage, Bari Region, Puntland S tate of Somalia. SO-MOPIC - PL-287631-CW-R Component 1: Support the D Request for Quota FQ / Construction of Haffir Da Request for Quota Single Stage - One E 2022-12-0 IDA / D4970 evelopment of Multiple Use Prior Limited tions (Non Bank-S 169,083.27 181,089.32 Signed 2022-04-10 2022-04-15 2022-06-05 2022-05-18 m in Adinzone Village, Bari R tions nvelope 2 Water Sources PD) egion, Puntland Somalia SO-MOPIC - PL-287633-CW-R Component 1: Support the D Request for Quota FQ / Construction of Sand Da Request for Quota Single Stage - One E 2022-12-0 IDA / D4970 evelopment of Multiple Use Prior Limited tions (Non Bank-S 105,365.66 122,063.85 Signed 2022-04-11 2022-04-15 2022-06-06 2022-05-17 m in Qaw Site, Bari Region, P tions nvelope 3 Water Sources PD) untland Somalia SO-MOPIC - PL-287635-CW-R Component 1: Support the D Request for Quota FQ / Construction of Haffir Da Request for Quota Single Stage - One E 2022-12-0 IDA / D4970 evelopment of Multiple Use Prior Limited tions (Non Bank-S 171,542.02 186,224.55 Signed 2022-04-09 2022-04-15 2022-06-04 2022-05-17 m in Beyra Village, Mudug Re tions nvelope 1 Water Sources PD) gion, Puntland Somalia SO-MOPIC - PL-288172-CW-R Component 3: Supporting Su Request for Quota FQ / Procurement of Office fu stainable Land Management Request for Quota Single Stage - One E 2022-12-0 IDA / D4970 Prior Limited tions (Non Bank-S 35,600.00 30,681.20 Signed 2022-04-14 2022-04-11 2022-06-09 2022-04-26 rniture in Galdogob, Rako, Al and Livelihoods Developmen tions nvelope 6 PD) ula, Garowe, Baargaal and Uf t Around Water Points eyn Offices. SO-MOPIC - PL-290622-CW-R Component 1: Support the D Request for Quota FQ / Construction of Subsurfa Request for Quota Single Stage - One E 2022-12-1 IDA / D4970 evelopment of Multiple Use Prior Limited tions (Non Bank-S 125,362.94 136,321.52 Signed 2022-04-24 2022-04-27 2022-06-19 2022-05-21 ce Sand Dam in Dareyle Villa tions nvelope 6 Water Sources PD) ge, Nugaal Region, Puntland Somalia SO-MOPIC - PL-290623-CW-R Component 1: Support the D Request for Quota FQ / Construction of Haffir Da Request for Quota Single Stage - One E 2022-12-1 IDA / D4970 evelopment of Multiple Use Prior Limited tions (Non Bank-S 173,523.02 171,125.18 Signed 2022-04-24 2022-04-27 2022-06-19 2022-05-19 m in Malaasle Village, Mudug tions nvelope 6 Water Sources PD) Region, Puntland Somalia SO-MOPIC - PL-290624-CW-R Component 1: Support the D Request for Quota FQ / Construction of Sand Da Request for Quota Single Stage - One E 2022-12-1 IDA / D4970 evelopment of Multiple Use Prior Limited tions (Non Bank-S 168,624.57 169,932.09 Signed 2022-04-24 2022-04-27 2022-06-19 2022-05-18 m in Biyo Kulule Site, Bari Re tions nvelope 6 Water Sources PD) gion, Puntland Somalia SO-MOPIC - PL-295324-CW-R FQ / Rehabilitation of three C Request for Quota Component 2. Institutional a Request for Quota Single Stage - One E Under Imple 2023-01-1 ommunity Centers and two R IDA / D4970 Prior Limited tions (Non Bank-S 184,713.40 0.00 2022-05-23 2022-06-06 2022-07-18 nd Capacity Development tions nvelope mentation 4 angelands in Beyra, Malaasle