Procurement Plan For Integrated Development for Source Sustainability and Climate Resilient Rain-fed Agriculture Project A World Bank Financed Project Project ID: P165129 [Procurement Plan Period: First 18 months of the Project] Covering the Period: January 2020 to June 2021 Submitted By Project Management Unit [PMU] Himachal Pradesh Forest Department Government of Himachal Pradesh India 2 3 PROCUREMENT PLAN Country: INDIA Borrower: Government of India on behalf of Government of Himachal Pradesh Project Name: Integrated Development for Source Sustainability and Climate Resilient Rain-fed Agriculture Project Project Implementation Agency: Project Management Unit [PMU], Himachal Pradesh Forestry Department [HPFD], Government of Himachal Pradesh Date of General Procurement Notice: December 18, 2019 Bank’s Approval Date of the Procurement Plan: Original … Revision 1: Revision 2: Date of the Procurement Plan: December 2019 Period covered by this Procurement Plan: January 2020 to June 2021 Applicable Procurement Rules. The Procurement of goods, works, consulting and non-consulting services to be financed by the Loan will be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers [dated July 2016; revised November 2017 and August 2018], and the provisions of the Loan Agreement. If there is conflict between government decrees, rules, and regulations and the Bank Procurement Regulations, then Bank’s Procurement Regulations shall prevail. The project will be subject to World Bank Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by IBRD Loans and IDA Credits and Grants [“Anti-Corruption Guidelines”], dated October 15, 2006 and revised in January 2011 and as of July 1, 2016. The project will use the online tool Systematic Tracking of Exchanges in Procurement [STEP] to prepare, clear, and update its procurement plan, for monitoring procurement activities and for communication between the Borrower and the Bank. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under Paragraph 4.4 of the Procurement Regulations are set forth in STEP. Unless otherwise agreed with the World Bank, the World Bank’s Standard Procurement Documents [SPD], Requests for Proposals, and Forms of Consultant Contract will be used. Procurement under national procedures will be carried out based on National Procurement Procedures [NPP] conditions agreed with the Government of India. Procurement estimated at Indian Rupees [INR] 5 Lakhs and above will be submitted through government eProcurement systems provided by NIC 4 www.hptender.gov.in which have been assessed and deemed acceptable by the Bank against Multilateral Development Bank [MDB] requirements. Financial Management [FM] Manual. The FM Manual prepared for the project shall have a separate chapter on Procurement which will provide clear guidance on applicable procurement arrangement, procedures and thresholds, and shall be made available on the project website. Community Operations Manual [COM]. The COM prepared for the project will have clear directives for the community [GPs/individual beneficiaries] with regard to eligible procurement expenditures and agreed procurement arrangements, procedures and thresholds, and shall be made available on the project website. This will serve as a guidebook for procurement, with a view to providing operating instructions and bring in greater transparency and predictability in procurement procedures under the Project. Procurement Arrangements and Profile. Procurement under the Project will be carried out at the central level by the Project Management Unit [PMU] headed by the Chief Project Director [CPD] established for the Project, at the District level by the District Project Officers assisted by the Accounts Assistant at the District Level in each of the 10 District Project Offices [DPOs] located in the Districts covered under the Project [Shimla, Solan, Sirmour, Bilaspur, Hamirpur, Mandi, Kullu, Chamba, Kangra and Una], and by beneficiary GPs [supported by DPOs] at the GP level, in accordance with their approved Gram Panchayat Resource Management Plans [GP-RMP]/MG/OMIF. Officials of the PMU have prior experience of implementing a World Bank financed project and have also undergone training in STEP. GPs will need to be capacitated and provided basic procurement training on applicable procurement procedures and procurement documentation requirements outlined in COM, before initiating their procurements. To meet the readiness requirements of the Department of Economic Affairs [DEA] of the Government of India, the Project has already initiated and awarded contract for critical consultancy package for Environmental and Social Assessment to be retroactively financed by the Bank. The project envisages procurement of low-risk, low-value goods, works and services as below: a. Goods and Non-Consulting Services to be procured under the project are likely to include the following. At State/PMU level, purchase of IT Equipment such laptops, computers, printer, etc., procurement of printing services for IEC, office vehicles, office furniture, etc. are envisaged. At District and GP level, procurement activities will include procurement of Barbed Wire, U/Staple, Tools, Gunny Bags, Vermicompost/ Farm yard Manure, Sand, Seeds, Wooden posts/ poles, Seedlings, Grass tufts, Sign boards/hand prints, seed testing instrument, Seed, Fertilizer, Pesticide, Livestock - Small and Large Ruminants, Agricultural Tools and Implements, equipment, Farm machinery, e.g., power tiller, chaff cutters, pipes, tarpaulins, Medicines, supplements, sprinklers, seedlings, etc. b. Procurement of Minor Civil Works is likely to include the following. At State/ PMU level, procurement of minor civil works will include extension, refurbishment and repair of office buildings, etc. At District and GP level, procurement activities will include procurement of works for construction of Water storage tanks, water channels, vermicompost pits, livestock Mangers, foot bridges, water lifting pumps, GI pipes, accessories, installation of ropeways, Ponds, Check Dams, Subsurface Dykes, Sump Wells etc. and labor contracts for preparing land 5 for nursery, preparing nursery beds, water tank, works of filling gunny bags, sowing of seeds, preparing temporary nursery sheds, watering, hoeing, weeding, , fencing, bush cutting, pit digging, planting seedlings, preparing contour trenches, planting grass tufts, drainage line treatment works, fire management works, allowances and incentives for fire management, Spring development, eradication of exotic weed- lantana, etc. It may be noted that civil works at GP level are demand driven. There are no major civil works contracts envisaged in the project. c. Consultancy Services to be procured under the project are likely to include services for developing a web-based portal for Integrated Financial Management Information System [IFMS], Water Monitoring and Modelling, Value Chain Scoping Studies, Technical Support Study for addressing the needs of Transhumant, M and E, MIS, Baseline Survey, External and Internal Audit, Third Party Verification agent to verify achievement of Disbursement Related Results [DLR]s, need based assessments and studies, individual experts, etc. No consultancy services contracts envisaged at the District/Sub-district levels. The project includes several features of a decentralized, demand-driven project, and activities to be taken up at the community level by selected beneficiaries shall be as per the GP-RMP approved by the PMU of the HP Forestry Department/MG/OMIF. The threshold of procurement activities at community level is expected not to exceed Request for Quotation [RFQ] threshold. Community-level procurement shall follow Community-Driven Development [CDD] arrangements as per the Bank’s Procurement Regulations and as outlined in the Community Operations Manual [COM] currently under preparation. Given other on-going government programs, the activities to be funded following COM shall be identified upfront to avoid double-dipping and will require very close monitoring and oversight. Project Procurement Strategy for Development [PPSD] and Procurement Plan. According to the requirement of the Regulations, a Project Procurement Strategy for Development [PPSD] has been developed, based on which the Procurement Plan for the first 18 months has been prepared. The PPSD describes how procurement in this project will support the Project Development Objective [PDO] and deliver value for money under a risk-based approach. It provides adequate supporting market analysis for the selection methods detailed in the procurement plan. The procurement plan specifies for each contract: [i] a description of the activities/contracts; [ii] selection methods to be applied; [iii] estimated cost; [iv] time schedules; [v] World Bank review requirements; and [vi] any other relevant procurement information. PMU shall submit to the World Bank, for its review and approval, any updates of the procurement plan approved by the World Bank. The project will use Systematic Tracking of Exchanges in Procurement [STEP] system for all its procurement activities carried out at the PMU [Centre] and District levels. Summary from PPSD. The project is preparing its Procurement Strategy document. As per the draft document, the project’s total value is US $100 million of which procurement spend is approximately 80 %. Extensive market analysis has been carried out for procurement packages and decisions on packages are made to ensure adequate participation of bidders. Consultancy contracts are framed based on market research and packaging decided in terms of scope of services and period. Based on the need assessment, the project has decided to 6 use Government e Marketplace [GeM]1 for procurement of Goods up to US $100,000 and as mentioned under the paragraph in the Procurement Plan on National Procurement Procedures. Procurement Capacity Building. Though project staff has past experience of implementing World Bank financed HP Mid-Himalayan Watershed Development Project [HPMHWDP] governed by the Bank’s Procurement Guidelines, however, they