PROCUREMENT PLAN (Textual Part) Country: Kyrgyz Republic Full Project Name: Enhancing Resilience in the Kyrgyz Republic Project (ERIK) Project Number: P162635 Project Implementation Project Implementation Unit of the Project agency under MoES Date of the Procurement December 26, 2017 Plan: Period covered by this December 26, 2017 - December 26, 2018 Procurement Plan: Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. PROCUREMENT Kyrgyz Republic : Enhancing Resilience in Kyrgyzstan Project PLAN General Information Country: Kyrgyz Republic 2017-12-27 Bank’s Approval Date of the Original Procurement Plan: 2022-08-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162635 GPN Date: 2020-11-09 Project Name: Enhancing Resilience in Kyrgyzstan Project Loan / Credit No: IDA / V1060, / , IDA / 62380, IDA / 66870, IDA / D6550 Ministry of Emergency Situations Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-CW/RFB-10 / Procuremen Improving Safety and Functi Open - Internationa Single Stage - One E 2023-04-2 IDA / 62380 Prior Request for Bids 0.00 Canceled 2021-11-30 2021-12-17 2022-02-15 2022-03-17 2022-04-28 t of civil works for schools onality of School Infrastructu l nvelope 8 re KG-CW/RFB-09 / Procuremen Improving Safety and Functi Open - Internationa Single Stage - One E Pending Imp 2022-01-2 IDA / 62380 Post Request for Bids 0.00 2020-08-25 2020-09-11 2020-11-10 2020-12-10 2021-01-21 t of civil works for schools onality of School Infrastructu l nvelope lementation 1 re KG-CW/RFB-01/AF / Procure Improving Safety and Functi Open - Internationa Single Stage - One E Pending Imp 2023-04-1 IDA / 66870 Prior Request for Bids 0.00 2021-10-01 2021-10-29 2021-12-13 2022-03-04 2022-04-15 ment of civil works for 10 sch onality of School Infrastructu l nvelope lementation 5 ools re KG-CW/RFB-02/AF / Procure Improving Safety and Functi Open - Internationa Single Stage - One E Pending Imp 2024-04-1 IDA / 66870 Prior Request for Bids 0.00 2022-10-01 2022-10-29 2022-12-13 2023-03-04 2023-04-15 ment of civil works for 10 sch onality of School Infrastructu l nvelope lementation 4 ools re KG-CW/RFB-03/AF / Procure Improving Safety and Functi Open - Internationa Single Stage - One E Pending Imp 2025-04-1 IDA / 66870 Prior Request for Bids 0.00 2023-10-01 2023-10-29 2023-12-13 2024-03-03 2024-04-14 ment of civil works for 20 sch onality of School Infrastructu l nvelope lementation 4 ools re KG-CW/RFQ-01/AF / Major re Project Management and Mo Request for Quota Single Stage - One E 2022-01-2 2021-10 IDA / 66870 Post Open - National 4,621.74 Completed 2021-06-12 2021-11-27 2021-09-24 pairs of the PIU office nitoring & Evaluation tions nvelope 6 -25 Request for KG-G/RFQ-23/ERIK / Renovat Strengthening Disaster Prep Request for Quota Single Stage - One E Quotations ( 2022-05-2 IDA / 62380 Post Open - National 0.00 Canceled 2021-10-08 2021-10-05 2021-11-26 ion of server room in CMC un aredness and Response Syst tions nvelope Non Bank-SP 5 der the MES ems D) Request for KG-G/RFQ-23/ERIK-2 / Renov Strengthening Disaster Prep Request for Quota Single Stage - One E Quotations ( 2022-08-1 2022-04 ation of server room in CMC IDA / 62380 aredness and Response Syst Post Open - National 6,924.66 Completed 2021-12-24 2022-01-01 2022-02-11 2022-02-03 tions nvelope Non Bank-SP 0 -01 under the MES (rebid) ems D) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-G/RFB-02 / Equipment fo Open - Internationa Single Stage - One E / Post Request for Bids 0.00 Canceled 2018-04-25 2018-05-23 2018-07-07 2018-08-04 2018-09-01 2019-02-28 r '112' Call Center l nvelope KG-G/RFB-02B / Equipment f Contingent Emergency Resp Open - Internationa Single Stage - One E IDA / V1060 Post Request for Bids 229,590.14 Completed 2018-05-28 2018-07-20 2018-06-08 2018-07-20 2018-07-20 2018-09-04 2018-08-19 2018-09-13 2018-09-23 2018-10-02 2019-03-22 2019-02-26 or '112' Call Center onse l nvelope KG-G/RFQ-02/1 / Software (1 Project Management and Mo C accounting system for PIU IDA / V1060 Post Direct Selection Direct 7,900.00 Completed 2018-05-29 2018-06-18 2018-06-01 2018-06-18 2018-06-14 2018-06-19 2018-07-14 2018-07-19 nitoring & Evaluation under the MOES) KG-G/RFQ-01 / Equipment fo Project Management and Mo Request for Quota Single Stage - One E IDA / V1060 Post Open - National 0.00 Canceled 2018-04-27 2018-05-18 2018-06-07 2018-07-17 r PIU nitoring & Evaluation tions nvelope KG-G/RFQ-02 / Software (1C Project Management and Mo Request for Quota Single Stage - One E IDA / V1060 Post Open - National 0.00 Canceled 2018-05-05 2018-06-15 2018-08-14 accounting system for MoES) nitoring & Evaluation tions nvelope KG-G/RFB-01 / Equipment fo Contingent Emergency Resp Open - Internationa Single Stage - One E IDA / V1060 Post Request for Bids 0.00 Canceled 2018-05-15 2018-05-29 2018-07-13 2018-08-10 2018-09-07 2019-03-06 r rescue team onse l nvelope KG-G/RFB-01A / Equipment f or rescue team: Lot #1- Procurement of rescu Contingent Emergency Resp Single Stage - One E IDA / V1060 Post Request for Bids Open - National 98,060.00 Completed 2018-06-22 2018-06-28 2018-06-29 2018-06-29 2018-08-03 2018-07-27 2018-09-02 2018-08-06 2018-10-07 2018-10-01 2018-11-21 2018-10-30 e tools onse nvelope Lot #2- Procurement of equi pment for rescue service KG-G/RFQ-01B / Furniture for Project Management and Mo Request for Quota Single Stage - One E IDA / V1060 Post Open - National 3,719.77 Completed 2018-06-29 2018-07-20 2018-08-17 2018-09-06 2018-09-16 2018-10-05 PIU nitoring & Evaluation tions nvelope KG-G/RFQ-01A / Computer e Project Management and Mo Request for Quota Single Stage - One E IDA / V1060 Post Open - National 19,146.94 Completed 2018-06-29 2018-06-29 2018-08-10 2018-07-12 2018-09-09 2018-08-24 quipment for PIU nitoring & Evaluation tions nvelope KG-G/RFB-02A / Software for Contingent Emergency Resp IDA / V1060 Post Direct Selection Direct 508,250.80 Completed 2018-07-09 2018-08-06 2018-07-14 2018-08-07 2018-08-30 2018-08-28 2019-01-17 2019-01-14 '112' call center onse KG-G/RFB-01B / Equipment f or rescue team: Lot#1 - Resc Contingent Emergency Resp Single Stage - One E IDA / V1060 Post Request for Bids Open - National 18,141.96 Completed 2018-08-15 2018-08-17 2018-08-17 2018-08-17 2018-09-14 2018-09-07 2018-10-14 2018-09-20 2018-11-11 2018-10-17 2018-12-26 2018-11-23 ue equipment, Lot#2 - Fire e onse nvelope quipment, Lot #3 - Diving eq uipment. KG-G/RFB-01C / Equipment f or rescue team: Lot#1 - Resc Contingent Emergency Resp Single Stage - One E IDA / V1060 Post Request for Bids Open - National 45,416.74 Completed 2018-10-04 2018-10-05 2018-10-05 2018-10-05 2018-10-26 2018-10-26 2018-11-15 2018-11-13 2018-12-10 2018-12-17 2019-01-24 2019-04-12 ue equipment, Lot#2 - Fire e onse nvelope quipment Re-advertisement KG-G/RFQ-04 / Procurement Enhancing Financial Protecti Request for Quota Single Stage - One E of office equipment for regio IDA / 62380 Post Open - National 0.00 Canceled 2019-04-11 2019-05-23 2019-07-22 on tions nvelope nal offices SIO KG-G/RFQ-05 / Procurement Enhancing Financial Protecti Request for Quota Single Stage - One E IDA / 62380 Post Open - National 0.00 Canceled 2019-04-11 2019-05-30 2019-07-29 of furniture for regional office on tions nvelope s SIO KG-G/RFQ-07 / Procurement Enhancing Financial Protecti Request for Quota Single Stage - One E IDA / 62380 Post Open - National 0.00 Canceled 2019-07-14 2019-09-13 2019-12-12 of mobile devices for SIO on tions nvelope Page 1 KG-G/RFB-05 / Establishing t Strengthening Disaster Prep Open - Internationa Single Stage - One E IDA / 62380 Post Request for Bids 0.00 Canceled 2019-03-28 2019-04-04 2019-05-19 2019-06-16 2019-07-14 2020-07-13 he Platform to Exchange the aredness and Response Syst l nvelope Data ems KG-G/RFQ-10 / Procurement Strengthening Disaster Prep Request for Quota Open - Internationa Single Stage - One E of Software for development IDA / 62380 aredness and Response Syst Post 55,000.00 Completed 2019-04-05 2019-04-05 2019-05-20 2019-07-09 2019-09-17 2019-09-04 tions l nvelope of the Unified Duty- Dispatchi ems ng Service 112 KG-G/RFB-03 / Development Strengthening Disaster Prep of the Country-Wide Integrat Open - Internationa Single Stage - One E IDA / 62380 aredness