PD) and Darayle, Mudug and Nug al Region SO-MOPIC - PL-295325-CW-R FQ / Rehabilitation of three C Request for Quota Component 2. Institutional a Request for Quota Single Stage - One E Under Imple 2023-01-1 ommunity Centers and one R IDA / D4970 Prior Limited tions (Non Bank-S 90,942.80 0.00 2022-05-23 2022-06-06 2022-07-18 nd Capacity Development tions nvelope mentation 4 angelands in Biyo kulule, Xid PD) da and Qaw, Bari Region SO-MOPIC - PL-295326-CW-R FQ / Rehabilitation of four Co Request for Quota Component 2. Institutional a Request for Quota Single Stage - One E Under Revie 2023-01-1 mmunity Centers and three IDA / D4970 Prior Limited tions (Non Bank-S 129,253.20 0.00 2022-05-23 2022-06-06 2022-07-18 nd Capacity Development tions nvelope w 4 Rangelands in Yidin yobin, A PD) dizone, Washington and Alul a, Bari Region SO-MOPIC - PL-296485-CW-R Component 1: Support the D Request for Quota FQ / Construction of Sand Da Request for Quota Single Stage - One E 2023-01-2 IDA / D4970 evelopment of Multiple Use Prior Limited tions (Non Bank-S 142,253.60 148,787.07 Signed 2022-06-02 2022-05-31 2022-07-28 2022-06-16 m in Goda Site, Karkaar Regi tions nvelope 4 Water Sources PD) on, Puntland, Somalia SO-MOPIC - PL-296489-CW-R Component 1: Support the D Request for Quota FQ / Construction of Sand Da Request for Quota Single Stage - One E 2023-01-2 IDA / D4970 evelopment of Multiple Use Prior Limited tions (Non Bank-S 168,741.10 175,276.94 Signed 2022-06-02 2022-05-31 2022-07-28 2022-06-16 m in Qoton Site, Karkaar Regi tions nvelope 4 Water Sources PD) on, Puntland Somalia SO-MOPIC - PL-296892-CW-R Component 1: Support the D Request for Quota FQ / Construction of Haffir Da Request for Quota Single Stage - One E 2023-01-2 IDA / D4970 evelopment of Multiple Use Prior Limited tions (Non Bank-S 175,469.68 181,737.59 Signed 2022-06-04 2022-05-31 2022-07-30 2022-06-18 m in Abaareey Village, Nuga tions nvelope 6 Water Sources PD) al Region, Puntland Somalia SO-MOPIC - PL-296896-CW-R FQ / Construction of an Impro Component 1: Support the D Request for Quota Request for Quota Single Stage - One E 2023-01-2 ved Haffir Dam near Reebent IDA / D4970 evelopment of Multiple Use Prior Limited tions (Non Bank-S 198,404.10 175,364.11 Signed 2022-06-05 2022-05-31 2022-07-31 2022-06-19 tions nvelope 7 i Village, Nugaal Region, Punt Water Sources PD) land State of Somalia. SO-MOPIC - PL-297976-CW-R Request for Bids - FB / Construction of 10 Com Component 2. Institutional a Single Stage - One E Small Works SPD Pending Imp 2023-03-2 munity Centers and 8 Rangel IDA / D4970 Prior Request for Bids Open - National 591,045.15 0.00 2022-06-07 2022-06-12 2022-07-24 2022-08-23 2022-09-27 nd Capacity Development nvelope (1 envelope proce lementation 6 ands Rehabilitations in Mudu ss) g, Nugal, and Bari Regions. SO-MOPIC - PL-298033-CW-R Component 1: Support the D Request for Quota FQ / Rehabilitation of two bor Request for Quota Single Stage - One E Under Imple 2023-02-0 IDA / D4970 evelopment of Multiple Use Prior Limited tions (Non Bank-S 132,748.13 0.00 2022-06-11 2022-06-12 2022-08-06 eholes in Biyocade and