PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, Urban Productive Safety Net and Jobs Project (P169943) Project Implementation agency: Ministry of Labor and Social Affairs (MoLSA), Ministry of Urban Development and Construction (MoUDC), Urban Job Creation and Food Security Agency (UJCFSA) Date of the Procurement Plan: November 2020. Period covered by this Procurement Plan: December 2020 to December 2021. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Section 33(1)(a) from page 35-48 of the Proclamation Number 649/2009 of the Ethiopian Federal Government Procurement and Property Administration Proclamation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. • Open Advertising of the procurement opportunity at the national level; • The procurement is open to eligible firms from any country; • The request for bids/Proposal documents shall require that bidders/proposers submitting Bids/Proposal present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the bank’s right to sanction and the Bank’s inspection and audit right; • Contracts with an appropriate allocation of responsibilities, risks and liabilities; • Application of Standstill period and Publication of contract award information; • Maintenance of records of the procurement process; and • The Bank has the right to review procurement documentation and activities. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Is applicable for those contracts identified in the Procurement Plan; Works: Is applicable for those contracts identified in the Procurement Plan. Other Relevant Procurement Information. None PROCUREMENT Ethiopia : Urban Productive Safety Net and Jobs Project PLAN General Information Country: Ethiopia 2022-06-27 Bank’s Approval Date of the Original Procurement Plan: 2022-06-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169943 GPN Date: 2020-12-18 Project Name: Urban Productive Safety Net and Jobs Project Loan / Credit No: IDA / D7320 Amhara Urban Development and Infrastructure Bureau Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-AMHARA GONDER-29862 Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-09-0 2-CW-RFQ / Semi-skilled labo IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 10,000.00 0.00 2022-06-25 2022-08-02 tions nvelope lementation 1 ur Urban Environment PD) Expand the Urban Productiv Request for Quota ET-AMHARA MOTTA-298623- Request for Quota Single Stage - One E Pending Imp 2022-09-1 IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 1,500.00 0.00 2022-07-01 2022-08-11 CW-RFQ / Semi-skilled labour tions nvelope lementation 0 Urban Environment PD) ET-AMHARA BAHIR DAR-298 Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-09-0 624-CW-RFQ / Semi-skilled la IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 2,000.00 0.00 2022-06-27 2022-08-09 tions nvelope lementation 8 bour Urban Environment PD) ET-AMHARA DEBREMARKOS- Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-08-2 298619-CW-RFQ / Semi-skille IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 2,200.00 0.00 2022-06-29 2022-07-29 tions nvelope lementation 3 d labour Urban Environment PD) ET-AMHARA DEBARK-29862 Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-08-1 5-CW-RFQ / Semi-skilled labo IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 1,000.00 0.00 2022-06-27 2022-07-29 tions nvelope lementation 8 ur Urban Environment PD) ET-AMHARA DIBRETABOR-29 Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-08-3 8626-CW-RFQ / Semi-skilled l IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 1,000.00 0.00 2022-06-27 2022-08-01 tions nvelope lementation 1 abour Urban Environment PD) ET-AMHARA DEBREBIRHAN-2 Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-09-1 98627-CW-RFQ / Semi-skilled IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 1,000.00 0.00 2022-06-29 2022-08-16 tions nvelope lementation 5 labour Urban Environment PD) ET-AMHARA SHEWAROBIT-2 Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-09-0 98621-CW-RFQ / semi-skilled IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 1,500.00 0.00 2022-06-27 2022-08-04 tions nvelope lementation 3 labour Urban Environment PD) Expand the Urban Productiv Request for Quota ET-AMHARA KEMISE-298628- Request for Quota Single Stage - One E Pending Imp 2022-08-3 IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 2,000.00 0.00 2022-06-28 2022-08-01 CW-RFQ / Semi-skilled labour tions nvelope lementation 1 Urban Environment PD) ET-AMHARA KOMBOLCHA-29 Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-08-3 8629-CW-RFQ / Semi-skilled l IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 1,200.00 0.00 2022-06-27 2022-08-01 tions nvelope