need to be exposed to the Procurement Regulations applicable to the Project. HP Forestry Department will be sending key procurement staff of PMU and DPOs to the Indian Institute of Management [IIM], Lucknow or the Administrative Staff College of India [ASCI], Hyderabad from time to time to attend procurement training on World Bank Procurement Framework [PF] applicable to the project. Presently, project staff from PMU and two DPOs will be attending the two-week residential training program on World Bank Procurement Regulations conducted at ASCI, Hyderabad in February 2020. These officials will subsequently provide training to other project staffs prior to implementation of the procurement activities in the project. The PMU/DPOs/APOs will also provide basic procurement training to GPs/Beneficiaries once the Gram Panchayat Resource Management Plan [GP-RMP] is approved by DPO/PMU, and before commencing implementation of GP-RMP. The project officials can also avail of the free Massive Open Online Course on public procurement www.procurementlearning.org offered by the Bank to build their capacity. The Bank had already conducted one training on STEP for PMU officials and will organize STEP training again on need basis for the concerned DPOs staff in near future. Procurement Planning. For each contract to be financed by the Loan, the different procurement methods or consultant selection methods to be used, the need for pre-qualification, estimated costs, prior review requirements, and time frame will be reflected in the Procurement Plan to be agreed between the Borrower and the Bank team. The Procurement Plan will be uploaded in STEP by PMU/DPOs and the approved procurement plan will be disclosed on the project website and Bank’s external website. The procurement plan for the first 18 months of project implementation and all its updates will be submitted to the Bank through STEP, and will lay out the appropriate, fit for purpose market approach and selection methods for procurement of goods, works, non-consulting and consulting services financed by the Bank. It will be updated at least annually or as required to reflect the actual project implementation needs and improvements in institutional capacity. eProcurement. Currently, the Himachal Pradesh Forestry Department of the Government of Himachal Pradesh is using e-procurement system for its procurement. However, PMU housed in the Forestry Department will be carrying out procurement using eProcurement for the first time in the project, therefore, their capacity building needs to be done for eProcurement. The project will make use of Government of India’s National Informatics Centre [NIC] platform assessed by the Bank against Multilateral Development Bank [MDB] requirements for procurements estimated at INR 5 Lakhs and above. Advance Contracting with Retroactive Financing. For effective project implementation and start-up, the project has initiated advance contracting of critical consultancies for Preparation of Environmental and Social Framework [ESF] and Project Implementation Plan [PIP], and procurement of small value goods such 1 https://gem.gov.in/ 7 as tools, gunny bags, seeds, IT equipment and accessories, vehicles, etc.] and works [very small value labor contracts for Development of Nurseries [52 nos.] in 26 clusters in 10 Districts covering 428 GPs. The total value of this spend is approximately 1.2 % of the Bank loan. Payment made by PMU/HPFD for these contracts following World Bank procurement procedures during the 12 months prior to the tentative Loan signing date shall be eligible for retroactive financing. Record Keeping. All records pertaining to award of tenders/selection of consultants, including tender notification/advertisement, register pertaining to sale and receipt of bids, bid/proposal opening minutes, bid/technical and financial evaluation reports, comparative statements, Goods, Receipt Note [GRN] and all correspondence pertaining to bid evaluation, communication sent to/with the Bank in the process, bid securities, and approval of invitation/evaluation of bids/proposals would be maintained by the PMU and at DPO/GP level. Contract Management. The PMU, HPFD will be responsible for overall procurement and contract management under the project. At the Centre, procurement staff will be responsible for contract monitoring and supervision of contracts awarded by PMU. At DPO level, contract monitoring and supervision will be done by technical staff at DPOs/APOs level [Agriculture, Animal Husbandry/Engineering staff of technical wing of DPO level and Forest Extension and Social Extension staff at APO level] to ensure timely delivery of quality outputs from the procurement contracts in the project areas. All payments will be made by DPOs for district and sub-district level procurements after receipt of Goods receipt Note [GRN]. Work Completion Certificates, etc. The Integrated Financial Management Information System [IFMIS] being developed under the Project will facilitate monitoring of various procurement activities in terms of physical and financial achievements on a monthly basis. The day to day monitoring of procurement activities will be done by APOs/DPOs at field level which will be updated in the online web-based system at district level and will be reviewed by PMU at the Centre. Complaint Handling Mechanism. A complaint handling mechanism to address procurement-related complaints under the Project will be developed and implemented by the PMU/DPOs to the satisfaction of the Bank. Upon receipt of complaints, immediate action would be initiated to acknowledge the complaint and to redress it within a reasonable timeframe. All complaints will be addressed at levels higher than the level at which the procurement process was undertaken, or the decision was taken. Any complaint received will also be forwarded to the Bank for information, and the Bank would be kept informed after the complaint is redressed. Leased Assets: Not Applicable Procurement of Secondhand Goods: Not Applicable Domestic Preference: The provision of domestic preference will be applied in the evaluation of bids in accordance with Annex VI of the Regulations. Procurement Thresholds and Prior Review Thresholds. The table below describes various procurement methods to be used for activities financed by the Loan. 8 Table 1: Procurement Thresholds Procurement approach and method Thresholds [US$ equivalent] Open International [Goods, IT, and >10 million Non-consulting services] – Request for Bids [RFB] Open National [Goods, IT, and Non- >100,000 and up to 10 million consulting services] – Request for Bids [RFB] National Request for Quotation Up to 100,000 [RFQ] – [Goods/Works/Non- consulting Services] Open International [Works] – >40 million Request for Bids [RFB] Open National [Works] - Request for >100,000 and up to 40 million Bids [RFB] Direct Selection With prior agreement, based on justification Framework Agreement For Goods/Works/Non-consulting services: According to paragraphs 6.57-6.59 of Section VI of the Regulations. For Consulting services: According to paragraph 7.33 of Section VII the Regulations. Force Account In accordance with paragraphs 6.54 and 6.55 of Section VI of the Procurement Regulations, and with prior agreement in Procurement plan with the Bank. Consulting Services [Firms] CQS: As per requirements of paragraphs 7.11 and 7.12 of Section VII of the Regulations. LCS, FBS: in justified cases QCBS, QBS: in all other packages Shortlist of National Consultants Up to 800,000 Procurement prior-review thresholds2. Based on the current procurement risk rating of ‘Moderate’, the World Bank will prior review the following contracts: (a) Works [including turnkey, supply and installation of plant and equipment and PPP]: All contracts more than US $15 million equivalent 2 Determination of whether a contract meets the prior review threshold is based on : (i) the total value of the contract, including all taxes and duties payable under the contract; (ii) a contract whose cost estimate was below the Bank’s prior review threshold is subject to prior review if the price of the lowest evaluated responsive bid (or, in the case of consulting services, the financial offer of the selected firm) exceeds such threshold at the bid evaluation stage; and (iii) in the case of a slice and package arrangement, the prior review threshold is determined based on the aggregate value of individual contracts to be awarded under such arrangement. 9 (b) Goods and Information Technology: All contracts > US $4 million equivalent (c) Non-consulting Services: All contracts > US $4 million equivalent (d) Consulting Services: Firms: All contracts >US $2 million equivalent (e) Consulting Services: Individuals: All contracts > US $400,000 equivalent (f) Direct Selection: The justification of Direct Selection for all contracts The above thresholds are for the initial 18-month implementation period. Based on the procurement performance of the project, these thresholds may be subsequently modified. Even for large-value post review cases, the inputs of the World Bank on technical specifications will be obtained by the project. Irrespective of the thresholds, Terms of Reference shall be prior reviewed by Bank. The prior review thresholds will also be indicated in the Procurement Plan. The Procurement Plan will be subsequently updated annually [or at any other time if required] and will reflect any change in the prior review thresholds. The details of National Procurement Procedures are outlined in the Procurement Plan. Prior review contracts. In the case of contracts subject to prior review, PMU, HPFD/DPOs will seek the World Bank’s no objection before granting/agreeing to: [a] an extension of the stipulated time for performance of a contract that either increases the contract price or has an impact on the planned completion of the project; [b] any substantial modification of the scope of Works, goods, IT system; non-consulting services, or consulting services and other significant changes to the terms and conditions of the contract; [c] any variation