PROCUREMENT PLAN (Textual Part) Project information: Uzbekistan - Early Childhood Developement Project - P165737 Project Implementation agency: PIU under the Preschool Education Ministry Procurement Plan: August 23, 2019 Period covered by this Procurement Plan: August, 2019 - December, 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Procurement Law dated April 9, 2018 , such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. None. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables. Other Relevant Procurement Information. None. PROCUREMENT Uzbekistan : Promoting Early Childhood Development Project PLAN General Information Country: Uzbekistan Bank’s Approval Date of the Original Procurement Plan: 2019-08-28 2022-01-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165737 GPN Date: 2020-08-24 Project Name: Promoting Early Childhood Development Project Loan / Credit No: TF / A8999, IDA / 64180 M Executing Agency(ies): inistry of pre-school education of the Republic of Uzbekistan WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UZ-MPSE-161638-GO-RFB / 1.1.5 Providing the MPSE with Printing Equipment to Produce 1 - Improving Quality of Single Stage - One Teaching and Learning IDA / 64180 Prior Request for Bids Open - International 1,700,000.00 0.00 Canceled 2020-05-25 2020-05-30 2020-07-14 2020-08-13 2020-09-17 2021-03-16 Preschool Education Envelope Materials, including service contract for maintenance of equipment and supplies UZ-MPSE-161641-GO-RFB / 2 - Increasing Access to 2.1.2 Providing Preschools Single Stage - One IDA / 64180 Quality Early Learning Prior Request for Bids Open - International 2,400,000.00 0.00 Canceled 2021-01-03 2021-01-08 2021-02-22 2021-03-24 2021-04-28 2021-10-25 and Education Institutions Envelope Environments with ICT Equipment RFBG/1/1/20 / 1.1.5 Providing the MPSE with 1 - Improving Quality of Single Stage - One Printing Equipment to Produce IDA / 64180 Prior Request for Bids Open - International 1,700,000.00 0.00 Canceled 2020-06-30 2020-08-17 2020-07-05 2020-08-19 2020-08-16 2020-10-20 2020-09-15 2021-01-13 2020-10-20 2021-04-18 Preschool Education Envelope Teaching and Learning Materials and related services RFQG/01/2020 / 5.1.4.1 5 - Supporting Project Request for Single Stage - One Purchasing of Equipment for IDA / 64180 Prior Open - National 20,000.00 0.00 Canceled 2020-04-29 2020-06-13 2020-12-10 Management Quotations Envelope Project Management Team RFQG/5/4/20 / 5.1.4.3 Pending 5 - Supporting Project Request for Single Stage - One Purchasing of vehicle for IDA / 64180 Post Open - International 20,000.00 0.00 Implementati 2020-05-23 2020-07-18 2021-01-14 Management Quotations Envelope Project Management Team on RFBG/4/03/20 / 4.2.3.5 Purchase of ICT Equipment for 4 - Establishing an Education Single Stage - One IDA / 64180 Post Request for Bids Open - International 240,000.00 222,500.00 Signed 2020-05-31 2020-07-14 2020-06-05 2020-07-14 2020-07-17 2020-08-27 2020-08-16 2020-09-11 2020-09-20 2020-10-23 2020-11-04 Computer-based Quality Measurement System Envelope Assessments RFQG/5/3/20 / 5.1.4.2 Pending 5 - Supporting Project Request for Single Stage - One Purchasing of Furniture for IDA / 64180 Post Open - National 20,000.00 0.00 Implementati 2020-07-31 2020-08-31 2020-09-30 Management Quotations Envelope Project Management Team on ECD-RFQG/2/1 / 2.1.3 Providing Preschools with 2 - Increasing Access to Request for Single Stage - One Noncontact Thermometers to IDA / 64180 Quality Early Learning Post Open - International 260,000.00 0.00 Canceled 2020-07-10 2020-07-15 2020-07-15 2020-07-30 Quotations