Bursa tions nvelope mentation 2 Water Sources PD) lax, Mudug Region SO-MOPIC - PL-298034-CW-R Component 1: Support the D Request for Quota Request for Quota Single Stage - One E Under Imple 2023-02-0 FQ / Rehabilitation of Borehol IDA / D4970 evelopment of Multiple Use Prior Limited tions (Non Bank-S 89,614.26 0.00 2022-06-11 2022-06-12 2022-08-06 tions nvelope mentation 2 e in Laanta-dusmada, Mudug Water Sources PD) Region SO-MOPIC - PL-298932-CW-R Component 3: Supporting Su Request for Quota FQ / Afforestation and Demo stainable Land Management Request for Quota Single Stage - One E Under Imple 2023-02-0 IDA / D4970 Prior Limited tions (Non Bank-S 199,295.25 0.00 2022-06-17 2022-06-16 2022-08-12 nstration Garden in Armaale, and Livelihoods Developmen tions nvelope mentation 8 PD) Garowe, Nugaal Region, Punt t Around Water Points land Somalia GOODS Page 2 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOPIC - PL-173788-GO-R FB / Procurement of 9 Vehicl es for Puntland Ministry of En Component 3: Supporting Su vironment Agriculture and Cli stainable Land Management Single Stage - One E mate Change, Ministry of Pla IDA / D4970 Prior Request for Bids Open - National 395,000.00 256,000.00 Completed 2020-05-17 2020-06-13 2020-05-22 2020-06-14 2020-07-03 2020-08-23 2020-08-02 2020-09-12 2020-09-06 2020-09-16 2021-03-05 2021-01-09 and Livelihoods Developmen nvelope nning, Economic Developme t Around Water Points nt and International Cooperat ion, Ministry of Livestock & A nimal Husbandry and Puntlan d Water Development Agenc y. SO-MOPIC - PL-173790-GO-R FQ / Purchase of Office Equip Component 4: Project Manag Request for Quota Single Stage - One E ments (Laptops, Desktops, Pr IDA / D4970 ement, M & E, Knowledge M Prior Limited 56,000.00 40,797.75 Completed 2020-05-24 2020-06-26 2020-07-19 2020-08-29 2021-01-15 2020-10-06 tions nvelope ojector, Printers, and accesso anagement and Learning ries) for Biyoole Puntland Imp lementing agencies. SO-MOPIC - PL-178199-GO-R Component 4: Project Manag Request for Quota Single Stage - One E FQ / Hydrological Monitoring IDA / D4970 ement, M & E, Knowledge M Prior Limited 18,000.00 16,990.00 Completed 2020-06-14 2020-11-10 2020-08-09 2020-11-28 2021-02-05 2021-07-07 tions nvelope Equipment (GPS tools) anagement and Learning SO-MOPIC - PL-183182-GO-R Component 3: Supporting Su FB / 4x4WD Double Cabin Pic stainable Land Management Single Stage - One E IDA / D4970 Prior Request for Bids Open - National 150,000.00 112,700.00 Completed 2020-07-15 2020-07-22 2020-07-20 2020-07-27 2020-08-31 2020-09-16 2020-09-30 2020-10-03 2020-11-04 2020-10-13 2021-05-03 2021-04-03 kup Vehicles with its Accesso and Livelihoods Developmen nvelope ries for Mobile Veterinary Cli t Around Water Points nics SO-MOPIC - PL-185015-GO-R Component 4: Project Manag FQ / Procurement of Office Fu Request for Quota Single Stage - One E IDA / D4970 ement, M & E, Knowledge M Prior Limited 3,500.00 3,410.00 Completed 2020-07-28 2020-08-11 2020-09-22 2020-08-19 2021-03-21 2020-08-28 rniture (tables, chairs, shelve tions nvelope anagement and Learning s etc.) for Puntland PIUs