order or amendment [except in cases of extreme urgency] that, singly or combined with all variation orders or amendments previously issued, increases the original contract amount by more than 15 percent; and [d] the proposed termination of the contract. Complaints received in all prior review cases shall be sent to Bank for review and the response to the complaint in such cases, shall be cleared with the Bank. Complaints with allegations of fraud and corruption, shall be shared with Bank, irrespective of the thresholds. Disclosure of procurement information. The following documents shall be disclosed on the project/state websites: [a] Procurement Plan and its updates; [b] an invitation for bids for procurement of Works, Goods, IT system procurement and non-consulting services; [c] request for expression of interest for selection/hiring of consulting services; [d] contract awards of Works, Goods, IT system procurement and non-consulting services procured following international and national procedures; [e] a list of contracts/purchase orders placed following RFQ [Request for Quotation] procedures on a quarterly basis; [f] a list of contracts following direct contracting [DC] on a quarterly basis; [g] an annual financial and physical progress report of all contracts; and [h] an action taken report on the complaints received on a quarterly basis. The following details shall be sent to the World Bank for publishing on the United Nations Development Business and the World Bank external website: [a] Specific Procurement Notice [i.e., invitation for bids] for procurement of Works, Goods, IT system procurement and non-consulting services using open international procedures; [b] Requests for Expression of Interests above US $800,000; [c] contract award details of all procurement of Works, Goods, IT system procurement and non-consulting services using open international procedure; and [d] a list of contracts/purchase orders placed following DC procedures on a quarterly basis. Further, the implementing agency will also publish on their websites any information required under the provisions of ‘suo moto’ disclosure as specified by the Right to Information Act. 10 National Procurement Procedure Conditions. National competition for the procurement of Works, Goods, IT system procurement and non-consulting services according to the established thresholds will be conducted in accordance with paragraphs 5.3–5.5 of Section V of the Regulations and the following provisions: I. Only the model bidding documents for National Competitive Procurement [NCP] agreed with the GOI Task Force [and as amended for time to time], shall be used for bidding. II. Invitations to bid shall be advertised on a widely used website or electronic portal with free open access at least 30 days prior to the deadline for the submission of bids, unless otherwise agreed in the approved procurement plan. III. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state- owned enterprises, small-scale enterprises or enterprises from any given State. IV. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder. V. Government e-Marketplace [GeM] set-up by Ministry of Commerce, Government of India will be acceptable for procurement under Request for Quotations [RFQ] method. VI. At the Borrower’s request, the Bank may agree to the Borrower’s use, in whole or in part, of its electronic procurement system, provided that the Bank is satisfied with the adequacy of such system. VII. Procurement will be open to eligible firms from any country. This eligibility shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. VIII. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals include a signed acceptance in the bid, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. IX. The Borrower shall use an effective complaints mechanism for handling procurement related complaints in a timely manner. X. Procurement Documents will include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social [including sexual exploitation and abuse and gender-based violence], health and safety [“ESHS”] risks and impacts. Oversight and Monitoring by the Bank. All contracts not covered under prior review by the Bank will be subject to post review during implementation support missions and/or special post review missions, including missions by consultants hired by the Bank. The Bank may conduct, at any time, Independent Procurement Reviews [IPRs] of all the contracts financed under the loan. High risk procurements, if any, will be identified for increased procurement and contract management support and indicated in the procurement plan. Bank team will provide additional due diligence and independent review of the contract performance of such identified procurements. 11 Procurement Review by the PMU, HPFD. Independent procurement post review [PPR] with reporting requirements and agreed with the Bank [As per Para 4 of Annex II of the Procurement Regulations] will be undertaken for the project for PMU’s own internal due diligence. PMU will hire PPR consultants as per Terms of Reference and reporting requirements agreed with the Bank to conduct PPR of PMU and DPOs on a half yearly basis. Other Special Selection Arrangements/Requirement Procurement by communities will be governed by the procedures outlined in the Community Operations Manual [COM] currently under preparation and in accordance with Paras 6.52 and 6.53 of Section VI of the Regulations. COM will be disclosed on the Project website. Procurement Plan as per STEP Tables: 12 PROCUREMENT India : Integrated Project for Source Sustainability and Climate Resilient Rain-fed Agriculture in Himachal Pradesh PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2020-10-12 Revised Plan Date(s): (comma delineated, leave blank if 2022-07-22 none) Project ID: P165129 GPN Date: 2019-12-19 Project Name: Integrated Project for Source Sustainability and Climate Resilient Rain-fed Agriculture in Himachal Pradesh Loan / Credit No: IBRD / 90410 District Project Office, Kangra, Himachal Pradesh Forestry Department Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-DPO, KANGRA-178845-C Component 1. Sustainable L W-RFQ / Development of Ne Request for Quota Single Stage - One E 2021-08-1 IBRD / 90410 and and Water Resource Ma Post Limited 3,850.00 3,915.49 Completed 2020-12-31 2020-02-26 2021-02-16 2020-03-17 w Nursery Site at Shivnagar tions nvelope 5 nagement under APO Panchrukhi IN-DPO, KANGRA-178850-C W-RFQ / Development of Ne Component 1. Sustainable L Request for Quota Single Stage - One E 2021-02-0 w Nursery Site at Tatehal un IBRD / 90410 and and Water Resource Ma Post Limited 2,580.00 2,609.88 Completed 2020-06-15 2020-02-26 2020-08-10 2020-03-16 tions nvelope 6 der APO Panchrukhi. this acti nagement vity is already completed and is bein uploaded now. IN-DPO, KANGRA-178852-C W-RFQ / Development of Ne Component 1. Sustainable L Request for Quota Single Stage - One E 2021-02-0 w Nursery Site at Ochha und IBRD / 90410 and and Water Resource Ma Post Limited 2,375.00 3,317.59 Completed 2020-06-15 2020-02-26 2020-08-10 2020-03-17 tions nvelope 6 er APO Nagrota. this activity i nagement s already executed and is bei ng uploaded now. IN-DPO, KANGRA-178853-C Component 1. Sustainable L W-RFQ / Raising of Seedling Request for Quota Single Stage - One E 2021-02-0 IBRD / 90410 and and Water Resource Ma Post Limited 3,250.00 3,891.04 Completed 2020-06-15 2020-02-27 2020-08-10 2020-03-17 at Shivnagar Nursery under A tions nvelope 6 nagement PO Unit Panchrukhi IN-DPO, KANGRA-178868-C Component 1. Sustainable L Request for Quota Single Stage - One E 2021-02-0 W-RFQ / Raising of seedlings IBRD / 90410 and and Water Resource Ma Post Limited 1,950.00 2,445.49 Completed 2020-06-15 2020-02-27 2020-08-10 2020-03-17 tions nvelope 6 in Tatehal Nursery under APO nagement Panchrukhi IN-DPO, KANGRA-178870-C W-RFQ / Raising of nursery s Component 1. Sustainable L Request for Quota Single Stage - One E 2021-02-0 eedling in Nursery Ochha un IBRD / 90410 and and Water Resource Ma Post Limited 1,950.00 4,059.04 Completed 2020-06-15 2020-02-27 2020-08-10 2020-03-17 tions nvelope 6 der APO Nagrota, this activity nagement is already completed is bein g uploaded now. IN-DPO, KANGRA-178886-C W-RFQ / CW-RFQ / Pre-monso on/ advance work for raising Component 1. Sustainable L of plantations along drainage Request for Quota Single Stage - One E 2020-10-0 IBRD / 90410 and and Water Resource Ma Post Limited 49,700.00 40,053.46 Completed 2020-06-15 2020-06-12 2020-08-06 2020-07-20 line (both side of stream) i.e. tions nvelope 5 nagement fencing of plantation area wit h wooden poles and barbed wire. There are 7 jobs (contra ct) at different locations havi ng 2 to 5 ha area. IN-DPO, KANGRA-178923-C W-RFQ / CW-RFQ / Pre-monso on/ advance work i.e. fencing of plantation area with wood Component 1. Sustainable L Request for Quota Single Stage - One E 2020-09-2 en fence post and barbed wir IBRD / 90410 and and Water Resource Ma Post Limited 29,800.00 28,812.77 Completed 2020-06-20 2020-06-12 2020-07-27 2020-07-20 tions nvelope 5 e for raising of plantation in t nagement he rainy season of 2020 in th e forest area having open ca nopy @ 800 plants per/ha. Th ere will be 7 jobs (contract). IN-DPO, KANGRA-178936-C W-RFQ / CW-RFQ / Pre-monso on/ advance work i.e. fencing Component 1. Sustainable L of plantation area with wood Request for Quota Single Stage - One E 2020-09-3 IBRD / 90410 and and Water Resource Ma Post Limited 25,000.00 23,504.96 Completed 2020-06-15 2020-06-12 2020-08-01 2020-07-20 en fence post and barbed wir tions nvelope 0 nagement e for raising of plantation in t he rainy season of 2020 in th e forest area to increase tree cover by planting 400 plants per/ha. IN-DPO, KANGRA-178947-C W-RFQ / Raising of plantation s In the rainy season of 2020 Component 1. Sustainable L along drainage line on both s Request for Quota Single Stage - One E 2020-10-1 IBRD / 90410 and and Water Resource Ma Post Limited 11,500.00 10,757.11 Completed 2020-06-20 2020-06-15 2020-07-31 2020-07-20 ide of stream with fast growi tions nvelope 4 nagement