Envelope Mitigate the Risk with the Environments Spread of the COVID-19 ECD-RFBG/4/1 / 4.1.1.1 Providing the National Center 4 - Establishing an Education Single Stage - One for Quality Education (NCQE) IDA / 64180 Post Request for Bids Open - International 668,150.00 0.00 Canceled 2020-08-01 2020-08-06 2020-09-17 2020-10-17 2020-11-21 2021-05-20 Quality Measurement System Envelope with ICT Equipment and Supplies ECD-RFQG/4/1 / 4.1.1.2 Providing the National Center 4 - Establishing an Education Request for Single Stage - One IDA / 64180 Post Open - National 70,850.00 55,429.29 Signed 2020-09-06 2020-10-24 2020-11-01 2020-12-04 2021-04-30 for Quality Education (NCQE) Quality Measurement System Quotations Envelope with Furniture ECD- RFQG/2/1 / 2.1.3 Providing Preschools with 2 - Increasing Access to Request for Single Stage - One Noncontact Thermometers to IDA / 64180 Quality Early Learning Post Open - International 260,000.00 175,000.00 Completed 2020-08-24 2020-10-19 2020-08-17 2021-04-17 2020-09-18 Quotations Envelope Mitigate the Risk with the Environments Spread of the COVID-19 UZ-MPSE-161641-GO- RFB / 2 - Increasing Access to 2.1.2 Providing Preschools Single Stage - One IDA / 64180 Quality Early Learning Prior Request for Bids Open - International 2,225,000.00 0.00 Canceled 2020-10-01 2020-10-25 2020-10-31 2020-10-26 2020-12-15 2020-12-14 2021-01-14 2021-03-05 2021-02-07 2021-05-30 and Education Institutions Envelope Environments with ICT Equipment UZ-MPSE-161643-GO-RFB / 2.2.3 Equipping Early Learning 2 - Increasing Access to Pending Single Stage - One Hubs with Materials for the IDA / 64180 Quality Early Learning Post Request for Bids Open - International 1,000,000.00 0.00 Implementati 2021-05-01 2021-05-06 2021-06-20 2021-07-20 2021-08-24 2022-03-22 Envelope Implementation of the Environments on Alternative Models RFBG/1/1/20-1 / 1.1.5 Providing the MPSE with Under 1 - Improving Quality of Single Stage - One Printing Equipment to Produce IDA / 64180 Post Request for Bids Open - International 1,700,000.00 1,823,000.00 Implementati 2021-04-20 2021-06-21 2021-04-25 2021-06-21 2021-06-14 2021-08-09 2021-07-14 2021-09-06 2021-08-18 2022-02-14 Preschool Education Envelope Teaching and Learning on Materials RFQG/1/2/20 / Activity # Pending 1.1.6 Providing the MPSE with 1 - Improving Quality of Request for Single Stage - One IDA / 64180 Post Open - International 500,000.00 0.00 Implementati 2022-02-19 2022-05-02 2024-12-31 Publishing Supplies - PIP Preschool Education Quotations Envelope on dated March 3, 2020 Page 1 RFBG/2/02/20 / 2.1.1 Providing Preschools with 2 - Increasing Access to Under Single Stage - One Furniture, Equipment and IDA / 64180 Quality Early Learning Prior Request for Bids Open - International 43,200,000.00 0.00 Implementati 2021-04-25 2021-05-17 2021-04-26 2021-05-20 2021-06-15 2021-07-07 2021-07-15 2022-01-07 2021-08-19 2022-08-19 Envelope Teaching and Learning Environments on Materials ECD-RFQG/4/2 / 4.2.2.7 Under 4 - Establishing an Education Request for Single Stage - One Purchasing of minibus for IDA / 64180 Post Open - International 80,000.00 0.00 Implementati 2021-03-06 2021-03-19 2021-05-08 2021-11-04 Quality Measurement System Quotations Envelope NCQE on ECD-RFBG/2/1 / 2.1.2 2 - Increasing Access to Under Providing Preschools and Single Stage - One IDA / 64180 Quality Early Learning Prior Request for Bids Open - International 2,400,000.00 0.00 Implementati 2021-06-30 2021-06-30 2021-07-05 2021-06-30 2021-08-16 2021-08-20 2021-09-15 2021-09-08 2021-10-20 2022-04-18 Education Institutions with ICT Envelope Environments on Equipment