and Response Syst Prior Request for Bids 1,241,130.00 Completed 2019-04-04 2019-06-26 2019-04-19 2019-08-21 2019-06-03 2019-08-22 2019-07-01 2019-10-30 2019-08-12 2019-11-14 2020-02-08 2021-03-23 ed Public Notification and Wa l nvelope ems rning System - OKSION Syste m KG-G/RFB-04 / Development of Routine Management Bod y - Crisis Management Cente Strengthening Disaster Prep Open - Internationa Single Stage - One E r: Lot #1 purchase of controll IDA / 62380 aredness and Response Syst Post Request for Bids 103,167.69 Completed 2019-03-25 2019-04-05 2019-03-29 2019-04-05 2019-05-13 2019-05-20 2019-06-10 2019-06-19 2019-07-08 2019-07-10 2019-12-15 2019-12-10 l nvelope er for video wall. Lot# 2 purc ems hase of satellite equipment. Lot #3 purchase of radio sta tion equipment. KG-G/RFB-09 / Disaster Lear Strengthening Disaster Prep Open - Internationa Single Stage - One E ning Platform for Professional IDA / 62380 aredness and Response Syst Post Request for Bids 94,087.13 Completed 2020-06-22 2021-05-28 2020-06-26 2021-05-28 2020-08-07 2021-07-12 2020-09-04 2021-08-27 2020-10-16 2021-09-27 2021-02-13 2022-03-26 l nvelope Training Center MES ems KG-G/RFB-10 / Procurement Enhancing Financial Protecti Request for Quota Single Stage - One E IDA / 62380 Post Open - National 47,782.91 Completed 2019-04-18 2019-05-13 2019-06-17 2019-07-19 2019-08-16 2019-10-22 of furniture for regional office on tions nvelope s SIO KG-G/RFB-12 / Procurement Enhancing Financial Protecti Request for Quota Single Stage - One E of office equipment for regio IDA / 62380 Post Open - National 67,943.35 Completed 2019-04-18 2019-05-13 2019-06-17 2019-07-19 2019-08-16 2019-09-17 on tions nvelope nal offices SIO KG-G/RFQ-11 / Computer eq Project Management and Mo IDA / V1060 Post Direct Selection Direct 3,924.70 Completed 2019-05-07 2019-05-17 2019-05-12 2019-05-21 2019-06-16 2019-05-22 2019-07-31 2019-06-05 uipment for PIU nitoring & Evaluation KG-G/RFQ-12 / Additional fur Project Management and Mo IDA / V1060 Post Direct Selection Direct 909.09 Completed 2019-05-07 2019-05-17 2019-05-12 2019-05-21 2019-05-24 2019-05-22 2019-06-23 2019-05-29 niture for PIU nitoring & Evaluation KG-G/RFQ-09 / Procurement Contingent Emergency Resp Request for Quota Single Stage - One E of office equipment for Unifie IDA / 62380 Post Open - National 0.00 Canceled 2019-03-22 2019-05-08 2019-06-24 onse tions nvelope d Duty- Dispatching Service 112 KG-G/RFQ-09A / Procuremen Strengthening Disaster Prep Request for Quota Single Stage - One E IDA / 62380 Post Open - National 0.00 Canceled 2019-06-14 2019-07-11 2019-07-24 2019-09-12 t of computer equipment for aredness and Response Syst tions nvelope 112 system ems KG-G/RFB-11 / Procurement Enhancing Financial Protecti Open - Internationa Single Stage - One E IDA / 62380 Post Request for Bids 163,420.25 Completed 2019-06-24 2019-07-22 2019-06-28 2019-07-22 2019-08-09 2019-09-02 2019-08-23 2019-10-01 2019-09-20 2019-10-18 2019-11-19 2020-02-28 of server equipment for SIO on l nvelope KG-G/RFB-08 / Strengthenin g the capacity of the newly c reated 15 cluster interdistrict Strengthening Disaster Prep Open - Internationa Single Stage - One E points (points) of monitoring IDA / 62380 aredness and Response Syst Post Request for Bids 0.00 Canceled 2019-06-17 2019-06-21 2019-08-02 2019-08-16 2019-09-13 2019-12-12 l nvelope of hazardous natural process ems es within the framework of th e creation of mobile monitori ng points of the ESCMP KG-G/RFQ-13 / Procurement Strengthening Disaster Prep Request for Quota Single Stage - One E IDA / V1060 Post Open - National 0.00 Canceled 2019-06-16 2019-08-23 2019-07-31 2019-09-29 of compressed air apparatus aredness and Response Syst tions nvelope ems KG-G/RFB-13 / Procurement of hardware for Web portal a nd newly created 15 cluster i Strengthening Disaster Prep Open - Internationa Single Stage - One E nterdistrict points (points) of IDA / 62380 aredness and Response Syst Post Request for Bids 0.00 Canceled 2019-08-07 2019-08-16 2019-08-09 2019-08-16 2019-09-20 2019-11-12 2019-10-21 2019-12-04 2019-11-25 2020-02-24 l nvelope monitoring of hazardous natu ems ral processes within the fram ework of the creation of mobi le monitoring points of the E SCMP. KG-G/RFB-14 / Production of Enhancing Financial Protecti Single Stage - One E Pending Impl Branded and Promotional Pro IDA / 62380 Post Request for Bids Open - National 0.00 2019-08-12 2019-08-15 2019-09-26 2019-10-26 2019-11-26 2020-02-24 on nvelope ementation ducts for SIO KG-G/RFB-04A / Developmen Strengthening Disaster Prep t of Routine Management Bo Open - Internationa Single Stage - One E IDA / 62380 aredness and Response Syst Post Request for Bids 0.00 Canceled 2019-08-02 2019-08-13 2019-08-05 2019-08-13 2019-09-19 2019-09-25 2019-10-17 2019-12-05 2019-11-14 2020-02-12 dy - Crisis Management Cent l nvelope ems er: Purchase of satellite equi pment KG-G/RFB-15 / Procurement Enhancing Financial Protecti Open - Internationa Single Stage - One E IDA / 62380 Post Request for Bids 0.00 Terminated 2019-08-07 2019-08-16 2019-08-09 2019-08-16 2019-09-23 2019-09-27 2019-10-23 2019-11-18 2019-11-25 2019-12-25 2020-01-24 of mobile devices for SIO on l nvelope KG-G/RFB-06A / Goods for o perational survey of landslide Strengthening Disaster Prep s: Lot #1 - Equipment and ca Open - Internationa Single Stage - One E IDA / 62380 aredness and Response Syst Post Request for Bids 0.00 Canceled 2019-06-03 2019-06-07 2019-06-06 2019-06-06 2019-07-18 2019-07-19 2019-08-01 2019-08-12 2019-08-29 2019-12-17 r. Lot # 2 - Mobile meteorolo l nvelope ems gical station and measuring equipment. Lot #3 - UAV a nd land surveying equipment KG-G/RFB-06C / Procuremen Strengthening Disaster Prep Single Stage - One E IDA / 62380 Post Request for Bids Open - National 0.00 Canceled 2019-09-27 2019-09-16 2019-09-30 2019-09-17 2019-11-11 2019-12-26 2020-01-23 2020-05-22 t of Off-road Vehicle aredness and Response Syst nvelope ems KG-G/RFB-06D / Procuremen Strengthening Disaster Prep Single Stage - One E IDA / 62380 Post Request for Bids Open - National 47,819.01 Completed 2019-10-03 2019-09-16 2019-10-07 2019-09-17 2019-11-18 2019-10-08 2020-01-02 2019-10-31 2020-01-30 2019-11-12 2020-05-29 2020-03-18 t of UAV and land survey equ aredness and Response Syst nvelope ipment ems KG-G/RFB-06Е / Procurement Strengthening Disaster Prep Single Stage - One E IDA / 62380 Post Request for Bids Open - National 0.00 Canceled 2019-09-27 2019-09-16 2019-09-30 2019-09-17 2019-11-11 2019-10-09 2019-12-26 2020-01-23 2020-05-22 of Measuring Equipment aredness and Response Syst nvelope ems KG-G/RFB-06F / Procurement Strengthening Disaster Prep Open - Internationa Single Stage - One E of Mobile Weather Station an IDA / 62380 aredness and Response Syst Post Request for Bids 0.00 Canceled 2019-09-27 2019-10-17 2019-09-30 2019-10-18 2019-11-14 2019-12-03 2019-12-30 2019-12-19 2020-02-03 2020-06-02 l nvelope d Forecast Equipment ems KG-G/RFQ-13A / Procuremen Strengthening Disaster Prep Request for Quota Single Stage - One E IDA / V1060 Post Open - National 19,574.61 Completed 2019-10-02 2019-09-24 2019-12-30 2019-12-06 2020-02-28 2020-02-06 t of compressed air apparatu aredness and Response Syst tions nvelope s ems KG-G/DC-01 / Procurement o f Software for newly created 15 cluster interdistrict points Strengthening Disaster Prep (points) of monitoring of haz IDA / 62380 aredness and Response Syst Post Direct Selection Direct 176,305.00 Completed 2019-09-30 2019-09-20 2019-10-11 2019-09-26 2019-11-08 2019-10-18 2020-03-07 2019-12-03 ardous natural processes wit ems hin the framework of the cre ation of mobile monitoring po ints of the ESCMP Page 2 KG-G/RFQ-09A-2 / Procurem Strengthening Disaster Prep Request for Quota Single Stage - One E ent of office equipment for U IDA / 62380 aredness and Response Syst Post Open - National 9,694.14 Completed 2019-10-05 2019-09-27 2019-11-19 2019-11-14 2020-01-08 2019-12-26 tions nvelope nified Duty- Dispatching Serv ems ice 112 KG-G/RFB-06C-2 / Procurem Strengthening Disaster Prep Open - Internationa Single Stage - One E IDA / 62380 Post Request for Bids 55,798.40 Completed 2020-02-06 2020-01-24 2020-02-12 2020-01-23 2020-04-02 