ng forestry species @ 1100 p lants per/ha is done in 17 ha . at 7 different sites . This act ivity is completed and being uploaded now. IN-DPO, KANGRA-178949-C W-RFQ / Raising of plantation s in the rainy season of 2020 in the forest area having ope Component 1. Sustainable L Request for Quota Single Stage - One E 2020-10-0 n canopy (tree density less t IBRD / 90410 and and Water Resource Ma Post Limited 25,100.00 23,035.61 Completed 2020-06-15 2020-06-15 2020-07-20 2020-07-20 tions nvelope 3 han 0.4) @ 800 plants per/ha nagement . There are jobs (contract) of 2 to 10 ha area in different c atchments. The work is comp leted and being uploaded no w IN-DPO, KANGRA-178955-C W-RFQ / Raising of plantation s in the rainy season of 2020 Component 1. Sustainable L Request for Quota Single Stage - One E 2020-10-1 in the forest area were initia IBRD / 90410 and and Water Resource Ma Post Limited 11,700.00 10,821.40 Completed 2020-06-15 2020-06-15 2020-07-30 2020-07-20 tions nvelope 3 ted in 39 ha @ 400 plants pe nagement r/ha. There are fix jobs (contr act) of 4 to 10 ha area in diff erent catchment. IN-DPO, KANGRA-178956-C W-RFQ / Pre-winter/ advance work i.e. fencing of plantatio Component 1. Sustainable L Request for Quota Single Stage - One E 2021-03-2 n area with wooden fence po IBRD / 90410 and and Water Resource Ma Post Limited 6,400.00 5,570.93 Completed 2020-12-03 2020-10-28 2020-12-29 2020-12-01 tions nvelope 9 st and barbed wire for raising nagement of plantation in the winter se ason of 2020 in the forest ar ea having open canopy @ 80 0 plants per/ha. Page 1 IN-DPO, KANGRA-178968-C W-RFQ / Contour trenching in plantation area including gra Component 1. Sustainable L Request for Quota Single Stage - One E 2021-02-1 ss seeding in 106 ha. This act IBRD / 90410 and and Water Resource Ma Post Limited 22,900.00 23,120.17 Completed 2020-07-14 2020-06-15 2020-08-21 2020-07-20 tions nvelope 7 ivity has been executed and nagement being uploaded now. there ar e 14 jobs (contract) involving 14 sites at different locations . IN-DPO, KANGRA-178983-C W-RFQ / Treatment of Draina Component 1. Sustainable L ge Line (Soil Conservation W Request for Quota Single Stage - One E Under Imple 2021-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 475,300.00 0.00 2020-12-05 2020-12-16 2021-01-30 orks) by constricting Vegetati tions nvelope mentation 1 nagement ve check barriers, Dry stone check barriers, Create Wire c heck barriers, CC check barri ers IN-DPO, KANGRA-178984-C W-RFQ / Renovation and impr ovement of already existing Natural Water Sources (Well, Component 1. Sustainable L Request for Quota Single Stage - One E 2021-03-2 springs, traditional water bau IBRD / 90410 and and Water Resource Ma Post Limited 53,500.00 51,464.62 Signed 2020-12-20 2021-04-09 2021-01-27 2021-02-26 tions nvelope 8 ries,etc) and to improve the nagement water availability and hydro-l ogical health there will be 30 to 50 different jobs (contract s) in different locations. IN-DPO, KANGRA-178985-C W-RFQ / Management of exot Component 1. Sustainable L ic species - Removal of Lanta Request for Quota Single Stage - One E 2021-03-2 IBRD / 90410 and and Water Resource Ma Post Limited 110,450.00 114,050.24 Completed 2020-11-20 2020-10-28 2021-01-08 2020-12-01 na from target area by cut r tions nvelope 4 nagement oot stock method (75 to 100 % ) in 215 ha. at 25 to 35 diff erent locations IN-DPO, KANGRA-179055-C W-RFQ / three nurseries shall Component 1. Sustainable L be developed Baldhar in clus Request for Quota Single Stage - One E 2021-03-2 IBRD / 90410 and and Water Resource Ma Post Limited 6,000.00 5,953.51 Signed 2020-11-20 2020-10-28 2020-12-21 2020-11-21 ter- I under APO Nagrotabag tions nvelope 1 nagement wan and two under APO Baij nath shall be done cluster wi se at Shodgun and Kandwari . IN-DPO, KANGRA-179064-C W-RFQ / The raising of seedli ngs in six nurseries will be d Component 1. Sustainable L Request for Quota Single Stage - One E 2021-06-3 one during the financial yea IBRD / 90410 and and Water Resource Ma Post Limited 70,000.00 70,679.05 Signed 2020-11-20 2020-10-28 2021-01-01 2020-11-21 tions nvelope 0 r 2020-21 for planting during nagement 2021-22. Total 315000 seedli ngs will be raised at differen t location . IN-DPO, KANGRA-179083-C W-RFQ / Pre-monsoon/ advan ce work i.e. fencing of planta Component 1. Sustainable L tion area with wooden fence Request for Quota Single Stage - One E 2021-10-2 IBRD / 90410 and and Water Resource Ma Post Limited 231,400.00 207,025.52 Completed 2021-06-25 2021-06-04 2021-07-24 2021-06-28 post and barbed wire for raisi tions nvelope 2 nagement ng of plantation in the rainy s eason of 2021 in the forest a rea to increase tree cover by planting 400 plants per/ha. IN-DPO, KANGRA-179091-C W-RFQ / Pre-monsoon/ advan ce work i.e. fencing of planta Component 1. Sustainable L tion area with wooden fence Request for Quota Single Stage - One E 2021-10-1 IBRD / 90410 and and Water Resource Ma Post Limited 63,400.00 59,789.11 Completed 2021-06-20 2021-06-04 2021-07-19 2021-06-28 post and barbed wire for raisi tions nvelope 7 nagement ng of plantation in the rainy s eason of 2021 in the forest a rea having open canopy @ 8 00 plants per/ha. IN-DPO, KANGRA-179094-C W-RFQ / Pre-monsoon/ advan ce work i.e. fencing of planta Component 1. Sustainable L tion area with wooden fence Request for Quota Single Stage - One E 2021-10-0 IBRD / 90410 and and Water Resource Ma Post Limited 260,000.00 132,026.01 Completed 2021-06-10 2021-06-04 2021-07-09 2021-06-28 post and barbed wire for raisi tions nvelope 7 nagement ng of D.L.T. plantations@ 11 00 plants per/ha in 83 ha dur ing the rainy season of 2021 for treatment of 44 different drainage lines IN-DPO, KANGRA-179096-C Component 1. Sustainable L W-RFQ / Contour trenching in Request for Quota Single Stage - One E 2022-01-2 IBRD / 90410 and and Water Resource Ma Post Limited 115,560.00 109,176.29 Completed 2021-06-09 2021-05-05 2021-07-29 2021-06-28 plantation area including gra tions nvelope 5 nagement ss seeding. there will be 35 t o 50 jobs (contract). IN-DPO, KANGRA-179110-C W-RFQ / Repair, Maintenance and Wood ceiling/ Paneling of Component 1. Sustainable L Request for Quota Single Stage - One E 2021-03-1 DPO Residence Dharamshala IBRD / 90410 and and Water Resource Ma Post Limited 8,000.00 4,490.61 Completed 2020-11-05 2020-06-12 2020-11-18 2020-11-09 tions nvelope 8 , Electric, sanitary , flooring nagement & distemper painting and ot her minor repair etc. there wi ll be 4 to 5 jobs. IN-DPO, KANGRA-182918-C W-RFQ / Procurement of Nurs ery Plants. 25000 nursery pla nts,17000 Dendrocalamus str Component 1. Sustainable L Request for Quota Single Stage - One E 2020-09-2 ictus (Bamboo) ,4000 Phyllan IBRD / 90410 and and Water Resource Ma Post Limited 5,000.00 4,754.14 Completed 2020-07-14 2020-06-12 2020-08-21 2020-07-13 tions nvelope 0 thus emblica (Amla) and 400 nagement 0 Szygium cumini have been procured during July ,2020 f or use in plantations during monsoon season. IN-DPO, KANGRA-184075-C W-RFQ / Primary water harve Component 1. Sustainable L sting and storage, constructi Request for Quota Single Stage - One E 2021-05-2 IBRD / 90410 and and Water Resource Ma Post Limited 36,180.00 19,081.26 Completed 2020-12-20 2021-02-26 2021-01-27 2021-03-01 on of ponds manual excavati tions nvelope 7 nagement on.there will be 15 to 20 diffe rent jobs (contracts) in differ ent locations. IN-DPO, KANGRA-184183-C W-RFQ / Management of exot Component 1. Sustainable L ic species Removal of Lanta Request for Quota Single Stage - One E 2021-03-2 IBRD / 90410 and and Water Resource Ma Post Limited 48,800.00 49,974.66 Completed 2020-11-20 2020-10-28 2021-01-08 2020-12-01 na from targeted area infeste tions nvelope 4 nagement d with lantana 50% to 75% b y cut root stock method in 1 16ha. IN-DPO, KANGRA-184184-C W-RFQ / Management of exot ic species - Removal of Lanta Component 1. Sustainable L na from target area by cut r Request for Quota Single Stage - One E 2021-03-2 IBRD / 90410 and and Water Resource Ma Post Limited 18,500.00 18,994.95 Completed 2020-10-05 2020-10-28 2020-11-23 2020-12-01 oot stock method with lantan tions nvelope 3 nagement a infestation 25 to 50% in 56 ha There will be six no's of di fferent jobs (contracts) at six different locations. Page 2 IN-DPO, KANGRA-184185-C W-RFQ / Management of exot Component 1. Sustainable L Request for Quota Single Stage - One E 2021-03-1 ic species - Removal of Lanta IBRD / 90410 and and Water Resource Ma Post Limited 3,655.00 3,753.71 Completed 2020-12-05 2020-10-28 2021-01-09 2020-12-01 tions nvelope 0 na from target area by cut r nagement oot stock method (up to 25% ) IN-DPO, KANGRA-189862-C W-RFQ / The grass sowing/ tu ft planting along drainage lin Component 1. Sustainable L Request for Quota Single Stage - One E 2021-03-2 e plantations in 17 ha area at IBRD / 90410 and and Water Resource Ma Post Limited 2,180.00 2,244.60 Completed 2020-12-25 2020-10-28 2021-01-23 2020-12-01 tions nvelope 4 seven different locations in s nagement hall be been done during 202 0-21 using RFQ separately fo r each location . IN-DPO, KANGRA-178966-C W-RFQ / Pre-winter/ advance work i.e. fencing of plantatio Component 1. Sustainable L Request for Quota Single Stage - One E 2021-03-2 n area with wooden fence po IBRD / 90410 and and Water Resource Ma Post Limited 6,400.00 3,196.31 Completed 2020-12-03 2020-10-28 2020-12-26 2020-12-01 tions nvelope 6 st and barbed wire for raising nagement of plantation in the winter se ason of 2020 in the forest ar ea having open canopy @ 40 0 plants per/ha. IN-DPO, KANGRA-204495-C W-DIR / Demonstration and p romotion of climate resilient Component 1. Sustainable L Request for Quota Single Stage - One E 2021-07-1 agriculture for Rabi crops sha IBRD / 90410 and and Water Resource Ma Post Limited 8,500.00 8,179.19 Completed 2020-11-25 2020-10-23 2021-01-20 2021-05-05 tions nvelope 9 ll be done by involving lead f nagement armers and through institutio nal partnership with partner i nstitutions like SAU,KVK's. IN-DPO, KANGRA-220266-C W-RFQ / Raising of plantation