ECD- RFBG/4/1 / 4.1.1.1 Providing the State Under 4 - Establishing an Education Single Stage - One Inspectorate for Supervision IDA / 64180 Post Request for Bids Open - International 449,000.00 0.00 Implementati 2021-12-10 2021-12-09 2021-12-15 2021-12-09 2022-01-26 2022-02-25 2022-04-01 2022-09-28 Quality Measurement System Envelope of the Quality of Education on (SISQE) with ICT equipment NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ECD-RFQNC/4/1 / 4.1.2 Under 4 - Establishing an Education Request for Single Stage - One Development and IDA / 64180 Post Open - National 41,000.00 0.00 Implementati 2021-03-05 2021-03-30 2021-04-30 2022-04-30 Quality Measurement System Quotations Envelope Maintenance of a Website for on the NCQE ECD-RFQNC/1/2 / 1.1.10 Development of Videos for 1 - Improving Quality of Request for Single Stage - One IDA / 64180 Post Open - National 38,000.00 0.00 Canceled 2021-04-05 2021-05-31 2021-09-28 Teachers and Children for Preschool Education Quotations Envelope COVID-19 Response ECD-RFQNC/1/1 / 1.1.11 Logistical Support to Training 1 - Improving Quality of Request for Single Stage - One IDA / 64180 Post Open - International 100,000.00 0.00 Canceled 2021-04-05 2021-05-31 2021-09-28 Activities for COVID-19 Preschool Education Quotations Envelope Response ECD-RFQNC/1/3 / 1.2.11 Supporting a Forum for Cross- Pending Sectoral Systematic 1 - Improving Quality of Request for Single Stage - One IDA / 64180 Post Open - National 50,000.00 0.00 Implementati 2022-07-06 2022-08-31 2024-12-31 Discussions of Holistic ECD Preschool Education Quotations Envelope on Initiatives Promoted through the Project ECD-DS/1/1 / 1.1.8 Procurement of a License for the non-exclusive right to Under exhibit the “Sesame Street” 1 - Improving Quality of IDA / 64180 Post Direct Selection Direct 70,000.00 0.00 Implementati 2021-08-01 2021-08-16 2021-08-06 2021-09-10 2022-03-09 Programs for Children for Preschool Education on COVID-19 Response and habits of healthy life, safety and hygiene ECD-RFQNC/2/1 / Providing logistical and technical Under 1 - Improving Quality of Request for Single Stage - One support for conducting IDA / 64180 Post Limited 50,000.00 0.00 Implementati 2021-09-20 2021-11-15 2022-05-14 Preschool Education Quotations Envelope trainings On Child-centered on Approach to Teaching ECD-RFQNC/4/2 / 4.2.3.7 Under Development, Adaptation and 4 - Establishing an Education Request for Single Stage - One IDA / 64180 Post Open - National 50,000.00 0.00 Implementati 2021-11-06 2021-11-05 2022-01-01 2022-06-30 Translation of Assessments Quality Measurement System Quotations Envelope on Materials ECD-DS/1/2 / 1.1.9 Pending Providing related services for 1 - Improving Quality of IDA / 64180 Post Direct Selection Direct 20,000.00 0.00 Implementati 2021-12-31 2022-01-05 2022-02-09 2022-08-08 COVID-19 Response and Preschool Education on habits of healthy life ECD- RFQNC/1/1 / 1.1.11 Providing logistical and Pending technical support for 1 - Improving Quality of Request for Single Stage - One IDA / 64180 Post Limited 50,000.00 0.00 Implementati 2022-01-22 2022-03-19 2022-09-15 conducting trainings On Child- Preschool Education Quotations Envelope on centered Approach to Teaching (Module 2) Pending ECD-DS/4/1 / 4.2.2.8 COVID- 4 - Establishing an Education IDA / 64180 Post Direct Selection Direct 45,600.00 0.00 Implementati 2021-12-24 2021-12-29 2022-02-02 2022-08-01 19 learning loss assessment Quality Measurement System on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ECDP/CQS/05 / Support to Consultant 1 - Improving Quality of the Test of MELQO Tools