2020-03-16 2020-05-12 2020-05-18 2020-06-16 2020-06-05 2020-10-14 2020-10-01 ent of Special Vehicles aredness and Response Syst l nvelope ems KG-G/RFB-13-2 / Procuremen t of hardware for newly creat ed 15 cluster interdistrict poi Strengthening Disaster Prep Single Stage - One E nts (points) of monitoring of IDA / 62380 aredness and Response Syst Post Request for Bids Open - National 0.00 Canceled 2020-02-13 2020-03-11 2020-02-18 2020-03-11 2020-03-16 2020-04-01 2020-04-30 2020-06-04 2020-09-02 nvelope hazardous natural processes ems within the framework of the c reation of mobile monitoring points of the ESCMP KG-G/RFB-04A-2 / Developm Strengthening Disaster Prep ent of Routine Management Open - Internationa Single Stage - One E IDA / 62380 aredness and Response Syst Post Request for Bids 0.00 Canceled 2020-02-18 2020-02-07 2020-02-21 2020-02-07 2020-04-06 2020-05-11 2020-06-08 2020-10-06 Body - Crisis Management Ce l nvelope ems nter: Purchase of satellite eq uipment KG-G/RFB-06Е-2 / Procureme Strengthening Disaster Prep Open - Internationa Single Stage - One E IDA / 62380 Post Request for Bids 0.00 Canceled 2020-03-10 2020-03-13 2020-03-13 2020-03-13 2020-04-30 2020-06-30 2020-06-19 2020-07-17 2020-11-14 nt of measuring equipment aredness and Response Syst l nvelope ems KG-G/RFB-06F-2 / Procureme Strengthening Disaster Prep Open - Internationa Single Stage - One E nt of a mobile weather statio IDA / 62380 aredness and Response Syst Post Request for Bids 57,208.80 Completed 2020-03-23 2020-06-04 2020-03-25 2020-06-05 2020-05-14 2020-07-27 2020-07-03 2020-08-27 2020-07-31 2020-09-14 2020-11-28 2021-01-12 l nvelope n and forecast equipment ems KG/ERIK-CERC/G/RFQ/2020-0 1 / Personal Protective Equip Contingent Emergency Resp Request for Quota Open - Internationa Single Stage - One E ment for RRTs, 24 designate IDA / 62380 Post 0.00 Canceled 2020-04-07 2020-04-06 2020-04-19 2020-05-19 onse tions l nvelope d quarantine hospitals, PHC, I CUs and designated hospitals KG/ERIK-CERC/G/RFQ/2020-0 2 / Disinfectants for RRTs, 24 Contingent Emergency Resp Request for Quota Open - Internationa Single Stage - One E IDA / 62380 Post 0.00 Canceled 2020-04-07 2020-04-06 2020-04-19 2020-05-19 designated quarantine hospit onse tions l nvelope als, PHC, ICUs and designate d hospitals KG/ERIK-CERC/G/RFQ/2020-0 3 / Laboratory reagents need Contingent Emergency Resp Request for Quota Open - Internationa Single Stage - One E ed for diagnosis for RRTs, 24 IDA / 62380 Post 71,415.39 Signed 2020-04-07 2020-04-06 2020-05-19 2020-04-29 2020-11-15 2020-05-22 onse tions l nvelope designated quarantine hospit als, PHC, ICUs and designate d hospitals KG/ERIK-CERC/G/RFQ/2020-0 4 / Lifesaving essential drugs Contingent Emergency Resp Request for Quota Open - Internationa Single Stage - One E for diagnosis for RRTs, 24 de IDA / 62380 Post 749,828.10 Completed 2020-04-07 2020-04-06 2020-05-19 2020-04-23 2020-11-15 2020-07-06 onse tions l nvelope signated quarantine hospital s, PHC, ICUs and designated hospitals KG/ERIK-CERC/G/RFQ/2020-0 5 / Medical devices for diagn Contingent Emergency Resp Request for Quota Open - Internationa Single Stage - One E osis for RRTs, 24 designated IDA / 62380 Post 2,510.00 Completed 2020-04-07 2020-04-06 2020-04-19 2020-04-23 2020-05-19 2020-06-29 onse tions l nvelope quarantine hospitals, PHC, IC Us and designated hospitals KG/ERIK-CERC/G/RFQ/2020-0 9 / Procurement of 13 fully e Contingent Emergency Resp Request for Quota Open - Internationa Single Stage - One E IDA / 62380 Post 764,900.00 Completed 2020-04-07 2020-04-06 2020-04-19 2020-04-22 2020-06-18 2020-09-01 quipped ambulances - Advan onse tions l nvelope ced Life Support (ALS) vehicl es KG/ERIK-CERC/G/RFQ/2020-0 6 / Medical equipment for dia Contingent Emergency Resp Request for Quota Open - Internationa Single Stage - One E gnosis for RRTs, 24 designat IDA / 62380 Post 571,333.53 Completed 2020-04-07 2020-04-06 2020-04-19 2020-04-28 2020-06-18 2020-10-14 onse tions l nvelope ed quarantine hospitals, PHC, ICUs and designated hospital s KG/ERIK-CERC/G/RFQ/2020-0 Contingent Emergency Resp Request for Quota Open - Internationa Single Stage - One E 8 / Other products (paper to IDA / 62380 Post 0.00 Canceled 2020-04-07 2020-04-06 2020-04-19 2020-05-19 onse tions l nvelope wels, shipping containers, et c.) KG/ERIK-CERC/G/RFQ/2020-0 Contingent Emergency Resp Request for Quota Open - Internationa Single Stage - One E IDA / 62380 Post 1,431,298.56 Completed 2020-04-07 2020-04-06 2020-04-19 2020-05-07 2020-06-18 2020-10-21 7 / Respiratory Support Equip onse tions l nvelope ment KG/ERIK-CERC/G/RFQ/2020-0 1B / PPEs for RRTs, 24 design Contingent Emergency Resp Request for Quota Open - Internationa Single Stage - One E IDA / 62380 Post 330,763.38 Completed 2020-04-17 2020-04-17 2020-04-29 2020-05-08 2020-05-29 2020-08-03 ated quarantine hospitals, PH onse tions l nvelope C, ICUs and designated hospi tals - 2 lots KG/ERIK-CERC/G/RFQ/2020-0 2B / Disinfectants for RRTs, 2 Contingent Emergency Resp Request for Quota Open - Internationa Single Stage - One E IDA / 62380 Post 33,803.70 Completed 2020-04-17 2020-04-17 2020-04-29 2020-04-30 2020-05-29 2020-05-18 4 designated quarantine hos onse tions l nvelope pitals, PHC, ICUs and designa ted hospitals KG/ERIK-CERC/G/RFQ/2020-0 Contingent Emergency Resp Request for Quota Open - Internationa Single Stage - One E 8B / Other products (paper to IDA / 62380 Post 6,157.70 Signed 2020-04-17 2020-04-17 2020-04-29 2020-05-08 2020-05-29 2020-07-19 onse tions l nvelope wels, liquid soap, shipping co ntainers, etc.) G/ERIK-CERC/G/RFQ/2020-05 B / Medical devices for diagn osis for RRTs, 24 designated Contingent Emergency Resp Request for Quota Open - Internationa Single Stage - One E IDA / 62380 Post 21,614.87 Completed 2020-04-20 2020-04-20 2020-05-02 2020-05-04 2020-06-01 2020-06-01 quarantine hospitals, PHC, IC onse tions l nvelope Us and designated hospitals - Lot No 2 - Consumables for medicament injection KG/ERIK-CERC/G/RFQ/2020-0 4B / Procurement of lifesavin Contingent Emergency Resp Request for Quota Open - Internationa Single Stage - One E g essential drugs for diagnosi IDA / 62380 Post 152,657.78 Completed 2020-04-23 2020-04-23 2020-05-05 2020-05-04 2020-06-04 2020-06-04 onse tions l nvelope s for RRTs, 24 designated qu arantine hospitals, PHC, ICUs and designated hospitals KG/ERIK-CERC/G/RFQ/2020-0 3B / Laboratory reagents nee Contingent Emergency Resp Request for Quota Open - Internationa Single Stage - One E ded for diagnosis for RRTs, 2 IDA / 62380 Post 0.00 Canceled 2020-05-11 2020-05-11 2020-06-24 2020-07-24 onse tions l nvelope 4 designated quarantine hos pitals, PHC, ICUs and designa ted hospitals -Lot No 1 KG-G/DC-02 / Procurement o Enhancing Financial Protecti f database of residential prop IDA / 62380 Post Direct Selection Direct 0.00 Canceled 2020-05-10 2020-05-27 2020-05-15 2020-05-28 2020-05-25 2020-07-24 on erties for SIO Page 3 KG/ERIK-CERC/G/RFQ/2020-0 6B / Medical equipment for di Contingent Emergency Resp Request for Quota agnosis for RRTs, 24 designa IDA / 62380 Post 63,213.67 Completed 2020-05-18 2020-05-19 2020-06-09 2020-08-11 2020-08-08 2020-12-17 onse tions ted quarantine hospitals, PH C, ICUs and designated hospi tals. KG/ERIK-CERC/G/RFQ/2020-1 0 / Procurement of equipmen Contingent Emergency Resp Request for Quota Open - Internationa Single Stage - One E IDA / 62380 Post 196,854.00 Completed 2020-05-26 2020-05-28 2020-06-22 2020-07-07 2020-08-21 2020-11-13 t for disinfection and reductio onse tions l nvelope n of medical waste KG-G/RFB-13-2B / Procurem ent of hardware for newly cre ated 15 cluster interdistrict p Strengthening Disaster Prep Single Stage - One E oints (points) of monitoring o IDA / 62380 aredness and Response Syst Post Request for Bids Open - National 0.00 Canceled 2020-06-22 2020-06-22 2020-06-25 2020-06-22 2020-07-25 2020-07-15 2020-08-29 2020-08-28 2020-09-08 2020-12-07 nvelope f hazardous natural processe ems s within the framework of the creation of mobile monitoring points of the ESCMP KG/ERIK-CERC/G/UNA/2020/ Contingent Emergency Resp UN Agencies (Dire 1 / Procurement of Personel P IDA / 62380 Post Direct 460,978.76 Completed 2020-07-01 