Component 3: Supporting Su SO-MOPIC - PL-204178-GO-R stainable Land Management Request for Quota Single Stage - One E FQ / Purchase of Mobile veter IDA / D4970 Prior Limited 49,908.00 54,683.20 Completed 2020-11-20 2020-12-23 2021-01-15 2021-01-18 2021-07-14 2021-02-21 and Livelihoods Developmen tions nvelope inary clinics kits t Around Water Points SO-MOPIC - PL-214237-GO-R Component 4: Project Manag FQ / Procurement of Monitori Request for Quota Single Stage - One E IDA / D4970 ement, M & E, Knowledge M Prior Limited 8,000.00 8,506.30 Completed 2021-01-25 2021-02-16 2021-03-22 2021-03-04 2021-09-18 2021-03-08 ng and Evaluation equipment tions nvelope anagement and Learning (drones, smartphones, GPS, etc) SO-MOPIC - PL-219383-GO-R Component 4: Project Manag FQ / Conference room furnitu Request for Quota Single Stage - One E IDA / D4970 ement, M & E, Knowledge M Prior Limited 14,140.00 19,959.47 Completed 2021-02-28 2021-03-01 2021-04-25 2021-03-21 2021-10-22 2021-05-10 re for newly constructed MoL tions nvelope anagement and Learning AH's Conference Hall SO-MOPIC - PL-226152-GO-R FQ / Procurement of Office Fu Component 2. Institutional a Request for Quota Single Stage - One E rniture (tables, chairs, shelve IDA / D4970 Post Limited 36,000.00 0.00 Canceled 2021-04-04 2021-05-30 2021-11-26 nd Capacity Development tions nvelope s etc.) for Puntland Ministry o f Environment, Agriculture an d Climate Change. SO-MOPIC - PL-231286-GO-R FQ / Procurement of Office Fu Component 2. Institutional a Request for Quota Single Stage - One E rniture (tables, chairs, shelve IDA / D4970 Prior Limited 36,000.00 0.00 Canceled 2021-05-01 2021-06-26 2021-12-23 nd Capacity Development tions nvelope s etc.) for Puntland Ministry o f Environment, Agriculture an d Climate Change. SO-MOPIC - PL-231558-GO-R FQ / Purchase of Office Equip ments (Laptops, Desktops, Pr Component 2. Institutional a Request for Quota Single Stage - One E IDA / D4970 Prior Limited 22,825.00 24,985.80 Completed 2021-05-05 2021-05-10 2021-06-30 2021-06-03 2021-12-27 2021-07-05 ojector, Printers, and accesso nd Capacity Development tions nvelope ries) for Puntland Ministry of Environment, Agriculture and Climate Change. SO-MOPIC - PL-232799-GO-R FQ / Procurement of Office Fu Component 2. Institutional a Request for Quota Single Stage - One E rniture (tables, chairs, shelve IDA / D4970 Prior Limited 13,175.00 25,042.00 Completed 2021-05-10 2021-05-10 2021-07-05 2021-06-03 2022-01-01 2021-06-15 nd Capacity Development tions nvelope s etc.) for Puntland Ministry o f Environment, Agriculture an d Climate Change. SO-MOPIC - PL-235843-GO-R Component 3: Supporting Su FQ / Procurement of Laborato stainable Land Management Request for Quota Single Stage - One E IDA / D4970 Prior Limited 57,810.00 59,339.28 Signed 2021-06-05 2021-06-13 2021-07-31 2021-07-03 2022-01-27 ry Kits for Puntland Ministry o and Livelihoods Developmen tions nvelope f Livestock and Animal Husba t Around Water Points ndry Component 3: Supporting Su SO-MOPIC - PL-240954-GO-R stainable Land Management Request for Quota Single Stage - One E FQ / Procurement of seeds an IDA / D4970 Prior Limited 15,000.00 8,314.38 Completed 2021-07-05 2021-06-25 2021-08-30 2021-07-25 2022-02-26 2021-08-22 and Livelihoods Developmen tions nvelope d tools for fodder production t Around Water Points SO-MOPIC - PL-242683-GO-R Component 4: Project Manag FQ / Purchase of Office Equip Request for Quota Single Stage - One E IDA / D4970 ement, M & E, Knowledge M Prior Limited 14,381.00 9,953.63 Completed 2021-07-16 2021-07-16 2021-09-10 2021-08-11 2022-03-09 2021-09-16 ment (Desktop, Projector, Pri tions nvelope anagement and Learning nters, and accessories) for P WDA/MoEMW. SO-MOPIC - PL-281394-GO-R Component 3: Supporting Su FQ / Purchase of Drugs and M stainable Land Management Request for Quota Single Stage - One E IDA / D4970 Prior Limited 39,885.00 48,109.32 Signed 2022-03-08 2022-03-21 2022-05-03 2022-04-09 2022-10-30 edical Equipment for Mobile and Livelihoods Developmen tions nvelope Vet Clinics t Around Water Points SO-MOPIC - PL-285710-GO-R Component 3: Supporting Su FQ / Procurement of seeds an stainable Land Management Request for Quota Single Stage - One E IDA / D4970 Prior Limited 83,820.00 90,884.87 Signed 2022-03-31 2022-03-31 2022-05-26 2022-04-09 2022-11-22 d tools for Agricultural Suppo and Livelihoods Developmen tions nvelope rt t Around Water Points Component 3: Supporting Su SO-MOPIC - PL-288168-GO-R stainable Land Management Request for Quota Single Stage - One E FQ / Procurement of seeds an IDA / D4970 Prior Limited 47,120.00 52,147.76 Signed 2022-04-14 2022-04-11 2022-06-09 2022-04-26 2022-12-06 and Livelihoods Developmen tions nvelope d tools for fodder production. t Around Water Points SO-MOPIC - PL-288169-GO-R Component 3: Supporting Su FQ / Procurement of Veterina stainable Land Management Request for Quota Single Stage - One E ry drugs and equipment for v IDA / D4970 Prior Limited 98,710.00 109,932.01 Signed 2022-04-14 2022-04-11 2022-06-09 2022-04-26 2022-12-06 and Livelihoods Developmen tions nvelope et clinics in Baargaal, Ufeyn, t Around Water Points Garowe, Rako and Galdogob. SO-MOPIC - PL-289467-GO-R Component 3: Supporting Su FB / Purchase of Equipments stainable Land Management Single Stage - One E Under Imple IDA / D4970 Prior Request for Bids Open - National 312,000.00 0.00 2022-04-16 2022-05-19 2022-04-21 2022-05-20 2022-06-02 2022-06-25 2022-07-02 2022-08-06 2023-02-02 for Prosopis Management Me and Livelihoods Developmen nvelope mentation asures. t Around Water Points Page 3 SO-MOPIC - PL-292835-GO-R Component 3: Supporting Su FQ / Procurement of seeds an stainable Land Management Request for Quota Single Stage - One E IDA / D4970 Prior Limited 98,500.00 102,848.90 Signed 2022-05-05 2022-05-16 2022-06-30 2022-06-01 2022-12-27 d tools for Agricultural Suppo and Livelihoods Developmen tions nvelope rt t Around Water Points SO-MOPIC - PL-293327-GO-R FQ / Procurement of office fur Component 4: Project Manag Request for Quota Single Stage - One E niture for newly constructed IDA / D4970 ement, M & E, Knowledge M Prior Limited 70,000.00 67,841.40 Signed 2022-05-13 2022-05-17 2022-07-08 2022-05-30 2023-01-04 tions nvelope Ministry of