and TF / A8999 Post Qualification Open - International 50,000.00 0.00 Canceled 2019-09-15 2019-10-04 2019-10-10 2019-10-15 2019-10-18 2019-12-17 Preschool Education Related Training Selection ECDP/CQS/06 / Analysis of Consultant 1 - Improving Quality of Conditions for Service Delivery TF / A8999 Post Qualification Open - National 5,000.00 0.00 Canceled 2019-10-05 2019-10-24 2019-10-30 2019-11-01 2019-11-07 2019-12-22 Preschool Education by Non-Public Providers Selection 3 - Partnering with the Consultant ECDP/CQS/09 / Preparation TF / A8999 Private Sector through a Post Qualification Open - International 50,000.00 0.00 Under Review 2019-09-05 2019-09-18 2019-09-24 2019-09-30 2019-09-30 2019-10-08 2019-11-22 of SIB Documents Social Impact Bond Selection 3 - Partnering with the Consultant ECDP/CQS/10 / Preparation Pending TF / A8999 Private Sector through a Post Qualification Open - National 55,000.00 0.00 2019-08-20 2019-09-03 2019-09-05 2019-09-06 2019-09-08 2019-12-07 of Feasibility Study Implementation Social Impact Bond Selection Page 2 ECDP/CQS/11 / Training of Consultant 5 - Supporting Project MPSE Staff for Project TF / A8999 Post Qualification Open - National 13,000.00 0.00 Canceled 2019-09-05 2019-09-24 2019-09-30 2019-10-05 2019-10-08 2019-11-22 Management Implementation Selection Consultant ECDP/CQS/15 / 5 - Supporting Project Under TF / A8999 Post Qualification Open - National 11,000.00 0.00 2019-09-05 2019-10-15 2019-09-24 2019-11-08 2019-09-30 2019-10-05 2019-10-08 2019-11-22 Customization of FM Software Management Implementation Selection Consultant 5 - Supporting Project Under ECDP/CQS/16 / Grant Audit TF / A8999 Post Qualification Open - National 10,000.00 0.00 2019-09-17 2019-10-21 2019-10-08 2019-11-08 2019-10-29 2019-11-12 2019-11-26 2019-12-26 Management Implementation Selection UZ-MPSE-161656-CS-QCBS / 1.2.5 Development of a Communication and Awareness Raising Campaigns 1 - Improving Quality of Quality And Cost- Under IDA / 64180 Post Open - International 440,000.00 0.00 2020-08-25 2020-09-15 2020-10-29 2020-11-26 2020-12-26 2021-01-30 2021-03-06 2022-03-06 Plan Preschool Education Based Selection Implementation 1.2.6 Implementation of Communication and Awareness Raising Campaigns UZ-MPSE-161691-CS-CQS / Consultant 5 - Supporting Project 5.1.7 Supporting Project IDA / 64180 Post Qualification Open - International 135,000.00 53,760.00 Signed 2020-10-05 2020-07-07 2020-10-26 2020-08-12 2020-12-09 2020-09-14 2021-01-08 2020-10-19 2021-02-12 2020-10-20 2021-08-11 Management Financial Audits Selection Consultant CQS/5/2/20 / 5.1.5 5 - Supporting Project IDA / 64180 Post Qualification Open - National 10,000.00 6,082.70 Signed 2020-05-04 2020-06-04 2020-05-18 2020-06-05 2020-06-04 2020-06-27 2020-06-09 2020-07-17 2020-07-01 2020-07-17 2020-12-28 customization of 1C program Management Selection ECD-CQS-1 / 3.1.1 3 - Partnering with the Consultant Supporting the Development IDA / 64180 Private Sector through a Prior Qualification Open - International 250,000.00 220,421.46 Signed 2020-05-10 2020-05-30 2020-05-31 2020-07-05 2020-06-03 2020-07-08 2020-10-25 2020-07-08 2020-11-09 2021-05-04 of SIB Documents Social Impact Bond Selection UZ-MPSE-161671-CS-QCBS / 3 - Partnering with the 3.1.1 Supporting the Quality And Cost- IDA / 64180 Private Sector through a Prior Open - International 300,000.00 0.00 Canceled 2020-03-09 2020-03-30 2020-05-13 2020-06-10 2020-07-10 2020-08-14 2020-09-18 2021-09-18 Development of SIB Based Selection Social Impact Bond Documents ECD-QCBS/1/1 / 1.1.3 Assistance for Developing New Training Programs for 1 - Improving