2020-06-25 2020-07-03 2020-06-24 2020-07-10 2020-06-25 2020-08-29 2020-10-26 onse ct) rotective Equipment and me dical drugs KG/ERIK-CERC/G/DC/2020-0 2 / Procurement of lifesaving Contingent Emergency Resp IDA / 62380 Post Direct Selection Direct 70,575.11 Completed 2020-07-01 2020-06-30 2020-07-01 2020-07-01 2020-07-04 2020-07-04 2020-07-29 2020-08-21 essential drugs for RRTs of h onse ealth care organizations KG/ERIK-CERC/G/DC/2020-0 3 / Procurement of lifesaving Contingent Emergency Resp IDA / 62380 Post Direct Selection Direct 843,411.22 Completed 2020-07-01 2020-06-30 2020-07-01 2020-07-01 2020-07-04 2020-07-04 2020-07-29 2020-07-18 essential drugs for RRTs of h onse ealth care organizations KG/ERIK-CERC/G/DC/2020-0 4 / Procurement of lifesaving Contingent Emergency Resp IDA / 62380 Post Direct Selection 52,596.49 Completed 2020-07-01 2020-06-30 2020-07-01 2020-07-01 2020-07-04 2020-07-04 2020-07-06 2020-07-21 essential drugs for RRTs of h onse ealth care organizations KG/ERIK-CERC/G/DC/2020-0 5 / Procurement of lifesaving Contingent Emergency Resp IDA / 62380 Post Direct Selection Direct 9,465.82 Completed 2020-07-01 2020-06-30 2020-07-01 2020-07-04 2020-07-04 2020-07-04 2020-07-29 2020-07-07 essential drugs for RRTs of h onse ealth care organizations KG/ERIK-CERC/G/RFQ/2020-0 3B-2 / Purchase of consumab Contingent Emergency Resp Request for Quota Open - Internationa Single Stage - One E IDA / 62380 Post 181,860.95 Completed 2020-07-13 2020-07-08 2020-08-08 2020-08-11 2020-09-07 2020-09-21 les for polymerase chain reac onse tions l nvelope tion (PCR) analysis KG/ERIK-CERC/G/RFQ/2020-1 Contingent Emergency Resp Request for Quota Open - Internationa Single Stage - One E 0-2 / Procurement of Microwa IDA / 62380 Post 632,322.65 Completed 2020-07-15 2020-07-09 2020-08-15 2020-08-21 2020-11-13 2020-12-14 onse tions l nvelope ve equipment for disinfection of medical waste KG/ERIK-CERC/G/DC/2020-0 1 / Procurement of lifesaving Contingent Emergency Resp IDA / 62380 Post Direct Selection Direct 4,056.78 Completed 2020-07-08 2020-06-30 2020-07-08 2020-07-01 2020-07-09 2020-07-09 2020-08-03 2020-07-15 essential drugs for diagnosis onse for RRTs of health care organ ization KG-G/RFQ-14 / Procurement Enhancing Financial Protecti Request for Quota Open - Internationa Single Stage - One E of mobile devices for OJSC St IDA / 62380 Post 90,477.34 Completed 2020-08-20 2020-08-27 2020-10-14 2020-10-21 2020-12-13 2021-01-15 on tions l nvelope ate Insurance Organization KG/ERIK-CERC-COVID19/G/R Contingent Emergency Resp Open - Internationa Single Stage - One E FB/2020-01 / Procurement of IDA / 62380 Prior Request for Bids 0.00 Canceled 2020-08-21 2020-08-23 2020-08-28 2020-08-25 2020-09-14 2020-09-09 2020-10-29 2020-11-24 2021-03-24 onse l nvelope computer tomographs KG-G/DC-02-2 / Procurement of database of residential pro Enhancing Financial Protecti IDA / 62380 Post Direct Selection Direct 28,740.25 Signed 2020-09-10 2020-09-04 2020-09-15 2020-09-04 2020-10-13 2020-09-16 2020-12-12 perties for OJSC "State Insur on ance Organization" KG-G/DC-03 / Procurement o Strengthening Disaster Prep IDA / 62380 Post Direct Selection Direct 37,734.28 Completed 2020-09-10 2020-09-08 2020-09-24 2020-09-08 2020-10-29 2020-10-21 2021-01-27 2021-03-16 f measuring equipment aredness and Response Syst ems KG-G/RFQ-06/AF / Procurem Project Management and Mo Request for Quota Single Stage - One E IDA / 66870 Post Open - National 3,314.50 Completed 2020-12-15 2020-11-27 2021-04-01 2021-01-12 2021-06-10 2021-02-03 ent of Office Furniture for PIU nitoring & Evaluation tions nvelope KG-G/RFQ-07/AF / Office Equ Project Management and Mo Request for Quota Single Stage - One E IDA / 66870 Post Open - National 0.00 Canceled 2020-12-01 2020-11-27 2021-03-18 2021-05-27 ipment for PIU nitoring & Evaluation tions nvelope KG-G/RFB-06/AF / Procureme Project Management and Mo Single Stage - One E IDA / 66870 Post Request for Bids Open - National 0.00 Canceled 2020-11-26 2020-12-01 2021-01-15 2021-02-14 2021-03-28 2021-07-26 nt cars for PIU nitoring & Evaluation nvelope KG-G/RFB-04/AF / Procureme Improving Safety and Functi Open - Internationa Single Stage - One E Pending Impl IDA / 66870 Post Request for Bids 0.00 2023-03-01 2023-03-29 2023-05-13 2023-08-02 2023-09-13 2024-04-10 nt of Furniture for 10 schools onality of School Infrastructu l nvelope ementation re KG-G/RFB-05/AF / Procureme Improving Safety and Functi Open - Internationa Single Stage - One E Pending Impl IDA / 66870 Prior Request for Bids 0.00 2024-03-01 2024-03-29 2024-05-13 2024-08-02 2024-09-13 2025-04-11 nt of Furniture for 20 schools onality of School Infrastructu l nvelope ementation re KG-G/RFB-13-2C / Procurem ent of hardware for newly cre ated 15 cluster interdistrict p Strengthening Disaster Prep Single Stage - One E oints (points) of monitoring o IDA / 62380 aredness and Response Syst Post Request for Bids Open - National 65,562.40 Completed 2020-10-22 2020-11-25 2020-10-27 2020-11-25 2020-11-17 2020-12-15 2020-12-27 2020-12-22 2021-01-06 2021-01-21 2021-04-06 2021-05-17 nvelope f hazardous natural processe ems s within the framework of the creation of mobile monitoring points of the ESCMP KG-G/RFB-01/AF / Procureme Strengthening Disaster Prep nt of vehicles Lot No 1 - Firefi Open - Internationa Single Stage - One E IDA / 66870 aredness and Response Syst Prior Request for Bids 0.00 Canceled 2021-07-15 2021-08-12 2021-09-26 2021-12-16 2022-01-27 2023-01-27 ghting vehicle; Lot No 2- Feet l nvelope ems maintaining vehicles KG-G/RFB-13A / Procuremen Strengthening Disaster Prep Open - Internationa Single Stage - One E t of hardware for Web portal IDA / 62380 aredness and Response Syst Post Request for Bids 176,861.06 Completed 2020-11-20 2020-12-03 2020-11-25 2020-12-03 2021-01-11 2021-01-20 2021-02-25 2021-03-23 2021-03-25 2021-04-16 2021-07-23 2021-10-29 l nvelope of the USCEMF ems KG-G/RFQ-07/AF-2 / Procure Project Management and Mo Request for Quota Single Stage - One E IDA / 66870 Post Open - National 11,839.09 Completed 2020-12-25 2021-06-07 2021-02-16 2021-08-16 2021-03-27 ment of office equipment for nitoring & Evaluation tions nvelope PIU KG-G/RFB-06/AF-2 / Procure Project Management and Mo Single Stage - Two E IDA / 66870 Post Request for Bids Open - National 0.00 Canceled 2020-10-15 2020-12-11 2020-10-20 2020-12-10 2020-11-24 2021-01-05 2021-02-08 2021-02-25 2021-06-25 ment of cars for PIU nitoring & Evaluation nvelope Page 4 KG-G/RFB-06/AF-3 / Procure Project Management and Mo Single Stage - One E IDA / 66870 Post Request for Bids Open - National 29,413.01 Completed 2021-01-25 2021-01-22 2021-01-30 2021-01-22 2021-02-17 2021-02-09 2021-03-03 2021-03-11 2021-03-20 2021-03-17 2021-06-18 2021-04-04 ment of vehicle for PIU nitoring & Evaluation nvelope KG-G/RFB-01/AF-2 / Procure Strengthening Disaster Prep Open - Internationa Single Stage - Two E IDA / 66870 Prior Request for Bids 5,137,736.67 Completed 2021-02-19 2021-04-09 2021-03-19 2021-04-14 2021-05-10 2021-07-09 2021-08-20 2021-11-02 2021-09-17 2021-11-25 2022-09-17 2022-03-15 ment of vehicles aredness and Response Syst l nvelope ems KG-G/RFB-16/ERIK / Develop Strengthening Disaster Prep ment of Routine Managemen Single Stage - One E IDA / 62380 aredness and Response Syst Post Request for Bids Open - National 56,954.06 Completed 2021-03-23 2021-03-30 2021-03-26 2021-03-30 2021-04-16 2021-04-19 2021-05-31 2021-05-07 2021-06-17 2021-05-19 2021-10-15 2021-07-09 t Body (CMC): Procurement o nvelope ems f radio equipment KG-G/RFB-17/ERIK / Procure Strengthening Disaster Prep Single Stage - One E ment of land surveying equip IDA / 62380 aredness and Response Syst Post Request for Bids Open - National 0.00 Canceled 2021-05-28 2021-05-20 2021-05-31 2021-05-20 2021-06-21 2021-06-11 2021-08-05 2021-08-11 2021-08-22 2021-12-20 nvelope ment for USCEMF (software a ems nd UAV) KG-G/RFB-21/ERIK / Procure Strengthening Disaster Prep Single Stage - One E ment of special vehicle (oper IDA / 62380 aredness and Response Syst Post Request for Bids Open - National 57,734.89 Completed 2021-05-18 2021-05-20 2021-05-21 2021-05-20 2021-06-11 2021-06-21 2021-07-26 2021-08-02 2021-08-12 2021-09-09 2022-01-09 2021-11-15 