Planning, Economi anagement and Learning c Development, and Internati onal Cooperation. Puntland. SO-MOPIC - PL-295327-GO-R Component 3: Supporting Su FQ / Procurement of Drugs a stainable Land Management Request for Quota Single Stage - One E IDA / D4970 Prior Limited 85,620.00 87,004.61 Signed 2022-05-23 2022-05-17 2022-07-18 2022-05-31 2023-01-14 nd Equipment for Mobile Vet and Livelihoods Developmen tions nvelope erinary Clinic Team t Around Water Points NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOPIC - PL-169621-CS-C QS / Consulting Firm for Provi Component 1: Support the D Consultant Qualifi sion of continuous engineerin IDA / D4970 evelopment of Multiple Use Prior International 213,150.00 389,360.00 Signed 2020-04-25 2020-05-12 2020-05-16 2020-05-20 2020-06-29 2020-07-21 2020-07-29 2020-09-18 2020-09-02 2020-09-19 2021-03-01 cation Selection g support - Site selection, sur Water Sources veying, designing & BOQs, bi dding & Contracting SO-MOPIC - PL-224681-CS-C QS / Consultant Firm for Dev Component 2. Institutional a Consultant Qualifi IDA / D4970 Prior Limited 50,000.00 130,000.00 Signed 2021-03-26 2021-04-22 2021-04-09 2021-06-28 2021-05-09 2021-08-13 2021-06-13 2021-08-14 2021-12-10 eloping 10 Community Invest nd Capacity Development cation Selection ment Plans in Puntland. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 4: Project Manag SO-MOPIC - PL-160036-CS-IN Individual Consult IDA / D4970 ement, M & E, Knowledge M Prior Limited 150,000.00 118,570.00 Signed 2020-02-24 2020-02-23 2020-02-29 2020-03-10 2020-03-21 2020-04-06 2020-04-25 2020-03-28 2021-02-28 DV / Project Coordinator ant Selection anagement and Learning SO-MOPIC - PL-160043-CS-IN Component 4: Project Manag Individual Consult DV / Finance Management Sp IDA / D4970 ement, M & E, Knowledge M Prior Limited 90,000.00 78,440.00 Signed 2020-02-24 2020-03-09 2020-02-29 2020-03-10 2020-03-21 2020-04-06 2020-04-25 2020-03-28 2021-02-28 ant Selection ecialist anagement and Learning Component 4: Project Manag SO-MOPIC - PL-160039-CS-IN Individual Consult IDA / D4970 ement, M & E, Knowledge M Prior Limited 90,000.00 93,600.00 Signed 2020-02-24 2020-02-20 2020-02-29 2020-02-21 2020-03-21 2020-04-08 2020-04-25 2020-03-28 2021-02-28 DV / Procurement Specialist ant Selection anagement and Learning SO-MOPIC - PL-160034-CS-IN Component 4: Project Manag Individual Consult DV / Environmental and Soci IDA / D4970 ement, M & E, Knowledge M Prior Limited 72,000.00 66,405.00 Signed 2020-02-24 2020-02-21 2020-02-29 2020-02-23 2020-03-21 2020-04-06 2020-04-25 2020-03-28 2021-02-28 ant Selection al Safeguards Specialist anagement and Learning SO-MOPIC - PL-160042-CS-IN Component 4: Project Manag Individual Consult DV / Monitoring and Evaluati IDA / D4970 ement, M & E, Knowledge M Prior Limited 90,000.00 66,405.00 Signed 2020-02-24 2020-02-20 2020-02-29 2020-02-23 2020-03-21 2020-04-07 2020-04-25 2020-03-28 2021-02-28 ant Selection on Specialist anagement and Learning SO-MOPIC - PL-168511-CS-C Component 4: Project Manag Individual Consult DS / Senior Rangeland Specia IDA / D4970 ement, M & E, Knowledge M Prior