Quality of Quality And Cost- Under IDA / 64180 Post Open - International 387,000.00 0.00 2020-10-01 2020-10-22 2020-12-05 2021-01-02 2021-02-01 2021-03-08 2021-04-12 2022-10-10 Preschool Teachers and Preschool Education Based Selection Implementation Teaching and Learning Materials LCS/3/01/20 / 3.1.3 3 - Partnering with the Least Cost Pending Independent Verification of IDA / 64180 Private Sector through a Post Open - International 900,000.00 0.00 2021-09-30 2021-10-21 2021-12-04 2022-01-01 2022-01-31 2022-03-07 2022-04-11 2022-10-08 Selection Implementation SIB Results Social Impact Bond ECD-LCS/4/1 / 4.2.2.4 Development and 4 - Establishing an Education Least Cost Pending implementation of IDA / 64180 Post Open - International 220,000.00 0.00 2021-09-30 2021-10-21 2021-12-04 2022-01-01 2022-01-31 2022-03-07 2022-04-11 2022-10-08 Quality Measurement System Selection Implementation communication campaigns and public relations ECD-CQS/2/1 / 2.2.2.1 2 - Increasing Access to Consultant Supporting the Pending IDA / 64180 Quality Early Learning Post Qualification Open - International 100,000.00 0.00 2022-01-31 2022-02-21 2022-04-06 2022-05-06 2022-06-10 2022-12-07 implementation of an ECD Implementation Environments Selection Home Visiting Program ECD-CQS/2/2 / 2.2.2.2 Supporting the 2 - Increasing Access to Consultant Pending implementation of a IDA / 64180 Quality Early Learning Post Qualification Open - International 100,000.00 0.00 2022-01-31 2022-02-21 2022-04-06 2022-05-06 2022-06-10 2022-12-07 Implementation Community Based Early Environments Selection Learning Playgroup Program INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ECDP/IC/01 / Building Individual Capacity in the Utilization of 1 - Improving Quality of TF / A8999 Post Consultant Open 10,000.00 0.00 Canceled 2019-08-20 2019-11-01 2019-09-02 2019-09-02 2019-09-05 2019-12-31 Data for Planning and Preschool Education Selection Decision Making ECDP/IC/02 / Adaptation of Individual 1 - Improving Quality of MELQO Instruments TF / A8999 Post Consultant Open 80,000.00 19,911.25 Signed 2019-08-20 2019-09-16 2019-09-02 2019-10-12 2019-09-03 2019-10-24 2019-09-05 2019-10-26 2019-12-31 Preschool Education (lead consultant) Selection ECDP/IC/03 / Adaptation of Individual 1 - Improving Quality of MELQO Instruments TF / A8999 Post Consultant Open 40,000.00 0.00 Canceled 2019-08-20 2019-09-16 2019-09-02 2019-09-03 2019-09-05 2019-12-31 Preschool Education (junior consultant) Selection Individual ECDP/IC/04 / Translation of 1 - Improving Quality of TF / A8999 Post Consultant Open 20,000.00 2.10 Signed 2019-09-20 2019-09-19 2019-10-03 2019-10-15 2019-10-04 2019-10-24 2019-10-06 2019-10-26 2019-12-30 MELQO Instruments Preschool Education Selection 3 - Partnering with the Individual ECDP/IC/07 / Preparation of TF / A8999 Private Sector through a Post Consultant Open 30,000.00 9,600.00 Signed 2019-08-20 2019-08-23 2019-09-02 2019-10-24 2019-09-03 2019-10-08 2019-09-05 2019-10-08 2019-12-31 Project Operations Manual Social Impact Bond Selection 3 - Partnering with the Individual ECDP/IC/08 / Preparation of TF / A8999 Private Sector through a Post Consultant Open 40,000.00 18,000.00 Signed 2019-08-20 2019-09-18 2019-09-02 2019-09-30 2019-09-03 2019-10-22 2019-09-05 2019-10-24 2019-12-31 SIB Operations Manual Social Impact Bond Selection Individual ECDP/IC/12 / Hiring of FM 5 - Supporting Project TF / A8999 Post Consultant Open 4,000.00 4,000.00 Signed 2019-08-18 2019-08-01 2019-08-27 2019-07-02 2019-08-28 2019-07-10 2019-09-12 2019-07-10 2020-01-10 Specialist Management Selection Individual ECDP/IC/13 / Hiring of 