Component 1. Sustainable L s in the winter season of 202 Request for Quota Single Stage - One E 2021-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 4,850.00 4,926.35 Completed 2021-02-19 2020-10-28 2021-03-09 2020-12-01 0-21 in the forest area UP107 tions nvelope 1 nagement p Nadli in GP Tatehal were ini tiated in 10ha @ 800 Plants p er/ha. IN-DPO, KANGRA-220267-C W-RFQ / Raising of plantation Component 1. Sustainable L Request for Quota Single Stage - One E 2021-04-0 s in the winter season of 202 IBRD / 90410 and and Water Resource Ma Post Limited 2,585.00 2,622.84 Completed 2021-02-19 2020-10-28 2021-03-10 2020-12-01 tions nvelope 1 0-21 in the forest area =10 h nagement a. Shajmlat Chombu in GP G adiyara @ 400 plants per/ha. IN-DPO, KANGRA-220272-C W-RFQ / Primary water harve Component 1. Sustainable L sting and storage, constructi Request for Quota Single Stage - One E 2021-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 66,700.00 88,901.34 Signed 2021-02-18 2021-02-05 2021-03-11 2021-03-01 on of ponds manual excavati tions nvelope 1 nagement on.there will be 31 different j obs (contracts) in different lo cations. IN-DPO, KANGRA-220275-C W-RFQ / Renovation and impr ovement of already existing Component 1. Sustainable L Natural Water Sources (Well, Request for Quota Single Stage - One E Pending Imp 2021-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 17,850.00 0.00 2021-02-19 2021-03-10 springs, traditional water bau tions nvelope lementation 0 nagement ries,etc) and to improve the water availability and hydro-l ogical health there will be 8 different jobs (contracts) in d ifferent locations. IN-DPO, KANGRA-220279-C Component 1. Sustainable L W-RFQ / Treatment of Draina Request for Quota Single Stage - One E 2021-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 50,000.00 46,477.59 Signed 2021-02-19 2021-02-12 2021-03-10 2021-03-01 ge Line (Soil Conservation W tions nvelope 0 nagement orks) by constricting CC che ck barriers. IN-DPO, KANGRA-220286-C W-RFQ / Primary water harve Component 1. Sustainable L sting and storage by constru Request for Quota Single Stage - One E Under Imple 2021-06-2 IBRD / 90410 and and Water Resource Ma Post Limited 80,000.00 0.00 2021-03-02 2021-02-26 2021-03-29 cting cement concrete check tions nvelope mentation 0 nagement dam. There will be site specif ic different jobs (contracts) a t different locations. IN-DPO, KANGRA-220314-C W-RFQ / Development of Mod ern Nursery includes constru ction of agro-net shed for roo Component 1. Sustainable L Request for Quota Single Stage - One E Pending Imp 2022-03-3 t trainers , poly house , Mali IBRD / 90410 and and Water Resource Ma Post Limited 66,700.00 0.00 2021-03-15 2021-05-10 tions nvelope lementation 1 hut, material mixing shed in nagement addition to site development , fencing , solar lights , devel opment of paths , irrigation and electric provision etc. IN-DPO, KANGRA-236896-C W-RFQ / Raising of plantation s is proposed during the rain y season of 2021 in the fores Component 1. Sustainable L Request for Quota Request for Quota Single Stage - One E 2021-09-1 t area having open canopy (t IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 60,000.00 53,282.61 Completed 2021-05-27 2021-06-04 2021-07-06 2021-06-28 tions nvelope 9 ree density less than 0.4)@ 8 nagement PD) 00 plants per/ha . There will be 20 to 30 jobs (contracts) o f 2 to 10 ha area in different GP's in Kangra District. IN-DPO, KANGRA-236909-C W-RFQ / Raising of plantation s during the rainy season of 2021 along drainage line on Component 1. Sustainable L Request for Quota Request for Quota Single Stage - One E 2021-09-2 both side of stream with fast IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 63,000.00 61,857.43 Signed 2021-06-02 2021-06-07 2021-07-13 2021-07-05 tions nvelope 6 growing forestry species @ 1 nagement PD) 100 plants per/ha is to be do ne in 83 ha. There will be 4 0to 50 jobs (contracts) of 1 t o 5 ha.at different site. IN-DPO, KANGRA-236910-C W-RFQ / Contour trenching in Component 1. Sustainable L Request for Quota Request for Quota Single Stage - One E 2022-02-0 forest areas outside the plant IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 23,900.00 25,236.94 Completed 2021-06-24 2021-08-18 2021-08-13 2021-10-04 tions nvelope 9 ation area including grass se nagement PD) eding. there will be 15 to 20 j obs (contract). IN-DPO, KANGRA-236912-C W-RFQ / The grass sowing/ tu ft planting along drainage lin Component 1. Sustainable L Request for Quota Request for Quota Single Stage - One E 2021-09-2 e plantation areas in 83ha ar IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 11,900.00 10,521.66 Completed 2021-06-25 2021-06-07 2021-07-24 2021-07-05 tions nvelope 2 ea at different locations in sh nagement PD) all be been done during 2021 -22 using RFQ separately for each location . Page 3 IN-DPO, KANGRA-236914-C W-RFQ / First year maintenan ce of 389 ha. plantation area Component 1. Sustainable L Request for Quota s done during 2020-21 under Request for Quota Single Stage - One E 2021-09-1 IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 45,000.00 47,465.56 Completed 2021-06-20 2021-06-07 2021-07-17 2021-06-28 different schemes i.e. draina tions nvelope 5 nagement PD) ge line treatment=103ha. ,re -afforestation=137ha. and en richment plantations=149ha. in district Kangra. IN-DPO, KANGRA-236917-C W-RFQ / Management of exot ic species -2nd year activity i Component 1. Sustainable L Request for Quota n the targeted area in 551 h Request for Quota Single Stage - One E Under Imple 2022-03-1 IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 42,900.00 40,950.03 2021-06-02 2021-06-04 2021-07-21 2021-06-28 a and 3rd year activity in the tions nvelope mentation 8 nagement PD) targeted area in 73 ha, wher e removal of Lantana was do ne by cut root stock during t he year 2020-21 and 2019-2 0 respectively. IN-DPO, KANGRA-237217-C W-RFQ / Removal of Lantana Component 1. Sustainable L Request for Quota Request for Quota Single Stage - One E 2022-03-2 from target area by cut root IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 52,190.00 67,618.47 Completed 2021-10-05 2021-09-24 2021-11-23 2022-01-11 tions nvelope 3 stock method (75 to 100% ) i nagement PD) n 110 ha. at 10 to 20 differen t locations IN-DPO, KANGRA-237230-C W-RFQ / Sub Surface Dykes/S ump well will be constructed Component 1. Sustainable L Request for Quota in the sandy type river beds Request for Quota Single Stage - One E Pending Imp 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 88,000.00 0.00 2021-09-05 2021-10-02 where impervious layer lies a tions nvelope lementation 1 nagement PD) t small depth to harvest the s ub-surface flow for the purpo se of irrigation. There will be site specific different jobs (co ntracts) IN-DPO, KANGRA-237254-C W-RFQ / Treatment of Draina ge Line by vegetative check Component 1. Sustainable L Request for Quota barriers. Vegetative check ba Request for Quota Single Stage - One E 2022-02-2 IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 10,000.00 6,788.03 Completed 2021-12-18 2022-01-01 2022-01-14 2022-01-27 rriers shall be provided by us tions nvelope 8 nagement PD) ing local species capable of s prouting in small and mediu m gullies having side slopes l ess than 45 degrees. IN-DPO, KANGRA-237259-C W-RFQ / filling of P/bags for r aising of seedling in eight nur Component 1. Sustainable L Request for Quota series at different location in Request for Quota Single Stage - One E 2022-02-1 IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 70,000.00 27,587.78 Completed 2021-09-06 2021-12-06 2021-10-18 2022-03-31 all four units during 2021-22 tions nvelope 5 nagement PD) for raising of new planting , maintenance of plantation ar eas and Agri-silvi pasture dis tribution@ 500 seedling per GP during 2022-23. IN-DPO, KANGRA-237260-C W-RFQ / Raising and mainten ance of seedling in p/bags in Component 1. Sustainable L Request for Quota all eight nurseries at differen Request for Quota Single Stage - One E 2022-09-1 IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 55,000.00 35,943.34 Completed 2021-10-04 2021-12-06 2021-11-15 2022-02-25 t location in all four units for tions nvelope 1 nagement PD) new planting , maintenance of plantation areas and Agri- silvi pasture distribution@ 50 0 seedling per GP during 202 2-23. IN-DPO, KANGRA-237268-C W-RFQ / Demonstration and promotion of climate resilient Component 1. Sustainable L Request for Quota Request for Quota Single Stage - One E Under Imple 2022-06-2 agriculture shall be done by i IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 43,000.00 0.00 2021-06-30 2022-04-04 2021-08-25 tions nvelope mentation 1 nvolving lead farmers and th nagement PD) rough institutional partnershi p with partner institutions lik e SAU,KVK's and Dr. YSP UHF . IN-DPO, KANGRA-237269-C W-RFQ / Secondary water dis tribution and water use effici Component 1. Sustainable L Request for Quota ency with tanks, channels, sp Request for Quota Single Stage - One E Under Imple 2022-03-2 IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 70,000.00 0.00 2021-09-20 2022-01-24 2021-10-17 rinklers etc and by constructi tions nvelope mentation 6 nagement PD) ng water harvesting, storage and distribution infrastructur e shall be developed to incre ase the water productivity . IN-DPO, KANGRA-237270-C W-RFQ / Primary Water Distri Component 1. Sustainable L Request for Quota Request for Quota Single Stage - One E Under Imple 2022-03-3 bution (Pipes & Pumps) for g IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 27,600.00 0.00 2021-10-05 2021-11-01 tions nvelope mentation 1 ravity and lift intake distribut nagement PD) ion system from primary wat er harvesting structures. IN-DPO, KANGRA-237272-C W-RFQ / construction of 10 to 12 foot bridges in different G Component 1. Sustainable L ram Panchayat in the Project Request for Quota Single Stage - One E Other (with field f 2022-03-2 IBRD / 90410 and and Water Resource Ma Post Limited 20,500.00 10,275.33 Completed 2021-11-06 2022-01-24 2021-12-21 2022-03-03 area of Kangra District