lementation 1 abour Urban Environment PD) ET-AMHARA LALIBELA-29863 Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-08-2 0-CW-RFQ / Semi-skilled labo IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 1,200.00 0.00 2022-06-24 2022-07-28 tions nvelope lementation 7 ur Urban Environment PD) ET-AMHARA WOLDYA-29861 Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-09-0 2-CW-RFQ / Semi-skilled labo IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 1,000.00 0.00 2022-06-27 2022-08-04 tions nvelope lementation 3 ur Urban Environment PD) ET-AMHARA SEKOTA-298618 Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-08-2 -CW-RFQ / Semi-skilled labou IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 1,000.00 0.00 2022-07-03 2022-08-04 tions nvelope lementation 4 r Urban Environment PD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-AMHARA ENJEBARA-2982 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 93-GO-RFQ / Industrial Constr IDA / D7320 e Safety Net to Improve the Post Limited 8,000.00 0.00 2022-06-15 2022-07-15 2022-08-04 tions nvelope ementation uction materials Urban Environment ET-AMHARA ENJEBARA-2982 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 97-GO-RFQ / Local Constructi IDA / D7320 e Safety Net to Improve the Post Limited 2,000.00 0.00 2022-06-15 2022-07-15 2022-08-04 tions nvelope ementation on materials Urban Environment ET-AMHARA FINOTESELAM-2 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 98298-GO-RFQ / Water suppl IDA / D7320 e Safety Net to Improve the Post Limited 1,600.00 0.00 2022-06-13 2022-07-12 2022-08-01 tions nvelope ementation y installation to greenery are Urban Environment a ET-AMHARA FINOTESELAM-2 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 98299-GO-RFQ / Barbed wire, IDA / D7320 e Safety Net to Improve the Post Limited 30,000.00 0.00 2022-06-15 2022-07-15 2022-08-04 tions nvelope ementation angle iron, and gabion box Urban Environment ET-AMHARA FINOTESELAM-2 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 98300-GO-RFQ / Tree and fru IDA / D7320 e Safety Net to Improve the Post Limited 2,500.00 0.00 2022-06-24 2022-07-18 2022-08-17 tions nvelope ementation it seed and seedlings Urban Environment ET-AMHARA FINOTESELAM-2 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 98301-GO-RFQ / Local constr IDA / D7320 e Safety Net to Improve the Post Limited 2,000.00 0.00 2022-06-14 2022-07-15 2022-08-09 tions nvelope ementation uction materials Urban Environment ET-AMHARA DESSE-298302- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Tree and fruit seed IDA / D7320 e Safety Net to Improve the Post Limited 12,000.00 0.00 2022-06-24 2022-07-19 2022-08-08 tions nvelope ementation and seedling Urban Environment ET-AMHARA DESSE-298303- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Local construction IDA / D7320 e Safety Net to Improve the Post Limited 17,500.00 0.00 2022-06-15 2022-07-18 2022-08-02 tions nvelope ementation materials Urban Environment Page 1 ET-AMHARA DESSE-298306- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Water supply and s IDA / D7320 e Safety Net to Improve the Post Limited 7,570.00 0.00 2022-06-20 2022-07-19 2022-08-08 tions nvelope ementation anitary equipment with acces Urban Environment sories Expand the Urban Productiv ET-AMHARA DESSE-298307- Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 6,000.00 0.00 2022-06-17 2022-07-19 2022-08-08 GO-RFQ / Doors and windows tions nvelope ementation Urban Environment Expand the Urban Productiv ET-AMHARA DESSE-298310- Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 7,615.00 0.00 2022-06-20 2022-07-19 2022-08-08 GO-RFQ / Hollow blocks tions nvelope ementation Urban Environment ET-AMHARA GONDER-29831 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 5-GO-RFQ / Local Constructio IDA / D7320 e Safety Net to Improve the Post Limited 8,658.00 0.00 2022-06-24 2022-07-25 2022-08-24 tions nvelope ementation n materials Urban Environment ET-AMHARA GONDER-29831 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 6-GO-RFQ / Tree seed or see IDA / D7320 e Safety Net to Improve the Post Limited 785.00 0.00 2022-06-24 2022-07-26 2022-08-25 tions nvelope ementation dlings Urban Environment ET-AMHARA GONDER-29831 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 7-GO-RFQ / Industrial Constru IDA / D7320 e Safety Net to Improve the Post Limited 15,000.00 0.00 2022-06-24 2022-07-19 2022-08-08 tions nvelope ementation ction Materials Urban Environment ET-AMHARA GONDER-29831 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 8-GO-RFQ / Doors and windo IDA / D7320 e Safety Net to Improve the Post Limited 5,950.00 0.00 2022-06-25 2022-07-26 