5 - Supporting Project TF / A8999 Post Consultant Open 4,000.00 4,000.00 Signed 2019-08-18 2019-08-01 2019-08-27 2019-08-01 2019-08-27 2019-08-01 2019-08-27 2019-08-01 2019-12-25 Procurement Specialist Management Selection Individual ECDP/IC/14 / Hiring of 5 - Supporting Project TF / A8999 Post Consultant Open 6,000.00 6,000.00 Signed 2019-08-18 2019-08-08 2019-08-26 2019-08-22 2019-08-26 2019-08-23 2019-08-26 2019-08-23 2019-12-24 Projectr Coordinator Management Selection Page 3 UZ-MPSE-142563-CS-INDV / Individual 5 - Supporting Project selection of project IDA / 64180 Post Consultant Open 88,500.00 14,400.00 Signed 2019-11-24 2019-11-21 2019-12-14 2019-12-12 2019-12-15 2019-12-12 2019-12-17 2019-12-12 2024-10-21 Management coordinator Selection UZ-MPSE-142567-CS-INDV / Individual 5 - Supporting Project selection of financial IDA / 64180 Post Consultant Open 70,800.00 1.30 Signed 2019-11-24 2019-11-21 2019-12-14 2019-12-12 2019-12-15 2019-12-12 2019-12-17 2019-12-12 2024-10-21 Management management specialist Selection UZ-MPSE-143818-CS-INDV / Individual 5 - Supporting Project selection of financial IDA / 64180 Post Consultant Open 70,800.00 12,000.00 Signed 2019-11-24 2019-11-21 2019-12-14 2019-12-12 2019-12-15 2019-12-12 2019-12-17 2019-12-12 2024-10-21 Management management assistant Selection UZ-MPSE-143819-CS-INDV / Individual 5 - Supporting Project selection of procurement IDA / 64180 Post Consultant Open 70,800.00 13,200.00 Signed 2019-11-24 2019-11-21 2019-12-14 2019-12-12 2019-12-15 2019-12-12 2019-12-17 2019-12-12 2024-10-21 Management specialist Selection UZ-MPSE-143820-CS-INDV / Individual 5 - Supporting Project selection of monitoring and IDA / 64180 Post Consultant Open 70,800.00 13,200.00 Signed 2019-11-24 2019-11-21 2019-12-14 2019-12-12 2019-12-15 2019-12-12 2019-12-17 2019-12-12 2024-10-21 Management evaluation specialist Selection UZ-MPSE-143821-CS-INDV / Individual 5 - Supporting Project selection of quality IDA / 64180 Post Consultant Open 64,900.00 13,200.00 Signed 2019-11-24 2019-11-21 2019-12-14 2019-12-12 2019-12-15 2019-12-12 2019-12-17 2020-02-01 2024-10-21 Management measurement specialist Selection UZ-MPSE-143822-CS-INDV / Individual 5 - Supporting Project selection of procurement IDA / 64180 Post Consultant Open 31,900.00 12,000.00 Signed 2019-11-24 2019-11-21 2019-12-14 2019-12-12 2019-12-15 2019-12-12 2019-12-17 2020-02-19 2022-05-05 Management assistant Selection UZ-MPSE-161665-CS-INDV / Individual 1.2.9 Review or Development 1 - Improving Quality of IDA / 64180 Post Consultant Open 60,000.00 0.00 Canceled 2020-06-07 2020-07-26 2020-08-16 2020-09-20 2021-03-19 of Regulations on Inclusive Preschool Education Selection Preschool Education UZ-MPSE-161690-CS-INDV / Individual 5.1.2 Assistance from 5 - Supporting Project IDA / 64180 Post Consultant Open 150,000.00 0.00 Canceled 2020-03-09 2020-03-18 2020-04-27 2020-05-18 2020-06-22 2020-12-19 Experienced International Management Selection Procurement Specialist IC/5/1/20 / 5.1.2 Assistance Individual from Experienced 5 - Supporting Project IDA / 64180 Post Consultant Open 100,000.00 100,000.00 Signed 2020-05-04 2020-06-02 2020-06-02 2020-06-20 2020-06-23 2020-06-19 2020-07-28 2020-06-26 2021-01-24 International Procurement Management Selection Specialist ECD-IC/1/1 / 1.1.1. Consulting Services for Assistance on the Individual Development of a Framework 1 - Improving Quality of IDA / 64180 Post Consultant Open 100,000.00 42,480.00 Signed 2020-06-16 2020-07-17 2020-08-04 2020-08-19 2020-08-25 2020-09-01 2020-09-29 2020-09-02 2021-03-28 for Professional Development Preschool