to im tions nvelope or explanation) 1 nagement prove connectivity of the far mers from poor accessibility areas with the market for sup ply of inputs and sale of prod uce . IN-DPO, KANGRA-237234-C W-RFQ / Construction of CC c heck barriers for treatment o Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-0 f Drainage Line . There will b IBRD / 90410 and and Water Resource Ma Post Limited 99,300.00 31,388.08 Signed 2021-10-16 2022-01-27 2021-11-04 2022-03-07 tions nvelope or explanation) 4 e 40 to 50 Different jobs (Con nagement tracts) in different Gram Pan chayats in the selected Drai nage lines of the entire distri ct. IN-DPO, KANGRA-237228-C W-RFQ / Construction of 40 t o 50 ponds is proposed for Pr Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-1 imary water harvesting and s IBRD / 90410 and and Water Resource Ma Post Limited 97,800.00 65,614.57 Signed 2021-10-05 2022-03-01 2021-11-12 2022-02-12 tions nvelope or explanation) 2 torage at different locations nagement for harvesting rain water in the Project area in selected G P's of Kangra district . IN-DPO, KANGRA-237218-C W-RFQ / Renovation and impr ovement of 55 already existi ng Natural Water Sources (W Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-1 ell, springs, traditional water IBRD / 90410 and and Water Resource Ma Post Limited 94,000.00 77,381.09 Signed 2021-10-20 2022-01-24 2021-12-15 2022-02-12 tions nvelope or explanation) 5 bauries, etc ) to improve the nagement water availability and hydro-l ogical health ,there will be 5 5 different jobs (contracts) at different locations . Page 4 IN-DPO, KANGRA-237252-C W-RFQ / Treatment of Draina Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-3 ge Line (Soil Conservation W IBRD / 90410 and and Water Resource Ma Post Limited 20,400.00 32,210.29 Completed 2021-10-05 2022-01-01 2021-11-30 2022-02-12 tions nvelope or explanation) 0 orks) by constricting dry ston nagement e check barriers check barrie rs in Panchrukhi unit . IN-DPO, KANGRA-237253-C W-RFQ / Treatment of Draina ge Line (Soil Conservation W Component 1. Sustainable L orks/civil structure treatment Request for Quota Single Stage - One E Other (with field f 2022-03-1 IBRD / 90410 and and Water Resource Ma Post Limited 95,000.00 108,780.97 Completed 2021-10-18 2022-01-24 2021-11-14 2022-02-28 ) by constructing crate wire c tions nvelope or explanation) 4 nagement heck barriers for retention of debris in gullies(drainage line ) receiving relatively large qu antity of run-off IN-DPO, KANGRA-236906-C W-RFQ / Raising of enrichme nt plantations is proposed un Component 1. Sustainable L der APO Dehra in Cluster - I Request for Quota Single Stage - One E Other (with field f 2021-09-2 IBRD / 90410 and and Water Resource Ma Post Limited 50,000.00 41,608.49 Completed 2021-05-27 2021-06-07 2021-07-11 2021-06-28 & II during the rainy season o tions nvelope or explanation) 4 nagement f 2021 in the forest area @ 4 00 plants per/ha . There are 12 jobs (contracts) of 9 to 15 ha area in different GP's in D ehra unit. IN-DPO, KANGRA-237219-C W-RFQ / There will be 7-8 sit e specific different jobs (cont racts) for construction of ch Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-1 eck dams in the selected Dra IBRD / 90410 and and Water Resource Ma Post Limited 99,200.00 52,322.84 Completed 2021-11-05 2021-11-24 2021-12-02 2022-01-03 tions nvelope or explanation) 2 inage lines for Primary wate nagement r harvesting and storage by c onstructing cement concrete/ RCC check dam in the projec t area of Panchrukhi unit . IN-DPO, KANGRA-237216-C W-RFQ / Removal of Lantana from target area by cut root Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-0 stock method (75 to 100% ) i IBRD / 90410 and and Water Resource Ma Post Limited 79,500.00 74,151.32 Completed 2021-09-20 2021-09-24 2021-11-08 2021-11-11 tions nvelope or explanation) 8 n 140 ha. at 10 to 20 differen nagement t locations. There will be 10 t o 20 different jobs (contracts ) at different locations. IN-DPO, KANGRA-240030-C W-RFQ / Raising plantation is proposed in 85 ha. by plantin Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2021-09-1 g 400 plants per ha. in 8 GPs IBRD / 90410 and and Water Resource Ma Post Limited 28,500.00 28,385.74 Completed 2021-06-17 2021-06-05 2021-07-17 2021-07-05 tions nvelope or explanation) 5 of Baijnath unit there will be nagement 8 different jobs/contracts at different locations with area varying from 5 to 15 ha. at d ifferent sites. IN-DPO, KANGRA-240045-C W-RFQ / Enrichment plantati on is proposed in 80 ha area under APO Nagrota Bagwan Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2021-08-3 there will be 9 different jobs/ IBRD / 90410 and and Water Resource Ma Post Limited 26,500.00 22,393.13 Completed 2021-06-17 2021-06-04 2021-07-17 2021-06-28 tions nvelope or explanation) 1 contracts in different Gram P nagement anchayats of the unit in diff erent areas at different locati ons. Under this scheme 400 plants will be planted per ha. IN-DPO, KANGRA-240048-C W-RFQ / Monsoon planting of Enrichment plantation by pla Component 1. Sustainable L nting 400 plants per ha shall Request for Quota Single Stage - One E Other (with field f 2021-08-3 IBRD / 90410 and and Water Resource Ma Post Limited 21,500.00 17,344.04 Completed 2021-06-17 2021-06-07 2021-07-17 2021-06-28 be done in 64 ha area at 6 lo tions nvelope or explanation) 1 nagement cations in different GP's with area of 5 to 15 ha at each sit e in Panchrukhi unit of Kangr a district, there will be 6 diffe rent jobs/contracts . IN-DPO, KANGRA-240097-C W-RFQ / Renovation of existi ng village pond in GP Khaira Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2022-03-1 under Panchrukhi Unit is pro IBRD / 90410 and and Water Resource Ma Post Limited 67,600.00 0.00 2021-11-06 2021-12-30 2021-12-14 tions nvelope or explanation) mentation 4 posed by excavating earth , nagement forming embankments for ha rvesting rain water in the Pro ject area in Kangra district . IN-DPO, KANGRA-240099-C W-RFQ / Primary water harve sting and storage by renovat ing 4 existing ponds at differ Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-1 ent locations in GP Baddal, IBRD / 90410 and and Water Resource Ma Post Limited 60,000.00 17,747.44 Completed 2021-10-05 2021-12-10 2021-11-12 2021-12-29 tions nvelope or explanation) 2 Chanour and Bathal by exca nagement vating earth ,forming emban kments for harvesting rain w ater in the Project area in De hra unit of Kangra district . IN-DPO, KANGRA-240101-C W-RFQ / Treatment of Draina Component 1. Sustainable L ge Line (Soil Conservation W Request for Quota Single Stage - One E Other (with field f 2022-03-1 IBRD / 90410 and and Water Resource Ma Post Limited 40,700.00 35,424.02 Completed 2021-10-20 2022-01-01 2021-12-15 2022-02-12 orks) by constricting dry ston tions nvelope or explanation) 5 nagement e check barriers check barrie rs in the project area under A PO Nagrota Bagwan. IN-DPO, KANGRA-240102-C W-RFQ / Treatment of Draina Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-3 ge Line (Soil Conservation W IBRD / 90410 and and Water Resource Ma Post Limited 61,000.00 31,546.16 Completed 2021-09-06 2022-01-01 2021-11-01 2022-02-12 tions nvelope or explanation) 1 orks) by constricting dry ston nagement e check barriers check barrie rs in Baijnath unit. IN-DPO, KANGRA-240105-C W-RFQ / Treatment of Draina Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-2 ge Line (Soil Conservation W IBRD / 90410 and and Water Resource Ma Post Limited 61,200.00 32,467.66 Completed 2021-10-25 2022-01-01 2021-12-20 2022-02-12 tions nvelope or explanation) 0 orks) by constricting dry ston nagement e check barriers check barrie rs in Dehra unit. IN-DPO, KANGRA-240111-C W-RFQ / construction of cem ent concrete/RCC check dam Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-04-0 in Mehva,Sher Luhara, Kallar IBRD / 90410 and and Water Resource Ma Post Limited 94,500.00 118,085.23 Signed 2021-10-06 2021-11-22 2021-11-02 2022-01-28 tions nvelope or explanation) 1 & Jhaklehar GPs of Dehra uni nagement t for Primary water harvestin g and storage . there will be 5 to 7 check dams/ jobs(cont racts). Page 5 IN-DPO, KANGRA-240114-C W-RFQ / There will be site sp ecific different jobs (contract Component 1. Sustainable L s) at different locations Prima Request for Quota Single Stage - One E Other (with field f 2022-05-0 IBRD / 90410 and and Water Resource Ma Post Limited 94,500.00 69,201.50 Signed 2021-11-05 2021-11-25 2021-12-02 2022-02-14 ry water harvesting and stor tions nvelope or explanation) 1 nagement age by constructing cement concrete/RCC check dam in d ifferent GPs of Baijnath unit. There will be 3 to 5 jobs(cont ract) for each location. IN-DPO, KANGRA-240116-C W-RFQ / Primary water harve sting and storage by constru Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-05-0 cting cement concrete/RCC c IBRD / 90410 and and Water Resource Ma Post Limited 88,000.00 99,467.97 Signed 2021-11-05 2021-12-06 2021-12-02 2022-04-16 tions nvelope or explanation) 1 heck dam in Nagrota Bagwan nagement unit .There will be site specifi c 5to7 jobs (contracts) at diff erent locations. IN-DPO, KANGRA-242775-C W-RFQ / Removal of Lantana Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-2 from target area by cut root IBRD / 90410 and and Water Resource Ma Post Open - National 23,500.00 23,172.35 Completed 2021-09-16 2021-11-08 2021-11-11 tions nvelope or explanation) 3 stock method (50 to 75% ) in nagement 50 ha. at 5 to 10 different loc ations. IN-DPO, KANGRA-242779-C W-RFQ / Pre-monsoon/ advan ce work i.e. fencing of planta tion area with wooden fence Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2021-09-0 post and barbed wire for raisi IBRD / 90410 and and Water Resource Ma Post Open - National 63,000.00 59,508.54 Signed 2021-07-11 2021-08-02 2021-07-28 tions nvelope or explanation) 1 ng of plantation in the rainy s nagement eason of 2021 in the forest a rea to increase tree cover by planting 400 plants per/ha. u nder Enrichment Plantation. IN-DPO, KANGRA-242783-C W-RFQ / Afforestation includi ng advance work i.e. fencing