nvelope ational research laboratory of ems MoES) KG/ERIK-CERC-COVID19/G/R Contingent Emergency Resp Open - Internationa Single Stage - Two E FB/2021-02 / Procurement of IDA / 62380 Prior Request for Bids 1,745,000.00 Signed 2021-06-01 2021-06-22 2021-06-22 2021-06-24 2021-08-06 2021-09-03 2021-10-19 2022-04-20 2021-11-16 2022-05-31 2022-03-16 onse l nvelope computed tomography KG-G/RFB-07 / Scaling-up of Strengthening Disaster Prep Open - Internationa Single Stage - One E Pending Impl IDA / 62380 Post Request for Bids 0.00 2021-01-25 2021-02-01 2021-03-18 2021-04-15 2021-05-13 2021-11-09 the operational monitoring aredness and Response Syst l nvelope ementation ems KG-G/RFB-06/AF-1 / Procure Project Management and Mo Request for Quota Single Stage - One E IDA / D6550 Post Open - National 30,304.54 Completed 2021-06-12 2021-06-02 2021-08-07 2021-07-07 2022-02-03 2021-07-16 ment for car for PIU nitoring & Evaluation tions nvelope KG/ERIK-CERC-/G/RFB/2021- Contingent Emergency Resp Open - Internationa Single Stage - One E 01 / Procurement of neurosur IDA / 62380 Post Request for Bids 183,412.93 Completed 2021-06-30 2021-07-08 2021-07-05 2021-07-08 2021-08-16 2021-08-09 2021-09-15 2021-08-24 2021-10-20 2021-10-18 2021-10-29 2021-12-22 onse l nvelope gical equipment KG-G/RFB-23/2021 / Procure ment of computer and office equipment for State Service f Enhancing Financial Protecti Open - Internationa Single Stage - One E or Regulation and Supervisio IDA / 62380 Post Request for Bids 3,948.00 Completed 2021-08-11 2021-08-10 2021-08-16 2021-08-10 2021-09-27 2021-09-27 2021-10-27 2021-11-25 2021-12-01 2022-01-10 2022-05-30 2022-02-16 on l nvelope n of the Financial Market und er the Ministry of Economy a nd Finance of the Kyrgyz Rep ublic (Gosfinnadzor) KG-G/RFQ-24/2021 / Procure Enhancing Financial Protecti Request for Quota Single Stage - One E IDA / 62380 Post Open - National 17,668.87 Completed 2021-08-16 2021-08-13 2021-10-11 2021-10-05 2022-04-09 2021-11-03 ment of office furniture for G on tions nvelope osfinnadzor KG-G/RFQ-15B/ERIK / Procur Strengthening Disaster Prep ement of hardware for newly Request for Quota Single Stage - One E IDA / 62380 aredness and Response Syst Post Open - National 0.00 Canceled 2021-08-25 2021-09-14 2021-10-20 2022-04-18 created 15 cluster interdistric tions nvelope ems t points of ES monitoring KG-G/RFB-22B/ERIK / Procur Strengthening Disaster Prep ement of digital and analog r Request for Quota Single Stage - One E IDA / 62380 aredness and Response Syst Post Open - National 58,719.07 Completed 2021-08-25 2021-09-13 2021-10-20 2021-10-22 2022-04-18 2021-12-08 adio stations for the Unified I tions nvelope ems nformation and Control Syste m KG-G/RFB-22C/ERIK / Procur Strengthening Disaster Prep ement of digital-to-analog re Request for Quota Single Stage - One E IDA / 62380 aredness and Response Syst Post Open - National 48,369.38 Completed 2021-08-25 2021-09-13 2021-10-20 2021-10-22 2022-04-18 2021-12-08 peaters and 4G routers for th tions nvelope ems e Unified Information and Co ntrol System KG-G/RFB-22/ERIK / Procure Strengthening Disaster Prep Open - Internationa Single Stage - One E ment of communication devi IDA / 62380 aredness and Response Syst Post Request for Bids 0.00 Canceled 2021-06-15 2021-06-18 2021-08-02 2021-10-01 2021-11-05 2022-02-03 l nvelope ces for development of UIMS ems KG-G/RFB-19B/ERIK / Procur Strengthening Disaster Prep Single Stage - One E ement of measuring equipme IDA / 62380 aredness and Response Syst Post Request for Bids Open - National 0.00 Canceled 2021-09-13 2021-09-16 2021-10-07 2021-11-21 2021-12-08 2022-04-07 nvelope nt for USCEMF ems KG-G/RFB-19/ERIK / Procure Strengthening Disaster Prep Single Stage - One E ment of measuring equipmen IDA / 62380 aredness and Response Syst Post Request for Bids Open - National 0.00 Canceled 2021-06-01 2021-05-20 2021-06-04 2021-05-20 2021-06-25 2021-06-14 2021-08-09 2021-08-11 2021-08-26 2021-12-24 nvelope t for USCEMF ems KG-G/RFB-17B/ERIK / Procur Strengthening Disaster Prep Single Stage - One E ement of land surveying equi IDA / 62380 aredness and Response Syst Post Request for Bids Open - National 58,722.66 Completed 2021-09-20 2021-09-23 2021-09-23 2021-09-23 2021-10-14 2021-10-07 2021-10-20 2021-10-29 2021-11-07 2021-11-25 2022-03-07 2022-02-22 nvelope pment for USCEMF (software ems and UAV) KG-G/RFQ-15D/ERIK / Procur Strengthening Disaster Prep ement of hardware for newly Request for Quota Single Stage - One E IDA / 62380 aredness and Response Syst Post Open - National 0.00 Canceled 2021-10-04 2021-10-05 2021-11-29 2022-05-28 created 15 cluster interdistric tions nvelope ems t points of ES monitoring (ret ender) KG-G/DS-15/ERIK / Procurem Strengthening Disaster Prep ent of hardware for newly cre IDA / 62380 aredness and Response Syst Post Direct Selection Direct 0.00 Canceled 2021-10-14 2021-10-19 2021-11-02 2021-11-26 ated 15 cluster interdistrict p ems oints of ES monitoring (reten der) KG/ERIK-CERC-/G/RFB/2021- 01/1A / Procurement of neuro Contingent Emergency Resp Open - Internationa Single Stage - One E IDA / 62380 Post Request for Bids 291,344.00 Completed 2021-10-25 2021-10-29 2021-10-29 2021-10-28 2021-11-28 2021-11-30 2022-01-27 2021-12-27 2022-02-20 2022-01-28 2022-05-20 2022-06-16 surgical equipment (Neurona onse l nvelope vigational system – retender ) KG-G/RFQ-15E/ERIK / Procur Strengthening Disaster Prep ement of hardware for newly Request for Quota Single Stage - One E IDA / 62380 aredness and Response Syst Post Open - National 0.00 Canceled 2021-11-12 2021-11-26 2021-12-15 2022-02-01 created 15 cluster interdistric tions nvelope ems t points of ES monitoring (ret ender) KG-G/RFQ-07/AF-2/1A / Offic Project Management and Mo Request for Quota Single Stage - One E IDA / D6550 Post Open - National 3,935.30 Completed 2021-12-12 2022-01-12 2022-02-06 2022-03-04 2022-08-05 2022-03-14 e Equipment for PIU nitoring & Evaluation tions nvelope KG-G/RFB-18/ERIK / Procure Strengthening Disaster Prep Single Stage - One E ment of land surveying equip IDA / 62380 aredness and Response Syst Post Request for Bids Open - National 0.00 Canceled 2021-05-03 2021-05-20 2021-05-06 2021-05-20 2021-05-27 2021-06-21 2021-07-11 2021-09-02 2021-07-28 2021-11-25 nvelope ment for USCEMF (GNSS) ems KG-G/RFB-18A/ERIK / Procur Strengthening Disaster Prep Request for Quota Single Stage - One E Pending Impl ement of land surveying equi IDA / 62380 aredness and Response Syst Post Open - National 0.00 2021-12-27 2022-02-21 2022-08-20 tions nvelope ementation pment for USCEMF (GNSS) re ems bid KG-G/RFQ-05/ERIK / Procure Project Management and Mo Request for Quota Single Stage - One E IDA / 62380 Post Open - National 1,297.65 Completed 2022-01-01 2022-02-26 2022-02-28 2022-08-25 2022-03-25 ment of ofiice furniture for PI nitoring & Evaluation tions nvelope U Page 5 KG-G/SSS-15/ERIK / Procure Strengthening Disaster Prep ment of hardware for newly c IDA / 62380 aredness and Response Syst Post Direct Selection Direct 5,152.51 Completed 2021-12-20 2021-12-28 2021-12-25 2021-12-28 2022-01-29 2022-01-19 2022-07-28 2022-02-02 reated 15 cluster interdistrict ems points of ES monitoring (UPS , notebook, camera) KG-G/RFB-23-2/2021-1 / Proc urement of videoconference Enhancing Financial Protecti Request for Quota Single Stage - One E system Service for Regulatio IDA / 62380 Post Open - National 103,861.21 Signed 2022-01-25 2022-03-22 2022-04-20 2022-09-18 on tions nvelope n and Supervision of the Fina ncial Market (Gosfinnadzor) KG-G/RFB-08/AF / Procureme Strengthening Disaster Prep nt of GPS trakers, Video survi Request for Quota Single Stage - One E IDA / 66870 aredness and Response Syst Post Open - National 47,166.91 Signed 2022-02-12 2022-02-13 2022-04-09 2022-04-20 2022-10-06 allance cameras and Video c tions nvelope ems onference system KG-G/RFB-02/AF / Procureme Strengthening Disaster Prep Open - Internationa Single Stage - One E nt of necessary fire extinguis IDA / 66870 aredness and Response Syst Post Request for Bids 0.00 Canceled 2022-07-15 2022-02-11 2022-08-12 2022-02-11 2022-09-26 2022-03-25 2022-11-25 2022-06-09 2023-01-27 2023-04-27 l nvelope hing means and other equip ems ment