2022-08-25 tions nvelope ementation w Urban Environment ET-AMHARA MOTTA-298321- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Industrial construct IDA / D7320 e Safety Net to Improve the Post Limited 19,000.00 0.00 2022-06-20 2022-07-17 2022-08-11 tions nvelope ementation ion materials Urban Environment ET-AMHARA MOTTA-298322- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Local Construction IDA / D7320 e Safety Net to Improve the Post Limited 11,000.00 0.00 2022-06-21 2022-07-18 2022-08-07 tions nvelope ementation Materials Urban Environment ET-AMHARA MOTTA-298323- Expand the Urban Productiv Request for Quota Pending Impl GO-RFQ / Tree and fruit seedl IDA / D7320 e Safety Net to Improve the Post 7,960.00 0.00 2022-06-23 2022-07-18 2022-08-12 tions ementation ing and seed Urban Environment ET-AMHARA BAHIR DAR-298 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 332-GO-RFQ / Industrial Cons IDA / D7320 e Safety Net to Improve the Post Limited 40,000.00 0.00 2022-06-20 2022-07-15 2022-08-09 tions nvelope ementation truction Materials Urban Environment ET-AMHARA BAHIR DAR-298 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 333-GO-RFQ / Local Construc IDA / D7320 e Safety Net to Improve the Post Limited 12,000.00 0.00 2022-06-22 2022-07-22 2022-08-16 tions nvelope ementation tion materials Urban Environment ET-AMHARA BAHIR DAR-298 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 334-GO-RFQ / Tree and fruit IDA / D7320 e Safety Net to Improve the Post Limited 2,000.00 0.00 2022-06-24 2022-07-22 2022-08-11 tions nvelope ementation seedling and seed Urban Environment ET-AMHARA DEBRE MARKOS Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl -298347-GO-RFQ / Industrial IDA / D7320 e Safety Net to Improve the Post Limited 5,000.00 0.00 2022-06-24 2022-07-20 2022-08-14 tions nvelope ementation construction materials Urban Environment ET-AMHARA DEBRE MARKOS Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl -298348-GO-RFQ / Local cons IDA / D7320 e Safety Net to Improve the Post Limited 2,000.00 0.00 2022-06-24 2022-07-19 2022-08-08 tions nvelope ementation truction materials Urban Environment ET-AMHARA DEBRE MARKOS Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl -298350-GO-RFQ / Tree and f IDA / D7320 e Safety Net to Improve the Post Limited 1,700.00 0.00 2022-06-24 2022-07-20 2022-08-09 tions nvelope ementation ruit seedling and seeds Urban Environment ET-AMHARA DEBARK-29835 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 9-GO-RFQ / Industrial constru IDA / D7320 e Safety Net to Improve the Post Limited 4,000.00 0.00 2022-06-24 2022-07-28 2022-08-17 tions nvelope ementation ction materials Urban Environment ET-AMHARA DEBARK-29836 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 1-GO-RFQ / Local constructio IDA / D7320 e Safety Net to Improve the Post Limited 3,000.00 0.00 2022-06-27 2022-07-28 2022-08-22 tions nvelope ementation n materials Urban Environment ET-AMHARA DEBARK-29836 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 4-GO-RFQ / Tree and fruit see IDA / D7320 e Safety Net to Improve the Post Limited 12,000.00 0.00 2022-06-24 2022-07-18 2022-08-17 tions nvelope ementation dling Urban Environment ET-AMHARA DIBRETABORE-2 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 98371-GO-RFQ / Industrial co IDA / D7320 e Safety Net to Improve the Post Limited 2,000.00 0.00 2022-06-27 2022-08-12 2022-08-22 tions nvelope ementation nstruction materials Urban Environment ET-AMHARA DEBREBIRHAN-2 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 98375-GO-RFQ / Industrial co IDA / D7320 e Safety Net to Improve the Post Limited 7,540.00 0.00 2022-06-29 2022-07-27 2022-08-26 tions nvelope ementation nstruction materials Urban Environment ET-AMHARA DEBREBIRHAN-2 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 98379-GO-RFQ / Local constr IDA / D7320 e Safety Net to Improve the Post Limited 4,900.00 0.00 2022-06-24 2022-07-29 2022-08-23 tions nvelope ementation uction materials Urban Environment ET-AMHARA DEBREBIRHAN-2 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 98382-GO-RFQ / Tree and fru IDA / D7320 e Safety Net to Improve the Post Limited 1,000.00 0.00 2022-06-24 2022-07-15 2022-08-04 tions nvelope ementation it seedling and seeds Urban Environment ET-AMHARA GENDAWUHA-2 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 98390-GO-RFQ / Tree and fru IDA / D7320 e Safety Net to Improve the Post Limited 1,000.00 0.00 2022-06-24 2022-07-18 2022-08-17 tions nvelope ementation it seedlings Urban Environment ET-AMHARA SHEWAROBIT-2 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 98395-GO-RFQ / Industrial co IDA / D7320 e Safety Net to