Component 1. Sustainable L of plantation area with wood Request for Quota Single Stage - One E Other (with field f 2021-09-0 IBRD / 90410 and and Water Resource Ma Post Open - National 6,500.00 5,712.30 Completed 2021-07-12 2021-08-03 2021-07-28 en fence post and barbed wir tions nvelope or explanation) 2 nagement e and raising of plantation b y planting 800 plants per ha. in the rainy season of 2021 i n the forest area having ope n canopy . IN-DPO, KANGRA-242788-C W-RFQ / Raising of enrichme nt plantations is proposed un der APO Dehra, Panchrukhi & Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2021-09-0 Nagrota Bagwan . during the IBRD / 90410 and and Water Resource Ma Post Open - National 31,300.00 27,573.95 Signed 2021-07-11 2021-08-02 2021-07-26 tions nvelope or explanation) 1 rainy season of 2021 in the f nagement orest area @ 400 plants per/ ha . There are 12 jobs (contr acts) of 4 to 15 ha area in di fferent GP's in different unit. IN-DPO, KANGRA-242799-C W-RFQ / Contour trenching in plantation areas including rai sing of grass along the berm Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-02-0 of the contour trench. there IBRD / 90410 and and Water Resource Ma Post Open - National 20,900.00 23,952.94 Signed 2021-07-11 2021-08-05 2021-07-26 tions nvelope or explanation) 1 will 12 to13 jobs (contract). nagement This target is additional to th e already approved similar a ctivity vide reference No.IN-D PO, KANGRA-179096-CW-RF Q IN-DPO, KANGRA-281059-GO -RFQ / renovation of old she ep dip tank in Madhonagar G Component 1. Sustainable L P for dipping/bathing of shee Request for Quota Single Stage - One E Other (with field f Under Imple 2022-10-2 IBRD / 90410 and and Water Resource Ma Post Open - National 13,500.00 0.00 2022-03-07 2022-05-02 p flocks of transhumant in di tions nvelope or explanation) mentation 9 nagement sinfectant solutions including construction of soakpits for s afe disposal of waste contam inated water after bathing IN-DPO, KANGRA-288878-C W-RFQ / Contour trenching in Component 1. Sustainable L plantation area including gra Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-0 IBRD / 90410 and and Water Resource Ma Post Open - National 53,500.00 0.00 2022-05-15 2022-07-10 ss sowing ./ planting on the b tions nvelope or explanation) mentation 6 nagement erm of contour trenches ther e will be 35 to 50 jobs (contr act). IN-DPO, KANGRA-288882-C W-RFQ / Contour trenching in Component 1. Sustainable L forest areas outside the plant Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-01-1 IBRD / 90410 and and Water Resource Ma Post Open - National 20,500.00 0.00 2022-05-20 2022-07-15 ation area including grass so tions nvelope or explanation) lementation 1 nagement wing/ planting on the berm of contour trenches there will b e 15 to 20 jobs (contract). IN-DPO, KANGRA-288889-C Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-01-0 W-RFQ / Planting of grass tuft IBRD / 90410 and and Water Resource Ma Post Open - National 5,200.00 0.00 2022-06-16 2022-07-11 tions nvelope or explanation) lementation 7 s in 39 ha. along Drainage Li nagement ne areas IN-DPO, KANGRA-288920-C W-RFQ / Treatment of Draina ge Line by vegetative check Component 1. Sustainable L barriers. Vegetative check ba Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-03-1 IBRD / 90410 and and Water Resource Ma Post Open - National 5,000.00 0.00 2022-12-06 2023-01-15 rriers shall be provided by us tions nvelope or explanation) lementation 6 nagement ing local species capable of s prouting in small and mediu m gullies having side slopes l ess than 45 degrees. IN-DPO, KANGRA-288924-C W-RFQ / Treatment of Draina Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2022-12-2 ge Line (Soil Conservation W IBRD / 90410 and and Water Resource Ma Post Open - National 38,000.00 0.00 2022-05-06 2022-07-01 tions nvelope or explanation) lementation 8 orks) by constricting dry ston nagement e check barriers under APO B aijnath. IN-DPO, KANGRA-288928-C W-RFQ / Treatment of Draina Component 1. Sustainable L ge Line (Soil Conservation W Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-04-0 IBRD / 90410 and and Water Resource Ma Post Open - National 98,000.00 0.00 2022-09-05 2022-10-05 orks) by constricting dry ston tions nvelope or explanation) lementation 3 nagement e check barriers under APO D ehra, Nagrota Bagwan and P anchrukhi units IN-DPO, KANGRA-288931-C W-RFQ / Treatment of Draina ge Line (Soil Conservation W Component 1. Sustainable L orks/civil structure treatment Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-05-1 IBRD / 90410 and and Water Resource Ma Post Open - National 52,000.00 0.00 2022-09-20 2022-11-15 ) by constructing crate wire c tions nvelope or explanation) lementation 4 nagement heck barriers for retention of debris in gullies(drainage line ) receiving relatively large qu antity of run-off under APO P anchrukhi. Page 6 IN-DPO, KANGRA-288932-C W-RFQ / Treatment of Draina ge Line (Soil Conservation W Component 1. Sustainable L orks/civil structure treatment Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-05-1 IBRD / 90410 and and Water Resource Ma Post Open - National 52,000.00 0.00 2022-09-20 2022-11-15 ) by constructing crate wire c tions nvelope or explanation) lementation 4 nagement heck barriers for retention of debris in gullies(drainage line ) receiving relatively large qu antity of run-off under APO B aijnath. IN-DPO, KANGRA-288933-C W-RFQ / Treatment of Draina ge Line (Soil Conservation W Component 1. Sustainable L orks/civil structure treatment Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-05-1 IBRD / 90410 and and Water Resource Ma Post Open - National 52,000.00 0.00 2022-09-20 2022-11-15 ) by constructing crate wire c tions nvelope or explanation) lementation 4 nagement heck barriers for retention of debris in gullies(drainage line ) receiving relatively large qu antity of run-off under APO N agrota Bagwan. IN-DPO, KANGRA-288935-C W-RFQ / Treatment of Draina ge Line (Soil Conservation W Component 1. Sustainable L orks/civil structure treatment Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-05-1 IBRD / 90410 and and Water Resource Ma Post Open - National 52,000.00 0.00 2022-09-20 2022-11-15 ) by constructing crate wire c tions nvelope or explanation) lementation 4 nagement heck barriers for retention of debris in gullies(drainage line ) receiving relatively large qu antity of run-off Under APO D ehra. IN-DPO, KANGRA-289134-C W-RFQ / Construction of CC c heck barriers for treatment o Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-05-1 f Drainage Line . There will b IBRD / 90410 and and Water Resource Ma Post Open - National 90,000.00 0.00 2022-09-20 2022-11-15 tions nvelope or explanation) lementation 4 e 20 to 25 Different jobs (Con nagement tracts) in different Gram Pan chayats in the selected Drain age lines in Kangra District. IN-DPO, KANGRA-289171-C W-RFQ / Removal of Lantana Component 1. Sustainable L from target area by cut root Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-02-1 IBRD / 90410 and and Water Resource Ma Post Open - National 22,000.00 0.00 2022-06-20 2022-08-15 stock method (50 to 75% ) in tions nvelope or explanation) lementation 1 nagement 50 ha. at 10 to 15 different l ocations under the jurisdictio n of DPO Kangra at Dharmah sla. IN-DPO, KANGRA-289184-C W-RFQ / Removal of Lantana Component 1. Sustainable L from target area by cut root Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-02-1 IBRD / 90410 and and Water Resource Ma Post Open - National 54,000.00 0.00 2022-06-20 2022-08-15 stock method (75 to 100% ) i tions nvelope or explanation) lementation 1 nagement n 100 ha. at 10 to 20 differen t locations under the jurisdict ion of DPO Kangra at Dharam shala. IN-DPO, KANGRA-289193-C W-RFQ / Primary water harve sting and storage by constru Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-02-1 cting Ponds( Manual Excavati IBRD / 90410 and and Water Resource Ma Post Open - National 68,000.00 0.00 2022-06-20 2022-08-15 tions nvelope or explanation) lementation 1 on) under the jurisdiction of nagement DPO Kangra at Dharamshala. There will be site specific 25 to 30 jobs (contracts) at diffe rent locations. IN-DPO, KANGRA-289214-C W-RFQ / Primary water harve sting and storage by constru Component 1. Sustainable L cting cement concrete check Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-01-1 IBRD / 90410 and and Water Resource Ma Post Open - National 41,000.00 0.00 2022-05-20 2022-07-15 dams under the jurisdiction o tions nvelope or explanation) lementation 1 nagement f DPO,IDP Kangra at Dharams hala.There will be site specifi c 15 to20 jobs (contracts) at different locations. IN-DPO, KANGRA-289628-C W-RFQ / First year maintenan ce of 650 ha. plantation area s done during 2021-22 under Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-2 different schemes i.e. draina IBRD / 90410 and and Water Resource Ma Post Open - National 56,000.00 0.00 2022-06-07 2022-08-02 tions nvelope or explanation) mentation 9 ge line treatment=83 ha. ,re- nagement afforestation=106 ha. and en richment plantations=461ha. Total=650ha under the jurisd iction of DPO Kangra at Dhar amshala. IN-DPO, KANGRA-289636-C W-RFQ / 2nd year maintenan ce of 389 ha. plantation area s done during 2020-21 under Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-2 different schemes i.e. draina IBRD / 90410 and and Water Resource Ma Post Open - National 16,000.00 0.00 2022-06-07 2022-08-02 tions nvelope or explanation) mentation 9 ge line treatment=103ha. ,re nagement -afforestation=137ha. and en richment plantations=149ha. Total=389 ha. under the juris diction of DPO Kangra at Dha ramshala. IN-DPO, KANGRA-289639-C W-RFQ / Management of exot Component 1. Sustainable L ic species -2nd year activity i Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-2 IBRD / 90410 and and Water Resource Ma Post Open - National 21,500.00 0.00 2022-06-07 2022-08-02 n the targeted area in 300 ha tions nvelope or explanation) mentation 9 nagement ., where removal of Lantana was done by cut root stock m ethod during the