KG-G/RFB-06/AF-4 / Procure Project Management and Mo Single Stage - One E Pending Impl IDA / 66870 Post Request for Bids Open - National 0.00 2022-10-10 2022-10-10 2022-11-24 2022-12-24 2023-01-14 2023-04-14 ment of vehicles for PIU nitoring & Evaluation nvelope ementation KG-G/RFQ-20/ERIK / Procure Strengthening Disaster Prep ment of office equipment an Request for Quota Single Stage - One E IDA / 62380 aredness and Response Syst Post Open - National 0.00 Canceled 2022-01-25 2022-03-22 2022-09-18 d furniture for the Emergenc tions nvelope ems y Monitoring and Forecasting Center KG-G/RFB-03/AF / Improving Improving Safety and Functi Open - Internationa Single Stage - One E Pending Impl IDA / 66870 Post Request for Bids 0.00 2022-04-25 2022-05-23 2022-07-07 2022-09-26 2022-11-07 2023-05-06 IT infrastructure of the MOeS onality of School Infrastructu l nvelope ementation re KG-G/RFB-23-3/2021-2 / Proc urement of computer and offi Enhancing Financial Protecti Request for Quota Single Stage - One E ce equipment for Service for IDA / 62380 Post Open - National 0.00 Canceled 2022-01-25 2022-03-22 2022-09-18 on tions nvelope Regulation and Supervision o f the Financial Market under ( Gosfinnadzor) KG-G/RFQ-15/ERIK-2022 / Pr ocurement of hardware for n Strengthening Disaster Prep Request for Quota Single Stage - One E ewly created 15 cluster inter IDA / 62380 aredness and Response Syst Post Open - National 2,783.29 Completed 2022-05-15 2022-07-10 2022-06-13 2023-01-06 2022-06-30 tions nvelope district points of ES monitorin ems g (retender: working station) KG-G/RFQ-25/ERIK / Procure Strengthening Disaster Prep ment of survey equipment fo Request for Quota Open - Internationa Single Stage - One E Pending Impl IDA / 62380 aredness and Response Syst Post 0.00 2022-05-15 2022-07-10 2023-01-06 r USCEMF (Deeper CHIRP+ wi tions l nvelope ementation ems reless fish finder, Underwater scanner Gladius etc) KG-G/RFQ-19D/ERIK / Procur Strengthening Disaster Prep ement of measuring equipme Request for Quota Open - Internationa Single Stage - One E IDA / 62380 aredness and Response Syst Post 0.00 Canceled 2022-05-15 2022-05-11 2022-07-10 2023-01-06 nt for USCEMF (Lot1:Piezome tions l nvelope ems trs 6 pcs. Lot 2:Small-sized dr illing rig 2 pcs.) KG-G/RFQ-20/ERIK-2022 / Pr Strengthening Disaster Prep ocurement of office equipme Request for Quota Single Stage - One E Under Imple IDA / 62380 aredness and Response Syst Post Open - National 0.00 2022-05-15 2022-07-07 2022-07-10 2023-01-06 nt and furniture for the Emer tions nvelope mentation ems gency Monitoring and Foreca sting Center KG-G/RFQ-23-4/2022 / Procu rement of computer and offic e equipment for the Service f Enhancing Financial Protecti Request for Quota Single Stage - One E or Regulation and Supervisio IDA / 62380 Post Open - National 0.00 Canceled 2022-05-21 2022-07-16 2023-01-12 on tions nvelope n of the Financial Market und er the Ministry of Economy a nd Commerce of the Kyrgyz Republic (Gosfinnadzor) KG-G/RFQ-19D/RT/ERIK / Pro Strengthening Disaster Prep curement of measuring equip Request for Quota Open - Internationa Single Stage - One E Pending Impl IDA / 62380 aredness and Response Syst Post 0.00 2022-06-11 2022-08-06 2023-02-02 ment (Lot №1: piezometers, tions l nvelope ementation ems Lot №2: small-sized drilling ri g with spare parts) KG-G/RFQ-23-4/2022-2 / Pro Enhancing Financial Protecti Request for Quota Single Stage - One E Under Imple curement of computer and of IDA / 62380 Post Open - National 0.00 2022-06-18 2022-08-13 2023-02-09 on tions nvelope mentation fice equipment for Gosfinnad zor. KG-G/RFQ-27/ERIK / Procure Strengthening Disaster Prep Request for Quota Single Stage - One E Pending Impl ment of special land surveyin IDA / 62380 aredness and Response Syst Post Open - National 0.00 2022-07-17 2022-09-11 2023-03-10 tions nvelope ementation g equipment for USCEMF ems KG-G/RFQ-25/AF / Capacity b Strengthening Disaster Prep uilding of employees of the M Request for Quota Single Stage - One E Under Imple IDA / 62380 aredness and Response Syst Post Open - National 0.00 2022-07-16 2022-07-07 2022-09-10 2023-03-09 ES KR in firefighting: procure tions nvelope mentation ems ment the necessary equipme nt for training KG-G/RFQ-26/ERIK / Procure Strengthening Disaster Prep Request for Quota Single Stage - One E IDA / 62380 Post Open - National 0.00 Canceled 2022-07-17 2022-07-08 2022-09-11 2023-03-10 ment of MFU for USCEMF aredness and Response Syst tions nvelope ems KG-G/RFB-02/AF-2 / Procure Strengthening Disaster Prep Open - Internationa Single Stage - One E Under Imple ment the necessary fire extin IDA / 66870 aredness and Response Syst Post Request for Bids 0.00 2022-07-22 2022-07-21 2022-08-19 2022-07-22 2022-10-03 2022-12-02 2023-02-03 2023-05-04 l nvelope mentation guishing means and other eq ems uipment KG-G/RFQ-26/ERIK-2 / Procur Strengthening Disaster Prep Request for Quota Single Stage - One E Under Imple IDA / 62380 Post Open - National 0.00 2022-07-27 2022-07-26 2022-09-21 2023-03-20 ement of MFU (rebid) aredness and Response Syst tions nvelope mentation ems NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-G/RFB-06B / Procuremen Strengthening Disaster Prep Open - Internationa Single Stage - One E t of Digital terrain model (DT IDA / 62380 aredness and Response Syst Post Request for Bids 0.00 Canceled 2019-04-05 2019-04-12 2019-05-24 2019-06-21 2019-08-02 2019-12-20 l nvelope M) and orthophotographs ems KG-G/DS-24-1/AF / Procurem Strengthening Disaster Prep Under Imple ent of delivery and installatio IDA / 62380 aredness and Response Syst Post Direct Selection Direct 0.00 2022-05-20 2022-05-13 2022-05-25 2022-05-18 2022-06-29 2022-12-26 mentation n services of GPS trackers ems CONSULTING FIRMS Page 6 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-CS/QCBS-02 / Business p rocess review for catastrophe Enhancing Financial Protecti Quality And Cost- Open - Internationa IDA / V1060 Prior 1,333,333.33 Signed 2018-03-15 2018-03-25 2018-04-14 2018-05-11 2018-05-12 2018-06-25 2018-06-09 2018-07-25 2018-06-29 2018-09-12 2018-08-03 2018-11-26 2018-09-18 2018-12-26 2020-09-17 insurance and supporting IT on Based Selection l customization services KG-CS/LCS-01 / Financial au Least Cost Selecti Open - Internationa / Post 0.00 Canceled 2018-02-25 2018-03-03 2018-03-27 2018-04-24 2018-05-22 2018-06-11 2018-07-09 2018-07-23 2019-12-31 dit (annual) of project for 201 on l 8-2020 KG-CS/QCBS-01 / Preparatio n of Feasibility Studies and D Quality And Cost- Open - Internationa esigns for Improved Seismic / Prior 0.00 Canceled 2018-04-25 2018-05-25 2018-06-22 2018-07-20 2018-08-09 2018-09-13 2018-10-29 2020-10-28 Based Selection l Safety and Energy Efficiency of Schools and Technical Sup ervision of construction. KG-CS/QCBS-01/2 / Preparati on of Feasibility Studies and Improving Safety and Functi Quality And Cost- Open - Internationa Designs for Improved Seismi IDA / V1060 onality of School Infrastructu Post 0.00 Canceled 2020-03-02 2020-03-23 2020-04-27 2020-06-08 2020-06-28 2020-08-02 2020-09-11 2021-04-09 Based Selection l c Safety and Energy Efficienc re y of Schools and Technical S upervision of construction. KG-CS/LCS-01/A / Financial a Project Management and Mo Least Cost Selecti Open - Internationa IDA / 62380 Post 76,832.00 Signed 2019-01-18 2019-02-05 2019-02-03 2019-02-08 2019-02-24 2019-03-06 2019-03-24 2019-04-03 2019-04-07 2019-04-10 2019-04-22 2019-04-19 2019-05-13 2019-05-17 2024-01-31 udit of project (annual) nitoring & Evaluation on l KG-CS/QCBS-01/1 / Preparati on of Feasibility Studies and Improving Safety and Functi Quality And Cost- Open - Internationa Designs for Improved Seismi IDA / V1060 onality of School Infrastructu Prior 668,639.33 Signed 2019-06-28 2020-01-16 2019-07-12 2020-02-03 2019-08-12 2020-08-11 2019-09-11 2020-09-28 2019-10-09 2021-01-15 2019-11-13 2021-04-23 2019-12-18 2021-05-24 2020-12-17 Based Selection l c Safety and Energy Efficienc re y of Schools and Author sup ervision KG-CS/QCBS-01/3 / Preparati on of Feasibility Studies and Improving Safety and Functi Quality And Cost- Open - Internationa Designs for Improved Seismi IDA / V1060 onality of School Infrastructu Prior 0.00 