Improve the Post Limited 12,000.00 0.00 2022-06-29 2022-08-01 2022-08-31 tions nvelope ementation nstruction materials Urban Environment ET-AMHARA SHEWAROBIT-2 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 98396-GO-RFQ / Local constr IDA / D7320 e Safety Net to Improve the Post Limited 2,500.00 0.00 2022-06-27 2022-08-01 2022-08-31 tions nvelope ementation uction materials Urban Environment ET-AMHARA SHEWAROBIT-2 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 98397-GO-RFQ / Tree and fru IDA / D7320 e Safety Net to Improve the Post Limited 4,000.00 0.00 2022-06-24 2022-07-19 2022-08-08 tions nvelope ementation it seedling and seeds Urban Environment Page 2 ET-AMHARA KEMISE-298400- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Industrial construct IDA / D7320 e Safety Net to Improve the Post Limited 10,000.00 0.00 2022-06-27 2022-07-28 2022-08-22 tions nvelope ementation ion materials Urban Environment ET-AMHARA KEMISE-298401- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Local construction IDA / D7320 e Safety Net to Improve the Post Limited 4,800.00 0.00 2022-06-29 2022-08-05 2022-08-30 tions nvelope ementation materials Urban Environment ET-AMHARA KEMISE-298402- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Tree, fruit and gras IDA / D7320 e Safety Net to Improve the Post Limited 7,000.00 0.00 2022-06-24 2022-07-21 2022-08-10 tions nvelope ementation s seedlings and seeds Urban Environment ET-AMHARA KOMBOLCHA-29 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 8405-GO-RFQ / Industrial con IDA / D7320 e Safety Net to Improve the Post Limited 8,000.00 0.00 2022-06-28 2022-07-28 2022-08-22 tions nvelope ementation struction materials Urban Environment ET-AMHARA KOMBOLCHA-29 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 8406-GO-RFQ / Local constru IDA / D7320 e Safety Net to Improve the Post Limited 2,000.00 0.00 2022-06-28 2022-08-01 2022-08-31 tions nvelope ementation ction materials Urban Environment ET-AMHARA KOMBOLCHA-29 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 8407-GO-RFQ / Tree, fruit an IDA / D7320 e Safety Net to Improve the Post Limited 2,000.00 0.00 2022-06-24 2022-07-20 2022-08-09 tions nvelope ementation d grass seedling and seeds Urban Environment ET-AMHARA LALIBELA-29841 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 2-GO-RFQ / Industrial constru IDA / D7320 e Safety Net to Improve the Post Limited 10,000.00 0.00 2022-06-29 2022-08-01 2022-08-31 tions nvelope ementation ction materials Urban Environment ET-AMHARA LALIBELA-29841 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 3-GO-RFQ / Local constructio IDA / D7320 e Safety Net to Improve the Post Limited 4,000.00 0.00 2022-07-04 2022-08-04 2022-09-03 tions nvelope ementation n materials Urban Environment ET-AMHARA LALIBELA-29841 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 4-GO-RFQ / Tree and fruit see IDA / D7320 e Safety Net to Improve the Post Limited 2,000.00 0.00 2022-06-24 2022-07-21 2022-08-10 tions nvelope ementation dlings and seed Urban Environment ET-AMHARA WOLDYA-29860 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 1-GO-RFQ / Industrial constru IDA / D7320 e Safety Net to Improve the Post Limited 7,000.00 0.00 2022-06-29 2022-07-29 2022-08-18 tions nvelope ementation ction materials Urban Environment ET-AMHARA WOLDYA-29860 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 5-GO-RFQ / Local constructio IDA / D7320 e Safety Net to Improve the Post Limited 1,000.00 0.00 2022-07-01 2022-08-05 2022-08-25 tions nvelope ementation n materials Urban Environment ET-AMHARA WOLDYA-29861 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 1-GO-RFQ / Tree and fruit see IDA / D7320 e Safety Net to Improve the Post Limited 1,000.00 0.00 2022-06-24 2022-08-11 2023-02-07 tions nvelope ementation dling Urban Environment ET-AMHARA SEKOTA-298613 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl -GO-RFQ / Industrial construc IDA / D7320 e Safety Net to Improve the Post Limited 12,500.00 0.00 2022-07-01 2022-07-27 2022-08-16 tions nvelope ementation tion materials Urban Environment ET-AMHARA SEKOTA-298615 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl -GO-RFQ / Local construction IDA / D7320 e Safety Net to Improve the Post Limited 4,000.00 0.00 2022-06-27 2022-07-28 2022-08-27 tions nvelope ementation materials Urban Environment ET-AMHARA SEKOTA-298617 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl -GO-RFQ / Tree and fruit seed IDA / D7320 e Safety Net to Improve the Post Limited 1,000.00 0.00 2022-06-29 2022-08-02 2022-08-22 tions nvelope ementation lings Urban Environment NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3