year 2021-2 2 IN-DPO, KANGRA-289640-C W-RFQ / Management of exot Component 1. Sustainable L ic species -3rd year activity i Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-2 IBRD / 90410 and and Water Resource Ma Post Open - National 31,600.00 0.00 2022-06-07 2022-08-02 n the targeted area in 551 ha tions nvelope or explanation) mentation 9 nagement ., where removal of Lantana was done by cut root stock d uring the year 2020-21. IN-DPO, KANGRA-289868-C W-RFQ / Pre-monsoon/ advan ce work i.e. fencing of planta tion area with wooden fence Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-1 post and barbed wire for raisi IBRD / 90410 and and Water Resource Ma Post Open - National 26,000.00 0.00 2022-05-20 2022-07-15 tions nvelope or explanation) mentation 1 ng of plantation in the rainy s nagement eason of 2022-23 in the fores t area to increase tree cover by planting 1100 plants per/h a. under DPO Kangra. IN-DPO, KANGRA-289874-C W-RFQ / Raising plantation is proposed in 39 ha. by plantin Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-02-0 g 1100 plants per ha. in Kang IBRD / 90410 and and Water Resource Ma Post Open - National 29,000.00 0.00 2022-06-15 2022-08-10 tions nvelope or explanation) mentation 6 ra District. There will be 15 t nagement o 20 different jobs/contracts at different locations at diffe rent sites. Page 7 IN-DPO, KANGRA-289876-C W-RFQ / Pre-monsoon/ advan ce work i.e. fencing of planta tion area with wooden fence Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-1 post and barbed wire for raisi IBRD / 90410 and and Water Resource Ma Post Open - National 16,000.00 0.00 2022-05-20 2022-07-15 tions nvelope or explanation) mentation 1 ng of plantation in the rainy s nagement eason of 2022-23 in the fores t area to increase tree cover by planting 800 plants per/ha . under DPO Kangra. IN-DPO, KANGRA-289878-C W-RFQ / Raising plantation is Component 1. Sustainable L proposed in 24 ha. by plantin Request for Quota Single Stage - One E Other (with field f Under Imple 2023-02-0 IBRD / 90410 and and Water Resource Ma Post Open - National 15,000.00 0.00 2022-06-15 2022-08-10 g 800 plants per ha. in Kangr tions nvelope or explanation) mentation 6 nagement a District. There will be up to 5 different jobs/contracts at different locations at differen t sites. IN-DPO, KANGRA-289881-C W-RFQ / Pre-monsoon/ advan ce work i.e. fencing of planta Component 1. Sustainable L tion area with wooden fence Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-1 IBRD / 90410 and and Water Resource Ma Post Open - National 100,000.00 0.00 2022-05-20 2022-07-15 post and barbed wire for raisi tions nvelope or explanation) mentation 1 nagement ng of plantation in the rainy s eason of 2022-23 in the fores t area to increase tree cover by planting 400 plants per/ha . under APO Dehra. IN-DPO, KANGRA-289883-C W-RFQ / Raising plantation is proposed in 154 ha. by planti Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-02-0 ng 400 plants per ha. in Dehr IBRD / 90410 and and Water Resource Ma Post Open - National 52,000.00 0.00 2022-06-15 2022-08-10 tions nvelope or explanation) mentation 6 a unit of Kangra District. The nagement re will be up to 20 to 25 diffe rent jobs/contracts at differe nt locations at different sites IN-DPO, KANGRA-289903-C W-RFQ / Pre-monsoon/ advan ce work i.e. fencing of planta tion area with wooden fence Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-1 post and barbed wire for raisi IBRD / 90410 and and Water Resource Ma Post Open - National 55,000.00 0.00 2022-05-20 2022-07-15 tions nvelope or explanation) mentation 1 ng of plantation in the rainy s nagement eason of 2022-23 in the fores t area to increase tree cover by planting 400 plants per/ha . under DPO Kangra. IN-DPO, KANGRA-289906-C W-RFQ / Raising plantation is proposed in 83 ha. by plantin Component 1. Sustainable L g 400 plants per ha. in Nagro Request for Quota Single Stage - One E Other (with field f Under Imple 2023-02-0 IBRD / 90410 and and Water Resource Ma Post Open - National 28,000.00 0.00 2022-06-15 2022-08-10 ta Bagwan , Panchrukhi and tions nvelope or explanation) mentation 6 nagement Baijnath unit of Kangra Distri ct. There will be up to 8 to 10 different jobs/contracts at dif ferent locations at different si tes IN-DPO, KANGRA-300396-C W-RFQ / Pre-monsoon/ advan ce work i.e. fencing of planta tion area with wooden fence Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2022-08-2 post and barbed wire for raisi IBRD / 90410 and and Water Resource Ma Post Open - National 43,400.00 0.00 2022-07-04 2022-07-28 tions nvelope or explanation) lementation 7 ng of plantation in the rainy s nagement eason of 2022-23 in the fores t area to increase tree cover by planting 400 plants per/ha .under DPO Kangra. Total=65 ha. IN-DPO, KANGRA-300397-C W-RFQ / Raising plantation is proposed in 65 ha. by plantin g 400 plants per ha. under A Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2022-08-0 PO Nagrota Bagwan=25 ha , IBRD / 90410 and and Water Resource Ma Post Open - National 22,000.00 0.00 2022-07-10 2022-08-01 tions nvelope or explanation) lementation 4 Panchrukhi=20 ha and Dehra nagement =20ha. Total=65ha. There wi ll be up to 8 to 10 different jo bs/contracts at different locat ions at different sites IN-DPO, KANGRA-300400-C W-RFQ / Contour trenching in Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-02-0 plantation area including gra IBRD / 90410 and and Water Resource Ma Post Open - National 18,000.00 0.00 2022-07-15 2022-08-08 tions nvelope or explanation) lementation 4 ss sowing ./ planting on the b nagement erm of contour trenches ther e will be 8to10 jobs (contract ). IN-DPO, KANGRA-301467-C W-RFQ / Eradication of 50 to 75% lantana infested areas i Component 1. Sustainable L s proposed during 2022-23 in Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-03-2 IBRD / 90410 and and Water Resource Ma Post Open - National 22,000.00 0.00 2022-08-20 2022-09-21 addition to the already appro tions nvelope or explanation) lementation 0 nagement ved similar activity vide IN-D PO, KANGRA-289171.There w ill be 8to10 different jobs (co ntracts) at different locations . IN-DPO, KANGRA-301474-C W-RFQ / Additional removal o f lantana in 50ha area infeste d 75to100% is proposed by C Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-03-1 RS method during the year 2 IBRD / 90410 and and Water Resource Ma Post Open - National 27,000.00 0.00 2022-08-20 2022-09-20 tions nvelope or explanation) lementation 9 022-23 in addition to the alre nagement ady approved similar activity vide IN-DPO, KANGRA-28918 4.There will be 8 to 10 differe nt jobs (contracts) . GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-DPO, KANGRA-178842-GO -RFQ / Procurement of Polyth ene bags for raising nurserie Component 1. Sustainable L s. Black recycled Polythene b Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Limited 2,170.00 2,037.90 Completed 2020-06-15 2020-02-26 2020-08-10 2020-03-13 2021-02-06 2020-03-15 ags of Size 5’x9”gauze 150 h tions nvelope nagement aving 6 hole’s in 2 rows of 3 hole’s in each Lower 2/3 Porti on automatically double seal ed by heat process dia of hol e 0.3 mm. IN-DPO, KANGRA-199067-GO Component 1. Sustainable L -RFQ / Black Recycled Poly B Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Limited 5,000.00 4,748.40 Completed 2020-11-20 2020-10-28 2021-01-15 2020-11-20 2021-02-14 2020-12-10 ags shall be procured for rai tions nvelope nagement sing of plants in all six nurser ies under DPO Kangra . Page 8 IN-DPO, KANGRA-204490-GO -RFQ / Forestry seeds Dendro calamus strictus= 5kg and D Component 1. Sustainable L endrocalamus hamiltonii =5k Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Limited 5,000.00 5,005.89 Completed 2020-11-12 2020-10-28 2021-01-07 2021-01-13 2021-02-06 2021-01-27 g and root shoot cuttings of tions nvelope nagement forestry plants i.e. Tectona gr andis (Teak), Terminalia Arju na (Arjun)and salix =95000 f or raising of nursery plants. IN-DPO, KANGRA-216715-GO -RFQ / Forestry seeds Dendro calamus strictus= 15kg and Component 1. Sustainable L Dendrocalamus hamiltonii = Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Limited 5,000.00 4,735.30 Completed 2021-02-06 2020-10-28 2021-03-01 2021-02-01 2021-03-08 2021-02-01 15kg and root shoot cuttings tions nvelope nagement of forestry plants i.e. Tectona grandis (Teak), Terminalia Arj una (Arjun)and salix =90000 for raising of nursery plants u nder APO Dehra. IN-DPO, KANGRA-237265-GO Component 1. Sustainable L -RFQ / Black Recycled Poly B Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Limited 13,500.00 11,844.20 Completed 2021-07-20 2021-09-23 2021-08-31 2021-12-09 2021-09-30 2021-12-09 ags shall be procured for rais tions nvelope nagement ing of plants in all eight nurs eries under DPO Kangra IN-DPO, KANGRA-240094-GO Component 1. Sustainable L Request for Quota Single Stage - One E -RFQ / Procurement of GI wir IBRD / 90410 and and Water Resource Ma Post Limited 26,000.00 31,584.55 Completed 2021-09-20 2021-12-10 2021-10-12 2022-01-24 2021-11-11 2022-01-26 tions nvelope e for construction of crate wir nagement e structure . IN-DPO, KANGRA-274238-GO -RFQ / Providing and fixing of Component 1. Sustainable L sign boards for various activi Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Open - National 13,500.00 14,503.60 Completed 2022-02-13 2022-03-09 2022-03-03 2022-04-08 2022-03-22 ties taken up under the Proje tions nvelope nagement ct i.e. plantations, drainage li ne treatment and water harv esting etc. in all 64 GP's IN-DPO, KANGRA-281064-GO -RFQ / procurement of tarpa ulins,drenching guns,castrato rs,tents with sleeping bags, r Component 1. Sustainable L Request for Quota Single Stage - One E Pending Impl ucksacks,LED based torchs,s IBRD / 90410 and and Water Resource Ma Post Open - National 35,000.00 0.00 2022-03-06 2022-03-24 2022-09-20 tions nvelope ementation now shoes,water resistant ra nagement in jackets on cost shairing b asis @90:10 and medical kit s,sheep shairing units free of cost for transhumants. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 9