Canceled 2020-07-28 2020-08-27 2020-09-27 2020-10-27 2020-11-24 2020-12-29 2021-02-02 2022-10-25 Based Selection l c Safety and Energy Efficienc re y of Schools and Author sup ervision KG-CS/CQS-02 / Supervision Improving Safety and Functi Consultant Qualifi IDA / V1060 Post Open - National 0.00 Canceled 2021-04-01 2021-04-15 2021-05-13 2021-05-27 2021-07-03 2022-06-28 and monitoring onality of School Infrastructu cation Selection re KG-CS/QCBS-05 / Supervisio Improving Safety and Functi Quality And Cost- Open - Internationa Under Implement IDA / V1060 Prior 0.00 2021-02-02 2022-07-14 2021-02-23 2022-07-18 2021-04-08 2021-05-06 2021-06-05 2021-07-10 2021-08-14 2022-12-27 n and monitoring onality of School Infrastructu Based Selection l ation re KG-CS/CQS-03 / Establishing Strengthening Disaster Prep Consultant Qualifi Open - Internationa IDA / 62380 Post 131,370.00 Completed 2019-08-05 2019-08-27 2019-08-26 2019-09-06 2019-10-09 2019-12-02 2019-10-16 2020-02-25 2019-11-13 2020-03-17 2020-02-11 2021-12-20 a Platform to Exchange the D aredness and Response Syst cation Selection l ata ems KG-CS/QCBS-03 / Optimisati Enhancing Financial Protecti Quality And Cost- Open - Internationa Pending Impleme IDA / 62380 Prior 0.00 2020-10-01 2020-10-15 2020-12-10 2021-01-07 2021-02-06 2021-03-03 2021-04-18 2022-04-18 on of SIO core business proc on Based Selection l ntation esses KG-CS/CQS-04 / Risk manag Enhancing Financial Protecti Consultant Qualifi Open - Internationa Pending Impleme IDA / 62380 Post 0.00 2020-10-15 2020-10-29 2020-12-14 2021-01-25 2021-03-01 2021-03-13 ement and regulatory compli on cation Selection l ntation ance KG-CS/LCS-01/AF / Financial Project Management and Mo Least Cost Selecti Open - Internationa IDA / 66870 Post 43,904.00 Signed 2021-04-16 2022-01-24 2021-05-01 2021-06-28 2022-01-28 2021-07-26 2022-02-03 2021-08-15 2022-02-03 2021-09-05 2022-02-09 2021-10-09 2022-03-15 2025-09-28 audit (annual) - 2021-2027 nitoring & Evaluation on l KG-CS/CQS-01/AF / Develop Strengthening Disaster Prep Consultant Qualifi Open - Internationa Pending Impleme IDA / 66870 Post 0.00 2021-11-01 2021-11-22 2022-01-05 2022-01-21 2022-02-25 2022-08-24 ment of Fire Service Program aredness and Response Syst cation Selection l ntation ems KG-CS/CQS-03/AF / Develop Improving Safety and Functi Consultant Qualifi Pending Impleme IDA / 66870 Post Open - National 0.00 2021-01-01 2021-01-22 2021-03-07 2021-04-06 2021-04-27 2025-08-31 ment of communication strat onality of School Infrastructu cation Selection ntation egy re KG-CS/CQS-05 / Expansion o f the activities of the web por Strengthening Disaster Prep Consultant Qualifi Open - Internationa Pending Impleme tal of the USCEMF: Developm IDA / 62380 aredness and Response Syst Post 0.00 2021-06-17 2021-07-01 2021-07-29 2021-08-26 2021-09-09 2021-12-08 cation Selection l ntation ent of software to expand th ems e activities of the USCEMF w eb portal KG-CS/CQS-03-1-2021/AF / O Improving Safety and Functi Consultant Qualifi IDA / 62380 Post Open - National 4,834.50 Signed 2021-07-16 2021-08-04 2021-08-06 2021-08-04 2021-09-19 2021-09-22 2021-10-19 2021-10-12 2021-11-23 2021-11-01 2022-07-02 utreach and media coverage onality of School Infrastructu cation Selection re KG-CS/QCBS-01/AF / Prepara tion of Feasibility Studies and Improving Safety and Functi Quality And Cost- Open - Internationa Designs for Improved Seismi IDA / 66870 onality of School Infrastructu Prior 0.00 Under Review 2021-07-26 2021-09-04 2021-08-02 2021-09-10 2021-09-28 2022-03-28 2021-11-12 2022-05-13 2021-12-03 2022-01-14 2022-03-11 2023-03-11 Based Selection l c Safety and Energy Efficienc re y of Schools and Author sup ervision for 30 schools KG-CS/QCBS-03/AF / Prepara tion of Feasibility Studies and Improving Safety and Functi Quality And Cost- Open - Internationa Designs for Improved Seismi IDA / 66870 onality of School Infrastructu Prior 0.00 Canceled 2021-12-25 2022-01-01 2022-03-01 2022-04-15 2022-05-06 2022-06-17 2022-08-12 2023-08-12 Based Selection l c Safety and Energy Efficienc re y of Schools and Author sup ervision for 20 schools KG-CS/QCBS-04/AF / Technic Improving Safety and Functi Quality And Cost- Open - Internationa IDA / 66870 Prior 0.00 Canceled 2023-09-01 2023-09-15 2023-10-26 2023-12-10 2023-12-31 2024-02-04 2024-04-07 2025-04-07 al supervision for 20 schools onality of School Infrastructu Based Selection l re KG-CS/QCBS-02/AF / Technic Improving Safety and Functi Quality And Cost- Open - Internationa Pending Impleme IDA / 66870 Prior 0.00 2022-09-15 2022-10-06 2022-11-19 2022-12-17 2023-01-16 2023-02-20 2023-03-27 2024-03-26 al supervision for 30 schools onality of School Infrastructu Based Selection l ntation re KG-CS/CQS-02/AF / Develop Improving Safety and Functi Consultant Qualifi ment of special technical con IDA / 66870 onality of School Infrastructu Post Open - National 0.00 Canceled 2021-01-01 2021-01-22 2021-02-21 2021-03-14 2021-04-27 2021-10-24 cation Selection ditions for 30 schools re KG-CS/CQS-03-2-2022/AF / O Improving Safety and Functi Consultant Qualifi Under Implement utreach and media coverage IDA / 66870 onality of School Infrastructu Post Open - National 0.00 2022-05-30 2022-05-27 2022-06-20 2022-08-03 2022-09-02 2022-10-07 2023-04-05 cation Selection ation - Second Phase re KG-CS/CQS-06 / Consulting s ervices: Development of insu Enhancing Financial Protecti Consultant Qualifi Open - Internationa Pending Impleme rance (financial) module of pr IDA / 62380 Post 0.00 2022-08-10 2022-08-24 2022-10-09 2022-11-08 2022-12-13 2023-06-11 on cation Selection l ntation obabilistic model of earthqua ke risk for the insurance mar ket of the Kyrgyz Republic KG-CS/CQS-07 / Consulting s Enhancing Financial Protecti Consultant Qualifi Open - Internationa Pending Impleme ervices: Procurement of actu IDA / 62380 Post 0.00 2023-01-10 2023-01-24 2023-03-11 2023-04-10 2023-05-15 2023-11-11 on cation Selection l ntation arial services to set rates Page 7 KG-CS/CQS-08 / Consulting s Enhancing Financial Protecti Consultant Qualifi Open - Internationa Pending Impleme ervices: Development of the IDA / 62380 Post 0.00 2023-04-30 2023-05-14 2023-06-29 2023-07-29 2023-09-02 2024-02-29 on cation Selection l ntation reinsurance program KG-CS/CQS-09 / Consulting s ervices: Strengthening the a Enhancing Financial Protecti Consultant Qualifi Open - Internationa Pending Impleme IDA / 62380 Prior 0.00 2023-06-10 2023-06-24 2023-08-09 2023-09-08 2023-10-13 2024-04-10 pproach to the management on cation Selection l ntation of insurance claims (insuranc e requirements). INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-IOC/IC-07 / Local Coordin Project Management and Mo Individual Consult IDA / V1060 Post Open 12,731.86 Completed 2018-02-15 2018-02-15 2018-03-29 2018-04-02 2018-03-30 2018-04-02 2018-04-17 2018-04-16 2020-04-06 2019-04-30 ator for the Component 1 nitoring & Evaluation ant Selection KG-IOC/IC-08 / Local Coordin Project Management and Mo Individual Consult IDA / V1060 Post Open 11,086.74 Completed 2018-02-15 2018-02-19 2018-03-29 2018-04-25 2018-03-30 2018-04-28 2018-04-17 2018-05-14 2020-04-06 2019-04-30 ator for the Component 2 nitoring & Evaluation ant Selection KG-IOC/IC-09 / Local Coordin Project Management and Mo Individual Consult IDA / V1060 Post Open 13,404.13 Completed 2018-02-15 2018-02-15 2018-03-29 2018-04-04 2018-03-30 2018-04-06 2018-04-17 2018-04-23 2020-04-06 2019-04-30 ator for the Component 3 nitoring & Evaluation ant Selection KG-IOC/IC-03 / Local Financi Project Management and Mo Individual Consult IDA / V1060 Prior Direct 20,923.36 Completed 2018-02-15 2018-03-02 2018-03-08 2018-03-19 2018-03-22 2018-04-04 2018-03-29 2018-04-01 2019-11-19 2019-04-30 al Manager nitoring & Evaluation ant Selection KG-IOC/IC-04 / Local Disburs Project Management and Mo Individual Consult IDA / V1060 Post Open 11,986.87 Completed 2018-02-15 2018-02-19 2018-03-20 2018-04-03 2018-03-22 2018-04-03 2018-04-08 2018-04-18 2019-04-03 2019-04-30 ment Specialist nitoring & Evaluation ant Selection KG-IOC/IC-05 / Local assistan Project Management and Mo Individual Consult IDA / V1060 Post Open 4,791.60 Terminated 2018-02-15 2018-02-19 2018-03-29 