Education Selection of Preschool Education Staff Promoting Early Childhood Development Project. ECD-IC/2/1 / 2.2.1 Consulting Services for 2 - Increasing Access to Individual Assistance to the Design and IDA / 64180 Quality Early Learning Post Consultant Open 150,000.00 144,997.00 Signed 2020-06-16 2020-07-17 2020-08-04 2020-08-28 2020-08-25 2020-09-17 2020-09-29 2020-09-21 2021-11-23 Implementation of Alternative Environments Selection Models of Service Provision 3 - Partnering with the ECD-DS/3/1 / 3.1.4 IDA / 64180 Private Sector through a Post Direct Selection Direct 20,000.00 11,000.00 Signed 2020-06-29 2020-07-07 2020-07-09 2020-07-09 2020-09-12 2020-08-06 2020-11-11 Completion of the SIBOM Social Impact Bond ECD-IC/1/2 / 1.2.12 Individual Targeted Assistance for a 1 - Improving Quality of IDA / 64180 Post Consultant Open 20,000.00 13,200.00 Terminated 2020-08-01 2020-07-17 2020-08-25 2020-10-26 2020-09-04 2020-10-27 2020-09-24 2020-10-28 2021-09-24 More Effective Implementation Preschool Education Selection of the Project Component 1 ECD-IC/3/1 / 3.1.5 Targeted 3 - Partnering with the Individual Assistance for a More Effective Under IDA / 64180 Private Sector through a Post Consultant Open 20,000.00 0.00 2020-08-01 2020-07-17 2020-08-25 2020-09-04 2020-09-19 2021-09-19 Implementation of the Project Implementation Social Impact Bond Selection Component 3 ECD-IC/5/1 / 5.1.8 Individual 5 - Supporting Project Assistance for Updating the IDA / 64180 Post Consultant Open 20,000.00 5,000.00 Signed 2020-07-09 2020-07-14 2020-08-27 2020-07-23 2020-09-17 2020-07-23 2020-10-22 2020-08-10 2020-12-24 Management Project Operations Manual Selection ECD-IC/4/1 / 4.2.1.1 Assistance for Development Individual 4 - Establishing an Education Under and Implementation of a IDA / 64180 Post Consultant Open 100,000.00 0.00 2020-07-27 2021-04-29 2020-09-14 2020-10-05 2020-11-09 2022-07-02 Quality Measurement System Implementation System to Assess the Selection Preschool Education Quality ECD-IC/4/2 / 4.2.1.2 Individual Adaptation of Instruments to 4 - Establishing an Education IDA / 64180 Post Consultant Open 100,000.00 26,208.00 Completed 2020-09-01 2020-07-24 2020-10-20 2020-09-10 2020-11-10 2020-09-18 2020-12-15 2020-09-21 2021-06-13 2021-03-20 Measure Quality and Children Quality Measurement System Selection Development ECD-IC/4/4 / 4.2.1.6 Development of a Framework Individual 4 - Establishing an Education and Implementation Plan for IDA / 64180 Post Consultant Open 150,000.00 150,000.00 Signed 2020-08-02 2020-11-06 2020-09-20 2021-01-05 2020-10-11 2021-04-27 2020-11-15 2021-04-27 2023-11-15 Quality Measurement System Establishing a Large-scale Selection National Assessment System ECD-IC/4/5 / 4.2.1.7 Assistance for the Individual Development of Standardized 4 - Establishing an Education IDA / 64180 Post Consultant Open 250,000.00 250,000.00 Signed 2020-08-03 2020-11-06 2020-09-21 2021-01-05 2020-10-12 2021-04-27 2020-11-16 2021-04-27 2023-11-16 Items for National Quality Measurement System Selection Assessments of Learning Outcomes ECD-IC/4/3 / 4.1.3 Strategic Guidance for the Operation of Individual the National Center for 4 - Establishing an Education IDA / 64180 Post Consultant Open 120,000.00 120,000.00 Signed 2020-08-04 2020-11-06 2020-09-22 2021-01-05 2020-10-13 2021-04-27 2020-11-17 2021-04-27 2023-11-17 International Studies on the Quality Measurement System Selection Assessment of Quality of Education ECD-IC/1/3 / 1.1.2 Individual Assistance for Developing 1 - Improving Quality of IDA / 64180 Post Consultant Open 100,000.00 97,115.00 Signed 2020-08-31 2020-08-26 