Limited 43,200.00 131,430.00 Signed 2020-04-23 2020-04-26 2020-04-28 2020-05-06 2020-05-05 2020-05-07 2020-05-15 2020-05-09 2020-05-20 ant Selection list Consultant anagement and Learning SO-MOPIC - PL-168512-CS-C Component 4: Project Manag Individual Consult DS / Community Developmen IDA / D4970 ement, M & E, Knowledge M Prior Limited 43,200.00 125,010.00 Signed 2020-04-23 2020-05-10 2020-04-28 2020-05-13 2020-05-05 2020-05-14 2020-05-15 2020-05-13 2020-05-20 ant Selection t Specialist anagement and Learning SO-MOPIC - PL-168513-CS-C Component 4: Project Manag Individual Consult DS / Senior institutional Deve IDA / D4970 ement, M & E, Knowledge M Prior Limited 48,000.00 136,950.00 Signed 2020-04-23 2020-04-29 2020-04-28 2020-05-09 2020-05-05 2020-05-11 2020-05-15 2020-05-09 2020-05-20 ant Selection lopment Advisor anagement and Learning SO-MOPIC - PL-168514-CS-C Component 4: Project Manag Individual Consult DS / Senior Water Engineer C IDA / D4970 ement, M & E, Knowledge M Prior Limited 48,000.00 123,840.00 Signed 2020-04-23 2020-05-10 2020-04-28 2020-06-03 2020-05-05 2020-06-09 2020-05-15 2020-06-03 2020-05-20 ant Selection onsultant anagement and Learning SO-MOPIC - PL-174621-CS-IN Component 1: Support the D Individual Consult DV / 1st - Site Supervision En IDA / D4970 evelopment of Multiple Use Prior Open 18,000.00 0.00 Canceled 2020-05-27 2020-05-27 2020-07-15 2020-08-05 2020-09-09 2021-03-08 ant Selection gineer Water Sources SO-MOPIC - PL-175171-CS-IN Component 1: Support the D Individual Consult DV / 2nd - Site Supervision E IDA / D4970 evelopment of Multiple Use Prior Open 18,000.00 0.00 Canceled 2020-05-27 2020-05-27 2020-07-15 2020-08-05 2020-09-09 2021-03-08 ant Selection ngineer Water Sources SO-MOPIC - PL-175173-CS-IN Component 1: Support the D Individual Consult DV / 3rd - Site Supervision En IDA / D4970 evelopment of Multiple Use Prior Open 18,000.00 0.00 Canceled 2020-05-27 2020-05-27 2020-07-15 2020-08-05 2020-09-09 2021-03-08 ant Selection gineer Water Sources SO-MOPIC - PL-175175-CS-IN Component 1: Support the D Individual Consult DV / 4th - Site Supervision En IDA / D4970 evelopment of Multiple Use Prior Open 18,000.00 0.00 Canceled 2020-05-27 2020-05-27 2020-07-15 2020-08-05 2020-09-09 2021-03-08 ant Selection gineer Water Sources SO-MOPIC - PL-176299-CS-IN Component 1: Support the D Individual Consult DV / 1st - Site Supervision En IDA / D4970 evelopment of Multiple Use Prior Limited 18,000.00 36,000.00 Signed 2020-05-30 2020-05-31 2020-06-04 2020-06-25 2020-06-25 2020-06-29 2020-07-30 2020-08-01 2021-01-26 ant Selection gineer Water Sources SO-MOPIC - PL-176300-CS-IN Component 1: Support the D Individual Consult DV / 2nd - Site Supervision E IDA / D4970 evelopment of Multiple Use Prior Limited 18,000.00 36,000.00 Signed 2020-05-30 2020-05-31 2020-06-04 2020-06-24 2020-06-25 2020-06-29 2020-07-30 2020-08-01 2021-01-26 ant Selection ngineer Water Sources Page 4 SO-MOPIC - PL-176302-CS-IN Component 1: Support the D Individual Consult DV / 3rd - Site Supervision En IDA / D4970 evelopment of Multiple Use Prior Limited 18,000.00 36,000.00 Signed 2020-05-30 