2018-04-03 2018-03-30 2018-04-05 2018-04-19 2018-04-16 2019-04-14 t of Procurement Specialist nitoring & Evaluation ant Selection KG-IOC/IC-06 / Local Translat Project Management and Mo Individual Consult IDA / V1060 Post Open 8,286.74 Terminated 2018-02-15 2018-02-19 2018-03-29 2018-04-02 2018-03-30 2018-04-02 2018-04-19 2018-04-16 2019-04-14 or-office-manager nitoring & Evaluation ant Selection KG-CS/IC-02 / Selection of Lo Project Management and Mo Individual Consult / Post Limited 3,235.30 Terminated 2017-12-29 2018-01-09 2017-12-30 2018-01-17 2018-01-05 2018-01-23 2018-01-17 2018-02-28 cal Social Consultant nitoring & Evaluation ant Selection KG-CS/IC-01 / Selection of Lo Individual Consult / Post Limited 3,970.59 Completed 2017-12-29 2018-01-30 2017-12-31 2018-01-17 2018-01-05 2018-01-22 2018-01-17 2018-02-04 2018-02-28 2018-04-06 cal Environmental Consultant ant Selection KG-IOC/IC-02 / Local Senior P Project Management and Mo Individual Consult IDA / V1060 Prior Direct 13,575.10 Terminated 2018-02-22 2018-03-02 2018-02-22 2018-03-19 2018-02-22 2018-04-04 2018-04-01 2018-04-01 2019-11-22 rocurement Specialist nitoring & Evaluation ant Selection KG-MES-54500-CS-INDV / Lo Project Management and Mo Individual Consult IDA / V1060 Prior Limited 14,390.21 Completed 2018-03-19 2018-03-22 2018-03-19 2018-04-06 2018-04-02 2018-04-24 2018-04-26 2018-05-16 2019-04-21 2019-04-30 cal Director PIU nitoring & Evaluation ant Selection KG-IOC/IC-01 / Local Director Individual Consult / Prior Open 0.00 Canceled 2018-02-15 2018-02-19 2018-03-29 2018-04-12 2018-05-17 2020-05-06 PIU ant Selection KG-CS/IC-03 / Selection of Lo Individual Consult cal Consultant for preparatio / Post Open 0.00 Canceled 2018-04-15 2018-05-27 2018-06-10 2018-06-24 2019-06-19 ant Selection n of bidding documents for g oods for MoES KG-CS/IC-03-2 / Local IT Con sultant for preparation of bid Project Management and Mo Individual Consult IDA / V1060 Post Limited 0.00 Canceled 2018-05-10 2018-05-15 2018-06-05 2018-07-03 2019-07-03 ding documents for Compone nitoring & Evaluation ant Selection nt #1 and Component #3 KG-CS/IC-03/1 / Local Consul Project Management and Mo Individual Consult tant for Business Processes a IDA / V1060 Post Open 12,778.57 Completed 2018-06-21 2018-06-21 2018-07-30 2018-08-06 2018-08-02 2018-08-06 2018-08-21 2018-08-22 2019-08-21 2019-08-21 nitoring & Evaluation ant Selection nd Information Technologies KG-CS/IC-04 / International С Improving Safety and Functi Individual Consult IDA / V1060 Post Open 0.00 Canceled 2018-10-26 2018-12-05 2018-12-21 2019-01-09 2020-12-29 ivil engineer onality of School Infrastructu ant Selection re KG-CS/IC-04/A / Local civil en Improving Safety and Functi Individual Consult IDA / 62380 Post Open 26,288.61 Terminated 2019-02-17 2019-03-01 2019-03-14 2019-04-10 2019-03-21 2019-04-24 2019-04-11 2019-04-25 2020-04-10 gineer onality of School Infrastructu ant Selection re KG-CS/IC-05 / Local Social & Improving Safety and Functi Individual Consult IDA / 62380 Post Open 0.00 Canceled 2019-02-27 2019-02-25 2019-04-04 2019-04-10 2019-04-11 2019-05-02 2020-05-01 Environment Consultant onality of School Infrastructu ant Selection re KG-CS/IC-07 / Local IT Cons Strengthening Disaster Prep Individual Consult IDA / V1060 Post Open 5,213.26 Terminated 2019-03-25 2019-04-10 2019-04-19 2019-06-04 2019-04-22 2019-05-31 2019-05-10 2019-06-19 2020-05-09 ultant for MES KR aredness and Response Syst ant Selection ems KG-CS/IC-09 / Local Translat Improving Safety and Functi Individual Consult IDA / 62380 Post Open 0.00 Canceled 2019-03-25 2019-04-02 2019-04-11 2019-06-28 2019-04-12 2019-04-29 2020-04-28 or Consultant for Component onality of School Infrastructu ant Selection #2 re KG-CS/IC-10 / Local Translat Enhancing Financial Protecti Individual Consult IDA / 62380 Post Open 0.00 Canceled 2019-03-25 2019-04-02 2019-04-11 2019-07-02 2019-04-12 2019-04-29 2020-04-28 or Consultant for Component on ant Selection #3 KG-CS/IC-05-2 / Local Social Improving Safety and Functi Individual Consult IDA / 62380 Post Limited 18,631.04 Terminated 2019-05-03 2019-05-15 2019-05-10 2019-05-21 2019-05-24 2019-05-31 2019-06-14 2019-07-04 2020-06-13 &Enviroment Consultant onality of School Infrastructu ant Selection re KG-CS/IC-08 / Local Translat Strengthening Disaster Prep Individual Consult IDA / 62380 Post Open 0.00 Canceled 2019-03-25 2019-04-02 2019-04-11 2019-07-17 2019-04-12 2019-04-29 2020-04-28 or Consultant for Component aredness and Response Syst ant Selection #1 ems KG-CS/IC-03/2 / Local Consul Enhancing Financial Protecti Individual Consult tant for Business Processes a IDA / 62380 Post Direct 12,808.23 Completed 2019-08-21 2019-09-06 2019-08-21 2019-08-20 2019-08-21 2019-08-20 2019-08-22 2019-08-20 2020-08-31 2020-08-31 on ant Selection nd Information Technologies KG/CS/SSS-01/SDC / Develop Improving Safety and Functi IDA / 62380 Post Direct Selection Direct 48,252.84 Completed 2020-07-01 2020-06-24 2020-07-15 2020-07-23 2020-09-09 2020-09-25 2020-11-08 2021-10-13 ment of special design criteri onality of School Infrastructu a re KG-CS/IC-07/B / Local IT Con Strengthening Disaster Prep Individual Consult IDA / 62380 Post Open 10,085.87 Signed 2020-05-22 2020-06-12 2020-06-20 2020-08-24 2020-07-04 2020-08-24 2020-07-07 2020-09-09 2021-07-07 sultant for MES aredness and Response Syst ant Selection ems KG-CS/IC-03/3 / Local Consul Enhancing Financial Protecti Individual Consult tant for Business Processes a IDA / 62380 Post Direct 25,809.03 Terminated 2020-08-28 2020-08-24 2020-08-31 2020-08-25 2020-08-31 2020-08-25 2020-09-01 2020-09-01 2021-03-31 on ant Selection nd Information Technologies KG-CS/IC-01/AF / Communic Improving Safety and Functi Individual Consult IDA / 66870 Post Open 10,522.20 Signed 2020-10-26 2020-10-13 2020-12-02 2021-01-11 2020-12-09 2021-01-11 2020-12-30 2021-01-25 2025-08-31 ations Strategy Specialist onality of School Infrastructu ant Selection re Page 8 KG-CS/IC-02/AF / Fire Safety Strengthening Disaster Prep Individual Consult IDA / 66870 Post Open 0.00 Canceled 2020-10-27 2020-12-10 2020-12-17 2020-12-31 2021-12-31 Specialist aredness and Response Syst ant Selection ems KG-CS/IC-11 / Local Сonsulta Improving Safety and Functi Individual Consult IDA / 62380 Post Open 8,992.22 Completed 2021-02-03 2021-02-03 2021-03-17 2021-03-12 2021-03-24 2021-03-12 2021-03-27 2021-04-01 2021-07-25 2021-07-30 nt Engineer on energy efficie onality of School Infrastructu ant Selection ncy re KG-CS/IC-12 / Local Сonsulta Improving Safety and Functi Individual Consult IDA / 62380 Post Open 8,992.22 Completed 2021-02-03 2021-02-03 2021-03-17 2021-03-12 2021-03-24 2021-03-12 2021-03-27 2021-04-01 2021-07-25 2021-07-31 nt Engineer on energy efficie onality of School Infrastructu ant Selection ncy re KG-CS/IC-13 / Local Consulta Improving Safety and Functi Individual Consult IDA / 62380 Post Open 0.00 Canceled 2021-02-03 2021-02-03 2021-03-17 2021-03-12 2021-03-24 2021-03-27 2021-07-25 nt on water supply and sanit onality of School Infrastructu ant Selection ation re KG-CS/IC-13-2 / Local Consul Improving Safety and Functi Individual Consult IDA / 62380 Post Limited 8,994.63 Completed 2021-03-30 2021-03-30 2021-04-13 2021-04-05 2021-04-27 2021-04-15 2021-05-11 2021-04-30 2021-09-08 2021-08-30 tant on water supply and san onality of School Infrastructu ant Selection itation re KG-CS/IC-03/AF / IT Consulta Improving Safety and Functi Individual Consult IDA / 66870 Post Open 9,623.94 Completed 2021-04-01 2021-03-30 2021-05-06 2021-05-04 2021-05-13 2021-06-20 2021-05-27 2021-06-24 2023-05-27 2022-05-01 nt for Component 2 onality of School Infrastructu ant Selection re KG-CS/SSS-02/AF-SDC / Dev Improving Safety and Functi elopment of special technical IDA / 62380 onality of School Infrastructu Post Direct Selection Direct 151,848.91 Signed 2021-12-20 2021-12-28 2021-12-30 2022-01-13 2022-03-05 2022-02-17 2022-09-01 conditions for 30 schools re KG-CS/IC-03/4 / Local Consul Enhancing Financial Protecti Under Implement tant for Business Processes a IDA / 62380 Post Direct Selection Direct 0.00 2022-06-22 2022-06-24 2022-06-28 2022-07-01 2023-07-01 on ation nd Information Technologies Page 9