2020-10-19 2020-10-16 2020-11-09 2020-10-23 2020-12-14 2020-10-23 2022-04-08 Child-centered Approaches to Preschool Education Selection Teaching Page 4 ECD-IC/1/4 / 1.2.7 Assistance to the Individual 1 - Improving Quality of Under Development of Evaluations, IDA / 64180 Post Consultant Open 30,000.00 0.00 2020-08-31 2020-09-30 2020-10-19 2021-01-13 2020-11-09 2020-12-14 2022-04-08 Preschool Education Implementation Researches, Studies and Selection Surveys on ECD ECD-IC/1/5 / 1.2.1 Individual 1 - Improving Quality of Development of a Capacity IDA / 64180 Post Consultant Open 50,000.00 48,000.00 Signed 2020-08-04 2020-07-31 2020-09-22 2020-10-16 2020-10-13 2020-10-21 2020-11-17 2020-10-23 2021-05-16 Preschool Education Enhancement Plan Selection ECD-IC/1/6 / 1.1.8 Development of Curriculum Individual 1 - Improving Quality of Framework and Related IDA / 64180 Post Consultant Open 28,000.00 0.00 Canceled 2020-09-10 2020-09-09 2020-10-29 2020-11-19 2020-12-24 2021-04-23 Preschool Education Resources for COVID-19 Selection Response ECD-IC/1/7 / 1.1.9 Development of Training Individual 1 - Improving Quality of Materials and Training IDA / 64180 Post Consultant Open 24,000.00 0.00 Canceled 2020-09-10 2020-09-09 2020-10-29 2020-11-19 2020-12-24 2021-04-23 Preschool Education Activities for COVID-19 Selection Response ECD-IC/1/8 / 1.1.10 Individual Development of Videos for 1 - Improving Quality of IDA / 64180 Post Consultant Open 38,000.00 0.00 Canceled 2020-09-10 2020-09-10 2020-10-29 2020-11-19 2020-12-24 2021-04-23 Teachers and Children for Preschool Education Selection COVID-19 Response ECD-IC/1/2-1 / 1.2.12 Individual Targeted Assistance to 1 - Improving Quality of Under IDA / 64180 Post Consultant Open 20,000.00 0.00 2021-02-15 2021-02-16 2021-03-11 2021-03-21 2021-04-10 2022-04-10 Expedite the Implementation Preschool Education Implementation Selection of Component 1 UZ-MPSE-161666-CS-INDV / 1.2.10 Review or Development Individual 1 - Improving Quality of Pending of Regulations on Climate and IDA / 64180 Post Consultant Open 30,000.00 0.00 2022-03-31 2022-05-19 2022-06-09 2022-07-14 2023-01-10 Preschool Education Implementation Seismic Resilience in Selection Preschool Buildings ECD-IC/2/2 / Early Learning 2 - Increasing Access to Individual Hub Coordinator in IDA / 64180 Quality Early Learning Post Consultant Limited 40,000.00 0.00 Canceled 2021-09-15 2021-09-13 2021-09-20 2021-10-11 2021-11-15 2022-05-14 Samarkand region Environments Selection ECD-IC/2/3 / Early Learning 2 - Increasing Access to Individual Hub Coordinator in Namangan IDA / 64180 Quality Early Learning Post Consultant Limited 40,000.00 0.00 Canceled 2021-09-15 2021-09-13 2021-09-20 2021-10-11 2021-11-15 2022-05-14 region Environments Selection ECD-IC/4/6 / 4.2.3.7 Individual Development, Adaptation and 4 - Establishing an Education IDA / 64180 Post Consultant Open 50,000.00 0.00 Canceled 2021-09-30 2021-11-18 2021-12-09 2022-01-13 2022-07-12 Translation of Assessments Quality Measurement System Selection Materials ECD-IC/1/9 / 1.2.13 Individual Targeted Assistance to 1 - Improving Quality of Pending IDA / 64180 Post Consultant Open 20,000.00 0.00 2022-04-01 2022-04-25 2022-05-05 2022-05-25 2023-05-25 Expedite the Implementation Preschool Education Implementation Selection of Component 1 (stage 2) ECD- IC/2/2 / 2.2.9 Targeted 2 - Increasing Access to Individual Assistance to Expedite the Pending IDA / 64180 Quality Early Learning Post Consultant Open 20,000.00 0.00 2022-01-31 2022-02-24 2022-03-06 2022-03-26 2023-03-26 Implementation of Implementation Environments Selection Component 2 Page 5