2020-05-31 2020-06-04 2020-06-25 2020-06-25 2020-06-29 2020-07-30 2020-08-01 2021-01-26 ant Selection gineer Water Sources SO-MOPIC - PL-176303-CS-IN Component 1: Support the D Individual Consult DV / 4th - Site Supervision En IDA / D4970 evelopment of Multiple Use Prior Limited 18,000.00 36,000.00 Signed 2020-05-30 2020-05-31 2020-06-04 2020-06-25 2020-06-25 2020-07-08 2020-07-30 2020-08-01 2021-01-26 ant Selection gineer Water Sources Component 3: Supporting Su SO-MOPIC - PL-214244-CS-IN stainable Land Management Individual Consult DV / Livestock Development IDA / D4970 Prior Limited 39,840.00 79,680.00 Signed 2021-01-22 2021-02-11 2021-01-27 2021-03-01 2021-02-17 2021-03-03 2021-03-24 2021-03-04 2021-09-20 and Livelihoods Developmen ant Selection Specialists t Around Water Points SO-MOPIC - PL-248997-CS-IN DV / Individual Consultant to Component 2. Institutional a Individual Consult IDA / D4970 Prior Limited 10,000.00 9,900.00 Signed 2021-08-27 2021-11-29 2021-09-01 2022-04-05 2021-09-22 2022-04-20 2021-10-27 2022-04-21 2022-04-25 Develop Sustainable Land Ma nd Capacity Development ant Selection nagement Guideline SO-MOPIC - PL-249000-CS-IN Component 3: Supporting Su DV / Individual Consultant to stainable Land Management Individual Consult Under Implement IDA / D4970 Prior Limited 10,000.00 0.00 2021-08-28 2021-10-29 2021-09-02 2021-09-23 2021-10-28 2022-04-26 prepare Laboratory Standard and Livelihoods Developmen ant Selection ation Operating Procedures (SOPs) t Around Water Points and Guidelines SO-MOPIC - PL-249048-CS-IN Component 2. Institutional a Individual Consult DV / Individual Consultant to IDA / D4970 Prior Limited 10,000.00 9,900.00 Signed 2021-08-31 2021-10-07 2021-09-05 2022-03-13 2021-09-26 2022-03-17 2021-10-31 2022-03-17 2022-04-29 nd Capacity Development ant Selection Develop Agricultural Support Guidelines SO-MOPIC - PL-249642-CS-IN Component 2. Institutional a Individual Consult DV / Individual Consultant to IDA / D4970 Prior Limited 40,000.00 39,600.00 Signed 2021-08-31 2021-10-29 2021-09-05 2022-02-28 2021-09-26 2022-03-13 2021-10-31 2022-03-13 2022-04-29 nd Capacity Development ant Selection Develop Rangeland Manage ment Guideline SO-MOPIC - PL-267282-CS-IN Component 1: Support the D Individual Consult DV / 6th - Site Supervision En IDA / D4970 evelopment of Multiple Use Prior Limited 18,000.00 18,000.00 Signed 2021-12-11 2021-12-09 2021-12-16 2022-02-27 2022-01-06 2022-03-21 2022-02-10 2022-03-21 2022-08-09 ant Selection gineer Water Sources SO-MOPIC - PL-267287-CS-IN Component 1: Support the D Individual Consult DV / 5th - Site Supervision En IDA / D4970 evelopment of Multiple Use Prior Limited 18,000.00 18,000.00 Signed 2021-12-11 2021-12-09 2021-12-16 2022-02-27 2022-01-06 2022-03-03 2022-02-10 2022-03-03 2022-08-09 ant Selection gineer Water Sources SO-MOPIC - PL-301594-CS-IN Component 4: Project Manag Individual Consult Pending Impleme DV / Puntland Procurement S IDA / D4970 ement, M & E, Knowledge M Prior Limited 26,880.00 0.00 2022-06-29 2022-07-04 2022-07-25 2022-08-29 2023-02-25 ant Selection ntation pecialist anagement and Learning Page 5